EXHIBIT 99.1
                                                                   ------------

- -------------------------------------------------------------------------------

[GRAPHICS OMITTED - LOGO, PHOTOGRAPHS]

- ---------------
  News Release        -------------       ---------------     ------------
                        Discipline          Opportunity         Strategy

- -------------------------------------------------------------------------------



                  CANADIAN NATURAL RESOURCES LIMITED ANNOUNCES
                 FOURTH QUARTER 2007 UPDATE ON THE PROGRESS OF
                         THE HORIZON OIL SANDS PROJECT
          CALGARY, ALBERTA - FEBRUARY 12, 2008 - FOR IMMEDIATE RELEASE


Canadian Natural Resources Limited  ("Canadian  Natural") is pleased to provide
its  regular  quarterly  update  on the  Horizon  Oil Sands  Project  ("Horizon
Project").

Commenting on fourth quarter  progress on the Horizon Oil Sands  Project,  Real
Doucet,  Sr. Vice President,  Oil Sands stated,  "We achieved 90% completion of
the Horizon Project by year-end 2007, a major accomplishment,  which remains on
track for first oil in the third quarter of 2008. The remaining  10%,  however,
is in many ways the toughest as it is the most labour intensive  portion of the
Horizon  Project.  Unfortunately,  mid to late January and early February saw a
significant  deterioration in labour  productivity on the construction  site as
much colder than normal weather seriously curtailed activity.  The weather also
affected the commissioning schedule of certain plants; however, at present this
is not expected to have any impact on our targeted completion of Phase 1."

"As of December 31, 2007 our forecasted total costs of the Horizon Project were
at 13.4%  over our $6.8  billion  Board  of  Directors  authorization.  We just
completed  a  thorough  review  of  the  productivity  that  we  have  recently
experienced at the Horizon Project  construction  site and have determined that
should no improvements  in  productivity  be achieved  through the remainder of
construction,  then the cost estimate for Phase 1 of the Horizon  Project would
need  to  be  increased  to  28%  above  the   original   $6.8  billion   Board
authorization.  If we can regain targeted labour efficiencies and productivity,
this overage  could be reduced to  approximately  25% above the  original  $6.8
billion Board authorization. This range of outcomes will result in an on-stream
cost of less than  $80,000  bbl/d of  capacity,  including  the benefits of the
significant pre-build capital invested for Phase 2/3.

In the fourth quarter of 2007, we reached many significant milestones including
completion  of the tailings  pond,  filling of the raw water pond and preparing
two tanks to receive  start-up diluent in January.  We have  experienced  minor
slippage in certain  non-critical  path plants where mechanical  completion has
moved from the end of the second quarter to early in the third quarter - having
no expected impact however on targeted  Project  completion.  Our critical path
plants,  Delayed Coker / Diluent Recovery Unit and Hydrotreater remain on track
for first oil in the third quarter of this year.

In parallel with completing major systems, we are getting ready for operations.
Our rate of operations hiring and training has gained significant momentum with
100%  of  Mining,  89% of  Bitumen  Extraction,  80% of  Upgrading  and  76% of
Utilities and Offsites  staffing  requirements  hired to date. We have also now
awarded all of the maintenance  contracts,  with these contractors  immediately
mobilizing to site in the last part of the fourth quarter of 2007.

We remain  focused  on timely  completion  of Phase 1, while  getting  ready to
operate the new facilities. Meanwhile, following Board authorization to proceed
with  Tranche  2 of our next  expansion,  we were  immediately  able to award a
contract for an  additional  Ore Prep Plant to an existing  contractor  that is
performing  well.  In  addition,  other  long lead  equipment  (Coke  Drums and
Reactors)  for Phase 2/3 will be delivered to site during the first  quarter of
2008, as we look forward to successful  construction  and  completion of future
phases."




                                                                         Page 2
- -------------------------------------------------------------------------------


PROJECT STATUS SUMMARY



                                             SEPTEMBER 30, 2007            DECEMBER 31, 2007           MARCH 31, 2008
                                             ------------------            -----------------           --------------
                                                                                 Q4/07    Original    Q1/08   Original
                                                   ACTUAL            ACTUAL     FORECAST    PLAN     FORECAST   PLAN
                                                   ------            ------     --------    ----     --------   ----

                                                                                               
Phase 1 - Work progress (cumulative)                 84%               90%         90%       94%       95%       97%

Phase 1 - Construction capital spending*             89%               99%         99%       92%      110%       97%
(cumulative)


*Relative to overall Phase 1 project capital of $6.8 billion

ACCOMPLISHED TO THE END OF THE FOURTH QUARTER OF 2007

DETAILED ENGINEERING
o Overall detailed  engineering  98.5% complete and  substantially  complete in
  most areas.

