EXHIBIT 10.116

                                             Contract No. DE-MS79-94BP94521

                  PNW AC INTERTIE CAPACITY OWNERSHIP AGREEMENT
                                executed by the
                           UNITED STATES OF AMERICA
                             DEPARTMENT OF ENERGY
                           acting by and through the
                       BONNEVILLE POWER ADMINISTRATION
                                     and
                      PUGET SOUND POWER & LIGHT COMPANY

                              Index to Sections
- ---------------------------------------------------------------------------
SECTION                                                                PAGE
 1.  Definitions..........................................................4
 2.  Term and Termination................................................15
 3.  Capacity Rights.....................................................16
 4.  Scheduling..........................................................22
 5.  Upgrades............................................................24
 6.  Sale or Assignment..................................................28
 7.  Operation, Maintenance, and Management..............................29
 8.  Existing Agreements.................................................31
 9.  Payment Provisions..................................................32
10.  Transmission Losses.................................................49
11.  Remedial Actions....................................................50
12.  Capacity Owners' Committee..........................................52
13.  Operating Plan and Amendments to the Operating Plan.................56
14.  Arbitration.........................................................70
15.  Nonbinding Arbitration..............................................75
16.  Audit Rights........................................................85
17.  Protected Areas.....................................................90
18.  Establishment and Maintenance of Rates and Relief from
     Regulatory Action...................................................91
19.  Exhibits...........................................................102

                                       1

20.  Rules of Law.......................................................104
21.  Notices............................................................105
22.  Waiver.............................................................106
23.  Miscellaneous......................................................106

     Exhibit A  (CO-94, AC-93, IS-93 Rate Schedules and General
                Transmission Rate Schedule Provisions)
     Exhibit B  (Annual Costs Rate)
     Exhibit C  (Capacity Ownership Share, Capacity Ownership Percentage,
                Scheduling Percentage, and Scheduling Share)
     Exhibit D  (Lump Sum Payment Calculation)
     Exhibit E  (Transmission Loss Factors)
     Exhibit F  (Bonneville's PNW AC Intertie)
     Exhibit G  (Capacity Owners)
     Exhibit H  (Provisions Required by Statute or Executive Order)
     Exhibit I  (Bonneville's PNW AC Intertie Costs)
     Exhibit J  (Puget's Initial Transaction with California Utility)

     This PNW AC INTERTIE CAPACITY OWNERSHIP AGREEMENT (Agreement) is
entered into as of ____________, 1994, by the UNITED STATES OF AMERICA,
Department of Energy, acting by and through the BONNEVILLE POWER
ADMINISTRATION (Bonneville or BPA) and PUGET SOUND POWER & LIGHT COMPANY
(Puget), a corporation of the state of Washington.  Each of Bonneville and
Puget is sometimes referred to individually in this Agreement as "Party";
Bonneville and Puget are sometimes referred to together in this Agreement as
"Parties."

                            W I T N E S S E T H :
                                      
     WHEREAS Bonneville, Portland General Electric Company (Portland), and
PacifiCorp Electric Operations (PacifiCorp) planned and constructed
improvements and additions to the Northwest portion of the PNW-PSW Intertie;
and

     WHEREAS such construction was completed in December 1993 resulting in
1600 MW of additional PNW AC Intertie Rated Transfer Capability in a north-

                                       2

to-south direction and 1225 MW of additional PNW AC Intertie Rated Transfer
Capability in a south-to-north direction; and

     WHEREAS pursuant to the Northwest Intertie Agreements, Bonneville
operates the PNW AC Intertie, in coordination with Portland and PacifiCorp,
as a single system so as to maximize PNW AC Intertie Rated Transfer
Capability and Operational Transfer Capability consistent with Prudent
Utility Practice; and

     WHEREAS Bonneville has developed a proposal to offer to PNW non-Federal
scheduling utilities and joint agencies capacity ownership rights in 725 MW
of Bonneville's PNW AC Intertie Rated Transfer Capability; and

     WHEREAS such proposal has been studied in Bonneville's Final Non-
Federal Participation Environmental Impact Statement, dated January 1994,
and was the selected alternative in the Administrator's Record of Decision,
dated March 25, 1994; and

     WHEREAS Bonneville and Puget executed a Memorandum of Understanding, DE-
MS79-91BP93466, dated September 18, 1991, which, among other things, sets
forth the principles for Puget's capacity ownership rights in Bonneville's
PNW AC Intertie; and

     WHEREAS interest expressed in capacity ownership by PNW non-Federal
scheduling utilities and joint agencies exceeded the 725 MW of Bonneville's
PNW AC Intertie Rated Transfer Capability offered by Bonneville, and as a
result Bonneville developed and applied an allocation methodology selected
in the Administrator's Capacity Ownership Record of Decision, dated March
25, 1994; and

     WHEREAS concurrent with the execution of this Agreement, Bonneville and
Puget are executing Contract No. DE-MS79-94BP93947 to provide Puget with,
among other things, network wheeling between the John Day Substation and
Puget's transmission system; and

     WHEREAS Bonneville is authorized pursuant to law to dispose of electric
power generated at various Federal hydroelectric projects in the PNW, or
acquired

                                       3

from other resources, to construct and operate transmission facilities, to
provide transmission and other services, and to enter into agreements to
carry out such authority;

     NOW, THEREFORE, Bonneville and Puget agree as follows:

 1.  DEFINITIONS

     (a)  "Adjusted Capacity Ownership Price" means the price calculated
          pursuant to column 2, section B of Exhibit D and section IV.B of
          the CO-94 rate in Exhibit A.

     (b)  "Adjusted Lump Sum Payment" means the Adjusted Capacity Ownership
          Price multiplied by Puget's Capacity Ownership Share (in
          kilowatts), as described with more particularity in section D of
          Exhibit D.

     (c)  "Allocated Direct Costs" means for each fiscal year the Operations
          Cost as allocated to Bonneville's PNW AC Intertie in accordance
          with section I.C of Exhibit I for such fiscal year.  Allocated
          Direct Costs are not included in Direct Costs, Indirect Costs, or
          Overhead Costs.

     (d)  "Allowance for Funds Used During Construction" or "AFUDC"
          constitutes interest on the funds used for utility plant under
          construction.  The AFUDC rate approximates the cost of money being
          used to finance current construction work in progress and is
          calculated in accordance with FERC's Uniform System of Accounts,
          18 CFR, Part 101, Electric Plant Instructions 3.A(17), or its
          successors.  AFUDC shall be capitalized in accordance with
          Bonneville's accounting procedures and practices, and in any event
          consistent with FERC's Uniform System of Accounts, 18 CFR, Part
          101, Electric Plant Instructions 3.A(17), or its successors.

     (e)  "Billing Provisions" means those provisions set forth in Exhibit
          B, Part B.

                                       4

     (f)  "Bonneville's PNW AC Intertie" means facilities of the PNW AC
          Intertie owned partially or entirely by Bonneville specified in
          Exhibit F together with the equipment and facilities installed in
          or connected to such facilities specified in Exhibit F, to the
          extent such facilities are necessary for the transmission of power
          on the PNW AC Intertie.

     (g)  "Bonneville's PNW AC Intertie Operational Transfer Capability"
          means Bonneville's PNW AC Intertie Rated Transfer Capability as
          reduced by limitations beyond the control of the Parties, and by
          operational limitations (as determined by Bonneville in accordance
          with the agreement between Bonneville and PacifiCorp, Contract No.
          DE-MS79-94BP94332, as amended from time to time pursuant to the
          terms thereof, and with the agreement between Bonneville and
          Portland, Contract No. DE-MS79-87BP92340, as amended from time to
          time pursuant to the terms thereof, and in accordance with Prudent
          Utility Practice) resulting from, among other things, line or
          equipment outages, stability limits, or loopflow.

     (h)  "Bonneville's PNW AC Intertie Rated Transfer Capability" means
          Bonneville's share of the PNW AC Intertie Rated Transfer
          Capability as determined in accordance with the agreement between
          Bonneville and PacifiCorp, Contract No. DE-MS79-94BP94332, as
          amended from time to time pursuant to the terms thereof, and with
          the agreement between Bonneville and Portland, Contract No. DE-
          MS79-87BP92340, as amended from time to time pursuant to the terms
          thereof.

     (i)  "Capacity Owner" means each of the parties listed in Exhibit G to
          the extent that such party has entered into a Capacity Ownership
          Agreement.

     (j)  "Capacity Ownership Agreement" means, in the singular, this
          Agreement or the agreement, substantially identical to this
          Agreement, entered into by each Capacity Owner (other than Puget)
          and Bonneville, and in the plural, this Agreement and all such
          substantially identical agreements entered into respectively by

                                       5

          Capacity Owners (other than Puget) and Bonneville, as each such
          agreement may be amended or supplemented from time to time
          pursuant to the terms of such agreement, concerning (among other
          things) the rights of such Capacity Owner with respect to the PNW
          AC Intertie.

     (k)  "Capacity Ownership Percentage" means, as of the Effective Date,
          in the singular, the percentage of Bonneville's PNW AC Intertie
          Rated Transfer Capability owned by Puget pursuant to this
          Agreement, which percentage is determined by dividing Puget's
          Capacity Ownership Share as of the Effective Date by Bonneville's
          PNW AC Intertie Rated Transfer Capability as of the Effective Date
          (such percentage being subject to change pursuant to the terms of
          this Agreement), and in the plural, the  percentages of
          Bonneville's PNW AC Intertie Rated Transfer Capability owned by
          the other Capacity Owners, respectively, pursuant to their
          respective Capacity Ownership Agreements (other than this
          Agreement), which percentages are set forth in Exhibit G (each of
          such percentages being subject to change pursuant to the
          respective terms of such Capacity Ownership Agreements).

     (l)  "Capacity Ownership Rights" means the rights of Puget pursuant to
          this Agreement.

     (m)  "Capacity Ownership Share" means, except as such term is otherwise
          used in sections III.A and III.B of the CO-94 rate set forth in
          Exhibit A on the Effective Date, in the singular, the MW amount of
          Bonneville's PNW AC Intertie Rated Transfer Capability owned by
          Puget pursuant to this Agreement, which MW amount is set forth in
          Exhibit C (such amount being subject to change pursuant to the
          terms of this Agreement), and in the plural, the MW amounts of
          Bonneville's PNW AC Intertie Rated Transfer Capability owned by
          the other Capacity Owners, respectively, pursuant to their
          respective Capacity Ownership Agreements (other than this
          Agreement), which amounts are set forth in Exhibit G (each of such
          amounts being subject to

                                       6

          change pursuant to the respective terms of such Capacity Ownership
          Agreements).

     (n)  "Committee" has the meaning set forth in subsection 12(a).

     (o)  "Contracts and Rates Costs" means, upon and after the effective
          date of Exhibit B pursuant to this Agreement, for any fiscal year
          Bonneville's total contracts and rates costs (as described in
          section VI of Exhibit I) for such fiscal year as functionalized
          and allocated in accordance with section VI of Exhibit I to
          determine Contracts and Rates Costs for Bonneville's PNW AC
          Intertie.

     (p)  "Direct Costs" means any costs incurred by Bonneville which are
          readily identifiable, or obviously traceable to, and directly
          benefit, a specific Bonneville program, project, or other cost
          objective.  Direct Costs are not included in Allocated Direct
          Costs, Overhead Costs, or Indirect Costs.  The methods for
          determining Direct Costs for Bonneville's PNW AC Intertie are set
          forth in sections II.B and III.A of Exhibit I.

     (q)  "Effective Date" means the date as of which this Agreement becomes
          effective pursuant to section 2.

     (r)  "End of Term Costs" means, upon and after the effective date of
          Exhibit B pursuant to this Agreement, Bonneville's costs
          associated with decommissioning the PNW AC Intertie determined in
          accordance with section VIII of Exhibit  I.

     (s)  "FERC" means the Federal Energy Regulatory Commission or its
          regulatory successor.

     (t)  "General Plant Cost" means, upon and after the effective date of
          Exhibit B pursuant to this Agreement, for any fiscal year any
          costs (including direct costs, indirect costs, overhead costs, and
          AFUDC) for Bonneville's general plant investment for such fiscal
          year.  The

                                       7

          method for determining General Plant Cost is set forth in section
          IV of Exhibit I.

     (u)  "GTRSP" or "GTRSPs" means Bonneville's General Transmission Rate
          Schedule Provisions, set forth in Exhibit A, as such provisions
          may be revised from time to time.

     (v)  "Indirect Costs" means any costs incurred by Bonneville which
          indirectly benefit and are directly charged to a specific
          Bonneville program, project, or other cost objective for which a
          Direct Cost or Allocated Direct Cost is charged.  Indirect Costs
          shall not be included in Allocated Direct Costs, Direct Costs, or
          Overhead Costs.  The methods for determining Indirect Costs for
          Bonneville's PNW AC Intertie are set forth in sections I.D, II.D,
          and III.B of Exhibit I.

     (w)  "Initial Capacity Ownership Price" means $215 per kilowatt, the
          calculation of which charge is set forth in column 1, section B of
          Exhibit D and in section III.A of the CO-94 rate in Exhibit A.

     (x)  "Initial Lump Sum Payment" means the Initial Capacity Ownership
          Price multiplied by Puget's Capacity Ownership Share (in
          kilowatts), as described with more particularity in section C of
          Exhibit D.

     (y)  "Interconnection Agreement" means the "Interim Interconnection
          Agreement Between Certain California-Oregon Transmission Project
          Participants and Northwest Participants," Contract No. DE-MS79-
          91BP93158, as amended or superseded.

     (z)  "Joint AC Intertie" is as defined in the agreement between
          Bonneville and Portland, Contract No. DE-MS79-87BP92340, as
          amended from time to time pursuant to the terms thereof.

    (aa)  "Joint Intertie Scheduling Office" or "JISO" means the group of
          Bonneville, Portland, and PacifiCorp schedulers, which, among
          other things, accepts PNW-PSW Intertie Preschedules.

                                       8

    (bb)  "Maintenance Cost" means, upon and after the effective date of
          Exhibit B pursuant to this Agreement, for any fiscal year any
          maintenance Direct Costs for Bonneville's PNW AC Intertie,
          maintenance Indirect Costs for Bonneville's PNW AC Intertie, and
          maintenance Overhead Costs for Bonneville's PNW AC Intertie for
          such fiscal year, each being determined in accordance with section
          II of Exhibit I.

    (cc)  "MW" means megawatt.

    (dd)  "Northwest Intertie Agreements" means the agreement between
          Bonneville and PacifiCorp, Contract No. DE-MS79-94BP94332, as
          amended from time to time pursuant to the terms thereof, and the
          agreement between Bonneville and Portland, Contract No. DE-MS79-
          87BP92340, as amended from time to time pursuant to the terms
          thereof.

    (ee)  "Operating Plan" means, subject to subsection 13(o), with respect
          to any fiscal year commencing on or after the day on which the
          annual costs rate set forth in Exhibit B has been approved on an
          interim or final basis by FERC, the written document containing
          the information described in subsection 13(c), as such document
          may be amended pursuant to section 13, 14, or 16.

    (ff)  "Operations Cost" means, upon and after the effective date of
          Exhibit B pursuant to this Agreement, for any fiscal year any
          Allocated Direct Costs for Bonneville's PNW AC Intertie,
          operations Indirect Costs for Bonneville's PNW AC Intertie, and
          operations Overhead Costs for Bonneville's PNW AC Intertie for
          such fiscal year, each being determined in accordance with section
          I of Exhibit I.

    (gg)  "Other Costs" means, upon and after the effective date of
          Exhibit B pursuant to this Agreement, Bonneville's other costs for
          Bonneville's PNW AC Intertie described in and determined pursuant
          to section V of Exhibit I.

                                       9

    (hh)  "Overhead Cost" means administrative and general costs, support
          service costs, or other costs similar in nature which are
          distributed or allocated by Bonneville to Bonneville's PNW AC
          Intertie.  Overhead Costs are not included in Direct Costs,
          Allocated Direct Costs, or Indirect Costs.  The methods for
          determining Overhead Costs are set forth in sections I.E, II.E,
          and III.B of Exhibit I.

    (ii)  "Pacific Northwest" or "PNW" means the area defined as the Pacific
          Northwest in the Pacific Northwest Electric Power Planning and
          Conservation Act, 16 U.S.C. section 839a(14).

    (jj)  "Pacific Time" means Pacific Standard Time and Pacific Daylight
          Time as each is in force.

    (kk)  "PNW AC Intertie" means facilities including, but not limited to,
          the following:  two 500 kV transmission lines extending from John
          Day Substation to the Malin Substation and to the California-
          Oregon border; portions of John Day, Grizzly, and Malin
          Substations and the Sand Springs, Fort Rock, and Sycan
          Compensation Stations; a portion of the Buckley-Summer Lake 500 kV
          transmission line and associated substations; portions of the
          Buckley-Marion and Marion-Alvey 500 kV transmission lines and
          associated facilities; a portion of Bonneville's capacity rights
          in the Summer Lake-Malin 500 kV transmission line; Bonneville's
          rights in the Meridian-Malin 500 kV transmission line and
          Bonneville's share of ownership of the Alvey-Meridian 500 kV
          transmission line; Captain Jack Substation; the 500 kV
          transmission line from Captain Jack Substation to the California-
          Oregon border; and any modifications, additions, improvements, or
          other alterations thereto.

    (ll)  "PNW AC Intertie Operational Transfer Capability" means the PNW AC
          Intertie Rated Transfer Capability as reduced by limitations
          beyond the control of the Parties, and operational limitations (as
          determined by Bonneville in accordance with the agreement between
          Bonneville and PacifiCorp, Contract No. DE-MS79-94BP94332, as
          amended from time to time pursuant to the terms thereof, and with

                                      10

          the agreement between Bonneville and Portland, Contract No. DE-
          MS79-87BP92340, as amended from time to time pursuant to the terms
          thereof, and in accordance with Prudent Utility Practice)
          resulting from, among other things, line or equipment outages,
          stability limits, or loopflow.

    (mm)  "PNW AC Intertie Rated Transfer Capability" means the north-to-
          south and south-to-north capability of the PNW AC Intertie to
          transfer power in a reliable manner as determined consistent with
          Prudent Utility Practice.

    (nn)  "Pacific Northwest-Pacific Southwest Intertie" or "PNW-PSW
          Intertie" means the DC transmission line between the Celilo
          Converter Station in The Dalles, Oregon, and the Sylmar Converter
          Station near Los Angeles, California, the PNW AC Intertie, and the
          AC Intertie in California including, without limitation, the
          California-Oregon Transmission Project.

    (oo)  "Pacific Northwest Non-Federal Utility" means any electric utility
          that serves retail load in the region consisting of (1) the states
          of Oregon, Washington, and Idaho, the portion of the state of
          Montana west of the Continental Divide, and such portions of the
          States of Nevada, Utah, and Wyoming as are within the Columbia
          River Basin drainage basin, and (2) any contiguous areas, not in
          excess of seventy-five air miles from the area referred to in (1)
          above, which areas are a part of the service area of a rural
          electric cooperative power customer served by Bonneville on the
          effective date of the Pacific Northwest Power Planning and
          Conservation Act (P.L. 96-501) having a distribution system from
          which it serves both within and without such region.

    (pp)  "Power Scheduling Costs" means, upon and after the effective date
          of Exhibit B pursuant to this Agreement, Bonneville's total power
          scheduling costs (as described in section VII of Exhibit I) as
          functionalized and allocated in accordance with section VII of
          Exhibit

                                      11

          I to determine Power Scheduling Costs for Bonneville's PNW AC
          Intertie.

    (qq)  "Preschedule" means the schedule submitted by Puget to the JISO
          pursuant to paragraph 4(b)(1) for transactions prepared each
          Working Day for the period beginning 2400 hours of the current
          Working Day through 2400 hours of the next Working Day.

    (rr)  "Prudent Utility Practice" means, at any particular time, the
          generally accepted practices, methods, and acts in the electrical
          utility industry in the Western Systems Coordinating Council area
          prior thereto that would achieve the desired result or, if there
          are no such practices, methods, and acts, the practices, methods,
          and acts which, in the exercise of reasonable judgment in the
          light of facts known at the time the decision was made, could have
          been expected to achieve the desired result consistent with
          reliability and safety.

    (ss)  "Real-time Schedule" means a schedule, or change to the
          Preschedule, submitted during the period which begins when the
          Preschedule is deemed by the JISO to be complete and concludes at
          2400 hours on the day for which the Preschedule is submitted by
          Puget.

    (tt)  "Reinforcement" means any transmission plant modification,
          addition, improvement, or other alteration to the Federal Columbia
          River Transmission System which is not a Replacement or an Upgrade
          and which is made pursuant to subsection 7(c).

    (uu)  "Reinforcement Costs" means, upon and after the effective date of
          Exhibit B pursuant to this Agreement, for any Reinforcement, the
          Direct Costs, Indirect Costs, Overhead Costs, and AFUDC for such
          Reinforcement, all capitalized to plant-in-service together with
          (1) simple interest on the foregoing costs accrued from the date
          on which Bonneville stops accruing AFUDC on the foregoing costs
          until the due date of the bill to Puget for the foregoing costs
          pursuant to subparagraph 9(b)(2)(B) and (2) the costs of removal
          and any salvage credit with respect to any PNW AC Intertie
          facility removed on

                                      12

          account of such Reinforcement.  Reinforcement Costs do not include
          capitalized general plant cost.  The method for determining
          Reinforcement Costs for Bonneville's PNW AC Intertie is set forth
          in section III of Exhibit I.

    (vv)  "Replacement" means for any transmission plant addition,
          betterment, renewal and equipment or facility that takes the place
          of or adds to any existing equipment or facility on Bonneville's
          PNW AC Intertie that does not increase Bonneville's PNW AC
          Intertie Rated Transfer Capability.

    (ww)  "Replacement Costs" means, upon and after the effective date of
          Exhibit B pursuant to this Agreement, for any Replacement, the
          Direct Costs, Indirect Costs, Overhead Costs, and AFUDC for such
          Replacement, all capitalized to plant-in-service together with (1)
          simple interest on the foregoing costs accrued from the date on
          which Bonneville stops accruing AFUDC on the foregoing costs until
          the due date of the bill to Puget for the foregoing costs pursuant
          to subparagraph 9(b)(2)(B) and (2) the costs of removal and any
          salvage credit with respect to any PNW AC Intertie facility
          removed on account of such Replacement.  General Plant Cost is not
          included in Replacement Costs.  The method for determining
          Replacement Costs for Bonneville's PNW AC Intertie is set forth in
          section III of Exhibit I.

    (xx)  "Revised Adjusted Capacity Ownership Price" means a price
          calculated pursuant to column 3, section B of Exhibit D and
          section IV.B of the CO-94 rate in Exhibit A.

    (yy)  "Revised Adjusted Lump Sum Payment" means a Revised Adjusted
          Capacity Ownership Price multiplied by Puget's Capacity Ownership
          Share (in kilowatts), as described with more particularity in
          section E of Exhibit D.

    (zz)  "Scheduler" means the person authorized by a Party to accept or
          submit schedules pursuant to section 4 and authorized to
          implement,

                                      13

          interpret, and vary the scheduling procedures set forth in such
          section pursuant to this Agreement.

   (aaa)  "Scheduling Percentage" means the percentage of the PNW AC
          Intertie Rated Transfer Capability owned by Puget pursuant to this
          Agreement, which percentage is determined by dividing Puget's
          Capacity Ownership Share by the PNW AC Intertie Rated Transfer
          Capability.

   (bbb)  "Scheduling Share" means, for any given hour, the MW amount equal
          to the product of Puget's Scheduling Percentage and the PNW AC
          Intertie Operational Transfer Capability for such hour.

   (ccc)  "Scheduling Utility" means either (i) a Pacific Northwest Non-
          Federal Utility that serves a retail service area and operates a
          generation control area, or (ii) a Pacific Northwest Non-Federal
          Utility designated by Bonneville as a "computed requirements
          customer" or its equivalent.

   (ddd)  "Term" means the period of effectiveness of this Agreement set
          forth in subsection 2(a).

   (eee)  "Third AC Intertie" means the Third AC Intertie Project, which
          project increased the PNW AC Intertie Rated Transfer Capability by
          1600 MW in a north-to-south direction and by 1225 MW in a south-to-
          north direction.

   (fff)  "Third AC Intertie Project" means the Third AC Intertie System
          Reinforcement and the construction of the Alvey-Meridian 500 kV
          transmission line and of facilities related to such transmission
          line during the period from July 1984 through December 1993.

   (ggg)  "Third AC Intertie System Reinforcement" means the improvements,
          additions and modifications to the PNW AC Intertie constructed
          during the period from July 1984 through December 1993 plus the
          construction of the Captain Jack substation and of facilities
          related to

                                      14

          such substation during the period from July 1984 through December
          1993.

   (hhh)  "Upgrade" means any MW increase to Bonneville's PNW AC Intertie
          Rated Transfer Capability which arises from or is related to an
          increase to the PNW AC Intertie Rated Transfer Capability.

   (iii)  "Working Day" means any day other than Saturday, Sunday, and a
          legal holiday recognized by the Federal government or Puget.

 2.  TERM AND TERMINATION

     (a)  This Agreement shall become effective as of the later of (1) the
          date of execution and delivery of this Agreement by both of the
          Parties, and (2) the date by which this Agreement has, with
          respect to Puget, been approved, accepted for filing or otherwise
          permitted to become effective by FERC; provided, that if FERC
          approves this Agreement for filing or otherwise permits this
          Agreement to become effective with any change or new condition,
          this Agreement shall not be or become effective unless both of the
          Parties have agreed in writing, and until the date by which both
          of the Parties have so agreed to such change or new condition.  To
          the extent Puget is required to submit this Agreement to FERC,
          Puget shall submit this Agreement to FERC for approval no later
          than three Working Days after the date on which this Agreement is
          executed and delivered by both Parties.  Bonneville shall provide
          Puget with a copy of the executed Agreement on the next Working
          Day after Bonneville executes the Agreement.  Without limiting any
          of the foregoing, Puget shall use best efforts to obtain from FERC
          on the earliest possible date (following the date on which Puget
          is required to submit this Agreement to FERC pursuant to this
          subsection 2(a)) FERC's acceptance for filing or permission that
          this Agreement become effective in accordance with this subsection
          2(a).  This Agreement shall continue in effect so long as any
          facilities of the PNW AC Intertie are in existence and operable,
          unless otherwise
     
                                       15
     
          earlier terminated by written agreement of both of the Parties or
          unless terminated pursuant to the terms of this Agreement.  All
          liabilities incurred under this Agreement shall be preserved until
          satisfied.
     
     (b)  Notwithstanding subsection 2(a), no Capacity Ownership Rights may
          be exercised by Puget until payment is made by Puget pursuant to
          paragraph 9(a)(1) and received by Bonneville.
     
     (c)  If Bonneville does not receive the payment from Puget pursuant to
          paragraph 9(a)(1), then Bonneville shall have the option to
          terminate this Agreement by delivering to Puget written notice of
          such termination.
     
     (d)  Notwithstanding subsection 2(a), if Bonneville incurs End of Term
          Costs, the following provisions of this Agreement, and all rights
          and obligations thereunder, shall continue in full force and
          effect until Bonneville renders its final bill to Puget pursuant
          to subsection 9(b), unless this Agreement is earlier terminated by
          mutual agreement of the Parties:  subsections 2(b), 2(c), and
          2(d), sections 1, 7, 8, 9, 12, 13, 14, 15, 16, 18, 19, 20, 21, 22,
          and 23, and Exhibits A, B, C, D, F, G, H, and I.  All liabilities
          incurred under such provisions of this Agreement shall be
          preserved until satisfied.
     
     (e)  If this Agreement has not become effective pursuant to subsection
          2(a) within 12 months following the date upon which Bonneville
          executes and delivers this Agreement to Puget, this Agreement
          shall be void ab initio and of no force or effect.
     
 3.  CAPACITY RIGHTS

     (a)  Purchase and Sale of Capacity

          Pursuant to the terms and conditions of this Agreement, Puget
          purchases from Bonneville and Bonneville sells to Puget the
          Capacity Ownership Rights.
          
                                       16
          
     (b)  Right to Wheel for Third Parties
     
          No later than 30 days after the Effective Date, Puget shall notify
          Bonneville in writing of Puget's decision to utilize its
          Scheduling Share pursuant to either paragraph 3(b)(1) or paragraph
          3(b)(2), and Puget shall have the right to utilize its Scheduling
          Share pursuant to the paragraph Puget elects.  Prior to
          Bonneville's receipt of such notification, Puget shall utilize its
          Scheduling Share pursuant to paragraph 3(b)(1).  If Puget fails to
          make an election within the prescribed time period, Puget shall be
          deemed to have elected the option set forth in paragraph 3(b)(1).
          
          (1)  No Third Party Wheeling
          
               (A)  Except as expressly provided in subparagraph 3(b)(1)(B),
                    Puget shall not use its Scheduling Share to transmit
                    power or energy (except for inadvertent power flows)
                    that Puget does not own at the California-Oregon border
                    or for which transmission Puget receives any revenue
                    that would be reportable in Puget's accounting system
                    where revenues received for wheeling for other entities
                    would be booked.
                    
               (B)  If Puget's Scheduling Share is not fully utilized by
                    Puget in any hour, Bonneville may schedule for such hour
                    Bonneville's transactions (including, without
                    limitation, Bonneville wheeling for other entities) and
                    wheel such transactions over the unused portion of
                    Puget's Scheduling Share for such hour but no longer
                    than such hour.  Puget shall be compensated for such
                    wheeling solely by the payments as described in sections
                    3(b)(1)(B)(i) and (ii) below.  For purposes of this
                    subparagraph 3(b)(1)(B), Puget's Scheduling Share shall
                    be deemed to be not fully utilized in a given hour to
                    the extent that Puget has not scheduled, or does not
                    schedule, on a Preschedule or Real-time Schedule basis,
               
                                       17
               
                    any transaction for such hour on any MW amount of
                    Puget's Scheduling Share.  In return for Puget's
                    Scheduling Share being made available to Bonneville
                    pursuant to this subparagraph 3(b)(1)(B), Bonneville
                    shall pay Puget
                    
                       (i) an amount equal to the product of (1) all
                          wheeling revenues received by Bonneville from
                          providing short term wheeling in a north-to-south
                          direction under the IS-93 rate, section II.A, or
                          its successor to other entities in such hour, and
                          (2) the ratio of Puget's unused Scheduling Share
                          in such hour to the total amount of PNW AC
                          Intertie Operational Transfer Capability made
                          available by Bonneville for such wheeling in such
                          hour, and
                    
                      (ii) an amount equal to the product of (1) all
                          wheeling revenues received by Bonneville from
                          providing short term wheeling in a south-to-north
                          direction under the IS-93 rate, section II.A or
                          its successor to other entities in such hour, and
                          (2) the ratio of Puget's unused Scheduling Share
                          in such hour to the total amount of PNW AC
                          Intertie Operational Transfer Capability made
                          available by Bonneville for such wheeling in such
                          hour; provided, however, that Bonneville shall not
                          be required to make payments for such south-to-
                          north wheeling pursuant to this section
                          3(b)(1)(B)(ii) earlier than two years after the
                          Effective Date.
                    
                    Bonneville shall make payments pursuant to this
                    subparagraph 3(b)(1)(B) in accordance with paragraph
                    9(f)(1).
                    
                                      18
               
               (C)  During an outage resulting from maintenance activities
                    on the PNW AC Intertie performed by Bonneville other
                    than maintenance activities undertaken due to
                    emergencies or uncontrollable forces, the following
                    shall apply:
               
                       (i) When Puget's Scheduling Share for any given hour
                          is reduced as a consequence of such outage which
                          reduces in Bonneville's PNW AC Intertie
                          Operational Transfer Capability such that Puget's
                          Scheduling Share for such hour is less than the MW
                          amount of the aggregate of Puget's net firm
                          transactions identified by Puget to Bonneville
                          pursuant to section 3(b)(1)(C)(iv) for such hour,
                          Bonneville shall, subject only to sections
                          3(b)(1)(C)(ii) and (iii) and to the immediately
                          succeeding sentence, wheel on a firm basis that
                          portion of Puget's firm transactions that equals
                          the difference between Puget's Scheduling Share
                          for such hour and the MW amount of the aggregate
                          of Puget's firm transactions for such hour up to,
                          but not in excess of, Puget's Capacity Ownership
                          Share.  Notwithstanding the foregoing, Bonneville
                          shall only be obligated to provide such wheeling
                          to the extent that each party with whom Puget is
                          conducting such firm transactions has received a
                          sufficient AC Intertie capacity allocation in
                          California to accommodate such transactions.
                          Puget shall pay the IS-93 rate, section II.A, or
                          its successor for such wheeling pursuant to this
                          section 3(b)(1)(C)(i) in accordance with
                          subsection 9(d).
                    
                      (ii) Bonneville shall not be obligated to provide such
                          wheeling to Puget pursuant to section
                    
                                       19
                    
                           3(b)(1)(C)(i) if no PNW AC Intertie Operational
                          Transfer Capability is available to Bonneville
                          after Bonneville has scheduled all of Bonneville's
                          Firm Schedules.  For purposes of this section,
                          "Bonneville's Firm Schedules" shall mean schedules
                          for assured delivery or other firm transmission
                          contracts pursuant to the Long-Term Intertie
                          Access Policy, as revised or amended, or its
                          successor, and schedules for Bonneville's firm
                          power and energy sales and exchange transactions.
                    
                     (iii) Bonneville shall not be obligated to provide such
                          wheeling to Puget pursuant to section
                          3(b)(1)(C)(i) until Bonneville has successfully
                          developed software to allow Bonneville to provide
                          such wheeling to Puget or until October 1, 1994,
                          whichever occurs sooner.
                    
                      (iv) No later than ten Working Days prior to the first
                          day of deliveries under a firm transaction, Puget
                          shall identify such firm transaction to
                          Bonneville.  Puget shall identify such firm
                          transaction to Bonneville by providing to
                          Bonneville a copy of Puget's contract for such
                          firm transaction (after information considered
                          proprietary by Puget has been redacted by Puget).
                          Bonneville shall review such contract to verify
                          that the transaction is firm.  If Puget and its
                          contractor represent or state in writing that the
                          transaction set forth in their contract is firm,
                          Bonneville shall accept that written
                          representation or statement as dispositive of the
                          question of whether such transaction is firm.
                          Implementation of such procedures in this section
                          3(b)(1)(C)(iv) may be varied by the
                    
                                              20
                    
                           mutual agreement of the Parties' Schedulers.
                          Such mutual agreement may, but need not, be
                          written.
                    
               (D)  Puget retains any and all rights of access which it
                    would otherwise have to Bonneville's PNW-PSW Intertie
                    through the Long-Term Intertie Access Policy, as revised
                    or amended, or its successor.
               
          (2)  Third Party Wheeling
          
               (A)  Puget may use its Scheduling Share to transmit any and
                    all power and energy, whether or not such power or
                    energy is owned by Puget.  Puget shall have no
                    obligation under this Agreement to make available to
                    Bonneville any portion of Puget's Scheduling Share which
                    is unused in any hour, and Bonneville shall not schedule
                    over Puget's Scheduling Share without Puget's prior
                    consent.
               
               (B)  Puget hereby waives any and all rights of access to
                    Bonneville's PNW-PSW Intertie through the Long-Term
                    Intertie Access Policy, as revised or amended, or its
                    successor; provided, however, that Bonneville may, at
                    its option, provide Puget with access to Bonneville's
                    PNW-PSW Intertie pursuant to any provision of the Long-
                    Term Intertie Access Policy, as revised or amended, or
                    its successor.
               
               (C)  Puget shall provide Bonneville with the information set
                    forth in sections 3(b)(2)(C)(i) through 3(b)(2)(C)(iii)
                    when Puget uses its Scheduling Share to export from the
                    Pacific Northwest energy or power received from third
                    parties.  Such exports of energy or power on a real-time
                    basis or for durations of less than four months are
                    excluded from this obligation.  For exports of four
               
                                      21
               
                    months or longer duration made on behalf of third
                    parties pursuant to paragraph 3(b)(2), such information
                    shall include:
               
                       (i) the name and business address of the third party;
                    
                      (ii) the amount of power or energy and the duration of
                           the transaction; and
                    
                     (iii) the name of the recipient or purchaser of such
                           power.
                    
                    Any additional information needed by Bonneville will be
                    obtained from such third party.

 4.  SCHEDULING

     (a)  Puget (and only Puget) shall be entitled to schedule on the PNW AC
          Intertie, in any hour, a MW amount up to Puget's Scheduling Share
          for such hour.  The MW amount of Puget's Scheduling Share deemed
          to be scheduled on the PNW AC Intertie pursuant to this Agreement,
          in any hour, shall be determined as the net of Puget's north-to-
          south schedules and south-to-north schedules (net schedules) for
          such hour.
     
     (b)  Puget shall submit all schedules of its Scheduling Share on its
          own behalf in accordance with the procedures set forth in
          paragraphs 4(b)(1) and 4(b)(2).  Such procedures may be varied by
          the mutual agreement of the Parties' Schedulers.  Such mutual
          agreement may, but need not, be written.  All hours referenced in
          paragraphs 4(b)(1) and 4(b)(2) are Pacific Time.
     
          (1)  Preschedules
          
               (A)  Bonneville shall make available to Puget on each Working
                    Day as soon as practicable after 0800 hours
               
                                      22
               
                    information regarding the PNW AC Intertie Operational
                    Transfer Capability with respect to Preschedules.  In
                    the event an emergency or uncontrollable force causes a
                    change in the PNW AC Intertie Operational Transfer
                    Capability, Bonneville shall notify Puget of such change
                    as soon as practicable.
               
               (B)  If Long-Term Intertie Access Policy Condition 1 Formula
                    Allocation Procedures or their successor (Condition 1)
                    are expected by Bonneville to become effective,
                    Bonneville shall so notify Puget no later than 0930
                    hours on the Working Day prior to the day on which
                    Condition 1 is expected to become effective.  Bonneville
                    shall notify Puget no later than 0930 hours on the
                    Working Day prior to the day on which Condition 1 ceases
                    to be in effect.
               
               (C)  Puget shall submit its Preschedule to the Joint Intertie
                    Scheduling Office no later than 1000 hours on each
                    Working Day if Condition 1 is in effect.  If Condition 1
                    is not in effect, Puget shall submit its Preschedule to
                    the JISO no later than 1430 hours on each Working Day.
               
          (2)  Real-time Scheduling
          
               (A)  Real-time Schedules shall be arranged through
                    Bonneville's real-time scheduling office.  Bonneville's
                    real-time Scheduler shall make reasonable efforts to
                    receive Real-time Schedules; provided, however, that
                    Bonneville's real-time Scheduler may, but is not
                    required to, accept Real-time Schedules between 1500 and
                    2200 hours on the Working Day preceding the day for
                    which such Real-time Schedule is submitted.
               
                                         23
               
               (B)  Real-time Schedules shall be arranged for a full hour.
                    Arrangements shall be completed no later than 30 minutes
                    prior to that hour.
               
               (C)  Puget shall use best efforts to keep schedule changes to
                    a minimum; provided, however, that for purposes of this
                    subparagraph 4(b)(2)(C), "best efforts" shall not be
                    deemed to refer to efforts made regardless of their
                    economic effect.
               
