1
EXHIBIT NO. 10(C)








                              DEVELOPMENT AGREEMENT
                              ---------------------

                                 BY AND BETWEEN

                        GP OHIO, L.L.C. (AS "DEVELOPER")

                                       AND

            PROGRESSIVE CASUALTY INSURANCE COMPANY (AS "PROGRESSIVE")




   2




                                TABLE OF CONTENTS
                                -----------------


1.  Recitals Incorporated......................................................1

2.  The Project................................................................1

3.  Changes in the Work........................................................4

4.  Developer's Compliance Responsibilities....................................5

5.  Construction Timetable.....................................................5

6.  Progress Payments..........................................................7

7.  Stipulated Sum.............................................................8

8.  Insurance.................................................................10

9.  Architect, Engineer and Other Professionals...............................10

10.  Payment and Performance Bonds............................................11

11.  Delay Damages............................................................11

12.  Termination of Agreement.................................................11

13.  Dispute Resolution.......................................................12

14.  Warranties...............................................................13

15.  Lien Removal.............................................................14

16.  Progressive Delay........................................................15

17.  Force Majeure............................................................15

18.  Indemnification..........................................................16

19.  Non-Developer Work.......................................................16

20.  Maintain Project.........................................................17

21.  Governing Law............................................................17

22.  Notices..................................................................17
   3

23.  Progressive's Authorized Representative/Consultant.......................18

24.  Successors and Assigns...................................................18

25.  Regulated Substances.....................................................18

26.  Time of the Essence......................................................19

27.  Independent Contractor...................................................19

28.  No Waiver................................................................19

29.  Severability.............................................................19

30.  Cooperation..............................................................19

31.  Counterparts.............................................................19

32.  Interest.................................................................19

33.  Entire Agreement.........................................................20

34.  Intentionally left blank.................................................20

35.  Termination..............................................................20

36.  Facsimile Signatures.....................................................20

37.  Contingency..............................................................20





EXHIBITS:

EXHIBIT A         Site Plan/Survey..............................................

EXHIBIT B         Description of Building and Outline Specifications, Schematic
                  Building Plans and Master Site Plan...........................

EXHIBIT C         Project Schedule..............................................

EXHIBIT D         Termination Fee Schedule......................................

EXHIBIT E         Expense Categories............................................

EXHIBIT F         Notice of Commencement........................................


                                       ii

   4




                              DEVELOPMENT AGREEMENT
                              ---------------------


         This Development Agreement ("AGREEMENT"), made and entered into as of
the 16th day of November, 1999, by and between GP Ohio, L.L.C., a Rhode Island
limited liability company ("Developer"), and Progressive Casualty Insurance
Company, an Ohio corporation ("Progressive").

                              W I T N E S S E T H:

         WHEREAS, Progressive has acquired the fee interest in certain parcel(s)
of land, located in Mayfield Village, Ohio, as more particularly depicted on the
site plan attached hereto as EXHIBIT A ("Property") and desires to have
developed on the Property a data center and operations facility ("Building")
containing approximately 80,000 square feet of gross rentable space and
incidental improvements, including surface parking of approximately 70 spaces
and landscaping;

         WHEREAS, Developer will oversee, develop and construct the improvements
more particularly delineated herein in a timely manner;

         WHEREAS, Developer and Progressive desire to set forth their
understanding of the respective rights and responsibilities of the parties in
connection with the development, design, construction, equipping and furnishing
of the Project (hereinafter defined) and the payment for such services; and

         WHEREAS, the obligations of Developer hereunder are being guaranteed by
Gilbane Properties, Inc.

         NOW, THEREFORE, in consideration of the mutual covenants set forth
herein, and intending to be legally bound hereby, the parties do hereby agree as
follows:

         1. RECITALS INCORPORATED. The recitals are hereby incorporated by
reference and made a part of this Agreement.

         2. THE PROJECT. Developer shall cause the completion of the design,
construction and development of the Building upon the Property consisting of the
base building elements (including parking) and interior improvements and the
site work on the Property consisting of landscaping, sidewalks, driveways and
related improvements, the preliminary scope of which is outlined on EXHIBIT B
attached hereto and as shall be outlined in the Scope Documents to be prepared
and approved in accordance with Section 2(b), below (collectively, the
"Project") all in accordance with the final set of approved plans, drawings,
specifications and schedules (collectively the "Plans"). As part of the "Work"
defined below, Developer (A) shall advise Progressive and take the lead in
negotiating and obtaining all governmental and private approvals necessary or
required in connection with acquiring the Property, (B) shall enter into a


   5

construction contract with Gilbane Building Company ("Contractor"), which
Contractor shall hire subcontractors for construction of the Project, (C) shall
retain, or cause to be retained, (x) Burt Hill Kosar Rittlemann Assoc., as
architect ("Architect") to perform architectural and design services, and (y) H.
F. Lenz, as engineers ("Engineer"), and other professionals to perform all other
professional services required for the design and construction of the Project
and (D) shall advise Progressive and take the lead in negotiating and obtaining
all governmental subsidies. The contract with Contractor shall provide for
payment to Contractor of a profits fee of 2% for contractor management services.
All major subcontractors and equipment suppliers retained by Contractor shall be
identified on a list submitted to Progressive for Progressive's approval within
ten days after the date of execution of this Agreement. Progressive shall not
unreasonably withhold or unduly delay its approval of the list of such major
subcontractors and equipment suppliers. If Progressive timely objects to any
major subcontractor or equipment supplier, Progressive, Developer and Contractor
shall in good faith attempt to resolve their disagreement. If the parties are
unable to reach agreement on the list of major subcontractors and equipment
suppliers within a reasonable period, the matter shall be submitted to mediation
as provided in Section 13.

                  (a) The "Work" shall mean all professional design and
         engineering services and project administration for, and the completed
         new construction of, the Project in accordance with the Contract
         Documents (as hereinafter defined), in a timely manner with a specified
         target delivery date of October 30, 2000 (the "Delivery Date") and
         Final Completion Date (as hereinafter defined) of the 90th day after
         the Substantial Completion Date (as hereinafter defined), and includes
         labor necessary to produce such new construction, and materials and
         equipment incorporated or to be incorporated in such construction. All
         Work shall be performed in accordance with the Contract Documents. The
         "Contract Documents" shall consist of this Agreement, the Plans, the
         Building Description and Outline Specifications, the Schematic Building
         Plans, the Master Site Plan, the Project Schedule (hereinafter defined)
         and Change Orders.

                  (b) Within the time frame established under the Project
         Schedule, Developer shall cause to be prepared and delivered to
         Progressive the "Building Description and Outline Specifications",
         "Schematic Building Plans" and "Master Site Plan" for the Project
         ("Scope Documents"), together with a supplement to this Development
         Agreement in substantially the form as that attached hereto as EXHIBIT
         B-1, formally adopting such Building Description and Outline
         Specifications, Schematic Building Plans and Master Site Plan into this
         Agreement. Progressive shall have 15 days after receipt of Developer's
         submittals to raise any objection thereto. If Progressive disapproves
         of the Scope Documents, Progressive's notice of disapproval shall
         specify in detail the basis for such disapproval. Developer shall
         promptly cause to be made such revisions to the Scope Documents as may
         be necessary to address Progressive's objections, and shall resubmit
         the Scope Documents for Progressive's approval to maintain the Project
         Schedule. Progressive shall review such revisions and notify Developer
         whether Progressive approves or disapproves the Scope Documents as
         modified. This process shall be repeated, if necessary, until
         Progressive's objections


                                       2
   6

         have been addressed and Progressive has approved the Scope Documents;
         provided that, if the parties do not reach final agreement on the Scope
         Documents on or before November 10, 1999, either party shall have the
         right to terminate this Agreement by written notice to the other at any
         time thereafter and prior to the parties reaching agreement on the
         Scope Documents; provided that Progressive reimburses Developer for
         out-of-pocket third party expenses (not including Gilbane Building
         Company) incurred by Developer consistent with the schedule of
         anticipated expense categories set forth on EXHIBIT E attached hereto
         and pays to Developer the termination fee as required under Section 37.
         If Progressive fails to give Developer written notice of disapproval of
         the Scope Documents within 15 days after receipt of any submittal by
         Developer, Progressive shall be deemed to have approved the same. Upon
         approval of the Scope Documents, Progressive and Developer shall
         execute a supplement to this Agreement in substantially the form as
         that attached hereto as EXHIBIT B-1, formally adopting the Scope
         Documents as part of EXHIBIT B to this Agreement.

                  (c) All Work shall be performed with all new material in a
         good and workmanlike manner, in accordance with the Plans mutually
         approved by Developer and Progressive. Developer shall cause to be
         delivered to Progressive proposed drawings, specifications and
         schedules consisting of (i) design development drawings and
         specifications and (ii) finish schedule. Such deliverables shall be
         prepared, reviewed, revised and approved or disapproved by the parties
         hereto in accordance with Sections 2 and 5, hereof, to produce a final
         set of Plans. Progressive's approval of all of the above plans,
         drawings, specifications and schedules shall not be unreasonably
         withheld, conditioned or delayed, and except as hereinafter set forth,
         Progressive shall not be entitled to condition its approval of such
         plans, drawings, specifications and schedules upon the inclusion
         therein of any design specifications that are materially inconsistent
         with the Scope Documents (including requiring a higher performance
         standard than any performance standard expressly set forth in the Scope
         Documents). Progressive's approval of such plans, drawings,
         specifications and schedules shall not be deemed an acknowledgement,
         representation or warranty that any of such plans, drawings,
         specifications or schedules meet code or represent good engineering,
         design or construction practices or be deemed to waive any design flaw
         or code violation. In the event Progressive disapproves plans,
         drawings, specifications or schedules or any portion thereof or any
         modifications thereto, Progressive's notice of disapproval shall
         specify in detail the reasonable basis for such disapproval. Developer
         shall promptly cause to be made such revisions to the plans, drawings,
         specifications or schedules as may be necessary to address
         Progressive's reasonable objections, and shall resubmit the plans,
         drawings, specifications or schedules to Progressive for Progressive's
         approval to maintain the Project Schedule. Progressive shall review
         such revisions and notify Developer whether Progressive approves or
         reasonably disapproves the plans, drawings, specifications and
         schedules as modified. This process shall be repeated, if necessary,
         until Progressive's reasonable objections have been addressed and
         Progressive has approved the Plans; provided that, if the parties do
         not reach final agreement on the Plans after a reasonable review
         period, the matter may be submitted by either party to


                                       3
   7

         mediation under Section 13. If Progressive fails to give Developer
         written notice of disapproval of any plans, drawings, specifications or
         schedules within 15 days after receipt of any submittal by Developer,
         Progressive shall be deemed to have approved the same.

                  (d) Developer shall maintain in good order one record copy of
         the Plans, Change Orders and other related documents, marked currently
         to record changes made during construction, and during construction
         Progressive shall have the right to review all such Plans, Change
         Orders and other related documents during regular business hours upon
         one business day's notice. Upon completion of the design and
         construction and prior to termination of this Agreement, Developer
         shall deliver to Progressive the following: (i) as-builts (to be
         provided by hard copy and computer diskette); (ii) all written
         specifications as amended; (iii) complete copies of all operations and
         maintenance manuals for all equipment installed in the Project as part
         of the Work; (iv) the warranties for the foregoing in conformity with
         Section 14 hereof and transfer of the same to Progressive; and (v)
         provide the necessary training and validation of operating systems to
         ensure a smooth transition to Progressive's management/operation of the
         facility.

