EXHIBIT 99(a)

(8)  COMMITMENTS AND CONTINGENCIES

 (a) HL&P.  HL&P has various commitments for capital expenditures,
     fuel, purchased power, cooling water and operating leases.
     Commitments in connection with HL&P's capital program are
     generally revocable by HL&P subject to reimbursement to
     manufacturers for expenditures incurred or other cancellation
     penalties.  HL&P's other commitments have various quantity
     requirements and durations.  However, if these requirements could
     not be met, various alternatives are available to mitigate the
     cost associated with the contracts' commitments.

     HL&P's capital program (exclusive of AFUDC) is presently
     estimated to cost $478 million in 1994, $381 million in 1995 and
     $418 million in 1996.  These amounts do not include expenditures
     on projects for which HL&P expects to be reimbursed by customers
     or other parties.

     HL&P has entered into several long-term coal, lignite and natural
     gas contracts which have various quantity requirements and
     durations.  Minimum obligations for coal and transportation
     agreements are approximately $167 million in 1994, and $165
     million in 1995 and 1996.  In addition, the minimum obligations
     under the lignite mining and lease agreements will be
     approximately $14 million annually during the 1994-1996 period.
     HL&P has entered into several gas purchase agreements containing
     contract terms in excess of one year which provide for specified
     purchase and delivery obligations.  Minimum obligations for
     natural gas purchase and natural gas storage contracts are
     approximately $57.4 million in 1994, $58.9 million in 1995 and
     $60.5 million in 1996.  Collectively, the gas supply contracts
     included in these figures could amount to 11% of HL&P's annual
     natural gas requirements.  The Utility Commission's rules provide
     for recovery of the coal, lignite and natural gas costs described
     above through the energy component of HL&P's electric rates.
     Nuclear fuel costs are also included in the energy component of
     HL&P's electric rates based on the cost of nuclear fuel consumed
     in the reactor.

     HL&P has commitments to purchase firm capacity from cogenerators
     of approximately $145 million in 1994, $32 million in 1995 and
     $22 million in 1996.  The Utility Commission's rules allow
     recovery of these costs through HL&P's base rates for electric
     service and additionally authorize HL&P to charge or credit
     customers for any variation in actual purchased power cost from
     the cost utilized to determine its base rates.  In the event that
     the Utility Commission, at some future date, does not allow
     recovery through rates of any amount of purchased power payments,
     the three principal firm capacity contracts contain provisions
     allowing HL&P to suspend or reduce payments and seek repayment
     for amounts disallowed.

     In November 1990, the Clean Air Act was extensively amended by
     Congress.  HL&P has already made an investment in pollution
     control facilities, and all of its generating facilities
     currently comply in all material respects with sulfur dioxide
     emission standards established by the legislation.  Provisions of
     the Clean Air Act dealing with urban air pollution required
     establishing new emission limitations for  nitrogen oxides from
     existing sources.  The cost of modifications necessary to reduce
     nitrogen oxide emissions from existing sources has been estimated
     at $29 million in 1994 and $10.5 million in 1995.  In addition,
     continuous emission monitoring regulations are anticipated to
     require expenditures of $12 million in 1994 and $2 million in
     1995.  Capital expenditures are expected to total $71 million for
     the years 1994 through 1996.

     The Energy Policy Act of 1992, which became law in October 1992,
     includes a provision that assesses a fee upon domestic utilities
     having purchased enrichment services from the Department of
     Energy before October 22, 1992.  This fee is to cover a portion
     of the cost to decontaminate and decommission the enrichment
     facilities.  It is currently estimated that the assessment to the
     South Texas Project Electric Generating Station (South Texas
     Project) will be approximately $4 million in 1994 and
     approximately $2 million each year thereafter (subject to
     escalation for inflation), of which HL&P's share is 30.8%.  This
     assessment will continue until the earlier of 15 years or when
     $2.25 billion (adjusted for inflation) has been collected from
     domestic utilities.  Based on HL&P's actual payment of $579,810
     in 1993, it recorded an estimated liability of $8.7 million.

     HL&P's service area is heavily dependent on oil, gas, refined
     products, petrochemicals and related business.  Significant
     adverse events affecting these industries would negatively impact
     the revenues of the Company and HL&P.

(9)  JOINTLY-OWNED NUCLEAR PLANT

 (a) HL&P INVESTMENT.  HL&P is project manager and one of four co-
     owners in the South Texas Project, which consists of two 1,250
     megawatt nuclear generating units.  Unit Nos. 1 and 2 of the
     South Texas Project achieved commercial operation in August 1988
     and June 1989, respectively.  Each co-owner funds its own share
     of capital and operating costs associated with the plant, with
     HL&P's interest in the project being 30.8%.  HL&P's share of the
     operation and maintenance expenses is included in electric
     operation and maintenance expenses on the Company's Statements of
     Consolidated Income and in the corresponding operating expense
     amounts on HL&P's Statements of Income.

     As of December 31, 1993, HL&P's investments (net of accumulated
     depreciation and amortization) in the South Texas Project and in
     nuclear fuel, including AFUDC, were $2.1 billion and $119
     million, respectively.

 (b) CITY OF AUSTIN LITIGATION.  In 1983, the City of Austin (Austin),
     one of the four co-owners of the South Texas Project, filed a
     lawsuit against the Company and HL&P alleging that it was
     fraudulently induced to participate in the South Texas Project
     and that HL&P failed to perform properly its duties as project
     manager.  After a jury trial in 1989, judgment was entered in
     favor of HL&P, and that judgment was affirmed on appeal.  In May
     1993, following the expiration of Austin's rights to appeal to
     the United States Supreme Court, the judgment in favor of the
     Company and HL&P became final.

