- ------------------------------------------------------------------------------- AIA DOCUMENT A131/CMC AND AGC DOCUMENT 566 STANDARD FORM OF AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER WHERE THE CONSTRUCTION MANAGER IS ALSO THE CONSTRUCTOR; AND WHERE THE BASIS OF PAYMENT IS THE COST OF THE WORK PLUS A FEE AND THERE IS NO GUARANTEE OF COST. 1994 EDITION THIS DOCUMENT HAS IMPORTANT LEGAL CONSEQUENCES; CONSULTATION WITH AN ATTORNEY IS ENCOURAGED WITH RESPECT TO ITS COMPLETION OR MODIFICATION THE 1987 EDITION OF AIA DOCUMENT A201, GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION, IS REFERRED TO HEREIN. THIS AGREEMENT REQUIRES MODIFICATION IF OTHER GENERAL CONDITIONS ARE UTILIZED. - ------------------------------------------------------------------------------- AGREEMENT made as of the 1st day of June in the year of 1996 (IN WORDS, INDICATE DAY, MONTH AND YEAR) BETWEEN the Owner: Lifecore Biomedical, Inc. (NAME AND ADDRESS) 3515 Lyman Blvd. Chaska, MN 55318-3051 and the Construction Manager: Marshall Contractors, Inc. (NAME AND ADDRESS) 2690 Perimeter Center East Atlanta, GA 30346 The Project is: (NAME, ADDRESS AND BRIEF DESCRIPTION) Phase 1-C: Phase 2-A: Phase 2-B: Phase 2-C: Lifecore headquarters in Chaska, MN The Architect is: Facility Planning & Resources (NAME AND ADDRESS) 2101 Greentree Road Pittsburgh, PA 15220 The Owner and Construction Manager agree as set forth below. - ------------------------------------------------------------------------------- THIS DOCUMENT IS MODIFIED FROM THE AIA DOCUMENT 131/CMC AND AGC DOCUMENT 566- 1991 EDITION -AIA @1991-AGC@1991 TABLE OF CONTENTS - ------------------------------------------------------------------------------- ARTICLE 1 GENERAL PROVISIONS 1.1 Relationship of Parties 1.2 General Conditions 1.3 Contract Sum, Contract Time and Changes in the Work ARTICLE 2 CONSTRUCTION MANAGER'S RESPONSIBILITIES 2.1 Preconstruction Phase 2.2 Control Estimate and Contract Time 2.3 Construction Phase 2.4 Professional Services 2.5 Unsafe Materials ARTICLE 3 OWNER'S RESPONSIBILITIES 3.1 Information and Services 3.2 Owner's Designated Representative 3.3 Architect 3.4 Legal Requirements ARTICLE 4 COMPENSATION AND PAYMENTS FOR PRECONSTRUCTION PHASE SERVICES 4.1 Compensation 4.2 Payments ARTICLE 5 COMPENSATION FOR CONSTRUCTION PHASE SERVICES 5.1 Compensation 5.2 Change in the Work ARTICLE 6 COST OF THE WORK FOR CONSTRUCTION PHASE 6.1 Costs To Be Reimbursed 6.2 Costs Not To Be Reimbursed 6.3 Discounts, Rebates and Refunds 6.4 Accounting Records ARTICLE 7 CONSTRUCTION PHASE PAYMENTS 7.1 Progress Payments 7.2 Final Payment ARTICLE 8 INSURANCE AND BONDS 8.1 Insurance Required of the Construction Manager 8.2 Insurance Required of the Owner 8.3 Performance Bond and Payment Bond ARTICLE 9 MISCELLANEOUS PROVISIONS 9.1 Dispute Resolution for the Preconstruction Phase 9.2 Dispute Resolution for the Construction Phase 9.3 Other Provisions ARTICLE 10 TERMINATION OR SUSPENSION 10.1 Termination Prior to the Owner's Approval of the Control Estimate 10.2 Termination Subsequent to the Owner's Approval of the Control Estimate 10.3 Notice of Termination 10.4 Suspension ARTICLE 11 OTHER CONDITIONS AND SERVICES 2 STANDARD FORM OF AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER WHERE THE CONSTRUCTION MANAGER IS ALSO THE CONSTRUCTOR ARTICLE 1 GENERAL PROVISIONS 1.1 RELATIONSHIP OF PARTIES The Construction Manager accepts the relationship of trust and confidence established with the Owner by this Agreement, and covenants with the Owner to furnish the Construction Manager's reasonable skill and judgment and to cooperate with the Architect in furthering the interests of the Owner. The Construction Manager shall furnish construction administration and management services and use the Construction Manager's best efforts to perform the Project in an expeditious and economical manner consistent with the interests of the Owner. The Owner shall endeavor to promote harmony and cooperation among the Owner, Architect, Construction Manager and other persons or entities employed by the Owner for the Project. 1.2 GENERAL CONDITIONS For the Construction Phase, the General Conditions of the Contract shall be the 1987 Edition of AIA Document A201, General Conditions of the Contract for Construction, as modified by the parties, which is incorporated herein by reference and attached hereto as Exhibit "A" and which shall apply except as specifically noted in this Agreement. For the Preconstruction Phase, including Preconstruction Phase activities which proceed concurrently with the Construction Phase, AIA Document A201 shall not apply except as specifically provided in this Agreement. If anything in AIA Document A201 is inconsistent with or is modified by this Agreement, this Agreement shall govern. Modifications of AIA Document A201 by this Agreement shall not apply to Subcontractors except as provided in Paragraph 2.5 of this Agreement. The term "Contractor" as used in AIA Document A201 shall mean the Construction Manager. 1.3 CONTRACT SUM, CONTRACT TIME AND CHANGES IN THE WORK The Contract Sum is the total Cost of the Work as described in Article 6, plus the Construction Manager's Fee as set forth in Article 5. The Contract Time is the duration from the date of commencement of the Construction Phase until the date of Substantial Completion. Changes in the Work shall be governed by Paragraph 5.2 of this Agreement and not by Article 7 of AIA Document A201. If, however, the Contract Time has been established in accordance with Clause 2.2.4.5 of this Agreement, adjustments to the Contract Time shall be made in accordance with Article 7 of AIA Document A201. ARTICLE 2 CONSTRUCTION MANAGER'S RESPONSIBILITIES The Construction Manager shall perform the services described in this Article. The services to be provided under Paragraphs 2.1 and 2.2 constitute the Preconstruction Phase services. The Construction Phase may commence before the Preconstruction Phase is completed, in which case both phases will proceed concurrently. 2.1 PRECONSTRUCTION PHASE 2.1.1 PRELIMINARY EVALUATION The Construction Manager shall provide a preliminary evaluation of the Owner's program, Project budget and schedule requirements, each in terms of the other. 2.1.2 CONSULTATION The Construction Manager with the Architect shall jointly schedule and attend regular meetings with the Owner and Architect. The Construction Manager shall consult with the Owner and Architect regarding site use and improvements, and the selection of materials, building systems and equipment. The Construction Manager shall provide recommendations on construction feasibility; actions designed to minimize adverse effects of labor or material shortages; time requirements for procurement, installation and construction completion; and factors related to construction cost including estimates of alternative designs or materials, preliminary budgets and possible economies. 2.1.3 PRELIMINARY PROJECT SCHEDULE When Project requirements described in Subparagraph 3.1.1 have been sufficiently identified, the Construction Manager shall prepare, and periodically update, a preliminary Project schedule for the Architect's review and the Owner's approval of the portion of the preliminary Project schedule relating to the performance of the Architect's services. The Construction Manager shall coordinate and integrate the preliminary Project schedule with the services and activities of the Owner, Architect and Construction Manager. As design proceeds, the preliminary Project schedule shall be updated to indicate proposed activity sequences and durations, milestone dates for receipt and approval of pertinent information, submittal of the Control Estimate, preparation and processing of shop drawings and samples, delivery of materials or equipment requiring long-lead time procurement, Owner's occupancy requirements showing portions of the Project having occupancy priority, and estimated date of Substantial Completion. If preliminary Project schedule updates indicate that previously approved schedules may not be met, the Construction Manager shall make appropriate recommendations to the Owner and Architect. 