1
                                                                 EXHIBIT 10.25


         [PORTIONS OF THIS DOCUMENT HAVE BEEN OMITTED PURSUANT TO AN
         APPLICATION FOR AN ORDER FOR CONFIDENTIAL TREATMENT REQUESTED BY
         CARNIVAL CORPORATION]





                            SHIPBUILDING CONTRACT
                                      
                             FOR HULL NO. 491 AT
                           KVAERNER MASA-YARDS INC
                                --------------





                          Sinclair Roche & Temperley
   2


                            SHIPBUILDING CONTRACT



Between, CARNIVAL CORPORATION., a company organized and existing under the laws
of the Republic of Panama with its principal offices located at 3655 N.W. 87th
Avenue, Miami, Florida, USA 33178 - 2428 hereinafter called the "PURCHASER",

and

KVAERNER MASA-YARDS, INC., a company organized and existing under the laws of
the Republic of Finland with a registered office in Helsinki, Finland
hereinafter called the "CONTRACTOR",

In respect of yard No.491 :

WHEREAS

(i)      By a contract dated 15th September 1987 made between Wartsila Marine
         Industries Inc. ("WMI") and the PURCHASER, WMI agreed to design, build
         and deliver to the PURCHASER a passenger cruise vessel known as hull
         no. 1299 (and following the contract referred to in recital (ii) as
         480 at the yard of the CONTRACTOR) and after delivery named ms
         "ECSTASY".

(ii)     By an agreement dated 25th January 1990 the CONTRACTOR agreed to
         complete ms "ECSTASY" following the bankruptcy of WMI and has
         delivered ms "ECSTASY" to the PURCHASER.

(iii)    By a contract dated 15th September 1987 WMI agreed to design, build
         and deliver to the PURCHASER a further passenger cruise vessel known
         as hull no. 1300 to be named MS "SENSATION" and by a contract dated
         12th May 1991 between the CONTRACTOR and the PURCHASER the CONTRACTOR
         agreed to complete the construction of ms "SENSATION" (as Hull no.
         484) on the terms set out therein.

(iv)     By a further contract dated  5th September 1991 the CONTRACTOR agreed
         to design build and deliver to the PURCHASER a further passenger
         cruise vessel to be known during construction as Hull 487 and on
         delivery to be named ms "FASCINATION".

(v)      By a further contract dated 25 March 1992 the CONTRACTOR agreed to
         design, build and deliver to the PURCHASER a further passenger cruise
         vessel to be known during construction as Hull 488 and on delivery to
         be named "IMAGINATION".

(vi)     By a further contract dated  23 December 1993 the CONTRACTOR agreed to
         design, build and deliver to the PURCHASER  a further passenger cruise
         vessel to be known during construction as Hull 489 and on delivery to
         be named "INSPIRATION".
   3


(vii)    This agreement sets out the terms on which the CONTRACTOR will design
         and build for the PURCHASER a further passenger cruise ship to be
         known during construction as Hull 491.


IT IS HEREBY AGREED AND STIPULATED AS FOLLOWS:


ARTICLE 1:       SUBJECT OF THE CONTRACT


(A)      VESSEL'S Description and Main Characteristics

The CONTRACTOR undertakes to design and build and complete at the Building Site
(as hereinafter defined) and to deliver to the PURCHASER, who orders and
undertakes to accept delivery of one passenger cruise ship (hereinafter called
the "VESSEL"), which will be a "carbon-copy" sistership to MS "IMAGINATION",
hull No. 488 as built except that modifications shall be made:-

1.       as required to ensure that the VESSEL complies with the laws, rules,
         regulations and enactments referred to in paragraph (E) of this
         Article 1.

2.       as required to ensure that the VESSEL is a repeat of m.s.
         "IMAGINATION" (Hull 488) except that the PURCHASER has the freedom to
         make decorative changes as in previous ships ordered from the
         CONTRACTOR, it being understood that the quality, standard and finish
         of such decorative changes will be the same as m.s. "IMAGINATION"
         (Hull 488), it being understood that such decorative changes will not
         make the building cost higher.  All alterations agreed in regard to
         Hull 488 to  the date of November 10, 1994 will be incorporated in the
         VESSEL without any cost additional to the purchase price specified
         herein.

The specifications and plans for MS "FASCINATION" as built (modified in
accordance with the foregoing provisions of this paragraph (A) and the
provisions referred to in paragraph (E) of this Article 1) shall hereinafter be
referred to as the "SPECIFICATIONS" and the "PLAN" respectively.  Drawings and
specifications for public areas will be agreed within the timetable set out in
the Addendum to this CONTRACT of even date herewith and initialled on behalf of
the CONTRACTOR and the PURCHASER.

Regarding the Makers List, the CONTRACTOR is entitled to make changes as
compared with MS "FASCINATION".  The changes will be submitted for technical
approval by the PURCHASER.  Such approval shall not be withheld, if the
relevant characteristics of the Specification are fulfilled, and the reputation
of the supplier is acceptable to the PURCHASER.





                                      3
   4

         [MARKED TEXT OMITTED PURSUANT TO AN APPLICATION FOR AN ORDER FOR
         CONFIDENTIAL TREATMENT BY CARNIVAL CORPORATION]


In the event of any conflict between this CONTRACT and the SPECIFICATIONS and
the PLAN, the provisions of this CONTRACT shall prevail.  In the event of any
conflict between the SPECIFICATIONS and the PLAN, the provisions of the
SPECIFICATIONS shall prevail.

(B)      Speed

The VESSEL's speed shall be as follows:-

         -    (a)         Trial Speed
                          With the propulsion motors
                          developing each XXXXX at about XXX
                          RPM and at XXXX Meter draft and
                          other conditions as per paragraph
                          XXXXX of the SPECIFICATIONS: XXXX
                          knots

         -    (b)         Service Speed
                          With X diesel alternators 8ZAL40S
                          and X diesel alternators
                          12ZAV40S developing a total output
                          not exceeding XXXX percent MCR, at
                          XXX RPM, and after allowing XXX MW
                          for the VESSEL'S other electrical
                          services, the residual power shall
                          enable the VESSEL to reach XXXX
                          knots with a margin of XX percent,
                          at a draught of XXXXm.


(C)      Building Site

The Building Site shall be the CONTRACTOR's shipyard at Helsinki, Finland
provided that the CONTRACTOR may have parts of the VESSEL constructed at its
yard at Turku.  The CONTRACTOR shall nevertheless be at liberty to carry out
work elsewhere provided that the main work of erection, assembly and
construction of the VESSEL shall take place at the Building Site aforesaid.

(D)      Yard Number, Marking of Materials

The VESSEL shall, for the purpose of identification only be known as Yard
No.491.





                                      4
   5




As soon as possible after the arrival at the Building Site, all materials,
machinery and other equipment intended to be incorporated in the VESSEL shall
be marked with the above Yard Number for the purpose of identification and
establishing that such materials, machinery and equipment belong to the VESSEL.
The CONTRACTOR may not use any such marked material, machinery, and equipment
for the construction of any other vessel without the approval of the PURCHASER,
such approval not to be unreasonably withheld.  The CONTRACTOR may not use for
the construction of the VESSEL materials, machinery and other equipment marked
for use in the construction of any other vessel without the approval of the
PURCHASER, such approval not to be unreasonably withheld.

The CONTRACTOR is obliged to pay all deliveries promptly on or before delivery.
Upon the PURCHASER'S request, the CONTRACTOR shall supply proof of payment
having been properly effected as well as further evidence that it is under no
residual obligations towards its suppliers in respect of other deliveries.

(E)      VESSEL'S Classification and Standard

The VESSEL shall comply with the laws, rules, regulations and enactments
published and in force on the date hereof as stated in the SPECIFICATIONS,
including also Stability Regulations for Passenger Vessels (April 1990) and
Fire Protection for Lifeboats and Rafts in way of windows and screens (SOLAS
74, as amended) to the requirements of the Classification Society and the
Panamanian Government.  The Vessel shall also comply with the requirements of
the following:

1.       U.S.P.H including "Vessel Sanitation Programme - Operation Manual
         (edition August 1989) and W.H.O "Guide to Ship Sanitation"; and

2.       SOLAS Regulations and Wireless in relation to Global Marine Distress
         Signal Systems; and

3.       Panamanian Government regulations for registration of vessels under
         Panamanian flag.  The VESSEL shall be built to class and under survey
         of Lloyd's Register of Shipping and, if not otherwise stated in the
         SPECIFICATIONS, in accordance with good shipbuilding practice in
         Scandinavia for new passenger cruise vessels of the type and general
         characteristics and in any event in no respect inferior to the
         standards of M.S. "FASCINATION" as built. Classification, survey and 
         testing and any other charges relating to the CONTRACTOR'S 
         obligations and items of supply under this CONTRACT shall be for the 
         account of the CONTRACTOR.

