EXHIBIT 10.31


                      POWER PURCHASE CONTRACT
                              BETWEEN
                SOUTHERN CALIFORNIA EDISON COMPANY
                                AND
                      MAGMA ELECTRIC COMPANY






    





                         TABLE OF CONTENTS

SECTION    TITLE                                           PAGE
- -------    -----                                           ----
      1    PROJECT SUMMARY                                    1
      2    DEFINITIONS                                        4
      3    TERM                                              10
      4    GENERATING FACILITY                               10
      5    OPERATING OPTIONS                                 19
      6    INTERCONNECTION FACILITIES                        20
      7    METERING                                          20
      8    POWER PURCHASE PROVISIONS                         22
      9    PAYMENT AND BILLING PROVISIONS                    41
     10    TAXES                                             44
     11    TERMINATION                                       44
     12    SALE OF GENERATING FACILITY                       44
     13    ABANDONMENT OF PROJECT                            46
     14    LIABILITY                                         46
     15    INSURANCE                                         48
     16    UNCONTROLLABLE FORCES                             50
     17    NONDEDICATION OF FACILITIES                       52
     18    PRIORITY OF DOCUMENTS                             52
     19    NOTICES AND CORRESPONDENCE                        53
     20    PREVIOUS COMMUNICATIONS                           53
     21    THIRD PARTY BENEFICIARIES                         53
     22    NONWAIVER                                         54
     23    DISPUTES                                          54
     24    SUCCESSORS AND ASSIGNS                            55

                                i




    







     25    EFFECT OF SECTION HEADINGS                       56
     26    TRANSMISSION                                     56
     27    AMENDMENT                                        57
     28    GOVERNING LAW                                    57
     29    CONFIDENTIALITY                                  57
     30    MULTIPLE ORIGINALS                               59
           SIGNATURES                                       59
           APPENDIX A                                      A-l
           APPENDIX B                                      B-1
           APPENDIX C                                      C-1



                               ii





    





1.    PROJECT SUMMARY
      This Contract is entered into between Southern California Edison Company
      ("Edison") and Magma Electric Company, a Nevada Corporation ("Seller").
      Seller is willing to construct, own, and operate a Qualifying Facility
      and sell electric power to Edison and Edison is willing to purchase
      electric power delivered by Seller to Edison at the Point of
      Interconnection pursuant to the terms and conditions set forth as
      follows:

      1.1 All Notices shall be sent to Seller at the following
           address:  Magma Electric Company
                     P.O. Box 17760
                     Los Angeles, CA 90017
                     Attn: President
      1.2  Seller's Generating Facility:
           a.   Nameplate Rating: 10,000 kW
           b.   Location: Niland, Imperial County, California
           c.   Type (Check One):
                _____  Cogeneration Facility
                  X    Small Power Production Facility
      1.3  Contract Capacity: 8,000 kW
           1.3.1     Estimated as-available capacity: 2,000 kW
      1.4  Expected annual production: 56,064,000 kWh
      1.5  Expected Date of Firm-Operation: July 1, 1986
      1.6  Contract Term: 30 years






    






           1.7  Operating Options pursuant to Section 5: (Check One)
                  X  Operating Option I.  Excess Generator output
                     dedicated to Edison.  No electric service or
                     standby service required from Edison.
                ____ Operating Option II. Entire Generator output dedicated to
                     Edison with separate electric service required from
                     Edison.
      1.8  The Capacity Payment Option selected by Seller pursuant to Section
           8.1 shall be: (Check One)
                  _____  Option A - As-available capacity  based upon:
                  _____  Standard Offer No. 1 Capacity Payment
                         Schedule, or
                  _____  Forecast of Annual As-Available Capacity
                         Payment Schedule
             X    Option B - Firm Capacity
                    X    Standard Offer No. 2 Capacity Payment
                         Schedule in effect at time of Contract
                         execution
                  _____  Standard Offer No. 2 Capacity Payment
                         Schedule in effect at time of Firm
                         Operation
                         a.    The Contract Capacity Price: $158
                               kW-yr. (Firm Capacity)


                               2





    






           1.9  The Energy Payment Option selected by Seller pursuant
           to Section 8.2 shall be: (Check One)
             X  Option 1 - Forecast of Annual Marginal Cost of Energy in
                effect at date of execution of this Contract. (Appendix B)
           ____ Option 2 - Levelized Forecast of Marginal Cost of Energy in
                effect at date of execution of this Contract. (Appendix C) For
                the energy payment refund pursuant to Section 8.5 under Option
                2, Edison's Incremental Cost of Capital is 15%.
           Seller may change once between Options 1 and 2, provided Seller
           delivers written notice of such change at least 90 days prior to
           the date of Firm Operation. For Option 1 or 2, Seller elects to
           receive the following percentages in 20% increments, the total of
           which shall equal 100%: 100 percent of Forecast of Annual Marginal
           Cost of Energy, and 0 percent of Edison's published avoided cost of
           energy as updated periodically and accepted by the Commission.

                               3





    





                   GENERAL TERMS AND CONDITIONS
2.    DEFINITIONS
      When used with initial capitalizations, whether in the
      singular or in the plural, the following terms shall have
      the following meanings:
      2.1  Adjusted Capacity Price: The $/kW-yr. capacity purchase
           price based on the Capacity Payment Schedule in effect at the time
           of Contract execution for the time period beginning on the date of
           Firm Operation for the first generating unit and ending on the date
           of termination or reduction of Contract Capacity under Capacity
           Payment Option B.
      2.2  Appendix A: Capacity Payment Schedule - Forecast of
           Annual As-Available Capacity
      2.3  Appendix B: Energy Payment Schedule - Forecast of
           Annual Marginal Cost of Energy
      2.4  Appendix C: Energy Payment Schedule - Levelized
           Forecast of Marginal Cost of Energy
      2.5  Capacity Payment Schedule(s): Published capacity
           payment schedule(s) as authorized by the Commission and
           in effect at the time of execution of this Contract for
           as-available or firm capacity.
      2.6  Commission: The Public Utilities Commission of the
           State of California.
      2.7  Contract: This document and Appendices, as amended from
           time to time.


                               4





    






      2.8  Contract Capacity: The electric power producing
           capability of the Generating Facility which is
           committed to Edison.
      2.9  Contract Capacity Price: The capacity purchase price from the
           Capacity Payment Schedule approved by the Commission and in effect
           on the date of execution of this Contract for Capacity Payment
           Option B.
      2.10 Contract Term: Period in years commencing with date of
           Firm Operation during which Edison shall purchase
           electric power from Seller.
      2.11 Current Capacity Price: The $/kW-yr. capacity price
           provided in the Capacity Payment Schedule determined by
           the year of termination or reduction of Contract
           Capacity and the number of years from such termination
           or reduction to the expiration of the Contract Term for
           Capacity Payment Option B.
      2.12 Edison: The Southern California Edison Company.
      2.13 Edison Electric System Integrity: The state of operation of
           Edison's electric system in a manner which is deemed to minimize
           the risk of injury to persons and/or property and enables Edison to
           provide adequate and reliable electric service to its customers.
      2.14 Emergency: A condition or situation which in Edison's sole judgment
           affects Edison Electric System Integrity.
      2.15 Energy: Kilowatt hours generated by the Generating
           Facility which are purchased by Edison at the Point of
           Interconnection.


                               5





    






      2.16 Firm Operation: The date agreed on by the Parties on which
           each generating unit of the Generating Facility is determined to be
           a reliable source of generation and on which such unit can be
           reasonably expected to operate continuously at its effective rating
           (expressed in kW).
      2.17 First Period: The period of the Contract Term specified in
           Section 3.1.
      2.18 Forced Outage: Any outage other than a scheduled outage of the
           Generating Facility that fully or partially curtails its electrical
           output.
      2.19 Generating Facility: All of Seller's generators, together with all
           protective and other associated equipment and improvements, necessary
           to produce electrical power at Seller's Facility excluding associated
           land, land rights, and interests in land.
      2.20 Generator: The generator(s) and associated prime mover(s), which are
           a part of the Generating Facility.
      2.21 Interconnection Facilities: The electrical interconnection
           facilities furnished, at no cost to Edison, by Seller, or by the
           Interconnecting Utility on the Seller's behalf, which are
           appurtenant to, and/or incidental to, the Project. The
           Interconnection Facilities shall include, but are not limited to,
           transmission lines and/or distribution lines between the Project
           and transmission lines and/or distribution lines of the
           Interconnecting Utility, relays, power-


                               6





    






           circuit breakers, metering devices, telemetering devices, and other
           control and protective devices specified by the Interconnecting
           Utility as necessary for operation of the Project in parallel with
           the Interconnecting Utility's electric system.
      2.22 Interconnecting Utility: The electric utility, or any
           other utility which takes delivery of electric energy
           generated by the Generating Facility.
      2.23 Operate: To provide the engineering, purchasing, repair,
           supervision, training, inspection, testing, protection, operation,
           use, management, replacement, retirement, reconstruction, and
           maintenance of and for the Generating Facility in accordance with
           applicable California utility standards and good engineering
           practices.
      2.24 Operating Representatives: Individual(s) appointed by each Party
           for the purpose of securing effective cooperation and interchange
           of information between the Parties in connection with
           administration and technical matters related to this Contract.
      2.25 Parties: Edison and Seller.
      2.26 Party: Edison or Seller.
      2.27 Peak Months: Those months which the Edison annual system peak
           demand could occur. Currently, but subject to change with notice,
           the peak months for the Edison system are June, July, August, and
           September.


