Exhibit 10.108

                                                     Contract No. 14-06-300-2131

                                 NAVAJO PROJECT

                            PARTICIPATION AGREEMENT

                                    BETWEEN

                          THE UNITED STATES OF AMERICA

                         ARIZONA PUBLIC SERVICE COMPANY

                         DEPARTMENT OF WATER AND POWER
                           OF THE CITY OF LOS ANGELES

                              NEVADA POWER COMPANY

                        SALT RIVER PROJECT AGRICULTURAL
                         IMPROVEMENT AND POWER DISTRICT

                         TUCSON GAS & ELECTRIC COMPANY



                     NAVAJO PROJECT PARTICIPATION AGREEMENT

                                TABLE OF CONTENTS



SECTION                                                                        PAGE
- -------                                                                        ----
                                                                         
      1     PARTIES                                                              1

      2     RECITALS                                                             1

      3     AGREEMENT                                                            2

      4     DEFINITIONS                                                          2

            4.1   CAPACITY                                                       2

            4.2   CONTRACTING OFFICER                                            2

            4.3   CO-TENANTS                                                     2

            4.4   ENERGY                                                         3

            4.5   FIRM OPERATION                                                 3

            4.6   GENERATION ENTITLEMENT SHARE                                   3

            4.7   NAVAJO GENERATING STATION                                      3

            4.8   NAVAJO PLANT SITE                                              4

            4.9   NAVAJO PROJECT                                                 4

            4.10  NET EFFECTIVE GENERATING CAPABILITY                            4

            4.11  OPERATING AGENT                                                4

            4.12  PARTICIPANTS                                                   4

            4.13  POWER                                                          4

            4.14  PROJECT AGREEMENTS                                             4

            4.15  PROJECT INSURANCE                                              5

            4.16  PROJECT MANAGER                                                5

            4.17  SECRETARY                                                      5

            4.18  STATION WORK                                                   5

            4.19  STATION WORK LIABILITY                                         5


                                      (i)




SECTION                                                                        PAGE
- -------                                                                        ----
                                                                         
      4     DEFINITIONS (Continued)

            4.20  TRANSMISSION SYSTEM                                            6

            4.21  TRANSMISSION WORK                                              6

            4.22  TRANSMISSION WORK LIABILITY                                    6

            4.23  WILLFUL ACTION                                                 7

            4.24  ZERO NET LOAD                                                  9

      5     OWNERSHIP OF NAVAJO PROJECT                                          9

      6     GENERATING STATION CAPACITY AND ENERGY ENTITLEMENTS                 10

      7     TRANSMISSION SYSTEM                                                 11

      8     ADMINISTRATION                                                      15a

      9     OTHER COMMITTEES                                                    21

     10     PROJECT MANAGERS                                                    21

     11     OPERATING AGENTS                                                    23

     12     CONSTRUCTION SCHEDULES                                              24

     13     CONSTRUCTION COSTS                                                  24

     14     OPERATION AND MAINTENANCE COSTS                                     25

     15     ADVANCEMENT OF FUNDS                                                27

     16     TAXES                                                               29

     17     NONPARTITIONMENT                                                    30

     18     MORTGAGE AND TRANSFER OF INTERESTS                                  30

     19     RIGHT OF FIRST REFUSAL                                              33

     20     DESTRUCTION                                                         33

     21     INSURANCE                                                           35

     22     LIABILITY                                                           38


                                      (ii)




SECTION                                                                        PAGE
- -------                                                                        ----
                                                                         
     23           INTERESTS HELD FOR THE USE AND BENEFIT OF UNITED STATES       41

     24           REIMBURSEMENT FOR COSTS AND EXPENSES                          43

     25           DEFAULTS                                                      43

     26           ARBITRATION                                                   45

     27           ACTIONS PENDING RESOLUTION OF DISPUTES                        46

     28           REMOVAL OF OPERATING AGENTS                                   47

     29           RELATIONSHIP OF PARTICIPANTS                                  47

     30           FEES                                                          48

     31           OFFICIALS NOT TO BENEFIT                                      48

     32           COVENANT AGAINST CONTINGENT FEES                              49

     33           EQUAL OPPORTUNITY                                             49

     34           WORK HOURS ACT OF 1962                                        54

     35           EXAMINATION OF RECORDS                                        56

     36           ASSIGNMENT OF CLAIMS                                          56

     37           CONVICT LABOR                                                 58

     38           UNCONTROLLABLE FORCES                                         58

     39           GOVERNING LAW                                                 59

     40           BINDING OBLIGATIONS                                           59

     41           NONDEDICATION OF FACILITIES                                   60

     42           PROJECT AGREEMENTS                                            60

     43           TERM                                                          61

     44           ASSIGNMENT OF INTERESTS                                       61

     45           NOTICES                                                       62

     46           MISCELLANEOUS PROVISIONS                                      63


                                     (iii)




SECTION                                                                        PAGE
- -------                                                                        ----
                                                                         
     47     USE OF FACILITIES OF LOS ANGELES                                    65

     48     AGREEMENT SUBJECT TO COLORADO RIVER COMPACT                         66


                                      (iv)


                                 NAVAJO PROJECT
                             PARTICIPATION AGREEMENT

1.    PARTIES: The parties to this agreement are: THE UNITED STATES OF AMERICA,
      hereinafter referred to as the "United States", acting through the
      Secretary of the Interior; ARIZONA PUBLIC SERVICE COMPANY, an Arizona
      corporation, hereinafter referred to as "Arizona"; DEPARTMENT OF WATER AND
      POWER OF THE CITY OF LOS ANGELES, a department organized and existing
      under the Charter of the City of Los Angeles, a municipal corporation of
      the State of California, hereinafter referred to as "Los Angeles"; NEVADA
      POWER COMPANY, a Nevada corporation, hereinafter referred to as "Nevada";
      SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT, an
      agricultural improvement district organized and existing under the laws of
      the State of Arizona, hereinafter referred to as "Salt River Project"; and
      TUCSON GAS & ELECTRIC COMPANY, an Arizona corporation, hereinafter
      referred to as "Tucson".

2.    RECITALS: This agreement is made with reference to the following facts,
      among others:

            2.1 By the Colorado River Basin Project Act (82 Stat. 885) the
      Congress of the United States authorized the construction, operation and
      maintenance of the Central Arizona Project. Pursuant to Section 303 of
      said Act, the Secretary is authorized to enter into agreements



      with non-Federal interests proposing to construct thermal generating
      powerplants whereby the United States shall acquire the right to such
      portions of their capacity, including delivery of power and energy over
      appurtenant transmission facilities to mutually agreed upon delivery
      points, as he determines is required in connection with the operation of
      the Central Arizona Project.

            2.2 The Secretary has determined that the acquisition of a right to
      a portion of the capacity of the Navajo Project is the most feasible plan
      for supplying the power requirements of the Central Arizona Project and
      augmenting the Lower Colorado River Basin Development Fund.

            2.3 The parties desire to participate in the construction, operation
      and maintenance of the Navajo Project in accordance with the provisions of
      this Participation Agreement and the other Project Agreements.

3.    AGREEMENT: In consideration of the mutual covenants herein, the parties
      agree as follows:

4.    DEFINITIONS: The following terms, when used herein, shall have the
      meanings specified:

            4.1 CAPACITY: Electrical rating expressed in megawatts (mw) or
      megavolt-amperes (mva).

            4.2 CONTRACTING OFFICER: The Secretary of the Interior or his duly
      authorized representative.

            4.3 CO-TENANTS: Any one or all of the parties other

                                      -2-


      than the United States.

            4.4 ENERGY: Kilowatt-hours (kwh).

            4.5 FIRM OPERATION: The state of completion at which a component of
      the Navajo Project is determined by the appropriate engineering and
      operating committee to be reliable and at which that component can
      reasonably be expected to operate continuously at its rated Capacity.

            4.6 GENERATION ENTITLEMENT SHARE: The percentage entitlement of each
      Participant in each unit of the Navajo Generating Station. Each
      Participant's percentage is as follows:

                4.6.1     United States  =  24.3 per cent.

                4.6.2     Arizona        =  14.0 per cent.

                4.6.3     Los Angeles    =  21.2 per cent.

                4.6.4     Nevada         =  11.3 per cent.

                4.6.5     Salt River     =  21.7 per cent.
                            Project

                4.6.6     Tucson         =  7.5 per cent.

            4.7 NAVAJO GENERATING STATION: Three coal-fired steam electric
      generating units, each having a nameplate rating of 750 mw and an
      estimated Net Effective Generating Capability of 770 mw, and all
      facilities and structures used therewith or related thereto, to be
      constructed at or adjacent to the Navajo Plant Site. The Navajo Generating
      Station is generally described in

                                      -3-


      Exhibit A-1 hereto.

            4.8 NAVAJO PLANT SITE: A parcel of land in Coconino County, Arizona,
      consisting of approximately 1,020 acres and being generally depicted on
      Exhibit B hereto.

            4.9 NAVAJO PROJECT: The Navajo Project shall consist of the Navajo
      Generating Station and the Transmission System, all as generally described
      and depicted on Exhibit A hereto.

            4.10 NET EFFECTIVE GENERATING CAPABILITY: The maximum continuous
      ability of each unit of the Navajo Generating Station to produce Power
      which is available to the Participants at the high voltage terminals of
      the generator step-up transformers.

            4.11 OPERATING AGENT: A Co-Tenant responsible for the operation and
      maintenance of a component of the Navajo Project in accordance with the
      Project Agreements,

            4.12 PARTICIPANTS: Any one or more of the parties, including the
      United States.

            4.13 POWER: Kilowatts (kw) or megawatts (mw).

            4.14 PROJECT AGREEMENTS: This Participation Agreement, the grants
      from the United States for use of Indian lands pursuant to 25 U.S.C.
      Section 323 (Section 323 grants), the plant site lease, the co-tenancy
      agreements, the construction agreements, the operating agreements, other
      agreements for rights of way and easements for the Navajo Project
      facilities, the Navajo Station Coal

                                      -4-



      Supply Agreement, agreements related to the transportation of fuel, the
      Water Service Contract dated the 17th day of January, 1969 (Contract No.
      14-06-400-5033), the agreements establishing the rights of the
      Participants in water rights or coal lands, the agreement between the Salt
      River Project and the United States concerning the capacity entitlements
      of the United States, as such agreements are originally executed or as
      they may thereafter be supplemented or amended.

            4.15 PROJECT INSURANCE: Policies of insurance to be procured and
      maintained in accordance with Section 21 hereof.

            4.16 PROJECT MANAGER: A Co-Tenant responsible for the construction
      and completion of a component of the Navajo Project in accordance with the
      Project Agreements.

            4.17 SECRETARY: The Secretary of the Interior.

            4.18 STATION WORK: Engineering, design, contract preparation,
      purchasing, construction, supervision, expediting, inspection, accounting,
      testing, protection, operation, repair, maintenance, replacement,
      reconstruction or use of and for the Navajo Generating Station.

            4.19 STATION WORK LIABILITY: Liability of one or more Participants
      for damage suffered by anyone other than a Participant, whether or not
      resulting from the negligence of any Participant, its directors, officers,

                                      -5-


      employees or any other person or entity whose negligence would be imputed
      to such Participant, resulting from:

                  4.19.1 The performance or non-performance of Station Work.

                  4.19.2 The use or ownership of the Navajo Generating Station.

                  4.19.3 The past or future performance or non-performance of
                         the obligations of any Participant under any of the
                         Project Agreements, except obligations relating solely
                         to the Transmission System.

            4.20 TRANSMISSION SYSTEM: The Transmission System as generally
      described in Exhibit A-2 hereto.

            4.21 TRANSMISSION WORK: Engineering, design, contract preparation,
      purchasing, construction, supervision, expediting, inspection, accounting,
      testing, protection, operation, repair, maintenance, replacement,
      reconstruction or use of and for the Transmission System.

            4.22 TRANSMISSION WORK LIABILITY: Liability of one or more
      Participants for damage suffered by anyone other than a Participant,
      whether or not resulting from the negligence of any Participant, its
      directors, officers, employees or any other person or entity whose
      negligence would be imputed to such Participant,

                                      -6-


      resulting from:

                  4.22.1 The performance or non-performance of Transmission
                         Work.

                  4.22.2 The use or ownership of the Transmission System or any
                         component thereof.

                  4.22.3 The past or future performance or non-performance of
                         the obligations of any Participant under any of the
                         Project Agreements, except obligations relating solely
                         to the Navajo Generating Station.

            4.23  WILLFUL ACTION:

                  4.23.1 Action taken or not taken by a Participant at the
                         direction of its directors, officers, Contracting
                         Officer or employees having management or
                         administrative responsibility affecting its performance
                         under any of the Project Agreements, which action is
                         knowingly or intentionally taken or failed to be taken
                         with conscious indifference to the consequences thereof
                         or with intent that injury or damage would result or
                         would probably result therefrom.

                                      -7-


                         Willful Action does not include any act or failure to
                         act which is merely involuntary, accidental or
                         negligent.

                  4.23.2 Action taken or not taken by a Participant at the
                         direction of its directors, officers, Contracting
                         Officer or employees having management or
                         administrative responsibility affecting its performance
                         under any of the Project Agreements, which action has
                         been determined by final arbitration award or final
                         judgment or judicial decree to be a material default
                         under any of the Project Agreements and which occurs or
                         continues beyond the time specified in such arbitration
                         award or judgment or judicial decree for curing such
                         default or, if no time to cure is specified therein,
                         occurs or continues thereafter beyond a reasonable time
                         to cure such default.

                  4.23.3 Action taken or not taken by a Participant at the
                         direction of its directors, officers, Contracting
                         Officer or employees having management

                                      -8-


                         or administrative responsibility affecting its
                         performance under any of the Project Agreements, which
                         action is knowingly or intentionally taken or failed to
                         be taken with the knowledge that such action taken or
                         failed to be taken is a material default under any
                         Project Agreements.

                  4.23.4 The phrase "employees having management or
                         administrative responsibility" as used in this Section
                         4.23 means employees of a Participant who are
                         responsible for one or more of the executive functions
                         of planning, organizing, coordinating, directing,
                         controlling and supervising such Participant's
                         performance under any of the Project Agreements.

            4.24 ZERO NET LOAD: The load upon a generating unit when the
      generator gross output equals the total unit auxiliary consumption.

5.    OWNERSHIP OF NAVAJO PROJECT:

            5.1 The Co-Tenants shall acquire and own the Navajo Generating
      Station as tenants in common, as follows:

                  5.1.1  Arizona shall own an undivided 14.0 per cent interest
                         therein.

                                      -9-


                  5.1.2  Los Angeles shall own an undivided 21.2 per cent
                         interest therein.

                  5.1.3  Nevada shall own an undivided 11.3 per cent interest
                         therein.

                  5.1.4  Salt River Project shall own:

                              (i)   an undivided 21.7 per cent interest therein
                                    for its own use and benefit, and

                              (ii)  an undivided 24.3 per cent interest therein
                                    for the use and benefit of the United States
                                    in accordance with the Project Agreements.

                  5.1.5  Tucson shall own an undivided 7.5 per cent interest
                         therein.

            5.2 The Co-Tenants shall acquire the ownership interests in the
      Transmission System components as described in Exhibit C hereto and shall
      own the same as tenants in common. Not every Co-Tenant will own an
      interest in every component of the Transmission System.

6.    GENERATING STATION CAPACITY AND ENERGY ENTITLEMENTS:

            6.1 The Capacity entitlement of each Participant in each unit of the
      Navajo Generating Station shall be the product of its Generation
      Entitlement Share and the Net Effective Generating Capability of such
      unit.

            6.2 Each Participant shall be entitled to schedule

                                      -10-


      for its account Power and Energy from any generating unit up to the amount
      of its available Capacity entitlement in such unit.

            6.3 When a Participant requests operation of a unit, each
      Participant shall, unless otherwise mutually agreed, schedule for its
      account its share of minimum net generation which shall be the product of
      its Generation Entitlement Share and the minimum net generation
      established for such unit. At any time any Participant has scheduled from
      any unit an amount of Power in excess of its minimum net generation, then
      each of the other Participants shall only be obligated to schedule for its
      account an amount of Power equal to the product of its Generation
      Entitlement Share and the remaining amount of minimum net generation,
      provided that such reductions do not result in economic detriment to any
      Participant or the Operating Agent.

            6.4 Operation of any unit by the Operating Agent shall be subject to
      scheduled outages or curtailments, operating emergencies and unscheduled
      outages or curtailments of such unit.

7. TRANSMISSION SYSTEM:

            7.1 The Transmission System shall be designed, constructed and
      operated with the objective of permitting each Participant to transmit
      under normal operating conditions its share of entitlement in the Navajo

                                      -11-


      Generating Station from the Navajo Generating Station to its designated
      points of delivery in a manner which will not, unreasonably affect the
      operation of the electric systems of the Participants, and, so that when
      operated in parallel with such systems, the loss of any one circuit will
      not cause any other circuit or element of and of the parallel transmission
      systems of a Participant to carry Power in excess of the short-time rating
      of such parallel transmission system as may be established by the owner of
      such system.

            7.2 Each Participant shall have the right to use the Transmission
      System to transmit to its designated delivery points under normal
      operating conditions Power in an amount equivalent to its Capacity
      entitlement share in the Navajo Generating Station or to reserve the
      Transmission System for such transmission without regard to the origin,
      source, ownership or type of generation used to produce such Power.

            7.3 Any Participant may acquire firm entitlement in the Transmission
      System, in addition to that provided for in Section 7.2 hereof upon the
      written agreement of all Participants having cost responsibility for the
      facilities over which such firm entitlement is sought, provided that said
      firm entitlement does not materially interfere with the right of any other
      Participant to transmit its entitlement as provided in Section 7.2

                                      -12-


      hereof. Such written agreement shall specify the amount of monetary
      compensation to be paid to and the allocation among the Participants for
      such firm entitlement.

            7.4 Any Participant may make non-firm use of transmission Capacity
      in addition to its use under Section 7.2 hereof to the extent that
      transmission Capacity is determined to be available by the Operating
      Agents in accordance with criteria to be developed by the engineering and
      operating committee.

            7.5 If two or more Participants concurrently desire to make non-firm
      use of transmission Capacity in the same segment of the Transmission
      System pursuant to Section 7.4 hereof, and the available transmission
      Capacity in such segment is not adequate to satisfy all such requests,
      then, unless otherwise agreed to, the available Capacity will be shared by
      those Participants concurrently requesting such Capacity in proportion to
      their cost responsibility in such segment.

            7.6 The Participants' designated points of delivery shall be as
      follows:

                  7.6.1 Arizona     =  Navajo 500 KV Switchyard and Phoenix Area
                                       Substation (s).

                  7.6.2 Los Angeles =  Navajo 500 KV Switchyard and McCullough
                                       500 KV Switchyard.

                                      -13-


                  7.6.3  Nevada     =  Navajo 500 KV Switchyard and McCullough
                                       287 KV Switchyard.

                  7.6.4  Salt River =  Navajo 500 KV Switchyard
                           Project     and Phoenix Area Substation (s).

                  7.6.5  Tucson     =  Navajo 500 KV Switchyard and Phoenix Area
                                       Substation (s).

                  7.6.6  United     =  Navajo 500 KV Switchyard,
                           States      McCullough 500 KV Switchyard, Phoenix
                                       Area Substation (s), and the Moenkopi
                                       Switchyard during the period in which the
                                       United States is selling power to
                                       Southern California Edison Company
                                       pursuant to the Contract With Southern
                                       California Edison Company For Interim
                                       Sale Of United States' Entitlement In
                                       Navajo Project for delivery at Moenkopi
                                       switchyard.

            7.7 Each Participant shall be entitled to interconnect its
      transmission system with the Transmission System at its designated points
      of delivery, and the costs of such interconnection shall be paid by such
      Participant.

            7.8 In the event of an outage or curtailment of any circuit or
      element of the Transmission System, the Operating Agents shall make every
      effort to furnish temporary alternate service through other circuits or
      elements of the Transmission System, and the Participants shall make
      every effort to furnish alternate

                                      -14-


      service to the other Participants over available parallel transmission
      systems, and, in the event of an outage or curtailment of any such
      parallel transmission system of a Participant, the Operating Agents shall
      make every effort to furnish temporary alternate service over the
      Transmission System. There will be no charge to any Participant for such
      service provided pursuant to this Section 7.8, except for compensation in
      Energy for additional losses that may be incurred as a result of providing
      such alternate service.

            7.9 Upon agreement with all the other Participants, a Participant
      may at its expense make interconnections to the Transmission System at
      other points. Such agreement shall specify the terms and conditions
      under which such interconnections may be made and the charges to the
      interconnecting Participant, if any, and the distribution of such charges
      to the other Participants.

            7.10 Unless otherwise agreed to by the engineering and operating
      committee, when the Capacity available to the Participants in any segment
      of the Transmission System is insufficient to accommodate all of the firm
      use of the Transmission System pursuant to Section 7.2 hereof, then the
      use of the available Capacity of that segment of the Transmission System
      will be allocated in proportion to the Participants' cost responsibility
      in such segment. It is not the intention of the Participants

                                      -15-


      to dedicate any Capacity in the Transmission System for use by third
      parties.

            7.11 The Transmission System will be interconnected with the Four
      Corners-Eldorado 500 KV transmission line at the Moenkopi Switchyard in
      accordance with the memorandum of intent attached as Exhibit H hereto.

            7.12 For the purposes of Section 7, any use of any section of line
      by the United States which is in excess of the greater of (i) the United
      States' percentage cost responsibility in such line times the capability
      of such, or (ii) the capability required to supply the power requirements
      of the Central Arizona Project, shall be deemed to be non-firm use unless
      the right to such use shall have been acquired pursuant to Section 7.3
      hereof.

8.    ADMINISTRATION:

            8.1 The Participants shall establish the following Committees, whose
      functions and shall be as described herein or in the subsequent Project
      Agreements:

                                      -15a-


                  8.1.1 One coordinating committee for the Navajo Project,
                        consisting of one representative from each Participant,
                        who shall be an officer or general manager of a
                        Participant or the designee of the Secretary, or his
                        authorized alternates.

                  8.1.2 One engineering and operating committee for the Navajo
                        Generating Station, consisting of two representatives
                        from each Participant.

                  8.1.3 One engineering and operating committee for the
                        Transmission System, consisting of two representatives
                        from each Participant.

                  8.1.4 One auditing committee for the Navajo Project,
                        consisting of two representatives from each
                        Participant.

            8.2 The coordinating committee shall have the following functions,
      among others:

                  8.2.1 To provide liaison among the Participants at the
                        management level.

                  8.2.2 To exercise general supervision over the engineering and
                        operating committees and the auditing committee.

                                      -16-


                  8.2.3 To consider matters referred to it by another committee.

                  8.2.4 To perform such other functions and duties as may be
                        assigned to it in the Project Agreements.

            8.3 The engineering and operating committees shall have the
      following functions, among others, at the construction stages:

                  8.3.1 To provide liaison among the Participants and between
                        them and the respective Project Managers and Operating
                        Agents with respect to the engineering, construction and
                        start-up of the components of the Navajo Project.

                  8.3.2 To consider such matters and take such actions as are
                        assigned to them in the Project Agreements.

                  8.3.3 To perform such other functions and duties as may be
                        assigned to them by the coordinating committee.

            8.4 The engineering and operating committee for the Navajo
      Generating Station shall have the following functions, among others, with
      respect to the operation of the Navajo Generating Station:

                  8.4.1 To provide liaison among the

                                      -17-


                        Participants and between them and the Operating Agent.

                  8.4.2 To review and act upon the Operating Agent's
                        recommendations concerning:

                              Budgets for operation and maintenance and for
                                capital expenditures

                              Manning tables

                              Operating and maintenance practices and procedures

                              Planned maintenance schedules

                              Policies for establishing inventories

                              Statistical and administrative reports, budgets
                                and information and other similar records, and
                                the form and preparation thereof, to be kept and
                                performed by the Operating Agent

                              Procedures for determining Capacities of
                                facilities

                              Procedures for capital expenditures

                              Procedures for performance and efficiency testing

                              Procedures for maintaining Power and Energy
                                accounting

                              Procedures for dealing with operating emergencies
                                or curtailed operations

                              Practices and procedures for scheduling Power and
                                Energy

                  8.4.3 To perform such other functions and duties as may be
                        assigned to it in the Project Agreements or by the
                        coordinating committee.

            8.5 The engineering and operating committee for the Transmission
      System shall have the following functions, among others, with respect to
      the operation of the Transmission System:

                                      -18-


                  8.5.1 To provide liaison among the Participants and between
                        them and the Operating Agents.

                  8.5.2 To review and act upon the Operating Agents'
                        recommendations concerning:

                              Practices and procedures for accounting for
                                transmission losses

                              Budgets for operation and maintenance and for
                                capital expenditures

                              Operating and maintenance practices and procedures

                              Planned maintenance schedules

                              Policies for establishing inventories

                              Statistical and administrative reports, budgets
                                and information and other similar records, and
                                the form and preparation thereof, to be kept and
                                performed by the Operating Agents

                              Procedures for determining Capacities of
                                facilities

                              Procedures for capital expenditures

                              Procedures for performance testing

                              Procedures for maintaining Power and Energy
                                accounting

                              Procedures for dealing with operating emergencies
                                or curtailed operations

                  8.5.3 To perform such other functions and duties as may be
                        assigned to it in the Project Agreements or by the
                        coordinating committee.

            8.6 The auditing committee shall have the following functions, among
      others:

                  8.6.1 To develop procedures for proper

                                      -19-


                        accounting and financial liaison among the Participants
                        in connection with the engineering, construction,
                        operation, replacement and reconstruction of the Navajo
                        Project.

                  8.6.2 To review accounting and financial aspects thereof.

                  8.6.3 To advise and make recommendations to the coordinating
                        committee, the Project Managers and the Operating Agents
                        on matters involving auditing and financial
                        transactions.

                  8.6.4 To perform such other functions and duties as may be
                        assigned to it in the Project Agreements or by the
                        coordinating committee.

            8.7 Within thirty (30) days after the execution of this agreement,
      each Participant shall designate its representatives on the committees
      hereby established. Such designation shall be in writing, with copies
      mailed to each of the Participants.

            8.8 Any action or determination of a committee must be unanimous.

            8.9 All actions, agreements or determinations made by the committees
      shall be reduced to writing. In addition, the engineering and operating
      committees and

                                      -20-


      the auditing committee shall keep written minutes and records of all
      meetings.

         8.10  The committees shall have no authority to
         modify any of the terms, covenants or conditions of the
      Project Agreements.

            8.11 If the engineering and operating committees or the auditing
      committee fail to agree while performing the functions and duties assigned
      to them in this agreement or in the other Project Agreements, then such
      disagreement shall be referred to the coordinating committee.

9. OTHER COMMITTEES:

            9.1 Other committees may be established by the coordinating
      committee to perform such other functions and have such responsibility as
      may be assigned to them by the coordinating committee.

10. PROJECT MANAGERS:

            10.1  The Project Managers shall be as follows:

                  10.1.1 Salt River Project shall be the Project Manager for the
                         Navajo Generating Station.

                  10.1.2 Arizona shall be the Project Manager for the
                         Transmission System, except for the Navajo-McCullough
                         500 KV line and the McCullough Substation.

                                      -21-

                  10.1.3 Los Angeles shall be the Project Manager for the
                         Navajo-McCullough 500 KV line and the McCullough
                         Substation.

            10.2  A Project Manager shall:

                  10.2.1 Provide for the engineering, design, contract
                         preparation, purchasing, construction, supervision,
                         expediting, inspection, accounting, testing and
                         start-up of its designated component so as to complete
                         such component for Firm Operation.

                  10.2.2 Promptly supply the Participants with information on
                         major matters regarding its designated component and
                         significant factors which affect construction
                         schedules.

                  10.2.3 Provide the committees with all necessary records and
                         information pertaining to matters within their
                         designated responsibilities.

            10.3 The Project Managers of the Transmission System shall optimize
      the design of the Transmission System. The Participants recognize that
      such optimization may result in modifications in the Transmission System
      as described in Exhibit A-2. In the event of such

                                      -22-


      modifications, the Participants shall agree on an equitable method of
      allocating the construction, operation and maintenance cost
      responsibilities.

11. OPERATING AGENTS:

            11.1  The Operating Agents shall be as follows:

                        11.1.1 Salt River Project shall be the Operating Agent
                               for the Navajo Generating Station.

                        11.1.2 Arizona shall be the Operating Agent for the
                               Transmission System, except for the
                               Navajo-McCullough 500 KV line and the McCullough
                               Substation.

                        11.1.3 Los Angeles shall be the Operating Agent for the
                               McCullough Substation.

                        11.1.4 Nevada shall be the Operating Agent for the
                               Navajo-McCullough 500 KV line.

            11.2 The Operating Agents shall be responsible for the operation and
      maintenance of their designated components of the Navajo Project, and in
      connection therewith shall:

                        11.2.1 Provide for engineering, contract preparation,
                               purchasing, repair, supervision, training,
                               expediting, inspection, testing, protection,
                               operation, maintenance, retirement

                                      -23-


                               and replacement.

                        11.2.2 Prepare recommendations covering the matters
                               which are to be reviewed and acted upon by the
                               engineering and operating committees.

                        11.2.3 Follow the practices and procedures which have
                               been reviewed and approved by the engineering and
                               operating committees and generally accepted
                               practices in the electric utility industry.

                        11.2.4 Keep the Participants fully and promptly advised
                               of material changes in conditions or other
                               material developments affecting the performance
                               of their designated responsibilities.

12.   CONSTRUCTION SCHEDULES:

            12.1 Construction of the Navajo Project has been planned with the
      objective of having each component available for start-up operation or
      energization for test date and for Firm Operation on the dates specified
      in Exhibit D hereto.

13.   CONSTRUCTION COSTS:

            13.1 Construction costs shall include all payments made and
      obligations incurred by the Project Managers for or in connection with the
      construction of the

                                      -24-


      Navajo Project, including but not limited to those costs specified in
      Exhibit E hereto.

            13.2 The construction costs of the Navajo Generating Station shall
      be shared and paid for by the Participants in proportion to their
      Generation Entitlement Shares.

            13.3 The construction costs of the Transmission System shall be
      shared and paid for by the Participants in the manner shown in Exhibit C
      hereto.

            13.4 United States shall not bear any part of any other
      Participant's costs for interest, interest during construction, financing
      charges and franchise fees.

14.   OPERATION AND MAINTENANCE COSTS:

            14.1 Operation and maintenance costs of the Navajo Generating
      Station shall include all payments made and obligations incurred by the
      Operating Agent for or in connection with operation and maintenance,
      including but not limited to those costs specified in Exhibit F hereto.

            14.2 The operation and maintenance costs of the Navajo Generating
      Station, including costs of water but excluding costs of fuel, shall be
      shared by the Participants in proportion to their Generation Entitlement
      Shares. The amount of fuel required for active storage and the initial
      emergency fuel storage, the rate of fuel consumption for Zero Net Load
      operation and the costs of start-up shall be determined in accordance with
      procedures to be established by the engineering and

                                      -25-


      operating committee, and the costs thereof and fixed fuel transportation
      charges, if any, shall be shared by the Participants in proportion to
      their Generation Entitlement Shares.

            14.3 Except as provided in Section 14.2 hereof, the costs of fuel
      for each generating unit and the variable fuel transportation charges
      shall be shared by each Participant in the ratio that such Participant's
      monthly net energy generation scheduled from such unit bears to the total
      monthly net energy generation scheduled from such unit.

            14.4 The costs of ash disposal shall be shared among the
      Participants in the same proportions as the monthly allocations of fuel
      costs among the Participants.

            14.5 The operation and maintenance costs of the Transmission System
      shall include all payments made and obligations incurred by the Operating
      Agent for and in connection with such operation and maintenance, including
      but not limited to those costs specified in Exhibit G hereto.

            14.6 The operation and maintenance costs of the Transmission System
      shall be shared and paid for by the Participants in the manner specified
      in Exhibit C hereto.

            14.7 United States shall not bear any part of any other
      Participant's costs for interest, interest during

                                      -26-

      construction, financing charges and franchise fees.

15.   ADVANCEMENT OF FUNDS:

            15.1 Each Participant shall advance its share of construction costs
      and the operating and maintenance costs prior to the date when funds are
      required by the Project Managers or Operating Agents to pay such costs so
      that the Project Managers and Operating Agents in their capacity as such
      will not have to advance any funds on behalf of another Participant.