         It is understood that the CONTRACTOR shall carry out such work as is
         necessary in accordance with this CONTRACT so that the VESSEL on
         arrival in the U.S.A is approved by the United States Public Health
         authorities.





                                      5
   6

(F)      Decisions of the Classification Society

The decisions of Lloyds Register of Shipping the ("Classification Society")
shall be final and binding on both contracting parties as to the VESSEL'S
compliance or non-compliance with the rules and regulations, observance of
which is to be controlled by the said Society.

(G)      Sub-contracting

Subject to the requirements of Article 1(A) the CONTRACTOR has the right to
sub-contract part of the work to third parties on the Building Site or
elsewhere.

                                         
ARTICLE 2:       INSPECTION AND APPROVALS


(A)      Inspection

The PURCHASER shall have the right to have the VESSEL and all engines,
machinery, outfit and equipment intended for her inspected during construction
by its authorized representative(s) to whom the CONTRACTOR shall grant free
access for such purpose during working hours to the VESSEL and to the
CONTRACTOR'S shipyard and workshops wherever the VESSEL is being built and/or
designed.  The CONTRACTOR will obtain for the PURCHASER the right of access to
subcontractors' premises.  The inspection will be at the PURCHASER's risk and
expense.

The PURCHASER'S authorized representative(s) whose name(s) and duties are to be
made known in advance, shall observe the works' rules prevailing at the
CONTRACTOR'S and the subcontractors' premises.  They shall address their
remarks exclusively to the CONTRACTOR'S appointed representative(s) whose
name(s) shall be made known to the PURCHASER.

Should the PURCHASER elect to entrust the inspection to firms or persons
outside its organisation, such firms or persons and their duties shall be
subject to the CONTRACTOR'S prior approval.

(B)      Effect of Approvals

Approval by the PURCHASER or the PURCHASER'S representative of inspections,
tests, trials, documents, or plans shall not relieve the CONTRACTOR of its
obligations under Article 1 of this CONTRACT.





                                      6
   7


ARTICLE 3:       MODIFICATIONS


(A)      Modifications

Either party may request the other in writing to make modifications to the
SPECIFICATIONS and/or PLAN and provided that the CONTRACTOR and the PURCHASER
fully agree in writing within ten days from the dispatch of the CONTRACTOR'S
notification of any (a) appropriate adjustment of price, (b) appropriate
adjustment of delivery date; (c) appropriate adjustment of the deadweight; (d)
appropriate adjustment of speed requirements; and (e) any other appropriate
adjustment of this CONTRACT, the SPECIFICATIONS and the PLAN, the CONTRACTOR
will carry out such modifications.

The CONTRACTOR has the right to continue production on the basis of the
SPECIFICATIONS and the PLAN until agreement has been reached as above stated.

All agreed modifications and alterations shall be subject to the conditions of
this CONTRACT and the SPECIFICATIONS.

(B)      Modifications by Regulatory Bodies and Classification Society

In the event that subsequent to the date hereof any modifications, deletions or
additions are made to the laws, rules, regulations and enactments applicable to
the VESSEL or their interpretation or their application (including withdrawal
of provisional approvals of the Classification Society and/or additional
requirements of said Society) as compared with the basis of this CONTRACT
and/or similar measures of other bodies as referred to in Article 1, paragraph
(E), and such modifications, deletions or additions are compulsory for the
VESSEL, the CONTRACTOR will effect them and will notify the (a) adjustment of
price; (b) adjustment of delivery date; (c) adjustment of deadweight; (d)
adjustment of speed requirements; and (e) any other adjustment of the CONTRACT,
SPECIFICATIONS and PLAN, all as may be appropriate in the circumstances.

The PURCHASER may require that the CONTRACTOR shall first apply for a formal
waiver of compliance with such modifications, deletions or additions from the
authority by whom the modifications, deletions or additions have been
promulgated, should the PURCHASER consider that the operation of the VESSEL in
its intended service would permit of such waiver.  In such agreement the
CONTRACTOR will fix a reasonable time limit after which if the waiver has not
been obtained, the CONTRACTOR will go on with the required modifications,
deletions or additions.  Any additional cost caused by the application for such
waiver whether or not obtained shall be for account of the PURCHASER and the
date of delivery of the VESSEL if actually delayed thereby shall be extended by
the time necessary as a result of the application for waiver.





                                      7
   8

Modifications by regulatory bodies and by the Classification Society which are
not compulsory for the VESSEL shall be treated as the PURCHASER'S modifications
according to paragraph (A) above but the CONTRACTOR will in any case advise the
PURCHASER of such modifications as soon as they are published and obtain the
PURCHASER'S approval in writing before proceeding to make such modifications.

(C)      Payment of Adjustments of Price

The adjustments of price made under paragraphs (A) and (B) above shall be
settled in accordance with paragraph (D) of Article 7.

(D)      Information

When required the CONTRACTOR shall furnish reasonable information relating to
the basis and method of determining any adjustment of price and other effects
of modifications referred to in this Article.


ARTICLE 4:       TRIALS


The VESSEL shall run the following tests and trials:

         (1)     Dock trials as specified in the SPECIFICATIONS.

         (2)     Official sea-trials as provided for in the SPECIFICATIONS
                 during which the trial speed, the propulsion machinery plant
                 output and the propeller revolutions shall be determined in
                 accordance with Article 1, paragraph (B)(a).

                 An endurance test as well as all other trials and tests
                 included in the sea trial program in the SPECIFICATIONS, shall
                 also be carried out with recording of measurements of all
                 parameters, enabling determination of performance relevant to
                 each test.

         (3)     All other trials specified in the SPECIFICATIONS.

Such speed runs and endurance test shall be run at the draft attainable by
ballasting the VESSEL with ballast water using tanks and compartments intended
for this purpose and as far as practicable the draft shall be as close as
possible to the corresponding draft at which tank model tests have been carried
out.

Should the speed trial draft aforementioned be other than the draft specified
in Article 1(B)(a), the speed, the main engine output and the revolutions
corresponding to the latter draft shall be





                                      8
   9

determined by the Netherlands Model Basin in Wageningen by means of data from
their model tests on the basis of the results recorded at the sea trials.

All trials and measurements will be conducted in a manner and to an extent as
prescribed in a detailed schedule based on the SPECIFICATIONS.

The methods to be used will be selected by the CONTRACTOR to suit the VESSEL'S
trial trip programme to the approval of the PURCHASER.

The CONTRACTOR has the right to subcontract speed and power measurements to an
independent model basin or research institute.  However, the PURCHASER will be
kept fully informed and allowed to observe and ascertain measurements recorded
during the trials as if the CONTRACTOR had carried out the tests with its own
personnel.

Should conditions which properly qualify to delay delivery as provided in
Article 6  paragraph (D) prevent the CONTRACTOR from carrying out properly the
official  trial on the day scheduled therefor, the CONTRACTOR has the right to
postpone the trial or such part of it as deemed necessary.  In such case the
CONTRACTOR shall be entitled to an extension of the VESSEL'S delivery time
covering the whole period of postponement.

The CONTRACTOR shall have the right to repeat any trial whatsoever after giving
reasonable notice to the PURCHASER.

All expenses for the trials and adjustments of all the VESSEL'S equipment shall
be borne by the CONTRACTOR who during the sea trials will provide the necessary
crew at its own expense.  If, during any sea trial, any breakdowns occur
entailing interruption or irregular performance which can be repaired by the
normal means available on board, the trial shall be continued after repairs and
be valid in all respects.

However, should the VESSEL require to return to a port to enable the breakdown
to be remedied, a further trial shall be undertaken, if necessary at sea, to
prove the outstanding performance and complete demonstrations.

The CONTRACTOR shall give the PURCHASER thirty days notice of the anticipated
date of the first sea trials.

Within seven (7) days from the completion of the sea trial or the above further
trial, the CONTRACTOR shall present the PURCHASER with a full set of results of
the tests carried out during the sea trials and the PURCHASER shall give the
CONTRACTOR within 3 days from the receipt of the results a notice in writing,
or by telex or telefax confirmed in writing, of completion and acceptance of
the trial run, advising whether the PURCHASER considers that the results of the
trial run indicate conformity of the VESSEL to this Contract the SPECIFICATIONS
and the PLAN.





                                      9
   10

In the event that the PURCHASER rejects the results of the trial run as not
conforming to this CONTRACT or to the SPECIFICATIONS or the PLAN, the PURCHASER
shall indicate in its notice of rejection in what respect the VESSEL, or any
part or equipment thereof, does not conform to this CONTRACT and/or the
SPECIFICATIONS.