                               7





    






      2.28 Point of Interconnection: The point where the electrical
           energy generated by the Seller, at the Project, is delivered to the
           Edison electric system.
      2.29 Project: The Generating Facility and Interconnection Facilities
           required to permit the Generator to deliver electric energy and
           make capacity available to Interconnecting Utility.
      2.30 Qualifying Facility: Cogeneration or Small Power
           Production Facility which meets the criteria as defined in Title
           18, Code of Federal Regulations, Section
           292.201 through 292.207.
      2.31 Renewable Resources: Wind parks, small hydroelectric,
           solar, and geothermal resources which produce electric
           power.
      2.32 Second Period: The period of the Contract Term
           specified in Section 3.2.
      2.33 Seller: The Party identified in Section 1.0.
      2.34 Seller's Facility: The premises and equipment of Seller
           located as specified in Section 1.2.
      2.35 Small Power Production Facility: The facilities and equipment which
           use biomass, waste, or Renewable Resources, including wind, solar,
           geothermal, and water, to produce electrical energy as defined in
           Title 18, Code of Federal Regulations, Section 292.201 through
           292.207.


                               8





    






      2.36 Summer Period: Defined in Edison's Tariff Schedule No.
           TOU-8 as now in effect or as may hereafter be
           authorized by the Commission.
      2.37 Tariff Schedule No. TOU-8: Edison's time-of-use energy
           tariff for electric service exceeding 500 kW, as now in
           effect or as may hereafter be authorized by the
           Commission.
      2.38 Uncontrollable Forces: Any occurrence beyond the control of a Party
           which causes that Party to be unable to perform its obligations
           hereunder and which a Party has been unable to overcome by the
           exercise of due diligence, including but not limited to flood,
           drought, earthquake, storm, fire, pestilence, lightning and other
           natural catastrophes, epidemic, war, riot, civil disturbance or
           disobedience, strike, labor dispute, action or inaction of
           government or other proper authority, which may conflict with the
           terms of this Contract, or failure, threat of failure or sabotage
           of facilities which have been maintained in accordance with good
           engineering and operating practices in California. The failure of
           the Interconnecting Utility to deliver electrical energy to the
           Point of Interconnection shall be an Uncontrollable Force only if
           such failure is beyond the control of the Interconnecting Utility.


                               9





    






      2.39 Winter Period: Defined in Edison's Tariff Schedule No.
           TOU-8 as now in effect or as may hereafter be
           authorized by the Commission.
3.    TERM
      This Contract shall be effective upon execution by the Parties and shall
      remain effective until either Party gives 90 days' prior written notice
      of termination to the other Party, except that such notice of
      termination shall not be effective to terminate this Contract prior to
      expiration of the Contract Term specified in Section 1.6.
      3.1 The First Period of the Contract Term shall commence upon date of Firm
          Operation but not later than 5 years from the date of execution of
          this Contract.
           a.   If the Contract Term specified in Section 1.6 is
                15 years, the First Period of the Contract Term
                shall be for 5 years.
           b.   If the Contract Term specified in Section 1.6 is 20, 25, or 30
                years, the First Period of the Contract Term shall be for 10
                years.
      3.2  The Second Period of the Contract Term shall commence upon
           expiration of the First Period and shall continue for the remainder
           of the Contract Term.
4.   GENERATING FACILITY
      4.1  Ownership
           The Generating Facility shall be owned by Seller.


                               10





    






           4.2  Design
           4.2.1     Seller, at no cost to Edison, shall:
                     a.   Design the Generating Facility.
                     b.   Acquire all permits and other approvals
                          necessary for the construction,
                          operation, and maintenance of the
                          Generating Facility.
                     c.   Complete all environmental impact
                          studies necessary for the construction,
                          operation, and maintenance of the
                          Generating Facility.
           4.2.2     Edison shall have the right to review the
                     design of the Generating Facility's
                     electrical system and the Seller's
                     Interconnection Facilities.  Edison shall
                     have the right to request modifications to
                     the design of the Generating Facility's
                     electrical system and the Seller's
                     Interconnection Facilities.  Such
                     modifications shall be required if necessary
                     to maintain Edison Electric System Integrity.
                     If Seller does not agree to such
                     modifications, resolution of the difference
                     between the Parties shall be made pursuant to
                     Section 23.


                               11





    






           4.3  Construction
                     Edison shall have the right to review, consult with, and
                     make recommendations regarding Seller's construction
                     schedule and to monitor the construction and start-up of
                     the Project. Seller shall notify Edison, as far in
                     advance of Firm Operation as reasonably possible, of
                     changes in Seller's Construction Schedule which may
                     affect the date of Firm Operation.
     4.4   Operation
           4.4.1     Edison shall have the right to monitor operation of the
                     Project and may require changes in Seller's method of
                     operation if such changes are necessary, in Edison's sole
                     judgment, to maintain Edison Electric System
                     Integrity.
           4.4.2     Seller shall notify, in writing, Edison's Operating
                     Representative at least 14 days prior to the initial
                     delivery of electrical energy from the Project to the
                     Point of Interconnection.
           4.4.3     Edison shall have the right to require Seller to curtail
                     or reduce the delivery of electrical energy from the
                     Project to the Edison electric system whenever Edison
                     determines, in its sole judgment, that such curtailment
                     or reduction is necessary to


                               12





    






                     facilitate maintenance of Edison's facilities, or to
                     maintain Edison Electric System Integrity. If Edison
                     requires Seller to curtail or reduce the delivery of
                     electrical energy from the Project to the Edison electric
                     system pursuant to this Section 4.4.3, Seller shall have
                     the right to continue to serve its total electrical
                     requirements. Each Party shall endeavor to correct,
                     within a reasonable period, the condition on its system
                     which necessitates the curtailment or the reduction of
                     delivery of electrical energy from the Project. The
                     duration of the curtailment or the reduction shall be
                     limited to the period of time such a condition exists.

           4.4.4     Each Party shall keep the other Party's Operating
                     Representative informed as to the operating schedule of
                     their respective facilities affecting each other's
                     operation hereunder, including any reduction in
                     Contract Capacity availability. In addition, Seller shall
                     provide Edison with reasonable advance notice regarding
                     its scheduled outages including any reduction in Contract
                     Capacity availability. Reasonable advance notice is as
                     follows:


                               13





    






                    SCHEDULED OUTAGE              ADVANCE NOTICE
                    EXPECTED DURATION               TO EDISON

                    Less than one day            24 Hours

                    one day or more
                    (except major overhauls)     1 Week

                    Major overhaul               6 Months

           4.4.5     Notification by each Party's Operating Representative of
                     outage date and duration should be directed to the other
                     Party's Operating Representative by telephone.
           4.4.6     Seller shall not schedule major overhauls
                     during Peak Months.
           4.4.7     Seller shall maintain an operating log at
                     Seller's Facility with records of: real and
                     reactive power production; changes in
                     operating status, outages, Protective
                     Apparatus operations; and any unusual
                     conditions found during inspections.  Changes
                     in setting shall also be logged for
                     Generators which are "block-loaded" to a
                     specific kW capacity. In addition, Seller
                     shall maintain records applicable to the
                     Generating Facility, including the electrical
                     characteristics of the Generator and
                     settings, adjustments of the Generator
                     control equipment, and well-field
                     information.  Information maintained pursuant


                               14





    






                     to this Section 4.4.7 shall be provided to Edison, within
                     30 days of Edison's request.
           4.4.8     At Edison's request, Seller shall make all
                     reasonable effort to deliver power at an
                     average rate of delivery at least equal to
                     the Contract Capacity during periods of
                     Emergency.  In the event that the Seller has
                     previously scheduled an outage coincident
                     with an Emergency, Seller shall make all
                     reasonable efforts to reschedule the outage.
                     The notification periods listed in Section
                     4.4.4 shall be waived by Edison if Seller
                     reschedules the outage.
           4.4.9     Seller shall demonstrate the ability to
                     provide Edison the specified Contract
                     Capacity within 30 days of the date of Firm
                     operation.  Thereafter, at least once per
                     year at Edison's request, Seller shall
                     demonstrate the ability to provide Contract
                     Capacity for a reasonable period of time as
                     required by Edison.  Seller's demonstration
                     of Contract Capacity shall be at Seller's
                     expense and conducted at a time and pursuant
                     to procedures mutually agreed upon by the
                     Parties.  If Seller fails to demonstrate the
                     ability to provide the Contract Capacity, the
                     Contract Capacity shall be reduced by


                               15





    






                     agreement of the Parties pursuant to Section
                     8.1.2.5.
           4.4.10    The Seller warrants that the Generating Facility meets
                     the requirements of a Qualifying Facility as of the
                     effective date of this Contract and continuing through
                     the Contract Term.
           4.4.11    The Seller warrants that the Generating
                     Facility shall, at all times, conform to all
                     applicable laws and regulations.  Seller
                     shall obtain and maintain any governmental
                     authorizations and permits for the continued
                     operation of the Generating Facility.  If, at
                     any time, Seller does not hold such
                     authorizations and permits, Seller agrees to
                     reimburse Edison for any loss which Edison
                     incurs as a result of the Seller's failure to
                     maintain governmental authorization and
                     permits.
           4.4.12    In the event electrical energy from the
                     Project is curtailed or reduced pursuant to
                     Sections 4.4.3, 16 or 8.4, the Seller, in its
                     sole discretion, may elect to (i) sell said
                     electrical energy to a third party or (ii)
                     deliver said electrical energy to a third
                     party for future delivery to Edison at times
                     and at amounts agreeable to Edison.  The


                               16





    






                     Seller shall be responsible for making all such
                     arrangements. The provisions in this Section 4.4.12 shall
                     only apply for the duration of the curtailment or
                     reduction.
           4.4.13    Seller shall maintain operating
                     communications with the Edison switching
                     center designated by the Edison Operating
                     Representative.  The operating communications
                     shall include, but not be limited to, system
                     paralleling or separation, scheduled and
                     unscheduled shutdowns, equipment clearances,
                     levels of operating voltage or power factors,
                     and daily capacity and generation reports.
      4.5  Maintenance
           4.5.1     Seller shall maintain the Generating Facility
                     in accordance with applicable California
                     utility industry standards and good
                     engineering and operating practices.  Edison
                     shall have the right to monitor such
                     maintenance of the Generating Facility.
                     Seller shall maintain and deliver a
                     maintenance record of the Generating Facility
                     to Edison's Operating Representatives upon
                     request.
           4.5.2     Seller shall make a reasonable effort to
                     schedule routine maintenance during Off-Peak
                     Months and expected minimal generation


