Pacific Gas Transmission Company
FERC Gas Tariff                                      Second Revised Sheet No. 12
First Revised Volume No. 1-A              Superseding
                                                      First Revised Sheet No. 12
________________________________________________________________________________

                                                                    EXHIBIT 10.1

                              RATE SCHEDULE FTS-1
                          FIRM TRANSPORTATION SERVICE

1.  AVAILABILITY

    This rate schedule is available to any party (hereinafter called "Shipper")
    qualifying for service pursuant to the Commission's Regulations contained in
    18 CFR Part 284, and who has executed a Firm Transportation Service
    Agreement with PGT in the form contained in this FERC Gas Tariff First
    Revised Volume No. 1-A.

2.  APPLICABILITY AND CHARACTER OF SERVICE

    This rate schedule shall apply to firm gas transportation services performed
    by PGT for Shipper pursuant to the executed Firm Transportation Service
    Agreement between PGT and Shipper. PGT shall receive from Shipper such daily
    quantities of gas up to the Shipper's Maximum Daily Quantity as specified in
    the executed Firm Transportation Service Agreement between PGT and Shipper
    plus the required quantity of gas for fuel and line loss associated with
    service under this Rate Schedule FTS-1 and redeliver an amount equal to the
    quantity received less the required quantity of gas for fuel and line loss.
    This transportation service shall be firm and not subject to curtailment or
    interruption except as provided in the Transportation General Terms and
    Conditions.

    Firm transportation service shall be subject to all provisions of the
    executed Firm Transportation Service Agreement between PGT and Shipper and
    the applicable Transportation General Terms and Conditions.

3.  RATES

    Shipper shall pay PGT each month the sum of the Reservation Charge, the
    Delivery Charge, plus any applicable Extension Charge, Overrun Charge and
    applicable surcharges for the quantities of natural gas delivered. The
    rate(s) set forth in PGT's current Statement of Effective Rates and Charges
    for Transportation of Natural Gas in this FERC Gas Tariff First Revised
    Volume No. 1-A are applied to transportation service rendered under this
    rate schedule.

                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: SEPTEMBER 30, 1996                       Effective: NOVEMBER 01, 1996
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RP94-149, 76-61,246, dated SEPTEMBER 11, 1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      Second Revised Sheet No. 13
First Revised Volume No. 1-A              Superseding
                                                      First Revised Sheet No. 13
________________________________________________________________________________
                              RATE SCHEDULE FTS-1
                          FIRM TRANSPORTATION SERVICE
                                  (Continued)
3.RATES (Continued)

  3.1  Reservation Charge

       The Reservation Charge shall be the sum of the Mileage and the Non-
       Mileage Component: 

       (a)  Mileage Component
 
       The Mileage Component shall be the product of the currently effective
       Mileage Rate as set forth on Effective Tariff Sheet No. 4, the distance,
       in pipeline miles, from the Primary Point(s) of receipt to the Primary
       Point(s) of Delivery on Mainline Facilities as set forth in Shipper's
       Contract, and the Shipper's Maximum Daily Quantity at such Point(s).

       (b) Non-Mileage Component

       The Non-Mileage Component shall be the product of the currently effective
       Non-Mileage Rate as set forth on Effective Tariff Sheet No. 4 and the
       Shipper's Maximum Daily Quantity at Primary Point(s) of Delivery on
       Mainline Facilities.

       (c) Mitigation Revenue Recovery Surcharge

       If Shipper is a Subject Shipper, the Mitigation Revenue Recovery
       Surcharge for the Mileage and Non-Mileage Components as set forth on
       Effective Tariff Sheet No. 4 shall be included in, and become a part of,
       the maximum Mileage and Non-Mileage Base Reservation Rates used for
       computing the Mileage and Non-Mileage Components of the Reservation
       Charge. The Mileage Component shall be designed to recover, on the basis
       of the mileage billing determinants of the Subject Shippers underlying
       PGT's currently effective rates, mileage mitigation revenues not
       recovered from other shippers in accordance with Article IV, Section 1(b)
       of the Stipulation and Agreement in Docket No. RP94-149-000, et al., and
       the Non-Mileage Component shall be designed to recover, on the basis of
       the Non-Mileage billing determinants of the Subject Shippers underlying
       PGT's currently effective rates, Non-Mileage mitigation revenues not
       recovered from other shippers in accordance with Article IV, Section 1(b)
       of the Stipulation and Agreement in Docket No. RP94-149-000, et al.

                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: SEPTEMBER 30, 1996                       Effective: NOVEMBER 01, 1996
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RP94-149, 76-61,246, dated SEPTEMBER 11, 1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                           Original Sheet No. 13A
First Revised Volume No. 1-A
________________________________________________________________________________
                              RATE SCHEDULE FTS-1
                          FIRM TRANSPORTATION SERVICE
                                  (Continued)
3.RATES (Continued)

  3.1  Reservation Charge (Continued)

       (d)   Shipper's obligation to pay the Reservation Charge and applicable
             Reservation Surcharge is independent of Shipper's ability to obtain
             export authorization from the National Energy Board of Canada,
             Canadian provincial removal authority, and/or import authorization
             from the United States Department of Energy, and shall begin with
             the execution of the Firm Transportation Service Agreement by both
             parties. The Reservation Charge and Reservation Surcharge due and
             payable shall be computed beginning in the month in which service
             is first available (prorated if beginning in the month in which
             service is available on a date other than the first day of the
             month). Thereafter, the monthly Reservation Charge and Reservation
             Surcharge shall be due and payable each month during the Initial
             (and Subsequent) Term(s) of the Shipper's executed Firm
             Transportation Service Agreement and is unaffected by the quantity
             of gas transported by PGT to Shipper's delivery point(s) in any
             month except as provided for in Paragraphs 3.10 and 3.11 of this
             rate schedule.

 3.2  Delivery Charge

      The Delivery Charge shall be the product of the Delivery Rate as set forth
      on Effective Tariff Sheet No. 4, the quantities of gas delivered in the
      month (in MMBtu) (excluding Authorized Overrun) at point(s) of delivery on
      Mainline Facilities, and the distance, in pipeline miles, from the
      point(s) of receipt to point(s) of delivery on Mainline Facilities.

                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: SEPTEMBER 30, 1996                       Effective: NOVEMBER 01, 1996
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RP94-149, 76-61,246, dated SEPTEMBER 11, 1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      Second Revised Sheet No. 14
First Revised Volume No. 1-A              Superseding
                                                      First Revised Sheet No. 14
________________________________________________________________________________
                              RATE SCHEDULE FTS-1
                          FIRM TRANSPORTATION SERVICE
                                  (Continued)
3.  RATES (Continued)

    3.3  Extension Charge
 
         If Shipper designates a Primary Point of delivery on an Extension
         Facility, then in addition to all other charges that are applicable,
         Shipper shall pay the Extension Charge, which shall consist of a
         reservation and delivery component.

         (a)   The reservation component of the Extension Charge shall be the
               product of Shipper's Maximum Daily Quantity at the Primary
               Point(s) of delivery on the Extension Facility, the applicable
               Extension reservation rate as set forth on Effective Tariff Sheet
               No. 4, and the distance, in pipeline miles, from the Receipt
               Point(s) on the Extension Facility to the Primary Point(s) of
               delivery.

         (b)   The delivery component of the Extension Surcharge shall be the
               product of the quantities delivered at the point(s) of delivery
               on the Extension Facility, the applicable Extension delivery rate
               as set forth on Effective Tariff Sheet No. 4, and the distance,
               in pipeline miles, from the Receipt Point(s) on the Extension
               Facility to the point(s) of delivery.

    3.4  Authorized Overrun Charge

         Quantities in excess of Shipper's MDQ shall be transported when
         capacity is available on the PGT system and when the provision of such
         Authorized Overruns shall not effect any Shipper's rights on the PGT
         System. Authorized Overruns are interruptible in nature. The rate
         charged shall be the same as the rates and charges for interruptible
         transportation under Rate Schedule ITS-1 as set forth on effective
         tariff Sheet No. 4, and such Authorized Overruns shall be subject to
         the priority of service provisions of Paragraph 19 of the
         Transportation General Terms and Conditions.

    3.5  Applicability of Surcharges
 
         Shipper shall pay all reservation and usage surcharges applicable to
         the service provided to such Shipper as set forth in PGT's FERC Gas
         Tariff, First Revised Volume No. 1-A. Such surcharges shall be deemed
         to be part of Shipper's Reservation and Delivery Charges.

                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: SEPTEMBER 30, 1996                       Effective: NOVEMBER 01, 1996
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RP94-149, 76-61,246, dated SEPTEMBER 11, 1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                           Original Sheet No. 14A
First Revised Volume No. 1-A
________________________________________________________________________________
                              RATE SCHEDULE FTS-1
                          FIRM TRANSPORTATION SERVICE
                                  (Continued)
3.  RATES (Continued)


    3.6  Shipper shall pay the Reservation Charge, and the Maximum Delivery
         Charge for service under this Rate Schedule unless PGT offers to
         discount the Mileage Rate components or the Non-Mileage Rate components
         of the Reservation Rate or the Delivery Rate or the GRI surcharge under
         this rate schedule. If PGT elects to discount any such rate, PGT shall,
         up to forty-eight (48) hours prior to such discount, by written notice,
         advise Shipper of the effective date of such charges and the quantity
         of gas so affected; provided, however, such discount shall not be
         anticompetitive or unduly discriminatory between individual shippers.
         The rates for service under this rate schedule shall not be discounted
         below the Minimum Reservation Charge, the Minimum Delivery Rate, and
         applicable GSR and ACA Surcharges.

                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: SEPTEMBER 30, 1996                       Effective: NOVEMBER 01, 1996
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RP94-149, 76-61,246, dated SEPTEMBER 11, 1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                       First Revised Sheet No. 15
First Revised Volume No. 1-A              Superseding
                                                           Original Sheet No. 15
________________________________________________________________________________
                              RATE SCHEDULE FTS-1
                          FIRM TRANSPORTATION SERVICE
                                  (Continued)

3.  RATES (Continued)

    3.7  Gas Supply Restructuring (GSR) Transition Cost Surcharge

         Shipper shall pay a GSR Transition Cost Surcharge for PGT's approved
         GSR costs as defined in Paragraph 30 of the Transportation General
         Terms and Conditions. This surcharge is stated on the Statement of
         Effective Rates and Charges and is defined in Paragraph 30 of the
         Transportation General Terms and Conditions. The surcharge shall be the
         product of the surcharge rate, the quantities of gas delivered during
         the month and the distance in pipeline miles from the point(s) of
         receipt to the point(s) of delivery.

    3.8  Backhauls or upstream deliveries shall be subject to the same charges
         as forward haul or downstream transportation arrangements except that
         no gas shall be retained by PGT for compressor station fuel, line loss
         and other unaccounted-for gas.

    3.9  Direct Bills

         PG&E shall pay a Direct Bill for 100% of the costs allocated to the
         Direct Bill portion of Approved Gas Supply Restructuring (GSR) Costs
         excluding the amount to be collected from the Northwest Shippers as
         defined in Paragraph 30 of the Transportation General Terms and
         Conditions and credited against the Direct Bill portion of Approved GSR
         Costs as defined in Paragraph 30 of the Transportation General Terms
         and Conditions. In accordance with Paragraph 30.5(b) of the
         Transportation General Terms and Conditions, PG&E may elect to pay its
         Direct Bill in a lump sum or select one of three payment plans as shown
         on the Statement of Rates and Charges for Transportation of Natural
         Gas.

                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: SEPTEMBER 30, 1996                       Effective: NOVEMBER 01, 1996
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RP94-149, 76-61,246, dated SEPTEMBER 11, 1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                       First Revised Sheet No. 16
First Revised Volume No. 1-A              Superseding
                                                           Original Sheet No. 16
________________________________________________________________________________
                              RATE SCHEDULE FTS-1
                          FIRM TRANSPORTATION SERVICE
                                  (Continued)

3.  RATES (Continued)

    3.10 Capacity Release

         (a)  Releasing Shippers:

                Shipper shall have the option to release capacity pursuant to
                the provisions of PGT's capacity release program as specified in
                the Transportation General Terms and Conditions. Shipper may
                release its capacity, up to Shipper's Maximum Daily Quantity
                under this rate schedule, in accordance with the provisions of
                Paragraph 28 of PGT's Transportation General Terms and
                Conditions of this FERC Gas Tariff, First Revised Volume No. 1-
                A. Shipper shall pay a fee associated with the marketing of
                capacity by PGT (if applicable) in accordance with Paragraph 28
                of the Transportation General Terms and Conditions. This fee
                shall be negotiated between PGT and the Releasing Shipper.

         (b)  Replacement Shippers:

                Shipper may receive released capacity service under this rate
                schedule pursuant to Paragraph 28 of the Transportation General
                Terms and Conditions and is required to execute a service
                agreement in the form contained for capacity release under Rate
                Schedule FTS-1 in this First Revised Volume No. 1-A.

                Shipper shall pay PGT each month for transportation service
                under this rate schedule and as set forth in PGT's current
                Statement of Effective Rates and Charges in this First Revised
                Volume No. 1-A. Charges to be paid shall be the sum of the
                Reservation Charge, Delivery Charge, and other applicable
                surcharges or penalties.

                The rates paid by Shipper receiving capacity release
                transportation service shall be adjusted as provided on Exhibit
                R in the executed Transportation Service Agreement For Capacity
                Release between PGT and Shipper.

                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: SEPTEMBER 30, 1996                       Effective: NOVEMBER 01, 1996
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RP94-149, 76-61,246, dated SEPTEMBER 11, 1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                     Second Revised Sheet No. 16A
First Revised Volume No. 1-A              Superseding
                                                     First Revised Sheet No. 16A
________________________________________________________________________________
                              RATE SCHEDULE FTS-1
                          FIRM TRANSPORTATION SERVICE
                                  (Continued)

3.11  Reservation Charge Credit - Malin Primary Delivery Point

        If PGT fails to deliver to Malin, Oregon ninety-five percent (95%) or
        more of the aggregate Confirmed Daily Nominations (as hereinafter
        defined) of all Shippers with a Malin primary delivery point receiving
        service under this rate schedule (hereinafter referred to as the "Non-
        Deficiency Amount") for more than twenty-five (25) days in any given
        Contract Year, then for each day during that Contract Year in excess of
        twenty-five (25) days that PGT so fails to deliver the Non-Deficiency
        Amount (a "Credit Day") Shipper, as its sole remedy, shall be entitled
        to a Reservation Charge Credit calculated in the manner hereinafter set
        forth.

        For the purpose of this Paragraph 3.10, Confirmed Daily Nomination shall
        mean for any day, the lesser of (1) Shipper's Maximum Daily Quantity or
        (2) the actual quantity of gas that the connecting pipeline upstream of
        PGT is capable of delivering for Shipper's account to PGT at Shipper's
        primary point of receipt(s) on PGT less Shipper's requirement to provide
        compressor fuel and line losses under the Statement of Effective Rates
        and Charges of PGT's FERC Gas Tariff, First Revised Volume No. 1-A or
        (3) the quantity of gas that Pacific Gas And Electric Company (PG&E) is
        capable of accepting at Malin for Shipper's account or (4) Shipper's
        nomination to PGT.

        The Reservation Charge Credit for each Credit Day for a particular
        Shipper shall be computed as follows:

        Reservation Charge      A             B - C
        Credit for Each        ____     x     _____
        Credit Day          =  30.4             B   

        where  A =  Shipper's Monthly Reservation Charge
               B =  Shipper's confirmed daily nomination for the Credit Day
               C =  Actual quantity of gas delivered by PGT to PG&E at Malin for
                    Shipper's account for the Credit Day

        Except as provided for in Paragraph 3.11 of this rate schedule, this
        Reservation Charge Credit is Shipper's sole remedy for nondelivery of
        gas by PGT.

                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: SEPTEMBER 30, 1996                       Effective: NOVEMBER 01, 1996
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RP94-149, 76-61,246, dated SEPTEMBER 11, 1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                     Second Revised Sheet No. 16B
First Revised Volume No. 1-A              Superseding
                                                     First Revised Sheet No. 16B
________________________________________________________________________________
                              RATE SCHEDULE FTS-1
                    FIRM TRANSPORTATION SERVICE (Continued)
3.12  Reservation Charge Credit - Other than Malin Primary Delivery Point

        If PGT fails to deliver to a primary delivery point on its system other
        than Malin, Oregon, ninety-five percent (95%) or more of the aggregate
        Confirmed Daily Nominations (as hereinafter defined) of all Shippers at
        such primary delivery point other than Malin receiving service under
        this rate schedule (hereinafter referred to as the "Non-Deficiency
        Amount") for more than twenty-five (25) days in any given Contract Year,
        then for each day during that Contract Year in excess of twenty-five
        (25) days that PGT so fails to deliver the Non-Deficiency Amount (a
        "Credit Day") Shipper, as its sole remedy, shall be entitled to a
        Reservation Charge Credit calculated in the manner hereinafter set
        forth.

        For the purpose of this Paragraph 3.11, Confirmed Daily Nomination shall
        mean for any day, the lesser of (1) Shipper's Maximum Daily Quantity or
        (2) the quantity of gas that the connecting downstream pipeline(s),
        local distribution company pipeline(s), or end-user(s) is/are capable of
        accepting for Shipper's account at Shipper's point(s) of primary
        delivery on PGT or (3) the quantity of gas that the connecting pipeline
        upstream of PGT is capable of delivering to PGT for Shipper's account to
        PGT at Shipper's primary point of receipt(s) on PGT less Shipper's
        requirement to provide compressor fuel and line losses under the
        Statement of Effective Rates and Charges of PGT's FERC Gas Tariff, First
        Revised Volume No. 1-A or (4) Shipper's nomination to PGT.

        The Reservation Charge Credit for each Credit Day for a particular
        Shipper shall be computed as follows:

        Reservation Charge      A             B - C
        Credit for Each        ____     x     _____
        Credit Day          =  30.4             B

        where  A =  Shipper's Monthly Reservation Charge
               B =  Shipper's confirmed daily nomination for the Credit Day
               C =  Actual quantity of gas delivered by PGT to a Shipper's
                    primary delivery point(s) (other than Malin) for Shipper's
                    account for the Credit Day

        Except as provided for in Paragraph 3.10 of this rate schedule, this
        Reservation Charge Credit is Shipper's sole remedy for nondelivery of
        gas by PGT.
                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: SEPTEMBER 30, 1996                       Effective: NOVEMBER 01, 1996
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RP94-149, 76-61,246, dated SEPTEMBER 11, 1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                       Third Revised Sheet No. 17
First Revised Volume No. 1-A              Superseding
                                                     Second Revised Sheet No. 17
________________________________________________________________________________
                              RATE SCHEDULE FTS-1
                          FIRM TRANSPORTATION SERVICE
                                  (Continued)

4. FUEL AND LINE LOSS

   Shipper shall furnish to PGT quantities of gas for compressor station fuel,
   line loss and other utility purposes, plus other unaccounted for gas used in
   the operation of PGT's combined pipeline system between the International
   Boundary near Kingsgate, British Columbia and the Oregon-California boundary
   for the transportation quantities of gas delivered by PGT to Shipper, based
   upon the effective fuel and line loss percentages in accordance with
   Paragraph 37 of the General Terms and Conditions.

5. TRANSPORTATION GENERAL TERMS AND CONDITIONS

   All of the Transportation General Terms and Conditions are applicable to this
   rate schedule, unless otherwise stated in the executed Firm Transportation
   Service Agreement between PGT and Shipper. Any future modifications,
   additions or deletions to said Transportation General Terms and Conditions,
   unless otherwise provided, are applicable to firm transportation service
   rendered under this rate schedule, and by this reference, are made a part
   hereof.
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: SEPTEMBER 30, 1996                       Effective: NOVEMBER 01, 1996
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RP94-149, 76-61,246, dated SEPTEMBER 11, 1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      Eighth Revised Sheet No. 51
First Revised Volume No. 1-A              Superseding
                                                    Seventh Revised Sheet No. 51
________________________________________________________________________________
 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                               TABLE OF CONTENTS


Paragraph No.                  Provision                   Sheet No.
                                                          
1       Definitions                                             52
2       Gas Research Institute Charge Adjustment Provision      55 
3       Quality of Gas                                          56 
4       Measuring Equipment                                     58 
5       Measurements                                            60 
6       Inspection of Equipment and Records                     61 
7       Billing                                                 61 
8       Payment                                                 62 
9       Reserved                                                63 
10      Force Majeure                                           63 
11      Warranty of Eligibility for Transportation              64 
12      Possession of Gas and Responsibility                    64 
13      Indemnification                                         65 
14      Arbitration                                             65 
15      Governmental Regulations                                66
16      Miscellaneous Provision                                 66 
17      Transportation Service Agreement                        66 
18      Operating Provisions                                    67 
19      Priority of Service, Scheduling and Nominations         81 
20      Curtailment                                             81C 
21      Balancing                                               82 
22      Annual Charge Adjustment (ACA) Provision                85 
23      Shared Operating Personnel and Facilities               85 
24      Complaint Procedures                                    86 
25      Information Concerning Availability and Pricing 
        of Transportation Service and Capacity Available for 
        Transportation                                          87 
26      Market Centers                                          88 
27      Planned PGT Capacity Curtailments and Interruptions     88A 
28      Capacity Release                                        89 
29      Flexible Receipt and Delivery Points                    119 
30      Gas Supply Restructuring Transition Costs               123 
31      Reserved                                                127 
32      Equality of Transportation Service                      129 
33      Right of First Refusal Upon Termination of 
        Firm Shipper's Service Agreement                        130 
34      Electronic Bulletin Board                               132 
35      Reserved                                                137 
35A     Crediting of Interruptible Transportation Revenues for 
        Extensions                                              138A 
36      Discount Policy                                         139
37      Adjustment Mechanism for Fuel, Line Loss and Other 
        Unaccounted For Gas Percentages                         140 
38      Reserved                                                142 
39      Sales of Excess Gas                                     143
                                                                     (Continued)

________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: SEPTEMBER 30, 1996                      Effective: SEPTEMBER 13, 1996
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RP94-149, 76-61,246, dated SEPTEMBER 11, 1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      Second Revised Sheet No. 52
First Revised Volume No. 1-A              Superseding
                                                      First Revised Sheet No. 52
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

1.  DEFINITIONS

    1.1   The word "day" shall mean a period of twenty-four (24) consecutive
          hours, beginning and ending at 7:00 o'clock a.m. Pacific Standard Time
          or such other time as Shipper and PGT may agree upon.

