SECURITIES AND EXCHANGE COMMISSION

                             WASHINGTON, D.C. 20549

                                -----------------


                                    FORM 8-K

                                 CURRENT REPORT


                       Pursuant to Section 13 or 15(d) of
                       the Securities Exchange Act of 1934

                       Date of Report: September 23, 1997

                  CONSOLIDATED EDISON COMPANY OF NEW YORK, INC.
               (Exact name of registrant as specified in charter)



                  New York         1-1217          13-5009340
                 (State of      (Commission      (I.R.S. Employer
              incorporation)    File Number)    Identification No.)


                       4 Irving Place, New York, NY 10003
                    (Address of principal executive offices)


                  Registrant's telephone number: (212) 460-4600





                                      - 2 -


INFORMATION TO BE INCLUDED IN THE REPORT


ITEM 5.     OTHER EVENTS


PSC SETTLEMENT AGREEMENT

      The New York State Public Service Commission  ("PSC"), by order issued and
effective May 20, 1996 in its "Competitive Opportunities" proceeding, endorsed a
fundamental  restructuring  of the electric  utility industry in New York State,
based on  competition  in the  generation  and  energy  services  sectors of the
industry. On March 13, 1997, Con Edison, the PSC staff and certain other parties
to the  proceeding  entered into a settlement  agreement,  dated March 12, 1997,
with  respect to the  proceeding.  On August 20,  1997,  the PSC  requested  the
parties  to  negotiate  certain  modifications  to  the  March  1997  settlement
agreement.  On August 29,  1997,  Con Edison,  the PSC staff and  certain  other
parties entered into a modified settlement agreement.

      The PSC, by order issued and  effective  September  23, 1997,  approved an
amended and restated settlement agreement, dated September 19, 1997, between Con
Edison,  the PSC staff and certain other parties (the  "Settlement  Agreement").
The order  provides  that the PSC's  approval  of the  Settlement  Agreement  is
subject  to  certain  conditions,  including  that (i) Con  Edison be the energy
supplier of last resort during the Transition  (defined below) until relieved of
that obligation,  (ii) the PSC may require auctions for the divestiture to third
parties  or  transfer  to a Con Edison  affiliate  of  generation  plant and may
subject affiliates of Con Edison to whatever  limitations the PSC determines are
necessary for any market  participant  following the PSC  examination  of market
power  issues  in  connection  with  the  divestiture  plan  (See   "Divestiture
Commitment,"  below),  and (iii) Con Edison be  committed  to  cooperate  in the
development of the infrastructure (e.g., the independent system operator,  etc.)
needed to allow competition in New York.

      The  Settlement  Agreement  provides  for a  transition  to a  competitive
electric  market by  instituting  "retail  access,"  a rate plan for the  period
ending March 31, 2002 (the  "Transition"),  a reasonable  opportunity to recover
prior utility  investments  and  commitments  that may not be  recoverable  in a
competitive  electric  market (often  referred to as  "strandable"  costs),  the
divestiture by Con Edison to  unaffiliated  third parties of at least 50 percent
of its New York City  fossil-fueled  generating  capacity  and,  subject  to Con
Edison  shareholder  and other  approvals,  a  corporate  reorganization  into a
holding company structure.





                                     - 3


      The Settlement Agreement reflects the following significant  amendments to
the August 1997 modified settlement agreement:

      -   the reductions to  generation-related  revenues that Con Edison will
          provide  over the  Transition  will  increase  from $890  million to
          approximately $1 billion. (These amounts are exclusive of additional
          revenue reductions from lower gross receipt taxes.)

      -   the revenues applicable to the delivery service provided by Con Edison
          for the New York Power  Authority  will be  increased by $45 million
          over the Transition.

      -   Con Edison will retain for its shareholders the first $50 million of
          any  net  after-tax   gains,   calculated  in  accordance  with  the
          Settlement  Agreement,  from the divestiture of generating capacity.
          In  addition,  any  additional  net gains from the  divestiture,  or
          transfer to an  affiliate  of Con  Edison,  of  generating  capacity
          during the Transition will be deferred for disposition by the PSC.

      -   the  additional  depreciation  that Con Edison will  provide for its
          generating  units will be reduced  from $110 million to $75 million,
          and Con Edison will spend an additional  $35 million on SBC Programs
         (defined below).