            15.2 The Participants shall pay in advance all construction costs in
      accordance with cost estimates and payment schedules to be established by
      the Project Managers. The first such cost estimate and payment schedule
      shall be established not less than sixty (60) days following the execution
      of this agreement and shall be updated monthly thereafter. At least once
      each month following the initial payment of construction costs, as called
      for by such cost estimates and payment schedules, the Project Managers
      shall notify each Participant of the estimated weekly expenditures for the
      succeeding month, and each Participant shall pay to the Project Managers
      once each week its share of such estimate. Following completion of
      construction, each Project Manager shall compute the total costs of
      construction of its designated component of the Navajo Project and each
      Participant shall promptly settle any

                                      -27-


      balance of its indebtedness in accordance therewith. If at any time it is
      determined that a Participant has made advances which are greater or less
      than its share of the construction costs, the difference shall be paid,
      refunded or credited.

            15.3 Each Participant shall pay its share of operating and
      maintenance costs in accordance with requests for funds submitted by the
      Operating Agents. Funds shall be requested as near to the date such funds
      are required by the Operating Agents as is practical under the
      circumstances, but a Participant shall have not less than three (3)
      business days advance notice prior to the due date for requested funds.

            15.4 The United States shall be given appropriate credit for any
      interest in Federal lands, other than Indian lands, administered by the
      Department of the Interior which are made available for the Navajo
      Project. In instances where Federal laws or regulations prescribe fees or
      charges, or the basis or method for determining such fees or charges, for
      the use of Federal lands which are so administered and made available for
      the Navajo Project, the amount of such fees or charges or the provisions
      of such laws or regulations shall govern the determination of the credit
      to be given to the United States. In the absence of applicable Federal
      laws or regulations, the amount of the credit to be

                                      -28-


      given to the United States shall be as mutually agreed upon by the
      Participants or, failing such agreement, as conclusively determined by the
      Secretary.

16.   TAXES:

            16.1 The Participants shall use their best efforts to have any
      taxing authority imposing any taxes or assessments on the Navajo Project,
      or any interests or rights therein, assess and levy such taxes or
      assessments directly against the ownership or beneficial interest of each
      Participant.

            16.2 All taxes or assessments levied against each Participant's
      ownership or beneficial interest in the Navajo Project, excepting those
      taxes or assessments levied against an individual Participant in behalf of
      any or all of the other Participants, shall be the sole responsibility of
      the Participant upon whose ownership or beneficial interest said taxes or
      assessments are levied.

            16.3 If any property taxes or any other taxes or assessments are
      levied or assessed in a manner other than as specified in Section 16.1
      hereof, it shall be the responsibility of the coordinating committee to
      establish equitable practices and procedures for the apportionment among
      the Participants of such taxes and assessments and the payment thereof.

                                      -29-


17.   NONPARTITIONMENT:

            17.1 Each Co-Tenant hereto agrees to waive any rights which it may
      have to partition any component of the Navajo Project, whether by
      partitionment in kind or by sale and division of the proceeds, and further
      agrees that it will not resort to any action in law or in equity to
      partition such component, and it waives the benefits of all laws that may
      now or hereafter authorize such partition for a term (i) which shall be
      co-terminus with the co-tenancy agreement for such component, or (ii)
      which shall be for such lesser period as may be required under applicable
      law.

18.   MORTGAGE AND TRANSFER OF INTERESTS:

            18.1 Except as provided in Section 18.6 hereof, each Co-Tenant shall
      have the right at any time and from time to time to mortgage, create or
      provide for a security interest in or convey in trust all or a part of its
      ownership share in the Navajo Project, together with an equal interest in
      the Project Agreements to a trustee or trustees under deeds of trust,
      mortgages or indentures, or to secured parties under a security agreement,
      as security for its present or future bonds or other obligations or
      securities, and to any successors or assigns thereof, without need for the
      prior written consent of any other Participant, and without such
      mortgagee, trustee or secured party assuming or becoming

                                      -30-


      in any respect obligated to perform any of the obligations of the
      Participants.

            18.2 Except as provided in Section 18.6 hereof, any mortgagee,
      trustee or secured party under present or future deeds of trust,
      mortgages, indentures or security agreements of any of the Co-Tenants and
      any successor or assign thereof, and any receiver, referee or trustee in
      bankruptcy or reorganization of any of the Co-Tenants, and any successor
      by action of law or otherwise, and any purchaser, transferee or assignee
      of any thereof may, without need for the prior written consent of the
      other Participants, succeed to and acquire all the rights, titles and
      interests of such Co-Tenant in the Navajo Project and the Project
      Agreements, and may take over possession of or foreclose upon said
      property, rights, titles and interests of such Co-Tenant.

            18.3 Except as provided in Section 18.6 hereof, each Co-Tenant shall
      have the right to transfer or assign all or part of its ownership share in
      the Navajo Project, together with an equal interest in the Project
      Agreements, to any of the following without the need for prior written
      consent of any other Participant:

                 18.3.1 To any entity acquiring all or substantially all of the
                        property of such Co-Tenant; or

                 18.3.2 To any entity merged or consolidated

                                      -31-


                        with such Co-Tenant; or

                 18.3.3 To any entity which is wholly-owned by a Co-Tenant; or

                 18.3.4 To the Salt River Valley Water Users' Association, an
                        Arizona corporation, in the case of a transfer by Salt
                        River Project.

            18.4 Except as otherwise provided in Sections 18.1, 18.2, and 18.6
      hereof, any successor to the rights, titles and interests of a Co-Tenant
      in the Navajo Project, together with an equal interest in the Project
      Agreements, shall assume and agree to fully perform and discharge all of
      the obligations hereunder of such Co-Tenant, and such successor shall
      notify each of the other Participants in writing of such transfer,
      assignment or merger, and shall furnish to each Participant evidence of
      such transfer, assignment or merger.

            18.5 No Participant shall be relieved of any of its obligations
      under the Project Agreements by an assignment under this Section 18
      without the express prior written consent of all of the remaining
      Participants.

            18.6 The rights set forth in Sections 18.1, 18.2 and 18.3 hereof
      shall not apply to such interests of Salt River Project in the Navajo
      Project or in the Project Agreements as are held for the use and benefit
      of the United States, and Salt River Project shall transfer,

                                      -32-


      convey, mortgage, encumber or hypothecate any such interest only upon the
      prior written instruction of the United States.

19.   RIGHT OF FIRST REFUSAL:

            19.1 Except as provided in Section 18 hereof, should any Co-Tenant
      desire to transfer its ownership in the Navajo Project, or any portion
      thereof, to any person, entity or another Co-Tenant, each remaining
      Co-Tenant shall have the right of first refusal to purchase such interest
      on the basis of the greater of the following amounts:

                 19.1.1 The amount of the bona fide written offer from the
                        buyers, or

                 19.1.2 The fair market value.

            19.2 If more than one of the Co-Tenants desire to purchase such
      interest, it shall be transferred in the ratio that the Generation
      Entitlement Share of each Co-Tenant desiring to purchase bears to the
      total Generation Entitlement Shares of such Co-Tenants.

            19.3 The provisions of this Section 1.9 shall not apply to any
      interest held by the Salt River Project for the use and benefit of the
      United States.

20.   DESTRUCTION:

            20.1 If a generating unit of the Navajo Generating Station should be
      destroyed to the extent that the cost of repairs or reconstruction is less
      than 60% of the

                                      -33-


      original cost thereof, the Participants shall, unless otherwise agreed,
      repair or reconstruct such generating unit to substantially the same
      general character or use as the original. The Participants shall share the
      costs of such repairs or reconstruction in proportion to their Generation
      Entitlement Shares in the generating unit so destroyed.

            20.2 If a generating unit of the Navajo Generating Station should be
      destroyed to the extent that the cost of repairs or reconstruction is 60%
      or more of the original cost, the Participants shall, upon agreement,
      restore or reconstruct such unit to substantially the same general
      character or use as the original; provided, however, that should all of
      the Participants not agree to restore or reconstruct such unit, but some
      of the Participants nevertheless desire so to do, then the Participants
      who do not agree to restore or reconstruct shall sell their interests in
      such unit to the remaining Participants at their proportionate interests
      in the salvage value thereof. The Participants agreeing to repair or
      reconstruct such unit shall share the costs of repair or reconstruction in
      the proportion that the Generation Entitlement Share of each bears to the
      total Generation Entitlement Share of such Participants.

            20.3 If any facilities of the Transmission System should be
      destroyed, the Participants shall, unless

                                      -34-


      otherwise agreed, repair or reconstruct such facilities to substantially
      the same general character or use as the original. The Participants shall
      share the costs of such repair or reconstruction in proportion to their
      original cost responsibility for the facilities so destroyed.

21.   INSURANCE:

            21.1 During the construction stage, each Project Manager shall
      procure or cause to be procured and maintain in force policies of
      comprehensive bodily injury and property damage liability insurance; all
      risk builder's risk insurance; contractor's equipment all risk floater
      insurance; employees' dishonesty bonds; automobile liability insurance;
      and workmen's compensation insurance covering employees of such Project
      Manager engaged in the performance of its responsibilities under the
      Project Agreements at the job site, and such other coverage as the
      Participants may agree is desirable.

            21.2 During the operating stage, each Operating Agent shall procure
      or cause to be procured and maintain broad form steam turbine insurance,
      including reasonable expediting expenses; broad form boiler and pressure
      vessel insurance, including reasonable expediting expenses; work men's
      compensation insurance covering employees of the Operating Agent engaged
      in the performance of its responsibilities under the Project Agreements at
      the job site; physical damage insurance; comprehensive bodily

                                      -35-


      injury and property damage liability insurance; employees dishonesty
      bonds; and automobile liability insurance; and such other coverage as the
      Participants may agree is desirable.

            21.3 Each Participant shall be named an insured, individually and
      jointly with the other Participants, on all insurance, and the
      comprehensive bodily injury and property damage liability insurance shall
      carry cross-liability endorsements.

            21.4 Salt River Project shall be the loss payee for all property
      insurance covering such interests in the Navajo Project as it holds for
      the use and benefit of the United States. Any proceeds paid to Salt River
      Project by reason of the destruction or damage of such interests shall be
      held or disposed of by it pursuant to the terms of the Project Agreements.

            21.5 The insurable values, limits, deductibles, retentions and other
      special terms of the Project Insurance shall be agreed upon by the
      Participants prior to the placement of such Project Insurance. Pending
      such agreement, the Project Managers or Operating Agents shall procure
      insurance binders providing such coverage as in their respective judgments
      is necessary. After such agreement, a policy of Project Insurance shall
      not be changed without the prior written consent of all of the
      Participants, except for minor changes and insurance

                                      -36-


      binders procured pursuant to this Section 21.5, as to which notification
      shall be given to the other Participants by the Project Manager or
      Operating Agent responsible for procuring such Project Insurance.

            21.6 Each Participant shall be furnished with either a certified
      copy of each of the policies of the Project Insurance or a certified copy
      of each of the policy forms of Project Insurance, together with a line
      sheet therefor (and any subsequent amendments) naming the insurers and
      underwriters and the extent of their participation.

            21.7 Each Co-Tenant shall have the right, by written notice to the
      party procuring the policy, to name any mortgagee, trustee or secured
      party on all or any of the Project Insurance policies as loss payees or
      additional insureds as their interests may appear.

            21.8 Each of the Project Insurance policies shall be endorsed so as
      to provide that all additional named insureds shall be given the same
      advance notice of cancellation or material change as that required to be
      given to the party having procured the policy.

            21.9 Project Insurance policies shall be primary insurance for all
      purposes and shall be so endorsed. Any insurance carried by a Participant
      individually shall not participate with the Project Insurance as respects
      any loss or claim for which valid and collectible Project Insurance shall
      apply and shall apply solely as respects

                                      -37-


      the individual interest of the Participant carrying such insurance.

            21.10 In the event that any other Co-Tenant's insurance program
      affords equal or better coverage on a more favorable cost basis than that
      available to the Project Manager or Operating Agent responsible for
      procuring such Project Insurance, the Participants may agree by separate
      written agreement that such insurance program may be utilized to afford
      all or part of the Project Insurance coverage required by Sections 21.1 or
      21.2 hereof.

22.   LIABILITY:

            22.1 Except for any damage resulting from Willful Action, and except
      to the extent of any damage covered by valid and collectible Project
      Insurance, liability on the part of any Participant (first Participant),
      or any of its directors, officers or employees, for any damage to any
      Participant (second Participant), whether or not caused by negligence,
      which occurs as the result of performance or non-performance of its
      responsibilities under the Project Agreements may not be collected from
      the Participant (first Participant), or any of its directors, officers or
      employees, by any action in law or equity by the Participant (second
      Participant).

            22.2 In the event any insurer providing Project Insurance refuses to
      pay any judgment obtained by a Participant (second Participant) against
      another

                                      -38-


      Participant (first Participant), or any of its directors, officers or
      employees, on account of liability referred to in Section 22.1 hereof, the
      Participant (first Participant), or any of its directors, officers or
      employees, against whom the judgment is obtained, shall, at the request of
      the prevailing Participant (second Participant) and in consideration for
      the release given in Section 22.1 hereof, execute such documents as may be
      necessary to effect an as assignment of its contractual rights against the
      non-paying insurer and thereby give the prevailing Participant (second
      Participant) the opportunity to enforce its judgment directly against such
      insurer.

            22.3 Except for Station Work Liability resulting from Willful
      Action, and except as provided in Section 22.6 hereof, the costs and
      expenses of discharging all Station Work Liability imposed upon one or
      more of the Participants for which payment is not made by Project
      Insurance shall be allocated among the Participants in proportion to their
      Generation Entitlement Shares.

            22.4 Except for Transmission Work Liability resulting from Willful
      Action, and except as provided in Section 22.6 hereof, the costs and
      expenses of discharging all Transmission Work Liability imposed upon one
      or more of the Participants for which payment is not made by the Project
      Insurance shall be allocated among the Participants in proportion to their
      cost responsibility in the

                                      -39-


      facilities involved in the operative facts which give rise to the
      Transmission Work Liability. However, if the proximate cause of such
      liability cannot be determined or is not related to any particular
      facilities, then such costs and expenses shall be allocated among the
      Participants in proportion to their Generation Entitlement Shares.

            22.5 Each Participant shall be responsible for the consequences of
      its own Willful Action, and shall indemnify and hold harmless the other
      Participants from the consequences thereof.

            22.6 Except for liability resulting from Willful Action, any
      Participant whose electric customer shall make a claim or bring an action
      for any death, injury, loss or damage arising out of electric service to
      such customer, shall indemnify and hold harmless all other Participants,
      their directors, officers and employees, from and against any liability
      for such death, injury, loss or damage. The term "electric customer" shall
      mean an electric consumer to whom no Power is delivered for resale.

            22.7 The provisions of this Section 22 shall not be construed so as
      to relieve any insurer of its obligation to pay any insurance proceeds in
      accordance with the terms and conditions of valid and collectible Project
      Insurance policies.

            22.8 The terms "Participant" and "Participants",

                                      -40-


      as used in this Section 22, shall include any Project Manager or Operating
      Agent, in its capacity as such.

23.   INTERESTS HELD FOR THE USE AND BENEFIT OF UNITED STATES:

            23.1 Salt River Project shall acquire and hold the interests
      acquired for the use and benefit of the United States so that the United
      States will realize the full use and benefit of its entitlement as
      provided for in the Project Agreements.

            23.2 Salt River Project shall not execute any Project Agreement or
      any other agreement which purports to apply to the rights, titles or
      interests held for the use and benefit of the United States to which the
      United States is not a contracting party in its capacity as a Participant
      without the prior written consent of the United States. Except as
      otherwise provided in the Project Agreements, Salt River Project shall not
      exercise any rights, privileges or options in any such agreement for or on
      behalf of the United States without the prior written consent of the
      United States. With respect to any Project Agreement to which the United
      States is not a contracting party, except as otherwise provided in the
      Project Agreements, the United States shall have a right, co-equal with
      the rights of the Participants who are contracting parties to such Project
      Agreement, to participate in any decision or action taken under such
      Project Agreement which in any manner applies to or affects a right,

                                      -41-


      title or interest held by Salt River Project for the use and benefit of
      the United States, to the same extent and to the same effect as though the
      United States were a contracting party to such Project Agreement.

            23.3 Although it is the intention of the Participants that no
      Co-Tenant should incur any additional liability or burden by reason of the
      generating and transmission Capacity dedicated for the use and benefit of
      the United States,should any such liability or burden be imposed upon
      Salt River Project solely by reason of its holding legal title to any
      property or holding an interest in the Project Agreements for the use and
      benefit of the United States such liability or burden shall be shared by
      the Co-Tenants and allocated among them in the ratio that each Co-Tenant's
      Generation Entitlement Share bears to the total Generation Entitlement
      Shares of the Co-Tenants.

            23.4 All moneys paid to Salt River Project pursuant to the Project
      Agreements which are for the use and benefit of the United States shall
      be segregated from its general funds and, upon written request of the
      Contracting Officer, such funds will be invested by Salt River Project in
      the manner specified in such request. All interest earned and appreciation
      in value on such investments shall inure to the benefit of the United
      States and all losses on such investments shall be at the risk of the
      United States. If the proceeds exceed the amount

                                      -42-


      of the obligation for which they are designated or held, then, upon
      written request of the United States, Salt River Project shall pay such
      excess to the United States or its designee.

24.   REIMBURSEMENT FOR COSTS AND EXPENSES:

            24.1 The United States shall reimburse Salt River Project for all
      costs and expenses not otherwise specifically provided for in the Project
      Agreements but which are imposed upon, measured by and associated with the
      interests held by Salt River Project for the use and benefit of the United
      States.

25.   DEFAULTS:

            25.1 Unless otherwise provided in the Project Agreements, in the
      event of a default by any Participant under any of the Project Agreements:

                  25.1.1 The non-defaulting Participants, following receipt of
                         reasonable notice, shall remedy the default, with the
                         costs thereof allocated among and paid by each of the
                         non-defaulting Participants in the ratio that their
                         Generation Entitlement Shares bear to the total
                         Generation Entitlement Shares of all non-defaulting
                         Participants.

                                      -43-


                  25.1.2 The defaulting Participant shall remedy such default as
                         soon as possible and shall pay upon demand to each non-
                         defaulting Participant any amount paid by such
                         non-defaulting Participant for the account of the
                         defaulting Participant plus interest thereon at the
                         rate of ten per cent (10%) per annum or the legal
                         maximum rate of interest, whichever is the lesser, from
                         the date of expenditure by the non-defaulting
                         Participant.

                  25.1.3 If such default by a Co-Tenant shall continue for a
                         period of six (6) months or more without having been
                         remedied by the defaulting Co-Tenant, following a
                         determination as a result of arbitration or judicial
                         proceeding that an act of default exists, the matter
                         may be re-submitted to arbitration as permitted by law,
                         with a request that the arbitrators determine what
                         additional remedies may be reasonably necessary or
                         required under the circumstances.

                  25.1.4 The United States shall not be liable

                                      -44-


                        for any interest charges or attorneys' fees.

            25.2 Any Participant may dispute an asserted default by it, provided
      that such Participant shall pay the disputed payment or perform the
      disputed obligation under written protest. Payments made without protest
      shall be deemed to be correct, except to the extent that audits may reveal
      the necessity for adjustments.

26    ARBITRATION:

            26.1 If a dispute between any of the Participants should arise under
      the Project Agreements which does not involve the legal rights of or which
      will not create a legal obligation upon the United States under the
      Project Agreements, or will not affect the interests or rights held for
      the use and benefit of the United States under the Project Agreements, any
      Participant may call for submission of the dispute to arbitration, which
      call shall be binding upon all of the other Participants. Except as
      specifically provided in the Project Agreements, the arbitration shall be
      governed by the rules and practices of the American Arbitration
      Association. The award of the arbitrators shall be final and binding upon
      the Participants, and the costs and expenses of the arbitrators shall be
      shared equally by the Participants participating in the arbitration,
      unless otherwise decided by the arbitrators.

                                      -45-

            26.2 If a dispute arises between any of the Participants which does
      or may involve the legal rights of or which will or may create a legal
      obligation upon the United States under the Project Agreements, or which
      affects or may affect the interests or rights held for the use and benefit
      of the United States under the Project Agreements, then any Participant
      may call for submission to arbitration of any part of the dispute, issue
      or action related thereto which the United States may lawfully submit to
      arbitration. If the Contracting Officer agrees to such arbitration, or if
      the Contracting Officer refuses or fails to arbitrate and a court of
      competent jurisdiction thereafter finally decides that the United States
      may lawfully submit the matter in dispute to arbitration, it shall be
      conducted in the manner set forth in Section 26.1 hereof, or in such
      other manner as may be provided for by Federal law.

27.   ACTIONS PENDING RESOLUTION OF DISPUTES:

            27.1 If a dispute should arise which is not resolved by the
      coordinating committee, then, pending the resolution of the dispute by
      arbitration or judicial proceedings, the Project Managers or Operating
      Agents shall proceed with the Station Work or Transmission Work in a
      manner consistent with the Project Agreements and generally accepted
      practice in the electric utility industry, and the Participants shall
      advance the funds required to

                                      -46-


      perform such Station Work or Transmission Work in accordance with the
      applicable provisions of the Project Agreements. The resolution of any
      dispute involving the failure of one of the committees to reach agreement
      upon matters involving future expenditures shall have prospective
      application from the date of final determination, and amounts advanced by
      the Participants pursuant to this Section 27.1 during the pendency of such
      dispute shall not be subject to refund except upon a final determination
      that the expenditures were not made in a manner consistent with generally
      accepted practice in the electric utility industry.

28.   REMOVAL OF OPERATING AGENTS:

            28.1 If an Operating Agent shall fail to remedy any material act of
      default within a reasonable time following a final determination by a
      panel or arbitrators or judicial proceeding that the Operating Agent is in
      default, then any Participant may cause the Operating Agent to be removed
      by serving written notice of removal upon such Operating Agent and upon
      all of the other Participants.

29.   RELATIONSHIP OF PARTICIPANTS:

            29.1 The covenants, obligations and liabilities of the Participants
      are intended to be several and not joint or collective and, except as
      expressly provided in the Project Agreements, nothing herein contained
      shall ever

                                      -47-


      be construed to create an association, joint venture, trust or
      partnership, or to impose a trust or partnership covenant, obligation or
      liability on or with regard to any one or more of the Participants. Each
      Participant shall be individually responsible for its own covenants,
      obligations and liabilities as herein provided. No Participant or group of
      Participants shall be under the control of or shall be deemed to control
      any other Participant or the Participants as a group. No Participant shall
      be the agent of or have a right or power to bind any other Participant
      without its express written consent, except as provided in the Project
      Agreements.

            29.2 The Co-Tenants hereby elect to be excluded from the application
      of Subchapter "K" of Chapter 1 of Subtitle "A" of the Internal Revenue
      Code of 1954, or such portion or portions thereof as may be permitted or
      authorized by the Secretary of the Treasury or his delegate insofar as
      such Subchapter, or any portion or portions thereof, may be applicable to
      the Co-Tenants under the Project Agreements.

30.   FEES:

            30.1 No Project Manager or Operating Agent shall receive any fee or
      profit hereunder.

31.   OFFICIALS NOT TO BENEFIT:

            31.1 No Member of or Delegate to Congress or Resident Commissioner
      shall be admitted to any share or part of

                                      -48-


      this agreement or to any benefit that may arise herefrom, but this
      restriction shall not be construed to extend to this agreement if made
      with a corporation or company for its general benefit.

32.   COVENANT AGAINST CONTINGENT FEES:

            32.1 The Co-Tenants warrant that no person or selling agency has
      been employed or retained to solicit or secure this agreement upon an
      agreement or understanding for a commission, percentage, brokerage or
      contingent fee, excepting bona fide employees or bona fide established
      commercial or selling agencies maintained by a Co-Tenant for the purpose
      of securing business. For breach or violation of this warranty the United
      States shall have the right to annul this agreement without liability or
      in its discretion to deduct from the payments to be made hereunder, or
      otherwise recover the full amount of such commission, percentage,
      brokerage or contingent fee.

33.   EQUAL OPPORTUNITY:

            33.1 Except as provided in Title.42 U.S.C. Section 2000-e-2(i) and
      in keeping with any obligation undertaken by any of the Co-Tenants, in
      this section referred to as the Contractor, or their assigns, pursuant to
      the terms of said Title 42 U.S.C. Section 2000-e-2(i) to give preference
      for employment to qualified Indians for work on or near an Indian
      Reservation, during the performance of this

                                      -49-


      agreement, the Contractor agrees as follows:

                  33.1.1 The Contractor will not discriminate against any
                         employee or applicant for employment because of race,
                         color, religion, sex or national origin. The Contractor
                         will take affirmative action to insure that applicants
                         are employed, and that employees are treated during
                         employment without regard to their race, color,
                         religion, sex or national origin. Such action shall
                         include, but not be limited to the following:
                         Employment, upgrading, demotion or transfer;
                         recruitment or recruitment advertising; layoff or
                         termination; rates of pay or other forms of
                         compensation; and selection for training, including
                         apprenticeship. The Contractor agrees to post in
                         conspicuous places available to employees and
                         applicants for employment, notices to be provided by
                         the Contracting Officer setting forth the provisions of
                         this equal

                                      -50-


                         opportunity clause.

                  33.1.2 The Contractor will, in all solicitations or
                         advertisements for employees placed by or on behalf of
                         the Contractor, state that all qualified applicants
                         will receive consideration for employment without
                         regard to race, color, religion, sex or national
                         origin.

                  33.1.3 The Contractor will send to each labor union or
                         representative of workers with which it has a
                         collective bargaining agreement or other contract or
                         understanding, a notice to be provided by the agency
                         Contracting Officer advising the labor union or
                         workers' representative of the Contractor's commitments
                         under this equal opportunity clause, and shall post
                         copies of the notice in conspicuous places available to
                         employees and applicants for employment.

                  33.1.4 The Contractor will comply with all provisions of
                         Executive Order No. 11246 of September 24, 1965, and of
                         the rules, regulations and

                                      -51-


                         relevant orders of the Secretary of Labor.

                  33.1.5 The Contractor will furnish all information and reports
                         required by Executive Order No. 11246 of September 24,
                         1965, and by the rules, regulations and orders of the
                         Secretary of Labor, or pursuant thereto, and will
                         permit access to its book, records and accounts by the
                         contracting agency and the Secretary of Labor for
                         purposes of investigation to ascertain compliance with
                         such rules, regulations and orders.

                  33.1.6 In the event of the Contractor's non-compliance with
                         this equal opportunity clause, or with any of the said
                         rules, regulations or orders, this agreement may be
                         cancelled, terminated or suspended in whole or in part,
                         and the Contractor may be declared ineligible for
                         further government contracts in accordance with
                         procedures authorized in Executive Order

                                      -52-



                         No. 11246 of September 24, 1965, and such other
                         sanctions may be imposed and remedies invoked as
                         provided in Executive Order No. 11246 of September 24,
                         1965, or by rule, regulation or order of the Secretary
                         of Labor, or as otherwise provided by law.

                  33.1.7 The Contractor will include the provisions Of Sections
                         33.1.1 through 33.1.7 hereof in every subcontract or
                         purchase order unless exempted by rules, regulations or
                         orders of the Secretary of Labor issued pursuant to
                         Section 204 of Executive Order No. 11246 of September
                         24, 1965, so that such provisions will be binding upon
                         each subcontractor or vendor. The Contractor will take
                         such action with respect to any subcontract or purchase
                         order as the contracting agency may direct as a means
                         of enforcing such provisions, including sanctions for
                         non-compliance; provided, however, that, in the event
                         the Contractor becomes involved in,

                                      -53-


                        or is threatened with, litigation with a subcontractor
                        or vendor as a result of such direction by the
                        contracting agency, the Contractor may request the
                        United States to enter into such litigation to protect
                        the interests of the United States.

34.   WORK HOURS ACT OF 1962:

            34.1 This agreement, to the extent that it is of a character.
      specified in the Contract Work Hours Standards Act (Public Law 87-581,
      76 Stat. 357) and is not covered by the Walsh-Healey Public Contracts Act
      (41 U.S.C. Sections 35-45), is subject to the following provisions and to
      all other provisions and exceptions of said Contract Work Hours Standards
      Act:

                  34.1.1 No Contractor or subcontractor contracting for any
                         part of the contract work which may require or involve
                         the employment of laborers or mechanics shall require
                         or permit any laborer or mechanic in any workweek in
                         which he is employed on such work, to work in excess of
                         eight (8) hours in any calendar day or in excess of
                         forty (40) hours in any workweek unless such laborer or
                         mechanic receives compensation at a

                                      -54-


                        rate not less than one and one-half times his basic rate
                        of pay for all hours worked in excess of eight (8) hours
                        in any calendar day or in excess of forty (40) hours in
                        such workweek, whichever is the greater number of
                        overtime hours.

                  34.1.2 In the event of any violation of the provisions of
                         Section 34.1.1 hereof, the Contractor and any
                         subcontractor responsible for such violation shall be
                         liable to any affected employee for his unpaid wages.
                         In addition, such Contractor or subcontractor shall be
                         liable to the United States for liquidated damages.
                         Such liquidated damages shall be computed, with respect
                         to each individual laborer or mechanic employed in
                         violation of the provisions of Section 34.1.1 hereof,
                         in the sum of Ten Dollars ($10.00) for each calendar
                         day on which such employee was required or permitted to
                         work in excess of eight (8) hours or in excess of forty
                         (40) hours in a workweek without payment of the
                         required overtime wages.

                                      -55-


                  34.1.3 The Secretary may withhold, or cause to be withheld,
                         from any monies payable on account of work performed by
                         the Contractor or subcontractor, the full amount of
                         wages required by this agreement, and such sums as may
                         administratively be determined to be necessary to
                         satisfy any liabilities of such Contractor or
                         subcontractor for liquidated damages as provided in
                         Section 34.1.2 hereof.

                  34.1.4 The Contractor shall require the foregoing Sections
                         34.1.1, 34.1.2, 34.1.3 and this Section 34.1.4 to be
                         inserted in all subcontracts.

35.   EXAMINATION OF RECORDS:

            35.1 The Co-Tenants agree that the Comptroller General of the United
      States, or any of his duly authorized representatives, shall, until the
      expiration of three (3) years after final payment under the Project
      Agreements, have access to and the right to examine any directly pertinent
      books, documents, papers and records of the Co-Tenants involving
      transactions related to this agreement.

36.   ASSIGNMENT OF CLAIMS:

            36.1 Pursuant to the provisions of the Assignment

                                      -56-


      of Claims Act of 1940, as amended (31 U.S.C. Section 203, 41 U.S.C.
      Section 15), if this agreement provides for payments aggregating $1,000 or
      more, claims for monies due or to become due any Co-Tenant from the
      Government under this agreement may be assigned to a bank, trust company,
      or other financing institution, including any Federal lending agency, and
      may thereafter be further assigned and reassigned to any such institution.
      Any such assignment or reassignment shall cover all amounts payable under
      this agreement and not already paid, and shall not be made to more than
      one party, except that any such assignment or reassignment may be made to
      one party as agent or trustee for two or more parties participating in
      such financing. Unless otherwise provided in this agreement, payments to
      an assignee of any monies due or to become due under this agreement shall
      not, to the extent provided in said Act, as amended, be subject to
      reduction or setoff. (The preceding sentence applies only if this
      agreement is made in time of war or national emergency as defined in said
      Act and is with the Department of Defense, the General Services
      Administration, the Atomic Energy Commission, the National Aeronautics and
      Space Administration, the Federal Aviation Agency, or any other department
      or agency of the United States designated by the President pursuant to
      Clause 4 of the proviso of Section 1 of the Assignment of Claims Act of
      1940, as amended by the Act

                                      -57-


      of May 15, 1951, 65 Stat. 41.)

            36.2 In no event shall copies of this agreement or of any plans,
      specifications, or other similar documents relating to work under this
      agreement, if marked "Top Secret", "Secret", or "Confidential", be
      furnished to any assignee of any claim arising under this agreement or to
      any other person not entitled to receive the same. However, a copy of any
      part or all of this agreement so marked may be furnished, or any
      information contained therein may be disclosed, to such assignee upon the
      prior written authorization of the Contracting Officer.

37.   CONVICT LABOR:

            37.1 In connection with the performance of work under this
      agreement, the Contractor agrees not to employ any person undergoing
      sentence or imprisonment at hard labor.

38.   UNCONTROLLABLE FORCES:

            38.1 No Participant shall be considered to be in default in the
      performance of any of its obligations under the Project Agreements (other
      than obligations of said Participant to pay costs and expenses) when a
      failure of performance shall be due to uncontrollable forces. The term
      "uncontrollable forces" shall be any cause beyond the control of the
      Participant affected, including but not restricted to failure of or threat
      of failure of facilities, flood, earthquake, storm, fire, lightning,

                                      -58-


      epidemic, war, riot, civil disturbance or disobedience, labor dispute,
      labor or material shortage, sabotage, restraint by court order or public
      authority, and action or non-action by or failure to obtain the necessary
      authorizations or approvals from any governmental agency or authority,
      which by exercise of due diligence such Participant could not reasonably
      have been expected to avoid and which by exercise of due diligence it
      shall be unable to overcome. Nothing contained herein shall be construed
      so as to require a Participant to settle any strike or labor dispute in
      which it may be involved. Any Participant rendered unable to fulfill any
      of its obligations under the Project Agreements by reason of
      uncontrollable forces shall exercise due diligence to remove such
      inability with all reasonable dispatch. The term "Participant" as used in
      this Section 38.1 shall include any Project Manager or Operating Agent, in
      its capacity as such.