               (D)  The requirements set forth in subparagraphs 4(b)(2)(B)
                    and 4(b)(2)(C) do not preclude schedule changes at other
                    times as may be deemed necessary by any control area
                    operators or other entities involved in effectuating
                    such schedule changes.  Such control area operators and
                    other entities shall be notified by Bonneville of such
                    schedule changes as soon as practicable in accordance
                    with Prudent Utility Practice for purposes of
                    coordinating ramps and proper accounting.  Such schedule
                    changes shall be deemed to occur at mid-ramp.  The mid-
                    ramp time and the integrated value for the hour shall be
                    subject to the mutual agreement by such control area
                    operators and other entities.
               
               (E)  Subject to compliance with subparagraphs 4(b)(2)(A)
                    through 4(b)(2)(D) and with other applicable PNW AC
                    Intertie scheduling practices then in effect, Bonneville
                    shall make Puget's schedule change.
               
                                     24
               

     (c)  Bonneville shall make deliveries of power or energy to the
          California-Oregon border or the John Day Substation, as
          appropriate, pursuant to schedules submitted in accordance with
          this section 4; provided, however, that Bonneville shall not be
          required to make such deliveries in an hour to the extent that
          Puget's schedule exceeds Puget's Scheduling Share for such hour,
          except as may be expressly provided pursuant to subparagraph
          3(b)(1)(C).

 5.  UPGRADES
     
     (a)  Bonneville shall consult with the Committee one time each year
          regarding any plans for Upgrades.
     
     (b)  Prior to the completion of an Upgrade, Bonneville shall provide to
          Puget information in writing regarding estimated costs and the MW
          amount of such Upgrade, to the extent that such information is
          available to Bonneville.
     
     (c)  As soon as practicable following the completion of an Upgrade,
          Bonneville shall notify Puget in writing of the following:  (1)
          the MW amount of such Upgrade; (2) the capital and related costs
          (less any amount of such costs collected by Bonneville through
          rates or charges other than pursuant to the CO-94 rate in Exhibit
          A), if any, to Bonneville for completing or implementing such
          Upgrade; and (3) calculations of (A) Puget's Capacity Ownership
          Percentage multiplied by the MW amount of such Upgrade and (B)
          Puget's Capacity Ownership Percentage multiplied by the capital
          and related costs, if any, to Bonneville for completing or
          implementing such Upgrade.  Puget may elect to acquire a share of
          such Upgrade in an amount up to Puget's Capacity Ownership
          Percentage multiplied by the MW amount of such Upgrade.  Within
          100 days from receipt of such written notice from Bonneville,
          Puget shall notify Bonneville in writing of Puget's decision
          regarding such acquisition.  If Puget elects to acquire, pursuant
          to this subsection 5(c), a portion of such Upgrade, Puget's notice
          to Bonneville shall include the percentage of such Upgrade that
          Puget elects to acquire (Acquisition Percentage).  If
     
                                      25
     
          Puget fails to notify Bonneville within such 100-day period, Puget
          shall be deemed to have elected not to acquire any of such
          Upgrade.
     
     (d)  If Puget elects to acquire a portion of an Upgrade pursuant to
          subsection 5(c), the cost to Puget shall be Puget's Acquisition
          Percentage multiplied by the capital and related costs for such
          Upgrade pursuant to the CO-94 rate and subsection 9(c) (less any
          amount of such cost collected by Bonneville through rates or
          charges other than pursuant to the CO-94 rate in Exhibit A), if
          any, incurred by Bonneville for completing or implementing such
          Upgrade.  Puget shall pay such costs pursuant to such payment
          terms as may be mutually agreed to in writing by the Parties.

     (e)  If Puget's Acquisition Percentage with respect to an Upgrade
          equals its Capacity Ownership Percentage and the Acquisition
          Percentage of any other Capacity Owner with respect to such
          Upgrade is  less than its Capacity Ownership Percentage, then the
          following shall apply:
     
          (1)  Bonneville shall, in a timely manner, provide written notice
               simultaneously to Puget and to each other Capacity Owner
               (whose Acquisition Percentage equals its Capacity Ownership
               Percentage) of the MW amount equal to 100 percent of that
               portion of an Upgrade offered to, but not acquired by, the
               Capacity Owners pursuant to subsection 5(c) (Unacquired
               Share).  If Puget and each of such other Capacity Owners have
               agreed in writing to an apportionment as among themselves of
               the Unacquired Share (Apportionment), Puget may, within 45
               days following receipt of such written notice from
               Bonneville, by written notice request Bonneville to offer in
               writing to Puget such portion of the Unacquired Share as has
               been apportioned to Puget pursuant to the Apportionment, and
               Bonneville shall offer to Puget such portion of the
               Unacquired Share.
          
          (2)  If Bonneville does not receive from Puget and from each
               Capacity Owner referred to in paragraph 5(e)(1) the requests
               for offer pursuant to paragraph 5(e)(1) within the 45-day
               period
          
                                      26
          
               specified in such paragraph, Bonneville shall, in a timely
               manner, offer in writing simultaneously to Puget and to each
               other Capacity Owner (whose Acquisition Percentage equals its
               Capacity Ownership Percentage), respectively, a portion of an
               Upgrade offered to, but not acquired by, the other Capacity
               Owners pursuant to paragraph 5(e)(1) (Second Unacquired
               Share) up to the "Additional Share Offered" determined as
               follows:
     
               Additional Share Offered  =  (A divided by B) x C
               
               where:  A  =  Puget's Capacity Ownership Percentage.

                       B  =  Percentage equal to the sum of Capacity
                            Ownership Percentages of Capacity Owners that
                            acquired respectively an Acquisition Percentage
                            equal to their Capacity Ownership Percentage.
               
                       C  =  Second Unacquired Share.
          
          (3)  Within 30 days following Puget's receipt of Bonneville's
               written offer pursuant to paragraph 5(e)(2), Puget shall
               notify Bonneville in writing of Puget's decision regarding
               acquisition of the Additional Share Offered.  If Puget fails
               to notify Bonneville within such 30-day period, Puget shall
               be deemed to have elected not to acquire any of the
               Additional Share Offered.  If Puget elects pursuant to this
               paragraph 5(e)(3) to acquire any or all of the Additional
               Share Offered, then:
          
               (A)  Puget shall include in its notice to Bonneville pursuant
                    to this paragraph 5(e)(3) such share (Additional Share
                    Acquired) of the Additional Share Offered as Puget
                    elects to acquire pursuant to this paragraph 5(e)(3),
                    and
          
               (B)  the cost to Puget with respect to such acquisition shall
                    be equal to the proportion of the Additional Share
                    Acquired to such Upgrade multiplied by the capital and
                    related costs for such Upgrade pursuant to the CO-94
               
                                       27
               
                    rate and subsection 9(c) (less any amount of such costs
                    collected by Bonneville through charges other than
                    payments by Puget pursuant to subsection 5(d) or
                    subparagraph 5(e)(3)(B)), if any, to Bonneville for
                    completing or implementing such Upgrade.  Puget shall
                    pay such costs pursuant to such payment terms as may be
                    mutually agreed to in writing by the Parties.
               
     (f)  All capacity offered but not acquired pursuant to subsections 5(c)
          and (e) shall for purposes of this Agreement remain with
          Bonneville.

     (g)  After Puget has either accepted or declined all offers of capacity
          by Bonneville pursuant to subsections 5(c) and (e), Puget's
          Capacity Ownership Share, Capacity Ownership Percentage, and
          Scheduling Percentage in Exhibit C shall be revised to reflect
          changes resulting from Puget's elections pursuant to subsections
          5(c) and (e).  Revision of Exhibit C shall be pursuant to
          subsection 19(d).  Exhibit G shall be revised accordingly pursuant
          to subsection 19(i).
          
 6.  SALE OR ASSIGNMENT

     (a)  This Agreement or any interest herein shall not be transferred,
          sold, alienated, or assigned by Puget to any person without
          Bonneville's prior and express written consent.  Such consent
          shall not be unreasonably withheld.  In determining whether to
          grant its consent under this subsection 6(a), Bonneville shall
          take into consideration information including, but not limited to,
          whether the person or entity to whom this Agreement or any
          interest therein is proposed to be transferred, sold, alienated,
          or assigned is a person or entity entitled to request and receive
          transmission services pursuant to section 211 of the Federal Power
          Act, whether such person or entity can either provide its own
          scheduling services or has contracted with another entity to
          provide such scheduling services, whether such person or entity
          has the financial capability to meet the payment obligations under
          this Agreement, and whether the person or entity is either
          electrically interconnected to Bonneville's transmission system or
          has
     
                                      28
     
          contractual arrangements for wheeling with others who are
          electrically interconnected to Bonneville's transmission system.
          This Agreement shall inure to the benefit of and be binding upon
          the Parties, their respective legal representatives, permitted
          assigns, and successors in interest.  Any transfer, sale,
          alienation, or assignment made by Puget in violation of this
          section 6 shall be void ab initio and without any force or effect
          whatsoever.
     
     (b)  Bonneville hereby consents to the transfer, sale, alienation, or
          assignment by Puget to any other Capacity Owner of all or part of
          its Capacity Ownership Share and all of Puget's rights and
          obligations pursuant to this Agreement with respect thereto.
          Bonneville hereby further consents to the transfer, sale,
          alienation, or assignment by Puget of the entire Agreement and of
          all of Puget's rights and obligations under this Agreement to a
          Scheduling Utility.
     
     (c)  Bonneville hereby consents to the assignment by Puget of this
          Agreement or of any of Puget's rights under this Agreement as
          security for any indebtedness, whether present or future, of Puget
          pursuant to any mortgage, trust, security agreement or similar
          instrument of indebtedness (each such instrument, a Debt
          Instrument) made by and between Puget and any mortgagee, trustee,
          secured party or holder of such instrument of indebtedness,
          respectively; provided, however, that if Puget has defaulted in
          the performance of its obligations under any Debt Instrument, such
          that the mortgagee, trustee, secured party or holder of such Debt
          Instrument, as the case may be, would be entitled at that time to
          accelerate the amount of indebtedness under such Debt Instrument,
          Puget shall give Bonneville prompt written notice in reasonable
          detail of such default and shall, at Bonneville's election, enter
          into good faith discussions with Bonneville regarding the cure of
          such default.
     
     (d)  If Puget transfers, sells, alienates, or assigns, with
          Bonneville's consent, all or any portion of this Agreement and any
          rights and obligations pursuant to this Agreement to any person or
          party, Puget shall give Bonneville written notice of such
          transfer, sale, alienation,
     
                                      29
     
          or assignment within 10 days after the execution and delivery of
          the agreement effectuating such transaction by all parties to such
          transaction.
     
 7.  OPERATION, MAINTENANCE, AND MANAGEMENT

     (a)  Pursuant to the terms and conditions of the Northwest Intertie
          Agreements, Bonneville is the operator of the PNW AC Intertie.  As
          such, Bonneville is responsible for the dispatch of the PNW AC
          Intertie in accordance with Prudent Utility Practice.
          Bonneville's duties as operator of the PNW AC Intertie shall
          include, but are not limited to, consistent with Prudent Utility
          Practice and Northwest Intertie Agreements:  (1) determining the
          PNW AC Intertie Operational Transfer Capability; (2) implementing
          and assisting in rectifying emergency outages on the PNW AC
          Intertie due to system emergencies or uncontrollable forces; (3)
          implementing maintenance outages; and (4) giving and receiving
          switching orders on the PNW AC Intertie.  In making any
          determination or in taking any other action referred to in the
          immediately preceding sentence, Bonneville shall give fair
          consideration to Puget's interests to the extent such interests
          have been expressed to Bonneville in writing.  Bonneville shall
          operate, maintain, and manage Bonneville's PNW AC Intertie, and
          study, plan, and implement Upgrades, consistent with Prudent
          Utility Practice.
     
     (b)  Bonneville shall determine and revise as necessary the PNW AC
          Intertie Rated Transfer Capability consistent with Prudent Utility
          Practice and engineering studies based on then existing
          reliability criteria developed by the North American Electric
          Reliability Council, the Western Systems Coordinating Council, the
          Northwest Power Pool, and Bonneville.  In the event the PNW AC
          Intertie Rated Transfer Capability is changed, Bonneville shall
          promptly notify Puget in writing of such change and the new PNW AC
          Intertie Rated Transfer Capability.  If and to the extent that the
          reliability criteria for determining the PNW AC Intertie Rated
          Transfer Capability
     
                                       30
     
          change substantially, Bonneville shall notify Puget in writing of
          such change.
     
     (c)  If at any time during the Term, Bonneville's PNW AC Intertie Rated
          Transfer Capability becomes less than 3450 MW, or if at any time
          during the Term there is an imminent likelihood that Bonneville's
          PNW AC Intertie Rated Transfer Capability would become less than
          3450 MW, then Bonneville shall reinforce the Federal Columbia
          River Transmission System so as to raise Bonneville's PNW AC
          Intertie Rated Transfer Capability to 3450 MW or otherwise to
          prevent Bonneville's PNW AC Intertie Rated Transfer Capability
          from becoming less than 3450 MW.  Puget's Capacity Ownership Share
          shall not be decreased on account of any failure by Bonneville to
          reinforce the Federal Columbia River Transmission System pursuant
          to this subsection 7(c).
     
     (d)  In the event that Bonneville implements a Reinforcement pursuant
          to subsection 7(c), Bonneville shall equitably allocate the
          Reinforcement Cost for such Reinforcement between Bonneville and
          Puget based on factors including, but not limited to, load
          responsibility, contractual obligation and generation integration
          responsibility.  Any equitable allocation or agreed to allocation
          (pursuant to the immediately succeeding sentence) of a
          Reinforcement Cost pursuant to this subsection 7(d) shall be
          reflected as a Reinforcement Cost in an Operating Plan proposed by
          Bonneville pursuant to section 13.  To the extent that Bonneville
          and Puget have agreed in writing to an allocation of a
          Reinforcement Cost incurred by Bonneville pursuant to an agreement
          or modification referred to in subsection 8(b), the Reinforcement
          Cost so allocated shall not be subject to arbitration pursuant to
          section 14 or section 15.  Any Reinforcement Cost not allocated to
          Puget pursuant to this subsection 7(d) shall not be payable by
          Puget pursuant to this Agreement.
     
     (e)  Bonneville shall provide Puget notice of maintenance outages in
          accordance with the accepted standards for notice on the PNW AC
          Intertie.  Such notice shall include an evaluation of the impact
          on
     
                                      31
     
          Puget's Scheduling Share.  In scheduling or planning maintenance
          on PNW AC Intertie, Bonneville shall give fair consideration to
          Puget's interests to the extent such interests have been expressed
          to Bonneville in writing.
     
 8.  EXISTING AGREEMENTS

     (a)  Bonneville shall use good faith efforts to maintain in effect the
          Interconnection Agreement or its successor.
     
     (b)  Bonneville shall use its best efforts to maintain Puget's rights
          under this Agreement (i) by making no modification to the
          Northwest Intertie Agreements, (ii) by not entering into any other
          agreement with respect to the ownership, operation, maintenance,
          or management of the PNW AC Intertie, and (iii) by making no
          modification to the agreements referred to in the immediately
          preceding clause (ii) that would have a substantial negative
          impact on Puget's rights pursuant to sections 3, 4, 7, or to
          subsection 9(b), 9(c), or 11(a) without Puget's prior written
          consent.  Without limiting, modifying, or otherwise affecting any
          of its rights pursuant to sections 9, 13, 14, 15, and 16, Puget
          hereby consents to Bonneville's modification of the Northwest
          Intertie Agreements or Bonneville's entering into other agreements
          or modification to such Agreements with respect to the ownership,
          operation, maintenance, or management of the PNW AC Intertie to
          the extent that such modification or such agreement is made or
          entered into by Bonneville for the purpose of performing
          Bonneville's obligations pursuant to subsection 7(c).
     
 9.  PAYMENT PROVISIONS

     As full compensation for their respective payment obligations under
     this Agreement, Puget shall make payments to Bonneville in accordance
     with the provisions of this section 9, and Bonneville shall make
     payments and refunds to Puget in accordance with the provisions of this
     section 9.
                                      32
     
     (a)  Lump Sum Payment

          (1)  As soon as practicable after the Effective Date, Bonneville
               shall render a bill to Puget for the Initial Lump Sum Payment
               (less the negotiation deposit, if any, with applicable
               interest as described in section C of Exhibit D) and such
               bill shall include as an attachment and as part of such bill
               a completed section C of Exhibit D, setting forth the
               calculation of such Initial Lump Sum Payment due Bonneville
               in accordance with section IV.A of the CO-94 rate set forth
               in Exhibit A.  Puget shall make such payment pursuant to the
               CO-94 rate and the applicable GTRSPs set forth in Exhibit A.
               Each of Bonneville and Puget agrees that section C of Exhibit
               D is consistent with the CO-94 rate set forth in Exhibit A on
               the Effective Date.
          
          (2)  Calculation and Billing of the Adjusted Capacity Ownership
               Price
          
               (A)  Approximately December 1995, or as soon as practicable
                    thereafter, Bonneville shall, in accordance with section
                    IV.B of the CO-94 rate set forth in Exhibit A, calculate
                    the Adjusted Capacity Ownership Price to reflect actual
                    construction costs of the facilities listed in section A
                    of Exhibit D and the actual AFUDC with respect to such
                    facilities.  Such calculation shall be made in
                    accordance with column 2, section B of Exhibit D.
               
               (B)  Promptly after Bonneville has calculated the Adjusted
                    Capacity Ownership Price pursuant to subparagraph
                    9(a)(2)(A), Bonneville shall render a bill or refund
                    voucher to Puget, and such bill or refund voucher shall
                    include as an attachment and as part of such bill or
                    refund voucher section A of Exhibit D (with a completed
                    column 2), section B of Exhibit D (with a completed
                    column 2), and a completed section D of Exhibit D
                    reflecting the Adjusted Lump Sum Payment.  If the
                                     33
                    Adjusted Lump Sum Payment is greater than the Initial
                    Lump Sum Payment, Puget shall pay to Bonneville, within
                    45 days from the date of such bill or within such other
                    time period to which the Parties may mutually agree, the
                    amount set forth in such bill, which amount shall be
                    equal to the amount set forth on line 7, section D of
                    Exhibit D (such amount including interest as set forth
                    on line 6, section D of Exhibit D).  If the Adjusted
                    Lump Sum Payment is less than the Initial Lump Sum
                    Payment, Bonneville shall pay to Puget, within 30 days
                    after the date of such refund voucher, the amount set
                    forth in such refund voucher, which amount shall be
                    equal to the amount set forth on line 7, section D, of
                    Exhibit D (such amount including interest as set forth
                    on line 6, section D, of Exhibit D).  Each of Bonneville
                    and Puget agrees that sections A, B, and D of Exhibit D
                    are consistent with the CO-94 rate set forth in Exhibit
                    A on the Effective Date.
               
          (3)  Calculation and Billing of the Revised Adjusted Capacity
               Ownership Price
               
               (A)  After payment is made by Puget pursuant to subparagraph
                    9(a)(2)(B), or a refund is made by Bonneville to Puget
                    pursuant to subparagraph 9(a)(2)(B), Bonneville may, in
                    accordance with the CO-94 rate set forth in Exhibit A,
                    make one or more adjustments to the Adjusted Capacity
                    Ownership Price; provided, that any such adjustment
                    shall be made by Bonneville within 30 days after the
                    date on which (i) Bonneville receives, pursuant to any
                    audit with respect to the Third AC Intertie Project by
                    Bonneville, Transmission Agency of Northern California,
                    PacifiCorp or any other entity performing work for
                    Bonneville on the Third AC Intertie Project, payment
                    from Transmission Agency of Northern California,
                    PacifiCorp, or any other entity performing work for
                    Bonneville on the Third AC Intertie Project, or
                    (ii) Bonneville pays, pursuant to any audit with respect
                    to the Third AC Intertie Project by Bonneville,
                    Transmission Agency of Northern California, PacifiCorp,
                    or any other entity performing work for Bonneville on
                    the Third AC Intertie Project, any amount to
                    Transmission Agency of Northern California,
               
                                       34
               
                    PacifiCorp, or any other entity performing work for
                    Bonneville on the Third AC Intertie Project; and
                    provided, further, that no adjustment of the Adjusted
                    Capacity Ownership Price or of any Revised Adjusted
                    Capacity Ownership Price shall be made by Bonneville
                    after December 31, 2005.
               
               (B)  Promptly after Bonneville has calculated a Revised
                    Adjusted Capacity Ownership Price, Bonneville shall
                    render to Puget a bill or refund voucher with respect to
                    such Revised Adjusted Capacity Ownership Price and such
                    bill or refund voucher shall include as an attachment
                    and as part of such bill or refund voucher section A of
                    Exhibit D (with a completed column 2 and a completed
                    column with respect to each Revised Adjusted Capacity
                    Ownership Price), section B of Exhibit D (with a
                    completed column 2 and a completed column with respect
                    to each Revised Adjusted Capacity Ownership Price), and
                    a completed section E of Exhibit D reflecting the
                    current Revised Adjusted Capacity Ownership Price and
                    the current Revised Adjusted Lump Sum Payment.  If the
                    current Revised Adjusted Lump Sum Payment with respect
                    to such Revised Adjusted Capacity Ownership Price is
                    greater than the Adjusted Lump Sum Payment or the
                    immediately preceding Revised Adjusted Lump Sum Payment,
                    as the case may be, then Puget shall pay to Bonneville,
                    within 45 days from the date of such bill or within such
                    other time period to
               
                                      35
               
                    which the Parties may mutually agree, the amount set
                    forth in the bill referred to in this subparagraph
                    9(a)(3)(B), which amount shall be equal to the amount
                    set forth on line 7, section E, of Exhibit D with
                    respect to the current Revised Adjusted Lump Sum Payment
                    (such amount including interest as set forth on line 6,
                    section E, of Exhibit D).  If the current Revised
                    Adjusted Lump Sum Payment is less than the Adjusted Lump
                    Sum Payment or the immediately preceding Revised
                    Adjusted Lump Sum Payment, as the case may be,
                    Bonneville shall pay to Puget, within 30 days after the
                    date of such refund voucher, the amount set forth in the
                    refund voucher referred to in this subparagraph
                    9(a)(3)(B), which amount shall be equal to the amount
                    set forth on line 7, section E of Exhibit D with respect
                    to the current Revised Adjusted Lump Sum Payment (such
                    amount including interest as set forth on line 6,
                    section E of Exhibit D).  Each of Bonneville and Puget
                    agrees that section E of Exhibit D is consistent with
                    the CO-94 rate set forth in Exhibit A on the Effective
                    Date.
               
          (4)  For purposes of implementing the CO-94 rate, the following
               shall apply:
               (A)  the calculations pursuant to paragraphs 9(a)(2) and
                    9(a)(3) shall be deemed to be the adjustment "to reflect
                    the difference between the actual and the estimated
                    Capacity Ownership Price" required under section IV.B of
                    the CO-94 rate;
               (B)  the calculations of interest pursuant to footnote 2 of
                    section D of Exhibit D and footnote 2 of section E of
                    Exhibit D shall be deemed to be the computation of
                    "interest using the weighted average interest rate on
                    Bonneville's outstanding bonds" required pursuant to
                    section IV.B of the CO-94 rate;
               
                                        36
               (C)  the calculations of the Adjusted Capacity Ownership
                    Price and of the Revised Adjusted Capacity Ownership
                    Price pursuant to paragraphs 9(a)(2) and 9(a)(3) shall
                    be deemed to be the determination of the "actual
                    Capacity Ownership Price" required pursuant to section
                    IV.B of the CO-94 rate;
               
               (D)  as used in the CO-94 rate, the terms "Bonneville's PNW
                    AC Intertie," "PNW AC Intertie," "Third AC Intertie,"
                    "Third AC Intertie Project," and "Third AC Intertie
                    System Reinforcement" shall be deemed to have the
                    respective meanings of such terms set forth in section
                    1;
               
               (E)  as used in the CO-94 rate, the term "Capacity Ownership
                    Share" shall be deemed to mean "Capacity Ownership
                    Percentage" as defined in section 1;
               
               (F)  the indirect costs and overhead costs described in
                    footnote 5 of section B of Exhibit D shall be deemed to
                    be the indirect costs and overhead costs referred to in
                    section III.A of the CO-94 rate; and
               
               (G)  the last paragraph of section I.B of the General
                    Transmission Rate Schedule Provisions set forth in
                    Exhibit A shall be deemed to read in its entirety as
                    follows:
               
                         The meaning of terms used in the transmission rate
                         schedules shall be as defined in the Agreement or
                         in provisions which are attached to the Agreement
                         or, if not defined therein, such terms shall be as
                         defined in any of the above Acts.
                         
                                       37
          
          (5)  For purposes of application of the CO-94 rate set forth in
               Exhibit A, no provision of the General Transmission Rate
               Schedule Provisions set forth in Exhibit A, other than the
               following provisions of the General Transmission Rate
               Schedule Provisions set forth in Exhibit A (or their
               successors in substance), shall have any application or
               effect with respect to this Agreement:
          
               (A)  section I;
               
               (B)  section III.A;
               
               (C)  the last three sentences of section IV.A, without regard
                    to subsections 1, 2, 3, 4, 5, 6 and 7 of such section
                    IV.A;
               
               (D)  subsection 4 of section IV.A;
               
               (E)  the first paragraph and the first sentence of the second
                    paragraph of subsection 5 of section IV.A; and
               
               (F)  for purposes of subsection 16(e) of this Agreement and
                    as deemed necessary by Bonneville to correct
                    mathematical and computational errors on bills,
                    subsection 7 of section IV.A.

     (b)  Annual Charges

          (1)  Payments Pursuant to AC-93 Rate
               
               (A)  From and after the first Working Day after Bonneville
                    receives payment from Puget pursuant to paragraph
                    9(a)(1), Bonneville shall bill Puget on the monthly
                    power bill in accordance with the AC-93 rate set forth
                    in Exhibit A.  Puget shall pay such bill in accordance
                    with the applicable GTRSPs set forth in Exhibit A.
               
                                       38
               
               (B)  For purposes of application of the AC-93 rate, no
                    provision of the General Transmission Rate Schedule
                    Provisions set forth in Exhibit A, other than the
                    following provisions of the General Transmission Rate
                    Schedule Provisions set forth in Exhibit A (or their
                    successors in substance), shall have any application or
                    effect with respect to this Agreement:
          
                       (i) section I;
                    
                      (ii) section III.A;
                    
                     (iii) the last three sentences of section IV.A,
                           without regard to subsections 1, 2, 3, 4, 5, 6
                           and 7 of such section IV.A;
                    
                      (iv) the first sentence of subsection 3 of section
                           IV.A;
                    
                       (v) subsection 4 of section IV.A;
                    
                      (vi) the first paragraph and the first sentence of
                           the second paragraph of subsection 5 of section
                           IV.A;
                    
                     (vii) the first paragraph of subsection 6 of section
                           IV.A; and
                    
                    (viii) as deemed necessary by Bonneville to correct
                           mathematical and computational errors on bills,
                           subsection 7 of section IV.A.
          
               (C)  The last paragraph of section I.B of the General
                    Transmission Rate Schedule Provisions set forth in
                    Exhibit A shall be deemed to read in its entirety as
                    follows:
               
                                      39
               
                         The meaning of terms used in the transmission rate
                         schedules shall be as defined in the Agreement or
                         in provisions which are attached to the Agreement
                         or, if not defined therein, such terms shall be as
                         defined in any of the above Acts.
               
               (D)  Bonneville hereby agrees that the provisions of the AC-
                    93 rate shall have no application or effect with respect
                    to the following:
               
                       (i) any replacement of the series capacitor banks
                          containing polychlorinated biphenyl at the Sand
                          Springs, Sycan and Fort Rock Substations; and
                    
                      (ii) any replacement commenced prior to the Effective
                          Date or not completed prior to September 30, 1995.
                    
               (E)  Upon and after the effective date of the annual costs
                    rate set forth in Exhibit B, Bonneville shall cease
                    billing Puget pursuant to the AC-93 rate.
          
          (2)  Payments Pursuant to Annual Costs Rate
          
               From and after the date the annual costs rate set forth in
               Exhibit B becomes effective, the following shall apply:
               
               (A)  Operations Costs, Maintenance Costs, General Plant
                    Costs, Other Costs, Contracts and Rates Costs, Power
                    Scheduling Costs, and End of Term Costs

                       (i) During each fiscal year during the Term,
                          Bonneville shall bill Puget on the monthly power
                          bill, and Puget shall pay, pursuant to Exhibit B,
                    
                                        40
                    
                           forecast Operations Costs,  forecast Maintenance
                          Costs, General Plant Costs, forecast Other Costs,
                          forecast Contracts and Rates Costs, forecast Power
                          Scheduling Costs, and forecast End of Term Costs
                          for such fiscal year.  Such costs shall be,
                          respectively, the forecast Operations Costs,
                          forecast Maintenance Costs, General Plant Costs,
                          forecast Other Costs, forecast Contracts and Rates
                          Costs, forecast Power Scheduling Costs, and
                          forecast End of Term Costs set forth in the
                          Operating Plan for the fiscal year in which such
                          month occurs.
                    
                      (ii) Within eight months after the end of each fiscal
                          year during the Term (such fiscal year being
                          hereinafter referred to as a "Fiscal Year"),
                          Bonneville shall determine and calculate, pursuant
                          to Exhibit I, Schedules A, B, D, E, F, G, and H,
                          actual Operations Costs, actual Maintenance Costs,
                          General Plant Costs, actual Other Costs, actual
                          Contracts and Rates Costs, actual Power Scheduling
                          Costs, and actual End of Term Costs for the Fiscal
                          Year most recently ended.
                    
                     (iii) If, based on the calculation performed pursuant
                          to section 9(b)(2)(A)(ii), the sum of the forecast
                          Operations Costs, forecast Maintenance Costs,
                          General Plant Costs, forecast Other Costs,
                          forecast Contracts and Rates Costs, forecast Power
                          Scheduling Costs, and forecast End of Term Costs
                          for the Fiscal Year is greater than the sum of the
                          actual Operations Costs, actual Maintenance Costs,
                          General Plant Costs, actual Other Costs, actual
                          Contracts and Rates Costs, actual Power Scheduling
                          Costs, and actual End
                    
                                         41
                    
                           of Term Costs for the Fiscal Year, Bonneville
                          shall refund to Puget the difference between such
                          forecast costs and such actual costs as a lump sum
                          payment, with interest pursuant to section
                          9(b)(2)(A)(vi), within 30 days after the date on
                          which the calculation referred to in section
                          9(b)(2)(A)(ii) is made.  Bonneville shall,
                          promptly following the date on which the
                          calculation of such difference is made, provide
                          Puget written notice of such refund.  Within the
                          30-day period referred to in the first sentence of
                          this section 9(b)(2)(A)(iii), Bonneville shall
                          provide to Puget an Operating Plan amended in
                          accordance with subsection 13(k) containing
                          revised schedules in the format set forth in
                          Exhibit I, Schedules A, B, D, E, F, G, and H,
                          respectively, with a completed last column
                          reflecting the difference between actual and
                          forecast Operations Costs, actual and forecast
                          Maintenance Costs, General Plant Costs, actual and
                          forecast Other Costs, actual and forecast
                          Contracts and Rates Costs, actual and forecast
                          Power Scheduling Costs, and actual and forecast
                          End of Term Costs for the Fiscal Year.
                    
                      (iv) If, based on the calculation performed pursuant
                          to subparagraph 9(b)(2)(A)(ii), the sum of the
                          actual Operations Costs, actual Maintenance Costs,
                          General Plant Costs, actual Other Costs, actual
                          Contracts and Rates Costs, actual Power Scheduling
                          Costs, and actual End of Term Costs for the Fiscal
                          Year is equal to or less than 105 percent, but
                          greater than 100 percent, of the sum of the
                          forecast Operations costs, forecast Maintenance
                          Costs, General Plant Costs, forecast Other Costs,
                          forecast Contracts and
                    
                                         42
                    
                           Rates Costs, forecast Power Scheduling Costs, and
                          forecast End of Term Costs in the Operating Plan
                          for the Fiscal Year, Bonneville shall bill to
                          Puget on the monthly power bill the difference
                          between such actual costs and such forecast costs
                          as a lump sum charge, with interest pursuant to
                          section 9(b)(2)(A)(vi), within 30 days after the
                          date on which the calculation referred to in
                          section 9(b)(2)(A)(ii) is made.  Puget shall pay
                          such bill in accordance with the Billing
                          Provisions.  Within the 30-day period referred to
                          in the immediately preceding sentence, Bonneville
                          shall provide to Puget an amended Operating Plan
                          containing revised schedules in the format set
                          forth in Exhibit I, Schedules A, B, D, E, F, G,
                          and H, respectively, with a completed last column
                          reflecting the difference between actual and
                          forecast Operations Costs, actual and forecast
                          Maintenance Costs, General Plant Costs, actual and
                          forecast Other Costs, actual and forecast
                          Contracts and Rates Costs, actual and forecast
                          Power Scheduling Costs, and actual and forecast
                          End of Term Costs for the Fiscal Year.
                    
                       (v) If, based on the calculation performed pursuant
                          to section 9(b)(2)(A)(ii), the sum of the actual
                          Operations Cost, actual Maintenance Cost, General
                          Plant Costs, actual Other Costs, actual Contracts
                          and Rates Costs, actual Power Scheduling Costs,
                          and actual End of Term Costs for the Fiscal Year
                          is greater than 105 percent of the sum of the
                          forecast Operations Cost, forecast Maintenance
                          Cost, General Plant Costs, forecast Other Costs,
                          forecast Contracts and Rates Costs, forecast Power
                          Scheduling Costs, and forecast
                    
                                      43
                    
                           End of Term Costs for the Fiscal Year, Bonneville
                          shall bill to Puget on the monthly power bill the
                          difference between such actual costs and such
                          forecast costs as a lump sum charge, with interest
                          pursuant to section 9(b)(2)(A)(vi), within 30 days
                          after the date on which the calculation referred
                          to in section 9(b)(2)(A)(ii) is made.  Puget shall
                          pay such bill in accordance with the Billing
                          Provisions; provided, however, that Bonneville
                          shall not bill Puget pursuant to this section
                          9(b)(2)(A)(v) any amount which exceeds 105 percent
                          of the sum of the forecast Operations Costs,
                          forecast Maintenance Costs, General Plant Costs,
                          forecast Other Costs, forecast Contracts and Rates
                          Costs, forecast Power Scheduling Costs, and
                          forecast End of Term Costs set forth in the
                          Operating Plan for the Fiscal Year unless and
                          until such amount which exceeds 100 percent of the
                          sum of the forecast Operations Costs, forecast
                          Maintenance Costs, General Plant Costs, forecast
                          Other Costs, forecast Contracts and Rates Costs,
                          forecast Power Scheduling Costs, and forecast End
                          of Term Costs set forth in the Operating Plan for
                          the Fiscal Year has been included in an Operating
                          Plan amended pursuant to subsection 13(k).
                    
                      (vi) Simple interest shall be accrued on payments or
                          refunds due pursuant to this paragraph 9(b)(2)
                          with respect to any fiscal year during the Term
                          using the weighted average interest rate on
                          Bonneville's outstanding bonds or other debt
                          instruments then used by Bonneville and such
                          interest shall accrue from (and including) the
                          date of the last day of such fiscal year to (but
                    
                                       44
                    
                           excluding) the date of refund to Puget or to (but
                          excluding) the due date of a payment due
                          Bonneville.

               (B)  Replacement Cost and Reinforcement Cost
               
                    Bonneville shall bill Puget on the monthly power bill
                    Replacement Costs for any Replacement and Reinforcement
                    Costs for any Reinforcement.  Bonneville shall render
                    such bill within 15 months following the date on which
                    the project work order for such Replacement or such
                    Reinforcement, as the case may be, is closed.  Puget
                    shall pay such bill pursuant to Exhibit B and sections
                    9(b)(2)(B)(i), 9(b)(2)(B)(ii), 9(b)(2)(B)(iii) and
                    9(b)(2)(B)(iv).
                    
                       (i) If the forecast Replacement Cost for a
                          Replacement is greater than the actual Replacement
                          Cost for such Replacement or if the forecast
                          Reinforcement Cost for a Reinforcement is greater
                          than the actual Reinforcement Cost for such
                          Reinforcement, Bonneville shall bill Puget the
                          actual Replacement Cost for such Replacement or
                          the actual Reinforcement Cost for such
                          Reinforcement, as the case may be.  Bonneville
                          shall provide to Puget an Operating Plan amended
                          in accordance with subsection 13(k) containing a
                          revised schedule in the format set forth in
                          Exhibit I, Schedule C, reflecting the actual and
                          forecast Replacement Cost for such Replacement or
                          the actual and forecast Reinforcement Cost for
                          such Reinforcement, as the case may be.
                    
                      (ii) If, for each Replacement or Reinforcement, the
                          actual Replacement Cost or actual
                    
                                       45
                    
                           Reinforcement Cost is equal to or less than 105
                          percent, but greater than 100 percent, of the
                          forecast Replacement Cost or forecast
                          Reinforcement Cost, Bonneville shall bill Puget
                          such actual Replacement Cost or such actual
                          Reinforcement Cost, as the case may be, on the
                          monthly power bill and Puget shall pay such bill
                          pursuant to subparagraph 9(b)(2)(B).  Bonneville
                          shall provide to Puget an amended Operating Plan
                          containing a revised schedule in the format set
                          forth in Exhibit I, Schedule C, reflecting the
                          difference between the actual and forecast
                          Replacement Cost for such Replacement or the
                          actual and forecast Reinforcement Cost for such
                          Reinforcement.
                    
                     (iii) If, for each Replacement or Reinforcement, the
                          actual Replacement Cost or actual Reinforcement
                          Cost is greater than 105 percent of the forecast
                          Replacement Cost or forecast Reinforcement Cost,
                          Bonneville shall bill Puget such actual
                          Replacement Cost or such actual Reinforcement
                          Cost, as the case may be, on the monthly power
                          bill and Puget shall pay such bill pursuant to
                          subparagraph 9(b)(2)(B); provided, however, that
                          Bonneville shall not bill Puget pursuant to this
                          subparagraph 9(b)(2)(B) any amount which exceeds
                          105 percent of the forecast Replacement Cost or
                          forecast Reinforcement Cost, as the case may be,
                          unless and until such amount which exceeds
                          100 percent of such forecast Replacement or such
                          forecast Reinforcement Cost, as the case may be,
                          has been included in an amended Operating Plan
                          pursuant to subsection 13(k).
                    
                                      46
                    
                      (iv) Charges pursuant to sections 9(b)(2)(B)(i), (ii)
                          and (iii) for Replacement Costs and Reinforcement
                          Costs shall accrue simple interest pursuant to
                          section III.D of Exhibit I.
                    