    1.2   The word "month" shall mean a period extending from the beginning of
          the first day in a calendar month to the beginning of the first day in
          the next succeeding calendar month.

    1.3   The term "Maximum Daily Quantity" (MDQ) shall mean the maximum daily
          quantity in MMBtu of gas which PGT agrees to deliver exclusive of an
          allowance for compressor station fuel, line loss and other unaccounted
          for gas and transport for the account of Shipper to Shipper's point(s)
          of delivery on each day during each year during the term of Shipper's
          Transportation Service Agreement with PGT.

    1.4   The term "marketing affiliate" shall mean Pacific Gas and Electric
          Company and Hermiston Generating Company, L.P.

    1.5   The word "gas" shall mean natural gas.

    1.6   The term "cubic foot of gas" shall mean that quantity of gas which, at
          a temperature of sixty degrees (60/./) Fahrenheit and at a pressure of
          14.73 pounds per square inch absolute, occupies one (1) cubic foot.

    1.7   The term "Mcf" shall mean one thousand (1,000) cubic feet of gas and
          shall be measured as set forth in Paragraph 5 hereof. The term "MMcf"
          shall mean one million (1,000,000) cubic feet of gas.

    1.8   The term "Btu" shall mean British Thermal Unit. The term "MMBtu" shall
          mean one million (1,000,000) British Thermal Units.

    1.9   The term "gross heating value" shall mean the number of Btu's in a
          cubic foot of gas at a temperature of sixty degrees (60/./)
          Fahrenheit, saturated with water vapor, and at an absolute pressure
          equivalent to thirty (30) inches of mercury at thirty-two degrees
          (32/./) Fahrenheit.

    1.10  The term "psig" shall mean pounds per square inch gauge.
 
                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: MARCH 01, 1996                              Effective:  APRIL 01,1996



 
Pacific Gas Transmission Company
FERC Gas Tariff                                       First Revised Sheet No. 53
First Revised Volume No. 1-A              Superseding
                                                           Original Sheet No. 53
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

1.  DEFINITIONS (Continued)

    1.11   Releasing Shipper: A firm transportation Shipper which intends to
           post its service to be released to a Replacement Shipper, has posted
           the service for release, or has released its service.

    1.12   Replacement Shipper: A Shipper which has contracted to utilize a
           Releasing Shipper's service for a specified period of time.

    1.13   Posting Period: The period of time during which a Releasing Shipper
           may post, or have posted by the pipeline, all or a part of its
           service for release to a Replacement Shipper.

    1.14   Release Term: The period of time during which a Releasing Shipper
           intends to release, or has released all or a portion of its
           contracted quantity of service to a Replacement Shipper.

    1.15   Bid Period: The period of time during which a Replacement Shipper may
           bid to contract for a parcel which has been posted for release by a
           Releasing Shipper.

    1.16   Parcel: The term utilized to describe an amount of capacity,
           expressed in MMBtu/d, from a specific receipt point to a specific
           delivery point for a specific period of time which is released and
           bid on pursuant to the capacity release provisions contained in
           Paragraph 28 of these Transportation General Terms and Conditions.

    1.17   Primary Release: The term used to describe the release of capacity by
           a Releasing Shipper receiving service under a Part 284 firm
           transportation rate schedule.

    1.18   Secondary Release: The term used to describe the release of capacity
           by a Replacement Shipper receiving service under a Part 284 firm
           transportation rate schedule.

                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: AUGUST 13, 1996                         Effective: SEPTEMBER 13, 1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                       Third Revised Sheet No. 54
First Revised Volume No. 1-A              Superseding
                                                     Second Revised Sheet No. 54
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

1.  DEFINITIONS (Continued)

    1.19   Bid Reconciliation Period: The period of time subsequent to the Bid
           Period during which bids are evaluated by PGT.

    1.20   Match Period: The period of time subsequent to the Bid Reconciliation
           Period and before the notification deadline for awarding capacity for
           Prearranged Deal C during which the Prearranged Shipper may match any
           higher bids for the Parcel.

    1.21   The term Mainline Facilities shall mean the 36-inch and 42-inch mains
           and appurtenant facilities extending from the interconnection with
           the pipeline facilities of Alberta Natural Gas Company and Foothills
           Pipe Lines (South B.C.) Ltd., near Kingsgate, British Columbia to the
           interconnection with the pipeline facilities of Pacific Gas and
           Electric Company near Malin, Oregon.

    1.22   The term Extension Facilities shall mean the 12-inch mains and
           appurtenant facilities extending from PGT's mainline facilities at
           Milepost 304.25 and the 16-inch and 12-inch mains and appurtenant
           facilities extending from PGT's Mainline Facilities at Milepost
           599.20 that were authorized in Docket No. CP93-618-000. The term
           "Extension Facility" shall mean one of the Extension Facilities.

    1.23   The term "Subject Shipper" shall mean the Shippers identified in
           Appendix G of the Stipulation and Agreement in Docket No. RP94-149-
           000, et al., and Shippers that have obtained service rights from such
           Shippers.

                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: SEPTEMBER 30, 1996                       Effective: NOVEMBER 01, 1996
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RP94-149, 76-61,246, dated SEPTEMBER 11, 1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      Second Revised Sheet No. 55
First Revised Volume No. 1-A              Superseding
                                                      First Revised Sheet No. 55
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

2.  GAS RESEARCH INSTITUTE CHARGE ADJUSTMENT PROVISION

    2.1    Purpose: PGT has joined with other gas enterprises in the formation
           of, and participation in, the activities and financing of the Gas
           Research Institute (GRI), an Illinois Not For Profit corporation. GRI
           has been organized for the purpose of sponsoring Research,
           Development and Demonstration (RD&D) programs in the field of natural
           and manufactured gas for the purpose of assisting all segments of the
           gas industry in providing adequate, reliable, safe, economic and
           environmentally acceptable gas service for the benefit of gas
           consumers and the general public.

           For the purpose of funding GRI's approved expenditures, this
           Paragraph 2 establishes a GRI Adjustment Charge to be applicable to
           PGT's Rate Schedules ITS-1, AIS-1, PS-1 and FTS-1 in this FERC Gas
           Tariff First Revised Volume No. 1-A; provided, however, such charge
           shall not be applicable in the event gas is delivered to a downstream
           interstate pipeline that is a member of GRI.

    2.2    Basis for the GRI Adjustment Charges: The rate schedule specified in
           Paragraph 2.1 hereof shall include an increment for a GRI Adjustment
           Charge for RD&D. Such GRI Adjustment Charge shall be that increment,
           adjusted to PGT's pressure base and heating value if required, which
           has been approved by Federal Energy Regulatory Commission Orders
           approving GRI's RD&D expenditures. The GRI Adjustment Charge shall be
           reflected in the current Statement of Effective Rates and Charges for
           Transportation of Natural Gas in this FERC Gas Tariff First Revised
           Volume No. 1-A.

    2.3    Filing Procedure: The notice period and proposed effective date of
           filings pursuant to this paragraph shall be as permitted under
           Section 4 of the Natural Gas Act; provided, however, that any such
           filing shall not become effective unless it becomes effective without
           suspension or refund obligation.

   2.4     Remittance to GRI: PGT shall remit to GRI, not later than fifteen
           (15) days after the receipt thereof, all monies received by virtue of
           the GRI Adjustment Charge, less any amounts properly payable to a
           Federal, State or Local authority relating to the monies received
           hereunder.

                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: AUGUST 13, 1996                         Effective: SEPTEMBER 13, 1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                           Original Sheet No. 55A
First Revised Volume No. 1-A              
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

2.  GAS RESEARCH INSTITUTE CHARGE ADJUSTMENT PROVISION (Continued)

    2.5    A high load factor Shipper is a Shipper with a load factor greater
           than fifty (50) percent. A low load factor Shipper is a Shipper with
           a load factor equal to or less than fifty (50) percent. A Shipper's
           load factor for each service agreement shall be determined annually
           using the most recent twelve (12) months of actual throughput
           available (including throughput using capacity released pursuant to
           Paragraph 28 of the Transportation General Terms and Conditions). The
           Shipper's load factor shall remain in effect during the calendar
           year. In the event twelve (12) months of actual data does not exist,
           the Shipper's load factor shall be determined monthly based on the
           latest recorded throughput data. The appropriate GRI demand surcharge
           is applied monthly until such time as twelve (12) months of actual
           data is accumulated. At such time the Shipper's load factor shall
           remain in effect during the calendar year.

    2.6    For the purpose of funding GRI's approved expenditures, and subject
           to the further terms and conditions set forth in the Stipulation and
           Agreement Concerning the Post-1993 GRI Funding Mechanism and the
           orders approving such Stipulation and Agreement found at Gas Research
           Institute, 62 FERC (P)61,316 (1993) this Paragraph 2 establishes a
           GRI Funding Unit which shall be collected for quantities of gas
           transported under PGT's rate schedules provided, however, such charge
           shall not be applicable to discounted transactions except where the
           discounted rate is less than the GRI Funding Unit. In this instance
           PGT shall remit that portion of the GRI Funding Unit actually
           collected. For purposes of discounted transactions, any GRI Funding
           Unit shall be considered to be the first component of rates
           discounted. The GRI Funding Unit may be discounted to zero and shall
           not be applied to the same quantity of gas more than once.



                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: JANUARY 10, 1994                          Effective: JANUARY 01, 1994
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. TM94-2-86-000, dated DECEMBER 30, 1993


 
Pacific Gas Transmission Company
FERC Gas Tariff                                       First Revised Sheet No. 56
First Revised Volume No. 1-A              Superseding
                                                           Original Sheet No. 56
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)
3.  QUALITY OF GAS

    3.1    Quality Standards: The gas which Shipper delivers hereunder to PGT
           for transport (and the gas which PGT transports hereunder for
           Shipper) shall be merchantable gas at all times complying with the
           following quality requirements:

           (a) Heating Value: The gas shall have a gross heating value of not
               less than nine hundred ninety-five (995) Btus per standard cubic
               foot on a dry basis, but with the consent of Shipper, PGT may
               deliver gas at a lower gross heating value.

           (b) Freedom from Objectionable Matter:  The gas:

               (1)   Shall be commercially free from sand, dust, gums, crude
                     oil, impurities and other objectionable substances which
                     may be injurious to pipelines or which may interfere with
                     its transmission through pipelines or its commercial
                     utilization.

               (2)   Shall not have a hydrocarbon dew-point in excess of fifteen
                     degrees (15/./) Fahrenheit at pressures up to eight hundred
                     (800) psig.

               (3)   Shall not contain more than one-quarter (1/4) grain of
                     hydrogen sulfide per one hundred        (100) standard
                     cubic feet.

               (4)   Shall not contain more than ten(10) grains of total sulphur
                     per one hundred (100) standard cubic feet.

               (5)   Shall not contain more than two percent (2%) by volume of
                     carbon dioxide.

               (6)   Shall not contain more than four (4) pounds of water vapor
                     per one million (1,000,000) standard cubic feet.

               (7)   Shall not exceed one hundred ten degrees (110/./)
                     Fahrenheit in temperature at the point of measurement.

               (8)   Shall be as free of oxygen as it can be kept through the
                     exercise of all reasonable precautions, and shall not in
                     any event contain more than four-tenths of one percent
                     (0.4%) by volume of oxygen.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      Second Revised Sheet No. 57
First Revised Volume No. 1-A              Superseding
                                                      First Revised Sheet No. 57
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

3.  QUALITY OF GAS (Continued)

 3.2    Quality Tests:

         (a) The quality specifications of the gas received by PGT hereunder
             shall be determined by tests which PGT shall cause to be made at
             the International Boundary or such other locations on PGT's system
             if required accordance with this Paragraph 3.2.

         (b) The gross heating value of gas delivered hereunder shall be
             determined from read-outs of continuously operating measuring
             instruments.  The method shall consist of one or more of the
             following:

            (1)  calorimeter

            (2)  gas chromatograph

            (3)  any other method mutually agreed upon by the parties.

             Measurement of gross heating value with the calorimeters shall
             comply with the standards set forth in the American Society for
             Testing and Materials' ASTM D 1826.  Analysis of gas with gas
             chromatograph shall comply with the standards set forth in ASTM D
             1945.  Calculation of the gross heating value from compositional
             analysis by gas chromatography shall comply with the standards set
             forth in ASTM D 3588.

             PGT or its agent shall calibrate and maintain the gross heating
             value measurement device at intervals as agreed upon by PGT and
             Shipper.  Shipper shall have access to PGT's devices and shall be
             allowed to inspect the devices and all charts or other records of
             measurement at any reasonable time.



                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: AUGUST 13, 1996                         Effective: SEPTEMBER 13, 1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                            Original Sheet No. 58
First Revised Volume No. 1-A
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)
3.  QUALITY OF GAS (Continued)

 3.2    Quality Tests (Continued)

        (c) Tests shall be made to determine the total sulphur, hydrogen
            sulfide, carbon dioxide and oxygen content of the gas, by approved
            standard methods in general use in the gas industry, and to
            determine  the hydrocarbon dew-point and water vapor content of such
            gas by methods satisfactory to the parties.  Tests shall be made
            frequently enough to ensure that the gas is conforming continuously
            to the quality requirements.  Shipper shall have the right to
            require PGT to have remedied any deficiency in quality of the gas
            and, in the event such deficiency is not remedied, the right, in
            addition to all other remedies available to it by law, to refuse to
            accept such deficient gas until such deficiency is remedied.

4.  MEASURING EQUIPMENT

 4.1    Installation:  Unless PGT and Shippers agree otherwise, all gas volume
        measuring equipment, devices and materials at the point(s) of receipt
        and/or delivery shall be furnished and installed by PGT at Shipper's
        expense including the tax-on-tax effect.   All such equipment, devices
        and materials shall be owned, maintained and operated by PGT.  Shipper
        may install and operate check measuring equipment provided it does not
        interfere with the use of PGT's equipment.

 4.2    Testing Meter Equipment:  The accuracy of either PGT's or Shippers
        measuring equipment shall be verified by test, using means and methods
        acceptable to the other party, at intervals mutually agreed upon, and at
        other times upon request.  Notice of the time and nature of each test
        shall be given by the entity conducting the test to the other entity
        sufficiently in advance to permit convenient arrangement for the
        presence of the representative of the other entity.  If, after notice,
        the other entity fails to have a representative present, the results of
        the test shall nevertheless be considered accurate until the next test.
        If any of the measuring equipment is found to be registering
        inaccurately  in any  percentage, it shall be adjusted at once to read
        as accurately as possible.   All  tests  of such  measuring equipment
        shall be made at the expense of the entity conducting the same, except
        that the other entity shall bear the expense of tests made at its
        request if the inaccuracy is found to be two percent (2%) or less.
        (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: AUGUST 02, 1993                          Effective: NOVEMBER 01, 1993
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RS92-46-000, et al, dated JULY 12, 1993


 
Pacific Gas Transmission Company
FERC Gas Tariff                                            Original Sheet No. 59
First Revised Volume No. 1-A
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

4.  MEASURING EQUIPMENT (Continued)

 4.3    Correction and Adjustment:  If at any time any of the measuring

        equipment is registering inaccurately by an amount exceeding two percent
        (2%) at a reading corresponding to the average hourly rate of flow, the
        previous readings of such equipment shall be corrected to zero error for
        any period definitely known or agreed upon, or if not so known or agreed
        upon, one-half (1/2) of the elapsed time since the last test.  If the
        measuring equipment is out-of-service, the volume of gas delivered
        during such period shall be determined:

        (a) By using the data recorded by any check measuring equipment
            accurately registering; or

        (b) If such check measuring equipment is not registering accurately but
            the percentage of error is ascertainable by a calibration test, by
            using the data recorded, corrected to zero error; or

        (c) If neither of the methods provided in (a) and (b) above can be used,
            by estimating the quantity delivered, by reference to deliveries
            under similar conditions during a period when the equipment was
            registering accurately.

            No correction shall be made in the recorded volumes of gas delivered
            hereunder for measuring equipment inaccuracies of two percent (2%)
            or less, and in no event shall inaccuracies less than 25 Mcf be
            considered for adjustment.



                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: AUGUST 02, 1993                          Effective: NOVEMBER 01, 1993
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RS92-46-000, et al, dated JULY 12, 1993


 
Pacific Gas Transmission Company
FERC Gas Tariff                                       First Revised Sheet No. 60
First Revised Volume No. 1-A              Superseding
                                                           Original Sheet No. 60
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

5.  MEASUREMENTS

         5.1  Metering: The gas shall be metered by one or more orifice,
              turbine, or displacement-type meters, at the discretion of PGT.
              When orifice meters are used, they shall be installed and
              maintained, and volumes shall be measured, in accordance with the
              methods prescribed in ANSI/API 2530, also published as A.G.A No.
              3. When turbine meters are used, they shall be installed and
              maintained, and volumes shall be measured, in accordance with
              methods prescribed in AGA Report No. 4 or any subsequent revision.
              When displacement meters are used, they shall be installed and
              maintained and quantities shall be measured in accordance with
              methods prescribed in A.G.A. No. 2, and the number of Mcf
              delivered hereunder shall be computed by including factors for
              pressure, temperature and deviation from Boyle's Law. To
              accurately determine the deviation from Boyle's Law, a
              quantitative analysis of the gas components shall be made at
              reasonable intervals with such apparatus as shall be agreed upon
              by both parties.

         5.2  Specific Gravity: The specific gravity of the gas delivered
              hereunder shall be determined from the read-outs of continuously
              operating measuring instruments. The method shall consist of one
              of the following:

         (a)  gravitometer
         (b)  gas chromatography
         (c)  other instruments acceptable to both parties

         Analysis of chromatograph shall comply with the standards set forth in
         ASTM D 1945. Calculation of the specific gravity from compositional
         analysis by gas chromatography shall comply with the standards set
         forth in ASTM D 3588. Measurement of the specific gravity with a
         gravitometer shall comply with the standards set forth in ASTM D 1070.

         5.3  Flowing Temperature:  Flowing gas temperature shall be
             continuously measured and used in flow calculations.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994


 
Pacific Gas Transmission Company
FERC Gas Tariff                                       First Revised Sheet No. 61
First Revised Volume No. 1-A              Superseding
                                                           Original Sheet No. 61
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)


6.  INSPECTION OF EQUIPMENT AND RECORDS

  6.1  Inspection of Equipment and Data: PGT and Shipper shall have the right to
       inspect equipment installed or furnished by the other, and the charts and
       other measurement or test data of the other, at all times during business
       hours; but the reading, calibration and adjustment of such equipment and
       changing of charts shall be done only by the entity installing or
       furnishing same. Unless PGT and Shipper otherwise agree, each shall
       preserve all original test data, charts and other similar records in such
       party's possession, for a period of at least six (6) years.

  6.2  Information for Billing: When information necessary for billing by PGT is
       in the control of Shipper, Shipper shall furnish such information,
       estimated if actual is not available, to PGT on or before the third (3rd)
       working day of the month following the month transportation service was
       rendered. If shipper furnishes estimated information, the actual
       information shall be furnished to PGT on or before the sixth (6th)
       working day of the month following the month transportation service was
       rendered.

  6.3  Verification of Computations: PGT and Shipper shall have the right to
       examine at reasonable times the books, records and charts of the other to
       the extent necessary to verify the accuracy of any statement, charge or
       computation made pursuant to these Transportation General Terms and
       Conditions and to the rate schedules to which they apply, within twelve
       (12) months of any such statement, charge or computation.

7.  BILLING

  7.1  Billing under all Rate Schedules: On or before the twentieth (20th) day
       of each month, PGT shall render a bill to each Shipper under all
       applicable Rate Schedules for the service(s) rendered during the
       preceding month.


                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 24, 1994                           Effective: MARCH 27, 1994


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      Second Revised Sheet No. 62
First Revised Volume No. 1-A              Superseding
                                                      First Revised Sheet No. 62
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)


8.  PAYMENT

  8.1  Payment under all Rate Schedules: On or before the last day of each
       month, each Shipper under all applicable Rate Schedules shall pay to or
       upon the order of PGT in lawful money of the United States at PGT's
       office in Portland, Oregon, the amount of the bill rendered by PGT during
       the month in accordance with Paragraph 7.1 of these Transportation
       General Terms and Conditions.

  8.2  Interest on Unpaid Amounts: Should Shipper fail to pay the amount of any
       bill rendered by PGT when such amount is due, interest thereon shall
       accrue from the due date until paid at the rate of interest effective
       from time to time under 18 CFR Section 154.67.

  8.3  Remedies for Failure to Pay: If such failure to pay continues for thirty
       (30) days after payment is due, PGT, in addition to any other remedy it
       may have, may suspend further delivery of gas until such amount is paid,
       unless Shipper in good faith disputes the amount owing and pays such
       amount as it concedes to be correct. Either party may submit to
       arbitration in accordance with Paragraph 14 of these Transportation
       General Terms and Conditions any dispute as to the amount due PGT
       hereunder.

  8.4  Late Billing: If presentation of a bill by PGT is delayed after the date
       specified in Paragraph 7.1 hereof, then the time for payment shall be
       extended correspondingly unless Shipper is responsible for such delay.

  8.5  Adjustment of Billing Error: In the event an error is discovered in any
       bill rendered by PGT, the amount of such error shall be adjusted,
       provided that claim therefor shall have been made within twelve (12)
       months from the date such bill was rendered. The adjustment shall be made
       within thirty (30) days of such timely claim.

                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: OCTOBER 18, 1995                         Effective: NOVEMBER 18, 1995


 
Pacific Gas Transmission Company
FERC Gas Tariff                                       First Revised Sheet No. 63
First Revised Volume No. 1-A              Superseding
                                                           Original Sheet No. 63
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)


9.  NOTICE OF CHANGES IN OPERATING CONDITIONS

         PGT and Shipper shall each ensure that the other is notified from time
         to time as necessary of expected changes in the rates of delivery or
         receipt of gas, or in the pressures or other operating conditions, and
         the reason for such expected changes, so that they may be accommodated
         when they occur.

