EXHIBIT 99(a)
  (8)  COMMITMENTS AND CONTINGENCIES

   (a) HL&P.  HL&P has various commitments for capital expenditures, fuel,
       purchased power, cooling water and operating leases.  Commitments in
       connection with HL&P's capital program are generally revocable by HL&P
       subject to reimbursement to manufacturers for expenditures incurred or
       other cancellation penalties.  HL&P's other commitments have various
       quantity requirements and durations.  However, if these requirements
       could not be met, various alternatives are available to mitigate the
       cost associated with the contracts' commitments.

       HL&P's capital program (exclusive of AFUDC) is presently estimated to
       cost $478 million in 1994, $381 million in 1995 and $418 million in
       1996.  These amounts do not include expenditures on projects for which
       HL&P expects to be reimbursed by customers or other parties.

                                      -83-

       HL&P has entered into several long-term coal, lignite and natural gas
       contracts which have various quantity requirements and durations.
       Minimum obligations for coal and transportation agreements are
       approximately $167 million in 1994, and $165 million in 1995 and 1996.
       In addition, the minimum obligations under the lignite mining and lease
       agreements will be approximately $14 million annually during the
       1994-1996 period.  HL&P has entered into several gas purchase agreements
       containing contract terms in excess of one year which provide for
       specified purchase and delivery obligations.  Minimum obligations for
       natural gas purchase and natural gas storage contracts are approximately
       $57.4 million in 1994, $58.9 million in 1995 and $60.5 million in 1996.
       Collectively, the gas supply contracts included in these figures could
       amount to 11% of HL&P's annual natural gas requirements.  The Utility
       Commission's rules provide for recovery of the coal, lignite and natural
       gas costs described above through the energy component of HL&P's
       electric rates.  Nuclear fuel costs are also included in the energy
       component of HL&P's electric rates based on the cost of nuclear fuel
       consumed in the reactor.

       HL&P has commitments to purchase firm capacity from cogenerators of
       approximately $145 million in 1994, $32 million in 1995 and $22 million
       in 1996.  The Utility Commission's rules allow recovery of these costs
       through HL&P's base rates for electric service and additionally
       authorize HL&P to charge or credit customers for any variation in actual
       purchased power cost from the cost utilized to determine its base rates.
       In the event that the Utility Commission, at some future date, does not
       allow recovery through rates of any amount of purchased power payments,
       the three principal firm capacity contracts contain provisions allowing
       HL&P to suspend or reduce payments and seek repayment for amounts
       disallowed.

       In November 1990, the Clean Air Act was extensively amended by Congress.
       HL&P has already made an investment in pollution control facilities, and
       all of its generating facilities currently comply in all material
       respects with sulfur dioxide emission standards established by the
       legislation.  Provisions of the Clean Air Act dealing with urban air
       pollution required establishing new emission limitations for  nitrogen
       oxides from existing sources.  The cost of modifications necessary to
       reduce nitrogen oxide emissions from existing sources has been estimated
       at $29 million in 1994 and $10.5 million in 1995.  In addition,
       continuous emission monitoring regulations are anticipated to require
       expenditures of $12 million in 1994 and $2 million in 1995.  Capital
       expenditures are expected to total $71 million for the years 1994
       through 1996.

       The Energy Policy Act of 1992, which became law in October 1992,
       includes a provision that assesses a fee upon domestic utilities having
       purchased enrichment services from the Department of Energy before
       October 22, 1992.  This fee is to cover a portion of the cost to
       decontaminate and decommission the enrichment facilities.  It is
       currently estimated that the assessment to the South Texas Project
       Electric Generating Station (South Texas Project) will be approximately
       $4 million in 1994 and approximately $2 million each year thereafter
       (subject to escalation for inflation), of which HL&P's share is 30.8%.
       This assessment will continue until the earlier of 15 years or when
       $2.25 billion (adjusted for inflation) has been collected from domestic
       utilities.  Based on HL&P's actual payment of $579,810 in 1993, it
       recorded an estimated liability of $8.7 million.

       HL&P's service area is heavily dependent on oil, gas, refined products,
       petrochemicals and related business.  Significant adverse events
       affecting these industries would negatively impact the revenues of the
       Company and HL&P.
                                      -84-
  (9)  JOINTLY-OWNED NUCLEAR PLANT

   (a) HL&P INVESTMENT.  HL&P is project manager and one of four co-owners in
       the South Texas Project, which consists of two 1,250 megawatt nuclear
       generating units.  Unit Nos. 1 and 2 of the South Texas Project achieved
       commercial operation in August 1988 and June 1989, respectively.  Each
       co-owner funds its own share of capital and operating costs associated
       with the plant, with HL&P's interest in the project being 30.8%.  HL&P's
       share of the operation and maintenance expenses is included in electric
       operation and maintenance expenses on the Company's Statements of
       Consolidated Income and in the corresponding operating expense amounts
       on HL&P's Statements of Income.

       As of December 31, 1993, HL&P's investments (net of accumulated
       depreciation and amortization) in the South Texas Project and in nuclear
       fuel, including AFUDC, were $2.1 billion and $119 million, respectively.

   (b) CITY OF AUSTIN LITIGATION.  In 1983, the City of Austin (Austin), one of
       the four co-owners of the South Texas Project, filed a lawsuit against
       the Company and HL&P alleging that it was fraudulently induced to
       participate in the South Texas Project and that HL&P failed to perform
       properly its duties as project manager.  After a jury trial in 1989,
       judgment was entered in favor of HL&P, and that judgment was affirmed on
       appeal.  In May 1993, following the expiration of Austin's rights to
       appeal to the United States Supreme Court, the judgment in favor of the
       Company and HL&P became final.