     (c)  Upgrade Charges
     
          For purposes of implementing the CO-94 rate, the following shall
          apply:
          
          (1)  as used in the CO-94 rate, the term "upgrade" shall be deemed
               to mean "Upgrade" as defined in section 1, the term "rated
               transfer capability" shall be deemed to mean "PNW AC Intertie
               Rated Transfer Capability" as defined in section 1 and the
               term "AFUDC" shall be deemed to have the meaning set forth
               for such term in section 1;
          
          (2)  the "Capacity Ownership Share of the capital and related cost
               of the upgrade," referred to in section III.B of the CO-94
               rate shall be deemed to be the costs pursuant to subsection
               5(d) and subparagraph 5(e)(3)(B), as applicable; and
          
          (3)  "construction costs (including direct, indirect and overhead
               costs) and AFUDC" referred to in section III.B of the CO-94
               rate and "related costs" referred to in section III.B of the
               CO-94 rate together shall be deemed to be Upgrade costs and
               shall be determined in the same manner in which Replacement
               Costs are determined pursuant to section III of Exhibit I;
               provided, however, that expenses that are properly allocable
               to an Upgrade (i.e., "related costs" referred to in section
               III.B of the CO-94 rate) in accordance with generally
               accepted accounting principles (as defined in Exhibit I) may
               be included by Bonneville in Upgrade costs for such Upgrade.
          
                                       47
          
     (d)  Payments of Charges Pursuant to Section 3(b)(1)(C)(i)
     
          Bonneville shall bill Puget for wheeling provided pursuant to
          section 3(b)(1)(C)(i) on Puget's monthly power bill in accordance
          with the IS-93 rate, section II.A, or its successor, set forth in
          Exhibit A and Puget shall pay such bill in accordance with the IS-
          93 rate, section II.A, or its successor, set forth in Exhibit A;
          provided, however, that under any successor to the IS-93 rate,
          Puget shall not be obligated to pay any rate or charge greater
          than the rate or charge payable by any other party to which
          Bonneville provides nonfirm wheeling services on Bonneville's PNW
          AC Intertie for such party's nonfirm transaction of a duration
          similar to Puget's wheeling transaction pursuant to section
          3(b)(1)(C)(i).
          
     (e)  Suspension for Failure to Perform
     
          (1)  If at any time during the term of this Agreement Bonneville
               does not receive payment due and owing to Bonneville pursuant
               to paragraph 9(a)(2) or 9(a)(3) or to subsection 9(b) or
               9(d), Bonneville shall be entitled to suspend performance of
               its obligations to Puget pursuant to section 4 without
               incurring any liability to Puget therefor; provided, that
               Bonneville shall not be entitled to suspend performance
               pursuant to this paragraph 9(e)(1) earlier than five Working
               Days following receipt from Bonneville by Puget of written
               notice of such suspension.  Such suspension shall continue in
               effect until the next Working Day following the Working Day
               on which Puget makes payment in full to Bonneville of the
               balance owed to Bonneville pursuant to paragraph 9(a)(2) or
               9(a)(3) or to subsection 9(b) or 9(d).  During the period of
               such suspension, Puget shall not be entitled to participate
               through the Committee in any review of an Operating Plan
               commenced by the Committee pursuant to section 13 during such
               period of suspension, or to participate in any arbitration
               commenced by the Committee pursuant to sections 14 and 15
               during such period of suspension, or to participate in any
               audit commenced
          
                                      48
               by the Committee pursuant to section 16 during such period of
               suspension.
     
          (2)  If during any period in any month Bonneville fails to make
               deliveries in accordance with subsection 4(c), Puget shall be
               entitled, without incurring any liability to Bonneville
               therefor, to delay any payment due and owing to Bonneville by
               Puget pursuant to subsection 9(b) or 9(d) for a period, equal
               to the period during which Bonneville failed to make such
               deliveries, commencing on the date the monthly power bill for
               such month would otherwise be payable by Puget pursuant to
               this Agreement; provided, however that Puget's entitlement
               pursuant to this paragraph 9(e)(2) shall apply only with
               respect to the amount of such monthly power bill to be paid
               directly to Bonneville or its agent.

     (f)  Payments or Refunds by Bonneville
     
          (1)  Bonneville shall make any payment to Puget pursuant to
               subparagraph 3(b)(1)(B) within 30 days following the end of
               the month in which such payment becomes due to Puget pursuant
               to subparagraph 3(b)(1)(B).
          
          (2)  Bonneville shall pay to Puget, in a lump sum, any refund due
               to Puget pursuant to subsection 16(e) or paragraph 16(f)(2)
               within 30 days following the date on which such refund
               becomes due to Puget pursuant to subsection 16(e) or
               paragraph 16(f)(2), respectively.
          
          (3)  Bonneville shall pay any refund, credit, or payment due to
               Puget under section 18 pursuant to the terms and conditions
               set forth in section 18.
          
          (4)  Each payment, credit or refund due to Puget by Bonneville
               pursuant to this Agreement shall be made by Bonneville, at
               Bonneville's option, (A) by check payable to the order of
               Puget,
          
                                     49
          
           (B) by electronic funds transfer of immediately available funds
               into such account as may be designated in writing by Puget
               from time to time for such purpose or (C) by crediting the
               amount of such payment, credit or refund on Puget's power
               bill.

10.  TRANSMISSION LOSSES

     (a)  To compensate Bonneville for transmission losses incurred by
          Bonneville in making deliveries scheduled by Puget pursuant to
          this Agreement, Puget shall make available, or arrange to have
          made available, to Bonneville, at any point mutually acceptable to
          the Parties at which the respective electric systems of Puget and
          Bonneville are interconnected, on the corresponding hour 168 hours
          later or on another hour to be agreed upon, the amounts of
          electric power equal to Puget's net PNW AC Intertie schedule
          multiplied by the appropriate loss factor specified in Exhibit E.
          Puget's net PNW AC Intertie schedule shall be, for any given hour,
          the absolute value of the sum of Puget's north-to-south schedules
          (positive) and south-to-north schedules (negative) for such hour.
     
     (b)  Upon the conclusion of any review by Bonneville of the loss factor
          in Exhibit E, Part A, pursuant to subsection 19(f), Bonneville
          shall present the results of its review, including any revisions
          to the loss factor in Exhibit E, Part A, to the Committee as part
          of the Operating Plan provided to the Committee pursuant to
          section 13.  The Committee may make recommendations regarding such
          results and any revisions to the loss factor in Exhibit E, Part A.
          Only recommendations regarding assumptions (including, without
          limitation, data inputs and source of date) made by Bonneville in
          its review or revision of the loss factor in Exhibit E, Part A,
          and recommendations regarding the results of such review or
          revision shall be subject to arbitration pursuant to section 14.
     
     (c)  Puget's Scheduling Share shall not be reduced by any amount of
          losses returned to Bonneville pursuant to subsection 10(a).
          
                                      50
          
11.  REMEDIAL ACTIONS

     (a)  Bonneville's Responsibilities

          (1)  Within five days after the Effective Date, Bonneville shall
               notify Puget in writing of the plan for remedial actions
               required to maintain the PNW AC Intertie Rated Transfer
               Capability, which plan shall be consistent with Western
               System Coordinating Council standards and Prudent Utility
               Practice.  If and to the extent that such plan is amended,
               modified, or replaced, Bonneville shall, promptly following
               such amendment, modification, or replacement, provide written
               notice to Puget of such amendment, modification, or
               replacement, as the case may be.  Bonneville shall be
               responsible for providing a capability to arm and having
               available appropriate remedial actions, which may include
               generator dropping, load tripping, or other acceptable
               remedial actions, required to maintain the portion of
               Bonneville's PNW AC Intertie Rated Transfer Capability not
               purchased by Capacity Owners.  Such remedial actions shall be
               consistent with Western System Coordinating Council standards
               and Prudent Utility Practice.
          
          (2)  Bonneville shall be responsible for generating appropriate
               control signals for transmission to Puget for purposes of
               effectuating remedial actions pursuant to this section.
          
     (b)  Puget's Responsibilities
          
          (1)  Puget shall be responsible for providing a capability to arm
               and having available appropriate remedial actions, which may
               include generator dropping, load tripping, or other remedial
               actions required to maintain Puget's Capacity Ownership
               Share.  Such remedial actions shall be consistent with
               Western System Coordinating Council standards, the plan
               referred to in paragraph 11(a)(1) and Prudent Utility
               Practice.  Bonneville
          
                                   51
          
               may perform engineering analyses to confirm Puget's providing
               capability to arm and having available appropriate remedial
               actions pursuant to this paragraph 11(b)(1).
          
          (2)  In any given hour, Puget shall be responsible for providing
               sufficient remedial actions, which may include generator
               dropping, load tripping, or other acceptable remedial
               actions, to maintain Puget's schedule on the PNW AC Intertie
               for such hour.  To the extent that load tripping or generator
               dropping is required as a remedial action by Puget pursuant
               to this paragraph 11(b)(2) in any given hour, the required
               amount of such load tripping or such generator dropping shall
               be determined by dividing the amount of power scheduled by
               Puget on Puget's Scheduling Share in such hour by the total
               amount of power scheduled on the PNW AC Intertie in such hour
               and multiplying the result by the total amount of generation
               or load (in MW) to be armed for the PNW AC Intertie in such
               hour.
          
          (3)  Puget shall provide, design, operate, and maintain the
               necessary equipment to accept control signals from Bonneville
               and to transmit such signals to Puget's generator dropping,
               load tripping, or other remedial action sites, and to arm and
               initiate the appropriate control action(s).  Such design,
               operation, and maintenance shall be consistent with Western
               System Coordinating Council standards, the plan referred to
               in paragraph 11(a)(1), and Prudent Utility Practice.
          
          (4)  Puget and Bonneville may mutually agree that Bonneville will,
               pursuant to terms and conditions mutually acceptable to the
               Parties, provide the remedial actions required of Puget
               pursuant to subsection 11(b).
          
                                       52
          
12.  CAPACITY OWNERS' COMMITTEE

     (a)  Composition of Committee
     
          Puget may appoint one representative (and an alternate who may act
          in the absence of such representative) as a member of the Capacity
          Owners' Committee (Committee).  If during any period Puget fails
          to appoint a representative to the Committee, Puget waives any and
          all rights during such period that would otherwise have accrued to
          it, individually or as a member of the Committee, pursuant to
          sections 12, 13, 14, 15, and 16 of this Agreement.  Puget hereby
          appoints as its representative pursuant to this subsection the
          following representative and alternate to the Committee:
               
               Representative:  Vice President Power Planning
               
               Alternate:  Manager Power Contracts
          
     (b)  Convening Meetings
     
          (1)  Any Capacity Owner that has appointed a representative to the
               Committee may convene a meeting of the Committee pursuant to
               the procedures set forth in subsection 12(e).  The Capacity
               Owner convening a Committee meeting shall be responsible for
               preparing any necessary notices, identifying the subject
               matter and issues to be discussed, and transmitting notices
               and relevant documents to the other Committee members and, if
               appropriate, to Bonneville.
               
          (2)  At the written request of any Capacity Owner that has
               appointed a representative to the Committee, Bonneville shall
               attend Committee meetings.
               
          (3)  The Committee may conduct business only at a properly
               convened meeting at which a quorum, as defined in subsection
               12(c), is present. The Committee shall make or convey any
          
                                    53
          
               request, designation, recommendation, notice, appointment,
               submission, audit report or exception, or statement to which
               Bonneville is required to respond or which creates or
               triggers an obligation of Bonneville, pursuant to this
               Agreement, only upon a decision of the Committee made at a
               properly convened meeting at which a quorum is present.
               
          (4)  Each fiscal year, Bonneville shall convene an annual meeting
               of the Committee.  The purpose of such annual meeting shall
               be to discuss the Operating Plan delivered, pursuant to
               subsection 13(b), to each Capacity Owner that has appointed a
               representative to the Committee.  Bonneville shall convene
               such annual meeting no earlier than 15 days, but no later
               than 30 days, following the date of such delivery of the
               Operating Plan.
               
          (5)  In addition to the meeting referred to in paragraph 12(b)(4),
               Bonneville may, at its discretion, convene meetings of the
               Committee, pursuant to the procedures set forth in
               subsection 12(e), to present to the Committee any information
               Bonneville deems relevant.
               
     (c)  Meeting Quorum
     
          The respective representatives of all of the Capacity Owners that
          have appointed a representative to the Committee, less one, shall
          constitute a quorum.
          
     (d)  Meetings by Telephone Conference
     
          Committee meetings pursuant to the Capacity Ownership Agreements
          may be conducted by telephone provided all Capacity Owners and, if
          appropriate, Bonneville, are notified pursuant to the procedures
          set forth in subsection 12(e) of any such meeting.
                                     54
     (e)  Meeting Notices
          
          (1)  All Committee meeting notices pursuant to the Capacity
               Ownership Agreements shall be provided in writing no less
               than 14 days prior to such meeting.
          
          (2)  Any Committee meeting notice required by this section shall
               be deemed properly made if delivered in person, by electronic
               facsimile, or by mail or other qualified delivery service,
               postage prepaid, to the person specified below:
          
               If to Bonneville:
                 Group Vice President for Marketing, Conservation and
                 Production
                 Bonneville Power Administration
                 905 NE 11th Avenue
                 Portland, OR 97232
                 Telephone (503) 230-5152
                 Facsimile (503) 230-5207
                 
               If to Puget:
                 Vice President Power Planning
                 Puget Sound Power & Light Company
                 411  108th Avenue NE  15th Floor
                 Bellevue, WA 98004-5515
                 Telephone (206) 462-3137
                 Facsimile (206) 462-3175
                 
               If to Seattle:
                 Director, Power Management Division
                 Seattle City Light
                 1111 Third Avenue, Room 420
                 Seattle, WA 98101
                 Telephone (206) 386-4530
                 Facsimile (206) 386-4955
                 
                                       55
                 
               If to PNGC:
                 Director of Power Management
                 Pacific Northwest Generating Cooperative
                 711 NE Halsey Street, Suite 200
                 Portland, OR 97232
                 Telephone (503) 288-1234
                 Facsimile (503) 288-2334
                 
               If to Snohomish:
                 Manager of Power Supply
                 Public Utility District No. 1 of Snohomish
                 County, Washington
                 2320 California Street
                 P.O. Box 1107
                 Everett, WA 98201
                 Telephone (206) 258-8211
                 Facsimile (206) 258-8305
                 
               If to Tacoma:
                 Light Division Superintendent
                 Tacoma Public Utilities
                 3628 S. 35th Street
                 Tacoma, WA 98411
                 Telephone (206) 502-8294
                 Facsimile (206) 502-8628
                 
               Attendance at a meeting by a representative of a Capacity
               Owner constitutes waiver by such Capacity Owner of notice of
               such meeting.
                 
          (3)  Either Party may, by written notice to the other Party and to
               the Capacity Owners other than Puget, change the designation,
               address, or facsimile number of the person so specified by it
               in subsection 12(a) or paragraph 12(e)(2).

                                       56

13.  OPERATING PLAN AND AMENDMENTS TO THE OPERATING PLAN

     (a)  The provisions of this section shall become effective commencing
          August 1, 1995; provided, however, that unless and until the
          annual costs rate set forth in Exhibit B is approved by FERC on an
          interim basis, Bonneville shall not have any right pursuant to
          this Agreement to bill or charge to Puget, and Puget shall not
          have any obligation pursuant to this Agreement to pay to
          Bonneville, any amount pursuant to any Operating Plan.
     
     (b)  Delivery of Operating Plan
     
          (1)  On or before August 1, 1995, Bonneville shall deliver to each
               Capacity Owner that has appointed a representative to the
               Committee an Operating Plan for Bonneville's PNW AC Intertie
               for fiscal year 1996 and an Operating Plan for Bonneville's
               PNW AC Intertie for fiscal year 1997.
     
          (2)  Not later than one year preceding the first day of each
               fiscal year, other than the fiscal years specified in
               paragraph 13(b)(1), Bonneville shall deliver to each Capacity
               Owner that has appointed a representative to the Committee an
               Operating Plan for Bonneville's PNW AC Intertie for such
               fiscal year.

     (c)  Each Operating Plan delivered pursuant to subsection 13(b) shall
          contain the following information for Bonneville's PNW AC Intertie
          with respect to forecast costs for the fiscal year to which such
          Operating Plan pertains, and such Operating Plan may contain such
          other information as Bonneville may deem relevant; and each
          amendment of an Operating Plan delivered pursuant to subsection
          13(k) shall contain the following information for Bonneville's PNW
          AC Intertie with respect to forecast or actual costs, as
          appropriate, for the fiscal year to which such Operating Plan
          pertains, and such amendment may contain such other information as
          Bonneville may deem relevant:
                                         57
          (1)  a forecast of, or the actual, Allocated Direct Cost of
               Operations Cost (pursuant to section I.C of Exhibit I),
               Indirect Cost of Operations Cost (pursuant to section I.D of
               Exhibit I), and Overhead Cost of Operations Cost (pursuant to
               section I.E of Exhibit I) in the format set forth in Exhibit
               I, Schedule A;
          
          (2)  a forecast of, or the actual, Direct Cost of Maintenance Cost
               (pursuant to section II.B of Exhibit I), Indirect Cost of
               Maintenance Cost (pursuant to section II.D of Exhibit I), and
               Overhead Cost of Maintenance Cost (pursuant to section II.E
               of Exhibit I) in the format set forth in Exhibit  I, Schedule
               B;
          
          (3)  a forecast of, or the actual, Direct Cost of Replacements and
               Reinforcements (pursuant to section III.A of Exhibit I),
               Indirect Cost and Overhead Cost of Replacements and
               Reinforcements (pursuant to section III.B of Exhibit I), and
               AFUDC of Replacements and Reinforcements (pursuant to section
               III.C of Exhibit I) in the format set forth in Exhibit I,
               Schedule C, for each Reinforcement and Replacement which is
               expected to be, in the fiscal year to which the Operating
               Plan pertains, a planned new start, construction work in
               progress on a previously initiated Reinforcement or
               Replacement, as the case may be, or a closed work order.  The
               forecast shall include for each such Reinforcement or
               Replacement an estimate of the total cost of construction and
               the cost to be incurred with respect to such Reinforcement or
               Replacement during each fiscal year until the work order for
               such Reinforcement or Replacement has been closed.
               Bonneville may elect, but shall not be required, to include
               in any such forecast the information set forth in the
               immediately preceding sentence regarding any Replacement and
               Reinforcement which is expected to be planned a new start in
               any fiscal year following the fiscal year to which the
               Operating Plan pertains.  In the event Bonneville elects to
               forecast Direct Cost, Indirect Cost, and Overhead Cost of any
               Reinforcement or Replacement which is expected to be a
          
                                      58
          
               planned new start in any fiscal year subsequent to the fiscal
               year to which the Operating Plan pertains, Bonneville shall
               provide to the Committee such forecast costs, in the format
               set forth in Exhibit I, Schedule C (together with additional
               information pertinent to such forecast costs as required by
               paragraph 13(c)(9)), 30 days prior to the date such Operating
               Plan is delivered to the Committee pursuant to subsection
               13(b).  In addition, Bonneville shall include such forecast
               costs in the Operating Plan delivered to the Committee
               pursuant to subsection 13(b);
          
          (4)  the General Plant Cost (pursuant to section IV of Exhibit I)
               in the format set forth in Exhibit I, Schedule D;
          
          (5)  a forecast of, or the actual, Other Costs (pursuant to
               section V of Exhibit I) in the format set forth in Exhibit I,
               Schedule E;

          (6)  a forecast of, or the actual, Contracts and Rates Costs
               (pursuant to section VI of Exhibit I) in the format set forth
               in Exhibit I, Schedule F;
          
          (7)  a forecast of, or the actual, Power Scheduling Costs
               (pursuant to section VII of Exhibit I) in the format set
               forth in Exhibit I, Schedule G;
          
          (8)  a forecast of, or the actual, End of Term Costs (pursuant to
               section VIII of Exhibit I) in the format set forth in Exhibit
               I, Schedule H.  Such forecast shall include Bonneville's
               proposed apportionment of such End of Term Costs among Puget
               and Capacity Owners other than Puget and Bonneville's
               rationale for such apportionment;
          
          (9)  additional information pertinent to the forecast costs,
               actual costs, and General Plant Cost provided pursuant to
               paragraphs 13(c)(1) through 13(c)(8), including, without
               limitation, descriptions of the activities or projects and
               explanations of the
          
                                       59
          
               costs comprising the Direct Cost components of such forecast
               costs, actual costs, and General Plant Cost, and explanations
               of MFU counts; and
          
          (10) if Bonneville has reviewed the loss factor in Exhibit E, Part
               A, pursuant to subsection 19(f), the Operating Plan shall
               contain the results of such review, including any revision to
               the loss factor in Exhibit E, Part A, pursuant to subsection
               10(b), and any additional information pertinent to such
               review.

     (d)  Requests by Committee

          (1)  No later than 15 days after the date on which the annual
               meeting was convened pursuant to paragraph 12(b)(4), the
               Committee may make a single request of Bonneville in writing
               for:
     
               (A)  such supporting documentation, data, and information as
                    may be reasonably necessary to analyze (i) the Operating
                    Plan, or its constituent parts, delivered  to the
                    Committee pursuant to subsection 13(b), or (ii) any
                    amendment to an Operating Plan pursuant to subsection
                    13(k); and
          
               (B)  such documentation, data, and information relating to
                    Bonneville's present or past activities or practices
                    concerning Bonneville's PNW AC Intertie and to
                    alternatives considered by Bonneville to costs or
                    activities described in the Operating Plan or any
                    amendment to an Operating Plan as may be reasonably
                    necessary for the Committee to formulate recommendations
                    pursuant to subsection 13(e);
          
               provided, however, that with regard to requests for
               documentation, data, and information pursuant to this
               paragraph 13(d)(1), the Committee must designate in such
          
                                    60
          
               request the specific item in the Operating Plan or in any
               amendment to an Operating Plan to which such requested
               documentation, data, or information is directly related and
               explain the need for such documentation, data, or
               information.  Such single request may contain multiple parts.
     
          (2)  The Committee shall use reasonable efforts to minimize and
               limit the scope and number of parts of the request for
               documentation, data, and information made pursuant to
               paragraph 13(d)(1).
     
          (3)  Bonneville shall have 20 days from the date it receives any
               request pursuant to paragraph 13(d)(1) to provide the
               documentation, data, and information requested; provided,
               however, that Bonneville shall be under no obligation (A) to
               create additional documentation, data, or information, (B) to
               provide documentation, data, or information that is not
               readily available to it, (C) to provide to the Committee
               documentation, data, or information that Bonneville has
               previously provided to the Committee, or (D) to provide
               documentation, data, or information that Bonneville would not
               otherwise be required to provide or that would otherwise be
               exempted from disclosure pursuant to the Freedom of
               Information Act, 5 U.S.C. section 552 (including, without
               limitation, the Freedom of Information Reform Act of 1986),
               as amended or superseded, or any regulation and Executive
               Order applicable to Bonneville.
     
          (4)  The Committee in such request shall designate one of its
               members to be its representative for the sole purpose of
               receiving such documentation, data, or information from
               Bonneville pursuant to this subsection 13(d).  Bonneville
               shall deliver such documentation, data, or information to the
               representative designated by the Committee to receive such
               materials.
     
                                        61
     
          (5)  For purposes of this subsection 13(d) and subsection 13(f),
               each of Bonneville and the Committee shall cooperate and use
               reasonable efforts to, in a timely manner, resolve disputes
               regarding, and clarify requests for, documentation, data, and
               information and responses to such requests.
     
     (e)  The Committee shall have 20 days from the date on which it
          receives documentation, data, or information from Bonneville
          pursuant to subsection 13(d) or, if none was requested, 50 days
          from the date on which the annual meeting was convened pursuant to
          paragraph 12(b)(4), whichever date is later, to recommend to
          Bonneville in writing a revision or revisions to any forecast cost
          or General Plant Cost in the Operating Plan.  The Committee shall
          have the time periods set forth in subsection 13(m) to recommend
          to Bonneville in writing a revision or revisions to a forecast
          cost or actual cost or General Plant Cost in any amendment to an
          Operating Plan.  Such recommendation shall set forth, at a
          minimum, the exact revisions to the forecast cost or General Plant
          Cost proposed by the Committee and the reasons for such revisions.
          Failure of the Committee to recommend a revision or revisions to
          all or any portion of a forecast cost or General Plant Cost in the
          Operating Plan or a forecast cost or actual cost or General Plant
          Cost in any amendment to an Operating Plan within the applicable
          time limit set forth above shall be deemed to constitute
          acceptance by the Committee of all portions of the forecast costs
          and General Plant Cost of the Operating Plan for which the
          Committee has not recommended a revision.
     
     (f)  No later than 15 days after receipt of a Committee recommendation
          made pursuant to subsection 13(e), Bonneville may make a single
          request (which may contain multiple parts) in writing of the
          Committee for such supporting documentation, data, and information
          as may be reasonably necessary to analyze the Committee's
          recommendation, including without limitation, any estimated costs
          or forecast costs contained in such recommendation; provided,
          however, that the Capacity Owners that have appointed a
          representative to the Committee shall be under no obligation (1)
          to create additional
     
                                      62
     
          documentation, data, or information, (2) to provide documentation,
          data, or information that is not readily available to the
          Committee or to any Capacity Owner that has appointed a member to
          the Committee, (3) to provide to Bonneville documentation, data,
          or information that the Committee has previously provided to
          Bonneville; provided, further, that with regard to requests for
          documentation, data, and information pursuant to this subsection
          13(f), (1) Bonneville must designate in such request the specific
          item in the Committee's recommendation to which such requested
          documentation, data, or information is directly related and
          explain the need for such documentation, data, or information, and
          (2) Bonneville shall use reasonable efforts, consistent with
          Bonneville's needs as set forth in this subsection 13(f), to
          minimize and limit the scope and number of parts of the request
          for documentation, data, and information made pursuant to this
          subsection.  Such single request shall be made of the Committee by
          delivering a copy of the request to each Capacity Owner that has
          appointed a representative to the Committee.  The Committee shall
          have 20 days from the date of its receipt of Bonneville's request
          to provide a single response containing the documentation, data,
          and information requested.
     
     (g)  If the Committee makes any recommendation in writing pursuant to
          subsection 13(e), Bonneville shall have the greater of 15 days
          from the date of receipt of the requested documentation, data, and
          information requested pursuant to subsection 13(f) or, if none was
          requested, 30 days from the date of receipt of the Committee's
          recommendations made pursuant to subsection 13(e) to, by written
          notice to each Capacity Owner that has appointed a representative
          to the Committee, accept the recommendation, accept the
          recommendation in part, reject the recommendation, or propose an
          action that is responsive to the Committee's recommendation and
          that is different from Bonneville's proposal contained in the
          Operating Plan.  If Bonneville makes such a proposal, Bonneville
          shall set forth in such written notice the exact revisions to the
          Operating Plan.  The Committee shall have 7 days from the date of
          receipt of Bonneville's proposal to make any requests in writing
          for supporting
     
                                        63
     
          documentation, data, and information as set forth in subsection
          13(d).  Bonneville shall have 7 days to respond to those requests
          as set forth in subsection 13(d).  Failure of Bonneville to
          respond in writing to any recommendation of the Committee within
          the applicable time period set forth in this subsection 13(g)
          shall be deemed to constitute rejection of such recommendation.
     
     (h)  If Bonneville rejects all or any portion of the Committee's
          recommendation, or if the Committee elects not to accept a
          proposal made by Bonneville pursuant to subsection 13(g), then the
          Committee may
     
          (1)  elect by written notice to Bonneville to refer to binding
               arbitration, pursuant to section 14 and consistent with
               subsections 13(i) and 14(b), that portion of such
               recommendation of the Committee not accepted by Bonneville or
               that portion of a recommendation of the Committee to which
               Bonneville responded with a proposal pursuant to subsection
               13(g); and
          
          (2)  elect by written notice to Bonneville to refer to nonbinding
               arbitration pursuant to section 15 and consistent with
               subsections 15(a) and 15(d), that portion of such
               recommendation of the Committee not accepted by Bonneville or
               that portion of a recommendation of the Committee to which
               Bonneville responded with a proposal pursuant to subsection
               13(g).
          
          Failure of the Committee to elect to refer to arbitration
     
          (A)  such portion of any recommendation of the Committee not
               accepted by Bonneville within 15 days following Bonneville's
               rejection or acceptance in part of such recommendation of the
               Committee pursuant to subsection 13(g), or
                                        64
          
          (B)  any proposal made by Bonneville pursuant to subsection 13(g)
               within 15 days following Bonneville's written notice of such
               proposal or, if documentation, data, or information was
               requested by the Committee pursuant to subsection 13(g),
               within 15 days following receipt by the Committee of such
               documentation, data, or information pursuant to subsection
               13(g),
          
          shall be deemed to constitute acceptance by the Committee of
          Bonneville's rejection or acceptance in part of the recommendation
          of the Committee or of Bonneville's proposal and waiver by the
          Committee of any right pursuant to this section 13 or to section
          15 to arbitrate such recommendation or portion thereof.
     
     (i)  The Committee may, subject to the immediately succeeding sentence,
          arbitrate, pursuant to subsection 13(h), any recommendation by the
          Committee concerning a revision pursuant to this Agreement to a
          loss factor set forth in any Operating Plan or in any amendment to
          an Operating Plan or concerning any forecast cost or actual
          (allocated or otherwise) cost set forth in any Operating Plan or
          in any amendment to an Operating Plan (including the following
          costs and related items set forth in any Operating Plan, or in any
          amendment to an Operating Plan, pursuant to Exhibit I, Schedule A,
          lines 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12 and 13; Exhibit I,
          Schedule B, lines 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14
          and 15; Exhibit I, Schedule C, lines 1, 2, 3, 4 and 5; Exhibit I,
          Schedule D, lines 3, 4, 5, 6, 7, 8, 9, 10 and 11; Exhibit I,
          Schedule E, lines 2 and 3; Exhibit I, Schedule F, lines 1, 2, 3,
          4, 5, 6, 7, 8, and 9; Exhibit I, Schedule G, lines 1, 2, 3, 4, 5,
          6 7, 8, and 9; and Exhibit I, Schedule H, lines 1, 2, 3, and 4).
          The Committee's right pursuant to this subsection 13(i) to
          arbitrate any such recommendation shall be subject to the
          following limitations:
     
          (1)  if such recommendation, or portion thereof, includes a
               Replacement Cost for a Replacement or a Reinforcement Cost
               for a Reinforcement, and such Replacement Cost or
               Reinforcement Cost was included in a previous Operating Plan
          
                                        65
          
               (either of such costs, a Previous Operating Plan Cost), the
               Committee may arbitrate pursuant to this subsection 13(i)
               such recommendation, or portion thereof, only to the extent
               that such recommendation, or portion thereof, includes any
               Replacement Cost or Reinforcement Cost in excess of the
               Previous Operating Plan Cost;
          
          (2)  the Committee may arbitrate pursuant to this subsection 13(i)
               any such recommendation, or portion thereof, pertaining to a
               revision to a loss factor pursuant to this Agreement only to
               the extent such arbitration is permitted by subsection 10(b);
          
          (3)  the Committee may arbitrate pursuant to this subsection 13(i)
               any recommendation, or portion thereof, concerning an Other
               Cost only to the extent that such Other Cost is a cost set
               forth in an Operating Plan or amendment to an Operating Plan
               pursuant to Exhibit I, Schedule E, line 2 and such
               recommendation, or portion thereof pertains to whether such
               Other Cost is properly allocated to Bonneville's PNW AC
               Intertie pursuant to Exhibit I, section V;
          
          (4)  if the sum of the actual Operations Costs, actual Maintenance
               Costs, General Plant Costs, actual Other Costs, actual
               Contracts and Rates Costs, actual Power Scheduling Costs, and
               actual End of Term Costs in any Operating Plan exceeds 105
               percent of the sum of the forecast Operations Costs, forecast
               Maintenance Costs, General Plant Costs, forecast Other Costs,
               forecast Contracts and Rates Costs, forecast Power Scheduling
               Costs, and forecast End of Term Costs set forth in such
               Operating Plan or in any amendment to an Operating Plan, the
               Committee may arbitrate pursuant to this subsection 13(i) any
               such recommendation, or portion thereof, concerning any
               actual cost for any activity or project described in such
               Operating Plan only to the extent that such actual cost
               exceeds 105 percent of the forecast cost for such activity or
               such project; provided, however, that, without limiting any
               of Puget's rights
          
                                         66
          
               and benefits pursuant to subsection 16(c), the Committee may
               not arbitrate pursuant to this subsection 13(i) any
               recommendation, or portion thereof, concerning any actual
               cost for any activity or project described in such Operating
               Plan or in any amendment to an Operating Plan if such actual
               cost is less than 105 percent of the forecast for such
               activity or such project;
          
          (5)  the Committee may not arbitrate, pursuant to this subsection
               13(i), (a) the allocation by Bonneville pursuant to this
               Agreement of any of its costs to overall overhead costs or to
               overall indirect costs, or (b) the allocation by Bonneville
               pursuant to this Agreement of a portion of Bonneville's
               overall overhead costs and overall indirect costs to its
               total system operations costs, its total system maintenance
               costs, its total capital costs or its total indirect and
               overhead power scheduling costs; provided, however, that
               nothing in this paragraph (5) shall be deemed to prevent or
               restrict the Committee from arbitrating pursuant to this
               subsection 13(i) the level (rather than the allocation) of
               any of Bonneville's Exhibit I, Schedule A, line 9 total
               system operations indirect costs and line 11 total system
               operations overhead costs; Bonneville's Exhibit I, Schedule
               B, line 11 total system maintenance indirect costs and line
               13 total system maintenance overhead costs; Bonneville's
               total capital costs; Bonneville's Exhibit I, Schedule F,
               line 6 total indirect contracts and rates costs and
               Bonneville's Exhibit I, Schedule F, line 7 total overhead
               contracts and rates costs; or Bonneville's Exhibit I,
               Schedule G, line 6 total indirect power scheduling costs and
               Bonneville's Exhibit I, Schedule G, line 7 total overhead
               power scheduling costs;
          
                                               67
          
          (6)  the Committee may not arbitrate any recommendation, or any
               portion thereof, regarding any amendment to an Operating Plan
               made pursuant to sections 9(b)(2)(A)(iv) and 9(b)(2)(B)(ii),
               or subsection 14(j), 16(e), or paragraph 16(f)(2);
          
          (7)  the Committee may not arbitrate any such recommendation, or
               portion thereof, to the extent that in doing so the
               arbitrators would be required to decide a matter of law in
               order to render a decision pursuant to subsection 14(h).  If,
               subsequent to the Effective Date, Bonneville is given legal
               authority to submit to binding arbitration matters of law,
               Bonneville shall enter into good faith negotiations with
               Puget and Capacity Owners other than Puget regarding a
               revision to this paragraph 13(i)(7) enabling arbitration of
               matters of law pursuant to this subsection 13(i) consistent
               with such legal authority; and
          
          (8)  the Committee may not arbitrate any recommendation, or
               portion thereof, regarding an allocation of a Reinforcement
               Cost to the extent prohibited by subsection 7(d).
          
          In arbitrating any recommendation, or portion thereof, pursuant to
          this subsection 13(i), the Committee may raise in support of such
          recommendation arguments regarding whether any forecast or actual
          cost should be based upon activities different in degree, but not
          in kind, from the activities upon which such forecast or actual
          cost in the Operating Plan is based.
     
     (j)  Each Operating Plan provided pursuant to subsection 13(b) which
          has completed the Committee review process set forth in
          subsections 13(d) through 13(g) shall take effect on the first day
          of the fiscal year to which such Operating Plan pertains and shall
          remain in effect for the duration of such fiscal year.
     
     (k) At any time during the fiscal year in which an Operating Plan is in
          effect, or within 8 months after the end of such fiscal year,
          Bonneville may amend such Operating Plan, pursuant to subsections
          13(l) through 13(n), to reflect a different forecast or actual
          Operations Cost, Maintenance Cost, General Plant Cost, Other Cost,
          Contracts and Rates Cost, Power Scheduling Cost, or End of Term
          Cost in such Operating Plan.  At any time during the fiscal year
          an Operating Plan
     
                                      68
     
          is in effect, or within 30 months after a work order for a
          Replacement or Reinforcement is closed, Bonneville may amend such
          Operating Plan, pursuant to subsections 13(l) through 13(n), to
          reflect a different forecast cost or actual cost component for
          such Replacement or Reinforcement.
     
     (l)  Any amendment made to any Operating Plan pursuant to subsection
          13(k) shall be provided by delivery of a copy in writing of such
          amendment by Bonneville to each Capacity Owner that has appointed
          a representative to the Committee.
     
     (m)  Consideration of amendments to the Operating Plan pursuant to
          subsection 13(l) shall be consistent with the procedures set forth
          above in subsections 13(c) through 13(k), except that the time
          limits set forth in such subsections shall be reduced as follows:
          15 days shall be 7 days, 20 days shall be 10 days, 30 days shall
          be 15 days, and 50 days shall be 25 days.  For purposes of
          computing the time limits in this subsection 13(m), the date
          Bonneville provides the Capacity Owners with a proposed amendment,
          pursuant to subsection 13(k), shall be deemed to be the date the
          annual meeting was convened for purposes of paragraph 13(d)(1) and
          subsection 13(e).
     
     (n)  Without limiting any of Puget's rights and benefits pursuant to
          subsection 13(i) and sections 14 and 15, any Operating Plan
          amended pursuant to section 9(b)(2)(A)(v) or 9(b)(2)(B)(iii), or
          subsection 13(k) shall take effect when such amendment is accepted
          by the Committee pursuant to subsection 13(e) or 13(h).  Any
          Operating Plan amended pursuant to section 9(b)(2)(A)(iii),
          9(b)(2)(A)(iv), 9(b)(2)(B)(i), or 9(b)(2)(B)(ii), or subsection
          14(j), 16(e), or paragraph 16(f)(2) shall take effect as soon as
          such amendment is delivered by Bonneville to each Capacity Owner
          that has appointed a representative to the Committee.
     
     (o)  An Operating Plan shall, during the fiscal year in which such
          Operating Plan is in effect, establish the costs which Puget is
          obligated to pay pursuant to the terms and conditions of this
     
                                        69
     
          Agreement.  In no event shall such Operating Plan, or any portion
          thereof, contain or constitute an obligation of Bonneville to
          undertake, or to expend funds on, activities described or
          indicated in such Operating Plan.

14.  ARBITRATION
     
     (a)  During any arbitration process conducted pursuant to this section
          14, Puget shall act through the Committee.  Each of Bonneville and
          Puget agrees to be bound by any decision rendered by the
          arbitrators in any arbitration brought pursuant to
          subsection 13(i) and this section 14.
     
     (b)  The Committee may initiate arbitration pursuant to subsection
          13(i) by taking the following actions:
     
          (1)  an affirmative vote to initiate arbitration by at least the
               respective representatives of all of the Capacity Owners that
               have appointed representatives to the Committee, less one;
               and
     
          (2)  either of the following:
          
               (a)  giving written notice to Bonneville of the Committee's
                    decision to initiate arbitration pursuant to subsection
                    13(i) within the applicable time period established in
                    subsection 13(h); or
               
               (b)  giving written notice to Bonneville of the Committee's
                    decision to initiate arbitration within 20 days after
                    the date on which Bonneville notifies in writing each
                    Capacity Owner that has appointed a representative to
                    the Committee of Bonneville's disagreement with any
                    exception pursuant to subsection 16(f).
               