10. FORCE MAJEURE

         10.1  If either party shall fail to perform any obligation imposed upon
               it by these Transportation General Terms and Conditions or by an
               executed Transportation Service Agreement, and such failure shall
               be caused, or materially contributed to, by force majeure which
               means any acts of God, strikes, lockouts, or other industrial
               disturbances, acts of public enemies, sabotage, wars, blockades,
               insurrections, riots, epidemics, landslides, lightning,
               earthquakes, floods, storms, fires, washouts, extreme cold or
               freezing weather, arrests and restraints of rulers and people,
               civil disturbances, explosions, breakage of or accident to
               machinery or lines of pipe, hydrate obstructions of lines of
               pipe, inability to obtain pipe, materials or equipment,
               legislative, administrative or judicial action which has been
               resisted in good faith by all reasonable legal means, any acts,
               omissions or causes whether of the kind herein enumerated or
               otherwise not reasonably within the control of the party invoking
               this paragraph and which by the exercise of due diligence such
               party could not have prevented, the necessity for making repairs
               to, replacing, or reconditioning machinery, equipment, or
               pipelines not resulting from the fault or negligence of the party
               invoking this paragraph, such failure shall be deemed not to be a
               breach of the obligation of such party, but such party shall use
               reasonable diligence to put itself in a position to carry out its
               obligations. Nothing contained herein shall be construed to
               require either party to settle a strike or lockout by acceding
               against its judgment to the demands of the opposing parties.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994


 
Pacific Gas Transmission Company
FERC Gas Tariff                                       First Revised Sheet No. 64
First Revised Volume No. 1-A              Superseding
                                                           Original Sheet No. 64
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)


10.  FORCE MAJEURE (Continued)

     10.2  No such cause as described in Paragraph 10.1 affecting the
           performance of either party shall continue to relieve such party from
           its obligation after the expiration of a reasonable period of time
           within which by the use of due diligence such party could have
           remedied the situation preventing its performance, nor shall any such
           cause relieve either party from any obligation unless such party
           shall give notice thereof in writing to the other party with
           reasonable promptness; and like notice shall be given upon
           termination of such cause.

     10.3  No cause whatsoever, including without limitation the failure of PGT
           to perform including the causes specified in Paragraph 10.1, shall
           relieve Shipper from its obligations to make payments due, including
           the payments of reservation charges for the duration of such cause
           except as provided for in Paragraphs 3.10 and 3.11 of Rate Schedule
           FTS-1.

11.  WARRANTY OF ELIGIBILITY FOR TRANSPORTATION

     Any Shipper transporting gas on the PGT system under this FERC Gas Tariff
     First Revised Volume No. 1-A warrants for itself, its successors and
     assigns, that it will have at the time of delivery of the gas to PGT
     hereunder good title to such gas and that all gas delivered to PGT for
     transportation hereunder is eligible for the requested transportation in
     interstate commerce under applicable rules, regulations or orders of the
     FERC, or other agency having jurisdiction. Shipper will indemnify PGT and
     save it harmless from all suits, actions, damages, costs, losses, expenses
     (including reasonable attorney fees) and costs connected with regulatory
     proceedings, arising from breach of this warranty.

12.  POSSESSION OF GAS AND RESPONSIBILITY

     PGT shall be deemed to be in control and possession of, and responsible
     for, all gas delivered from the time that such gas is received by it at the
     point of receipt to the time that it is delivered at the point of delivery.


                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994


 
Pacific Gas Transmission Company
FERC Gas Tariff                                            Original Sheet No. 65
First Revised Volume No. 1-A
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)
13.  INDEMNIFICATION

     Shipper agrees to indemnify and hold harmless PGT, its officers, agents,
     employees and contractors against any liability, loss or damage whatsoever
     occurring in connection with or relating in any way to the executed
     Transportation Service Agreement, including costs and attorneys' fees,
     whether or not such liability, loss or damage results from any demand,
     claim, action, cause of action, or suit brought by Shipper or by any
     person, association or entity, public or private, that is not a party to
     the executed Transportation Service Agreement, where such liability, loss
     or damage is suffered by PGT, its officers, agents, employees or
     contractors as a direct or indirect result of any breach of the executed
     Transportation Service Agreement or sole or concurrent negligence or gross
     negligence or other tortious act(s) or omission(s) by Shipper, its
     officers, agents, employees or contractors.

14.  ARBITRATION

     Any arbitration provided for or agreed to by Shipper and PGT shall be
     conducted in accordance with the following procedures and principles:

     Upon the written demand of either PGT or Shipper and within ten (10) days
     from the date of such demand, each entity shall appoint an arbitrator and
     the two arbitrators so appointed shall promptly thereafter appoint a third.
     If either PGT or Shipper shall fail to appoint an arbitrator within ten
     (10) days from the date of such demand, then the arbitrator shall be
     appointed by a Superior Court of the State of California in accordance with
     the California Code of Civil Procedure. If the two arbitrators shall fail
     within ten (10) days from their appointment to agree upon and appoint the
     third arbitrator, then upon the application of either PGT or Shipper such
     third arbitrator shall be appointed by a Superior Court of the State of
     California in accordance with the California Code of Civil Procedure.

     The arbitrators shall proceed immediately to hear and determine the matter
     in controversy. The award of the arbitrators, or a majority of them, shall
     be made within forty-five (45) days after the appointment of the third
     arbitrator, subject to any reasonable delay due to unforeseen
     circumstances. The award of the arbitrators shall be drawn up in writing
     and signed by the arbitrators, or a majority of them, and shall be final
     and binding on both PGT and Shipper, and PGT and Shipper shall abide by the
     award and perform the terms and conditions thereof. Unless otherwise
     determined by the arbitrators, the fees and expenses of the arbitrator
     named for each party shall be paid by that party and the fees and expenses
     of the third arbitrator shall be paid in equal proportion by both PGT and
     Shipper.   
                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: AUGUST 02, 1993                          Effective: NOVEMBER 01, 1993
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RS92-46-000, et al, dated JULY 12, 1993


 
Pacific Gas Transmission Company
FERC Gas Tariff                                            Original Sheet No. 66
First Revised Volume No. 1-A
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)
15.  GOVERNMENTAL REGULATIONS

     These Transportation General Terms and Conditions, the rate schedules to
     which they apply, and any executed Transportation Service Agreement are
     subject to valid laws, orders, rules and regulations of duly constituted
     authorities having jurisdiction.

16.  MISCELLANEOUS PROVISION

     16.1   Waiver of Default: No waiver by either PGT or Shipper of any default
            by the other in the performance of any provisions of an executed
            Transportation Service Agreement shall operate as a waiver of any
            continuing or future default, whether of a like or different
            character.

     16.2   Assignability: An executed Transportation Service Agreement shall
            bind and inure to the respective successors and assignees of PGT and
            Shipper thereto, but no assignment shall release either party
            thereto from such party's obligations without the written consent of
            the other party, which consent shall not be unreasonably withheld;
            provided, however, nothing contained herein shall give Shipper the
            right to reassign or broker its right to ship the quantities of gas
            specified in the Transportation Service Agreement on PGT's system to
            others. Further, nothing contained herein shall prevent either party
            from pledging, mortgaging or assigning its rights as security for
            its indebtedness and either party may assign to the pledgee or
            mortgagee (or to a trustee for the holder of such indebtedness) any
            money due or to become due under any service agreement.

     16.3   Effect of Headings: The headings used throughout these
            Transportation General Terms and Conditions, the rate schedules to
            which they apply, and the executed Transportation Service Agreements
            are inserted for reference purposes only and are not to be
            considered or taken into account in construing the terms and
            provisions of any paragraph nor to be deemed in any way to qualify,
            modify or explain the effects of any such terms or provisions.

17.  TRANSPORTATION SERVICE AGREEMENT

     17.1   Form: Shipper shall enter into a contract with PGT utilizing PGT's
            appropriate standard form of Transportation Service Agreement.
     17.2   Term: The term of the Transportation Service Agreement shall be
            agreed upon between Shipper and PGT at the time of the execution
            thereof.
                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: AUGUST 02, 1993                          Effective: NOVEMBER 01, 1993
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RS92-46,000, et al., dated JULY 12, 1993


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      Second Revised Sheet No. 67
First Revised Volume No. 1-A              Superseding
                                                      First Revised Sheet No. 67
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

18.  OPERATING PROVISIONS

     Initial Service: For purposes of scheduling commencement of initial
     transportation service five (5) business days prior to the day on which
     Shipper desires service to commence, or such lesser period of time as
     mutually agreed upon by PGT and Shipper, Shipper will provide PGT a
     completed Customer Nomination Form provided to:

          Pacific Gas Transmission Company 
          Gas Transportation and Services 
          2100 Southwest River Parkway 
          Portland, OR 97201 
          Phone - 503-833-4300 
          Fax -503-833-4396

     Shipper shall not be entitled to receive transportation service under this
     FERC Gas Tariff First Revised Volume No. 1-A if Shipper is not current in
     its payments to PGT for any charge, rate or fee authorized by the
     Commission for transportation service; provided, however, if the amount not
     current pertains to a bona fide dispute, including but not limited to force
     majeure claims relating to this FERC Gas Tariff, Shipper shall be entitled
     to receive or continue to receive transportation service if Shipper posts a
     bond satisfactory to PGT to cover the payment due PGT.

     18.1 Firm Service

          The provisions of this Paragraph 18.1 shall be applicable to firm
          transportation service under Rate Schedule FTS-1 contained in this
          First Revised Volume No. 1-A. Firm transportation service under this
          First Revised Volume No. 1-A shall be provided when, and to the extent
          that, PGT determines that firm capacity is available on PGT's existing
          facilities. PGT shall not be required to provide firm transportation
          service in the event firm capacity is unavailable or to construct new
          facilities to provide firm service.

                                                          (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: OCTOBER 18, 1995                         Effective: NOVEMBER 18, 1995


 
Pacific Gas Transmission Company
FERC Gas Tariff                                       First Revised Sheet No. 68
First Revised Volume No. 1-A              Superseding
                                                           Original Sheet No. 68
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

18.  OPERATING PROVISIONS (Continued)

  18.1   Firm Service (Continued)

         For capacity that becomes available other than the circumstances
         identified in Paragraphs 28 and 33, requests for firm capacity shall be
         accommodated in the following manner and subject to the following
         conditions and limitations:

         (a) In order to be eligible for firm capacity, a party requesting
             service (requestor) must be deemed credit-worthy per Paragraph 18.3
             and submit a valid request in accordance with the provisions
             herein.

         (b) PGT will post on Pacific Trail, PGT's Electronic Bulletin Board
             (EBB), available capacity. A requestor that submits a valid request
             may submit a bid via the EBB for the available capacity subsequent
             to PGT's posting of such capacity on the EBB. The Bid Period will
             be 5 business days, during which time other requestors with valid
             requests may submit a bid. All bids not withdrawn prior to the
             close of the Bidding Period shall be binding. At the end of the
             Bidding Period, PGT will evaluate the bids and determine the bid(s)
             having the greatest economic value as determined in Paragraph
             18.1(c) below.

         (c) After the close of the Bidding Period, PGT may tender a Service
             Agreement for execution to the requestor(s) submitting the bid(s)
             having the greatest economic value for the capacity available,
             subject to the provisions of Paragraph 18.1(e). The criteria for
             determining which requestor(s) has submitted the bid(s) with the
             greatest economic value shall be the Net Present Value (NPV) of the
             reservation charge as calculated at Paragraph 28 that requestor(s)
             would pay at the rates requestor(s) has bid, which shall not be
             less than the Minimum Rate nor greater than the Maximum Rate, as
             stated on the currently effective Statement of Rates and Charges
             governing such service, over the term of service specified in the
             request. If the economic values of separate bids are equal, then
             service shall be offered to such requestors on a pro-rata basis.

                                                            (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994


 
Pacific Gas Transmission Company
FERC Gas Tariff                                       First Revised Sheet No. 69
First Revised Volume No. 1-A              Superseding
                                                           Original Sheet No. 69
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

18.  OPERATING PROVISIONS (Continued)

  18.1   Firm Service (Continued)

         (d) If PGT accepts the winning bid(s) and tenders a Service Agreement,
             requestor(s) shall complete and return the Service Agreement within
             thirty (30) days.
         (e) Except as provided in Paragraph 28, PGT shall not be obligated to
             tender or execute a Service Agreement for service at any rate less
             than the Maximum Rate set forth in the Statement of Effective Rates
             and Charges applicable to the service requested.
         (f) A Shipper receiving service under FTS-1 shall not lose its priority
             for purposes of Paragraph 19 by the renewal or extension of term of
             that service; provided, however, any renewal or extension must be
             pursuant to a rollover or evergreen provision of the Service
             Agreement.  Shipper's preexisting priority shall not apply,
             however, to any increase in transportation quantity or new primary
             point of delivery.

  18.2   Interruptible Service

         The provisions of this Paragraph 18.2 shall be applicable to
         interruptible transportation service under Rate Schedule ITS-1
         contained in this First Revised Volume No. 1-A.
         (a) Interruptible transportation service under this First Revised
             Volume No. 1-A shall be provided when, and to the extent that,
             capacity is available in PGT's existing facilities, which capacity
             is not subject to a prior claim under a pre-existing agreement
             pursuant to Rate Schedule FTS-1 or under another class of firm
             service.
         (b) In the event where natural gas tendered by Shipper to PGT at the
             receipt point(s) for transportation, or delivered by PGT to Shipper
             (or for Shipper's account) at the delivery point(s), is commingled
             with other natural gas at the time of measurement, the
             determination of deliveries applicable to Shipper shall be made in
             accordance with operating arrangements satisfactory to Shipper, PGT
             and any third party transporting to or from PGT's system.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994


 
Pacific Gas Transmission Company
FERC Gas Tariff                                       First Revised Sheet No. 70
First Revised Volume No. 1-A              Superseding
                                                           Original Sheet No. 70
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

18.  OPERATING PROVISIONS (Continued)

  18.2   Interruptible Service (Continued)

         (c) PGT shall process the requests of potential Shippers requesting
             similar interruptible transportation service under this FERC Gas
             Tariff First Revised Volume No. 1-A on a first-come, first-served
             basis, to the extent practicable, taking into account the nature
             and character of the service requested.  Available interruptible
             capacity shall be allocated by PGT on a first-come, first-served
             basis as provided in Paragraph 19 and determined by the date and
             time PGT receives a completed request for service under this FERC
             Gas Tariff which conforms to Paragraph 18 of these Transportation
             General Terms and Conditions.

         (d) A Shipper receiving service under ITS-1 shall not lose its priority
             for purposes of Paragraph 19 by the renewal or extension of term of
             that service; provided, however, any renewal or extension must be
             pursuant to a rollover or evergreen provision of the Service
             Agreement. Shipper's pre-existing priority shall not apply,
             however, to any increase in transportation quantity or new primary
             points of delivery.

         (e) If Shipper fails to nominate and tender gas within the later of:
             (a) fifteen (15) days after initial notification by PGT of the
             availability of service, (b) receipt of any necessary regulatory
             approvals, or (c) the installation of any necessary facilities,
             Shipper's priority date shall be deemed null and void, and the day
             Shipper first tenders gas to PGT at any receipt point shall be
             Shipper's new assigned priority date for service. Shipper's
             priority date designation pursuant to Section 2.3 of the
             Transportation Service Agreement shall not be deemed null and void
             if Shipper's failure to nominate and tender gas is caused by an
             event of force majeure as defined in PGT's Transportation General
             Terms and Conditions.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      First Revised Sheet No. 70A
First Revised Volume No. 1-A              Superseding
                                                          Original Sheet No. 70A
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

18.  OPERATING PROVISIONS (Continued)

  18.3   Credit-worthiness

         (A) Credit-worthiness for Firm Transportation Service

             (1)  PGT shall not be required to perform or to continue
                  transportation service under this FERC Gas Tariff First
                  Revised Volume 1-A on behalf of any Shipper who is or has
                  become insolvent or who, after PGT's request, fails within a
                  reasonable period to establish or confirm credit-worthiness.
                  Shippers shall provide, initially and on a continuing basis,
                  financial statements, evidence of debt and/or credit ratings,
                  and other such information as is reasonably requested by PGT
                  to establish or confirm Shipper's qualification for service.
                  Credit limits will be established based on the level of
                  requested service and Shipper credit-worthiness as established
                  by the following:

             (a)  Credit-worthiness must be evidenced by at least a long term
                  bond (or other senior debt) rating of BBB or an equivalent
                  rating.

                  Such rating may be obtained in one of three ways:

                  (i)  The rating will be determined by Standard and Poors or
                       another recognized U.S. or Canadian debt rating service;
 
                  (ii) If Shipper's debt is not rated by a recognized debt
                       rating service, an equivalent rating as determined by
                       PGT, based on the financial rating methodology, criteria
                       and ratios for the industry of the Shipper as published
                       by the above rating agencies from time to time. In
                       general, such equivalent rating will be based on the
                       audited financial statements for the Shipper's two most
                       recent fiscal years, all interim reports, and any other
                       relevant information;

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: APRIL 20, 1994                                Effective: MAY 21, 1994


 
Pacific Gas Transmission Company
FERC Gas Tariff                                       Third Revised Sheet No. 71
First Revised Volume No. 1-A              Superseding
                                                     Second Revised Sheet No. 71
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

18.  OPERATING PROVISIONS (Continued)

  18.3   (A) Credit-worthiness for Firm Transportation Service (Continued)

                (iii)  Shipper may, at its own expense, obtain a private rating
                       from a recognized debt rating service, or request that an
                       independent accountant or financial advisor, mutually
                       acceptable to PGT and the Shipper, prepare an equivalent
                       evaluation based on the financial rating methodology,
                       criteria, and ratios for the industry of the Shipper as
                       published by the above rating agencies from time to time;
                       or

             (b)  Approval by PGT's lenders; or

             (c)  If Shipper is requesting credit to bid on a parcel that is for
                  one year (365 days) or less of service through PGT's Capacity
                  Release Program contained in Paragraph 28, and this option is
                  selected by the Releasing Shipper, Shipper may demonstrate
                  credit-worthiness by providing two years of audited financial
                  statements for itself, or for its parent company if it is a
                  subsidiary which is consolidated with its parent company and
                  does not issue stand-alone financial statements, demonstrating
                  adequate financial strength to justify the amount of credit to
                  be extended.  PGT shall apply consistent evaluation practices
                  to determine credit-worthiness.

             (2)  If Shipper does not establish or maintain credit-worthiness as
                  described above, Shipper has the option of receiving
                  transportation service under this FERC Gas Tariff by providing
                  to PGT one of the following alternatives:



                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: AUGUST 13, 1996                         Effective: SEPTEMBER 13, 1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      Second Revised Sheet No. 72
First Revised Volume No. 1-A              Superseding
                                                      First Revised Sheet No. 72
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

18.      OPERATING PROVISIONS (Continued)

  18.3   (A) Credit-worthiness for Firm Transportation Service (Continued)

             (a)  A guarantee of Shipper's financial performance in a form
                  satisfactory to PGT and for the term of the Gas Transportation
                  Agreement from a corporate affiliate of the Shipper or a third
                  party either of which meets the credit-worthiness standard
                  discussed above.

             (b)  Other security acceptable to PGT's lenders.

  18.3 (B)  Credit-worthiness for Interruptible Transportation Service

         (1)  PGT shall not be required to perform or to continue interruptible
         transportation service under this FERC Gas Tariff First Revised Volume
         No. 1-A on behalf of any Shipper who is or has become insolvent or who,
         at PGT's request, fails within a  reasonable period to demonstrate
         credit-worthiness.  Shipper's credit-worthiness shall be determined by
         providing proof of least two of the items listed below:

             (a)  A long-term bond or commercial paper rating from Standard and
                  Poors or Moody's equivalent to a "Ba" or better, or a
                  commercial paper rating from Standard and Poors or Moody's
                  equivalent to Prime-3 or better.

             (b)  Audited financial statements for itself, or for its parent
                  company if it is a subsidiary which is consolidated with its
                  parent company and does not issue stand-alone financial
                  statements, for the two preceding years showing good financial
                  strength.

             (c)  An estimated financial strength rating by Dun and Bradstreet
                  sufficient to cover the credit to be extended and a
                  corresponding Dun and Bradstreet composite credit appraisal of
                  "fair" or better.

                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: AUGUST 13, 1996                         Effective:SEPTEMBER 13, 1996 



 
Pacific Gas Transmission Company
FERC Gas Tariff                                       First Revised Sheet No. 73
First Revised Volume No. 1-A              Superseding
                                                           Original Sheet No. 73
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

18.  OPERATING PROVISIONS (Continued)

     18.3 (B)  Credit-worthiness for Interruptible Transportation Service
           (Continued)

                (d)  A demonstration by the Shipper that the Company has
                     sufficient financial capacity or backing to warrant an
                     extension of credit. This demonstration could include proof
                     of banking relationships sufficient to cover the service
                     agreement, or a detailed listing of credit references
                     within the industry, exhibiting a good credit history.

          (2)  If Shipper does not demonstrate credit-worthiness, Shipper has
               the option of receiving interruptible transportation service
               under this FERC Gas Tariff First Revised Volume No. 1-A if
               Shipper provides PGT a letter of credit in an amount equal to the
               cost of performing the maximum level of service requested for a
               three (3) month period of time. The letter of credit must be from
               a credit worthy financial institution and be in place before the
               Transportation Service Agreement can be signed. The Shipper also
               has the option of receiving transportation service if Shipper
               prepays for transportation services on a month-to-month basis
               pursuant to the following terms:
               (a)  For a calendar month in which transportation service is
                    desired (delivery month), Shipper must notify PGT no later
                    than eight (8) business days prior to the commencement of
                    delivery month (estimation date) of its estimation of the
                    maximum, cumulative gas deliveries (monthly estimation)
                    desired for the delivery month. (For Shipper's initial
                    monthly estimation, the delivery month, or remaining portion
                    thereof, shall commence eight (8) days after the estimation
                    date.) Notice of monthly estimation may be telephonic or
                    written; telephonic notices must be confirmed in writing and
                    received by PGT within five (5) business days. PGT will
                    advise Shipper within forty-eight (48) hours of the
                    estimation date of the exact dollar amount of the
                    prepayment. Shipper shall not deliver or receive gas in
                    excess of the monthly estimation during delivery month.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994

 
Pacific Gas Transmission Company
FERC Gas Tariff                                       First Revised Sheet No. 74
First Revised Volume No. 1-A              Superseding
                                                           Original Sheet No. 74
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

18.      OPERATING PROVISIONS (Continued)

  18.3 (B)  Credit-Worthiness for Interruptible Transportation Service
             (Continued)

         (b) No later than three (3) business days (settlement date) prior to
             commencement of delivery month, Shipper shall pay to PGT and PGT
             shall have received from Shipper lawful money  of the United States
             in an amount equal to the prepayment  amount provided to Shipper by
             PGT described above.

