EXHIBIT 99(a)
                HOUSTON INDUSTRIES INCORPORATED AND SUBSIDIARIES

                   NOTES TO CONSOLIDATED FINANCIAL STATEMENTS

                   FOR THE THREE YEARS ENDED DECEMBER 31, 1994


 (1)SUMMARY OF SIGNIFICANT ACCOUNTING POLICIES


    (f)   DEFERRED PLANT COSTS. The Utility Commission authorized deferred
          accounting treatment for certain costs related to the South Texas
          Project Electric Generating Station (South Texas Project) in two
          contexts. The first was "deferred accounting" where HL&P was permitted
          to continue to accrue carrying costs in the form of AFUDC and defer
          and capitalize depreciation and other operating costs on its
          investment in the South Texas Project until such costs were reflected
          in rates. The second was the "qualified phase-in plan" where HL&P was
          permitted to capitalize as deferred charges allowable costs, including
          return, deferred for future recovery

                                      -39-

          under the approved plan. The accumulated deferrals for "deferred
          accounting" and "qualified phase-in plan" are being recovered over the
          estimated depreciable life of the South Texas Project and within the
          ten year phase-in period, respectively. The amortization of these
          deferrals totaled $25.8 million for each of the years 1994, 1993, and
          1992 and is included on the Company's Statements of Consolidated
          Income and HL&P's Statements of Income in depreciation and
          amortization expense. Under the terms of the settlement agreement
          regarding the issues raised in Docket Nos. 12065 and 13126 (Proposed
          Settlement), see Note 3, the South Texas Project deferrals will
          continue to be amortized using the schedules discussed above.

                                      -40-

(2) JOINTLY-OWNED NUCLEAR PLANT

    (a)   HL&P INVESTMENT. HL&P is the project manager (and one of four
          co-owners) of the South Texas Project, which consists of two 1,250
          megawatt nuclear generating units. HL&P has a 30.8 percent interest in
          the project and bears a corresponding share of capital and operating
          costs associated with the project. As of December 31, 1994, HL&P's
          investments (net of accumulated depreciation and amortization) in the
          South Texas Project and in nuclear fuel, including AFUDC, were $2.1
          billion and $99 million, respectively.

    (b)   UNITED STATES NUCLEAR REGULATORY COMMISSION (NRC) INSPECTIONS AND
          OPERATIONS. Both generating units at the South Texas Project were out
          of service from February 1993 to February 1994, when Unit No. 1 was
          returned to service. Unit No. 2 was returned to service in May 1994.
          HL&P removed the units from service in February 1993 when a problem
          was encountered with certain of the units' auxiliary feedwater pumps.

          In February 1995, the NRC removed the South Texas Project from its
          "watch list" of plants with weaknesses that warranted increased NRC
          attention. The NRC placed the South Texas Project on the "watch list"
          in June 1993, following the issuance of a report by an NRC Diagnostic
          Evaluation Team (DET) which conducted a review of the South Texas
          Project operations.

          Certain current and former employees of HL&P or contractors of HL&P
          have asserted claims that their employment was terminated or disrupted
          in retaliation for their having made safety-related complaints to the
          NRC. Civil proceedings by the complaining personnel and administrative
          proceedings by the Department of Labor remain pending against HL&P,
          and the NRC has jurisdiction to take enforcement action against HL&P
          and/or individual employees with respect to these matters. Based on
          its own internal investigation, in October 1994 the NRC issued a
          notice of violation and proposed a $100,000 civil penalty against HL&P
          in one such case in which HL&P had terminated the site access of a
          former contractor employee. In that action, the NRC also requested
          information relating to possible further enforcement action in this
          matter against two HL&P managers involved in such termination. HL&P
          strongly disagrees with the NRC's conclusions, and has requested the
          NRC to give further consideration of its notice. In February 1995, the
          NRC conducted an enforcement conference with respect to that matter,
          but no result has been received.