2.1.4 PHASED CONSTRUCTION The Construction Manager shall make recommendations to the Owner and Architect regarding the phased issuance of Drawings and Specifications to facilitate phased construction of the Work, if such phased construction is appropriate for the Project, taking into consideration such factors as economies, time of performance, availability of labor and materials, and provisions for temporary facilities. 2.1.5 PRELIMINARY COST ESTIMATES 2.1.5.1 When the Owner has sufficiently identified the Project requirements and the Architect has prepared other basic design criteria, the Construction manager shall prepare, for the review of the Architect and approval of the Owner, a preliminary cost estimate utilizing area, volume or similar conceptual estimating techniques. 3 2.1.5.2 When Schematic Design Documents have been prepared by the Architect and approved by the Owner, the Construction Manager shall prepare for the review of the Architect and approval of the Owner, a more detailed estimate with supporting data. During the preparation of the Design Development Documents, the Construction Manager shall update and refine this estimate at appropriate intervals agreed to by the Owner, Architect and Construction Manager. 2.1.5.3 When Design Development Documents have been prepared by the Architect and approved by the Owner, the Construction Manger shall prepare a detailed estimate with supporting data for review by the Architect and approval by the Owner. During the preparation of the Construction Documents, the Construction Manager shall update and refine this estimate at appropriate intervals agreed to by the Owner, Architect and Construction Manger. 2.1.5.4 If any estimate submitted to the Owner exceeds previously approved estimates or the Owner's budget, the Construction Manager shall make appropriate recommendations to the Owner and Architect. 2.1.6 SUBCONTRACTORS AND SUPPLIERS The Construction Manager shall seek to develop subcontractor interest in the Project and shall furnish to the Owner and Architect for their information a list of possible subcontractors, including suppliers who are to furnish materials or equipment fabricated to a special design, from whom proposals will be requested for each principal portion of the Work. The Architect will promptly reply in writing to the Construction Manager if the Architect or Owner know of any objection to such subcontractor or supplier. The receipt of such list shall not require the Owner or Architect to investigate the qualifications of proposed subcontractors or suppliers, nor shall it waive the right of the Owner or Architect later to object to or reject any proposed subcontractor or supplier. 2.1.7 LONG-LEAD TIME ITEMS The Construction Manager shall recommend to the Owner and Architect a schedule for procurement of long-lead time items which will constitute part of the Work as required to meet the Project schedule. Upon the Owner's approval of the Control Estimate, all contracts for such items shall be assigned by the Owner to the Construction Manager, who shall accept responsibility for such items as if procured by the Construction Manager. The Construction Manager shall expedite the delivery of long-lead time items. 2.1.8 EXTENT OF RESPONSIBILITY The Construction Manager agrees to exercise reasonable skill and judgment in the preparation of schedules and estimates, but does not warrant or guarantee any schedules or estimates or line items within such estimates, even though approved by the Owner, including the Control Estimate and the estimated date of Substantial Completion, except as otherwise provided under Clause 2.2.4.5. The recommendations and advice of the Construction Manager concerning design alternatives shall be subject to the review and approval of the Owner and the Owner's professional consultants. It is not the Construction Manager's responsibility to ascertain that the Drawings and Specifications are in accordance with applicable laws, statutes, ordinances, building codes, rules and regulations. However, if the Construction Manager recognizes that portions of the Drawings and Specifications are at variance, the Construction Manager shall promptly notify the Architect and Owner in writing. 2.1.9 EQUAL EMPLOYMENT OPPORTUNITY AND AFFIRMATIVE ACTION The Construction Manager shall comply with applicable laws, regulations and special requirements of the Contract Documents regarding equal employment opportunity and affirmative action programs. 2.2 CONTROL ESTIMATE AND CONTRACT TIME 2.2.1 In accordance with the preliminary Project schedule established in Subparagraph 2.1.3, the Construction Manager shall prepare and submit to the Owner in writing a Control Estimate using current information to update the most recently prepared Preliminary Estimate. The Control Estimate shall be the sum of the then-estimated Cost of the Work and the Construction Manager's Fee, and is the estimate against which actual costs will be measured. 2.2.2 The Construction Manager shall develop and implement a detailed system of cost control that will provide the Owner with timely information as to the anticipated total Cost of the Work. The cost control system shall compare the Control Estimate with the actual cost for activities in progress and estimates for uncompleted tasks and proposed changes. This information shall be reported to the Owner in writing at mutually agreeable intervals. 2.2.3 As the Drawings and Specifications may not be finished at the time the Control Estimate is prepared, the Construction Manager shall provide in the Control Estimate for further development of the Drawings and Specifications of the Architect that is consistent with the Contract Documents and reasonably inferable therefrom. Such further development does not include such things as changes in scope, systems, kinds and quality of materials, finishes or equipment. 2.2.4 The Control Estimate shall include: .1 A list of the Drawing and Specifications, including all addenda thereto and the Conditions of the Contract. .2 A list of the clarifications and assumptions made by the Construction Manager in the preparation of the Control Estimate to supplement the information contained in the Drawings and Specifications. .3 A statement of the estimated Cost of the work organized by trade categories or systems, and the Construction Manager's fee. .4 A statement of the actual or estimated date of commencement of the Construction Phase and the estimated date of Substantial Completion, with a schedule of the construction documents issuance dates upon which the estimated date of Substantial Completion is based. .5 A statement as to whether or not the duration from the stated date of commencement of the Construction Phase to the estimated date of Substantial Completion shall become the Contract Time and be subject to the provisions of Article 8 of AIA Document A201. 2.2.5 The Construction Manager shall meet with the Owner and Architect to review the Control Estimate. In the event that the Owner or Architect discover any inconsistencies or inaccuracies in the information presented, they shall promptly notify the Construction Manager, who shall make appropriate adjustments to the Control Estimate. When the Control Estimate is acceptable to the Owner, the Owner shall approve it in writing. 4 2.2.6 Upon the Owner's approval of the Control Estimate, the Contract Documents shall consist of (1) this Agreement, (2) AIA Document A201 and other documents referred to in this Agreement, (3) the documents enumerated in Clause 2.2.4 with the adjustments described in Clause 2.2.5, and (4) Modifications issued subsequent to the Owner's approval of the Control Estimate. If anything in the other Contract Documents is inconsistent with this Agreement, this Agreement shall govern. 2.2.7 The Owner shall authorize and cause the Architect to revise the Drawings and Specifications to the extent necessary to reflect the agreed upon assumptions and clarifications on which the Control Estimate is based. Such revised Drawings and Specifications shall be furnished to the Construction Manager in accordance with schedules agreed to by the Owner, Architect, and Construction Manager. The Construction Manager shall promptly notify the Architect and Owner if such revised Drawings and Specifications are inconsistent with the agreed upon assumptions and clarifications. 