          The notice referred to in this subsection 14(b) shall set forth in
          detail the matter or matters to be arbitrated and the name, street
          address and telephone number of the arbitrator appointed by the
          Committee.
          
                                              70

     (c)  Bonneville shall, within 10 Working Days after receipt of the
          notice by the Committee referred to in subsection 14(b), appoint a
          second arbitrator and provide by written notice to each Capacity
          Owner that has appointed a representative to the Committee the
          name, street address and telephone number of the arbitrator
          appointed by Bonneville.  The two arbitrators appointed by the
          Committee and by Bonneville, respectively, shall appoint a third
          arbitrator within 15 days after the date of the appointment of an
          arbitrator by Bonneville.
     
          (1)  If the arbitrators appointed by the Committee and by
               Bonneville, respectively, fail to appoint a third arbitrator
               within 15 days after the date of the appointment of an
               arbitrator by Bonneville, then within 30 days after the date
               of the appointment of an arbitrator by Bonneville, the
               Committee may apply to the Chief Judge of the United States
               District Court for the District of Oregon for appointment of
               a third arbitrator.
          
          (2)  If Bonneville fails to appoint an arbitrator within 15 days
               after receipt of the notice by the Committee referred to in
               subsection 14(b), then within 30 days after the date of such
               notice, the Committee may apply to the Chief Judge of the
               United States District Court for the District of Oregon for
               appointment of two arbitrators.
          
          (3)  If, pursuant to either paragraph 14(c)(1) or 14(c)(2), the
               Committee applies to the Chief Judge of the United States
               District Court for the District of Oregon for appointment of
               one or more arbitrators, then the Committee shall give
               Bonneville written notice of such application within 5 days
               after the date of filing such application.
     
     (d)  The three arbitrators appointed pursuant to subsections 14(b) and
          14(c) shall select by a majority vote an alternative pursuant to
          subsection 14(g).
     
                                             71
     
     (e)  Within 10 days after the appointment of a third arbitrator
          pursuant to subsection 14(c), the arbitrators shall establish a
          schedule for submission of written positions by Bonneville and
          Puget, respectively.  The arbitrators must establish a schedule
          for such submissions pursuant to this subsection 14(e) that will
          allow the arbitration to be concluded, and the decision of the
          arbitrators rendered pursuant to subsection 14(g), within 120 days
          following the date of the appointment of the third arbitrator.  A
          copy of any submission by the Committee to the arbitrators
          pursuant to this section 14 shall be simultaneously served by the
          Committee on Bonneville, and a copy of any submission by
          Bonneville to the arbitrators pursuant to this section 14 shall be
          simultaneously served by Bonneville on each Capacity Owner that
          has appointed a representative to the Committee.  The Committee
          shall state, in a letter to the arbitrators, as its proposed
          alternative to each Bonneville proposal in dispute, the
          recommendation proposed by the Committee pursuant to subsection
          13(g) and rejected in whole or in part by Bonneville pursuant to
          subsection 13(g).  Bonneville shall state its position and
          proposed resolution of the dispute in a letter to the arbitrators.
          If Bonneville made a proposal in response to such recommendation
          of the Committee pursuant to subsection 13(g), then such position
          and proposed resolution shall set forth such proposal, or if
          Bonneville made no such proposal, then such position and proposed
          resolution shall set forth the relevant portion of the Operating
          Plan.  If, however, the arbitration concerns an exception pursuant
          to paragraph 16(f)(3), then the positions and proposed resolutions
          of Bonneville and the Committee shall be as established pursuant
          to such subsection.  The Committee may then submit a response to
          Bonneville's letter, and Bonneville may thereafter submit a reply
          to the Committee's response.  Bonneville and the Committee shall
          have an equal number of days to prepare and serve their replies.
     
     (f)  No submission by either the Committee or Bonneville to the
          arbitrators pursuant to subsection 14(e) shall be more than 50
          pages in length (not including exhibits).  If requested in writing
          by either the
     
                                       72
     
          Committee or Bonneville, and for good cause shown, the arbitrators
          may permit any submission by such Party to exceed 50 pages.
     
     (g)  The arbitrators shall select, as between the Committee's
          recommendation pursuant to subsection 13(e), on the one hand, and
          the portion of Bonneville's proposed Operating Plan to which the
          Committee's recommendation pertains or Bonneville's proposal
          pursuant to subsection 13(g) not accepted by the Committee, on the
          other, the alternative which
     
          (1)  is consistent with the provisions of this Agreement and
          
          (2)  (A) in conformity with the generally accepted practices,
               methods, and acts in the electrical utility industry in the
               Western Systems Coordinating Council area prior thereto,
               would better achieve the desired result consistent with
               safety, reliability, and cost-benefit or (B) if there are no
               such generally accepted practices, methods, and acts in the
               electrical utility industry in the Western Systems
               Coordinating Council area, would, in the exercise of
               reasonable judgment in light of the facts known at the time
               the decision is made, be reasonably expected to better
               achieve the desired result consistent with safety,
               reliability, and cost-benefit.
          
     (h)  In applying the standards set forth in subsection 14(g), the
          arbitrators shall take into consideration, among other things (a)
          that Bonneville and Puget each have responsibilities for service
          to customers within and without the Pacific Northwest region in
          accordance with applicable law, (b) that Bonneville and others
          jointly own the PNW AC Intertie and Bonneville owes contractual
          obligations to those parties regarding the PNW AC Intertie, (c)
          that Bonneville must operate, as a practical matter, the PNW AC
          Intertie in coordination with the operation of the interconnected
          intertie facilities in California, and (d) that the PNW AC
          Intertie is a major import-export facility important to the
          service of loads in and out of the region.
     
                                         73
     
     (i)  In any arbitration pursuant to this section 14, the arbitrators
          shall choose, pursuant to subsection 14(g), only between the
          alternatives proposed by Bonneville and the Committee and shall
          have no authority to resolve such arbitration other than by
          selecting an alternative proposed by either Bonneville or the
          Committee.
     
     (j)  Upon selection by the arbitrators of an alternative pursuant to
          subsection 14(g), then Bonneville shall amend the Operating Plan
          to cause it to conform to the decision of the arbitrators.

     (k)  If the arbitrators have not made a selection of an alternative
          pursuant to subsection 14(i) before the date on which the
          Operating Plan becomes effective pursuant to subsection 13(j),
          then Puget shall make payments of annual charges pursuant to such
          Operating Plan.  If the arbitrators subsequently select the
          Committee's alternative, then Bonneville shall, subsequent to
          amending such Operating Plan pursuant to subsection 14(j), refund
          to or bill Puget its pro rata share of the amount of the
          incremental difference between the costs set forth in such
          Operating Plan as amended pursuant to subsection 14(j) and 105
          percent of the costs set forth in such Operating Plan, prior to
          its amendment pursuant to subsection 14(j), to the extent that
          such costs were incurred during the period from the first day of
          effectiveness of such Operating Plan pursuant to subsection 13(j)
          to the date of the arbitrators' decision, such refund to be made
          pursuant to subsection 9(f) and such payment to be made pursuant
          to subsection 9(b).
     
     (l)  Bonneville shall be responsible to pay a fraction of the costs for
          the services and expenses of the arbitrators pursuant to this
          section 14 equal to 1  (n + 1), where "n" equals the number of
          Capacity Owners.  The Committee shall be responsible to pay the
          balance of the costs for the services and expenses of the
          arbitrators.  Each of Bonneville and the Committee shall pay its
          own expenses related to the arbitration proceeding including,
          without limitation, attorney fees, costs incurred in development
          and preparation of documents, staff costs, and compensation for
          consultants.
     
                                       74
     
     (m)  Any judgment rendered by a court of competent jurisdiction upon an
          award made by the arbitrators pursuant to this section 14 may be
          entered in any court having jurisdiction thereof.

15.  NONBINDING ARBITRATION

     (a)  The Initiating Party (as defined in paragraph 15(e)(1)) may,
          subject to the immediately succeeding sentence, elect by written
          notice to Responding Party (as defined in paragraph 15(e)(1)) to
          refer to nonbinding arbitration pursuant to the other provisions
          of this section 15 the following:  (i) if the Initiating Party is
          the Committee, any recommendation by the Committee, or any portion
          thereof, concerning any forecast cost or actual cost set forth in
          any Operating Plan or in any amendment to an Operating Plan
          pursuant to Exhibit I, Schedule A, lines 9 and 11; Exhibit I,
          Schedule B, lines 11 and 13; Exhibit I, Schedule D, lines 1 and 2;
          Exhibit I, Schedule F, lines 6 and 7; and Exhibit I, Schedule G,
          lines 6 and 7 and (ii) any other issue, dispute, or controversy
          regarding the Parties' respective rights and obligations pursuant
          to this Agreement.  The Initiating Party's right pursuant to this
          subsection 15(a) to arbitrate any recommendation or any issue,
          dispute or controversy shall be subject to the following
          limitations:
     
          (1)  the Initiating Party may not arbitrate pursuant to this
               subsection 15(a):  (A) any recommendation with respect to an
               Operating Plan or any amendment to an Operating Plan or
               (B) any issue, dispute, or controversy, which recommendation,
               issue, dispute or controversy may be arbitrated pursuant to
               subsection 13(i) or 16(f);
          
          (2)  the Initiating Party may not arbitrate pursuant to this
               subsection 15(a) any recommendation not permitted to be
               arbitrated pursuant to paragraphs 13(i)(1), 13(i)(3),
               13(i)(4), and 13(i)(8);
          
          (3)  the Initiating Party may not arbitrate pursuant to this
               subsection 15(a) any recommendation, issue, dispute, or
          
                                               75
          
               controversy concerning a loss factor or revision to a loss
               factor set forth in Exhibit E, Part A or Part B pursuant to
               this Agreement;
          
          (4)  the Committee may not (but the Puget or Bonneville may)
               arbitrate pursuant to this subsection 15(a) any
               recommendation, issue, dispute, or controversy concerning any
               right or obligation of Puget pursuant to this Agreement that
               is not a right or obligation, as the case may be, of each
               other Capacity Owner under its respective Capacity Ownership
               Agreement; or
          
          (5)  if the sum of the actual Operations Costs, actual Maintenance
               Costs, General Plant Costs, actual Other Costs, actual
               Contracts and Rates Costs, actual Power Scheduling Costs and
               actual End of Term Costs in any Operating Plan exceeds 105
               percent of the sum of the forecast Operating Costs, forecast
               Maintenance Costs, General Plant Costs, forecast Other Costs,
               forecast Contracts and Rates Costs, forecast Power Scheduling
               Costs and forecast End of Term Costs set forth in such
               Operating Plan, the Committee may arbitrate pursuant to this
               subsection 15(a) any recommendation, or portion thereof,
               concerning any actual cost for any activity or project set
               forth in any Operating Plan or in any amendment to an
               Operating Plan pursuant to Exhibit I, Schedule A, lines 9 and
               11; Exhibit I, Schedule B, lines 11 and 13; Exhibit I,
               Schedule D, lines 1 and 2; Exhibit I, Schedule F, lines 6 and
               7; and Exhibit I, Schedule G, lines 6 and 7 only to the
               extent that such actual cost exceeds 105 percent of the
               forecast for such activity or such project; provided,
               however, that, without limiting any of Puget's rights and
               benefits pursuant to section 16(f), no Initiating Party may
               arbitrate pursuant to this subsection 15(a) any
               recommendation, or portion thereof, concerning any actual
               cost for any activity or project set forth in any Operating
               Plan or in any amendment to an Operating Plan pursuant to
               Exhibit I, Schedule A, lines 9 and 11; Exhibit I, Schedule B,
          
                                               76
          
               lines 11 and 13; Exhibit I, Schedule D, lines 1 and 2;
               Exhibit I, Schedule F, lines 6 and 7; and Exhibit I, Schedule
               G, lines 6 and 7 if such actual cost is less than 105 percent
               of the forecast for such activity or such project; and
          
          (6)  the Initiating Party may not arbitrate pursuant to this
               subsection 15(a) any issue, dispute, or controversy (A)
               concerning matters of ratemaking (for purposes of this
               subsection 15(a), the term "ratemaking" shall mean the
               determination of matters appropriately determined pursuant to
               section 7(i) of the Regional Act, including (i) Bonneville's
               revenue requirements (including without limitation
               Bonneville's depreciation and repayment standards and planned
               net revenues for risk, but excluding program level issues
               determined in the Federal budget process), (ii) Bonneville's
               cost of service analysis (including functionalization,
               segmentation, and allocation of costs contained in such
               analysis, but excluding any allocation of costs contemplated
               in Exhibit I), (iii) Bonneville's rate design, and (iv) any
               related environmental analysis of proposed rates; (B)
               concerning a final action of Bonneville, which final action
               is not itself performance of any obligation of Bonneville or
               Bonneville's Administrator under this Agreement; or (C)
               concerning, or requiring the decision of, a matter not
               arising under this Agreement or the other Capacity Ownership
               Agreements.
     
     (b)  Except as otherwise provided in paragraph 15(a)(4), all
          arbitrations pursuant to this section 15 shall be between
          Bonneville and the Committee.

     (c)  A copy of any submission (including, without limitation, any
          statement of position or any brief) by the Initiating Party or the
          Responding Party to the arbitrators pursuant to this section 15
          shall be simultaneously served by such party on the Responding
          Party or Initiating Party, respectively.  No submission by either
          the Initiating
     
                                        77
     
          Party or the Responding Party to the arbitrators shall be more
          than 50 pages in length (not including exhibits).  If requested in
          writing by either the Initiating Party or the Responding Party,
          and for good cause shown, the arbitrators may permit any
          submission by such party to exceed 50 pages.
     
     (d)  With respect to any arbitration pursuant to this section 15 of any
          forecast cost or actual cost set forth in any Operating Plan or in
          any amendment to an Operating Plan pursuant to Exhibit I, Schedule
          A, lines 9 and 11; Exhibit I, Schedule B, lines 11 and 13; Exhibit
          I, Schedule D, lines 1 and 2; Exhibit I, Schedule F, lines 6 and
          7; and Exhibit I, Schedule G, lines 6 and 7, the following shall
          apply:
          
          (1)  Only the Committee may initiate arbitration with respect to
               any forecast cost or actual cost set forth in any Operating
               Plan or in any amendment to an Operating Plan pursuant to
               Exhibit I, Schedule A, lines 9 and 11; Exhibit I, Schedule B,
               lines 11 and 13; Exhibit I, Schedule D, lines 1 and 2;
               Exhibit I, Schedule F, lines 6 and 7; and Exhibit I, Schedule
               G, lines 6 and 7.  The Committee may initiate nonbinding
               arbitration pursuant to this section 15 by taking the
               following actions:
          
               (A)  an affirmative vote to initiate arbitration pursuant to
                    this section 15 by the respective representatives of all
                    of the Capacity Owners that have appointed
                    representatives to the Committee, less one; and
               
               (B)  either of the following:
               
                       (i) giving written notice to Bonneville of the
                          Committee's decision to initiate arbitration
                          pursuant to this section 15 within the applicable
                          time period set forth in subsection 13(h); or
                    
                      (ii) giving written notice to Bonneville of the
                          Committee's decision to initiate arbitration
                    
                                             78
                    
                           within 20 days after the date on which Bonneville
                          notifies in writing each Capacity Owner that has
                          appointed a representative to the Committee of
                          Bonneville's disagreement with any exception
                          pursuant to subsection 16(f).
                    
                    The notice referred to in this subparagraph 15(d)(1)(B)
                    shall (x) indicate that such vote has been taken and (y)
                    set forth in detail the matters to be arbitrated and the
                    name, street address and telephone number of the
                    arbitrator appointed by the Committee.
          
          (2)  The respective rights and obligations of the Committee and of
               Bonneville with respect to arbitration pursuant to this
               subsection 15(d), unless otherwise provided in this
               subsection 15(d), shall be as set forth in subsections 14(d)
               through 14(l).
          
     (e)  With respect to any arbitration pursuant to this section 15 of any
          issue, dispute, or controversy other than with respect to any
          forecast cost or actual cost set forth in any Operating Plan or in
          any amendment to an Operating Plan pursuant to Exhibit I, Schedule
          A, lines 9 and 11; Exhibit I, Schedule B, lines 11 and 13; Exhibit
          I, Schedule D, lines 1 and 2; Exhibit I, Schedule F, lines 6 and
          7; and Exhibit I, Schedule G, lines 6 and 7, the following shall
          apply:
     
          (1)  The party (which term, for purposes of this subsection 15(e),
               shall refer to Bonneville, on the one hand, and to the
               Committee or Puget, on the other) initiating arbitration
               (Initiating Party) shall initiate arbitration pursuant to
               this section 15 by serving written notice on the other party
               (Responding Party) of its initiation of arbitration.  If the
               Committee is the party initiating arbitration, the Committee,
               in addition to serving such notice, shall initiate such
               arbitration by an affirmative vote to do so of at least the
               respective representatives of all of the Capacity Owners that
               have appointed representatives to the Committee, less one.
          
                                             79
          
               The Committee shall indicate that such vote has been taken in
               such notice to Bonneville.  Any such notice by an Initiating
               Party shall set forth in detail the following:  (A) the
               issue, dispute, or controversy to be arbitrated and the
               Initiating Party's position regarding such issue, dispute, or
               controversy; (B) the relief sought by the Initiating Party;
               and (C) the name, street address, and telephone number of the
               arbitrator appointed by the Initiating Party.  The Responding
               Party shall, within 15 days after receipt of the notice by
               the Initiating Party referred to in this subsection 15(e),
               appoint a second arbitrator and provide written notice to the
               Initiating Party and to the arbitrator appointed by the
               Initiating Party of the name, street address and telephone
               number of the arbitrator appointed by the Responding Party.
               The arbitrators appointed by the Initiating Party and by
               Bonneville, respectively, shall appoint a third arbitrator
               within 15 days after the date of the appointment of an
               arbitrator by the Responding Party.
     
               (A)  If the arbitrators appointed by the Initiating Party and
                    by the Responding Party, respectively, fail to appoint a
                    third arbitrator within 15 days after the date of the
                    appointment of an arbitrator by the Responding Party,
                    then within 30 days after the date of the appointment of
                    an arbitrator by the Responding Party the Initiating
                    Party may apply to the Chief Judge of the United States
                    District Court for the District of Oregon for
                    appointment of a third arbitrator.
          
               (B)  If the Responding Party fails to appoint an arbitrator
                    within 15 days after receipt of the notice by the
                    Initiating Party referred to in paragraph 15(e)(1), then
                    within 30 days after the date of such notice the
                    Initiating Party may apply to the Chief Judge of the
                    United States District Court for the District of Oregon
                    for appointment of two arbitrators.
               
                                        80
          
               (C)  If, pursuant to either subparagraph 15(e)(1)(A) or
                    15(e)(1)(B), the Initiating Party applies to the Chief
                    Judge of the United States District Court for the
                    District of Oregon for appointment of one or more
                    arbitrators, then the Initiating Party shall give the
                    Responding Party written notice of such application
                    within one day after the date of filing such
                    application.
     
          (2)  The three arbitrators appointed pursuant to paragraph
               15(e)(1) shall decide any issue, dispute, or controversy by
               majority vote.
     
          (3)  Within 20 days after the appointment of a third arbitrator
               pursuant to paragraph 15(e)(1) with respect to any
               arbitration pursuant to this subsection 15(e), the
               arbitrators shall establish a schedule for the completion of
               such arbitration.  The first day pursuant to such schedule
               shall be hereafter referred to in this subsection 15(e) as
               the "Arbitration Commencement Date."
          
          (4)  No later than 15 days after the Arbitration Commencement
               Date, the Initiating Party may make a single request in
               writing to the Responding Party for documentation, data, and
               information relevant to or reasonably necessary to support
               the Initiating Party's position communicated to the
               Responding Party pursuant to paragraph 15(e)(1).  Such single
               request may contain multiple parts.  The Initiating Party
               shall use reasonable efforts to minimize and limit the scope
               and number of parts of the request for documentation, data,
               and information pursuant to this paragraph.
          
          (5)  The Responding Party shall have 20 days from the date it
               receives the request from the Initiating Party pursuant to
               paragraph 15(e)(4) to provide the documentation, data, and
               information requested; provided, however, that the Responding
               Party shall be under no obligation pursuant to this paragraph
               15(e)(5)(A) to create additional documentation, data, or
          
                                                 81
               information, (B) to provide documentation, data, or
               information that is not readily available to it, (C) to
               provide to the Committee documentation, data, or information
               that Bonneville has previously provided to the Initiating
               Party or (D) if Bonneville is the Responding Party, to
               provide documentation, data, or information that Bonneville
               would not otherwise be required to provide or that would
               otherwise be exempted from disclosure pursuant to the Freedom
               of Information Act, 5 U.S.C. section 552 (including, without
               limitation, the Freedom of Information Reform Act of 1986),
               as amended or superseded, or pursuant to any regulation and
               Executive Order applicable to Bonneville.
          
          (6)  No later than 15 days after the Arbitration Commencement
               Date, the Responding Party may make a single request in
               writing to the Initiating Party for documentation, data and
               information relevant to Initiating Party's position
               communicated to the Responding Party pursuant to subsection
               15(e)(4).  Such single request may contain multiple parts.
               The Responding Party shall use reasonable efforts to minimize
               and limit the scope and number of parts of the request for
               documentation, data and information pursuant to this
               paragraph.
          
          (7)  The Initiating Party shall have 20 days from the date it
               receives the request from the Responding Party pursuant to
               paragraph 15(e)(6) to provide the documentation, data and
               information requested; provided, however, that the Initiating
               Party shall be under no obligation pursuant to this paragraph
               15(e)(7) (A) to create additional documentation, data, or
               information, (B) to provide documentation, data or
               information that is not readily available to it, (C) to
               provide to the Responding Party documentation, data, or
               information that the Initiating Party has previously provided
               to the Responding Party or (D) if Bonneville is the
               Initiating Party, to provide documentation, data, or
               information that Bonneville would not
          
                                        82
          
               otherwise be required to provide or that would otherwise be
               exempted from disclosure pursuant to the Freedom of
               Information Act, 5 U.S.C. section 552 (including, without
               limitation, the Freedom of Information Act of 1986), as
               amended or superseded, or pursuant to any regulation and
               Executive Order applicable to Bonneville.
          
          (8)  For purposes of this subsection 15(e), each of the Initiating
               Party and the Responding Party shall cooperate and use
               reasonable efforts to, in a timely manner, resolve disputes
               regarding, and clarify requests by it for, documentation,
               data, and information and responses to such requests.
     
          (9)  Within 65 days following the Arbitration Commencement Date,
               each of the Initiating Party and the Responding Party may
               state in reasonable detail its position regarding any issue,
               dispute or controversy to be arbitrated pursuant to this
               subsection 15(e) in a letter to the arbitrators and to the
               other party to the arbitration of such issue, dispute, or
               controversy  Within 85 days following the Arbitration
               Commencement Date, each of the Initiating Party and the
               Responding Party may submit a letter to the arbitrators and
               to the other party responding to the letter that the other
               submitted to the arbitrators pursuant to the immediately
               preceding sentence.
          
          (10) The arbitrators shall resolve any issue, dispute, or
               controversy pursuant to this subsection 15(e) by deciding
               (taking into consideration, among other things, any letter
               submitted by the Initiating Party or the Responding Party
               with respect to such issue, dispute, or controversy) whether
               the position of the Initiating Party or the position of the
               Responding Party regarding the action taken or proposed to be
               taken by the Responding Party conforms more closely with the
               standard for such action set forth in this Agreement.  The
               arbitrators shall have no authority to fashion a resolution
               of such arbitration other than pursuant to this paragraph
               15(e)(10).
          
                                         83
     
     (f)  Any selection by the arbitrators of an alternative pursuant to
          subsection 15(d) and any decision by the arbitrators pursuant to
          subsection 15(e) shall be reported by the Initiating Party to the
          Bonneville Administrator (Administrator) for review within 30 days
          after such selection or decision is made.  The Administrator shall
          either accept or reject in writing such selection or decision.  If
          the Administrator fails to either accept or reject such selection
          or decision, as the case may be, within 90 days after such
          selection or decision is made, such selection or decision, as the
          case may be, shall be deemed to be accepted by the Administrator.

     (g)  If the Administrator accepts any selection by the arbitrators of
          an alternative pursuant to subsection 15(d) or any decision by the
          arbitrators pursuant to subsection 15(e), such selection or
          decision shall become binding upon Puget and Bonneville at the
          time of its acceptance.

     (h)  The Administrator may reject any selection by the arbitrators of
          an alternative pursuant to subsection 15(d) or any decision by the
          arbitrators pursuant to subsection 15(e) only for one or more of
          the following reasons:

          (1)  the arbitrators did not follow the arbitration procedures set
               forth in this section 15;
          
          (2)  the arbitrators decided a matter that is not a matter arising
               under this Agreement as set forth in paragraph 15(a)(6);
          
          (3)  the arbitrators did not completely apply the appropriate
               standard for arbitration pursuant to this section 15;
          
          (4)  the arbitrators granted relief in contravention of this
               Agreement;                  84
          
          (5)  the arbitrators' decision is not supported by substantial,
               competent evidence; or
          
          (6)  implementation of the arbitrators' decision would cause
               Bonneville to violate a statutory obligation of Bonneville's
               or would cause Bonneville to breach a contractual obligation
               not in contravention of this Agreement.
          
     (i)  Bonneville shall be responsible to pay a fraction of the costs for
          the services and expenses of the arbitrators pursuant to this
          section 15 equal to 1 divided by (n + 1), where "n" equals the
          number of Capacity Owners.  The Committee shall be responsible to
          pay the balance of the costs for the services and expenses of the
          arbitrators.  Each of Bonneville and the Committee shall pay for
          its own expenses related to the arbitration proceeding, including,
          without limitation, attorney fees, costs incurred in development
          and preparation of documents, staff costs, and compensation for
          consultants.
     
     (j)  If the Initiating Party elects to arbitrate any issue, dispute, or
          controversy pursuant to this section 15, the Initiating Party must
          initiate arbitration of such issue, dispute, or controversy within
          one year following the occurrence of the event giving rise to such
          issue, dispute, or controversy.  Failure of the Initiating Party
          to initiate arbitration of any such issue, dispute, or controversy
          within such one-year period shall constitute a waiver of the
          Initiating Party's right to arbitrate such issue, dispute, or
          controversy pursuant to this section 15.

16.  AUDIT RIGHTS

     (a)  The Committee shall have the right to perform an audit of
          Bonneville's books, records, and documents used in or relating to
          the determination of the Adjusted Capacity Ownership Price, or
          used in or relating to any billing or refund with respect to the
          Adjusted Capacity Ownership Price.  Such audit shall be performed
          within 24 months
     
                                       85
     
          after the date of Bonneville's bill or refund voucher rendered by
          Bonneville pursuant to subparagraph 9(a)(2)(B).
     
     (b)  The Committee shall have the right to perform an audit of
          Bonneville's books, records and documents used in or relating to
          the determination of any Revised Adjusted Capacity Ownership
          Price, or used in or relating to any billing or refund with
          respect to any Revised Adjusted Capacity Ownership Price.  Such
          audit shall be performed within 24 months after the date of
          Bonneville's bill or refund voucher rendered by Bonneville
          pursuant to subparagraph 9(a)(3)(B).
     
     (c)  The Committee shall have the right to audit Bonneville's books,
          records, and documents (i) used in or relating to the
          determination of any charge (including, without limitation, any
          MFU count made pursuant to section I.A of Exhibit I) billed to
          Puget pursuant to paragraph 9(b)(2) and subsection 9(c), or
          (ii) used in or relating to any billing or refund with respect to
          any such charge.  Such audit shall be performed within 36 months
          after the date of Bonneville's bill or refund voucher for such
          charge rendered by Bonneville to Puget pursuant to paragraph
          9(b)(2) or subsection 9(c), as the case may be.
     
     (d)  Bonneville shall not be responsible to pay any of the expenses
          incurred by any of the Capacity Owners in performing any audit
          pursuant to this section 16.  Bonneville shall not directly charge
          Puget or any Capacity Owner other than Puget for Bonneville's
          costs incurred by Bonneville with respect to any audit pursuant to
          this section 16 unless Bonneville develops a general practice of
          charging, through direct charges, each of its customers for such
          costs incurred by Bonneville in connection with audits undertaken
          pursuant to those customers' respective contracts with Bonneville.
     
     (e)  After completing any audit specified above, the Committee shall
          promptly provide to Bonneville a written report of the results of
          such audit.  If such audit report includes any exception taken as
          a result of such audit and Bonneville agrees with such exception,
          Bonneville
     
                                        86
     
         shall, within 30 days following Bonneville's receipt of such audit
          report and consistent with such audit exception,
     
          (1)  if such exception is with respect to the Adjusted Lump Sum
               Payment or to any Revised Adjusted Lump Sum Payment, render
               to Puget a revised bill or refund voucher pursuant to
               paragraph 9(a)(2)(B) or 9(a)(3)(B), respectively, with
               respect to such Adjusted Lump Sum Payment or such Revised
               Adjusted Lump Sum Payment, and
          
          (2)  if such exception is with respect to an Operating Plan, amend
               the Operating Plan to which such exception pertains and
               either (A) render to Puget a revised bill, consistent with
               such Operating Plan, pursuant to the applicable GTRSPs set
               forth in Exhibit A and to the Billing Provisions set forth in
               Part B of Exhibit B or (B) cause to be refunded to Puget as a
               lump sum payment, within 30 days after the date on which such
               Operating Plan is so amended, an amount consistent with such
               Operating Plan (multiplied by Puget's Capacity Ownership
               Percentage).
          
          The amount of any refund or bill payable pursuant to this
          subsection 16(e) shall be paid with interest on such amount
          calculated at a rate equal to the weighted average of Bonneville's
          then-outstanding bonds or other debt instruments from (and
          including) the date on which such audit report is received by
          Bonneville to (but excluding) the date on which such amount is
          refunded to Puget.
     
     (f)  If an audit report provided to Bonneville by Puget pursuant to
          subsection 16(e) includes any exception taken as a result of such
          audit and Bonneville does not agree with such exception, then the
          following shall apply:
     
          (1)  Bonneville may, within 30 days following its receipt of such
               audit report, propose to the Committee a resolution of any
          
                                            87
          
               inconsistency noted in any exception taken as a result of
               such audit;
          
          (2)  If the Committee accepts such resolution proposed by
               Bonneville, then Bonneville shall, within 30 days following
               Bonneville's receipt of such audit report and consistent with
               such resolution,
          
               (A)  if such exception is with respect to the Adjusted Lump
                    Sum Payment or to any Revised Adjusted Lump Sum Payment,
                    render to Puget a revised bill or refund voucher
                    pursuant to subparagraph 9(a)(2)(B) or 9(a)(3)(B),
                    respectively, with respect to such Adjusted Lump Sum
                    Payment or such Revised Adjusted Lump Sum Payment, and
          
               (B)  if such exception is with respect to an Operating Plan,
                    amend the Operating Plan to which such exception
                    pertains and shall either (i) render to Puget a revised
                    bill, consistent with such Operating Plan, pursuant to
                    the applicable GTRSPs set forth in Exhibit A and to the
                    Billing Provisions set forth in Part B of Exhibit B or
                    (ii) cause to be refunded to Puget as a lump sum
                    payment, within 30 days after the date on which such
                    Operating Plan is so amended, an amount consistent with
                    such Operating Plan (multiplied by Puget's Capacity
                    Ownership Percentage).
          
               The amount of any refund or bill payable pursuant to this
               paragraph 16(f)(2) shall be paid with interest on such amount
               calculated at a rate equal to the weighted average of
               Bonneville's then-outstanding bonds or other debt instruments
               from (and including) the date on which such resolution is
               accepted by the Committee to (but excluding) the date on
               which such amount is refunded to Puget; and
               
                                              88
          
          (3)  If the Committee does not accept such resolution, if any,
               proposed by Bonneville with respect to any such exception, or
               if Bonneville does not propose any such resolution, then the
               Committee
          
               (A)  shall have the right to arbitrate, pursuant to section
                    14, any cost with respect to which such exception is
                    taken to the extent that such cost is permitted to be
                    arbitrated pursuant to subsection 13(i); and
               
               (B)  shall have the right to arbitrate, pursuant to section
                    15, any cost with respect to which such exception is
                    taken to the extent that such cost is permitted to be
                    arbitrated pursuant to section 15.
               
          The Committee must refer to arbitration pursuant to subparagraph
          16(f)(3)(A) or 16(f)(3)(B) any cost to which exception is taken as
          a result of any audit within eight months after the date the
          Committee commences such audit.  Failure of the Committee to elect
          to so refer to arbitration any cost within such eight-month period
          shall be deemed to constitute waiver by the Committee of any right
          pursuant to this section 16 to arbitrate such cost.
     
     (g)  Puget shall have the right to participate in any audit pursuant to
          this section 16 only by acting through the Committee.  If Puget
          chooses not to participate in any audit undertaken by the
          Committee, then Puget shall accept the findings of the Committee
          with respect to such audit and any resolution by the Committee and
          Bonneville of any inconsistency noted in any exception taken as a
          result of such audit.
     
     (h)  Any audits undertaken by the Committee shall be upon reasonable
          notice to Bonneville and at reasonable times and shall commence no
          more frequently than once in any 24 consecutive months.  The audit
          rights provided in this section shall not be construed to permit a
          general audit of Bonneville's books, records, and documents.
          Audits shall be in conformance with generally accepted auditing
          standards.
     
                                           89
     
          Prior to and for the duration of any audit, Bonneville shall
          retain all pertinent books, records, and documents prepared in the
          normal course of business.  After commencement of an audit
          pursuant to subsection 16(a), 16(b), or 16(c), the Committee may
          request and Bonneville shall promptly provide reasonably available
          supporting documentation for any cost or charge subject to audit.
          If the Committee fails to commence an audit pursuant to subsection
          16(a), 16(b), or 16(c) within the time periods set forth in
          subsection 16(a), 16(b), or 16(c), such failure shall constitute
          waiver by Puget of any right pursuant to this section 16 to
          arbitrate any charge or refund billed or refunded by Bonneville.
     
     (i)  If Puget is operating pursuant to paragraph 3(b)(1), Bonneville
          shall have the right, at its own expense, to review Puget's books,
          records, and documents that directly pertain to the revenue
          reportable in Puget's accounting system where revenues received
          for wheeling for other entities would be booked for the purpose of
          verifying compliance with paragraph 3(b)(1).  Bonneville shall
          have the right to perform such audit no more frequently than once
          every 36 months.

17.  PROTECTED AREAS

     Puget shall not use its Scheduling Share for transmission of power on
     the PNW AC Intertie from new hydroelectric projects which are
     constructed in Columbia River Basin Protected Areas after designation
     thereof by Bonneville unless Puget is required by regulatory authority
     to purchase or provide transmission for the output of such project or
     unless Bonneville receives sufficient demonstration that a particular
     project would provide benefits to Bonneville's existing or planned fish
     and wildlife investments or the Pacific Northwest Electric Power and
     Conservation Planning Council's Fish and Wildlife Program.  The Parties
     agree that System Sales shall not be taken into consideration in any
     determination of whether Puget has used its Scheduling Share for
     transmission of power on the PNW AC Intertie from the hydroelectric
     projects referred to in the immediately preceding sentence.  For
     purposes of this section 17, "System Sale" means any sale of power or
     energy to Puget or by a seller of power or energy, which power or
     energy is not
     
                                     90
     
     resource-specific and is delivered to Puget at a point that connects
     one or more resources or transmission systems.

18.  ESTABLISHMENT AND MAINTENANCE OF RATES AND RELIEF FROM REGULATORY
     ACTION

     (a)  Bonneville shall use good faith efforts to maintain in effect such
          of the following rates that has been approved by FERC on an
          interim or final basis, during the rate approval period
          established by FERC for such rate:
     
          (1)  any rate containing the terms set forth in Exhibit B, Part A
               and Part B, on the Effective Date;
          
          (2)  the Initial Successor Rate;
          
          (3)  the Alternative Successor Rate; and
          
          (4)  the Bonneville Successor Rate.
     
     (b)  If Bonneville's Administrator submits to FERC a rate that is
          different from that set forth in Exhibit B, Part A and Part B, on
          the Effective Date, as the first rate proposed by Bonneville
          (Initial Successor Rate) to replace the AC-93 rate set forth in
          Exhibit A or that is for a rate approval period which is less than
          the remainder of the Term following the expiration of the AC-93
          rate, Puget may, within 90 days after Bonneville submits the
          Initial Successor Rate to FERC and without regard to FERC's
          interim or final disposition of such rate, elect by written notice
          to Bonneville to terminate this Agreement and shall in such notice
          to Bonneville elect to exercise one of the two following options:
     
          (1)  Puget may elect to proceed pursuant to paragraphs 18(f)(1),
               18(f)(2), and 18(f)(3); or
          
                                             91
          
          (2)  Puget may elect to have its Initial Lump Sum Payment,
               Adjusted Lump Sum Payment, or any Revised Adjusted Lump Sum
               Payment, whichever has been most recently paid by Puget to
               Bonneville pursuant to subsection 9(a), refunded by
               Bonneville subject to the following terms and conditions:
          
               (A)  This Agreement shall terminate upon the date Bonneville
                    receives Puget's notification to terminate this
                    Agreement pursuant to this subsection 18(b) except for
                    those rights and obligations set forth in this paragraph
                    18(b)(2).
               
               (B)  Bonneville shall refund within the next three succeeding
                    rate periods but, in any event, within 8 years after
                    Puget has made its election for such refund (such period
                    to begin no later than the 25th month after Bonneville's
                    receipt of Puget's notification to terminate this
                    Agreement and to end on the 96th month after
                    Bonneville's receipt of such notification) in equal
                    monthly amounts an amount equal to the "Refunded Lump
                    Sum Payment" calculated as follows:
               
                    A-((B/540)XA)+ I = Refunded Lump Sum Payment
                    
                    where:
                    
                    A  =  The Initial Lump Sum Payment, Adjusted Lump Sum
                          Payment, or any Revised Adjusted Lump Sum Payment,
                          whichever has been most recently paid by Puget to
                          Bonneville pursuant to subsection 9(a).
                    
                    B  =  The number of months between the Effective Date
                          and the termination date of this Agreement
                          pursuant to this subsection 18(b).
                    
                                                    92
                    
                    540 = 12 months X 45-year period over which Bonneville
                          will amortize the Initial Lump Sum Payment,
                          Adjusted Lump Sum Payment, or such Revised
                          Adjusted Lump Sum Payment, as the case may be.
                    
                    I  =  Interest on A-((B/540)XA), accruing from (and
                          including) the date of Bonneville's receipt of
                          Puget's Initial Lump Sum Payment to (but
                          excluding) the date on which Bonneville receives
                          Puget' notification to terminate this Agreement
                          pursuant to this subsection 18(a), at the 5-year
                          Treasury note rate in effect on the date on which
                          Bonneville receives Puget's Initial Lump Sum
                          Payment.
                    
               (C)  Bonneville shall, subject to the immediately succeeding
                    sentence, pay interest on the Refunded Lump Sum Payment
                    at a rate equal to Bonneville's weighted average
                    interest rate on Bonneville's then-outstanding bonds and
                    on Bonneville's then-outstanding debt instruments.  Such
                    interest payable pursuant to this subparagraph
                    18(b)(2)(C) shall be paid by Bonneville on the amount of
                    each monthly amount of the Refunded Lump Sum Payment
                    payable by Bonneville pursuant to subparagraph
                    18(b)(2)(B).
                    