                               17





    






                     periods for renewable resources. Outages for scheduled
                     maintenance shall not exceed a total of 30 peak hours for
                     the Peak Months.
           4.5.3     The allowance for scheduled maintenance is as
                     follows:
                     a.   Outage periods for scheduled maintenance
                          shall not exceed 840 hours (35 days) in any 12-month
                          period. This allowance may be used in increments of
                          an hour or longer on a consecutive or nonconsecutive
                          basis.
                     b.   Seller may accumulate unused maintenance hours on a
                          year-to-year basis up to a maximum of 1,080 hours
                          (45 days). This accrued time must be used
                          consecutively and only for major overhauls.
      4.6  Any review by Edison of the design, construction,
           operation, or maintenance of the Project is solely for
           the information of Edison.  By making such review,
           Edison makes no representation as to the economic and
           technical feasibility, operational capability, or
           reliability of the Project.  Seller shall in no way
           represent to any third party that any such review by
           Edison of the Project, including, but not limited to,
           any review of the design, construction, operation, or
           maintenance of the Project by Edison, is a
           representation by Edison as to the economic and


                               18





    






           technical feasibility, operational capability, or reliability of
           said facilities. Seller is solely responsible for economic and
           technical feasibility, operational capability, and reliability
           thereof.
      4.7  Edison shall have access to the Seller's geothermal
           field and power-generating facilities for the purpose
           of gathering technical information and records.  The
           technical information and records shall include, but
           not be limited to, drilling data, well-testing data,
           well-production data and design, power plant
           performance data and design, environmental data, brine
           handling design, and operation and maintenance data.
           Edison agrees not to interfere with Seller's rules and
           operating regulations.
5.    OPERATING OPTIONS
      5.1  Seller shall elect in Section 1.7 to Operate its
           Generating Facility pursuant to one of the following
           options:
           a.   Operating Option 1: Seller dedicates the excess
                Generator output to Edison with no electrical service or
                standby service required from Edison.
           b.   Operating Option II: Seller dedicates the entire
                Generator output to Edison with electrical service
                required from Edison.
      5.2  After expiration of the First Period of the Contract Term, Seller
           may change the Operating Option, but not more than once per year
           upon at least 90 days' prior


                               19





    






           written notice to Edison. A reduction in Contract Capacity as a
           result of a change in operating options shall be subject to Section
           8.1.2.5. Edison shall not be required to remove or reserve capacity
           of Interconnection Facilities made idle by a change in operating
           options. Edison may dedicate any such idle Interconnection
           Facilities at any time to serve other customers or to interconnect
           with other electric power sources. Edison shall process requests
           for changes of operating option in the chronological order
           received.
6.   INTERCONNECTION FACILITIES
      6.1  Seller shall design, engineer, procure, construct, and test the
           Interconnection Facilities in accordance with applicable California
           utility standards and good engineering practices and the rules and
           regulations of the Interconnecting Utility.
      6.2  The design, installation, operation, maintenance, and modifications
           of the Interconnection Facilities shall be at Seller's expense.
      6.3  Seller, at no cost to Edison, shall acquire all permits and
           approvals and complete all environmental impact studies necessary
           for the design, installation, operation, and maintenance of the
           Interconnection Facilities.
7.    METERING
      7.1  All meters and equipment used for the measurement of
           electrical power for determining Edison's payments to


                               20





    






           Seller pursuant to this Contract shall be provided, owned, and
           maintained by Edison and/or the Inter- connecting Utility at
           Seller's expense.
      7.2  If Seller's Generating Facility is rated at a Capacity of 500 kW or
           greater, then Edison, at its option, may install at Seller's
           expense, generation metering and/or telemetering equipment.
      7.3  Edison's or the Interconnecting Utility's meters shall
           be sealed and the seals shall be broken only when the
           meters are to be inspected, tested, or adjusted by
           Edison or Interconnecting Utility.  Seller shall be
           given reasonable notice of testing and have the right
           to have its Operating Representative present on such
           occasions.
      7.4  Edison's or Interconnecting Utility's meters installed
           pursuant to this Contract shall be tested by Edison or
           Interconnecting Utility, at Edison's or Interconnecting
           Utility's expense, at least once each year and at any
           reasonable time upon request by either Party, at the
           requesting Party's expense.  If Seller makes such
           request, Seller shall reimburse said expense to Edison
           or Interconnecting Utility within thirty days after
           presentation of a bill therefor.
      7.5  Metering equipment found to be inaccurate shall be repaired,
           adjusted, or replaced by Edison or Interconnecting Utility such
           that the metering accuracy of said equipment shall be within plus
           or minus two


                               21





    






           percent. If metering equipment inaccuracy exceeds plus or minus two
           percent, the correct amount of Energy and capacity delivered during
           the period of said inaccuracy shall be estimated by Edison and
           agreed upon by the Parties.

8.    POWER PURCHASE PROVISIONS
      Prior to the date of Firm Operation, Seller shall be paid for Energy
      only pursuant to Edison's published avoided cost of energy based on
      Edison's full avoided operating cost as periodically updated and
      accepted by the Commission. If at any time electrical energy can be
      delivered to Edison and Seller is contesting the claimed jurisdiction of
      any entity which has not issued a license or other approval for the
      Project, Seller, in its sole discretion and risk, may deliver electrical
      energy to Edison and for any electrical energy purchased by Edison
      Seller shall receive payment from Edison for (i) Energy pursuant to this
      Section, and (ii) as- available capacity based on a capacity price from
      the Standard Offer No. 1 Capacity Payment Schedule as approved by the
      Commission. Unless and until all required licenses and approvals have
      been obtained, Seller may discontinue deliveries at any time.

      8.1  Capacity Payments Seller shall sell to Edison and Edison shall
           purchase from Seller capacity pursuant to the Capacity Payment Option
           selected by Seller in Section 1.8. The Capacity Payment Schedules
           will be based on Edison's full


                               22





    






           avoided operating costs as approved by the Commission
           throughout the life of this Contract.
           8.1.1     Capacity Payment Option A -- As-Available
                     Capacity.
                If Seller selects Capacity Payment Option A, Seller shall be
                paid a Monthly Capacity Payment calculated pursuant to the
                following formula:

Monthly Capacity Payment  =    (A x D)+(B x D)+(C x D)
                  Where A =    kWh purchased by Edison during on-peak
                               periods defined in Edison's Tariff
                               Schedule No. TOU-8.
                        B =    kWh purchased by Edison during mid-peak
                               periods defined in Edison's Tariff Schedule No.
                               TOU-8.
                        C =    kWh purchased by Edison during off-peak
                               periods defined in Edison's Tariff Schedule No.
                               TOU-8.
                        D =    The appropriate time differentiated capacity
                               price from either the Standard Offer No. 1
                               Capacity Payment Schedule or Forecast of Annual
                               As- Available Capacity Payment Schedule as
                               specified by Seller in Section 1.8.
                     8.1.1.1   If Seller specifies the Standard
                               Offer No. 1 Capacity Payment
                               Schedule in Section 1.8, then the
                               formula set forth in Section 8.1.1


                               23





    






                               shall be computed with D equal to
                               the appropriate time differentiated
                               capacity price from the Standard
                               Offer No. 1 Capacity Payment
                               Schedule for the Contract Term.
                     8.1.1.2   If Seller specifies the Forecast of
                               Annual As-Available Capacity
                               Payment Schedule in Section 1.8,
                               the formula set forth in Section
                               8.1.1 shall be computed as follows:
                               a.   During the First Period of the
                                    Contract Term, D shall equal the
                                    appropriate time differentiated capacity
                                    price from the Forecast of Annual
                                    As-Available Capacity Payment Schedule.
                               b.   During the Second Period of
                                    the Contract Term, the formula
                                    shall be computed with D equal
                                    to the appropriate time
                                    differentiated capacity price
                                    from Standard Offer No. 1
                                    Capacity Payment Schedule, but
                                    not less than the greater of
                                    (i) the appropriate time
                                    differentiated capacity price


                               24





    






                                    from the Forecast of Annual As-Available
                                    Capacity Payment Schedule for the last
                                    year of the First Period, or (ii) the
                                    appropriate time differentiated capacity
                                    price from the Standard Offer No. 1
                                    Capacity Payment Schedule for the first
                                    year of the Second Period.
           8.1.2     Capacity Payment Option B--Firm Capacity
                     Purchase
                          If Seller selects Capacity Payment Option B, Seller
                          shall provide to Edison for the Contract Term the
                          Contract Capacity specified in Section 1.3, or as
                          adjusted pursuant to Section 8.1.2.6, and Seller
                          shall be paid as follows:
                     8.1.2.1   If Seller meets the performance
                               requirements set forth in Section
                               8.1.2.2, Seller shall be paid a
                               monthly Capacity Payment, beginning
                               from the date of Firm Operation
                               equal to the sum of the on-peak,
                               mid-peak, and off-peak Capacity
                               Period Payments.  Each capacity
                               period payment is calculated
                               pursuant to the following formula:


                               25





    






Monthly Capacity Period      =      A x B x C x D
Payment
                    Where  A =     Contract Capacity Price specified in
                                   Section 1.8 based on the Standard Offer No.
                                   2 Capacity Payment Schedule as approved by
                                   the Commission and in effect on the date of
                                   the execution of this Agreement.
                           B =     Conversion factors to convert annual
                                   capacity prices to monthly payments by time
                                   of delivery as specified in Standard Offer
                                   No. 2 Capacity Payment Schedule and subject
                                   to periodic modifications as approved by
                                   the Commission.
                           C =     Contract Capacity specified in
                                   Section 1.3.
                           D =     Period Performance Factor, not
                                   to exceed 1.0, calculated as
                                   follows:
Period Performance Factor          [period kWh Purchased by Edison
                                   (Limited by the Level of
                                   Contract Capacity)]
                                   -----------------
                                   [0.8 x Contract Capacity x
                                   (Period Hours minus Maintenance
                                   Hours Allowed in Section 4.5.)]