      Con Edison  expects  to  discontinue  the use of  Statement  of  Financial
Accounting  Standards  ("SFAS") No. 71,  "Accounting  for the Effects of Certain
Types of  Regulation"  for, and apply the standards in SFAS No. 101,  "Regulated
Enterprises-Accounting  for the Discontinuation of Application of FASB Statement
No. 71" to, the separable portion of its business that is being deregulated as a
result of the Settlement Agreement (the "Deregulated Portion").  Con Edison does
not expect that  discontinuation of SFAS No. 71 for the Deregulated Portion will
have a material adverse effect on Con Edison's financial position.


      The following is a summary of the material  provisions  of the  Settlement
Agreement, including those provisions that remain unchanged from the August 1997
modified settlement agreement,  and is qualified in its entirety by reference to
the Settlement Agreement, a copy of which is filed as an exhibit to this report.





                                      -4-


Retail Access.  Con Edison will  implement an energy and capacity  retail access
program that will permit its customers to choose  alternative  energy suppliers.
The  delivery  of  electricity  to  customers  will  continue  to be through the
Company's  transmission and distribution systems. The program will begin by June
1998 with up to 500 megawatts of customer load. This schedule is contingent upon
timely approval of a retail access implementation plan and retail access tariffs
to be  filed  by Con  Edison  with  the PSC and the  Federal  Energy  Regulatory
Commission ("FERC"),  as applicable.  The program will be expanded in increments
and Con Edison will target the phase-in of retail access to make it available to
all of its  customers  by the earlier of 18 months after an  independent  system
operator (the "ISO"),  which is to administer the wholesale  electric  market in
New York,  becomes  fully  operational  or December 31, 2001.  This  schedule is
subject to  adjustment  as  circumstances  warrant.  In  general,  Con  Edison's
delivery rates for retail access  customers during the Transition will equal the
rate  applicable  to  other   comparable  Con  Edison   customers  less  a  rate
representing  the market  value of the energy and  capacity  being  supplied for
customers by the other sellers.

     Rate Plan. The rate plan reduces the  generation-related  revenues that Con
Edison  would have  received  over the  Transition  had rate levels in effect on
March 31, 1997  remained in effect by  approximately  $1 billion,  exclusive  of
additional revenue reductions from lower gross receipts taxes (or approximately,
$1.2 billion  including  such  additional  reductions).  The gross  receipts tax
reductions will result from lower customer  billingsunder the rate plan and from
a law  enacted  in July 1997 to reduce the New York State  gross  receipts  tax.
Financing savings from any  securitization of strandable costs (see "Recovery of
Prior  Investments  and  Commitments,"  below),  in excess of the amount of such
savings,  if any, that is allocated by the PSC for SBC Programs (defined below),
and any further  reductions in New York State utility taxes will be utilized for
additional rate reductions.  In general,  base electric rates will not otherwise
be changed during the  Transition  except in the event of changes in costs above
anticipated  annual  levels  resulting  from  legal or  regulatory  requirements
(including a requirement or interpretation  resulting in Con Edison's  refunding
its tax-exempt debt),  inflation in excess of a 4 percent annual rate,  property
tax  increases  and  environmental  costs,  or in the event Con Edison's rate of
return becomes unreasonable for the provision of safe and adequate service.

      The  Settlement  Agreement  also  provides,  among  other  things,  for  a
non-bypassable  system benefits  charge to recover,  to the extent not otherwise
recovered,  the costs of required  research and development,  energy  efficiency
programs,  programs to assist low-income customers and environmental  protection
programs (collectively,  "SBC Programs").  In addition, the Settlement Agreement
includes a penalty  mechanism  (estimated  maximum,  $26  million  per year) for
failure to maintain certain service quality and reliability standards.






                                     - 5 -


      For any rate year  during the  Transition,  50 percent of any  earnings in
excess of a rate of return of 12.9  percent on  electric  common  equity will be
retained for shareholders  and 50 percent will be applied for customer  benefit,
with  one-half  of the  amount  to be  applied  to a  reduction  of  rates or as
otherwise  determined  by the PSC and the balance to be deferred  and applied to
reduce the Company's  generating plant balances through additional  depreciation
expense.  The rate of return calculation will exclude any incentives and reflect
any amounts by which the rate of return for earlier  Transition  rate years fell
below 11.9  percent.  This  earnings  sharing will end  beginning in the year in
which  Con  Edison  fulfills  its  divestiture   commitment  (see   "Divestiture
Commitment,"  below)  or in which 15  percent  of the  service  area  peak  load
(excluding the existing load served by the New York Power Authority) is supplied
other than by Con Edison.