         3.  CHANGES IN THE WORK.

                  (a) A "Change Order" is a written order to Developer signed
         and approved by Progressive issued after execution of this Agreement,
         authorizing a change in the Work or an adjustment in the Stipulated
         Sum, the Delivery Date or the Final Completion Date. The Stipulated Sum
         may be changed only by Change Order. The Non-Developer Work (as defined
         in Section 19 hereof) shall be incorporated into the Developer's Work
         only by Change Order. The Delivery Date and Final Completion Date may
         be changed only by Change Order, Force Majeure (hereinafter defined)
         and Progressive Delay (hereinafter defined). A Change Order signed by
         Developer indicates its agreement therewith, including the adjustment
         (if any) in the Stipulated Sum (as defined in Section 7), the Delivery
         Date and the Final Completion Date.

                  (b) Progressive, without invalidating this Agreement, may
         order changes in the Work within the general scope of this Agreement
         consisting of additions, deletions or other revisions; provided the
         Stipulated Sum, the Delivery Date and the Final Completion Date are
         adjusted in a manner reasonably satisfactory to Developer which
         approval of any proposed change in the Work shall not be unreasonably
         withheld, conditioned or delayed. All such changes in the Work must be
         authorized by Change Order, and shall be performed under the applicable
         conditions of the Contract Documents.

                  (c) The cost or credit to Progressive resulting from a Change
         Order shall be determined by taking into account the increase or
         decrease in (i) the engineered cost for labor and materials of all
         contractors and subcontractors affected by the Change Order




                                       4
   8

         and (ii) such contractors' and subcontractors' general overhead as a
         result of the Change Order. The Stipulated Sum shall be further
         increased or decreased to reflect the parties' agreed upon adjustment
         to the Developer's overhead and profit as a result of any Change Order,
         as follows: 5% of any net increase or decrease in costs attributable to
         a Change Order up to $100,000.00 and 3% of any net increase or decrease
         in costs attributable to a Change Order of more than $100,000.00;
         provided that no overhead or profit fee shall be charged by Developer
         for Change Orders adding any "future equipment" (i.e., generator,
         chiller, UPS, EGU's) contemplated in the Scope Documents.

                  (d) If unit prices are stated in the Contract Documents or
         subsequently agreed upon, and if the quantities originally contemplated
         are so changed in a proposed Change Order that application of the
         agreed unit prices to the quantities of Work proposed will cause
         substantial inequity to Progressive or Developer, the applicable unit
         prices shall be equitably adjusted.

                  (e) Developer shall prepare Change Orders for Progressive's
         approval and execution and shall have authority to make minor changes
         (not material in relation to the intent of this document, the Project
         and Project Schedule, Project quality or performance requirements as
         hereinafter defined) in the design and construction consistent with the
         intent of this Agreement, not materially inconsistent with the Plans,
         and not involving an adjustment in the Stipulated Sum or an extension
         of the Delivery Date and Final Completion Date.

         4. DEVELOPER'S COMPLIANCE RESPONSIBILITIES. Developer shall be
responsible for causing the Work (including, without limitation, all changes
thereto) to comply with all applicable legal requirements existing as of
execution of this Agreement, including (without limitation) requirements of
building codes and zoning codes, all federal, state and municipal laws,
including, without limitation, the Americans With Disabilities Act, and all
recorded protective covenants and restrictions. Developer shall also be
responsible for obtaining a certificate of occupancy for the Project. If there
is any change between the date hereof and the Final Completion Date in any
applicable legal requirements which requires a change in the Work in order to
avoid a violation of any such applicable legal requirement, Developer shall be
responsible for changing the Work in order to avoid a violation of such legal
requirements, but the parties shall execute a Change Order to adjust the
Stipulated Sum, if applicable, as a result of any increase or decrease in costs
as a result of such change in legal requirements. If there is a change in any
applicable legal requirement but the Work or portion thereof affected by such
change is deemed to be "grandfathered" (i.e., the applicable legal requirement
does not require that the Work be changed), such portion of the Work shall
nevertheless be deemed to be in compliance with such applicable legal
requirements and Developer shall not be required to change the Work to otherwise
comply with such changed legal requirements.

         5. CONSTRUCTION TIMETABLE.


                                       5
   9

                  (a) In performing the Work, Developer shall achieve the
         milestone dates set forth in the schedule (the "Project Schedule") in
         EXHIBIT C attached hereto so that the Substantial Completion Date shall
         occur on or before the Delivery Date and the Final Completion Date
         shall be achieved on the 90th day after the Substantial Completion
         Date. Time shall be of the essence as to the Delivery Date and Final
         Completion Date. The Project Schedule shall be updated by Developer
         from time to time in accordance with the progress of the Work, and
         copies of such updates shall be promptly furnished to Progressive; it
         being expressly understood, however, that such updates may not extend
         the Delivery Date and Final Completion Date, except pursuant to
         subsection 5(b) hereof.

                  (b) The Delivery Date may be extended only by reason of (i) a
         Change Order or (ii) a Progressive Delay, or (iii) the occurrence of
         Force Majeure. In the event of a Change Order, the Delivery Date shall
         be accelerated or postponed, if at all, only as set forth in such
         Change Order. In the event (i) a Progressive Delay or Force Majeure
         occurs and (ii) Developer would have otherwise been able to perform all
         its obligations under the Contract Documents but for such delay,
         Developer's remedy shall be an extension of the Delivery Date by the
         number of days equal to the days Developer is actually delayed thereby,
         notwithstanding the exercise of commercially reasonable efforts. In the
         event of a Progressive Delay or Force Majeure, the Stipulated Sum shall
         be subject to an equitable adjustment to reflect the increase or
         decrease in costs incurred by Developer as a result of such Progressive
         Delay.

                  (c) If at any time in the course of the performance of its
         Work, Developer shall fall materially behind the Project Schedule which
         is not due to a Change Order, Force Majeure or Progressive Delay, then
         Developer shall promptly submit to Progressive a plan, including
         proposed adjustments to the Project Schedule, if any, showing how the
         Developer plans to mitigate impact upon the timely completion of the
         other portions of the Work and how it plans to accelerate performance
         so as to regain any time lost. The cost and expense of overtime, or any
         other measures implemented to achieve the foregoing, shall be borne
         entirely by Developer.

                  (d) For purposes herein, "Substantial Completion" (as
         identified on the Project Schedule) shall mean the stage in the
         progress of the Work when the Work or designated portion thereof is
         sufficiently complete in accordance with the Plans so that Progressive
         can legally occupy or utilize the Work or designated portion thereof
         for its intended use. For purposes herein, "Substantial Completion
         Date" shall mean the date on which (i) the Architect and Engineer have
         certified to Progressive that the Work has been substantially completed
         within the definition of "Substantial Completion" set forth above ;
         (ii) a certificate of occupancy for the Project has been delivered;
         provided, however, that no certificate of occupancy shall be required
         of Developer to establish Substantial Completion if and to the extent
         such a certificate cannot be obtained because of a failure of
         Progressive to complete any of Progressive's Non-Developer Work
         (hereinafter defined) or because any Non-Developer Work fails to comply
         with any

                                       6
   10
         applicable governmental codes, regulations, rules, ordinances
         or laws (provided that Developer shall not be excused if Progressive
         has retained Developer by separate agreement to perform such
         Non-Developer Work and it is Developer's default under such separate
         agreement that has in fact caused Progressive's failure to complete the
         Non-Developer Work or has caused the Non-Developer Work to fail to
         comply with any applicable governmental codes, regulations, rules,
         ordinances and laws); and (iii) Architect and Engineer deliver to
         Progressive a list of "Punch List Items" (as hereinafter defined), if
         any.

                  (e) For purposes herein, "Final Completion Date" shall mean
         the date on which Architect and Engineer shall certify to Progressive
         that the Work is finally completed and shall be evidenced by (i)
         completion of all Punch List Items and (ii) delivery of as-built
         drawings and warranties. The parties expressly understand that the
         Final Completion Date may be changed only by Change Order, Force
         Majeure or Progressive Delay.

                  (f) The Architect and Engineer shall deliver to Progressive
         for Progressive's review and approval a listing of the Punch List Items
         that the Architect and Engineer believe Developer is obligated by the
         provisions of this Agreement to complete. Progressive shall advise
         Developer and the Architect and Engineer within 15 days after receipt
         of Architect's and Engineer's lists of Punch List Items of any
         additional Punch List Items which Progressive believes Developer is
         obligated by the provisions of this Agreement to complete. Any
         disagreements between Developer and Progressive regarding Punch List
         Items shall be resolved in accordance with Section 13. The term "Punch
         List Items" shall mean details of construction and mechanical and
         electrical adjustments which are minor in character and do not
         materially interfere with Progressive's use or enjoyment of the Project
         or designated portion thereof for its business operations, and may also
         include landscaping and other items which do not materially affect
         Progressive's use of the Project but which cannot be immediately
         completed because of weather.

         6. PROGRESS PAYMENTS. Payment to Developer of that portion of the
Stipulated Sum included within the Professional Fees/Project Management category
shall be disbursed: (i) 20% to Developer in the first monthly draw, and (ii) the
balance in monthly progress payments on a percentage-of-completion basis, as
hereinafter provided. Payment of that portion of the Stipulated Sum included
within the Construction/Development Costs category shall be disbursed in monthly
progress payments based on actual costs incurred by Developer, as hereinafter
provided. No more than once each calendar month (which the parties expect in the
ordinary course to be by the tenth day of the calendar month), Developer will
submit to Progressive or its designee a requisition ("Requisition") for the
percentage of the Project completed, with respect to payments toward the
Professional Fees/Project Management portion of the Stipulated Sum, and for the
actual costs incurred by Developer, with respect to payments toward the
Construction/Development Costs portion of the Stipulated Sum, through the last
day of the immediately preceding calendar month, less the aggregate of previous
payments made by


                                       7
   11

Progressive to Developer hereunder and less Retainage (as hereinafter defined).
Each Requisition will be in the form of AIA Document G702/703 and will be based
on the Schedule of Values. Each Requisition shall be approved in writing by
Developer confirming that the portion of the Work for which payment is requested
has been completed. Each Requisition shall further include a certification by
the Developer that the Developer has paid the Architect and Engineer, the
Contractor and design professionals retained by Developer for all work performed
by such parties for which Developer has received payment under previous
Requisitions, and by the Contractor and major subcontractors that all of their
respective subcontractors have been paid for all work performed by such
subcontractors for which the Contractor has received payment under previous
Requisitions. Within 20 days after the receipt of each approved Requisition,
Progressive shall, unless Progressive and Developer otherwise agree, pay the
full amount requested to Developer to disburse in accordance with the
Requisition. In the case of a dispute, Developer and Progressive shall agree on
the disputed value which shall be deducted from the payment while dispute
resolution in Paragraph 13 is implemented. Progressive understands and
acknowledges that prompt payment of all approved Requisitions is a critical
component in Developer's ability to complete the Project within the time frame
required and if any Requisition is not paid to Developer in full or as otherwise
set forth in the Requisition, within 20 days after its due date, interest shall
accrue (and be immediately due) on the unpaid amounts at the rate of 10% per
annum until paid. As used herein, "Retainage" shall mean an amount equal to 10%
of construction hard costs (but not of design or soft costs for which there
shall be no retainage) until the Work is 50% completed, and zero percent (0%) of
the final 50% of the Work, which Retainage balance shall be released/disbursed
to Developer upon Final Completion of the Work.