                               26




    






                       8.1.2.2 Performance Reguirements
                               To receive the Monthly Capacity Payment in
                               Section 8.1.2.1, Seller shall provide the
                               Contract Capacity in each Peak Month for all
                               on-peak hours as such peak hours are defined in
                               Edison's Tariff Schedule No. TOU-8 on file with
                               the Commission, except that Seller is entitled
                               to a 20% allowance for Forced Outages for each
                               Peak Month. Seller shall not be subject to such
                               performance requirements for the remaining
                               hours of the year.
                              a. If Seller fails to meet the requirements
                                 specified in Section 8.1.2.2, Seller, in
                                 Edison's sole discretion, may be placed on
                                 probation for a period not to exceed 15 months.
                                 If Seller fails to meet the requirements
                                 specified in Section 8.1.2.2 during the
                                 probationary period, Edison may derate the
                                 Contract Capacity to the greater of the
                                 capacity


                               27





    






                                    actually delivered during the probationary
                                    period, or the capacity at which Seller
                                    can reasonably meet such requirements. A
                                    reduction in Contract Capacity as a result
                                    of this Section 8.1.2.2 shall be subject
                                    to Section 8.1.2.5.
                               b.   If Seller fails to meet the
                                    requirements set forth in this
                                    Section 8.1.2.2 due to a
                                    Forced Outage on the Edison
                                    system, or a request to reduce
                                    or curtail delivery under
                                    Section 8.4, Edison shall
                                    continue Monthly Capacity
                                    Payments pursuant to Capacity
                                    Payment Option B.  The
                                    Contract Capacity curtailed
                                    shall be treated the same as
                                    scheduled maintenance outages
                                    in the calculation of the
                                    Monthly Capacity Payment.
                     8.1.2.3   If Seller is unable to provide
                               Contract Capacity due to
                               Uncontrollable Forces, Edison shall
                               continue Monthly Capacity Payments


                               28




    






                               pursuant to Capacity Payment option B for 90
                               days from the occurrence of the Uncontrollable
                               Force. Monthly Capacity Payments payable during
                               a period of interruption or reduction by reason
                               of an Uncontrollable Force shall be treated the
                               same as scheduled maintenance outages.
                     8.1.2.4   Capacity Bonus Payment
                               For Capacity Payment Option B,
                               Seller may receive a Capacity Bonus
                               Payment as follows:
                               a.   Bonus During Peak Months
                                    ------------------------
                                    For a Peak Month, Seller shall
                                    receive a Capacity Bonus
                                    Payment if (i) the
                                    requirements set forth in
                                    Section 8.1.2.2 have been met,
                                    and (ii) the on-peak capacity
                                    factor exceeds 85%.
                               b.   Bonus During Non-Peak Months
                                    ----------------------------
                                    For a non-peak month, Seller
                                    shall receive a Capacity Bonus
                                    Payment if (i) the
                                    requirements set forth in
                                    Section 8.1.2.2 have been met,


                               29





    






                                    (ii) the on-peak capacity factor for each
                                    Peak Month during the year was at least
                                    85%, and (iii) the on-peak capacity factor
                                    for the non- peak month exceeds 85%.
                               c.   For any eligible month, the
                                    Capacity Bonus Payment shall
                                    be calculated as follows:
      Capacity Bonus Payment =      A x B x C x D
                     Where A =      (1.2 x On-Peak Capacity Factor)-
                                    1.02
                       Where the On-Peak Capacity Factor, not to exceed 1.0,
                       is calculated as follows:
                                    [Period kWh Purchased by
                                    Edison (Limited by the Level
                                    of Contract Capacity)]
      On-Peak capacity Factor  =    ((Contract capacity) x (Period
                                    Hours minus Maintenance Hours
                                    Allowed in Section 4.5))
                            B  =    Contract Capacity Price specified
                                    in Section 1.8 for Capacity
                                    Payment Option B
                            C =     1/12
                            D =     Contract Capacity specified in
                                    Section 1.3


                               30





    






                                    d. When Seller is entitled to receive a
                                    Capacity Bonus Payment, the Monthly
                                    Capacity Payment shall be the sum of the
                                    Monthly Capacity Payment pursuant to
                                    Section 8.1.2.1 and the Monthly Capacity
                                    Bonus Payment pursuant to this Section
                                    8.1.2.4.
                     8.1.2.5   Capacity Reduction
                               a.   Seller may reduce the Contract
                                    Capacity specified in Section 1.3,
                                    provided that Seller gives Edison prior
                                    written notice for a period determined by
                                    the amount of Contract Capacity reduced as
                                    follows:

                          Amount of Contract        Length of
                          Capacity Reduced       Notice Required

                          25,000 kW or under        12 months
                          25,001 - 50,000 kW        36 months
                          50,001 - 100,000 kW       48 months
                          over 100,000 kW           60 months

                               b.   Seller shall refund to Edison
                                    with interest at the current
                                    published Federal Reserve
                                    Board three months prime
                                    commercial paper rate, an
                                    amount equal to the difference


                               31





    






                                    between (i) the accumulated Monthly
                                    Capacity Payments paid by Edison pursuant
                                    to Capacity Payment Option B up to the
                                    time the reduction notice is received by
                                    Edison, and (ii) the total capacity
                                    payments which Edison would have paid if
                                    based on the Adjusted Capacity Price.
                               c.   From the date the reduction
                                    notice is received to the date
                                    of actual capacity reduction,
                                    Edison shall make capacity
                                    payments based on the Adjusted
                                    Capacity Price for the amount
                                    of Contract Capacity being
                                    reduced.
                               d.   Seller may reduce Contract
                                    Capacity without the notice
                                    prescribed in Section
                                    8.1.2.5(a), provided that
                                    Seller shall refund to Edison
                                    the amount specified in
                                    Section 8.1.2.5(b) and an
                                    amount equal to: (i) the
                                    amount of Contract Capacity


                               32





    






                                    being reduced, times (ii) the difference
                                    between the Current Capacity Price and the
                                    Contract Capacity Price, times (iii) the
                                    number of years and fractions thereof (not
                                    less than one year) by which the Seller
                                    has been deficient in giving the
                                    prescribed notice. If the Current Capacity
                                    Price is less than the Contract Capacity
                                    Price, only payment under Section
                                    8.1.2.5(b) shall be due to Edison.
                     8.1.2.6   The Parties may agree in writing at
                               any time to adjust the Contract
                               Capacity.  Seller may reduce the
                               Contract Capacity pursuant to
                               Section 8.1.2.5.  Seller may
                               increase the Contract Capacity with
                               Edison's approval and thereafter
                               receive payment for the increased
                               capacity in accordance with the
                               Contract Capacity Price for the
                               Capacity Payment Option selected by
                               Seller for the remaining Contract
                               Term.


                               33





    






                               8.1.2.7 For Capacity Payment Option B, Seller
                               shall be paid for capacity in excess of
                               Contract Capacity based on the as-available
                               capacity price in Standard Offer No. 1 Capacity
                               Payment Schedule, as updated and approved by
                               the commission.
      8.2  Energy Payments - First Period
           During the First Period of the Contract Term, Seller shall be paid
           a Monthly Energy Payment for the electrical energy delivered by the
           Seller and purchased by Edison at the Point of Interconnection
           pursuant to the Energy Payment Option selected by the Seller in
           Section 1.9, as follows.

           8.2.1    Energy Payment Option 1 -- Forecast of Annual
                    Marginal Cost of Energy.
                 If Seller selects Energy Payment Option 1, then during the
                 First Period of the Contract Term, Seller shall be paid a
                 Monthly Energy Payment for electrical energy delivered by
                 Seller and purchased by Edison at the Point of Interconnection
                 during each month in the First Period of the Contract Term
                 pursuant to the following formula:


                               34







    






Monthly Energy Payment  =     [(A x D) + (B x D) + (C x D)] x E
                Where A =     kWh purchased by Edison during on-
                              peak periods defined in Edison's
                              Tariff Schedule No. TOU-8.
                      B =     kWh purchased by Edison during mid- peak
                              periods defined in Edison's Tariff Schedule No.
                              TOU-8.
                      C =     kWh purchased by Edison during off-peak
                              periods defined in Edison's Tariff Schedule No.
                              TOU-8.
                      D =     The sum of:
                              (i) the appropriate time differentiated energy
                              price from the Forecast of Annual Marginal Cost
                              of Energy, multiplied by the decimal equivalent
                              of the percentage of the forecast specified in
                              Section 1.9, and (ii) the appropriate time
                              differentiated energy price from Edison's
                              published avoided cost of energy multiplied by
                              the decimal equivalent of the percentage of the
                              published energy price specified in Section 1.9.