39.   GOVERNING LAW:

            39.1 To the extent permitted by law, this agreement shall be
      governed by the laws of the State of Arizona, except insofar as
      controversies involving the rights of the United States are concerned.

40.   BINDING OBLIGATIONS:

            40.1 All of the obligations set forth in the Project Agreements
      shall bind the Participants and their

                                      -59-


      successors and assigns, and such obligations shall run with the
      Co-Tenants' rights, titles and interests in the Navajo Project and with
      all of the interests of each Participant in the Project Agreements;
      provided that any mortgagee, trustee or secured party shall not be finally
      obligated for obligations arising prior to taking of possession or the
      initiation of remedial proceedings.

41.   NONDEDICATION OF FACILITIES:

            41.1 The Project Agreements shall not be construed to grant to any
      Co-Tenant any rights of ownership in, possession of or control over the
      electric system of the United States.

            41.2 The Project Agreements shall not be construed to grant to the
      United States any rights of ownership in, possession of, or control over
      the electric system of any Co-Tenant.

            41.3 The Co-Tenants do not intend to dedicate and nothing in the
      Project Agreements shall be construed as constituting a dedication by any
      Co-Tenant of its properties or facilities, or any part thereof, to the
      United States or to any other Co-Tenant or to the customers of the
      United States or to the customers of any other Co-Tenant.

42.   PROJECT AGREEMENTS:

            42.1 The Participants hereto agree to negotiate in good faith and to
      proceed with diligence to obtain all

                                      -60-


      of the Project Agreements among the Participants and between the
      Participants and other entities.

            42.2 It is acknowledged by the Participants that one or more of the
      Project Agreements may contain provisions which are in conflict with or
      contrary to the terms of this agreement, and any such provision in a
      Project Agreement executed subsequent to the execution of this agreement
      shall be deemed to supersede, amend or modify any conflicting or contrary
      provision herein. The mutual agreement of the Participants to supersede,
      amend or modify the terms hereof shall constitute the legal consideration
      to support such change in the legal rights and obligations of the
      Participants.

43.   TERM:

            43.1 This agreement shall become effective when it has been duly
      executed and delivered on behalf of all of the Participants and shall be
      effective during the interim between the date of execution thereof and the
      effective date of the last of the Project Agreements; provided if any of
      the Project Agreements shall fail to become effective, then this
      agreement shall have a term of fifty (50) years from its effective date.

44.   ASSIGNMENT OF INTERESTS:

            44.1 Any Co-Tenant who acquires in its name an interest in any real
      or personal property or contract which is part of the Navajo Project shall
      transfer and assign an

                                      -61-


      undivided interest therein to the other Co-Tenants so that the ownership
      and rights of the Co-Tenants in such property or contract shall be as
      provided for in the Project Agreements.

            45. NOTICES:

            45.1 Any notice, demand or request provided for in the Project
      Agreements shall be deemed properly served, given or made if delivered in
      person or sent by registered or certified mail, postage prepaid, to the
      persons specified below:

                  45.1.1      United States of America
                              c/o The Secretary of the Interior
                              United States Department of the Interior
                              Washington, D. C.  20240

                  45.1.2      Arizona Public Service Company
                              c/o Secretary
                              P. O. Box 21666
                              Phoenix, Arizona  85036

                  45.1.3      Department of Water and Power of the City of
                                Los Angeles
                              c/o General Manager
                              P. O. Box 111
                              Los Angeles, California  90054

                  45.1.4      Nevada Power Company
                              c/o President
                              P. O. Box 230
                              Las Vegas, Nevada  89109

                  45.1.5      Salt River Project Agricultural
                                Improvement and Power District
                              c/o Secretary
                              P. O. Box 1980
                              Phoenix, Arizona  85001

                  45.1.6      Tucson Gas & Electric Company
                              c/o Secretary
                              P. O. Box 711
                              Tucson, Arizona  85702

                                      -62-


            45.2 Any Participant may, at any time, by written notice to all
      other Participants, designate different or additional persons or different
      addresses for the giving of notices hereunder.

            45.3 Any Project Manager or Operating Agent shall provide to each
      Participant a copy of any notice, demand or request given or received by
      it in connection with any of the Project Agreements.

46.   MISCELLANEOUS PROVISIONS:

            46.1 Each Participant agrees, upon request by the other
      Participants, to make, execute and deliver any and all documents
      reasonably required to implement the Project Agreements,

            46.2 The captions and headings appearing in the Project Agreements
      are inserted merely to facilitate reference and shall have no bearing upon
      the interpretation thereof.

            46.3 Each term, covenant and condition of the Project Agreements is
      deemed to be an independent term, covenant and condition, and the
      obligation of any Participant to perform all of the terms, covenants and
      conditions to be kept and performed by it is not dependent on the
      performance by the other Participants of any or all of the terms,
      covenants and conditions to be kept and performed by them.

            46.4 In the event that any of the terms, covenants or conditions of
      any of the Project Agreements, or the

                                      -63-


      application of any such term, covenant or condition, shall be held invalid
      as to any person or circumstance by any court having jurisdiction in the
      premises, the remainder of such Project Agreement, and the application of
      its terms, covenants or conditions to such persons or circumstances shall
      not be affected thereby.

            46.5 The Project Agreements shall be subject to filing with, and to
      such changes or modifications as may from time to time be directed by,
      competent regulatory authority, if any, in the exercise of its
      jurisdiction.

            46.6 The Co-Tenants shall install and diligently operate in the
      Navajo Generating Station equipment offering the most effective
      commercially proven electrostatic concept, or other equally effective and
      acceptable equipment available under the technology known at the time of
      design, having a design efficiency for removal of particulate matter of
      99.5% to minimize smoke, flyash and dust in stack emissions; provided
      that, except as amended in this Section 46.6, the provisions of Article 16
      of the Water Service Contract dated January 17, 1969 (Contract No.
      14-06-400-5033) shall remain in full force and effect.

            46.7 Any waiver at any time by any Participant of its rights with
      respect to a default or any other matter arising in connection with this
      agreement shall not be deemed a waiver with respect to any subsequent
      default or matter.

                                      -64-


47.   USE OF FACILITIES OF LOS ANGELES:

            47.1 The United States may use, for such period or periods of time
      as it desires, the 500 KV transmission line of Los Angeles between
      McCullough Substation and Eldorado Substation and associated terminal
      facilities to the extent of the right of Los Angeles to use such terminal
      facilities. Unless otherwise agreed, the United States' right to use the
      facilities of Los Angeles shall not exceed 250 megawatts. Payment shall be
      made annually by the United States to Los Angeles for any period of such
      use at the rate of eight percent (8%) per annum of the capital cost of Los
      Angeles in such line and in switching facilities at Eldorado and
      McCullough Substations installed to terminate the line, as described in
      Exhibit C, times the ratio that the Capacity desired by the United States
      in megawatts in such line bears to 1,000 megawatts.

            47.2 The land presently held by Los Angeles under Bureau of Land
      Management Grant No. N-2763, dated January 23, 1969, which land comprises
      the site of McCullough Substation, may be utilized by Nevada and United
      States without charge for such use other than as provided in Section 47.3.
      If and when Los Angeles acquires fee title to such land, Nevada and United
      States shall each continue to have the right to use such land, and for any
      period of such use the user shall pay

                                      -65-

      Los Angeles annually at the rate of six percent (6%) of the investment of
      Los Angeles in such land times the user's Common Facilities cost
      responsibility percentage in McCullough Substation as provided for in
      Exhibit C.

            47.3 During any period of use of land by Nevada or United States
      pursuant to Section 47.2, the user shall reimburse Los Angeles for all
      costs and expenses not otherwise specifically provided for in the Project
      Agreements but which are imposed upon Los Angeles by virtue of its holding
      interests in or owning the land comprising the site for the McCullough
      Substation in the amount determined by multiplying such costs and expenses
      by the user's Common Facilities cost responsibility percentage in
      McCullough Substation as provided in Exhibit C.

48.   AGREEMENT SUBJECT TO COLORADO RIVER COMPACT:

            48.1 This agreement is made upon the express condition and with the
      express understanding that all rights hereunder shall be subject to and
      controlled by the Colorado River Compact, being the compact or agreement
      signed at Santa Fe, New Mexico, November 24, 1922, pursuant to Act of
      Congress approved August 19, 1921, entitled "An Act to permit a compact or
      agreement between the States of Arizona, California, Colorado, Nevada, New
      Mexico, Utah and Wyoming respecting the disposition and apportionment of
      the waters of the Colorado River, and for other purposes", which Compact
      was approved in

                                      -66-



      Section 13 (a) of the Boulder Canyon Project Act.

            IN WITNESS WHEREOF, the parties hereto have caused this
      Participation Agreement to be executed as of the 30th day of
      September, 1969.

                                     THE UNITED STATES OF AMERICA

                                     By /s/ Walter J. Hickel
                                        --------------------------
                                        Secretary of the Interior

                                     ARIZONA PUBLIC SERVICE COMPANY

ATTEST:                              By /s/ M. C. Titus
/s/ Gerald Griffin                      -------------------------
- ---------------                         Executive VICE PRESIDENT
Assistant Secretary
                                     DEPARTMENT OF WATER AND POWER
                                     OF THE CITY OF LOS ANGELES

                                                    by

                                     BOARD OF WATER AND POWER COMMISSIONERS
                                     OF THE CITY OF LOS ANGELES

ATTEST:

/s/ Mary J. Born                     By    /s/ Frank R. Palmieri
- ---------------                            ---------------------
SECRETARY                                   PRESIDENT


                                     NEVADA POWER COMPANY

ATTEST:

/s/ Authorized Signatory             By  /s/ Harry Allen
- ---------------                          ----------------
Secretary                                President


[STAMP]                                               [STAMP]

                                      -67-



                                     SALT RIVER PROJECT AGRICULTURAL
                                     IMPROVEMENT AND POWER DISTRICT

ATTEST:

/s/ F. E. Smith                      By /s/ V. I. Corbell
- ---------------                         ------------------
Secretary                               President

                                     TUCSON GAS & ELECTRIC COMPANY

ATTEST:
                                     By /s/ H. R. Catlin
/s/ W. D. Brooks                        ------------------
- ----------------                        VICE PRESIDENT
ASSISTANT SECRETARY

                                      -68-



District of Columbia   )
                       ) ss.
City of Washington     )

      On this the 3rd day of November, 1970, before me, the undersigned officer,
personally appeared Walter J. Hickel, Secretary of the Interior of the United
States of America, known to me to be the person described in the foregoing
Navajo Project Participation Agreement (Contract No. 14-06-300-2131), and
acknowledged that he executed the same in the capacity therein stated and for
the purposes therein contained.

      In witness whereof I hereunto set my hand and official seal.

                                     /s/ Kathy A. Willing
[SEAL]                               -------------------------------------
                                     My Commission Expires May 14, 1974

State of Arizona     )
                     ) ss.
County of Maricopa   )

      On this the 16th day of March, 1970, before me, the undersigned officer,
personally appeared M. C. Titus, who acknowledged himself to be the Executive
Vice President of ARIZONA PUBLIC SERVICE COMPANY, an Arizona corporation, and
that he, as such Executive Vice President, being authorized so

                                      -69-



to do, executed the foregoing Navajo Project Participation Agreement (Contract
No. 14-06-300-2131) for the purposes therein contained, by signing the name of
the corporation by himself as such Executive Vice President.

        In witness whereof I hereunto set my hand and official

[SEAL]                               /s/ Authorized Signatory
                                     ------------------------
                                     Notary Public

My commission expires:

My Commission Expires Oct. 15, 1971
- -----------------------------------

State of California    )
                       )  ss.
County of Los Angeles  )                See Page 74



      On this, the _______________ day of_____________________________, 1970,
before me the undersigned officer, personally appeared Frank R. Palmieri, the
President of the Board of Water and Power Commissioners of the DEPARTMENT OF
WATER AND POWER OF THE CITY OF LOS ANGELES, a department organized and existing
under the Charter of the City of Los Angeles, a municipal corporation of the
State of California, known to me to be the person described in the foregoing
Navajo Project Participation Agreement (Contract No. 14-06-300-2131), and
acknowledged that he executed the same in the capacity therein stated and for
the purposes therein contained.

                                      -70-



      In witness whereof I hereunto set my hand and official seal.

                                                            ____________________
                                                              Notary Public
My commission expires:

________________________

State of Nevada       )
                      ) ss.
County of Clark       )

      On this the 12th day of June, 1970, before me, the undersigned officer,
personally appeared Harry Allen, known to me to be the President of NEVADA POWER
COMPANY, a Nevada corporation, and that he, as such President, being authorized
so to do, executed the foregoing Navajo Project Participation Agreement
(Contract No. 14-06-300-2131) for the purposes therein contained, by signing the
name of the corporation by himself as President.

      In witness whereof, I hereunto set my hand and official seal.

                                                         /s/  Myrtice L. Carroll
                                                         -----------------------
                                                               Notary Public
My commission expires:

_____________________

[STAMP]

                                      -71-



State of Arizona    )
                    ) ss.
County of Maricopa  )

      On this the 16th day of March, 1970, before me, the undersigned officer,
personally appeared V. I. Corbell and F. E. Smith, the President and Secretary,
respectively, of SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT,
an Arizona agricultural improvement district, known to me to be the persons
described in the foregoing Navajo Project Participation Agreement (Contract No.
14-06-300-2131), and acknowledged that they executed the same in the capacity
therein stated and for the purposes therein contained.

      In witness whereof I hereunto set my hand and official seal.

                                                 /s/ Joanne Claridge
                                                --------------------     [SEAL]
                                                   Notary Public

My commission expires:

My Commission Expires July 11, 1972
- -----------------------------------

State of Arizona       )
                       ) ss.
County of Pima         )

      On this the 11th day of June, 1970, before me, the undersigned officer,
personally appeared H. R. Catlin, who acknowledged himself to be the Vice
President of TUCSON GAS & ELECTRIC COMPANY, an Arizona corporation, and that he,

                                      -72-



as such Vice President, being authorized so to do, executed the foregoing Navajo
Project Participation Agreement (Contract No. 14-06-300-2131) for the purposes
therein contained, by signing the name of the corporation by himself as Vice
President.

      In witness whereof I hereunto set my hand and official seal.

                                                              /s/ Diana Howland
                                                            --------------------
                                                               Notary Public

       My commission expires:
[SEAL]
       My.Commission Expires Dec. 8, 1972
       -----------------------------------

                                      -73-



State of California     )
                        ) ss.
County of Los Angeles   )

      On this, the 1st day of October, 1970, before me, the undersigned officer,
personally appeared Frank R. Palmieri and Mary J. Born, who were on November 20,
1969, the President and Secretary, respectively, of the Board of Water and Power
Commissioners of the DEPARTMENT OF WATER AND POWER OF THE CITY OF LOS ANGELES, a
department organized and existing under the Charter of The City of Los Angeles,
a municipal corporation of the State of California, known to me to be the
persons described in the foregoing Navajo Project Participation Agreement
(Contract No. 14-06-300-2131; DWP No. 10334), and acknowledged that they
executed the same on November 20, 1969, in the capacity therein stated and for
the purposes therein contained.

      In witness whereof I hereunto set my hand and official seal.

                                                            /s/ Linda L. Newman
                                                            --------------------
                                                             Notary Public

My commission expires:
                                                                 [STAMP]
______________________

                                      -74-



                                    EXHIBIT A

                          DESCRIPTION OF NAVAJO PROJECT

Exhibit A-l - Description of Navajo Generating Station


      The Navajo Generating Station shall consist of the following:

            I. Three steam electric generating units (Unit 1, Unit 2 and Unit
3), which shall have a nameplate rating of 750,000 KW and shall be
tandem-compound, four flow, single reheat, turbine-generator units with initial
steam conditions of 3500 psig and 1000 F. and reheat to 1000 F. and designed to
take steam from three pulverized coal-fired super-critical steam generator
units.

            II. All auxiliary equipment associated with said units.

            III. An administration building machine shop and warehouse to be
located adjacent to the powerplant.

            IV. A pumping station and all associated equipment to be located on
the Colorado River.

            V. 500 KV step-up transformers and all equipment associated
therewith up to the point where the leads from the said transformers terminate
at the dead-end structure in the Navajo 500 KV Switchyard.

            VI. Standby auxiliary power transformation equipment and related
facilities.



            VII. Plant control and communication facilities and associated
buildings or equipment.

Exhibit A-2 - Description of Transmission System

      The Transmission System shall consist of the following:

            I. Navajo 500 KV Switchyard

               A. The Navajo 500 KV Switchyard shall be a basic
breaker-and-a-half scheme providing termination for facilities as presently
planned:

                  1.    Navajo Generating Unit #1.

                  2.    Navajo Generating Unit #2.

                  3.    Navajo Generating Unit #3.

                  4.    Navajo-McCullough 500 KV Line.

                  5.    Navajo-Moenkopi 500 KV Line.

                  6.    Navajo-Phoenix Area 500 KV Line.

               B. The switchyard limits for purposes shown on Exhibit C will be
the low voltage bushings of the generator step-up transformer and where the 500
KV leads from the series and shunt compensation attach to the switchyard
structure. The switchyard limits for purposes of design, construction, operation
and maintenance shall be the switchyard side of the first 500 KV transmission
line dead-end tower located outside the switchyard or where the 500 KV leads
from the generator step-up transformers attach to the switchyard structure. The
switchyard will include the metering, protective equipment, communications
equipment,

                                       -2-



relaying and associated equipment, etc.

            II. Navajo-McCullough 500 KV Line

                The Navajo-McCullough 500 KV line for purposes shown on Exhibit
C shall consist of approximately 250 miles of 500 KV line with associated series
and shunt compensation, terminated at the appropriate 500 KV switchracks in the
Navajo 500 KV Switchyard and McCullough 500 KV Switchyard.

            III. Navajo-Moenkopi 500 KV Line

                The Navajo-Moenkopi 500 KV line for purposes shown on Exhibit C
shall consist of approximately 76 miles of 500 KV line with associated series
and shunt compensation, terminated at the appropriate 500 KV switchracks in the
Navajo 500 KV Switchyard and Moenkopi 500 KV Switchyard.

            IV. Navajo-Phoenix Area 500 KV Line

                The Navajo-Phoenix Area 500 KV line for purposes shown on
Exhibit C shall consist of approximately 249 miles of 500 KV line with
associated series and shunt compensation, terminated at the appropriate
switchracks in the Navajo 500 KV Switchyard and Phoenix Area Substation(s).

            V. Moenkopi-Phoenix Area 500 KV Line

                The Moenkopi-Phoenix Area 500 KV line for purposes shown on
Exhibit C shall consist of approximately 173 miles of 500 KV line with
associated series and shunt compensation, terminated at the appropriate 500 KV
switchracks in the Moenkopi 500 KV Switchyard and Phoenix Area

                                       -3-



Substation(s).

            VI. Other Associated Components

                A. Moenkopi 500 KV Switchyard to be owned and expanded by
Arizona Public Service Company in accordance with Section 7.11 and Exhibit H of
this agreement.

                B. Additions to series capacitors in the Moenkopi-Eldorado 500
KV line.

                C. Additions to series capacitors in the Arizona Public Service
Company Cholla-Pinnacle Peak 345 KV line.

                D. Additions to series capacitors in the Arizona Public Service
Company Four Corners-Moenkopi 500 KV line.

            VII.  McCullough Substation

                The McCullough Substation shall consist of the following
components:

                  A. The 500 KV switchyard comprising the termination facilities
for the Navajo-McCullough 500 KV Line, McCullough-Victorville 500 KV Line,
McCullough-Eldorado 500 KV Line and transformer bank, including but not limited
to the 500 KV AC buses, power circuit breakers and disconnect switches and the
structures therefor.

                  B. A 400 MVA 500/287 KV transformer bank and the equipment
associated therewith, spare 133 MVA 500/287 KV transformer and the transformer
leads from the high and low voltage transformer bushings to the points of

                                       -4-



termination on the buses in the 500 KV and 287 KV switchyards.

                  C. The 287 KV switchyards comprising the termination
facilities for two McCullough-Nevada 287 KV Lines, McCullough-Hoover 287 KV Line
and transformer bank, including, but not limited to, the 287 KV buses, power
circuit breakers, disconnect switches and the structures therefor.

                  D. The common facilities, which shall include, but not limited
to, communications equipment, protection equipment controls, batteries,
auxiliary equipment, station grounding grid, lighting and yard improvements, but
shall not include the substation site.

                  E. The substation limits for the purposes shown on Exhibit C
shall be where the leads from the series and shunt compensation for the
Navajo-McCullough 500 KV Line and McCullough-Victorville 500 KV Line, from the
McCullough-Eldorado 500 KV Line, from the two McCullough-Nevada 287 KV Lines,
and from the McCullough-Hoover 287 KV Line attach to the substation structure.
The substation limits for the purpose of design, construction, operation and
maintenance shall be the substation side of the first 500 KV and 287 KV
transmission line dead-end towers located outside the substation. The substation
shall include the metering, protective equipment, communications equipment,
relaying and associated equipment, etc.

                                       -5-



            VIII. Phoenix Area Substation(s)

                  A. The Phoenix Area Substation(s) shall be a basic
breaker-and-a-half scheme providing termination for facilities presently
planned:

                        1.    Moenkopi-Phoenix Area 500 KV Line.

                        2.    Navajo-Phoenix Area 500 KV Line.

                        3.    A 500/230 KV step-down transformer #1.

                        4.    A 500/230 KV step-down transformer #2.

                        5.    A 500/345 KV step-down transformer.

                  B. The substation limits for purposes shown on Exhibit C will
be where the 500 KV leads from the series and shunt compensation attach to the
switchyard structure and where the 230 KV and 345 KV leads from the step-down
transformer attach to the substation structure in the 230 KV and 345 KV
substation. The substation limits for purposes of design, construction,
operation and maintenance shall be the substation side of the first 500 KV
transmission line dead-end tower located outside the switchyard or where the 230
KV and 345 KV leads from the step-down transformer attach to the substation
structure in the 230 KV and 345 KV substation.

                                       -6-


                                                                       EXHIBIT B

                                                                  Navajo Project

[MAP]




                                    EXHIBIT C
                            TRANSMISSION ALLOCATION




                                                                                        CONSTRUCTION AND O&M COST
                                                      OWNERSHIP %                           RESPONSIBILITY %
                                       --------------------------------------     ----------------------------------
                                       SRP 1/   APS    TGE   NPC   L.A.  SRP 2/   SRP   APS   TGE    NPC  L.A.  U.S.
                                       ------  ------  ----  ----  ----  ----     ----  ----  ----  ----  ----  ----
                                                                            
  I.  Navajo 500 KV Switchyard         21.7    14.0     7.5  11.3  21.2  24.3     21.7  14.0   7.5  11.3  21.2  24.3
 II.  Navajo-McCullough 500 KV Line                          26.1  48.9  25.0                       26.1  48.9  25.0
III.  Navajo-Moenkopi 500 KV Line      21.7    14.0     7.5  11.3  21.2  24.3     21.7  14.0   7.5  11.3  21.2  24.3
 IV.  Navajo-Phoenix Area 500 KV Line  38.3    24.7    13.3              23.7     38.3  24.7  13.3              23.7
  V.  Moenkopi-Phoenix Area 500 KV
       Line                            38.3    24.7    13.3              23.7     38.3  24.7  13.3              23.7

 VI.  Other Associated Components 3/
      A. Moenkopi 500 KV Switchyard            100.00                             21.7  14.0   7.5  11.3  21.2  24.3
      B. Moenkopi-Eldorado 500 KV
         Series Capacitor Additions 4/                                                              26.1  48.9  25.0
      C. Cholla-Pinnacle Peak 345 KV
         Series Capacitor Additions            100.00                             38.3  24.7  13.3              23.7
      D. Four Corners-Moenkopi 500 KV
         Series Capacitor Additions            100.00                             38.3  24.7  13.3              23.7

VII.  McCullough Substation 5/

VIII. Phoenix Area 500 KV Substation(s)38.3    24.7    13.3              23.7     38.3  24.7  13.3              23.7


1/    SRP's ownership for its own use and benefit

2/    SRP's ownership for the use and benefit of the United States.

3/    O&M cost responsibility applies only to the facilities added at these
      locations in conjunction with the Navajo Project.

4/    The capacitors on the Eldorado end of this line will be owned 100% by
      Southern California Edison Co. and those on the Moenkopi end will be owned
      100% by APS.

5/    See Exhibit C-1A for details of ownership and cost responsibility. There
      is attached to this Exhibit C, Exhibits C-1, C-1A and C-1B, which by this
      reference are made a part of this Exhibit C.

                                  EXHIBIT C-1
                     NAVAJO PROJECT [ILLEGIBLE] DIAGRAM OF
             COST RESPONSIBILITY, PROJECT MANAGER & OPERATING AGENT
                         LIMITS FOR TRANSMISSION SYSTEM

                             [NAVAJO PROJECT PLAN]



                                  EXHIBIT C-1A
                                 NAVAJO PROJECT
                              MCCULLOUGH SUBSTATION

                                                            NEVADA POWER COMPANY

                             [NAVAJO PROJECT PLAN]



                                                            CONSTRUCTION AND MAINTENANCE
                                        OWNERSHIP %             COST RESPONSIBILITY %
                                --------------------------------------------------------
SUBSTATION COMPONENT             LA       NPC     SRP(1)      LA        NPC       U.S.
                                --------------------------------------------------------
                                                                
500 kv Switchyard               77.4     16.4       6.2       77.4      16.4         6.2
287 kv Switchyard               40.1     59.9        --       40.1      59.9          --
500/287 kv Transformer Bank     60.5     39.5        --       60.5      39.5          --
Common Facilities               67.9     23.9       8.2       67.9      23.9         8.2


(1)  SRP's ownership for the use and benefit of the United States.

      The cost responsibility percentage for each Participant in Common
Facilities is the proportion that the investment of each Participant in line
compensation within McCullough Substation and in the other components of
McCullough Substation bears to the total investment of the Participants in such
line compensation and components expressed as a percentage and the percentages
for Common Facilities shown in the above table are to be recalculated using this
method when actual cost determinations are made.

      The ownership percentage for each Participant in Common Facilities shall
be the same as the cost responsibility percentage in Common Facilities for such
Participant, except that the ownership percentage in Common Facilities of Salt
River Project shall be the same as the cost responsibility percentage in Common
Facilities of United States.

      The Substation operation cost responsibility percentage shall be the same
as the construction and maintenance cost responsibility percentage Common
Facilities.

      Los Angeles shall construct, operate and maintain additional facilities



                                  EXHIBIT C-1B

    500 KV TRANSMISSION LINE OF LOS ANGELES BETWEEN McCULLOUGH SUBSTATION AND
     ELDORADO SUBSTATION AND SWITCHING FACILITIES AT ELDORADO AND McCULLOUGH
                  SUBSTATIONS INSTALLED TO TERMINATE THE LINE.

                          [NAVAJO PROJECT FLOW CHART]

SWITCHING FACILITIES INSTALLED TO TERMINATE THE 500KV LINE BETWEEN McCULLOUGH
SUBSTATION AND ELDORADO SUBSTATION ALLOCATED AS A PERCENTAGE OF SUBSTATION
COMPONENTS.

                McCullough Substation

                25.0% of 500 kv Switchyard
                 5.8% of Common Facilities         Note for Exhibit C:

                Eldorado Substation                Exhibit C-1B by this
                                                   [ILLEGIBLE] is made a
                16.7% of 500 kv Switchyard         part of this Exhibit



                                    EXHIBIT D

                         SCHEDULE OF CONSTRUCTION DATES

                                 NAVAJO PROJECT



                             SCHEDULED           SCHEDULED
      NAVAJO                  START UP             FIRM
GENERATING STATION             DATE              OPERATION
- ------------------           ---------           ---------
                                           
Unit #1                         3-1-74              6-1-74
Unit #2                         3-1-75              6-1-75
Unit #3                         3-1-76              6-1-76




                                                     SCHEDULED
                                      ENERGIZATION     FIRM
TRANSMISSION SYSTEM                   FOR TEST DATE  OPERATION
- ------------------------------------  -------------  ---------
                                               
Navajo 500 KV Switchyard                 2-1-74        3-1-74
Navajo-McCullough 500 KV Line            2-1-74        3-1-74
Navajo-Moenkopi 500 KV Line              2-1-74        3-1-74
Navajo-Phoenix Area 500 KV Line          2-1-75        3-1-75
Moenkopi -Phoenix Area 500 KV Line       2-1-74        3-1-74
Moenkopi 500 KV Switchyard               2-1-74        3-1-74
Cholla-Pinnacle Peak 345 KV Line **      2-1-75        3-1-75
Four Corners-Moenkopi 500 KV Line **     2-1-74        3-1-74
Moenkopi-Eldorado 500 KV Line **         2-1-74        3-1-74
McCullough Substation                    2-1-74        3-1-74
Phoenix Area Substation (#1) *           2-1-74        3-1-74
Phoenix Area Substation (#2) *           2-1-75        3-1-75


- ----------
*     Phoenix Area #2 Substation needed only if both Phoenix 500 KV lines are
      not terminated in same substation.

**    Compensation only



                                    EXHIBIT E

                    CONSTRUCTION COSTS OF THE NAVAJO PROJECT,
                     INCLUDING THE NAVAJO GENERATING STATION
                           AND THE TRANSMISSION SYSTEM

      1.1 Construction costs shall consist of payments made and obligations
incurred (other than obligations for interest during construction) for the
account of Station Work or Transmission Work and shall consist of, but not be
limited to, the following:

            1.1.1 All costs of labor, services and studies performed in
                  connection with Station Work or Transmission Work if
                  authorized and approved by the Project Managers.

            1.1.2 Payroll and other expenses of the Project Managers'
                  engineering departments for their employees who perform
                  Station Work or Transmission Work, including customary labor
                  loading charges applicable thereto, such as department
                  overheads, time-off allowances, payroll taxes, compensation
                  insurance and employee benefits.

            1.1.3 All components of the costs of construction, all overhead
                  costs associated with construction (including the allowance
                  for the Project Managers' administrative and



                  general expenses described in Exhibit E-l of this agreement),
                  all temporary facilities, all land and land rights, all
                  structures and improvements, and all equipment for the Navajo
                  Project, as set forth in the Electric Plant Instructions of
                  the FPC Accounts.

            1.1.4 All costs and expenses, including those of outside consultants
                  and attorneys, incurred by the Project Managers or other
                  Parties in regard to the land and water rights and fuel
                  requirements and supply for the Navajo Project and to the
                  preparation of other agreements relating to Station Work or
                  Transmission Work with entities other than (i) the United
                  States acting in its capacity as a contractor for resources to
                  supply Central Arizona Project pumping power requirements and
                  (ii) the Participants. All Parties anticipating such costs and
                  expenses shall submit an estimate of such costs and expenses
                  to the respective Project Managers for authorization and
                  approval. Any Party incurring such costs and expenses shall
                  bill the respective Project Manager therefor.

                                      -2-



            1.1.5 All costs, including any rental charges, of materials,
                  supplies, tools, machinery, equipment, apparatus and
                  construction power used in connection with Station Work or
                  Transmission Work.

            1.1.6 All costs of Project Insurance and all costs of any loss,
                  damage or liability arising out of or caused by Station Work
                  or Transmission Work which is not satisfied under the coverage
                  of Project Insurance.

            1.1.7 All federal, state or local taxes of any character imposed
                  upon Station Work or Transmission Work, except any tax
                  assessed directly against an individual Party, unless such tax
                  was assessed to such individual Party in behalf of any or all
                  of the other Parties.

            1.1.8 Expenses of other Parties incurred in the performance of
                  Station Work or Transmission Work, if authorized and approved
                  by the respective Project Manager, and the expenses of the
                  Operating Agents incurred during the engineering design
                  period, the construction period and the testing, the start-up
                  period of each unit of construction,

                                      -3-

                  excluding any training expenses not properly chargeable to
                  construction costs.

            1.1.9 All costs of relocating existing facilities by Station Work
                  or Transmission Work. Relocation of facilities and costs in
                  connection therewith shall be subject to agreement between the
                  Project Manager and the owners of the facilities involved.

      1.2 In cases where the allocation of a cost item is made between Station
Work or Transmission Work and other work, such allocation shall be made on a
fair and equitable basis.

      1.3 The Project Managers shall use the FPC Accounts to account for
construction costs in the final completion report and any supplement thereto.

      1.4 The Project Managers and the other Parties shall not be entitled to a
fee, price, percentage or any other compensation over and above the costs of
services rendered by them in the performance of Station Work or Transmission
Work.