         7.  STIPULATED SUM.

                  (a) Progressive shall pay to Developer in consideration for
         Developer's performance of the Work, an agreed upon stipulated sum (the
         "Stipulated Sum"). The Stipulated Sum shall be divided into two
         categories, the first category sometimes referred to herein as the
         "Professional Fee/Project Management" category and the second category
         sometimes referred to as the "Construction/Development Costs" category.
         The Stipulated Sum shall be established in coordination with the
         preparation and approval of the Scope Documents. Upon approval of the
         Scope Documents by Progressive, Developer shall submit to Progressive
         the total amount of the "Stipulated Sum" to be paid Developer for the
         work hereunder. Progressive shall have ten business days after receipt
         of Developer's notice of the Stipulated Sum to object to such amount.
         If Progressive timely objects, Developer and Progressive shall
         negotiate in good faith to resolve any disagreement and confirm the
         Stipulated Sum. If Developer and Progressive are not able to reach
         agreement on the Stipulated Sum on or before November 18, 1999, either
         party may terminate this Agreement by written notice to the other given
         on or after November 19, 1999 and prior to reaching agreement on the
         Stipulated Sum; provided that Progressive reimburses Developer for
         out-of-pocket third party expenses incurred by Developer and pays to
         Developer the termination fee as required under Section 37. Upon
         establishment of the Stipulated Sum, the parties shall


                                       8
   12

         execute the supplement to this Agreement in substantially the form as
         that attached hereto as EXHIBIT B-1, establishing the Scope Documents
         and Stipulated Sum agreed to by the parties. If Progressive fails to
         give Developer written notice of disapproval of the Stipulated Sum
         within ten days after receipt of Developer's notice thereof,
         Progressive shall be deemed to have approved the same.

                  (b) Once established, the Stipulated Sum, subject to
         adjustment by approved Change Orders constitutes Developer's complete
         compensation for the Work and, without limitation, includes
         compensation for all (i) design, construction and development services
         rendered by Developer, the Architect, the Engineer, the Contractor and
         all other subcontractors and design and engineering professionals used
         by Developer, Architect, Engineer and/or Contractor pursuant to this
         Agreement; (ii) expenses of Developer, the Architect, the Engineer, the
         Contractor and all other subcontractors and design and engineering
         professionals used by Developer, Architect, Engineer and/or Contractor
         including, without limitation, the cost of all equipment, taxes,
         royalties, insurance premiums, and permits; (iii) fees earned by
         Developer, the Architect, the Engineer, the Contractor and all other
         subcontractors and design and engineering professionals used by
         Developer, Architect, Engineer and/or Contractor with respect to the
         design, construction and development services rendered pursuant to this
         Agreement; and (iv) all legal and other fees and expenses incurred by
         or on behalf of Developer.

                  (c) The Stipulated Sum shall be broken into two categories,
         one category for professional fees and the second category for all
         other construction and development costs included within the scope of
         the Work ("Construction/Development Costs"). Within 45 days after the
         Final Completion Date, Developer shall submit to Progressive
         documentation detailing the total actual costs incurred by the
         Developer in completing the Work included within the
         Construction/Development Cost category of the Stipulated Sum. If such
         final accounting indicates that the total actual costs for that portion
         of the Work included within the Construction/Development Cost category
         is less than the portion of the Stipulated Sum established by the
         parties hereunder, Progressive shall pay Developer one-half of such
         savings within 20 days after receipt of Developer's statement and
         Progressive shall be deemed to have received a credit against the
         Stipulated Sum otherwise due from Progressive to Developer hereunder in
         an amount equal to the balance of such savings. If the actual costs of
         completing that portion of the Work included within the
         Construction/Development Cost category of the Stipulated Sum is greater
         than the amount of the Stipulated Sum for such category, Developer
         shall be solely responsible for such excess costs. Any decrease in the
         Stipulated Sum due to a Change Order modifying the scope of the Work
         shall accrue 100% to the benefit of Progressive. Progressive shall have
         the right to audit Developer's and Contractor's books and records to
         verify actual costs incurred by Developer and Contractor for all Work
         included within the Construction/Development Cost category of the
         Stipulated Sum; and Developer and Contractor shall make their


                                       9
   13

         books and records available to Progressive and its accountants and
         agents during regular business hours.

         8.  INSURANCE.

                  (a) Developer shall maintain until final completion or, as the
         case may be, shall be responsible for ensuring that Contractor
         maintain, as part of the Project and at no additional expense to
         Progressive, the insurance set forth in clause (b) below. The Developer
         shall also be responsible for the filing and settling of claims and
         liaison with insurance adjusters. The Developer shall send a copy of
         all policies to Progressive, which shall be deemed to have approved of
         such policies unless, within 30 days after receipt thereof, it shall by
         notice in writing advise the Developer to the contrary.

                  (b) The Contractor shall maintain worker's compensation
         insurance, commercial general liability insurance (on an occurrence
         basis), automobile liability insurance and umbrella liability insurance
         with companies reasonably satisfactory to Progressive. The general
         liability policy shall be for a combined single limit for personal
         injury and property damage of not less than $2,000,000, and shall
         provide coverage, at a minimum, for (i) broad form contractual
         liability; (ii) products liability and completed operations; and (iii)
         broad form property damage coverage. The automobile liability policy
         shall be written for a combined single limit for bodily injury and
         property damage of not less than $1,000,000. The umbrella liability
         policy shall be for a maximum single limit of $20,000,000 for
         supplementing the comprehensive general liability policy and automobile
         liability policy. In the case of worker's compensation coverage,
         insurance shall be in amount statutorily required. The comprehensive
         general liability automobile liability and umbrella liability insurance
         policies shall name Progressive, Developer and any mortgagee of the
         Property ("Lender") as additional insureds. The foregoing insurance
         coverage shall be at the expense of Developer. The Contractor policies
         shall be maintained throughout the Project duration, shall include a
         Waiver of Subrogation, shall provide that such policy may not be
         cancelled or reduced in coverage without thirty days notice and shall
         have deductable levels of not more than: Worker's Compensation
         $250,000; Commercial General Liability %150,000; and automibile
         liability policy $0 (zero dollars).

                  (c) Progressive shall also procure and maintain a builder's
         risk insurance policy on an "all risk" 100% replacement cost basis and
         shall name Developer and Contractor, as additional insureds.

         9. ARCHITECT, ENGINEER AND OTHER PROFESSIONALS. Developer represents
that the design agreements (the "Design Agreements") with Architect, Engineer
and other professionals retained by Developer and/or Contractor for the Work
shall, without limitation, contain the following:


                                       10
   14

                  (a) The Architect and Engineer shall be required to carry
         errors and omissions insurance, on an occurrence basis, in an amount
         not less than $2,000,000, and such other professionals shall be
         required to carry errors and omissions insurance in amounts reasonably
         acceptable to Developer and to Progressive. All such professionals
         shall be required to indemnify Progressive against errors and omissions
         including patent infringement; and

                  (b) The rights to use the Plans and other related documents
         prepared in connection with the Work are and shall remain under the
         control of Progressive and may not be used by others without
         Progressive's consent (except that Developer and its agents may use
         such Plans and related documents only in connection with their
         performance of this Agreement). Such professionals shall be required to
         deliver to Progressive copies, including reproducible copies and
         computer diskettes, of the Plans and other related documents for
         information and reference in connection with Progressive's use and
         occupancy of the Project. Further, the Plans and other related
         documents may be used by Developer and Progressive, in whole or in
         part, or in modified form, for completion and maintenance of the
         Project by others, without further employment of, or payment of any
         compensation to, Architect, Engineer and other design professionals, in
         which event, Developer and Progressive shall release such professionals
         from any responsibility for the conformance of the incomplete portions
         of the Project to the Plans and other related documents and shall
         indemnify such professionals against and hold them harmless from all
         claims arising from causes other than the negligence or fault of such
         professionals. In the event of the termination of this Agreement for
         whatever reason, Developer shall immediately return and deliver to
         Progressive all originals, copies and reproductions of the Plans and
         other related documents then in the possession or control of Developer,
         Architect, Engineer and such other professionals retained by Developer.

         10. PAYMENT AND PERFORMANCE BONDS. Developer shall, at its own cost and
expense, procure payment and performance bonds for (i) each subcontractor or
materialman, irrespective of contract value, involved with the Building envelope
(exterior or roof) and (ii) at Developer's discretion, each subcontractor or
materialman whose contract for the Project exceeds $100,000 in the aggregate.
Progressive shall be a co-obligee with respect to such bonds.

         11. DELAY DAMAGES. If the Substantial Completion Date does not occur on
or before the Delivery Date, as such date may be extended by reason of Change
Order, Force Majeure, or Progressive Delay, then Developer shall pay to
Progressive, as liquidated damages for each business day of such delay, the Per
Diem Delay Damage Amount from the Delivery Date until the Substantial Completion
Date ("Delay Damages"). The "Per Diem Delay Damage Amount" shall be $3,000.00.

         12. TERMINATION OF AGREEMENT. If Developer defaults or fails or
neglects to carry out its Work in accordance with the Contract Documents,
Progressive may give written notice that Progressive intends to terminate this
Agreement, which notice shall contain a reasonably


                                       11
   15

detailed explanation of the reasons for the proposed termination. Developer
shall correct the defaults, failure or neglect within 10 days after being given
such notice; provided, however, if (i) the nature of such defaults, failure or
neglect is such that they are not reasonably capable of being corrected within
such 10 day period and (ii) Developer notifies Progressive of a reasonable
alternative period reasonably acceptable to Progressive within fifteen days of
receipt of such notice, Developer shall be allowed such reasonable alternative
period to correct the defaults, failure or neglect so long as Developer promptly
commences and diligently pursues such corrections to completion. If Developer
fails to make such corrections within the 30 day period or fails to commence and
diligently pursue to completion such corrections within the alternative period,
then Progressive may, at its sole discretion and without prejudice to any other
remedy, (x) make good such deficiencies and cause the deduction of the cost
thereof from the payment due Developer or (y) with fifteen days notice,
terminate the employment of Developer and take possession of the site and of all
materials, equipment, tools and construction equipment and machinery thereon
owned by Developer and, if Progressive so chooses, finish the Work by whatever
method Progressive may deem expedient. If the expense of finishing the Work
exceeds the unpaid balance of the Stipulated Sum, Developer shall pay the
difference to Progressive on demand.

         Upon termination hereunder, those contracts for the design and/or
construction of the Work designated by Progressive shall be assigned to
Progressive for Progressive to use at Progressive's option to complete the Work.
Progressive's remedies set forth hereunder are not exclusive, and Progressive
has the right to pursue any other right or remedy available to it at law or in
equity.

         13. DISPUTE RESOLUTION. Any dispute arising out of or relating to this
Agreement shall be resolved in accordance with the procedures specified in this
Section 13, which shall be the sole and exclusive procedure for the resolution
of any such dispute.

                  (a) The parties shall attempt in good faith to resolve any
         dispute arising out of or relating to this Agreement promptly by direct
         negotiation between executives who have authority to settle the
         controversy and who are at a higher level of management than the
         persons with direct responsibility for administration of this
         Agreement. Any party may give the other party written notice of any
         dispute not resolved in the normal course of business. Within fifteen
         (15) days after delivery of the notice, the receiving party shall
         submit to the other a written response. The notice and the response
         shall include (a) a statement of each party's position and a summary of
         arguments supporting that position, and (b) the name and title of the
         executive who will represent that party and of any other person who
         will accompany the executive. Within 30 days after the delivery of the
         disputing party's notice, the executives of both parties shall meet at
         a mutually acceptable time and place, and thereafter as often as they
         reasonably deem necessary, to attempt to resolve the dispute. All
         reasonable requests for information made by one party to the other will
         be honored. All negotiations pursuant to this clause are confidential
         and shall be treated as compromise and settlement negotiations for
         purposes of applicable rules of evidence.