     On February 22, 1994, Austin filed a new suit against HL&P.  In
     that suit, filed in the 164th District Court for Harris County,
     Texas, Austin alleges that the outages at the South Texas Project
     since February 1993 are due to HL&P's failure to perform
     obligations it owed to Austin under the Participation Agreement
     among the four co-owners of the South Texas Project
     (Participation Agreement).  Austin asserts that such failures
     have caused Austin damages of at least $125 million, which are
     continuing, due to the incurrence of increased operating and
     maintenance costs, the cost of replacement power and lost profits
     on wholesale transactions that did not occur.  Austin states that
     it will file a "more detailed" petition at a later date.  For a
     discussion of the 1993 outage, see Note 9(f).

     As it did in the litigation filed against HL&P in 1983, Austin
     asserts that HL&P breached obligations HL&P owed under the
     Participation Agreement to Austin, and Austin seeks a declaration
     that HL&P had as duty to exercise reasonable care in the
     operation and maintenance of the South Texas Project.  In that
     earlier litigation, however, the courts concluded that the
     Participation Agreement did not impose on HL&P a duty to exercise
     reasonable skill and care as Project Manager.

     Austin also asserts in its new suit that certain terms of a
     settlement reached in 1992 among HL&P and Central and South West
     Corporation (CSW) and its subsidiary, Central Power and Light
     Company (CPL), are invalid and void.  The Participation Agreement
     permits arbitration of certain disputes among the owners, and the
     challenged settlement terms provide that in any future
     arbitration, HL&P and CPL would each appoint an arbitrator
     acceptable to the other.  Austin asserts that, as a result of
     this agreement, the arbitration provisions of the Participation
     Agreement are void and Austin should not be required to
     participate in or be bound by arbitration proceedings;
     alternatively, Austin asserts that HL&P's rights with respect to
     CPL's appointment of an arbitrator should be shared with all the
     owners or canceled, and Austin seeks injunctive relief against
     arbitration of its dispute with HL&P.  For a further discussion
     of the settlement among HL&P, CSW and CPL, see Note 9(c) below.

     HL&P and the Company do not believe there is merit to Austin's
     claims, and they intend to defend vigorously against them.
     However, there can be no assurance as to the ultimate outcome of
     this matter.

 (c) ARBITRATION WITH CO-OWNERS.  During the course of the litigation
     filed by Austin in 1983, the City of San Antonio (San Antonio)
     and CPL, the other two co-owners in the South Texas Project,
     asserted claims for unspecified damages against HL&P as project
     manager of the South Texas Project, alleging HL&P breached its
     duties and obligations.  San Antonio and CPL requested
     arbitration of their claims under the Participation Agreement.
     This matter was severed from the Austin litigation and is pending
     before the 101st District Court in Dallas County, Texas.

     The 101st District Court ruled that the demand for arbitration is
     valid and enforceable under the Participation Agreement, and that
     ruling has been upheld by appellate courts.  Arbitrators were
     appointed by HL&P and each of the other co-owners in connection
     with the District Court's ruling.  The Participation Agreement
     provides that the four appointed arbitrators will select a fifth
     arbitrator, but that action has not yet occurred.

     In 1992, the Company and HL&P entered into a settlement with CPL
     and CSW, with respect to various matters including the
     arbitration and related legal proceedings.  Pursuant to the
     settlement, CPL withdrew its demand for arbitration under the
     Participation Agreement, and the Company, HL&P, CSW and CPL
     dismissed litigation associated with the dispute.  The settlement
     also resolved other disputes between the parties concerning
     various transmission agreements and related billing disputes.  In
     addition, the parties also agreed to support, and to seek consent
     of the other owners of the South Texas Project to, certain
     amendments to the Participation Agreement, including changes in
     the management structure of the South Texas Project through which
     HL&P would be replaced as project manager by an independent
     entity.

     Although settlement with CPL does not directly affect San
     Antonio's pending demand for arbitration,  HL&P and CPL have
     reached certain other understandings which contemplate that:  (i)
     CPL's arbitrator previously appointed for that proceeding would
     be replaced by CPL;  (ii) arbitrators approved by CPL and HL&P
     for any future arbitrations will be mutually acceptable to HL&P
     and CPL; and (iii) HL&P and CPL will resolve any future disputes
     between them concerning the South Texas Project without resorting
     to the arbitration provision of the Participation Agreement.  The
     settlement with CPL did not have a material adverse effect on the
     Company's or HL&P's financial position and results of operations.

     In February 1994, San Antonio indicated a desire to move forward
     with its demand for arbitration and suggested that San Antonio
     considers all allegations of mismanagement against HL&P to be
     appropriate subjects for arbitration in that proceeding, not just
     allegations related to the planning and construction of the South
     Texas Project.  It is unclear what additional allegations San
     Antonio may make, but it is possible that San Antonio will assert
     that HL&P has liability for all or some portion of the additional
     costs incurred by San Antonio due to the 1993 outage of the South
     Texas Project.  For a discussion of that outage see Note 9(f).

     HL&P and the Company continue to regard San Antonio's claims to
     be without merit.  From time to time, HL&P and other parties to
     these proceedings have held discussions with a view toward
     settling their differences on these matters.

     While HL&P and the Company cannot give definite assurance
     regarding the ultimate resolution of the San Antonio litigation
     and arbitration, they presently do not believe such resolutions
     will have a material adverse impact on HL&P's or the Company's
     financial position and results of operations.