       On February 22, 1994, Austin filed a new suit against HL&P.  In that
       suit, filed in the 164th District Court for Harris County, Texas, Austin
       alleges that the outages at the South Texas Project since February 1993
       are due to HL&P's failure to perform obligations it owed to Austin under
       the Participation Agreement among the four co-owners of the South Texas
       Project (Participation Agreement).  Austin asserts that such failures
       have caused Austin damages of at least $125 million, which are
       continuing, due to the incurrence of increased operating and maintenance
       costs, the cost of replacement power and lost profits on wholesale
       transactions that did not occur.  Austin states that it will file a
       "more detailed" petition at a later date.  For a discussion of the 1993
       outage, see Note 9(f).
                                      -85-

       As it did in the litigation filed against HL&P in 1983, Austin asserts
       that HL&P breached obligations HL&P owed under the Participation
       Agreement to Austin, and Austin seeks a declaration that HL&P had as
       duty to exercise reasonable care in the operation and maintenance of the
       South Texas Project.  In that earlier litigation, however, the courts
       concluded that the Participation Agreement did not impose on HL&P a duty
       to exercise reasonable skill and care as Project Manager.

       Austin also asserts in its new suit that certain terms of a settlement
       reached in 1992 among HL&P and Central and South West Corporation (CSW)
       and its subsidiary, Central Power and Light Company (CPL), are invalid
       and void.  The Participation Agreement permits arbitration of certain
       disputes among the owners, and the challenged settlement terms provide
       that in any future arbitration, HL&P and CPL would each appoint an
       arbitrator acceptable to the other.  Austin asserts that, as a result of
       this agreement, the arbitration provisions of the Participation
       Agreement are void and Austin should not be required to participate in
       or be bound by arbitration proceedings; alternatively, Austin asserts
       that HL&P's rights with respect to CPL's appointment of an arbitrator
       should be shared with all the owners or canceled, and Austin seeks
       injunctive relief against arbitration of its dispute with HL&P.  For a
       further discussion of the settlement among HL&P, CSW and CPL, see Note
       9(c) below.

       HL&P and the Company do not believe there is merit to Austin's claims,
       and they intend to defend vigorously against them.  However, there can
       be no assurance as to the ultimate outcome of this matter.

   (c) ARBITRATION WITH CO-OWNERS.  During the course of the litigation filed
       by Austin in 1983, the City of San Antonio (San Antonio) and CPL, the
       other two co-owners in the South Texas Project, asserted claims for
       unspecified damages against HL&P as project manager of the South Texas
       Project, alleging HL&P breached its duties and obligations.  San Antonio
       and CPL requested arbitration of their claims under the Participation
       Agreement.  This matter was severed from the Austin litigation and is
       pending before the 101st District Court in Dallas County, Texas.

       The 101st District Court ruled that the demand for arbitration is valid
       and enforceable under the Participation Agreement, and that ruling has
       been upheld by appellate courts.  Arbitrators were appointed by HL&P and
       each of the other co-owners in connection with the District Court's
       ruling.  The Participation Agreement provides that the four appointed
       arbitrators will select a fifth arbitrator, but that action has not yet
       occurred.

       In 1992, the Company and HL&P entered into a settlement with CPL and
       CSW with respect to various matters including the arbitration and
       related legal proceedings.  Pursuant to the settlement, CPL withdrew its
       demand for arbitration under the Participation Agreement, and the
       Company, HL&P, CSW and CPL dismissed litigation associated with the
       dispute.  The settlement also resolved other disputes between the
       parties concerning various transmission agreements and related billing
       disputes.  In addition, the parties also agreed to support, and to seek
       consent of the other owners of the South Texas Project to, certain
       amendments to the Participation Agreement, including changes in the
       management structure of the South Texas Project through which HL&P would
       be replaced as project manager by an independent entity.

       Although settlement with CPL does not directly affect San Antonio's
       pending demand for arbitration,  HL&P and CPL have reached certain other
       understandings which contemplate that:  (i) CPL's arbitrator previously
       appointed for that proceeding would be replaced by CPL; (ii) arbitrators

                                      -86-

       approved by CPL and HL&P for any future arbitrations will be mutually
       acceptable to HL&P and CPL; and (iii) HL&P and CPL will resolve any
       future disputes between them concerning the South Texas Project without
       resorting to the arbitration provision of the Participation Agreement.
       The settlement with CPL did not have a material adverse effect on the
       Company's or HL&P's financial position and results of operations.

       In February 1994, San Antonio indicated a desire to move forward with
       its demand for arbitration and suggested that San Antonio considers all
       allegations of mismanagement against HL&P to be appropriate subjects for
       arbitration in that proceeding, not just allegations related to the
       planning and construction of the South Texas Project.  It is unclear
       what additional allegations San Antonio may make, but it is possible
       that San Antonio will assert that HL&P has liability for all or some
       portion of the additional costs incurred by San Antonio due to the 1993
       outage of the South Texas Project.  For a discussion of that outage see
       Note 9(f).

       HL&P and the Company continue to regard San Antonio's claims to be
       without merit.  From time to time, HL&P and other parties to these
       proceedings have held discussions with a view toward settling their
       differences on these matters.

       While HL&P and the Company cannot give definite assurance regarding the
       ultimate resolution of the San Antonio litigation and arbitration, they
       presently do not believe such resolutions will have a material adverse
       impact on HL&P's or the Company's financial position and results of
       operations.