PROCUREMENT
o Overall procurement progress is 99% complete.
o Awarded over $5.6 billion in purchase orders and contracts to date.
o Only one significant  contract remains to be awarded for Phase 1 - mechanical
  for  Sulphur  Blocking.
o Commenced receipt and site assembly of Mine Operations Equipment (Shovels and
  Heavy Haul Trucks).
o Operations and maintenance service and supply agreements have been awarded.

MODULARIZATION
o Delivered  an  additional  54  oversized  loads  to site for a total of 1,560
  loads,  representing  approximately 94% of the total  requirement.  Remaining
  deliveries  consist  primarily  of the  balance of required  Mine  Operations
  Equipment (Shovels and Heavy Haul Trucks).

CONSTRUCTION
o Overall construction progress is 85% complete.
o Mine  overburden  removal has moved 49.9  million  bank cubic  meters,  which
  represents approximately 72% of the total to be moved and is 0.6 million bank
  cubic meters ahead of schedule.
o Main Control Room Distributed Control Systems equipment powered and tested.
o Commissioned 260kV Transmission line and turned over to operations.
o Commissioned Raw Water Pumphouse and turned over to operations.
o Completed reformer erection in Hydrogen Plant.
o Completed installation and pre-commissioning of CPI Separator Building.
o Completed the closure of Dyke 10 (external tailings pond) in Mining.
o Completed erection of Crushing Plants and conveyors in Ore Preparation Area.
o Completed Primary Separation Cells in Extraction.
o Completed construction of Main Laboratory.

MILESTONES FOR THE FIRST QUARTER OF 2008

o Mechanically Complete Extraction Plant.
o Mechanically Complete Froth Treatment Plant.
o Mechanically Complete Amine Plant.
o Complete Auxiliary Boiler installation in Cogeneration.
o Complete Piping in Heat Integration.




                                                                         Page 3
- -------------------------------------------------------------------------------


PLANT AND SYSTEM COMMISSIONING SCHEDULE

COMPLETED
  o  Permanent Potable Water Treatment
  o  Permanent Sewage Treatment
  o  Natural Gas Pipeline
  o  Raw and Recycled Water Pipelines
  o  River Water Intake and Pumphouse
  o  Raw Water Pond and Pumphouse
  o  Recycle Water Pond and Pumphouse
  o  Electrical Distribution System

Q1 2008
  o  Tanks 11 and 12 completed for early diluent fill
  o  Main Piperack
  o  Instrument and Utility Air System
  o  Flare System

Q2 2008
  o  Cogeneration
  o  Cooling and Heating
  o  Delayed Coker / Diluent Recovery Unit
  o  Gas Treating and Sulphur Recovery
  o  West Tank Farm (inter plant)
  o  Sulphur Block Pipelines
  o  Synthetic Crude Oil Pipeline

Q3 2008
  o  Ore Preparation Plant
  o  Extraction
  o  Froth Treatment
  o  Pipeline Corridors
  o  Hydrogen Plant
  o  Hydrotreater
  o  East Tank Farm (product)

A  picture  gallery  providing  visual  updates  on  construction  progress  is
available on the Company's website
(HTTP://WWW.CNRL.COM/HORIZON/ABOUT_HORIZON/PHOTO_GALLERY.HTML).

CONFERENCE CALL
A conference call will be held at 7:30 a.m.  Mountain Time,  9:30 a.m.  Eastern
Time on Tuesday,  February 12, 2008. The North American  conference call number
is  1-866-540-8136  and the outside North  American  conference  call number is
001-416-340-8010.  Please call in about 10 minutes  before the starting time in
order to be patched into the call. The  conference  call will also be broadcast
live on the internet and may be accessed  through the Canadian  Natural website
at WWW.CNRL.COM.

A taped rebroadcast will be available until 6:00 p.m.  Mountain Time,  Tuesday,
February  19,   2008.   To  access  the   postview  in  North   America,   dial
1-800-408-3053.  Those outside of North  America,  dial  001-416-695-5800.  The
passcode to use is 3252546.




                                                                         Page 4
- -------------------------------------------------------------------------------


WEBCAST
This call is being  webcast by Vcall and can be accessed on Canadian  Natural's
website at WWW.CNRL.COM/INVESTOR_INFO/CALENDAR.HTML.

The webcast is also being distributed over PrecisionIR's  Investor Distribution
Network to both institutional and individual investors. Investors can listen to
the call through  www.vcall.com  or by visiting  any of the  investor  sites in
PrecisionIR's Individual Investor Network.

2007 FOURTH QUARTER RESULTS
The  Company's  results  for the  fourth  quarter of 2007 will be  released  on
February  28,  2008.  A  conference  call will be held on that day at 9:00 a.m.
Mountain Time, 11:00 a.m. Eastern Time.