 (d) NUCLEAR INSURANCE.  HL&P and the other owners of the South Texas
     Project  maintain nuclear property and nuclear liability
     insurance coverages as required by law and periodically review
     available limits and coverage for additional protection.  The
     owners of the South Texas Project currently maintain $500 million
     in primary property damage insurance from American Nuclear
     Insurers (ANI).  Effective November 15, 1993, the maximum amounts
     of excess property insurance available through the insurance
     industry increased from $2.125 billion to $2.2 billion.  This
     $2.2 billion of excess property insurance coverage includes $800
     million of excess insurance from ANI and $1.4 billion of excess
     property insurance coverage through participation in the Nuclear
     Electric Insurance Limited (NEIL) II program.  The owners of the
     South Texas Project have approved the purchase of the additional
     available excess property insurance coverage.  Additionally,
     effective January 1, 1994, ANI will be increasing their excess
     property insurance limits to $850 million, and the owners of the
     South Texas Project have also approved the purchase of the
     additional limits at the March 1, 1994 renewal for ANI excess
     property insurance.  Under NEIL II, HL&P and the other owners of
     the South Texas Project are subject to a maximum assessment, in
     the aggregate, of approximately $15.9 million in any one policy
     year.  The application of the proceeds of such property insurance
     is subject to the priorities established by the United States
     Nuclear Regulatory Commission (NRC) regulations relating to the
     safety of licensed reactors and decontamination operations.

     Pursuant to the Price Anderson Act, the maximum liability to the
     public for owners of nuclear power plants, such as the South
     Texas Project, was increased from $7.9 billion to $9.3 billion
     effective February 18, 1994.  Owners are required under the Act
     to insure their liability for nuclear incidents and protective
     evacuations by maintaining the maximum amount of financial
     protection available from private sources and by maintaining
     secondary financial protection through an industry retrospective
     rating plan.  Effective August 20, 1993, the assessment of
     deferred premiums provided by the plan for each nuclear incident
     has increased from $63 million to up to $75.5 million per reactor
     subject to indexing for inflation, a possible 5% surcharge (but
     no more than $10 million per reactor per incident in any one
     year) and a 3% state premium tax.  HL&P and the other owners of
     the South Texas Project currently maintain the required nuclear
     liability insurance and participate in the industry retrospective
     rating plan.

     There can be no assurance that all potential losses or
     liabilities will be insurable, or that the amount of insurance
     will be sufficient to cover them.  Any substantial losses not
     covered by insurance would have a material effect on HL&P's and
     the Company's financial condition.

 (e) NUCLEAR DECOMMISSIONING.  HL&P and the other co-owners of the
     South Texas Project are required by the NRC to meet minimum
     decommissioning funding requirements to pay the costs of
     decommissioning the South Texas Project.  Pursuant to the terms
     of the order of the Utility Commission in Docket No. 9850, HL&P
     is currently funding decommissioning costs for the South Texas
     Project with an independent trustee at an annual amount of $6
     million.

     As of December 31, 1993, the trustee held approximately $18.7
     million for decommissioning, for which the asset and liability
     are reflected on the Company's Consolidated and HL&P's Balance
     Sheets in deferred debits and deferred credits, respectively.
     HL&P's funding level is estimated to provide approximately $146
     million in 1989 dollars, an amount which currently exceeds the
     NRC minimum.  However, the South Texas Project co-owners have
     engaged an outside consultant to review the estimated
     decommissioning costs of the South Texas Project which review
     should be completed by the end of 1994.  While changes to present
     funding levels, if any, cannot be estimated at this time, a
     substantial increase in funding may be necessary.  No assurance
     can be given that the amounts held in trust will be adequate to
     cover the decommissioning costs.

 (f) NRC INSPECTIONS AND OPERATIONS.  Both generating units at the
     South Texas Project were out of service from February 1993 to
     February 1994, when Unit No. 1 was authorized by the NRC to
     return to service.  Currently, Unit No. 1 is out of service for
     repairs to a small steam generator leak encountered following the
     unit's shutdown to repair a feedwater control valve.  Those
     repairs are scheduled for completion by mid-March 1994, and no
     formal NRC approval is required to resume operation of Unit No.
     1.  Unit No. 2 is currently scheduled to resume operation after
     completion of regulatory reviews, in the spring of 1994. HL&P
     removed the units from service in February 1993 when a problem
     was encountered with certain pumps.  At that time HL&P concluded
     that the units should not resume operation until HL&P had
     determined the root cause of the failure and had briefed the NRC
     and corrective action had been taken.  The NRC formalized that
     commitment in a Confirmatory Action Letter, which confirmed that
     HL&P would not resume operations until it had briefed the NRC on
     its findings and actions.  Subsequently, that Confirmatory Action
     Letter was supplemented by the NRC to require HL&P, prior to
     resuming operations, to address additional matters which were
     identified during the course of analyzing the issues associated
     with the original pump failure and during various subsequent NRC
     inspections and reviews.

     In June 1993, the NRC announced that the South Texas Project had
     been placed on the NRC's "watch list" of plants with "weaknesses
     that warrant increased NRC attention."  Plants in this category
     are authorized to operate but are subject to close monitoring by
     the NRC.  The NRC reviews the status of plants on this list semi-
     annually, but HL&P does not anticipate that the South Texas
     Project would be removed from that list until there has been a
     period of operation for both units, and the NRC concludes that
     the concerns which led the NRC to place the South Texas Project
     on that list have been satisfactorily addressed.

     The NRC's decision to place the South Texas Project on its "watch
     list" followed the June 1993 issuance of a report by its
     Diagnostic Evaluation Team (DET) which conducted a review of the
     South Texas Project in the spring of 1993 and identified a number
     of areas requiring improvement at the South Texas Project.
     Conducted infrequently, NRC diagnostic evaluations do not
     evaluate compliance with NRC regulations but are broad-based
     evaluations of overall plant operations and are intended to
     review the strengths and weaknesses of the licensee's performance
     and to identify the root cause of performance problems.