                                       12
   16

                  (b) If the dispute has not been resolved by negotiation within
         45 days of the disputing party's notice, or if the parties fail to meet
         within 20 days, the parties shall endeavor to settle the dispute by
         mediation using a mediator and mediation mutually agreeable to the
         parties. In the event that the parties are unable or unwilling to agree
         on a mediator or the mediation procedure to employ, then the parties
         shall endeavor to settle the dispute by mediation under the then
         current American Arbitration Association Commercial Mediation Rules.
         The cost of the mediator's services incurred in conjunction with any
         mediation conducted under this Section 13 shall be shared equally by
         the parties.

                  (c) If the dispute has not been resolved by non-binding means
         as provided herein within 90 days of the initiation of such procedure,
         either party may initiate litigation upon 10 days written notice to the
         other party; provided, however, that if one party has requested the
         other to participate in a non-binding procedure and the other has
         failed to participate, the requesting party may initiate litigation
         before the expiration of the above period.

                  (d) All applicable statutes of limitation and defenses upon
         the passage of time shall be tolled while the procedures specified in
         this Section 13 are pending. The parties will take such action, if any,
         required to effectuate such tolling.

                  (e) Each party is required to continue to perform its
         obligations under this contract pending final resolution of any dispute
         arising out of or related to this Agreement, unless to do so would be
         impossible or impracticable under the circumstances.

                  (f) If Progress Payment (Paragraph 6) has been reduced due to
         Progressive action, the amount deducted shall accrue interest as stated
         in Paragraph 32 if it is determined in the Dispute Resolution that the
         deduction from payment was not justified.

         14.  WARRANTIES.

                  (a) Developer warrants and represents to Progressive that the
         Work (i) will be completed in accordance with the Contract Documents,
         (ii) will comply with all applicable covenants and restrictions and all
         applicable governmental codes, rules and regulations in effect at the
         execution of this Agreement, (iii) will be new (except for those
         portions of any existing improvements located upon the Property which
         are to remain as a part of the Project under the Plans), and (iv) will
         be free of all liens, claims and encumbrances consistent with the
         provisions of Section 15, hereof. In addition, Developer (i) shall
         obtain from the roofing manufacturer an industry standard 20 year
         warranty against roof leakage due to defective materials , (ii) shall
         obtain from the roofing subcontractor a one year warranty against roof
         leakage due to defective workmanship and (iii) shall use commercially
         reasonable efforts to obtain extended


                                       13
   17

         warranties relating to major equipment included in the construction of
         the Project or the Work provided under any construction and/or supply
         contracts now or hereafter entered into by Developer or Contractor for
         construction of the Project and the Work.

                  (b) Developer hereby guaranties to Progressive that all Work
         for the Project will be in conformance with the Contract Documents free
         from defects in workmanship and materials for a period of one year
         after Substantial Completion Date.

                  (c) In the event that the Work or any portion thereof is found
         defective or not in accordance with the Contract Documents within the
         one year time period set forth in Section 14(b), Developer shall
         correct it or cause it to be corrected promptly after written notice
         from Progressive to do so. Developer shall not have any liability for
         any claimed breach of the above guarantee unless Progressive gives
         Developer written notice of breach of such guarantee, specifying the
         nature of the breach, within one year after the Substantial Completion
         Date.

                  (d) On the first anniversary of the date following the
         Substantial Completion Date, Developer shall assign, and cause
         Contractor to assign, to Progressive the nonexclusive right along with
         Developer and Contractor to enforce, at Progressive's cost, if
         Progressive elects to pursue such enforcement, any and all warranties
         which Developer or Contractor may have relating to construction of the
         Project or the Work provided under any construction and/or supply
         contracts now or hereafter entered into by Developer or Contractor for
         construction of the Project and the Work. After such assignment,
         Progressive shall have the right, at Progressive's cost, to pursue any
         such claims in the name of Developer or Contractor. In such event,
         Developer and Contractor, at their sole cost, shall cooperate with
         Progressive in connection therewith; provided, however, that Developer
         and Contractor shall not be obligated to incur third-party costs.

                  (e) Except as specifically set forth above, Developer makes no
         warranty or representation to Progressive as to the condition and/or
         suitability of the Project and Progressive waives and releases
         Developer from any other claim or cause of action Progressive may now
         or hereafter have or claim to have against Developer for or on account
         of the construction or condition of the Project, excepting only claims
         against Developer for (i) fraud or willful misconduct, (ii) Delay
         Damages, and/or (iii) failure to complete the Work in accordance with
         the Contract Documents and the terms of this Agreement.

         15.  LIEN REMOVAL.

                  (a) If, at any time, there is any lien or claim of any kind
         whatsoever filed against the Project by Contractor, a subcontractor,
         Architect, Engineer or other design professional or anyone claiming
         under or through Developer, Contractor, a subcontractor, Architect,
         Engineer or other design professional for work performed or


                                       14
   18

         materials, supplies or equipment furnished in connection with the Work,
         Developer shall, within 60 days, or such shorter period as is required
         by any loan secured by the Project, after the filing of same, cause
         such lien or encumbrance to be canceled and discharged of record by
         payment, bonding or otherwise, at Developer's sole cost and expense,
         and at no cost to Progressive.

                  (b) If any lien or other encumbrance required to be removed at
         Developer's sole cost and expense pursuant to subsections 15(a),
         hereof, is not canceled and discharged of record as aforesaid,
         Progressive shall have the right to take such action as Progressive
         shall deem appropriate (which shall include the right to cause such
         lien or other encumbrance to be canceled and discharged of record), and
         in such event, all costs and expenses incurred by Progressive in
         connection therewith (including, without limitation, premiums for any
         bond furnished in connection therewith, and reasonable attorneys' fees,
         court costs and disbursements), together with interest thereon at the
         rate set forth in Section 32 hereof, shall be paid by Developer to
         Progressive, as applicable, on demand, or at the option of Progressive,
         as applicable, deducted from any payment then due or thereafter
         becoming due to Developer in accordance with provisions of this
         Agreement; and such deducted amount to be paid to Progressive.

         16. PROGRESSIVE DELAY. For purposes hereof, a Progressive Delay shall
mean delays or hindrances in the Work caused by the acts or omissions of
Progressive in its performance of its obligations under this Agreement for the
Project, or its failure to respond and give approvals and/or disapprovals within
10 business days after Progressive's Authorized Representative has acknowledged
receipt of submittal. In the event of a Progressive Delay, Developer shall seek
to minimize the period of delay or hindrance by means which include, without
limitation, seeking alternate sources of labor or materials or acceleration of
the Work. If in seeking to minimize the period of delay or hindrance added costs
would be incurred, Developer shall have no obligation to act unless Progressive
executes a Change Order to cover such added costs. If Developer wishes to make a
claim for an extension of the Delivery Date and Final Completion Date or
increase in the Stipulated Sum by reason of a Progressive Delay, Developer shall
give prompt notice to Progressive of such claim.

         17. FORCE MAJEURE. For purposes hereof, a Force Majeure shall mean
delays or hindrances in the Work caused by (i) acts of God; (ii) strikes, labor
disputes, labor shortages or material shortages (for reasons outside of
Developer's reasonable control using Developer's professional expertise and good
faith diligent efforts); (iii) blackouts; (iv) acts of public enemy; (v) orders
of any kind of the government of the United States or of the State of Ohio or
any department, agency, political subdivision or official of either of them, or
any civil or military authority; (vi) riots; (vii) epidemics disabling the labor
force; (viii) landslides; (ix) earthquakes affecting the Project; (x) fires;
(xi) hurricanes and/or tornadoes; (xii) adverse weather conditions (i.e., the
number of days in excess of the normal weather [rain or snow days] as defined
for a 30 day period by the National Weather Bureau for the Cleveland, Ohio
metropolitan area); (xiii) floods; (xiv) partial or entire failure of public
utilities affecting the Project; (xv) delays associated with the existence,
removal or remediation of any Regulated



                                       15
   19


Substance (as defined below); (xvi) delay in obtaining any necessary or required
building permits, licenses and approvals (for reasons outside of Developer's
reasonable control using Developer's professional expertise and good faith
diligent efforts); (xvii) delays due to unforeseen soil or other underground
conditions; or (xviii) any other similar cause or event beyond Developer's
control. Developer shall give notice to Progressive of the occurrence of any
event of Force Majeure that may give rise to a claim for an extension of the
Delivery Date and Final Completion Date or adjustment to the Stipulated Sum as
soon as reasonably possible after the discovery by Developer of such Force
Majeure event. Developer shall thereafter use all reasonable diligence in
attempting to overcome or lessen the impact of such Force Majeure event and
shall keep Progressive reasonably informed of Developer's progress in mitigating
the effects of any such Force Majeure event. Developer shall cooperate with
Progressive, and allow Progressive to participate in attempting, to resolve or
mitigate any such Force Majeure event, but Progressive shall not have any
obligation to do so.

         18. INDEMNIFICATION. Developer shall indemnify and hold Progressive
harmless, to the extent permitted by law, from any and all third party claims or
causes of action for loss, liability, damage or expense, including reasonable
attorney's fees and disbursements, directly arising out of (i) the performance
of the Work, including, but not limited to, any mechanics or construction liens
arising as a result thereof, (ii) any failure of the Project or Work to comply
with any applicable governmental laws, ordinances, rules and regulations in
effect as of the Substantial Completion Date, (iii) any negligence of Developer,
the Contractor or any subcontractor, (iv) any breach of Developer's warranties
and representations under this Agreement, and (v) Developer's failure to comply
with the performance of any of its other covenants or obligations under this
Agreement; provided that such indemnity and hold harmless shall not apply to any
loss, liability, damage or expense, including attorneys' fees, to the extent
arising out of any negligent act or omission of Progressive or any officer,
employee, agent, representative or contractor of Progressive.

         19. NON-DEVELOPER WORK. Any other work, installations, furniture,
fixtures and equipment relating to the Project desired by Progressive, to the
extent not included within the scope of the Work under the Plans shall be deemed
to be "Non-Developer Work" and shall be performed by and at the sole cost of
Progressive. Developer shall cooperate with and afford Progressive's separate
contractors reasonable opportunity for introduction and storage of their
materials and equipment in a reasonably safe and secure area for execution of
their Non-Developer Work. All such materials and equipment shall be insured by
Progressive or its contractors or subcontractors, and all risk of loss,
liability and responsibility for such stored materials and equipment shall
belong to Progressive or its contractors or subcontractors. Any and all such
Non-Developer Work performed by or on behalf of Progressive shall be performed
in such a manner so as to cause the least amount of interference with
Developer's completion of the Work; and Developer shall have overall control of
coordinating any such Non-Developer Work so as to insure that such Non-Developer
Work does not hinder or delay completion of the Work.


                                       16
   20

         20. MAINTAIN PROJECT. Throughout the performance of the Work, Developer
shall keep the Project free from accumulation of waste materials or rubbish
caused by Developer's operations; it being expressly understood by the parties
hereto that Progressive and its contractors shall be responsible for such
obligation with respect to any Non-Developer Work. On or before the Final
Completion Date, Developer shall remove from and about the Project Developer's
tools, construction equipment, machinery, surplus materials, waste materials and
rubbish and provide the Project in a clean state (i.e., relative to the Work).

         21. GOVERNING LAW. This Agreement shall be governed by, and construed
in accordance with, the laws of the State of Ohio. If any provision of this
Agreement or the application thereof to any person or circumstances shall, to
any extent, be invalid or unenforceable, the remainder of this Agreement shall
not be affected thereby and each provision of the Agreement shall be valid and
enforceable to the fullest extent permitted by law.