Canadian  Natural is a senior oil and  natural  gas  production  company,  with
continuing  operations  in its core areas located in Western  Canada,  the U.K.
portion of the North Sea and Offshore West Africa.




                                                                         Page 5
- -------------------------------------------------------------------------------


FORWARD-LOOKING STATEMENTS

Certain  statements  in this  document  or  documents  incorporated  herein  by
reference for Canadian  Natural  Resources  Limited (the "Company")  constitute
"forward-looking  statements"  within the meaning of the United States  Private
Securities Litigation Reform Act of 1995. These forward-looking  statements can
generally  be  identified  as such  because of the  context  of the  statements
including  words  such as the  Company  "believes",  "anticipates",  "expects",
"plans", "estimates", "targets", or words of a similar nature.

The  forward-looking  statements  are  based on  current  expectations  and are
subject to known and unknown  risks,  uncertainties  and other factors that may
cause the actual  results,  performance  or  achievements  of the  Company,  or
industry  results,  to  be  materially   different  from  any  future  results,
performance  or  achievements  expressed  or  implied  by such  forward-looking
statements.  Such factors include,  among others: general economic and business
conditions which will, among other things,  impact demand for and market prices
of the Company's products; foreign currency exchange rates; economic conditions
in the countries and regions in which the Company conducts business;  political
uncertainty,  including actions of or against  terrorists,  insurgent groups or
other conflict including conflict between states; industry capacity; ability of
the Company to  implement  its business  strategy,  including  exploration  and
development  activities;  impact  of  competition;  availability  and  cost  of
seismic,  drilling and other equipment;  ability of the Company to complete its
capital  programs;  ability of the Company to transport its products to market;
potential delays or changes in plans with respect to exploration or development
projects  or  capital  expenditures;  ability of the  Company  to  attract  the
necessary  labour required to build its projects;  operating  hazards and other
difficulties  inherent in the  exploration for and production and sale of crude
oil and natural gas; availability and cost of financing; success of exploration
and development activities;  timing and success of integrating the business and
operations of acquired  companies;  production  levels;  uncertainty of reserve
estimates; actions by governmental authorities;  government regulations and the
expenditures  required to comply with them (especially safety and environmental
laws and regulations);  asset retirement  obligations;  and other circumstances
affecting  revenues  and  expenses.  Our  domestic  operations  are  subject to
governmental risks that may impact our operations. Our domestic operations have
been, and at times in the future may be affected by political  developments and
by federal,  provincial and local laws and regulations  such as restrictions on
production,   changes  in  taxes,   royalties  and  other  amounts  payable  to
governments  or  governmental  agencies,  price or gathering  rate controls and
environmental  protection  regulations.  The  impact  of any  one  factor  on a
particular forward-looking statement is not determinable with certainty as such
factors are  interdependent  upon other  factors,  and the Company's  course of
action  would  depend  upon  its  assessment  of  the  future  considering  all
information then available.

Statements  relating to "reserves" are deemed to be forward-looking  statements
as  they  involve  the  implied  assessment  based  on  certain  estimates  and
assumptions  that the  reserves  described  can be  profitably  produced in the
future.

Readers are  cautioned  that the  foregoing  list of  important  factors is not
exhaustive. Although the Company believes that the expectations conveyed by the
forward-looking  statements are reasonable based on information available to it
on the date such  forward-looking  statements  are made, no  assurances  can be
given as to future results, levels of activity and achievements. All subsequent
forward-looking  statements,  whether  written  or  oral,  attributable  to the
Company  or  persons  acting on its behalf  are  expressly  qualified  in their
entirety by these cautionary statements. Except as required by law, the Company
assumes no obligation to update forward-looking statements should circumstances
or Management's estimates or opinions change.


For further information, please contact:


CANADIAN NATURAL RESOURCES LIMITED
2500, 855 - 2nd Street S.W.
Calgary, Alberta
T2P 4J8

TELEPHONE:      (403) 514-7777                   ALLAN P. MARKIN
FACSIMILE:      (403) 514-7888                   Chairman
EMAIL:          IR@CNRL.COM
WEBSITE:        WWW.CNRL.COM                     JOHN G. LANGILLE
                                                 Vice-Chairman

TRADING SYMBOL - CNQ                             STEVE W. LAUT
Toronto Stock Exchange                           President &
New York Stock Exchange                          Chief Operating Officer

                                                 DOUGLAS A. PROLL
                                                 Chief Financial Officer &
                                                 Senior Vice-President, Finance

                                                 COREY B. BIEBER
                                                 Vice-President,
                                                 Finance & Investor Relations