                                      -4-



                                   EXHIBIT E-1

                 ADMINISTRATIVE AND GENERAL EXPENSES APPLICABLE
                  TO CONSTRUCTION COSTS OF THE NAVAJO GENERATING
                       STATION AND THE TRANSMISSION SYSTEM

      1.1 The allowance for the Project Manager's administrative and general
expenses to cover the costs of services rendered by it in the performance of
Station Work or Transmission Work shall be allocated monthly at the rate of
one per cent (1%) of construction costs incurred during the preceding month,
excluding from such construction costs:

            1.1.1 Any allowance for administrative and general expenses provided
                  for in this Section 1.1.

            1.1.2 Expenses of other Participants incurred in the performance of
                  Station Work or Transmission Work if authorized and approved
                  by the Project Manager, and the expenses of the Operating
                  Agent incurred during the engineering design period, the
                  construction period and the start-up period of each unit,
                  excluding any training expenses not charged to construction
                  costs, but including expenses which are billed by the
                  Operating Agent to the Project Manager pursuant to Section
                  1.1.3 of this Exhibit E-1.



            1.1.3 All charges relating to the operation and maintenance of all
                  units during the start-up period of each said unit. Charges
                  shall include (a) the cost of fuel, (b) the cost of all
                  operation and maintenance expenses (exclusive of the cost of
                  maintenance performed by the engineer-constructor start-up
                  crews), and (c) an allowance for the Operating Agent's payroll
                  loading and administrative and general expenses.

            1.1.4 Excepting only death, injury, loss or damage resulting from
                  Willful Action, the Participants shall pay to the extent of
                  their respective Generation Entitlement Shares for the costs
                  of discharging all legal liability imposed upon a Participant
                  for which payment shall not be made on account of valid and
                  collectible Project Insurance, and the expenses incurred in
                  settlement of injury and damage claims, including the costs of
                  labor and related supplies and expenses incurred in injury and
                  damage activities (all as referred to in FPC Account 925),
                  because of any claim arising out of or attributable to the
                  construction of the Navajo Project, the past

                                      -2-


                  or future performance or non-performance of the obligations
                  and duties of any Participant (including the Project
                  Manager)or the past or future performance or non-performance
                  of Station Work or Transmission Work, including but not
                  limited to any claim resulting from death or injury to persons
                  or damage to property.

      1.2 The allowance for the Operating Agent's administrative and general
expenses to cover the costs of services rendered by it in the performance of
capital additions, capital betterments and capital replacements shall be derived
in accordance with the procedure on Attachment No. 1 to this Exhibit E-1.

                                      -3-



                                   EXHIBIT E-1

                                ATTACHMENT NO. 1

                    CAPITAL ADMINISTRATIVE AND GENERAL RATIO
                                 NAVAJO PROJECT

      The rate to be applied to the Operating Agent's labor charges, which are
included in expenses for capital additions, capital betterments, and capital
replacements, to determine the Operating Agent's Administrative and General
expenses applicable thereto shall be established annually on the basis of the
Operating Agent's preceding year's construction expenses by the method set
forth herein unless otherwise agreed to by the Participants. The Administrative
and General Ratio will be adjusted to actual at year-end and the adjusted ratio
used in preparation of a revised billing to the Participants. A percentage based
on the Operating Agent's Administrative and General expenses shall be applied to
total construction costs on the following basis:

            I     Administrative and General expenses shall include:

                  (a)   Expenses in F.P.C. accounts 920 and 921 applicable to
                        construction costs. The percentage for determining the
                        amount of such expenses allocable to construction shall
                        be determined as provided in Exhibit F-1, Attachment No.
                        1A.

                  (b)   Payroll taxes applicable to the Administrative



                        and General salaries in F.P.C. accounts 920 and 921
                        allocable to construction, as provided in Exhibit F,
                        Attachments Nos. 1 and 1A.

                  (c)   Compensation insurance applicable to the Administrative
                        and General salaries in F.P.C. accounts 920 and 921
                        allocable to construction, as provided in Exhibit F,
                        Attachments Nos. 3 and 3A.

                  (d)   Pensions and benefits applicable to the Administrative
                        and General salaries in F.P.C. accounts 920 and 921
                        allocable to construction, as provided in Exhibit F,
                        Attachments Nos. 2 and 2A.

            II    Total pensions and benefits expense allocable to to total
                  labor charged to construction accounts at rate determined as
                  provided in Exhibit F, Attachment No. 2A.

            III   Total Administrative and General expenses allocable to
                  construction accounts shall be reduced by the amount of
                  Administrative and General expenses allocable to contract
                  construction.

      The rate for application of Administrative and General expense to
construction costs, hereinafter referred to as "Capital A & G Ratio", is
expressed as percentage of total allocable Administrative and General expense
to total direct



labor charged to construction.

        A & G Rate = A / C

  where

             A =  net allocable A & G expenses as set forth
                  in I, II and III above

             C =  total direct labor charged to construction
                  accounts

                                      -3-


                                    EXAMPLE
                       DEVELOPMENT OR CAPITAL A & G RATIO
                                     FOR THE
                            NAVAJO GENERATING STATION



                                                      Nevada Power Company          Ariz Public Service Co.
                                                      ---------------------         -----------------------
                                                      (Based on 1968 Costs)          (Based on 1968 Costs)
                                                        Labor       Total             Labor        Total
                                                      ----------  ---------         ----------   ----------
                                                                               
Net Allocable A & G Expenses

  A & G salaries and expenses
  charged to F.P.C. Accounts
  920 and 921                                         $  422,728  $ 531,802         $1,363,877   $1,910,668
                                                      ==========  =========         ==========   ==========

  Percent (See Exh. F-1) allocable
  to construction                             29.74%  $  125,719  $158,158   37.14% $  506,544   $  709,622

  Add:
     Payroll Taxes on allocated
     labor (Exh. F, Attach. 1A)                3.83%                  4,815   3.78%                  19,147

     Compensation Ins. on allocated
     labor (Exh. F, Attach. 3A)                1.11%                 1,395    1.14%                   5,775

     Pensions & Benefits on allocated
     labor (Exh. F, Attach. 2A)                7.66%                  9,630  11.92%                  60,380
                                                                  ---------                      ----------

  Total A & G expense allocable
  to construction                                                 $ 173,998                      $  794,924

  Pensions & Benefits expense
  allocable to total labor charged
  to construction accounts
  (Exh. F, Attachment 2A)                      7.66%  $1,282,333  $  98,227  11.92% $4,879,188   $  581,600
                                                                  ---------                      ----------

  Total A & G expense plus pensions
  and benefits expenses
  allocable to construction                                       $ 272,225                      $1,376,524

  Less amount of A & G expenses
  allocable to contract construction.                                 2,580                         188,230
                                                                  ---------                      ----------

  Remainder of A & G plus benefits
  expense allocable to construction                               $ 269,645                      $1,188,294
                                                                  =========                      ==========

Total Direct labor Charged to
Construction Accounts                                             $ 933,695                      $4,293,248
                                                                  =========                      ==========

Capital A & G Ratio =                                 $  269,645                    $1,188,294
                                                      ----------  = 28.88%          ----------   = 27.68%
                                                      $  933,695    =====           $4,293,248     =====

                                                        Salt River Project                  L. A. DWP
                                                      -----------------------        ------------------------
                                                      (Based on 1969 Budget)         (Based on 68-69 Costs)
                                                         Labor       Total              Labor        Total
                                                      -----------  ----------        -----------  -----------
                                                                                
Net Allocable A & G Expenses

  A & G salaries and expenses
  charged to F.P.C. Accounts
  920 and 921                                         $1,730,086  $2,334,498          $ 3,412,254  $ 6,126,895
                                                      ==========  ==========          ===========  ===========

  Percent (See Exh. F-1) allocable
  to construction                             38.83%  $  671,792  $  906,486   49.50%  $1,689,066  $ 3,032,813

  Add:
     Payroll Taxes on allocated
     labor (Exh. F, Attach. 1A)                3.38%                  22,707    0.11%                    1,858

     Compensation Ins. on allocated
     labor (Exh. F, Attach. 3A)                2.90%                  19,482    0.94%                   15,877

     Pensions & Benefits on allocated
     labor (Exh. F, Attach. 2A)               12.56%                  84,377   13.66%                  230,726
                                                                  ----------                       -----------

  Total A & G expense allocable
  to construction                                                 $1,033,052                       $ 3,281,274

  Pensions & Benefits expense
  allocable to total labor charged
  to construction accounts
  (Exh. F, Attachment 2A)                     12.56%  $6,606,824  $  829,817   13.66% $43,581,981  $ 5,953,299
                                                                  ----------                       -----------

  Total A & G expense plus pensions
  and benefits expenses allocable to
  construction                                                    $1,862,869                       $ 9,234,573

  Less amount of A & G expenses
  allocable to contract construction.                                 33,806                           692,604
                                                                  ----------                       -----------

  Remainder of A & G plus benefits
  expense allocable to construction                               $1,829,063                       $ 8,541,969
                                                                  ==========                       ===========

Total Direct labor Charged to
Construction Accounts                                             $5,898,725                       $24,417,890
                                                                  ==========                       ===========

                                                      $1,829,063                      $ 8,541,969
Capital A & G Ratio =                                 ----------  = 31.00%            -----------  = 34.98%
                                                      $5,898,725    =====             $24,417,890    =====



                                    EXHIBIT F

                       OPERATION AND MAINTENANCE COSTS OF
                          THE NAVAJO GENERATING STATION

1.    Generating Plant:

            1.1 Operation and maintenance costs shall include the following
      expenses to the extent that they are charge-able to the Navajo Generating
      Station in accordance with sound accounting practice:

                  1.1.1 The operation expenses chargeable to FPC Accounts 500,
                        502, 503, 504, 505, 506, 507, 556, 557 and any costs in
                        the following FPC Accounts pertaining to load
                        dispatching:

                        1.1.1.1 560, 561, 562, 566 and 567.

                  1.1.2 The maintenance expenses chargeable to FPC Accounts 510
                        through 514, inclusive, and any costs in the following
                        FPC Accounts pertaining to load dispatching:

                        1.1.2.1 568, 569, 570 and 573.

                  1.1.3 Overhead expenses included in Sections 1.1.1 and 1.1.2
                        of this Exhibit F incurred by the Operating Agent
                        which are allocable to the operation and maintenance
                        of the Navajo Generating Station.



                  Such overhead expenses shall be determined in accordance with
                  the following allocation procedure:

                  1.1.3.1 Overhead expenses of the Operating Agent applicable
                        to the Navajo Generating Station operation and
                        maintenance expenses will be generated at two sources:

                        1.1.3.1.1 The salaries and expenses of the Operating
                              Agent's functional area responsible for power
                              supply and system operations, the supervisory,
                              administrative and clerical staff, including
                              members of the staff that perform system
                              protection, operation and production functions,
                              including appropriate system dispatching costs.

                        1.1.3.1.2 The salaries and expenses of the Operating
                              Agent's supervisor of steam generation, if not
                              included within Section 1.1.3.1.1 of

                                       -2-


                        this Exhibit F, and his supervisory, administrative,
                        engineering and clerical staff.

                              These overhead costs shall be applicable to the
                        total payroll supervised by said functional areas of
                        the Operating Agent, respectively. The Navajo Generating
                        Station's share of such costs shall be equal to the sum
                        of: (a) the Operating Agent's functional area overhead
                        costs as described in Section 1.1.3.1.1 of this
                        Exhibit F multiplied by a ratio, the numerator of which
                        is the total Navajo Generating Station payroll and the
                        denominator of which is the Operating Agent's total
                        payroll supervised by said functional area, and (b) the
                        Operating Agent's functional area overhead costs as
                        described in Section 1.1.3.1.2 of this Exhibit F
                        multiplied by a ratio, the numerator of which is the
                        total Navajo Generating Station payroll and the
                        denominator of which is the Operating

                                       -3-


                        Agent's total payroll supervised by said functional
                        area.

                              The total of the Navajo Generating Station
                        overhead costs set forth herein shall be allocated to
                        all direct labor charges at said Navajo Generating
                        Station, which shall include operation and maintenance
                        labor and work order labor charges. All such overhead
                        charges shall be allocated to the appropriate FPC
                        Account(s).

                  1.1.4 Applicable labor loading charges for Operating Agent's
                        employees whose salaries and wages are charged to the
                        operation and maintenance expense accounts. Such
                        labor loading charges shall include but not be limited
                        to time-off allowances employee payroll taxes chargeable
                        to FPC Account 408 and employee benefits chargeable to
                        FPC Accounts 925 and 926.

                        1.1.4.1 Payroll tax expenses incurred by the Operating
                              Agent which are allocable to the Navajo
                              Generating Station pursuant to Section 1.1.4 of
                              this Exhibit F shall be

                                       -4-


                              determined by multiplying the sum of the Operating
                              Agent's total labor charges included in the
                              expenses determined in accordance with Sections
                              1.1.1 and 1.1.2 of this Exhibit F by a decimal
                              fraction, hereinafter referred to as the Payroll
                              Tax Ratio. Such Payroll Tax Ratio shall be derived
                              annually in accordance with the procedure and
                              example shown on Attachment Nos. 1 and 1A to this
                              Exhibit F.

                      1.1.4.2 Employee pensions and benefits expenses incurred
                              by the Operating Agent which are allocable to
                              the Navajo Generating Station pursuant to Section
                              1.1.4 of this Exhibit F shall be determined by
                              multiplying the sum of the Operating Agent's total
                              labor charges included in the expenses determined
                              in accordance with Sections 1.1.1 and 1.1.2 of
                              this Exhibit F by a decimal fraction, hereinafter

                                      -5-


                              referred to as the Benefits Ratio. Such Benefits
                              Ratio shall be derived annually in accordance with
                              the procedure and example shown on Attachment Nos.
                              2 and 2A to this Exhibit F.

                      1.1.4.3 That portion of employee Workmen's Compensation
                              Insurance expenses and the related administrative
                              expenses incurred by the Operating Agent which are
                              allocable to the Navajo Generating Station
                              pursuant to Section 1.1.4 of this Exhibit F shall
                              be determined by multiplying the sum of the
                              Operating Agent's total labor charges included in
                              the expenses determined in accordance with
                              Sections 1.1.1 and 1.1.2 of this Exhibit F by a
                              decimal fraction, hereinafter referred to as the
                              Compensation Insurance Ratio. Such Compensation
                              Insurance Ratio shall be derived annually in
                              accordance with the procedure and example

                                      -6-


                              shown on Attachment Nos. 3 and 3A to this Exhibit
                              F.

                        1.1.5 Administrative and general expenses of the
                              Operating Agent allocable to operation and
                              maintenance of the Navajo Generating Station
                              pursuant to Exhibit F-1 hereto.

                        1.1.6 The training expenses of operation and maintenance
                              personnel for the Navajo Generating Station,
                              including labor loading charges in accordance
                              with Section 1.1.4 of this Exhibit F and
                              applicable administrative and general expenses as
                              computed in accordance with Exhibit F-1 hereto,
                              which are incurred prior to the date of firm
                              operation and not properly chargeable to the costs
                              of construction of the Navajo Generating Station
                              shall be accumulated by the Operating Agent and
                              shall be apportioned to the Participants in
                              accordance with their Generation Entitlement
                              Shares and billed to the Participants.

                        1.1.7 All expenses of procuring and maintaining policies
                              of Project Insurance.

                        1.1.8 All costs chargeable to FPC Account 501.

                                       -7-


                                    EXHIBIT F
                                ATTACHMENT NO. 1

                                PAYROLL TAX RATIO
                 APPLICABLE TO OPERATING & MAINTENANCE EXPENSES
                        OF THE NAVAJO GENERATING STATION

            The Payroll Tax Ratio to be applied to the labor expense portion of
the Navajo Generating Station Operation & Maintenance Expenses shall be
determined annually on the basis of the Operating Agent's preceding year's
expenses as set forth herein unless otherwise agreed to by the Participants.
The Payroll Tax Ratio will be adjusted to actual at year-end and the adjusted
ratio used in preparation of a revised billing to Participants.

                              Payroll Tax Ratio =  T/P

Where:  T =           The Operating Agent's payroll tax expenses
                      chargeable to F.P.C. account 408 as applicable
                      to the labor expenses included in its total
                      system operation, maintenance, construction,
                      and general ledger accounts.

        P =           The Operating Agent's labor expenses as paid to
                      employees and distributed to total system operation,
                      maintenance, construction, and general ledger accounts.



            The example in Exhibit F, Attachment No. 1A, sets forth the method
to be employed by the Operating Agent to determine the Payroll Tax Ratio.

                                      -2-


                                                                   EXHIBIT F

                                                                   ATTACHMENT 1A

                                     EXAMPLE

                        DEVELOPMENT OF PAYROLL TAX RATIO
              APPLICABLE TO OPERATING & MAINTENANCE EXPENSES OF THE
                            NAVAJO GENERATING STATION




                                           N. P. Co.              A.P.S. Co.               S.R.P.                L.A. DWP
                                         ------------            ------------           -------------          -------------
                                         (1968 Costs)            (1968 Costs)           (1969 Budget)          (68-69 Costs)
                                         ------------            ------------           -------------          -------------
                                                                                          
(T)  Total Payroll Taxes                 $    183,746            $    933,421           $     580,000          $     106,112*
                                         ============            ============           =============          =============

(P)  Labor Base

      Total labor charged
      to operation, maintenance,
      construction, and general
      ledger accounts                    $  4,797,468            $ 24,690,234           $  17,148,862          $  93,904,454
                                         ============            ============           =============          =============

                                         $    183,746            $    933,421           $     580,000          $     106,112
                                         ------------ = 3.83%    ------------ = 3.78%   ------------- = 3.38%  ------------- = 0.11%
Payroll Tax Ratio =                      $  4,797,468   ====     $ 24,690,234   ====    $  17,148,862   ====   $  93,904,454   ====


* Yearly estimate on basis of payroll periods from 5/18/69 to 6/30/69.



                                    EXHIBIT F
                                ATTACHMENT NO. 2

                          BENEFITS RATIO APPLICABLE TO
                        OPERATING & MAINTENANCE EXPENSES
                        OF THE NAVAJO GENERATING STATION

      The Benefits Ratio to be applied to the labor expense portion of the
Navajo Generating Station Operations and Maintenance Expenses shall be
determined annually on the basis of the Operating Agent's preceding year's
experience as set forth herein unless otherwise agreed to by the Participants.
The Benefits Ratio will be adjusted to actual at year-end and the adjusted ratio
used in preparation of a revised billing to Participants.

                       Benefits Ratio = B/L

Where:  B =  That portion of the Operating Agent's total system employee
             pensions and benefits chargeable to F.P.C. account 926, including
             payroll taxes and Employee Compensation Insurance Expense on labor
             charges to account 926.

        L =  The Operating Agent's labor expenses as paid to employees and
             distributed to its total system operation, maintenance,
             construction, and general ledger accounts less labor charges to
             F.P.C. account 926.



      The example in Exhibit F, Attachment No. 2A, sets forth the method to be
employed by the Operating Agent to determine the Benefits Ratio.

                                       -2-


                                                                       EXHIBIT F
                                                                   Attachment 2A

                                     EXAMPLE

                         DEVELOPMENT OF BENEFITS RATIO
             APPLICABLE TO OPERATING & MAINTENANCE EXPENSES OF THE
                            NAVAJO GENERATING STATION



                          Nevada Power Company   Ariz. Public Service Co.   Salt River Project              L. A. DWP
                          --------------------   ------------------------ ----------------------   ------------------------
                          (based on 1968 Costs)  (Based on 1968 Costs)    (Based on 1969 budget)    (Based on 68-69 Costs)
                            Labor       Total      Labor         Total      Labor       Total        Labor         Total
                          ---------  ----------- ---------   ------------ ---------  ------------  ----------  ------------
                                                                                       
Pensions & Benefits

  Employee
   Pensions
   & Benefits
   Charged to
   Account 926             $ 15,331  $   279,249 $ 216,978   $  2,905,654 $ 164,315  $  2,124,326  $  199,426  $ 12,802,019

  Add: Pensions &
       Benefits
       Capitalized                        86,488                       --                      --                        --
                                     -----------             ------------            ------------              ------------
  Subtotal                           $   365,737             $  2,905,654            $  2,124,326              $ 12,802,019

  Add:

       Payroll Taxes
       (Exh. F,
       Attach, 1A)        @ 3.83%                @ 3.78%                  @ 3.38%                  @ 0.11%
                          of labor = $       587 of labor =  $      8,202 of labor = $      5,554  of labor =  $        219

       Compensation Ins.
       (Exh. F,
       Attach, 3A)        @1.11%                 @ 1.14%                  @ 2.69%                  @ 0.94%
                          of labor = $       170 of labor =  $      2,474 of labor = $      4,421  of labor =  $      1,875
                                     -----------             ------------            ------------              ------------
  Total Pensions &
   Benefits Expense                  $   366,494             $  2,916,330            $  2,134,301              $ 12,804,113
                                     ===========             ============            ============              ============

Labor Base

  Total labor charged
  to Operation, Main-
  tenance, Construc-
  tion,  and General
  Ledger Accounts,
  exclusive of labor
  charged to Account 926.            $ 4,782,137             $ 24,473,256            $ 16,984,547              $ 93,705,028
                                     ===========             ============            ============              ============

Benefits Ratio =                     $   366,494             $  2,916,330            $  2,134,301              $ 12,804,113
                                     -----------  =  7.66%   ------------ = 11.92%   ------------ = 12.56%     ------------ = 13.66%
                                     $ 4,782,137    =====    $ 24,473,256   =====    $ 16,984,547   =====      $ 93,703,028   =====


                                   EXHIBIT F
                                ATTACHMENT NO. 3

                          COMPENSATION INSURANCE RATIO
                                     FOR THE
                            NAVAJO GENERATING STATION

      The Compensation Insurance Ratio to be applied to the labor expenses
included in the Operating Agent's Administrative and General expense accounts
shall be determined annually on the basis of the Operating Agent's preceding
year's expenses as set forth herein unless otherwise agreed to by the
Participants. The Compensation Insurance Ratio will be adjusted to actual at
year-end and the adjusted ratio used in preparation of a revised billing to
Participants.

      Compensation Insurance Ratio = l/P

Where:   l =  The Operating Agent's total system Compensation Insurance
              premiums and accruals for self-insurance charges to F.P.C. Account
              925, less amounts billed to others under participation agreements.

         P =  The Operating Agent's labor expenses included in its total
              system operation, maintenance, construction, and general ledger
              accounts, less amounts for labor billed to others under joint
              participation project agreements.


      The example in Exhibit F, Attachment No. 3A, sets forth the method to be
employed by the Operating Agent to determine the Compensation Insurance Ratio.

                                       -2-



                                                                   EXHIBIT F
                                                                   ATTACHMENT 3A

                                     EXAMPLE
                   DEVELOPMENT OF COMPENSATION INSURANCE RATIO
             APPLICABLE TO OPERATING & MAINTENANCE EXPENSES
                                     OF THE
                           NAVAJO GENERATING STATION


                                              N.P. Co.              A.P.S. Co.             S.R.P.               L.A. DWP
                                            -----------            -----------          ------------          ------------
                                            (1968 Costs)           (1968 Costs)         (1969 Budget)         (68-69 Costs)
                                            -----------            -----------          ------------          ------------
                                                                                                  
(T) Total Compensation Insurance Cost

   Total Compensation Insurance             $   39,114             $   282,548          $   496,494           $    879,659
   Cost in Account 925                      ==========             ===========          ===========           ============

(P) Labor Base

   Total labor charged to operation,
   maintenance, and general ledger
   accounts                                 $3,515,135             $15,541,752          $11,250,137           $50,322,473

   Total labor charged to                   *(Not Applicable)      $ 9,148,482          $ 5,898,725           $43,581,981
   construction accounts                    ----------------       -----------          -----------           -----------

       Total Labor Expense                  $3,515,135             $24,690,234          $17,148,862           $93,904,454
                                            ==========             ===========          ===========           ===========

 Compensation Insurance Ratio =             $   39,114             $   282,548          $   496,494           $   879,659
                                            ---------- = 1.11%     ----------- = 1.14%  ----------- = 2 .90%  ----------- = 0.94%
                                            $3,515,135   ====      $24,690,234   ====   $17,148,862   =====   $93,904,454   ====




*     Nevada Power Company charges Compensation Insurance costs to plant labor
      from liability account 232.2.



                                   EXHIBIT F-1

                 ADMINISTRATIVE AND GENERAL EXPENSES APPLICABLE
                        TO OPERATION AND MAINTENANCE OF
                         THE NAVAJO GENERATING STATION

      1.1 The allowance for the Operating Agent's administrative and general
expenses to cover the costs of services rendered by it in the performance of
operation and maintenance of the Navajo Generating Station shall be derived in
accordance with the procedure and examples shown on Attachment Nos. 1, 1A, 2
and 2A to this Exhibit F-1.



                                   EXHIBIT F-1
                                ATTACHMENT NO. 1

                    DETERMINATION OF RATIO OF O & M LABOR AND
                    CONSTRUCTION LABOR TO TOTAL LABOR FOR THE
                            NAVAJO GENERATING STATION

            I.    Determination of the ratio of operating and maintenance labor
to total labor shall be as follows:

                          O & M Ratio = O/L

            where
                          O = total labor charged to operation and
                              maintenance accounts less labor charged to
                              A & G accounts 920 through 932 inclusive

                          L = total labor charged to operating and
                              maintenance, construction, and general ledger
                              accounts, less labor charged to A & G accounts
                              920 through 932 inclusive

            II.   Determination of the ratio of construction labor to total
labor shall be as follows:

                          Construction Ratio = C/L

            where

                          C = total labor in construction accounts

                          L = total labor charged to operation and
                              maintenance, construction, and general ledger
                              accounts, less labor charged to A & G accounts
                              920 through 932 inclusive



                                                                   EXHIBIT F-1
                                                                   ATTACHMENT 1A

                                     EXAMPLE
   DETERMINATION OF RATIO OF O & M LABOR AND CONSTRUCTION LABOR TO TOTAL LABOR
                                    FOR THE
                           NAVAJO GENERATING STATION



                                                N. P. Co.           A.P.S. Co.               S.R.P.              L. A. DWP
                                              -----------          -----------           ------------          ------------
                                              (1968 Costs)         (1968 Costs)          (1969 Budget)         (68-69 Costs)
                                              -----------          -----------           ------------          ------------
                                                                                                   
(1) Total Labor in
    Operation and Maintenance Accounts        $ 3,290,399          $  9,663,668          $ 11,245,752          $ 50,300,847

    Less Labor charged to A &
    G Accounts 920, thru 932
    inclusive                                     485,437             1,405,923             1,958,894             5,863,153
                                              -----------          ------------          ------------          ------------

    Net Labor in O & M Accounts               $ 2,804,962          $  8,257,745          $  9,286,858          $ 44,437,694

    Total Labor charged to
      General Ledger Accounts                     224,736                     -                 4,385                21,626

    Total Labor in
      Construction Accounts                     1,282,333             4,879,188             5,898,725            43,581,981
                                              -----------          ------------          ------------          ------------

         Total Labor Base                     $ 4,312,031          $ 13,136,933          $ 15,189,968          $ 88,041,301
                                              ===========          ============          ============          ============

    Ratio of Net O & M Labor to Total         $ 2,804,962          $  8,257,745          $  9,286,858          $ 44,437,694
                                              ----------- = 65.05% ------------ = 62.86% ------------ = 61.14% ------------ = 50.47%
    Labor  =                                  $ 4,312,031   =====  $ 13,136,933   =====  $ 15,189,968   =====  $ 88,041,301   =====


(11) Ratio of Construction Labor to Total     $ 1,282,333          $  4,879,188          $  5,898,725          $ 43,581,981
                                              ----------- = 29.74% ------------ = 37.14% ------------ = 38.83% ------------ = 49.50%
     Labor =                                  $ 4,312,031   =====  $ 13,136,933   =====  $ 15,189,968   =====  $ 88,041,301   =====





                                   EXHIBIT F-1
                                ATTACHMENT NO. 2

                       ADMINISTRATIVE AND GENERAL EXPENSE
                     APPLICABLE TO OPERATION & MAINTENANCE
                        OF THE NAVAJO GENERATING STATION

      That portion of the Operating Agent's administrative and general expenses
which are allocable to operation and maintenance of the Navajo Generating
Station shall be determined by multiplying the total operating and maintenance
labor of the Navajo Generating Station by a decimal fraction hereinafter
referred to as the "Administrative and General Expense Ratio." Such
Administrative and General Ratio shall be derived annually based on the
preceding year's expenses, as set forth herein unless otherwise agreed to by the
participants. The Administrative and General Ratio will be adjusted to actual at
year-end, and the adjusted ratio used in preparation of a revised billing to
participants.

      The Administrative and General expenses charged to F.P.C. accounts 920 and
921 shall be multiplied by a percentage representing the ratio of operation and
maintenance labor to total labor. To the result shall be added the total in
F.P.C. accounts 923 and 932 plus additives to labor in F.P.C. accounts 920, 921,
and 932 as illustrated in Attachment No. 2A hereof. The resulting Administrative
and General expenses applicable to Operating and Maintenance



expense shall be divided by the total Operating and Maintenance expense labor
subject to Administrative and General expense allocation.

      Administrative and General Expense Ratio = A/B

Where:  A = Portion of Administrative and General Expenses charged to F.P.C.
            accounts 920 and 921, plus total in F.P.C. accounts 923 and 932,
            plus additives to labor in F.P.C. account 932 and to a portion of
            the labor in F.P.C. accounts 920 and 921, as illustrated in
            Attachment No. 2A hereof.

        B = Total operating and maintenance labor, less labor, less labor in
            Administrative and General expense accounts 920 thru 932 inclusive.

                                      -2-



                                                                     EXHIBIT F-1
                                                                   ATTACHMENT 2A

                                     EXAMPLE

                 DEVELOPMENT OF ADMINISTRATIVE & GENERAL RATIO
                  APPLICABLE TO OPERATION & MAINTENANCE EXPENSE
                                     OF THE
                            NAVAJO GENERATING STATION



                                         Nevada Power Company          Ariz. Public Service Co.        Salt River Project
                                        ---------------------          ------------------------       ---------------------
                                        (Based on 1968 Costs)           (Based on 1968 Costs)         (Based on 1969 Costs)
                                        Labor         Total             Labor        Total             Labor        Total
                                       -------      ---------           -------    --------           -------      -------
                                                                                                 
   Administrative & General
     Expenses

   Account 920 A & G Salaries          $   422,728  $  422,728         $1,363,877  $1,428,643         $1,647,490   $1,647,490
   Account 921 A & G
     Office Supplies &
     Expense                                           109,074                        482,025             82,596      687,008
                                       -----------  ----------         ----------  ----------         ----------   ----------

       Total Accounts 920
        and 921                        $   422,728  $  531,802         $1,363,877  $1,910,668         $1,730,086   $2,334,498
                                       ===========  ==========         ==========  ==========         ==========   ==========

   Percent Applicable to
     Operation and Maintenance
     (See Exh. F-1, Attach. 1A) 65.05% $   274,985  $  345,937 62.86%  $  857,333  $1,201,046 61.14%  $1,057,775   $1,427,312

   Account 923 Outside
     Services                                           31,247                        225,952                          93,356
           932 General Maintenance          28,161      65,978            264,235     456,799             64,493       94,263
                                       -----------  ----------         ----------  ----------         ----------   ----------

                  Subtotal             $   303,146  $ 443,162          $1,121,568  $1,883,797         $1,122,268   $1,614,931

   Payroll Taxes as a
     percentage of labor
     (Exh. F, Attach. 1A)        3.83%              $   11,610  3.78%              $   42,395  3.38%               $   37,933
   Compensation Ins. as a
     percentage of labor (Exh.
     F, Attach. 3A)              1.11%                   3,365  1.14%                  12,786  2.69%                   30,189
   Pensions & Benefits as a
     percentage of labor
    (Exh. F, Attach. 2A)         7.66%                  23,221 11.92%                 133,691 12.56%                  140,957
                                                    ----------                     ----------                      ----------
       Total A & G
       Expense allocable
       to Operation
       & Maintenance Accounts                       $  481,358                     $2,072,669                      $1,824,010
                                                    ==========                     ==========                      ==========
3) Net Labor Charged to
   Operation & Maintenance
   Accounts
   (Excluding labor in A & G
   Accounts 920 thru 932
   inclusive)                                       $2,804,962                     $8,257,745                      $9,286,858
                                                    ==========                     ==========                      ==========

   [ILLEGIBLE] & G Ratio =             $   481,358                     $2,072,669                      $1,824,010
                                       ----------- = 17.16%            ---------- = 25.10%             ---------- = 19.64%
                                       $ 2,804,962   ======            $8,257,745   =====              $9,286,858   =====



                                                   L.A. DWP
                                           ------------------------
                                           (Based on 60-69 Costs)
                                             Labor         Total
                                           -----------  -----------
                                                  
    Administrative & General
      Expenses

    Account 920 A & G Salaries             $ 3,412,254  $ 3,412,254
    Account 921 A & G
      Office Supplies &
      Expense                                             2,714,641
                                           -----------  -----------

        Total Accounts 920
         and 921                           $ 3,412,254  $ 6,126,895
                                           ===========  ===========

    Percent Applicable to
      Operation and Maintenance (See
      Exh. F-1, Attach. 1A)            50.47%    $ 1,722,165  $ 3,092,244
    Account 923 Outside
      Services                                                    404,288
            932 General Maintenance                   77,719      471,040
                                                 -----------  -----------

                 Subtotal                        $ 1,799,884  $ 3,967,572

    Payroll Taxes as a
      percentage of labor
      (Exh. F, Attach. 1A)              0.11%                 $     1,980
    Compensation Ins. as a
      percentage of labor (Exh.
      F, Attach. 3A)                    0.94%                      16,919
    Pensions & Benefits as a
      percentage of labor (Exh, F.
      Attach. 2A)                      13.66%                     245,864
                                                              -----------

        Total A & G
        Expense allocable
        to Operation
        & Maintenance Accounts                          $ 4,232,335
                                                        ===========

3)  Net Labor Charged to
    Operation & maintenance
    Accounts
    (Excluding labor in A & G                           $44,437,694
                                                        ===========
    Accounts 920 thru 932
    inclusive)

    [ILLEGIBLE] & G Ratio =                $ 4,232,335
                                           ----------- = 9.52%
                                           $44,437,694   ====






                                    EXHIBIT G

                         OPERATION AND MAINTENANCE COSTS
                           OF THE TRANSMISSION SYSTEM

      1.1 Operation and maintenance costs shall include the following expenses
to the extent that they are chargeable to the Transmission System in accordance
with sound accounting practice:

            1.1.1 The Transmission System operation costs chargeable to FPC
                  Accounts 560, 561, 562, 563, 566 and 567.