         22. NOTICES. All notices and demands by any party to any other shall be
given in writing and sent by a nationally recognized overnight courier or by
United States certified mail, postage prepaid, return receipt requested, and
addressed as follows:

         To Developer:   GP Ohio, L.L.C.
                         c/o Gilbane Properties, Inc.
                         7 Jackson Walkway
                         Providence, Rhode Island 02903
                         Attn.: Michael E. Culbert

         With a copy to: GP Ohio, L.L.C.
                         c/o Gilbane Properties, Inc.
                         7 Jackson Walkway
                         Providence, Rhode Island 02903
                         Attn.: Robert V. Gilbane

         With a copy to: Michael J. Dwyer
                         Godfrey & Kahn, S.C.
                         780 North Water Street
                         Milwaukee, Wisconsin 53202

         To Progressive: Progressive Casualty Insurance Company
                         300 North Commons Boulevard
                         Mayfield Village, OH 44143
                         Attention: Daniel Schluer

         With a copy to: Michael Uth
                         Assistant General Counsel
                         Progressive Casualty Insurance Company
                         6300 Wilson Mills Road


                                       17
   21

                         Mayfield Village, Ohio 44143

         Any party may, upon prior notice to the others, specify a different
address for the giving of notice. Notices shall be effective one day after
sending if sent by overnight courier or two days after sending if sent by
certified mail, return receipt requested.

         23. PROGRESSIVE'S AUTHORIZED REPRESENTATIVE/CONSULTANT. Progressive
designates Daniel Schluer as a "Progressive's Authorized Representative", and
anyone else whom, with prior notice to Developer, Progressive may designate as a
Progressive's Authorized Representative. Any Progressive's Authorized
Representative shall have the authority to act individually or jointly with any
other Progressive Authorized Representative to approve in writing all plans,
drawings, specifications, Change Orders, charges and approvals to this Agreement
on behalf of Progressive. Progressive's Authorized Representative shall inform
Developer of any errors, omissions, defects, deficiencies or other problems that
such Progressive's Authorized Representative believes may exist in order to
assist Developer in rectifying same, but this undertaking shall not in any way
affect the obligations and responsibilities of Developer under this Agreement.
Developer shall keep Progressive's Authorized Representative informed as to the
progress of the Work, shall provide Progressive's Authorized Representative with
copies of the Project Monthly Report and updates or refinements to the Project
Schedule and keep Progressive's Authorized Representative reasonably informed of
upcoming key milestone events in the Project Schedule.

         24. SUCCESSORS AND ASSIGNS. Except as expressly otherwise provided, all
of the terms, covenants and conditions hereof shall be binding upon and inure to
the benefit of the parties hereto and their respective successors and assigns.
This Agreement may not be assigned without the prior written consent of all
parties to this Agreement, which consent shall not unreasonably be withheld
except that Progressive may assign this Agreement or delegate any of its rights
or obligation hereunder to any of its affiliates upon notice to Developer;
provided that Progressive shall remain liable for the full performance of all of
its obligations under this Agreement.

         25. REGULATED SUBSTANCES. As used herein, the term "Regulated
Substance" shall mean and include any, each and all substances or materials now
or hereafter regulated pursuant to any Environmental Laws, including, but not
limited to, any such substance or material now or hereafter defined as or deemed
to be a "Regulated Substance", "Pesticide", "Hazardous Substance" or "Hazardous
Waste" or included in any similar or like classification or categorization
thereunder. As used herein, the term "Environmental Laws" shall mean and include
the Resource Conservation and Recovery Act, as amended by the Hazardous and
Solid Waste Amendments of 1984, the Comprehensive Environmental Response,
Compensation and Liability Act, the Hazardous Materials Transportation Act, the
Toxic Substances and Control Act, the Federal Insecticide, Fungicide and
Rodenticide Act and all applicable state and local environmental laws,
ordinances, rules, requirements, and regulations, as any of the foregoing may
have been or may be from time to time amended, supplemented or supplanted and
any and all other federal, state or local laws, ordinances, rules, requirements,
and regulations, now or


                                       18
   22

hereafter existing, relating to the preservation of the environment or the
regulation or control of petroleum products, toxic or hazardous substances or
materials or other environment threatening substances or materials. Developer
shall not bring unto the Project site (or allow to be brought onto the Project
site) any Regulated Substance, except such materials as are routinely used in
connection with construction and then only in accordance with appropriate
guidelines, standards, and practices in the industry. Developer shall advise
Progressive immediately if Developer becomes aware of Regulated Substances on or
near the Project site.

         26. TIME OF THE ESSENCE. Time shall be of the essence with respect to
this Agreement and of every provision hereof.

         27. INDEPENDENT CONTRACTOR. It is expressly understood and agreed by
the parties hereto that Developer, in performing its obligations under the
Contract Documents, shall be deemed an independent contractor and not an agent,
employee or partner of Progressive.

         28. NO WAIVER. The failure of Progressive to insist upon the strict
performance of any provisions of the Contract Documents, the failure of
Progressive to exercise any right, option or remedy hereby reserved, or the
existence of any course of performance hereunder shall not be construed as a
waiver of any provision hereof or of any such right, option or remedy or as a
waiver for the future of any such provision, right, option or remedy or as a
waiver of a subsequent breach thereof. The consent or approval by Progressive of
any act by Developer requiring Progressive's consent or approval shall not be
construed to waive or render unnecessary the requirement for Progressive's
consent or approval of any subsequent similar act by Developer. Progressive's
approval of payment of any amount due hereunder with knowledge of a breach of
any provision or requirement of the Contract Documents shall not be deemed a
waiver of such breach. No provision of the Contract Documents shall be deemed to
have been waived unless such waiver shall be in writing signed by the party to
be charged.

         29. SEVERABILITY. If any term or provision of this Agreement shall be
determined to be invalid or unenforceable in any respect, it shall be replaced
with a substantially similar provision to the greatest extent possible and the
Agreement shall remain in full force and effect.

         30. COOPERATION. The parties agree to cooperate to achieve the
objectives of this Agreement and to use reasonable and good faith efforts to
resolve all disputes and disagreements that may arise hereunder.

         31. COUNTERPARTS. This Agreement may be executed in two or more
counterparts, each of which shall be deemed an original, but both of such
counterparts together shall be deemed to be one and the same instrument. It
shall not be necessary in making proof of this Agreement or any counterpart
hereof to produce or account for the other counterpart.

         32. INTEREST. Any amount due hereunder which is not paid when due shall
bear interest at an annual rate equal to the greater of (i) 1% per annum in
excess of the Prime Rate or (ii) 10% per annum (but in no event shall such rate
of interest exceed the maximum rate of interest


                                       19
   23

permitted to be charged by law) from the date due until paid, compounded
monthly, but the payment of such interest shall not excuse or cure any default
by any party under this Agreement. "Prime Rate" means the highest base rate on
corporate loans posted by at least 75% of the 30 largest banks in the United
States as published from time to time by THE WALL STREET JOURNAL.

         33. ENTIRE AGREEMENT. This Agreement and the exhibits attached hereto
and forming a part hereof, set forth all the covenants, promises, agreements,
conditions and understandings between Developer and Progressive concerning the
Property and the development of the Project thereon and there are no covenants,
promises, agreements, conditions or understandings, either oral or written,
between them other than are herein set forth. No alteration, amendment, change
or addition to this Agreement shall be binding upon Developer or Progressive
unless reduced to writing and signed by each party.

         34. INTENTIONALLY LEFT BLANK.

         35. TERMINATION. Except for Developer's obligation under Section 14,
Section 15 and Section 18, and except for any liability for Delay Damages under
Section 11, Developer's obligations and liability under this Agreement shall
expire following the occurrence of the Final Completion Date and the assignment
of any documents to be assigned upon final completion (i.e. assignment of
warranties). This Section 35 shall in no way lessen or otherwise affect the
liability the Architect, Engineer and other design professionals may have with
respect to the Project.

         36. FACSIMILE SIGNATURES. Either party hereto may execute this
Agreement by facsimile signature which facsimile signature shall be deemed to be
an original signature.

         37. CONTINGENCY. Notwithstanding anything contained in this Agreement
to the contrary, Developer's and Progressive's obligations under this Agreement
shall be contingent upon (a) Developer obtaining government approvals, permits
and licenses necessary or required for the start of construction of the Project,
and (b) Progressive and Developer agreeing on the Scope Documents and Stipulated
Sum as contemplated under Sections 2(b) and 7(a). Upon satisfaction of
contingencies (a) and (b), prior to commencement of construction of the Project,
Developer shall notify Progressive of Developer's intent to commence
construction of the Project and Progressive shall have 3 days after receipt of
any such notice to give notice of termination of this Agreement; the failure of
Progressive timely to terminate upon receipt of such notice shall be deemed a
waiver of Progressive's right to terminate this Agreement under this Section 37.
In addition, if such contingencies have not been satisfied or waived on or
before November 18, 1999, Progressive and/or Developer shall have the right to
terminate this Agreement effective as of November 19, 1999 by written notice to
the other. In the event of termination under this Section 37, Progressive shall
pay to Developer all out-of-pocket third party expenses incurred by Developer in
design and pre-construction development activities together with a termination
fee in the amount set forth on EXHIBIT D for the applicable date


                                       20
   24

of termination to compensate Developer for its labor and efforts hereunder
through the date of termination.

         38. NOTICE OF COMMENCEMENT. Developer acknowledges that it has received
a copy of the Notice of Commencement attached hereto as EXHIBIT F and that at
all times following the date Work commences, Developer will keep a copy of such
Notice of Commencement posted in a conspicuous place on the Project site.

         IN WITNESS WHEREOF, the undersigned have executed this Agreement as of
the day, month and year first above written.

                                 (Developer)

                                 GP Ohio, L.L.C.

                                 By:  Gilbane Properties,  Inc., Managing Member

                                      By: /s/  Edward T. Broderick
                                          --------------------------------------
                                          Title:  Vice President

                                 (Progressive)

                                 Progressive Casualty Insurance Company

                                 By: /s/  Daniel E. Schluer
                                     -------------------------------------------
                                     TITLE:  Senior Real Estate Project Manager




                                       21
   25


                                    EXHIBIT A
                                    ---------

                            Property Depiction/Survey



(Property Depiction/Survey)





   26


                                    EXHIBIT B
                                    ---------

                           Preliminary Scope Documents

   27


                                               Development Agreement - Exhibit B
                                                        Exhibit B-1 - Schedule A

                     PROGRESSIVE CASUALTY INSURANCE COMPANY

                 Building Description and Outline Specification
                 ----------------------------------------------
                                October 29, 1999

This section outlines the design specifications, which have been developed for
Progressive's requirements.


I. GENERAL PROJECT OVERVIEW

Project Description
- -------------------

Progressive intends to develop a state-of-the-art Data/Information Systems
Center in suburban Mayfield Village, Ohio. The project will be master planned to
accommodate growth.

The Phase I project is designed to house the data center for Progressive's
primary computer and processing equipment. The Phase I building will be
approximately 80,000 square feet comprised of the following space:

        37,600 sf  Data Processing Area
        25,000 sf  Mechanical Room/Utility & Support Area
         2,400 sf  Loading
        11,550 sf  Office/Support Area
         3,450 sf  Core Area
        -------
        80,000 sf  Total Area *

* A generator building of approximately 6,000 -square-feet will be provided

The design criteria for the mechanical and electrical systems will be as
follows:

- -        Uninterruptible Power Supply       = 2N+2
- -        Generators                         = 2N
- -        Chilled Water Plant                = 2N
- -        Make-up Water                      = 2N
- -        Fire Protection                    = N
- -        Electrical Distribution            = 2N
- -        Chilled Water Distribution         = 1.5N
- -        Other                              = N

The above design criteria is based on the final system configuration with all
future equipment installed.