                               35





    






                     E =   Energy Loss Adjustment Factor For Remote Generating
                           Sites*
           8.2.2     Energy Payment Option 2 -- Levelized Forecast
                     of Marginal Cost of Energy.  If Seller
                     selects Energy Payment Option 2, then during
                     the First Period of the Contract Term, Seller
                     shall be paid a Monthly Energy Payment for
                     electrical energy delivered by Seller and
                     purchased by Edison each month during the
                     First Period of the Contract Term pursuant to
                     the following formula:
Monthly Energy Payment   =     [(A x D) + (B x D) + (C x D)] x E
Where A  =       kWh purchased by Edison during on-peak periods defined
                 in Edison's Tariff Schedule No. TOU-8.
      B  =       kWh purchased by Edison during mid- peak periods
                 defined in Edison's Tariff Schedule No. TOU-8.
      C  =       kWh purchased by Edison during off-peak periods
                 defined in Edison's Tariff Schedule No. TOU-8.
      D  =       The sum of:
                 (i) the appropriate time differentiated energy
                 price from

- --------
*     The Energy Loss Adjustment Factor For Remote Generating
      Sites shall be 1.0, subject to adjustment by Commission
      orders and rulings.

                               36





    






                               the Levelized Forecast of Marginal Cost of
                               Energy, for the First Period of the Contract
                               Term multiplied by the decimal equivalent of
                               the percentage of the levelized forecast
                               specified in Section 1.9, and (ii) the
                               appropriate time differentiated energy price
                               from Edison's published avoided cost of energy
                               multiplied by the decimal equivalent of the
                               percentage of the published energy price
                               specified in Section 1.9.
                     E =       Energy Loss Adjustment Factor For Remote
                               Generating Sites*
                     8.2.2.1   Performance Requirement for Energy
                               ----------------------------------
                               Payment Option 2
                               ----------------
                               During the First Period when the
                               annual forecast referred to in
                               Section 8.2.1 is greater than the
                               levelized forecast referred to in
                               Section 8.2.2, Seller shall deliver
                               to Edison at least 70 percent of

- --------
*     The Energy Loss Adjustment Factor For Remote Generating
      Sites shall be 1.0, subject to adjustment by Commission
      orders and rulings.

                               37





    






                               the average annual kWh delivered to Edison
                               during those previous periods when the
                               levelized forecast referred to in Section 8.2.2
                               is greater than the annual forecast referred to
                               in Section 8.2.1. If Seller does not meet the
                               performance requirements of this Section
                               8.2.2.1, Seller shall be subject to Section
                               8.5.
      8.3  Energy Payments - Second Period
           During the Second Period of the Contract Term, Seller shall be paid
           a Monthly Energy Payment for electrical energy delivered by Seller
           and purchased by Edison at the Point of Interconnection at a rate
           equal to 100% of Edison's published avoided cost of energy as
           updated periodically and accepted by the Commission, pursuant to
           the following formula:
Monthly Energy Payment = kWh purchased by Edison for each on-peak, mid-peak, and
                         off-peak time period defined in Edison's Tariff
                         Schedule No. TOU-8
                       x Edison's published avoided cost of energy by time of
                         delivery for each time period


                               38





    






                               x    Energy Loss Adjustment Factor for
                               Remote Generating Sites*
      8.4  Edison shall not be obligated to accept or pay for
           electrical energy generated by the Generating Facility,
           and may request Seller whose Generating Facility is one
           (1) MW or greater to discontinue or reduce delivery of
           electric energy, for not more than 300 hours annually
           during off-peak hours when (i) purchases would result
           in costs greater than those which Edison would incur if
           it did not purchase electrical energy from Seller but
           instead utilized an equivalent amount of electrical
           energy generated from another Edison source, or (ii)
           the Edison Electric System demand would require that
           Edison hydro-energy be spilled to reduce generation.
      8.5  Energy Payment Refund
           If Seller elects Energy Payment Option 2, Seller shall
           be subject to the following:
           8.5.1     If Seller fails to perform the Contract
                     obligations for any reason during the First Period of the
                     Contract Term, or fails to meet the performance
                     requirements set forth in Section 8.2.2.1, and at the
                     time of such failure to perform, the net present value of
                     the cumulative Energy payments received by Seller
                     pursuant to Energy Payment Option 2

- --------
*    The Energy Loss Adjustment Factor For Remote Generating
     Sites shall be 1.0, subject to adjustment by Commission
     orders and rulings.

                               39





    







                     exceeds the net present value of what Seller would have
                     been paid pursuant to Energy Payment Option 1, Seller
                     shall make an energy payment refund equal to the
                     difference in such net present values in the year in
                     which the refund is due. The present value calculation
                     shall be based upon the rate of Edison's incremental cost
                     of capital specified in Section 1.9.
           8.5.2     Not less than 90 days prior to the date
                     Energy is first delivered to the Point of
                     Interconnection, Seller shall provide and
                     maintain a performance bond, surety bond,
                     performance insurance, corporate guarantee,
                     or bank letter of credit, satisfactory to
                     Edison, which shall insure payment to Edison
                     of the Energy Payment Refund at any time
                     during the First Period.  Edison may, in its
                     sole discretion, accept another form of
                     security except that in such instance a 1-1/2
                     percent reduction shall then apply to the
                     levelized forecast referred to in Section
                     8.2.2 in computing payments for Energy.
                     Edison shall be provided with certificates
                     evidencing Seller's compliance with the
                     security requirements in this Section which
                     shall also include the requirement that


                               40





    







                     Edison be given 90 days' prior written notice of the
                     expiration of such security.
           8.5.3     If Seller fails to provide replacement
                     security not less than 60 days prior to the
                     date of expiration of existing security, the
                     Energy Payment Refund provided in Section 8.5
                     shall be payable forthwith.  Thereafter,
                     payments for Energy shall be 100 percent of
                     the Monthly Energy Payment provided in
                     Section 8.2.1.
           8.5.4     If Edison at any time determines the security
                     to be otherwise inadequate, and so notifies
                     Seller, payments thereafter for Energy shall
                     be 100 percent of the Monthly Energy Payment
                     provided in Section 8.2.1.  If within 30 days
                     of the date Edison gives notice of such
                     inadequacies, Seller satisfies Edison's
                     security requirements, Energy Payment Option
                     2 shall be reinstated.  If Seller fails to
                     satisfy Edison's security requirements within
                     the 30-day period, the Energy Payment Refund
                     provided in Section 8.5 shall be payable
                     forthwith.
9.    PAYMENT AND BILLING PROVISIONS
      9.1  For Energy and capacity purchased by Edison:
           9.1.1      Edison shall mail to Seller no later than
                      thirty days after the end of each monthly


                               41





    







                      billing period (1) a statement showing the Energy and
                      capacity delivered to Edison during the on-peak,
                      mid-peak, and off-peak periods, as those periods are
                      specified in Edison's Tariff Schedule No. TOU-8 for that
                      monthly billing period, (2) Edison's computation of the
                      amount due Seller, and (3) Edison's check in payment of
                      said amount.
           9.1.2      If the monthly payment period involves portions of two
                      different published Energy payment schedule periods, the
                      monthly Energy payment shall be prorated on the basis of
                      the percentage of days at each price.
           9.1.3      If the payment period is less than 27 days or greater
                      than 33 days, the capacity payment shall be prorated on
                      the basis of the average days per month per year.
           9.1.4      If, within thirty days of receipt of the statement,
                      Seller does not make a report in writing to Edison of an
                      error, Seller shall be deemed to have waived any error
                      in Edison's statement, computation, and payment, and
                      they shall be considered correct and complete.
      9.2  Edison shall bill the Seller, on a monthly basis, for
           the costs Edison has incurred in the transmission of


                               42





    






           the electrical energy from the Project to the Point of
           Interconnection pursuant to the provisions of Section 26.
      9.3  Payments Due to Contract Capacity Reduction
           9.3.1     The Parties agree that the refund and
                     payments provided in Section 8.1.2.5 represent a fair
                     compensation for the reasonable losses that would result
                     from such reduction of Contract Capacity.
           9.3.2     in the event of a reduction in Contract Capacity, the
                     quantity, in kW, by which the Contract Capacity is
                     reduced shall be used to calculate the refunds and
                     payments due Edison in accordance with Section 8.1.2.5,
                     as applicable.
           9.3.3     Edison shall provide invoices to Seller for all refunds
                     and payments due Edison under this Section 9 which shall
                     be due within 60 days.
           9.3.4     If Seller does not make payments as required in Section
                     9.2.3, Edison shall have the right to offset any amounts
                     due it against any present or future payments due Seller
                     and may pursue any other remedies available to Edison as
                     a result of Seller's failure to perform.


                               43




    







           9.4  Energy Payment Refund
           Energy Payment Refund is immediately due and payable upon Seller's
           failure to perform the contract obligations as specified in Section
           8.5.
10.   TAXES
      10.1 Seller shall pay ad valorem taxes and other taxes properly
           attributable to the Project. If such taxes are assessed or levied
           against Edison, Seller shall pay Edison for such assessment or
           levy.
      10.2 Seller shall pay ad valorem taxes and other taxes properly
           attributed to land, land rights, or interest in land for the
           Project. If such taxes are assessed or levied against Edison,
           Seller shall pay Edison for such assessment or levy.
      10.3 Seller or Edison shall provide information concerning the Project
           to any requesting taxing authority.
11.   TERMINATION
      This Contract shall terminate if Firm Operation does not occur within 5
      years of the date of Contract execution.
12.   SALE OF GENERATING FACILITY
      12.1 If Seller desires to sell the Generating Facility, Seller shall
           promptly offer to Edison, or any entity designated by Edison in its
           sole discretion, the right to purchase the Generating Facility.
           Edison, or any such entity designated by Edison, shall have up to
           sixty days following the offer to accept Seller's offer or reach
           agreement with Seller.