In the event that the PURCHASER fails to notify the CONTRACTOR as aforesaid of
the acceptance of or the rejection, together with the reason therefor, of the
trial within the period as provided above, the PURCHASER shall be deemed to
have accepted the trial run of the VESSEL.

Acceptance of the results of the trial run as above provided shall be final and
binding so far as conformity of the VESSEL to the CONTRACT and the
SPECIFICATIONS and the PLAN to the extent demonstrated on such trial is
concerned and shall preclude the PURCHASER from refusing formal delivery of the
VESSEL as hereinafter provided, on the grounds of non conformity of the VESSEL
in respect of items whose conformity has been demonstrated and accepted during
the trial run, if the CONTRACTOR complies with all other requirements for
delivery as provided in this CONTRACT.

Should any fuel oil lubricating oil, greases and ship's stores, including fresh
water furnished by the CONTRACTOR for the sea trial remain on board the VESSEL
at the time of acceptance thereof by the PURCHASER, the PURCHASER agrees to buy
the same from the CONTRACTOR at the price reasonably paid by the CONTRACTOR and
evidenced by invoices of the supplier and payment by the PURCHASER shall be
effected in accordance with paragraph (D) of Article 7.


ARTICLE 5:       GUARANTEE FOR SPEED, DEADWEIGHT AND FUEL
                 CONSUMPTION


Subject to the provision contained in Article 7 (E) the rights and obligations
of the CONTRACTOR and PURCHASER in regard of the VESSEL'S trial speed,
deadweight and consumption of fuel of the propulsion plant are delimited as
follows:

(A)      Speed

For the purpose of determining the VESSEL'S actual trial speed, the speed of
the VESSEL recorded on the official sea trials under Article 4 shall be
adjusted in accordance with Article 4 as if the official sea trials had been
carried out under the conditions specified in Article 1, paragraph (B)(a) and
paragraph 1.2.6 of the SPECIFICATIONS.  If the actual trial speed so computed
is less than the adjusted trial speed under Article 1, paragraph (B)(a), the
CONTRACTOR shall pay to the PURCHASER as liquidated damages and not by way of
penalty the following amounts:





                                      10
   11

         [MARKED TEXT OMITTED PURSUANT TO AN APPLICATION FOR AN ORDER FOR
         CONFIDENTIAL TREATMENT BY CARNIVAL CORPORATION]



- -        for the first two tenths (2/10ths) of a knot of such speed deficiency:
         XXXXXXX

- -        U.S.$XXXXXX for the third complete tenth of one knot deficiency and
         that amount increased by U.S.$XXXXXX for each successive complete one
         tenth of a knot of such deficiency, save and except that the
         CONTRACTOR shall have the right to remedy the deficiency and repeat
         the trial.

If the VESSEL'S trial speed determined or computed as provided in this
paragraph (A) is more than one knot below the adjusted trial speed under
Article 1, paragraph (B)(a), the PURCHASER, as an alternative to receiving the
above mentioned liquidated damages, shall have the option to terminate this
CONTRACT, with the consequences provided for in Article 8 and Article 11, save
and except that the CONTRACTOR shall have the right to remedy the deficiency
and repeat the trial.

Should the actual trial speed of the VESSEL determined or computed as provided
in this paragraph (A) be greater than the adjusted trial speed under Article 1,
paragraph (B)(a), the PURCHASER shall pay to the CONTRACTOR as premiums the
following amounts:

- -        for the first two tenths (2/10ths) of the knot of extra speed: XXXXXXX

- -        U.S.$XXXXXX for the third complete tenth of one knot of extra speed
         and that amount increased by U.S.$XXXXXX for each successive complete
         one tenth of a knot up to a maximum extra speed of one half of one
         knot.

(B)      Deadweight

If the VESSEL'S deadweight determined as stated in the SPECIFICATIONS is more
than XXX metric tons less than the deadweight specified, then the CONTRACTOR
shall pay to the PURCHASER as liquidated damages and not by way of penalty an
amount of US $XXXXX for each full XXX metric tons of such deficiency in excess
of XXX metric tons, save and except that the CONTRACTOR shall have the right to
remedy the deficiency.

If the VESSEL'S deadweight determined as stated in the SPECIFICATIONS is more
than XXX metric tons less than the deadweight specified, the PURCHASER, as an
alternative to receiving the above mentioned liquidated  damages, shall have
the option to terminate this CONTRACT with the consequences provided for in
Article 8 and Article 11, save and except that the CONTRACTOR shall have the
right to remedy the deficiency.





                                      11
   12

         [MARKED TEXT OMITTED PURSUANT TO AN APPLICATION FOR AN ORDER FOR
         CONFIDENTIAL TREATMENT BY CARNIVAL CORPORATION]


(C)      Fuel Consumption

For the main propulsion plant a shop test shall be carried out in accordance
with the SPECIFICATIONS.  During such shop test the specified fuel consumption
shall be ascertained and corrected to the design parameters.

The shop test shall be run on heavy fuel oil with each diesel engine developing
XX% MCR at XXX revolutions.  The measured fuel consumption shall be corrected
to a reference lower calorific value of XXXXXX kilojoules per kg and ISO
standard conditions.  The fuel consumption of the main propulsion plant so
corrected shall not exceed XXXXXXXXXXXXX for engines type 12ZAV40S and
XXXXXXXXXXXXXXXXX for engines type 8ZAL40S.

With respect to any of the engines, should the corrected fuel consumption be in
excess of XXX percent of XXXXXXXXXXXXXXXXX for engines type 12ZAV40S and
XXXXXXXXXXXX for engines type 8ZAL40S, the CONTRACTOR shall pay to the
PURCHASER, as liquidated damages and not by way of penalty, an amount of US
$XXXXXX for each full one percent in excess of XXX percent of XXXXXXXXXXXXXXXXX
for engines type 12ZAV40S and XXXXXXXXXXXXXXXXX for engines type 8ZAL40S, save
and except that the CONTRACTOR shall have the right to remedy any defect
causing such excessive fuel consumption and repeat the trial.

With respect to any of the engines, should the corrected fuel consumption be in
excess of XXX percent of XXXXXXXXXXXXXXXXX for engines type 12ZAV40S and
XXXXXXXXXXXXX for engines type 8ZAL40S, the PURCHASER, as an alternative to
receiving the above mentioned liquidated damages shall have the option to
terminate this CONTRACT with the consequences provided for in Article 8 and
Article 11, save and except that the CONTRACTOR shall have the right to remedy
any defect causing such excessive fuel consumption and repeat the trial.



ARTICLE 6:                DELIVERY OF THE VESSEL


(A)      Delivery Date and Place of Delivery

The VESSEL shall be delivered to the PURCHASER at the Building Site or other
agreed place.

The date for delivery of the VESSEL (the "Delivery Date") shall be 26 February
1998 subject to permissible extensions as provided in this CONTRACT.





                                      12
   13

         [MARKED TEXT OMITTED PURSUANT TO AN APPLICATION FOR AN ORDER FOR
         CONFIDENTIAL TREATMENT BY CARNIVAL CORPORATION]



Six (6) months prior to the date on which the CONTRACTOR expects the VESSEL to
be ready for delivery the CONTRACTOR shall give notice to the PURCHASER in
writing (the "Delivery Notice") specifying the actual expected delivery date.

The PURCHASER shall promptly take delivery of the VESSEL when properly
completed in accordance with this CONTRACT and shall with reasonable dispatch
as applies to a passenger cruise ship remove her from the CONTRACTOR'S
shipyard.

(B)      Liquidated Damages for Delayed Delivery

If the VESSEL is not delivered (duly completed in accordance with this
CONTRACT, the SPECIFICATIONS and the PLAN) on or before the Delivery Date (as
extended by virtue of the provisions of this CONTRACT specifically permitting
such extension), the CONTRACTOR shall pay to the PURCHASER by way of liquidated
damages and not by way of penalty the amount of UNITED STATES DOLLARS
XXXXXXXXXXXXXXXX (US$XXXXXXX) for each full calendar day of delay following the
Delivery Date as so extended.

(C)      Termination for Delay

If the VESSEL is not delivered (duly completed in accordance with this
CONTRACT, the SPECIFICATIONS and the PLAN), by the date falling twelve (12)
months after the Delivery Date (as extended by virtue of the provisions of this
CONTRACT expressly permitting such extension), the PURCHASER may terminate this
CONTRACT by notice to the CONTRACTOR with the consequences provided for in
Article 8 and Article 11.  On such valid termination the CONTRACTOR shall
forthwith also pay to the PURCHASER the liquidated damages payable by virtue of
paragraph (B) above as if the VESSEL had been delivered on the date on which
this CONTRACT is terminated by the PURCHASER under this paragraph.

