1 EXHIBIT 99 NEVADA MANHATTAN MINING, INC. MANHATTAN MINE PROJECT REVIEW & BUSINESS PLAN By William R. Wilson July 1995 2 TABLE OF CONTENTS PAGE INTRODUCTION 1 HISTORY AND OWNERSHIP OF PROPERTY 2 REGIONAL AND PROJECT GEOLOGY 2 MINERAL RESOURCE 3 DEVELOPMENT & MINING 4 PROCESSING 5 ENVIRONMENTAL SETTING AND PERMITS 6 PROJECT REVIEW 7 RECOMMENDED BUSINESS PLAN 8 SUMMARY 10 APPENDIX A - MAPS (POCKET) 11 APPENDIX B - FINANCIAL INFORMATION 12 APPENDIX C - MILL INFORMATION 13 3 NEVADA MANHATTAN MINING, INC. MANHATTAN MINE PROJECT REVIEW & BUSINESS PLAN By: William R. Wilson(1) INTRODUCTION William R. Wilson was engaged by Nevada Manhattan Mining, Inc. ("Nevada Manhattan") in May 1995 to prepare a project review and business plan for their mining properties in the Manhattan Mining District 45 miles northeast of Tonopah, Nevada, in which Nevada Manhattan has a 24.5% ownership. The purpose of the project review was to prepare a valuation of Nevada Manhattan's ownership. The purpose of the business plan was to present various options that would provide short-term cash flow for Nevada Manhattan and its joint venture partners in the properties through initial production. The business plan also presents a method to expand potential ore deposits in existing mine workings and establish access to deeper targets. Two alternative mining plans are examined that utilize the 1,200 foot long decline ("Decline") constructed by Nevada Manhattan and its joint venture partners in 1994. The first plan considers mining ore from the Consolidated Manhattan Mine accessed from the Decline; drifting to the area near the high grade WC 49 Drill Hole, drilled by Freeport in 1985 and mining ore in that area; extending the existing decline ("Decline") to the existing but caved White Caps shaft, rehabilitating the White Caps shaft to the 1,300' Level and mining high grade ore in all the levels connected to White Caps Shaft below the 565' Level. The second plan considers all of the same elements except stopping at the 565' Level; mining the remaining high grade ore in the 565' Level without rehabilitating the White Caps shaft below the 565' Level. The second alternative mining plan is recommended as this plan still allows continued exploration in the lower levels leading to additional ore development and requires less capital. Two milling alternatives were examined. The first alternative considered was being to purchase a used crushing plant and process plant and recover only free gold in a gravity circuit. The second alternative is to wait until New Concept Mining, Inc. completes the construction of the mill, scheduled to be completed in late 1995 and mill the ore in that new mill. The second alternative was the preferred option because of the mill's accessibility in a short period of time. (1) Wilson has a professional degree in metallurgical engineering from the Colorado School of Mines and an MBA from the University of Southern California. His more than thirty years of experience includes ten years in senior positions with engineering, construction and consulting firms and ten years as president of several mining companies operating in the United States and internationally. He is a part chairman of the Colorado Mining Association and currently is president of Gold King Mines Corporation, a subsidiary of Taylor Rand Incorporated, a publicly traded resource company based in Toronto, Ontario, Canada. 4 The work in this report was conducted primarily by William R. Wilson, President, Gold King Mines Corporation. He was assisted by Jeff Kramer, Senior Vice President, Nevada Manhattan and his staff; Marlowe Harvey, the project operator and president of Calais Resources and Argus Resources, Inc.; Robert Martin, Vice President, Construction of Harrison Western, a well known underground mining contracting company; Bill Foster, President and Dale Moore, Mill Superintendent of New Concept Mining, Inc., the owners of the new mill at Manhattan; and Bill Carlson, Manager, Process Design of Lynteck, Inc. a process metallurgical contracting company. HISTORY AND OWNERSHIP OF PROPERTY The historic mining in the Manhattan district extends from 1866 to present with the major activity in the late 1860's, between 1906 and 1921, and from the 1960's until present. Placer and lode mining took place principally in the Reliance, the White Caps Mine, the Union Amalgamated Mine, the Manhattan Consolidated mine, the Earle Mine, the Big Four Mine and the April Fool Mine. The United States Geological Survey reports historic production through 1959 of 280,000 ounces of lode gold and 206,000 ounces of placer gold mined in the district. since that time the more significant production was from the Echo Bay and Nevada Goldfields mines (bordering the subject property) totaling in excess of 500,000 ounces of gold. Several companies and individuals have owned part or all of the various mines currently shared in ownership by Nevada Manhattan (24.5%) with Argus Resources Inc. (24.5%) and Marlowe Harvey (51%). Included in the property are 28 patented and 83 unpatented claims totaling approximately 1,800 acres. REGIONAL AND PROJECT GEOLOGY The bedrock in the Manhattan district contains the Gold Hill Formation including quartzite, limestone and schist, phyllite and slate of the Cambrian age and chert, slate, quartzite and limestone of the Palmetto Formation of Ordovician age. The Gold Hill formation over thrusts the Palmetto Formation with gold production normally found in the hanging wall of the thrust fault, in limestones and quartzose schist of the Gold Hill Formation. Mineralization generally occurs as assemblages of pyrite, stibnite, realgar, orpiment, cinnabar and free gold associated with calcite, quartz, fluorite, sericite, leverrierite and sparse adularia. The most productive ore bodies have been in quartzose schist in networks of small quartz-adularia veins containing pyrite and free gold. Mineralization is generally theorized to be the result of epidermal deposition in the limestone and related to secondary replacement in the volcanic activity associated with the south margin of the Manhattan caldera. The Manhattan property lies in several shallow gullies at 7,500 to 7,800 feet elevation. Further, mineralization appears to be structurally controlled by a series of parallel east-northeast trending faults, dipping from 50 to 75 degrees southwest and with some cross or perpendicular faults. Geophysical studies indicate the structure contains magnetic highs and resistivity lows and geochemical studies indicate outcrops and mineralization associated with arsenic and mercury. Mineralization is consistent with the district and is 2 5 often in highly altered areas and in limestone with gold and silver found in quartz, quartz-carbonate including pyrite, arsenophyrite, stibnite and cinnabar. Veins tend to range in size from stringers of less than six inches to larger veins of seven feet. The deeper ores lie in the Consolidated Manhattan and White Caps mines while shallow ores in the area frequently contain disseminated, lower grade gold in larger ore bodies. MINERAL RESOURCE Several studies have been made to help quantify and delineate ore targets in the remaining portions of existing mines, the areas between the old mines and the un-mined areas to the south of the Consolidated Manhattan and White Caps mines. A summary of geologic investigations conducted by Nevada Manhattan and its joint venture partners of mineralized areas along the fault zone through the center of the property includes general surface sampling, underground sampling, production records, drilling (surface and underground), geochemical sampling and geophysics. Historic mining records and accounts add to the total picture but often lack completeness or substantiation in more recent times. As is often the case in epithermal, veined systems all information points toward more ore grade material, often of higher grade, and the potential for bonanza-type ore bodies. Satisfying the standards for reserve definition imposed by the Securities and Exchange Commission and other technical societies such as the Society for Mining, Metallurgy, and Exploration, Inc. is always difficult in this setting, i.e., small high grade vein systems with little widely disseminated mineralization. Therefore, this report does not include discussions relating to reserves in any category. The work in this report identified areas in and adjacent to the Decline constructed by Nevada Manhattan and its joint venture partners in 1994. The areas considered for mining include the Adit Level of the Consolidated Manhattan Mine, the area around the high grade intercept in Drill Hole WC49 (reported by Freeport to be twenty-five feet of 0.698 ounces per ton of gold) and the mined levels in the White Caps Mine from the 565' Level to the 1,300' Level. From the identification of mining targets, ore blocks were estimated on underground sampling, historic production, drill hole assays and level maps for the White Caps Mine (See Maps VII and VIII). These areas were then quantified using simple geometry, tonnage calculations and average grade. The average grade selected was based on the same information as the estimated ore blocks and was further defined by an average of 0.25 ounces per ton as a minable underground grade and a minimum cut off grade of 0.10 ounces per ton. The resulting estimated ore blocks were used in an economic model. The model further identified the capital required to initiate mining in the various areas, mill the ore at the New Concept Mining, Inc.'s mill, and an estimated cash flow and a NPV (net present value) analysis at 10% and 15% discount rates of the cash flow for the two alternate plans. The resulting analysis was intended to be used by Nevada Manhattan and its joint venture partners to determine the advisability of proceeding immediately with development and mining. The work included is not intended to be a reserve calculation of any type and no reference is made to proven, probable or possible reserves. However, initial investigations indicate commercial grade mineralization. Details of the calculations are shown in Appendix B, Schedules 1, 2 and 3 and can 3 6 be summarized as follows: 1. Mining on Adit Level of Manhattan Consolidated Mine (access from Decline). The total estimated ore block for this area is 4,293 tons. Using a 20 per cent dilution factor and average grade of 0.25 ounces per ton at a 0.10 ounces per ton cutoff, this block is estimated to contain 859 minable ounces. Additional tonnage may be quantified as a result of additional sampling and development in this area. 2. Drifting from an approximate depth on the Decline in the area of the high grade, intercept the WC49 drill hole. The total estimated ore block in this area is 1,555 tons. Using the same factors with an average grade of 0.50 ounces per ton, this block contains 1,555 minable ounces. Additional tonnage may be quantified as a result of additional sampling and development in this area. 3. Rehabilitating the White Caps shaft below the 565' Level and mining in the old workings on the 565', 670', 800', 910', 1,100', 1,200', 1,300' Levels. The total estimated ore block in the White Caps is 18,306 tons. Using the same factors but with a 0.75 ounce per ton average grade for the 1,300' Level, these blocks contain 7,420 minable ounces. Again, additional tonnage may be quantified as a result of additional sampling and development in this area. The total minable ounces in all the calculated blocks are 9,833 ounces of gold. Typically silver grades are about equal or less than the gold grade so no silver grades were calculated. The total estimated ore blocks total 26,487 tons is not an even number because areas of ore in the blocks were estimated by cubic footage and then converted to tons using a factor of 162 pounds per cubic foot for converting to tonnage. The higher grade ore shoots associated with the East Fault, the Morning Glory Fault, the White Caps Faults appear to be continuous and extend at least to the 1,300' Level. Grades, if anything, appear to increase with depth with a reported ore shoot on the 1,300' Level of 2.73 ounces of gold per ton (Reference - Map VIII). Because of limited drilling information below 450 feet, any confirmation of ore reserves in specific categories is not possible. Structural control may, however, continue below the 1,300' Level. The project operator intends to complete a surface geochemical survey coordinated with magnetic and resistivity geophysics. The project operator will then drill several targets to the south of the White Caps shaft as predicted by the recent geo-chemical survey and geophysical examinations. Upon completion of this