          HL&P has provided documents and other assistance to a subcommittee of
          the U. S. House of Representatives (Subcommittee) that is conducting
          an inquiry related to the South Texas Project. Although the precise
          focus and timing of the inquiry has not been identified by the
          Subcommittee, it is anticipated that the Subcommittee will inquire
          into matters related to HL&P's handling of employee concerns and to
          issues related to the NRC's 1993 DET review of the South Texas
          Project. In connection with that inquiry, HL&P has been advised that
          the U. S. General Accounting Office (GAO) is conducting a review of
          the NRC's inspection process as it relates to the South Texas Project
          and other plants, and HL&P is cooperating with the GAO in its
          investigation and with the NRC in a similar review it has initiated.
          While no prediction can
                                      -41-

          be made at this time as to the ultimate outcome of these matters, the
          Company and HL&P do not believe that they will have a material adverse
          effect on the Company's or HL&P's financial condition or results of
          operations.

    (c)   LITIGATION WITH CO-OWNERS OF THE SOUTH TEXAS PROJECT. In February
          1994, the City of Austin (Austin), one of the four co-owners of the
          South Texas Project, filed suit (Austin II Litigation) against HL&P.
          That suit is pending in the 152nd District Court for Harris County,
          Texas, which has set a trial date for October 1995. Austin alleges
          that the outages at the South Texas Project from early 1993 to early
          1994 were due to HL&P's failure to perform obligations it owed to
          Austin under the Participation Agreement among the four co-owners of
          the South Texas Project (Participation Agreement). Austin also asserts
          that HL&P breached certain undertakings voluntarily assumed by HL&P
          under the terms and conditions of the Operating Licenses and Technical
          Specifications relating to the South Texas Project. Austin claims that
          such failures have caused Austin damages of at least $125 million due
          to the incurrence of increased operating and maintenance costs, the
          cost of replacement power and lost profits on wholesale transactions
          that did not occur. In May 1994, the City of San Antonio (San
          Antonio), another co-owner of the South Texas Project, intervened in
          the litigation filed by Austin against HL&P and asserted claims
          similar to those asserted by Austin. San Antonio has not identified
          the amount of damages it intends to seek from HL&P. HL&P is contesting
          San Antonio's intervention and has called for arbitration of San
          Antonio's claim under the arbitration provisions of the Participation
          Agreement. The trial court has denied HL&P's requests, but review of
          these decisions is currently pending before the 1st Court of Appeals
          in Houston.

          In a previous lawsuit (Austin I Litigation) filed in 1983 against the
          Company and HL&P, Austin alleged that it had been fraudulently induced
          to participate in the South Texas Project and that HL&P had failed to
          perform properly its duties as project manager. In May 1993, the
          courts entered a judgement in favor of the Company and HL&P,
          concluding, among other things, that the Participation Agreement did
          not impose on HL&P a duty to exercise reasonable skill and care as
          project manager. During the course of the Austin I Litigation, San
          Antonio and Central Power and Light Company (CPL), a subsidiary of
          Central and South West Corporation, two of the co-owners in the South
          Texas Project, also asserted claims for unspecified damages against
          HL&P as project manager of the South Texas Project, alleging HL&P
          breached its duties and obligations. San Antonio and CPL requested
          arbitration of their claims under the Participation Agreement. In
          1992, the Company and HL&P entered into a settlement agreement with
          CPL (CPL Settlement) providing for CPL's withdrawal of its demand for
          arbitration. San Antonio's claims for arbitration remain pending.
          Under the Participation Agreement, San Antonio's arbitration claims
          will be heard by a panel of five arbitrators consisting of four
          arbitrators named by each co-owner and a fifth arbitrator selected by
          the four appointed arbitrators.

          Although the CPL Settlement did not directly affect San Antonio's
          pending demand for arbitration, HL&P and CPL reached certain
          understandings in such agreement which contemplated that: (i) CPL's
          previously appointed arbitrator would be replaced by CPL; (ii)
          arbitrators approved by CPL or HL&P in any future arbitrations would
          be mutually acceptable to HL&P and CPL; and (iii) HL&P and CPL would
          resolve any future disputes between them concerning the South Texas
          Project without resorting to the arbitration provision of the

                                      -42-

          Participation Agreement. Austin and San Antonio have asserted in the
          pending Austin II Litigation that such understandings have rendered
          the arbitration provisions of the Participation Agreement void and
          that neither Austin nor San Antonio should be required to participate
          in or be bound by such proceedings.

          Although HL&P and the Company do not believe there is merit to either
          Austin's or San Antonio's claims and have opposed San Antonio's
          intervention in the Austin II Litigation, there can be no assurance as
          to the ultimate outcome of these matters.