If the VESSEL is not delivered (duly completed in accordance with this CONTRACT
and the SPECIFICATIONS and the PLAN) by 26 October 1999 then, notwithstanding
the provisions of paragraphs (D) and (E) below which would otherwise operate to
permit the Delivery Date to be extended, the PURCHASER may terminate this
CONTRACT by notice to the CONTRACTOR with the consequences provided for in
Article 8 and Article 11.  On such valid termination the CONTRACTOR shall
forthwith also pay to the PURCHASER the liquidated damages payable by virtue of
paragraph (B) above as if the VESSEL had been delivered on the date on which
this CONTRACT is terminated by the PURCHASER under this paragraph.





                                      13
   14

(D)      Permissible Extensions due to "Force Majeure"

Should the CONTRACTOR be prevented from having the VESSEL constructed for
delivered by the Delivery Date owing to: - Acts of God; engagement in war or
other hostilities, civil war, civil commotions, riots or insurrections;
requirements of civil or military authorities in contemplation of war;
blockades; embargoes, vandalism; sabotage; epidemics; strikes; lockouts;
officially agreed reduction of working hours relating to the Finnish workforce
as a whole; earthquakes; landslides; floods; failure of electric current for a
period of more than three working days; damages by lightning; explosions,
collisions, strandings or fires; damage to the VESSEL and time taken to repair
such damage; shortage of materials and equipment or inability to obtain
delivery thereof, provided that such materials and equipment at the time of
ordering could reasonably be expected by the CONTRACTOR to be delivered in
time; defects in materials and equipment such as castings or forgings which
could not have been detected by the CONTRACTOR or its subcontractors using
reasonable care; delays caused by delay of the Classification Society or other
bodies whose documents are required in issuing such documents; delays caused by
events similar to the foregoing; the effect of the foregoing on the
CONTRACTOR'S other commitments; then and in any such case the Delivery Date of
the VESSEL shall, subject to paragraphs (E) and (F) below, be extended by the
number of calendar days of delay incurred by the CONTRACTOR in completing or
delivering the VESSEL in consequence of any of these events.

(E)      Definitive Notice of Delivery

Following the giving of the Delivery Notice by the CONTRACTOR pursuant to
paragraph (A) above the only events which shall be permitted to extend the
Delivery Date (as previously properly extended by virtue of other provisions of
this CONTRACT permitting such extension) shall (subject to paragraph (F) below)
be: Acts of God, engagement in war or other hostilities, civil wars, civil
commotions, riots or insurrections requirements of military authorities in
contemplation of war, blockades, embargoes, vandalism, sabotage, epidemics,
earthquakes, landslides, flood, damage by lightning, explosions, collisions,
strandings, fires or nationwide strikes or lockouts either general or affecting
nationwide a particular sector of the labour force.

(F)      Conditions for Claims for Permissible Delays

Not later than 7 days from the date of commencement of any of the above
contingencies on account of which the CONTRACTOR claims that it is entitled to
an extension of the Delivery Date, the CONTRACTOR shall provide the PURCHASER
with telex or telefax advice particularising the date such contingency
commenced and the reasons therefor and the nature thereof, the estimated
duration thereof and the action which is being taken by the CONTRACTOR to
overcome the effect of the contingency.  If any such contingency continues for
a period in excess of 30 days the CONTRACTOR shall, at regular fortnightly
intervals thereafter, continue to keep the PURCHASER advised by delivery to the
PURCHASER of further statements containing the particulars specified above.
Within 7 days after the CONTRACTOR becomes aware that such contingency has
ended the CONTRACTOR shall





                                      14
   15

specify the period of time by which it claims the Delivery Date is to be
extended by reason of delay due to such contingency.

The CONTRACTOR shall not be entitled to claim any extension of the Delivery
Date in respect of any particular delay unless:

         1.      The CONTRACTOR has given all the proper notices and statements
                 required by this paragraph (F) in relation to that particular
                 item of delay; and

         2.      that particular item of delay has not in any way been caused
                 or contributed to by any error, neglect or omission on the
                 part of the CONTRACTOR; and

         3.      the CONTRACTOR has, since the date of commencement of the
                 contingency in question, taken all reasonable steps to remove
                 the cause of delay and to mitigate its effect on the delivery
                 of the VESSEL; and

         4.      the cause of delay could not reasonably have been foreseen by
                 the CONTRACTOR at the date of this CONTRACT.

In the event of there being any dispute between the parties under this Article
the burden of proof shall be upon the CONTRACTOR to establish the facts
entitling it to an extension of the Delivery Date and that all requirements
specified in this paragraph have been fully satisfied.

(G)      Termination of the CONTRACTOR'S Responsibilities

On delivery of the VESSEL to the PURCHASER all risk and every responsibility
for the safety and generally for the condition of the VESSEL is transferred to
the PURCHASER, and thereafter all responsibilities  on the part of the
CONTRACTOR shall cease with the exception of the guarantee obligations provided
for in Article 12 and Article 13 hereof and the rights of the parties under
Article 8(A).

If it is not practicable before delivery for the CONTRACTOR to demonstrate the
contractual performance of any of the specified equipment or the contractual
performance of any of the specified technical systems of the VESSEL in their
intended operating conditions, the CONTRACTOR will demonstrate such performance
as soon as practicable, and if not practicable within 180 days of delivery
compliance or non-compliance shall be determined by calculations.  In case of
deficiencies in performance the CONTRACTOR will remedy such deficiencies in
performance under the guarantee contained in Article 12.

(H)      Protocol of Delivery and Acceptance

At the delivery and acceptance of the VESSEL the PURCHASER and the CONTRACTOR
shall execute, in duplicate, a Protocol of Delivery and Acceptance one original
copy of which is to be retained by each party.





                                      15
   16

         [MARKED TEXT OMITTED PURSUANT TO AN APPLICATION FOR AN ORDER FOR
         CONFIDENTIAL TREATMENT BY CARNIVAL CORPORATION]


ARTICLE 7:                PRICE AND PAYMENT



(A)      Contract Price

The PURCHASER shall pay to the CONTRACTOR the CONTRACT price of UNITED STATES
DOLLARS XXXXXXXXXXXXXXXXXXXXXXXXXX (US $ XXXXX) inclusive of building period
financing cost.

(B)      Instalments

Payment of the CONTRACT Price shall be made by the PURCHASER to the CONTRACTOR
by instalments as follows:

    -       XX% equal to USDXXXXXXXXX on the date of signature of this CONTRACT;

    -       XX% equal to USDXXXXXXXXXX XXXXXXXXXXXXX after delivery of m.s. 
            "IMAGINATION" (KMY HULL XXX);

    -       XX% equal to USDXXXXXXXXXX XXXXXXXXXXXXXX;

    -       XX% equal to USDXXXXXXXXXXX on delivery of the VESSEL duly
            completed in accordance with this CONTRACT, the SPECIFICATIONS
            and the PLAN.

(C)      Payment Procedures

Except for the first instalment the CONTRACTOR shall notify the PURCHASER at
least 10 days in advance of the estimated dates of the instalment payments
falling due.

All payments to the CONTRACTOR are to be made in U.S. Dollars for same day
value at a bank in Helsinki to be designated by the CONTRACTOR without any
deduction whatsoever on the dates on which the payments are due as aforesaid.

Expenses for remitting payments and any other expenses connected with such
payments shall be for the account of the PURCHASER.





                                      16
   17

If for any reason the PURCHASER cannot take delivery of the VESSEL on the date
the CONTRACTOR has notified that the VESSEL will be ready for delivery, the
PURCHASER shall, subject to paragraph (A) of Article 6, nevertheless be liable
to make full and final payment on that date, provided the VESSEL is tendered in
accordance with the terms of this CONTRACT.

(D)      Payment for Modifications

The sum due for modifications under Article 3 of this CONTRACT shall be paid by
or credited to the PURCHASER as the case may be to the CONTRACTOR on delivery.

(E)      Payment for Liquidated Damages and Premiums

Any amount of liquidated damages or any premiums under Articles 5 and 6 shall
be calculated and determined on delivery of the VESSEL or on termination in
accordance with Article 6(C) or 11(B) and the balance (of one over the other)
shall be paid to the party entitled thereto at the delivery of the VESSEL or,
in the event of termination of this CONTRACT in accordance with Article 6(C) as
provided herein, provided that (notwithstanding any other provision in this
CONTRACT to the contrary) the net amount payable under this paragraph shall not
exceed XXX per cent of the CONTRACT Price referred to in paragraph (A) of this
Article.