         (c) On or before the twentieth (20th) day following delivery month, PGT
             shall provide a statement to Shipper detailing the transportation
             service provided during the delivery month.  The statement will
             reconcile the amount prepaid in accordance with the monthly
             estimation, with the actual cost  of transportation service
             provided, and provide a credit to Shipper, if applicable.  Any such
             credit will be deducted  from the prepayment for the following
             month.  Should the  Shipper elect not to receive transportation
             services for the following month, Shipper shall so notify PGT in
             writing; PGT  will issue a check to the Shipper within seven (7)
             business days following receipt by PGT of such notice.

  18.3 (C)  Credit-worthiness for Firm and Interruptible Transportation Service

             For purposes of this FERC Gas Tariff First Revised Volume No. 1-A
             the insolvency of a Shipper shall be evidenced by the filing by
             such  Shipper or any parent entity thereof (hereinafter
             collectively referred in this paragraph to as "the Shipper") of a
             voluntary petition in bankruptcy or the entry of a decree or order
             by a court having jurisdiction in the premises adjudging the
             Shipper as bankrupt or insolvent, or approving as properly filed a
             petition  seeking reorganization, arrangement, adjustment or
             composition of or in respect of the Shipper under the Federal
             Bankruptcy Act or any Act or any other applicable federal or state
             law, or appointing a receiver, liquidator, assignee, trustee,
             sequestrator (or other similar official) of the Shipper

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994

 
Pacific Gas Transmission Company
FERC Gas Tariff                                       First Revised Sheet No. 75
First Revised Volume No. 1-A              Superseding
                                                           Original Sheet No. 75
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)


18.      OPERATING PROVISIONS (Continued)

  18.3   (C) Credit-worthiness for Firm and Interruptible Transportation Service
             (Continued)

             or composition of or in respect of the Shipper under the Federal
             Bankruptcy Act or any Act or any other applicable federal or state
             law, or appointing a receiver, liquidator, assignee, trustee,
             sequestrator (or other similar official) of the Shipper or of any
             substantial part of its property, or the ordering of the winding-up
             liquidation of its  affairs, with said order or decree continuing
             unstayed and in effect for a period of sixty (60) consecutive days.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994

 
Pacific Gas Transmission Company
FERC Gas Tariff                                       First Revised Sheet No. 76
First Revised Volume No. 1-A              Superseding
                                                           Original Sheet No. 76
________________________________________________________________________________

 
                      TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

18.  OPERATING PROVISIONS (Continued)

  18.4   Upon request of PGT, Shipper shall from time to time submit estimates
         of daily, monthly and annual quantities of gas to be transported,
         including peak day requirements.

  18.5   PGT shall not be obligated to install additional facilities, other than
         those specified in Paragraph 4.1 herein, that are required to provide
         service under this FERC Gas Tariff First Revised Volume No. 1-A;
         provided, however, PGT may install or Shipper may pay all of the
         expenses incurred for installing additional facilities on a
         nondiscriminatory basis and under terms that are mutually agreeable. In
         the event PGT incurs the cost of installing additional facilities on
         behalf of a Shipper, Shipper shall pay, in addition to the rate(s)
         stated in the applicable rate schedule, the prorated(based on
         Transportation Contract Demand) cost of service attributable to any
         such additional facilities until such time as a different allocation
         procedure is specified by Commission order.

  18.6   No transportation service will be conducted for the account of Shipper
         by PGT until PGT has received the completed service request form,
         unedited and complete as to form, and Shipper has been advised by PGT
         that the transportation service may commence.

  18.7   Requests for interruptible and firm transportation service hereunder
         shall be made by providing the information contained in PGT's
         Transportation Request Form to PGT.



                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994

 
Pacific Gas Transmission Company
FERC Gas Tariff                                       First Revised Sheet No. 77
First Revised Volume No. 1-A              Superseding
                                                           Original Sheet No. 77
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

18.      OPERATING PROVISIONS (Continued)

         18.8   Transportation Request Form

Gentlemen:

________________________________ (Shipper) hereby requests gas transportation
service from Pacific Gas Transmission Company (PGT) in accordance with Paragraph
18.8 of the Transportation General Terms and Conditions of PGT's tariff and
concurrently provides the following information relative to this request:

1.  Shipper's Name  ___________________________________________
    Business Address __________________________________________
    State or Province of Incorporation ________________________

2.  Requesting Party ____________________ Title _______________
    Contact Name ________________________ Phone _______________

3.  Shipper's Status: LDC ____  Intrastate ____  End User ____
    (Check one)       Producer ____  Marketer/Broker __________
                      Gatherer ____  Interstate ____
                      Other __________________________________

4.   Type of Service Requested:  (Check all applicable)
     a.  Part 284  Interruptible ____
     b.  Part 284  Firm ____*
     c.  New Service ____
     d.  Amendment to PGT Contract #_______
     e.  Add/Change Receipt/Delivery Point ____
     f.  Authority to Bid for Released Capacity ____

     * PGT will accept requests for firm transportation service.  At such time
     that firm capacity may become available, PGT will evaluate such requests.
     Currently, no excess firm capacity is available on the PGT system.

5.   Type of Authority: Blanket Section 7 (Part 284,
                        Subpart G)____
                        Section 311(a) (Part 284, Subpart B)____

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994

 
Pacific Gas Transmission Company
FERC Gas Tariff                                      Second Revised Sheet No. 78
First Revised Volume No. 1-A              Superseding
                                                      First Revised Sheet No. 78
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

18.  OPERATING PROVISIONS (Continued)

     18.8   Transportation Request Form (Continued)

6.   If Shipper requests service under Section 311(a), provide the following
     information concerning the party on whose behalf the transportation will be
     provided (the "On Behalf of" party):

     (a)  The exact legal name of the "On Behalf Of" party:
     ________________________________________________________________  
     (b)  The "On Behalf Of" party's address (if other than Shipper):
     ________________________________________________________________
     ________________________________________________________________
     ________________________________________________________________
     (c)  Is the "On Behalf Of" party:
                 A Local Distribution Company ______
                 An Intrastate Pipeline       ______

7.   If Shipper requests service under Section 311(a), Shipper must provide a
     certification that the service qualifies under 18 C.F.R. (S) 284.102.  To
     enable PGT to verify that the requested transportation service will qualify
     under 18 C.F.R. (S) 284.102, the certification must provide facts showing
     that:

     (a)  the "On Behalf Of" party will have physical custody of and
          transport the natural gas at some point; or

     (b)  the "On Behalf Of" party will hold title to the natural gas at
          some point, which may occur prior to , during, or after the time that
          the gas is transported by PGT, for a purpose related to the "On Behalf
          Of" party's status and function as an intrastate pipeline or its
          status and function as a local distribution company; or

     (c)  the gas will be delivered to a customer that is either located
          in the "On Behalf Of" party's service area, if the "On Behalf Of"
          party is a local distribution company, or is physically able to
          receive direct deliveries of gas from the "On Behalf Of" party, if the
          "On Behalf Of" party is an interstate pipeline, and that "On Behalf
          Of" party has certified that it is on its behalf that PGT will be
          providing the requested transportation service.  (The "On Behalf Of"
          party's certification must be submitted with the Transportation
          Request Form.)

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994

 
Pacific Gas Transmission Company
FERC Gas Tariff                                       First Revised Sheet No. 79
First Revised Volume No. 1-A              Superseding
                                                Substitute Original Sheet No. 79
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)


18.  OPERATING PROVISIONS (Continued)

     18.8   Transportation Request Form (Continued)

8.   The intended use of the gas is:
     _____ utility or pipeline system supply
     _____ end use by industry or commerce
     _____ other (specify)


9.   Requested Commencement Date _______________ (not to exceed
     3 months from request date)
     Termination Date __________________
     Evergreen clause desired (Complete for Part 284 Interruptible or Firm
     Service only):   Yes _____       No _____


10.  Transportation Quantities:
     a)   Total Maximum Daily Quantity (MDQ): __________ MMBtu/day
     b)   Total quantity for contract period: __________ MMBtu


11.  Notices to:
        _______________________________________________________
                           Mailing Address
        _______________________________________________________
                           City            State     Zip
        _______________________________________________________
                 Street Address (if P.O. Box was used above)
        _______________________________________________________
                           City            State     Zip
        _______________________________________________________
                           Attention                 Title
        _______________________________________________________
                           Telephone Number     Fax Number

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994

 
Pacific Gas Transmission Company
FERC Gas Tariff                                       First Revised Sheet No. 80
First Revised Volume No. 1-A              Superseding
                                                 Substitute Revised Sheet No. 80
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)



18.         OPERATING PROVISIONS (Continued)

     18.8   Tranportation Request Form (Continued)

            Invoices to:

                _______________________________________________________
                           Mailing Address
                _______________________________________________________
                           City            State     Zip
                _______________________________________________________
                           Street Address (if P.O. Box was used above)
                _______________________________________________________
                           City            State     Zip
                _______________________________________________________
                           Attention                 Title
                _______________________________________________________
                           Telephone Number     Fax Number



                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      Second Revised Sheet No. 81
First Revised Volume No. 1-A              Superseding
                                                      First Revised Sheet No. 81
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

19.  PRIORITY OF SERVICE, SCHEDULING AND NOMINATIONS

     19.1 Priority of Firm Service

          PGT shall provide service first for firm transportation Shippers for
          service at Shipper's primary receipt and delivery points in accordance
          with the applicable executed service agreements and rate schedules.

          Next, PGT will provide firm transportation service for service at
          Shipper's secondary receipt and delivery points or primary receipt and
          secondary delivery points in accordance with the applicable executed
          service agreements and rate schedules.

          If full service cannot be provided, PGT shall provide service on a pro
          rata basis according to the respective total Maximum Daily Demand or
          Maximum Daily Quantity, as appropriate, specified in each executed
          service agreement, first for service at Shipper's primary receipt and
          delivery points and second for service at Shipper's secondary receipt
          and delivery points.

          These provisions also apply for capacity released under PGT's capacity
          release program, and are subject to the terms and conditions as
          specified in an executed firm service agreement between PGT and
          Shipper. All service under the capacity release program shall be
          considered firm for purposes of priority of service.

     19.2 Priority of Interruptible Service

          Interruptible transportation service under this FERC Gas Tariff First
          Revised Volume No. 1-A shall be provided when, and to the extent that,
          capacity is available in PTG's existing facilities, which capacity is
          not subject to a prior claim under a pre-existing contract, service
          agreement, certificate or under Priority 1 - Firm Service. PGT will
          provide interruptible transportation service, as set forth in
          Paragraph 19 of these Transportation General Terms and Conditions, on
          a first-come, first-served basis, as determined by the date and time
          PGT receives a completed request for service conforming to Paragraph
          18.8, as approved by the Commission in Docket No. CP87-159-000.

                                                                  (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: AUGUST 13, 1996                         Effective: SEPTEMBER 13, 1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                         Original Sheet No. 81.01
First Revised Volume No. 1-A
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

19.  PRIORITY OF SERVICE, SCHEDULING AND NOMINATIONS (Continued)

     19.2 Priority of Interruptible Service

          Interruptible transportation service under this FERC Gas Tariff First
          Revised Volume No. 1-A shall be provided when, and to the extent that,
          capacity is available in PGT's existing facilities, which capacity is
          not subject to a prior claim under a pre-existing contract, service
          agreement, certificate or under Priority 1 - Firm Service. PGT will
          provide interruptible transportation service, as set forth in
          Paragraph 19 of these Transportation General Terms and Conditions,
          first to shippers paying the maximum rate in accordance with PGT's IT
          Queue, which is determined by the date and time PGT receives a
          completed request for service conforming to Paragraph 18.8, as
          approved by the Commission in Docket No. CP87-159-000.  PGT will next
          allocate capacity to shippers paying a discounted rate to the
          shipper(s) paying the highest rate.  For the purposes of this Section
          19.2, the term "highest rate" shall be determined by multiplying the
          distance in pipeline miles from the receipt point to the delivery
          point by the sum of the Base Tariff Rate, GRI Surcharge, GSR
          Surcharge, and ACA Surcharge.  In the event of a tie, shippers shall
          receive a pro-rata allocation based on the quantity that otherwise
          would be scheduled if not for the capacity limitation.

                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: AUGUST 13, 1996                         Effective: SEPTEMBER 13, 1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      First Revised Sheet No. 81A
First Revised Volume No. 1-A              Superseding
                                                          Original Sheet No. 81A
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

19.  PRIORITY OF SERVICE, SCHEDULING AND NOMINATIONS (Continued)

     19.3 Priority of Authorized Overrun Service

          Authorized overrun service shall have a priority lower than firm or
          interruptible as defined above. Priority within the overrun class
          shall be determined using a first-come, first-serve procedure.

     19.4 Nominations

          Quantities nominated for transportation shall be for previously
          approved and valid receipt and delivery points and shall be provided
          by Shipper via the Electronic Bulletin Board (EBB), to PGT's Gas
          Control no later than 10:00 a.m. Pacific Time for the following day.
          Nominations for an entire month may be made at any time up to 10:00
          a.m. Pacific Time on the last day of the month. PGT shall have the
          discretion to accept nominations at such other later times as
          operating conditions may permit and without detrimental impact to
          other Shippers and upon confirmation that corresponding upstream and
          downstream arrangements in a manner satisfactory to PGT have been
          made. The receipt of the nomination by PGT is notice that all
          necessary regulatory approvals have been received and that valid
          upstream and downstream transportation and other contractual
          arrangements are in place. Shipper shall provide as a component of its
          nomination such other information as may be required by PGT to enable
          it to identify, confirm and schedule the nomination. Shipper shall
          also prioritize nominated receipts and deliveries when there is more
          than one supplier and more than one shipper customer respectively.
          Shipper designated priorities will be used to allocate gas when the
          upstream and downstream nominations vary from PGT's Shipper
          nominations. PGT shall be allowed to rely conclusively on the
          information submitted as part of the nomination in confirming the
          nomination for scheduling and allocation.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994


 
Pacific Gas Transmission Company
FERC Gas Tariff                                     Second Revised Sheet No. 81B
First Revised Volume No. 1-A              Superseding
                                                     First Revised Sheet No. 81B
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)
19.  PRIORITY OF SERVICE, SCHEDULING AND NOMINATIONS (Continued)
     19.4 Nominations (Continued)

          Requests to amend previously scheduled nominations may be accepted
          during the gas day, subject to operational conditions and, further
          that corresponding upstream and downstream adjustments in a manner
          satisfactory to PGT can be confirmed. A request to increase a
          nomination for firm transportation up to the MDQ specified in the
          Service Agreement will be accommodated to the extent operating
          conditions permit; provided, however an increased nomination will not
          be scheduled to the extent it would affect another Shipper's flowing
          quantities during the Gas Day that the increased nomination is
          received. A request to increase a nomination for interruptible
          transportation shall be permitted only to the extent that capacity is
          available and that no displacement of other interruptible
          transportation occurs. Such changes will become effective only when
          system operating conditions, as determined by PGT, permit changes to
          occur.

          Quantities nominated are for a daily rate, and will be received and
          delivered at a uniform hourly rate of confirmed quantity divided by
          24, unless as determined by PGT, variance from the hourly rate will
          not be detrimental to the operation of the pipeline or adversely
          affect other PGT Shippers. Nominations, as amended by Shipper and
          received by PGT, shall remain in effect during the month for which the
          nomination is applicable, whether or not transportation occurs, until
          a new or amended nomination is provided by Shipper and received by
          PGT. PGT reserves the right to reject any nominated quantity of less
          than 24 MMBTU/day. PGT's primary method of nomination transmission
          shall be the EBB. If and only if, the EBB is inoperable, shall PGT
          accept nominations via alternative means such as fax transmittal. PGT
          requires that a Shipper designate, in writing, those individuals who
          will be authorized to place nominations for transportation on the
          system.

     19.5 Priority of Parking and Authorized Imbalance Service

          Parking and Authorized Imbalance Service shall have the lowest
          priority on PGT's system.  All other transportation service, including
          rectification of imbalances, have superior priority to these services.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: AUGUST 12, 1994                         Effective: SEPTEMBER 14, 1994
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RP94-145-000, dated AUGUST 03, 1994


 
Pacific Gas Transmission Company
FERC Gas Tariff                                     Second Revised Sheet No. 81C
First Revised Volume No. 1-A              Superseding
                                                     First Revised Sheet No. 81C
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

20.  CURTAILMENT

     PGT shall have the right to curtail, interrupt, or discontinue
     Transportation Service on any portion of its system at any time for reasons
     of Force Majeure or when capacity, supply, or operating conditions so
     require or it is necessary or desirable to make modifications, repairs, or
     operating changes to its system. PGT shall provide notice of such
     occurrences as is reasonable under the circumstances.

     Capacity may become constrained at individual receipt points, delivery
     points or on segments of the pipeline. PGT shall exercise this curtailment
     provision only at the point(s) or segment(s) of the pipeline affected by
     the constraint. When capacity is constrained or otherwise insufficient to
     serve all the transportation requirements which are scheduled to receive
     service, transportation service will be curtailed in reverse order of the
     scheduling provided in Paragraph 19.

     Curtailment of firm service if necessary, will be performed pro rata based
     on the MDQ across the contracts scheduled to use capacity at the applicable
     delivery point(s) or mainline segment(s) of pipeline, applied first to
     secondary delivery points.

     Curtailment of firm service, if necessary, at receipt points will be
     performed pro rata based on the quantities scheduled at the affected
     receipt point(s), applied first to secondary receipt points.

     If, on any day, PGT determines the capacity of its mainline system, or any
     portion thereof, including the points at which gas is tendered for
     transportation, is insufficient to serve transportation requirements which
     are otherwise scheduled to receive service on such day, or to accept the
     quantities of gas tendered, capacity which requires allocation shall be
     allocated in a manner which results in curtailment of capacity, to zero if
     necessary, first to the last quantities scheduled, and then sequentially in
     reverse order to the scheduling provided for in Paragraph 19, except that
     mid-gas day nomination increases by interruptible Shippers shall not bump
     those interruptible Shippers' volumes already confirmed for that gas day.

                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: AUGUST 13, 1996                          Effective: SEPTMBER 13, 1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                       First Revised Sheet No. 82
First Revised Volume No. 1-A              Superseding
                                                           Original Sheet No. 82
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

21.  BALANCING

     Balancing of thermally equivalent quantities of gas received and delivered
     by PGT shall be achieved as nearly as feasible on a daily basis, with any
     cumulative imbalance accounted for on a monthly basis. Correction of
     imbalances shall be the responsibility of the Shipper whether or not
     notified by PGT at the time of incurrence of the imbalance. Correction of
     imbalances shall be scheduled with PGT using the nomination process as soon
     as an imbalance is known to exist based on the best available current data.
     Nominations to correct imbalances shall have the lowest priority for
     scheduling purposes and shall be subject to the availability of capacity
     and other operational constraints for imbalance correction. If on any day
     capacity is insufficient to schedule all imbalance nominations, all such
     nominations shall be prorated accordingly. To maintain the operational
     integrity of its system, PGT shall have the right to balance any Shipper's
     account as conditions may warrant.

     Imbalances shall exist as defined below and be subject to the applicable
     charges and penalties if not corrected.

     a)   Actual delivered quantity exceeds MDQ

          An imbalance shall exist if the actual delivered quantity on any day
          exceeds the MDQ and the delivered quantity in excess of the MDQ has
          not been authorized by PGT (Unauthorized Overrun).

          Penalty: A Shipper shall be assessed $5/MMBTU for the quantity that is
          greater than 10% of the MDQ or 1000 MMBTU, whichever is greater.

          In addition, the quantity delivered in excess of the MDQ shall be
          charged the Authorized Overrun charge as provided in the applicable
          rate schedule of Shipper.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994


 
Pacific Gas Transmission Company
FERC Gas Tariff                                       First Revised Sheet No. 83
First Revised Volume No. 1-A              Superseding
                                                           Original Sheet No. 83
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

21.  BALANCING (Continued)

     (b)  Actual delivered quantity exceeds receipt quantity

          A net positive imbalance shall exist if the difference between the
          delivered quantity and the quantity received, taking into account the
          reduction in quantity for compressor fuel use, yields a positive
          result. Commencing upon notification by PGT of the existence of the
          imbalance, Shipper shall have 3 days to correct the imbalance.

          Penalty: If, at the end of the 3 day period the difference between the
          actual delivered quantity and the receipt quantity is in excess of 10%
          of the delivered quantity or 1000 MMBTU, whichever is greater, the
          Shipper shall be assessed a charge of $5/MMBTU applied to the excess
          quantities. If the imbalance is not corrected within 45 days of PGT's
          notice of an imbalance, the Shipper shall be assessed an additional
          charge of $5/MMBTU, applied to the net imbalance remaining at the end
          of the 45 day balancing period.



                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994


 
Pacific Gas Transmission Company
FERC Gas Tariff                                       First Revised Sheet No. 84
First Revised Volume No. 1-A              Superseding
                                                           Original Sheet No. 84
________________________________________________________________________________


 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

21.  BALANCING (Continued)

     (c)  Actual quantity received exceeds delivered quantity

          A net negative imbalance shall exist if the difference between the
          delivered quantity and the quantity received taking into account the
          reduction in quantity for compressor fuel use, yields a negative
          result. Commencing upon notification by PGT of the existence of the
          imbalance, Shipper shall have 3 days to correct the imbalance.