   (d) NUCLEAR INSURANCE.  HL&P and the other owners of the South Texas Project
       maintain nuclear property and nuclear liability insurance coverages as
       required by law and periodically review available limits and coverage
       for additional protection.  The owners of the South Texas Project
       currently maintain $500 million in primary property damage insurance
       from American Nuclear Insurers (ANI).  Effective November 15, 1993, the
       maximum amounts of excess property insurance available through the
       insurance industry increased from $2.125 billion to $2.2 billion.  This
       $2.2 billion of excess property insurance coverage includes $800 million
       of excess insurance from ANI and $1.4 billion of excess property
       insurance coverage through participation in the Nuclear Electric
       Insurance Limited (NEIL) II program.  The owners of the South Texas
       Project have approved the purchase of the additional available excess
       property insurance coverage.  Additionally, effective January 1, 1994,
       ANI will be increasing their excess property insurance limits to $850
       million, and the owners of the South Texas Project have also approved
       the purchase of the additional limits at the March 1, 1994 renewal for
       ANI excess property insurance.  Under NEIL II, HL&P and the other owners
       of the South Texas Project are subject to a maximum assessment, in the
       aggregate, of approximately $15.9 million in any one policy year.  The
       application of the proceeds of such property insurance is subject to the
       priorities established by the United States Nuclear Regulatory
       Commission (NRC) regulations relating to the safety of licensed reactors
       and decontamination operations.

       Pursuant to the Price Anderson Act, the maximum liability to the public
       for owners of nuclear power plants, such as the South Texas Project, was
       increased from $7.9 billion to $9.3 billion effective February 18, 1994.
       Owners are required under the Act to insure their liability for nuclear
       incidents and protective evacuations by maintaining the maximum amount
       of financial protection available from private sources and by
       maintaining secondary financial protection through an industry
       retrospective rating plan.  Effective August 20, 1993, the assessment of
       deferred premiums provided by the plan for each nuclear incident has
       increased from $63 million to up to $75.5 million per reactor subject to
       indexing for inflation, a possible 5%

                                      -87-

       surcharge (but no more than $10 million per reactor per incident in
       any one year) and a 3% state premium tax.  HL&P and the other owners of
       the South Texas Project currently maintain the required nuclear
       liability insurance and participate in the industry retrospective rating
       plan.

       There can be no assurance that all potential losses or liabilities will
       be insurable, or that the amount of insurance will be sufficient to
       cover them.  Any substantial losses not covered by insurance would have
       a material effect on HL&P's and the Company's financial condition.

   (e) NUCLEAR DECOMMISSIONING.  HL&P and the other co-owners of the South
       Texas Project are required by the NRC to meet minimum decommissioning
       funding requirements to pay the costs of decommissioning the South Texas
       Project.  Pursuant to the terms of the order of the Utility Commission
       in Docket No. 9850, HL&P is currently funding decommissioning costs for
       the South Texas Project with an independent trustee at an annual amount
       of $6 million.

       As of December 31, 1993, the trustee held approximately $18.7 million
       for decommissioning, for which the asset and liability are reflected on
       the Company's Consolidated and HL&P's Balance Sheets in deferred debits
       and deferred credits, respectively.  HL&P's funding level is estimated
       to provide approximately $146 million in 1989 dollars, an amount which
       currently exceeds the NRC minimum.  However, the South Texas Project
       co-owners have engaged an outside consultant to review the estimated
       decommissioning costs of the South Texas Project which review should be
       completed by the end of 1994.  While changes to present funding levels,
       if any, cannot be estimated at this time, a substantial increase in
       funding may be necessary.  No assurance can be given that the amounts
       held in trust will be adequate to cover the decommissioning costs.

   (f) NRC INSPECTIONS AND OPERATIONS.  Both generating units at the South
       Texas Project were out of service from February 1993 to February 1994,
       when Unit No. 1 was authorized by the NRC to return to service.
       Currently, Unit No. 1 is out of service for repairs to a small steam
       generator leak encountered following the unit's shutdown to repair a
       feedwater control valve.  Those repairs are scheduled for completion by
       mid-March 1994, and no formal NRC approval is required to resume
       operation of Unit No. 1.  Unit No. 2 is currently scheduled to resume
       operation after completion of regulatory reviews, in the spring of 1994.
       HL&P removed the units from service in February 1993 when a problem was
       encountered with certain pumps.  At that time HL&P concluded that the
       units should not resume operation until HL&P had determined the root
       cause of the failure and had briefed the NRC and corrective action had
       been taken.  The NRC formalized that commitment in a Confirmatory Action
       Letter, which confirmed that HL&P would not resume operations until it
       had briefed the NRC on its findings and actions.  Subsequently, that
       Confirmatory Action Letter was supplemented by the NRC to require HL&P,
       prior to resuming operations, to address additional matters which were
       identified during the course of analyzing the issues associated with the
       original pump failure and during various subsequent NRC inspections and
       reviews.

       In June 1993, the NRC announced that the South Texas Project had been
       placed on the NRC's "watch list" of plants with "weaknesses that warrant
       increased NRC attention."  Plants in this category are authorized to
       operate but are subject to close monitoring by the NRC.  The NRC reviews
       the status of plants on this list semi-annually, but HL&P does not
       anticipate that the South Texas Project would be removed from that list
       until there has been a period of operation for both units, and the NRC
       concludes that the concerns which led the NRC to place the South Texas
       Project on that list have been satisfactorily addressed.

                                      -88-

       The NRC's decision to place the South Texas Project on its "watch list"
       followed the June 1993 issuance of a report by its Diagnostic Evaluation
       Team (DET) which conducted a review of the South Texas Project in the
       spring of 1993 and identified a number of areas requiring improvement at
       the South Texas Project.  Conducted infrequently, NRC diagnostic
       evaluations do not evaluate compliance with NRC regulations but are
       broad-based evaluations of overall plant operations and are intended to
       review the strengths and weaknesses of the licensee's performance and to
       identify the root cause of performance problems.