Payment of liquidated damages under Article 5 and/or 6 of this CONTRACT shall
be to the exclusion of any other claims in respect of the matters giving rise
to such payment except that this provision shall not affect the rights of the
PURCHASER under Article 6 (C) and Article 11 of this CONTRACT or the
alternative right of the PURCHASER to terminate this CONTRACT in the
circumstances provided in Article 5 of this CONTRACT.

(F)      Prompt Payment

The PURCHASER shall not delay any payment of the Contract Price in the event of
any disagreement as to the amount of extras, liquidated damages or premiums, or
in the event of other exceptions or claims the PURCHASER may have asserted or
may intend to assert against the CONTRACTOR, whether in connection with this
CONTRACT or otherwise without prejudice to the PURCHASER'S right to apply
subsequently to arbitration.





                                      17

   18



         [MARKED TEXT OMITTED PURSUANT TO AN APPLICATION FOR AN ORDER FOR
         CONFIDENTIAL TREATMENT BY CARNIVAL CORPORATION]


(G)      Bank Guarantee

On the date of signature of this CONTRACT in respect of the first instalment
and not less than five (5) business days before the date on which the PURCHASER
is obliged to make payment to the CONTRACTOR of respectively the second and
third  instalments of the Contract Price as provided in Article 7(B) and as a
condition precedent to the obligation of the PURCHASER to make payment of such
instalments, the CONTRACTOR shall deliver to the PURCHASER a bank guarantee of
payment by the CONTRACTOR of all amounts which the CONTRACTOR may become liable
to pay to the PURCHASER under Article 11(A) of this CONTRACT.

Each such guarantee shall be issued by a first class bank acceptable to the
PURCHASER in the form of Exhibit A hereto and shall be authenticated in such
manner as the PURCHASER may require.  The PURCHASER and the CONTRACTOR shall
share equally the cost of providing and maintaining such guarantees.  Each
guarantee shall be for an amount not less than the amount specified with
respect to the relevant instalment below:

Instalment No                                                  Amount US$
- -------------                                                  ----------

1                                                               XXXXXXXXX
2                                                              XXXXXXXXXX
3                                                              XXXXXXXXXX


Each such bank guarantee shall be initially valid until 30 April 1998.  If, in
the PURCHASER'S opinion the delivery of the VESSEL will for any reason be
postponed beyond such date, the validity of the bank guarantee shall, before 30
April 1998 be extended until 30 November 1999.

Irrespective of the dates indicated in this paragraph (G) the bank/s issuing
the bank guarantee shall be informed that the original bank guarantee will be
returned to the bank/s on the actual date when vessel is delivered and accepted
by the purchaser.  The issuing bank/s  shall be instructed that fees will be
charged until the date of delivery of vessel.

(H)      Statements of Financial Conditions

The CONTRACTOR shall provide to the PURCHASER at four monthly intervals
following the date of this CONTRACT statements of the financial condition of
the CONTRACTOR in such form and substance as the PURCHASER may reasonably
request to enable the PURCHASER to monitor the current financial condition of
the CONTRACTOR during the construction of the VESSEL.





                                      18
   19



ARTICLE 8:                PROPERTY


(A)      General Plans, Specification and Working Drawings

All rights in the SPECIFICATIONS, plans and working drawings, technical
descriptions, calculations, test results and other data, information land
documents concerning the design and constructions of the VESSEL shall belong to
the CONTRACTOR  before actual delivery and after actual delivery shall belong
to the PURCHASER provided always that the CONTRACTOR shall  be entitled to use
the same to the extent of the hull form and all parts below the main
accommodation decks.

The PURCHASER shall have the right to use the SPECIFICATIONS, plans and working
drawings, technical descriptions, calculations, test results and other data,
information and documents concerning the design and the construction of the
VESSEL prior to delivery of the VESSEL with the consent of the CONTRACTOR, such
consent not to be unreasonably withheld and to be given promptly following the
PURCHASER'S request.

(B)      Title to the VESSEL

As from signing of this CONTRACT the PURCHASER has title to:-

         1.      All materials and equipment for building of the VESSEL
                 purchased from and delivered by suppliers and sub-contractors.

                 The title to all such materials and equipment for building of
                 the VESSEL shall be with the PURCHASER already before such
                 materials and equipment arrive at the shipyard.

         2.      All materials and equipment out of the CONTRACTOR'S own stock
                 allocated for the construction of the VESSEL which for this
                 purpose shall be stored separately and marked as early as
                 possible.

         3.      Parts manufactured from the materials listed above.

         4.      The VESSEL itself as it is in the course of progressive stages
                 of construction, together with equipment installed.

Until the CONTRACT Price (as adjusted) has been paid in full the PURCHASER may
not at any time, prior or subsequent to the delivery of the VESSEL transfer,
whether finally or conditionally, or mortgage or hypothecate the VESSEL without
the CONTRACTOR'S written consent in each particular case.





                                      19
   20

Subject to the provisions of Article 11 this paragraph shall in no way impair
the CONTRACTOR'S right to retain the VESSEL until the PURCHASER has complied
with its obligations under Article 7 of this CONTRACT.

(C)      Effect of Termination on the Title to the VESSEL under Construction

If the CONTRACTOR justly terminates this CONTRACT, the CONTRACTOR becomes the
sole owner of the VESSEL.

If the PURCHASER justly terminates this CONTRACT, the PURCHASER thereby waives
its right to the VESSEL, provided that all amounts payable or repayable to the
PURCHASER by the CONTRACTOR on such termination in accordance with this
CONTRACT shall have been paid or repaid or security satisfactory to the
PURCHASER shall have been provided for such payment or repayment.


ARTICLE 9:                INSURANCE


The VESSEL and all materials, machinery and other equipment belonging to the
VESSEL and within the precincts of the Building Site shall until delivery of
the VESSEL (including during trials) be insured by the CONTRACTOR at the
CONTRACTOR'S expense in the joint names of the CONTRACTOR and the PURCHASER
against all risks customarily insured against in the Finnish shipbuilding
industry and in accordance with and subject to the terms of the usual
construction policy for a total of not less than the aggregate of (1) the
amount for the time being paid by the PURCHASER to the CONTRACTOR in respect of
the VESSEL and (2) interest thereon at the rates specified in Article 11 from
the date such payment was made to the CONTRACTOR and (3) the value of equipment
or materials supplied by the PURCHASER and present within the precincts of the
Building Site or already installed in the VESSEL.  If considered necessary by
the CONTRACTOR or if required by the PURCHASER, war risks insurance for not
less than the CONTRACT Price is to be effected by the CONTRACTOR up to the date
of delivery to the extent that such insurance is obtainable on the London
insurance market provided, however, that the CONTRACTOR shall effect war risk
insurance at its own expense during sea trials.

In the event of the VESSEL and/or such materials etc. as aforesaid sustaining
damage, including war damage, before delivery of the VESSEL then any monies
received in respect of any insurance effected under this Article shall be
applied by the CONTRACTOR in making good such damage with all due despatch
during ordinary working hours in a reasonable and workmanlike manner and the
PURCHASER shall not on account of any such damage or any repair thereof be
entitled to object to the VESSEL or to make any claim for alleged consequential
loss or depreciation provided that such damage is made good in accordance with
this CONTRACT, the SPECIFICATIONS and the PLAN as if it was the VESSEL'S new
construction.





                                      20
   21


Underwriters are entitled to settle claims concerning repairable damage to the
VESSEL directly with the CONTRACTOR, and make all payments on these claims
directly to the CONTRACTOR.

Should the VESSEL at any time from any cause become an actual total loss or an
agreed or compromised constructive total loss under the insurance policy, this
CONTRACT shall thereupon absolutely cease and terminate without any liability
whatsoever on the part of the CONTRACTOR provided that the CONTRACTOR has
complied with its obligations under the preceding provisions of this Article.
In the event of such total loss insurance monies shall be paid to the PURCHASER
for reimbursement (1) of the amounts paid by the PURCHASER to the CONTRACTOR
hereunder and (2) interest thereon at the rates specified in Article 11 from
the dates such payments were made and (3) the value of equipment and materials
supplied by the PURCHASER and within the precincts of the Building Site or
installed on the VESSEL at the time of such total loss; any balance shall
belong to the CONTRACTOR.  Under no circumstances shall the CONTRACTOR be
liable to replace the VESSEL.

The CONTRACTOR'S liability to the PURCHASER in respect of damage - including
war damage - or in respect of the actual or constructive total loss of the
VESSEL, shall not in any event extend further or otherwise than provided in
this Article.

The PURCHASER agrees to notify the CONTRACTOR before each item of equipment or
material supplied by the PURCHASER is delivered to the Building Site and to
advise the CONTRACTOR of the value thereof.