     The DET report found, among other things, weaknesses in
     maintenance and testing, deficiencies in training and in the
     material condition of some equipment, strained staffing levels in
     operations and several weaknesses in engineering support.  The
     report cited the need to reduce backlogs of engineering and
     maintenance work and to simplify work processes which, the DET
     found, placed excessive burdens on operating and other plant
     personnel.  The report also identified the need to strengthen
     management communications, oversight and teamwork as well as the
     capability to identify and correct the root causes of problems.
     The DET also expressed concern with regard to the adequacy of
     resources committed to resolving issues at the South Texas
     Project but noted that many issues had already been identified
     and were being addressed by HL&P.

     In response to the DET report, HL&P presented its plan to address
     the issues raised in that report and began its action program to
     address those concerns. While those programs were being
     implemented, HL&P also initiated additional activities and
     modifications that were not previously scheduled during 1993 but
     which are designed to eliminate the need for some future outages
     and to enhance operations at the South Texas Project.  The NRC
     conducted additional inspections and reviews of HL&P's plans and
     agreed in February 1994 that HL&P's progress in addressing the
     NRC's concerns had satisfied the issues raised in the
     Confirmatory Action Letter with respect to Unit No. 1.  The NRC
     concurred in HL&P's determination that Unit No. 1 could resume
     operation.  Work is now underway to address the NRC's concerns
     with respect to Unit No. 2, which HL&P anticipates will not
     require as extensive an effort as was required by the NRC for
     Unit No. 1.  However, difficulties encountered in completing
     actions required on Unit No. 2 and any additional issues which
     may be raised in the conduct of those activities or in the
     operation of Unit No. 1 could adversely affect the anticipated
     schedule for resuming operation of Unit No. 2.  During the
     outage, HL&P has not had, and does not anticipate having,
     difficulty in meeting its energy needs.

     During the outage, both fuel and non-fuel expenditures have been
     higher for HL&P than levels originally projected for the year.
     HL&P's non-fuel expenditures for the South Texas Project during
     1993 were approximately $115 million greater than originally
     budgeted levels (of which HL&P's share was $35 million) for work
     undertaken in connection with the DET and for other initiatives
     taken during the year.  It is expected that, subsequent to 1993,
     operation and maintenance costs will continue to be higher than
     previous levels in order to support additional initiatives
     developed in 1993.  Fuel costs also were necessarily higher due
     to the use of higher cost alternative fuels.  However, these
     increased expenditures are expected to be offset to some extent
     by savings from future outages that can now be avoided as a
     result of activities accelerated into 1993 and from overall
     improvement in operations resulting from implementing the
     programs developed during the outage.  For a discussion of
     regulatory treatment related to the outage, see Notes 10(f) and
     10(g).

     During 1993, the NRC imposed a total of $500,000 in civil
     penalties (of which HL&P's share was $154,000) in connection with
     violations of NRC requirements.

     In March 1993, a Houston newspaper reported that the NRC had
     referred to the Department of Justice allegations that the
     employment of three former employees and an employee of a
     contractor to HL&P had been terminated or disrupted in
     retaliation for their having made safety-related complaints to
     the NRC.  Such retaliation, if proved, would be contrary to
     requirements of the Atomic Energy Act and regulations promulgated
     by the NRC.  The NRC has confirmed to HL&P that these matters
     have been referred to the Department of Justice for consideration
     of further action and has notified HL&P that the NRC is
     considering enforcement action against HL&P and one or more HL&P
     employees in connection with one of those cases.  HL&P has been
     advised by counsel that most referrals by the NRC to the
     Department of Justice do not result in prosecutions.  The Company
     and HL&P strongly believe that the facts underlying these events
     would not support action by the Department of Justice against
     HL&P or any of its personnel; accordingly, HL&P intends to defend
     vigorously against such charges.  HL&P also intends to defend
     vigorously against civil proceedings filed in the state court in
     Matagorda County, Texas, by the complaining employees and against
     administrative proceedings before the Department of Labor and the
     NRC, which, independently of the Department of Justice, could
     impose administrative sanctions if they find violations of the
     Atomic Energy Act or the NRC regulations.  These administrative
     sanctions may include civil penalties in the case of the NRC and,
     in the case of the Department of Labor, ordering reinstatement
     and back pay and/or imposing civil penalties.  Although the
     Company and HL&P do not believe these allegations have merit or
     will have a material adverse effect on the Company or HL&P,
     neither the Company nor HL&P can predict at this time their
     outcome.

(10) UTILITY COMMISSION PROCEEDINGS

     Pursuant to a series of applications filed by HL&P in recent
     years, the Utility Commission has granted HL&P rate increases to
     reflect in electric rates HL&P's substantial investment in new
     plant construction, including the South Texas Project.  Although
     Utility Commission action on those applications has been
     completed, judicial review of a number of the Utility Commission
     orders is pending.  In Texas, Utility Commission orders may be
     appealed to a District Court in Travis County, and from that
     Court's decision an appeal may be taken to the Court of Appeals
     for the 3rd District at Austin (Austin Court of Appeals).
     Discretionary review by the Supreme Court of Texas may be sought
     from decisions of the Austin Court of Appeals.  The pending
     appeals from the Utility Commission orders are in various stages.
     In the event the courts ultimately reverse actions of the Utility
     Commission in any of these proceedings, such matters would be
     remanded to the Utility Commission for action in light of the
     courts' orders.  Because of the number of variables which can
     affect the ultimate resolution of such matters on remand, the
     Company and HL&P generally are not in a position at this time to
     predict the outcome of the matters on appeal or the ultimate
     effect that adverse action by the courts could have on the
     Company and HL&P.  On remand, the Utility Commission's action
     could range from granting rate relief substantially equal to the
     rates previously approved, to a reduction in the revenues to
     which HL&P was entitled during the time the applicable rates were
     in effect, which could require a refund to customers of amounts
     collected pursuant to such rates.