    (d)   NUCLEAR INSURANCE. HL&P and the other owners of the South Texas
          Project maintain nuclear property and nuclear liability insurance
          coverage as required by law and periodically review available limits
          and coverage for additional protection. The owners of the South Texas
          Project currently maintain the maximum amount of property damage
          insurance currently available through the insurance industry,
          consisting of $500 million in primary property damage insurance and
          excess property insurance in the amount of $2.25 billion. Under the
          excess property insurance which became effective on March 1, 1995 and
          under portions of the excess property insurance coverage in effect
          prior to March 1, 1995, HL&P and the other owners of the South Texas
          Project are subject to assessments, the maximum aggregate assessment
          under current policies being $26.9 million during any one policy year.
          The application of the proceeds of such property insurance is subject
          to the priorities established by the NRC regulations relating to the
          safety of licensed reactors and decontamination operations.

          Pursuant to the Price Anderson Act (Act), the maximum liability to the
          public for owners of nuclear power plants, such as the South Texas
          Project, was decreased from $9.0 billion to $8.92 billion effective in
          November 1994. Owners are required under the Act to insure their
          liability for nuclear incidents and protective evacuations by
          maintaining the maximum amount of financial protection available from
          private sources and by maintaining secondary financial protection
          through an industry retrospective rating plan. The assessment of
          deferred premiums provided by the plan for each nuclear incident is up
          to $75.5 million per reactor subject to indexing for inflation, a
          possible 5 percent surcharge (but no more than $10 million per reactor
          per incident in any one year) and a 3 percent state premium tax. HL&P
          and the other owners of the South Texas Project currently maintain the
          required nuclear liability insurance and participate in the industry
          retrospective rating plan.

          There can be no assurance that all potential losses or liabilities
          will be insurable, or that the amount of insurance will be sufficient
          to cover them. Any substantial losses not covered by insurance would
          have a material effect on HL&P's and the Company's financial
          condition.

    (e)   NUCLEAR DECOMMISSIONING. HL&P and the other co-owners of the South
          Texas Project are required by the NRC to meet minimum decommissioning
          funding requirements to pay the costs of decommissioning the South
          Texas Project. Pursuant to the terms of the order of the Utility
          Commission in Docket No. 9850, HL&P is currently funding
          decommissioning costs for the South Texas Project with an independent
          trustee at an annual amount of $6 million, which is recorded in
          depreciation and amortization expense. HL&P's funding level is
          estimated to provide approximately $146 million, in 1989 dollars, an
          amount which exceeds the current NRC minimum.

                                      -43-

          The Company adopted SFAS No. 115, "Accounting for Certain Investments
          in Debt and Equity Securities," effective January 1, 1994. At December
          31, 1994, the securities held in the Company's nuclear decommissioning
          trust totaling $25.1 million (reflected on the Company's Consolidated
          and HL&P's Balance Sheets in deferred debits and deferred credits) are
          classified as available for sale. Such securities are reported on the
          balance sheets at fair value, which at December 31, 1994 approximates
          cost, and any unrealized gains or losses will be reported as a
          separate component of common stock equity. Earnings, net of taxes and
          administrative costs, are reinvested in the funds.

          In May 1994, an outside consultant estimated HL&P's portion of
          decommissioning costs to be approximately $318 million, in 1994
          dollars. The consultant's calculation of decommissioning costs for
          financial planning purposes used the DECON methodology (prompt
          removal/dismantling), one of the three alternatives acceptable to the
          NRC, and assumed deactivation of Unit Nos. 1 and 2 upon the expiration
          of their 40 year operating licenses. Under the terms of the Proposed
          Settlement, HL&P would increase funding of decommissioning costs to an
          annual amount of approximately $14.8 million consistent with such
          study. While the current and projected funding levels presently exceed
          minimum NRC requirements, no assurance can be given that the amounts
          held in trust will be adequate to cover the actual decommissioning
          costs of the South Texas Project or the assumptions used in estimating
          decommissioning costs will ultimately prove to be correct.

(3) RATE REVIEW, FUEL RECONCILIATION AND OTHER PROCEEDINGS

          In February 1994, the Utility Commission initiated a proceeding
          (Docket No. 12065) to determine whether HL&P's existing rates are just
          and reasonable. Subsequently, the scope of the docket was expanded to
          include reconciliation of HL&P's fuel costs from April 1, 1990 to July
          31, 1994. The Utility Commission also initiated a separate proceeding
          (Docket No. 13126) to review issues regarding the prudence of
          operation of the South Texas Project from the date of commercial
          operation through the present. That review would encompass the outage
          at the South Texas Project during 1993 through 1994.