ARTICLE 10:      DEFAULTS BY THE PURCHASER


(A)      Suspension/Termination by the CONTRACTOR

If any of the following events should occur :-

         1.      the PURCHASER fails to pay to the CONTRACTOR any of the first,
                 second and third instalments of the CONTRACT Price when such
                 instalments become due and payable under the provisions of
                 Article 7 hereof; or

         2.      the PURCHASER fails to take delivery of the VESSEL when the
                 VESSEL is duly tendered for delivery by the CONTRACTOR under
                 the provisions of Article 6 hereof; or

         3.      a bona fide petition is filed and is not dismissed within
                 thirty (30) days, or an effective resolution is passed for the
                 winding up of the PURCHASER (other than for the purpose of a
                 reconstruction or amalgamation which has received the prior
                 written approval of the CONTRACTOR); or





                                      21
   22


         4.      a receiver is appointed of the undertaking or property of the
                 PURCHASER; or

         5.      the PURCHASER suspends payment of its debts or ceases to carry
                 on its business or makes any composition with its creditors or
                 is declared bankrupt or goes into liquidation;

 Then:

         (a)     the delivery date shall be automatically postponed for a
                 period of continuance of such event in excess of two (2) days.

         (b)     If such event continues for a period of fifteen (15) days the
                 CONTRACTOR shall have the option to suspend the CONTRACTOR's
                 obligations under this CONTRACT until such event has ceased.

         (c)     If any of the events set out in sub-paragraphs (1) - (4)
                 above, continues for a period of thirty (30) days after
                 notice, to the PURCHASER or if any of the events set out in
                 sub-paragraph, (5) occurs, the CONTRACTOR may, at its option,
                 terminate this CONTRACT by giving notice of such effect to the
                 PURCHASER by fax confirmed by letter.

(B)      Interest

Should the PURCHASER be in default in payment of any of the first, second,
third or fourth instalments of the CONTRACT Price and/or other amounts due
under this CONTRACT on or before delivery of the VESSEL, then the PURCHASER
shall pay to the CONTRACTOR as from the due date interest thereon at the rate
which is two (2) per cent per annum above the rate certified by Citibank N.A.
to be the rate at which deposits of United States Dollars can be obtained by
Citibank N.A. to fund the defaulted amount from the London Interbank
Eurocurrency market for such periods as may be reasonable in the circumstances.

In case the PURCHASER shall fail to take delivery of the VESSEL as provided
above in this Article, the PURCHASER shall be deemed in default as regards the
fourth instalment of the CONTRACT PRICE and shall pay interest thereon at the
rate aforesaid from and including the day on which the VESSEL is tendered for
delivery by the CONTRACTOR.

(C)      CONTRACTOR'S Rights on Termination

         1.      In the event of such termination of this CONTRACT, the
                 CONTRACTOR shall be entitled to retain any instalment or
                 instalments of the CONTRACT price theretofore paid by the
                 PURCHASER to the CONTRACTOR on account of this CONTRACT to the
                 extent of proved damages and loses including costs and
                 expenses permitted by law.





                                      22
   23

         2.      In the event of termination of this CONTRACT as provided in
                 this Article 10, the CONTRACTOR shall have full right and
                 power either to complete or not to complete the VESSEL as it
                 deems fit, and to sell the VESSEL at public or private sale on
                 such terms and conditions as the CONTRACTOR thinks fit without
                 being answerable for any loss or damage except as provided in
                 paragraph (4) below.

         3.      In the event of the sale of the VESSEL in its completed state,
                 the proceeds of sale received by the CONTRACTOR shall be
                 applied firstly to payment of all proven incidental damages
                 and losses permitted by law attending such sale, and then to
                 payment of all unpaid instalments of the CONTRACT Price and
                 interest on such instalments at the rate as provided for above
                 from the respective due dates thereof to the date of
                 application.

         4.      In the event of sale of the VESSEL in its incomplete state,
                 the proceeds of sale received by the CONTRACTOR shall be
                 applied firstly to all proven incidental damages and losses
                 permitted by law attending such sale, and then to payment of
                 all costs of construction of the VESSEL and compensation to
                 the CONTRACTOR for a loss of reasonable profit due to the
                 termination of this CONTRACT together with interest at the
                 rate as provided for above, less the instalments retained by
                 the CONTRACTOR.

         5.      In either of the above events of sale, if the proceeds of sale
                 exceed the total of amounts to which such proceeds are to be
                 applied as aforesaid, the CONTRACTOR shall promptly pay the
                 excess to the PURCHASER without interest.

         6.      If the proceeds of sale are insufficient to pay to the
                 CONTRACTOR such total amounts payable as aforesaid, the
                 PURCHASER shall promptly pay the deficiency to the CONTRACTOR
                 upon request.





                                      23
   24

         [MARKED TEXT OMITTED PURSUANT TO AN APPLICATION FOR AN ORDER FOR
         CONFIDENTIAL TREATMENT BY CARNIVAL CORPORATION]


ARTICLE 11:      DEFAULTS BY THE CONTRACTOR


(A)      Termination and Reimbursement and Liquidated Damages

If, in accordance with any of the provisions of Article 5 or 6 or paragraph (B)
of this Article, the PURCHASER properly exercises its option to terminate this
CONTRACT, then the CONTRACTOR shall :-

         (1)     return to the PURCHASER all equipment and material supplied by
                 the PURCHASER or pay to the PURCHASER the value thereof and
                 pay to the PURCHASER the amount of consulting, engineering,
                 architectural and similar fees and expenses incurred by the
                 PURCHASER in connection with the construction of the VESSEL up
                 to a maximum of XXXXXXXXX United States Dollars; and

         (2)     pay to the PURCHASER any accumulated liquidated damages
                 payable under Article 6(C); and

         (3)     repay to the PURCHASER in United States Dollars the amount of
                 all moneys paid by the PURCHASER for or on account of the
                 CONTRACT Price of the VESSEL together with interest calculated
                 from the respective dates such amounts were paid by the
                 PURCHASER to the CONTRACTOR up to the date of repayment
                 thereof at the rate certified by Citibank N.A. to be the rate
                 paid by the Citibank N.A. to depositors for deposits of
                 amounts equal to the instalments paid by the PURCHASER for the
                 periods from receipt thereof by the CONTRACTOR to the date of
                 repayment.

The CONTRACTOR'S liability in the event of such termination shall be limited to
the above which the parties hereto reasonably estimate to be the amount of the
loss which will be sustained by the PURCHASER in the event that this CONTRACT
is terminated by the PURCHASER in accordance with Article 5 or 6 hereof or
paragraph (B) of this Article.

(B)      Termination on Bankruptcy, Etc.

In any of the following events:





                                      24
   25

         (1)     a bona fide petition is filed and is not dismissed within
                 thirty (30) days or an effective resolution is passed for the
                 winding up of the CONTRACTOR or any other similar proceedings
                 with similar effect on the CONTRACTOR are instituted in
                 Finland affecting the CONTRACTOR (other than for the purpose
                 of a reconstruction or amalgamation which has received the
                 prior written approval of the PURCHASER); or

         (2)     the CONTRACTOR merges with any other entity without the prior
                 written approval of the PURCHASER;

         (3)     the CONTRACTOR ceases to be controlled by Kvaerner A/S;

         (4)     a receiver is appointed of the undertaking or property of the
                 CONTRACTOR; or

         (5)     the CONTRACTOR suspends payment of its debts or threatens to
                 do so or ceases to carry on its business or makes any
                 composition with its creditors or convenes a meeting of its
                 creditors to propose such compositions or is declared bankrupt
                 or goes into liquidation; or

         (6)     the construction of the VESSEL is suspended for a period of
                 more than thirty days for reasons other than any of the events
                 specified in Article 6 (D) or, if applicable, Article 6 (E)
                 and it is apparent that the CONTRACTOR will be unable to
                 fulfil its obligations hereunder; or

         (7)     there is a material adverse change in the financial condition
                 of the CONTRACTOR;

         (8)     the CONTRACTOR fails to provide any of the guarantees relating
                 to the first, second or third instalments of the CONTRACT
                 Price payable in accordance with Article 7(B) within thirty
                 (30) days of the date on which such guarantee should otherwise
                 have been delivered to the PURCHASER;

         (9)     if the CONTRACTOR fails to have the bank guarantees extended
                 on or before 30 April 1998 if required to do so under the
                 terms of Article 7(G);

         (10)    the CONTRACTOR fails to comply with its obligations under
                 Article 7 (H) and such default continues for a period of
                 fourteen days after the PURCHASER gives notice to the
                 CONTRACTOR requiring such default to be remedied.