     Judicial review has been concluded or currently is pending on the
     final orders of the Utility Commission described below.

 (a) DOCKET NOS. 6765, 6766 AND 5779.  In February 1993, the Austin
     Court of Appeals granted a motion by the Office of Public Utility
     Counsel (OPC) to voluntarily dismiss its appeal of the Utility
     Commission's order in HL&P's 1984 rate case (Docket No. 5779).
     In December 1993, the Supreme Court of Texas granted a similar
     motion by OPC to dismiss its appeal of the Utility Commission's
     order in HL&P's 1986 rate case (Docket Nos. 6765 and 6766).  As a
     result, appellate review of the Utility Commission's orders in
     those dockets has been concluded, and the orders have been
     affirmed.

 (b) DOCKET NO. 8425.  In October 1992, a District Court in Travis
     County, Texas affirmed the Utility Commission's order in HL&P's
     1988 rate case (Docket No. 8425).  An appeal to the Austin Court
     of Appeals is pending.  In its final order in that docket, the
     Utility Commission granted HL&P a $227 million increase in base
     revenues, allowed a 12.92% return on common equity, authorized a
     qualified phase-in plan for Unit No. 1 of the South Texas Project
     (including approximately 72% of HL&P's investment in Unit No. 1
     of the South Texas Project in rate base) and authorized HL&P to
     use deferred accounting for Unit No. 2 of the South Texas
     Project.  Rates substantially corresponding to the increase
     granted were implemented by HL&P in June 1989 and remained in
     effect until May 1991.

     In the appeal of the Utility Commission's order, certain parties
     have challenged the Utility Commission's decision regarding
     deferred accounting, treatment of federal income tax expense and
     certain other matters.  A recent decision of the Austin Court of
     Appeals, in an appeal involving another utility (and to which
     HL&P was not a party), adopted some of the arguments being
     advanced by parties challenging the Utility Commission's order in
     Docket No. 8425.  In that case, PUBLIC UTILITY COMMISSION OF
     TEXAS VS. GTE-SW, the Austin Court of Appeals ruled that when a
     utility pays federal income taxes as part of a consolidated
     group, the utility's ratepayers are entitled to a fair share of
     the tax savings actually realized, which can include savings
     resulting from unregulated activities.  The Texas Supreme Court
     has agreed to hear an appeal of that decision, but on points not
     involving the federal income tax issues, though tax issues could
     be decided in such opinion.

     In its final order in Docket No. 8425, the Utility Commission did
     not reduce HL&P's tax expense by any of the tax savings resulting
     from the Company's filing of a consolidated tax return.  Although
     the GTE decision was not legally dispositive of the tax issues
     presented in the appeal of Docket No. 8425, it is possible that
     the Austin Court of Appeals could utilize the reasoning in GTE in
     addressing similar issues in the appeal of Docket No. 8425.
     However, in February 1993 the Austin Court of Appeals,
     considering an appeal involving another telephone utility, upheld
     Utility Commission findings that the tax expense for the utility
     included the utility's fair share of the tax savings resulting
     from a consolidated tax return, even though the utility's fair
     share of the tax savings was determined to be zero.  HL&P
     believes that the Utility Commission findings in Docket No. 8425
     and in Docket No. 9850 (see Note 10(c)) should be upheld on the
     same principle (i.e., that the Utility Commission determined that
     the fair share of tax savings to be allocated to ratepayers is
     determined to be zero).  However, no assurance can be made as to
     the ultimate outcome of this matter.

     The Utility Commission's order in Docket No. 8425 may be affected
     also by the ultimate resolution of appeals concerning the Utility
     Commission's treatment of deferred accounting.  For a discussion
     of appeals of the Utility Commission's orders on deferred
     accounting, see Notes 10(e) and 11.

 (c) DOCKET NO. 9850.  In August 1992, a district court in Travis
     County affirmed the Utility Commission's final order in HL&P's
     1991 rate case (Docket No. 9850).  That decision was appealed by
     certain parties to the Austin Court of Appeals, raising issues
     concerning the Utility Commission's approval of a non-unanimous
     settlement in that docket, the Utility Commission's calculation
     of federal income tax expense and the allowance of deferred
     accounting reflected in the settlement.  In August 1993, the
     Austin Court of Appeals affirmed on procedural grounds the ruling
     by the Travis County District Court, and applications for writ of
     error were filed with the Supreme Court of Texas by one of the
     other parties to the proceeding.  The Supreme Court has not yet
     ruled on these applications.  In Docket No. 9850, the Utility
     Commission approved a settlement agreement reached with most
     parties.  That settlement agreement provided for a $313 million
     increase in HL&P's base rates, termination of deferrals granted
     with respect to Unit No. 2 of the South Texas Project and of the
     qualified phase-in plan deferrals granted with respect to Unit
     No. 1 of the South Texas Project, and recovery of deferred plant
     costs.  The settlement authorized a 12.55% return on common
     equity for HL&P, and HL&P agreed not to request additional
     increases in base rates that would be implemented prior to May 1,
     1993.  Rates contemplated by that settlement agreement were
     implemented in May 1991 and remain in effect.