work, a more accurate estimate of ore reserves should be possible. Several geological studies of the White Caps area have predicted bonanza-type ore bodies in the area but little has been quantified for a resource or reserves of this magnitude. See the section PROJECT REVIEW for more discussion of this subject. DEVELOPMENT & MINING The Manhattan District has experienced surface mining for placer gravels, shallow underground mining using shafts and drifts to bedrock for placer gravels, open pit mining for lower grade ores and underground mining in open stopes for higher grade ores. 4 7 Two alternate mining plans are considered in this report. The first plan includes: extending the Decline to the 565' Level of the White Caps Mine; mining remaining higher grade ore in the Consolidated Manhattan Mine; mining higher grade ore in a small but high grade area around the WC49 Drill intercept at approximately 300 foot depth and sixty feet from the existing Decline; rehabilitating the White Caps Shaft from the 565' Level to the 1,300' Level; and mining higher grade ore in the old workings of the White Caps Mine between the 565' Level and the 1,300' Level. The second plan includes all aspects of the first plan but the rehabilitation of the White Caps Shaft will not proceed until an extensive evaluation of the ore grades in the old workings of the White Caps mine is evaluated by detailed underground sampling. In both plans the rehabilitation of the White Caps shaft will be dependent on the condition of the shaft upon reaching the White Caps shaft on the Decline and evaluating the condition of the shaft. The safety of working in the White Caps shaft and the costs of the rehabilitation this shaft, depending on its condition, will be key elements in determining the acceptability of either plan. A raised bore for ventilation and access will also be considered. In other words, until the shaft can be accessed from the Decline, additional ore evaluated and the condition of the White Caps shaft and workings can be evaluated, much of the work and costs related to the two plans is preliminary in nature. Within the old workings of the Consolidated Manhattan Mine and the White Caps mine, the mining will be accomplished using a modified cut and fill or open stope method by drilling and blasting. The extension of the Decline down to the 565' Level of the White Caps Mine will also be drilled and blasted. Rehabilitation of the White Caps Shaft will be required to reach the lower levels of the mine and will consist of re-timbering and rock bolting where necessary. Depending on conditions encountered when the Decline is connected to the White Caps mine shaft, a ventilation and escape shaft may be required. Because of the uncertainty of the need for this shaft, no provision has been made in this report for the cost is its installation. It is further assumed that any ventilation and access will utilize the extended Decline. A charge of $1 per ton was added to the Harrison Western estimate to provide for pumping and ventilation using the Decline. Equipment includes underground Jumbo drills, jackleg drills, scoop trams, haul trams, fans and pumps. It is intended to use Harrison Western as a mining contractor for both development and mining. A summary of their estimated costs is included in the cash flow analyses. An allowance has been provided for the pumping and treatment of mine water. PROCESSING A preliminary investigation was made to ascertain the feasibility of "high grading" the old mine workings and then processing the free gold in a used portable gravity processing plant. This option would also require permitting because of the tailings produced from the gravity plant and possible discharge from process water. A used crushing plant priced at $36,000 was located. The unit included a 10 X 16 jaw crusher, a 16 inch roll crusher and a double deck screen that would size ore to -10 5 8 mesh. A used ball mill for crushing to -200 mesh costing $8,000 needed to be purchased. A used gravity processing plant was located that included 4 X 8 Double Deck Derrick Screens and thirty-eight MDL spirals were located for a price of $200,000. It was felt that a cash payment of $125,000 would satisfy the seller. The estimated cost of purchasing, shipping and installing this portable plant was $200,000. Other items such a power line or portable generator, electrical connections and controls, piping, conveyors, engineering and installation represent 50 per cent of the total installed cost and therefore, the portable facility was estimated to cost $400,000. The experience of the writer is that a hurried schedule almost always is extended beyond original estimates and milling equipment not specifically designed for the operation requires modification and recovery suffers. Considering these factors and the time to acquire and assemble to be at least sixty days or longer, and to secure a permit to be six months, the alternative of securing this portable equipment is not recommended. New Concept Mining, Inc. provided a proposed flow sheet and equipment list. (See Appendix C). The processing circuit includes crushing, grinding, gravity separation, cyanide leach, flotation and thickening. A finalized balanced flow sheet was not provided but a review of the proposed circuit and equipment indicates the mill should provide approximately 200 to 250 tons per day of production and the predicted 85 to 90 per cent recovery. Nevada Manhattan has an agreement to utilize up to 30 per cent of the milling capacity or approximately sixty tons per day. The ore to be mined contains free gold and gold associated with pyrite and arsenopyrite. The gold in the sulphides was assumed to be less than 10% as suggested by Dale Moore, Mill Superintendent for New Concept Mining. He also estimated ore recovery to be as high as 90 per cent. For purposes of this report a mill recovery of 81 per cent was used to account for the loss of gold in the sulphides. The mill flow sheet planned by New Concept Mining, Inc. will not include a flotation circuit until the mill has operated up to one year. (90% recovery times 90% gold from non-sulphide ore = 81% overall recovery.) Mr. Moore estimated ore milling costs will be $15 per milled ton after a two to three-month start up period when costs were expected to be $20 per milled ton. Because the mill may take up to six months to construct, this report assumes ore will be mined for six months, stockpiled and then milled. This causes a six-month delay in cash flow from gold mined. The report also assumes that the mill will produce Dore' cones that will be shipped to a refinery to be further refined to gold and silver at a $2.00 per gold ounce refinery charge. Since it is expected that less than one ounce of silver will be produced for each ounce of gold, no credits for silver are shown in the financial analyses. ENVIRONMENTAL SETTING AND PERMITS For purposes of this report, it was assumed all necessary permits are held or will be obtained by Nevada Manhattan. New Concept Mining, Inc. has applied for permits required for the milling operations including approval of an operational plan by the BLM. Nevada Manhattan will pump water internally in the underground mine but will not discharge water to the surface. No reclamation is required for the ore mined other than restoration of the 6 9 Decline portal area if the Decline is closed. Should Nevada Manhattan sometime in the future decide to discharge mine water to the surface a Point Source Discharge Permit will be required. Such a permit would take from six months to two years to secure. In the interim period it is recommended that Nevada Manhattan periodically (monthly) sample any running water on its property and sample underground water at several locations to establish a baseline for future operations. PROJECT REVIEW The auditing firm of Jackson & Rhodes has requested Nevada Manhattan to provide a valuation in conjunction of capitalized acquisition and development costs of the Manhattan property for the purposes of confirming the value carried on the Company's balance sheet. Without a detailed ore reserve available, an alternate method used by Gold king Mines Corporation in the past is to place a value on the various tangible assets of a company and the intangible assets that potentially can enhance the value of a company. For Nevada Manhattan the following assets should be considered: Acquisition Costs - Typically acquisition of a mining property of this type, size and potential in Nevada in the last five years has ranged in value between $2.5 million and $5 million. Nevada Manhattan has a capitalized acquisition and development cost of $3.2 million on its balance sheet. For the purposes of this report a conservative value for capitalized acquisition and development costs is $1,600,000. Manhattan Decline - The cost of construction of the Decline was a total of $465,000. This has added significant value to the Consolidated Manhattan Mine and potentially to the White Caps Mine and other potential mineralization. Full value should be assigned to this asset for those reasons. Nevada Manhattan's share of that cost is 24.5% or $114,000. Other Exploration and Development Costs - Total costs of exploration and development by Nevada Manhattan including drilling, surface sampling, geophysical work, assays and other development costs incurred by the Nevada Manhattan attributable to future ore reserves are $830,000 less the cost of the decline or a total of $710,000. Considering the specific plans of the project operator to complete his exploration program and the plan to achieve near-term production outlined in this report, these costs form a basis of value for the Nevada Manhattan. The full value of the accrued cost should be included in this valuation as the cost can lead to future potential production and additional reserves in the future. Access to Milling Capacity - Nevada Manhattan controls 30 per cent of the milling capacity in the New Concept Mining, Inc.'s mill approximately one mile from the Manhattan Decline portal. This mill, now under construction, will be rated at approximately 200 to 250 tons per day. Mills of this capacity and type are currently worth a minimum of $2,000,000. For Nevada Manhattan to permit and build their own mill including tailings disposal would cost at a minimum of $3,000,000. As the New Concept mill is under construction and the required permits are anticipated to 7 10 be in place by January 1, 1996, a value of Nevada Manhattan's interest in the mill can be established. A thirty per cent interest has a value of $900,000 but as the mill is not in place, a value of $450,000 is assigned to these mill rights. Minable Ore Blocks - As stated in the section on MINERAL RESOURCE, estimated ore blocks total 9,800 ounces of which 7,900 ounces may be recovered. As the recovery of these ounces is predicated on implementation of the proposed business plan, a conservative approach is to place a value of $15 per ounces on this projected production. This total value is therefore $118,500 of which $30,000 can be assigned to Nevada Manhattan. Other Mineral Value - The Hughes and Cameron report indicate a resource of 250,000 ounces in the lower levels of the White Caps mine. This was further substantiated by drilling in the 1960's on the 1,200 foot level. At $10 per ounce this has a value of $2,500,000 of which $600,000 can be assigned to Nevada Manhattan. The $15 and $10 values are frequently assigned to un-mined reserves and resources. In this case, the $15 value was assigned to the minable ore blocks. However, in the future, Nevada Manhattan may recover much higher value than the value assigned in this valuation. Infrastructure - The Manhattan property is approximately 45 miles from Tonapah, Nevada and approximately one mile from Manhattan, Nevada. As Tonapah has facilities for most mine supply requirements and available employees and community infrastructure, the Manhattan property requires minimal local infrastructure in the form of an office and a maintenance shop. Therefore, a value of $100,000 can be placed on infrastructure related to the Manhattan property and approximately $25,000 for Nevada Manhattan's portion. Based on the above assets valuation, the total value of Nevada Manhattan's portion of the Manhattan Property is $3,529,000. RECOMMENDED BUSINESS PLAN As described in the section, DEVELOPMENT AND MINING, two alternative plans are considered in this report. Plan 1 Work Item 1. Extend Decline to White Caps 565' Level Work Item 2: Rehabilitate and mine old workings in Consolidated Manhattan Mine Work Item 3: Drift and Mine new area near WC49 Work Item 4: Rehabilitate White Caps Shaft Work Item 