Then:

                 the PURCHASER may immediately (without being bound thereto)
                 terminate this CONTRACT by giving notice in writing to the
                 CONTRACTOR.





                                      25
   26

         [MARKED TEXT OMITTED PURSUANT TO AN APPLICATION FOR AN ORDER FOR
         CONFIDENTIAL TREATMENT BY CARNIVAL CORPORATION]


(C)      The PURCHASER'S Right to Take Possession

If in accordance with the provisions of paragraph (B) above or Article 6 (C),
the PURCHASER is entitled to terminate this CONTRACT but does not do so, then
the PURCHASER shall have an optional right after giving notice to the
CONTRACTOR to take possession of the VESSEL in her then state and all parts,
plans, materials, machinery and equipment appropriated to the VESSEL and remove
the same from the CONTRACTOR'S yard.  The PURCHASER agrees that it will,  on
taking possession and in consideration of the CONTRACTOR releasing its lien on
the vessel, pay to the CONTRACTOR XXX XXXXXXXXXXXXXXXXXXX UNITED STATES DOLLARS
less the aggregate of:

         (1)     the total amount of the instalments of the CONTRACT Price paid
                 by the PURCHASER under Article 7(A) of this CONTRACT; and

         (2)     the reasonable estimate cost of completing the VESSEL in the
                 CONTRACTOR'S yard or at another shipyard and of removing to
                 such other shipyard the VESSEL and all parts, materials,
                 machinery and equipment appropriated to the Vessel.

If the actual cost of completing the VESSEL exceeds the estimated cost the
CONTRACTOR shall pay the difference to the PURCHASER on completion of the
vessel.  If the actual cost of completing the vessel is less than the estimate
cost the PURCHASER shall pay the difference to the CONTRACTOR on completion of
the VESSEL.

(D)      Notice of bankruptcy filing

The CONTRACTOR shall not take any steps to obtain the appointment of bankruptcy
trustees under the relevant provisions of Finnish bankruptcy law without first
giving to the PURCHASER at least 30 days notice of its intention to do so.


ARTICLE 12:      GUARANTEE


(A)      Extent of Guarantee

The CONTRACTOR shall remedy at the Building Site or at any other yard
controlled by the CONTRACTOR and in normal working hours, by repairing or if
necessary replacing,

         1.      any defect notified in writing by the PURCHASER on the
                 VESSEL'S delivery; and





                                      26
   27

         [MARKED TEXT OMITTED PURSUANT TO AN APPLICATION FOR AN ORDER FOR
         CONFIDENTIAL TREATMENT BY CARNIVAL CORPORATION]



         2.      any defect due to faulty design, bad workmanship or use of
                 defective material and not apparent on delivery which becomes
                 apparent during the period of XXXXXXXXXXXXXXXXXX from the date
                 of delivery of the VESSEL provided the defect is notified in
                 writing as soon as reasonably practicable after its discovery.

If for operational reasons the guarantee drydocking cannot reasonably be
carried out before the expiration of the said XXXXXXXXXXXX period, then in
relation to defects not reasonably discoverable without such drydocking the
guarantee period hereunder shall, subject to paragraph (D) of this Article,
expire on completion of such drydocking but in any event not later than
XXXXXXXXXXXXXXX after delivery of the VESSEL.

Except as provided in paragraph (F) below, the guarantee shall apply only to
the work of and materials and equipment supplied by the CONTRACTOR, its
subcontractors and suppliers.

The CONTRACTOR'S obligations under this Article shall be limited in duration
and extent as herein provided.

(B)      Paint

The CONTRACTOR shall provide a guarantee to the PURCHASER in relation to the
paint for the VESSEL on the same terms as that provided by the paint supplier
to the CONTRACTOR.  Such guarantee shall be on the basis that the paintwork
shall be carried out under the supervision of and to the satisfaction of
authorised representatives of the paint supplier.

(C)      Liability for Consequential Loss or Damage

The Guarantee contained in this Article is in lieu of and excludes any other
liability, guarantee, warranty and/or condition imposed or implied by law
custom, statute, tort or otherwise by reason of the construction or sale of the
VESSEL by the CONTRACTOR for and to the PURCHASER.

Except as provided in this Article and Article 8(A) and Article 13 after
delivery the CONTRACTOR shall not under any circumstances have any liability,
whether arising from claims for breach of warranty or guarantee, negligence or
strict liability, for any consequential damages or for loss of time, cost of
capital, loss of profit or earnings, demurrage, claims of third parties, or for
any other kind whatsoever of consequential, contingent or incidental damages
directly or indirectly occasioned by the CONTRACTOR'S activities pertinent to
this CONTRACT.





                                      27
   28

         [MARKED TEXT OMITTED PURSUANT TO AN APPLICATION FOR AN ORDER FOR
         CONFIDENTIAL TREATMENT BY CARNIVAL CORPORATION]


The CONTRACTOR shall however be liable under the guarantee contained in this
Article for damage to any part of the VESSEL (including her equipment) caused
directly by defects to which paragraph (A) above applies provided that the
CONTRACTOR'S liability in respect of damage so caused shall be limited to
UNITED STATES DOLLARS XXXXXXXXXXX XXXXXXXXXXXXXXXXXXXXXX.

(D)      Extensions of Guarantee Period

The time during which the VESSEL is not available for service on account of
defects which the CONTRACTOR is liable to make good under paragraph (A) above
and the time required to remedy such defects shall be added to extend the
guarantee period specified in paragraph (A) above up to a maximum of
XXXXXXXXXXXXXXXXXX after delivery.

If the CONTRACTOR itself makes good any defects during the guarantee period
specified in paragraph (A) above (as extended if appropriate by the preceding
sub-paragraph of this paragraph (D)) or such defects are remedied elsewhere in
accordance with paragraph (F) below under the supervision and with the approval
of the CONTRACTOR, then the provisions of paragraph (A) shall apply to the
parts repaired or replaced and the repair or replacement work for a period of
XXXXXXXXXXXXX after the repair or replacement was completed up to a maximum of
XXXXXXXXXXXXXXXXXX after delivery.

(E)      Investigation of Recurrent Defects

The CONTRACTOR agrees within the terms of this Article to investigate the cause
of any recurrent defect to which paragraph (A) applies with a view to providing
a satisfactory remedy therefor.

(F)      Guarantee Work Outside Building Site

If in the PURCHASER'S opinion the replacements or repairs under this Article
cannot be conveniently made at the Building Site or at any other yard
controlled by the CONTRACTOR, the PURCHASER may have such repairs and/or
replacements carried out elsewhere; in such a case the CONTRACTOR is discharged
from the guarantee under this Article in respect of the repairs or replacements
carried out by the third party unless carried out under the supervision and
with the approval of the CONTRACTOR.  Provided the guarantee work is contracted
for in a businesslike manner having regard to the nature, urgency and extent of
the defect to be remedied, the CONTRACTOR shall reimburse the PURCHASER the
documented expenses incurred by the PURCHASER in effecting such repairs and/or
replacements including expenses of independent contractors in travelling to the
VESSEL and the cost of transportation of materials and equipment (including by
air freight if the PURCHASER reasonably so requires).





                                      28
   29


In any case, the VESSEL shall be taken at the PURCHASER'S cost and
responsibility  to the place elected for the work to be carried out ready in
all respects for the guarantee work to be commenced.

(G)      Assignment of Suppliers' and Sub-contractors' Guarantees

In the event that the guarantee stipulated by manufacturers or suppliers of
machinery, material, equipment, appurtenances and outfit furnished to the
CONTRACTOR and embodied in the VESSEL exceeds the guarantee given by the
CONTRACTOR to the PURCHASER hereunder, such extended guarantee rights are to be
assigned and made available to the PURCHASER by the CONTRACTOR.

(H)      Verification of Guarantee Claims

The CONTRACTOR, at its own cost, is to have the right to investigate the
validity of the PURCHASER'S claim either by the attendance aboard the VESSEL
(at its point of service) of an accredited representative or, if in the opinion
of the CONTRACTOR it is practicable to do so after suitable replacement is
made, by the removal from the VESSEL and the transportation to the Building
Site of the defective part.

(I)      Guarantee Engineer

During any time of the guarantee period the CONTRACTOR shall have the option to
place on board one Guarantee Engineer who shall act as the CONTRACTOR'S
observer and to whom every assistance shall be granted for the fulfilment of
his tasks.  Should this option be exercised then such Guarantee Engineer shall
not be discharged by the PURCHASER without the CONTRACTOR'S approval, otherwise
the PURCHASER shall immediately forfeit its rights under the guarantee in this
Article.