       The DET report found, among other things, weaknesses in maintenance and
       testing, deficiencies in training and in the material condition of some
       equipment, strained staffing levels in operations and several weaknesses
       in engineering support.  The report cited the need to reduce backlogs of
       engineering and maintenance work and to simplify work processes which,
       the DET found, placed excessive burdens on operating and other plant
       personnel.  The report also identified the need to strengthen management
       communications, oversight and teamwork as well as the capability to
       identify and correct the root causes of problems.  The DET also
       expressed concern with regard to the adequacy of resources committed to
       resolving issues at the South Texas Project but noted that many issues
       had already been identified and were being addressed by HL&P.

       In response to the DET report, HL&P presented its plan to address the
       issues raised in that report and began its action program to address
       those concerns. While those programs were being implemented, HL&P also
       initiated additional activities and modifications that were not
       previously scheduled during 1993 but which are designed to eliminate the
       need for some future outages and to enhance operations at the South
       Texas Project.  The NRC conducted additional inspections and reviews of
       HL&P's plans and agreed in February 1994 that HL&P's progress in
       addressing the NRC's concerns had satisfied the issues raised in the
       Confirmatory Action Letter with respect to Unit No. 1.  The NRC
       concurred in HL&P's determination that Unit No. 1 could resume
       operation.  Work is now underway to address the NRC's concerns with
       respect to Unit No. 2, which HL&P anticipates will not require as
       extensive an effort as was required by the NRC for Unit No. 1.  However,
       difficulties encountered in completing actions required on Unit No. 2
       and any additional issues which may be raised in the conduct of those
       activities or in the operation of Unit No. 1 could adversely affect the
       anticipated schedule for resuming operation of Unit No. 2.  During the
       outage, HL&P has not had, and does not anticipate having, difficulty in
       meeting its energy needs.

       During the outage, both fuel and non-fuel expenditures have been higher
       for HL&P than levels originally projected for the year.  HL&P's non-fuel
       expenditures for the South Texas Project during 1993 were approximately
       $115 million greater than originally budgeted levels (of which HL&P's
       share was $35 million) for work undertaken in connection with the DET
       and for other initiatives taken during the year.  It is expected that,
       subsequent to 1993, operation and maintenance costs will continue to be
       higher than previous levels in order to support additional initiatives
       developed in 1993.  Fuel costs also were necessarily higher due to the
       use of higher cost alternative fuels.  However, these increased
       expenditures are expected to be offset to some extent by savings from
       future outages that can now be avoided as a result of activities
       accelerated into 1993 and from overall improvement in operations
       resulting from implementing the programs developed during the outage.
       For a discussion of regulatory treatment related to the outage, see
       Notes 10(f) and 10(g).

       During 1993, the NRC imposed a total of $500,000 in civil penalties (of
       which HL&P's share was $154,000) in connection with violations of NRC
       requirements.
                                      -89-

       In March 1993, a Houston newspaper reported that the NRC had referred to
       the Department of Justice allegations that the employment of three
       former employees and an employee of a contractor to HL&P had been
       terminated or disrupted in retaliation for their having made
       safety-related complaints to the NRC.  Such retaliation, if proved,
       would be contrary to requirements of the Atomic Energy Act and
       regulations promulgated by the NRC.  The NRC has confirmed to HL&P that
       these matters have been referred to the Department of Justice for
       consideration of further action and has notified HL&P that the NRC is
       considering enforcement action against HL&P and one or more HL&P
       employees in connection with one of those cases.  HL&P has been advised
       by counsel that most referrals by the NRC to the Department of Justice
       do not result in prosecutions.  The Company and HL&P strongly believe
       that the facts underlying these events would not support action by the
       Department of Justice against HL&P or any of its personnel; accordingly,
       HL&P intends to defend vigorously against such charges.  HL&P also
       intends to defend vigorously against civil proceedings filed in the
       state court in Matagorda County, Texas, by the complaining employees and
       against administrative proceedings before the Department of Labor and
       the NRC, which, independently of the Department of Justice, could impose
       administrative sanctions if they find violations of the Atomic Energy
       Act or the NRC regulations.  These administrative sanctions may include
       civil penalties in the case of the NRC and, in the case of the
       Department of Labor, ordering reinstatement and back pay and/or imposing
       civil penalties.  Although the Company and HL&P do not believe these
       allegations have merit or will have a material adverse effect on the
       Company or HL&P, neither the Company nor HL&P can predict at this time
       their outcome.

 (10)  UTILITY COMMISSION PROCEEDINGS

       Pursuant to a series of applications filed by HL&P in recent years, the
       Utility Commission has granted HL&P rate increases to reflect in
       electric rates HL&P's substantial investment in new plant construction,
       including the South Texas Project.  Although Utility Commission action
       on those applications has been completed, judicial review of a number of
       the Utility Commission orders is pending.  In Texas, Utility Commission
       orders may be appealed to a District Court in Travis County, and from
       that Court's decision an appeal may be taken to the Court of Appeals for
       the 3rd District at Austin (Austin Court of Appeals).  Discretionary
       review by the Supreme Court of Texas may be sought from decisions of the
       Austin Court of Appeals.  The pending appeals from the Utility
       Commission orders are in various stages.  In the event the courts
       ultimately reverse actions of the Utility Commission in any of these
       proceedings, such matters would be remanded to the Utility Commission
       for action in light of the courts' orders.  Because of the number of
       variables which can affect the ultimate resolution of such matters on
       remand, the Company and HL&P generally are not in a position at this
       time to predict the outcome of the matters on appeal or the ultimate
       effect that adverse action by the courts could have on the Company and
       HL&P.  On remand, the Utility Commission's action could range from
       granting rate relief substantially equal to the rates previously
       approved, to a reduction in the revenues to which HL&P was entitled
       during the time the applicable rates were in effect, which could require
       a refund to customers of amounts collected pursuant to such rates.