                                       1
   28

The building shall be designed to accommodate state-of-the-art systems with the
intent of expanding to meet long-term data processing requirements. The building
utility infrastructure will enable building operation to be independent of local
utilities during an outage for approximately three days for on-site fuel and one
day for water storage. For the office/support area design and planning will
incorporate relevant office building technology and also provide an
infrastructure for long-term future growth and ongoing facility change.

Building Concept
- ----------------

The exterior building appearance in both design and finish shall be responsive
to surrounding topography and the corporate image/culture the Company intends to
portray. The building will be broken into four (4) principal elements: the data
processing area; office/support areas; the entrance/ core lobby area, and; the
mechanical/electrical and utility service area. These building elements will be
focused in a single-story building where the facade will be concrete panels with
minimum window openings. The main lobby will be a focal point of the building
and act as a central security/control point. The finishes planned for the main
entrance are ceramic tile with a walk off mat insert in the vestibules. The
lobby will have a pass-through counter/window separating Lobby and adjacent
Security Room. A separate generator building will be provided.

Add alternates shall be obtained from all major equipment suppliers and
subcontractors for future equipment attic stock and extended equipment
maintenance/warranties. These alternatives will be presented to Progressive
during project implementation for approval/funding or rejection.


Bay Size
- --------

Shall be approximately 30'x 40'; with mechanical and electrical plant bays being
approximately 30' x 50'.

Building Module
- ---------------

 24" x 48" shall be incorporated

Floor Configuration
- -------------------

General
- -------

- -       Floor size is approximately 80,000 square feet for a single-story
        configuration

        General building area Phase I building:

        Data processing             37,600

        Mech/Elec. & support        25,000

        Loading                      2,400

        Office/Support              11,550

        CORE AREA                    3,450
        ----------------------------------
        Total                       80,000 SF


                                       2
   29

- -    In addition an independent generator building of approximately 6,000 SF
     will be constructed as shown on the site plan.

- -    All slabs shall be designed to accommodate a 2' x 2' raised floor system,
     48" high, designed for a uniform load of 300 lbs. and a concentrated load
     of 1,250 lbs). Raised floor shall be installed in accordance with the
     attached approved Schematic Floor Plan.


Codes/Standards/Requirements
- ----------------------------

All design and construction shall be in accordance with applicable local, state,
federal codes and standards, ADA, Progressive and their underwriters'
requirements as identified herein. In the event of a conflict between the
applicable codes or standards, the more stringent shall prevail.


Loading
- -------


Loading/Receiving
- -----------------


- -    Two four foot (4') high docks shall be provided with appropriate bumpers,
     seals, lighting and air pillow levelers. Loading dock area shall be
     enclosed and a secured and heated receiving area shall be provided.
     Overhead doors shall be motorized and interior walls shall be painted
     white.


Geotechnical
- ------------

Geotechnical report will be prepared for the site. Building and site shall be
designed accordingly utilizing an appropriate foundation system. Spread footing
design has been assumed for this proposal.

Environmental
- -------------

A Phase I environmental survey has been completed by Progressive and no
environmental problems were noted as a result thereof.


II. SITEWORK

Site Plan - See attached approved Schematic Plan
- ---------

Site Utilities

- -    All required utilities shall be extended underground from points indicated
     on Bialosky Partners Drawings M400 and #100A, both dated October 5, 1999,
     Bulletin #67 , to the building with adequate capabilities to meet the
     project requirements as described herein. All utility work beyond limits of
     Work shall be by others.

- -    Required communication service will be identified and coordinated by
     Progressive. Base building will provide Main Distribution Frame Room and
     access via conduit. The conduit will be provided to points as shown on the
     above referenced plans.


                                       3
   30

- -    Domestic water will be supplied from the Campus Water Distribution System
     to the building and on-site storage tank.

- -    Fire protection water will be supplied from the Campus Water Distribution
     System to the building and on-site storage tank.

- -    Site storm drainage and exterior gutter drains shall be piped underground
     and discharged into appropriate storm drainage system, as provided by
     Progressive to a point approximately 30 feet outside building and shown on
     Exhibit A. Sheet draining of parking lot to catch basins and/or swells in
     non-paved areas may be incorporated prior to runoff entering underground
     piping system.

- -    Separate waste and sanitary lines will be extended from the building and
     converge at the sanitary man-hole located outside of the building.

- -    Two primary electric services shall be provided at Progressive's cost.
     Conduit to a match point shown on Exhibit A (30' from building) will be
     provided. An allowance of $20,000 is provided for the two primary feeder
     cables from Central Chilled Water Plant to project transformers.


Roads and Driveways
- -------------------

- - Paving sections shall conform to final civil geotechnical recommendations.

- - Heavy duty paving section shall be provided for truck access.

- - Fire access shall be provided around building as required by code.

- - Concrete curbs shall be provided at all site and building entrances.


Parking
- -------

A minimum of 60 parking spaces (other parking spaces will be provided on-site by
Progressive, if needed) will be provided for the project. Security with regards
to vehicle access and visitor parking will be a site plan consideration.

Parking Stalls - Minimum 9' width striped stalls
- --------------

- - Visitor and service parking areas shall be provided as appropriate.


Lighting
- --------

- -    Metal halide lamps on poles (match existing) achieving between one-half and
     one foot candles and laid out to match existing.


Landscaping
- -----------

- -    Will be consistent with surrounding area and integrated with final site
     master plan creating a corporate campus environment. All work included in
     Landscape Allowance of $25,000.

Access, Security - $50,000 Allowance
- ------------------------------------


                                       4
   31

- -    The building shall be equipped with an electronic surveillance system to
     monitor areas of the building interior and exterior (cameras shall be
     provided in appropriate location).

- -    A card access system with programmable levels of security shall be provided
     at exterior doors and raised floor perimeter. The base system will be
     expandable to permit future monitoring of systems and be an extension of
     the existing campus system.

- -    System shall be CardKey.

- -    Base building shall include rough-in for fifteen cameras on/or within the
     building and contacts at all exterior doors. Three (3) electronic strikes
     shall be provided at exterior doors. All other security cost provided in
     Security System Allowance of $50,000.




Signage
- -------

- -    Signage shall meet applicable Code and ADA requirements (signage allowance
     of $20,000 has been included).

Loading Area
- ------------

- -    Security: surveillance camera (see Security Section).

- -    Finishes: Sealed exposed concrete floor.

- -    Eight foot chain link fence and access/security gates to be provided via
     Fencing Allowance of $20,000.


III.   STRUCTURAL

Design Loads - Floors
- ---------------------

Structural floor systems shall be designed with the minimum live loads,
including partitions:

- -    Dock Areas: 200 psf

- -    All Other Areas: 150 psf, including partitions.


Structural System
- -----------------

- -    The structural system will be designed to meet load requirements and
     applicable codes.

Foundations
- -----------

- -    Foundations shall be designed and constructed with proper consideration
     given to soil, rock and ground water conditions of the site.

- -    Final foundation design (assumed to be a spread footer) shall be consistent
     with geotechnical and structural engineers' recommendations. All concrete
     shall have a minimum 28-day compressive strength of 3,000 psi. Slab on
     grade floors shall be consistent with design loads described above.





                                       5
   32


IV. EXTERIOR WALL

Combination of cast concrete and punched windows.

System Performance Criteria
- ---------------------------

- -    Wind Loads: Minimum as required by code or higher as recommended by
     structural engineer.

- -    Thermal Values: As required by Ohio Code.

- -    Walls/Spandrels: Minimum to be selected by architect.

- -    Glass: Insulated double pane.

- -    Water infiltration: no uncontrolled leakage inboard of system (as designed
     by system performance criteria.)

- -    Fire protection: as required by code.

- -    A vapor barrier system will be incorporate to permit elevated humidity
     levels (50%RH) during the winter.


V.  ROOFING

Roofing materials shall comply with all applicable codes.

Roofing System Criteria
- -----------------------

- -    The system shall be a three-ply modified Bitumen roofing system.

- -    Warranty: Twenty years from the system manufacturer.

- -    The roof will be pitched at a slope of .25" per 12".

- -    Insulation: Polyisocianurate at a thickness required complying with Ohio
     Energy Code. (Minimum R20).

- -    Insulation mechanically fastened to meet FM 1-90.

- -    Pavers: Pavers are not being provided since roof mounted equipment is
     minimal.

- -    All roof drainage will be outside the data processing building.


VI. PUBLIC AREAS

The design and selection of finish materials for public areas should be
appropriate for Progressive's corporate image. Durability and ease of
maintenance be considered in the selection of finishes.

Main Lobby
- ----------

- -    Lobby floors shall be a ceramic tile with walk off mat insert in the
     vestibule.

- -    A pass-through counter with glass window shall be provided between Security
     Room and entrance lobby.


                                       6
   33


- -    Rough-in for a Lobby pay telephone shall be provided.

- -    A building directory shall be incorporated into the lobby design.

- -    The ceiling shall be a flat painted dry-wall for perimeter with 2 x 2
     tegular edge tile inserts. Lobby wall finishes shall be a combination of
     Type II wall covering and paint.





Toilets
- -------

- -    Toilet areas shall be located as shown on floor plan and installation is to
     comply with code and ADA requirements.

- -    Fixture count will conform to variance request and floor plan.

- -    Ceilings shall be flat drywall tile with can downlight cove lighting.

- -    At the wet wall, full height glazed ceramic tile.

- -    At all other toilet room walls a serviceable vinyl wall covering.

- -    Corian, or equal for lavatory countertops with under-counter sinks.

- -    Toilet partitions shall be ceiling hung with baked enamel finish.

- -    Toilets shall be wall-mounted.

- -    Flooring shall be ceramic tile.

- -    Provide floor drain in each toilet room.


BASE BUILDING FINISHES


Electrical/Telephone Closet/ Mechanical Room
- --------------------------------------------

- -    Ceiling - Exposed structure

- -    Walls- Painted

- -    Flooring - sealed concrete


Walls and Partitions
- --------------------


CORE AREAS AND DEMISING WALLS

- -    5/8" gypsum board on metal studs 16" on center, all joints and
     corners to be taped, bedded and ready for finishing. Erect from floor to
     underside of roof deck.

- -    Insulation will be provided.





                                       7
   34



Toilet Rooms
- ------------

- -    5/8" gypsum (water resistant) board on metal studs 16" on center. Erected
     from floor to structure with insulation blanket.


Doors
- -----

Building Entries

- -    Front entrance doors shall be a part of the entry glazing system with
     automatic opening capabilities. Doors shall be aluminum storefront.


Other Exterior Doors

- -        UL labeled hollow metal painted. Rated per code.


Core Area Doors

- -    3'x 8' solid core stain grade wood doors equipped with hinges and
     standard hardware package. Doors and frames shall be rated where required
     by code. Kick plates shall be provided at all bathrooms.


Core Area Frames

- -    Hollow metal frames painted to match adjacent wall surface.


Double Doors

- -    All double doors shall have 4' to 2' leafs. 4' leaf shall have
     a piano hinge or four hinges.

0

VII. MECHANICAL


Heating, Ventilating and Air Conditioning
- -----------------------------------------

- -    Electrical centrifugal chillers shall be as manufactured by Carrier, Trane
     or York.

- -    Chiller efficiency shall be 0.6kw/ton for R134A or 0.55 kw/ton for R123 at
     full load conditions. Chillers shall be furnished with inverter-rated
     motors with variable frequency drives.

- -    Building envelope (base on ASHRAE standard 90.1) will have a wall U-factor
     of .082 and a roof U-factor of .053.