          Hearings began in Docket No. 12065 in January 1995, and the Utility
          Commission has retained a consultant to review the South Texas Project
          for the purpose of providing testimony in Docket No. 13126 regarding
          the prudence of HL&P's management of operation of the South Texas
          Project. In February 1995, all major parties to these proceedings
          signed the Proposed Settlement resolving the issues with respect to
          HL&P, including the prudence issues related to operation of the South
          Texas Project. Approval of the Proposed Settlement by the Utility
          Commission will be required. To that end, the parties have established
          procedural dates for a hearing on issues raised by the parties who are
          opposed to the Proposed Settlement. A decision by the Utility
          Commission on the Proposed Settlement is not anticipated before early
          summer.

          Under the Proposed Settlement, HL&P's base rates would be reduced by
          approximately $62 million per year, effective retroactively to January
          1, 1995, and rates would be frozen for three years, subject to certain
          conditions. Under the Proposed Settlement, HL&P would amortize its
          remaining investment of $218 million in the cancelled Malakoff plant
          over a period not to exceed
                                      -44-

          seven years. HL&P also would increase its decommissioning expense for
          the South Texas Project by $9 million per year.

          Under the Proposed Settlement, approximately $70 million of fuel
          expenditures and related interest incurred by HL&P during the fuel
          reconciliation period would not be recoverable from ratepayers. This
          $70 million was recorded as a one-time, pre-tax charge to reconcilable
          fuel revenues to reflect the anticipation of approval of the Proposed
          Settlement. HL&P also would establish a new fuel factor approximately
          17 percent below that currently in effect and would refund to
          customers the balance in its fuel over-recovery account, estimated to
          be approximately $180 million after giving effect to the amounts not
          recoverable from ratepayers.

          HL&P recovers fuel costs incurred in electric generation through a
          fixed fuel factor that is set by the Utility Commission. The
          difference between fuel revenues billed pursuant to such factor and
          fuel expense incurred is recorded as an addition to or a reduction of
          revenue, with a corresponding entry to under- or over-recovered fuel,
          as appropriate. Amounts collected pursuant to the fixed fuel factor
          must be reconciled periodically against actual, reasonable costs as
          determined by the Utility Commission. Currently, HL&P has an
          over-recovery fuel account balance that will be refunded pursuant to
          the Proposed Settlement.

          In the event that the Proposed Settlement is not approved by the
          Utility Commission, including issues related to the South Texas
          Project, Docket No. 12065 will be remanded to an Administrative Law
          Judge (ALJ) to resume detailed hearings in this docket. Prior to
          reaching agreement on the terms of the Proposed Settlement, HL&P
          argued that its existing rates were just and reasonable and should not
          be reduced. Other parties argued that rate decreases in annual amounts
          ranging from $26 million to $173 million were required and that
          additional decreases might be justified following an examination of
          the prudence of the management of the South Texas Project and the
          costs incurred in connection with the outages at the South Texas
          Project. Testimony filed by the Utility Commission staff included a
          recommendation to remove from rate base $515 million of HL&P's
          investment in the South Texas Project to reflect the staff's view that
          such investment was not fully "used and useful" in providing service,
          a position HL&P vigorously disputes.

          In the event the Proposed Settlement is not approved by the Utility
          Commission, the fuel reconciliation issues in Docket Nos. 12065 and
          13126 would be remanded to an ALJ for additional proceedings. A major
          issue in Docket No. 13126 will be whether the incremental fuel costs
          incurred as a result of outages at the South Texas Project represent
          reasonable costs. HL&P filed testimony in Docket No. 13126, which
          testimony concluded that the outages at the South Texas Project did
          not result from imprudent management. HL&P also filed testimony
          analyzing the extent to which regulatory issues extended the outages.
          In that testimony an outside consultant retained by HL&P concluded
          that the duration of the outages was controlled by both the resolution
          of NRC regulatory issues as well as necessary equipment repairs
          unrelated to NRC regulatory issues and that the incremental effect of
          NRC regulatory issues on the duration of the outages was only 39 days
          per unit. Estimates as to the cost of replacement power may vary
          significantly based on a number of factors, including the capacity
          factor at which the South Texas Project might be assumed to have
          operated had it not been out of service due to the outages. However,
          HL&P believes that applying a reasonable range

                                      -45-

          of assumptions would result in replacement fuel costs of less than $10
          million for the 39 day periods identified by HL&P's consultant and
          less than $100 million for the entire length of the outages. Any fuel
          costs determined to have been unreasonably incurred would not be
          recoverable from customers and would be charged against the Company's
          earnings.