       Judicial review has been concluded or currently is pending on the
       final orders of the Utility Commission described below.

   (a) DOCKET NOS. 6765, 6766 AND 5779.  In February 1993, the Austin Court of
       Appeals granted a motion by the Office of Public Utility Counsel (OPC)
       to voluntarily dismiss its appeal of the Utility Commission's order in
       HL&P's 1984 rate case (Docket No. 5779).  In December 1993, the Supreme
       Court of Texas granted a similar motion by OPC to dismiss its appeal of
       the Utility
                                      -90-

       Commission's order in HL&P's 1986 rate case (Docket Nos. 6765 and 6766).
       As a result, appellate review of the Utility Commission's orders in
       those dockets has been concluded, and the orders have been affirmed.

   (b) DOCKET NO. 8425.  In October 1992, a District Court in Travis County,
       Texas affirmed the Utility Commission's order in HL&P's 1988 rate case
       (Docket No. 8425).  An appeal to the Austin Court of Appeals is pending.
       In its final order in that docket, the Utility Commission granted HL&P a
       $227 million increase in base revenues, allowed a 12.92% return on
       common equity, authorized a qualified phase-in plan for Unit No. 1 of
       the South Texas Project (including approximately 72% of HL&P's
       investment in Unit No. 1 of the South Texas Project in rate base) and
       authorized HL&P to use deferred accounting for Unit No. 2 of the South
       Texas Project.  Rates substantially corresponding to the increase
       granted were implemented by HL&P in June 1989 and remained in effect
       until May 1991.

       In the appeal of the Utility Commission's order, certain parties have
       challenged the Utility Commission's decision regarding deferred
       accounting, treatment of federal income tax expense and certain other
       matters.  A recent decision of the Austin Court of Appeals, in an appeal
       involving another utility (and to which HL&P was not a party), adopted
       some of the arguments being advanced by parties challenging the Utility
       Commission's order in Docket No. 8425.  In that case, Public Utility
       Commission of Texas vs. GTE-SW, the Austin Court of Appeals ruled that
       when a utility pays federal income taxes as part of a consolidated
       group, the utility's ratepayers are entitled to a fair share of the tax
       savings actually realized, which can include savings resulting from
       unregulated activities.  The Texas Supreme Court has agreed to hear an
       appeal of that decision, but on points not involving the federal income
       tax issues, though tax issues could be decided in such opinion.

       In its final order in Docket No. 8425, the Utility Commission did not
       reduce HL&P's tax expense by any of the tax savings resulting from the
       Company's filing of a consolidated tax return.  Although the GTE
       decision was not legally dispositive of the tax issues presented in the
       appeal of Docket No. 8425, it is possible that the Austin Court of
       Appeals could utilize the reasoning in GTE in addressing similar issues
       in the appeal of Docket No. 8425.  However, in February 1993 the Austin
       Court of Appeals, considering an appeal involving another telephone
       utility, upheld Utility Commission findings that the tax expense for the
       utility included the utility's fair share of the tax savings resulting
       from a consolidated tax return, even though the utility's fair share of
       the tax savings was determined to be zero.  HL&P believes that the
       Utility Commission findings in Docket No. 8425 and in Docket No. 9850
       (see Note 10(c)) should be upheld on the same principle (i.e., that the
       Utility Commission determined that the fair share of tax savings to be
       allocated to ratepayers is determined to be zero).  However, no
       assurance can be made as to the ultimate outcome of this matter.

       The Utility Commission's order in Docket No. 8425 may be affected also
       by the ultimate resolution of appeals concerning the Utility
       Commission's treatment of deferred accounting.  For a discussion of
       appeals of the Utility Commission's orders on deferred accounting, see
       Notes 10(e) and 11.

   (c) DOCKET NO. 9850.  In August 1992, a district court in Travis County
       affirmed the Utility Commission's final order in HL&P's 1991 rate case
       (Docket No. 9850).  That decision was appealed by certain parties to the
       Austin Court of Appeals, raising issues concerning the Utility
       Commission's approval of a non-unanimous settlement in that docket, the
       Utility Commission's calculation of federal income tax expense and the
       allowance of deferred accounting reflected in the settlement.  In August
       1993, the Austin Court of Appeals
                                      -91-

       affirmed on procedural grounds the ruling by the Travis County District
       Court, and applications for writ of error were filed with the Supreme
       Court of Texas by one of the other parties to the proceeding.  The
       Supreme Court has not yet ruled on these applications.  In Docket No.
       9850, the Utility Commission approved a settlement agreement reached
       with most parties.  That settlement agreement provided for a $313
       million increase in HL&P's base rates, termination of deferrals granted
       with respect to Unit No. 2 of the South Texas Project and of the
       qualified phase-in plan deferrals granted with respect to Unit No. 1 of
       the South Texas Project, and recovery of deferred plant costs.  The
       settlement authorized a 12.55% return on common equity for HL&P, and
       HL&P agreed not to request additional increases in base rates that would
       be implemented prior to May 1, 1993.  Rates contemplated by that
       settlement agreement were implemented in May 1991 and remain in effect.