               (D)  Bonneville shall refund the Refunded Lump Sum Payment
                    pursuant to paragraph 9(f)(4).
               
               (E)  At any time during the repayment period referenced in
                    subparagraph 18(b)(2)(B), Bonneville may accelerate
                    payment to Puget of the amount of the Refunded Lump Sum
                    Payment.
          
               If Puget elects to proceed under this paragraph 18(b)(2),
               Bonneville shall not develop a rate or charge that would
               
                                              93
               
               inequitably allocate to Puget and Capacity Owners other than
               Puget, or to any of them, the cost to Bonneville of the
               Refunded Lump Sum Payment; provided, however, that such
               allocation shall not be deemed to be inequitable solely
               because it causes the recovery of a portion of the cost to
               Bonneville of the Refunded Lump Sum Payment from Puget or any
               Capacity Owner other than Puget.
     
     (c)  If FERC approves the Initial Successor Rate, the Alternative
          Successor Rate (as defined in subsection 18(d)), or the Bonneville
          Successor Rate (as defined in subsection 18(d)) for a term less
          than the remainder of the Term following the expiration of the AC-
          93 rate, and if Bonneville's Administrator thereafter submits to
          FERC a rate (Replacement Rate) that is different from the Initial
          Successor Rate, the Alternative Successor Rate or the Bonneville
          Successor Rate (whichever had been approved by FERC on an interim
          or final basis) or that is for a rate approval period which is
          less than the remainder of the Term following the expiration of
          the Initial Successor Rate, the Alternative Successor Rate or the
          Bonneville Successor Rate (whichever had been approved by FERC on
          an interim or final basis), Puget may, within 90 days after
          Bonneville submits such rate to FERC and without regard to FERC's
          interim or final disposition of such rate, elect by written notice
          to Bonneville to terminate this Agreement and shall in such notice
          to Bonneville elect to exercise one of the two following options:
     
          (1)  Puget may elect to proceed pursuant to paragraphs 18(f)(1),
               18(f)(2), and 18(f)(3); or
          
          (2)  Puget may elect to have its Initial Lump Sum Payment,
               Adjusted Lump Sum Payment, or any Revised Adjusted Lump Sum
               Payment, whichever has been most recently paid by Puget to
               Bonneville pursuant to subsection 9(a), refunded by
               Bonneville subject to the following terms and conditions:
          
                                       94
          
               (A)  This Agreement shall terminate upon the date Bonneville
                    receives Puget's notification to terminate this
                    Agreement pursuant to this subsection 18(c) except for
                    those rights and obligations set forth in this paragraph
                    18(c)(2).
               
               (B)  Bonneville shall refund within the next three succeeding
                    rate periods but, in any event, within 8 years after
                    Puget has made its election for such refund (such period
                    to begin no later than the 25th month after Bonneville's
                    receipt of Puget's notification to terminate this
                    Agreement and to end on the 96th month after
                    Bonneville's receipt of such notification) in equal
                    monthly amounts an amount equal to the "Refunded Lump
                    Sum Payment" calculated as follows:
               
                    A-((B/540)XA)+ R = Refunded Lump Sum Payment
                    
                    where:
                    
                    A  =  The Initial Lump Sum Payment, Adjusted Lump Sum
                          Payment, or any Revised Adjusted Lump Sum Payment,
                          whichever has been most recently paid by Puget to
                          Bonneville pursuant to subsection 9(a).
                    
                    B  =  The number of months between the Effective Date
                          and the termination date of this Agreement.
                    
                    540 = 12 months X 45-year period over which Bonneville
                          will amortize the Initial Lump Sum Payment,
                          Adjusted Lump Sum Payment, or such Revised
                          Adjusted Lump Sum Payment, as the case may be.
                    
                    R  =  2.5 times the amount paid pursuant to
                          subparagraphs 9(b)(2)(A) and 9(b)(2)(B) for the
                    
                                                   95
                    
                          immediately preceding fiscal year times the ratio
                          of (a) the amount forecast to be paid pursuant to
                          subparagraphs 9(b)(2)(A) and 9(b)(2)(B) for the
                          first fiscal year during the proposed rate
                          approval period pursuant to the rate submitted by
                          Bonneville to FERC to replace the immediately
                          preceding annual costs rate over (b) the amount
                          forecast to be paid pursuant to subparagraphs
                          9(b)(2)(A) and 9(b)(2)(B) for the same fiscal year
                          were the immediately preceding annual costs rate
                          to remain in effect; provided, however, that the
                          ratio of (a) over (b) shall in no event be less
                          than one for purposes of this subsection.
                    
               (C)  Bonneville shall, subject to the immediately succeeding
                    sentence, pay interest on the Refunded Lump Sum Payment
                    at a rate equal to Bonneville's weighted average
                    interest rate on Bonneville's then-outstanding bonds and
                    on Bonneville's then-outstanding debt instruments.  Such
                    interest payable pursuant to this subparagraph
                    18(c)(2)(C) shall be paid by Bonneville on the amount of
                    each monthly amount of the Refunded Lump Sum Payment
                    payable by Bonneville pursuant to subparagraph
                    18(c)(2)(B).

               (D)  Bonneville shall refund the Refunded Lump Sum Payment
                    pursuant to paragraph 9(f)(4).
               
               (E)  At any time during the repayment period referenced in
                    subparagraph 18(c)(2)(B), Bonneville may accelerate
                    payment to Puget of the amount of Refunded Lump Sum
                    Payment.
          
               If Puget elects to proceed under this paragraph 18(c)(2),
               Bonneville shall not develop a special rate or charge that
               would inequitably allocate to Puget and Capacity Owners other
               than
               
                                          96
               
               Puget, or to any of them, the cost to Bonneville of the
               Refunded Lump Sum Payment; provided, however, that such
               allocation shall not be deemed to be inequitable solely
               because it causes the recovery of a portion of the cost to
               Bonneville of the Refunded Lump Sum Payment from Puget or any
               Capacity Owner other than Puget.
               
          The terms of this subsection 18(c) shall be effective through
          December 31, 2040.
          
     (d)  If (i) FERC remands or approves a rate which materially differs
          from the rate schedule and Billing Provisions set forth in Exhibit
          B, Part A and Part B, on the Effective Date, or (ii) FERC grants
          final approval to a rate containing the terms set forth in
          Exhibit B, Part A and Part B, on the Effective Date, or to the
          Initial Successor Rate for a rate approval period of less than the
          remainder of the Term following the expiration of the AC-93 rate,
          or (iii) FERC remands or disapproves the Initial Successor Rate,
          then in any such event Bonneville, Puget, and Capacity Owners
          other than Puget shall use good faith efforts to develop an
          alternative successor rate (Alternative Successor Rate) which
          would place Puget in substantially the same position with respect
          to Puget's rights and obligations under this Agreement as if the
          rate schedule and Billing Provisions set forth in Exhibit B, Part
          A and Part B, on the Effective Date, had been approved by FERC for
          the remainder of the Term following the expiration of the AC-93
          rate.  Bonneville, Puget, and Capacity Owners other than Puget
          shall use good faith efforts to reach agreement on an Alternative
          Successor Rate within 6 months after the date of the FERC order
          regarding the Initial Successor Rate contemplated in this
          subsection 18(d) or within the time period established in such
          FERC order, whichever is earlier.
     
          (1)  If Bonneville, Puget, and Capacity Owners other than Puget
               reach such an agreement regarding an Alternative Successor
               Rate within the applicable time period referred to in the
               immediately preceding sentence, then Bonneville shall,
               subject
          
                                        97
          
           to section 7(i) of the Regional Act, submit such Alternative
               Successor Rate to FERC for approval and confirmation.
          
          (2)  If Bonneville, Puget, and Capacity Owners other than Puget do
               not reach such an agreement regarding an Alternative
               Successor Rate within the applicable time period referred to
               in the immediately preceding sentence, Bonneville shall
               develop a rate, which, among other things, in Bonneville's
               judgment, protects the rights and obligations of Puget and
               Capacity Owners other than Puget and, subject to section 7(i)
               of the Regional Act, shall submit such rate (Bonneville
               Successor Rate) to FERC for approval and confirmation.
          
          Nothing in this subsection 18(d) shall limit or otherwise affect
          any provisions of subsection 18(b) or 18(c).

     (e)  If Bonneville, Puget, and Capacity Owners other than Puget are
          unable to agree upon an Alternative Successor Rate pursuant to
          subsection 18(d), or if FERC approves the Alternative Successor
          Rate for a period of less than 15 years or with terms and
          conditions that differ from the terms and conditions of the
          Alternative Successor Rate, or if FERC remands the Alternative
          Successor Rate, or if FERC approves the Bonneville Successor Rate,
          Puget may elect, within 6 months of any of the foregoing events,
          to terminate this Agreement and execute a long-term contract with
          Bonneville for firm wheeling on the PNW-PSW Intertie for a term
          not less than the remaining term of the agreement(s) specified in
          Exhibit J for wheeling of an amount of power on the PNW-PSW
          Intertie up to Puget's Capacity Ownership Share, pursuant to
          subsection 18(f).

     (f)  Should Puget elect to proceed pursuant to paragraph 18(b)(1) or
          18(c)(1) or subsection 18(e), the Parties shall take the following
          steps:

          (1)  Puget shall provide Bonneville with written notification of
               its election to terminate this Agreement and with a written
               request for a long-term contract for firm wheeling on the PNW-
               PSW
          
                                          98
          
               Intertie for a period not less than the remaining term of the
               agreement(s) specified in Exhibit J for wheeling of an amount
               of power on the PNW-PSW Intertie up to Puget's Capacity
               Ownership Share.

          (2)  As soon as practicable after receipt by Bonneville of the
               written notice sent pursuant to paragraph 18(f)(1),
               Bonneville shall offer to Puget a long-term contract for firm
               wheeling on the PNW-PSW Intertie of an amount of power equal
               to the amount of power specified in Puget's written request
               pursuant to paragraph 18(f)(1), such offered contract to
               contain other terms and conditions substantially similar to
               those then being offered by Bonneville to its other firm
               wheeling customers for transactions on the PNW-PSW Intertie.
          
          The termination date of this Agreement shall be the same date as
          the effective date of the long-term contract for firm wheeling
          referred to in this paragraph 18(f)(2), and such date shall in any
          event be no more than 6 months after Bonneville's receipt of
          Puget's notification pursuant to paragraph 18(f)(1).

          (3)  The long-term contract for firm wheeling offered to Puget
               pursuant to paragraph 18(f)(2) shall also contain provisions
               which:

               (A)  Require Bonneville to credit or pay (any such payment to
                    be made pursuant to paragraph 9(f)(4)), in equal monthly
                    amounts during the term of such long-term contract for
                    firm wheeling, against the amount payable by Puget to
                    Bonneville pursuant to such long-term wheeling agreement
                    an amount equal to the "Credited Lump Sum Payment"
                    calculated as follows:
               
                    A-((B/540)XA)= credited Lump Sum Payment
                    
                    where:
                    
                                             99
                    
                    A  =  The Initial Lump Sum Payment, Adjusted Lump Sum
                          Payment, or any Revised Adjusted Lump Sum Payment,
                          whichever has been most recently paid by Puget to
                          Bonneville pursuant to subsection 9(a).
                    
                    B  =  The number of months between the Effective Date
                          and the termination date of this Agreement
                          pursuant to this subsection 18(e).
                    
                    540 = 12 months X 45-year period over which Bonneville
                          will amortize the Initial Lump Sum Payment,
                          Adjusted Lump Sum Payment, or such Revised
                          Adjusted Lump Sum Payment, as the case may be.
                  
               (B)  Require Bonneville, subject to the immediately
                    succeeding sentence, to credit or pay interest on the
                    Credited Lump Sum Payment at a rate equal to
                    Bonneville's weighted average interest rate on
                    Bonneville's then-outstanding bonds and on Bonneville's
                    then-outstanding debt instruments.  Such interest to be
                    credited or paid pursuant to this provision shall be
                    credited or paid by Bonneville on the amount of each
                    monthly amount of the Credited Lump Sum Payment to be
                    credited or paid by Bonneville pursuant to the provision
                    set forth in subparagraph 18(f)(3)(A).

               (C)  Permit Bonneville to accelerate payment to Puget of the
                    amount of Credited Lump Sum Payment which remains
                    uncredited at any time during the term of such long-term
                    contract for firm wheeling.
               
     (g)  Puget's right to terminate this Agreement pursuant to subsections
          18(d) through 18(f) is a one-time only right that must be
          exercised after FERC action pursuant to subsection 18(d).  If
          Puget fails to
     
                                     100
     
          terminate the Agreement pursuant to subsection 18(e) as prescribed
          therein as a result of FERC action, Puget shall have no future
          rights to terminate the Agreement under this section 18 as a
          result of FERC action.
     
     (h)  Bonneville shall use best efforts to establish and maintain in
          effect the AC-93 rate, set forth in Exhibit A, during the
          remainder of the Term, but only until the annual costs rate set
          forth in Exhibit B, or other rate submitted to FERC, pursuant to
          subsections 18(b) through 18(d), that is confirmed and approved by
          FERC on an interim or final basis, becomes effective.  If FERC
          does not confirm and approve on a final basis the AC-93 rate for a
          rate approval period of sufficient duration so that the AC-93 rate
          is effective until the annual costs rate set forth in Exhibit B,
          or such other rate, becomes effective, then upon expiration of the
          rate approval period of such AC-93 rate, Bonneville shall submit
          to FERC a rate based on the methodology used to determine the AC-
          93 rate (revised AC-93 rate) and shall use best efforts to obtain
          a rate approval period for the revised AC-93 rate of sufficient
          duration so that the revised AC-93 rate is effective until the
          annual costs rate set forth in Exhibit B, or other rate submitted
          to FERC, pursuant to subsections 18(b) through 18(d), becomes
          effective.  If, at any time during the Term, FERC does not confirm
          and approve on an interim or final basis the AC-93 rate or revised
          AC-93 rate for any reason other than the duration of the rate
          approval period, Bonneville and Puget shall use best efforts to
          develop a rate that would replace the AC-93 rate or revised AC-93
          rate, and Bonneville shall submit such rate to FERC, pursuant to
          section 7(i) of the Regional Act, for confirmation and approval if
          such rate is agreed to by Bonneville, Puget and Capacity Owners
          other than Puget.  If Bonneville and Puget do not succeed in
          developing such rate, Bonneville shall submit to FERC, pursuant to
          section 7(i) of the Regional Act, a rate which in Bonneville's
          judgment recovers Bonneville's costs.  Bonneville shall bill
          Puget, and Puget shall pay Bonneville, in accordance with the AC-
          93 rate or, if FERC does not confirm and approve on an interim or
          final basis the AC-93 rate, the rate confirmed and approved by
          FERC on an interim or final basis.  Bonneville shall revise
          Exhibit A so that it contains, at a given time, the AC-93 or other
          rate confirmed and approved by FERC on an interim or final basis.
     
                                             101

19.  EXHIBITS

     (a)  Exhibits A through J attached to this Agreement are by this
          reference made a part of this Agreement.  In the event of a
          conflict between any provision in Exhibits A through J and the
          provisions of sections 1 through 23 of this Agreement, the
          provisions of sections 1 through 23 of this Agreement shall
          prevail.
     
     (b)  Bonneville shall revise Exhibit A pursuant to subsections 18(g)
          and 18(h) and this subsection 19(b).  The rate schedules attached
          hereto as Exhibit A have been conditionally or finally confirmed
          by FERC.  If the final rate schedules which are approved by FERC
          are an amendment or modification of the initial rate schedules,
          the applicable amended or modified rate schedules and associated
          GTRSPs shall be attached to and made part of this Agreement
          effective as of the date specified in FERC's approval.  The rate
          schedules and GTRSPs included in Exhibit A shall be replaced by
          successor rate schedules and provisions in accordance with the
          provisions of section 7(i) of the Regional Act and FERC rules.
     
     (c)  Upon interim or final approval by FERC of any rate submitted to
          FERC pursuant to subsections 18(a) through 18(g), Bonneville shall
          revise Exhibit B so that Exhibit B contains such rate approved by
          FERC as contemplated in this subsection 19(c).  For purposes of
          this Agreement, such rate shall be effective as of the date of
          effectiveness specified in FERC's approval of such rate.  Subject
          to the provisions of subsections 18(a) through 18(g), the rate
          schedule set forth in Exhibit B, Part A and Part B, on the
          Effective Date, shall be replaced by successor rate schedules and
          provisions pursuant to section 7(i) of the Northwest Power Act and
          applicable FERC rules.
     
                                     102
     
     (d)  Bonneville shall revise or modify Exhibit C from time to time to
          reflect changes hereafter agreed to in writing by the Parties in
          Puget's Capacity Ownership Share, Capacity Ownership Percentage,
          Scheduling Percentage, and Scheduling Share.
     
     (e)  Bonneville shall revise Exhibit D pursuant to subsection 9(a).
          Revision or modification of Exhibit D shall not require an
          executed amendment or revision to this Agreement.
     
     (f)  Not more frequently than annually, Bonneville shall review and, as
          appropriate, revise Exhibit E, Part A, in accordance with
          Bonneville's standard methodology and formula for calculation of
          average losses incurred by Bonneville in providing transmission on
          Bonneville's PNW AC Intertie.  Such methodology and formula are
          intended to forecast average annual actual losses incurred by
          Bonneville in providing transmission on Bonneville's PNW AC
          Intertie Operational Transfer Capability.  Any changes to the loss
          methodology or formula, other than numerical values, shall be made
          only after consultation with the Committee.  During such
          consultation, Bonneville shall provide to the Committee material
          pertinent to such changes to the loss methodology or formula.
          Upon conclusion of any review of the loss factor in Exhibit E,
          Part A, Bonneville shall present the results of its review,
          including any revisions to the loss factor in Exhibit E, Part A,
          to the Committee as part of the Operating Plan pursuant to section
          13.  If the Committee pursues arbitration pursuant to subsection
          10(b) and section 14, Bonneville shall revise Exhibit E, Part A,
          to reflect the selection of the arbitrators pursuant to subsection
          14(j).
          
     (g)  Bonneville shall revise the loss factor in Exhibit E, Part B, as
          necessary to equal the same factor for average losses as
          Bonneville generally applies to transmission over Bonneville's
          share of the PNW-PSW Intertie.  Revision of Exhibit E, Part B,
          shall not require an executed amendment or revision to this
          Agreement.
     
     (h)  Bonneville shall revise Exhibit F as appropriate to reflect the
          facilities in Bonneville's PNW AC Intertie.  Revision or
          modification of
     
                                          103
     
          Exhibit F shall not require an executed amendment or revision to
          this Agreement.
     
     (i)  Bonneville shall revise Exhibit G as appropriate to reflect the
          complete list of all of the Capacity Owners and their respective
          Capacity Ownership Shares and Capacity Ownership Percentages from
          time to time pursuant to this Agreement.
     
     (j)  Bonneville shall revise Exhibit H as appropriate to reflect all
          provisions required by statute or Executive Order.  Revision or
          modification of Exhibit H shall not require an executed amendment
          or revision to this Agreement.
     
     (k)  Bonneville shall revise Exhibit I to reflect changes as agreed to
          in writing by Puget and Capacity Owners other than Puget.
     
     (l)  Bonneville shall revise Exhibit J as mutually agreed to in writing
          by the Parties.

20.  RULES OF LAW

     (a)  Bonneville and Puget agree that each fully participated in the
          drafting of each provision of this Agreement.  The rule of law
          interpreting ambiguities against the drafting Party shall not be
          applicable to or utilized in resolving any dispute over the
          meaning or intent of this Agreement or any of its provisions.
     
     (b)  This Agreement shall not be construed to establish a partnership,
          association, agency relationship, joint venture, or trust.
          Neither Party shall be under the control of or shall be or
          represent itself as, the agent of, or have a right or power to
          bind, the other Party without the other's express written consent,
          except as provided in this Agreement.
     
     (c)  All applicable law is incorporated in and made part of this
          Agreement.
     
                                        104

21.  NOTICES

     (a)  Unless the Agreement requires otherwise, any notice, demand or
          request provided for in this Agreement, or served, given or made
          in connection with it, shall be in writing and shall be served,
          given, or made if delivered in person or sent by acknowledged
          delivery, or sent by registered or certified mail, postage
          prepaid, to the persons addressed as set forth below:
     
          To Bonneville:
            Group Vice President for Marketing, Conservation and Production
            Bonneville Power Administration
            905 NE 11th Avenue
            Portland, OR 97232
            
          To Puget:
            Vice President Power Planning
            Puget Sound Power & Light Company
            411  108th Avenue NE  15th Floor
            Bellevue, WA 98004-5515
          
          To Seattle:
            Director, Power Management Division
            Seattle City Light
            1111 Third Avenue, Room 420
            Seattle, WA 98101
          
          To PNGC:
            Director of Power Management
            Pacific Northwest Generating Cooperative
            711 NE Halsey Street, Suite 200
            Portland, OR 97232
          
                                    105
          
          To Snohomish:
            Manager of Power Supply
            Public Utility District No. 1 of Snohomish
                 County, Washington
            2320 California Street
            P.O. Box 1107
            Everett, WA 98201
            
          To Tacoma:
            Light Division Superintendent
            Tacoma Public Utilities
            3628 S. 35th Street
            Tacoma, WA 98411
     
     (b)  Either Party may, by written notice to the other Party pursuant to
          subsection 21(a), change the address set forth in subsection 21(a)
          for the notifying Party.
     
     (c)  All notices pursuant to this Agreement shall be effective on the
          date of receipt.

22.  WAIVER

     Any waiver at any time by a Party of its rights with respect to any
     matter arising in connection with this Agreement shall not be deemed a
     waiver with respect to any subsequent or other matter.  Except as
     otherwise provided herein or as agreed in writing by the Parties, no
     provision in this Agreement may be waived except as documented or
     confirmed in writing.
     
23.  MISCELLANEOUS

     (a)  Effect of Section Headings
     
          Section headings and subheadings appearing in this Agreement are
          inserted for convenience only and shall not be construed as
          interpretations of provisions of this Agreement.
     
                                    106

     (b)  Amendments
     
          Except as may be expressly otherwise provided in this Agreement,
          this Agreement may be amended only with the express written
          consent of both of the Parties, and no provision of this Agreement
          shall be varied or contradicted by any oral agreement, course of
          dealing or performance or any other matter not hereafter set forth
          in a written agreement signed by both of the Parties.
          
     (c)  Entire Agreement
     
          This Agreement constitutes, on and as of the date hereof, the
          entire agreement of the Parties with respect to the subject matter
          of this Agreement, and all prior understandings or agreements,
          whether written or oral, between the Parties with respect to the
          subject matter of this Agreement are hereby superseded in their
          entireties.
          
     (d)  No Third Party Beneficiaries
     
          There are no third party beneficiaries of this Agreement.  This
          Agreement shall not be construed to create rights in, or to grant
          remedies to, any third party as a beneficiary of this Agreement or
          of any duty, obligation, or undertaking established herein.
          
     (e)  Regulatory Approvals
     
          Each Party shall use its best efforts to obtain and maintain in
          effect regulatory approvals that are necessary to permit such
          Party to perform its obligations under this Agreement in
          accordance with its terms and conditions.  Neither Party shall
          oppose in any way or seek to alter or amend the terms and
          conditions of this Agreement by application to or participation in
          any application of any regulatory authority or court having
          jurisdiction.  Puget shall not oppose in any way or seek to alter
          or amend the terms or conditions of the annual costs rate set
          forth in Exhibit B, the CO-94 rate, the AC-93 rate, or
     
                                        107
     
          any rate described in section 18 that is agreed to by the Parties
          subsequent to each entering into this Agreement, in any proceeding
          pursuant to section 7 of the Pacific Northwest Electric Power
          Planning and Conservation Act before FERC or in any court of
          competent jurisdiction.
     
     (f)  Other Capacity Ownership Agreements
     
          If Bonneville offers to enter into (i) a Capacity Ownership
          Agreement with any other Capacity Owner or (ii) any written
          amendment of any Capacity Ownership Agreement (other than this
          Agreement), then Bonneville shall offer to Puget an amendment of
          this Agreement that contains the terms and conditions of such
          Capacity Ownership Agreement with such other Capacity Owner or of
          such written amendment, as the case may be.  Bonneville shall
          advise, and use reasonable efforts to consult with, Puget during
          the development or consideration of any offer to any Capacity
          Owner other than Puget to enter into a Capacity Ownership
          Agreement or any amendment of such agreement.
          
     (g)  Singular and Plural Forms
     
          For purposes of interpreting and construing this Agreement, the
          singular form of a word shall include its plural and the plural
          form of a word shall include its singular, unless otherwise
          expressly provided by this Agreement.
          
     (h)  Performance Pending Dispute
     
          Except as otherwise expressly provided in this Agreement, pending
          resolution of any dispute, issue, or controversy arising under
          this Agreement, the Parties shall each continue performance of
          their respective obligations pursuant to this Agreement.
     
                                          108
     
     (i)  Time Periods
     
          For purposes of calculating any time period prescribed by this
          Agreement, if the last day of the time period falls on a day that
          is not a Working Day, then the last day of the time period shall
          be the first Working Day following such day as would otherwise be
          the last day of the time period.
     
     (j)  Double Counting
     
          In developing rates or charges under section 7 of the Pacific
          Northwest Electric Power Planning and Conservation Act for any
          rate period, Bonneville shall not set rates or charges that
          recover, more than once, the costs associated with capital
          projects that are paid or forecast to be paid under the CO-94 rate
          and the AC-93 rate and annual costs rate set forth in Exhibit B,
          or the remaining Bonneville's PNW AC Intertie costs forecast to be
          paid under the AC-93 rate and annual costs rate set forth in
          Exhibit B.  Bonneville's forecast of revenues chargeable under the
          CO-94 rate, AC-93 rate, and annual costs rate set forth in Exhibit
          B shall be based on the best available information, including
          information provided pursuant to section 13 of this Agreement.
     
          In the event Bonneville proposes any wheeling rate for
          transmission service on Bonneville's main grid that includes costs
          of the PNW AC Intertie, such proposed rate shall include a credit
          or other mechanism that ensures that Puget is not charged any of
          the PNW AC Intertie costs for deliveries of power that utilize up
          to the Puget's Capacity Ownership Share, as that term is defined
          in this Agreement.
     
     (k)  Committee Action
     
          Each of the Parties agrees that to the extent it is provided in
          sections 13, 14, and 16 that the Committee shall take any action
          or shall make any decision, such action or decision shall be taken
          or made, as the case may be, by the Committee, and not by Puget
          acting individually.
     
                                       109
     
     (l)  Fiscal Year
     
          For purposes of this Agreement, the term "fiscal year" shall mean
          Bonneville's fiscal year.
     
     (m)  Rights and Remedies Cumulative
     
          All rights and remedies of either Party under this Agreement and
          at law and in equity shall be cumulative and not mutually
          exclusive and the exercise of one right or remedy shall not be
          deemed a waiver of any other right or remedy.  Nothing contained
          in any provision of this Agreement shall be construed to limit or
          exclude any right or remedy of either Party (arising on account of
          the breach or default by the other Party or otherwise) now or
          hereafter existing under any other provision of this Agreement, at
          law or in equity.
          
                                 110

IN WITNESS WHEREOF, the Parties hereto have executed this Agreement.


                                           UNITED STATES OF AMERICA
                                           Department of Energy
                                           Bonneville Power Administration

                                           By    Walter E. Pollock
                                              -------------------------
                                              Group Vice President for
                                              Marketing, Conservation and
                                              Production

                                           Name  Walter E. Pollock
                                                -------------------
                                                (Print/Type)

                                           Date  October 11, 1994
                                                ------------------


Puget Sound Power & Light Company


By   J. R. Lauckhart
  -------------------

Name J. R. Lauckhart
    -----------------
    (Print/Type)

Title  V. P. Power Planning
      ----------------------

Date  9/26/94
     ---------
                                           Effective Date _________________

                                                      Exhibit A, Page 1 of 14
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date


                                Schedule CO-94
                       CAPACITY OWNERSHIP RATE SCHEDULE



SECTION   I.  AVAILABILITY

    This schedule applies to all agreements which provide life-of-facilities
   capacity rights to non-Federal participants (Capacity Owners) in 725 MW
   of Bonneville's PNW AC Intertie and any upgrades thereto.  Service under
   this schedule is subject to Bonneville's General Transmission Rate
   Schedule Provisions.

SECTION  II.  RATE

    The charge for capital and related costs for non-Federal capacity
   ownership in Bonneville PNW AC Intertie shall be determined by the
   methodologies set out in Section III below.

SECTION III.  DETERMINATION OF RATE

A.  Capacity Ownership Price

    The charge for capacity ownership in Bonneville's PNW AC Intertie shall
   be the Capacity Ownership Share of the actual capital and related costs
   of facilities as determined by the formula shown below.  The Capacity
   Ownership Share shall be determined pursuant to the Capacity Ownership
   agreement.

                  (A-B)+C+D
                  ---------  =  Capacity Ownership Price in $/kW
                      E

    Capacity Ownership Price in $/kW x number of kW contracted for by
   Capacity Owner = Capacity Owner's payment to Bonneville.

    Where:

         A =  Bonneville's cost of new facilities for the Third AC
             Intertie, which increased the rated transfer capability
             of the PNW AC Intertie by approximately 1600 MW, is the
             construction costs (including direct, indirect and
             overhead costs) of the facilities associated with the
             Third AC Intertie System Reinforcements and the Alvey-
             Meridian Transmission Line (also known as Eugene-Medford
             500 kV Transmission Line), referred to jointly as the
             Third AC Intertie Project.
     
                                                     Exhibit A, Page 2 of 14
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company
                                             Effective on the Effective Date



     
         B =  Bonneville's cost of new facilities needed for the first
             800 MW increment of the 1600 MW Third AC Intertie
             Project, which includes a portion of the construction
             costs (including direct, indirect and overhead costs)
             associated with the Third AC Intertie System
             Reinforcement.
     
       A-B =  The cost of new facilities for the second 800 MW
             increment of the 1600 MW Third AC Intertie Project
             (presented in Exhibit C of the Capacity Ownership
             agreement).
     
         C =  Allowance for Funds Used During Construction (AFUDC)
             constitutes interest on the funds used for the Third AC
             Intertie Project while it was under construction.  AFUDC
             is calculated and capitalized consistent with FERC
             requirements as described in FERC's Uniform System of
             Accounts, 18 CFR, Part 101, Electric Plant Instructions,
             3.A(17).  The AFUDC applies to that amount capitalized on
             the second 800 MNW increment of the 1600 MW Third AC
             Intertie Project, or A-B.
     
         D =  Book value of existing Bonneville support facilities that
             are dedicated to the PNW AC Intertie equal to
             $19,100,000.
     
         E =  725,000 kW, which equals Bonneville's share of the second
             800 MW of the Third AC Intertie.
     
B.  PNW AC Intertie Upgrade Price

    The charge for upgrades to Bonneville's PNW AC Intertie facilities that
   occur after December 1993, and which result in an increase of rated
   transfer capability, shall be the Capacity Ownership Share of the capital
   and related costs of the upgrade.  The Capacity ownership Share of any
   upgrades shall be determined pursuant to the Capacity Ownership
   agreement.  The capital costs shall consist of the construction costs
   (including direct, indirect and overhead costs) and AFUDC (as described
   in Section III.A. Above) of the facilities associated with such upgrades.
                                                      Exhibit A, Page 3 of 14
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date


SECTION  IV.  ADJUSTMENTS AND SPECIAL PROVISIONS

A.  Initial Lump Sum Payment

    Capacity Owners shall make an initial, lump sum payment of an estimate of
   the Capacity Ownership Price equal to $215/kW pursuant to the Capacity
   Ownership agreement.

B.  Adjustment to Reflect Actual Construction Costs

    Approximately December 1995 or as soon as practicable thereafter, the
   Capacity owner's initial lump sum payment shall be adjusted to reflect
   the difference between the actual and the estimated Capacity ownership
   Price.  The actual Capacity Ownership Price shall be determined pursuant
   to Section III.A. above.  There will be no adjustment for the book value
   of the support facilities dedicated to the PNW AC Intertie.  Capacity
   Owners will either receive a refund, with interest, from Bonneville or
   make an additional payment, with interest, to Bonneville.  Bonneville
   shall compute interest using the weighted average interest rate on
   Bonneville's outstanding bonds.

C.  PNW AC Intertie Upgrade Payments

    Capacity Owners shall pay a share of the upgrades to Bonneville's PNW AC
   Intertie in the manner and time to be determined when participation in
   such upgrades are agreed to pursuant to the Capacity Ownership agreement.
                                                      Exhibit A, Page 4 of 14
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date


                                Schedule AC-93
                         Southern Intertie Annual Cost

SECTION   I.  AVAILABILITY

This schedule is applicable to all parties (New Owners) that execute PNW AC
Intertie Capacity Ownership Agreements (Agreements) and will be effective on
the date described in the Agreement.  Service under this schedule is subject
to BPA's General Transmission Rate Schedule Provisions.

SECTION  II.  RATE

The rate charges reflect the terms of the Memorandum of Understanding (MOU),
signed in the fall of 1991, between BPA and potential New owners.  The MOU
provides for the payment by New Owners of their prorated share of: (1) BPA's
annual operations, maintenance and general plant expense (including
applicable (overheads) properly chargeable to the AC Intertie facilities; and
(2) BPA's share of capitalized replacements on the AC Intertie.  The monthly
charge shall be the sum of the charges specified in sections II.A. and II.B.

A.  Operations, Maintenance, and General Plant

    The monthly charge shall equal $325 per megawatt of billing demand.

B.  Replacements

    The monthly charge shall equal $0 per megawatt of billing demand.

SECTION III.  ADJUSTMENT TO REPLACEMENT RATE

A.  Determination of Billing Adjustment

   New Owners will receive a billing adjustment if BPA incurs AC Intertie
   replacement cost during the rate period.  The Replacements Rate
   Adjustment equals
   
              AC Intertie work orders ($000) * %
              ----------------------------------
                    725 MW * # months
   
   where
   
             "# months" equals: (1) the number of months that this
             rate is in effect during the fiscal year for the Initial
             Replacements Rate Adjustment; or (2) the number of
             months in the rate period for the Final Replacements
             Rate Adjustment; and
             
             "%" equals the New Owners' percentage share of BPA's
             total AC Intertie Rated Transfer Capability as specified
             in the Agreements.
                                                      Exhibit A, Page 5 of 14
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date


B.  Initial Replacements Rate Adjustment

    New Owners will receive a billing adjustment for each fiscal year that
   BPA incurs AC Intertie replacement cost.  At the end of each fiscal year,
   the cost associated with AC Intertie capital replacement work orders that
   have closed during the fiscal year will be determined.  The unit rate
   that would result using these closed work orders is the basis of the
   Initial Replacements Rate Adjustment.
   
   1.  Notice Provisions
   
       Following each fiscal year, BPA shall notify all New Owners by
       December 15, of the proposed Replacements Rate Adjustment.  BPA will
       provide the calculation of the adjustment and a short description of
       the work performed and the associated cost used as the basis for the
       billing adjustment.  In addition to written notification, BPA may,
       but is not obligated to, hold a public meeting to clarify its
       determinations.
   
       Written comments on the Initial Replacements Rate Adjustment will be
       accepted through the end of January.  Consideration of comments
       submitted by the New Owners may result in the billing adjustment
       differing from the initially proposed adjustment.  BPA shall notify
       all New Owners of the Initial Replacements Rate Adjustment by the
       last day of February.
   
   2.  Adjustment of Monthly Bills
   
       An adjustment will be made on the New Owner's monthly bill prepared
       during March.  The Initial Replacements Rate adjustment will be
       multiplied by the sum of the monthly billing factors from the
       relevant fiscal year (i.e., the New Owner's share in megawatts of
       BPA's PNW AC Intertie Rated Transfer Capability multiplied by the
       numbers of months that this rate schedule is effective during the
       fiscal year).  The Initial Replacements Rate Adjustment will appear
       as a charge to the New Owner on the monthly bill prepared during
       March.
   
C.  Final Replacements Rate Adjustment

    The actual costs associated with the AC Intertie capital replacement work
   orders that occur during the rate period may change after BPA performs
   its final analysis of the work orders.  BPA shall compare the unit rate
   for the rate period using the results of the final work order analysis to
   the weighted average of the unit rates from the Initial Replacements Rate
   Adjustments.

   1.  Notice Provisions
   
       BPA shall notify all New Owners in May 1998 of the results of the
       calculations, an explanation of work order changes(s), and any
                                                      Exhibit A, Page 6 of 14
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date

   
       resulting billing adjustment.  Written comments from New Owners will
       be accepted through the end of June.  BPA shall notify all New Owners
       of the Final Replacements Rate Adjustment by July 31.  Consideration
       of comments submitted by the New Owners may result in the Final
       Replacements Rate Adjustment differing from the initially proposed
       adjustment.
   
   2.  Adjustment of Monthly Bills
   
       If the absolute value of the Final Replacements Rate Adjustment is
       greater than or equal to $1 per megawatt per month, an adjustment
       will be made on the New Owner's monthly bill prepared during August.
       For each New Owner, the Final Replacements Rate Adjustment will be
       multiplied by the sum of the monthly billing factors from the
       relevant fiscal years (i.e., the New Owner's share in megawatts of
       BPA's PNW AC Intertie Rated Transfer Capability multiplied by the
       number of months that this rate schedule is effective during the
       fiscal years).  The Final Replacements Rate Adjustment will appear as
       a charge or credit to the New Owner on the monthly bill prepared
       during August.  Interest, as determined by BPA's Office of Financial
       Management, will be included in any adjustment.
   
SECTION IV.  BILLING FACTOR

The billing demand shall be the New Owner's capacity ownership share in
megawatts of BPA's PNW AC Intertie Rated Transfer Capability as specified in
the Agreement.

                                                      Exhibit A, Page 7 of 14
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date


                               SCHEDULE IS-93

SECTION   I.  AVAILABILITY

This schedule supersedes IS-91 and is available for all transmission on the
Southern Intertie.  Service under this schedule is subject to BPA's General
Transmission Rate Schedule Provisions.

SECTION  II.  RATE

A.  Nonfirm Transmission Rate

    The charge for nonfirm transmission of non-BPA power shall be 3.11 mills
   per kilowatthour of billing energy.  This charge applies for both north-
   to-south and south-to-north transactions.

B.  Firm Transmission Rate

    The charge for firm transmission service shall be $0.706 per kilowatt per
   month of billing demand and 1.69 mills per kilowatthour of billing
   energy.  Firm transmission will only be made available to customers under
   this rate schedule who have executed a contract with BPA specifying use
   of the Firm Transmission rate for either north-to-south or south-to-north
   transactions.

SECTION III.  BILLING FACTORS

A.  For services under Section II.A. the billing energy shall be the monthly
   sum of the scheduled kilowatthours, plus the monthly sum of kilowatthours
   allocated but not scheduled.  The amount of allocated but not scheduled
   energy that is subject to billing may be reduced pro rata by BPA due to
   forced Intertie outages and other uncontrollable forces that may reduce
   Intertie capacity.  The amount of allocated but not scheduled energy that
   is subject to billing also may be reduced upon mutual agreement between
   BPA and the customer.