          Penalty: If, at the end of the 3 day period the difference between the
          actual quantity received and the delivered quantity is in excess of
          10% of the delivered quantity or 1000 MMBTU, whichever is greater, the
          Shipper shall be assessed a penalty of $2/MMBTU applied to the excess
          quantity. If the imbalance is not corrected within 45 days of PGT's
          notice of an imbalance, PGT shall be able to retain the remaining
          imbalance quantity without compensation to the Shipper and free and
          clear of any adverse claim.

     (d)  Scheduled delivery quantity exceeds actual delivered quantity

          An imbalance shall exist when the quantity scheduled (nominated and
          confirmed) for delivery exceeds the actual delivered quantity.

          Penalty: When the difference between the scheduled delivery quantity
          and actual delivered quantity is in excess of 10% of the actual
          deliveries, or 1000 MMBTU, whichever is greater, the Shipper shall be
          assessed the maximum applicable interruptible transportation rate
          applied to the excess quantities.

                                                                     (Continued)

                                                                                
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994


 
Pacific Gas Transmission Company
FERC Gas Tariff                                           Original Sheet No. 84A
First Revised Volume No. 1-A
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

21.  BALANCING (Continued)

     (e)  Actual delivered quantity exceeds scheduled delivery quantity

          An imbalance shall exist when the quantity delivered exceeds the
          quantity scheduled (nominated and confirmed).

          Penalty: When the difference between the actual delivered quantity and
          the scheduled delivery quantity is in excess of 10% of the scheduled
          quantity or 1000 MMBTU whichever is greater, the Shipper shall be
          assessed a charge of $5/MMBTU applied to the excess quantity.

     Imbalance determinations as described above will be performed on a daily
     basis and each daily occurrence will constitute a separate incident. It is
     recognized and understood that more than one penalty provision may apply to
     each imbalance incident.

     In the event that any penalty would otherwise be applicable under these
     provisions as a direct consequence of any action or failure to take action
     by PGT or the failure of any facility under PGT's control, or an event of
     force majeure as defined in these Transportation General Terms and
     Conditions, said penalty shall not apply.

     The payment of a penalty in dollars pursuant to Paragraph 21 shall under no
     circumstances be considered as giving any Shipper the right to deliver or
     take overrun quantities.

     Upon termination of a Service Agreement, Shipper shall have 60 days to
     correct any remaining imbalances. After his period has elapsed, PGT shall
     have the right to retain any negative imbalance quantity without
     compensation to the Shipper and shall assess a charge of $5/MMBTU for any
     positive imbalance quantity as applicable.



                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994


 
Pacific Gas Transmission Company
FERC Gas Tariff                                            Original Sheet No. 85
First Revised Volume No. 1-A
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)


22.  ANNUAL CHARGE ADJUSTMENT (ACA) PROVISION

     22.1  Purpose: PGT shall recover from Shippers the annual charge assessedto
           PGT by the Federal Energy Regulatory Commission for budgetary
           expenses pursuant to Section 154.38(d)(6) of the Commission's
           regulations and Order No. 472 issued May 29, 1987. PGT shall recover
           this charge by means of an Annual Charge Adjustment (ACA); a per unit
           rate equivalent to the unit rate assessed against PGT by the
           Commission shall be included in PGT's transportation rates. (During
           the period that this ACA provision is in effect, PGT shall not
           recover in a Natural Gas Act Section 4 rate case annual charges
           recorded in FERC Account No. 928 assessed to PGT by the Commission
           pursuant to Order No. 472.)

     22.2  Filing Procedure: The notice period and proposed effective date of
           filings pursuant to this paragraph shall be as permitted under
           Section 4 of the Natural Gas Act; provided, however, that any such
           filing shall not become effective unless they become effective
           without suspension or refund obligation.

     22.3  ACA Unit Rate Adjustment: PGT's ACA unit rate shall be the unit rate
           used by the Commission to determine the annual charge assessment to
           PGT, and shall be reflected in the Statement of Effective Rates and
           Charges of this FERC Gas Tariff First Revised Volume No. 1-A.

     22.4  Affected Rate Schedules: The ACA provision shall apply to all rate
           schedules contained in PGT's FERC Gas Tariff First Revised Volume No.
           1-A.

23.  SHARED OPERATING PERSONNEL AND FACILITIES

     PGT and its marketing affiliate do not share any operating personnel. PGT
     does not share any facilities with its marketing affiliate. To the extent
     PG&E elects service under Rate Schedule USS-1, PGT employees involved with
     the implementation of USS-1 service will operate independently from PGT's
     pipeline operating employees.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: AUGUST 02, 1993                       Effective: NOVEMBER 01, 1993
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RS92-46-000, et al., dated JULY 12, 1993


 
Pacific Gas Transmission Company
FERC Gas Tariff                                       First Revised Sheet No. 86
First Revised Volume No. 1-A              Superseding
                                                           Original Sheet No. 86
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)


24.  COMPLAINT PROCEDURES

     24.1 Any Shipper or potential Shipper may register a complaint regarding
          requested or provided transportation service.  The complaint may be
          communicated to PGT primarily by use of PGT's Electronic Bulletin
          Board (EBB) and secondarily either orally, and/or in writing.   Oral
          complaints should be made to PGT's Manager of Gas Transportation and
          Services, telephone (503) 833-4300. Written complaints should be sent
          via registered or certified mail, facsimile (FAX No. (503) 833-4396) ,
          or hand delivered to:

          Pacific Gas Transmission Company
          2100 Southwest River Parkway
          Portland, OR 97201
          Attention: Manager of Gas Transportation and Services

          Oral,  written and EBB-submitted complaints must contain the following
          minimum information:

          -    Shipper or potential Shipper's name, address, and FAX and
               telephone numbers;
          -    Shipper or potential Shipper's contact representative;
          -    A clear, concise statement of the complaint.
 
          Each complaint will be recorded in PGT's Transportation Service
          Complaint Log maintained by PGT's Gas Transportation and Services
          Department located in Portland.  Complaints will be logged by date and
          time received by PGT.

     24.2 PGT will initially respond to each complaint within forty-eight (48)
          hours after PGT receives it.  PGT will provide a written response to
          each complaint within thirty (30) days after PGT receives it.   PGT's
          written response will be sent to Shipper or potential Shipper by
          certified or registered mail If the complaint was filed by the EBB,
          then PGT shall respond via the EBB.  A copy of all complaints  will be
          filed in the Transportation Service Complaint Log.

                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: OCTOBER 18, 1995                         Effective: NOVEMBER 18, 1995


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      Second Revised Sheet No. 87
First Revised Volume No. 1-A              Superseding
                                                      First Revised Sheet No. 87
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)
25.  INFORMATION CONCERNING AVAILABILITY AND PRICING OF TRANSPORTATION SERVICE
     AND CAPACITY AVAILABLE FOR TRANSPORTATION

     25.1 Any affiliated or nonaffiliated Shipper or potential Shipper may
          obtain information concerning the availability and pricing of PGT's
          transportation services and the pipeline capacity available for
          transportation by:

          (a)  Contacting PGT at:
               Pacific Gas Transmission Company
               Marketing and Transportation Department
               2100 Southwest River Parkway
               Portland, OR 97201
               Telephone: (503) 833-4300

               or (California customers)

               Pacific Gas Transmission Company
               California Marketing Group
               101 Spear Street, Suite 200
               San Francisco, CA 94105
               Telephone: (415) 778-3000
               Fax: (415) 778-3091

               Inquiries may be made orally or in writing.

               Upon request, PGT will provide to any Shipper or potential
               Shipper a copy of its FERC Gas Tariff, First Revised Volume No.
               1-A, as well as any published notices concerning discounts then
               available to existing Shippers on the PGT system.

          (b)  Subscribing to PGT's twenty-four (24) hour Electronic Bulletin
               Board by calling 1-503-833-4310.  The Electronic Bulletin Board
               provides current information concerning the availability and
               pricing of transportation service on the PGT system, including
               all effective rates and discount notices, and capacity available
               for transportation.

     25.2 The procedures to be followed by a potential Shipper requesting
          transportation service from PGT or by an existing Shipper requesting
          an amendment to its existing service or additional service from PGT
          are specified in Paragraph 18 of these Transportation General Terms
          and Conditions.          
                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: OCTOBER 18, 1995                         Effective: NOVEMBER 18, 1995


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      Second Revised Sheet No. 88
First Revised Volume No. 1-A              Superseding
                                                      First Revised Sheet No. 88
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)


25.  INFORMATION CONCERNING AVAILABILITY AND PRICING OF TRANSPORTATION SERVICE
     AND CAPACITY AVAILABLE FOR TRANSPORTATION (Continued)

     25.3 The procedures to be followed by Shippers for submitting nominations
          for transportation service are specified in Paragraph 19 of these
          Transportation General Terms and Conditions.

26.  MARKET CENTERS

     The Market Center is defined as a point of interconnection between PGT and
     other pipelines and local distribution companies. PGT shall provide for
     Market Centers on PGT. Parties wishing to use Market Centers on the PGT
     system shall contact PGT for this service. At these Market Centers,
     entities may trade gas quantities without actively shipping the gas either
     upstream or downstream of the Market Center. Such entities must nominate
     for the gas transactions in accordance with the nomination procedures of
     the Transportation General Terms and Conditions of First Revised Volume No.
     1-A. An entity's nomination for upstream supply and downstream delivery
     must match the corresponding upstream Shipper nomination and the downstream
     customer request.



                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: AUGUST 13, 1996                         Effective: SEPTEMBER 13, 1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                           Original Sheet No. 88A
First Revised Volume No. 1-A              
                                                      
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)



27.  PLANNED PGT CAPACITY CURTAILMENTS AND INTERRUPTIONS

     27.1 When PGT needs to temporarily curtail or interrupt service to any
          Shipper hereunder for the purpose of making planned alterations or
          repairs, PGT shall give Shipper as much notice as possible of the
          process so that each Shipper's firm transportation requirements are
          taken into account in the planning process.

     27.2 In the spring of each year PGT shall publish on its electronic
          bulletin board (EBB) to all Shippers a schedule of planned major
          maintenance and repairs which affect system capacity.  The schedule
          shall show the estimated delivery point capacity for the next 12
          months.

     27.3 On a daily basis PGT shall post, on its EBB, capacity for each
          forthcoming gas day plus the estimated capacity for the next two gas
          days.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994



 
Pacific Gas Transmission Company
FERC Gas Tariff                                 Substitute Original Sheet No. 89
First Revised Volume No. 1-A              Superseding
                                                           Original Sheet No. 89
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

28.  CAPACITY RELEASE

     28.1 Eligibility to Release

          Any firm Shipper which contracts for firm transportation service under
          Part 284 of the Commission's regulations (Releasing Shipper) is
          eligible to release all or part of its capacity (Parcel) for use by
          another party (Replacement Shipper). Any Replacement Shipper which has
          previously contracted for a Parcel may also release its capacity to
          another party as a secondary release subject to the terms and
          conditions described herein.

          Upon releasing a Parcel, consistent with the terms and conditions
          described herein, all Releasing Shippers shall remain ultimately
          liable for all reservation charges billable for the originally
          contracted service. The Releasing Shipper, whether a primary or
          secondary capacity holder, must post the capacity it seeks to release
          on PGT's Electronic Bulletin Board (EBB) prior to the close of the
          Posting Period defined herein.

          A Releasing Shipper may release all or a portion of its capacity for
          the remainder of the term of its contract and extinguish its
          contractual obligations to PGT with respect to that portion provided
          that: 1) the Replacement Shipper for this capacity is creditworthy
          pursuant to PGT's credit standards; and 2) that the rate paid by the
          Replacement Shipper be no less than the rate contracted between the
          Releasing Shipper and PGT for the maximum volume, for the remaining
          term of the contract or the Releasing Shipper's maximum tariff rate.
          The release may be structured such that the right of first refusal may
          transfer to the Replacement Shipper even if the release has recall
          provisions and has been recalled by the Releasing Shipper at the end
          of the service agreement.


                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: OCTOBER 13, 1993                       Effective: NOVEMBER 01, 1993
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RS92-46-000, et al., dated OCTOBER 01, 1993



 
Pacific Gas Transmission Company
FERC Gas Tariff                                 Sub. Second Revised Sheet No. 90
First Revised Volume No. 1-A              Superseding
                                                      First Revised Sheet No. 90
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)
28.  CAPACITY RELEASE (Continued)

     28.2 Types of Release

          A Releasing Shipper may release a Parcel for a term (Release Term) up
          to or equivalent to the remaining term under its service agreement
          with PGT. Types of releases include:

          Rapid Release - thirty-one days or less, is not prearranged, requires
          bidding and is restricted to options 1 or 2 for the allocation of
          Parcels without special terms or conditions. A standard recall
          provision may be selected.  (Capacity up to the full quantity of the
          release maybe recallable on 2 business days notice. This capacity may
          be returned to the Replacement Shipper on 2 business days notice.
          Replacement Shipper may refuse to accept such capacity returned in
          this fashion.)

          Standard Release - greater than or equal to one day, is not
          prearranged, and requires bidding.

          Prearranged Deal-A - less than or equal to thirty-one days.  This type
          of release is prearranged and does not require bidding.  Such
          prearranged deals shall be posted for informational purposes within 48
          hours after the release transaction commences.  This release cannot be
          rolled-over, renewed or otherwise extended beyond the term described
          above unless the Releasing Shipper follows the posting and bidding
          procedures that apply to the particular term sought contained in this
          Paragraph 28. The Releasing Shipper may  not re-release this Parcel to
          the same Replacement Shipper until 28 days after the term of the
          initial release has ended.  Rollovers are permitted without bidding or
          a waiting period provided the Prearranged Shipper agrees to pay the
          maximum rate and meet all the other terms and conditions of the
          release.

          Prearranged Deal-B - greater than or equal to thirty-one days at the
          maximum rate bid pursuant to the methodology selected by Releasing
          Shipper.  This type of release is prearranged and does not require
          bidding.

          Prearranged Deal-C - greater than or equal to one day at a rate less
          than the maximum rate bid pursuant to the methodology selected by the
          Releasing Shipper.  This type of release is prearranged, allows for
          bidding, and allows the right of first refusal.

                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Mgr. Gas Supply & Reg. Affairs
Issued on: JUNE 19, 1995                                Effective: JULY 10, 1995
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RM95-5-00, dated MAY 31, 1995



 
Pacific Gas Transmission Company
FERC Gas Tariff                                      Second Revised Sheet No. 91
First Revised Volume No. 1-A              Superseding
                                                      First Revised Sheet No. 91
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

28.  CAPACITY RELEASE (Continued)

     28.3 Notice Requirements

               Any Releasing Shipper electing to release capacity shall submit a
               notice via PGT's EBB that it elects to release firm capacity.
               The notice shall set forth the following information:

               (a)  Releasing Shipper's legal name, contract number, and the
                    name, title, address, telephone number, and fax number of
                    the individual responsible for authorizing the release of
                    capacity.

               (b)  Rate schedule of the Releasing Shipper.

               (c)  Whether bidders will bid on the reservation charge or a
                    volumetric equivalent of the maximum reservation charge
                    applicable to the Parcel on a 100% load-factor basis.  If a
                    volumetric rate is used, Releasing Shipper must indicate
                    whether bids on a reservation charge basis will be accepted
                    as well and if so must specify the method of evaluating the
                    two types of bids.  Releasing Shipper also should indicate
                    whether bids will be accepted on a dollar basis or as a
                    percentage of the Releasing Shipper's as-billed rate.

               (d)  Daily quantity of capacity to be released, expressed in
                    MMBtu/d, at the designated delivery point(s).  (This must
                    not exceed Releasing Shipper's maximum contract demand
                    available for capacity release and shall state the minimum
                    quantity expressed in MMBtu/d acceptable for release.)

                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: AUGUST 13, 1996                        Effective: SEPTEMBER 13, 1996 



 
Pacific Gas Transmission Company
FERC Gas Tariff                                       First Revised Sheet No. 92
First Revised Volume No. 1-A              Superseding
                                                           Original Sheet No. 92
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

28.  CAPACITY RELEASE (Continued)

    28.3 Notice Requirements (Continued)

              (e)  The term of the release, identifying the date release is to
                   begin and terminate.  The minimum release term acceptable to
                   PGT shall be one day.

              (f)  Whether the Releasing Shipper is willing to consider release
                   for a shorter period of time than that specified in (e) above
                   and if so, the minimum acceptable period of release.

              (g)  The receipt and delivery point.

              (h)  Whether Option 1, 2, or 3 shall be used to determine the
                   highest valued bid.  If Option 3 is selected, Releasing
                   Shipper must describe the criteria by which bids are to be
                   evaluated.

              (i)  Whether the Releasing Shipper wants PGT to market its
                   released capacity.

              (j)  Whether the Releasing Shipper requests to waive the
                   creditworthiness requirements and agrees in such event to
                   remain liable for all charges, or, if the release is for one
                   year (365 days) or less, whether Releasing Shipper requests
                   that the creditworthiness provisions of Paragraph
                   18.3(A)(1)(c) shall apply.

              (k)  Whether Releasing Shipper is a marketing or other affiliate
                   of PGT.

              (l)  If release is a prearranged release, the Prearranged Shipper
                   must be qualified pursuant to the criteria of Paragraph
                   28.6(a) unless waived above.  Releasing Shipper shall include
                   the Prearranged Shipper bid information pursuant to Paragraph
                   28.6(b) with its release information and shall indicate
                   whether the Prearranged Shipper is affiliated with PGT or the
                   Releasing Shipper.

              (m)  Any special nondiscriminatory terms and conditions applicable
                   to the release.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: MAY 31, 1994                                  Effective: MAY 21, 1994
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RP94-211-000, dated MAY 20, 1994



 
Pacific Gas Transmission Company
FERC Gas Tariff                                 Substitute Original Sheet No. 93
First Revised Volume No. 1-A              Superseding
                                                           Original Sheet No. 93
________________________________________________________________________________
 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)
28.  CAPACITY RELEASE (Continued)

     28.3 Notice Requirements (Continued)

               (n)  Tie-breaker method preferred:  (1) pro rata, (2) lottery,
                    (3) order of submission (first-come/first-serve), (4) other.
                    Other method must be objectively stated, administratively
                    feasible as determined by PGT and nondiscriminatory.  If
                    none are selected, the system defaults to pro rata.

               (o)  Recall provisions.  These provisions must be objectively
                    stated, nondiscriminatory, applicable to all bidders,
                    operationally and administratively feasible as determined by
                    PGT and in accordance with PGT's tariff.

               (p)  The minimum rate (percentage of:  reservation charge or a
                    volumetric equivalent of the maximum reservation charge
                    applicable to the Parcel on a 100% load-factor basis)
                    acceptable to Releasor for this Parcel.  Releasing Shipper
                    also should indicate whether bids will be accepted on a
                    dollar basis or as a percentage of the Releasing Shipper's
                    as-billed rate.

               (q)  Whether the Releasing Shipper is willing to accept
                    contingent bids that extend beyond the close of the Bid
                    Period and, if so, any nondiscriminatory terms and
                    conditions applicable to such contingencies including the
                    date by which such contingency must be satisfied (which date
                    shall not be later than the last day upon which PGT must
                    award capacity) and whether, or for what time period, the
                    next highest bidder(s) will be obligated to acquire the
                    capacity should the winning contingent bidder be unable to
                    satisfy the contingency specified in its bid.

               (r)  Whether the Releasing Shipper wants to specify a longer
                    bidding period for its Parcel than specified at Paragraph
                    28.8.
                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: AUGUST 13, 1996                         Effective: SEPTEMBER 13, 1996



 
Pacific Gas Transmission Company
FERC Gas Tariff                                 Substitute Original Sheet No. 94
First Revised Volume No. 1-A              Superseding
                                                           Original Sheet No. 94
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

28.  CAPACITY RELEASE (Continued)

    28.4   Marketing of Capacity Fee

              PGT may act as a facilitator between a Releasing Shipper and a
              Replacement Shipper(s) that wishes to contract for that Releasing
              Shipper's capacity.  All such Parcels must be posted on the EBB
              initially.  A posting of a Parcel facilitated by PGT will include
              both the Parcel by the Releasing Shipper and the bid by the
              Prearranged Shipper.  A marketing of capacity fee shall be
              negotiated between PGT and Releasing Shipper in a
              nondiscriminatory manner.  Such a fee will apply when:  a
              Releasing Shipper requests PGT to market released capacity, PGT
              actively markets such capacity beyond posting on the EBB, and such
              marketing results in capacity being released to a Replacement
              Shipper.

    28.5 Posting of a Parcel

              The posting of a Parcel constitutes an offer to release the
              capacity provided a willing Replacement Shipper submits a valid
              bid consistent with PGT's Transportation General Terms and
              Conditions.  The posting must contain the information contained in
              Paragraph 28.3.  Any specific conditions posted by the Releasing
              Shipper must be operationally feasible, nondiscriminatory to other
              shippers, and in conformance with PGT's tariffs.  If the Parcel is
              being released as a secondary release, then any recall provisions
              included in the primary release which may affect the re-release of
              this capacity must be included in the terms and conditions of the
              secondary release.  Each Parcel will be reviewed by PGT prior to
              posting on the EBB for bidding.  The receipt of a valid release
              will be acknowledged by the issuance of a release confirmation to
              the Releasing Shipper's EBB mailbox by PGT.

              It is the Releasing Shipper's sole responsibility to provide
              release and Prearranged Shipper bid information in advance of the
              close of the Posting Period.



                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: OCTOBER 13, 1993                         Effective: NOVEMBER 01, 1993
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RS92-46-000, et al., dated OCTOBER 01, 1993


 
Pacific Gas Transmission Company
FERC Gas Tariff                                            Original Sheet No. 95
First Revised Volume No. 1-A              
                                          
________________________________________________________________________________
 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

28.  CAPACITY RELEASE (Continued)

    28.5 Posting of a Parcel (Continued)

              Releasing Shippers who elect to release capacity and select Option
              3 for the highest valued bid methodology and/or include, in their
              release, nondiscriminatory recall provisions and/or special terms
              and conditions are required to submit their request to release
              capacity by  12:00 p.m. Pacific Time at least two business days
              before the close of the Posting Period.  This is to ensure
              adequate time for PGT to review and validate that the Option 3
              criteria and/or any recall and special terms and conditions are
              not discriminatory.