The PURCHASER shall ensure the said Engineer a status on board not inferior to
the chief engineer and provide accommodation in an officer's cabin.  The
PURCHASER shall pay the CONTRACTOR a remuneration to be agreed upon in respect
of the Guarantee Engineer.

Notification of defects to the Guarantee Engineer shall be deemed to be notice
to the CONTRACTOR for the purposes of this Article.  The PURCHASER agrees to
give prompt confirmation in writing of such notice to the CONTRACTOR.

The presence on board of the Guarantee Engineer shall in no way affect the
CONTRACTOR'S and the PURCHASER'S responsibility as provided for in this
CONTRACT.  The duties and responsibilities of the Guarantee Engineer shall be
specified in writing by the CONTRACTOR to the PURCHASER at the time the
Guarantee Engineer is appointed.





                                      29
   30


ARTICLE 13:      PATENTS


The CONTRACTOR shall indemnify the PURCHASER against any infringement of patent
rights in connection with the construction of the VESSEL at the Building Site
but no such liability shall lie with the CONTRACTOR with regard to components
and/or equipment and/or design supplied by the PURCHASER.


ARTICLE 14:      LAW OF THE CONTRACT, REFERENCE TO EXPERT
                 AND ARBITRATION


(A)      Law of the CONTRACT

This CONTRACT and all other agreements relating thereto shall be construed and
interpreted under the laws of England.

(B)      Reference to Expert

If, save as provided in Article 1 paragraph (F), any dispute of a technical
nature arises during the construction of the VESSEL between the parties in
regard to the construction of the VESSEL, engines, material or workmanship, it
shall forthwith be referred to a technical expert nominated by agreement
between the parties hereto and his decision shall be final and binding upon
both parties.  Failing such agreement the dispute shall be referred to
arbitration in accordance with paragraph (C) of this Article 14.

(C)      Arbitration

In the event of any dispute between the parties hereto as to any matter arising
out of or relating to this CONTRACT or any stipulation herein or with respect
thereto which cannot be settled by the parties themselves, such dispute shall
be resolved by arbitration in London, England in accordance with the Laws of
England.  Either party may demand arbitration of any such dispute by giving
written notice to the other party.  Any demand for arbitration by either of the
parties hereto shall state the name of the arbitrator appointed by such party
and shall also state specifically the question or questions as to which such
party is demanding arbitration.  Within twenty (20) days after receipt of
notice of such demand for arbitration, the other party shall in turn appoint a
second arbitrator.  The two arbitrators thus appointed shall thereupon select a
third arbitrator, and the three arbitrators so named shall constitute the board
of arbitration (hereinafter called the "Arbitration Board") for the settlement
of such dispute.

In the event however, that said other party should fail to appoint a second
arbitrator as aforesaid within twenty (20) days following receipt of notice of
demand of arbitration, it is agreed that





                                      30
   31

such party shall thereby be deemed to have accepted and appointed as its own
arbitrator the one already appointed by the party demanding arbitration, and
the arbitration shall proceed forthwith before this sole arbitrator, who alone,
in such event, shall constitute the Arbitration Board.  And in the further
event that the two arbitrators appointed the parties hereto as aforesaid should
be unable to agree to the third arbitrator within twenty (20) days from the
date on which  the second arbitrator is appointed, either party of the said two
arbitrators may apply to any court in England or other official organisation
having jurisdiction in such matter to appoint the third arbitrator.  The award
of the arbitration made by the sole arbitrator or by the majority of the three
arbitrators as case may be shall be final, conclusive and binding upon the
parties hereto.

Judgment upon any award rendered may be entered in any court having
jurisdiction or application may be made to any competent court or authority for
a judicial acceptance of any award and an order of enforcement, as the case may
be.


ARTICLE 15:      ADDRESSES FOR CORRESPONDENCE


For all practical purposes, without it being a legal requirement, the
CONTRACTOR shall send all notices, letters and documents for the PURCHASER in
connection with or required under this CONTRACT to the following address :

         (a)     for all technical matters :

                 Address :        Technical Marine Planning Limited
                                  70 Great Eastern Street
                                  London EC2A 3JL
                 Telephone:       44-71-739-3533
                 Telefax:         44-71-729-1169

         (b)     for all legal and financial matters :

                 Address :        Carnival Corporation
                                  Koger Center
                                  5225 NW 87th Avenue
                                  3rd Floor,
                                  Miami
                                  Florida 33178-2193
                                  U.S.A.

                 Attention :      Captain Vittorio Fabietti (for)
                                  Mr. Micky Arison

                 Telephone :      (305) 471-5777
                 Telefax:         (305) 471-5778





                                      31
   32

For all practical  purposes without it being a legal requirement the PURCHASER
shall send all notices, letters and documents for the CONTRACTOR in connection
with or required under this CONTRACT to the following address :

                 Address :        Kvaerner Masa-Yards, Inc.
                                  Helsinki New Shipyard
                                  Munkisaarenkatu 1
                                  SF-00150 Helsinki, Finland

                 Attention :      Jukka Jaatinen
                 Telephone :      358-0-1941
                 Telefax :        358-0-170 132

All mail shall be sent by air.

Whenever this CONTRACT requires that notification shall be given in writing,
such notification may validly be given by telefax.  All approvals or consents
required by this CONTRACT shall be in writing, by telefax.  All such messages,
if sent by telefax, shall also be confirmed by official letter.


ARTICLE 16:      ASSIGNMENT


The CONTRACTOR shall not transfer, assign and/or pledge this CONTRACT or any
rights hereunder without the prior written consent of the PURCHASER which the
PURCHASER shall have full liberty to withhold.

The PURCHASER may assign to any bank or financial institution any or all of its
rights under this CONTRACT.





                                      32
   33




IN WITNESS WHEREOF, parties hereto have duly signed and executed this CONTRACT
in triplicate counterparts.


Date :  December 7, 1994
        ----------------


[signed] H. Frank                  [signed] Martti Saarikaagas/ Antti Pankakoski
- ----------------------------       ---------------------------------------------

CARNIVAL CORPORATION              KVAERNER MASA-YARDS, INC.





                                      33
   34


                                  EXHIBIT "A"

                              BANK GUARANTEE/DRAFT
                               [BANK LETTERHEAD]


To: Carnival Corporation
PANAMA




GUARANTEE NO. 
               ------------------


Dear Sirs,

We refer to the shipbuilding contract dated               1994 (the
"Shipbuilding Contract") made between (1) yourselves and (2) Kvaerner
Masa-Yards Inc. (the "Contractor") in respect of the construction of Yard
No.491.

In consideration of the receipt from you of Ten United States Dollars and other
good and valuable consideration, receipt whereof is hereby acknowledged, we
hereby irrevocably and unconditionally guarantee to you the payment by the
Contractor of all amounts which the Contractor may be liable to pay to you
under the Shipbuilding Contract and undertake to pay to you such amounts
forthwith on presentation of your certificate confirming that (A) you have duly
terminated the Shipbuilding Contract and that either (1) the Contractor has not
within fourteen days of your notice of termination to the Contractor applied to
arbitration contesting your right to terminate the Shipbuilding Contract or (2)
the arbitration board appointed to determine your entitlement to terminate the
Shipbuilding Contract has issued a final award confirming that you are so
entitled or (B) the Contractor has become the subject of bankruptcy (konkurs)
administration.

We shall not be exonerated from our obligations hereunder by:

1.       Any irregularity, unenforceability or invalidity of the Shipbuilding
         Contract (to the intent that the obligations hereunder shall remain in
         full force and effect and this guarantee shall be constructed as if
         there were no such irregularity, unenforceability or invalidity); or

2.       Any amendment to or variation of the Shipbuilding Contract; or





                                      34
   35

3.       Any other matter which may constitute a legal or equitable discharge
         of a surety or guarantor.

We hereby waive all or any of our rights as surety which may at any time be
inconsistent with any of the provisions of this guarantee and in particular,
but without prejudice to the foregoing, any right which we may have to compel
you to proceed to enforce a claim against the Contractor before enforcing this
guarantee against us.

All payments by us hereunder shall be made in United States Dollars without
set-off or counter-claim free and clear from all taxes.  Our liability under
this guarantee is, however, limited to a maximum amount of [                ]
United States Dollars.

This guarantee shall terminate upon the date on which the Vessel is delivered
to and accepted by you under the Shipbuilding Contract.

All claims under this guarantee shall, however, be made to us in writing latest
on 30 April 1998 in order to be taken into consideration.

This guarantee shall be governed by and construed in accordance with the laws
of England.  We hereby submit to the non-exclusive jurisdiction of the English
courts and agree if required to appoint an agent in England for service of any
proceedings before such courts.



Helsinki,                             , 199
          ----------------------------




                                      35