            1.1.2 The Transmission System maintenance costs chargeable to FPC
                  Accounts 568, 569, 570, 571 and 573.

            1.1.3 The general plant maintenance costs chargeable to FPC Account
                  932 for maintenance of equipment, the book cost of which is
                  includable in FPC Account 397, Communication Equipment, and
                  FPC Account 398, Miscellaneous Equipment.

            1.1.4 Overhead expenses included in Sections 1.1.1, 1.1.2 and 1.1.3
                  of this Exhibit G incurred by the Operating Agent which are
                  allocable to the operation and maintenance of the Transmission
                  System. Such overhead



                  expenses shall be determined in accordance with the following
                  allocation procedure:

                  1.1.4.1 Overhead expenses of the Operating Agent applicable to
                          Transmission System operation and maintenance expenses
                          will be generated at various functional areas. The
                          overhead costs of each functional area shall be
                          applicable to the total payroll supervised by said
                          functional areas of the Operating Agent. The
                          Transmission System's share of such costs shall be
                          equal to the sum of each applicable Operating Agent's
                          functional area overhead costs multiplied by a ratio,
                          the numerator of which is the total Transmission
                          System payroll and the denominator of which is the
                          Operating Agent's total payroll supervised by said
                          functional area.

                        The total of the Transmission System overhead costs set
                  forth herein shall be allocated to all direct labor charges at
                  said Transmission System, which shall

                                       -2-



                  include operation and maintenance labor and work order labor
                  charges. All such overhead charges shall be allocated to the
                  appropriate FPC Account(s).

                  1.1.5 Applicable labor loading charges for Operating Agent's
                        employees whose salaries and wages are charged to the
                        operation and maintenance expense accounts. Such labor
                        loading charges shall include but not be limited to
                        time-off allowances, employee payroll taxes chargeable
                        to FPC Account 408 and employee benefits chargeable to
                        FPC Accounts 925 and 926 as provided in Section 1.1.4 of
                        Exhibit F hereto.

                  1.1.6 Administrative and general expenses of the Operating
                        Agent allocable to operation and maintenance of the
                        Transmission System pursuant to Exhibit G-1 hereto.

                                       -3-



                                   EXHIBIT G-1

                 ADMINISTRATIVE AND GENERAL EXPENSES APPLICABLE
                      TO OPERATION AND MAINTENANCE OF THE
                              TRANSMISSION SYSTEM

      1.1 The allowance for the Operating Agent's administrative and general
expenses to cover the costs of services rendered by it in the performance of
operation and maintenance of the Transmission System shall be derived in
accordance with the procedure and examples shown on Attachment Nos. 1, 1A, 2 and
2A to Exhibit F-1 hereto.



                               SALT RIVER PROJECT

                                   RESOLUTION

WHEREAS, the Board of Directors of the Salt River Project Agricultural
Improvement and Power District (herein called "Salt River Project") has
determined that it is in Salt River Project's best interest to enter into
various contracts relating to the construction, operation and maintenance of the
proposed Navajo Project consisting of three 750 MW (nameplate rating) coal-fired
steam electric generating units (herein called "Navajo Generating Station"),
located on the Navajo Indian Reservation near Page, Arizona, and the related 500
KV transmission system (herein called "Navajo transmission system"), with
ownership interests in the Navajo Generating Station to be as follows:


                                          
Arizona Public Service Co. (Arizona)         14.0%

City of Los Angeles, Department of
Water and Power (Los Angeles)                21.2%

Nevada Power Company (Nevada)                11.3%

Salt River Project Agricultural
Improvement and Power District
(Salt River Project)                         46.0%

Tucson Gas and Electric Company
(Tucson)                                      7.5%


all of said entities referred to herein as the "Co-Owners," and

WHEREAS, Salt River Project shall own 21.7% of the Navajo Generating Station for
its own use and benefit and shall own and hold the remaining 24.3% of its
ownership interest in the Navajo Generating Station for the use and benefit of
the United States, Department of Interior, Bureau of Reclamation for the United
States' use to provide power and energy for Central Arizona Project pumping (the
"United States" and the above listed companies being herein collectively called
"Participants"), and

WHEREAS, the following described Agreements have been reviewed on this day with
this Board and this Board has determined that it is in the best interest of Salt
River Project to enter into said Agreements to effectuate the construction,
operation and maintenance of the Navajo Project;

NOW, THEREFORE, BE IT HEREBY RESOLVED, That the Board of Directors of Salt River
Project has and does hereby approve the Navajo Project Participation Agreement
among the Participants, and has and does hereby empower and direct that the
President or Vice President, and the



                               SALT RIVER PROJECT

Secretary or Assistant Secretary, make, execute and deliver said Participation
Agreement for, and on behalf of, the Salt River Project with such minor changes
or omissions therein as management may make in the premises, and

BE IT HEREBY FURTHER RESOLVED that the Board of Directors of Salt River Project
has and does hereby approve the Indenture of Lease for Navajo Units 1, 2 and 3,
and has and does hereby empower and direct that the President or Vice President,
and the Secretary or Assistant Secretary, make, execute, acknowledge and deliver
said Indenture of Lease for Navajo Units 1, 2 and 3 for and on behalf of the
Salt River Project with such minor changes or omissions therein as management
may make in the premises, and

BE IT HEREBY FURTHER RESOLVED that the Board of Directors of Salt River Project
has and does hereby approve that certain Federal Rights of Way, granted in
conformity with the Act of February 15, 1901, between the Secretary of Interior
and the Co-Owners as Grantees, and does hereby authorize, empower and direct
that the President or Vice President, and the Secretary or Assistant Secretary,
make, execute, acknowledge and deliver said Federal Rights of Way for, and on
behalf of, Salt River Project with such minor changes or omissions therein as
management may make in the premises, and this Board of Directors also
authorizes, empowers and directs its officers and management to make and file an
Application for Grant of Rights of Way under the Act of February 15, 1901, 31
Stat. 790, 43 U.S.C., Section 959, underlying any or all Project land rights,
and to take and perform all necessary acts in making and filing such
Application, and

BE IT HEREBY FURTHER RESOLVED that the Board of Directors of Salt River Project
has and does hereby approve that certain Federal Rights of Way and Easements,
granted in conformity of February 5, 1948, by and between the Secretary of
Interior and Salt River Project and the other Co-Owners as Grantees and does
hereby authorize, empower and direct that the President or Vice President, and
the Secretary or Assistant Secretary, make, execute, acknowledge and deliver
said Federal Rights of Way and Easements for, and on behalf of, the Salt River
Project with such minor changes and omissions therein as management may make in
the premises, and does hereby authorize, empower and direct its officers and
management to make and file an Application for the Grant of Rights of Way and
Easements under the Act of February 5, 1948, 62 Stat. 17, 25 U.S.C. Section 323,
underlying any or all Project land rights, and to take and perform all necessary
acts in making and filing such Application, and

BE IT HEREBY FURTHER RESOLVED that the Board of Directors of Salt River Project
has and does hereby approve the Memorandum of Agreement



                               SALT RIVER PROJECT

providing for execution of Navajo Station Coal Supply Agreement among it, the
other Co-Owners and Peabody Coal Company together with the Letter Agreement
relating thereto which sets forth additional understandings and agreements
concerning the Navajo Station Coal Supply Agreement, and has and does hereby
authorize, empower and direct that the President or Vice President, and the
Secretary or Assistant Secretary, make, execute, acknowledge and deliver said
Memorandum of Agreement and said Letter of Understanding for and on behalf of
the Salt River Project with such minor changes and omissions therein as
management may make in the premises, and

BE IT HEREBY FURTHER RESOLVED that the Board of Directors of Salt River Project
has and does hereby approve that certain Power Coordination Contract between the
Co-Owners and the United States and has and does hereby authorize, empower and
direct that the President or Vice President, and the Secretary or Assistant
Secretary, make, execute and deliver said Power Coordination Contract for and on
behalf of the Salt River Project with such minor changes and omissions therein
as management may make in the premises, and

BE IT HEREBY FURTHER RESOLVED that, the Board of Directors of Salt River Project
has and does hereby approve the Principles of Interconnected Operation for the
Navajo Project between the Co-Owners, the United States and the Southern
California Edison Company (whether or not said Southern California Edison
Company is party thereto), and does hereby authorize, empower and direct that
the President or Vice President, and the Secretary or Assistant Secretary make,
execute and deliver said Principles of Interconnected Operation for and on
behalf of the Salt River Project with such minor changes and omissions therein
as management may make in the premises, and

BE IT HEREBY FURTHER RESOLVED that the Board of Directors of Salt River Project
has and does hereby approve that certain Contract for Interim Use of United
States Entitlement in the Navajo Project (herein called "Layoff Contract")
between it and the United States and does hereby authorize, empower and direct
that the President or Vice President, and the Secretary or Assistant Secretary,
make, execute and deliver said Layoff Contract for and on behalf of the Salt
River Project with such minor changes and omissions therein as management may
make in the premises, and

BE IT HEREBY FURTHER RESOLVED that the Board of Directors of Salt River Project
has and does hereby approve that certain Memorandum Transmission Agreement
between it, the other Participants, and the Southern California Edison Company,
and has and does hereby authorize, empower and direct that the President or
Vice President, and the Secretary or Assistant Secretary, make, execute and
deliver said



                               SALT RIVER PROJECT

Memorandum Transmission Agreement for and on behalf of the Salt River Project
with such minor changes and omissions therein as management may make in the
premises, and

BE IT HEREBY FURTHER RESOLVED that the Board of Directors of Salt River Project
has and does hereby approve that certain Agreement for Delivery of the United
States Power and Energy for the McCullough Substation to the Mead Substation
between it, the United States and the other Eldorado System Co-Owners (whether
or not such entities become parties thereto), and has and does hereby authorize,
empower and direct that the President or Vice President, and the Secretary or
Assistant Secretary, make, execute and deliver said Agreement for and on behalf
of the Salt River Project with such minor changes and omissions therein as
management may make in the premises, and

BE IT HEREBY FURTHER RESOLVED that the Board of Directors of Salt River Project
has and does hereby approve that certain Spinning Reserve Pooling Agreement
between it, and the other Participants, excepting the City of Los Angeles,
Department of Water and Power (whether or not all such other Participants become
parties thereto), and has and does hereby authorize, empower and direct that the
President or Vice President, and the Secretary or Assistant Secretary, make,
execute and deliver said Spinning Reserve Fueling Agreement for and on behalf of
the Salt River Project with such minor changes and omissions therein as
management may make in the premises.

                                   CERTIFICATE

I, F. E. Smith, the duly appointed, qualified and acting Secretary of the Salt
River Project Agricultural Improvement and Power District, HEREBY CERTIFY that
the foregoing is a true and complete copy of a resolution adopted by the Board
of Directors of said District at a special meeting thereof duly held on the 25th
day of August 1969, at which meeting a quorum was present and voted.

WITNESS my hand and seal of Salt River Project Agricultural Improvement and
Power District this 19th day of November 1969.

                                             /s/ F. E. Smith
                                             -------------------------------
                                                 F. E. Smith, Secretary



                                   CERTIFICATE

      I, Samuel P. Cowley, certify that I am the Secretary of the Nevada Power
Company, a corporation named herein; that Harry Allen who signed the above
contract on behalf of said corporation was then its President; that said
contract was duly signed for and in behalf of said corporation by authority of
its governing body and is within the scope of its corporate powers.

                                             /s/ Samuel P. Cowley
                                             -------------------------------
                                             Samuel P. Cowley, Secretary



                          TUCSON GAS & ELECTRIC COMPANY

                          Certified Copy of Resolutions
                       Adopted by the Board of Directors

            RESOLVED, that the proper officers of the Company be, and they
      hereby are authorized to enter into a Participation Agreement between the
      United States of America, Arizona Public Service Company, Department of
      Water and Power of the City of Los Angeles, Nevada Power Company, Salt
      River Project Agricultural Improvement and Power District and Tucson Gas &
      Electric Company for the ownership of the Navajo Project wherein Tucson
      Gas & Electric Company shall own an undivided 7-1/2% interest in the
      Navajo Generating Station and varying percentage interests in the
      transmission system. The Agreement shall be substantially in the form of
      the draft filed with the Secretary of the Company marked "Filed September
      23, 1969 with the Secretary of Tucson Gas & Electric Company", and be it

            FURTHER RESOLVED, that the proper officers of the Company be, and
      they hereby are further authorized to execute and enter into on behalf of
      the Company the necessary Project Agreements contemplated by said
      Participation Agreement, and such other documents reasonably required to
      implement said Participation Agreement and Project Agreements.

                                 **************

            I, P. L. ABBOTT, Secretary of TUCSON GAS & ELECTRIC COMPANY
      (hereinafter called the "Company"), DO HEREBY CERTIFY that the above and
      foregoing is a true and complete copy of resolutions duly adopted by the
      Board of Directors at the Regular Monthly Meeting held on the 23rd day of
      September, 1969, at which meeting a quorum was present and acted thereon;
      and

            I DO FURTHER CERTIFY that said resolution is in full force and
      effect on the date hereof.

            IN WITNESS WHEREOF, I have hereunto set my hand and affixed the seal
      of the Company this 29th day of September, 1969.

                                           /s/ Authorized Signatory
                                           ------------------------



                                   CERTIFICATE

            I, GERALD J. GRIFFIN, certify that I am an Assistant Secretary of
      ARIZONA PUBLIC SERVICE COMPANY, the corporation named herein; that M. C.
      TITUS, who signed the above contract on behalf of said Corporation was
      then its Executive Vice President; that said contract was duly signed for
      and in behalf of said Corporation by authority of its governing body and
      is within the scope of its corporate powers.

                                             /s/ Gerald J. Griffin
                                             ---------------------------
                                             Assistant Secretary



                          CERTIFIED COPY OF RESOLUTION

      I, GERALD J. GRIFFIN, Assistant Secretary of ARIZONA PUBLIC SERVICE
COMPANY, an Arizona corporation, HEREBY CERTIFY that, at a meeting of the Board
of Directors of said Company, duly convened and held on August 21, 1969, at
which a quorum was present and acting throughout, the following resolution was
adopted and is now in full force and effect:

            RESOLVED, that the Board of Directors approves and ratifies the
      action of the officers in negotiating and carrying forward the proposal
      for the participation by the Company, along with others, in the so-called
      Navajo Project, involving the construction near Page, Arizona, of three
      generating units (presently estimated at 750 MW nameplate), with ownership
      being held as tenants in common in the following respective undivided
      interests:



                                          
Arizona Public Service Company               14.0%
Tucson Gas & Electric Company                 7.5%
City of Los Angeles                          21.2%
Nevada Power Company                         11.3%
Salt River Project Agricultural
   Improvement and Power District (For
   Itself)                                   21.7%
   (As Agent for U.S.B.R.)                   24.3%


      the said project to include certain transmission facilities to be located
      in Arizona, with APS to be the Project Manager and Operating Agent for
      said facilities, which are to be owned by APS and others as joint tenants
      in various percentages related to projected use, these facilities
      including a 500 kv line from the switchyard of the Navajo Plant near Page
      to the Moenkopi Switching Station and from there to the Westwing
      switchyard near Phoenix, and with another 500 kv line extending directly
      from the Navajo switchyard to Westwing, together with various related
      interconnections and switching facilities; and

            FURTHER RESOLVED, that in connection with the Navajo Project, the
      appropriate officers of the Company be, and they are hereby authorized to
      negotiate and to execute and effectuate the necessary instruments and
      agreements, including among others, the following:

                  (1)   Participation Agreement
                  (2)   Coordination Agreement
                  (3)   Interconnection Agreement
                  (4)   Plant Site Lease
                  (5)   Fuel Supply and Transportation
                           Agreement



                                                             RESOLUTION NO.  416

      BE IT RESOLVED by the Board of Water and Power Commissioners of The City
of Los Angeles that the President and the Secretary of this Board be and they
are hereby authorized to execute, on behalf of this Board, certain agreements
relating to the construction, ownership, operation and maintenance of facilities
for the generation of electrical power and energy and related facilities,
including fuel supply, copies of which agreements are on file with the Secretary
of this Board and which are identified as follows, that is:



Agreement Title                                                      DWP Number
- ---------------                                                      ----------
                                                                  
Navajo Project Participation Agreement                                 10334
Memorandum of Agreement Providing for Execution of Navajo              10335
  Station Coal Supply Agreement
Letter Agreement                                                       10336
Application for Federal Rights-of-Way and Easements                    10337
Application and Grant of Rights-of-Way and Easements (25 U.S.C.        10338
 Section 323)
United States, Department of the Interior, Power Coordination          10339
 Contract
Interim Arrangement for Interconnected Operations                      10340
Contract with Department of Water and Power of The City of             10341
 Los Angeles for Interim Sale of United States Entitlement of
 Navajo Project
Memorandum Transmission Agreement                                      10342
Victorville-Lugo Interconnection Agreement                             10343




                   (6)   Co-Tenancy Agreement
                   (7)   Moenkopi Agreement
                   (8)   Amendment to Navajo Wholesale Power Agreement
                   (9)   Plant Construction Agreement
                  (10)   Plant Operating Agreement
                  (11)   Transmission Construction Agreement
                  (12)   Transmission Operating Agreement
                  (13)   Applications for Various Rights-of-Way and Easements
                  (14)   Layoff Agreement

            and

                  FURTHER RESOLVED, that the appropriate officers of the Company
            are authorized to take such actions and to execute such further
            agreements, instruments, applications, certificates, contracts or
            other documents as may be necessary or appropriate in connection
            with the foregoing to complete and effectuate the Company's proposed
            participation in the Navajo Project.

            IN WITNESS WHEREOF, I have hereunto set my hand and the seal of said
      corporation this 3rd day of October, 1969.

                                             /s/ Gerald J. Griffin
                                             ---------------------------
                                             Assistant Secretary

                                      -2-


Agreement Title (Continued)              DWP Number
- --------------------------               ----------
Indenture of Lease                        10344
Letter Agreement                          10350

      I HEREBY CERTIFY that the foregoingis a full, true and correct copy of a
resolution adopted by the Board of Water and Power Commissioners of The City of
Los Angeles at its meeting held NOV 20 1969

                                                  /s/ Mary J. Born
                                                  ------------------------
                                                         Secretary



                              ORDINANCE NO. 139,629

      AN ORDINANCE APPROVING AGREEMENTS RELATING TO PARTICIPATION BY THE
DEPARTMENT OF WATER AND POWER IN THE NAVAJO PROJECT

          THE PEOPLE OF THE CITY OF LOS ANGELES DO ORDAIN AS FOLLOWS:

      Section 1. That the Board of Water and Power Commissioners of The City of
Los Angeles be and it is hereby authorized, in its discretion, to execute and
enter into the following agreements, substantially in the form of those which
are on file with the City Clerk and identified below, relating to the
transmission and use of electrical Power and energy associated with the Navajo
Project:



       AGREEMENT TITLE                                                  DWP NUMBER
- ----------------------------------------------------------------        ----------
                                                                     
Interim Arrangement for Interconnected                                       10340
  Operations
Contrast with Department of Water and Power of The City
  of Los Angeles for Interim Sale of United States, Entitle-
  ment of Navajo Project                                                     10341
Memorandum Transmission Agreement                                            10342
Victorville-Lugo Interconnection Agreement                                   10343
Letter Agreement                                                             10350


      Sec. 2. The City Clerk shall certify to the passage of this ordinance and
cause the same to be published in some daily newspaper printed and published in
the City of Los Angeles.

      I hereby certify that the foregoing ordinance was introduced at the
meeting of the Council of the City of Los Angeles of November 10, 1969 and was
passed at its meeting of November 17, 1969.

                                                    REX E.  LAYTON.  City Clerk,
                                                        By M. B. Wilson, Deputy.
Approved November 18, 1969.
File No. 147173 Sup #1                                      SAM YORTY, Mayor.

                               (E54726) Nov 19 It

                                  CERTIFICATION

STATE OF CALIFORNIA,
                        }   ss.
COUNTY OF LOS ANGELES,

      I, REX E. LAYTON, City Clerk of the City of Los Angeles and ex-officio
Clerk of the City Council of the City of Los Angeles, do hereby certify and
attest the foregoing to be a full, true and correct copy of the original
Ordinance No. 139,629 of the City of Los Angeles,

- --------------------------------------------------------------------------------

- --------------------------------------------------------------------------------

- --------------------------------------------------------------------------------

on file in my office, and that I have carefully compared the same with the
original.

                     IN WITNESS WHEREOF, I have hereunto set my hand and affixed
                     the Seal of the City of Los Angeles, this 19th day
                     of November, 1969
                                                 /s/ Rex E. Layton
                                        ----------------------------------------
                                        City Clerk of the City of  Los Angeles

                                     By /s/ Authorized Signatory
                                        ----------------------------------------
Form Clerk 22 -- 5M -- 11-68 (R)                          Deputy



                              ORDINANCE NO. 139,630

      AN ORDINANCE APPROVING AGREEMENTS RELATING TO PARTICIPATION BY THE
DEPARTMENT OF WATER AND POWER IN THE NAVAJO PROJECT

          THE PEOPLE OF THE CITY OF LOS ANGELES DO ORDAIN AS FOLLOWS:

      Section 1. That the Board of Water and Power Commissioners of The City of
Los Angeles be and it is hereby authorized in its discription, to execute and
enter into the following agreements, substantially in the form of those which
are on file with the City Clerk and identified below, relating to the
construction, ownership, operation and maintenance of facilities for generation
of electrical power and energy and related facilities, including fuel supply:



       AGREEMENT TITLE                                                  DWP NUMBER
- ----------------------------------------------------------------        ----------
                                                                     
Navajo  Project Participation Agreement                                      10384
Memorandum of Agreement Providing for Execution of
Navajo Station Coal Supply Agreement                                         10385
Letter Agreement                                                             10386
Application for Federal Rights-of-Way and Easements                          10387
Grant of Federal Rights-of-Way and Eassements                                10388
United States Department of the Interlor, Power Coor-
 dination Contract                                                           10339
Indenture of Lease                                                           10344


      Sec. 2. The City Clerk shall certify to the passage of this ordinance and
cause the same to be published in some daily newspaper printed and published in
the City of LOS Angeles.

      I hereby certify that the foregoing ordinance was introduced at the
meeting of the Council of the City of Los Angeles, of November , 10, 1965 and
was passed at its meeting of November 17, 1968.

                                                       REX E. LAYTEN City Clerk,
                                                        By M. B. Wilson, Deputy.
Approved November 18, 1969.
File No. 147178                                                SAM YORTY, Mayor.
                               (E54727) Nov 19 It

                                  CERTIFICATION

STATE OF CALIFORNIA,
                        } ss.
COUNTY OF LOS ANGELES,

      I, REX E. LAYTON, City Clerk of the City of Los Angeles and ex-officio
Clerk of the City Council of the City of Los Angeles, do hereby certify and
attest the foregoing to be a full, true and correct copy of the original
Ordiance No. 139,630 of the City of Los Angeles,

- --------------------------------------------------------------------------------

- --------------------------------------------------------------------------------

- --------------------------------------------------------------------------------

on file in my office, and that I have carefully compared the same with the
original.

                     IN WITNESS WHEREOF, I have hereunto set my hand and affixed
                     the Seal of the City of Los Angeles, this 19th day
                     of  November, 1969

                                                /s/ REX E. LAYTON
                                         --------------------------------------
                                         City Clerk of the City of  Los Angeles

                                        By  /s/ Authorized Signatory
                                            ------------------------------------
 Form Clerk 22 -- 5M -- 11-68 (R)                     Deputy


                                    ORIGINAL

                       Southern California Edison Company

                                 P. O. BOX 351

                         LOS ANGELES, CALIFORNIA 90053

                                 October 3, 1969

ARIZONA PUBLIC SERVICE COMPANY

DEPARTMENT OF WATER AND POWER OF THE
CITY OF LOS ANGELES, BY THE BOARD
OF WATER AND POWER COMMISSIONERS

NEVADA POWER COMPANY

SALT RIVER PROJECT AGRICULTURAL
IMPROVEMENT AND POWER DISTRICT

TUCSON GAS & ELECTRIC COMPANY

Gentlemen:

      This letter will confirm the agreement reached in. the course of
negotiations of the Memorandum Transmission Agreement between the Participants
in the Navajo Project and Southern California Edison Company, concerning the
liability provisions to be agreed upon by the non-Federal parties to such
Memorandum Transmission Agreement. These provisions are to be in effect among
such non-Federal parties concerning the disposition of certain liabilities
arising out of the operations of their respective electric systems. It is agreed
that the following liability provisions will apply to the Memorandum
Transmission Agreement and that the reference to "Party" and "Parties" therein
shall mean a party or the parties to the Memorandum Transmission Agreement other
than The United States of America.

6. LIABILITY

      6.1   Except for any loss, damage, claim, cost, charge or expense
            resulting from Willful Action, no Party (First Party), its
            directors, officers, or employees, shall be liable to any other
            Party (Second Party) for any loss, damage, claim, cost, charge or
            expense of any kind or nature incurred by any Second Party
            (including direct, indirect,


                                      - 2 -

            or consequential loss, damage, claim, cost, charge or expense; and
            whether or not resulting from the negligence of any Party, its
            directors, officers, employees, or any other person or entity whose
            negligence would be imputed to such Party) from (i) engineering,
            repair, supervision, inspection, testing, protection, operation,
            maintenance, replacement, reconstruction, use or ownership of First
            Party's electric system,or (ii) the performance or non-performance
            of the obligations of any Party under this Memorandum Transmission
            Agreement. Except for any loss, damage, claim, cost, charge or
            expense resulting from Willful Action, each Second Party releases
            each other First Party, its directors, officers, and employees, from
            any such liability.

      6.2   Except for liability resulting from Willful Action, any Party whose
            electric customer shall make a claim or bring an action for any
            death, injury, loss or damage arising out of electric service to
            such customer, shall indemnify and hold harmless all other Parties,
            their directors, officers, and employees, from and against any
            liability for such death, injury, loss or damage. The term "electric
            customer" shall mean an electric consumer to whom no power is
            delivered for resale.

      6.3   Each Party shall be responsible for the consequences of



                                      - 3 -

            its Willful Action, and shall indemnify and save harmless the other
            Parties, their directors, officers, and employees, from the
            consequences thereof.

      6.4   The term "Willful Action" as used in this Section 6 is defined as
            follows:

            6.4.1 Action taken or not taken by a Party at the direction of its
                  directors, officers, or employees, having management or
                  administrative responsibility affecting its performance under
                  the Memorandum Transmission Agreement, which action is
                  knowingly or intentionally taken or failed to be taken with
                  conscious indifference to the consequences thereof, or with
                  intent that injury or damage would result or would probably
                  result therefrom. Willful Action does not include any act or
                  failure to act which is merely involuntary, accidental or
                  negligent.

            6.4.2 Action taken or not taken by a Party at the direction of its
                  directors, officers, or employees, having management or
                  administrative responsibility affecting its performance under
                  the Memorandum Transmission Agreement, which action has been
                  determined by final arbitration award or final judgment or
                  judicial decree to be a material default under the Memorandum
                  Transmission Agreement


                                     - 4 -

                  and which occurs or continues beyond the time specified in
                  such arbitration award or judgment or judicial decree for
                  curing such default, or, if no time to cure is specified
                  therein, occurs or continues thereafter beyond a reasonable
                  time to cure such default.

            6.4.3 Action taken or not taken by a Party at the direction of its
                  directors, officers, or employees, having management or
                  administrative responsibility affecting its performance under
                  the Memorandum Transmission Agreement, which action is
                  knowingly or intentionally taken or failed to be taken with
                  the knowledge that such action taken or failed to be taken is
                  a material default under any Project Agreements.

            6.4.4 The phrase "employees having management or administrative,
                  responsibility" as used in this Section 6.4 means employees of
                  a Party who are responsible for one or more of the executive
                  functions of planning, organizing, coordinating, directing,
                  controlling and supervising such Party's performance under
                  this Memorandum Transmission Agreement.

      It is understood and agreed that as between The United States of America
and one or more of the non-Federal parties, liabilities within the purview of
Section 6 of the Memorandum Transmission Agreement shall be governed by the
provisions of Section 6 in such agreement, but that liability of one non-Federal
party to one or more other non-Federal parties to the Memorandum Transmission



                                      - 5 -

Agreement that are within the purview of Section 6 as set forth in this letter
agreement shall be governed by the Section 6 herein.

      Will you please signify your agreement to the terms and conditions of this
letter by executing the appropriate acceptance provisions hereof.

                                             Very truly yours,

 APPROVED AS TO FORM:
ROLLIN E. WOODBURY                           SOUTHERN CALIFORNIA EDISON COMPANY
Vice President & General Counsel

By /s/ David Barry
   ----------------------------
        Assistant Counsel

   10-3, 1969

                                             By /s/ William R. Gould
                                                ----------------------------
                                                Senior Vice President

     The terms and conditions of this letter are agreed to this 31st day of
October, 1969.

                              ARIZONA PUBLIC SERVICE COMPANY
                              By  /s/ MC Titus
                                  ----------------------------
                              Title   Executive Vice President

DEPARTMENT OF WATER AND POWER OF THE CITY OF LOS ANGELES, BY THE BOARD OF WATER
AND POWER COMMISSIONERS OF THE CITY OF LOS ANGELES

/s/ Authorized Signatory
- ------------------------
                              By  /s/ Authorized Signatory
                                  ----------------------------
                                  President

                              And /s/ Authorized Signatory
                                  ----------------------------
                                           Secretary

                             NEVADA POWER COMPANY

                              By  /s/ Authorized Signatory
                                  ----------------------------
                              Title President


                                      - 6 -

                              SALT RIVER PROJECT AGRICULTURAL
                              IMPROVEMENT AND POWER DISTRICT

                              By  /s/ Authorized Signatory
                                  --------------------------------
                              Title President

                              TUCSON GAS & ELECTRIC COMPANY

                              By  /s/ J. Luther Davies
                                  --------------------------------
                              Title President




                                                    Contract No. 14-06-300-2140

                       MEMORANDUM TRANSMISSION AGREEMENT

                                     between

                       PARTICIPANTS IN THE NAVAJO PROJECT

                                       and

                       SOUTHERN CALIFORNIA EDISON COMPANY


                                                                    DWPNO. 10342


                        MEMORANDUM TRANSMISSION AGREEMENT

                                TABLE OF CONTENTS



SECTION                                                  PAGE
- -------                                                  ----
                                                   
1             PARTIES                                       1

2             RECITALS                                      1

3             AGREEMENT                                     3

4             TRANSMISSION PRINCIPLES                      14

5             SUBSEQUENT AGREEMENTS                        16

6             LIABILITY AND INSURANCE                      16

7             ARBITRATION                                  19

8             EFFECTIVE DATE                               21

9             REGULATORY APPROVAL                          21

10            AGREEMENT SUBJECT TO COLORADO
                RIVER COMPACT                              22

11            AUTHORIZED REPRESENTATIVES OF THE            22
                PARTIES

12            GENERAL POWER CONTRACT PROVISIONS            22




                        MEMORANDUM TRANSMISSION AGREEMENT

1.    PARTIES

            The Parties to this Memorandum Transmission Agreement are: ARIZONA
      PUBLIC SERVICE COMPANY, an Arizona corporation ("Arizona"); DEPARTMENT OF
      WATER AND POWER OF THE CITY OF LOS ANGELES, a department organized and
      existing under the charter of the City of Los Angeles, a municipal
      corporation of the State of California ("Los Angeles"); NEVADA POWER
      COMPANY, a Nevada corporation ("Nevada"); SALT RIVER PROJECT AGRICULTURAL
      IMPROVEMENT AND POWER DISTRICT, an agricultural improvement district
      organized and existing under the laws of the State of Arizona ("Salt River
      Project"); TUCSON GAS & ELECTRIC COMPANY, an Arizona corporation
      ("Tucson"); THE UNITED STATES OF AMERICA ("United States") represented by
      the officer executing this Memorandum Transmission Agreement, his duly
      appointed successor or duly authorized representative ("contracting
      officer"); all of the above collectively referred to as the
      "Participants"; and SOUTHERN CALIFORNIA EDISON COMPANY, a California
      corporation ("Edison").