2.3 CONSTRUCTION PHASE 2.3.1 GENERAL 2.3.1.1 The Construction Phase shall commence on the earlier of: .1 the Owner's approval of the Control Estimate and issuance of a Notice to Proceed; or .2 the Owner's first authorization to the Construction Manager to award a subcontract, or to undertake a portion of the Work with the Construction Manager's own forces, or to issue a purchase order for materials or equipment required for the Work. 2.3.1.2 For purposes of Subparagraph 8.1.2 of AIA Document A201, the date of commencement of the Work shall mean the date of commencement of the Construction Phase. 2.3.1.3 Prior to the Owner's approval of the Construction Manager's Control Estimate and issuance of a Notice to Proceed, the Construction Manager shall not incur any cost to be reimbursed as part of the Cost of the Work, except as the Owner may specifically authorize in writing. 2.3.2 ADMINISTRATION 2.3.2.1 Those portions of the Work that the Construction Manager does not customarily perform with the Construction Manager's own personnel shall be performed under subcontracts or by other appropriate agreements with the Construction Manager. The Construction Manager shall obtain bids from Subcontractors and from suppliers of materials or equipment fabricated to a special design for the Work from the list previously reviewed and, after analyzing such bids, shall deliver such bids to the Owner and Architect. The Owner will then determine, with the advice of the Construction Manager and subject to the reasonable objection of the Architect, which bids will be accepted. The Owner may designate specific persons or entities from whom the Construction Manager shall obtain bids. The Construction Manager shall not be required to contract with anyone to whom the Construction Manager has reasonable objection. 2.3.2.2 Subcontracts and agreements with suppliers furnishing materials or equipment fabricated to a special design shall conform to the payment provisions of Subparagraphs 7.1.8 and 7.1.9 and shall not be awarded on the basis of cost plus a fee without the prior consent of the Owner. 2.3.2.3 The Construction Manager shall schedule and conduct meetings at which the Owner, Architect, Construction Manager and appropriate Subcontractors can discuss the status of the Work. The Construction Manager shall prepare and promptly distribute meeting minutes. 2.3.2.4 Promptly after the Owner's approval of the Control Estimate, the Construction Manager shall prepare a schedule in accordance with Paragraph 3.10 of AIA Document A201, and the following requirements: The construction schedule shall be in a detailed precedence-style critical path method (CPM) or primavera type format satisfactory to the Owner and the Architect which shall also: (1) provide a graphic representation of all activities and events that will occur during performance of the Work; (2) identify each phase of construction and occupancy; and (3) set forth dates that are critical in ensuring the timely and orderly completion of the Work in accordance with the requirements of the Contract Documents and Exhibit "B". Upon review and acceptance by the Owner and the Architect, the construction schedule shall be deemed part of the Contract Documents and attached to the Agreement as Exhibit B. If not accepted, the construction schedule shall be promptly revised by the Contractor in accordance with the recommendations of the Owner and the Architect and re-submitted for acceptance. The Contractor shall monitor the progress of the Work for conformance with the requirements of the construction schedule and shall promptly advise the Owner of any delays or potential delays. The accepted construction schedule shall be updated to reflect actual conditions as set forth in General Conditions, Paragraph 3.10.1 or, if requested by Owner. In the event any progress report indicates any delays, the Contractor shall propose an affirmative plan to correct the delay, including overtime and/or additional labor, if necessary. In no event shall any progress report constitute an adjustment in the Contract Time, any Milestone Date or the Contract Sum unless any such adjustment is agreed to by the Owner and authorized pursuant to Change Order. 2.3.2.5 The Construction Manager shall provide monthly written reports to the Owner and Architect on the progress of the entire Work. The Construction Manager shall maintain a daily log containing a record of weather, Subcontractors working on the site, number of workers, Work accomplished, problems encountered and other similar relevant data as the Owner may reasonably require. The log shall be available to the Owner and Architect. 2.4 PROFESSIONAL SERVICES The Construction Manager shall not be required to provide professional services which constitute the practice of architecture or engineering, unless such services are specifically required by the Contract Documents for a portion of the Work or unless the Construction Manager has specifically agreed in writing to provide such services. In such event, the Construction Manager shall cause such services to be performed by appropriately licensed professionals. 2.5 UNSAFE MATERIALS In addition to the provisions of Paragraph 10.1 in AIA Document A201, if reasonable precautions will be inadequate to prevent foreseeable bodily injury or death to persons resulting from a material or substance encountered but not created on the site by the Construction Manager, the Construction Manager shall, upon recognizing the condition, immediately stop work in the affected area and report the condition to the Owner and Architect in writing. The Owner, Construction Manager and Architect shall then proceed in the same manner described in Subparagraph 10.1.2 of AIA Document A201. The Owner shall be responsible for obtaining the 5 services of a licensed laboratory to verify the presence or absence of the material of substance reported by the Construction Manager and, in the event such material or substance is found to be present, to verify that it has been rendered harmless. ARTICLE 3 --------- OWNER'S RESPONSIBILITIES 3.1 INFORMATION AND SERVICES 3.1.1 The Owner shall provide full information in a timely manner regarding the requirements of the Project, including a program which sets forth the Owner's objectives, constraints and criteria, including space requirements and relationships, flexibility and expandability requirements, special equipment and systems, and site requirements. 3.1.2 The Owner, upon written request from the Construction Manager, shall furnish evidence of Project financing prior to the start of the Construction Phase. Furnishing of such evidence shall be a condition precedent to commencement of the Work. 3.1.3 The Owner shall establish and update an overall budget for the Project, based on consultation with the Construction Manager and Architect, which shall include contingencies for changes in the Work and other costs which are the responsibility of the Owner. 3.1.4 STRUCTURAL AND ENVIRONMENTAL TESTS, SURVEYS AND REPORTS In the Preconstruction Phase, the Owner shall furnish the following with reasonable promptness and at the Owner's expense: 3.1.4.1 Reports, surveys, drawings and tests concerning the conditions of the site which are required by law. 3.1.4.2 Surveys describing physical characteristics, legal limitations and utility locations for the site of the Project, and a written legal description of the site. The surveys and legal information shall include, as applicable, grades and lines of streets, alleys, pavements and adjoining property and structures; adjacent drainage; rights-of-way, restrictions, easements, encroachments, zoning, deed restrictions, boundaries and contours of the site; locations, dimensions and necessary data pertaining to existing buildings, other improvements and trees; and information concerning available utility services and lines, both public and private, above and below grade, including inverts and depths. All information on the survey shall be referenced to a project benchmark. 3.1.4.3 The services of a geotechnical engineer when such services are requested by the Construction Manager. Such services may include but are not limited to test borings, test pits, determinations of soil bearing values, percolation tests, evaluations of hazardous materials, ground corrosion and resistivity tests, including necessary operations for anticipating subsoil conditions, with reports and appropriate professional recommendations. 