       The Utility Commission's order in Docket No. 9850 found that HL&P would
       have been entitled to more rate relief than the $313 million agreed to
       in the settlement, but certain recent actions of the Austin Court of
       Appeals could, if ultimately upheld and applied to the appeal of Docket
       No. 9850, require a remand of that settlement to the Utility Commission.
       HL&P believes that the amount which the Utility Commission found HL&P
       was entitled to would exceed any disallowance that would have been
       required under the Austin Court of Appeals' ruling regarding deferred
       accounting (see Notes 10(e) and 11) or any adverse effect on the
       calculation of tax expense if the court's ruling in the GTE decision
       were applied to that settlement (see Note 10(b) above).  However, the
       amount of rate relief to which the Utility Commission found HL&P to be
       entitled in excess of the $313 million agreed to in the settlement may
       not be sufficient if the reasoning in both the GTE decision and the
       ruling on deferred accounting were to be applied to the settlement
       agreement in Docket No.  9850.  Although HL&P believes that it should be
       entitled to demonstrate entitlement to rate relief equal to that agreed
       to in the stipulation in Docket No. 9850, HL&P cannot rule out the
       possibility that a remand and reopening of that settlement would be
       required if decisions unfavorable to HL&P are rendered on both the
       deferred accounting treatment and the calculation of tax expense for
       ratemaking purposes.

  (d)  DOCKET NO. 6668.  In June 1990, the Utility Commission issued the final
       order in Docket No. 6668, the Utility Commission's inquiry into the
       prudence of the planning, management and construction of the South Texas
       Project.  The Utility Commission's findings and order in Docket No. 6668
       were incorporated in Docket No. 8425, HL&P's 1988 general rate case.
       Pursuant to the findings in Docket No. 6668, the Utility Commission
       found imprudent $375.5 million out of HL&P's $2.8 billion investment in
       the two units of the South Texas Project.

       The Utility Commission's findings did not reflect $207 million in
       benefits received in a settlement of litigation with the former
       architect-engineer of the South Texas Project or the effects of federal
       income taxes, investment tax credits or certain deferrals.  In addition,
       accounting standards require that the equity portion of AFUDC accrued
       for regulatory purposes under deferred accounting orders be utilized to
       determine the cost disallowance for financial reporting purposes.  After
       taking all of these items into account, HL&P recorded an after-tax
       charge of $15 million in 1990 and continued to reduce such loss with the
       equity portion of deferrals in 1991 related to Unit No. 2 of the South
       Texas Project.  The findings in Docket No. 6668 represent the Utility
       Commission's final determination regarding the prudence of expenditures
       associated with the planning and construction of the South Texas
       Project.  Unless the order is modified or reversed on appeal, HL&P will
       be precluded from recovering in rate proceedings the amount found
       imprudent by the Utility Commission.

                                      -92-

       Appeals by HL&P and other parties of the Utility Commission's order in
       Docket No. 6668 were dismissed by a District Court in Travis County in
       May 1991.  However, in December 1992 the Austin Court of Appeals
       reversed the District Court's dismissals on procedural grounds.  HL&P
       and other parties have filed applications for writ of error with the
       Supreme Court of Texas concerning the order by the Austin Court of
       Appeals, but unless the order is modified on further review, HL&P
       anticipates that the appeals of the parties will be reinstated and that
       the merits of the issues raised in those appeals of Docket No. 6668 will
       be considered by the District Court, with the possibility of subsequent
       judicial review once the District Court has acted on those appeals.  In
       addition, separate appeals are pending from Utility Commission orders in
       Dockets Nos. 8425 and 9850, in which the findings of the order in Docket
       No. 6668 are reflected in rates.  See Notes 10(b) and 10(c).

   (e) DOCKET NOS. 8230 AND 9010.  Deferred accounting treatment for Unit No. 1
       of the South Texas Project was authorized by the Utility Commission in
       Docket No. 8230 and was extended in Docket No. 9010.  Similar deferred
       accounting treatment with respect to Unit No. 2 of the South Texas
       Project was authorized in Docket No. 8425.  For a discussion of the
       deferred accounting treatment granted, see Note 11.  In September 1992,
       the Austin Court of Appeals, in considering the appeal of the Utility
       Commission's final order in Docket Nos. 8230 and 9010, upheld the
       Utility Commission's action in granting deferred accounting treatment
       for operation and maintenance expenses, but rejected such treatment for
       the carrying costs associated with the investment in Unit No. 1 of the
       South Texas Project.  That ruling followed the Austin Court of Appeals
       decision rendered in August 1992, on a motion for rehearing, involving
       another utility which had been granted similar deferred accounting
       treatment for another nuclear plant.  In its August decision, the court
       ruled that Texas law did not permit the Utility Commission to allow the
       utility to place the carrying costs associated with the investment in
       the utility's rate base, though the court observed that the Utility
       Commission could allow amortization of such costs.

       The Supreme Court of Texas has granted applications for writ of error
       with respect to the Austin Court of Appeals decision regarding Docket
       Nos. 8230 and 9010. The Supreme Court of Texas has also granted
       applications for writ of error on three other decisions by the Austin
       Court of Appeals regarding deferred accounting treatment granted to
       other utilities by the Utility Commission.  The Supreme Court heard oral
       arguments on these appeals on September 13, 1993.  The court has not yet
       ruled.

  (f)  DOCKET NO. 12065.  HL&P is not currently seeking authority to change its
       base rates for electric service, but the Utility Commission has
       authority to initiate a rate proceeding pursuant to Section 42 of the
       Public Utility Regulatory Policy Act (PURA) to determine whether
       existing rates are unjust or unreasonable.  In 1993, the Utility
       Commission referred to an administrative law judge (ALJ) the complaint
       of a former employee of HL&P seeking to initiate such a proceeding.