              All Prearranged Shipper bids are subject to the Prearranged
              Shipper(s) meeting the preliminary qualifications as defined in
              Paragraph 28.6(a) for Replacement Shippers.

              A Parcel may be revised or withdrawn by the Releasing Shipper at
              any time prior to the close of the Posting Period.  A Parcel
              cannot be revised after the close of the Posting Period.  Parcels
              may be withdrawn subsequent to the close of the Posting Period and
              up until the close of the Bid Period only in situations where the
              Releasing Shipper has an unanticipated need for the capacity.  In
              such instances, Releasing Shipper shall notify PGT via the EBB of
              its need to withdraw the Parcel due to an unanticipated need for
              the capacity.  The withdrawal or revision of a Parcel will
              terminate all bids submitted for that Parcel to date.  Replacement
              Shippers will need to resubmit their bids for the Parcel if the
              Parcel is resubmitted for release.



                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: AUGUST 02, 1993                          Effective: NOVEMBER 01, 1993
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RS92-46-000, et al., dated JULY 12, 1993


 
Pacific Gas Transmission Company
FERC Gas Tariff                                            Original Sheet No. 96
First Revised Volume No. 1-A              
                                          
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)
28.  CAPACITY RELEASE (Continued)

    28.6 Bidding for a Parcel

              (a)  Preliminary Qualification

                   To bid for a Parcel, a Replacement Shipper must: pre-qualify
                   by submitting a completed request for authority to bid for a
                   Parcel, meet PGT's credit criteria, and execute an FTS-1
                   service agreement for capacity release as set forth in these
                   Transportation General Terms and Conditions.

                   Replacement Shippers may carry out these requirements through
                   the use of PGT's EBB.  Replacement Shippers are encouraged to
                   pre-qualify in advance of any postings on PGT's EBB as credit
                   requirements will take differing amounts of time to process
                   depending on the particular financial profile of Replacement
                   Shippers.  The pre-qualification process will authorize a
                   pre-set maximum monthly financial exposure level for the
                   Replacement Shipper.  Such exposure levels may be adjusted by
                   PGT periodically re-evaluating a Replacement Shipper's
                   credit-worthiness.

                   Releasing Shippers may exercise their option to waive the
                   credit requirements for any Replacement Shipper wishing to
                   bid on a Parcel posted by that Releasing Shipper.  Such
                   waiver must be made on a nondiscriminatory basis.  PGT must
                   be informed of such waiver via the EBB before it will
                   authorize such Replacement Shipper's participation with
                   respect to that particular Parcel. In this instance, no pre-
                   set maximum monthly financial exposure level is applicable.

                   Should a Releasing Shipper waive the credit requirements for
                   a Replacement Shipper, the Releasing Shipper shall be liable
                   for all charges incurred by the Replacement Shipper in the
                   event such Replacement Shipper defaults on payment to PGT for
                   such capacity release service.   (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: AUGUST 02, 1993                          Effective: NOVEMBER 01, 1993
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RS92-46-000, et al., dated JULY 12, 1993


 
Pacific Gas Transmission Company
FERC Gas Tariff                                            Original Sheet No. 97
First Revised Volume No. 1-A              
                                          
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

28.  CAPACITY RELEASE (Continued)

    28.6 Bidding for a Parcel (Continued)

              (a) Preliminary Qualification (Continued)

                   The execution of the FTS-1 service agreement for capacity
                   release is to be signed "electronically" by the Replacement
                   Shipper. The Replacement Shipper shall execute the FTS-1
                   service agreement for capacity release (exhibits excluded)
                   through the use of an authorization code procedure on the
                   EBB.

                   Upon notification by PGT of an award of a Parcel, PGT shall
                   complete Exhibit R with the particulars of the awarded Parcel
                   and Replacement Shipper shall execute, electronically,
                   Exhibit R to the FTS-1 service agreement for capacity
                   release.

                   A hard copy of the FTS-1 service agreement for capacity
                   release, including Exhibit R (signed by hand by PGT and
                   Replacement Shipper), will follow subsequent to the awarding
                   of a Parcel.

                   A Replacement Shipper that subsequently obtains additional
                   Parcels is not required to execute an additional FTS-1
                   service agreement for capacity release; rather, for each such
                   additional Parcel obtained, an additional Exhibit R
                   (designated sequentially "Exhibit R-2", "Exhibit R-3", etc.)
                   will be executed and amended to such Replacement Shipper's
                   FTS-1 service agreement for capacity release.

                   Once the Replacement Shipper has met PGT's preliminary
                   contractual and credit requirements, PGT will amend the
                   Replacement Shipper's authorization to add access to the
                   bidding and releasing portions of PGT's capacity release
                   program on its EBB.  This authorization, in combination with
                   the Replacement Shipper's password, which will be unique and
                   known only by the Replacement Shipper, will entitle the

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: AUGUST 02, 1993                          Effective: NOVEMBER 01, 1993
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RS92-46-000, et al., dated JULY 12, 1993


 
Pacific Gas Transmission Company
FERC Gas Tariff                                            Original Sheet No. 98
First Revised Volume No. 1-A              
                                          
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

28.  CAPACITY RELEASE (Continued)

    28.6 Bidding for a Parcel (Continued)

              (a) Preliminary Qualification (Continued)

                   Replacement Shipper to submit a bid for a Parcel.  Once a
                   Replacement Shipper has acquired capacity, authority is
                   granted to the Replacement Shipper to release that capacity.

                   The execution of the FTS-1 service agreement for capacity
                   release and use of this authorization to submit a bid or to
                   release capacity will constitute an obligation on the part of
                   the Replacement Shipper to be bound by the terms and
                   conditions of PGT's capacity release program as set forth in
                   these Transportation General Terms and Conditions.

              (b)  Submitting a Bid

                   All bids must be submitted through the use of PGT's EBB.
                   Such bids shall be "open" for all participants to review.
                   The particulars of all bids will be available for review but
                   not the identity of bidders.  PGT will post the identity of
                   the winning bidder(s) only.

                   A Replacement Shipper cannot request that its bid be
                   "closed", nor can a Releasing Shipper specify that "closed"
                   bids be submitted on its releases.   A Replacement Shipper
                   may submit only one bid per Parcel posted at any one point in
                   time.  Bids received after the close of the Bid Period shall
                   be invalid.  The Replacement Shipper may bid for no more than
                   the quantity of the Parcel posted by the Releasing Shipper.
                   Simultaneous bids for more than one Parcel are permitted.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: AUGUST 02, 1993                          Effective: NOVEMBER 01, 1993
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RS92-46-000, et al., dated JULY 12, 1993


 
Pacific Gas Transmission Company
FERC Gas Tariff                                            Original Sheet No. 99
First Revised Volume No. 1-A           
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

28.  CAPACITY RELEASE (Continued)

    28.6 Bidding for a Parcel (Continued)

              (b)  Submitting a Bid (Continued)

                   A valid bid to contract for a Parcel must contain the
                   following information:

                   (1)  Replacement Shipper's legal name, address, telephone and
                        fax numbers and the name and title of the individual
                        responsible for authorizing the bid.

                   (2)  The identification of the Parcel bid on.

                   (3)  Term of service requested.  The term of service must not
                        exceed the term included in the Parcel.

                   (4)  Percentage of the applicable maximum rate, as identified
                        in the Parcel, that Replacement Shipper is willing to
                        pay.  A Replacement Shipper may not bid below the
                        minimum applicable charge or rate nor above the maximum
                        authorized charge or rate for the Parcel.

                   (5)  The quantity desired not to exceed the quantity
                        contained in the Parcel, expressed on a MMBtu/d
                        delivered basis and greater than the minimum quantity
                        acceptable to Replacement Shipper.

                   (6)  Under Options 1 or 2 acceptance or rejection of all
                        recall provisions and special nondiscriminatory terms
                        and conditions of service associated with the release.
                        Rejection of any terms results in an invalid bid.

                   (7)  Whether or not Replacement Shipper is an affiliate of
                        the Releasing Shipper.

                   (8)  A statement as to whether or not Replacement Shipper is
                        affiliated with PGT.
                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: AUGUST 02, 1993                          Effective: NOVEMBER 01, 1993
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RS92-46-000, et al, dated JULY 12, 1993


 
Pacific Gas Transmission Company
FERC Gas Tariff                                           Original Sheet No. 100
First Revised Volume No. 1-A         
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

28.  CAPACITY RELEASE (Continued)

    28.6 Bidding for a Parcel (Continued)

              (b)  Submitting a Bid (Continued)

                   (9)  An affirmative statement that Replacement Shipper agrees
                        to be bound by the terms and conditions of Rate Schedule
                        FTS-1 and PGT's capacity release provisions in its
                        tariff.

                   (10) Whether the bid is a contingent bid and the
                        contingencies which must be satisfied by the date
                        specified by the Releasing Shipper in its posting of the
                        Parcel.

              (c)  Confirmation of Bids

                   The receipt of a valid bid by PGT will be acknowledged by the
                   issuance of a bid confirmation to the Replacement Shipper's
                   EBB mailbox by PGT.  It is the Replacement Shipper's sole
                   responsibility to verify the correctness of the submitted bid
                   and to take any corrective action necessary by resubmitting a
                   bid when notified of an invalid or incomplete bid by PGT via
                   the EBB.  This must be done before the close of the Bid
                   Period.

              (d)  Withdrawn or Revision of Bids

                   A previously submitted bid may be withdrawn or revised and
                   resubmitted at any time prior to  the close of the Bid Period
                   with no obligation on the Replacement Shipper's part.
                   Resubmitted bids must be equal to or greater in value than
                   the initial bids.  Lower valued bids will be invalid.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: AUGUST 02, 1993                          Effective: NOVEMBER 01, 1993
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RS92-46-000, et al., dated JULY 12, 1993


 
Pacific Gas Transmission Company
FERC Gas Tariff                                           Original Sheet No. 101
First Revised Volume No. 1-A     
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

28.  CAPACITY RELEASE (Continued)

    28.7 Allocation of Parcels

              (a)  Primary Allocation

                      Winning bids for Parcels shall be awarded based on one  of
                      the following three options to be selected by the
                      Releasing Shipper when posting a Parcel:

                      Option 1 - Price

                      Bids will be given priority based on the maximum rate bid
                      as represented by a Replacement Shipper's bid of the
                      percentage of:  the maximum authorized reservation charge
                      or a volumetric equivalent of the maximum reservation
                      charge applicable to the Parcel on a 100% load factor
                      basis.  Releasing Shippers using a volumetric rate and
                      wishing to accept reservation charge bids will be
                      considered an Option 3 criteria.  In this instance
                      Releasing Shipper must define the method for evaluating
                      such bids.  A bid queue will be maintained for each
                      individual Parcel.

                      Option 2 - Net Present Value

                      Bids will be given priority based on the net present value
                      per MMBtu for the term of the bid according to the
                      following formula:
                                                              n
                                                        (1 + i) -1
                      Present Value per unit = P * R *   _________
                                                                 n
                                                         i (1 + i)

                      where:  P = percent of the rate or charge that the
                              Replacement Shipper is willing to pay.


                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: AUGUST 02, 1993                          Effective: NOVEMBER 01, 1993
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RS92-46-000, et al., dated JULY 12, 1993


 
Pacific Gas Transmission Company
FERC Gas Tariff                                           Original Sheet No. 102
First Revised Volume No. 1-A     
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

28.  CAPACITY RELEASE (Continued)

    28.7 Allocation of Parcels (Continued)

              (a) Primary Allocation (Continued)

                   R = Rate or charge calculated as:  The maximum authorized
                   reservation charge (or a volumetric equivalent of the maximum
                   reservation charge applicable to the Parcel on a 100% load
                   factor basis) in effect at the time of the bid for service
                   from the same receipt point to the same delivery point under
                   the Releasing Shipper's rate schedule.

                   i = FERC's annual interest rate divided by 12.

                   n = number of periods for which the bidder wishes to
                   contract, not to exceed the maximum periods to be released by
                   the Releasing Shipper.  For releases greater than or equal to
                   one month, the period is the number of months.  For releases
                   less than one month the period is the number of days.

                   A bid queue will be maintained for each individual Parcel.

                   Option 3 - Releasing Shipper's Criteria for Highest Valued
                   Bids

                   Bids will be given priority based on the criteria established
                   by the Releasing Shipper for determining the highest valued
                   bids.  The criteria must be objectively stated, applicable to
                   all potential bidders, operationally and administratively
                   feasible as determined by PGT, nondiscriminatory, and in
                   conformance with PGT's tariff.  A bid queue will be
                   maintained for each individual Parcel.

                   If Releasing Shipper does not specify an option for
                   determining best bid, Option 2 will be the default option
                   used.

                   Under all options, PGT will evaluate and rank all bids for
                   Parcels.            
                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: AUGUST 02,1993                           Effective: NOVEMBER 01, 1993
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RS92-46-000, et al., dated JULY 12, 1993


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      First Revised Sheet No. 103
First Revised Volume No. 1-A              Superseding
                                                          Original Sheet No. 103
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

28.  CAPACITY RELEASE (Continued)

     28.7 Allocation of Parcels (Continued)

               (b)  Right of First Refusal

                    In the case of a Prearranged Shipper's bid for a Parcel with
                    a term equal to one month or greater, at a rate other than
                    at the highest valued bid, pursuant to the methodology
                    specified by the Releasing Shipper, if the bid submitted by
                    a subsequent Replacement Shipper exceeds the value of the
                    Prearranged Shipper's bid, the Prearranged Shipper will be
                    allowed to match the higher valued bid.  The Prearranged
                    Shipper will be allowed  1 business day from the close of
                    the Bid Reconciliation Period to match the higher valued
                    bid, otherwise,  the allocation will be awarded to
                    subsequent Replacement Shipper(s) in accordance with the
                    primary and secondary allocation mechanisms.

               (c)  Secondary Allocation

                    To the extent there is more than one Replacement Shipper
                    submitting a winning bid, the Parcel shall be allocated
                    based on one of the following tie-breaker methodologies to
                    be selected by the Releasing Shipper:  pro rata, lottery,
                    order of submission (first come/first serve), or by a method
                    designated by the Releasing Shipper.  Releasing Shipper's
                    method must be objectively stated, applicable to all
                    bidders, nondiscriminatory, administratively feasible as
                    determined by PGT and in accordance with PGT's tariffs.



                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994

 
Pacific Gas Transmission Company
FERC Gas Tariff                                           Original Sheet No. 104
First Revised Volume No. 1-A   
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

28.  CAPACITY RELEASE (Continued)

    28.7 Allocation of Parcels (Continued)

              (d)  Confirmation of Allocation

                   Upon each completion of an allocation, the successful
                   Replacement Shipper(s) will be notified of the terms under
                   which they have contracted for the awarded Parcel.  The
                   notification will be provided in the form of a notice in the
                   Replacement Shipper's EBB mailbox.  The notice will include
                   an Exhibit R to the Replacement Shipper's Rate Schedule FTS-1
                   service agreement for capacity release which specifies the
                   pertinent terms of the Replacement Shipper's bid as well as
                   any additional terms specified by the Releasing Shipper.  The
                   Releasing Shipper will be notified of the terms under which
                   its Parcel has been awarded.  The notification will be
                   provided in the form of a notice in the Releasing Shipper's
                   EBB mailbox.  The notification will include an Exhibit C to
                   the Releasing Shipper's service agreement which specifies the
                   pertinent terms of the credit to be applied to the Releasing
                   Shipper as a result of the awarding of Parcel to the
                   Replacement Shipper(s).  In the case of multiple Replacement
                   Shippers and Parcels, an Exhibit C to the Releasing Shippers'
                   service agreement will be generated for each Parcel and
                   Replacement Shipper.  The Exhibit C's shall be numbered
                   sequentially as Exhibit C-1, C-2, etc.

              (e)  Purging of Expired Bids

                   All unfulfilled bids, as well as any unfulfilled portions of
                   bids which receive a partial award, will become ineffective
                   as of the completion of bid reconciliation and the close of
                   the Bid Period.  Each unsuccessful Replacement Shipper which
                   has bid shall receive a notice in its EBB mailbox indicating
                   the ineffectiveness of the bid.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: AUGUST 02, 1993                          Effective: NOVEMBER 01, 1993
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RS92-46-000, et al., dated JULY 12, 1993


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      First Revised Sheet No. 105
First Revised Volume No. 1-A              Superseding
                                                          Original Sheet No. 105
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

28.  CAPACITY RELEASE (Continued)

     28.7 Allocation of Parcels (Continued)

          (e) Purging of Expired Bids (Continued)

               Information regarding all bids for all Parcels shall be archived
               off-line before being purged from the system.

     28.8 Scheduling of Parcels, Bids and Notifications

          (a)  Rapid Release - one month or less, not prearranged.

               Posting Period - up to 12:00 p.m. Pacific Time on the 2nd
               business day before the commencement of the Release Term.

               Bid Period - a minimum  period of 2 hours subsequent to the close
               of the Posting Period. The bid period may be extended by the
               Releasing Shipper. The Bid Period closes at 2:00 p.m. Pacific
               Time on the 2nd business day before the commencement of the
               Release Term.  Notification of the results of the bidding for
               Parcels will be posted at 2:00 p.m. Pacific Time on the 2nd
               business day prior to the commencement of the Release Term.

          (b)  Standard Release-greater than or equal to one day, not
               prearranged.

               Posting Period - up to 12:00 p.m. Pacific Time 5 business days
               prior to the commencement of the Release Term.

               Bid Period - a minimum period of 1 business day subsequent to the
               close of the Posting Period.  The Bid Period closes at 2:00 p.m.
               Pacific Time 4 business days prior to the commencement of the
               Release Term.

               Bid Reconciliation Period - a period of 2 business days
               subsequent to the close of the Bid Period.  The Bid
               Reconciliation Period closes at 2:00 p.m. Pacific Time 2 business
               days prior to the commencement of the Release Term at which time
               notification of the results of the bidding for Parcels will be
               posted.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994

 
Pacific Gas Transmission Company
FERC Gas Tariff                                Sub. Second Revised Sheet No. 106
First Revised Volume No. 1-A              Superseding
                                                     First Revised Sheet No. 106
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)


28.  CAPACITY RELEASE (Continued)

     28.8 Scheduling of Parcels, Bids and Notifications (Continued)

          (c)  Prearranged Deal-A - less than or equal to thirty-one days.

               Releasing Shipper must inform PGT via the EBB of the particulars
               of the prearranged deal by  12:00 p.m. Pacific Time on the 2nd
               business day before the commencement of the Release Term.

               Posting Period - PGT will post the particulars of the prearranged
               deal no later than  12:00 p.m. Pacific Time 2 business days after
               the commencement of the Release Term.

          (d)  Prearranged Deal-B - equal to or greater than thirty-one days at
               the highest valued bid pursuant to the methodology selected by
               the Releasing Shipper.

               Posting Period - Releasing Shipper must submit the particulars of
               the prearranged deal to PGT for posting on the EBB no later than
               12:00 p.m. Pacific Time 2 business days before the commencement
               of the Release Term.

          (e)  Prearranged Deal-C - greater than or equal to one day.

               Posting Period - up to  12:00 p.m. Pacific Time on the 6th
               business day before the commencement of the Release Term.

               Bid Period - a minimum period of 1 business day subsequent to the
               close of the Posting Period.  The Bid Period closes at 2:00 p.m.
               Pacific Time on the  5th business day before the commencement of
               the Release Term.

               Bid Reconciliation Period - a period of 2 business days
               subsequent to the close of the Bid Period.  The Bid
               Reconciliation Period closes at 2:00 p.m. Pacific Time on the 3rd
               business day before the commencement of the Release Term.

                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Mgr. Gas Supply & Reg. Affairs
Issued on: JUNE 19, 1995                                Effective: JULY 10, 1995
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RM95-5-000, dated MAY 31, 1995

 
Pacific Gas Transmission Company
FERC Gas Tariff                                      First Revised Sheet No. 107
First Revised Volume No. 1-A              Superseding
                                                          Original Sheet No. 107
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

28.  CAPACITY RELEASE (Continued)

     28.8 Scheduling of Parcels, Bids and Notifications (Continued)

          (e)  Prearranged Deal-C - greater than or equal to one day (Continued)

               Match Period - a period of 1 business day subsequent to the close
               of the Bid Reconciliation Period.  The Match Period closes at
               2:00 p.m. Pacific Time on the  2nd business day before the
               commencement of the Release Term.  At that time results of the
               bidding shall be posted no later than 2:00 p.m. Pacific Time on
               the 2nd business day before the commencement of the Release Term.

 
                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      First Revised Sheet No. 108
First Revised Volume No. 1-A              Superseding
                                                          Original Sheet No. 108
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)



                            Reserved For Future Use.
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      First Revised Sheet No. 109
First Revised Volume No. 1-A              Superseding
                                                          Original Sheet No. 109
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

28.  CAPACITY RELEASE (Continued)

     28.9 Crediting, Billing Adjustments and Refunds

          (a)  Eligibility

               PGT shall provide revenue credits to any Releasing Shipper which
               releases capacity to a Replacement Shipper pursuant to the
               provisions of Paragraph 28.

          (b)  Monthly Crediting Procedure

               Revenue credits for released capacity shall be credited monthly
               as an offset to a Releasing Shipper's reservation charge (or the
               volumetric equivalent of the reservation charge on a 100% load-
               factor basis applicable to the Releasing Shipper.  This shall
               also be referred to in this Paragraph 28.9 as the equivalent
               volumetric rate) payable to PGT under the applicable rate
               schedule for the service that has been released.  PGT shall
               credit each month to the Releasing Shipper's account 100% of the
               revenues from the charges invoiced to the Replacement Shipper(s)
               for the reservation charge (or equivalent volumetric rate).

          (c)  Billing Adjustments

               PGT shall apply the revenues received from Replacement Shippers
               first to the reservation charge (or equivalent volumetric rate),
               next to the GRI reservation surcharge.

               Should Replacement shipper default on payment to PGT of the
               reservation charge (or equivalent volumetric rate) PGT shall bill
               Releasing Shipper for such unpaid charges and apply interest to
               such adjustments in accordance with the provisions of Paragraph 8
               of the Transportation General Terms and Conditions.