      The  Settlement  Agreement  supersedes the provisions of Con Edison's 1995
electric rate agreement  prescribing  overall electric revenue levels for the 12
months ending March 31, 1998.  The  Settlement  Agreement  also  eliminates  the
provisions  of the 1995  electric  rate  agreement  for  incentives or penalties
related to the Enlightened Energy program and customer service performance,  the
Electric  Revenue  Adjustment and related  Revenue per Customer  mechanisms (the
"modified  ERAM"),  earnings sharing and  reconciliation  of amounts included in
base rates with actual costs for pensions  and other  post-employment  benefits,
capacity  charges under Con Edison's  contracts with  non-utility  generators of
electricity ("NUGs"),  Enlightened Energy program and renewable energy expenses,
property taxes and research and development  expenses.  The Settlement Agreement
also  requires  the reversal of all related  balances on Con  Edison's  books of
account  at  March  31,  1997,  the net  effect  of which  is not  material.  An
incentive-based  fuel  adjustment  clause,  initially  similar  to  the  partial
pass-through fuel adjustment clause under the 1995 electric rate agreement, will
be in effect during the Transition.

Divestiture  Commitment.  Con Edison has agreed to divest to unaffiliated  third
parties  at  least 50  percent  of its New York  City  fossil-fueled  generating
capacity  no later  than  December  2002,  unless the PSC  determines  that such
divestiture  should be delayed or reduced  (to  maximize  sales price or address
other  developments).  Divestiture  could also be delayed  under  certain  other
circumstances.  Con  Edison  fossil-fueled  generating  units  not  divested  to
unaffiliated  third parties will be transferred  to an unregulated  affiliate of
Con Edison by December 2002.

      Con Edison has agreed to submit a detailed  divestiture plan to the PSC by
March 1998 and, unless otherwise  justified in the divestiture plan, to initiate
the divestiture process with respect to at least 30 percent of its New York City
fossil-fueled  generating  capacity  within 90 days  after PSC  approval  of the
divestiture  plan.  The PSC could approve the  divestiture  plan as submitted or
modify it to address market power or other concerns.





                                       - 6 -

     Con Edison will retain for its  shareholders  the first $50 million of any
net after-tax  gains,  calculated in accordance  with the Settlement  Agreement,
from the  divestiture of generating  capacity.  Any additional net gains, or net
losses,  from the  divestiture,  or transfer to an affiliate  of Con Edison,  of
generating  capacity  during the Transition  will be deferred for disposition by
the PSC. After the Transition, the difference between the remaining book cost of
generating  plant and the  "`market  values'  defined  by  divestiture"  will be
reflected in the strandable costs to be recovered following the Transition. (See
"Recovery of Prior Utility Investments and Commitments," below.)

Recovery of Prior  Investments and Commitments.  Potential  strandable costs for
Con Edison are those prior utility  investments and commitments  that may not be
recoverable in a competitive retail electric market. Investments for which there
could be strandable costs include Con Edison's  fossil-fueled  generating plants
and Con Edison's Indian Point 2 nuclear  generating unit.  Commitments for which
there could be strandable costs include  decommissioning of Con Edison's nuclear
generating operations and charges under Con Edison's contracts with NUGs.

      During the  Transition,  Con Edison will continue to recover its potential
electric strandable costs in the rates it charges all customers. Con Edison will
also provide for $75 million of additional  depreciation  for its  fossil-fueled
generating  units. In addition,  as indicated above,  certain "excess"  earnings
will be applied as an offset to strandable costs. (See "Rate Plan," above.)

      Following  the   Transition,   Con  Edison  will  be  given  a  reasonable
opportunity to recover remaining electric  strandable costs, as adjusted for net
gains in excess of $50 million or net losses from divestiture or transfer of Con
Edison generating capacity (see "Divestiture  Commitment,"  above),  including a
reasonable return on investments,  through a non-bypassable charge to customers.
For remaining  fossil-related  strandable  costs, the recovery period will be 10
years and for the Indian Point 2 nuclear unit,  the recovery  period will be the
then-remaining  life of the unit. With respect to its NUG contracts,  Con Edison
will be  permitted  to  recover  at least 90  percent of the amount by which the
actual costs of its purchases under the contracts  exceed market value after the
Transition.  Any potential  disallowance after the Transition will be limited to
the lower of (i) 10 percent of the  above-market  costs or (ii) $300 million (in
2002  dollars).  The  potential  disallowance  will be  offset  by NUG  contract
mitigation  achieved  by Con  Edison  after  April 1, 1997 and 10 percent of the
gross  proceeds of generating  unit sales to third  parties.  Con Edison will be
permitted a reasonable  opportunity to recover any costs subject to disallowance
that are not  offset by these two  factors  if it makes  good  faith  efforts in
implementing  provisions of the Settlement  Agreement leading to the development
of a competitive electric market in its service territory and the development of
an ISO.