     The Utility Commission's order in Docket No. 9850 found that HL&P
     would have been entitled to more rate relief than the $313
     million agreed to in the settlement, but certain recent actions
     of the Austin Court of Appeals could, if ultimately upheld and
     applied to the appeal of Docket No. 9850, require a remand of
     that settlement to the Utility Commission.  HL&P believes that
     the amount which the Utility Commission found HL&P was entitled
     to would exceed any disallowance that would have been required
     under the Austin Court of Appeals' ruling regarding deferred
     accounting (see Notes 10(e) and 11) or any adverse effect on the
     calculation of tax expense if the court's ruling in the GTE
     decision were applied to that settlement (see Note 10(b) above).
     However, the amount of rate relief to which the Utility
     Commission found HL&P to be entitled in excess of the $313
     million agreed to in the settlement may not be sufficient if the
     reasoning in both the GTE decision and the ruling on deferred
     accounting were to be applied to the settlement agreement in
     Docket No. 9850.  Although HL&P believes that it should be
     entitled to demonstrate entitlement to rate relief equal to that
     agreed to in the stipulation in Docket No. 9850, HL&P cannot rule
     out the possibility that a remand and reopening of that
     settlement would be required if decisions unfavorable to HL&P are
     rendered on both the deferred accounting treatment and the
     calculation of tax expense for ratemaking purposes.

 (d) DOCKET NO. 6668.  In June 1990, the Utility Commission issued the
     final order in Docket No. 6668, the Utility Commission's inquiry
     into the prudence of the planning, management and construction of
     the South Texas Project.  The Utility Commission's findings and
     order in Docket No. 6668 were incorporated in Docket No. 8425,
     HL&P's 1988 general rate case.  Pursuant to the findings in
     Docket No. 6668, the Utility Commission found imprudent $375.5
     million out of HL&P's $2.8 billion investment in the two units of
     the South Texas Project.

     The Utility Commission's findings did not reflect $207 million in
     benefits received in a settlement of litigation with the former
     architect-engineer of the South Texas Project or the effects of
     federal income taxes, investment tax credits or certain
     deferrals.  In addition, accounting standards require that the
     equity portion of AFUDC accrued for regulatory purposes under
     deferred accounting orders be utilized to determine the cost
     disallowance for financial reporting purposes.  After taking all
     of these items into account, HL&P recorded an after-tax charge of
     $15 million in 1990 and continued to reduce such loss with the
     equity portion of deferrals in 1991 related to Unit No. 2 of the
     South Texas Project.  The findings in Docket No. 6668 represent
     the Utility Commission's final determination regarding the
     prudence of expenditures associated with the planning and
     construction of the South Texas Project.  Unless the order is
     modified or reversed on appeal, HL&P will be precluded from
     recovering in rate proceedings the amount found imprudent by the
     Utility Commission.

     Appeals by HL&P and other parties of the Utility Commission's
     order in Docket No. 6668 were dismissed by a District Court in
     Travis County in May 1991.  However, in December 1992 the Austin
     Court of Appeals reversed the District Court's dismissals on
     procedural grounds.  HL&P and other parties have filed
     applications for writ of error with the Supreme Court of Texas
     concerning the order by the Austin Court of Appeals, but unless
     the order is modified on further review, HL&P anticipates that
     the appeals of the parties will be reinstated and that the merits
     of the issues raised in those appeals of Docket No. 6668 will be
     considered by the District Court, with the possibility of
     subsequent judicial review once the District Court has acted on
     those appeals.  In addition, separate appeals are pending from
     Utility Commission orders in Docket Nos. 8425 and 9850, in which
     the findings of the order in Docket No. 6668 are reflected in
     rates.  See Notes 10(b) and 10(c).

 (e) DOCKET NOS. 8230 AND 9010.  Deferred accounting treatment for
     Unit No. 1 of the South Texas Project was authorized by the
     Utility Commission in Docket No. 8230 and was extended in Docket
     No. 9010.  Similar deferred accounting treatment with respect to
     Unit No. 2 of the South Texas Project was authorized in Docket
     No. 8425.  For a discussion of the deferred accounting treatment
     granted, see Note 11.  In September 1992, the Austin Court of
     Appeals, in considering the appeal of the Utility Commission's
     final order in Docket Nos. 8230 and 9010, upheld the Utility
     Commission's action in granting deferred accounting treatment for
     operation and maintenance expenses, but rejected such treatment
     for the carrying costs associated with the investment in Unit No.
     1 of the South Texas Project.  That ruling followed the Austin
     Court of Appeals decision rendered in August 1992, on a motion
     for rehearing, involving another utility which had been granted
     similar deferred accounting treatment for another nuclear plant.
     In its August decision, the court ruled that Texas law did not
     permit the Utility Commission to allow the utility to place the
     carrying costs associated with the investment in the utility's
     rate base, though the court observed that the Utility Commission
     could allow amortization of such costs.

     The Supreme Court of Texas has granted applications for writ of
     error with respect to the Austin Court of Appeals decision
     regarding Docket Nos. 8230 and 9010. The Supreme Court of Texas
     has also granted applications for writ of error on three other
     decisions by the Austin Court of Appeals regarding deferred
     accounting treatment granted to other utilities by the Utility
     Commission.  The Supreme Court heard oral arguments on these
     appeals on September 13, 1993.  The court has not yet ruled.

 (f) DOCKET NO. 12065.  HL&P is not currently seeking authority to
     change its base rates for electric service, but the Utility
     Commission has authority to initiate a rate proceeding pursuant
     to Section 42 of the Public Utility Regulatory Policy Act (PURA)
     to determine whether existing rates are unjust or unreasonable.
     In 1993, the Utility Commission referred to an administrative law
     judge (ALJ) the complaint of a former employee of HL&P seeking to
     initiate such a proceeding.