3.1.4.4 Structural, mechanical, chemical, air and water pollution tests, tests for hazardous materials, and other laboratory and environmental tests, inspections and reports which are required by law. 3.1.4.5 The services of other consultants when such services are reasonably required by the scope of the Project and are requested by the Construction Manager. The Construction Manager shall be entitled to rely upon the accuracy of such information, reports, surveys, drawings and tests described in Clauses 3.1.4.1 through 3.1.4.5, except to the extent that the Construction Manager knows of any inaccuracy. 3.2 OWNER'S DESIGNATED REPRESENTATIVE The Owner's representative is Robert McCollough, who shall have express authority to bind the Owner with respect to all matters requiring the Owner's approval or authorization. This representative shall have the authority to make decisions on behalf of the Owner concerning estimates and schedules, construction budgets, and changes in the Work, and shall render such decisions promptly and furnish information expeditiously, so as to avoid the unreasonable delay in the services or Work of the Construction Manager. The Owner may designate another or additional representatives upon written notice to Construction Manager. 3.3 ARCHITECT The Owner shall retain an Architect to provide Basic Services, including normal structural, mechanical, electrical engineering services, other than cost estimating services, described in the edition of AIA Document B141 current as of the date of this Agreement. The Owner shall authorize and cause the Architect to provide those Additional Services described in AIA Document B141 requested by the Construction Manager which must necessarily be provided by the Architect for the Preconstruction and Construction Phases of the Work. Such services shall be provided in accordance with timely schedules agreed to by the Owner, Architect and Construction Manager. Upon request of the Construction Manager, the Owner shall furnish to the Construction Manager a copy of the Owner's Agreement with the Architect, from which compensation provisions may be deleted. ARTICLE 4 COMPENSATION AND PAYMENTS FOR PRECONSTRUCTION PHASE SERVICES The Owner shall compensate and make payments to the Construction Manager for Preconstruction Phase services as follows: 4.1 COMPENSATION 4.1.1 For the services described in Paragraphs 2.1 and 2.2, the Construction Manager's compensation shall be calculated as follows: At actual cost for personnel included in the Cost of the Work as defined herein, plus reimbursable costs as set forth in Article 6, plus a fee equal to % of the sum of such costs. 4.1.2 Compensation for Preconstruction Phase Services shall be equitably adjusted if such services extend beyond two years from the date of this Agreement or if the originally contemplated scope of services is significantly modified. 4.2 PAYMENTS 4.2.1 Payments shall be made monthly following presentation of the Construction Manager's invoice and, where applicable, shall be in proportion to services performed. 4.2.2 Payments are due and payable thirty (30) days from the date the Construction Manager's invoice is received by the Owner. Amounts unpaid after the date on which payment is due will bear interest of eight percent (8%) per annum. ARTICLE 5 --------- COMPENSATION FOR CONSTRUCTION PHASE SERVICES The Owner shall compensate the Construction Manager for Construction Phase services as follows: 5.1 COMPENSATION 5.1.1 For the Construction Manager's performance of the Work as described in Paragraph 2.3, the Owner shall pay the Construction Manager in current funds the Contract Sum consisting of the Cost of the Work as defined in Article 6 and the Construction Manager's Fee determined as follows: A Fee equal to % of the Cost of the Work. 5.2 CHANGES IN THE WORK 5.2.1 The Owner may, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions or other revisions. The Architect may make minor changes in the Work as provided in Paragraph 7.4 of AIA Document A201. 5.2.2 Increased costs for the items set forth in Article 6 which result from changes in the Work shall become part of the Cost of the Work, and the Construction Manager's Fee shall be adjusted if provided in Paragraph 5.1. 5.2.3 If the Construction Manager receives any drawings, specifications, interpretations or instructions from the Owner or Architect which are inconsistent with the Contract Documents, or encounters unanticipated conditions, any of which will result in a significant change in the cost, scope or estimated date of Substantial Completion in comparison with the Control Estimate, the Construction Manager shall promptly notify the Owner and Architect in writing and shall not proceed with the affected work until further written instructions are received from the Owner and Architect. ARTICLE 6 --------- COST OF THE WORK FOR CONSTRUCTION PHASE 6.1 COSTS TO BE REIMBURSED 6.1.1 The term "Cost of the Work" shall mean costs necessarily incurred by the Construction Manager in the proper performance of the Work. Such costs shall be at rates not higher than those customarily paid at the place of the Project except with prior consent to the Owner. The Cost of the Work shall include only the items set forth in this Article 6. 6.1.2 LABOR COSTS .1 Wages of construction workers directly employed by the Construction Manager to perform the construction of the Work at the site or, with the Owner's agreement, at off-site workshops. .2 Wages or salaries of the Construction Manager's supervisory and administrative personnel when stationed at the site with the Owner's agreement at actual cost. .3 Wages and salaries of the Construction Manager's supervisory or administrative personnel engaged, at factories, workshops or on the road, in expediting the production or transportation of materials or equipment required for the Work, and estimating, safety supervision, purchasing, scheduling and cost engineering staff located in Construction Manager's home office, but only for that portion of their time required for the Work, at actual cost. .4 Costs paid or incurred by the Construction Manager for taxes, insurance, contributions, assessments and benefits required by law or collective bargaining agreements, and, for personnel not covered by such agreements, customary benefits such as sick leave, 7 medical and health benefits, holidays, vacations and pensions, provided that such costs are based on wages and salaries included in the Cost of the Work under Clause 6.1.2.1. 6.1.3 SUBCONTRACT COSTS Payments made by the Construction Manager to Subcontractors in accordance with the requirements of the subcontracts. 6.1.4 COSTS OF MATERIALS AND EQUIPMENT INCORPORATED IN THE COMPLETED CONSTRUCTION .1 Costs, including transportation, of materials and equipment incorporated or to be incorporated in the completed construction. .2 Costs of materials described in the preceding Clause 6.1.4.1 in excess of those actually installed but required to provide reasonable allowance for waste and for spoilage. Unused excess materials, if any, shall be handed over to the Owner at the completion of the Work or, at the Owner's option, shall be sold by the Construction Manager; amounts realized, if any, from such sales shall be credited to the Owner as a deduction from the Cost of the Work. 6.1.5 COSTS OF OTHER MATERIALS AND EQUIPMENT, TEMPORARY FACILITIES AND RELATED ITEMS .1 Costs, including transportation, installation, maintenance, dismantling and removal of materials, supplies, temporary facilities, machinery, equipment, and hand tools not customarily owned by the construction workers, which are provided by the Construction Manager at the site and fully consumed in the performance of the Work; and cost less salvage value on such items if not fully consumed, whether sold to others or retained by the Construction Manager. Cost for items previously used by the Construction Manager shall mean fair market value. .2 Rental charges for temporary facilities, machinery, equipment, and hand tools not customarily owned by the construction workers, which are provided by the Construction Manager at the site, whether rented from the Construction Manager or others, and costs of transportation, installation, minor repairs and replacements, dismantling and removal thereof. Rates and quantities of equipment rented shall be subject to the Owner's prior approval. Rental charges for Contractor-owned equipment shall not exceed 75% of