          Although the Company and HL&P believe that the Proposed Settlement is
          in the best interest of HL&P, its ratepayers, and the Company and its
          shareholders, no assurance can be given that (i) the Utility
          Commission ultimately will approve the terms of the Proposed
          Settlement or (ii) in the event the Proposed Settlement is not
          approved and proceedings against HL&P resumed, that the outcome of
          such proceedings would be favorable to HL&P.

(4) APPEALS OF PRIOR UTILITY COMMISSION RATE ORDERS

          Pursuant to a series of applications filed by HL&P in recent years,
          the Utility Commission has granted HL&P rate increases to reflect in
          electric rates HL&P's substantial investment in new plant
          construction, including the South Texas Project. Although Utility
          Commission action on those applications has been completed, judicial
          review of a number of the Utility Commission orders is pending. In
          Texas, Utility Commission orders may be appealed to a District Court
          in Travis County, and from that Court's decision an appeal may be
          taken to the Court of Appeals for the 3rd District at Austin (Austin
          Court of Appeals). Discretionary review by the Supreme Court of Texas
          may be sought from decisions of the Austin Court of Appeals. The
          pending appeals from the Utility Commission orders are in various
          stages. In the event the courts ultimately reverse actions of the
          Utility Commission in any of these proceedings, such matters would be
          remanded to the Utility Commission for action in light of the courts'
          orders. Because of the number of variables which can affect the
          ultimate resolution of such matters on remand, the Company and HL&P
          generally are not in a position at this time to predict the outcome of
          the matters on appeal or the ultimate effect that adverse action by
          the courts could have on the Company and HL&P. On remand, the Utility
          Commission's action could range from granting rate relief
          substantially equal to the rates previously approved to a reduction in
          the revenues to which HL&P was entitled during the time the applicable
          rates were in effect, which could require a refund to customers of
          amounts collected pursuant to such rates. Judicial review has been
          concluded or currently is pending on the final orders of the Utility
          Commission described below.

    (a)   1991 RATE CASE. In HL&P's 1991 rate case (Docket No. 9850), the
          Utility Commission approved a non-unanimous settlement agreement
          providing for a $313 million increase in HL&P's base rates,
          termination of deferrals granted with respect to Unit No. 2 of the
          South Texas Project and of the qualified phase-in plan deferrals
          granted with respect to Unit No. 1 of the South Texas Project, and
          recovery of deferred plant costs. The settlement authorized a 12.55
          percent return on common equity for HL&P. Rates contemplated by the
          settlement agreement were implemented in May 1991 and remain in effect
          (subject to the outcome of the current rate proceeding described in
          Note 3).

          The Utility Commission's order in Docket No. 9850 was affirmed on
          review by a District Court, and the Austin Court of Appeals affirmed
          that decision on procedural grounds due to the failure of the
          appellant to file the record with the court in a timely manner. On
          review, the Texas
                                      -46-

          Supreme Court has remanded the case to the Austin Court of Appeals for
          consideration of the appellant's challenges to the Utility
          Commission's order, which include issues regarding deferred
          accounting, the treatment of federal income tax expense and certain
          other matters. As to federal tax issues, a recent decision of the
          Austin Court of Appeals, in an appeal involving GTE-SW (and to which
          HL&P was not a party), held that when a utility pays federal income
          taxes as part of a consolidated group, the utility's ratepayers are
          entitled to a fair share of the tax savings actually realized, which
          can include savings resulting from unregulated activities. The Texas
          Supreme Court has agreed to hear an appeal of that decision, but on
          points not involving the federal income tax issues, though tax issues
          could be decided in such opinion.