     On February 23, 1994, the ALJ concluded that a Section 42
     proceeding should be conducted and that HL&P should file full
     information, testimony and schedules justifying its rates.  The
     ALJ acknowledged that the decision was a close one, and is
     subject to review by the Utility Commission.  However, he
     concluded that information concerning HL&P's financial results as
     of December 1992 indicated that HL&P's adjusted revenues could be
     approximately $62 million (or 2.33% of its adjusted base
     revenues) more than might be authorized in a current rate
     proceeding.  The ALJ's conclusion was based on various accounting
     considerations, including use of a different treatment of federal
     income tax expense than the method utilized in HL&P's last rate
     case.  The ALJ also found that there could be a link between the
     1993 outage at the South Texas Project, the NRC's actions with
     respect to the South Texas Project and possible mismanagement by
     HL&P, which in turn could result in a reduction of HL&P's
     authorized rate of return as a penalty for imprudent management.

     HL&P and the Company believe that the examiner's analysis is
     incorrect, that the South Texas Project has not been imprudently
     managed, and that ordering a Section 42 proceeding at this time
     is unwarranted and unnecessarily expensive and burdensome.  HL&P
     has appealed the ALJ's decision to the Utility Commission.

     If HL&P ultimately is required to respond to a Section 42
     inquiry, it will assert that it remains entitled to rates at
     least at the levels currently authorized.  However, there can be
     no assurance as to the outcome of a Section 42 proceeding if it
     is ultimately authorized, and HL&P's rates could be reduced
     following a hearing.  HL&P believes that any reduction in base
     rates as a result of a Section 42 inquiry would take effect
     prospectively.

     HL&P is also a defendant in a lawsuit filed in a Fort Bend
     County, Texas, district court by the same former HL&P employee
     who originally initiated the Utility Commission complaint
     concerning HL&P's rates.  In that suit, Pace and Scott v. HL&P,
     the former employee contends that HL&P is currently charging
     illegal rates since the rates authorized by the Utility
     Commission do not allocate to ratepayers tax benefits accruing to
     the Company and to HL&P by virtue of the fact that HL&P's federal
     income taxes are paid as part of a consolidated group.  HL&P is
     seeking dismissal of that suit because in Texas exclusive
     jurisdiction to set electric utility rates is vested in
     municipalities and in the Utility Commission, and the courts have
     no jurisdiction to set such rates or to set aside authorized
     rates except through judicial appeals of Utility Commission
     orders in the manner prescribed in applicable law.  Although
     substantial damages have been claimed by the plaintiffs in that
     litigation, HL&P and the Company consider this litigation to be
     wholly without merit, and do not presently believe that it will
     have a material adverse effect on the Company's or HL&P's results
     of operations, though no assurances can be given as to its
     ultimate outcome at this time.

 (g) FUEL RECONCILIATION.  HL&P recovers fuel costs incurred in
     electric generation through a fixed fuel factor that is set by
     the Utility Commission.  The difference between fuel revenues
     billed pursuant to such factor and fuel expense incurred is
     recorded as an addition to or a reduction of revenues, with a
     corresponding entry to under- or over-recovered fuel, as
     appropriate.  Amounts collected pursuant to the fixed fuel factor
     must be reconciled periodically by the Utility Commission against
     actual, reasonable costs as determined by the Utility Commission.
     Any fuel costs which the Utility Commission determines are
     unreasonable in a fuel reconciliation proceeding would not be
     recoverable from customers, and a charge against earnings would
     result.  Under Utility Commission rules, HL&P is required to file
     an application to reconcile those costs in 1994.  Such a filing
     would also be required in conjunction with any rate proceeding
     that may be filed, such as the Section 42 proceeding described in
     Note 10(f).

     Unless filed earlier in conjunction with a rate proceeding, HL&P
     currently anticipates filing its fuel reconciliation application
     in the fourth quarter of 1994 in accordance with a  schedule
     proposed by the Utility Commission staff.  If that schedule is
     approved by the Utility Commission, HL&P anticipates that fuel
     costs through some time in 1994 will be submitted for
     reconciliation.  No hearing would be anticipated in that
     reconciliation proceeding before 1995.

     The schedule for a fuel reconciliation proceeding could be
     affected by the institution of a prudence inquiry concerning the
     outage at the South Texas Project.  The Utility Commission staff
     has indicated a desire to conduct an inquiry into the prudence of
     HL&P's management prior to and during the outage, but it is
     currently unknown what action the Utility Commission will take on
     that request or what the nature and scope of any such proceeding
     would be.  Such an inquiry could also be conducted in connection
     with a rate proceeding under Section 42 of PURA if one is
     instituted by the Utility Commission.

     Through the end of 1993, HL&P had recovered through the fuel
     factor approximately $115 million (including interest) less than
     the amounts expended for fuel, a significant portion of which
     under recovery occurred in 1993 during the outage at the South
     Texas Project.  In any review of costs incurred during the period
     of the 1993 outage at the South Texas Project, it is anticipated
     that other parties will contend that a portion of fuel costs
     incurred should be attributed to imprudence on the part of HL&P
     and thus should be disallowed as unreasonable, with recovery from
     ratepayers denied. Those amounts could be substantial.  HL&P
     intends to defend vigorously against any allegation that its
     actions have been imprudent or that any portion of its costs
     incurred should be judged to be unreasonable, but no prediction
     can be made as to the ultimate outcome of such a proceeding.

(11) DEFERRED PLANT COSTS

     Deferred plant costs were authorized for the South Texas Project
     by the Utility Commission in two contexts.  In the first context,
     or "deferred accounting," the Utility Commission orders permitted
     HL&P, for regulatory purposes, to continue to accrue carrying
     costs in the form of AFUDC (at a 10% rate) on its investment in
     the two units of the South Texas Project until costs of such
     units were reflected in rates (which was July 1990 for
     approximately 72% of Unit No. 1, and May 1991 for the remainder
     of Unit No. 1 and 100% of Unit No. 2) and to defer and capitalize
     depreciation, operation and maintenance, insurance and tax
     expenses associated with such units during the deferral period.
     Accounting standards do not permit the accrual of the equity
     portion of AFUDC for financial reporting purposes under these
     circumstances.  However, in accordance with accounting standards,
     such amounts were utilized to determine the amount of plant cost
     disallowance for financial reporting purposes.