the then current monthly rate set forth in the Rental Blue Book for Construction Equipment published by the Equipment Guide Book Company. .3 Costs of removal of debris from the site. .4 Reproduction costs, costs of telegrams, facsimile transmissions and long-distance telephone calls, postage and express delivery charges, telephone at the site and reasonable petty cash expenses of the site office. .5 That portion of the reasonable travel and subsistence expenses of the Construction Manager's personnel incurred while traveling in discharge of duties connected with the Work. 6.1.6 MISCELLANEOUS COSTS .1 That portion directly attributable to this Contract of premiums for insurance required of Construction Manager pursuant to the Contract Documents and the deductible portion of any losses under the Builder's Risk Insurance (not to exceed $5,000 per loss). .2 Sales, use or similar taxes imposed by a governmental authority which are related to the Work and for which the Construction Manager is liable. .3 Fees and assessments for the building permit and for other permits, licenses and inspections for which the Construction Manager is required by the Contract Documents to pay. .4 Fees of testing laboratories for tests required by the Contract Documents, except those related to nonconforming Work other than that for which payment is permitted by Clause 6.1.8.2. .5 Royalties and license fees paid for the use of a particular design, process or product required by the Contract Documents; the cost of defending suits or claims for infringement of patent or other intellectual property rights arising from such requirement by the Contract Documents; payments made in accordance with legal judgments against the Construction Manager resulting from such suits or claims and payments of settlements made with the Owner's consent; provided, however, that such costs of legal defenses, judgment and settlements shall not be included in the calculation of the Construction Manager's Fee and provided that such royalties, fees and costs are not excluded by the last sentence of Subparagraph 3.17.1 of AIA Document A201 or other provisions of the Contract Documents. .6 Data processing costs related to the Work. .7 Deposits lost for causes other than the Construction Manager's negligence or failure to fulfill a specific responsibility to the Owner set forth in this Agreement. .8 With the Owner's prior written permission, legal, mediation and arbitration costs, other than those arising from disputes between the Owner and Construction Manager, reasonably incurred by the Construction Manager in the performance of the Work. .9 Expenses incurred in accordance with the Construction Manager's standard personnel policy for relocation and temporary living allowances of personnel required for the Work, in case it is necessary to relocate such personnel from distant locations. 6.1.7 OTHER COSTS .1 Other costs incurred in the performance of the Work if and to the extent approved in advance in writing by the Owner. 8 6.1.8 EMERGENCIES AND REPAIRS TO DAMAGED OR NONCONFORMING WORK The Cost of the Work shall also include costs described in Subparagraph 6.1.1 which are incurred by the Construction Manager: .1 In taking action to prevent threatened damage, injury or loss in case of an emergency affecting the safety of persons and property, as provided in Paragraph 10.3 of AIA Document A201. .2 In repairing or correcting damaged or nonconforming Work executed by the Construction Manager or the Construction Manager's Subcontractors or suppliers, provided that such damaged or nonconforming Work was not caused by the negligence or failure to comply with the requirements of the Contract Documents of the Construction Manager or the Construction Manager's foremen, engineers or superintendents, or other supervisory, administrative or managerial personnel of the Construction Manager, or the failure of the Construction Manager's personnel to supervise adequately the Work of the Subcontractors or suppliers, and only to the extent that the cost of repair or correction is not recoverable by the Construction Manager from insurance, Subcontractors or suppliers. 6.1.9 The costs described in Subparagraphs 6.1.1 through 6.1.8 shall be included in the Cost of the Work, notwithstanding any provision of AIA Document A201 or other Conditions of the Contract which may require the Construction Manager to pay such costs, unless such costs are excluded by the provisions of Paragraph 6.2. 6.2 COSTS NOT TO BE REIMBURSED 6.2.1 The Cost of the Work shall not include: .1 Salaries and other compensation of the Construction Manager's personnel stationed at the Construction Manager's principal office or offices other than the site office, except as specifically provided in Clauses 6.1.2.1 through 6.1.2.3. .2 Expenses of the Construction Manager's principal office and offices other than the site office except as specifically provided in Paragraph 6.1. .3 Overhead and general expenses, except as may be expressly included in Paragraph 6.1. .4 The Construction Manager's capital expenses, including interest on the Construction Manager's capital employed for the Work. .5 Rental costs of machinery and equipment, except as specifically provided in Subparagraph 6.1.5.2. .6 Except as provided in Clause 6.1.8.2, costs due to the negligence of the Construction Manager or to the failure of the Construction Manager to comply with the Contract Documents. .7 Costs incurred in the performance of Preconstruction Phase Services. .8 Except as provided in Clause 6.1.7.1, any cost not specifically and expressly described in Paragraph 6.1. 6.3 DISCOUNTS, REBATES AND REFUNDS 6.3.1 Cash discounts obtained on payments made by the Construction Manager shall accrue to the Owner if (1) before making the payment, the Construction Manager included them in an Application for Payment and received payment therefor from the Owner, or (2) the Owner has deposited funds with the Construction Manager with which to make payments; otherwise, cash discounts shall accrue to the Construction Manager. Trade discounts, rebates, refunds and amounts received from sales of surplus materials and equipment shall accrue to the Owner, and the Construction Manager shall make provisions so that they can be secured. 6.3.2 Amounts which accrue to the Owner in accordance with the provisions of Subparagraph 6.3.1 shall be credited to the Owner as a deduction from the Cost of the Work. 6.4 ACCOUNTING RECORDS 6.4.1 The Construction Manager shall keep full and detailed accounts and exercise such controls as may be necessary for proper financial management under this Contract; the accounting and control systems shall be satisfactory to the Owner. At any time, upon reasonable notice, the Owner and the Owner's accountants shall be afforded access to the Construction Manager's records, books, correspondence, instructions, drawings, receipts, subcontracts, purchase orders, vouchers, memoranda and other data relating to this Project, and the Construction Manager shall preserve these for a period of three years after final payment, or for such longer period as may be required by law. ARTICLE 7 --------- CONSTRUCTION PHASE PAYMENTS 7.1 PROGRESS PAYMENTS 7.1.1 Based upon Applications for Payment submitted to the Architect by the Construction Manager and Certificates for Payment issued by the Architect, the Owner shall make progress payments on account of the Contract Sum to the Construction Manager as provided below and elsewhere in the Contract Documents. 7.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the month. 7.1.3 Provided an Application for Payment is received by the Architect not later than the 15th day of a month, the Owner shall make payment to the Construction Manager not later than the 15th day of the following month. If an Application for Payment is received by the 9 Architect after the application date fixed above, payment shall be made by the Owner not later than forty-five days after the Architect receives the Application for Payment. 7.1.4 With each Application for Payment, the Construction Manager shall submit payrolls, petty cash accounts, receipted invoices or invoices with check vouchers attached, and any other evidence required by the Owner to demonstrate that cash disbursements already made by the Construction Manager on account of the Cost of the Work equal or exceed (1) progress payments already received by the Construction Manager; less (2) that portion of those payments attributable to the Construction Manager's Fee; plus (3) payrolls for the period covered by the present Application for Payment. 