- -    The inside/outside parameters (based on ASHRAE Fundamentals - 1997)

     -    Inside Temperature: 72 (degrees)F @ 50% RH

     -    Summer Design Temperature: 91(degrees)F db, 73(degrees)F wb

     -    Winter Design Temperature: 1 (degree)F db


                                       8
   35

- -    Initial installation shall include three 500 ton centrifugal chillers and
     space for one additional machine.

- -    Commissioning of critical systems by H.F. Lenz shall be included.

- -    One year warranties for all equipment shall be included as part of the
     equipment purchase packages. Add alternates shall be provided for three or
     five years maintenance contracts on all critical equipment.

- -    Conditioning of computer room space shall be by chilled-water down-flow
     environmental control units (ECU), each equipped with manufacturer's
     standard humidification system. 34 units rated at 26 tons (total), each,
     shall be provided.

- -    Conditioning of occupied support areas shall by a central
     variable-air-volume air handling unit.

- -    Piping in Data Center Chilled Water Plant shall be furnished with colored
     PVC jacket for easy identification and durability.

- -    The data center shall be connected to the main Progressive chilled water
     plant to provide cooling equal to the critical load of 910 tons in the
     event that the data center's chiller plant is unable to satisfy the
     connected load. This shall be accomplished by tying into the existing
     chilled water plant's primary loop with a bridge and a `T to T' connection.
     The water will be pumped to two (2) plate-frame heat exchangers. The heat
     exchangers shall be piped in parallel with the data center's chillers to
     provide back-up/supplemental cooling to either of the 1,000-ton plants in
     the event of a failure.

- -    Butterfly valves in the chilled water system shall be used.

- -    Outdoor air provisions shall be as follows; human occupied areas = 20
     cfm/per person based on an occupancy of 80 plus an allowance for space
     pressurization.

- -    Outdoor air shall be introduced through the central air handling unit.

- -    A Smoking area shall be provided outside main entrance. A 5' x 10'
     bus shelter with light and electric heat shall be provided.

- -    Cooling towers shall be induced draft units, one cell per chiller. Towers
     shall have stainless steel basins. Towers shall be equipped for winter
     operation. Cooling towers shall be equipped with variable frequency drives.
     Cooling towers will be designed at 95 FDB and 78 FWB outside air
     conditions.

- -    Chilled water and condenser water circulating pumps shall be provided. Only
     the secondary chilled water pumps will be equipped with variable frequency
     drives. The drives will be equipped with a bypass feature.


VIII. MONITORING SYSTEM

All work outlined in this Section shall be included in the Monitoring System
Allowance. Allowance of $387,600 shall include cost of all work directly related
to this Scope of Work (contractor/sub-contractor related costs).

A central automated direct digital control Building Monitoring System (BMS)
shall be provided as described below.


                                       9
   36


The following functions should flow through the control points of the BMS by
taking each system individually and addressing the control points:

- -    Under raised floor monitoring

- -    HVAC Control

- -    Life Safety Interface (as required by code)

- -    Space comfort level monitoring

- -    Water detection system

- -    Water supply systems (per code)

- -    Electric power distribution

- -    Other programmable controls

It is important that the BMS design be capable of expansion and have a proven
track record of performance. System should include an additional view-only
monitor to be located at the Reception/Security Desk.

HVAC Control
- ------------

- -    The BMS system shall be designed to be expandable and provide initially 500
     pts.

- -    Start and stop designated equipment within the project. All controllable
     systems should have remote reset capabilities.

- -    The air handling unit should be controlled with not less than temperatures,
     stop/start, filter alarms and dampers.

- -    Space temperature and humidification level should be read one per air
     handler zone.



LIFE SAFETY (SEPARATE SYSTEM)

Life safety control measures which must be considered with the Building
Management System's comprehensive plan include:

- -    Remote control monitoring of fire and jockey pump.

- -    Status reporting of fire protection systems controls.

- -    Capability of printing hard copy in engineers office.



IX. PLUMBING

General
- -------


                                       10
   37

- -    This section establishes the design criteria for all plumbing work to be
     executed in the proposed facility and supplements local, state and national
     codes and laws applicable to the work being undertaken.

- -    In case of conflict between any code, standard or this RFP requirement, the
     more stringent provision shall prevail.


Systems
- -------

- -    Domestic water supply system.

- -    Sanitary fixtures.

- -    Sanitary drainage and vent system.

- -    Storm drainage system.

- -    HVAC system drainage

- -    Below raised floor drainage.


Plumbing
- --------


Domestic Water Supply System

- -    Metered domestic service will be extended from the campus distribution
     system.

- -    On-site storage tank (132,000 gallons) will be provided for fire reserve,
     cooling system make-up and domestic water requirements.

- -    Parallel back flow preventers will be provided. check valve.


Sanitary Fixtures

- -    All fixtures are to be wall hung.

- -    All fixtures are to be water saver type and utilize sensor controls.


Core Areas

- -    One (1) men's and one (1) women's toilet rooms.

- -    One electric hot water heater. Fixture count to be based on attached
     drawings. A variance shall be obtained for reduced count.

- -    All toilet rooms shall be accessible to and usable by the physically
     disabled, as required by local code and the Americans With Disabilities Act
     (ADA).

- -    Drinking fountains: Two (2) or per code.

- -    One vending area/kitchenette for building with water and drainage.


Sanitary Drainage System

- -    Provide a complete sanitary drainage system for the fixtures, floor drains,
     etc.



                                       11
   38

- -    Single system trap primer shall be utilized.

- -    Separate condensate and sanitary drainage systems will be placed below the
     slab. The systems will converge at the sanitary man-hole outside of the
     building. This is to protect the raised floor drainage system should the
     waste lines become blocked.


Storm Drainage

- -    Provide a complete system with gutters and downspouts and connect to the
     site drainage system. The design will avoid any penetrations through the
     data processing area.


X. FIRE PROTECTION


General
- -------

- -    This section establishes the design criteria for the fire protection work
     to be executed at the proposed facility.

- -    Provide an automatic cycling pre-action sprinkler system.

- -    Dry pendant, semi-recessed sprinkler heads will be provided in all areas
     with ceilings. Areas without ceilings will be equipped with up-turned
     sprinkler heads.

- -    Each sprinkler system shall have a water flow alarm, tamper switches and
     zone valves connected to a central annunciator panel.

- -    An underfloor water and smoke detection system throughout the entire raised
     floor area.

- -    All above raised floor computer equipment areas shall be protected with
     pre-action sprinkler system.

- -    The generator fuel storage rooms will be protected by foam systems.

- -    The generator room area will be protected by a dry sprinkler system.

- -    The fire protection system shall be supported by an electric fire pump. The
     fire pump shall operate from both a normal and emergency power source.



XI. ELECTRICAL


General
- -------

This document establishes electrical design criteria for the proposed facility
and shall be used to supplement local, state and national codes and laws which
are applicable to the work being undertaken, and those laws dealing with
environmental protection, occupational safety and health. In case of conflict,
the more stringent requirement shall govern.

Standards for Materials
- -----------------------


                                       12
   39

All materials shall be new and shall conform to the applicable standard or
standards where such have been established for particular material in question.
Publications and standards or the organizations listed below are applicable to
materials specified herein:

- -    Underwriters Laboratories, Inc. (UL)

- -    National Electrical Manufacturers Association (NEMA)

- -    Other general criteria:

- -    All electrical motors shall be premium efficiency, inverter duty rated.

- -    All variable frequency drives shall be of the same manufacturer and model
     to minimize parts inventory.

_    All variable frequency drives shall be provided with RFI/EMI shielding,
     line inductors, bypasses and 2 spare circuit boards of each type used.

- -    All circuit breakers 400 amps and larger shall be 100% rated.


Scope of Work
- -------------

Furnish all material, labor, transportation, tools, equipment and supervision to
completely install and leave ready for operation, complete electrical systems in
accordance with this proposal.

- -    Main switchgear, paralleling gear, switchboards, panel boards, distribution
     boards, transformers, feeders and other equipment for the complete power
     distribution system.

- -    Wiring, branch circuiting, conduit systems and devices.

- -    Lighting system.

- -    Power wiring and connection for mechanical equipment furnished under other
     sections.

- -    Emergency power distribution system should support selected
     lighting fixtures at all paths of egress as required by applicable code.

- -    Fire alarm system.

The Normal Power System consists of two in-coming services of 5,000 amperes,
each. Each service will be fed from a separate transformer rated 3000 KVA, 3
phase, 4 wire, 60 hertz. Each transformer will be fed from a separate utility
company primary feeder (provided by the power company).
EMERGENCY GENERATOR SYSTEM

- -    Initial installation shall include three, 2000 kw diesel generators with
     space for one additional unit .

- -    The diesel generators shall be as manufactured by CAT or equal.

- -    The diesel generators shall be standby-duty units with critical mufflers,
     engine mounted radiators.

- -    Four 5,000 gallon fuel storage tanks shall be provided. The tanks shall be
     housed within above-grade, fire-rated vaults as part of the generator
     building.

- -    These diesel generators shall furnish both critical and life safety loads.



                                       13
   40

UPS System
- ----------

- -    4,500 kva UPS shall be provided in six 750 kva modules. Initially four
     modules, with associated battery strings, will be installed with space for
     two additional units and their batteries.

- -    Battery capacity will be 8 minutes.

- -    PDU's will be furnished under the stated allowance. Progressive provided
     data will be used to size and configure the PDU arrangement.


Main Distribution Frame Room
- ----------------------------

- -    Provide four (4) sets of six (6) 4" incoming conduits stubbed 6" AFF in
     building main distribution frame room and extending beyond building site
     parameter wall underground to connect to conduits extending to utility
     access by others (see Exhibit A)

- -    Provide No. 16 galvanized iron "pull wire" or nylon zip string in each
     telephone conduit opening.

- -    Provide equipment backboards. Provide 4' x 8', 3/4" fireproof plywood
     sheets secured to wall around the interior of the room

- -    Provide one #1/0 copper ground wire for each backboard tied back to main
     switch gear ground.

- -    The ceiling shall be exposed structure.

- -    The finished floor shall be a sealed concrete.

- -    The Room dimension shall be approximately 30' x 50'.


Fire Alarm System
- -----------------

Provide a complete stand-alone fire alarm system to comply with Building Code,
ADA, and all ordinances having jurisdiction over this project.

Fire alarm system shall be individually addressable multiplexed type and shall
include, the following:

- -    Main FACP and one annunciator panel.

- -    Manual pull stations.

- -    Horn/strobe devices.

- -    Smoke detectors in all mechanical equipment rooms, electrical rooms,
     telephone rooms and lobbies and below the raised floor area.

- -    Smoke detectors in supply and return ducts or each air handler system in
     outside air intake fans as required by code.

- -    Monitoring of all sprinkler system alarm valves, flow switches, tamper
     switches, etc. as required by code.

- -    System shall be compatible with existing systems on campus and communicate
     with the local fire department.


                                       14
   41


Lighting System
- ---------------

- -    4' Utility Fluorescent - Mechanical and Electrical Equipment areas.

- -    27 cell parabolic in all office/support areas providing 50 initial foot
     candles at 3' above an open finish floor.

- -    All computer raised floor areas and storage areas shall utilize acrylic
     prismatic lensed fixtures.





                                       15
   42



Lightning Protection
- --------------------

- -    Provide and install a complete lightning protection system in compliance
     with NFPA No. 780. System shall be installed for a UL Master Label A.


Intermediate Distribution Frame Room
- ------------------------------------

- -    The Intermediate Distribution Frame Room shall be approx. 8'x 10'.

- -    The ceiling shall be exposed structure.

- -    The finished floor shall be a static-free tile.