B.  For services under Section II.B. the billing demand shall be the
   Transmission Demand as defined in the Agreement.  The billing energy
   shall be the monthly sum of scheduled kilowatthours, unless otherwise
   specified in the Agreement.

                                                      Exhibit A, Page 8 of 14
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date


                General Transmission Rate Schedule Provisions

SECTION   I.  ADOPTION OF REVISED TRANSMISSION RATE SCHEDULES AND GENERAL
              TRANSMISSION RATE SCHEDULE PROVISIONS (GTRSPs)

A.  Approval of Rates

    These rate schedules and GTRSPs shall become effective upon interim
   approval or upon final confirmation and approval by FERC.  BPA will
   request FERC approval effective October 1, 1993.

B.  General Provisions

    These 1993 Transmission Rate Schedules and associated GTRSPs are
   virtually identical to and supersede BPA's 1991 Transmission Rate
   schedules and GTRSPs (which became effective October 1, 1992) but do not
   supersede prior rate schedules required by agreement to remain in force.

    Transmission service provided shall be subject to the following Acts, as
   amended:  the Bonneville Project Act, the Regional Preference Act (P.L.
   88-552), the Federal Columbia River Transmission System Act, and the
   Pacific Northwest Electric Power Planning and Conservation Act, and the
   Energy Policy Act of 1992, Pub. L. 102-486, 106 Stat. 2776 (1992).

    The meaning of terms used in the transmission rate schedules shall be as
   defined in agreements or provisions which are attached to the Agreement
   or as in any of the above Acts.

C.  Interpretation

    If a provision in the executed Agreement is in conflict with a provision
   contained herein, the former shall prevail.

SECTION  II.  BILLING FACTOR DEFINITIONS AND BILLING ADJUSTMENTS

A.  Billing Factors

    1.  Scheduled Demand

       The largest of hourly amounts wheeled which are scheduled by the
       customer during the time period specified in the rate schedules.
   
   2.  Metered Demand
   
       The Metered Demand in kilowatts shall be the largest of the 60-minute
       clock-hour integrated demands measured by meters installed at each
       POD during each time period specified in the applicable rate
       schedule.  Such measurements shall be made as specified in the
       Agreement.  BPA, in determining the Metered Demand, will exclude any
       abnormal readings due to or resulting from:  (a) emergencies or

                                                      Exhibit A, Page 9 of 14
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date

   
       breakdowns on, or maintenance of, the FCRTS; or (b) emergencies on
       the customer's facilities, provided that such facilities have been
       adequately maintained and prudently operated as determined by BPA.
       If more than one class of power is delivered to any POD, the portion
       of the metered quantities assigned to any class of power shall be as
       agreed to by the parties.  The amount so assigned shall constitute
       the Metered Demand for such class of power.
   
   3.  Transmission Demand
   
       The demand as defined in the Agreement.
   
   4.  Total Transmission Demand
   
       The sum of the transmission demands as defined in the Agreement.
   
   5.  Ratchet Demand
   
       The maximum demand established during the previous 11 billing months.
       Exception:  if a Transmission Demand or Total Transmission Demand has
       been decreased pursuant to the terms of the Agreement during the
       previous 11 billing months, such decrease will be reflected in
       determining the Ratchet Demand.
   
B.  Billing Adjustments

    Average Power Factor

    The adjustment for average power factor, when specified in a transmission
   rate schedule or in the Agreement, shall be made in accordance with the
   average power factor section of the General Wheeling Provisions.

    To maintain acceptable operating conditions on the Federal system, BPA
   may restrict deliveries of power at any time that the average leading
   power factor or average lagging power factor for all classes of power
   delivered to such point or to such system is below 85 percent.

SECTION III.  OTHER DEFINITIONS

Definitions of the terms below shall be applied to these provisions and the
Transmission Rate Schedules, unless otherwise defined in the Agreement.

A.  Agreement

    An agreement between BPA and a customer to which these rate schedules and
   provisions may be applied.

                                                     Exhibit A, Page 10 of 14
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date


B.  Eastern Intertie

    The segment of the FCRTS for which the transmission facilities consist of
   the Townsend-Garrison double-circuit 500 kV transmission line segment
   including related terminals at Garrison

C.  Electric Power

    Electric peaking capacity (kW) and/or electric energy (kWh).

D.  Federal Columbia River Transmission System

    The transmission facilities of the Federal Columbia River Power System,
   which include all transmission facilities owned by the government and
   operated by BPA, and other facilities over which BPA has obtained
   transmission rights.

E.  Firm Transmission Service

    Transmission service which BPA provides for any non-BPA power except for
   transmission service which is scheduled as nonfirm.  If the firm service
   is provided pursuant to the Agreement, the terms of the Agreement may
   further define the service.

F.  Integrated Network

    The segment of the FCRTS for which the transmission facilities provide
   the bulk of transmission of electric power within the Pacific Northwest,
   excluding facilities not segmented to the network as shown in the
   Wholesale Power Rate Development Study used in BPA's rate development.

G.  Main Grid

    As used in the FPT and IR rate schedules, that portion of the Integrated
   Network with facilities rated 230 kV and higher.

H.  Main Grid Distance

    As used in the FPT rate schedules, the distance in airline miles on the
   Main Grid between the POI and the POD, multiplied by 1.15.

I.  Main Grid Interconnection Terminal

    As used in the FPT rate schedules, Main Grid terminal facilities that
   interconnect the FCRTS with non-BPA facilities.

J.  Main Grid Miscellaneous Facilities

    As used in the FPT rate schedules, switching, transformation, and other
   facilities of the Main Grid not included in other components.

                                                     Exhibit A, Page 11 of 14
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date


K.  Main Grid Terminal

    As used in the FPT rate schedules, the Main Grid terminal facilities
   located at the sending and/or receiving end of a line exclusive of the
   Interconnection terminals.

L.  Nonfirm Transmission Service

    Interruptible transmission service which BPA may provide for non-BPA
   power.

M.  Northern Intertie

    The segment of the FCRTS for which the transmission facilities consist of
   two 500 kV lines between Custer Substation and the United States-Canadian
   border, one 500 kV line between Custer and Monroe Substations, and two
   230 kV lines from Boundary Substation to the United States-Canadian
   border, and the associated substation facilities.

N.  Point of Integration (POI)

    Connection points between the FCRTS and non-BPA facilities where non-
   Federal power is made available to BPA for wheeling.

O.  Point of Delivery (POD)

    Connection points between the FCRTS and non-BPA facilities where non-
   Federal power is delivered to a customer by BPA.

P.  Secondary System

    As used in the FPT and IR rate schedules that portion of the Integrated
   Network facilities with operating voltage of 115 kV or 69 kV.

Q.  Secondary System Distance

    As used in the FPT rate schedules, the number of circuit miles of
   Secondary System transmission lines between the secondary POI and the
   Main Grid or the secondary POD, or the Main Grid and the secondary POD.

R.  Secondary System Interconnection Terminal

    As used in the FPT rate schedules, the terminal facilities on the
   Secondary System that interconnect the FCRTS with non-BPA facilities.

S.  Secondary System Intermediate Terminal

    As used in the FPT rate schedules, the first and final terminal
   facilities in the Secondary System transmission path exclusive of the
   Secondary System Interconnection terminals.

                                                     Exhibit A, Page 12 of 14
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date


T.  Secondary Transformation

    As used in the FPT rate schedules, transformation from Main Grid to
   Secondary System facilities.

U.  Southern Intertie

    The segment of the FCRTS for which the major transmission facilities
   consist of two 500 kV AC lines from John Day Substation to the Oregon-
   California border, a portion of the 500 kV AC line from Buckley
   Substation to Summer Lake Substation; when completed, the Third AC
   facilities which include Captain Jack Substation and the Alvey-Meridian
   500 kV AC line; one 1,000 kV DC line between the Celilo Substation and
   the Oregon-Nevada border, and associated substation facilities.

V.  Transmission Service

    As used in the MT rate schedule, Transmission Service is as defined in
   the Western Systems Power Pool Agreement.

SECTION  IV.  BILLING INFORMATION

A.  Payment of Bills

    Bills for transmission service shall be rendered monthly by BPA.  Failure
   to receive a bill shall not release the customer from liability for
   payment.  Bills for amounts due of $50,000 or more must be paid by direct
   wire transfer, customers who expect that their average monthly bill will
   not exceed $50,000 and who expect special difficulties in meeting this
   requirement may request, and BPA may approve, an exemption from this
   requirement.  Bills for amounts due BPA under $50,000 may be paid by
   direct wire transfer or mailed to the Bonneville Power Administration,
   P.O. Box 6040, Portland, Oregon 97228-6040, or to another location as
   directed by BPA.  The procedures to be following in making direct wire
   transfers will be provided by the Office of Financial Management and
   updated as necessary.

    1.  Computation of Bills
   
       The transmission billing determinant is the electric power quantified
       by the method specified in the agreement or Transmission Rate
       Schedule.  Scheduled power or metered power will be used.
   
       The transmission customer shall provide necessary information to BPA
       for any computation required to determine the proper charges for use
       of the FCRTS, and shall cooperate with BPA in the exchange of
       additional information which may be reasonably useful for respective
       operations.
   
       Demand and energy billings for transmission service under each
       applicable rate schedule shall be rounded to whole dollar amounts, by
                                                     Exhibit A, Page 13 of 14
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date

       eliminating any amount which is less than 50 cents and increasing any
       amounts from 50 cents through 99 cents to the next higher dollar.
   
   2.  Estimated Bills
   
       At its option, BPA may elect to render an estimated bill to be
       followed at a subsequent billing date by a final bill.  The estimated
       bill shall have the validity of and be subject to the same payment
       provisions as a final bill.
   
   3.  Billing Month
   
       For charges based on scheduled quantities, the billing month is the
       calendar month.  For charges based on metered quantities, the billing
       month is defined as the interval between scheduled meter-reading
       dates.  The billing month will not exceed 31 days in any case.  While
       it may be necessary to read meters on a day other than the scheduled
       meter-reading date, for determination of billing demand, the billing
       month will cease at 2400 hours on the last scheduled meter-reading
       date.  Schedules will be predetermined.  The customer must give 30
       days notice to request a change to the schedule.
   
   4.  Due Date
   
       Bills shall be due by close of business on the 20th day after the
       date of the bill (due date).  should the 20th day be a Saturday,
       Sunday, or holiday (as celebrated by the customer), the due date
       shall be the next following business day.
   
   5.  Late Payment
   
       Bills not paid in full on or before close of business on the due date
       shall be subject to a penalty charge of $25.  In addition, an
       interest charge of one-twentieth percent (0.05 percent) shall be
       applied each day to the sum of the unpaid amount and the penalty
       charge.  This interest charge shall be assessed on a daily basis
       until such time as the unpaid amount and penalty charge are paid in
       full.
   
       Remittances received by mail will be accepted without assessment of
       the charges referred to in the preceding paragraph provided the
       postmark indicates the payment was mailed on or before the due date.
       Whenever a power bill or a portion thereof remains unpaid subsequent
       to the due date and after giving 30 days' advance notice in writing,
       BPA may cancel the contract for service to the customer.  However,
       such cancellation shall not affect the customer's liability for any
       charges accrued prior thereto under such agreement.
   
   6.  Disputed Billings
   
       In the event of a disputed billing, full payment shall be rendered to
       BPA and the disputed amount noted.  Disputed amounts are subject to
                                                     Exhibit A, Page 14 of 14
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date


       the late payment provisions specified above.  BPA shall separately
       account for the disputed amount.  If it is determined that the
       customer is entitled to the disputed amount, BPA shall refund the
       disputed amount with interest, as determined by BPA's Office of
       Financial Management.
   
       BPA retains the right to verify, in a manner satisfactory to the
       Administrator, all data submitted to BPA for use in the calculation
       of BPA's rates and corresponding rate adjustments.  BPA also retains
       the right to deny eligibility for any BPA rate or corresponding rate
       adjustment until all submitted data have been accepted by BPA as
       complete, accurate, and appropriate for the rate or adjustment under
       consideration.
   
   7.  Revised Bills
   
       As necessary, BPA may render a revised bill.
       
       a.  If the amount of the revised bill is less than or equal to the
           amount of the original bill, the revised bill shall replace all
           previous bills issued by BPA that pertain to the specified
           customer for the specified billing period and the revised bill
           shall have the same date as the replaced bill.
       
       b.  If a revision causes an additional amount to be due BPA or the
           specified customer beyond the amount of the original bill, a
           revised bill will be issued for the difference and the date of
           the revised bill shall be its date of issue.
                                                      Exhibit B, Page 1 of 9
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company


                              ANNUAL COSTS RATE


A.   PROPOSED SOUTHERN INTERTIE ANNUAL COST RATE


SECTION I.  AVAILABILITY

This schedule is applicable to each party (Capacity Owner) that executes a
PNW AC Intertie Capacity Ownership Agreement (Agreement).  Billings pursuant
to this schedule is subject to the Billing Provisions in Exhibit B of the
Agreement.  This rate schedule shall be effective on the first day of the
fiscal year following the earlier of interim or final FERC approval of this
rate schedule.  Unless otherwise defined in this rate schedule, capitalized
terms used in this rate schedule shall have the respective definitions set
forth in section 1 of this Agreement.

SECTION II.  RATE

A.   OPERATIONS

     The monthly charge equals:

     Operations Cost * Capacity Ownership Percentage
     -----------------------------------------------
                          Months

     Where
  
       "Months" is equal to 12, or, if the Operating Plan has, during the
          fiscal year to which such Operating Plan pertains, been amended
          with respect to Operations Cost, the number of full months
          remaining in the fiscal year after such amended Operating Plan
          becomes effective for which Capacity Owners have not been billed.
       
       "Operations Cost" means, upon and after the effective date of Exhibit
          B pursuant to this Agreement, for any fiscal year any Allocated
          Direct Costs for Bonneville's PNW AC Intertie, operations Indirect
          Costs for Bonneville's PNW AC Intertie, and operations Overhead
          Costs for Bonneville's PNW AC Intertie for such fiscal year, each
          being determined in accordance with section I of Exhibit I.
       
       "Capacity Ownership Percentage" is as defined in subsection 1(k) of
          each Capacity Owner's Agreement.

     The monthly charge for the Operations rate shall be calculated using the
     forecast Operations Cost in the Operating Plan in effect during the
     month for which the monthly charge is calculated; provided, however, if
     the Operating Plan is amended during the fiscal year to which such
     Operating Plan pertains, the monthly charge for Operations Cost shall be
     calculated using the forecast Operations Cost less the Operations Cost
     
                                                      Exhibit B, Page 2 of 9
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company


     
     already billed for such fiscal year for the remaining months of the
     fiscal year following such amendment.

B.   MAINTENANCE

     The monthly charge equals:

     Maintenance Cost * Capacity Ownership Percentage
     ------------------------------------------------
                       Months

     Where
  
       "Months" is equal to 12, or, if the Operating Plan has, during the
          fiscal year to which such Operating Plan pertains, been amended
          with respect to Maintenance Cost, the number of full months
          remaining in the fiscal year after such amended Operating Plan
          becomes effective for which Capacity Owners have not been billed.
       
       "Maintenance Cost" means, upon and after the effective date of
          Exhibit B pursuant to this Agreement, for any fiscal year any
          maintenance Direct Costs for Bonneville's PNW AC Intertie,
          maintenance Indirect Costs for Bonneville's PNW AC Intertie, and
          maintenance Overhead Costs for Bonneville's PNW AC Intertie for
          such fiscal year, each being determined in accordance with section
          II of Exhibit I.
       
       "Capacity Ownership Percentage" is as defined in subsection 1(k) of
          each Capacity Owner's Agreement.

     The monthly charge for the Maintenance rate shall be calculated using
     the forecast Maintenance Cost in the Operating Plan in effect during the
     month for which the monthly charge is calculated; provided, however, if
     the Operating Plan is amended during the fiscal year to which such
     Operating Plan pertains, the monthly charge for Maintenance Cost shall
     be calculated using the forecast Maintenance Cost less the Maintenance
     Cost already billed for such fiscal year for the remaining months of the
     fiscal year following such amendment.

C.   GENERAL PLANT
  
     The monthly charge equals:

     General Plant Cost * Capacity Ownership Percentage
     --------------------------------------------------
                          Months

     Where

       "Months" is equal to 12, or, if the Operating Plan has, during the
          fiscal year to which such Operating Plan pertains, been amended
                                                      Exhibit B, Page 3 of 9
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company


       
          with respect to General Plant Cost, the number of full months
          remaining in the fiscal year after such amended Operating Plan
          becomes effective for which Capacity Owners have not been billed.
       
       "General Plant Cost" means, upon and after the effective date of
          Exhibit B pursuant to this Agreement, for any fiscal year any costs
          (including direct costs, indirect costs, overhead costs, and AFUDC)
          for Bonneville's general plant investment for such fiscal year.
          The method for determining General Plant Cost is set forth in
          section IV of Exhibit I.
       
       "Capacity Ownership Percentage" is as defined in subsection 1(k) of
          each Capacity Owner's Agreement.

     The monthly charge for the General Plant rate shall be calculated using
     the General Plant Cost in the Operating Plan in effect during the month
     for which the monthly charge is calculated; provided, however, if the
     Operating Plan is amended during the fiscal year to which such Operating
     Plan pertains, the monthly charge for General Plant Cost shall be
     calculated using the General Plant Cost less the General Plant Cost
     already billed for such fiscal year for the remaining months of the
     fiscal year following such amendment.

D.   OTHER COSTS
  
     The monthly charge equals:
     
     Other Costs * Capacity Ownership Percentage
     -------------------------------------------
                       Months
     Where
     
       "Months" is equal to 12, or, if the Operating Plan has, during the
          fiscal year to which such Operating Plan pertains, been amended
          with respect to Other Cost, the number of full months remaining in
          the fiscal year after such amended Operating Plan becomes effective
          for which Capacity Owners have not been billed.
       
       "Other Costs" means, upon and after the effective date of Exhibit B
          pursuant to this Agreement, Bonneville's other costs for
          Bonneville's PNW AC Intertie described in and determined pursuant
          to section V of Exhibit I.
       
       "Capacity Ownership Percentage" is as defined in subsection 1(k) of
          each Capacity Owner's Agreement.

     The monthly charge for the Other Costs rate shall be calculated using
     the forecast Other Costs in the Operating Plan in effect during the
     month for which the monthly charge is calculated; provided, however, if
     the Operating Plan is amended during the fiscal year to which such
     Operating Plan pertains, the monthly charge for Other Costs shall be
                                                      Exhibit B, Page 4 of 9
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company


     
     calculated using the forecast Other Costs less the Other Costs already
     billed for such fiscal year for the remaining months of the fiscal year
     following such amendment.
  
E.   CONTRACTS AND RATES
  
     The monthly charge equals:
     
     Contracts and Rates Costs * Capacity Ownership Percentage
     ---------------------------------------------------------
                            Months
  
     Where
     
       "Months" is equal to 12, or, if the Operating Plan has, during the
          fiscal year to which such Operating Plan pertains, been amended
          with respect to Contracts and Rates Cost, the number of full months
          remaining in the fiscal year after such amended Operating Plan
          becomes effective for which Capacity Owners have not been billed.

       "Contracts and Rates Costs" means, upon and after the effective date
          of Exhibit B pursuant to this Agreement, for any fiscal year
          Bonneville's total contracts and rates costs (as described in
          section VI of Exhibit I) for such fiscal year as functionalized and
          allocated in accordance with section VI of Exhibit I to determine
          Contracts and Rates Costs for Bonneville's PNW AC Intertie.
     
       "Capacity Ownership Percentage" is as defined in subsection 1(k) of
          each Capacity Owner's Agreement.

     Contracts and Rates Cost is determined in accordance with section VI of
     Exhibit I as of the Effective Date.  If Exhibit I is amended pursuant to
     subsection 19(k) of the Agreement to provide that the Contracts and
     Rates Cost determined in accordance with section VI of Exhibit I (and
     reflected in the Operating Plan for the fiscal year to which such
     Operating Plan pertains) is directly assigned to the Capacity Owners
     pursuant to such amended Exhibit I (and reflected in the Operating Plan
     for the fiscal year to which such Operating Plan pertains), the Capacity
     Ownership Percentage in the monthly charge calculation for such fiscal
     year shall be replaced by the ratio of (a) each Capacity Ownership Share
     to (b) the sum of all Capacity Ownership Shares.
  
     The monthly charge for the Contracts and Rates rate shall be calculated
     using the forecast Contracts and Rates Costs in the Operating Plan in
     effect during the month for which the monthly charge is calculated;
     provided, however, if the Operating Plan is amended during the fiscal
     year to which such Operating Plan pertains, the monthly charge for
     Contracts and Rates Cost shall be calculated using the forecast
     Contracts and Rates Cost less the Contracts and Rates Cost already
     billed for such fiscal year for the remaining months of the fiscal year
     following such amendment.
                                                      Exhibit B, Page 5 of 9
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company


F.   POWER SCHEDULING
  
     The monthly charge equals:
     
     Power Scheduling Costs * Capacity Ownership Percentage
     ------------------------------------------------------
                             Months
  
     Where
  
       "Months" is equal to 12, or, if the Operating Plan has, during the
          fiscal year to which such Operating Plan pertains, been amended
          with respect to Power Scheduling Cost, the number of full months
          remaining in the fiscal year after such amended Operating Plan
          becomes effective for which Capacity Owners have not been billed.
       
       "Power Scheduling Costs" means, upon and after the effective date of
          Exhibit B pursuant to this Agreement, Bonneville's total power
          scheduling costs (as described in section VII of Exhibit I) as
          functionalized and allocated in accordance with section VII of
          Exhibit I to determine Power Scheduling Costs for Bonneville's PNW
          AC Intertie.
       
       "Capacity Ownership Percentage" is as defined in subsection 1(k) of
          each Capacity Owner's Agreement.
   
     Power Scheduling Cost is determined in accordance with section VII of
     Exhibit I as of the Effective Date.  If Exhibit I is amended pursuant to
     subsection 19(k) of the Agreement to provide that the Power Scheduling
     Cost determined in accordance with section VII of Exhibit I (and
     reflected in the Operating Plan for the fiscal year to which such
     Operating Plan pertains) is directly assigned to the Capacity Owners
     pursuant to such amended Exhibit I (and reflected in the Operating Plan
     for the fiscal year to which such Operating Plan pertains), the Capacity
     Ownership Percentage in the monthly charge calculation for such fiscal
     year shall be replaced by the ratio of (a) each Capacity Ownership Share
     to (b) the sum of all Capacity Ownership Shares.
  
     The monthly charge for the Power Scheduling rate shall be calculated
     using the forecast Power Scheduling Costs in the Operating Plan in
     effect during the month for which the monthly charge is calculated;
     provided, however, if the Operating Plan is amended during the fiscal
     year to which such Operating Plan pertains, the monthly charge for Power
     Scheduling Cost shall be calculated using the forecast Power Scheduling
     Cost less the Power Scheduling Cost already billed for such fiscal year
     for the remaining months of the fiscal year following such amendment.

G.   END OF TERM
  
     The monthly charge shall equals:
  
     End of Term Costs * Capacity Ownership Percentage
                                                      Exhibit B, Page 6 of 9
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company


     
     
     -------------------------------------------------
                       Months
     
     Where
     
  
       "Months" is equal to 12, or, if the Operating Plan has, during the
          fiscal year to which such Operating Plan pertains, been amended
          with respect to End of Term Costs, the number of full months
          remaining in the fiscal year after such amended Operating Plan
          becomes effective for which Capacity Owners have not been billed.
       
       "End of Term Costs" means, upon and after the effective date of
          Exhibit B pursuant to this Agreement, Bonneville's costs associated
          with decommissioning the PNW AC Intertie determined in accordance
          with section VIII of Exhibit  I.
       
       "Capacity Ownership Percentage" is as defined in subsection 1(k) of
          each Capacity Owner's Agreement.
       
     The monthly charge for the End of Term rate shall be calculated using
     the forecast End of Term Costs in the Operating Plan in effect during
     the month for which the monthly charge is calculated; provided, however,
     if the Operating Plan is amended during the fiscal year to which such
     Operating Plan pertains, the monthly charge for End of Term Costs shall
     be calculated using the forecast End of Term Costs less the End of Term
     Cost already billed for such fiscal year for the remaining months of the
     fiscal year following such amendment.

H.   REPLACEMENTS AND REINFORCEMENTS

     1.  For each Replacement, the charge equals:

            Replacement Cost * Capacity Ownership Percentage
  
     2.  For each Reinforcement, the charge equals:
  
         Reinforcement Cost * Capacity Ownership Percentage

     Where

       "Replacement Cost" means, upon and after the effective date of
          Exhibit B pursuant to this Agreement, for any Replacement, the
          Direct Costs, Indirect Costs, Overhead Costs, and AFUDC for such
          Replacement, all capitalized to plant-in-service together with (1)
          simple interest on the foregoing costs accrued from the date on
          which Bonneville stops accruing AFUDC on the foregoing costs until
          the due date of the bill to Capacity Owner for the foregoing costs
          pursuant to subparagraph 9(b)(2)(B) and (2) the costs of removal
          and any salvage credit associated with removal or replacement of
                                                      Exhibit B, Page 7 of 9
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company


       
         existing facilities.  Replacement Cost does not include capitalized
          general plant cost.  The method for determining Replacement Costs
          for Bonneville's PNW AC Intertie is set forth in section III of
          Exhibit I.
       
       "Reinforcement Cost" means, upon and after the effective date of
          Exhibit B pursuant to this Agreement, for any Reinforcement, the
          Direct Costs, Indirect Costs, Overhead Costs, and AFUDC for such
          Reinforcement, all capitalized to plant-in-service together with
          (1) simple interest on the foregoing costs accrued from the date on
          which Bonneville stops accruing AFUDC on the foregoing costs until
          the due date of the bill to Capacity Owner for the foregoing costs
          pursuant to subparagraph 9(b)(2)(B) and (2) the costs of removal
          and any salvage credit associated with removal or replacement of
          existing facilities.  Reinforcement Cost does not include
          capitalized general plant cost.  The method for determining
          Reinforcement Costs for Bonneville's PNW AC Intertie is set forth
          in section III of Exhibit I.
       
       "Capacity Ownership Percentage" is as defined in subsection 1(k) of
          each Capacity Owner's Agreement.
          
     The charge for the Replacements and Reinforcements rate shall use the
     actual Replacement Cost and Reinforcement Cost in the Operating Plan.

SECTION III.  ADJUSTMENTS

     If an amendment to the Operating Plan results in a net amount that
     Bonneville owes the Capacity Owners pursuant to sections II.A-G or
     pursuant to section II.H, Bonneville shall refund such net amount
     pursuant to paragraph 9(f)(4) of the Agreement.
     
     The monthly charges assessed Capacity Owners under sections II.A-G shall
     be adjusted, and payment or refund made with interest, pursuant to
     paragraphs 9(b)(2) or 9(f)(4) of the Agreement, to reflect amendments to
     the Operating Plan that occur after the year to which such Operating
     Plan pertains.  A Capacity Owner's share of the adjustment shall be
     determined using the same Capacity Ownership Percentage used in the
     billings under sections II.A-G during the fiscal year that such
     Operating Plan is effective.

B.   BILLING PROVISIONS

I.   General Provisions

     A.   Approval of Rates

     The annual costs rate shall become effective upon interim approval or
     upon final confirmation and approval by FERC.  Bonneville will request
     FERC approval of such rate schedule effective on the first day of a
     Bonneville fiscal year.
                                                      Exhibit B, Page 8 of 9
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company


     B.   Application of Billing Provisions

     These Billing Provisions shall apply to bills rendered by Bonneville
     pursuant to the annual costs rate.

     C.   Definition of Terms

     The meaning of terms used in the AC-95 rate shall be as defined in the
     Agreement or, if no definition is provided by the Agreement, such terms
     shall be defined according to applicable Federal law.

II.  Billing Information

     Payment of Bills

     Charges pursuant to the AC-95 rate shall be included in Bonneville's
     monthly power bill to Capacity Owner.  Failure to receive a power bill
     shall not release Capacity Owner from liability for payment.  Power
     bills for amounts due of $50,000 or more must be paid by direct wire
     transfer.  If Capacity Owner anticipates special difficulties in meeting
     this requirement, Capacity Owner may request and Bonneville may approve
     an exemption from this requirement.  Power bills for amounts due
     Bonneville under $50,000 may be paid by direct wire transfer or mailed
     to the Bonneville Power Administration, P.O. Box 6040, Portland, Oregon
     97228-6040, or to another location as directed by Bonneville.  The
     procedures to be followed in making direct wire transfers will be
     provided by Bonneville's Financial Services Group and updated as
     necessary.

     (1)  Computation of Bills

          (a)  Bonneville shall bill Capacity Owner in accordance with the
          annual costs rate.
     
          (b)  Capacity Owner shall provide necessary information to
          Bonneville for any computation required to determine proper charges
          pursuant to the Agreement and shall cooperate with Bonneville in
          the exchange of additional information which may be reasonably
          useful for respective operations.
     
          (c)  Bills rendered pursuant to this Agreement shall be rounded to
          whole dollar amounts, by eliminating any amount which is less than
          50 cents and increasing any amounts from 50 cents to 99 cents to
          the next higher whole dollar.
     

     (2)  Billing Month

     For charges pursuant to the annual costs rate the billing month shall be
     the same as for the power bill rendered by Bonneville to Capacity Owner.
     
     (3)  Due Date
                                                      Exhibit B, Page 9 of 9
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company


     Charges pursuant to the annual costs rate shall be included in the power
     bill rendered by Bonneville to Capacity Owner and shall be due as part
     of the power bill when such power bill is due.

     (4)  Late Payment

     The penalties for failure to pay a bill in full on or before close of
     business on the due date shall be the same as those contained in the
     late payment provisions in Bonneville's General Transmission Rate
     Schedule Provisions in effect on the date of the bill; provided,
     however, that no other provision of any such General Transmission Rate
     Schedule Provisions, including, but not limited to, provisions regarding
     cancellation, termination, or suspension of service, shall have
     application with respect to the payment of any rate or charge pursuant
     to the annual costs rate set forth in Exhibit B.  Bonneville's right to
     suspend service for late payment under the Agreement shall be pursuant
     to paragraph 9(e)(1) of this Agreement, which right shall in no way be
     limited by this section.

     (5)  Disputed Bills

     In the event of a disputed bill, full payment shall be rendered to
     Bonneville and the disputed amount noted.  Disputed amounts are subject
     to the late payment provisions specified in section II(4) of the Billing
     Provisions of this Exhibit B.  Bonneville shall separately account for
     the disputed amount.  If it is determined that Capacity Owner is
     entitled to the disputed amount, Bonneville shall refund the disputed
     amount with interest, such interest to be determined by Bonneville's
     Financial Services Group.  In the event that Bonneville and Capacity
     Owner do not resolve such dispute, Capacity  Owner shall not be
     prevented by this section II(5)of the Billing Provisions of this Exhibit
     B from initiating arbitration pursuant to and to the extent allowed by
     section 15 of this Agreement.

     (6)  Revised Bills

     If Bonneville determines that it has over- or under-charged Capacity
     Owner due to a computational error or pursuant to an amendment to the
     Operating Plan in any given billing month, Bonneville may render to
     Capacity Owner a revised bill.

          (i)  If the amount of the revised bill is less than or equal to the
          amount of the original bill for such billing month, the revised
          bill shall replace the original bill issued by Bonneville.  The
          revised bill shall have the same date as the original bill.
     
          (ii) If the amount of the revised bill is greater than the amount
          of the original bill for such billing month, a new bill will be
          issued for the difference between the revised bill and the original
          bill.  The date of the new bill shall be its date of issuance, and
          Capacity Owner shall make payment to Bonneville as specified in the
          Billing Provisions of this Exhibit B.
                                                     Exhibit C, Page 1 of 1
                                             Contract No. DE-MS79-94BP94521
                                          Puget Sound Power & Light Company
                                            Effective on the Effective Date


            CAPACITY OWNERSHIP SHARE, CAPACITY OWNERSHIP PERCENTAGE
                 SCHEDULING PERCENTAGE, AND SCHEDULING SHARE



Capacity Ownership
         Share          =     400 MW


Capacity Ownership
         Percentage     =     Capacity Ownership Share divided by
                                 Bonneville's PNW AC Intertie Rated
                                 Transfer Capability (1)


Scheduling Percentage   =     Capacity Ownership Share divided by
                                 PNW AC Intertie Rated Transfer Capability


Scheduling Share        =     Scheduling Percentage    PNW AC Intertie
                                 Operational Transfer Capability

- --------------------

(1) As of the Effective Date, Bonneville's PNW AC Intertie Rated Transfer
   Capability in a north-to-south direction, calculated in accordance with
   the Northwest Intertie Agreements equals 3450 MW (total PNW AC Intertie
   Rated Transfer Capability (4800MW) - Portland's PNW AC Intertie Rated
   Transfer Capability (950 MW) - PacifiCorp's PNW AC Intertie Rated
   Transfer Capability (400 MW)).
                                                      Exhibit D, Page 1 of 5
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company
                                             Effective on the Effective Date

                        LUMP SUM PAYMENT CALCULATION
A.    SECOND 800 MW COSTS, ESTIMATED (1), ACTUAL (2), AND REVISED ACTUAL (3)
                                                 ($ in Thousands)

                                                        (2)        BPA's
                                              (1)       BPA's      Costs
FACILITIES WHOSE COSTS WILL BE ADJUSTED    BPA's Costs  Costs      Revised
Using Change Between Estimate And Actual   Estimated    Actual     Actual
- ----------------------------------------   -----------  --------   -------

 1. Alvey (Marion-Alvey Caps)              $5,739
 2. Slatt (Loop in - Breaker)               3,044
 3. Grizzly (BPA Breakers)                 11,044
 4. Loop into Slatt                           656
 5. Malin-Meridian loop into Captain Jack     982
 6. Alvey Substation - BPA                  8,168
 7. Dixonville - PacifiCorp                 8,635
 8. Meridian - PacifiCorp                   6,548
 9. Power System Control                    3,575
10. Alvey-Spencer - BPA                     1,346
11. Spencer-Dixonville - PacifiCorp        20,388
12. Dixonville-Meridian - PacifiCorp       32,140
                                          -------
    SUBTOTAL                              102,265

FACILITIES WHOSE COSTS WILL BE ADJUSTED USING CHANGE
BETWEEN ESTIMATE AND ACTUAL, MULTIPLIED BY 50 PERCENT

13. Captain Jack (BPA Breakers)           $14,335
14. Captain Jack (Communication
     and Control)                           5,100
15. Captain Jack (Series Capacitors)          722
16. Power System Control                    5,596
17. Captain Jack line to
    Oregon-Calif. border                    5,724
                                           ------
    SUBTOTAL                              $31,477
    50 PERCENT OF SUBTOTAL                 15,739
                                          -------
    TOTAL                                $118,004
                                          -------
- --------------------

(1) Based on mid-1989 program planning levels.
(2) Actual costs will be available approximately December 1995, or as soon as
   practicable thereafter.  Supporting documentation will be provided
   including work orders and accounting data for each line item.
(3) For each calculation of the Revised Adjusted Capacity Ownership Price,
   Bonneville will include the revised actual costs of facilities pertaining
   to each such calculation of the Revised Adjusted Capacity Ownership
   Price.
                                                     Exhibit D, Page 2 of 5
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company
                                             Effective on the Effective Date

B.  INITIAL, ADJUSTED, AND REVISED ADJUSTED CAPACITY OWNERSHIP PRICE (1)

                                             ($ in Millions)
                                       (1)           (2)        Revised
                                     Initial      Adjusted      Adjusted
                                     Capacity     Capacity      Capacity
                                     Ownership    Ownership     Ownership
                                     Price        Price         Price
    COST ITEM

1.  Second 800 MW                    $118         $___          $___

2.  AFUDC(3) on Second 800 MW       +  19        + ___         + ___

3.  Existing Support Facilities     +  19.1      +  19.1(4)    +  19.1(4)
                                      ---          ---           ---

4.  Total Cost(5)                    $156         $___          $___

5.  PRICE PER KW (CO-94)(6)          $215         $___          $___

- --------------------

(1) Initial, Adjusted, and Revised Adjusted Capacity Ownership Price are
   determined in accordance with the CO-94 rate in Exhibit A.

(2) Bonneville may make multiple calculations of the Revised Adjusted
   Capacity Ownership Price pursuant to paragraph 9(a)(3).  For each
   calculation of the Revised Adjusted Capacity Ownership Price, Bonneville
   will include the column pertaining to such calculation and the columns
   for any previous calculations of the Revised Adjusted Capacity Ownership
   Price.

(3) AFUDC will be calculated in accordance with the CO-94 rate in Exhibit A.

(4) Not adjusted in calculating the Adjusted Capacity Ownership Price or the
   Revised Adjusted Capacity Ownership Price.

(5) Bonneville's indirect costs and overhead costs shall be included.  Such
   indirect costs and overhead costs shall be allocated or distributed to
   the Third AC Intertie Project using the indirect and overhead allocation
   and distribution methodologies employed by Bonneville to allocate and
   distribute indirect and overhead costs to all of Bonneville's other
   capital projects during the time the Third AC Intertie Project was under
   construction.  Such allocation or distribution methodologies shall not be
   required to meet any stricter standard of benefit to Bonneville's Third
   AC Intertie Project than with respect to any other transmission projects
   under construction at the same time.

(6) Price per kW is derived by dividing the Total Cost by 725 MW.
                                                       Exhibit D, Page 3 of 5
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date



C.  INITIAL LUMP SUM PAYMENT


1.  Puget's Capacity Ownership Share         =     400 MW

2.  Initial Capacity ownership Price
                                             X     $215 ($215,000/MW)

3.  Initial Lump Sum Payment (1)
                                             =     $86,000,000

4.  Deduction:
      Negotiation Deposit with Interest (2)  -

5.  Due to Bonneville:                       =

- --------------------

(1) Initial Lump Sum Payment is calculated in accordance with section IV.A of
    the CO-94 rate in Exhibit A.

(2) Interest is calculated as specified in Bonneville's April 23, 1993,
    letter to Puget.  The rate of interest for the computation is the
    interest rate applicable to 3-month Treasury Bills as specified in the
    FEDERAL RESERVE Statistical Release G.13.  The rates are determined for
    the 3-month yield reported on the first day of the month of receipt of
    the negotiation deposit and on the first day of each subsequent third
    month thereafter.  Interest is compounded quarterly from May 11, 1993,
    through the date Bonneville receives payment pursuant to paragraph
    9(a)(1).

                                                       Exhibit D, Page 4 of 5
                                                        No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date


D.  ADJUSTED LUMP SUM PAYMENT

1.  Puget's Capacity Ownership Share         =     400 MW

2.  Adjusted Capacity Ownership Price
                                             X     $

3.  Adjusted Lump Sum Payment (1)            =

4.  Initial Lump Sum Payment                 -     ______________

5.  SUBTOTAL due to Bonneville, or Refund
    Due to Puget                             =

6.  Interest (2)                             +

7.  Due to Bonneville, or Refund
    Due to Puget                             =
- --------------------

(1) Adjusted Lump Sum Payment is calculated in accordance with the CO-94 rate
    in Exhibit A.