                               44





    






      12.2 If the Parties are unable to reach a satisfactory agreement
           within sixty days following the offer pursuant to Section 12.1, and
           the Generating Facility is offered to any third party or parties,
           Edison, or any such entity designated by Edison, has the right for
           thirty days following each offer to agree to purchase the
           Generating Facility under the same terms and conditions, if such
           terms and conditions are better to Edison than those offered in
           Section 12.1. Any offers to sell made more than two years after
           Edison's failure to accept a previous offer to sell under Section
           12.1, shall again be subject to the terms of Sections 12.1 and
           12.2.
      12.3 Notwithstanding the foregoing, Seller shall have the right at any
           time to sell or transfer the Generating Facility to an affiliate of
           Seller and an affiliate of Seller may sell, transfer, or lease to
           Seller without giving rise to any right of first refusal of Edison.
           An "affiliate" of Seller shall mean a Party's parent, a Party's
           subsidiary, or any company of which a Party's parent is a parent.
           An "affiliate" of Seller shall also mean a partnership or joint
           venture from which the Seller leases and operates the Generating
           Facility. A "parent" shall mean a company which owns directly or
           indirectly not less than 51% of the shares entitled to vote in an
           election of directors of another company.


                               45





    







13.   ABANDONMENT OF PROJECT
      13.1 The Generating Facility shall be deemed to be abandoned if Seller
           discontinues operation of the Generating Facility with the intent
           that such discontinuation be permanent. Such intent shall be
           conclusively presumed by either (i) Seller's notice to Edison of
           such intent, or (ii) Seller's operation of the Generating Facility
           in such a manner that no Energy is generated therefrom for 200
           consecutive days during any period after Firm Operation of the
           first generating unit, unless otherwise agreed to in writing by the
           Parties. If the Project is prevented from generating Energy due to
           an Uncontrollable Force, then such period shall be extended for the
           duration of the Uncontrollable Force, not to exceed one year.
      13.2 If Seller abandons the Generating Facility during the term of this
           Agreement, Edison, or any entity designated by Edison in its sole
           discretion, shall have the right to purchase the Generating
           Facility pursuant to the provisions of Section 12.
14.   LIABILITY
      14.1 Each Party (First Party) releases the other Party (Second Party),
           its directors, officers, employees and agents from any loss,
           damage, claim, cost, charge, or expense of any kind or nature
           (including any direct, indirect or consequential loss, damage,
           claim, cost, charge, or expense), including attorney's fees and


                               46





    






           other costs of litigation incurred by the First Party, in
           connection with damage to property of the First Party caused by or
           arising out of the Second Party's construction, engineering,
           repair, supervision, inspection, testing, protection, operation,
           maintenance, replacement, reconstruction, use or ownership of its
           facilities, to the extent that such loss, damage, claim, cost,
           charge, or expense is caused by the negligence of Second Party, its
           directors, officers, employees, agents, or any person or entity
           whose negligence would be imputed to Second Party.
      14.2 Each Party shall indemnify and hold harmless the other Party, its
           directors, officers, and employees or agents from and against any
           loss, damage, claim, cost, charge, or expense of any kind or nature
           (including direct, indirect or consequential loss, damage, claim,
           cost, charge, or expense), including attorney's fees and other
           costs of litigation, incurred by the other Party in connection with
           the injury to or death of any person or damage to property of a
           third party arising out of the indemnifying Party's construction,
           engineering, repair, supervision, inspection, testing, protection,
           operation, maintenance, replacement, reconstruction, use, or
           ownership of its facilities, to the extent that such loss, damage,
           claim, cost, charge, or expense is caused by the negligence of the
           indemnifying Party, its directors, officers, employees, agents, or
           any person


                               47




    







           or entity whose negligence would be imputed to the indemnifying
           Party; provided, however, that each Party shall be solely
           responsible for and shall bear all cost of claims brought by its
           contractors or its own employees and shall indemnify and hold
           harmless the other Party for any such costs including costs arising
           out of any workers compensation law. Seller releases and shall
           defend and indemnify Edison from any claim, cost, loss, damage, or
           liability arising from any contrary representation concerning the
           effect of Edison's review of the design, construction, operation,
           or maintenance of the Project.
      14.3 The provisions of this Section 14 shall not be construed so as to
           relieve any insurer of its obligations to pay any insurance claims
           in accordance with the provisions of any valid insurance policy.
      14.4 Neither Party shall be indemnified by the other Party under Section
           14.2 for its liability or loss resulting from its sole negligence
           or willful misconduct.
15.   INSURANCE
      15.1 Until Contract is terminated, Seller shall obtain and maintain in
           force as hereinafter provided comprehensive general liability
           insurance, including contractual liability coverage, with a
           combined single limit of not less than $1,000,000 each occurrence.
           The insurance carrier or carriers and form of policy shall be
           subject to review and approval by Edison.


                               48





    






      15.2 Prior to the date Seller's generating facility first delivers
           electrical energy to the Point of Interconnection, Seller shall (i)
           furnish certificate of insurance to Edison, which certificate shall
           provide that such insurance shall not be terminated nor expire
           except on thirty days prior written notice to Edison, (ii) maintain
           such insurance in effect for so long as Seller's Generating
           Facility is delivering electrical energy to the Point of
           Interconnection, and (iii) furnish to Edison an additional insured
           endorsement with respect to such insurance in substantially the
           following form: "In consideration of the premium charged, Southern
           California Edison Company (Edison) is named as additional insured
           with respect to all liabilities arising out of Seller's use and
           ownership of Seller's Generating Facility.
           "The inclusion of more than one insured under this policy shall not
           operate to impair the rights of one insured against another insured
           and the coverages afforded by this policy will apply as though
           separate policies had been issued to each insured. The inclusion of
           more than one insured will not, however, operate to increase the
           limit of the carrier's liability. Edison will not, by reason of its
           inclusion under this policy, incur liability to the insurance carrier
           for payment of premium for this policy.


                               49










           "Any other insurance carried by Edison which may be applicable
           shall be deemed excess insurance and Seller's insurance primary for
           all purposes despite any conflicting provisions in Seller's policy
           to the contrary."
      15.3 If Seller fails to comply with the provisions of this Section 15,
           Seller shall, at its own cost, defend, indemnify, and hold harmless
           Edison, its directors, officers, employees, agents, assigns, and
           successors in interest from and against any and all loss, damage,
           claim, cost, charge, or expense of any kind or nature (including
           direct, indirect or consequential loss, damage, claim, cost,
           charge, or expense, including attorney's fees and other costs of
           litigation) resulting from the death or injury to any person or
           damage to any property, including the personnel and property of
           Edison, to the extent that Edison would have been protected had
           Seller complied with all of the provisions of this Section 15.
16.   UNCONTROLLABLE FORCES
      16.1 Neither Party shall be considered to be in default in the
           performance of any of the agreements contained in this Contract,
           except for obligations to pay money, when and to the extent failure
           of performance shall be caused by an Uncontrollable Force.
      16.2 If either Party, because of an Uncontrollable Force, is
           rendered wholly or partly unable to perform its


                               50





    






           obligations under this Contract, the Party shall be executed from
           whatever performance is affected by the Uncontrollable Force to the
           extent so affected provided that:
           (1)  The non-performing Party, within two weeks after
                the occurrence of the Uncontrollable Force, gives
                the other Party written notice describing the
                particulars of the occurrence;
           (2)  The suspension of performance is of no greater
                scope and of no longer duration than is required
                by the Uncontrollable Force;
           (3)  The non-performing Party uses its best efforts to
                remedy its inability to perform (this subsection
                shall not require the settlement of any strike,
                walkout, lockout or other labor dispute on terms
                which, in the sole judgment of the party involved
                in the dispute, are contrary to its interest.  It
                is understood and agreed that the settlement of
                strikes, walkouts, lockouts or other labor
                disputes shall be at the sole discretion of the
                Party having the difficulty);
           (4)  When the non-performing Party is able to resume performance of
                its obligations under this Contract, that Party shall give the
                other Party written notice to that effect; and


                               51





    







                (5) Capacity payments during such periods of Uncontrollable
                Force on Seller's part shall be governed by Section 8.1.2.3.
      16.3 In the event that either Party's ability to perform cannot be
           corrected when the Uncontrollable Force is caused by the actions or
           inactions of legislative, judicial or regulatory agencies or other
           proper authority, this Contract may be amended to comply with the
           legal or regulatory change which caused the nonperformance.
           If a loss of Qualifying Facility status occurs due to an
           Uncontrollable Force and Seller fails to make the changes necessary
           to maintain its Qualifying Facility status, the Seller shall
           compensate Edison for any economic detriment incurred by Edison as a
           result of such failure.
17.   NONDEDICATION OF FACILITIES
      Neither Party, by this Contract, dedicates any part of its facilities
      involved in this Project to the public or to the service provided under
      the Contract, and such service shall cease upon termination of the
      Contract.
18.   PRIORITY OF DOCUMENTS
      If there is a conflict between this document and any Appendix, the
      provisions of this document shall govern. Each Party shall notify the
      other immediately upon the determination of the existence of any such
      conflict.


                               52





    







19.   NOTICES AND CORRESPONDENCE
      All notices and correspondence pertaining to this Contract shall be in
      writing and shall be sufficient if delivered in person or sent by
      certified mail, postage prepaid, return receipt requested, to Seller as
      specified in Section 1.1, or to Edison as follows:
                Southern California Edison Company
                Post Office Box 800
                Rosemead, California  91770
                Attention:  Secretary

      All notices sent pursuant to this Section 19 shall be effective when
      received, and each Party shall be entitled to specify as its proper
      address any other address in the United States upon written notice to
      the other Party.
20.   PREVIOUS COMMUNICATIONS
      This Contract contains the entire agreement and understanding between
      the Parties, their agents, and employees as to the subject matter of
      this contract, and merges and supersedes all prior agreements,
      commitments, representations, and discussions between the Parties. No
      Party shall be bound to any other obligations, conditions, or
      representations with respect to the subject matter of this Contract.
21.   THIRD PARTY BENEFICIARIES
      This Contract is for the sole benefit of the Parties and shall not be
      construed as granting any rights to any person or entity other than the
      Parties or imposing obligations on either Party to any person or entity
      other than the Parties.