                                     - 7 -


      Financing  savings from any  "securitization"  of Con Edison's  strandable
costs, in excess of the amount of such savings, if any, that is allocated by the
PSC for SBC  Programs,  are  expected to be applied to further  reduce  customer
rates.  Subject to satisfying any conditions of any  securitization  legislation
enacted in New York State,  Con Edison could  transfer its right to recover from
customers the payment for the strandable  costs to a financing entity that would
in return  remit to Con  Edison the  proceeds  of debt  issued by the  financing
entity.  The debt,  which would be non-recourse to Con Edison,  would be secured
by, and repaid from, the future customer payments.

Corporate Structure.  The Settlement Agreement authorizes Con Edison to create a
holding  company  and  establishes   guidelines  governing   transactions  among
affiliates.  The formation of the holding  company is subject to the approval of
Con  Edison's  shareholders,  approval  of FERC and the  consent of the  Nuclear
Regulatory Commission.

     Upon formation of the holding company,  Con Edison will become a subsidiary
of the holding company,  and Con Edison's common shareholders will automatically
become  the  shareholders  of  the  holding  company.   Con  Edison's   existing
subsidiaries,  Consolidated  Edison  Solutions,  Inc.  (formerly ProMark Energy,
Inc.,  "CE  Solutions")  and  Consolidated  Edison  Development,  Inc.(formerly
Gramercy Development, Inc., "CE Development") will be transferred to the holding
company. CE Solutions was formed by Con Edison in 1993 to market gas and related
services,  and is  expanding  its  operations  to become a  full-service  energy
service company.  CE Development was formed by Con Edison in late 1996 to invest
in energy infrastructure  development projects and the marketing of Con Edison's
technical  services.  It is expected  that CE  Development  will  develop  other
opportunities  in  both  the  energy  and  non-energy  fields  domestically  and
internationally.  The holding company may establish other subsidiaries from time
to time,  including  one or more  subsidiary  holding  companies to hold its Con
Edison stock and the stock of other subsidiaries.

      The Settlement Agreement limits the dividends that Con Edison could pay to
the  holding  company  to not more  than 100  percent  of income  available  for
dividends calculated on a two-year rolling average basis.  Excluded from "income
available  for  dividends"  will be non-cash  charges to income  resulting  from
accounting changes or charges to income resulting from significant unanticipated
events. The limitation will not apply to dividends  necessary to transfer to the
holding  company  proceeds from major  transactions,  such as asset sales, or to
dividends  reducing Con Edison's  capital  ratio to a level  appropriate  to Con
Edison's business risk.






                                      - 8 -


      Without PSC approval,  Con Edison is  prohibited  from making loans to, or
guaranteeing  the obligations of, the holding company or any other subsidiary of
the holding company,  or pledging its assets as security for the indebtedness of
the holding company or any affiliate of the holding company.  Con Edison and the
holding  company's other  subsidiaries  must operate as separate  entities,  and
transfers  of  assets,  services  and  information  between  Con  Edison and its
affiliates  are  subject to  certain  restrictions.  Con Edison and the  holding
company's  other  subsidiaries  must  have  separate  operating  employees,  and
non-administrative  operating  officers  of Con  Edison  may  not  be  operating
officers  of any of the  holding  company's  other  subsidiaries.  Transfers  of
employees from Con Edison to the holding  company's other  subsidiaries are also
restricted.

Litigation.  Pursuant to the Settlement Agreement,  Con Edison will terminate an
appeal of the November  1996  rejection by the Supreme Court of the State of New
York of a challenge to the PSC's May 20, 1996 order.


ITEM 7.     FINANCIAL STATEMENTS AND EXHIBITS

(b)   Exhibits

10    Amended and Restated Agreement and Settlement, dated September 19, 1997,
between  Consolidated  Edison Company of New York, Inc. and the Staff of the New
York State Public Service Commission (without Appendices).


                                    SIGNATURE

      Pursuant to the  requirements of the Securities  Exchange Act of 1934, the
registrant  has duly  caused  this  report  to be  signed  on its  behalf by the
undersigned hereunto duly authorized.

                                    CONSOLIDATED EDISON COMPANY
                                         OF NEW YORK, INC.

                                    By:           JOHN F. CIOFFI
                                                  JOHN F. CIOFFI
                                                  Vice President and Controller

DATE:  September 24, 1997