(2) Interest will be calculated in accordance with the CO-94 rate in Exhibit
    A using the weighted average interest rate on Bonneville's outstanding
    bonds.  Simple interest will be accrued from the date Bonneville receives
    payment pursuant to paragraph 9(a)(1) through the date Bonneville or
    Puget receives payment pursuant to subparagraph 9(a)(2)(B).


                                                       Exhibit D, Page 5 of 5
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date


E.  REVISED ADJUSTED LUMP SUM PAYMENT

1.  Puget's Capacity Ownership Share         =     400 MW

2.  Current Revised Adjusted Capacity
    Ownership Price                          x     $

3.  Current Revised Adjusted Lump Sum
    Payment (1)                              =

4.  Adjusted Lump Sum Payment/immediately    -     ____________________
    preceding Revised Adjusted Lump Sum
    Payment

5.  SUBTOTAL due to Bonneville, or Refund
    Due to Puget                             =

6.  Interest (2)                             +

7.  Due to Bonneville, or Refund
    Due to Puget                             =

- --------------------

(1) Revised Adjusted Lump Sum Payment is calculated in accordance with the CO-
    94 rate in Exhibit A.  Bonneville will calculate a Revised Adjusted Lump
    Sum Payment each time a Revised Adjusted Capacity Ownership Price is
    calculated pursuant to paragraph 9(a)(3).

(2) Interest will be calculated in accordance with the CO-94 rate in Exhibit
    A using the weighted average interest rate on Bonneville's outstanding
    bonds.  Simple interest will be accrued from (a) the date Bonneville or
    Puget receives payment with respect to the Adjusted Lump Sum Payment
    pursuant to paragraph 9(a)(2)(B) or (b) the date Bonneville or Puget
    receives payment with respect to the Revised Adjusted Lump Sum Payment
    immediately preceding the current Revised Adjusted Lump Sum Payment
    through the date Bonneville or Puget receives payment with respect to the
    current Revised Adjusted Lump Sum Payment pursuant to subparagraph
    9(a)(3)(B).

                                                       Exhibit E, Page 1 of 1
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date



                             Transmission Loss Factors


A.   The transmission loss factor to be applied to Puget's schedules for
     transactions transmitted on Puget's Scheduling Share shall be 2.5
     percent.

B.   The transmission loss factor to be applied to Puget's schedules for
     transactions transmitted pursuant to subparagraph 3(b)(1)(C) shall be
     3.0 percent.

                                                    Exhibit F, Page 1 of 10
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company
                                             Effective on the Effective Date


                         BONNEVILLE'S PNW AC INTERTIE

A.  TRANSMISSION LINE FACILITIES
                                                           % APPLICABLE TO
                                          % BPA OWNED      PNW AC INTERTIE
                                          -----------      ---------------
 1. McNary-John Day 500 kV Line               100               100
    ---------------------------
    Loop into Slatt:
    ---------------
      McNary-Slatt Str. 108/1 to
      substation dead end tower,
      155 meters
      Slatt-John Day Str. 1/1 to
      substation dead end tower,
      194 meters
 2. John Day-Grizzly No. 1 500 kV             100               100
 3. John Day-Grizzly No. 2 500 kV             100               100
 4. Grizzly-Captain Jack No. 1 500 kV         100               100
 5. Captain Jack-Malin No. 1 500 kV           100               100
 6. Buckley-Grizzly 500 kV                    100                57
 7. Grizzly-Summer Lake 500 kV                100                57
 8. 500 kV double circuit between             100                25
    Buckley and Marion that supports
    the Buckley-Marion No. 1 and the
    Ashe-Marion No. 2 500 kV circuits
    (Str. No. 1/3 to Marion, 159 km)
 9. Marion-Alvey 500 kV                       100                50
10. Captain Jack-COB (10 km) 500 kV           100               100
11. Alvey-Dixonville 500 kV                    50               100
12. Dixonville-Meridian 500 kV                 50               100


B.  SUBSTATION FACILITIES (1)(2)

                                                           % APPLICABLE TO
                                          % BPA OWNED      PNW AC INTERTIE
                                          -----------      ---------------

 1. SLATT 500 kV (Dispatch one-line
    diagram No. 228962)
    John Day line terminal
    ----------------------
      New Breaker D#5021                      100               100
      Existing 500 kV MOD D#5020/7022         100               100
      New 500 kV MOD D#5022                   100               100
      Existing 500 kV MOD D#5019              100                50
      Existing Breaker D#5018                 100                50
                                                     Exhibit F, Page 2 of 10
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company
                                             Effective on the Effective Date

                                                           % APPLICABLE TO
                                          % BPA OWNED      PNW AC INTERTIE
                                          -----------      ---------------

      Associated Terminal Arresters           100               100
      Associated Line PTs                     100               100
    McNary line terminal
    --------------------
      500 kV MOD D#5023/7847                  100               100
      Associated Terminal Arresters           100               100
      Associated Line PTs                     100               100
    Station General
 2. JOHN DAY 500 kV (Dispatch one-line
    diagram No. 132281)
    Grizzly No.2 line terminal
    --------------------------
      Breaker D#4131                          100                50
      Breaker D#4134                          100               100
      MOD D#4132                              100                50
      MOD D#4133/7867                         100               100
      MOD D#4135                              100               100
      Associated Line PTs                     100               100
    Grizzly No.1 line terminal
    --------------------------
      Breaker D#4140                          100                50
      Breaker D#4143                          100               100
      MOD D#4141                              100                50
      MOD D#4142/7869                         100               100
      MOD D#4144                              100               100
      Associated Terminal Arresters           100               100
      Associated Line PTs                     100               100
    Station General
 3. BUCKLEY 500 KV, GAS INSULATED
    SUBSTATION (Dispatch one-line
    diagram No. 232583)
    Slatt No. 1 line terminal
    -------------------------
      Breaker D#4967                          100                57
      Isolating switch D#4966/7328            100                57
      Isolating switch D#4968/7355            100                57
      Ground switch D#7415                    100                57
      Associated Terminal Arresters           100                57
      Associated Line PTs                     100                57
    Summer Lake No. 1 line terminal
    -------------------------------
      Breaker D#4961                          100                57
                                                     Exhibit F, Page 3 of 10
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company
                                             Effective on the Effective Date

                                                           % APPLICABLE TO
                                          % BPA OWNED      PNW AC INTERTIE
                                          -----------      ---------------

      Isolating switch D#4960/7312            100                57
      Isolating switch D#4962/7313            100                57
      Ground switch D#7311                    100                57
      Associated Terminal Arresters           100                57
      Associated Line PTs                     100                57
    Marion No. 1 line terminal
    --------------------------
      Breaker D#4964                          100                57
      Isolating switch D#4963/7314            100                57
      Isolating switch D#4965/7321            100                57
      Ground switch D#7477                    100                57
      Associated Terminal Arresters           100                57
      Associated Line PTs                     100                57
    Station General
 4. MARION 500 kV (Dispatch one-line
    diagram No. 136180)
    Buckley line terminal
    ---------------------
      Breaker D#4389                          100                50
      Breaker D#4386                          100                25
      MOD D#4387                              100                25
      MOD D#4390                              100                50
      MOD D#4388/7751                         100                50
      Associated Line PTs                     100                50
    Alvey line terminal
    -------------------
      Breaker D#4374                          100                50
      Breaker D#4377                          100                25
      MOD D#4376                              100                25
      MOD D#4375/7922                         100                50
      MOD D#4373                              100                50
      Associated Line PTs                     100                50
    Station General
 5. ALVEY 500 kV (Dispatch one-line
    diagram No. 121424)
    Bank No. 5 terminal
    -------------------
      Breaker D#5081                           50               100
      MOD D#5080                               50               100
      MOD D#5082                               50               100
      MOD D#5090                               50               100
                                                     Exhibit F, Page 4 of 10
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company
                                             Effective on the Effective Date

                                                           % APPLICABLE TO
                                          % BPA OWNED      PNW AC INTERTIE
                                          -----------      ---------------

      MOD D#5089/8157                          50               100
      Associated Terminal Arresters            50               100
      Associated Line PTs                      50               100
    Marion No. 1 line terminal
    --------------------------
      Breaker D#5084                           50               100
      MOD D#5083/8155                          50               100
      MOD D#5085                               50               100
      Associated Terminal Arresters            50               100
      Associated Line PTs                      50               100
    Dixonville No. 1 line terminal
    ------------------------------
      Breaker D#5087                           50               100
      MOD D#5086/8156                          50               100
      MOD D#5088                               50               100
      Associated Terminal Arresters            50               100
      Associated Line PTs                      50               100
    500 kV Series Capacitor Bank               50               100
    ---------------------------
    (Marion-Alvey 500 kV line)
      MODs D#5100/8160,5101/8159,
      5102/8158                                50               100
      Bypass breaker D#5103                    50               100
    Station General
 6. BPA/PACIFICORP DIXONVILLE 500 kV STATION
    (PacifiCorp's one-line diagram PD-40020)
   Note:  PacifiCorp will be invoicing BPA for any future replacements of
   these items listed consistent with Exhibit C of Bonneville-PacifiCorp
   Amendatory Agreement No. 2 to Contract No. DE-MS79-86BP92299, as revised
   or amended.
   For Alvey and Meridian line terminals
   -------------------------------------
      Breakers 11U1, 11U2, 11U3                50               100
      Isolating MODs 11U701, 11U700/ 11U507,
      11U702, 11U703/11U505, 11U704, 11U705/
      11U506, 11U706, 11U707, 11U708/11U501    50               100
      Two sets of line terminal PTs            50               100
      Two sets of line terminal arresters      50               100
                                                     Exhibit F, Page 5 of 10
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company
                                             Effective on the Effective Date

                                                           % APPLICABLE TO
                                          % BPA OWNED      PNW AC INTERTIE
                                          -----------      ---------------

    Series Capacitor Bank in Alvey-            50               100
    Dixonville 500 kV line and
    associated isolating devices
    180 MVAR Shunt Reactor Bank S664, 665,     50               100
    666, 667 and associated arresters,
    PTs, and isolating devices
    Station General
 7. BPA/PACIFICORP MERIDIAN 500 kV
    YARD (PacifiCorp's one-line diagram
    PD-32976)
   Note:  PacifiCorp will be invoicing BPA for any future replacements of
   these items listed consistent with Exhibit C of Bonneville-PacifiCorp
   Amendatory Agreement No. 2 to Contract No. DE-MS79-86BP92299.
   For Dixonville line terminal
   ---------------------------
      Breakers 11R2, 11R6                      50                50
      Isolating MODs 11R702, 11R703/          100               100
      11R501, 11R704, 11R710, 11R711
      One set of line PTs                      50               100
      One set of line terminal arresters       50               100
      for the Dixonville line and one set
      for the Captain Jack line
      180 MVAR Shunt Reactor Bank S690,        50               100
      691 ,692, 693 and associated
      arresters, PTs, and isolating devices
      Series Capacitor Bank in the             50               100
      Dixonville- Meridian 500 kV line
      and associated isolating devices.
    Station General
 8. GRIZZLY 500 kV (Dispatch one-line
    diagram No. 103924)
    John Day No. 1 line terminal
    ----------------------------
      Breaker D#4058                          100               100
      Breaker D#5040                          100               100
      MOD D#4059                              100               100
      MOD D#4057/7848                         100               100
                                                     Exhibit F, Page 6 of 10
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company
                                             Effective on the Effective Date

                                                           % APPLICABLE TO
                                          % BPA OWNED      PNW AC INTERTIE
                                          -----------      ---------------

      MOD D#4056                              100               100
      MOD D#5039                              100               100
      Associated Terminal Arresters           100               100
      Associated Line PTs                     100               100
    John Day No. 2 line terminal
    ----------------------------
      Breaker D#4042                          100               100
      Breaker D#4046                          100               100
      MOD D#4043                              100               100
      MOD D#4044/7845                         100               100
      MOD D#4045                              100               100
      MOD D#4047                              100               100
      Associated Terminal Arresters           100               100
      Associated Line PTs                     100               100
    Buckley No. 1 line terminal
    ---------------------------
      Breaker D#5031                          100               100
      Breaker D#5028                          100               100
      MOD D#5032                              100               100
      MOD D#5030/8122                         100               100
      MOD D#5029                              100               100
      MOD D#5027                              100               100
      Associated Line PTs                     100               100
    Captain Jack No. 1 line terminal
    --------------------------------
      Breaker D#5037                          100               100
      Breaker D#5034                          100               100
      MOD D#5038                              100               100
      MOD D#5036/8123                         100               100
      MOD D#5035                              100               100
      MOD D#5033                              100               100
      Associated Terminal Arresters           100               100
      Associated Line PTs                     100               100
    Summer Lake line terminal
    -------------------------
      Breaker D#5025                          100               100
      MOD D#5026/8121                         100               100
      MOD D#5024                              100               100
      Associated Terminal Arresters           100               100
      Associated Line PTs                     100               100
                                                     Exhibit F, Page 7 of 10
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company
                                             Effective on the Effective Date

                                                           % APPLICABLE TO
                                          % BPA OWNED      PNW AC INTERTIE
                                          -----------      ---------------

    180 MVAR Reactor Bank No. 1               100               100
    ---------------------------
      Breaker D#4222                          100               100
      Isolating Switch D#4060                 100               100
      Associated Arresters                    100               100
    300 MVAR Reactor Bank No. 2               100               100
    ---------------------------
      Breaker D#4720                          100               100
      Isolating Switch D#4719                 100               100
      Associated Arresters                    100               100
      300 MVAR Reactor Bank No. 3 and         100               100
      Neutral Reactor
      Breaker D#4038                          100               100
      Isolating Switch D#4062                 100               100
      Neutral isolating switch D#4109/4081    100               100
      Associated Arresters                    100               100
      Associated PTs                          100               100
      North Main Bus 500 kV PTs               100               100
      South Main Bus 500 kV PTs               100               100
    Station General
 9. SAND SPRING 500 kV COMPENSATION
    STATION (Dispatch one-line
    diagram No. 142239)
    Series Cap.Bank No. 1                     100               100
    ---------------------
    (Grizzly-Captain Jack line)
    and associated equipment
    Series Cap. Bank No. 3                    100               100
    ----------------------
    (Grizzly-Summer Lake line)
     and associated equipment
    Station General
10. FORT ROCK 500 kV COMPENSATION STATION
    (Dispatch one-line diagram No. 142237)
    Series Cap. Bank No. 1                    100               100
    ----------------------
    (Grizzly-Captain Jack line)
    and associated equipment
    Series Cap. Bank No. 3                    100               100
    ---------------------------
    (Grizzly-Summer Lake line)
    and associated equipment
    Station General
11. SYCAN 500 kV COMPENSATION STATION
    (Dispatch one-line diagram No. 142238)
                                                     Exhibit F, Page 8 of 10
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company
                                             Effective on the Effective Date

                                                           % APPLICABLE TO
                                          % BPA OWNED      PNW AC INTERTIE
                                          -----------      ---------------

    Series Cap. Bank No. 1                    100               100
    ----------------------
    (Grizzly- Captain Jack line) and
    associated equipment
    Series Cap. Bank No. 3                     65               100
    ----------------------
    (Summer Lake-Malin line) and
    associated equipment but EXCLUDING
    the bypass MOD D#5065 and
    transmission tower
    Station General
12. SUMMER LAKE 500 kV (Dispatch one-
    line diagram No. 232667)
    Grizzly line terminal
    ----------------------
    (formerly Buckley-Ponderosa Tap)
      Breaker D#4959                          100                57
      MOD D#4955                              100                57
      MOD D#4956/7309                         100                57
      Associated Terminal Arresters           100                57
      Associated Line PTs                     100                57
    Malin line terminal
    -------------------
      Line protective relays                    0               100
    Station General
13. MALIN 500 kV (Dispatch one-
    line diagram No. 103923)
    Captain Jack No. 1 line terminal
    --------------------------------
      Breaker D#4066                          100               100
      Breaker D#4064                          100               100
      MOD D#4068                              100               100
      MOD D#4067/7849                         100               100
      MOD D#4065
      Associated Terminal Arresters           100               100
      Associated Line PTs                     100               100
    Round Mountain line No. 1 terminal
    ----------------------------------
      Breaker D#4186                           50               100
      MOD D#4063/7970                         100               100
      MOD D#4185                               50               100
      MOD D#4187                               50               100
      Associated Terminal Arresters           100               100
      Associated Line PTs                     100               100
    Round Mountain line No. 2 terminal
    ----------------------------------
                                                     Exhibit F, Page 9 of 10
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company
                                             Effective on the Effective Date

                                                           % APPLICABLE TO
                                          % BPA OWNED      PNW AC INTERTIE
                                          -----------      ---------------

      Breaker D#4582                           50               100
      MOD D#4583                               50               100
      MOD D#4581                               50               100
      MOD D#4074/7856                          75               100
    Grizzly No. 2/Round Mountain No. 2
    ----------------------------------
    line position
    -------------
      Breaker D#4072                           75               100
      MOD D#4073                               75               100
    North Main Bus 500 kV PTs                 100               100
    -------------------------
    South Main Bus 500 kV PTs                  50               100
    -------------------------
    300 MVAR Shunt Reactor Bank No. 1         100               100
    ---------------------------
    and associated arresters and
    isolating devices (D#4327, 4393)          100               100
    2-239 MVAR Shunt Cap. Banks and
    ---------------------------
    associated isolating devices (D#4183,
    4181, 4184, 4182, 8065, 8066)
    Line protective relays for Summer           0               100
    ---------------------------------
    Lake line
    ---------
    Station General
14. CAPTAIN JACK 500 kV (Dispatch one-line
    diagram No. 248548)
    Series Cap. Bank No. 1
    ----------------------
    (Captain Jack-Olinda line)                100               100
      MODs D#4974/8101, 4973/8099,            100               100
      4975/ 8100
      Bypass breaker D#4971, 4972
    Grizzly No. 1 line terminal
    ---------------------------
      Breaker D#4990                          100               100
      Breaker D#4993                          100               100
      MOD D#4989                              100               100
      MOD D#4991/8104                         100               100
      MOD D#4992                              100               100
      MOD D#4994/8105                         100               100
      Associated Terminal Arresters           100               100
      Associated Line PTs                     100               100
    Malin No. 1 line terminal
    -------------------------
      Breaker D#4996                          100               100
                                                    Exhibit F, Page 10 of 10
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company
                                             Effective on the Effective Date

                                                           % APPLICABLE TO
                                          % BPA OWNED      PNW AC INTERTIE
                                          -----------      ---------------


      MOD D#4995                              100               100
      MOD D#4997                              100               100
      Associated Terminal Arresters           100               100
      Associated Line PTs                     100               100
    Olinda No. 1 line terminal
    --------------------------
      Breaker D#4977                          100               100
      Breaker D#4980                          100               100
      MOD D#4976                              100               100
      MOD D#4978                              100               100
      MOD D#4979                              100               100
      MOD D#4981                              100               100
      Associated Terminal Arresters           100               100
      Associated Line PTs (2 sets)            100               100
    North Main Bus 500 kV PTs                 100               100
    -------------------------
    South Main Bus 500 kV PTs                 100               100
    Station General
15. CHIEF JOSEPH SUBSTATION (Dispatch         100               100
    one-line diagram No. 124313)
    230kV, 1400 MW Braking Resistor
    -------------------------------
    Includes  breaker dispatch No. A-594,
    a high speed vacuum switch and one 230 kV
    isolating switch in Bay 12
    -----------------------------

(1) Station General will be allocated to each substation according to
    Bonneville's standard methodology.

(2) Each substation includes associated relays.
                                                       Exhibit G, Page 1 of 1
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date



                               CAPACITY OWNERS


                                         CAPACITY         CAPACITY
                        CONTRACT        OWNERSHIP        OWNERSHIP
CAPACITY OWNER           NUMBER         SHARE (MW)      PERCENTAGE

PNGC               DE-MS79-94BP94523        50              1.4
Puget              DE-MS79-94BP94521       400             11.6
Seattle            DE-MS79-94BP94522       160              4.6
Snohomish          DE-MS79-94BP94525        42              1.2
Tacoma             DE-MS79-94BP94524        41              1.1




PNGC:       Pacific Northwest Generating Cooperative
Puget:      Puget Sound Power & Light Company
Seattle:    City of Seattle, City Light Department
Snohomish:  Public Utility District No. 1 of Snohomish County
Tacoma:     Tacoma Public Utilities

                                                       Exhibit H, Page 119 of
6
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date


              Provisions Required by Statute or Executive Order


1.   Contract Work Hours and Safety Standards Act (40 U.S.C. & 327, et seq.).
     -----------------------------------------------------------------------
     (a)  Overtime Requirements.
          ---------------------
     Puget, contracting for any part of the contract work which may require
     or involve the employment of laborers or mechanics, shall not require or
     permit any such laborers or mechanics in any workweek in which the
     individual is employed on such work to work in excess of 40 hours in
     such workweek unless such laborer or mechanic receives compensation at a
     rate not less than 1-1/2 times the basic rate of pay for all hours
     worked in excess of 40 hours in such workweek.
     
     (b)  Violation:  liability for unpaid wages; liquidated damages.
          ----------------------------------------------------------
     In the event of any violation of the provisions set forth in section 1
     of this Exhibit H, Puget and any subcontractor responsible therefore
     shall be liable for the unpaid wages.  In addition, Puget and such
     subcontractor shall be liable to the United States for liquidated
     damages.  Such liquidated damages shall be computed with respect to each
     individual laborer or mechanic employed in violation of the provisions
     set forth in section 1 of this Agreement in the sum of $10.00 for each
     calendar day on which such individual was required or permitted to work
     in excess of the standard workweek of 40 hours without payment of the
     overtime wages required by provision set forth in section 1 of this
     Exhibit.
     
     (c)  Withholding for unpaid wages and liquidated damages.
          ---------------------------------------------------
     The person designated in writing by Bonneville's Administrator with the
     Authority to enter into, administer, modify, suspend or terminate this
     Exhibit, make related determinations and findings and bind Bonneville
     only to the extent of delegated authority shall upon his or her own
     action or upon written request of an authorized representative of the
     Department of Labor withhold or cause to be withheld, from any moneys
     payable on account of work performed by Puget or its subcontractor, if
     any, under any such contract or any other federal contract subject to
     the Contract Work Hours and Safety Standards Act which is held by the
     same prime contractor, such sums as may be determined to be necessary to
     satisfy any liabilities of Puget or such subcontractor for unpaid wages
     and liquidated damages as provided in section 2 of this Exhibit.
     
2.   Convict Labor (Exec. Order No. 11755, Dec. 29, 1979).
     ----------------------------------------------------
     In connection with the performance or work under this Agreement, Puget
     and any subcontractor, if any agrees not to employ any person undergoing
     sentence of imprisonment except as otherwise provided by law.


                                                       Exhibit H, Page 2 of 6
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date

3.   Equal Opportunity (Exec. Order No. 11246, Sep. 24, 1965).
     --------------------------------------------------------
     (a)  If , during any 12-month period (including the 12 months preceding
     the award of this contract), Puget has been or is awarded nonexempt
     federal contracts and/or subcontracts that have an aggregate value in
     excess of $25,000.00, Puget shall comply with sections 3(b)(1) through
     3(b)(11) below.  Upon request, Puget shall provide information necessary
     to determine the applicability of this clause.
     
     (b)  During performance of this Agreement, Puget agrees as follows:
     
          (1)  Puget shall not discriminate against any employee or applicant
          for employment because of race, color, religion, sex or national
          origin.
          
          (2)  Puget shall take affirmative action to ensure that applicants
          are employed, and that employees are treated during employment,
          without regard to their race, color, religion, sex or national
          origin.  Such action shall include, but not be limited to:
          (1) employment; (2) upgrading; (3) demotion; (4) transfer;
          (5) recruitment or recruitment advertising;  (6) layoff or
          termination; (7) rates of pay or other forms of compensation; and
          (8) selection for training, including apprenticeship.
          
          (3)  Puget shall post in conspicuous places, available to employees
          and applicants for employment, the notices that explain this
          clause, such notices to be provided by the person designated in
          writing by Bonneville's Administrator with the authority to enter
          into, administer, modify, suspend or terminate this Agreement, make
          related determinations and findings and bind Bonneville only to the
          extent of delegated authority (Contracting Officer).
          
          (4)  Puget shall, in all solicitations or advertisements for
          employees placed by or on behalf of Puget, state that all qualified
          applicants will receive consideration for employment without regard
          to race, color, religion, sex or national origin.
          
          (5)  Puget shall send, to each labor union or representative or of
          workers with which it has a collective bargaining agreement or
          other contract or understanding, the notice provided by the
          Contracting Officer advising the labor union or workers'
          representative of Puget's commitments under this clause, and post
          copies of the notice in conspicuous places available to employees
          and applicants for employment.
          
          (6)  Puget shall comply with Executive Order No. 11246,
          Sep. 24, 1965 (30 Fed. Reg. 12319), as amended, and the rules,
          regulations and orders of the Secretary of Labor.
          
          (7)  Puget shall furnish to Bonneville all information required by
          Executive Order No. 11246, as amended, and by the rules,
          regulations and orders of the Secretary of Labor.  Standard Form
                                                       Exhibit H, Page 3 of 6
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date
          
          
          100 (EEO-1), or any successor form, is the prescribed form to be
          filed within 30 days following the award of this contract, unless
          filed within 12 months preceding the date of the award of this
          contract.
          
          (8)  Puget shall permit access to its books, records and accounts
          by Bonneville or the Office of Federal Contract Compliance Programs
          (OFCCP) for purpose of investigation to ascertain Puget's
          compliance with such rules, regulations and orders.
          
          (9)  If the OFCCP determines that Puget is not in compliance with
          this clause or any rule, regulation or order of the Secretary of
          Labor, this Agreement may be canceled, terminated, or suspended in
          whole or in part and Puget may be declared ineligible for further
          Government contracts, under the procedures authorized in Executive
          Order No. 11246, as amended.  In addition, sanctions may be imposed
          and remedies invoked against Puget as provided in Executive Order
          No. 11246, as amended, the rules, regulations and orders of the
          Secretary of Labor, or as otherwise provided by law.
          
          (10)  Puget shall include the terms and conditions of sections
          3(b)(1) through 3(b)(11) of this Exhibit in every subcontract or
          purchase order that is not exempted by the rules, regulations, or
          orders of the Secretary of Labor issued under Executive Order No.
          11246, as amended, so that these terms and conditions will be
          binding upon each subcontractor or vendor.
          
          (11)  Puget shall take such action with respect to any subcontract
          or purchase order as may direct as means of enforcing these terms
          and conditions, including sanctions for noncompliance:  Provided,
          that if Puget becomes involved in, or is threatened with,
          litigation with a subcontractor or vendor as a result of any
          direction, Puget may request the Government to enter into the
          litigation to protect the interest of the United States.
          
     (c)  Notwithstanding any other clause in this Agreement, disputes
     relative to this clause will be governed by the procedures in 41 CFR
     66-1.1.
     
4.   Certification of Non-segregated Facilities (48 CFR Section 22.810).
     ------------------------------------------------------------------
     (a)  Puget certifies that it does not and will not maintain or provide
     for employees any segregated facilities at any of its establishments and
     that it does not and will not permit its employees to perform their
     services at any location under its control where segregated facilities
     are maintained.  Puget agrees that a breach of this certification is a
     violation of section 3 (the Equal Opportunities Clause) of this Exhibit.
     
     (b)  Puget agrees that it will (1) obtain identical certifications from
     proposed subcontractors prior to the award of subcontracts exceeding
     $10,000.00 which are not exempt from the provisions of the Equal
     
                                                       Exhibit H, Page 4 of 6
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date

         Opportunity Clause; (2) retain such certifications in its files (3)
         forward the following notice to such proposed subcontractors,
         except where the proposed subcontractors have submitted identical
         certifications of specific time periods:
          
          "Notice to Prospective Subcontractors of Requirement for
          Certifications of Non-segregated Facilities.
          
          "A Certification of Non-segregated Facilities must be submitted
          prior to the award of a subcontract under which the subcontractor
          will be subject to the Equal Opportunity clause.  This
          certification may be submitted either for each subcontract or for
          all subcontracts during a period (i.e., quarterly, semiannually or
          annually)."
          
5.   Officials Not to Benefit (41 U.S.C. Section 22).
     -----------------------------------------------
     No member of or delegate to Congress, or resident commissioner, shall be
     admitted to any share or part of this Agreement or to any benefit
     arising from it.  However, this clause does not apply to this Agreement
     to the extent that this Agreement is made with a corporation for the
     corporation's general benefit.
     
6.   Bonneville's Obligations Not General Obligations of the United States
     ---------------------------------------------------------------------
     (16 U.S.C. Section 839(j)).
     -------------------------
     None of the offerings of obligations, or promotional materials for such
     obligations, which may be offered by Puget to fund its activities
     pursuant to this Agreement, shall be construed to be, general
     obligations of the United States, nor are such obligations intended to
     be or are they secured by the full faith and credit of the United
     States.
     
7.   Small Business Act (15 U.S.C. Sections 631 and 637).
     ---------------------------------------------------
     (a)  It is the policy of the Government that small business concerns
     owned and controlled by socially and economically disadvantaged
     individuals shall have the maximum practicable opportunity to
     participate in the performance of contracts let by any federal agency.
     
     (b)  Puget hereby agrees to carry out the policy set forth in 7(a) in
     awarding subcontracts to the fullest extent consistent with the
     efficient performance of this Agreement.  Puget further agrees to
     cooperate on any studies or surveys as may be conducted by the United
     States Small Business Administration or Bonneville as may be necessary
     to determine the extent of Puget's compliance with this clause.
     
     (c)  As used in this agreement the term "small business concern" shall
     mean a small business as defined in section 3 of Small Business Act
                                                       Exhibit H, Page 5 of 5
                                                       Exhibit H, Page 5 0f 6
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date

     
     (15 U.S.C. Section 632) and relevant regulations promulgated pursuant
     thereto.  The term "small business concern owned and controlled by
     socially and economically disadvantaged individuals" shall mean a small
     business concern:
     
          (1)  which is at least 51 percent owned by one or more socially
          disadvantaged individuals; or, in the case of any publicly owned
          business, at least 51 percent of the stock of which is owned by one
          or more socially or economically disadvantaged individuals; and
          (2)  whose management and daily business operations are controlled
          by one or more such individuals.
          
          Puget shall presume that socially and economically disadvantaged
          individuals include Black Americans, Hispanic Americans, Native
          Americans, Asian Pacific Americans and other minorities, or any
          other individual found to be disadvantaged by the United States
          Small Business Administration pursuant to section 8(a) of the Small
          Business Act.
     
     (d)  Puget acting in good faith may rely on written representations by
     its subcontractor regarding its status as either a small business
     concern or a small business concern owned and controlled by socially and
     economically disadvantaged individuals.
     
8.   Other Statutes, Executive Orders and Regulations.
     ------------------------------------------------
     (a)  Puget agrees to comply with the following statutes, executive
     orders and regulations to the extent applicable:
     
          (1)  False Claims Act, 31 U.S.C. Section 3729, et seq.  Whoever
          makes or presents to any person or officer in the civil military or
          naval service of the United States, or to any department or agency
          thereof, any claim upon or against the United States, or any
          department or agency thereof, knowing such claim to be false,
          fictitious or fraudulent, shall be fined not more than $10,000.00
          or imprisoned not more than 5 years, or both;
          
          (2)  Rehabilitation Act of 1973, 29 U.S.C. Section 793, as amended,
          Executive Order No. 11758, Jan. 15, 1974, and the regulations of
          the Secretary of Labor, 41 CFR Part 60-250, et seq., which concern
          affirmative action for handicapped workers;
          
          (3)  Vietnam Era Veterans Readjustment Assistance Act of 1972,
          38 U.S.C. Sections 101, 102, 240, 241, 1502, 1504, 1507, as
          amended, and the clauses contained in 41 CFR Part 60-250, et seq.,
          which concern affirmative action for disabled veterans and veterans
          of the Vietnam Era;
          
          (4)  Executive Order No. 11625, Oct. 13, 1971, and implementing
          regulations which concern utilization of small disadvantaged
          business concerns;
          
          
                                                       Exhibit H, Page 6 of 6
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date

          
          
          
          (5)  Anti-Kickback Act, 41 U.S.C. Section 51, et seq.; and
          
          (6)  Privacy Act of 1974, 5 U.S.C. Section 552a
          
     (b)  Puget agrees to comply with requirements deemed necessary by
     Bonneville in order to implement Bonneville's obligations under the
     National Historic Preservation Act of 1966, U.S.C. Section 470, et seq.


                                                      Exhibit I, Page 1 of 15
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                 Effective on the effective date of Exhibit B


                      BONNEVILLE'S PNW AC INTERTIE COSTS

All costs in sections I through VIII of this Exhibit I shall be subject to
the following provisions:

PURPOSE
- -------
Bonneville shall determine and calculate Operations Costs, Maintenance Costs,
Replacement Costs and Reinforcement Costs, General Plant Costs, Other Costs,
Contracts and Rates Costs, Power Scheduling Costs, and End of Term Costs with
respect to Bonneville's PNW AC Intertie in accordance with this Exhibit I.
None of Operations Costs, Maintenance Costs, Replacement Costs and
Reinforcement Costs, General Plant Costs, Other Costs, Contracts and Rates
Costs, and End of Term Costs (each of the foregoing for purposes of this
sentence, a Cost) shall include any other Cost.

SOURCE OF INFORMATION AND COSTS
- -------------------------------
Bonneville shall forecast in accordance with this Exhibit I the costs
reflected in any Operating Plan pursuant to Schedules A through H of this
Exhibit using the most detailed information available to Bonneville from its
budget process at the time the forecast is made.  Bonneville shall determine
the actual costs reflected in any Operating Plan pursuant to Schedules A
through H, using Bonneville's then existing accounting system in accordance
with this Exhibit  I.  All costs reflected in Schedules A through H shall be
net of credit.

Bonneville shall determine its overall overhead and overall indirect costs.
A portion of Bonneville's overall overhead and indirect costs shall be
allocated to such total system operations costs (pursuant to section I
below), total system maintenance costs (pursuant to section II below), total
capital costs (pursuant to sections III and IV below), Other Costs (pursuant
to section V below), Contracts and Rates Costs (pursuant to section VI
below), Power Scheduling Costs (pursuant to section VII below), and End of
Term Costs (pursuant to section VIII below) using Bonneville's normal
allocation or distribution methodologies for such costs, as such
methodologies may be changed by Bonneville from time to time.  Such
allocations or distribution methodologies shall not be required to meet any
stricter standard of benefit to Bonneville's PNW AC Intertie than with
respect to other transmission facilities.

Bonneville shall record its costs into its accounting systems in accordance
with generally accepted accounting principles.  For purposes of this
Agreement, "generally accepted accounting principles" means the common set of
accounting concepts, standards, and procedures that are adopted by entities
(such as the utility industry) for purposes of financial statement
disclosure.

Whenever Bonneville alters its accounting system or methods to permit costs
referred to in this Exhibit I, which were previously allocated to functions

                                                      Exhibit I, Page 2 of 15
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                 Effective on the effective date of Exhibit B


and activities, to be directly assigned to function and activities, then in
that event Puget and Bonneville shall, in concert with the Capacity Owners
other than Puget, in good faith negotiate revisions to this Exhibit I to
include such directly assigned costs.

COSTS
- -----
   I.  Operations Costs
       ----------------
      A.   Operations Costs - Allocation Factor
      
      The allocation factor (Schedule A, line 3) used to determine the
      Allocated Direct Cost of Operations Cost, Indirect Cost of Operations
      Cost, and Overhead Cost of Operations Cost is the ratio of major
      facility units (MFUs) of Bonneville's PNW AC Intertie operated by
      Bonneville to MFUs of the Federal Columbia River Transmission System.
      
      An MFU (Schedule A, lines 1 and 2) is any of the following major
      pieces of power system equipment which, at any given time, is
      installed on and is a part of the Federal Columbia River Transmission
      System:  substation switchgear (such as power circuit breakers;
      potential devices; disconnects, load interrupters, hot-stick operated
      bus links; switching devices, circuit switchers, ground switches; and
      switchyard equipment terminals); protective equipment (such as
      grounding devices; reactors; arrestors and resistors; voltage
      regulators; engine generators and motor generators; and high voltage
      fuses); transformation equipment (such as power transformers; diesel
      generators; grounding transformers; regulators and shunt reactors;
      synchronous condensers; and shunt or series capacitors); station
      equipment (such as switchyard lighting, batteries and chargers, air
      compressors, station service equipment, and lightening arrestors);
      instruments, control, and supervisory equipment (such as switchboards,
      instruments, and control panels; relay panels, transfer trip, and
      single-pole relaying; and oscillographs; fault detectors and locators;
      sequential events recorders, supervisory control, and data acquisition
      equipment; and indicating meters, instruments, and loggers); and
      equipment specific to direct current and static var compensator
      stations (such as mercury arc valves; thyristor systems; air handling
      packages; water control packages; harmonic filtering systems; motor
      control centers, such as fans, pumps, and dampening resistors; and
      valve damping resistors); or devices that perform similar types of
      functions.
      
      Once each fiscal year, Bonneville shall count the number of MFUs on
      Bonneville's PNW AC Intertie (exclusive of facilities operated by
      others) (Schedule A, line 1) and the number of MFUs on the Federal
      Columbia River Transmission System (Schedule A, line 2).  In
      calculating the forecast Allocated Direct Cost, Indirect Cost, and
      Overhead Cost components of Operations Costs, Bonneville shall use the
      most recent MFU count available at the time of such calculation in

                                                      Exhibit I, Page 3 of 15
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                 Effective on the effective date of Exhibit B


      developing its initial Operating Plan for a given fiscal year.  For
      each Operating Plan which is for the same fiscal year, Bonneville
      shall use the same MFU count in calculating the forecast and actual
      Allocated Direct Cost, Indirect Cost, and Overhead Cost components of
      Operations Costs.

      B.   Operations Costs - Operations Functionalization Factor
      
      For each Operating Plan, Bonneville's total system operations direct
      cost, indirect cost and overhead cost (Schedule A, lines 7, 9, and 11)
      shall be adjusted by an operations functionalization factor
      (Schedule A, line 6) so that Capacity Owners pay only transmission-
      related system operations costs.  The operations functionalization
      factor shall be based on a ratio of costs from Bonneville's general
      rate case most recently approved by FERC on an interim basis.  Using
      the costs developed for the last year of the rate period for which
      Bonneville has developed rates, the operations functionalization
      factor shall be the ratio of (a) Bonneville's total system operations
      cost functionalized to transmission (Schedule A, line 4) over
      (b) Bonneville's total system operations cost (Schedule A, line 5).
      For each Operating Plan, Bonneville shall use the same
      functionalization factor in calculating the forecast and actual
      Allocated Direct Cost, Indirect Cost, and Overhead Cost components of
      Operations Costs.
      
      C.   Operations Costs - Allocated Direct Costs
      
      For each Operating Plan, Bonneville shall allocate its total system
      operations direct costs as set forth in Schedule A, lines 7 and 8, to
      determine Allocated Direct Costs of Operations Cost (Schedule A, line
      8).
      