     The deferred expenses and the debt portion of the carrying costs
     associated with the South Texas Project are included on the
     Company's Statements of Consolidated Income in deferred expenses
     and deferred carrying costs, respectively.

     Beginning with the June 1990 order in Docket No. 8425, deferrals
     were permitted in a second context, a "qualified phase-in plan"
     for Unit No. 1 of the South Texas Project.  Accounting standards
     require allowable costs deferred for future recovery under a
     qualified phase-in plan to be capitalized as a deferred charge if
     certain criteria are met.  The qualified phase-in plan as
     approved by the Utility Commission meets these criteria.

     During the period June 1990 through May 15, 1991, HL&P deferred
     depreciation and property taxes related to the 28% of its
     investment in Unit No. 1 of the South Texas Project not reflected
     in the Docket No. 8425 rates and recorded a deferred return on
     that investment as part of the qualified phase-in plan.  Deferred
     return represents the financing costs (equity and debt)
     associated with the qualified phase-in plan.  The deferred
     expenses and deferred return related to the qualified phase-in
     plan are included on the Company's Statements of Consolidated
     Income and HL&P's Statements of Income in deferred expenses and
     deferred return under phase-in plan, respectively.  Under the
     phase-in plan, these accumulated deferrals will be recoverable
     within ten years of the June 1990 order.

     On May 16, 1991, HL&P implemented under bond, in Docket No. 9850,
     a $313 million base rate increase consistent with the terms of
     the settlement.  Accordingly, HL&P ceased all cost deferrals
     related to the South Texas Project and began the recovery of such
     amounts.  These deferrals are being amortized on a straight-line
     basis as allowed by the final order in Docket No. 9850.  The
     amortization of these deferrals totaled $25.8 million for both
     1993 and 1992 and $16.1 million in 1991, and is included on the
     Company's Statements of Consolidated Income and HL&P's Statements
     of Income in depreciation and amortization expense.  See also
     Notes 10(b), 10(c) and 10(e).

     The following table shows the original balance of the deferrals
     and the unamortized balance at December 31, 1993.

                                                      Balance at
                                        Original     December 31,
                                        Balance          1993
                                         (Thousands of Dollars)

  Deferred Accounting: (a)

    Deferred Expenses                  $ 250,151     $ 233,341

    Deferred Carrying Costs on
       Plant Investment                  399,972       373,094
       Total                             650,123       606,435

  Qualified Phase-In Plan: (b)            82,254        58,264

  Total Deferred Plant Cost            $ 732,377     $ 664,699


  (a)  Amortized over the estimated depreciable life of the South
       Texas Project.

  (b)  Amortized over nine years beginning in May 1991.

        As of December 31, 1993, HL&P has recorded deferred income
        taxes of $200.9 million with respect to deferred accounting
        and $14.5 million with respect to the deferrals associated
        with the qualified phase-in plan.

(12) MALAKOFF ELECTRIC GENERATING STATION

        The scheduled in-service dates for the Malakoff Electric
        Generating Station (Malakoff) units were postponed during the
        1980's as expectations of continued strong load growth were
        tempered.  These units have been indefinitely deferred due to
        the availability of other cost effective resource options.  In
        1987, all developmental work was stopped and AFUDC accruals
        ceased.

        Due to the indefinite postponement of the in-service date for
        Malakoff, the engineering design work is no longer considered
        viable.  The costs associated with this engineering design
        work are currently included in rate base and are earning a
        return per the Utility Commission's final order in Docket No.
        8425.  Pursuant to HL&P's determination that such costs will
        have no future value, $84.1 million was reclassified from
        plant held for future use to recoverable project costs as of
        December 31, 1992.  An additional $7.0 million was
        reclassified to recoverable project costs in 1993.
        Amortization of these amounts began in 1993.  Amortization
        amounts will correspond to the amounts being earned as a
        result of the inclusion of such costs in rate base.  The
        Utility Commission's action in allowing treatment of those
        costs as plant held for future use has been challenged in the
        pending appeal of the Utility Commission's final order in
        Docket No. 8425.  Also, recovery of such Malakoff costs may be
        addressed if rate proceedings are initiated such as that
        proposed under Section 42 of PURA.  See Notes 10(b) and 10(f)
        for a discussion of these respective proceedings.

        In June 1990, HL&P purchased from its then fuel supply
        affiliate, Utility Fuels, all of Utility Fuels' interest in
        the lignite reserves and lignite handling facilities for
        Malakoff.  The purchase price was $138.2 million, which
        represented the net book value of Utility Fuels' investment in
        such reserves and facilities.  As part of the June 1990 rate
        order (Docket No. 8425), the Utility Commission ordered that
        issues related to the prudence of the amounts invested in the
        lignite reserves be considered in HL&P's next general rate
        case which was filed in November 1990 (Docket No. 9850).
        However, under the October 1991 Utility Commission order in
        Docket No. 9850, this determination was postponed to a
        subsequent docket.

        HL&P's remaining investment in Malakoff through December 31,
        1993 of $167 million, consisting primarily of lignite reserves
        and land, is included on the Company's Consolidated and HL&P's
        Balance Sheets in plant held for future use.  For the 1994-
        1996 period, HL&P anticipates $14 million of expenditures
        relating to lignite reserves, primarily to keep lignite leases
        and other related agreements in effect.