- -    Provide equipment backboards. Provide 4'x 8', 3/4" fireproof plywood
     sheets secured to wall around the interior of the room and painted white.

- -    Provide one #1/0 copper ground wire for each backboard tied back to main
     switch gear ground



XII. VERTICAL TRANSPORTATION

- -        None Required






                                       16
   43


XIII. ALLOWANCES: ALL ALLOWANCES SHALL INCLUDE COST OF ALL WORK DIRECTLY RELATED
TO THE SPECIFIC SCOPE OF WORK INCLUDING ALL EQUIPMENT CONTRACTOR/SUBCONTRACTOR
COSTS.



        BMS/Monitoring System(s)                                    $387,600

        Fencing                                                     $ 20,000

        Commissioning by Independent Contractor                     $ 75,000

        Architectural Screening                                     $ 10,000

        Landscaping                                                 $ 25,000

        Appliance                                                   $  8,000

        Control Room Millwork                                       $ 15,000

        Compactor                                                   $ 40,000

        Bailer                                                      $ 15,000

        Attic Stock/Spare Parts - Equipment                         $ 30,000

        Signage                                                     $ 20,000

        Modifications within Central Chilled Water Plant            $ 75,000

        PDU's                                                       $428,000

        Security                                                    $ 50,000

        Emergency Power-Off System                                  $ 20,000

        Primary feeder cables from Chilled Water Plant.             $ 20,000







                                       17
   44


                                   EXHIBIT B-1
                                   -----------

                       Supplement to Development Agreement

         This Supplement to Development Agreement is made and entered into as of
the 16th day of November, 1999, by and between GP Ohio, L.L.C., a Rhode Island
limited liability company ("Developer") and Progressive Casualty Insurance
Company, a Ohio corporation ("Progressive").

                                    RECITALS:

         A. Developer and Progressive have previously entered into a Development
Agreement dated as of November 16, 1999.

         B. Section 2(b) of the Development Agreement anticipates that Developer
and Progressive will mutually agree on certain "Scope Documents" consisting of a
building description and outline specifications, schematic building plans and
master site plan for the Project (as defined in the Development Agreement).
Section 7(a) of the Development Agreement further anticipates that Developer and
Progressive will establish the "Stipulated Sum" to be paid by Progressive to
Developer for Developer's performance of the Work under the Development
Agreement.

         C. Developer and Progressive have reached agreement on the Scope
Documents and Stipulated Sum for the Development Agreement.

         NOW, THEREFORE, in consideration of the mutual covenants set forth
herein, the parties do hereby agree as follows:

         1. Attached hereto as SCHEDULE A is the final, approved Building
Description and Outline Specifications, Schematic Building Plans and Master Site
Plan for the Project. SCHEDULE A attached hereto is hereby incorporated in and
shall be deemed a part of EXHIBIT B to the Development Agreement, superseding
the preliminary Scope Documents identified in the EXHIBIT B previously attached
to the Development Agreement. From and after the date hereof, any and all
reference to the Scope Documents and/or EXHIBIT B in the Development Agreement
shall be deemed to refer to SCHEDULE A attached hereto.

         2. The agreed upon Stipulated Sum under the Development Agreement is
hereby established and confirmed to be $24,713,000.00, consisting of a
Professional Fees/Project Management category of $2,131,000.00 and a
Construction/Development Cost category of $22,582,000.00.

         3. Except as expressly modified herein, the Development Agreement
remains in full force and effect.


   45

         4. Terms and conditions of this Supplement shall be binding upon and
shall insure to the benefit of the parties hereto and their respective
successors and assigns.

         IN WITNESS WHEREOF, the undersigned have executed this Supplement as of
the date first written above.

                                 (Developer)

                                 GP Ohio, L.L.C.


                                 By:  Gilbane Properties, Inc., Managing Member

                                      By: /s/  Robert V. Gilbane
                                          ----------------------------------
                                      Title: President


                                 (Progressive)

                                 Progressive Casualty Insurance Company


                                 By: /s/  Daniel E. Schluer
                                          ----------------------------------
                                 Title: Senior Real Estate Project Manager










                                       1
   46






                                    EXHIBIT C
                                    ---------

                                Project Schedule


(Construction Schedule)



   47






                                    EXHIBIT D
                                    ---------

                            Termination Fee Schedule


PERIOD                                               TERMINATION FEE
- ------                                               ---------------

On or before September 1, 1999                         $100,000

September 1, 1999 to October 31, 1999                  $175,000

November 1, 1999 to November 15, 1999                  $225,000

On or after November 16, 1999                          $275,000




   48






                                    EXHIBIT E
                                    ---------

                               Expense Categories

               Design Services                            $1,477,000
               Permits and Fees                               25,000
               Professional Services Expenses                165,000



   49


                                    EXHIBIT F
                                    ---------

                             Notice of Commencement


   50

                                    ORIGINAL
                                    --------
                             NOTICE OF COMMENCEMENT
                             ----------------------
                              ( SECTION 1311.04 O.R.C.)
STATE OF OHIO,
COUNTY OF CUYAHOGA, SS:

         Daniel E. Schluer being first duly cautioned and sworn states that he
is the Senior Real Estate Project Manager of Progressive Casualty Insurance
Company, the Owner, that he is duly authorized to give this Notice of
Commencement, that the information contained hereinbelow is true as he verily
believes, and states the following:

1. NOTICE. Notice is hereby given pursuant to section 1311.04 of the Ohio
Revised Code that an Improvement which may be the subject of Mechanic Lien is
about to begin.

2. DESCRIPTION. The legal description of the real property upon which the
Improvement is to be made is attached as Exhibit A hereto, said exhibit being
incorporated by reference into this notice as if fully set forth herein.

3. IMPROVEMENT. The Improvement will be new construction of an approximately
80,000 square foot data center building and associated site improvements. The
building will share an address of 300 North Commons Boulevard, Mayfield Village,
OH with other buildings on the site. Construction is scheduled to begin
November 1, 1999.

4. CONTRACTING PARTY. Progressive Casualty Insurance Company, whose address is
6300 Wilson Mills Road, Mayfield Village, Ohio 44143, is the Owner who
contracted for the Improvement.

5. OWNERS DESIGNEE. No designee has been appointed by the Owner for this
Improvement.

6. ORIGINAL CONTRACTOR(S). The following is a complete list of the original
contractors working on the Improvement and the dates of their contracts:

         1)       Name:             Gilbane Properties, L.L.C.
                  Address:          7 Jackson Walkway
                                    Providence, RI 02903-3623

7. LENDING INSTITUTION(S). There are no lending institutions providing financing
for the Improvement.

8. SURETIES. No sureties have provided any bonds for the Improvement.



   51


9. NOTICE.

                  TO LIEN CLAIMANTS AND SUBSEQUENT PURCHASERS
                  TAKE NOTICE THAT LABOR OR WORK IS ABOUT TO BEGIN ON OR
MATERIALS ARE ABOUT TO BE FURNISHED FOR AN IMPROVEMENT TO THE REAL PROPERTY
DESCRIBED IN THIS INSTRUMENT. A PERSON HAVING A MECHANICS' LIEN MAY PRESERVE THE
LIEN BY PROVIDING A NOTICE OF FURNISHING TO THE ABOVE-NAMED DESIGNEE AND HIS
ORIGINAL CONTRACTOR, IF ANY, AND BY TIMELY RECORDING AN AFFIDAVIT PURSUANT TO
SECTION 1311.06 OF THE REVISED CODE.

                  A COPY OF THIS NOTICE MAY BE OBTAINED UPON MAKING A WRITTEN
REQUEST BY CERTIFIED MAIL TO THE ABOVE-NAMED OWNER, PART OWNER, LESSEE,
DESIGNEE, OR THE PERSON WITH WHOM YOU HAVE CONTRACTED.

10. PREPARER. The following is the name and address of the person who prepared
this Notice of Commencement.

                  1)       Name:    Daniel E. Schluer
                           Address: 300 North Commons Boulevard
                                    Mayfield Village, OH 44143

11.      Further Affiant sayeth naught.

                                              /s/  Daniel E. Schluer
                                              ----------------------
                                              Daniel E. Schluer

         Sworn to and subscribed in my presence this 26th day of October, 1999.

                                              /s/  Rachael J. Lardie
                                              ----------------------
                                              NOTARY PUBLIC


   52


                                    EXHIBIT A
                                LEGAL DESCRIPTION


         Situated in the Village of Mayfield, County of Cuyahoga and State of
Ohio, and known as being part of Original Mayfield Township Lot Nos. 15 and 25,
Tract No. 1, and being further bounded and described as follows:

         Commencing at a 1 inch diameter iron pin monument found in the
centerline of S.O.M. Center Road, (S.R. 91), 60 feet wide, at its intersection
with the Southerly line said Original Lot No. 15; Thence North 1(degree)15'18"
East, along the centerline of S.O.M. Center Road a distance of 692.89 feet to
the Southeasterly corner of land conveyed to the Village of Mayfield by deed
recorded in Volume 97-11623, Page 25 of Cuyahoga County Records; Thence North
89(degree)23'28" West along the Southerly line of land so conveyed to the
Village of Mayfield a distance of 777.90 feet to capped iron pin set at the
principal place of beginning of the parcel of land herein described;

         Thence South 43(degree)26'00" West, a distance of 940.00 feet to a
capped iron pin set;

         Thence South 56(degree)26'40" West, a distance of 881.08 feet to a
capped iron pin set in the Easterly Limited Right of Way of State Highway No. 1,
(Interstate 271);

         Thence North 3(degree)14'16" West, along said Easterly Limited Right of
Way line a distance of 129.87 feet to a capped iron pin set at an angle therein;

         Thence North 5(degree)47'36" East, continuing along said Easterly
Limited Right of Way line a distance of 560.68 feet to a capped iron pin set at
an angle therein;

         Thence North 0(degree)17'43" East, continuing along said Easterly
Limited Right of Way line distance of 116.18 feet to a capped iron pin set at
the Southwesterly corner of land conveyed to the C.E.I. Co. by deed recorded in
Volume 14210, Page 869 of Cuyahoga County Records;

         Thence South 89(degree)23'28" East, along the Southerly line of land so
conveyed the C.E.I. Co. a distance of 30.00 feet to a capped iron pin set at the
Southeasterly corner of said land;

         Thence North 2(degree)20'48" East, along the Easterly line of land so
conveyed to the C.E.I. Co. a distance of 108.52 feet to a capped iron pin set at
the Northeasterly corner of said land;

         Thence North 89(degree)23'28" West, along the Northerly line of land so
conveyed to the C.E.I. Co. distance of 35.00 feet to a capped iron pin set at
the Northwesterly corner of said land, in the Easterly Limited Right of Way of
State Highway No. 1, (Interstate 271);

         Thence North 0(degree)17'43" West, along said Easterly Limited Right of
Way line a distance of 181.02 feet to a capped iron pin set at an angle therein;

         Thence North 3(degree)25'45" East, continuing along said Easterly
Limited Right of Way line a distance of 90.58 feet to a 3/4 inch diameter iron
pin found at the Southwesterly corner of land conveyed to the Village of
Mayfield, aforesaid;

         Thence South 89(degree)23'28" East, along said Southerly line a
distance of 1313.32 feet to principal place of beginning and containing 19.6383
acres of land, be the same more or less as surveyed by Stephen Hovancsek and



   53


Associates, Inc., Registered Surveyor No. 5160, State of Ohio in January 1998,
but subject to all legal highways. Bearings are to an assumed meridian and are
used to denote angles only. All capped iron pins set are 5/8 inch diameter
rebar, 30 inches long, with a plastic cap marked SH&A 5160.

         Prior instrument reference: Volume 97-11876, Page 01.