       On February 23, 1994, the ALJ concluded that a Section 42 proceeding
       should be conducted and that HL&P should file full information,
       testimony and schedules justifying its rates.  The ALJ acknowledged that
       the decision was a close one, and is subject to review by the Utility
       Commission.  However, he concluded that information concerning HL&P's
       financial results as of December 1992 indicated that HL&P's adjusted
       revenues could be approximately $62 million (or 2.33% of its adjusted
       base revenues) more than might be authorized in a current rate
       proceeding.  The ALJ's conclusion was based on various accounting
       considerations, including use of a different treatment of federal income
       tax expense than the method utilized in HL&P's last rate case.  The ALJ
       also found that there could be a link between the 1993 outage at the

                                      -93-

       South Texas Project, the NRC's actions with respect to the South Texas
       Project and possible mismanagement by HL&P, which in turn could result
       in a reduction of HL&P's authorized rate of return as a penalty for
       imprudent management.

       HL&P and the Company believe that the examiner's analysis is incorrect,
       that the South Texas Project has not been imprudently managed, and that
       ordering a Section 42 proceeding at this time is unwarranted and
       unnecessarily expensive and burdensome.  HL&P has appealed
       the ALJ's decision to the Utility Commission.

       If HL&P ultimately is required to respond to a Section 42 inquiry, it
       will assert that it remains entitled to rates at least at the levels
       currently authorized.  However, there can be no assurance as to the
       outcome of a Section 42 proceeding if it is ultimately authorized, and
       HL&P's rates could be reduced following a hearing.  HL&P believes that
       any reduction in base rates as a result of a Section 42 inquiry would
       take effect prospectively.

       HL&P is also a defendant in a lawsuit filed in a Fort Bend County,
       Texas, district court by the same former HL&P employee who originally
       initiated the Utility Commission complaint concerning HL&P's rates.  In
       that suit, Pace and Scott v. HL&P, the former employee contends that
       HL&P is currently charging illegal rates since the rates authorized by
       the Utility Commission do not allocate to ratepayers tax benefits
       accruing to the Company and to HL&P by virtue of the fact that HL&P's
       federal income taxes are paid as part of a consolidated group.  HL&P is
       seeking dismissal of that suit because in Texas exclusive jurisdiction
       to set electric utility rates is vested in municipalities and in the
       Utility Commission, and the courts have no jurisdiction to set such
       rates or to set aside authorized rates except through judicial appeals
       of Utility Commission orders in the manner prescribed in applicable law.
       Although substantial damages have been claimed by the plaintiffs in that
       litigation, HL&P and the Company consider this litigation to be wholly
       without merit, and do not presently believe that it will have a material
       adverse effect on the Company's or HL&P's results of operations, though
       no assurances can be given as to its ultimate outcome at this time.

   (g) FUEL RECONCILIATION.  HL&P recovers fuel costs incurred in electric
       generation through a fixed fuel factor that is set by the Utility
       Commission.  The difference between fuel revenues billed pursuant to
       such factor and fuel expense incurred is recorded as an addition to or a
       reduction of revenues, with a corresponding entry to under- or
       over-recovered fuel, as appropriate. Amounts collected pursuant to the
       fixed fuel factor must be reconciled periodically by the Utility
       Commission against actual, reasonable costs as determined by the Utility
       Commission.  Any fuel costs which the Utility Commission determines are
       unreasonable in a fuel reconciliation proceeding would not be
       recoverable from customers, and a charge against earnings would result.
       Under Utility Commission rules, HL&P is required to file an application
       to reconcile those costs in 1994.  Such a filing would also be required
       in conjunction with any rate proceeding that may be filed, such as the
       Section 42 proceeding described in Note 10(f).

       Unless filed earlier in conjunction with a rate proceeding, HL&P
       currently anticipates filing its fuel reconciliation application in the
       fourth quarter of 1994 in accordance with a  schedule proposed by the
       Utility Commission staff.  If that schedule is approved by the Utility
       Commission, HL&P anticipates that fuel costs through some time in 1994
       will be submitted for reconciliation.  No hearing would be anticipated
       in that reconciliation proceeding before 1995.

       The schedule for a fuel reconciliation proceeding could be affected by
       the institution of a prudence inquiry concerning the outage at the South
       Texas Project.  The Utility Commission staff has indicated a desire to
       conduct an inquiry into the prudence of HL&P's management prior to and
       during the outage, but it is currently unknown what action the Utility
       Commission will take on that request or what the nature and scope of any
       such proceeding
                                      -94-

       would be.  Such an inquiry could also be conducted in connection with a
       rate proceeding under Section 42 of PURA if one is instituted by the
       Utility Commission.

       Through the end of 1993, HL&P had recovered through the fuel factor
       approximately $115 million (including interest) less than the amounts
       expended for fuel, a significant portion of which under recovery
       occurred in 1993 during the outage at the South Texas Project.  In any
       review of costs incurred during the period of the 1993 outage at the
       South Texas Project, it is anticipated that other parties will contend
       that a portion of fuel costs incurred should be attributed to imprudence
       on the part of HL&P and thus should be disallowed as unreasonable, with
       recovery from rate payers denied.  Those amounts could be substantial.
       HL&P intends to defend vigorously against any allegation that its
       actions have been imprudent or that any portion of its costs incurred
       should be judged to be unreasonable, but no prediction can be made as to
       the ultimate outcome of such a proceeding.

 (11)  DEFERRED PLANT COSTS

       Deferred plant costs were authorized for the South Texas Project by the
       Utility Commission in two contexts.  In the first context, or "deferred
       accounting," the Utility Commission orders permitted HL&P, for
       regulatory purposes, to continue to accrue carrying costs in the form of
       AFUDC (at a 10% rate) on its investment in the two units of the South
       Texas Project until costs of such units were reflected in rates (which
       was July 1990 for approximately 72% of Unit No. 1, and May 1991 for the
       remainder of Unit No. 1 and 100% of Unit No. 2) and to defer and
       capitalize depreciation, operation and maintenance, insurance and tax
       expenses associated with such units during the deferral period.
       Accounting standards do not permit the accrual of the equity portion of
       AFUDC for financial reporting purposes under these circumstances.
       However, in accordance with accounting standards, such amounts were
       utilized to determine the amount of plant cost disallowance for
       financial reporting purposes.