                               53





    






 22.  NONWAIVER
      None of the provisions of the Contract shall be considered waived by
      either Party except when such waiver is given in writing. The failure of
      either Edison or Seller to insist in any one or more instances upon
      strict performance of any of the provisions of the Contract or to take
      advantage of any of its rights hereunder shall not be construed as a
      waiver of any such provisions or the relinquishment of any such rights
      for the future, but the same shall continue to remain in full force and
      effect.
23.   DISPUTES
      23.1 Any dispute arising between the Parties relating to interpretation
           of the provisions of this Contract or to performance of the Parties
           hereunder, other than matters which may not be settled without the
           consent of an involved insurance company, shall be reduced to
           writing stating the complaint and proposed solution and submitted
           to the appropriate Edison manager, whose interpretation and
           decision thereon shall be incorporated into a written document
           which shall specify Edison's position and that it is the final
           decision of such manager. A copy of such document shall be
           furnished to Seller within ten days following the receipt of
           Seller's written complaint.
      23.2 The decision of such manager pursuant to Section 23.1 shall be
           final and conclusive from the date of receipt of such copy by the
           complaining Party, unless within


                               54




    






           thirty days Seller furnishes a written appeal to such manager.
           Following receipt of such appeal, a joint hearing shall be held
           within fifteen days of said appeal, at which time the Parties shall
           each be afforded an opportunity to present evidence in support of
           their respective positions. Such joint hearing shall be conducted
           by one authorized representative of Seller and one authorized
           representative of Edison and other necessary persons. Pending final
           decision of a dispute hereunder, the Parties shall proceed
           diligently with the performance of their obligations under this
           Contract and in accordance with Edison's position pursuant to
           Section 23.1.
      23.3 The final decision by the Parties' authorized representatives shall
           be made within fifteen days after presentation of all evidence
           affecting the dispute, and shall be reduced to writing. The
           decision shall be final and conclusive.
      23.4 If the authorized representatives cannot reach a final decision
           within the fifteen-day period, any remedies which are provided by
           law may be pursued.
24.   SUCCESSORS AND ASSIGNS
      Neither Party shall voluntarily assign its rights nor delegate its
      duties under this Contract, or any part of such rights or duties,
      without the written consent of the other Party, except in connection
      with the sale or merger of a substantial portion of its properties. Any
      such assignment


                               55





    






      or delegation made without such written consent shall be null and void.
      Consent for assignment shall not be unreasonably withheld. Such
      assignment shall include, unless otherwise specified therein, all of
      Seller's rights to any refunds which might become due under the
      Contract. Seller may assign all or any part of its interest under this
      Contract to a financing institution to facilitate financing for the
      Project by the Seller.
25.   EFFECT OF SECTION HEADINGS
      Section headings appearing in this Agreement are inserted for
      convenience only, and shall not be construed as interpretations of text.
26.   TRANSMISSION
      26.1 Edison shall endeavor to make arrangements with third parties for
           the necessary transmission of the electrical energy from the
           Project to the Point of Interconnection. Seller shall be
           responsible for all costs associated with such transmission of
           electrical energy, including the cost of transmission losses from
           the Project to the Point of Interconnection as determined by Edison
           in its sole judgment.
      26.2 If Edison is unable to secure firm transmission service or
           equivalent arrangements from third parties which are required to
           transmit the electrical energy from the Project to the Point of
           Interconnection at terms and conditions satisfactory to Edison in
           its sole judgment, then Edison shall not be liable to the Seller
           for any


                               56





    






           damages arising from Edison's failure to secure said transmission
           service or arrangements nor will Edison be required to purchase
           Energy which is not delivered or capacity which is not made
           available at the Point of Interconnection.
27.   AMENDMENT
      If at any time during the term of this Agreement a change in
      circumstances not anticipated at the time this Agreement was executed
      significantly alters the rights or obligations of either Party, the
      terms of the Agreement which are directly affected by the change shall
      be amended by mutual agreement of Parties.
28.   GOVERNING LAW
      This Contract shall be interpreted, governed, and construed under the
      laws of the State of California as if executed and to be performed
      wholly within the State of California.
29.   CONFIDENTIALITY
      29.1 Except as provided herein, the Parties shall hold all information
           in this Contract and all information related to or received
           pursuant to this Contract as confidential.
      29.2 Neither Party shall disclose any part nor the whole of this
           Contract to any third party without the express prior written
           consent of the other Party; such consent shall not be unreasonably
           withheld.
      29.3 From time to time governmental and/or regulatory
           agencies may request disclosure of the Contract or


                               57





    







           Contract-related information from either Party or both Parties and
           if such is the case either Party or both Parties may consent to
           such disclosure provided, that (i) the requestor(s) be notified by
           the disclosing Party that the information being released is
           confidential, and that (ii) the disclosing Party inform the other
           Party, in writing, as to the nature of the information disclosed
           and to whom disclosed.

                               58






    






30.   MULTIPLE ORIGINALS
      This Contract is executed in two counterparts, each of which shall be
      deemed an original.
SIGNATURES
      IN WITNESS WHEREOF, the Parties hereto have executed this Contract this
15 of June, 1984.

                               SOUTHERN CALIFORNIA EDISON COMPANY


                               By: /s/ Edward A. Myers, Jr.
                                       Vice President




                               MAGMA ELECTRIC CO.


                               By: /s/ Andrew W. Hoch
                                       Vice President



                               59





    







                               APPENDIX A
                   SOUTHERN CALIFORNIA EDISON COMPANY
                        LONG-TERM STANDARD OFFER
                       CAPACITY PAYMENT SCHEDULE-
               FORECAST OF ANNUAL AS-AVAILABLE CAPACITY1

        Line                            As-Available Capacity2
         No.             Year                      ($/kW-year)
- --------------------------------------------------------------------------


           1             1983                         70

           2             1984                         76

           3             1985                         81

           4             1986                         87

           5             1987                         94

           6             1988                        101

           7             1989                        109

           8             1990                        117

           9             1991                        126

          10             1992                        148

          11             1993                        158

          12             1994                        169

          13             1995                        180

          14             1996                        194

          15             1997                        206

- -------------------------

1     This forecast to be used in conjunction with Capacity Payment
      Option A.

2     The annual as-available capacity ($/kW-yr) will be converted to a
      seasonal time-of-delivery ((cent)/kWh) value that is consistent with
      as-available time-of-delivery rates current authorized by the Commission
      for Avoided As-Available Capacity.



                               A-1





    





                                APPENDIX B
                    SOUTHERN CALIFORNIA EDISON COMPANY
                         LONG-TERM STANDARD OFFER
                         ENERGY PAYMENT SCHEDULE -
                FORECAST OF ANNUAL MARGINAL COST OF ENERGY1

         Line                               Annual Marginal Cost of
          No.             Year               Energy ((cent)/kWh)
- -----------------------------------------------------------------------------

            1             1983                        5.3

            2             1984                        5.6

            3             1985                        5.7

            4             1986                        6.0

            5             1987                        6.4

            6             1988                        6.9

            7             1989                        7.6

            8             1990                        8.1

            9             1991                        8.6

           10             1992                        9.3

           11             1993                       10.1

           12             1994                       10.9

           13             1995                       11.8

           14             1996                       12.6

           15             1997                       13.6

1     This forecast to be used in conjunction with Energy Payment Option
      1.

2     The annual energy payments in the table will be converted to seasonal
      time-of-delivery energy-payment rates that are consistent with the
      time-of-delivery rates currently authorized by the Commission for
      Avoided Energy Cost Payments.


                              B-1





    






                            APPENDIX C
                SOUTHERN CALIFORNIA EDISON COMPANY
        LONG-TERM STANDARD OFFER ENERGY PAYMENT SCHEDULE -
          LEVELIZED FORECAST OF MARGINAL COST OF ENERGY1

                             5-Year
            Initial         Levelized          Levelized
Line        Year of         Forecast           Forecast
No.         Delivery        ((cent)/kWh)      ((cent)/KWh)
- ------------------------------------------------------------------------


   1          1983            5.7                 6.5

   2          1984            6.0                 6.9

   3          1985            6.4                 7.3

   4          1986            6.8                 7.9

   5          1987            7.3                 8.5

   6          1988            7.9                 9.1





- ------------------------

1     Levelized Forecast to be used in conjunction with Energy
      Payment Option 2.

2     The annual energy payments in the table will be converted to seasonal
      time-of-delivery energy payment rates that are consistent with the
      time-of-delivery rates currently authorized by the Commission for
      Avoided Energy Cost Payments.


                              C-1





    
























                          AMENDMENT No. 1

                                TO

                      POWER PURCHASE CONTRACT

                              BETWEEN

                SOUTHERN CALIFORNIA EDISON COMPANY

                                AND

                      MAGMA ELECTRIC COMPANY









    






                        AMENDMENT NO. 1 TO
                  POWER PURCHASE CONTRACT BETWEEN
              SOUTHERN CALIFORNIA EDISON COMPANY AND
                      MAGMA ELECTRIC COMPANY

1.    Parties
      The Parties to this Amendment No. 1 to the Power Purchase Contract
      between Southern California Edison Company and Magma Electric Company,
      executed on June 15, 1984, hereinafter referred to as "Amendment No. 1",
      are Southern California Edison Company, a California corporation,
      hereinafter referred to as "Edison", and Magma Electric Company, a
      Nevada corporation, hereinafter referred to as "Seller", hereinafter
      sometimes referred to individually as "Party" and collectively as
      "Parties".
2.    Recitals
      This Amendment No. 1 is made with reference to the following
      facts, among others:
      2.1  On June 15, 1984, Edison and Seller executed the Power
           Purchase Contract to provide the terms and conditions for the sale
           by Seller and the purchase by Edison of electrical power delivered
           by Seller to Edison at the Point of Interconnection from the 10,000
           kW electrical generating facility, located at Niland, California.
      2.2  The Parties desire to amend the Power Purchase Contract to modify
           the rating of the Seller's generating facility and its expected
           date of firm operation.