          Because the Utility Commission's order in Docket No. 9850 found that
          HL&P would have been entitled to rate relief greater than the $313
          million agreed to in the settlement, HL&P believes that any
          disallowance that might be required if the court's ruling in the GTE
          decision were applied in Docket No. 9850 would be offset by that
          greater amount. However, that amount may not be sufficient if the
          Austin Court of Appeals also concludes that the Utility Commission's
          inclusion of deferred accounting costs in the settlement was improper.
          For a discussion of the Texas Supreme Court's decision on deferred
          accounting treatment, see Note 4(c). Although HL&P believes that it
          could demonstrate entitlement to rate relief equal to that agreed to
          in the stipulation in Docket No. 9850, HL&P cannot rule out the
          possibility that a remand and reopening of that settlement would be
          required if decisions unfavorable to HL&P are rendered on both the
          deferred accounting treatment and the calculation of tax expense for
          rate making purposes.

          The parties to the Proposed Settlement have agreed to withdraw their
          appeals of the Utility Commission's orders in such docket, subject to
          HL&P's dismissing its appeal in Docket No. 6668.

    (b)   1988 RATE CASE. In HL&P's 1988 rate case (Docket No. 8425), the
          Utility Commission granted HL&P a $227 million increase in base
          revenues, allowed a 12.92 percent return on common equity, authorized
          a qualified phase-in plan for Unit No. 1 of the South Texas Project
          (including approximately 72 percent of HL&P's investment in Unit No. 1
          of the South Texas Project in rate base) and authorized HL&P to use
          deferred accounting for Unit No. 2 of the South Texas Project. Rates
          substantially corresponding to the increase granted were implemented
          by HL&P in June 1989 and remained in effect until May 1991.

          In August 1994, the Austin Court of Appeals affirmed the Utility
          Commission's order in Docket No. 8425 on all matters other than the
          Utility Commission's treatment of tax savings associated with
          deductions taken for expenses disallowed in cost of service. The court
          held that the Utility Commission had failed to require that such tax
          savings be passed on to ratepayers, and ordered that the case be
          remanded to the Utility Commission with instructions to adjust HL&P's
          cost of service accordingly. Discretionary review is being sought from
          the Texas Supreme Court by all parties to the proceeding.

          The parties to the Proposed Settlement have agreed to dismiss their
          respective appeals of Docket No. 8425, subject to HL&P's dismissing
          its appeal in Docket No. 6668. A separate party to this appeal,
          however, has not agreed to dismiss its appeal.

                                      -47-

    (c)   DEFERRED ACCOUNTING. Deferred accounting treatment for certain costs
          associated with Unit No. 1 of the South Texas Project was authorized
          by the Utility Commission in Docket No. 8230 and was extended in
          Docket No. 9010. Similar deferred accounting treatment with respect to
          Unit No. 2 of the South Texas Project was authorized in Docket No.
          8425. For a discussion of the deferred accounting treatment granted,
          see Note 1(f).

          In June 1994, the Texas Supreme Court decided the appeal of Docket
          Nos. 8230 and 9010, as well as all other pending deferred accounting
          cases involving other utilities, upholding deferred accounting
          treatment for both carrying costs and operation and maintenance
          expenses as within the Utility Commission's statutory authority and
          reversed the Austin Court of Appeals decision to the extent that the
          Austin Court of Appeals had rejected deferred accounting treatment for
          carrying charges. Because the lower appellate court had upheld
          deferred accounting only as to operation and maintenance expenses, the
          Texas Supreme Court remanded Docket Nos. 8230 and 9010 to the Austin
          Court of Appeals to consider the points of error challenging the
          granting of deferred accounting for carrying costs which it had not
          reached in its earlier consideration of the case. The Texas Supreme
          Court opinion did state, however, that when deferred costs are
          considered for addition to the utility's rate base in an ensuing rate
          case, the Utility Commission must then determine to what extent
          inclusion of the deferred costs is necessary to preserve the utility's
          financial integrity. Under the terms of the Proposed Settlement, South
          Texas Project deferrals will continue to be amortized under the
          schedule previously established.

          The Office of the Public Utility Counsel (OPUC) has agreed, pursuant
          to the Proposed Settlement, to withdraw and dismiss its appeal if the
          Proposed Settlement becomes effective and on the condition that HL&P
          dismisses its appeal in Docket No. 6668. However, the appeal of the
          State of Texas remains pending.