      Schedule A, line 7, shall reflect Bonneville's total system operations
      direct costs for a fiscal year.  Bonneville's total system operations
      direct costs for a fiscal year shall include all system operations
      expenses for such fiscal year for any of the following:  salaries,
      wages, employee benefits, overtime pay, travel, service contracts,
      consulting contracts, materials, spare parts, tools, direct support
      services (including equipment use activities, general shops
      activities, and heavy mobile equipment maintenance), and other
      expenses, each of which being incurred by Bonneville in connection
      with the performance of any of the following activities:  substation
      operations (which provides for, among other things, making equipment
      adjustments to maintain loads and voltages within acceptable limits,
      switching to de-energize lines and equipment during maintenance
      outages, isolating damaged equipment, restoring service to customers,
      visually inspecting equipment, and reading meters that record line and
      equipment loading and voltages), power system control and dispatching
      (which provides for, among other things, central dispatching, control,


                                                      Exhibit I, Page 4 of 15
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                 Effective on the effective date of Exhibit B


      and monitoring of the electric operation of the Federal transmission
      system; load, frequency, and voltage control of Federal generating
      plants; the operating of the system control and data computers at the
      Dittmer and Eastern Control Centers; and modification and maintenance
      of the operation-related computers), and operations standards and
      engineering (which provides for, among other things, analyzing system
      loads, voltage levels, outage information, stability levels, and other
      data; making policy recommendations for system operations; planning
      operations' practices, restoration plans and disturbance ports;
      development of control center requirements for centralized automation
      of substations and generation; and Bonneville's participation with
      other utilities in developing utility operating standards and guides);
      and other system operations activities undertaken by Bonneville that
      are consistent with system operations activities similar to the above-
      listed activities undertaken by utilities in the Western Systems
      Coordinating Council.
      
      Schedule A, line 8, shall reflect Allocated Direct Cost of Operations
      Cost.
      
      D.   Operations Costs - Indirect Costs
      
      For each Operating Plan, Bonneville shall allocate its total system
      operations indirect costs as set forth in Schedule A, lines 9 and 10,
      to determine Indirect Costs of Operations Costs.
      
      Schedule A, line 9, shall reflect Bonneville's total system operations
      indirect costs for a fiscal year.  Bonneville's total system
      operations indirect costs for a fiscal year shall include all system
      operations indirect expenses for such fiscal year for any of the
      following:  salaries, wages, employee benefits, overtime pay, travel,
      service contracts, consulting contracts, materials, tools, direct
      support services (including equipment use activities, general shops
      activities, and heavy mobile equipment maintenance), and other
      expenses, each of which being incurred by Bonneville in connection
      with the performance of any of the following activities:  general
      supervision and management, office support, planning, budgeting,
      training, direction of facilities' operation, and other system
      operations activities undertaken by Bonneville that are consistent
      with system operations activities similar to the above-listed
      activities undertaken by utilities in the Western Systems Coordinating
      Council.
      
      Schedule A, line 10, shall reflect Indirect Cost of Operations Cost.
      
      
      
      
      
      
                                                      Exhibit I, Page 5 of 15
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                 Effective on the effective date of Exhibit B


      E.   Operations Costs - Overhead Costs
      
      For each Operating Plan, Bonneville shall allocate its total system
      operations overhead costs as set forth in Schedule A, lines 11 and 12,
      to determine Overhead Costs of Operations Costs.
      Schedule A, line 11, shall reflect Bonneville's total system
      operations overhead costs for a fiscal year.  Bonneville's total
      system operations overhead costs for a fiscal year shall include all
      system operations overhead expenses for such fiscal year for any of
      the following:  salaries, wages, employee benefits, overtime pay,
      travel, service contracts, consulting contracts, materials, spare
      parts, and other expenses, each of which being incurred by Bonneville
      in connection with any of the following activities and services of
      Bonneville:  (a) support services (including services with respect to
      mainframe computers, microcomputers, laboratories, building
      management, materials and procurement, Electric Power Research
      Institute, fixed-wing aircraft, helicopter, tools, and work
      equipment); (b) general and administrative activities (including
      general and administrative activities with respect to the office of
      the Administrator, the Washington DC office, and the offices of:
      contracts and property management; fish and wildlife; equal employment
      opportunity; information resources; environment; internal audit;
      external affairs; general counsel; quality improvement; planning
      council liaison; financial management; power sales; energy resources;
      management services; area offices; operations, maintenance, and
      construction; and engineering); and (c) other system operations
      overhead activities undertaken by Bonneville that are consistent with
      system operations activities similar to the above-listed activities
      undertaken by utilities in the Western System Coordinating Council.
      
      Schedule A, line 12, shall reflect Overhead Cost of Operations Cost.
      
      Schedule A, line 13, shall reflect Operations Cost.
      
  II.  Maintenance Costs
      -----------------
      A.   Maintenance Costs - Power System Control Maintenance
           Functionalization Factor
      
      For each Operating Plan, the Power System Control (PSC) maintenance
      cost (Schedule B, line 4) shall be adjusted by a PSC maintenance
      functionalization factor (Schedule B, line 3).  PSC maintenance is the
      testing, repair, and engineering support for Bonneville's
      communications and control systems.  The PSC maintenance
      functionalization factor shall be based on a ratio of costs from
      Bonneville's general rate case most recently approved by FERC on an
      interim basis.  Using costs for the last year of the rate period for
      which Bonneville has developed rates, the PSC functionalization factor
      
      

                                                      Exhibit I, Page 6 of 15
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                 Effective on the effective date of Exhibit B


      shall be the ratio of (a) Bonneville's total PSC maintenance cost
      functionalized to transmission from such general rate case
      (Schedule B, line 1) over (b) Bonneville's total PSC maintenance cost
      from such general rate case (Schedule B, line 2).
      
      B.   Maintenance Costs - Direct Costs
      
      The Direct Costs of Maintenance Costs for a fiscal year (Schedule B,
      line 7) shall be Bonneville's direct costs of maintaining Bonneville's
      PNW AC Intertie and shall include all maintenance expenses for such
      fiscal year for any of the following:  salaries, wages, employee
      benefits, overtime pay, travel, service contracts, consulting
      contracts, materials, spare parts, transportation of spare parts,
      tools, direct support services (including equipment use activities,
      general shops activities, and heavy mobile equipment maintenance), and
      other expenses, each of which being incurred by Bonneville in
      connection with the performance of any of the following activities for
      maintenance of Bonneville's PNW AC Intertie:  transmission line
      maintenance; substation maintenance; power system control maintenance;
      nonelectric plant maintenance; pollution control and abatement; and
      other system maintenance activities related to preventive and
      corrective maintenance of Bonneville's PNW AC Intertie undertaken by
      Bonneville that are consistent with activities similar to the above-
      listed activities undertaken by utilities in the Western Systems
      Coordinating Council.
      
      With the exception of PSC maintenance costs, Bonneville shall
      specifically identify the direct costs of maintaining Bonneville's PNW
      AC Intertie (Schedule B, line 7).  To determine PSC direct maintenance
      cost for Bonneville's PNW AC Intertie (Schedule B, line 6), the total
      PSC direct maintenance cost (Schedule B, line 4) shall be multiplied
      by (a) the PSC maintenance functionalization factor (Schedule B, line
      3) and (b) the MFU allocation factor (Schedule B, line 5) set forth in
      Schedule A, line 3.  The Direct Costs of Maintenance Costs (Schedule
      B, line 8) shall be the sum of (a) PSC direct maintenance cost for
      Bonneville's PNW AC Intertie (Schedule B, line 6) and (b) the direct
      cost of maintaining Bonneville's PNW AC Intertie excluding PSC
      maintenance cost (Schedule B, line 7).
      
      C   Maintenance Costs - Allocation Factor
      The allocation factor (Schedule B, line 10) used to determine Indirect
      Cost of Maintenance Cost and Overhead Cost of Maintenance Cost shall
      be the ratio of the Direct Cost of Maintenance Cost (Schedule B, line
      8) to Bonneville's total system maintenance direct cost (Schedule B,
      line 9), as described below.
      
      Schedule B, line 9, shall reflect Bonneville's total system
      maintenance direct costs for a fiscal year.  Bonneville's total system
      maintenance direct costs for a fiscal year shall include all
      
      
                                                      Exhibit I, Page 7 of 15
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                 Effective on the effective date of Exhibit B


      maintenance expenses for such fiscal year for any of the following:
      salaries, wages, employee benefits, overtime pay, travel, service
      contracts, consulting contracts, materials, spare parts,
      transportation of spare parts, tools, direct support services
      (including equipment use activities, general shops activities, and
      heavy mobile equipment maintenance), and other expenses, each of which
      being incurred by Bonneville in connection with the performance of any
      of the following activities:  transmission line maintenance;
      substation maintenance; power system control maintenance; nonelectric
      plant maintenance; establishing, monitoring, and updating system
      maintenance standards, policies, and procedures; pollution control and
      abatement; and other system maintenance activities related to
      preventive and corrective maintenance of the Federal Columbia River
      Transmission System undertaken by Bonneville that are consistent with
      system maintenance activities similar to the above-listed activities
      undertaken by utilities in the Western Systems Coordinating Council.
      
      Schedule B, line 10, shall reflect the percentage which shall be used
      to allocate Bonneville's total system maintenance indirect cost and
      total system maintenance overhead cost to Bonneville's PNW AC
      Intertie.
      
      D.   Maintenance Costs - Indirect Costs
      
      For each Operating Plan, Bonneville shall allocate its total system
      maintenance indirect costs as set forth in Schedule B, lines 11 and
      12, to determine Indirect Costs of Maintenance Costs.
      
      Schedule B, line 11, shall reflect Bonneville's total system
      maintenance indirect costs for a fiscal year.  Bonneville's total
      system maintenance indirect costs for a fiscal year shall include all
      system maintenance indirect expenses for such fiscal year for any of
      the following:  salaries, wages, employee benefits, overtime pay,
      travel, service contracts, consulting contracts, materials, spare
      parts, administration of spare parts, transportation of spare parts,
      tools, tools procurement and administration, direct support services
      (including equipment use activities, general shops activities, and
      heavy mobile equipment maintenance), and other expenses, each of which
      being incurred by Bonneville in connection with the performance any of
      the following activities:  supervision and management, office support,
      technical analyses, engineering studies, program analyses, planning,
      budgeting, training, and other system maintenance activities
      undertaken by Bonneville that are consistent with system maintenance
      activities similar to the above-listed activities undertaken by
      utilities in the Western Systems Coordinating Council.
      
      Schedule B, line 12, shall reflect Indirect Cost of Maintenance Cost.
      
      
      
      
      
                                                      Exhibit I, Page 8 of 15
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                 Effective on the effective date of Exhibit B


      E.   Maintenance Costs - Overhead Costs
      
      For each Operating Plan, Bonneville shall allocate its total system
      maintenance overhead costs as set forth in Schedule B, lines 13 and
      14, to determine Overhead Costs of Maintenance Costs.
      
      Schedule B, line 13, shall reflect Bonneville's total system
      maintenance overhead costs for a fiscal year.  Bonneville's total
      system maintenance overhead costs for a fiscal year shall include all
      system maintenance overhead expenses for such fiscal year for any of
      the following:  salaries, wages, employee benefits, overtime pay,
      travel, service contracts, consulting contracts, materials, spare
      parts, and other expenses, each of which being incurred by Bonneville
      in connection with any of the following activities and services of
      Bonneville:  (a) support services (including services with respect to
      mainframe computers, microcomputers, laboratories, building
      management, materials and procurement, Electric Power Research
      Institute, fixed-wing aircraft, helicopter, tools, and work
      equipment); (b) general and administrative activities (including
      general and administrative activities with respect to the office of
      the Administrator, the Washington DC office, and the offices of:
      contracts and property management; fish and wildlife; equal employment
      opportunity; information resources; environment; internal audit;
      external affairs; general counsel; quality improvement; planning
      council liaison; financial management; power sales; energy resources;
      management services; area offices; operations, maintenance, and
      construction; and engineering); and (c) other system maintenance
      overhead activities undertaken by Bonneville that are consistent with
      system maintenance activities similar to the above-listed activities
      undertaken by utilities in the Western System Coordinating Council.
      
      Schedule B, line 14, shall reflect Overhead Cost of Maintenance Cost.
      
      Schedule B, line 15, shall reflect Maintenance Cost.
     
 III.  Replacement Costs and Reinforcement Costs
       -----------------------------------------
      A.  Replacement Costs and Reinforcement Costs - Direct Costs
      
      The Direct Costs for Replacements and Reinforcements for a fiscal year
      (Schedule C, line 1) shall be Bonneville's direct capital costs for
      Replacements and Reinforcements for such fiscal year and shall include
      all costs for any of the following:  salaries, wages, employee
      benefits, overtime pay, travel, service contracts, consulting
      contracts, land, materials and equipment, spare parts, administration
      of spare parts, transportation of spare parts, tools, tools
      procurement and administration, direct support services (including
      equipment use activities, general shops activities, and heavy mobile
      equipment maintenance), and other costs, each of which being incurred
      by Bonneville in connection with the performance of the following
      
                                                      Exhibit I, Page 9 of 15
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                 Effective on the effective date of Exhibit B


      activities:  planning, environmental analyses and mitigation, survey,
      design, land, materials and equipment, turnkey contracts, contract
      construction, force account construction, and other reinforcement and
      replacement activities undertaken by Bonneville that are consistent
      with reinforcement and replacement activities similar to the above-
      listed activities undertaken by utilities in the Western Systems
      Coordinating Council.  The Direct Costs for any Replacement or
      Reinforcement for a fiscal year shall also include the costs of
      removal and any salvage credits with respect to any PNW AC Intertie
      facility removed on account of such Replacement or Reinforcement.
      
      B.   Replacement Costs and Reinforcement Costs - Indirect Costs and
           Overhead Costs
      
      For each Replacement and Reinforcement project, the Indirect Costs and
      Overhead Costs for Replacements and Reinforcements (Schedule C, line
      2) shall be allocated or distributed to such Replacements and
      Reinforcements using the indirect and overhead allocation and
      distribution methodologies employed by Bonneville to allocate and
      distribute indirect and overhead costs to all of Bonneville's other
      capital projects during the time the Replacements and Reinforcements
      are under construction.  Schedule C, line 2, shall reflect the
      Indirect Costs and Overhead Costs of Replacements and Reinforcements.
      
      Indirect Costs of Replacements and Reinforcements shall include all
      costs for any of the following:  salaries, wages, employee benefits,
      overtime pay, travel expenses, service contracts, consulting
      contracts, administration of materials, tools, tools procurement and
      administration, direct support services (including equipment use
      activities, general shops activities, and heavy mobile equipment
      maintenance), and other costs, each of which being incurred by
      Bonneville in connection with the performance of any of the following
      activities:  supervision, technical analyses, engineering studies,
      program analyses, planning, budgeting, training, and other
      reinforcement and replacement activities undertaken by Bonneville that
      are consistent with reinforcement and replacement activities similar
      to the above-listed activities undertaken by utilities in the Western
      Systems Coordinating Council.
       
      Overhead Costs for Replacements and Reinforcements shall include all
      costs for any of the following:  salaries, wages, employee benefits,
      overtime pay, travel, service contracts, consulting contracts,
      materials, spare parts, and other costs, each of which being which
      being incurred by Bonneville in connection with any of the following
      activities and services of Bonneville:  (a) support services
      (including services with respect to mainframe computers,
      microcomputers, laboratories, building management, materials and
      procurement, Electric Power Research Institute, fixed-wing aircraft,
      helicopter, tools, and work equipment); (b) general and administrative
      activities (including general and administrative activities with
      
                                                     Exhibit I, Page 10 of 15
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                 Effective on the effective date of Exhibit B


      respect to the office of the Administrator, the Washington DC office,
      and the offices of:  contracts and property management; fish and
      wildlife; equal employment opportunity; information resources;
      environment; internal audit; external affairs; general counsel;
      quality improvement; planning council liaison; financial management;
      power sales; energy resources; management services; area offices;
      operations, maintenance, and construction; and engineering); and (c)
      other replacement and reinforcement activities undertaken by
      Bonneville that are consistent with replacement and reinforcement
      activities similar to the above-listed activities undertaken by
      utilities in the Western System Coordinating Council.
      
      C.  Replacement Costs and Reinforcement Costs - Allowance for Funds
      Used During Construction (AFUDC)
      
      Schedule C, line 3, shall reflect AFUDC for Replacements and
      Reinforcements.  At the beginning of each fiscal year, Bonneville
      shall calculate the AFUDC rate for such fiscal year.  Bonneville shall
      apply such AFUDC rate monthly to the costs in accounts for
      construction work in progress for Replacements and Reinforcements.
      
      D.   Replacement Costs and Reinforcement Costs - Interest
      
      Schedule C, line 4, shall reflect the interest cost payable by Puget
      pursuant to this Agreement with respect to any Replacement or
      Reinforcement.  Such interest cost for any Replacement or any
      Reinforcement shall be simple interest calculated at a rate equal to
      the weighted average interest rate on Bonneville's then outstanding
      bonds or other debt instruments and such interest shall accrue from
      the date Bonneville stops accruing AFUDC (approximately the date the
      work order for such Replacement or such Reinforcement is closed) with
      respect to such Replacement or such Reinforcement to the due date of
      the monthly power bill containing the charge for such Replacement or
      such Reinforcement.

  IV.  General Plant Costs
       -------------------

      For each Operating Plan, Bonneville shall adjust, amortize, and
      allocate Bonneville's total general plant investment (as described
      below) and Bonneville's Dittmer control equipment investment as set
      forth in Schedule D, lines 1 through 11, to determine General Plant
      Cost.
      
Schedule D, line 1, shall reflect for a fiscal year Bonneville's total
cumulative general plant investment.  Bonneville's total general plant
investment shall include Bonneville's investments in any of the following:
land-general plant, structures/improvements-general plant, office furniture
and equipment, transportation equipment, stores equipment, tools/shop/garage
equipment, laboratory equipment, power operated equipment, communication
equipment, miscellaneous equipment
                                                     Exhibit I, Page 11 of 15
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                 Effective on the effective date of Exhibit B

      (including equipment or apparatus used in Bonneville's utility
      operations which are not includable in any other general plant
      investment category), and other similar investment made by Bonneville
      that is consistent with general plant investment made by utilities in
      the Western Systems Coordinating Council.
      
      Schedule D, line 2, shall reflect for a fiscal year Bonneville's
      cumulative investment in Dittmer control equipment.
      
      Schedule D, line 3, shall reflect Bonneville's total general plant
      investment and Bonneville's Dittmer control equipment investment
      functionalized to generation using the methodology for functionalizing
      general plant as set forth in Bonneville's general rate case most
      recently approved by FERC on an interim basis.
      
      Schedule D, line 4, shall reflect any general plant investment
      recovered from all Capacity Owners under the CO-94 rate as such
      general plant investment is unitized by Bonneville; provided, however,
      for the first two Operating Plans Bonneville shall estimate the amount
      of the general plant investment included in the Initial Capacity
      Ownership Price, which estimate shall be reflected in Schedule D, line
      4, and Bonneville shall modify such Operating Plans by December 1995,
      or as soon as practicable thereafter, to reflect in Schedule D, line
      4, the actual general plant investment included in the Adjusted
      Capacity Ownership Price.
      
      Schedule D, line 5, shall reflect any general plant investment
      recovered from Capacity Owners pursuant to section 5 for Upgrades.
      The agreements referred to in subsection 5(d) and subparagraph
      5(e)(3)(B) shall specify the portion of costs of an Upgrade that will
      be considered general plant investment.
      
      Schedule D, line 6, shall reflect Bonneville's adjusted general plant
      investment functionalized to transmission and shall be calculated by
      adding line 1 and line 2, and from the sum of line 1 and line 2
      subtracting line 3, line 4, and line 5.
      
      Schedule D, line 7, shall reflect Bonneville's annual cost of
      Bonneville's adjusted general plant investment functionalized to
      transmission (Schedule D, line 6).  Such annual cost shall be the sum
      of the annual interest and amortization amounts for each category of
      adjusted general plant investment.  The annual interest and
      amortization amounts for each category shall be calculated by using
      the investment amounts for each such category, the weighted average
      interest rate for all Bonneville then outstanding bonds, and the
      average service lives for each such category from Bonneville's most
      recent depreciation study.  If Bonneville changes its practice of
      financing general plant investment with bonds, the interest rate used
      in the calculation referred to in the immediately preceding sentence
      shall reflect the weighted average interest rate for all of
      Bonneville's then outstanding debt instruments.

                                                     Exhibit I, Page 12 of 15
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                 Effective on the effective date of Exhibit B


      
      Schedule D, line 8, shall reflect for a fiscal year Bonneville's total
      cumulative transmission plant-in-service investment (not including
      general plant investment).  Bonneville's total transmission plant-in-
      service investment shall include Bonneville's investment in any of the
      following items reflected as total transmission plant-in-service (not
      including general plant investment) in the Segmentation Study (from
      Bonneville's general rate case most recently approved by FERC on an
      interim basis:  land and land rights-transmission plant,
      structures/improvements-transmission plant, station equipment, towers
      and fixtures, poles and fixtures, overhead conductor, underground
      conductor, roads and trails, and other transmission plant investment
      made by Bonneville that is consistent with transmission plant
      investments made by utilities in the Western Systems Coordinating
      Council.
      
      Schedule D, line 9, shall be the annual cost ratio of Bonneville's PNW
      AC Intertie transmission-related general plant derived by dividing
      Schedule D, line 7, by Schedule D, line 8.
      
      Schedule D, line 10, shall reflect Bonneville's PNW AC Intertie
      investment.  Bonneville's PNW AC Intertie investment shall include
      Bonneville's investment in any of the following items reflected as
      Bonneville's PNW AC Intertie plant-in-service in the Segmentation
      Study from Bonneville's general rate case most recently approved by
      FERC on an interim basis (or the successor to the Segmentation Study,
      as determined by Bonneville):  land and land rights-transmission
      plant, structures/improvements-transmission plant, station equipment,
      towers and fixtures, poles and fixtures, overhead conductor,
      underground conductor, roads and trails, and other transmission plant
      investment made by Bonneville that is consistent with transmission
      plant investments made by utilities in the Western Systems
      Coordinating Council.
      

   V.  Other Costs

      For each Operating Plan, Bonneville shall include Other Costs
      associated with Bonneville's PNW AC Intertie for a fiscal year.  Such
      Other Costs (Schedule E, line 3) for a fiscal year shall include for
      such fiscal year any of the following:  (1) the costs of operation;
      maintenance; capital replacements, reinforcements, additions,
      betterments, renewals; or related costs which Bonneville is obligated
      to pay pursuant to the Northwest Intertie Agreements or other
      contracts referred to in subsection 8(b) of this Agreement; and (2)
      costs paid by Bonneville including monetary judgments, settlements,
      binding awards, non-contract penalties, contract penalties, liquidated
      damages, or forfeiture costs, and Bonneville's costs related to such
      monetary judgments, settlements, binding awards, non-contract
      penalties, contract penalties, liquidated damages, or forfeiture costs
      
                                                     Exhibit I, Page 13 of 15
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                 Effective on the effective date of Exhibit B


      assessed against or incurred by Bonneville as a facilities owner of,
      or the operator of, the PNW AC Intertie; provided, however, that Puget
      shall not be obligated to pay a share of any such costs that are not
      properly allocated to Bonneville's PNW AC Intertie.
      
      Bonneville shall forecast its share of operations, maintenance,
      capital, and related costs for activities that PacifiCorp performs on
      Bonneville/PacifiCorp jointly-owned PNW AC Intertie facilities based
      on forecasts received from PacifiCorp or on actual costs for the most
      recent 12 consecutive month period prior to preparation of an
      Operating Plan.
      
  VI.  Contracts and Rates Costs
       -------------------------
      
      A.   Contracts and Rates Costs - Functionalization Factor
      
      For each Operating Plan, Bonneville's total contracts and rates direct
      costs, indirect costs, and overhead costs (Schedule F, lines 5, 6, and
      7) shall be adjusted by a contracts and rates functionalization factor
      (Schedule F, line 3).  The contracts and rates functionalization
      factor shall be based on a ratio of costs from Bonneville's general
      rate case most recently approved by FERC on an interim basis.  Using
      costs developed for the last year of the rate period for which
      Bonneville has developed rates, the contracts and rates
      functionalization factor shall be the ratio of (a) Bonneville's total
      transmission-related contracts and rates cost (Schedule F, line 1)
      over (b) Bonneville's total contracts and rates cost (Schedule F, line
      2).  For each Operating Plan, Bonneville shall use the same
      functionalization factor in calculating the forecast and actual
      Contracts and Rates Cost.
      
      B.   Contracts and Rates Costs - Allocation Factor
      
      The allocation factor (Schedule F, line 4) shall be the allocation
      factor established in Schedule A, line 3.
      
      C.   Contracts and Rates Costs - Total Contracts and Rates Costs
      
      Bonneville's total contracts and rates costs for a fiscal year
      (Schedule F, line 8) shall include Bonneville's expenses (including
      direct, indirect, and overhead costs) for such fiscal year for any of
      the following:  salaries, wages, employee benefits, overtime pay,
      travel, service contracts, consulting contracts, materials, tools, and
      direct support services (including equipment use activities, general
      shops activities, and heavy mobile equipment maintenance), and other
      expenses, each of which being incurred by Bonneville in connection
      with the performance of the following activities:  rate filings with
      FERC, development of rates customers pay Bonneville for electric power
      and for wheeling their own power on Bonneville's transmission system;
      
                                                     Exhibit I, Page 14 of 15
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                 Effective on the effective date of Exhibit B


      negotiation, administration, and coordination of contracts for power
      sales, power exchanges, conservation, wheeling and resource services;
      and analyzing, processing, and issuing all customer power bills; and
      other activities undertaken by Bonneville that are consistent with
      activities similar to the above-listed activities undertaken by
      utilities in the Western Systems Coordinating Council.
      
      Schedule F, line 9, shall reflect Contracts and Rates Cost.
      
 VII.  Power Scheduling Costs
       ----------------------
      For each Operating Plan, Bonneville's total power scheduling direct
      costs, indirect costs, and overhead costs (Schedule G, lines 5, 6, and
      7) shall be adjusted by a power scheduling functionalization factor
      (Schedule G, line 3).  The power scheduling functionalization factor
      shall be based on a ratio of costs from Bonneville's general rate case
      most recently approved by FERC on an interim basis.  Using costs
      developed for the last year of the rate period for which Bonneville
      has developed rates, the power scheduling functionalization factor
      shall be the ratio of (a) Bonneville's total transmission-related
      power scheduling cost (Schedule G, line 1) over (b) Bonneville's total
      power scheduling cost (Schedule G, line 2).  For each Operating Plan,
      Bonneville shall use the same functionalization factor in calculating
      the forecast and actual Power Scheduling Cost.
      
      B.   Power Scheduling Costs - Allocation Factor
      
      The allocation factor (Schedule G, line 4) shall be the allocation
      factor established in Schedule A, line 3.
      
      C.   Power Scheduling Costs - Total Power Scheduling Costs
      
      Bonneville's total power scheduling costs for a fiscal year (Schedule
      G, line 8) shall include Bonneville's expenses (including direct,
      indirect, and overhead costs) for such fiscal year for any of the
      following:  salaries, wages, employee benefits, overtime pay, travel,
      service contracts, consulting contracts, materials, tools, and direct
      support services (including equipment use activities, general shops
      activities, and heavy mobile equipment maintenance), and other
      expenses, each of which being incurred by Bonneville in connection
      with the performance of the following activities:  scheduling and
      marketing power to Bonneville customers and interconnected utilities,
      forecasting the hourly power requirements of Bonneville customers and
      the interchange of power with the region's interconnected electric
      utilities and with utilities outside the region, scheduling power to
      be generated at each Federal plant, weather and streamflow
      forecasting, controlling the reservoirs, implementing the intertie
      access policy, coordinating power production with the multi-purpose
      operation of the Federal power system, seasonal load/resource
      planning, developing current short-term operating plans, short-term
      
                                                     Exhibit I, Page 15 of 15
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                 Effective on the effective date of Exhibit B


      marketing of Bonneville's surplus firm power, exchanges, and nonfirm
      energy, and other activities undertaken by Bonneville that are
      consistent with activities similar to the above-listed activities
      undertaken by utilities in the Western Systems Coordinating Council.
      
      Schedule G, line 9, shall reflect Power Scheduling Cost.
      
VIII.  End of Term Costs
      -----------------
      When all facilities of the PNW AC Intertie are determined, in
      accordance with Northwest Intertie Agreements, to be no longer
      operable, Bonneville shall include a forecast of all Bonneville's
      costs associated with decommissioning the PNW AC Intertie and credits
      resulting from such decommissioning in the Operating Plan for each
      fiscal year that such End of Term Costs are to be incurred.
      Bonneville's End of Term Costs for a fiscal year (Schedule H, line 4)
      shall include Bonneville's costs (including direct, indirect, and
      overhead costs) for such fiscal year for any of the following:
      salaries, wages, employee benefits, overtime pay, travel, service
      contracts, consulting contracts, materials, spare parts,
      transportation of spare parts, tools, direct support services
      (including equipment use activities, general shops activities, and
      heavy mobile equipment maintenance), and other costs, each of which
      being incurred by Bonneville in connection with the performance of any
      of the following activities:  decommissioning, razing structures,
      disposal of debris, site restoration, meeting all requirements of
      Federal, state, or local applicable law relating to the foregoing
      activities, and other decommissioning activities undertaken by
      Bonneville that are consistent with decommissioning activities similar
      to the above-listed activities undertaken by utilities in the Western
      Systems Coordinating Council.

                                                       Exhibit I, Schedule A
                                                                      Page 1
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company
                                Effective on the effective date of Exhibit B


                                        Line
                                        No.1  Forecast   Actual   Difference
SCHEDULE A FOR FY XXXX


   I.  Operations Costs

       A.  Allocation Factor

           MFUs of Bonneville PNW AC
             Intertie                     1            ________

           MFUs of the FCRTS              2            ________

           Allocation factor              3            ________
             (Line 1/Line2)

       B.  Operations
             Functionalization Factor
          
           Bonneville's total             4            ________
             transmission-related 
             system operations cost
             from rate case
           Bonneville's total systems     5            ________
             operations cost from rate
             case
           Operations functionalization   6            ________
             factor (Line 4/Line5)

       C.  Allocated Direct Cost

           Bonneville's total system      7  ________  ________   __________

           Allocated Direct Cost of       8  ________  ________   __________
             Operations Cost
             (Line 3*Line 6*Line 7)

                                                       Exhibit I, Schedule A
                                                                      Page 2
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company
                                Effective on the effective date of Exhibit B


                                       Line
                                       No.1   Forecast   Actual   Difference

D.  Indirect Cost

    Bonneville's total system            9    ________  ________  __________
      operations indirect cost

    Indirect Cost of Operations Cost    10    ________  ________  __________
      (Line 3*Line 6*Line 9)

E.  Overhead Cost

    Bonneville's total system          11     ________  ________  __________
      operations overhead cost

    Overhead Cost of Operations Cost   12    _________  ________  __________
      (Line 3*Line 6*Line 11)

F.  Operations Cost                    13    _________  ________  __________
      (Lines 8+10+12)

                                                       Exhibit I, Schedule B
                                                                      Page 1
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company
                                Effective on the effective date of Exhibit B


SCHEDULE B FOR FY XXXX


                                        Line
                                        No.1  Forecast   Actual   Difference

  II.  Maintenance Cost

       A.  Power System Control (PSC)
           Maintenance Functionali-
           zatio Factor

           Bonneville's transmission-     1            ________
           related PSC maintenance
           cost from rate case

           Bonneville's total PSC         2            ________
           maintenance cost from
           rate case

           PSC maintenance                3            ________
             functionalization factor 
            (Line1/Line2)

       B.  Direct Cost

           Total PSC direct cost         4
             cost

           MFU Allocation Factor         5            ________
           (Schedule A, line 3)

           PSC direct maintenance        6  ________  ________   __________
             cost for Bonneville's
             PNW AC Intertie
             (Line 4*Line 3*Line 5)

           Bonneville's direct cost of   7  ________  ________   __________
             maintaining Bonneville's
             PNW AC Intertie excluding
             PSC maintenance cost

           Direct Cost of Maintenance    8  ________  ________   __________
             Cost (Line 6+Line 7)

                                                       Exhibit I, Schedule B
                                                                      Page 2
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company
                                Effective on the effective date of Exhibit B



       C.  Allocation Factor

           Bonneville's total system    9   ________  ________   __________
           maintenance direct cost

           Allocation factor for       10   ________  ________   __________
             Indirect Cost and 
             Overhead Cost 
            (Line 8/Line9)

       D.  Indirect Cost

           Bonneville's total          11   ________  ________   __________
             system maintenance 
             indirect cost

           Indirect Cost of            12   ________  ________   __________
             Maintenance Cost
             (Line 11*Line 10)

       E.  Overhead Cost

           Bonneville's total system   13   ________  ________   __________
             system maintenance
             overhead cost

           Overhead Cost of            14   ________  ________   __________
             Maintenance Cost 
             (Line 13*Line 10)

       F.  Maintenance Cost            15   ________  ________   __________
           (Lines 8+12+14)

                                                       Exhibit I, Schedule C
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company
                                Effective on the effective date of Exhibit B


SCHEDULE C


                                        Line
                                        No.1  Forecast   Actual   Difference

 III.  Replacement Costs and
       Reinforcement Costs

       A.  Direct Cost

           Direct Costs of Replace-        1  ________   ________  _________
           ments and Reinforcements

       B.  Indirect Costs and Overhead 
           Costs
           
           Indirect Costs and Overhead     2  ________   ________   ________
           Costs of Replacements 
           and Reinforcements

       C.  AFUDC

           AFUDC of Replacements and       3  ________   ________   ________
           Reinforcements

       D.  Interest

           Interest Cost of Replacements   4             ________
           and Reinforcements

       E.  Total Replacement Costs and     5  ________   ________   ________
           Reinforcement Costs
           (Lines 1+2+3+4)


Notes:
  A separate Schedule C will be provided in the Operating Plan for each
    Replacement and Reinforcement.

  Forecasts of Replacement Costs and Reinforcement Costs will be provided;
    Capacity Owners shall be billed for Replacements and Reinforcements 
    using actual cost pursuant to section 9(b)(2)(B).

                                                       Exhibit I, Schedule D
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company
                                Effective on the effective date of Exhibit B


SCHEDULE D FOR FY XXXX

                                                 Line    Allocated
                                                 No.      Actual

  IV.  General Plant Cost

           Bonneville's total general plant       1     __________
           investment

           Bonneville's Dittmer control           2     __________
           equipment investment

           General plant investment of lines 1    3     __________
           and 2 functionalized to generation

           General plant investment recovered     4     __________
           from all Capacity Owners in Adjusted
           Capacity Ownership Price and Revised
           Adjusted Capacity Ownership Price

           General plant investment recovered     5     __________
           from Capacity Owners for Upgrades

           Adjusted general plant investment      6     __________
           functionalized to transmission
           (Line 1 + Line 2 - Line 3 - Line 4
            - Line 5)

           BPA total annual cost of Line 6        7     __________
           general plant investment

           BPA total transmission plant-in-       8     __________
           service investment (not including
           general plant investment) from
           Segmentation Study

           ACR for Bonneville's PNW AC            9     __________
           Intertie (Line 7/Line 8)

           Bonneville's PNW AC Intertie          10     __________
           Investment from Segmentation Study

           General Plant Cost                    11     __________
           (Line 9*Line 10)

                                                       Exhibit I, Schedule E
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company
                                Effective on the effective date of Exhibit B


SCHEDULE E FOR FY XXXX

                                         Line
                                         No.1  Forecast  Actual  Difference


V.  Other Costs

    A.  PacifiCorp and related costs       1   ________  ______  __________

    B.  Other PNW AC Intertie costs        2   ________  ______  __________

    C.  Total Other Costs                  3   ________  ______  __________

                                                       Exhibit I, Schedule F
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company
                                Effective on the effective date of Exhibit B


SCHEDULE F FOR FY XXX


                                       Line
                                       No.1  Forecast   Actual   Difference


  VI.  Contracts and Rates Costs

       A.  Contracts and Rates
           Functionalization Factor

           Transmission-related          1            ________         
           contracts and rates cost
           from rate case

           Total contracts and rates     2            ________
           cost from rate case

           Contracts and rates cost      3            ________
           functionalization factor
           (Line 1/Line 2)

       B.  Allocation Factor

           MFU allocation factor         4           ________
           (Schedule A, line 3)

       C.  Total Contracts and
           Rates Costs

           Contracts and rates direct    5  ________  ________  __________
           costs

           Contracts and rates           6  ________  ________  __________
           indirect costs     

           Contracts and rates overhead  7  ________  ________  __________
           costs

           Bonneville's total contracts  8  ________  ________  __________
           and rates costs
           (Line 5 + Line 6 + Line 7)

       D.  Contracts and Rates Cost      9  ________  _________  __________
           (Line 8 * Line * Line 4)

                                                       Exhibit I, Schedule G
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company
                                Effective on the effective date of Exhibit B


SCHEDULE G FOR FY XXXX


                                          Line
                                          No.1  Forecast   Actual Difference


 VII.  Power Scheduling Costs

       A.  Power Scheduling
           Functionalization Factor

           Transmission-related power       1            ________
           scheduling costs from rate
           case

           Total power scheduling cost      2            ________
           from rate case

           Power scheduling cost            3            ________
           functionalization factor
           (Line 1/Line 2)

       B.  Allocation Factor

           MFU allocation factor            4            ________
           (Schedule A, line 3)

       C.  Total Power Scheduling Costs

           Power scheduling direct costs    5  ________  ________  _________

           Power scheduling indirect costs  6  ________  ________  _________

           Power scheduling overhead costs  7  ________  ________  _________

           Bonneville's total power         8  ________  ________  _________
           scheduling costs
           (Line 5 + Line 6 + Line 7)

       D.  Power Scheduling Cost            9  ________  ________  _________
           (Line 8 * Line 3 * Line 4)

                                                       Exhibit I, Schedule H
                                              Contract No. DE-MS79-94BP94521
                                           Puget Sound Power & Light Company
                                Effective on the effective date of Exhibit B


SCHEDULE H FOR FY XXXX


                                        Line
                                        No.1  Forecast   Actual   Difference


VIII.  End of Term Costs

       A.  Direct Cost

       Direct Cost of End of Term         1  ________  ________  __________
       Costs

       B.  Indirect Costs and Over-
       head Costs

      Indirect Costs and Overhead         2  ________  ________  __________
       Costsof End of Term costs

       C.  Credits

       Credits from decommissioning       3  ________  ________  __________
       PNW AC Intertie facilities

       D.  End of Term Costs              4  ________  ________  __________
<Page

                                                       Exhibit J, Page 1 of 1
                                               Contract No. DE-MS79-94BP94521
                                            Puget Sound Power & Light Company
                                              Effective on the Effective Date


             Puget's Initial Transaction with California Utility


Name of parties:             Puget/Pacific Gas & Electric Company

Terms of Contract:           Variable

Date of Execution:           October 25, 1991

Amount of Transaction (MW):  300 MW