                              -1-





    






3.    Agreement
      The Parties agree to the following.

4.    Effective Date
      This Amendment No. 1 shall become effective upon execution
      by the Parties.

5.    Amendment to Section 1.2
      Subparagraph a. in Section 1.2 is deleted in its entirety
      and replaced with the following:
           "a.  Nameplate Rating:  49,000 kW."

6.    Amendment to Section 1.3
      Section 1.3 is deleted in its entirety and replaced with the following:
           "1.3  Contract Capacity:  45,000 kW
               1.3.1  Estimated as-available capacity:  0 kW."

7.    Amendment to Section 1.4
      Section 1.4 is deleted in its entirety and replaced with the following:
           "1.4  Expected Annual Production:  315,360,000 kWh."

8.    Amendment to Section 1.5
      Section 1.5 is deleted in its entirety and replaced with following:
           "1.5  Expected Date of Firm Operation:
                1.5.1 Phase No. 1 (Nameplate Rating:  12,500 kW):
                      December 1, 1986
                1.5.2 Phase No. 2 (Nameplate Rating:  12,500 kW):
                      December 1, 1987
                1.5.3 Phase No. 3 (Nameplate Rating:  12,500 kW):
                      April 1, 1988


                              -2-





    






                      1.5.4    Phase No. 4 (Nameplate Rating:  12,500 kW):
                      December 1, 1988"
9.    Amendment to Section 1.8
      Subparagraph a. to Option B in Section 1.8 is deleted in its
      entirety and replaced with the following:
           "a.  The estimated Contract Capacity Price based on the
      estimated dates of Firm Operation (Firm Capacity) is:
               a.1     Phase No. 1:   $158 per kW-yr.
               a.2     Phase No. 2:   $170 per kW-yr.
               a.3     Phase No. 3:   $184 per kW-yr.
               a.4     Phase No. 4:   $184 per kW-yr.
10.   Amendment to Section 3.1
      The first sentence in Section 3.1 is deleted in its entirety and
      replaced with the following: "The First Period of the Contract Term for
      the project phases, as specified in Section 1.5, shall commence upon
      date of Firm Operation of Phase No. 1 but not later than 5 years from
      the date of execution of this Contract."
11.   Effect of this Amendment No. 1
      Except as amended herein, all terms, covenants and
      conditions contained in the Power Purchase Contract shall
      remain in full force and effect.


                              -3-





    







      12.  Signature Clause
      The signatories hereto represent that they have been
      appropriately authorized to enter into this Amendment No. 1
      on behalf of the Party for whom they sign.  This Amendment
      No. 1 is hereby executed as of this 30 day of November,
      1984.
                               SOUTHERN CALIFORNIA EDISON COMPANY


                               By /s/ Edward A. Myers, Jr.
                                      Vice President


                               MAGMA ELECTRIC COMPANY


                               By /s/ Andrew W. Hoch
                                      Vice President



                              -4-





    
















                          AMENDMENT NO. 2
                                TO
                      POWER PURCHASE CONTRACT
                              BETWEEN
                SOUTHERN CALIFORNIA EDISON COMPANY
                                AND
                      MAGMA ELECTRIC COMPANY








    





                        AMENDMENT NO. 2 TO
                  POWER PURCHASE CONTRACT BETWEEN
              SOUTHERN CALIFORNIA EDISON COMPANY AND
                      MAGMA ELECTRIC COMPANY

1.    Parties
      The Parties to this Amendment No. 2 to the Power Purchase Contract
      between Southern California Edison Company and Magma Electric Company,
      executed on June 15, 1984 ("Power Purchase Contract"), hereinafter
      referred to as "Amendment No. 2", are Southern California Edison
      Company, a California corporation, hereinafter referred to as "Edison",
      and Magma Electric Company, a Nevada corporation, hereinafter referred
      to as "Seller", hereinafter sometimes referred to individually as
      "Party" and collectively as "Parties".
2.    Recitals
      This Amendment No. 2 is made with reference to the following
      facts, among others:
      2.1  On June 15, 1984, Edison and Seller executed the Power
           Purchase Contract to provide the terms and conditions for the sale
           by Seller and the purchase by Edison of electrical power delivered
           by Seller to Edison at the Point of Interconnection from the 10,000
           kW electrical generating facility located at Niland, California.
      2.2  On November 30, 1984, Edison and Seller amended the Power Purchase
           Contract to modify the (i) Nameplate rating, (ii) Contract Capacity
           and Estimated as- available capacity, (iii) Expected Annual
           Production,


                              -1-





    






           (iv) Expected Date of Firm Operation, (v) Estimated Contract
           Capacity Price, and (vi) definition of the First Period of the
           Contract Term as it applies in Section 3.1.
      2.3  Seller is a wholly owned subsidiary of Magma Power
           Company ("Magma").
      2.4  On January 22, 1986, Magma acquired an option to purchase the
           geothermal leaseholds described in and pursuant to the terms and
           conditions contained in the Option to Acquire Adjacent Geothermal
           Leasehold ("Option") among Magma, Imperial Energy Corporation,
           Niland Power, Inc., and Salton Sea Associates.
      2.5  On January 22, 1986, in conjunction with the Option,
           Imperial Energy Corporation assigned to Magma its
           rights, title and interest in the Power Purchase
           Contract between Edison and Imperial Energy
           Corporation, dated February 22, 1984, and amended on
           November 13, 1984 ("Imperial I Contract").  Edison
           consented to such assignment on March 12, 1986.
      2.6  On January 22, 1986, in conjunction with the option,
           Niland Power, Inc., assigned to Magma its rights,
           title, and interest in the Power Purchase Contract
           between Edison and Imperial Energy Corporation, dated
           April 16, 1985, which it acquired from Imperial Energy
           Corporation on September 9, 1985 ("Imperial II
           Contract").  Edison consented to said assignment on
           March 12, 1986.


                              -2-





    






           2.7 On February 10, 1986, Vulcan/BN Geothermal Power Company, of
           which Vulcan Power Company, a wholly owned subsidiary of Magma and
           an affiliate of Seller, is a partner, declared its 29,500 kW
           geothermal project at Niland in firm operation. Based on the
           successful development of its first project at Niland, Magma has
           concluded that its succeeding projects should be duplicates of that
           project.
      2.8  On March 14, 1986, Imperial Energy Corporation, Niland Power, Inc.,
           and Salton Sea Associates assigned to Magma their rights, title and
           interest in those geothermal leaseholds described in and pursuant
           to the terms and conditions contained in the Option.
      2.9  The aforementioned Power Purchase Contracts provide for projects
           which will all be constructed and operated on contiguous sites.
      2.10 Concurrent with this Amendment No. 2, Edison and Magma have agreed
           to amend the Imperial I Contract and Imperial II Contract to
           effectively transfer Capacity to be purchased by Edison from the
           Power Purchase Contract and from Imperial II Contract to Imperial I
           Contract to account for the decrease in Capacity to be produced
           under the Power Purchase Contract.
      2.11 Seller, based on the aforementioned facts, desires to amend the
           Power Purchase Contract to reflect a change in the rating of the
           Seller's Generating Facility.
3.    Agreement
      The Parties agree to the following.


                              -3-





    



4.   Effective Date
      This Amendment No. 2 shall become effective upon execution
      by the Parties.
5.    Amendment to Section 1.2
      5.1  Subparagraph a. in Section 1.2 is deleted in its
           entirety and replaced with the following:
           "a.  Nameplate Rating:  38,000 kW."
      5.2  Add the following subparagraph "d."
           "d.  Generating Facility Designation:  Niland No. 3."
6.    Amendment to Section 1.3
      Section 1.3 is deleted in its entirety and replaced with the following:
           "1.3  Contract Capacity:  34,000 kW.
                 1.3.1  Estimated as-available capacity:  4,000 kW."
7.    Amendment to Section 1.4
      Section 1.4 is deleted in its entirety and replaced with the following:
           "1.4  Expected Annual Production:  238,272,000 kWh."
8.    Amendment to Section 1.5
      Section 1.5 is deleted in its entirety and replaced with the following:
           "l.5  Expected Date of Firm Operation:  June 1, 1989."
9.    Amendment to Section 1.8
      Subparagraph a. to Option B in Section 1.8 is deleted in its
      entirety.


                              -4-





    






      10.  Amendment to Section 3.1
      The first sentence in Section 3.1 is deleted in its entirety and
      replaced with the following:
           "The First Period of the Contract Term shall commence upon date of
           Firm Operation but not later than 5 years from the date of
           execution of this Contract."
11.   Amendment to Section 26
      Section 26 is deleted in its entirety and replaced with the following:
           "Seller shall be solely responsible, using all reasonable efforts,
           to negotiate and conclude all required transmission and
           interconnection agreements with the Interconnecting Utility. Such
           agreements shall provide for the transmission of electrical energy
           generated by the Generating Facility to the Point of
           Interconnection."
12.   Effect of this Amendment No. 2
      Except as amended herein, all terms, covenants and
      conditions contained in the Power Purchase Contract shall
      remain in full force and effect.

                              -5-





    









13.   Signature Clause
      The signatories hereto represent that they have been
      appropriately authorized to enter into this Amendment No. 2
      on the behalf of the Party for whom they sign.  This
      Amendment No. 2 is hereby executed as of this 10 day of
      April, 1985.

                               SOUTHERN CALIFORNIA EDISON COMPANY


                                     By /s/ EDWARD A. MYERS, JR.
                                            Vice President




                               MAGMA ELECTRIC COMPANY



                                   By /s/ ANDREW W. HOCH
                                          Vice President


                              -6-