       The deferred expenses and the debt portion of the carrying costs
       associated with the South Texas Project are included on the Company's
       Statements of Consolidated Income in deferred expenses and deferred
       carrying costs, respectively.

       Beginning with the June 1990 order in Docket No. 8425, deferrals were
       permitted in a second context, a "qualified phase-in plan" for Unit No.
       1 of the South Texas Project.  Accounting standards require allowable
       costs deferred for future recovery under a qualified phase-in plan to be
       capitalized as a deferred charge if certain criteria are met.  The
       qualified phase-in plan as approved by the Utility Commission meets
       these criteria.

       During the period June 1990 through May 15, 1991, HL&P deferred
       depreciation and property taxes related to the 28% of its investment in
       Unit No. 1 of the South Texas Project not reflected in the Docket No.
       8425 rates and recorded a deferred return on that investment as part of
       the qualified phase-in plan.  Deferred return represents the financing
       costs (equity and debt) associated with the qualified phase-in plan. The
       deferred expenses and deferred return related to the qualified phase-in
       plan are included on the Company's Statements of Consolidated Income and
       HL&P's Statements of Income in deferred expenses and deferred return
       under phase-in plan, respectively.  Under the phase-in plan, these
       accumulated deferrals will be recoverable within ten years of the June
       1990 order.
                                      -95-

        On May 16, 1991, HL&P implemented under bond, in Docket No. 9850, a
       $313 million base rate increase consistent with the terms of the
       settlement. Accordingly, HL&P ceased all cost deferrals related to the
       South Texas Project and began the recovery of such amounts.  These
       deferrals are being amortized on a straight-line basis as allowed by the
       final order in Docket No. 9850.  The amortization of these deferrals
       totaled $25.8 million for both 1993 and 1992 and $16.1 million in 1991,
       and is included on the Company's Statements of Consolidated Income and
       HL&P's Statements of Income in depreciation and amortization expense.
       See also Notes 10(b), 10(c) and 10(e).

       The following table shows the original balance of the deferrals and the
       unamortized balance at December 31, 1993.
                                                                  Balance at
                                              Original           December 31,
                                              Balance               1993
                                             ---------           -----------
                                                 (Thousands of Dollars)
       Deferred Accounting: (a)
           Deferred Expenses  . . . . .      $ 250,151           $ 233,341
           Deferred Carrying Costs on
                 Plant Investment . . .        399,972             373,094
                                             ---------           ---------
              Total . . . . . . . . . .        650,123             606,435

       Qualified Phase-In Plan: (b)   .         82,254              58,264
                                             ---------           ---------

       Total Deferred Plant Cost  . . .      $ 732,377           $ 664,699
                                             =========           =========
       __________
       (a)    Amortized over the estimated depreciable life of the South Texas
              Project.

       (b)    Amortized over nine years beginning in May 1991.

       As of December 31, 1993, HL&P has recorded deferred income taxes of
       $200.9 million with respect to deferred accounting and $14.5 million
       with respect to the deferrals associated with the qualified phase-in
       plan.

(12)   MALAKOFF ELECTRIC GENERATING STATION

       The scheduled in-service dates for the Malakoff Electric Generating
       Station (Malakoff) units were postponed during the 1980's as
       expectations of continued strong load growth were tempered.  These units
       have been indefinitely deferred due to the availability of other cost
       effective resource options.  In 1987, all developmental work was stopped
       and AFUDC accruals ceased.

       Due to the indefinite postponement of the in-service date for Malakoff,
       the engineering design work is no longer considered viable.  The costs
       associated with this engineering design work are currently included in
       rate base and are earning a return per the Utility Commission's final
       order in Docket No. 8425.  Pursuant to HL&P's determination that such
       costs will have no future value, $84.1 million was reclassified from
       plant held for future use to recoverable project costs as of December
       31, 1992.  An additional $7.0 million was reclassified to recoverable
       project costs in 1993.  Amortization of these amounts began in 1993.
       Amortization amounts will correspond to the amounts being earned as a
       result of the inclusion of such costs in rate base.  The Utility
       Commission's action in allowing treatment of those costs as plant held
       for future use has been challenged in the pending appeal of the Utility

                                      -96-

       Commission's final order in Docket No. 8425.  Also, recovery of such
       Malakoff costs may be addressed if rate proceedings are initiated such
       as that proposed under Section 42 of PURA. See Notes 10(b) and 10(f) for
       a discussion of these respective proceedings.

       In June 1990, HL&P purchased from its then fuel supply affiliate,
       Utility Fuels, all of Utility Fuels' interest in the lignite reserves
       and lignite handling facilities for Malakoff.  The purchase price was
       $138.2 million, which represented the net book value of Utility Fuels'
       investment in such reserves and facilities.  As part of the June 1990
       rate order (Docket No. 8425), the Utility Commission ordered that issues
       related to the prudence of the amounts invested in the lignite reserves
       be considered in HL&P's next general rate case which was filed in
       November 1990 (Docket No. 9850).  However, under the October 1991
       Utility Commission order in Docket No. 9850, this determination was
       postponed to a subsequent docket.

       HL&P's remaining investment in Malakoff through December 31, 1993 of
       $167 million, consisting primarily of lignite reserves and land, is
       included on the Company's Consolidated and HL&P's Balance Sheets in
       plant held for future use.  For the 1994-1996 period, HL&P anticipates
       $14 million of expenditures relating to lignite reserves, primarily to
       keep lignite leases and other related agreements in effect.

                                    -97-