2.    RECITALS

            This Memorandum Transmission Agreement is made with reference to the
      following facts, among others:

      2.1   Edison and Arizona entered into the Edison-Arizona



      Transmission Agreement dated July 20, 1966, and Amendment No. 1 thereto
      dated August 26, 1966, covering the terms and conditions of the
      construction, ownership, operation and maintenance of a 500-kv
      transmission line from the Four Corners Generating Station to the Eldorado
      Substation, and the Moenkopi Switchyard (hereinafter referred to as the
      "Edison-Arizona Transmission System").

      2.2   The Participants have entered into the Navajo Project Participation
            Agreement, which provides for the construction, ownership, operation
            and maintenance of the Navajo Project, including the Transmission
            System.

      2.3   The Transmission System will include the following transmission
            lines and related switchyard and substation facilities:

                  Navajo -        McCullough                     500-kv line
                  Navajo -        Moenkopi                       500-kv line
                  Navajo -        Phoenix Area                   500-kv line
                  Moenkopi -      Phoenix Area                   500-kv line

      2.4   The Transmission System will operate interconnected with the
            Edison-Arizona Transmission System.

      2.5   The Parties desire to provide series capacitors ("Project Series
            Capacitors") in the Transmission System and the Edison-Arizona
            Transmission System, which will enable said systems to transmit
            power in an amount equivalent to the Participants' entitlements

                                      -2-


            in the Navajo Generating Station, including the Central Arizona
            Project pumping requirements, to their respective delivery points.

      2.6   The Parties desire to provide series capacitors ("Incremental Series
            Capacitors"), in addition to those referred to in Section 2.5 above,
            which will provide an incremental amount of transmission capacity
            on both the Navajo-McCullough 500-kv line and the Moenkopi-Eldorado
            500-kv line between Moenkopi Switchyard and Eldorado Substation
            equal to the Edison Moenkopi Delivery (defined in Section 2.7
            hereof).

      2.7   The United States desires to sell to Edison for delivery to Edison
            at Moenkopi Switchyard a portion of its entitlement to power from
            the Navajo Generating Station in accordance with provisions of the
            Contract with Edison of even date for Interim Sale of United States
            Entitlement in Navajo Project (such portion herein referred to as
            the "Edison Moenkopi Delivery").

3.    AGREEMENT

            The Parties agree as follows:

      3.1   Arizona shall furnish, install, own, operate and maintain:

            3.1.1 Project Series Capacitors and associated equipment located in
                  the Moenkopi Switchyard

                                      -3-


                  on the Moenkopi-Eldorado 500-kv line.

            3.1.2 Incremental Series Capacitors and associated equipment located
                  in the Moenkopi Switchyard on the Moenkopi-Eldorado 500-kv
                  line.

      3.2   Edison shall furnish, install, own, operate and maintain:

            3.2.1 Project Series Capacitors and associated equipment in the
                  Eldorado Substation on the Moenkopi-Eldorado 500-kv line.

            3.2.2 Incremental Series Capacitors and associated equipment in the
                  Eldorado Substation on the Moenkopi-Eldorado 500-kv line, and
                  Edison shall assume the cost thereof.

      3.3   Arizona shall furnish, install, own, operate and maintain Project
            Series Capacitors and associated equipment in the Moenkopi
            Switchyard on the Navajo-Moenkopi 500-kv line.

      3.4   Arizona shall furnish, install, own, operate and maintain Project
            Series Capacitors, shunt reactors and associated equipment in the
            Moenkopi Switchyard on the Moenkopi-Phoenix Area 500-kv line.

      3.5   Arizona shall furnish, install, own, operate and maintain Project
            Series Capacitors and associated equipment in both the Four Corners
            Switchyard and the Moenkopi Switchyard on the Four Corners-Moenkopi
            500-kv line.

                                      -4-


      3.6   Arizona shall furnish, install, own, operate and maintain Project
            Series Capacitors and associated equipment in the Cholla Switchyard
            and Pinnacle Peak Substation on the Cholla-Pinnacle Peak 345-kv
            lines.

      3.7   Arizona shall furnish, install, own, operate and maintain power
            circuit breakers and related equipment (excluding series capacitors,
            shunt reactors and associated equipment) in the Moenkopi Switchyard
            for the interconnection of the Transmission System and the
            Edison-Arizona Transmission System.

      3.8   Participants in the Navajo-McCullough 500-kv line
            ("Navajo-McCullough Participants") shall furnish, install, operate
            and maintain at their cost Project Series Capacitors, shunt reactors
            and associated equipment at the terminals of the Navajo-McCullough
            500-kv line, or at the midpoint of said line, or at all such
            locations.

      3.9   The Navajo-McCullough Participants shall furnish, install, operate
            and maintain Incremental Series Capacitors and associated equipment
            at the terminals of the Navajo-McCullough 500-kv line, or at the
            mid-point of said line, or at all such locations.

      3.10  The Navajo-McCullough Participants shall make appropriate financial
            arrangements with Edison to cover the costs incurred by Edison in
            complying with Section 3.2.1 hereof.

                                      -5-


      3.11  The Navajo-McCullough Participants shall make appropriate financial
            arrangements with Arizona to cover the costs incurred by Arizona in
            complying with Section 3.1.1 hereof.

      3.12  The Participants shall make appropriate financial arrangements with
            Arizona to cover the costs incurred by Arizona in complying with
            Sections 3.3 and 3.7 hereof.

      3.13  The Participants in Moenkopi-Phoenix Area 500-kv line (hereinafter
            referred to as the "Moenkopi-Phoenix Area Participants") shall
            make appropriate financial arrangements with Arizona to cover the
            costs incurred by Arizona in complying with Sections 3.4, 3.5 and
            3.6 hereof.

      3.14  Edison shall make appropriate financial arrangements with Arizona to
            cover the costs incurred by Arizona in complying with Section 3.1.2
            hereof.

      3.15  Edison shall make appropriate financial arrangements with the
            Participants to cover the costs incurred by the Participants in
            complying with Section 3.9 hereof.

      3.16  The phrase "make appropriate financial arrangements" as used in
            Sections 3.10 through 3.15 hereof, shall mean one of two alternates:

            3.16.1 A contribution in aid of construction for the equipment to be
                  furnished and installed

                                      -6-


                   and a mutually agreed monthly payment to cover all costs
                   other than depreciation and return on investment.

            3.16.2 A monthly payment; substantially in accordance with present
                   formula and schedules of the Edison-Arizona Transmission
                   Agreement.

            Within one year after the effective date of this Memorandum
            Transmission Agreement, each Participant with a financial obligation
            hereunder shall choose either of the above described alternates.

      3.17  In lieu of the payment options provided in Section 3.16 hereof, the
            Parties may exchange obligations or property by mutual agreement of
            such Parties.

      3.18  Arizona's charges to the Parties to cover all costs other than
            depreciation and return on investment incurred in connection with
            the Moenkopi Switchyard (including all series capacitors, shunt
            reactors and associated equipment) shall be billed in proportion to
            the initial gross investment in the Moenkopi Switchyard for which
            they are responsible under the provisions of the Edison-Arizona
            Transmission Agreement in the case of Edison and under the
            provisions of the Participation Agreement in the case of the
            Participants.

      3.19  Edison and the Navajo-McCullough Participants shall each provide
            reciprocal emergency service rights in

                                      -7-




      accordance with this Section 3.19 for which there shall be no charge made
      by Edison to the Navajo-McCullough Participants, or by the
      Navajo-McCullough Participants to Edison.

      3.19.1 In the event of an outage of the Navajo-McCullough 500-kv line or
             associated terminal facilities, subject to Section 3.19.3 hereof,
             (i) the Navajo-McCullough Participants shall be entitled to have an
             amount of power equivalent to their entitlement in the Navajo
             Generating Station, less transmission losses, transmitted between
             said station and McCullough Substation over the Moenkopi-Eldorado
             and Eldorado-McCullough 500-kv lines and associated terminal
             facilities; provided that, for the purposes of computing such
             entitlements, the entitlement of the United States shall be deemed
             to be 250/561 of the United States' entitlement in the Navajo
             Generating Station; and (ii) Edison shall be entitled to have an
             amount of power equivalent to its entitlement of 48% of the net
             effective generating capacity of Four Corners Units 4 and 5 plus an
             amount of power equal to the Edison Mocnkopi Delivery,

                                      -8-



             less transmission losses, transmitted between the Moenkopi
             Switchyard and the Eldorado Substation over the Moenkopi-Eldorado
             500-kv line and associated terminal facilities.

      3.19.2 In the event of an outage of the Moenkopi-Eldorado 500-kv line or
             associated terminal facilities, subject to Section 3.19.3 hereof,
             (i) Edison shall be entitled to have an amount of power equivalent
             to its entitlement of 48% of the net effective generating capacity
             of Four Corners Units 4 and 5 plus an amount of power equal to the
             Edison Moenkopi Delivery, less transmission losses, transmitted
             between the Moenkopi Switchyard and the Eldorado Substation over
             the Navajo-Moenkopi, Navajo-McCullough and Eldorado-McCullough
             500-kv lines and associated terminal facilities; and (ii) the
             Navajo-McCullough Participants shall be entitled to have an amount
             of power equivalent to their entitlement in the Navajo Generating
             Station, less transmission losses, transmitted between said station
             and the McCullough Substation over the Navajo-McCullough 500-kv
             line and associated

                                      -9-



             terminal facilities; provided, that, for the purposes of computing
             such entitlements, the entitlement of the United States shall be
             deemed to be 250/561 of the United States' entitlement in the
             Navajo Generating Station.

      3.19.3 Unless otherwise agreed upon by the system dispatchers of Edison
             and the Navajo-McCullough Participants, in the event of an outage
             of the Navajo-McCullough 500-kv line or the Moenkopi-Eldorado
             500-kv line, the Navajo-McCullough Participants and Edison shall
             reduce transmission of power and associated energy within one-half
             hour after the occurrence of such outage so that the scheduled
             delivery over the remaining in-service line does not exceed 1,000
             megawatts. Said 1,000 megawatt limitation may be changed from time
             to time by mutual agreement of the authorized representatives of
             Edison and the Navajo-McCullough Participants. The entitlement of
             each Navajo-McCullough Participant to capacity in the remaining
             in-service transmission line shall be equal to the capacity of such
             remaining in-service line as established above times the ratio that
             such Participant's

                                      -10-



            entitlement in the Navajo Generating Station bears to the total
            capability described in Section 3.26 hereof. Edison's entitlement to
            capacity in the remaining in-service transmission line shall be
            equal to the capacity of such remaining in-service line as
            established above times the ratio that Edison's entitlement of 48%
            of the net effective generating capacity of Four Corners Units 4 and
            5 and the Edison-Moenkopi Delivery bears to the total capability
            described in Section 3.26 hereof. For the purposes of this Section
            3.19.3, the entitlement of the United States in the Navajo
            Generating Station shall be deemed to be 250/561 of its entitlement
            in the Navajo Generating Station.

      3.20  Equitable adjustment for transmission losses in the Edison-Arizona
            Transmission System and the Transmission System shall be agreed upon
            between Edison and the Participants.

      3.21  Edison and the Participants shall coordinate the design of the
            Transmission System, the additions to the Edison-Arizona
            Transmission System, and any interconnections thereto, including
            criteria related to line loading, series capacitor ratings and
            similar matters.

                                      -11-



      3.22  Arizona shall transmit for Edison between the Moenkopi Switchyard
            and the Colorado River over the Edison-Arizona Transmission System
            an amount of electric power equal to the Edison Moenkopi Delivery.

      3.23  The ownership interests and cost responsibilities of the
            Participants for the facilities to be installed pursuant to this
            Memorandum Transmission Agreement shall be as provided in the Navajo
            Project Agreements.

      3.24  The Participants shall have the right to transmit power in an amount
            equivalent to their entitlements in the Navajo Generating Station
            through the Moenkopi Switchyard.

      3.25  The Navajo-McCullough 500-kv line and the Moenkopi-Eldorado 500-kv
            line will be interconnected at each end through other facilities,
            and under normal operating conditions said two lines will be
            operated in parallel as a system.

      3.26  For the purposes of this Agreement, the total capability of the
            system described in Section 3.25 hereof shall be deemed to be an
            amount equivalent to the sum of: (i) the sum of the entitlements of
            Nevada and Los Angeles in the Navajo Generating Station and 250/561
            of the entitlement of the United States in the Navajo Generating
            Station; (ii) the Edison entitlement in Four Corners Units 4 and 5,

                                      -12-



            which is 48% of the net effective generating capacity of said units;
            and (iii) the Edison Moenkopi Delivery.

      3.27  In the event that the Navajo-McCullough Participants desire to
            schedule delivery of power over the Navajo-McCullough 500-kv line in
            an aggregate amount in excess of the amount described in Section
            3.26(i) hereof or Edison desires to schedule delivery of power over
            the Moenkopi-Eldorado 500-kv line in an amount in excess of the sum
            of the amounts described in Sections 3.26(ii) and 3.26(iii) hereof,
            the Navajo-McCullough Participants and Edison shall conduct
            engineering studies to determine the capability of the system
            described in Section 3.25 hereof to deliver such additional power.
            The deemed capability of said system as established in Section 3.26
            hereof may be changed upon mutual agreement of all the
            Navajo-McCullough Participants and Edison.

      3.28  Until such time as the United States recaptures all of the Edison
            Moenkopi Delivery, the Navajo-Phoenix Area Participants shall not
            schedule power over the Transmission System in an amount which is in
            excess of the sum of their entitlements in the Navajo Generating
            Station without the mutual agreement of the Navajo-Phoenix Area
            Participants and Edison.

      3.29  The Participants shall have the right  to interconnect

                                      -13-



            their systems with the Transmission System at their designated
            points of delivery for the purpose of transmitting power in amounts
            equivalent to their entitlements in the Navajo Generating Station.

      3.30  Except as provided in Section 3.29 hereof, the Participants shall
            not interconnect the Transmission System with their systems or
            permit any third party to interconnect the Transmission System with
            its system in a manner which would unreasonably jeopardize or
            unreasonably impair the operation by Edison and Arizona of the
            Edison-Arizona Transmission System.

      3.31  Edison and Arizona shall not interconnect the Edison-Arizona
            Transmission System with their systems or permit any third party to
            interconnect the Edison-Arizona Transmission System with its system
            in a manner which would unreasonably jeopardize or unreasonably
            impair the operation of the Transmission System.

4.    TRANSMISSION PRINCIPLES

      4.1   Each Party shall, independently of the transmission capacity
            otherwise maintained by others, maintain in its system, or between
            its system and the system of other Parties or other entities,
            sufficient capacity, by ownership or contract, which will permit it
            to transmit all power and energy introduced

                                      -14-




            into its system to meet its own commitments and to fulfill its
            written obligations, if any, to provide transmission service for
            other Parties or other entities, regardless of the origin, source,
            ownership or type of generation used to produce such power and
            energy.

      4.2   It is recognized that flows of electric energy may occur through
            interconnections between the systems of the Parties as a result of
            parallel operation of the systems of the Parties with each other and
            with other entities. Each Party shall use its best efforts at all
            times to maintain as nearly as practicable the scheduled quantities
            of power and energy into and out of the control area containing its
            system.

      4.3   The Parties agree that, should differences arise between them
            regarding the implementation of the foregoing principles, they will
            seek an equitable solution and, if necessary, will perform joint
            technical studies in an effort to agree upon (i) the amounts of
            power that can be scheduled and transmitted on their systems or
            between one Party's system and the systems of other Parties or other
            entities in accordance with the principles of Section 4.1 hereof, or
            (ii) upon whether any Party has been in violation of Section 4.2
            hereof. In

                                      -15-



            the event such agreement cannot be reached, the matter shall be
            submitted to arbitration, subject to and in accordance with the
            provisions of Section 7 hereof, and in accordance with guidelines to
            be established by the Parties for purposes of determining each
            particular dispute.

5.    SUBSEQUENT AGREEMENTS

      5.1   The Parties intend that the obligations and principles of this
            Memorandum Transmission Agreement will be implemented by definitive
            agreements, including appropriate amendments to the Edison-Arizona
            Transmission Agreement, which will be negotiated in good faith and
            executed by the applicable Parties. In the event that all required
            definitive agreements are not consummated, the Parties agree that
            this Memorandum Transmission Agreement shall serve as the basis for
            requiring the performance of all obligations herein set forth,
            subject to the terms and conditions herein set forth.

6.    LIABILITY AND INSURANCE

      6.1   The Parties agree to use their best efforts to obtain a policy or
            policies of liability insurance with cross liability endorsements
            specifically limited to protecting the Parties from claims and
            liabilities inter se arising out of the interconnected operation
            provided for in the Memorandum

                                      -16-



            Transmission Agreement.

      6.2   Except for any damage resulting from Willful Action, and except to
            the extent of any damage covered by valid and collectible insurance,
            if any, described in Section 6.1 hereof, and as between the
            Participants, except to the extent of any damage covered by valid
            and collectible Project Insurance as defined in the Navajo Project
            Participation Agreement, liability on the part of any Party (First
            Party), or any of its directors, officers or employees, for any
            damage to any Party (Second Party) whether or not caused by
            negligence, which occurs as the result of performance or
            non-performance of its responsibilities under this Memorandum
            Transmission Agreement may not be collected from the Party (First
            Party), or any of its directors, officers or employees, by any
            action in law or equity by the Party (Second Party).

      6.3   Except for liability resulting from Willful Action, any Party whose
            electric customer shall make a claim or bring an action for any
            death, injury, loss or damage arising out of electric service to
            such customer, shall indemnify and hold harmless all other Parties,
            their directors, officers and employees, from and against any
            liability for such death, injury, loss or damage. The term "electric

                                      -17-



            customer" shall mean an electric customer to whom no power is
            delivered for resale.

      6.4   Each Party shall be responsible for the consequences of its own
            Willful Action, and shall indemnify and save harmless the other
            Parties from the consequences thereof.

      6.5   The term "Willful Action" as used in this Section 6 is defined as
            follows:

            6.5.1 Action taken or not taken by a Party at the direction of its
                  directors, officers, contracting officer, or employees, having
                  management or administrative responsibility affecting its
                  performance under the Memorandum Transmission Agreement, which
                  action is knowingly or intentionally taken or failed to be
                  taken with conscious indifference to the consequences thereof,
                  or with intent that injury or damage would result or would
                  probably result therefrom. Willful Action does not include any
                  act or failure to act which is merely involuntary, accidental
                  or negligent.

            6.5.2 Action taken or not taken by a Party at the direction of its
                  directors, officers, contracting officer, or employees, having
                  management or administrative responsibility affecting its
                  performance under the Memorandum

                                      -18-



                  Transmission Agreement, which action has been determined by
                  final arbitration award or final judgment or judicial decree
                  to be a material default under the Memorandum Transmission
                  Agreement and which occurs or continues beyond the time
                  specified in such arbitration award or judgment or judicial
                  decree for curing such default, or, if no time to cure is
                  specified therein, occurs or continues thereafter beyond a
                  reasonable time to cure such default.

            6.5.3 Action taken or not taken by a Party at the direction of its
                  directors, officers, contracting officer, or employees, having
                  management or administrative responsibility affecting its
                  performance under the Memorandum Transmission Agreement, which
                  action is knowingly or intentionally taken or failed to be
                  taken with the knowledge that such action taken or failed to
                  be taken is a material default under this agreement.

            6.5.4 The phrase "employees having management or administrative
                  responsibility" as used in this Section 6.5 means employees of
                  a Party who are responsible for one or more of the executive
                  functions of planning, organizing,

                                      -19-





                  coordinating, directing, controlling and supervising such
                  Party's performance under this Memorandum Transmission
                  Agreement.

7.  ARBITRATION

      7.1   If a dispute between any of the Parties should arise under this
            Memorandum Transmission Agreement which does not involve the legal
            rights of or which will not create a legal obligation upon the
            United States under this Memorandum Transmission Agreement, or will
            not affect the interests or rights held for the use and benefit of
            the United States under the applicable Navajo Project Agreements,
            any Party may call for submission of the dispute to arbitration,
            which call shall be binding upon all of the other Parties. Except
            as specifically provided in an applicable agreement, the
            arbitration shall be governed by the rules and practices of the
            American Arbitration Association. The award of the arbitrators shall
            be final and binding upon the Parties, and the costs and expenses
            of the arbitrators shall be shared equally by the Parties
            participating in the arbitration, unless otherwise decided by the
            arbitrators.

      7.2   If a dispute arises between any of the Parties which does or may
            involve the legal rights of or which will or may create a legal
            obligation upon the United States under this Memorandum Transmission
            Agreement,

                                      -20-


            or which affects or may affect the interests or rights held for the
            use and benefit of the United States under the applicable Navajo
            Project Agreements, then any Party may call for submission to
            arbitration of any part of the dispute, issue or action related
            thereto which the United States may lawfully submit to arbitration.
            If the contracting officer agrees to such arbitration, or if the
            contracting officer refuses or fails to arbitrate and a court of
            competent jurisdiction thereafter finally decides that the United
            States may lawfully submit the matter in dispute to arbitration, it
            shall be conducted in the manner set forth in this Section 7, or in
            such other manner as may be provided for by Federal law.

8.    EFFECTIVE DATE

            This Memorandum Transmission Agreement shall become effective when
      it has been duly executed and delivered on behalf of the Parties.

9.    REGULATORY APPROVAL

      9.1   This Memorandum Transmission Agreement shall be subject to filing
            with, and to such changes or modifications as may from time to time
            be directed by, competent regulatory authority, if any, in the
            exercise of its jurisdiction.

                                      -21-


10.   AGREEMENT SUBJECT TO COLORADO RIVER COMPACT

      10.1  This agreement is made upon the express condition and with the
            express understanding that all rights hereunder shall be subject to
            and controlled by the Colorado River Compact, being the compact or
            agreement signed at Santa Fe, New Mexico, November 24, 1922,
            pursuant to Act of Congress approved August 19, 1921, entitled "An
            Act to permit a compact or agreement between the States of Arizona,
            California, Colorado, Nevada, New Mexico, Utah and Wyoming
            respecting the disposition and apportionment of the waters of the
            Colorado River, and for other purposes", which Compact was approved
            in Section 13(a) of the Boulder Canyon Project Act.

11.   AUTHORIZED REPRESENTATIVES OF THE PARTIES

      11.1  Each Party and the contracting officer, by written notice to the
            other, shall designate the representative who is authorized to act
            in its and his behalf with respect to those matters contained herein
            which are the functions and responsibilities of the authorized
            representatives of the Parties. Each Party may change the
            designation of its authorized representative upon written notice to
            the other.

12.   GENERAL POWER CONTRACT PROVISIONS

      12.1  The General Power Contract Provisions effective

                                      -22-


            April 27, 1961, with revised Page 2 dated August 7, 1968, revised
            Page 3 dated January 2, 1969, and revised Page 6 dated July 28,
            1969, attached hereto are hereby made a part of this Memorandum
            Transmission Agreement; provided, however, that Provisions A through
            D, F through N, Q through S, V, Y, Z and AA through GG shall not
            apply to this Memorandum Transmission Agreement; and provided that,
            as to Provision P, since Title 42 U.S.C. 2000-e-2(i) provides for
            the giving of preference to Indians in employment on or near an
            Indian Reservation, the obligations of the non-federal Parties under
            Provision P shall be subject to any obligation undertaken by said
            non-federal Parties to give preference to Indians for employment on
            or near an Indian Reservation.

      IN WITNESS WHEREOF, the Parties have caused this Memorandum Transmission
Agreement to be executed as of this 30th day of September, 1969.

                                            THE UNITED STATES OF AMERICA

                                            By /s/ Walter J. Hickel
                                               --------------------------------
                                               Secretary of the Interior

                                               ARIZONA PUBLIC SERVICE COMPANY

ATTEST:                                    By  /s/ M.C. Titus
/s/ Gerald J. Griffin                          --------------------------------
- ----------------------                         EXECUTIVE VICE PRESIDENT
Assistant Secretary

                                      -23-


                          DEPARTMENT OF WATER AND POWER
                           OF THE CITY OF LOS ANGELES

                                       by

By /s/ Donald J. Reisner        Board of Water and Power Commissioners of
- --------------------            the City of Los Angeles

ATTEST:                         By  /s/ Authorized Signatory
                                     -----------------------
/s/ Mary J. Born                     PRESIDENT
- --------------------
Secretary                       NEVADA POWER COMPANY

ATTEST:                         By /s/ Harry Allen
                                   -----------------
/s/ Authorized Signatory           President
- ------------------------
Secretary
                                SALT RIVER PROJECT AGRICULTURAL
                                IMPROVEMENT AND POWER DISTRICT

                                By  /s/ Authorized Signatory
ATTEST:                             ------------------------
                                   President
/s/ Authorized Signatory
- ------------------------
Secretary                       TUSCON GAS AND ELECTRIC COMPANY

                                By  /s/ HR Catlin
                                    ---------------
ATTEST:                             VICE PRESIDENT

/s/ W.D. Brooks
- ------------------------        SOUTHERN CALIFORNIA EDISON COMPANY
ASSISTANT SECRETARY
                                By  /s/ William R. Gould
                                    ----------------------------
                                    SENIOR VICE PRESIDENT
ATTEST:

/s/ Authorized Signatory            [STAMP]
- ------------------------
ASSISTANT SECRETARY                 Approved as to form

                                      -24-










































                                                        Effective April 27, 1961

                    UNITED STATES DEPARTMENT OF THE INTERIOR
                             BUREAU OF RECLAMATION

                       GENERAL POWER CONTRACT PROVISIONS

A.    Characteristics of Power and Energy.

            Electric energy supplied hereunder will be three-phase, alternating
      current, at a nominal frequency of sixty (60) cycles per second.

B.    Delivery of Energy in Excess of Contract Obligation.

            The Contractor may from time to time, in the absence of objection by
      the contracting officer, use energy at rates of power delivery greater
      than the contract rate of delivery in effect for each type of service
      provided for in this contract, but such greater use shall not be deemed to
      establish in the Contractor any right thereto and the Contractor shall
      cease any such greater use whenever and for the periods of time requested
      by the contracting officer. Nothing in this contract contained shall
      obligate or be construed to obligate the United States to increase any
      contract rate of delivery hereunder. If additional power is not available
      from the United States, the responsibility for securing additional power
      shall rest wholly with the Contractor.

C.    Continuity of Electric Service to be Furnished.

            The electric service, unless otherwise specified, will be furnished
      continuously except (1) for interruptions or reductions due to
      uncontrollable forces, as defined herein; (2) for interruptions or
      reductions due to operation of devices installed for power system
      protection; and (3) for temporary interruptions or reductions, which, in
      the opinion of the contracting officer, are necessary or desirable for the
      purposes of maintenance, repairs, replacements, installation of equipment,
      or investigation and inspection. The United States, except in case of
      emergency as determined by the contracting officer, will give the
      Contractor reasonable advance notice of such temporary interruptions or
      reductions and will remove the cause thereof with diligence.

D.    Multiple Points of Delivery.

            When electric service is furnished at two or more points of
      delivery under the same schedule of rates, said schedule of rates shall
      apply separately to the service supplied at each point of delivery;
      Provided, That where the meter readings are considered separately and the
      Contractor's system may be interconnected between points of delivery
      during emergencies, the meter readings at any point of delivery will be
      adjusted when necessary to compensate for duplication of power demand
      recorded by meters at alternate points of delivery due to emergency
      conditions which are beyond the Contractor's control or temporary
      conditions caused by scheduled outages.

E.    Uncontrollable Forces.

            Neither party shall be considered to be in default in respect to any
      obligation hereunder, if prevented from fulfilling such obligation by
      reason of uncontrollable forces, the term uncontrollable forces being
      deemed for the purpose of this contract to mean any cause beyond the
      control of the party affected, including, but not limited to, failure of
      facilities, flood, earthquake, storm, lightning, fire, epidemic, war,
      riot, civil disturbance, labor disturbance, sabotage, and restraint by
      court or public authority, which by exercise of due diligence and
      foresight such party could not reasonably have been expected to avoid.
      Either party rendered unable to fulfill any obligation by reason of
      uncontrollable forces shall exercise due diligence to remove such
      inability with all reasonable dispatch.

F.    Modification of Rates.

            The rate schedule specified in this contract shall be subject to
      successive modification by the United States through the promulgation of
      superseding rate schedules. If at any time the United States promulgates a
      rate schedule superseding the rate schedule then in effect under this
      contract, it will promptly notify the Contractor thereof. Said superseding
      rate schedule, as of its effective date, shall become effective as to this
      contract unless the Contractor, by notice in writing given to the
      contracting officer within 180 days after notice to it by the United
      States of promulgation of said superseding rate schedule, shall elect to
      terminate this contract effective as of such date not more than three (3)
      years subsequent thereto as the Contractor shall therein specify. In the
      event of such termination, said superseding rate schedule shall not be
      effective during the period of the remaining unexpired term of this
      contract or during a period of two years from the date of notice to the
      Contractor of the promulgation of said superseding rate schedule,
      whichever period is shorter.

G.    Minimum Annual Capacity Charge.

            When the rate schedule in effect under this contract provides for a
      minimum annual capacity charge, a statement of the minimum annual capacity
      charge due, if any, shall be included in the bill rendered for electric
      service for the last billing period of each calendar year, appropriately
      adjusted on a pro rata basis if the full billing periods for the
      adjustable items (including increases or decreases in the contract rate of
      delivery) in the calendar year are less than 12. Fractional billing
      periods will not be considered in such determination. Where multiple
      points of delivery are involved and the contract rate of delivery is
      stated to be a maximum aggregate rate of delivery for all points, in
      determining the minimum annual capacity charge due, if any, the monthly
      capacity charges at the individual points of delivery shall be added
      together. If this contract represents a continuation of electric service
      to an existing customer, for the purpose of determining the minimum annual
      capacity charge, (1) the first 24 full billing periods shall begin with
      the date that electric service was first rendered under the same or a
      similar rate schedule in the expired or superseded contracts, and (2) for
      the calendar year in which electric service is begun under this contract,
      the minimum annual capacity charges under this contract and the contracts
      it succeeded or superseded shall be combined into one such charge due at
      the end of said calendar year and the monthly capacity charges during said
      entire calendar year shall be credited against said combined minimum
      annual capacity charge.

H.    Billing and Payments.

            The United States will submit bills to the Contractor on or before
      the tenth day of each month for electric service furnished during the
      preceding month, and payments will be due and payable by the Contractor on
      the first day of the month immediately succeeding the date each bill is
      submitted.

I.    Nonpayment of Bills.

            If the Contractor fails to pay any bill when due an interest charge
      of one per cent (1%) of the amount unpaid shall be added thereto as
      liquidated damages, and thereafter, as further liquidated damages, an
      additional interest charge of one-half of one per cent (1/2%) of the
      principal sum unpaid shall be added on the first day of each succeeding
      calendar month until the amount due, including interest, is paid in full.
      The United States shall have the right upon not less than fifteen (15)
      days' advance written notice to discontinue furnishing electric service to
      the Contractor for nonpayment of bills and to refuse to resume same so
      long as any part of the amount due remains unpaid. Such a discontinuance
      of electric service will


                        GENERAL POWER CONTRACT PROVISIONS

      not relieve the Contractor of liability for the minimum charge during the
      time electric service is so discontinued. The rights given herein to the
      United States shall be in addition to all other remedies available to the
      United States, either at law or in equity, for the breach of any of the
      provisions hereof.