5: In White Caps Mine, mine 565' Level, 670' Level, 800' Level, 910' Level, 1,120' Level, 1,200' Level and 1,300' Level The major advantage to this plan is that access would be improved considerably to 8 11 the lower levels of the White caps mine, very possibly into high grade ore and also provide access to the high grade ore anticipated as a result of the proposed deep drilling contemplated by the project operator. A cash analysis of this plan was prepared and is shown in Appendix B, Schedule 4A & 4B. The project schedule would involve a period of 24 months and include a capital cost of $1,463,290 and an operating cost of $1,719,699 with production of 7,960 ounces of gold resulting in revenues of $3,088,430. This plan results in a positive cash flow of $92,804. The expenditure of the $1.4 million in capital provides the access required for any deep ore bodies and the gold production offsets a large portion of the capital cost. The cash flow may be improved by encountering lower shaft rehabilitation costs in the White Caps shaft and possibly higher than projected ore grade in the old White Caps workings. Additionally, the possibility exists to increase the total tonnage of ore through the planned sampling program. Plan 2 Work Item 1. Extend Decline to White Caps 565' Level Work Item 2. Rehabilitate and mine old workings in Consolidated Manhattan Mine Work Item 3. Drift and Mine new area near WC49 Work Item 4. In White Caps Mine, mine the 565' Level only Work Item 5. Underground sampling in the 670' through 1,300' Levels The major advantage to this plan is the reduced cash cost and the opportunity to sample underground in the White Caps mine without rehabilitating the White Caps shaft. The disadvantages of this plans are that mining access to the lower portions of the White Cap Mine may not be completed and it is still not known whether access can be obtained to each of the levels below the 565' Level. This plan is a compromise plan that can be modified as the project proceeds. A cash analysis of this plan was prepared and is shown in Appendix B, Schedule 5. The project schedule would involve a period of 12 months and include a capital cost of $605,840 and an operating cost of $1,046,063 and production of 4,568 ounces of gold resulting in revenues of $1,772,539. This plan results in a positive cash flow of $425,326. As exploration continues in the lower White Caps mine, additional ventilation will be required and was included as an allowance in the capital cost. The underground sampling may prove successful to the point that the lower levels can be opened. Further study will be required at that point. The major advantages of this plan are less capital is required, access to the lower levels of the White Caps Mine are at least possibly accessed and positive cash flow is generated. Additionally, the possibility exists to increase the total tonnage of ore through the planned sampling program. A third plan would be to mine only the Consolidated Manhattan Mine and the WC49 Area. A cursory review of Schedule 5, would indicate that the capital costs of this would be approximately $300,000 producing 2,400 ounces of gold with some cash flow generated. Some additional ore may be located under this plan. The fourth plan will be to wait until the on-going drilling is completed and New 9 12 Concept Mining, Inc.'s mill is completed. This alternative is the lower risk but provides nothing to the prospects of Nevada Manhattan. No cash flow is possible for Nevada Manhattan. SUMMARY The mining industry and investment community recognizes that in essentially all start up mining operations, negative cash flow can be expected. Recognizing that the two principal plans presented in this report are subject to the preliminary nature of the financial analyses prepared, both plans do provide positive cash flow. The recommended Plan 2 provides the opportunity to access the White Caps mine, explore for additional ore, generate positive cash flow and with less capital than Plan 1. The value of Nevada Manhattan's 24.5% interest in the Manhattan property as determined in this report, based on the geology, work to date on the mine, ownership and factors related to future mining and revenue was determined to be $3,529,000. No proven and probable ore reserves were calculated but an estimated ore block related to the business plan presented indicated it may be possible to mine and recover as much as 7,960 ounces of gold should Nevada Manhattan proceed with the first business plan developed in this report. Further, some consideration was given to the resource reported by Hughes and Cameron of a total resource in the White Caps of approximately 250,000 ounces of gold. The two principal plans presented, one providing for full production in the Consolidated Manhattan Mine, the Drill Hole WC49 area and all of the lower workings of the White Caps mine and the second being partial mining down to and including the White Caps 565 Level each has advantages and disadvantages. Plan 1 requires a larger capital cost ($1.46 million capital and a $93,000 cash flow from 7,960 ounces of gold) over 24 months. Plan 2 requires less capital with less gold produced ($606,000 of capital and a cash flow of $425,000 with 4,500 ounces of gold) over 12 months. Assuming availability of capital funds, Plan 2 is the recommended plan based on risk. If funding is limited, a modified form of Plan 2 could be adopted by Nevada Manhattan. 10 13 APPENDIX A MAPS (POCKET) I CLAIM AND DRILL HOLE LOCATION MAP II GEOLOGY MAP - WHITE CAPS MINE III UNDERGROUND GEOLOGY AND SAMPLE LOCATION MAP - MANHATTAN CONSOLIDATED MINE IV DECLINE/WC 49 INTERSECTION MAP - MANHATTAN CONSOLIDATED MINE V DECLINE LOCATION MAP VI DECLINE LOCATION MAP - CROSS SECTION VII WHITE CAPS MINE LEVEL MAP - SURFACE, 210' LEVEL, 310' LEVEL, 565' LEVEL, 800' LEVEL, 1,200' LEVEL, 1,300' LEVEL VIII WHITE CAPS MINE LEVEL MAP - GEOLOGIC FEATURES - SURFACE, 310 LEVEL, 565 LEVEL, 800 LEVEL, 900 LEVEL, 1,100 LEVEL, 1,200 LEVEL, 1,300 LEVEL IX MANHATTAN MINE - PROSPECTIVE LEVEL PLAN 11 14 APPENDIX B FINANCIAL INFORMATION SCHEDULE 1 CUBIC FEET OF ESTIMATED ORE BLOCKS SCHEDULE 2 ESTIMATED ORE BLOCKS, TONNAGE AND OUNCES OF GOLD SCHEDULE 3 MINING SCHEDULE - SEQUENCE OF ESTIMATED ORE BLOCKS BY MONTH SCHEDULE 4A CASH FLOW ANALYSIS - MINE ALL ESTIMATED ORE BLOCKS - COMPLETE REHAB OF WC SHAFT - 1ST 12 MONTHS SCHEDULE 4B CASH FLOW ANALYSIS - MINE ALL ESTIMATED ORE BLOCKS - COMPLETE REHAB OF WC SHAFT - 2ND 12 MONTHS SCHEDULE 5 CASH FLOW ANALYSIS - MINE ESTIMATED ORE BLOCKS DOWN TO AND INCLUDING 565 LEVEL 12 15 NEVADA MANHATTAN MINING, INC. PROJECT REVIEW & BUSINESS PLAN APPENDIX B SCHEDULE 1 - CUBIC FEET OF ESTIMATED ORE BLOCKS AREA BLOCK VOLUME TONS CUBIC FT. MANHATTAN CONSOLIDATED MINE 1 SLABBED OUT ADIT/DRIFT 700 FT. X 50 SQ. FT. 35,000 2,835 3 NEW STOPES 3 X 100 FT. X 6 FT. X 10 FT. 18,000 1,458 BLOCK TOTAL 53,000 4,293 WC49 - 300 LEVEL 2 8 NEW STOPES 8 X 100 FT. X 6 FT. X 10 FT. 48,000 3,888 WHITE CAPS MINE 565 LEVEL 3 EAST FAULT AREA STOPE 160 FT. X 50 FT. X 10 FT. 80,000 6,480 4 NEW STOPES 3 X 100 FT. X 6 FT. X 10 FT. 18,000 1,458 BLOCK TOTAL 98,000 7,938 WHITE CAPS MINE 670 LEVEL 4 EAST FAULT AREA STOPE 100 FT. X 40 FT. X 10 FT. 40,000 3,240 1 NEW STOPE 100 FT. X 6 FT. X 10 FT. 6,000 486 BLOCK TOTAL 46,000 3,726 WHITE CAPS MINE 800 LEVEL 5 3 NEW STOPES 3 X 100 FT. X 6 FT. X 10 FT. 18,000 1,458 WHITE CAPS MINE 910 LEVEL 6 EAST FAULT AREA STOPE 80 FT. X 20 FT. X 10 FT. 16,000 1,296 1 NEW STOPE 100 FT. X 6 FT. X 10 FT. 6,000 486 BLOCK TOTAL 22,000 1,782 WHITE CAPS MINE 1,120 LEVEL 7 4 NEW STOPES 4 X 100 FT. X 6 FT. X 10 FT. 24,000 1,944 WHITE CAPS MINE 1,200 LEVEL 8 2 NEW STOPES 2 X 100 FT. X 6 FT. X 10 FT. 12,000 972 WHITE CAPS MINE 1,300 LEVEL 9 1 NEW STOPE 100 FT. X 6 FT. X 10 FT. 6,000 486 TOTAL 327,000 26,487 16 NEVADA MANHATTAN MINING, INC. PROJECT REVIEW & BUSINESS PLAN APPENDIX B SCHEDULE 2 - ESTIMATED ORE BLOCKS, TONNAGE AND OUNCES OF GOLD AREA BLOCK TONS IN PLACE GRADE CUTOFF MINABLE OUNCES % % @ 20% DILUTION MANHATTAN CONSOLIDATED MINE 1 4,293 0.25 0.10 859 WC49 - 300 LEVEL 2 3,888 0.50 0.10 1,555 WHITE CAPS MINE 565 LEVEL 3 7,938 0.50 0.10 3,175 WHITE CAPS MINE 670 LEVEL 4 3,726 0.50 0.10 1,490 WHITE CAPS MINE 800 LEVEL 5 1,458 0.50 0.10 583 WHITE CAPS MINE 910 LEVEL 6 1,782 0.50 0.10 713 WHITE CAPS MINE 1,120 LEVEL 7 1,944 0.50 0.10 778 WHITE CAPS MINE 1,200 LEVEL 8 972 0.50 0.10 389 WHITE CAPS MINE 1,300 LEVEL (1) 9 486 0.75 0.10 292 26,487 9,833 (1) GRADE INCREASE TO 0.75 OPT GOLD BASED ON REPORTED ASSAYS ON THIS LEVEL IN EXCESS OF 2 OPT. 17 NEVADA MANHATTAN MINING, INC. PROJECT REVIEW & BUSINESS PLAN APPENDIX B SCHEDULE 3 - MINING SCHEDULE - SEQUENCE OF ESTIMATED ORE BLOCKS BY MONTH MONTH PRODUCTION CUMLATIVE PRODUCTION BLOCK TONS - START TONS - END TONS TONS 1 800 800 1 4,293 3,493 2 800 1,600 1 3,493 2,693 3 1,600 3,200 1 2,693 1,093 4 1,600 4,800 1 1,093 0 2 3,888 3,381 5 1,600 6,400 2 3,381 1,781 6 1,600 8,000 2 1,781 181 7 1,600 9,600 2 181 0 3 7,938 6,519 8 1,600 11,200 3 6,519 4,919 9 1,600 12,800 3 4,919 3,319 10 1,600 14,400 3 3,319 1,719 11 1,600 16,000 3 1,719 119 12 1,600 17,600 3 119 0 4 3,726 2,245 13 1,600 19,200 4 2,245 645 14 1,600 20,800 4 645 0 5 1,458 503 15 1,600 22,400 5 503 0 6 1,782 685 16 1,600 24,000 6 685 0 7 1,944 1,029 17 1,600 25,600 7 1,029 0 8 972 401 18 887 26,487 8 401 0 9 486 0 NMMI/D 7/12/95 18 NEVADA MANHATTAN MINING, INC. PROJECT REVIEW & BUSINESS PLAN APPENDIX B SCHEDULE 4A - CASH FLOW ANALYSIS - MINE ALL ESTIMATED ORE BLOCKS - COMPLETE REHAB OF WC SHAFT - lST 12 MONTHS $390/oz Gold MONTH 1 2 3 4 5 6 7 =================================================================================================================================== CAPITAL COSTS Mine Contractor Mobilization/Demobilization $30,000 Clean-up, resupport Decline $16,400 Slash entrance to Consolidated Manhattan $2,200 Drive drift for access to WC49 300 Level $9,600 (10' x 10" drift, 60 LF @!60/ft) Drive drift for to White Caps shaft (565 Level) $22,000 $22,000 $22,000 $22,000 (10' x 12" Decline, 400 LF @220/ft) Clean up/slash corners in Consolidated Manhattan $20,200 Access to 1,300 Level Rehab WC Shaft to 670 Level $9,000 $9,000 $9,000 Install headframe & hoist at 565 Level $25,000 $25,000 $25,000 Rehab WC Shaft to 800 Level Rehab WC Shaft to 910 Level Rehab WC Shaft to 1,300 Level Contractor supervision, overhead & profit $5,000 $5,000 $10,000 $10,000 $10,000 $10,000 $10,000 Subtotal - Mine Contractor $105,400 $27,000 $32,000 $32,000 $44,000 $44,000 $44,000 Other contract work Underground sampling (140 days @$400/d) $4,000 $4,000 $2,000 $2,000 $2,000 $2,000 $2,000 Assays (140 days x 20/d x $15) $3,000 $3,000 $1,500 $1,500 $1,500 $1,500 $1,500 Engineering & Consulting $15,000 Working Capital $50,000 $50,000 $50,000 Contigency @ 10% Excl. Working Capital $12,740 $3,400 $3,550 $3,550 $4,750 $4,750 $4,750 ----------------------------------------------------------------------------- TOTAL CAPITAL REQUIRED $190,140 $87,400 $89,050 $39,050 $52,250 $52,250 $52,250 =================================================================================================================================== PRODUCTION Area/block CM/1 CM/1 CM/1 CM/1 WC49/2 WC49/2 WC49/2 WC49/2 WC565/3 Ore Production-tons/mo 800 800 1,600 1,600 1,600 1,600 1,600 Diluted Head Grade - Troy Oz/ton (Au) 0.20 0.20 0.20 0.30 0.40 0.40 0.40 Ounces of gold mined 160.00 160.00 320.00 480.00 640.00 640.00 640.00 Tons of ore milled 0 0 0 0 400 400 1000 Diluted Head Grade to Mill - Troy Oz/ton (Au) 0.00 0.00 0.00 0.00 0.20 0.20 0.20 Ounces of gold milled (1) 0.00 0.00 0.00 0.00 80.00 80.00 200.00 Recovery (81%) 0.81 0.81 0.81 0.81 0.81 0.81 0.81 ----------------------------------------------------------------------------- Gold Production - Troy Oz 0 0 0 0 65 65 162 Average Gold Sales Price $/Troy Oz $0 $0 $0 $0 $390 $390 $390 Ref. Chgs $/Troy Oz Au $2 $2 $2 $2 $2 $2 $2 ----------------------------------------------------------------------------- NET SMELTER RECEIPTS $0 $0 $0 $0 $25,142 $25,142 $62,856 ROYALTY (% of NSR) 0.00% $0 $0 $0 $0 $0 $0 $0 ----------------------------------------------------------------------------- INCOME AFTER ROYALTY $0 $0 $0 $0 $25,142 $25,142 $62,856 ============================================================================= OPERATING COSTS - $/TON Mining $43 $43 $43 $43 $43 $43 $43 Mine water treatment & pumping $1 $1 $1 $1 $1 $1 $1 Processing & tailings $0 $0 $0 $0 $20 $20 $15 G & A @ 10% $4 $4 $4 $4 $6 $6 $6 ----------------------------------------------------------------------------- Total Cost $/Ton $48 $48 $48 $48 $70 $70 $65 OPERATING COSTS $36,960 $36,960 $73,920 $73,920 $84,800 $84,800 $93,070 ============================================================================= DEDUCTIBLE EXPENSES Depreciation Base $211,400 $211,400 $211,400 $211,400 $720,900 $720,900 $720,900 *Depreciation $7,558 $7,558 $7,558 $7,558 $8,591 $8,591 $8,591 Deductible Exploration $4,900 $4,900 $2,450 $2,450 $2,450 $2,450 $2,450 Amort. Non-deduct. Exp. & Dev. $1,050 $1,050 $525 $525 $525 $525 $525 Local taxes 1% $0 $0 $0 $0 $251 $251 $629 ----------------------------------------------------------------------------- Deductible Expenses Before Depletion $13,508 $13,508 $10,533 $10,533 $11,817 $11,817 $12,194 ============================================================================= Taxable Income Before Depletion ($50,468) ($50,468) ($84,453) ($84,453) ($71,475) ($71,475) ($42,408) Maximum allowed depletion - 50% rule $0 $0 $0 $0 $0 $0 $0 Depletion at 15% $0 $0 $0 $0 $0 $0 $0 Depletion allowed $0 $0 $0 $0 $0 $0 $0 *Includes all startup costs ============================================================================= TAXES Taxable Income After Depletion ($50,468) ($50,468) ($84,453) ($84,453) ($71,475) ($71,475) ($42,408) Loss Carried Forward Credit $50,468 $50,468 $84,453 $84,453 $71,475 $71,475 $42,408 Loss Carried Forward Credit Applied $0 $0 $0 $0 $0 $0 $0 Federal Income Tax (2) 0.34 $0 $0 $0 $0 $0 $0 $0 State Income Tax (2) 0.05 $0 $0 $0 $0 $0 $0 $0 ----------------------------------------------------------------------------- Net Income After Tax ($50,468) ($50,468) ($84,453) ($84,453) ($71,475) ($71,475) ($42,408) Loss Carried Forward $0 $0 $0 $0 $0 $0 $0 Dep., Depl., & Amort. $8,608 $8,608 $8,083 $8,083 $9,116 $9,116 $9,116 Deductible Exploration $4,900 $4,900 $2,450 $2,450 $2,450 $2,450 $2,450 Capital expenditures ($190,140) ($87,400) ($89,050) ($39,050) ($52,250) ($52,250) ($52,250) Reclamation $0 $0 $0 $0 $0 $0 $0 Salvage $0 $0 $0 $0 $0 $0 $0 ----------------------------------------------------------------------------- NET CASH FLOW ($227,100) ($124,360) ($162,970) ($112,970) ($112,159) ($112,159) ($83,093) CUMULATIVE CASH FLOW ($227,100) ($351,460) ($514,430) ($627,400) ($739,559) ($851,718) ($934,811) ================================================================================== 12-MONTH MONTH 8 9 10 11 12 TOTAL ========================================================================================================================= CAPITAL COSTS Mine Contractor Mobilization/Demobilization $30,000 Clean-up, resupport Decline $16,400 Slash entrance to Consolidated Manhattan $2,200 Drive drift for access to WC49 300 Level $9,600 (10' x 10" drift, 60 LF @!60/ft) Drive drift for to White Caps shaft (565 Level) $88,000 (10' x 12" Decline, 400 LF @220/ft) Clean up/slash corners in Consolidated Manhattan $20,200 Access to 1,300 Level Rehab WC Shaft to 670 Level $9,000 $9,000 $9,000 $9,000 $10,500 $73,500 Install headframe & hoist at 565 Level $25,000 $25,000 $25,000 $25,000 $25,000 $200,000 Rehab WC Shaft to 800 Level Rehab WC Shaft to 910 Level Rehab WC Shaft to 1,300 Level Contractor supervision, overhead & profit $10,000 $10,000 $10,000 $10,000 $10,000 $110,000 Subtotal - Mine Contractor $44,400 $44,000 $44,000 $44,000 $45,500 $549,900 Other contract work Underground sampling (140 days @$400/d) $2,000 $2,000 $2,000 $2,000 $2,000 $28,000 Assays (140 days x 20/d x $15) $1,500 $1,500 $1,500 $1,500 $1,500 $21,000 Engineering & Consulting $15,000 Working Capital $150,000 Contigency @ 10% Excl. Working Capital $4,750 $4,750 $4,750 $4,750 $4,900 $461,390 ------------------------------------------------------------------- TOTAL CAPITAL REQUIRED $52,250 $52,250 $52,250 $52,250 $53,900 $825,290 ========================================================================================================================= PRODUCTION Area/block WC565/3 WC565/3 WC565/3 WC565/3 WC565/3 WC670/4 Ore Production-tons/mo 1,600 1,600 1,600 1,600 1,600 17,600 Diluted Head Grade - Troy Oz/ton (Au) 0.40 0.40 0.40 0.40 0.40 Ounces of gold mined 640.00 640.00 640.00 640.00 640.00 6,240 Tons of ore milled 1600 1600 1600 1600 1600 9,800 Diluted Head Grade to Mill - Troy Oz/ton (Au) 0.30 0.30 0.40 0.40 0.40 Ounces of gold milled (1) 480.00 480.00 640.00 640.00 640.00 3,240 Recovery (81%) 0.81 0.81 0.81 0.81 0.81 ------------------------------------------------------------------- Gold Production - Troy Oz 389 389 518 518 518 2,624 Average Gold Sales Price $/Troy Oz $390 $390 $390 $390 $390 $390 Ref. Chgs $/Troy Oz Au $2 $2 $2 $2 $2 $2 ------------------------------------------------------------------- NET SMELTER RECEIPTS $150,854 $150,854 $201,139 $201,139 $201,139 $1,018,267 ROYALTY (% of NSR) 0.00% $0 $0 $0 $0 $0 ------------------------------------------------------------------- INCOME AFTER ROYALTY $150,854 $150,854 $201,139 $201,139 $201,139 $1,018,267 =================================================================== OPERATING COSTS - $/TON Mining $43 $43 $43 $43 $43 Mine water treatment & pumping $1 $1 $1 $1 $1 Processing & tailings $15 $15 $15 $15 $15 G & A @ 10% $6 $6 $6 $6 $6 ------------------------------------------------------------------- Total Cost $/Ton $65 $65 $65 $65 $65 OPERATING COSTS $103,840 $103,840 $104,000 $104,000 $104,000 $1,004,110 =================================================================== DEDUCTIBLE EXPENSES Depreciation Base $720,900 $720,900 $720,900 $720,900 $720,900 *Depreciation $8,591 $8,591 $8,591 $8,591 $8,591 $98,956 Deductible Exploration $2,450 $2,450 $2,450 $2,450 $2,450 $34,300 Amort. Non-deduct. Exp. & Dev. $525 $525 $525 $525 $525 $7,350 Local taxes 1% $1,509 $1,509 $2,011 $2,011 $2,011 $10,183 ------------------------------------------------------------------- Deductible Expenses Before Depletion $13,074 $13,074 $13,577 $13,577 $13,577 $150,789 =================================================================== Taxable Income Before Depletion $33,940 $33,940 $83,562 $83,562 $83,562 ($136,631) Maximum allowed depletion - 50% rule $15,970 $16,970 $41,781 $41,781 $41,781 $159,283 Depletion at 15% $22,628 $22,628 $30,171 $30,171 $30,171 $135,769 Depletion allowed $15,970 $16,970 $30,171 $30,171 $30,171 $124,453 *Includes all startup costs =================================================================== TAXES Taxable Income After Depletion $16,970 $16,970 $53,391 $53,391 $53,391 ($261,084) Loss Carried Forward Credit $0 $0 $0 $0 $0 $455,198 Loss Carried Forward Credit Applied ($16,970) ($16,970) ($53,391) ($53,391) ($53,391) ($194,114) Federal Income Tax (2) 0.34 $0 $0 $0 $0 $0 $0 State Income Tax (2) 0.05 $849 $849 $2,670 $2,670 $2,670 $9,706 ------------------------------------------------------------------- Net Income After Tax $16,122 $16,122 $50,722 $50,722 $50,722 ($270,790) Loss Carried Forward $16,970 $16,970 $53,391 $53,391 $53,391 $194,114 Dep., Depl., & Amort. $26,086 $26,086 $39,287 $39,287 $39,287 $230,759 Deductible Exploration $2,450 $2,450 $2,450 $2,450 $2,450 $34,300 Capital expenditures ($52,250) ($52,250) ($52,250) ($52,250) ($53,900) ($825,290) Reclamation $0 $0 $0 $0 $0 $0 Salvage $0 $0 $0 $0 $0 $0 ------------------------------------------------------------------- NET CASH FLOW $9,377 $9,377 $93,599 $93,599 $91,949 ($636,907) CUMULATIVE CASH FLOW ($925,433) ($916,056) ($822,456) ($728,857) ($636,907) ======================================================================== Total Net Cash Flow of The Project (24 mo.) $92,804 Net Present Value of The Project @ 15% (24 mo.) ($145,359) Net Present Value of The Project @ 10% (24 mo.) ($78,637) (1) Milled ounces vary slightly from Schedule 2 due to rounding. (2) Taxes are calculated using existing federal tax credits. Tax credit base is 7% of $9.0 million or $630,000. 19 NEVADA MANHATTAN MINING, INC. PROJECT REVIEW & BUSINESS PLAN APPENDIX B SCHEDULE 4B - CASH FLOW ANALYSIS - MINE ALL ESTIMATED ORE BLOCKS - COMPLETE REHAB OF WC SHAFT 2ND 12 MONTHS MONTH 13 14 15 !6 - -------------------------------------------------------------------------------------------------------------------- CAPITAL COSTS MINE CONTRACTOR Mobilization/Demobilization Clean-up, resupport Decline Slash entrance to Consolidated Manhattan Drive drift for access to WC49 300 Level (10' x 10" drift, 60 LF @!60/ft) Drive drift for to White Caps shaft (565 Level) (10' x 12" Decline, 400 LF @220/ft) Clean up/ slash corners in Consolidated Manhattan Access to 1,300 Level Rehab WC Shaft to 670 Level Install headframe & hoist at 565 Level Rehab WC Shaft to 800 Level $29,000 $31,000 $31,000 Rehab WC Shaft to 910 Level $25,000 Rehab WC Shaft to 1,300 Level Contractor supervision, overhead & profit $10,000 $10,000 $10,000 $10,000 Subtotal - Mine Contractor $39,000 $41,000 $41,000 $35,000 Other contract work Underground sampling (140 days @$400/d) $4,000 $2,000 $2,000 $4,000 Assays (140 days x 20/d x $15) $3,000 $1,500 $1,500 $3,000 ENGINEERING & CONSULTING WORKING CAPITAL CONTIGENCY @ 10% EXCL. WORKING CAPITAL $4,600 $4,450 $4,450 $4,200 --------------------------------------------------- TOTAL CAPITAL REQUIRED $50,600 $48,950 $48,950 $46,200 ==================================================================================================================== PRODUCTION Area/block WC670/4 WC670/4 WC800/5 WC910/6 WC800/5 WC910/6 WC1,120/7 Ore Production-tons/mo 1,600 1,600 1,600 1,600 Diluted Head Grade - Troy Oz/ton (Au) 0.40 0.40 0.40 0.40 Ounces of gold mined 640.00 640.00 640.00 640.00 Tons of ore milled 1600 1600 1600 1600 Diluted Head Grade to Mill - Troy Oz/ton (Au) 0.40 0.40 0.40 0.40 Ounces of gold milled (1) 640.00 640.00 640.00 640.00 Recovery (81%) 0.81 0.81 0.81 0.81 --------------------------------------------------- Gold Production - Troy Oz. 518 518 518 518 Average Gold Sales Price $/Troy Oz $390 $390 $390 $390 Ref. Chgs $/Troy Oz Au $2 $2 $2 $2 --------------------------------------------------- NET SMELTER RECEIPTS $201,139 $201,139 $201,139 $201,139 ROYALTY ( % of NSR) 0.00% $0 $0 $0 $0 --------------------------------------------------- INCOME AFTER ROYALTY $201,139 $201,139 $201,139 $201,139 =================================================== OPERATING COSTS - $/TON Mining $43 $43 $43 $43 Mine water treatment & pumping $1 $1 $1 $1 Processing & tailings $15 $15 $15 $15 G & A @ 10% $6 $6 $6 $6 --------------------------------------------------- Total Cost $/Ton $65 $65 $65 $65 OPERATING COSTS $104,000 $104,000 $104,000 $104,000 =================================================== DEDUCTIBLE EXPENSES Depreciation Base $720,900 $720,900 $720,900 $720,900 *Depreciation $8,591 $8,591 $8,591 $8,591 Deductible Exploration $4,900 $2,450 $2,450 $4,900 Amort. Non-deduct. Exp. & Dev. $1,050 $525 $525 $1,050 Local taxes 1% $2,011 $2,011 $2,011 $2,011 --------------------------------------------------- Deductible Expenses Before Depletion $16,552 $13,577 $13,577 $16,552 =================================================== Taxable Income Before Depletion $80,587 $83,562 $83,562 $80,587 Maximum allowed depletion - 50% rule $40,294 $41,781 $41,781 $40,294 Depletion at 15% $30,171 $30,171 $30,171 $30,171 Depletion allowed $30,171 $30,171 $30,171 $30,171 *Includes all mine development costs =================================================== TAXES Taxable Income After Depletion $50,416 $53,391 $53,391 $50,416 Loss Carried Forward Credit $0 $0 $0 $0 Loss Carried Forward Credit Applied ($50,416) ($53,391) ($53,391) ($50,416) Federal Income Tax (2) 0.34 $0 $0 $0 $0 State Income Tax (2) 0.05 $2,521 $2,670 $2,670 $2,521 --------------------------------------------------- Net Income After Tax $47,895 $50,722 $50,722 $47,895 Loss Carried Foreward $50,416 $53,391 $53,391 $50,416 Dep.,Depl.,& Amort. $39,812 $39,287 $39,287 $39,812 Deductible Exploration $4,900 $2,450 $2,450 $4,900 Capital expenditures ($50,600) ($48,950) ($48,950) ($46,200) Reclamation $0 $0 $0 $0 Salvage $0 $0 $0 $0 --------------------------------------------------- NET CASH FLOW $92,423 $96,899 $96,899 $96,823 CUMULATIVE CASH FLOW ($544,484) ($447,585) ($350,685) ($253,862) =============================================================== 17 18 19 20 21 - -------------------------------------------------------------------------------------------------------------------- CAPITAL COSTS MINE CONTRACTOR Mobilization/Demobilization Clean-up, resupport Decline Slash entrance to Consolidated Manhattan Drive drift for access to WC49 300 Level (10' x 10" drift, 60 LF @!60/ft) Drive drift for to White Caps shaft (565 Level) (10' x 12" Decline, 400 LF @220/ft) Clean up/ slash corners in Consolidated Manhattan Access to 1,300 Level Rehab WC Shaft to 670 Level Install headframe & hoist at 565 Level Rehab WC Shaft to 800 Level Rehab WC Shaft to 910 Level $25,000 $27,000 Rehab WC Shaft to 1,300 Level $53,000 $55,000 $55,000 Contractor supervision, overhead & profit $10,000 $10,000 $5,000 $5,000 $5,000 Subtotal - Mine Contractor $35,000 $37,000 $58,000 $60,000 $60,000 Other contract work Underground sampling (140 days @$400/d) $2,000 $2,000 $2,000 $2,000 $2,000 Assays (140 days x 20/d x $15) $1,500 $1,500 $1,500 $1,500 $1,500 ENGINEERING & CONSULTING WORKING CAPITAL CONTIGENCY @ 10% EXCL. WORKING CAPITAL $3,850 $4,050 $6,150 $6,350 $6,350 --------------------------------------------------------------- TOTAL CAPITAL REQUIRED $42,350 $44,550 $67,650 $69,850 $69,850 ==================================================================================================================== PRODUCTION Area/block WC1,120/7 WC1,200/8 WC1,200/8 WC1,300/9 Ore Production-tons/mo 1,600 887 Diluted Head Grade - Troy Oz/ton (Au) 0.40 0.44 0.40 0.40 0.40 Ounces of gold mined 640.00 390.28 0.00 0.00 0.00 Tons of ore milled 1600 1600 1600 1600 1600 Diluted Head Grade to Mill - Troy Oz/ton (Au) 0.40 0.40 0.40 0.40 0.40 Ounces of gold milled (1) 640.00 640.00 640.00 640.00 640.00 Recovery (81%) 0.81 0.81 0.81 0.81 0.81 --------------------------------------------------------------- Gold Production - Troy Oz. 518 518 518 518 518 Average Gold Sales Price $/Troy Oz $390 $390 $390 $390 $390 Ref. Chgs $/Troy Oz Au $2 $2 $2 $2 $2 --------------------------------------------------------------- NET SMELTER RECEIPTS $201,139 $201,139 $201,139 $201,139 $201,139 ROYALTY ( % of NSR) $0 $0 $0 $0 $0 --------------------------------------------------------------- INCOME AFTER ROYALTY $201,139 $201,139 $201,139 $201,139 $201,139 =============================================================== OPERATING COSTS - $/TON Mining $43 $43 $43 $43 $43 Mine water treatment & pumping $1 $1 $1 $1 $1 Processing & tailings $15 $15 $15 $15 $15 G & A @ 10% $6 $6 $6 $6 $6 --------------------------------------------------------------- Total Cost $/Ton $65 $65 $65 $65 $65 OPERATING COSTS $104,000 $70,489 $28,800 $28,800 $28,800 =============================================================== DEDUCTIBLE EXPENSES Depreciation Base $1,095,900 $1,095,900 $1,095,900 $1,095,900 $1,095,900 *Depreciation $19,589 $19,589 $19,589 $19,589 $19,589 Deductible Exploration $2,450 $2,450 $2,450 $2,450 $2,450 Amort. Non-deduct. Exp. & Dev. $525 $525 $525 $525 $525 Local taxes $2,011 $2,011 $2,011 $2,011 $2,011 --------------------------------------------------------------- Deductible Expenses Before Depletion $24,576 $24,576 $24,576 $24,576 $24,576 =============================================================== Taxable Income Before Depletion $72,564 $106,075 $147,764 $147,764 $147,764 Maximum allowed depletion - 50% rule $36,282 $53,037 $73,882 $73,882 $73,882 Depletion at 15% $30,171 $30,171 $30,171 $30,171 $30,171 Depletion allowed $30,171 $30,171 $30,171 $30,171 $30,171 *Includes all mine development costs =============================================================== TAXES Taxable Income After Depletion $42,393 $75,904 $117,593 $117,593 $117,593 Loss Carried Forward Credit $0 $0 $0 $0 $0 Loss Carried Forward Credit Applied ($42,393) ($11,077) $0 $0 $0 Federal Income Tax (2) $0 $22,041 $39,982 $39,982 $39,982 State Income Tax (2) $2,120 $3,795 $5,880 $5,880 $5,880 --------------------------------------------------------------- Net Income After Tax $40,273 $50,067 $71,732 $71,732 $71,732 Loss Carried Foreward $42,393 $11,077 $0 $0 $0 Dep.,Depl.,& Amort. $50,285 $50,285 $50,285 $50,285 $50,285 Deductible Exploration $2,450 $2,450 $2,450 $2,450 $2,450 Capital expenditures ($42,350) ($44,550) ($67,650) ($69,850) ($69,850) Reclamation $0 $0 $0 $0 $0 Salvage $0 $0 $0 $0 $0 --------------------------------------------------------------- NET CASH FLOW $93,051 $69,330 $56,817 $54,617 $54,617 CUMULATIVE CASH FLOW ($160,811) ($91,482) ($34,665) $19,952 $74,568 =============================================================== 12 MONTH GRAND 22 23 24 TOTAL TOTAL - -------------------------------------------------------------------------------------------------------------------- CAPITAL COSTS MINE CONTRACTOR Mobilization/Demobilization $30,000 Clean-up, resupport Decline $16,400 Slash entrance to Consolidated Manhattan $2,200 Drive drift for access to WC49 300 Level $9,600 (10' x 10" drift, 60 LF @!60/ft) Drive drift for to White Caps shaft (565 Level) $88,000 (10' x 12" Decline, 400 LF @220/ft) Clean up/ slash corners in Consolidated Manhattan $20,200 Access to 1,300 Level Rehab WC Shaft to 670 Level $73,500 Install headframe & hoist at 565 Level $200,000 Rehab WC Shaft to 800 Level $91,000 $91,000 Rehab WC Shaft to 910 Level $77,000 $77,000 Rehab WC Shaft to 1,300 Level $55,000 $55,000 $273,000 $273,000 Contractor supervision, overhead & profit $5,000 $5,000 $5,000 $90,000 $200,000 Subtotal - Mine Contractor $60,000 $60,000 $5,000 $531,000 $1,080,900 Other contract work Underground sampling (140 days @$400/d) $2,000 $2,000 $2,000 $28,000 $56,000 Assays (140 days x 20/d x $15) $1,500 $1,500 $1,500 $21,000 $42,000 ENGINEERING & CONSULTING $15,000 WORKING CAPITAL $150,000 CONTIGENCY @ 10% EXCL. WORKING CAPITAL $6,350 $6,350 $850 $58,000 $119,390 --------------------------------------------------------------- TOTAL CAPITAL REQUIRED $69,850 $69,850 $9,350 $638,000 $1,463,290 ==================================================================================================================== PRODUCTION Area/block Ore Production-tons/mo 8,887 26,487 Diluted Head Grade - Troy Oz/ton (Au) 0.40 0.40 0.00 0.00 Ounces of gold mined 0.00 0.00 0.00 3,590 9,830 Tons of ore milled 1600 550 0 16,550 26,350 Diluted Head Grade to Mill - Troy Oz/ton (Au) 0.40 0.34 0.00 Ounces of gold milled (1) 640.00 187.00 0.00 6,587 9,827 Recovery (81%) 0.81 0.81 0.81 --------------------------------------------------------------- Gold Production - Troy Oz. 518 151 0 5,335 7,960 Average Gold Sales Price $/Troy Oz $390 $390 $390 Ref. Chgs $/Troy Oz Au $2 $2 $2 --------------------------------------------------------------- NET SMELTER RECEIPTS $201,139 $58,770 $0 $2,070,162 $3,088,430 ROYALTY ( % of NSR) $0 $0 $0 $0 $0 --------------------------------------------------------------- INCOME AFTER ROYALTY $201,139 $58,770 $0 $2,070,162 $3,088,430 =============================================================== OPERATING COSTS - $/TON Mining $43 $43 $43 Mine water treatment & pumping $1 $1 $1 Processing & tailings $15 $15 $15 G & A @ 10% $6 $6 $6 --------------------------------------------------------------- Total Cost $/Ton $65 $65 $65 OPERATING COSTS $28,800 $9,900 $0 $715,589 $1,719,699 =============================================================== DEDUCTIBLE EXPENSES Depreciation Base $1,095,900 $1,095,900 $1,095,900 *Depreciation $19,589 $19,589 $19,589 $191,077 $290,033 Deductible Exploration $2,450 $2,450 $2,450 $34,300 $68,600 Amort. Non-deduct. Exp. & Dev. $525 $525 $525 $7,350 $14,700 Local taxes $2,011 $588 $0 $20,702 $30,884 --------------------------------------------------------------- Deductible Expenses Before Depletion $24,576 $23,152 $22,564 $253,428 $404,217 =============================================================== Taxable Income Before Depletion $147,764 $25,718 ($22,564) $1,101,145 $964,514 Maximum allowed depletion = 50% rule $73,882 $12,859 $0 $561,855 $721,138 Depletion at 15% $30,171 $8,816 $0 $310,524 $446,293 $0 $0 Depletion allowed $30,171 $8,816 $0 $310,524 $434,977 *Includes all mine development costs =============================================================== TAXES Taxable Income After Depletion $117,593 $16,903 ($22,564) $790,621 $529,537 Loss Carried Forward Credit $0 $0 $0 $0 $455,198 Loss Carried Forward Credit Applied $0 $0 $0 ($261,085) $455,198 Federal Income Tax (2) $39,982 $5,747 $0 $187,714 $187,714 State Income Tax (2) $5,880 $845 ($1,128) $39,531 $49,237 --------------------------------------------------------------- Net Income After Tax $71,732 $10,311 ($21,436) $563,376 $292,586 Loss Carried Foreward $0 $0 $0 $261,085 $455,198 Dep.,Depl.,& Amort. $50,285 $28,930 $20,114 $508,951 $739,710 Deductible Exploration $2,450 $2,450 $2,450 $34,300 $68,600 Capital expenditures ($69,850) ($69,850) ($9,350) ($638,000) ($1,463,290) Reclamation $0 $0 $0 $0 $0 Salvage $0 $0 $0 $0 $0 --------------------------------------------------------------- NET CASH FLOW $54,617 ($28,159) ($8,222) $729,711 $92,804 CUMULATIVE CASH FLOW $129,185 $101,025 $92,804 =============================================================== (1) Milled ounces vary slighty from Schedule 2 due to rounding. (2) Taxes are calculated using existing federal tax credits. Tax credit base is 7% of $9.0 mllion or $630,000. 20 NEVADA MANHATTAN MINING COMPANY,INC. PROJECT REVIEW & BUSINESS PLAN APPENDIX B SCHEDULE 4D - CASH FLOW ANALYSIS - MINE ALL ESTIMATED ORE BLOCKS - COMPLETE REHAB OF WC SHAFT $390/oz Gold MONTH 1 2 3 4 =================================================================================================================== CAPITAL COSTS MINE CONTRACTOR Mobilization/Demobilization $30,000 Clean-up, resupport Decline $16,400 Slash entrance to Consolidated Manhattan $2,200 Drive drift for access to WC49 300 Level $9,600 (10' x 10" drift, 60 LF @!60/ft) Drive drift for to White Caps shaft (565 Level) $22,000 $22,000 $22,000 $22,000 (10' x 12" Decline, 400 LF @220/ft) Clean up/ slash corners in Consolidated Manhattan $20,200 Access to 1,300 Level Rehab WC Shaft to 670 Level Install headframe & hoist at 565 Level Rehab WC Shaft to 800 Level Rehab WC Shaft to 910 Level Rehab WC Shaft to 1,300 Level Contractor supervision, overhead & profit $5,000 $5,000 $10,000 $10,000 Subtotal - Mine Contractor $105,400 $27,000 $32,000 $32,000 OTHER CONTRACT WORK Underground sampling (140 days @$400/d) $4,000 $4,000 $2,000 $2,000 Assays (140 days x 20/d x $15) $3,000 $3,000 $1,500 $1,500 ENGINEERING & CONSULTING $15,000 WORKING CAPITAL $50,000 $50,000 $50,000 CONTIGENCY @ 10% EXCL. WORKING CAPITAL $12,740 $3,400 $3,550 $3,550 ---------------------------------------------------- TOTAL CAPITAL REQUIRED $190,140 $87,400 $89,050 $39,050 =================================================================================================================== PRODUCTION Area/block CM/1 CM/1 CM/1 CM/1 WC49/2 Ore Production-tons/mo 800 800 1,600 1,600 Diluted Head Grade - Troy Oz/ton (Au) 0.20 0.20 0.20 0.30 Ounces of gold mined 160.00 160.00 320.00 480.00 Tons of ore milled 0 0 0 0 Diluted Head Grade to Mill - Troy Oz/ton (Au) 0.00 0.00 0.00 0.00 Ounces of gold milled (1) 0.00 0.00 0.00 0.00 Recovery (81%) 0.81 0.81 0.81 0.81 ---------------------------------------------------- Gold Production - Troy Oz. 0 0 0 0 Average Gold Sales Price $/Troy Oz $0 $0 $0 $0 Ref. Chgs $/Troy Oz Au $2 $2 $2 $2 ---------------------------------------------------- NET SMELTER RECEIPTS $0 $0 $0 $0 ROYALTY ( % of NSR) 0.00% $0 $0 $0 $0 ---------------------------------------------------- INCOME AFTER ROYALTY $0 $0 $0 $0 ==================================================== OPERATING COSTS - $/TON Mining $43 $43 $43 $43 Mine water treatment & pumping $1 $1 $1 $1 Processing & tailings $0 $0 $0 $0 G & A @ 10% $4 $4 $4 $4 ---------------------------------------------------- Total Cost $/Ton $48 $48 $48 $48 OPERATING COSTS $36,960 $36,960 $73,920 $73,920 ==================================================== DEDUCTIBLE EXPENSES Depreciation base $211,400 $211,400 $211,400 $211,400 *Depreciation $7,558 $7,558 $7,558 $7,558 Deductible Exploration $4,900 $4,900 $2,450 $2,450 Amort. Non-deduct. Exp. & Dev. $1,050 $1,050 $525 $525 Local taxes 1% $0 $0 $0 $0 ---------------------------------------------------- Deductible Expenses Before Depletion $13,508 $13,508 $10,533 $10,533 ==================================================== Taxable Income Before Depletion ($50,468) ($50,468) ($84,453) ($84,453) Maximum allowed depletion - 50% rule $0 $0 $0 $0 Depletion at 15% $0 $0 $0 $0 Depletion allowed $0 $0 $0 $0 *Includes all mine development costs ==================================================== TAXES Taxable Income After Depletion ($50,468) ($50,468) ($84,453) ($84,453) Loss Carried Forward Credit $50,468 $50,468 $84,453 $84,453 Loss Carried Forward Credit Applied $0 $0 $0 $0 Federal Income Tax (2) 0.34 $0 $0 $0 $0 State Income Tax (2) 0.05 $0 $0 $0 $0 ---------------------------------------------------- Net Income After Tax ($50,468) ($50,468) ($84,453) ($84,453) Loss Carried Foreward $0 $0 $0 $0 Dep.,Depl.,& Amort. $8,608 $8,608 $8,083 $8,083 Deductible Exploration $4,900 $4,900 $2,450 $2,450 Capital expenditures ($190,140) ($87,400) ($89,050) ($39,050) Reclamation $0 $0 $0 $0 Salvage $0 $0 $0 $0 ---------------------------------------------------- NET CASH FLOW ($227,100) ($124,360) ($162,970) ($112,970) CUMULATIVE CASH FLOW ($227,100) ($351,460) ($514,430) ($627,400) ================================================================= Total Net Cash Flow of The Project $92,804 Net Present Value of the Project @ 15% ($145,359) Net Present Value of the Project @ 10% ($78,637) 5 6 7 8 9 =================================================================================================================== CAPITAL COSTS MINE CONTRACTOR Mobilization/Demobilization Clean-up, resupport Decline Slash entrance to Consolidated Manhattan Drive drift for access to WC49 300 Level (10' x 10" drift, 60 LF @!60/ft) Drive drift for to White Caps shaft (565 Level) (10' x 12" Decline, 400 LF @220/ft) Clean up/ slash corners in Consolidated Manhattan Access to 1,300 Level Rehab WC Shaft to 670 Level $9,000 $9,000 $9,000 $9,000 $9,000 Install headframe & hoist at 565 Level $25,000 $25,000 $25,000 $25,000 $25,000 Rehab WC Shaft to 800 Level Rehab WC Shaft to 910 Level Rehab WC Shaft to 1,300 Level Contractor supervision, overhead & profit $10,000 $10,000 $10,000 $10,000 $10,000 Subtotal - Mine Contractor $44,000 $44,000 $44,000 $44,000 $44,000 OTHER CONTRACT WORK Underground sampling (140 days @$400/d) $2,000 $2,000 $2,000 $2,000 $2,000 Assays (140 days x 20/d x $15) $1,500 $1,500 $1,500 $1,500 $1,500 ENGINEERING & CONSULTING WORKING CAPITAL CONTIGENCY @ 10% EXCL. WORKING CAPITAL $4,750 $4,750 $4,750 $4,750 $4,750 ----------------------------------------------------------------- TOTAL CAPITAL REQUIRED $52,250 $52,250 $52,250 $52,250 $52,250 =================================================================================================================== PRODUCTION Area/block WC49/2 WC49/2 WC49/2 WC565/3 WC565/3 WC565/3 Ore Production-tons/mo 1,600 1,600 1,600 1,600 1,600 Diluted Head Grade - Troy Oz/ton (Au) 0.40 0.40 0.40 0.40 0.40 Ounces of gold mined 640.00 640.00 640.00 640.00 640.00 Tons of ore milled 400 400 1000 1600 1600 Diluted Head Grade to Mill - Troy Oz/ton (Au) 0.20 0.20 0.20 0.30 0.30 Ounces of gold milled (1) 80.00 80.00 200.00 480.00 480.00 Recovery (81%) 0.81 0.81 0.81 0.81 0.81 ----------------------------------------------------------------- Gold Production - Troy Oz. 65 65 162 389 389 Average Gold Sales Price $/Troy Oz $390 $390 $390 $390 $390 Ref. Chgs $/Troy Oz Au $2 $2 $2 $2 $2 ----------------------------------------------------------------- NET SMELTER RECEIPTS $25,142 $25,142 $62,856 $150,854 $150,854 ROYALTY ( % of NSR) $0 $0 $0 $0 $0 ----------------------------------------------------------------- INCOME AFTER ROYALTY $25,142 $25,142 $62,856 $150,854 $150,854 ================================================================= OPERATING COSTS - $/TON Mining $43 $43 $43 $43 $43 Mine water treatment & pumping $1 $1 $1 $1 $1 Processing & tailings $20 $20 $15 $15 $15 G & A @ 10% $6 $6 $6 $6 $6 ----------------------------------------------------------------- Total Cost $/Ton $70 $70 $65 $65 $65 OPERATING COSTS $84,800 $84,800 $93,070 $103,840 $103,840 ================================================================= DEDUCTIBLE EXPENSES Depreciation base $720,900 $720,900 $720,900 $720,900 $720,900 *Depreciation $8,591 $8,591 $8,591 $8,591 $8,591 Deductible Exploration $2,450 $2,450 $2,450 $2,450 $2,450 Amort. Non-deduct. Exp. & Dev. $525 $525 $525 $525 $525 Local taxes $251 $251 $629 $1,509 $1,509 ----------------------------------------------------------------- Deductible Expenses Before Depletion $11,817 $11,817 $12,194 $13,074 $13,074 ================================================================= Taxable Income Before Depletion ($71,475) ($71,475) ($42,408) $33,940 $33,940 Maximum allowed depletion - 50% rule $0 $0 $0 $16,970 $16,970 Depletion at 15% $0 $0 $0 $22,628 $22,628 Depletion allowed $0 $0 $0 $16,970 $16,970 *Includes all mine development costs ================================================================= TAXES Taxable Income After Depletion ($71,475) ($71,475) ($42,408) $16,970 $16,970 Loss Carried Forward Credit $71,475 $71,475 $42,408 $0 $0 Loss Carried Forward Credit Applied $0 $0 $0 ($16,970) ($16,970) Federal Income Tax (2) $0 $0 $0 $0 $0 State Income Tax (2) $0 $0 $0 $849 $849 ----------------------------------------------------------------- Net Income After Tax ($71,475) ($71,475) ($42,408) $16,122 $16,122 Loss Carried Foreward $0 $0 $0 $16,970 $16,970 Dep.,Depl.,& Amort. $9,116 $9,116 $9,116 $26,086 $26,086 Deductible Exploration $2,450 $2,450 $2,450 $2,450 $2,450 Capital expenditures ($52,250) ($52,250) ($52,250) ($52,250) ($52,250) Reclamation $0 $0 $0 $0 $0 Salvage $0 $0 $0 $0 $0 ----------------------------------------------------------------- NET CASH FLOW ($112,159) ($112,159) ($83,093) $9,377 $9,377 CUMULATIVE CASH FLOW ($739,559) ($851,718) ($934,811) ($925,433) ($916,056) ================================================================= 10 11 12 13 14 =================================================================================================================== CAPITAL COSTS MINE CONTRACTOR Mobilization/Demobilization Clean-up, resupport Decline Slash entrance to Consolidated Manhattan Drive drift for access to WC49 300 Level (10' x 10" drift, 60 LF @!60/ft) Drive drift for to White Caps shaft (565 Level) (10' x 12" Decline, 400 LF @220/ft) Clean up/ slash corners in Consolidated Manhattan Access to 1,300 Level Rehab WC Shaft to 670 Level $9,000 $9,000 $10,500 Install headframe & hoist at 565 Level $25,000 $25,000 $25,000 Rehab WC Shaft to 800 Level $29,000 $31,000 Rehab WC Shaft to 910 Level Rehab WC Shaft to 1,300 Level Contractor supervision, overhead & profit $10,000 $10,000 $10,000 $10,000 $10,000 Subtotal - Mine Contractor $44,000 $44,000 $45,500 $39,000 $41,000 OTHER CONTRACT WORK Underground sampling (140 days @$400/d) $2,000 $2,000 $2,000 $4,000 $2,000 Assays (140 days x 20/d x $15) $1,500 $1,500 $1,500 $3,000 $1,500 ENGINEERING & CONSULTING WORKING CAPITAL CONTIGENCY @ 10% EXCL. WORKING CAPITAL $4,750 $4,750 $4,900 $4,600 $4,450 ----------------------------------------------------------------- TOTAL CAPITAL REQUIRED $52,250 $52,250 $53,900 $50,600 $48,950 =================================================================================================================== PRODUCTION Area/block WC565/3 WC565/3 WC565/3 WC670/4 WC670/4 WC670/4 WC800/5 Ore Production-tons/mo 1,600 1,600 1,600 1,600 1,600 Diluted Head Grade - Troy Oz/ton (Au) 0.40 0.40 0.40 0.40 0.40 Ounces of gold mined 640.00 640.00 640.00 640.00 640.00 Tons of ore milled 1600 1600 1600 1600 1600 Diluted Head Grade to Mill - Troy Oz/ton (Au) 0.40 0.40 0.40 0.40 0.40 Ounces of gold milled (1) 640.00 640.00 640.00 640.00 640.00 Recovery (81%) 0.81 0.81 0.81 0.81 0.81 ----------------------------------------------------------------- Gold Production - Troy Oz. 518 518 518 518 518 Average Gold Sales Price $/Troy Oz $390 $390 $390 $390 $390 Ref. Chgs $/Troy Oz Au $2 $2 $2 $2 $2 ----------------------------------------------------------------- NET SMELTER RECEIPTS $201,139 $201,139 $201,139 $201,139 $201,139 ROYALTY ( % of NSR) $0 $0 $0 $0 $0 ----------------------------------------------------------------- INCOME AFTER ROYALTY $201,139 $201,139 $201,139 $201,139 $201,139 ================================================================= OPERATING COSTS - $/TON Mining $43 $43 $43 $43 $43 Mine water treatment & pumping $1 $1 $1 $1 $1 Processing & tailings $15 $15 $15 $15 $15 G & A @ 10% $6 $6 $6 $6 $6 ----------------------------------------------------------------- Total Cost $/Ton $65 $65 $65 $65 $65 OPERATING COSTS $104,000 $104,000 $104,000 $104,000 $104,000 ================================================================= DEDUCTIBLE EXPENSES Depreciation base $720,900 $720,900 $720,900 $720,900 $720,900 *Depreciation $8,591 $8,591 $8,591 $8,591 $8,591 Deductible Exploration $2,450 $2,450 $2,450 $4,900 $2,450 Amort. Non-deduct. Exp. & Dev. $525 $525 $525 $1,050 $525 Local taxes $2,011 $2,011 $2,011 $2,011 $2,011 ----------------------------------------------------------------- Deductible Expenses Before Depletion $13,577 $13,577 $13,577 $16,552 $13,577 ================================================================= Taxable Income Before Depletion $83,562 $83,562 $83,562 $80,587 $83,562 Maximum allowed depletion - 50% rule $41,781 $41,781 $41,781 $40,294 $41,781 Depletion at 15% $30,171 $30,171 $30,171 $30,171 $30,171 Depletion allowed $30,171 $30,171 $30,171 $30,171 $30,171 *Includes all mine development costs ================================================================= TAXES Taxable Income After Depletion $53,391 $53,391 $53,391 $50,416 $53,391 Loss Carried Forward Credit $0 $0 $0 $0 $0 Loss Carried Forward Credit Applied ($53,391) ($53,391) ($53,391) ($50,416) ($53,391) Federal Income Tax (2) $0 $0 $0 $0 $0 State Income Tax (2) $2,670 $2,670 $2,670 $2,521 $2,670 ----------------------------------------------------------------- Net Income After Tax $50,722 $50,722 $50,722 $47,895 $50,722 Loss Carried Foreward $53,391 $53,391 $53,391 $50,416 $53,391 Dep.,Depl.,& Amort. $39,287 $39,287 $39,287 $39,812 $39,287 Deductible Exploration $2,450 $2,450 $2,450 $4,900 $2,450 Capital expenditures ($52,250) ($52,250) ($53,900) ($50,600) ($48,950) Reclamation $0 $0 $0 $0 $0 Salvage $0 $0 $0 $0 $0 ----------------------------------------------------------------- NET CASH FLOW $93,599 $93,599 $91,949 $92,423 $96,899 CUMULATIVE CASH FLOW ($822,456) ($728,857) ($636,907) ($544,484) ($447,585) ================================================================= 21 NEVADA MANHATTAN MINING COMPANY,INC. PROJECT REVIEW & BUSINESS PLAN APPENDIX B SCHEDULE 4D - CASH FLOW ANALYSIS - MINE ALL ESTIMATED ORE BLOCKS - COMPLETE REHAB OF WC SHAFT (Continued) 15 16 17 18 ======================================================================================================= CAPITAL COSTS MINE CONTRACTOR Mobilization/Demobilization Clean-up, resupport Decline Slash entrance to Consolidated Manhattan Drive drift for access to WC49 300 Level (10' x 10" drift, 60 LF @!60/ft) Drive drift for to White Caps shaft (565 Level) (10' x 12" Decline, 400 LF @220/ft) Clean up/ slash corners in Consolidated Manhattan Access to 1,300 Level Rehab WC Shaft to 670 Level Install headframe & hoist at 565 Level Rehab WC Shaft to 800 Level $31,000 Rehab WC Shaft to 910 Level $25,000 $25,000 $27,000 Rehab WC Shaft to 1,300 Level Contractor supervision, overhead & profit $10,000 $10,000 $10,000 $10,000 Subtotal - Mine Contractor $41,000 $35,000 $35,000 $37,000 OTHER CONTRACT WORK Underground sampling (140 days @$400/d) $2,000 $4,000 $2,000 $2,000 Assays (140 days x 20/d x $15) $1,500 $3,000 $1,500 $1,500 ENGINEERING & CONSULTING WORKING CAPITAL CONTIGENCY @ 10% EXCL. WORKING CAPITAL $4,450 $4,200 $3,850 $4,050 ---------------------------------------------------- TOTAL CAPITAL REQUIRED $48,950 $46,200 $42,350 $44,550 ====================================================================================================== PRODUCTION Area/block WC800/5 WC910/6 WC1,120/7 WC1,200/8 WC910/6 WC1,120/7 WC1,200/8 WC1,300/9 Ore Production-tons/mo 1,600 1,600 1,600 887 Diluted Head Grade - Troy Oz/ton (Au) 0.40 0.40 0.40 0.44 Ounces of gold mined 640.00 640.00 640.00 390.28 Tons of ore milled 1600 1600 1600 1600 Diluted Head Grade to Mill - Troy Oz/ton (Au) 0.40 0.40 0.40 0.40 Ounces of gold milled (1) 640.00 640.00 640.00 640.00 Recovery (81%) 0.81 0.81 0.81 0.81 ---------------------------------------------------- Gold Production - Troy Oz. 518 518 518 518 Average Gold Sales Price $/Troy Oz $390 $390 $390 $390 Ref. Chgs $/Troy Oz Au $2 $2 $2 $2 ---------------------------------------------------- NET SMELTER RECEIPTS $201,139 $201,139 $201,139 $201,139 ROYALTY ( % of NSR) $0 $0 $0 $0 ---------------------------------------------------- INCOME AFTER ROYALTY $201,139 $201,139 $201,139 $201,139 ==================================================== OPERATING COSTS - $/TON Mining $43 $43 $43 $43 Mine water treatment & pumping $1 $1 $1 $1 Processing & tailings $15 $15 $15 $15 G & A @ 10% $6 $6 $6 $6 ---------------------------------------------------- Total Cost $/Ton $65 $65 $65 $65 OPERATING COSTS $104,000 $104,000 $104,000 $70,489 ==================================================== DEDUCTIBLE EXPENSES Depreciation base $720,900 $720,900 $1,095,900 $1,095,900 *Depreciation $8,591 $8,591 $19,589 $19,589 Deductible Exploration $2,450 $4,900 $2,450 $2,450 Amort. Non-deduct. Exp. & Dev. $525 $1,050 $525 $525 Local taxes $2,011 $2,011 $2,011 $2,011 ---------------------------------------------------- Deductible Expenses Before Depletion $13,577 $16,552 $24,576 $24,576 ==================================================== Taxable Income Before Depletion $83,562 $80,587 $72,564 $106,075 Maximum allowed depletion - 50% rule $41,781 $40,294 $36,282 $53,037 Depletion at 15% $30,171 $30,171 $30,171 $30,171 Depletion allowed $30,171 $30,171 $30,171 $30,171 *Includes all mine development costs ==================================================== TAXES Taxable Income After Depletion $53,391 $50,416 $42,393 $75,904 Loss Carried Forward Credit $0 $0 $0 $0 Loss Carried Forward Credit Applied ($53,391) ($50,416) ($42,393) ($11,077) Federal Income Tax (2) $0 $0 $0 $22,041 State Income Tax (2) $2,670 $2,521 $2,120 $3,795 ---------------------------------------------------- Net Income After Tax $50,722 $47,895 $40,273 $50,067 Loss Carried Foreward $53,391 $50,416 $42,393 $11,077 Dep.,Depl.,& Amort. $39,287 $39,812 $50,285 $50,285 Deductible Exploration $2,450 $4,900 $2,450 $2,450 Capital expenditures ($48,950) ($46,200) ($42,350) ($44,550) Reclamation $0 $0 $0 $0 Salvage $0 $0 $0 $0 ---------------------------------------------------- NET CASH FLOW $96,899 $96,823 $93,051 $69,330 CUMULATIVE CASH FLOW ($350,685) ($253,862) ($160,811) ($91,482) ==================================================== 19 20 21 22 ====================================================================================================== CAPITAL COSTS MINE CONTRACTOR Mobilization/Demobilization Clean-up, resupport Decline Slash entrance to Consolidated Manhattan Drive drift for access to WC49 300 Level (10' x 10" drift, 60 LF @!60/ft) Drive drift for to White Caps shaft (565 Level) (10' x 12" Decline, 400 LF @220/ft) Clean up/ slash corners in Consolidated Manhattan Access to 1,300 Level Rehab WC Shaft to 670 Level Install headframe & hoist at 565 Level Rehab WC Shaft to 800 Level Rehab WC Shaft to 910 Level Rehab WC Shaft to 1,300 Level $53,000 $55,000 $55,000 $55,000 Contractor supervision, overhead & profit $5,000 $5,000 $5,000 $5,000 Subtotal - Mine Contractor $58,000 $60,000 $60,000 $60,000 OTHER CONTRACT WORK Underground sampling (140 days @$400/d) $2,000 $2,000 $2,000 $2,000 Assays (140 days x 20/d x $15) $1,500 $1,500 $1,500 $1,500 ENGINEERING & CONSULTING WORKING CAPITAL CONTIGENCY @ 10% EXCL. WORKING CAPITAL $6,150 $6,350 $6,350 $6,350 ---------------------------------------------------- TOTAL CAPITAL REQUIRED $67,650 $69,850 $69,850 $69,850 ====================================================================================================== PRODUCTION Area/block Ore Production-tons/mo Diluted Head Grade - Troy Oz/ton (Au) 0.40 0.40 0.40 0.40 Ounces of gold mined 0.00 0.00 0.00 0.00 Tons of ore milled 1600 1600 1600 1600 Diluted Head Grade to Mill - Troy Oz/ton (Au) 0.40 0.40 0.40 0.40 Ounces of gold milled (1) 640.00 640.00 640.00 640.00 Recovery (81%) 0.81 0.81 0.81 0.81 ---------------------------------------------------- Gold Production - Troy Oz. 518 518 518 518 Average Gold Sales Price $/Troy Oz $390 $390 $390 $390 Ref. Chgs $/Troy Oz Au $2 $2 $2 $2 ---------------------------------------------------- NET SMELTER RECEIPTS $201,139 $201,139 $201,139 $201,139 ROYALTY ( % of NSR) $0 $0 $0 $0 ---------------------------------------------------- INCOME AFTER ROYALTY $201,139 $201,139 $201,139 $201,139 ==================================================== OPERATING COSTS - $/TON Mining $43 $43 $43 $43 Mine water treatment & pumping $1 $1 $1 $1 Processing & tailings $15 $15 $15 $15 G & A @ 10% $6 $6 $6 $6 ---------------------------------------------------- Total Cost $/Ton $65 $65 $65 $65 OPERATING COSTS $28,800 $28,800 $28,800 $28,800 ==================================================== DEDUCTIBLE EXPENSES Depreciation base $1,095,900 $1,095,900 $1,095,900 $1,095,900 *Depreciation $19,589 $19,589 $19,589 $19,589 Deductible Exploration $2,450 $2,450 $2,450 $2,450 Amort. Non-deduct. Exp. & Dev. $525 $525 $525 $525 Local taxes $2,011 $2,011 $2,011 $2,011 ---------------------------------------------------- Deductible Expenses Before Depletion $24,576 $24,576 $24,576 $24,576 ==================================================== Taxable Income Before Depletion $147,764 $147,764 $147,764 $147,764 Maximum allowed depletion - 50% rule $73,882 $73,882 $73,882 $73,882 Depletion at 15% $30,171 $30,171 $30,171 $30,171 Depletion allowed $30,171 $30,171 $30,171 $30,171 *Includes all mine development costs ==================================================== TAXES Taxable Income After Depletion $117,593 $117,593 $117,593 $117,593 Loss Carried Forward Credit $0 $0 $0 $0 Loss Carried Forward Credit Applied $0 $0 $0 $0 Federal Income Tax (2) $39,982 $39,982 $39,982 $39,982 State Income Tax (2) $5,880 $5,880 $5,880 $5,880 ---------------------------------------------------- Net Income After Tax $71,732 $71,732 $71,732 $71,732 Loss Carried Foreward $0 $0 $0 $0 Dep.,Depl.,& Amort. $50,285 $50,285 $50,285 $50,285 Deductible Exploration $2,450 $2,450 $2,450 $2,450 Capital expenditures ($67,650) ($69,850) ($69,850) ($69,850) Reclamation $0 $0 $0 $0 Salvage $0 $0 $0 $0 ---------------------------------------------------- NET CASH FLOW $56,817 $54,617 $54,617 $54,617 CUMULATIVE CASH FLOW ($34,665) $19,952 $74,568 $129,185 ==================================================== 23 24 TOTAL ========================================================================================= CAPITAL COSTS MINE CONTRACTOR Mobilization/Demobilization $30,000 Clean-up, resupport Decline $16,400 Slash entrance to Consolidated Manhattan $2,200 Drive drift for access to WC49 300 Level $9,600 (10' x 10" drift, 60 LF @!60/ft) Drive drift for to White Caps shaft (565 Level) $88,000 (10' x 12" Decline, 400 LF @220/ft) Clean up/ slash corners in Consolidated Manhattan $20,200 Access to 1,300 Level Rehab WC Shaft to 670 Level $73,500 Install headframe & hoist at 565 Level $200,000 Rehab WC Shaft to 800 Level $91,000 Rehab WC Shaft to 910 Level $77,000 Rehab WC Shaft to 1,300 Level $55,000 $273,000 Contractor supervision, overhead & profit $5,000 $5,000 $200,000 Subtotal - Mine Contractor $60,000 $5,000 $1,080,900 OTHER CONTRACT WORK Underground sampling (140 days @$400/d) $2,000 $2,000 $56,000 Assays (140 days x 20/d x $15) $1,500 $1,500 $42,000 ENGINEERING & CONSULTING $15,000 WORKING CAPITAL $150,000 CONTIGENCY @ 10% EXCL. WORKING CAPITAL $6,350 $850 $119,390 --------------------------------------- TOTAL CAPITAL REQUIRED $69,850 $9,350 $1,463,290 ========================================================================================= PRODUCTION Area/block Ore Production-tons/mo 26,487 Diluted Head Grade - Troy Oz/ton (Au) 0.40 0.00 Ounces of gold mined 0.00 0.00 9,830 Tons of ore milled 550 0 26,350 Diluted Head Grade to Mill - Troy Oz/ton (Au) 0.34 0.00 Ounces of gold milled (1) 187.00 0.00 9,827 Recovery (81%) 0.81 0.81 --------------------------------------- Gold Production - Troy Oz. 151 0 7,960 Average Gold Sales Price $/Troy Oz $390 $390 Ref. Chgs $/Troy Oz Au $2 $2 --------------------------------------- NET SMELTER RECEIPTS $58,770 $0 $3,088,430 ROYALTY ( % of NSR) $0 $0 $0 --------------------------------------- INCOME AFTER ROYALTY $58,770 $0 $3,088,430 ======================================= OPERATING COSTS - $/TON Mining $43 $43 Mine water treatment & pumping $1 $1 Processing & tailings $15 $15 G & A @ 10% $6 $6 --------------------------------------- Total Cost $/Ton $65 $65 OPERATING COSTS $9,900 $0 $1,719,699 ======================================= DEDUCTIBLE EXPENSES Depreciation base $1,095,900 $1,095,900 *Depreciation $19,589 $19,589 $290,033 Deductible Exploration $2,450 $2,450 $68,600 Amort. Non-deduct. Exp. & Dev. $525 $525 $14,700 Local taxes $588 $0 $30,884 --------------------------------------- Deductible Expenses Before Depletion $23,152 $22,564 $404,217 ======================================= Taxable Income Before Depletion $25,718 ($22,564) $964,514 Maximum allowed depletion - 50% rule $12,859 $0 $721,138 Depletion at 15% $8,816 $0 $446,293 Depletion allowed $8,816 $0 $434,977 *Includes all mine development costs ======================================= TAXES Taxable Income After Depletion $16,903 ($22,564) $529,537 Loss Carried Forward Credit $0 $0 $455,198 Loss Carried Forward Credit Applied $0 $0 $455,198 Federal Income Tax (2) $5,747 $0 $187,714 State Income Tax (2) $845 ($1,128) $49,237 --------------------------------------- Net Income After Tax $10,311 ($21,436) $292,586 Loss Carried Foreward $0 $0 $455,198 Dep., Depl.,& Amort. $28,930 $20,114 $739,710 Deductible Exploration $2,450 $2,450 $68,600 Capital Expenditures ($69,850) ($9,350) ($1,463,290) Reclamation $0 $0 $0 Salvage $0 $0 $0 --------------------------------------- NET CASH FLOW ($28,159) ($8,222) $92,804 CUMULATIVE CASH FLOW $101,025 $92,804 ======================================= (1) Milled ounces vary slightly from Schedule 2 due to rounding. (2) Taxes are calculated using existing federal tax credits. Tax credit base is 7% of $9.0 million or $630,000. 22 NEVADA MANHATTAN MINING, INC. PROJECT REVIEW & BUSINESS PLAN APPENDIX B SCHEDULE 5 - CASH FLOW ANALYSIS - MINE ESTIMATED ORE BLOCKS DOWN TO AND INCLUDING 565 LEVEL $390/oz Gold MONTH 1 2 3 4 =================================================================================================================== CAPITAL COSTS Mine Contractor Mobilization/Demobilization $30,000 Clean-up, resupport Decline $16,400 Slash entrance to Consolidated Manhattan $2,200 Drive drift for access to WC49 300 Level $9,600 (10' x 10" drift, 60 LF @!60/ft) Drive drift for to White Caps shaft (565 Level) $22,000 $22,000 $22,000 $22,000 (10' x 12" Decline, 400 LF @220/ft) Clean up/slash corners in Consolidated Manhattan $20,200 Provide add. ventilation for White Caps levels Contractor supervision, overhead & profit $5,000 $5,000 $10,000 $10,000 Subtotal - Mine Contractor $105,400 $27,000 $32,000 $32,000 Other contract work Underground sampling (140 days @$400/d) $4,000 $4,000 $4,000 $2,000 Assays (140 days x 20/d x $15) $3,000 $3,000 $3,000 $1,500 Engineering & Consulting $15,000 Working Capital $50,000 $50,000 $50,000 Contigency @ 10% Excl. Working Capital $12,740 $3,400 $3,900 $3,550 ---------------------------------------------------- TOTAL CAPITAL REQUIRED $190,140 $87,400 $92,900 $39,050 =================================================================================================================== PRODUCTION Area/block CM/1 CM/1 CM/1 CM/1 WC49/2 Ore Production-tons/mo 800 800 1,600 1,600 Diluted Head Grade - Troy Oz/ton (Au) 0.20 0.20 0.20 0.30 Ounces of gold mined 160.00 160.00 320.00 480.00 Tons of ore milled 0 0 0 0 Diluted Head Grade to Mill - Troy Oz/ton (Au) 0.00 0.00 0.00 0.00 Ounces of gold milled (1) 0.00 0.00 0.00 0.00 Recovery (81%) 0.81 0.81 0.81 0.81 ---------------------------------------------------- Gold Production - Troy Oz 0 0 0 0 Average Gold Sales Price $/Troy Oz $390 $390 $390 $390 Ref. Chgs $/Troy Oz Au $2 $2 $2 $2 ---------------------------------------------------- NET SMELTER RECEIPTS $0 $0 $0 $0 ROYALTY (% of NSR) 0.00% $0 $0 $0 $0 ---------------------------------------------------- INCOME AFTER ROYALTY $0 $0 $0 $0 ==================================================== OPERATING COSTS - $/TON Mining $43 $43 $43 $43 Mine water treatment & pumping $1 $1 $1 $1 Processing & tailings $0 $0 $0 $0 G & A @ 10% $4 $4 $4 $4 ---------------------------------------------------- Total Cost $/Ton $48 $48 $48 $48 ANNUAL OPERATING COSTS $36,960 $36,960 $73,920 $73,920 ==================================================== DEDUCTIBLE EXPENSES Depreciation Base $211,400 $211,400 $211,400 $211,400 *Depreciation $7,558 $7,558 $7,558 $7,558 Deductible Exploration $4,900 $4,900 $4,900 $2,450 Amort. Non-deduct. Exp. & Dev. $1,050 $1,050 $1,050 $525 Local taxes 1% $0 $0 $0 $0 ---------------------------------------------------- Deductible Expenses Before Depletion $13,508 $13,508 $13,508 $10,533 ==================================================== Taxable Income Before Depletion ($50,468) ($50,468) ($87,428) ($84,453) Maximum allowed depletion - percentage $0 $0 $0 $0 Depletion at 15% $0 $0 $0 $0 Depletion allowed $0 $0 $0 $0 *Includes all mine development costs ==================================================== TAXES Taxable Income After Depletion ($50,468) ($50,468) ($87,428) ($84,453) Loss Carried Forward Credit $50,468 $50,468 $87,428 $84,453 Loss Carried Forward Credit Applied $0 $0 $0 $0 Federal Income Tax (2) 0.34 $0 $0 $0 $0 State Income Tax (2) 0.05 $0 $0 $0 $0 ---------------------------------------------------- Net Income After Tax ($50,468) ($50,468) ($87,428) ($84,453) Loss Carried Forward $0 $0 $0 $0 Dep., Depl., & Amort. $8,608 $8,608 $8,608 $8,083 Deductible Exploration $4,900 $4,900 $4,900 $2,450 Capital expenditures ($190,140) ($87,400) ($92,900) ($39,050) Reclamation $0 $0 $0 $0 Salvage $0 $0 $0 $0 ---------------------------------------------------- NET CASH FLOW ($227,100) ($124,360) ($166,820) ($112,970) CUMULATIVE CASH FLOW ($227,100) ($351,460) ($518,280) ($631,250) ================================================================= Total Net Cash Flow of The Project $425,326 Net Present Value of The Project @ 15% $299,526 Net Present Value of The Project @ 10% $339,152 NEVADA MANHATTAN MINING, INC. PROJECT REVIEW & BUSINESS PLAN APPENDIX B SCHEDULE 5 - CASH FLOW ANALYSIS - MINE ESTIMATED ORE BLOCKS DOWN TO AND INCLUDING 565 LEVEL 5 6 7 8 9 =================================================================================================================== CAPITAL COSTS Mine Contractor Mobilization/Demobilization Clean-up, resupport Decline Slash entrance to Consolidated Manhattan Drive drift for access to WC49 300 Level (10' x 10" drift, 60 LF @!60/ft) Drive drift for to White Caps shaft (565 Level) (10' x 12" Decline, 400 LF @220/ft) Clean up/slash corners in Consolidated Manhattan Provide add. ventilation for White Caps levels $25,000 Contractor supervision, overhead & profit $10,000 $10,000 $10,000 $10,000 $10,000 Subtotal - Mine Contractor $35,000 $10,000 $10,000 $10,000 $10,000 Other contract work Underground sampling (140 days @$400/d) $2,000 $6,000 $6,000 $6,000 $6,000 Assays (140 days x 20/d x $15) $1,500 $4,500 $4,500 $4,500 $4,500 Engineering & Consulting Working Capital Contigency @ 10% Excl. Working Capital $3,850 $2,050 $2,050 $2,050 $2,050 ----------------------------------------------------------------- TOTAL CAPITAL REQUIRED $42,350 $22,550 $22,550 $22,550 $22,550 =================================================================================================================== PRODUCTION Area/block WC49/2 WC49/2 WC49/2 WC565/3 WC565/3 WC565/3 Ore Production-tons/mo 1,600 1,600 1,600 1,600 1,600 Diluted Head Grade - Troy Oz/ton (Au) 0.40 0.40 0.40 0.40 0.40 Ounces of gold mined 640.00 640.00 640.00 640.00 640.00 Tons of ore milled 400 400 1000 1600 2400 Diluted Head Grade to Mill - Troy Oz/ton (Au) 0.20 0.20 0.20 0.30 0.30 Ounces of gold milled (1) 80.00 80.00 200.00 480.00 720.00 Recovery (81%) 0.81 0.81 0.81 0.81 0.81 ----------------------------------------------------------------- Gold Production - Troy Oz 65 65 162 389 583 Average Gold Sales Price $/Troy Oz $390 $390 $390 $390 $390 Ref. Chgs $/Troy Oz Au $2 $2 $2 $2 $2 ----------------------------------------------------------------- NET SMELTER RECEIPTS $25,142 $25,142 $62,856 $150,854 $226,282 ROYALTY (% of NSR) $0 $0 $0 $0 $0 ----------------------------------------------------------------- INCOME AFTER ROYALTY $25,142 $25,142 $62,856 $150,854 $226,282 ================================================================= OPERATING COSTS - $/TON Mining $43 $43 $43 $43 $43 Mine water treatment & pumping $1 $1 $1 $1 $1 Processing & tailings $20 $20 $15 $15 $15 G & A @ 10% $6 $6 $6 $6 $6 ----------------------------------------------------------------- Total Cost $/Ton $70 $70 $65 $65 $65 ANNUAL OPERATING COSTS $84,800 $84,800 $93,070 $103,840 $118,200 ================================================================= DEDUCTIBLE EXPENSES Depreciation Base $316,400 $316,400 $316,400 $316,400 $316,400 *Depreciation $5,656 $5,656 $5,656 $5,656 $5,656 Deductible Exploration $2,450 $7,350 $7,350 $7,350 $7,350 Amort. Non-deduct. Exp. & Dev. $525 $1,575 $1,575 $1,575 $1,575 Local taxes $251 $251 $629 $1,509 $2,263 ----------------------------------------------------------------- Deductible Expenses Before Depletion $8,882 $14,832 $15,209 $16,089 $16,843 ================================================================= Taxable Income Before Depletion ($68,540) ($74,490) ($45,423) $30,925 $91,238 Maximum allowed depletion - percentage $0 $0 $0 $15,463 $45,619 Depletion at 15% $0 $0 $0 $22,628 $33,942 Depletion allowed $0 $0 $0 $15,463 $45,619 *Includes all mine development costs ================================================================= TAXES Taxable Income After Depletion ($68,540) ($74,490) ($45,423) $15,463 $45,619 Loss Carried Forward Credit $68,540 $74,490 $45,324 $0 $0 Loss Carried Forward Credit Applied $0 $0 $0 ($15,463) ($45,619) Federal Income Tax (2) $0 $0 $0 $0 $0 State Income Tax (2) $0 $0 $0 $773 $2,281 ----------------------------------------------------------------- Net Income After Tax ($68,540) ($74,490) ($45,423) $14,689 $43,338 Loss Carried Forward $0 $0 $0 $15,463 $45,619 Dep., Depl., & Amort. $6,181 $7,231 $7,231 $22,693 $52,850 Deductible Exploration $2,450 $7,350 $7,350 $7,350 $7,350 Capital expenditures ($42,350) ($22,550) ($22,550) ($22,550) ($22,550) Reclamation $0 $0 $0 $0 $0 Salvage $0 $0 $0 $0 $0 ----------------------------------------------------------------- NET CASH FLOW ($102,259) ($82,459) ($53,393) $37,645 $126,607 CUMULATIVE CASH FLOW ($733,509) ($815,968) ($869,361) ($831,715) ($705,108) ================================================================= NEVADA MANHATTAN MINING, INC. PROJECT REVIEW & BUSINESS PLAN APPENDIX B SCHEDULE 5 - CASH FLOW ANALYSIS - MINE ESTIMATED ORE BLOCKS DOWN TO AND INCLUDING 565 LEVEL 10 11 12 TOTAL ====================================================================================================== CAPITAL COSTS Mine Contractor Mobilization/Demobilization $30,000 Clean-up, resupport Decline $16,400 Slash entrance to Consolidated Manhattan $2,200 Drive drift for access to WC49 300 Level $9,600 (10' x 10" drift, 60 LF @!60/ft) Drive drift for to White Caps shaft (565 Level) $88,000 (10' x 12" Decline, 400 LF @220/ft) Clean up/slash corners in Consolidated Manhattan $20,200 Provide add. ventilation for White Caps levels $25,000 Contractor supervision, overhead & profit $10,000 $10,000 $10,000 $110,000 Subtotal - Mine Contractor $10,000 $10,000 $10,000 $301,400 Other contract work Underground sampling (140 days @$400/d) $6,000 $6,000 $4,000 $56,000 Assays (140 days x 20/d x $15) $4,500 $4,500 $3,000 $42,000 Engineering & Consulting $15,000 Working Capital $150,000 Contigency @ 10% Excl. Working Capital $2,050 $2,050 $1,700 $41,440 ---------------------------------------------------- TOTAL CAPITAL REQUIRED $22,550 $22,550 $18,700 $605,840 ====================================================================================================== PRODUCTION Area/block WC565/3 WC565/3 WC565/3 Ore Production-tons/mo 1,600 1,600 119 16,119 Diluted Head Grade - Troy Oz/ton (Au) 0.40 0.40 0.40 Ounces of gold mined 640.00 640.00 47.60 5,648 Tons of ore milled 3000 3600 3600 16,000 Diluted Head Grade to Mill - Troy Oz/ton (Au) 0.40 0.40 0.40 Ounces of gold milled (1) 1200.00 1440.00 1440.00 5,640 Recovery (81%) 0.81 0.81 0.81 ---------------------------------------------------- Gold Production - Troy Oz 972 1,166 1,166 4,568 Average Gold Sales Price $/Troy Oz $390 $390 $390 Ref. Chgs $/Troy Oz Au $2 $2 $2 ---------------------------------------------------- NET SMELTER RECEIPTS $377,136 $452,563 $452,563 $1,772,539 ROYALTY (% of NSR) $0 $0 $0 $0 ---------------------------------------------------- INCOME AFTER ROYALTY $377,136 $452,563 $452,563 $1,772,539 ==================================================== OPERATING COSTS - $/TON Mining $43 $43 $43 Mine water treatment & pumping $1 $1 $1 Processing & tailings $15 $15 $15 G & A @ 10% $6 $6 $6 ---------------------------------------------------- Total Cost $/Ton $65 $65 $65 ANNUAL OPERATING COSTS $129,200 $140,000 $70,393 $1,046,063 ==================================================== DEDUCTIBLE EXPENSES Depreciation Base $316,400 $316,400 $316,400 *Depreciation $5,656 $5,656 $5,656 $75,475 Deductible Exploration $7,350 $7,350 $4,900 $41,650 Amort. Non-deduct. Exp. & Dev. $1,575 $1,575 $1,050 $8,925 Local taxes $3,771 $4,526 $4,526 $17,725 ---------------------------------------------------- Deductible Expenses Before Depletion $18,352 $19,106 $16,131 $176,501 ==================================================== Taxable Income Before Depletion $229,584 $293,457 $366,039 $549,975 Maximum allowed depletion - percentage $114,792 $146,728 $183,019 $505,622 Depletion at 15% $56,570 $67,884 $67,884 $248,910 Depletion allowed $56,570 $67,884 $67,884 $253,421 *Includes all mine development costs ==================================================== TAXES Taxable Income After Depletion $173,014 $225,572 $298,154 $296,554 Loss Carried Forward Credit $0 $0 $0 $461,169 Loss Carried Forward Credit Applied ($173,014) ($225,572) ($1,501) $461,169 Federal Income Tax (2) $0 $0 $100,862 $100,862 State Income Tax (2) $8,651 $11,279 $14,908 $37,891 ---------------------------------------------------- Net Income After Tax $164,363 $214,294 $182,385 $157,801 Loss Carried Forward $173,014 $225,572 $1,501 $461,169 Dep., Depl., & Amort. $63,801 $75,115 $74,590 $343,596 Deductible Exploration $7,350 $7,350 $4,900 $68,600 Capital expenditures ($22,550) ($22,550) ($18,700) ($605,840) Reclamation $0 $0 $0 $0 Salvage $0 $0 $0 $0 ---------------------------------------------------- NET CASH FLOW $385,978 $499,781 $244,676 $425,326 CUMULATIVE CASH FLOW ($319,131) $180,651 $425,326 ==================================================== (1) Milled ounces vary slightly from Schedule 2 due to rounding. (2) Taxes are calculated using existing federal tax credits. Tax credit base is 7% of $9.0 million or $630,000. 23 APPENDIX C MILL INFORMATION June 21, 1995 letter from Dale Moore to Mr. Wilson regarding the proposed flow sheet for the New Concept Mining, Inc. mill. Undated equipment list for the New Concept Mining, Inc. mill. 13 24 June 21, 1995 Dear Mr. Wilson The Primary Crushing will be done at the mine site with a Portable Crusher, which consists of a 18"x 34" Jaw Crusher and a 24" Roll Crusher. The secondary crushing will be done at the Mill with a 3' short head Crusher. The Grinding Circuit will consist of 2 Ball Mills, one a 7'x9' Marcy for the Primary grind and a 4'x8' Marcy for the Regrind Mill. The underflow from the 8" Cyclones will go to a 2'x4' 2 cell Jig. The overflow will go to a 30' thickner. The Slurry will be thickened to 45 to 50% solids before it is pumped to the leach tanks. The first leach tank will be a Pachuca Tank. The Mids from the Jig will go to the tables (5-5'x7' Diester) product from the tables will go to the refinery. Tails from the leach circuit will go to the Floatation Cells (8 48" Denvers) product from the floats will go to a 12' thickner, then to a 2 Leaf Filter. It is impossible to design a balanced flow sheet when the equipment has not been purchased and the "Wheels" keep changing their minds as to what they want. The equipment list that I am sending to you is a bare minimum that will be needed and what I recommended that be purchased. The Strip Circuit and EW Cells are in storage in Las Vegas. All S.S. Steel and Custom made. I inspected this Circuit on June 16, 1995 and it is in very good condition and it is complete with EW Cells and Rectifiers. The water well will produce 50 gpm Fresh water usage in the Mill, will be approx. 20 gpm. The information that I am sending you is not exactly what you requested, but it is all that I have at this time and I hope it will be of some use to you. Sincerely, /s/ DALE MOORE ------------------------------------ Dale Moore 25 EQUIPMENT 1. PORTABLE CRUSHING PLANT (AT THE MINE SITE) 18" X 34" JAW CRUSHER 24" ROLL CRUSHER CONVEYORS (MILL SITE) 1. 3 FOOT SHORT HEAD KUE-KEN 100 H.P. 2. 100 TON FINE ORE STORAGE BIN 3. 18" X 6' BELT FEEDER 4. 24" X 34' FINE ORE CONVEYOR 5. BELT SCALES 6. 7' X 9' MARCY BALL MILL (INSTALLED IN MILL) ALREADY 7. 4" X 3" SLURRY PUMP & SUMP BOX 8. 4-8" CYCLONES & BOXES 9. 2' X 4' DECO JIG 10. 2" X 3" SLURRY PUMP 11. 30' THICKNER TANK 12. 6" O.D.s PUMP 13. 4- 12' X 18' LEACH TANKS WITH ADAPTER MECH ALREADY INSTALLED 14. 4' X 8' MARCY REGRIND MILL W/100 H.P. MOTOR & GEAR BOX 15. 5- 5' X 7' DIESTER TABLES 16. 2 X 3 SLURRY PUMP 17. AIR COMPRESSOR 18. NACN MIXING TANK (12,000 GAL) 19. LIME MIXING TANK (3,000 GAL) 20. LIME SLAKING MILL (2' X 2' BALL MILL) ? 21. NACN PUMP (POSITIVE DISPLACENT) 1" X 1 1/2" 22. REFINERY FURNACE (125 CRUCIBLE) 23. 2- RECTIFIERS (50 AMP) 110-220 24. STRIPPING PLANT SS STEEL, STRIP TANK, EW CELL CUSTOM MADE IN LAS VEGAS (USED) AVAILABLE 25. PUMPS FOR STRIPPING PLANT 1.5" X 1" SOLUTION PUMP 1" X 1" SOLUTION PUMP FEED TO E.W. CELLS 26. SECURITY SYSTEM FOR REFINERY 27. MISC. PIPING & PUMPS 28. PULP DENSITY SCALES 29. 25' CLARIFIER FOR ATG WASTE WATER TREATMENT SYSTEM 30. A.T.G. WASTE WATER SYSTEM 31. 3" GALIGER SUMP PUMP 32. 12 DENVER FLOAT CELLS (48") 33. 15' THICKNER TANK W/MECH 34. 2' LEAF FILTER W/BLOWER 26 LAB EQUIPMENT 1. RO-TAP AND SCREENS 2. CHIPMUNK LAB CRUSHER 3" X 6" 3. ROLL CRUSHER (6" X 8") 4. PULVERIZER 5. METTLER BALANCE 6. CAHN MICRO-BALANCE 7. HOT PLATES 8. LAB TABLES 9. VENT HOODS 10. CUPPLING FURNACE 11. CRUCIBLE FURNACE 12. MISC GLASS WARE