                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: AUGUST 13, 1996                         Effective: SEPTEMBER 13, 1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                           Original Sheet No. 110
First Revised Volume No. 1-A   
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

28. CAPACITY RELEASE (Continued)

    28.9 Crediting, Billing Adjustments and Refunds (Continued)

         (d)  Excess Revenue Credits

              Releasing Shipper is entitled to excess revenue credits resulting
              when the reservation charge (or equivalent volumetric rate)
              revenues actually received by PGT from the Replacement Shipper(s)
              exceed the reservation charge (or equivalent volumetric rate)
              revenues which would have been received by PGT from the Releasing
              Shipper if capacity was not released.

         (e)  Refunds

              PGT shall track all changes in its rates approved by the
              Commission.  In the event the Commission orders refunds of any
              such rates charged by PGT and previously approved, PGT shall make
              corresponding refunds to all affected Shippers including Shippers
              receiving capacity release service.

              In such instances when rates to Replacement Shippers are reduced,
              PGT shall make corresponding adjustments to the crediting of
              revenues to Releasing Shippers for the period such refunds are
              payable.


                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: AUGUST 02, 1993                          Effective: NOVEMBER 01, 1993
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RS92-46-000, et al., dated JULY 12, 1993



 
Pacific Gas Transmission Company
FERC Gas Tariff                                      First Revised Sheet No. 111
First Revised Volume No. 1-A              Superseding
                                                          Original Sheet No. 111
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

28.  CAPACITY RELEASE (Continued)
             
                              (STANDARD RELEASE)
                    SEE GRAPHIC INDEX AT REAR OF DOCUMENT.

                       (CAPACITY RELEASE TIMELINE GRAPH)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994


 
Pacific Gas Transmission Company
FERC Gas Tariff                                              First Sheet No. 112
First Revised Volume No. 1-A              Superseding
                                                          Original Sheet No. 112
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

28.  CAPACITY RELEASE (Continued)

                                (RAPID RELEASE)
                    SEE GRAPHIC INDEX AT REAR OF DOCUMENT.


                       (CAPACITY RELEASE TIMELINE GRAPH)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994


 
Pacific Gas Transmission Company
FERC Gas Tariff                                Sub. Second Revised Sheet No. 113
First Revised Volume No. 1-A              Superseding
                                                     First Revised Sheet No. 113
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

28.  CAPACITY RELEASE (Continued)


                            (PRE-ARRANGED DEAL - A)
                    SEE GRAPHIC INDEX AT REAR OF DOCUMENT.
        

                       (CAPACITY RELEASE TIMELINE GRAPH)
________________________________________________________________________________
Issued by: R.T. Howard, Mgr. Gas Supply & Regulatory Affairs
Issued on: JUNE 19, 1995                                Effective: JULY 10, 1995
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RM95-5-000, dated MAY 31, 1995

 
Pacific Gas Transmission Company
FERC Gas Tariff                                Sub. Second Revised Sheet No. 114
First Revised Volume No. 1-A              Superseding
                                                     First Revised Sheet No. 114
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

28.  CAPACITY RELEASE (Continued)

                            (PRE-ARRANGED DEAL - B)
                    SEE GRAPHIC INDEX AT REAR OF DOCUMENT.

                       (CAPACITY RELEASE TIMELINE GRAPH)
________________________________________________________________________________
Issued by: R.T. Howard, Mgr. Gas Supply & Reg. Affairs
Issued on: JUNE 19, 1995                                Effective: JULY 10, 1995
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RM95-5-000, dated MAY 31, 1995


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      First Revised Sheet No. 115
First Revised Volume No. 1-A              Superseding
                                                          Original Sheet No. 115
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

28.  CAPACITY RELEASE (Continued)

                            (PRE-ARRANGED DEAL - C)
                    SEE GRAPHIC INDEX AT REAR OF DOCUMENT.

                       (CAPACITY RELEASE TIMELINE GRAPH)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      First Revised Sheet No. 116
First Revised Volume No. 1-A              Superseding
                                                            Sheet Nos. 116 - 118
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)



                            Reserved For Future Use
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994

 
Pacific Gas Transmission Company
FERC Gas Tariff                                      First Revised Sheet No. 119
First Revised Volume No. 1-A              Superseding
                                                          Original Sheet No. 119
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

29.   FLEXIBLE RECEIPT AND DELIVERY POINTS

     29.1  Firm Service

          (a)  Addition of a Receipt Point

               Any firm Shipper receiving service under Part 284 of the
               Commission's regulations is entitled to use the receipt point
               specified in its service agreement as a primary receipt point.  A
               firm Shipper may add a secondary receipt point, provided the
               secondary receipt point is downstream of the primary receipt
               point at any time during the life of the contract.

               Firm Shippers who are billed under a reservation charge and a
               delivery rate will continue to be billed reservation charges
               based on the primary receipt point while delivery rates,
               including fuel, will be calculated on the receipt point actually
               used.

               To the extent additional meter station capacity or other
               facilities are required to effect the receipt point change, PGT
               will construct the additional capacity consistent with Paragraph
               18.5.

          (b)  Changing a Receipt Point

               A firm Shipper may change primary receipt points to a downstream
               receipt point but will continue to be billed reservation charges
               based on the original primary receipt point.  Changes in receipt
               points will be permitted provided sufficient receipt point
               capacity exists at the receiving meter station and subject to any
               operating constraints.  To the extent additional meter station
               capacity or other facilities are required to effect the receipt
               point change, PGT will construct the additional capacity at the
               firm Shipper's expense consistent with Paragraph 18.5.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994

 
Pacific Gas Transmission Company
FERC Gas Tariff                                      First Revised Sheet No. 120
First Revised Volume No. 1-A              Superseding
                                                          Original Sheet No. 120
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

29.   FLEXIBLE RECEIPT AND DELIVERY POINTS (Continued)

     29.1  Firm Service (Continued)

          (c)  Addition of a Delivery Point

               Each firm Shipper is entitled to an allocation of its MDQ to a
               delivery point(s) as its primary delivery point(s).

               A firm Shipper may add secondary delivery points provided the
               secondary delivery points are upstream of the primary delivery
               point, at any time during the life of the contract.  In this
               case, the firm Shipper will continue to be billed any applicable
               reservation charges based on the primary delivery point; however,
               delivery rates, including fuel, will be calculated based on the
               delivery point actually used.

               A firm Shipper with primary deliveries allocated to a minor
               delivery point may add secondary delivery points to its contract
               provided that the addition of the secondary delivery point does
               not materially impact service to other firm Shippers.

               To the extent additional meter station capacity is required to
               effect the delivery point(s) change, and subject to any operating
               constraints PGT will construct the additional capacity consistent
               with Paragraph 18.5.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      First Revised Sheet No. 121
First Revised Volume No. 1-A              Superseding
                                                          Original Sheet No. 121
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

29.   FLEXIBLE RECEIPT AND DELIVERY POINTS (Continued)

     29.1  Firm Service (Continued)

          (d)  Changing a Delivery Point

               A firm Shipper may change primary delivery points, to an upstream
               delivery point but will continue to be billed reservation charges
               based on the original primary delivery point.  Changes in
               delivery points will be permitted provided sufficient delivery
               point capacity exists at the delivery meter station.  To the
               extent additional meter station and subject to any operating
               constraints capacity is required to effect the delivery point
               change, PGT will construct the additional capacity at the firm
               Shipper's expense consistent with Paragraph 18.5.

               A firm Shipper with primary deliveries allocated to a minor
               delivery point may change primary delivery points in its contract
               provided that the change of primary delivery point does not
               materially impact service to other firm Shippers.

     29.2 Interruptible Service

          (a) Change of a Receipt/Delivery Point

               Interruptible Shippers will have the right to flexible receipt
               and delivery points, at a lower priority than firm or released
               services.

          (b)  Addition of a Receipt Point

               Except as otherwise provided in this paragraph, Shippers
               receiving service under any Part 284 interruptible transportation
               rate schedule may add any receipt point downstream of the primary
               receipt point on the PGT system at any time during the life of
               the contract with no effect on the Interruptible Shipper's
               previously granted interruptible transportation priority.
               However, requests by an interruptible Shipper to increase its
               total MDQ and/or to add an upstream receipt point will be
               considered a new request for service.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      First Revised Sheet No. 122
First Revised Volume No. 1-A              Superseding
                                                          Original Sheet No. 122
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

29.   FLEXIBLE RECEIPT AND DELIVERY POINTS (Continued)

     29.2 Interruptible Service (Continued)

          (c)  Addition of a Delivery Point

               An Interruptible Shipper may request interruptible service at
               additional delivery points at any time.  The request of an
               additional downstream delivery point, or a request to increase
               the delivery quantity at an existing delivery point, will be
               considered a new request for service with priority assigned in
               accordance with Paragraph 19.2.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: FEBRUARY 28, 1994                           Effective: APRIL 01, 1994


 
Pacific Gas Transmission Company
FERC Gas Tariff                                           Original Sheet No. 123
First Revised Volume No. 1-A              
                                          
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

30. GAS SUPPLY RESTRUCTURING TRANSITION COSTS

    30.1 Purpose

         This Paragraph 30 establishes the means by which PGT shall recover GSR
         Costs.  PGT will make one or more separate rate filings to recover GSR
         Costs pursuant to this Paragraph 30.

    30.2 Definitions

         The following defines certain terms as they are used in this Paragraph
         30:

         (a)  "Gas Supply Restructuring Costs" shall mean amounts in cash or
              other consideration eligible for recovery under Order Nos. 500, et
              seq., or 528, et seq., or 636, et seq., or which are incurred to
              restructure, reform or terminate the existing International
              Contract between PGT and A&S and underlying A&S gas supply
              contracts, or to resolve claims by Canadian gas suppliers related
              to past or future liabilities or obligations of PGT or A&S under
              the International Contract and underlying A&S gas supply
              contracts.

         (b)  "The Initial GSR Cost Collection Period" will consist of the three
              (3) years commencing with the effective date of the rate filing to
              recover GSR Costs.  An Initial GSR Cost Collection Period shall
              apply to each rate filing PGT makes to recover GSR Costs.

         (c)  "Carryover GSR Cost Collection Period" will consist of the
              extension of the Initial GSR Collection Period in accordance with
              Paragraph 30.6 hereof to complete the full recovery (but no
              overrecovery) of PGT's GSR Costs.

         (d)  "Approved GSR Costs" shall mean those GSR costs as defined in
              Paragraph 30.2(a) above, which are approved by FERC for recovery
              by PGT through the Transition Cost Recovery Mechanism as defined
              in this Paragraph 30.

         (e)  "Northwest Shippers", for purposes of this paragraph, are defined
              as Washington Natural Gas Company, Cascade Natural Gas Company,
              Washington Water Power Company/WP Natural Gas and Northwest
              Natural Gas Company.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: AUGUST 02, 1993                          Effective: NOVEMBER 01, 1993
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RS92-46-000, et al., dated JULY 12, 1993


 
Pacific Gas Transmission Company
FERC Gas Tariff                                Substitute Original Sheet No. 124
First Revised Volume No. 1-A              Superseding
                                                          Original Sheet No. 124
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)
30.  GAS SUPPLY RESTRUCTURING TRANSITION COSTS (Continued)
     30.3 Applicability of GSR Transition Costs

          GSR Transition Costs shall be applicable to all Shippers except those
          firm Shippers paying incremental rates on PGT which are also
          Supporting Parties to the FERC-approved settlement in Docket No. RS92-
          46-000.

     30.4 Recovery of Surcharge Amounts

          PGT shall recover from each Shipper meeting the applicability criteria
          defined in Paragraph 30.3 the affected Shipper's GSR Surcharge amounts
          and Direct Bill, if applicable, during the Initial GSR Cost Collection
          Period and shall continue to recover such amounts during any
          applicable Carryover GSR Cost Collection Period as necessary to
          complete the full recovery (but no overrecovery) of PGT's GSR Costs.

     30.5 Transition Cost Recovery Mechanism

          (a)  Absorption -- PGT's shareholder shall absorb 25% of all Approved
               GSR Costs.

          (b)  Direct Bill -- 25% of all Approved GSR Costs will be recovered by
               PGT through a Direct Bill.  A Direct Bill will be assessed to
               PG&E for 100% of the Direct Bill amount, excluding the amount to
               be collected from the Northwest Shippers and credited against the
               Direct Bill portion as defined in Paragraph 30.5(d).  PG&E may
               pay its Direct Bill in a lump sum, plus carrying charges on the
               principal amount accrued, in accordance with Paragraph 30.5(e)
               until the payment is made.  In lieu of paying the Direct Bill in
               a lump sum, PG&E may elect one of three payment schedules.
               PG&E's Direct Bill amount and the monthly amount due under each
               extended payment option, which shall include carrying charges
               accrued on the unpaid balance in accordance with Paragraph
               30.5(e), shall be specified in the Statement of Effective Rates
               and Charges of First Revised Volume No. 1-A.

         (c)   GSR Transition Cost Surcharge -- 50% of all Approved GSR Costs
               will be recovered by PGT through a volumetric MMBtu-mile
               surcharge. The GSR Transition Cost Surcharge shall include any
               applicable carrying charges accruing on the unrecovered balance.
               The GSR Transition Cost Surcharge shall be stated in the
               Statement of Effective Rates and Charges of PGT's FERC Gas Tariff
               First Revised Volume No. 1-A as the same may change from time to
               time, depending on PGT's GSR Costs.
                                                                     (Continued)


________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: DECEMBER 10, 1993                        Effective: NOVEMBER 15, 1993
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RP94-24-000, dated NOVEMBER 12, 1993

 
Pacific Gas Transmission Company
FERC Gas Tariff                                           Original Sheet No. 125
First Revised Volume No. 1-A              
                                          
________________________________________________________________________________


                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)
30. GAS SUPPLY RESTRUCTURING TRANSITION COSTS (Continued)

    30.5 Transition Cost Recovery Mechanism (Continued)

         (d)  Northwest Shippers' GSR Cost Responsibility -- All Northwest
              Shippers (excluding Washington Natural Gas Company) shall pay a
              Direct Bill and Washington Natural Gas shall pay a GSR transition
              cost surcharge (different from that provided in (c) above) for
              their share of GSR transition costs.  The Northwest Shippers'
              responsibility shall be equal to 1.3 percent of the Approved GSR
              costs that are not absorbed by PGT and in any event shall not
              exceed a total of $1,454,000.  Of this amount, one-third, up to
              $485,000, will be credited against the amount allocated to the
              Direct Bill as described in Paragraph 30.5(b), and two-thirds, up
              to $969,000, will be credited against the amount allocated to the
              GSR surcharge provided in Paragraph 30.5(c).  The amounts
              allocated to the Northwest Shippers as a group will be allocated
              among the individual Northwest Shippers based on the percentages
              shown below and will not exceed the applicable total amount for
              each Shipper.


                                                                     Total
                                                     Percentage      Amount
                                                             
              Washington Natural Gas Company         55.02% up to   $  800,000
              Cascade Natural Gas Corporation        24.07% up to      350,000
              Washington Water Power Company/
              WP Natural Gas                         18.57% up to      270,000
              Northwest Natural Gas Company           2.34% up to       34,000
 
              Total Northwest Shippers              100.00%         $1,454,000


              Washington Water Power Company/WP Natural Gas (WWP), Cascade
              Natural Gas Corporation (CNG), and Northwest Natural Gas Company
              (NNG) will be billed and will pay immediately all amounts of the
              Approved GSR Costs allocated to them up to the total maximums
              noted above.  The total amount allocated to Washington Natural Gas
              Company (WNG) will be recovered through a volumetric surcharge
              over a three-year amortization period based on the approved
              commodity throughput for WNG.  Any amounts not recovered at the
              end of the 36-month amortization period will be due and payable in
              one lump sum.  Once the maximum GSR Costs applicable to Northwest
              Shipper(s), as such amounts may be adjusted pursuant to the
              application of rolled-in rates on the PGT system, have been
              collected then the GSR Cost tariff provisions will no longer apply
              to such Northwest Shipper(s).   (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: AUGUST 02, 1993                          Effective: NOVEMBER 01, 1993
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RS92-46-000, et al., dated JULY 12, 1993



 
Pacific Gas Transmission Company
FERC Gas Tariff                                Substitute Original Sheet No. 126
First Revised Volume No. 1-A              Superseding
                                                          Original Sheet No. 126
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

30. GAS SUPPLY RESTRUCTURING TRANSITION COSTS (Continued)

    30.5 Transition Cost Recovery Mechanism (Continued)

         (e)  Carrying Charges --  Carrying charges shall accrue beginning on
              the effective date of PGT's filing to recover GSR costs or the
              date PGT initiates payment for GSR costs, whichever is later.
              Carrying charges shall be calculated in accordance with Section
              154.67 of the Commission's regulations.

    30.6 Reconciliation

         (a)  At the conclusion of the Initial GSR Cost Collection Period, PGT
              will determine its GSR Costs and the actual amounts of GSR
              Transition Cost Surcharge revenues.

         (b)  If PGT's collections hereunder shall equal or exceed its GSR
              Costs, PGT shall file to terminate further collections hereunder.
              The amount of any excess collected shall be repaid to all Shippers
              affected hereby in proportion to the principal amount of GSR
              Transition Cost Surcharge payments they have provided pursuant to
              this Paragraph 30.  Within ninety (90) days of the termination of
              collections pursuant to this Paragraph 30, PGT will submit a
              report to the Commission setting out a comparison of its GSR costs
              and the amounts collected hereunder and any repayments to be
              provided hereunder.  Within thirty (30) days of the Commission's
              approval of such report, repayments, with applicable carrying
              charges, shall be paid.

         (c)  If PGT's collections hereunder are less than its GSR Costs, PGT
              shall be permitted to recover such deficiency, including carrying
              charges, during the Carryover GSR Cost Collection Period by filing
              with the Commission GSR Transition Cost Surcharges within ninety
              (90) days of the conclusion of the Initial GSR Cost Collection
              Period.  The GSR Transition Cost Surcharge will be determined by
              dividing the remaining GSR costs by the applicable quantities
              underlying PGT's then-effective rates.  The GSR Transition Cost
              Surcharge shall be effective on the first day of the month
              following Commission approval of such filing.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: OCTOBER 13, 1993                         Effective: NOVEMBER 01, 1993
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RS92-46-000, et al., dated OCTOBER 01, 1993


 
Pacific Gas Transmission Company
FERC Gas Tariff                                     Second Revised Sheet No. 127
First Revised Volume No. 1-A              Superseding
                                                     First Revised Sheet No. 127
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

31.  Reserved



                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: AUGUST 13, 1996                          Effective: SEPTEMBER 13,1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      First Revised Sheet No. 128
First Revised Volume No. 1-A              Superseding
                                                          Original Sheet No. 128
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

                            Reserved for future use.



                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: AUGUST 13, 1996                          Effective: SEPTEMBER 13,1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                     Second Revised Sheet No. 129
First Revised Volume No. 1-A              Superseding
                                                     First Revised Sheet No. 129
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

32.   EQUALITY OF TRANSPORTATION SERVICE

          PGT hereby states that the terms and conditions of service for all
     unbundled sales and transportation services provided in PGT's FERC Gas
     Tariff Second Revised Volume No. 1 and First Revised Volume No. 1-A, are
     provided on a basis that is equal in quality for all Shippers.  All
     Shippers can access all sellers of gas and receive the same quality of
     service on PGT whether their gas supplies are purchased from PGT or any
     other seller.  Furthermore, no preference is accorded to any affiliate of
     PGT for sales and transportation services provided by PGT.


                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: AUGUST 13, 1996                          Effective: SEPTEMBER 13,1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                           Original Sheet No. 130
First Revised Volume No. 1-A              
                                          
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

33. RIGHT OF FIRST REFUSAL UPON TERMINATION OF FIRM SHIPPER'S SERVICE AGREEMENT

         Firm Shippers (original capacity holders) under PGT's firm
    transportation rate schedules of First Revised Volume No. 1-A shall have the
    right of first refusal at the termination of their service agreements.
    Original capacity holders must notify PGT one year prior to termination of
    their intent to terminate the service agreement.

         One year prior to the expiration of the service agreement, PGT will
    post a notice on its EBB that the original capacity holder's service
    agreement will terminate in one year and the original capacity holder has
    either elected or not elected to terminate.

    33.1 In the event original capacity holder elects termination, PGT shall
         subject this capacity to a bidding process.  PGT shall require bids be
         submitted no later than 6 months prior to the service agreement
         expiration.  The bid period will be 2 months.  PGT will announce the
         bid winner(s) 1 month after the close of the bid period.  Tied bids
         will be awarded on a pro rata basis.  Winning Shipper(s) and PGT must
         execute a new firm transportation service agreement prior to service
         commencement.

    33.2 In the event original capacity holder does not elect termination, PGT
         will commence open bidding 6 months prior to the service agreement
         termination.  The bid period will be 1 month.  The original capacity
         holder will have 1 month from the close of the bid period to match the
         highest bid(s).  PGT will announce the winning bid(s) within 1 month
         after the close of the match period.  If the original capacity holder
         matches the highest bid(s), the capacity is awarded to the original
         capacity holder.  If the original capacity holder does not match the
         highest bid(s), the original capacity holder's bid shall be rejected.
         If there is more than one winning bid, PGT shall award capacity on a
         pro rata basis.  New Shippers must execute a firm transportation
         service agreement with PGT prior to service commencement.  Original
         capacity holder is allowed to retain a portion of its capacity by
         matching price and term according to the procedure outlined in this
         provision.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: AUGUST 02, 1993                          Effective: NOVEMBER 01, 1993
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RS92-46-000, et al., dated JULY 12, 1993

 
Pacific Gas Transmission Company
FERC Gas Tariff                                           Original Sheet No. 131
First Revised Volume No. 1-A              
                                          
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

33. RIGHT OF FIRST REFUSAL UPON TERMINATION OF FIRM SHIPPER'S SERVICE AGREEMENT
    (Continued)

    33.3 Bids shall be evaluated on the net present value incorporating price
         and term.  The price shall be the rate Shippers are willing to pay up
         to the maximum authorized rate.  The maximum term is 20 years.