J.    Adjustments for Fractional Billing Period.

            (a) For a fractional part of a billing period at the beginning or
      end of service, and for fractional periods due to withdrawals of service,
      the demand or capacity charge, the kilowatthour blocks of the energy
      charge, and the minimum charge shall each be proportionately adjusted in
      the ratio that the number of hours that electric service is furnished to
      the Contractor in such fractional billing period bears to the total number
      of hours in the billing period involved.

            (b) Whenever irrigation and/or drainage pumping service is supplied
      under this contract, adjustments in the demand or capacity charge and in
      the kilowatthour blocks of the energy charge as applicable, and in the
      minimum charge of the rate schedule under which service is supplied, shall
      be made for the fractional part of the billing period at the beginning and
      end of pumping service in each year in like manner as is provided for in
      section (a) of this article. If pumping service is supplied in conjunction
      with service for other purposes and is not metered separately, the billing
      demand for pumping service shall be considered to be the difference
      between the highest 30-minute integrated demand measured during the
      billing period and the contract rate of delivery for firm power.

K.    Adjustments for Curtailments to Service.

            Unless curtailment of service is due to a request by the customer,
      billing adjustments will be made if the delivery of electric energy is
      curtailed because of conditions on the power system of the United States,
      which system for the purpose of such adjustments hereunder shall include
      transmission facilities utilized but not owned by the United States, for
      periods of one (1) hour or longer in duration each. The total number of
      hours of curtailed service in any billing period shall be determined by
      adding (1) the sum of the number of hours of interrupted service to (2)
      the product of: the number of hours of reduced service multiplied by the
      percentage of said reduction below the lesser of (a) the contract rate of
      delivery, or (b) the obligation of the United States to deliver firm power
      and energy as established under the operating agreement entered into
      pursuant to the Auxiliary Power Service article hereof, or (c) the rate of
      delivery required by the Contractor at the time of such reduction. The
      demand or capacity charge, the kilowatthour blocks of the energy charge,
      and the minimum charge shall each be proportionately adjusted in the ratio
      that the total number of hours of such curtailed service as herein
      determined bears to the total number of hours in the billing period
      involved. The Contractor shall make written claim within thirty (30) days
      after receiving the monthly bill, for adjustment on account of any
      curtailment to service, for periods of one (1) hour or longer in duration
      each, alleged to have occurred and which is not reflected in such bill.
      Failure to make such written claim, within said thirty (30) day period,
      shall constitute a waiver thereof. All curtailments to service, which are
      due to conditions on the power system of the United States, shall be
      subject to the provisions of this article and the Contractor shall be
      limited in its remedy to the relief granted by this article; Provided,
      That withdrawal of power and energy under contract provisions shall not be
      deemed curtailments to service.

L.    Metering.

            (a) The total electric power and energy delivered to the Contractor
      will be measured by metering equipment to be furnished and maintained by
      the United States. Meters shall be sealed and the seals shall be broken
      only upon occasions when the meters are to be inspected, tested, or
      adjusted, and representatives of the Contractor shall be afforded
      reasonable opportunity to be present upon such occasions. Metering
      equipment shall be inspected and/or tested at least once each year by the
      United States and at any reasonable time upon request therefor by either
      party. Any metering equipment found to be defective or inaccurate shall be
      repaired and readjusted or replaced. Should any meter fail to register,
      the electric power and energy delivered during such period of failure to
      register shall, for billing purposes, be estimated by the contracting
      officer from the best information available.

            (b) If any of the inspections and/or tests provided for herein
      disclose an error exceeding two per cent (2%), correction based upon the
      inaccuracy found shall be made of the records of electric service
      furnished since the beginning of the monthly billing period immediately
      preceding the billing period during which the test was made; Provided,
      That no correction shall be made for a longer period than such inaccuracy
      may be determined by the contracting officer to have existed. Any
      correction in billing resulting from such correction in meter records
      shall be made in the next monthly bill rendered by the United States to
      the Contractor, and such correction when made shall constitute full
      adjustment of any claim between the parties hereto arising out of such
      inaccuracy of metering equipment.

M.    Resale of Electric Energy.

            The Contractor shall not sell any of the electric energy delivered
      to it hereunder to any customer of the Contractor for resale by that
      customer.

N.    Power Factor.

            While the Contractor normally will be required to maintain the power
      factor as stated in the rate schedule then in effect under this contract,
      the Contractor will be permitted to operate at a lower power factor when
      conditions are such, as determined by the contracting officer, that a
      lower power factor will be mutually advantageous to the Contractor and to
      the United States.

O.    Cooperation of Contracting Parties.

            (a) If, in the maintenance of their respective power systems end/or
      electrical equipment and the utilization thereof for the purposes of this
      contract, it becomes necessary by reason of any emergency or extraordinary
      condition for either party to request the other to furnish personnel,
      materials, tools, and equipment For the accomplishment thereof, the party
      so requested shall cooperate with the other and render such assistance as
      the party so requested may determine to be available. The party making
      such request, upon receipt of properly itemized bills from the other
      party, shall reimburse the party rendering such assistance for all costs
      properly and reasonably incurred by it in such performance, including not
      to exceed fifteen percent (15%) thereof for administrative and general
      expenses, such costs to be determined on the basis of current charges or
      rates used in its own operations by the party rendering assistance.

                                        2


                        GENERAL POWER CONTRACT PROVISIONS

            (b) This contract shall be subject to all the provisions and
      conditions of the Act of Congress entitled the Work Hours Act of 1962,
      approved August 13, 1962 (76 Stat. 357), which establishes standards for
      hours of work and overtime pay of laborers and mechanics employed on work
      done under contract for, or with the financial aid of, the United States,
      the same as if that Act had been specifically set forth herein.

P. Provisions Relative to Employment

      (1)   During the performance of this contract, the Contractor agrees as
            follows:

            (a)   The Contractor will not discriminate against any employee or
                  applicant for employment because of race, color, religion,
                  sex, or national origin. The Contractor will take affirmative
                  action to ensure that applicants are employed, and that
                  employees are treated during employment, without regard to
                  their race, color, religion, sex, or national origin. Such
                  action shall include, but not be limited to, the following:
                  Employment, upgrading, demotion, or transfer; recruitment or
                  recruitment advertising; layoff or termination; rates of pay
                  or other forms of compensation; and selection for training,
                  including apprenticeship. The Contractor agrees to post in
                  conspicuous places, available to employees and applicants for
                  employment, notices to be provided by the Contracting Officer
                  setting forth the provisions of this Equal Opportunity clause.

            (b)   The Contractor will, in all solicitations or advertisements
                  for employees placed by or on behalf of the Contractor, state
                  that all qualified applicants will receive consideration for
                  employment without regard to race, color, religion, sex, or
                  national origin.

            (c)   The Contractor will send to each labor union or representative
                  of workers with which he has a collective bargaining agreement
                  or other contract or understanding, a notice, to be provided
                  by the agency Contracting Officer, advising the labor union or
                  workers' representative of the Contractor's commitments under
                  this Equal Opportunity clause, and shall post copies of the
                  notice in conspicuous places available to employees and
                  applicants for employment.

            (d)   The Contractor will comply with all provisions of Executive
                  Order No. 11246 of September 24, 1965, and of the rules,
                  regulations, and relevant orders of the Secretary of Labor.

            (e)   The Contractor will furnish all information and reports
                  required by Executive Order No. 11246 of September 24, 1965,
                  and by the rules, regulations, and orders of the Secretary of
                  Labor, or pursuant thereto, and will permit access to his
                  books, records, and accounts by the contracting agency and the
                  Secretary of Labor for purposes of investigation to ascertain
                  compliance with such rules, regulations, and orders.

            (f)   In the event of the Contractor's noncompliance with the Equal
                  Opportunity clause of this contract or with any of the said
                  rules, regulations, or orders, this contract may be canceled,
                  terminated, or suspended, in whole or in part, and the
                  Contractor may be declared ineligible for further Government
                  contracts in accordance with procedures authorized in
                  Executive Order No. 11246 of September 24, 1965, and such
                  other sanctions' may be imposed and remedies invoked as
                  provided in Executive Order No. 11246 of September 24, 1965,
                  or by rule, regulation, or order of the Secretary of Labor, or
                  as otherwise provided by law.

            (g)   The Contractor will include the provisions of paragraphs (a)
                  through (g) in every subcontract or purchase order unless
                  exempted by rules, regulations, or orders of the Secretary of
                  Labor issued pursuant to Section 204 of Executive Order No.
                  11246 of September 24, 1965, so that such provisions will be
                  binding upon each subcontractor or vendor. The Contractor will
                  take such action with respect to any subcontract or purchase
                  order as the contracting agency may direct as a means of
                  enforcing such provisions, including sanctions for
                  noncompliance: Provided, however, That in the event the
                  Contractor becomes involved in, or is threatened with,
                  litigation with a subcontractor or vendor as a result of such
                  direction by the contracting agency, the Contractor may
                  request the United States to enter into such litigation to
                  protect the interests of the United States.

      (2)   In the performance of any part of the work contemplated by this
            contract, the Contractor shall not employ any person undergoing
            sentence of imprisonment at hard labor.

Q. Transfer of Interest in Contract by Contractor

            No voluntary transfer of this contract or of the rights of the
      Contractor hereunder shall be made without the written approval of the
      Secretary of the Interior; Provided, That if the Contractor operates a
      project financed in whole or in part by the Rural Electrification
      Administration, the Contractor may transfer or assign its interest in the
      contract to the Rural Electrification Administration or any other
      department or agency of the Federal Government without such written
      approval; Provided further, That any successor to or assignee of the
      rights of the Contractor, whether by voluntary transfer, judicial sale,
      foreclosure sale, or otherwise, shall be subject to all the provisions and
      conditions of this contract to the same extent as though such successor or
      assignee were the original Contractor hereunder; and, Provided further,
      That the execution of a mortgage or trust deed, or judicial or foreclosure
      sales made thereunder, shall not be deemed voluntary transfers within the
      meaning of this article.

                                        3


                        GENERAL POWER CONTRACT PROVISION

R.    License to the Contractor.

            The United States hereby grants the Contractor a license to
      construct, install, operate, maintain, replace, or repair, either or all,
      upon property of the United States under the administrative control and
      jurisdiction of the Bureau of Reclamation such facilities as in the
      opinion of the contracting officer are necessary or desirable for the
      purposes of this contract. Said license shall remain in effect during the
      term of this contract and shall expire coincidently therewith. Any
      facilities so installed by the Contractor pursuant hereto shall be and
      remain the property of the Contractor, notwithstanding that the same may
      have been affixed to the promises, and the Contractor shall have a
      reasonable times after the expiration of said license in which to remove
      its facilities so installed.

S.    License to the United States.

            The Contractor, upon request from time to time by the contracting
      officer, will grant to the United States a license or licenses to
      construct, install, operate, maintain, replace, or repair, either or all,
      upon the property of the Contractor such facilities as in the opinion of
      the Contractor are necessary or desirable for the purposes of this
      contract. The license or licenses so granted shall be in form and of legal
      sufficiency acceptable to the contracting officer, shall be and remain in
      effect during the term of this contract, and shall expire coincidently
      therewith. Any facilities so installed by the United States pursuant to
      said license or licenses shall be and remain the property of the United
      States, notwithstanding that the same may have been affixed to the
      promises, and the United States shall have a reasonable times after the
      expiration of said license or licenses in which to remove the facilities
      so installed.

T.    Waivers.

            Any waiver at any time by either party hereto of its rights with
      respect to a default or any other matter arising in connection with this
      contract shall not be deemed to be a waiver with respect to any subsequent
      default or matter.

U.    Notices.

            Any notice, deemed or request required or authorized by this
      contract shall be deemed properly given if mailed, postage prepaid, to the
      contracting officer at the address shown on the signature page hereof, on
      behalf of the United States, except where otherwise herein specifically
      provided, and to the officer signing for the Contractor at the address
      shown on the signature page hereof, on behalf of the Contractor. The
      designation of the person to be notified or the address of such person may
      be changed at any time by similar notice.

V.    Contingent Upon Appropriations.

            Where the operations of this contract extend beyond the current
      fiscal year, the contract is made contingent upon Congress making the
      necessary appropriation for expenditures hereunder after such current year
      shall have expired. In such appropriation as may be all liability due to
      the failure of Congress to make such appropriation.

W.    Officials Not to Benefit.

            No Member of or Delegate to Congress or Resident Commissioner shall
      be admitted to any share or part of this contract or to any benefit that
      may arise herefrom, but this restriction shall not be construed to extend
      to this contract if made with a corporation or company for its general
      benefit.

X.    Covenant Against Contingent Fees.

            The Contractor warrants that no person or selling agency has been
      employed or retained to solicit or secure this contract upon an agreement
      or understanding for a commission, percentage, brokerage, or contingent
      fee, excepting bona fide employee or bona fide established commercial or
      selling agencies maintained by the Contractor for the purpose of securing
      business. For branch or violation of this warranty the United States shall
      have the right to annual this contract without liability or in its
      discretion to deduct from the contract price or consideration the full
      amount of such commission, percentage, brokerage, or contingent fee.

Y.    Assignment of Industrial Contract by the United States.

            When the Contractor hereunder is denominated an industrial customer,
      the United States may transfer and assign this contract at any time
      without the consent of the Contractor to any utility engaged in the
      business of distributing electric power and energy purchased at wholesale
      from the United States if such assignee agrees to take over and assume all
      the rights, duties, and obligations of the United States under this
      contract. Whenever a transfer or assignment of this contract is made by
      the United States to a utility pursuant hereto, such transfer or
      assignment shall be and constitute a novation and thereafter the United
      States shall be relieved of all liability under said contract and under
      said assignment and the Contractor shall look solely to the assignee for
      performance of this contract.

Z.    Contract Subject to Colorado River Compact.

            Where the energy sold hereunder is generated from waters of the
      Colorado River system, this contract is made upon the express condition
      and with the express covenant that all rights hereunder shall be subject
      to and controlled by the Colorado River Compact approved by section 13(a)
      of the Boulder Canyon Project Act of December 21, 1928, (45 Stat. 1057)
      and the parties hereto shall observe and be subject to and controlled by
      said Colorado River Compact in the construction, management, and operation
      of the dams, reservoirs, and powerplants from which electrical energy is
      to be furnished by the United States to the Contractor hereunder, and in
      the storage, diversion, delivery, and use of water for the generation of
      electrical energy to be delivered by the United States to the Contractor
      hereunder.

                                       4


                       GENERAL POWER CONTRACT PROVISIONS

         THE FOLLOWING PROVISIONS ARE APPLICABLE ONLY WHEN THE ELECTRIC SERVICE
    TO BE FURNISHED ARTICLE PROVIDES THAT SERVICE WILL BE FURNISHED OVER THE
    FACILITIES OF A THIRD PARTY:

AA. Existence of Transmission Service Contract.

         In search as the electric service hereunder is to be supplied over
    facilities not owned by the United States, the obligation of the United
    States to furnish electric service hereunder shall at all times be subject
    to and contingent upon the existence of a transmission service contract
    granting the United States the right to use such facilities not owned by it
    as are necessary to the rendering of electric service hereunder; Provided,
    That, if the United States acquires or constructs facilities which would
    enable it to furnish direct service to the contractor, the United States, at
    its option, may furnish the electric service hereunder over its own
    facilities.

BB. Conditions of Transmission Service.

         Anything to the contrary in this contract notwithstanding, when the
    electric service under this contract is furnished by the United States over
    the facilities of other by virtue of a transmission service arrangement,
    the electric power and energy will be furnished at the voltage available and
    under the conditions which exist from time to time on the transmission
    system over which the service is supplied. The United States will
    endeavor to inform the Contractor from time to time of any changes
    contemplated on the system over which the service is supplied but the costs
    of any changes made necessary in the Contractor's system because of changes
    or conditions on the system over which the service is supplied shall not be
    a charge against or a liability of the United States; Provided, That if the
    Contractor, because of changes or conditions on the system over which
    service hereunder is supplied, is subjected to the necessity of making
    changes on its system at its own expense in order to continue receiving
    service hereunder, then the Contractor may terminate this contract on not
    less than sixty (60) days' written notice given to the United States at any
    time prior to the making of said changes on its system, but not thereafter;
    Provided further. That if the electric service requirements of the
    Contractor, to the extent that the United States is obligated or determines
    that it can become obligated to furnish such requirements, are not being met
    or the United States advises the Contractor cannot be met because of
    an insufficiency of capacity available to the United States under its
    transmission service arrangement in the facilities of others over which
    service hereunder is supplied, than the contractor may terminate this
    contract on not less than sixty (60) days' written notice given to the
    United States at any time prior to the time that the United States advises
    the Contractor that the needed capacity is available, but not thereafter.

         THE FOLLOWING PROVISIONS ARE APPLICABLE ONLY WHEN SERVICE IS RENDERED
    TO CONTRACTORS UNDER A "SCHEDULE OF RATES FOR WHOLESALE POWER SERVICE TO
    CUSTOMERS HAVING THEIR OWN GENERATING FACILITIES."

CC. Purchase of System Energy Requirements.

         The Contractor agrees that it will, to the extent of the availability
    of secondary energy contracted for hereunder, purchase its system energy
    requirements in lieu of operating its own generating equipment except that
    this provision shall not be construed to prohibit the Contractor's use of
    by-product power and energy.

DD. Withdrawal of SecondaryEnergy.

         The United States shall have the right, upon not less than 24 hours'
    advance notice from the contracting officer to the Contractor, to withdraw
    secondary energy by reducing, in whole or in part, the contract rate of
    delivery for secondary energy provided for herein for such period or period
    of time as the contracting officer deem necessary or advisable. The
    United States also shall have the right, upon not less than 90 days, advance
    written notice from the contracting officer to the Contractor, to terminate
    the obligation of the United States hereunder to deliver secondary energy.
    The maximum rate of delivery shall be appropriately adjusted to conform to
    changes under this section in the contract rate of delivery for secondary
    energy as of the effective dates thereof.

EE. Contractor's Capacity.

         The Contractor's capacity as referred to herein is defined to be the
    sustained load carrying ability of the Contractor's electric generating
    plants, whether owned or leased, at system load factor, less station use, as
    limited by transmission and substation facilities. The Contractor's
    capacity, insofar as practicable, will be initially determined by a test
    jointly conducted by the parties hereto immediately prior to initial
    service hereunder. Therefore, the Contractor's capacity shall be
    redetermined from time to time upon the request of the contracting officer
    by additional jointly conducted tests to the extent practicable, but such
    tests shall not be required more frequently than once in each 12 months
    unless a permanent changed condition is known to exist. When tests are
    impracticable, the capacities shall be determined by the contracting officer
    from the best information available.

FF. Adjustments for Curtailments to service.

         Adjustments for curtailments to service for periods of one (1) hour or
    longer in duration each because of conditions on the power system of the
    United States, which system for the purpose of such adjustments hereunder
    shall include transmission facilities utilized but not owned by the United
    States, shall be made in the following manner in lieu of the procedure set
    out in Article K hereof:

         (1)   Energy Charge and Monthly Minimum Bill Adjustment:

               The total number of hours of curtailed service in any billing
         period shall be determined by adding (1) the sum of the hours of
         interrupted service to (2) the product of: the number of hours of
         reduced service multiplied by the percentage of said reduction below
         the lesser of (a) the maximum rate of delivery then in effect, or (b)
         the obligation of the United States to deliver firm power and energy
         and/or secondary energy as established under the operating agreement
         entered into pursuant to the Auxiliary Power Service article hereof, or
         (c) the rate

                                       5


                        GENERAL POWER CONTRACT PROVISIONS

            of delivery required by the Contractor at the time of such
            reduction. The kilowatt-hour blocks of the energy charge and the
            monthly minimum bill shall each be proportionately adjusted in the
            ratio that the total number of hours of such curtailed service as
            herein determined bears to the total number of hours in the billing
            period involved.

            (2)   Demand or Capacity Charge and Minimum Annual Capacity Charge
                  Adjustment:

                  The total number of hours of curtailed service in any billing
            period shall be determined by adding (1) the sum of the number of
            hours of interrupted service to (2) the product of: the number of
            hours of reduced service multiplied by the percentage of said
            reduction below the lesser of (a) the contract rate of delivery for
            firm power, or (b) the obligation of the United States to deliver
            firm power and energy as established under the operating agreement
            entered into pursuant to the Auxiliary Power Service article hereof,
            or (c) the rate of delivery required by the Contractor at the time
            of such reduction. The demand or capacity charge and the minimum
            annual capacity charge shall each be proportionately adjusted in the
            ratio that the total number of hours of such curtailed service as
            herein determined bears to the total number of hours in the billing
            period involved.

      The Contractor shall make written claim, within thirty (30) days after
      receiving the monthly bill for adjustment on account of any curtailment to
      service as specified in subsections (1) and (2) of this article for
      periods of one (1) hour or longer in duration each, alledged to have
      occurred and which is not reflected in such bill. Failure to make such
      written claim, within said thirty (30) day period, shall constitute a
      waiver thereof. All curtailments to service, which are due to conditions
      on the power system of the United States, shall be subject to the
      provisions of this article and the Contractor shall be limited in its
      remedy therefor to the relief granted by this article; Provided. That
      withdrawal of power and energy under contract provisions shall not be
      deemed curtailments to service.

            THE FOLLOWING PROVISION IS APPLICABLE ONLY WHEN ELECTRIC SERVICE
      INVOLVES MULTIPLE POINTS OF DELIVERY FROM BOTH DIRECT AND WHEELED POINTS:

GG.   Multiple Points of Delivery Involving Direct and Wheeled Deliveries

            The United States has provided line and substation capacity under
      the terms of this contract for the purpose of delivering electric service
      directly to the Contractor at specific points of delivery. It also has
      agreed to absorb wheeling allowances and/or discounts up to a specified
      maximum amount for deliveries of power over other system(s). In the event
      the Contractor shifts any of its loads served hereunder from direct
      delivery to wheeled delivery, the United States will not absorb the
      wheeling costs on such shifted load until the unused capacity, as
      determined solely by the contracting officer, available at the direct
      delivery point(s) affected is fully utilized.

                                        6


                               SALT RIVER PROJECT

                                   RESOLUTION

WHEREAS, the Board of Directors of the Salt River Project Agricultural
Improvement and Power District (herein called "Salt River Project") has
determined that it is in Salt River Project's best interest to enter into
various contracts relating to the construction, operation and maintenance of the
proposed Navajo Project consisting of three 750 MW (nameplate rating) coal-fired
steam electric generating units (herein called "Navajo Generating Station"),
located on the Navajo Indian Reservation near Page, Arizona, and the related 500
KV transmission system (herein called "Navajo transmission system"), with
ownership interests in the Navajo Generating Station to be as follows:


                                                   
Arizona Public Service Co. (Arizona)                  14.0%

City of Los Angeles, Department of
Water and Power (Los Angeles)                         21.2%

Nevada Power Company (Nevada)                         11.3%

Salt River Project Agricultural
Improvement and Power District
(Salt River Project)                                  46.0%

Tucson Gas and Electric Company
(Tucson)                                               7.5%


all of said entities referred to herein as the "Co-Owners," and

WHEREAS, Salt River Project shall own 21.7% of the Navajo Generating Station
for its own use and benefit and shall own and hold the remaining 24.3% of its
ownership interest in the Navajo Generating Station for the use and benefit of
the United States, Department of Interior, Bureau of Reclamation for the United
States' use to provide power and energy for Central Arizona Project pumping (the
"United States" and the above listed companies being herein collectively called
"Participants"), and

WHEREAS, the following described Agreements have been reviewed on this day with
this Board and this Board has determined that it is in the best interest of Salt
River Project to enter into said Agreements to effectuate the construction,
operation and maintenance of the Navajo Project;

NOW, THEREFORE, BE IT HEREBY RESOLVED, That the Board of Directors of Salt River
Project has and does hereby approve the Navajo Project Participation Agreement
among the Participants, and has and does hereby empower and direct that the
President or Vice President, and the



                               SALT RIVER PROJECT

Secretary or Assistant Secretary, make, execute and deliver said
Participation Agreement for, and on behalf of, the Salt River Project with such
minor changes or omissions therein as management may make in the premises, and

BE IT HEREBY FURTHER RESOLVED that the Board of Directors of Salt River Project
has and does hereby approve the Indenture of Lease for Navajo Units 1, 2 and 3,
and has and does hereby empower and direct that the President or Vice President,
and the Secretary or Assistant Secretary, make, execute, acknowledge and deliver
said Indenture of Lease for Navajo Units 1, 2 and 3 for and on behalf of the
Salt River Project with such minor changes or omissions therein as management
may make in the premises, and

BE IT HEREBY FURTHER RESOLVED that the Board of Directors of Salt River Project
has and does hereby approve that certain Federal Rights of Way, granted in
conformity with the Act of February 15, 1901, between the Secretary of Interior
and the Co-Owners as Grantees, and does hereby authorize, empower and direct
that the President or Vice President, and the Secretary or Assistant Secretary,
make, execute, acknowledge and deliver said Federal Rights of Way for, and on
behalf of Salt River Project with such minor changes or omissions therein as
management may make in the premises, and this Board of Directors also
authorizes, empowers and directs its officers and management to make and file an
Application for Grant of Rights of Way under the Act of February 15, 1901, 31
Stat. 790, 43 U.S.C., Section 959, underlying any or all Project land rights,
and to take and perform all necessary acts in making and filing such
Application, and

BE IT HEREBY FURTHER RESOLVED that the Board of Directors of Salt River Project
has and does hereby approve that certain Federal Rights of Way and Easements,
granted in conformity of February 5, 1948, by and between the Secretary of
Interior and Salt River Project and the other Co-Owners as Grantees and does
hereby authorize, empower and direct that the President or Vice President, and
the Secretary or Assistant Secretary, make, execute, acknowledge and deliver
said Federal Rights of Way and Easements for, and on behalf of, the Salt River
Project with such minor changes and omissions therein as management may make in
the premises, and does hereby authorize, empower and direct its officers and
management to make and file an Application for the Grant of Rights of Way and
Easements under the Act of February 5, 1948, 62 Stat. 17, 25 U.S.C. Section 323,
underlying any or all Project land rights, and to take and perform all necessary
acts in making and filing such Application, and

BE IT HEREBY FURTHER RESOLVED that the Board of Directors of Salt River Project
has and does hereby approve the Memorandum of Agreement



                               SALT RIVER PROJECT

providing for execution of Navajo Station Coal Supply Agreement among it, the
other Co-Owners and Peabody Coal Company together with the Letter Agreement
relating thereto which sets forth additional understandings and agreements
concerning the Navajo Station Coal Supply Agreement, and has and does hereby
authorize, empower and direct that the President or Vice President, and the
Secretary or Assistant Secretary, make, execute, acknowledge and deliver said
Memorandum of Agreement and said Letter of Understanding for and on behalf of
the Salt River Project with such minor changes and omissions therein as
management may make in the premises, and

BE IT HEREBY FURTHER RESOLVED that the Board of Directors of Salt River Project
has and does hereby approve that certain Power Coordination Contract between the
Co-Owners and the United States and has and does hereby authorize, empower and
direct that the President or Vice President, and the Secretary or Assistant
Secretary, make, execute and deliver said Power Coordination Contract for and on
behalf of the Salt River Project with such minor changes and omissions therein
as management may make in the premises, and

BE IT HEREBY FURTHER RESOLVED that the Board of Directors of Salt River Project
has and does hereby approve the Principles of Inter connected Operation for
the Navajo Project between the Co-Owners, the United States and the Southern
California Edison Company (whether or not said Southern California Edison
Company is party thereto), and does hereby authorize, empower and direct that
the President or Vice President, and the Secretary or Assistant Secretary make,
execute and deliver said Principles of Interconnected Operation for and on
behalf of the Salt River Project with such minor changes and omissions therein
as management may make in the premises, and

BE IT HEREBY FURTHER RESOLVED that the Board of Directors of Salt River Project
has and does hereby approve that certain Contract for Interim Use of United
States Entitlement in the Navajo Project (herein called "Layoff Contract")
between it and the United States and does hereby authorize, empower and direct
that the President or Vice President, and the Secretary or Assistant Secretary,
make, execute and deliver said Layoff Contract for and on behalf of the Salt
River Project with such minor changes and omissions therein as management may
make in the premises, and

BE IT HEREBY FURTHER RESOLVED that the Board of Directors of Salt River Project
has and does hereby approve that certain Memorandum Transmission Agreement
between it, the other Participants, and the Southern California Edison Company,
and has and does hereby authorize, empower and direct that the President or Vice
President, and the Secretary or Assistant Secretary, make, execute and deliver
said



                               SALT RIVER PROJECT

Memorandum Transmission Agreement for and on behalf of the Salt River Project
with such minor changes and omissions therein as management may make in the
premises, and

BE IT HEREBY FURTHER RESOLVED that the Board of Directors of Salt River Project
has and does hereby approve that certain Agreement for Delivery of the United
States Power and Energy for the McCullough Substation to the Mead Substation
between it, the United States and the other Eldorado System Co-Owners (whether
or not such entities become parties thereto), and has and does hereby authorize,
empower and direct that the President or Vice President, and the Secretary or
Assistant Secretary, make, execute and deliver said Agreement for and on behalf
of the Salt River Project with such minor changes and omissions therein as
management may make in the premises, and

BE IT HEREBY FURTHER RESOLVED that the Board of Directors of Salt River Project
has and does hereby approve that certain Spinning Reserve pooling Agreement
between it, and the other Participants, excepting the City of Los Angeles,
Department of Water and Power (whether or not all such other Participants become
parties thereto), and has and does hereby authorize, empower and direct that the
President or Vice President, and the Secretary or Assistant Secretary, make,
execute and deliver said Spinning Reserve Fueling Agreement for and on behalf of
the Salt River Project with such minor changes and omissions therein as
management may make in the premises.

                                   CERTIFICATE

I,F.E, Smith, the duly appointed, qualified and acting Secretary of the Salt
River Project Agricultural Improvement and Power District, HEREBY CERTIFY that
the foregoing is a true and complete copy of a resolution adopted by the Board
of Directors of said District at a special meeting thereof duly held on the 25th
day of August 1969, at which meeting a quorum was present and voted.

WITNESS my hand and seal of Salt River Project Agricultural Improvement and
Power District this 19th day of November 1969.

                                                    /s/ F. E. Smith
                                                    --------------------------
                                                    F. E. Smith, Secretary



                                   CERTIFICATE

      I, Samuel P. Cowley, certify that I am the Secretary of the Nevada power
Company, a corporation named herein; that Harry Allen who signed the above
contract on behalf of said corporation was then its President that said
contract was duly signed for and in behalf of said corporation by authority of
its governing body and is within the scope of its corporate powers.

                                                /s/ Samuel P. Cowley
                                                ---------------------------
                                                Samuel P. Cowley, Secretary



                          TUCSON GAS & ELECTRIC COMPANY

                          Certified Copy of Resolutions
                        Adopted by the Board of Directors

            RESOLVED, that the proper officers of the Company be, and they
hereby are authorized to enter into a Participation Agreement between the United
States of America, Arizona Public Service Company, Department of Water and Power
of the City of Los Angeles, Nevada Power Company, Salt River Project
Agricultural Improvement and Power District and Tucson Gas & Electric Company
for the ownership of the Navajo Project wherein Tucson Gas & Electric Company
shall own an undivided 7-1/2% Interest in the Navajo Generating Station and
varying percentage interests in the transmission system. The Agreement shall be
substantially in the form of the draft filed with the Secretary of the Company
marked "Filed September 23, 1969 with the Secretary of Tucson Gas & Electric
Company", and be it

            FURTHER RESOLVED, that the proper officers of the Company be, and
they hereby are further authorized to execute and enter into on behalf of the
Company the necessary Project Agreements contemplated by said Participation
Agreement, and such other documents reasonably required to implement said
Participation Agreement and Project Agreements.

                           * * * * * * * * * * * * * *

            I, P. L. ABBOTT, Secretary of TUCSON GAS & ELECTRIC COMPANY
(herein after called the "Company"), DO HEREBY CERTIFY that the above and
foregoing is a true and complete copy of resolutions duly adopted by the Board
of Directors at the Regular Monthly Meeting held on the 23rd day of September,
1969, at which meeting a quorum was present and acted thereon; and

            I DO FURTHER CERTIFY that said resolution is in full force and
effect on the date hereof.

            IN WITNESS WHEREOF, I have hereunto set my hand and affixed the seal
of the Company this 29th day of September, 1969.

                                                          /s/ P.L. Abbott
                                                          ----------------------
                                                          Secretary



                                   CERTIFICATE

      I, GERALD J. GRIFFIN, certify that I am an Assistant Secretary of ARIZONA
PUBLIC SERVICE COMPANY, the corporation named herein; that M. C. TITUS, who
signed the above contract on behalf of said Corporation was then its Executive
Vice President; that said contract was duly signed for and in behalf of said
Corporation by authority of its governing body and is within the scope of its
corporate powers.