7.1.5 Applications for Payment shall show the Cost of the Work actually incurred by the Construction Manager through the end of the period covered by the Application for Payment and for which the Construction Manager has made or intends to make actual payment prior to the next Application for Payment. 7.1.6 Subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows: .1 Take the Cost of the Work as described in Subparagraph 7.1.5. .2 Add the Construction Manager's Fee, less retainage of ten percent (10%). The Construction Manager's Fee shall be computed upon the Cost of the Work described in the preceding Clause 7.1.6.1 at the rate stated in Paragraph 5.1 or, if the Construction Manager's Fee is stated as a fixed sum in that Paragraph, an amount which bears the same ratio to that fixed-sum Fee as the Cost of the Work in the preceding Clause bears to a reasonable estimate of the probable Cost of the Work upon its completion. .3 Subtract the aggregate of previous payments made by the Owner. .4 Subtract the shortfall, if any, indicated by the Construction Manager in the documentation required by Subparagraph 7.1.4 or to substantiate prior Applications for Payment or resulting from errors subsequently discovered by the Owner's accountants in such documentation. .5 Subtract amounts, if any, for which the Architect has withheld or withdrawn a Certificate for Payment as provided in the Contract Documents. 7.1.7 Additional retainage, if any, shall be as follows: Ten percent to Substantial Completion, except as otherwise agreed to by Owner. Five percent to Final Completion. 7.1.8 Except with the Owner's prior approval, payments to Subcontractors included in the Construction Manager's Applications for Payment shall not exceed an amount for each Subcontractor calculated as follows: .1 Take that portion of the Subcontract Sum properly allocable to completed Work as determined by multiplying the percentage completion of each portion of the Subcontractor's Work by the share of the total Subcontract Sum allocated to that portion in the Subcontractor's schedule of values, less retainage of ten percent (10%). Pending final determination of amounts to be paid to the Subcontractor for changes in the Work, amounts not in dispute may be included as provided in Subparagraph 7.3.7 of AIA Document A201 even thought the Subcontract Sum has not yet been adjusted by Change Order. .2 Add that portion of the Subcontract Sum properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the Work or, if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing, less retainage of ten percent (10%). .3 Subtract the aggregate of previous payments made by the Construction Manager to the Subcontractor. .4 Subtract amounts, if any, for which the Architect has withheld or nullified a Certificate for Payment by the Owner to the Construction Manager for reasons which are the fault of the Subcontractor. .5 Add, upon Substantial Completion of the entire Work of the Construction Manager, a sum sufficient to increase the total payments to the Subcontractor to ninety-five percent (95%) of the Subcontract Sum, less amounts, if any, for incomplete Work and unsettled claims; and, if final completion of the entire Work is thereafter materially delayed through no fault of the Subcontractor, add any additional amounts payable on account of Work of the Subcontractor in accordance with Subparagraph 9.10.3 of AIA Document A201. The Subcontract Sum is the total amount stipulated in the subcontract to be paid by the Construction Manager to the Subcontractor for the Subcontractor's performance of the subcontract. 7.1.9 Except with the Owner's prior written approval, the Construction Manager shall not make advance payments to suppliers for materials or equipment which have not been delivered and stored at the site. 7.1.10 In taking action on the Construction Manager's Applications for Payment, the Architect shall be entitled to rely on the accuracy and completeness of the information furnished by the Construction Manager and shall not be deemed to represent that the Architect has made a detailed examination, audit or arithmetic verification of the documentation submitted in accordance with Subparagraph 7.1.4 or other supporting data; that the Architect has made exhaustive or continuous on-site inspections, or that the Architect has made examinations to ascertain how or for what purposes the Construction Manager has used amounts previously paid on account of the Contract. Such examinations, audits and verifications, if required by the Owner, will be performed by the Owner's accountants acting in the sole interest of the Owner. 10 7.2 FINAL PAYMENT 7.2.1 Final payment shall be made by the Owner to the Construction Manager when (1) the Contract has been fully performed by the Construction Manager, except for the Construction Manager's responsibility to correct nonconforming Work, as provided in Subparagraph 12.2.2 of AIA Document A201, and to satisfy other requirements, if any, which necessarily survive final payment; (2) a final Application for Payment and a final accounting for the Cost of the Work have been submitted by the Construction Manager and reviewed by the Owner's accountants; (3) the Construction Manager shall have complied with all of the requirements of Paragraph 9.10 of the General Conditions; and (4) a final Certificate for Payment has then been issued by the Architect; such final payment shall be made by the Owner not more than 30 days after the issuance of the Architect's final Certificate for Payment, or as follows: 7.2.2 The amount of the final payment shall be calculated as follows: .1 Take the sum of the Cost of the Work substantiated by the Construction Manager's final accounting and the Construction Manager's Fee. .2 Subtract amounts, if any, for which the Architect withholds, in whole or in part, a final Certificate for Payment as provided in Subparagraph 9.5.1 of AIA Document A201 or other provisions of the Contract Documents. .3 Subtract the aggregate of previous payments made by the Owner. If the aggregate of previous payment made by the Owner exceeds the amount due the Construction Manager, the Construction Manager shall reimburse the difference to the Owner. 7.2.3 The Owner's accountants will review and report in writing on the Construction Manager's final accounting within 60 days after delivery of the final accounting to the Architect by the Construction Manager. Based upon such Cost of the Work as the Owner's accountants report to be substantiated by the Construction Manager's final accounting, and provided the other conditions of Subparagraph 7.2.1 have been met, the Architect will, within seven days after receipt of the written report of the Owner's accountants, either issue to the Owner a final Certificate for Payment with a copy to the Construction Manager, or notify the Construction Manager and Owner in writing of the Architect's reasons for withholding a certificate as provided in Subparagraph 9.5.1 of AIA Document A201. The time periods stated in this Paragraph 7.2 supersede those stated in Subparagraph 9.4.1 of AIA Document A201. 7.2.4 If the Owner's accountants report the Cost of the Work as substantiated by the Construction Manager's final accounting to be less than claimed by the Construction Manager, the Construction Manager shall be entitled to proceed in accordance with Article 9 without a further decision of the Architect. Unless agreed to otherwise, a demand for mediation or arbitration of the disputed amount shall be made by the Construction Manager within 60 days after the Construction Manager's receipt of a copy of the Architect's final Certificate for Payment. Failure to make such demand within this 60-day period shall result in the substantiated amount reported by the Owner's accountants becoming binding on the Construction Manager. Pending a final resolution of the disputed amount, the Owner shall pay the Construction Manager the amount certified in the Architect's final Certificate for Payment. 