    (d)   PRUDENCE REVIEW OF THE CONSTRUCTION OF THE SOUTH TEXAS PROJECT. In
          June 1990, the Utility Commission ruled in a separate docket (Docket
          No. 6668) that had been created to review the prudence of HL&P's
          planning and construction of the South Texas Project that $375.5
          million out of HL&P's $2.8 billion investment in the two units of the
          South Texas Project had been imprudently incurred. That ruling was
          incorporated into HL&P's 1988 and 1991 rate cases and resulted in
          HL&P's recording an after-tax charge of $15 million in 1990. Several
          parties appealed the Utility Commission's decision, but a District
          Court dismissed these appeals on procedural grounds. The Austin Court
          of Appeals reversed and directed consideration of the appeals, and the
          Texas Supreme Court denied discretionary review in 1994. At this time,
          no action has been taken by the appellants to proceed with the
          appeals. Unless the order in Docket No. 6668 is modified or reversed
          on appeal, the amount found imprudent by the Utility Commission will
          be sustained.

          Under the Proposed Settlement, OPUC, HL&P and the City of Houston each
          has agreed to dismiss its respective appeals of Docket No. 6668. A
          separate party to this appeal, however, has not agreed to dismiss its
          appeal. If this party does not elect to dismiss its appeal, HL&P may
          elect to maintain its appeal, whereupon OPUC and City of Houston shall
          also be entitled to maintain their appeals.

                                      -48-

 (5)MALAKOFF

          The scheduled in-service dates for the Malakoff units were postponed
          during the 1980's as expectations of continued strong load growth were
          tempered. In 1987, all developmental work was stopped and AFUDC
          accruals ceased. These units have been cancelled due to the
          availability of other cost effective resource options.

          In Docket No. 8425, the Utility Commission allowed recovery of certain
          costs associated with the cancelled Malakoff units by amortizing those
          costs over ten years for rate making purposes. Such recoverable costs
          were not included in rate base and, as a result, no return on
          investment is being earned during the recovery period. The remaining
          balance at December 31, 1994 is $34 million with a recovery period of
          66 months.

          Also as a result of the final order in Docket No. 8425, the costs
          associated with the engineering design work for the Malakoff units
          were included in rate base and are earning a return. Subsequently, in
          December 1992, HL&P determined that such costs would have no future
          value and reclassified $84.1 million from plant held for future use to
          recoverable project costs. In 1993, an additional $7 million was
          reclassified to recoverable project costs. Amortization of these
          amounts began in 1993. The balance at December 31, 1994 was $65
          million with a remaining recovery period of 60 months. The
          amortization amount is approximately equal to the amount currently
          earning a cash return in rates. The Utility Commission's decision to
          allow treatment of these costs as plant held for future use has been
          challenged in the pending appeal of the Docket No. 8425 final order.
          See Note 4(b) for a discussion of this proceeding.

          In June 1990, HL&P purchased from its then fuel supply affiliate,
          Utility Fuels, Inc. (Utility Fuels), all of Utility Fuels' interest in
          the lignite reserves and lignite handling facilities for Malakoff. The
          purchase price was $138.2 million, which represented the net book
          value of Utility Fuels' investment in such reserves and facilities. As
          part of the June 1990 rate order (Docket No. 8425), the Utility
          Commission ordered that issues related to the prudence of the amounts
          invested in the lignite reserves be considered in HL&P's next general
          rate case which was filed in November 1990 (Docket No. 9850). However,
          under the October 1991 Utility Commission order in Docket No. 9850,
          this determination was postponed to a subsequent docket.

          HL&P's remaining investment in Malakoff lignite reserves as of
          December 31, 1994 of $153 million is included on the Company's
          Consolidated and HL&P's Balance Sheets in plant held for future use.
          HL&P anticipates that an additional $8 million of expenditures
          relating to lignite reserves will be incurred in 1995 and 1996.

          In Docket No. 12065, HL&P filed testimony in support of the
          amortization of substantially all of its remaining investment in
          Malakoff, including the portion of the engineering design costs for
          which amortization had not previously been authorized and the amount
          attributable to related lignite reserves which had not previously been
          addressed by the Utility Commission. Under the Proposed Settlement of
          Docket No. 12065, HL&P would amortize its investment in Malakoff over
          a period not to exceed seven years such that the entire investment
          will be written off no later than December 31, 2002. See Note 3. In
          the event that the Utility Commission does not

                                      -49-

          approve the Proposed Settlement, and if appropriate rate treatment of
          these amounts is not ultimately received, HL&P could be required to
          write off any unrecoverable portions of its Malakoff investment.

                                      -50-