    33.4 If there are no competing bids other than that of the original capacity
         holder, the rate and terms of continuing service is to be negotiated
         between existing capacity holder and PGT.  In addition, in this
         instance, if the existing capacity holder agrees to pay the maximum
         authorized rate, the existing capacity holder may determine the term it
         desires and PGT must extend its contract to the existing capacity
         holder accordingly.

    33.5 Shippers who terminate their service agreements are not liable for any
         reservation charges or other charges applicable to the new Shipper
         contracting for this capacity.

    33.6 Only bona fide bids will be accepted.  A bona fide bid offer shall be:
         (a) submitted via PGT's EBB; (b) accepted in principle; and (c)
         pursuant to an arms-length transaction.  If the Service Agreement is
         not executed within 30 days, the request for capacity shall expire
         without prejudice to the prospective Shipper's right to submit a new
         request for capacity.  PGT shall then notify the Shipper via the EBB of
         the acceptable offer, if any, having the next greatest economic value
         in accordance with the provisions of this Paragraph.  If there is no
         other acceptable offer, the Shipper may continue service in accordance
         with this Paragraph.

                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: AUGUST 02, 1993                          Effective: NOVEMBER 01, 1993
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RS92-46-000, et al., dated JULY 12, 1993

 
Pacific Gas Transmission Company
FERC Gas Tariff                                     Second Revised Sheet No. 132
First Revised Volume No. 1-A              Superseding
                                                     First Revised Sheet No. 132
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

34.  ELECTRONIC BULLETIN BOARD

     34.1 General

          PGT shall use its Electronic Bulletin Board (EBB), "Pacific Trail"
          for capacity release.  PGT shall maintain an EBB which will provide a
          range of electronic pipeline services and information to all parties
          on a nondiscriminatory basis.  The EBB is available to any party that
          has compatible equipment for electronic communication and transmission
          of data.  Access to the EBB is obtained by contacting PGT's Gas
          Control Department at 1-800-238-2781  and requesting a user
          identification.  The EBB will operate 24 hours a day; however, certain
          functions may be limited to specific operating times during the
          business day.  There is no direct connection charge to use the EBB.
          However, PGT reserves the right to change the telephone access from an
          "800" number to a "900" number at its sole discretion.

          PGT shall exercise reasonable efforts to ensure the accuracy and
          security of information presented on the EBB.

     34.2 Menu of Services and Information

          PGT's EBB will provide the following main menu of services and
          information:

          (a) Capacity Release
          (b) Bulletins and Capacity Available
          (c) Nominations
          (d) Submit Request for Firm or Interruptible Service
          (e) Interruptible Transportation Queue
          (f) Tariffs and Rates
          (g) Account Status of Shipper
          (h) Marketing Affiliate Information
          (i) Offers to Purchase Capacity
          (j) Procedures for Filing Complaints
          (k) E-mail to Other Shippers/PGT System Administrator
          (l) EBB Mailbox

                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: AUGUST 13, 1996                          Effective: SEPTEMBER 13,1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      First Revised Sheet No. 133
First Revised Volume No. 1-A              Superseding
                                                          Original Sheet No. 133
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

34.  ELECTRONIC BULLETIN BOARD (Continued)

     34.2  Menu of Services and Information (Continued)

            (a)  Capacity Release

                 The capacity release menu would allow the following options:

                 (1) Review Available Released Parcels
                 (2) Submit/Check Status of Request for Authority to\
                      Bid/Release Capacity
                 (3) Post/Withdraw Capacity for Release
                 (4) Submit/Withdraw Bid for Released Capacity
                 (5) Review the Status of Shipper's Active Bids
                 (6)  Review the Status of Shipper's Active Released    Parcels
                 (7) Review Shipper's Authority to Bid for Released
                      Capacity
                 (8) Review Transaction Log of Previous Releases

            (b) Bulletins and Capacity Available

               The bulletins and capacity available menu would allow the
               following options:

                 Capacity Availability Information:

                 (1)  At Receipt Points
                 (2)  At Major Delivery Points
                 (3)  At Minor Delivery Points
                 (4)  Projected Capacity
                 (5)  PGT Maintenance Schedules
                 (6) Whether the Capacity is Available From PGT or
                      Through PGT's Capacity Release Program
                 (7)  Operational Bulletins
                 (8)  Regulatory Bulletins

            (c)  Nominations

                 (1) Submit Nominations to PGT Gas Control
                 (2)  Review Confirmation
                 (3)  E-mail to Gas Control
                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: AUGUST 13, 1996                          Effective: SEPTEMBER 13,1996


 
Pacific Gas Transmission Company
FERC Gas Tariff                                      First Revised Sheet No. 134
First Revised Volume No. 1-A              Superseding
                                                          Original Sheet No. 134
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

34.  ELECTRONIC BULLETIN BOARD (Continued)

       34.2 Menu of Services and Information (Continued)

            (d) Submit Request for Firm or Interruptible Service

            (e) Interruptible Transportation Queue

            (f)  Tariffs and Rates

                 The tariffs and rates menu would allow the following options:

                 (1)  Transportation Rates
                 (2) Transportation Rate Discounts (including negotiated ITS-1
                    rates)
                 (3) First Revised Volume No. 1-A - Tariff
                 (4) Second Revised Volume No. 1 - Tariff

            (g)  Account Status of Shippers

            (h)  Marketing Affiliate Information

                 The marketing affiliate information would allow the following
                 options:

                 (1)  Transportation request data
                 (2)  Receipt/delivery point data
                 (3)  Delivery point discount data


                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: AUGUST 13, 1996                          Effective: SEPTEMBER 13,1996

 
Pacific Gas Transmission Company
FERC Gas Tariff                                      First Revised Sheet No. 135
First Revised Volume No. 1-A              Superseding
                                                          Original Sheet No. 135
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

34.  ELECTRONIC BULLETIN BOARD (Continued)

       34.2 Menu of Services and Information (Continued)

            (i)  Offers to Purchase Capacity

                 PGT shall post the following information on offers to purchase
                 capacity:

                 (1)  Legal Name of Offerer
                 (2)  Name, telephone Number, Fax Number, Address of Contact
                      Person and Alternate Contact Person
                 (3)  Firm or Interruptible Service Requested
                 (4)  Amount of Capacity Sought
                 (5)  Term Sought
                 (6)  Other Information

            (j)  Procedures for Filing Complaints

                 The Procedures for filing complaints menu offers the following
                 options:

                 (1)  Review Complaint Procedure
                 (2)  Enter a Complaint
                 (3)  Send E-Mail to PGT System Administrator

            (k)  E-Mail to other Shippers/PGT Systems Administrator

            (l)  EBB Mailbox

                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: AUGUST 13, 1996                          Effective: SEPTEMBER 13,1996

 
Pacific Gas Transmission Company
FERC Gas Tariff                                           Original Sheet No. 136
First Revised Volume No. 1-A              
                                          
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

34.  ELECTRONIC BULLETIN BOARD (Continued)

    34.3 Historical Information

         PGT will back up daily transaction information on the EBB.  This
         historical information shall be kept for a three-year period and may be
         archived off-line.  Information that may be accessed includes Parcel
         information and bid information associated with that Parcel, including
         the identity of the winning bid and bidder.

         PGT will provide access to historical data in one of the following
         manners:

         (a)  Direct access by parties via the EBB.  In such cases, data may be
              viewed, down loaded to a computer or printed by the party.

         (b)  PGT may elect to archive historical data off-line.  Parties may
              access this data by sending a written or an electronic mail
              request to the PGT Capacity Release System Administrator
              requesting such historical data.  PGT will make such information
              available to Shippers.



                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: AUGUST 02, 1993                          Effective: NOVEMBER 01, 1993
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RS92-46-000, et al., dated JULY 12, 1993

 
Pacific Gas Transmission Company
FERC Gas Tariff                                     Second Revised Sheet No. 137
First Revised Volume No. 1-A              Superseding
                                                     First Revised Sheet No. 137
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

35.  Reserved



                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: SEPTEMBER 30, 1996                      Effective: SEPTEMBER 11, 1996
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RP94-149, 76-61,246, dated SEPTEMBER 11, 1996

 
Pacific Gas Transmission Company
FERC Gas Tariff                                      First Revised Sheet No. 138
First Revised Volume No. 1-A              Superseding
                                                          Original Sheet No. 138
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)



                            Reserved for future use.



                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: SEPTEMBER 30, 1996                      Effective: SEPTEMBER 11, 1996
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RP94-149, 76-61,246, dated SEPTEMBER 11, 1996

 
Pacific Gas Transmission Company
FERC Gas Tariff                                          Original Sheet No. 138A
First Revised Volume No. 1-A              
                                          
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

35A.  CREDITING OF INTERRUPTIBLE TRANSPORTATION REVENUES ON EXTENSIONS

    (1)  Interruptible Transportation Revenue Credits on Coyote Springs
         Extension

    (a)  Applicability. Revenue credits from interruptible transportation
    revenues received by PGT from Rate Schedule ITS-1 (E-3) Shippers shall be
    provided to PGT's firm Shippers under Rate Schedules FTS-1 (E-3) ("Eligible
    Shippers"), excluding Shippers receiving service under a Capacity Release
    Service Agreement.

    (b)  Crediting Percentage.  PGT shall credit to Eligible Shippers 90 percent
    of interruptible transportation revenues received during each 12-month
    period, commencing November 1st of each year, but only to the extent that
    such transportation revenues exceed the amount of fixed costs which were
    allocated to interruptible transportation (Cost Allocation Amount) by PGT as
    part of designing PGT's effective transportation rates during such 12-month
    period. To the extent that PGT is required to provide interruptible
    transportation revenue credits during any period during which this Paragraph
    35A shall be or shall have been in effect for less than 12 months, a "Short
    Period", PGT shall pro rate the Cost Allocation Amount by the number of days
    during such Short Period as compared to the total number of days in such 12
    months.  To calculate the interruptible transportation revenue credit due
    under the provisions of this paragraph, where applicable, such pro rated
    Cost Allocation Amount shall be compared to PGT's actual interruptible
    revenues for the Short Period.

    (c)  Timing of Credits.  Within 45 days after November 1st of each 12-month
    period or after the end of a Short Period, if applicable, PGT shall
    determine the total amount of the applicable Rate Schedule ITS-1 (E-3)
    revenues received during the 12-month period or Short Period and the
    distribution of the interruptible revenue credits due to Eligible Shippers
    as described below.  Such revenue credits shall be reflected as a credit
    billing adjustment in the next invoices rendered to the Eligible Shippers.
    In the event that such credit billing adjustment would result in a credit
    total invoice to any Shipper, PGT will refund the excess credit billing
    adjustment to the Shipper in cash within 15 days after determination of the
    amount of the credit due to the Shipper.

                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: SEPTEMBER 29, 1995                       Effective: NOVEMBER 01, 1995

 
Pacific Gas Transmission Company
FERC Gas Tariff                                          Original Sheet No. 138B
First Revised Volume No. 1-A              
                                          
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

35A.  CREDITING OF INTERRUPTIBLE TRANSPORTATION REVENUES ON EXTENSIONS
      (Continued)

      (1)  Interruptible Transportation Revenue Credits on Coyote Springs
           Extension (Continued)

      (d) Exclusion. Revenue credits shall not be awarded for that portion of
      interruptible revenues that are attributable to: (1) the recovery by PGT
      of variable costs, which portion shall be equal to the minimum usage
      charge for Rate Schedule ITS-1 (E-3), (2) the recovery of Gas Supply
      Restructuring (GSR) costs to be recovered by a GSR volumetric surcharge
      under Rate Schedule ITS-1 (E-3), and (3) relate to other volumetric
      surcharges such as GRI and ACA.

      (e) Distribution Method. Interruptible transportation revenue credits
      shall be credited to each Eligible Shipper on a pro rata basis in
      proportion to the reservation revenues received during the 12-month period
      or Short Period from each Eligible Shipper divided by the total
      reservation revenue for each Eligible Shipper received during such period.
      The reservation revenues shall include the reservation charges which the
      Eligible Shippers actually pay prior to the distribution of all revenue
      credits, and including reservation charges applicable to capacity which
      was released into PGT's Capacity Release Programs during the 12-month
      period year or Short Period by the Eligible Shipper.

      (f) PGT shall pay interest to Eligible Shippers on any revenue credits
      from the date such credits accrue. Such interest shall be calculated based
      upon the rate of interest specified in Section 154.67(c) of the
      Commission's regulations.


                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: SEPTEMBER 29, 1995                       Effective: NOVEMBER 01, 1995

 
Pacific Gas Transmission Company
FERC Gas Tariff                                          Original Sheet No. 138C
First Revised Volume No. 1-A              
                                          
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

35A.  CREDITING OF INTERRUPTIBLE TRANSPORTATION REVENUES ON EXTENSIONS
      (Continued)

      (2)  Interruptible Transportation Revenue Credits on Medford Extension

      (a) Applicability.  Revenue credits from interruptible transportation
      revenues received by PGT from Rate Schedule ITS-1

      (E-1) Shippers shall be credited to the deferred account for Washington
      Water Power Company's WP Natural Gas subsidiary in accordance with the
      mechanism approved by Order of June 1, 1995, 71 FERC Paragraph 61,268.

      (b) Crediting Percentage. PGT shall credit to the deferred account 90
      percent of interruptible transportation revenues received during each 12-
      month period, commencing November 1st of each year, but only to the extent
      that such transportation revenues exceed the amount of fixed costs which
      were allocated to interruptible transportation (Cost Allocation Amount) by
      PGT as part of designing PGT's effective transportation rates during such
      12-month period. To the extent that PGT is required to provide
      interruptible transportation revenue credits during any period during
      which this Paragraph 35A shall be or shall have been in effect for less
      than 12 months, a "Short Period", PGT shall pro rate the Cost Allocation
      Amount by the number of days during such Short Period as compared to the
      total number of days in such 12 months. To calculate the interruptible
      transportation revenue credit due under the provisions of this paragraph,
      where applicable, such pro rated Cost Allocation Amount shall be compared
      to PGT's actual interruptible revenues for the Short Period.

      (c) Exclusion. Revenue credits shall not be awarded for that portion of
      interruptible revenues that are attributable to the recovery by PGT of
      variable costs, which portion shall be equal to the minimum usage charge
      for Rate Schedule ITS-1 (E-1).

                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: SEPTEMBER 29, 1995                       Effective: NOVEMBER 01, 1995

 
Pacific Gas Transmission Company
FERC Gas Tariff                             2nd Sub. First Revised Sheet No. 139
First Revised Volume No. 1-A              Superseding
                                                          Original Sheet No. 139
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

36.  DISCOUNT POLICY

     PGT may from time to time offer a discount from the maximum applicable rate
     for service under any service agreement governed by this FERC Gas Tariff.
     If and when PGT offers a discount, such discount shall first be applied to
     the GRI Surcharge and last to the base tariff rate.  PGT shall not discount
     its GSR Surcharge.
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: SEPTEMBER 26, 1996                      Effective: SEPTEMBER 13, 1996
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RM95-3, 76-61,300, dated SEPTEMBER 28, 1995

 
Pacific Gas Transmission Company
FERC Gas Tariff                                           Original Sheet No. 140
First Revised Volume No. 1-A              
                                          
________________________________________________________________________________

 
                          GENERAL TERMS AND CONDITIONS
                                  (Continued)

37. ADJUSTMENT MECHANISM FOR FUEL, LINE LOSS, AND OTHER UNACCOUNTED FOR GAS
    PERCENTAGES

    The effective fuel and line loss percentages under Rate Schedules FTS-1 and
    ITS-1 shall be adjusted downward to reflect reductions and may be adjusted
    upward to reflect increases in fuel usage and line loss in accordance with
    this Section 37.

    37.1  Computation of Effective Fuel and Line Loss Percentage

          The effective fuel and line loss percentage shall be the sum of the
          current fuel and line loss percentage and the fuel and line loss
          surcharge percentage.

    37.2  The Current Fuel and Line Loss Percentage

     (a) For each month, the current fuel and line loss percentage shall be
         determined in accordance with Section 37.2(c) hereof.  The current fuel
         and line loss shall be effective from the first day of such month and
         shall remain in effect for the month.

     (b) The current fuel and line loss percentage to be applicable for the
         month shall be posted on PGT's Electronic Bulletin Board not less than
         seven (7) days prior to the beginning of the month.

     (c) The current fuel and line loss percentage for the month shall be
         determined on the basis of (1) the estimated quantities of gas to be
         delivered by PGT for the account of Shippers during such month and (ii)
         the projected quantities of gas that shall be required for fuel and
         line loss during such month, adjusted for overrecoveries or
         underrecoveries of fuel and line loss during such month preceding the
         month in which the current fuel and line loss percentage is posted;
         provided, that the percentage shall not exceed the maximum current fuel
         and line loss percentage and shall not be less than the minimum current
         fuel and line loss percentage set forth on the Statement of Effective
         Rates and Charges.


                                                                     (Continued)
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: DECEMBER 22, 1993                         Effective: JANUARY 22, 1994

 
Pacific Gas Transmission Company
FERC Gas Tariff                                Substitute Original Sheet No. 141
First Revised Volume No. 1-A              Superseding
                                                          Original Sheet No. 141
________________________________________________________________________________

 
                          GENERAL TERMS AND CONDITIONS
                                  (Continued)

37. ADJUSTMENT MECHANISM FOR FUEL, LINE LOSS AND OTHER UNACCOUNTED FOR GAS
    PERCENTAGES (Continued)

    37.2  The Current Fuel and Line Loss Percentage (Continued)

     (d)  At least thirty (30) days prior to July 1 and January 1, PGT shall
          file with the Commission schedules supporting the current fuel and
          line loss percentages applicable during the six (6) months ending
          April 30 and October 31, respectively.

    37.3  The Fuel and Line Loss Surcharge Percentage

     (a) For each six (6) month period beginning July 1 and January 1, the fuel
         and line loss surcharge percentage shall be determined in accordance
         with Section 37.3(c) hereof.  The fuel and line loss surcharge
         percentage shall become effective on July 1 and January 1 and shall
         remain in effect for the six (6) month period ending December 31 and
         June 30, respectively.

     (b) At least thirty (30) days prior to each July 1 and January 1, PGT shall
         file with the Commission and post, as defined by Section 154.16 of the
         Commission's regulations, the fuel and line loss surcharge percentage,
         together with supporting documentation.

     (c) The fuel and line loss percentage shall be computed by (i) determining
         PGT's actual fuel and line loss for the six (6) month period ending
         April 30, if the effective date is July 1, or October 31, if the
         effective date is January 1, (ii) subtracting the actual quantities
         retained by PGT during such six (6) month period, and (iii) dividing
         the result by the estimated quantities of gas to be delivered by PGT
         for the account of Shippers during the six month period beginning with
         the effective date of the fuel and line loss surcharge percentage.  If
         the percentage so determined is 0.0001% or less, the fuel and line loss
         surcharge percentage shall be deemed to be zero.
________________________________________________________________________________
Issued by: P.G. Rosput, Senior Vice President
Issued on: JANUARY 10, 1994                          Effective: JANUARY 22, 1994
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. TM94-2-86-000, dated DECEMBER 30, 1993

 
Pacific Gas Transmission Company
FERC Gas Tariff                                      First Revised Sheet No. 142
First Revised Volume No. 1-A              Superseding
                                                          Original Sheet No. 142
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

38.  Reserved.



                                                                     (Continued)
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: SEPTEMBER 30, 1996                      Effective: SEPTEMBER 11, 1996
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RP94-149, 76-61,246, dated SEPTEMBER 11, 1996

 
Pacific Gas Transmission Company
FERC Gas Tariff                                      Third Revised Sheet No. 143
First Revised Volume No. 1-A              Superseding
                                                    Second Revised Sheet No. 143
________________________________________________________________________________

 
                  TRANSPORTATION GENERAL TERMS AND CONDITIONS
                                  (Continued)

39.  SALES OF EXCESS GAS

     PGT may from time to time purchase or sell gas on an interruptible basis at
     its Stanfield or Kingsgate receipt points as necessary to manage system
     pressure and maintain system integrity.  Prior to purchasing or selling gas
     pursuant to this section, PGT shall post notice of its intent to purchase
     or sell gas through its EBB.  Purchase or sale of gas shall be made on a
     nondiscriminatory basis.
________________________________________________________________________________
Issued by: R.T. Howard, Manager, Rates and Regulatory Affairs
Issued on: SEPTEMBER 30, 1996                      Effective: SEPTEMBER 11, 1996
Issued to comply with order of the Federal Energy Regulatory
Commission, Docket No. RP94-149, 76-61,246, dated SEPTEMBER 11, 1996

 
Graphic List to Exhibit 10.1 of the Form 10-K

The substantive information conveyed by the Capacity Release Timelines Standard
Release (Greater Than or Equal to One Day) graph (appearing in Paragraph 28) is
described in the body of the electronic document at Paragraph 28.2 and Paragraph
28.8 (b) as permitted by Item 304 of Regulation S-T.

The substantive information conveyed by the Capacity Release Timelines Rapid
Release (Equal to or Less Than One Month) graph (appearing in Paragraph 28) is
described in the body of the electronic document at Paragraph 28.2 and Paragraph
28.8 (a) as permitted by Item 304 of Regulation S-T.

The substantive information conveyed by the Capacity Release Timelines Pre-
Arranged Deal - A (Less Than or Equal to Thirty-One Days) graph (appearing in
Paragraph 28) is described in the body of the electronic document at Paragraph
28.2 and Paragraph 28.8 (c) as permitted by Item 204 of Regulation S-T.

The substantive information conveyed by the Capacity Release Timelines Pre-
Arranged Deal - B (Equal To or Greater Than Thirty-One Days At the Highest Value
Bid) graph (appearing at Paragraph 28) is described in the body of the
electronic document at Paragraph 28.2 and Paragraph 28.8 (d) as permitted by
Item 304 of Regulation S-T.

The substantive information conveyed by the Capacity Release Timelines Pre-
Arranged Deal - C (Greater Than or Equal to One Day) graph (appearing at
Paragraph 28) is described in the body of the electronic document at Paragraph
28.2 and Paragraph 28.8 (e) as permitted by Item 304 of Regulation S-T.