7.2.5 If, subsequent to final payment and at the Owner's request, the Construction Manager incurs costs described in Paragraph 6.1 and not excluded by Paragraph 6.2 (1) to correct nonconforming Work, or (2) arising from the resolution of disputes, the Owner shall reimburse the Construction Manager such costs and the Construction Manager's Fee, if any, related thereto on the same basis as if such costs had been incurred prior to final payment. ARTICLE 8 --------- INSURANCE AND BONDS 8.1 INSURANCE REQUIRED OF THE CONSTRUCTION MANAGER During both the Preconstruction and Construction phases of the Project and prior to commencing any Work or services hereunder, the Construction Manager shall purchase, maintain and pay for insurance as set forth in Paragraph 11.1 of AIA Document A201. Such insurance shall be written for not less than the following limits, or greater if required by law: 8.1.1 Workers' Compensation: Statutory Limits Employer's Liability $1,000,000 Bodily Injury by Accident $1,000,000 Bodily Injury by Disease $1,000,000 Each Employee 8.1.2 Commercial General Liability, including coverage for Premises-Operations, Independent Contractors' Protective, Products-Completed Operations, Contractual Liability, Personal Injury, and Broad Form Property Damage (including coverage for Explosion, Collapse and Underground hazards): 11 $15,000,000 Each Occurrence $15,000,000 General Aggregate $15,000,000 Personal and Advertising Injury $15,000,000 Products-Completed Operations Aggregate .1 The policy shall be endorsed to have the General Aggregate apply to this Project only. .2 Products and Completed Operations insurance shall be maintained for a minimum period of at least (Two) years after either 90 days following Substantial Completion or final payment, whichever is earlier. .3 The Contractual Liability insurance shall include coverage sufficient to meet the obligations in AIA Document A201 under Paragraph 3.18. 8.1.3 Comprehensive Automobile Liability (owned, non-owned and hired vehicles) for bodily injury and property damage: $15,000,000 Each Accident 8.1.4 Employer's Liability, Commercial General Liability and Comprehensive Automobile Liability insurance may be arranged under single policies for full minimum limits requires, or by a combination of underlying policies with the balance provided by an Excess or Umbrella Liability policy. 8.1.5 All such coverages required above shall be maintained by responsible insurance carriers authorized and licensed to do business in the State of Minnesota with an A.M. Best Rating of A or better, and acceptable to Owner. Construction Manager shall endorse its Commercial General Liability, Comprehensive Automobile Liability and Umbrella/Excess Liability policies (required by this Article) to add as additional insureds the Owner, Architect, Clark, Richardson & Biskup and their agents, employees, consultants and subcontractors or, at its option, shall provide a separate Owners' and Contractor's Protective policy, in a form satisfactory to Owner, which affords the equivalent coverages and limits to the aforesaid as insureds. Such insurance afforded shall be primary insurance and not excess over or contributing with any insurance purchased or maintained by the Owner or other additional insureds, or insureds. 8.2 PERFORMANCE BOND AND PAYMENT BOND 8.2.1 The Construction Manager shall not furnish bonds covering faithful performance of the Contract and payment of obligations arising thereunder. 12 ARTICLE 9 --------- MISCELLANEOUS PROVISIONS 9.1 DISPUTE RESOLUTIONS FOR THE PRECONSTRUCTION PHASE 9.1.1 Claims, disputes or other matters in question between the parties to this Agreement which arise prior to the commencement of the Construction Phase or which relate solely to the Preconstruction Phase services of the Construction Manager or to the Owner's obligations to the Construction Manager during the Preconstruction Phase, shall be resolved by mediation or by arbitration. Prior to arbitration, the parties shall endeavor to reach settlement by mediation. 9.1.2 Any mediation conducted pursuant to this Paragraph 9.1 shall be held in accordance with the Construction Industry Mediation Rules of the American Arbitration Association currently in effect, unless the parties mutually agree otherwise. Demand for mediation shall be filed in writing with the other party to this Agreement and with the American Arbitration Association. Any demand for mediation shall be made within a reasonable time after the claim, dispute or other matter in question has arisen. In no event shall the demand for mediation be made after the date when institution of legal or equitable proceedings based upon such claim, dispute or other matter in question would be barred by the applicable statute of limitations. 9.1.3 Any claim, dispute or other matter in question not resolved by mediation shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association currently in effect, unless the parties mutually agree otherwise. Arbitration proceedings shall be held in Minneapolis, Minnesota. 9.1.4 Demand for arbitration shall be filed in writing with the other party to this Agreement and with the American Arbitration Association. A demand for arbitration may be made concurrent with a demand for mediation and shall be made within a reasonable time after the claim, dispute or other matter in question has arisen. In no event shall the demand for arbitration be made after the date when institution of legal or equitable proceedings based upon such claim, dispute or other matter in question would be barred by the applicable statute of limitations. 9.1.5 In the event of an arbitration between the Owner and any third party, that involves an issue that is or could be the subject of a dispute between the Owner and the Construction Manager under this Agreement, the Owner, at its option, may join the Construction Manager as a party to such arbitration. The foregoing agreement to arbitrate shall be specifically enforceable under applicable law in any court having jurisdiction thereof. 9.1.6 The award rendered by the arbitrator or arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof. 9.2 DISPUTE RESOLUTION FOR THE CONSTRUCTION PHASE 9.2.1 Any other claim, dispute or other matter in question arising out of or related to this Agreement or breach thereof shall be settled in accordance with Article 4 of AIA Document A201, except that in addition to and prior to arbitration, the parties shall endeavor to reach settlement by mediation in accordance with the Construction Industry Mediation Rules of the American Arbitration Association currently in effect, unless the parties mutually agree otherwise. Any mediation arising under this Paragraph shall be conducted in accordance with the provisions of Subparagraphs 9.1.2 and 9.1.3. 9.3 OTHER PROVISIONS 9.3.1 Unless otherwise noted, the terms used in this Agreement shall have the same meaning as those in the 1987 edition of AIA Document A201, General Conditions of the Contract for Construction. 9.3.2 EXTENT OF CONTRACT This Contract, which includes this Agreement and the other documents incorporated herein by reference, represents the entire and integrated agreement between the Owner and the Construction Manager and supersedes all prior negotiations, representations or agreements, either written or oral. This Agreement may be amended only by written instrument signed by both the Owner and Construction Manager. If anything in any document incorporated into this Agreement is inconsistent with this Agreement, this Agreement shall govern. 9.3.3 OWNERSHIP AND USE OF DOCUMENTS The Drawings, Specifications and other documents prepared by the Architect, and copies thereof furnished to the Construction Manager, are for use solely with respect to this Project. They are not to be used by the Construction Manager, Subcontractors, Sub-subcontractors or suppliers on other projects, or for additions to this Project outside the scope of the Work, without the specific written consent of the Owner and Architect. The Construction Manager, Subcontractors, Sub-subcontractors and suppliers are granted a limited license to use and reproduce applicable portions of the Drawings, Specifications and other documents prepared by the Architect appropriate to and for use in the execution of their Work under the Contract Documents. 9.3.4 GOVERNING LAW The Contract shall be governed by the law of Minnesota. 9.3.5 ASSIGNMENT The Owner and Construction Manager respectively bind themselves, their partners, successors, assigns and legal representatives to the other party hereto and to partners, successors, assigns and legal representatives of such other party in respect to covenants, agreements and obligations contained in the Contract Documents. Neither party to the Contract shall assign the Contract as a whole without written consent of the other. If either party attempts to make such an assignment without such consent, that party shall nevertheless remain legally responsible for all obligations under the Contract. ARTICLE 10 ---------- TERMINATION OR SUSPENSION 10.1 TERMINATION PRIOR TO THE OWNER'S APPROVAL OF THE CONTROL ESTIMATE 10.1.1 Prior to the Owner's approval of the Control Estimate, the Owner may terminate this Contract at any time without cause, and the Construction Manager may terminate this Contract for any of the reason described in Subparagraph 14.1.1 of AIA document A201. The provisions of Article 14 of AIA Document A201 do not otherwise apply to this Paragraph 10.1. 10.1.2 If the Owner or Construction Manager terminates this Contract pursuant to this Paragraph 10.1 prior to commencement of 13 the Construction Phase, the Construction Manager shall be equitably compensated for Preconstruction Phase Services performed prior to receipt of notice of termination; provided, however, that the compensation for such services shall not exceed the compensation set forth in Subparagraph 4.1.1. 10.1.3 If the Owner or Construction Manger terminates this Contract pursuant to this Paragraph 10.1 after commencement of the Construction Phase, and prior to the Owner's approval of the Control Estimate, the Construction Manager shall, in addition to the compensation provided in Subparagraph 10.1.2, be paid an amount calculated as follows: .1 Take the Cost of the Work incurred by Construction Manager. .2 Add the Construction Manager's Fee computed upon the Cost of the Work to the date of termination at the rate stated in Paragraph 5.1 or, if the Construction Manager's Fee is stated as a fixed sum in that Paragraph, an amount which bears the same ratio to that fixed-sum Fee as the Cost of the Work at the time of termination bears to a reasonable estimate of the probable Cost of the Work upon its completion. .3 Subtract the aggregate of previous payments made by the Owner on account of the Construction Phase. The Owner shall also pay the Construction Manger fair compensation, either by purchase or rental at the election of the Owner, for any equipment owned by the Construction Manager which the Owner elects to retain and which is not otherwise included in the Cost of the Work under Clause 10.1.3.1. To the extent that the Owner elects to take legal assignment of subcontracts and purchase orders (including rental agreements), the Construction Manager shall, as a condition of receiving the payment referred to in this Article 10, execute and deliver all such papers and take all such steps, including the legal assignment of such subcontracts and other contractual rights of the Construction Manager, as the Owner may require for the purpose of fully vesting in the Owner the rights and benefits of the Construction Manager under such subcontracts or purchase orders. Subcontracts, purchase orders and rental agreements entered into by the Construction Manager and the Owner's written approval prior to the Owner's approval of the Control Estimate shall contain provisions permitting assignment to the Owner as described above. If the Owner accepts such assignment, the Owner shall reimburse or indemnify the Construction Manager with respect to all costs arising under the subcontract, purchase order or rental agreement, except those which would not have been reimbursable as Cost of the Work if the contract had not been terminated. If the Owner elects not to accept the assignment of any subcontract, purchase order or rental agreement which would have constituted a Cost of the Work had this agreement not been terminated, the Construction Manager shall terminate such subcontract, purchase order or rental agreement and the Owner shall pay the Construction Manager the costs necessarily incurred by the Construction Manager by reason of such termination. 10.2 TERMINATION SUBSEQUENT TO THE OWNER'S APPROVAL OF THE CONTROL ESTIMATE 10.2.1 Subsequent to the Owner's approval of the Control Estimate, the Contract may be terminated as provided in Sub-paragraphs 14.1.1 and 14.2.1 of AIA Document A201. The provisions of Article 14 of AIA Document A201 do not otherwise apply to this Paragraph 10.2. 10.2.2 In the event of such termination by the Owner, the amount payable to the Construction Manager shall not exceed the amount the Construction Manager would have been entitled to receive pursuant to Subparagraphs 10.1.2 and 10.1.3 of this Agreement, less any compensation that may be awarded to the Owner pursuant to Paragraph 9.2. 10.2.3 In the event of such termination by the Construction Manager, the amount payable to the Construction Manager shall be in accordance with Subparagraphs 10.1.2 and 10.1.3 of this Agreement, except that the Construction Manager's Fee shall be calculated as if the Work had been fully completed by the Construction Manager, including a reasonable estimate of the Cost of the Work for Work not actually completed. 10.2.4 In addition to the Owner's right to terminate this Agreement for cause as provided in Subparagraph 14.2.1 of AIA document A201, the Owner may terminate this Agreement without cause; in such case, the Construction Manager shall be paid as provided in Subparagraph 10.2.3. 10.3 NOTICE OF TERMINATION 10.3.1 The party seeking termination shall give the other party seven days' written notice. 10.4 SUSPENSION The Work may be suspended by the Owner as provided in Article 14 of AIA Document A201; in such case, the associated increase in costs shall become part of the Cost of Work, and the Construction Manager's Fee shall be adjusted in accordance with Paragraph 5.1. 14 ARTICLE 11 ---------- OTHER CONDITIONS AND SERVICES 11.1 CONFIDENTIAL AND PROPRIETARY INFORMATION Construction Manager acknowledges that in connection with the performance of the services and Work hereunder, Owner may disclose to Construction Manager certain confidential and proprietary business information. Construction Manager agrees to hold in confidence and not to disclose (1) internally, to any affiliate or business group not directly involved in the performance, management, or oversight of the Work hereunder, and (2) externally, to any person or entity, any proprietary business information disclosed to it by Owner. Proprietary business information shall include financial and operations information, business and manufacturing systems or procedures and any other material designated as "confidential" by Owner. Construction Manager shall take all steps necessary to assure adherence to the provisions of this paragraph 11.1 by its employees, officers and directors. Confidential information shall not include (1) information that was in the public domain prior to the effective date of this Agreement or prior to disclosure; (2) information which becomes part of the public domain by publication or otherwise, but not due to any unauthorized act or omission of the receiving party hereunder; (3) information within the prior knowledge of the receiving party; or (4) information received from a third party under no obligation of confidentiality with respect thereto. 11.2 LIMITATION OF LIABILITY Construction Manager's liability to Owner for consequential, incidental, special or indirect damages, including, without limitation, loss of use of the Project or Owner's existing property, loss of profits, interest, product or business interruption, increased cost of operations and maintenance, or staffing needs shall not exceed the sum of Five Million Dollars ($5,000,000.00). This Agreement entered into as of the day and year first written above. LIFECORE BIOMEDICAL, INC. MARSHALL CONTRACTORS, INC. By: /S/ DENNIS J. ALLINGHAM By: /S/ THOMAS BRADY ------------------------------- ------------------------------ VICE PRESIDENT & CFO Date: 7/2/97 Date: JUNE 16, 1997 ----------------------------- ----------------------------- ATTEST: /S/ ROBERT D. MCCOLLOUGH ATTEST: /S/ M.L. PHILLIPS --------------------------- --------------------------- /S/ RAM --------------------------- RAM 15