                                                       /s/ Gerald J. Griffin
                                                       -------------------------
                                                       Assistant Secretary

(SEAL)



                                                              RESOLUTION NO. 416

            BE IT RESOLVED by the Board of Water and Power Commissioners of The
City of Los Angeles that the President and the Secretary of this Board be and
they are hereby authorized to execute, on behalf of this Board, certain
agreements relating to the construction, ownership, operation and maintenance of
facilities for the generation of electrical power and energy and related
facilities, including fuel supply, copies of which agreements are on file with
the Secretary of this Board and which are identified as follows, that is:



         Agreement Title                                      DWP Number
         ---------------                                      ----------
                                                           
Navajo Project Participation Agreement                          10334

Memorandum of Agreement Providing for
 Execution of Navajo Station Coal
 Supply Agreement                                               10335

Letter Agreement                                                10336

Application for Federal Rights-of-Way
 and Easements                                                  10337

Application and Grant of Rights-of-
 Way and Easements (25 U.S.C. Section 323)                      10338

United States, Department of the Interior,
 Power Coordination Contract                                    10339

Interim Arrangement for Interconnected
 Operations                                                     10340

Contract with Department of Water and
 Power of The City of Los Angeles for
 Interim Sale of United States
 Entitlement of Navajo Project                                  10341

Memorandum Transmission Agreement                               10342

Victorville-Lugo Interconnection
 Agreement                                                      10343






         Agreement Title (Continued)                          DWP Number
         ---------------                                      ----------
                                                           
Indenture of Lease                                              10344
Letter Agreement                                                10350


            I HEREBY CERTIFY that the foregoing is a full, true and correct copy
of a resolution adopted by the Board of Water and Power Commissioners of The
City of Los Angeles at its meeting held NOV 20 1969

                                                        /s/ Mary J. Born
                                                        ---------------------
                                                        Secretary


                              ORDINANCE NO. 139,629

AN ORDINANCE APPROVING AGREEMENTS RELATING TO PARTICIPATION BY THE DEPARTMENT OF
      WATER AND POWER IN THE NAVAJO PROJECT

                      THE PEOPLE OF THE CITY OF LOS ANGELES
                              DO ORDAIN AS FOLLOWS:

      Section 1. That the Board of Water and Power Commissioners of The City of
Los Angeles be and it is hereby authorized in its discretion, to execute and
enter into the following agreements, substantially in the form of those which
are on file with the City Clerk and identified below, relating to the
transmission and use of electrical power and energy associated with the Navajo
Project:



                              AGREEMENT TITLE                                                DWP NUMBER
                                                                                          
Interim Arrangement for Interconnected Operations                                               10310
Contract with Department of Water and Power of The City of Los
  Angeles for Interim Sale of United States Entitlement of Navajo Project                       10341
Memorandum Transmission Agreement                                                               10342
Victorville-Lugo Interconnection Agreement                                                      10343
[ILLEGIBLE] Agreement                                                                           10350


      Sec. 2. The City Clerk shall certify to the passage of this ordinance and
cause the same to be published in some daily newspaper printed and published in
the City of Los Angeles.

      I hereby certify that the foregoing ordinance was introduced at the
meeting of the Council of the City of Los Angeles of November 10, 1969 and was
passed at its meeting of November 17, 1969.

                                                      REX E. LAYTON, City Clerk,
                                                        By M. B. Wilson, Deputy.

      Approved November 18, 1969.
File No. 147173 Sup #1                                    SAM YORTY, Mayor.
                               (E54726) Nov 19 1t

                                  CERTIFICATION

STATE OF CALIFORNIA,    )
                        )       ss.
COUNTY OF LOS ANGELES,  )

      I, REX E. LAYTON, City Clerk of the City of Los Angeles and ex-officio
Clerk of the City Council of the City of Los Angeles, do hereby certify and
attest the foregoing to be a full, true and correct copy of the original
Ordinance No. 139,629 of the City of Los Angeles, on file in my office, and that
I have carefully compared the same with the original.

                        IN WITNESS WHEREOF, I have hereunto set my hand and
                        affixed the Seal of the City of Los Angeles, this 19th
                        day of November, 1969

                                /s/ Rex E. Layton
                                -------------------------------------
                                City Clerk of the City of Los Angeles

                        By /s/ Authorized Signatory
                           ------------------------------------
                             Deputy

Form Clerk 22-5M-11-68 (R)


                              ORDINANCE NO. 139,630

AN ORDINANCE APPROVING AGREEMENTS RELATING TO PARTICIPATION BY THE DEPARTMENT OF
    WATER AND POWER IN THE NAVAJO PROJECT

                      THE PEOPLE OF THE CITY OF LOS ANGELES
                              DO ORDAIN AS FOLLOWS:

      Section 1. That the Board of Water and Power Commissioners of The City of
Los Angeles be and it is hereby authorised in its directors, to execute
and enter into the following agreements, substantially in the form of those
which are on file with the City Clerk and identified below, relating to
the construction, ownership, operation and maintenance of facilities for
generation of electrical power and energy and related facilities, including
fuel supply:



        AGREEMENT TITLE                                            DWP NUMBER
                                                                
Navajo Project Participation Agreement                               10384
Memorandum of Agreement Providing for Execution of Navajo
 Station Coal Supply Agreement
Letter Agreement
Application for Federal Rights-of-Way and Easements                  10337
Grant of Federal Rights-of-Way and Easements                         10338
United States Department of the Interior, Power
 Coordination Contract                                               10339
Indenture of Lease                                                   10344


      Sec. 2. The City Clerk shall certify to the passage of this ordinance and
cause the same to be published in some daily newspaper printed and published in
the City of Los Angeles.

      I hereby certify that the foregoing [ILLEGIBLE] was introduced at the
meeting of the Council of the City of Los Angeles of November 10, 1969
and was passed at its meeting of November 17, 1969.

                                                 REX E. LAYTON, City Clerk,
                                                 By M.B. Wilson, Deputy.
      Approved November 18, 1969.
File No. [ILLEGIBLE]                                            SAM YORTY Mayor.
                               (E54727) NOV 19 IT

                                  CERTIFICATION

STATE OF CALIFORNIA,    } ss.
COUNTY OF LOS ANGELES,

      I, REX E. LAYTON, City Clerk of the City of Los Angeles and ex-officio
Clerk of the City Council of the City of Los Angeles, do hereby certify and
attest the foregoing to be a full, true and correct copy of the original
Ordinance No. 139,630 of the City of Los Angeles, on file in my office, and that
I have carefully compared the same with the original.

                     IN WITNESS WHEREOF, I have hereunto set my hand and affixed
                     the Seal of the City of Los Angeles, this 19th day
                     of November, 1969

                                                  REX E. LAYTON
                                        City Clerk of the City of Los Angeles

                     By /s/ Authorized Signatory
                        ------------------------
                            Deputy

Form Clerk 22-5M-11-68 (R)


                      RESOLUTION OF THE BOARD OF DIRECTORS

                     OF SOUTHERN CALIFORNIA EDISON COMPANY

                            ADOPTED NOVEMBER 20, 1969

                    RE:    RATIFICATION OF EXECUTION OF
                           CONTRACTS WITH THE UNITED
                           STATES DEPARTMENT OF INTERIOR,
                           BUREAU OF RECLAMATION, AND OTHER
                           PARTICIPANTS IN THE NAVAJO
                           PROJECT, CONCERNING THE NAVAJO
                           PROJECT AND RELATED MATTERS

            WHEREAS, this corporation has executed a contract with the United
States of America, providing for the interim purchase of a portion of the United
States' entitlement to capacity and energy in the Navajo Project, which portion
shall amount to approximately 336 mw of capacity and associated energy from
Units 1, 2 and 3 of the Navajo Generating Station, and will provide for the
right to use part of the entitlement of the United States in the Navajo Project
transmission system for the purpose of delivering such portion of capacity and
associated energy from the Navajo Generating Station to this corporation's
points of delivery at Moenkopi Switchyard in Arizona, and the Eldorado
Substation in Nevada; and

            WHEREAS, a copy of said contract, entitled Contract With Southern
California Edison Company For Interim Sale Of United States' Entitlement Of
Navajo Project and bearing the designation Contract No. 14-06-300-2135, has been
presented to this meeting; and

            WHEREAS, this corporation has executed a contract with the United
States of America, Arizona Public Service Company, Department of water and power
of the City Los Angeles,



Nevada Power Company, Salt River Project Agricultural Improvement and Power
District, and Tucson Gas and Electric Company, providing certain principles
related to the interconnection of the Navajo Project transmission system with
the Edison-Arizona 500-kv transmission system at Moenkopi Switchyard, and for
the parallel operation of the Moenkopi-Eldorado 500 kv line and the proposed
Navajo-McCullough 500-kv line, and certain related matters, all of which
principles are to be incorporated in a more definitive and complete agreement to
be executed at a later time; and

            WHEREAS, a copy of said contract, entitled Memorandum Transmission
Agreement between Participants in the Navajo Project and Southern California
Edison Company, dated September 30, 1969, and bearing the designation Contract
No. 14-06-30-2140, has been presented to this meeting, and

            WHEREAS, this corporation has executed a letter agreement with
Arizona Public Service Company, Department of Water and Power of the City of Los
Angeles, Nevada Power Company, Salt River Project Agricultural Improvement and
Power District, Tucson Gas and Electric Company, and The United States of
America, adopting certain principles for the interconnected operations of the
respective electric systems of the parties, including establishment of
principles with respect to forecast capacity resources margin, spinning reserve
capacity, emergency service, interruptible load as a substitute for spinning
reserve capacity and system operations, all of which principles are to be
incorporated in a more definitive and complete

                                      -2-


agreement to be executed at a later time; and

            WHEREAS, a copy of said principles, entitled Principles of
Interconnected Operation For The Navajo Interconnection Agreement, September 30,
1969, together with a covering execution letter agreement entitled Interim
Arrangement For Interconnected Operations, dated September 30, 1969, and bearing
the designation Contract No. 14-06-300-2139, has been presented to this meeting
and;

            WHEREAS, execution of said three documents has not been completed by
all the other parties thereto.

            NOW, THEREFORE, BE IT RESOLVED that the execution and delivery of
the aforesaid three documents by and on behalf of this corporation is hereby
ratified, confirmed and approved;

            BE IT FURTHER RESOLVED, that the Chairman of the Board, the
President, a Senior Vice President, a Vice President of this corporation, and
any of them, is authorized hereby to execute and deliver in the name of and on
behalf of this corporation, the definitive Navajo Interconnection Agreement and
the definitive Transmission Agreement hereinabove described.

            BE IT FURTHER RESOLVED, that the Secretary of this corporation is
hereby directed to mark appropriately for Identification and to file with the
records of this corporation the aforesaid copies of said documents presented to
this meeting.

                                       -3-


            I, C. D. LESTER, Secretary of SOUTHERN CALIFORNIA EDISON COMPANY, do
hereby certify that the foregoing is a full, true, and correct copy of a
resolution of the Board of Directors of said corporation, adopted at a meeting
of said Board of Directors duly held on November 20, 1969.

            WITNESS my hand and the seal of said corporation this 20th day of
November, 1969.

                                  /s/ C.D.LESTER
                        ----------------------------------
                                    SECRETARY
                        SOUTHERN CALIFORNIA EDISON COMPANY



                        COORDINATING COMMITTEE AGREEMENT

                                      No. 1

            SUBJECT: All Risk Insurance for Navajo-Mohave SO2 Removal
                                   Pilot Plant

The Coordinating Committee hereby directs the Navajo Generating Station Project
Manager not to maintain all risk insurance insofar as the Navajo-Mohave S02
Removal Research Pilot Plant is concerned.

Section 21.1 of the Navajo Project Participation Agreement, as amended, provides
that during the construction stage each Project Manager shall procure or cause
to be procured and maintain in force certain insurance coverages, including all
risk insurance.

The Generating Station Project Manager contemplates entering into an agreement
with Southern California Edison Company (Edison) , as "project manager" and
"operating agent" for the Mohave Project, pursuant to which Edison as "program
manager" will provide for the design, engineering, construction and testing of
an S02 removal pilot plant on behalf of the Navajo Project Participants and the
Mohave Project Participants.

The pilot plant, to be constructed at the Mohave Plant Site, will be included
within the existing Mohave Project insurance program. The applicable Mohave
Project policy providing the all risk insurance coverage referred to in Section
21.1 of the Participation Agreement, as amended, for damage to the pilot plant,
carries a deductible of



$200,000.00. Engineering and insurance personnel of the "program manager" have
concluded the total potential loss upon the occurrence of any single event, in
their opinion, as reflected in Attachment A hereto, does not exceed the Edison
physical damage insurance deductible of $200,000.00. Therefore, any dollars paid
toward premiums would be wasted as there is no foreseeable loss of that
magnitude.

Notwithstanding this decision all contractors of the "program manager"
performing work on the pilot plant will be required to maintain all risk
coverages for any portion of work to be performed by them on the pilot plant.

Approved as of the 31 day of September, 1971.

                                         SALT RIVER PROJECT AGRICULTURAL
                                           IMPROVEMENT AND POWER DISTRICT

                                         By    /s/ Authorized Signatory
                                           -------------------------------------
                                           Coordinating Committee Representative

                                         ARIZONA PUBLIC SERVICE COMPANY

                                         By    /s/ Authorized Signatory
                                           -------------------------------------
                                           Coordinating Committee Representative

                                         TUCSON GAS & ELECTRIC COMPANY

                                         By    /s/ Authorized Signatory
                                           -------------------------------------
                                           Coordinating Committee Representative

                                     DEPARTMENT OF WATER AND POWER
                                     OF THE CITY OF LOS ANGELES

                                     By        /s/ Authorized Signatory
                                        ----------------------------------------
                                        Coordinating Committee Representative

                                     NEVADA POWER COMPANY

                                     By        /s/ Authorized Signatory
                                        ----------------------------------------
                                        Coordinating Committee Representative

                                     UNITED STATES OF AMERICA

                                     By        /s/ Authorized Signatory
                                        ----------------------------------------
                                        Coordinating Committee Representative



                           AMENDMENT AND SUPPLEMENT #1
                                       TO
                                 NAVAJO PROJECT
                             PARTICIPATION AGREEMENT

1.    PARTIES: The parties to this amendatory and supplemental agreement are:
      THE UNITED STATES OF AMERICA, hereinafter referred to as the "United
      States", acting through the Secretary of the Interior; ARIZONA PUBLIC
      SERVICE COMPANY, an Arizona corporation, hereinafter referred to as
      "Arizona"; DEPARTMENT OF WATER AND POWER OF THE CITY OF LOS ANGELES, a
      department organized and existing under the Charter of the City of Los
      Angeles, a municipal corporation of the State of California, hereinafter
      referred to as "Los Angeles"; NEVADA POWER COMPANY, a Nevada corporation,
      hereinafter referred to as "Nevada"; SALT RIVER PROJECT AGRICULTURAL
      IMPROVEMENT AND POWER DISTRICT, an agricultural improvement district
      organized and existing under the laws of the State of Arizona, hereinafter
      referred to as "Salt River Project"; and TUCSON GAS & ELECTRIC COMPANY, an
      Arizona corporation, hereinafter referred to as "Tucson".

2.    RECITALS: This amendatory and supplemental agreement is made with
      reference to the following facts, among others:

            2.1 By the Colorado River Basin Project Act (82 Stat. 885) the
      Congress of the United States authorized the construction, operation and
      maintenance of the Central Arizona Project. Pursuant to Section 303 of
      said Act, the Secretary is authorized to enter into agreements with

                                      - 1 -


      non-Federal interests proposing to construct thermal generating
      powerplants whereby the United States shall acquire the right to such
      portions of their capacity, including delivery of power and energy over
      appurtenant transmission facilities to mutually agreed upon delivery
      points, as he determines is required in connection with the operation of
      the Central Arizona Project.

            2.2 The Secretary has determined that the acquisition of a right to
      a portion of the capacity of the Navajo Project is the most feasible plan
      for supplying the power requirements of the Central Arizona Project and
      augmenting the Lower Colorado River Basin Development Fund.

            2.3 As of September 30, 1969, the parties entered into a
      Participation Agreement, to establish certain terms, covenants and
      conditions relating to participation in the construction, operation and
      maintenance of the Navajo Project in accordance with the provisions of the
      Participation Agreement and the other Project Agreements.

            2.4 The parties desire, by this Amendment and Supplement #1 to
      Navajo Project Participation Agreement, to amend and supplement certain
      terms, covenants and conditions in the Participation Agreement relating to
      the Navajo Project.

3.    AGREEMENT: In consideration of the mutual covenants herein, the parties
      agree as follows:

4.    DEFINITIONS: The following terms, when used herein, shall

                                      - 2 -


      have the meanings specified:

            4.1 AMENDMENT AND SUPPLEMENT #1 TO NAVAJO PROJECT PARTICIPATION
      AGREEMENT. This agreement.

5.    Section 4 of the Participation Agreement is amended and supplemented by
      the addition of the following definitions:

            "4.25 RAIL LOADING SITE: The site for the conveyor termination and
      rail loading facilities, related facilities and equipment and coal storage
      as described on Exhibit 3 to the Navajo Plant Site lease."

            "4.26 RAILROAD: The railroad described in Exhibit A-1 hereto."

6.    Section 18 of the Participation Agreement is amended and supplemented by
      the addition of the following section:

            "18.7 The 11.3% undivided ownership interest of Nevada in the
      Railroad may be transferred to Arizona by Nevada and subsequently
      transferred to Nevada by Arizona, pursuant to any agreement between
      Arizona and Nevada presently or hereafter existing, without the prior
      written consent of any other Participant; provided, however, that in each
      instance the transferee shall (i) notify each of the other Participants in
      writing of such transfer, (ii) furnish to each Participant evidence of
      such transfer, and (iii) assume and agree to fully perform and discharge
      all of the obligations created by the Project Agreements which arise out
      of said 11.3% undivided ownership interest in the Railroad. Appropriate
      amendments to the Project Agreements will be adopted

                                      - 3 -



      recognizing any such transfer."

7.    The Participation Agreement is supplemented by the addition of the
      following section:

            "49. COMPLIANCE WITH UPPER COLORADO RIVER BASIN COMPACT:

                        49.1 The Department of the Interior is the federal
                  department responsible for administering the terms of the
                  Water Service Contract dated January 17, 1969, Contract No.
                  14-06-400-5033. The Department of the Interior also has been
                  directed by P.L. 90-537 to comply with the terms of the
                  Colorado River Compact dated November 24, 1922 and the Upper
                  Colorado River Basin Compact dated October 11, 1948. In
                  compliance with that responsibility and those directives, the
                  Secretary of the Interior hereby agrees to take any and all
                  actions within the power and authority of the Department of
                  the Interior which are necessary and required to prevent total
                  depletions chargeable to the State of Arizona under the Upper
                  Colorado River Basin Compact resulting from consumptive use of
                  water from the Upper Colorado River System in the State of
                  Arizona as measured at Lee Ferry in the manner provided for in
                  Article VI of the Upper Colorado River Basin Compact from
                  exceeding the 50,000 acre feet apportioned to the State of
                  Arizona by the Upper

                                      - 4 -


                  Colorado River Basin Compact.

                        The Secretary of the Interior further agrees to make the
                  reports required by Section 601 (b) (1) of P.L. 90-537 as
                  they pertain to Arizona's Upper Basin uses annually rather
                  than every five years. Within fifteen days following the
                  completion of said reports, the Secretary of the Interior
                  shall furnish copies of such reports to the Co-Tenants, the
                  Navajo Tribe, each of the Upper Basin States, and the Upper
                  Colorado River Commission.

                        It is the intention of the parties to this contract that
                  each of the Upper Basin States shall be a third party
                  beneficiary of the terms and conditions of this Section 49."

8.    Exhibit A-1 to the Participation Agreement is amended and supplemented by
      the addition of the following:

            "VIII. Railroad right-of-way and railroad approximately 80 miles in
            length extending from the Rail Loading Site into the Navajo Plant
            Site, engines, coal cars, related facilities and equipment.

9.    Except as modified by this Amendment and Supplement #1 to Navajo Project
      Participation Agreement, the Navajo Project Participation Agreement dated
      as of September 30, 1969, shall remain in full force and effect in
      accordance with its terms.

                                      - 5 -


      IN WITNESS WHEREOF, the parties hereto have caused this Amendment and
Supplement #1 to Navajo Project Participation Agreement to be executed as of the
16th day of January, 1970.

                                     UNITED STATES OF AMERICA

                                     By /s/ Authorized Signatory
                                        ----------------------------------------

                                     ARIZONA PUBLIC SERVICE COMPANY

                                     By /s/ Keith L. Turkey
                                        ----------------------------------------
                                           Executive Vice President

[SEAL]

ATTEST:

/s/ Authorized Signatory
- -------------------------
Assistant Secretary

                                     DEPARTMENT OF WATER AND POWER
                                     OF THE CITY OF LOS ANGELES

                                                by

                                     BOARD OF WATER AND POWER COMMISSIONERS

[SEAL]

By /s/ Mary J. Born                   By /s/ John W. Luhring
   ----------------------                ---------------------------------------
         SECRETARY                                     PRESIDENT

                                     NEVADA POWER COMPANY

                                     By /s/ Harry Allen
                                        ----------------------------------------

ATTEST:

/s/ Authorized Signatory
- -------------------------

                                     SALT RIVER PROJECT AGRICULTURAL
                                     IMPROVEMENT AND POWER DISTRICT

                                     By /s/ N. Clifford Dobson
                                        ----------------------------------------
                                                     President

[SEAL]

ATTEST AND COUNTERSIGN:

/s/ F.E. Smith
- -----------------------
       Secretary


[STAMP]                                                                  [STAMP]

                                     - 6 -


                                     TUCSON GAS & ELECTRIC COMPANY

                                     By /s/  H. R. Catlin
                                        ----------------------------------------
                                                SENIOR VICE PRESIDENT

[SEAL]

ATTEST:

/s/ Authorized Signatory
- ----------------------
ASSISTANT SECRETARY

                        )
                        )ss
                        )

      On this the 9th day of July, 1970, before me, the undersigned officer,
personally appeared James R. Smith, of the United States of America, known to
me to be the person described in the foregoing instrument, and acknowledged
that he executed the same in the capacity therein stated and for the purposes
therein contained.

      In witness whereof I hereunto set my hand and official seal.

[SEAL]

My Commission expires                        /s/ Harold L. Carlson
November 14, 1973                       ----------------------------------------
                                                 Notary Public
State of Arizona      )
                      )ss
County of Maricopa    )

      On this the 11th day of June, 1970, before me, the undersigned officer,
personally appeared KEITH L TURLEY, who acknowledged himself to be the Executive
Vice President of ARIZONA PUBLIC SERVICE COMPANY, an Arizona corporation, and
that he, as such Executive Vice President, being authorized so to do, executed
the foregoing instrument for the purposes therein contained, by signing the name
of the corporation by himself as

                                      - 7 -


Executive Vice President.

      In witness whereof I hereunto set my hand and official seal

[SEAL]
                                              /s/ Authorized Signatory
                                             -----------------------------------
                                                Notary Public

My commission expires:
March 30, 1973

State of California       )
                          ) ss
County of Los Angeles     )

      On this, the 20 day of August, 1970, before me, the undersigned officer,
personally appeared JOHN W. LUHRING and Mary J. Born, the PRESIDENT and
SECRETARY, respectively, Board of Water & Power Commissioners of the DEPARTMENT
OF WATER AND POWER OF THE CITY OF LOS ANGELES, a department organized and
existing under the Charter of the City of Los Angeles, a municipal corporation
of the State of California, known to me to be the persons described in the
foregoing instrument, and acknowledged that they executed the same in the
capacity therein stated and for the purposes therein contained.

      In witness whereof I hereunto set my hand and official seal.

                                        /s/ Linda L. Newman
                                        ----------------------------------------
                                                    Notary Public

My commission expires:                     [STAMP]

- ---------------------------

                                      - 8 -


State of Nevada       )
                      ) ss
County of Clark       )

      On this the 12th day of June, 1970, before me, the undersigned officer,
personally appeared Harry Allen, known to me to be the President of NEVADA POWER
COMPANY, a Nevada corporation, and that he, as such President, being authorized
so to do, executed the foregoing instrument for the purposes therein contained,
by signing the name of the corporation by himself as President.

      In witness whereof, I hereunto set my hand and official seal.

MYRTICE L. CARROLL

                                        /s/ MYRTICE L. CARROLL
                                        ----------------------------------------
                                                   Notary Public

My commission expires:                                   [STAMP]
______________________

State of Arizona        )
                        )ss
County of Maricopa      )

      On this the 11th day of June, 1970, before me, the undersigned officer,
personally appeared N. CLIFFORD DOBSON and F.E. SMITH, The PRESIDENT and
SECRETARY, respectively, of SALT RIVER PROJECT. AGRICULTURAL IMPROVEMENT AND
POWER DISTRICT, an Arizona agricultural improvement district, known to me to be
the persons described in the foregoing instrument, and acknowledged that

                                      - 9 -


they executed the same in the capacity therein stated and for the purposes
therein contained.

      In witness whereof I hereunto set my hand and official seal.

                                       /s/ [ILLEGIBLE]
                                      ------------------------------------------
                                                     Notary Public

My commission expires:

My Commission Expires May 3, 1971

State of Arizona     )
                     )ss
County of Pima       )

      On this the 11th day of June, 1970, before me the undersigned officer,
personally appeared H. R. Catlin who acknowledged himself to be the SENIOR VICE
PRESIDENT of TUCSON GAS & ELECTRIC COMPANY, an Arizona corporation, and that he,
as such SENIOR VICE PRESIDENT, being authorized so to do, executed the
foregoing instrument for the purposes therein contained, by signing the name of
the corporation by himself as SENIOR VICE PRESIDENT.

                                      /s/ Diane Howland
                                      ------------------------------------------
                                                     Notary Public
[SEAL]

My commission expires:

My Commission Expires Dec. 8, 1972

                                      - 10 -


                          CERTIFIED COPY OF RESOLUTION

      I, GERALD J. GRIFFIN, Assistant Secretary of ARIZONA PUBLIC SERVICE
COMPANY, an Arizona corporation, HEREBY CERTIFY that, at a meeting of the Board
of Directors of said Company, duly convened and held on August 21, 1969, at
which a quorum was present and acting throughout, the following resolution was
adopted and is now in full force and effect:

            RESOLVED, that the Board of Directors approves and ratifies the
      action of the officers in negotiating and carrying forward the proposal
      for the participation by the Company, along with others, in the so-called
      Navajo Project, involving the construction near Page, Arizona, of three
      generating units (presently estimated at 750 MW nameplate), with ownership
      being held as tenants in common in the following respective undivided
      interests:


                                                    
Arizona Public Service Company                         14.0%
Tucson Gas & Electric Company                           7.5%
City of Los Angeles                                    21.2%
Nevada Power Company                                   11.3%
Salt River Project Agricultural Improvement
 and Power District
(For ITSELF)                                           21.7%
(As Agent for U.S.B.R.)                                24.3%


      the said Project to include certain transmission facilities to be located
      in Arizona, with APS to be the Project Manager and Operating Agent for
      said facilities, which are to be owned by APS and others as joint tenants
      in various percentages related to projected use, these facilities
      including a 500 kv line from the switchyard of the Navajo Plant near Page
      to the Moenkopi Switching Station and from there to the Westwing
      switchyard year Phoenix, and with another 500 kv line extending directly
      from the Navajo switchyard to Westwing, together with various related
      interconnections and switching facilities; and

            FURTHER RESOLVED, that in connection with the Navajo Project, the
      appropriate officers of the Company be, and they are hereby authorized to
      negotiate and to execute and effectuate the necessary instruments and
      agreements, including among others, the following:



                  (1)   Participation Agreement

                  (2)   Coordination Agreement

                  (3)   Interconnection Agreement

                  (4)   Plant Site Lease

                  (5)   Fuel Supply and Transportation Agreement

                  (6)   Co-Tenancy Agreement

                  (7)   Moenkopi Agreement

                  (8)   Amendment to Navajo Wholesale Power Agreement

                  (9)   Plant Construction Agreement

                  (10)  Plant Operating Agreement

                  (11)  Transmission Construction Agreement

                  (12)  Transmission Operating Agreement

                  (13)  Applications for Various Rights-of-Way and Easements

                  (14)  Layoff Agreement

      and

            FURTHER RESOLVED, that the appropriate officers of the Company are
      authorized to take such actions and to execute such further agreements,
      instruments, applications, certificates, contracts or other documents as
      may be necessary or appropriate in connection with the foregoing to
      complete and effectuate the Company's proposed participation in the Navajo
      Project.

      IN WITNESS WHEREOF, I have hereunto set my hand and the seal of said
corporation this 26th day of August, 1970.

                                       /s/ Gerald J. Griffin
                                      ------------------------------------------
                                                 Assistant Secretary

                                      -2-

                                                             RESOLUTION NO.  132

      BE IT RESOLVED that upon approval by ordinance by the City Council of The
City of Los Angeles of the Amendment and Supplement #1 to Navajo Project
Participation Agreement (DWP No. 10334), the President or Vice President of the
Board, or the General Manager and Chief Engineer or the Assistant General
Manager and Chief Engineer of the Department of Water and Power, and the
Secretary or Assistant Secretary of the Board be and they are hereby authorized
and directed to execute said Amendment and Supplement #1 to Navajo Project
Participation Agreement (DWP No. 10334) on behalf of this Department upon
publication of the Ordinance.

      I HEREBY CERTIFY that the foregoing is a full, true and correct copy of a
resolution adopted by the Board of Water and Power Commissioners of The City of
Los Angeles at its meeting held Aug 20 1970

                                                               /s/ Mary J. Born
                                                               ----------------
                                                                    Secretary




                             ORDINANCE NO. 119,849

                                  CERTIFICATION

STATE OF CALIFORNIA,
                        }  ss.
COUNTY OF LOS ANGELES,

      I, REX E. LAYTON, City Clerk of the City of Los Angeles and ex-officio
Clerk of the City Council of the City of Los Angeles, do hereby certify and
attest the foregoing to be a full, true and correct copy of the original
Ordinance No. 140,840, passed by the City Council of Los Angeles at its meeting
of August 18, 1970, on file in my office, and that I have carefully compared the
same with the original.

                          In Witness Whereof, I have hereunto set my hand and
                          affixed the Seal of the City of Los Angles, this 20th
                          day of August, 1970

                              /s/ REX E. LAYTON

                              City clerk or the City of Los Angeles

                              /s/ Lee C. Gable
                           By -------------------------------------
                                             Deputy



                                  CERTIFICATION

      I, the undersigned, being the duly elected Secretary of Nevada Power
Company, certify and declare that the following are true and correct copies of
resolutions adopted by the Board of Directors at its meeting held September 19,
1969 and by the Executive Committee at its meeting held October 23, 1969,
respectively:

      RESOLVED: That the Executive Committee shall have the authority to
      authorize the signing of any and all contracts necessary to proceed with
      the Company's participation in the Navajo Project.

      RESOLVED: That the officers of the Company are hereby authorized to sign
      all contracts necessary to proceed with the Company's proposed
      participation in the Navajo Project, to take the necessary action to
      qualify to do business in the State of Arizona and to take any other steps
      necessary or incidental thereto.

      IN WITNESS WHEREOF, I have hereunto set my hand and affixed the corporate
seal of the corporation this 26th day of August, 1970.

                                     /s/ Samuel P. Cowley
                                     --------------------------------
                                     Samuel P. Cowley, Secretary

[SEAL]



                                   RESOLUTION

      WHEREAS, the Salt River Project Agricultural Improvement and Power
      District (Salt River Project) entered into a Participation Agreement dated
      September 30, 1969, to construct the Navajo Generating Project, and

      WHEREAS, it is in the interest of the Salt River Project to amend and
      supplement said Participation Agreement to include necessary conditions
      for the efficient and successful construction and operation of said Navajo
      Project through an Amendment and Supplement No. 1;

      NOW, THEREFORE, BE IT RESOLVED, That this Board hereby approves, ratifies
      and confirms entering into such Amendment and Supplement No. 1 and hereby
      directs, empowers, ratifies and confirms the execution and delivery of
      such document on behalf of the Salt River Project Agricultural Improvement
      and Power District by its President or Vice President and Secretary or
      Assistant Secretary.

                                   CERTIFICATE

      I, F. E. Smith, the duly appointed, qualified and acting Secretary of the
      Salt River Project Agricultural Improvement and Power District, HEREBY
      CERTIFY that the foregoing is a true and complete copy of a resolution
      adopted by the Board of Directors Of said District at a meeting thereof
      duly held on the 6th day of July 1970, at which meeting a quorum was
      present and voted.

      WITNESS my hand and seal of Salt River Project Agricultural Improvement
      and Power District this 26th day of August 1970.

                                               /s/ F.E. Smith
                                               ----------------------
                                               F. E. Smith, Secretary



                          TUCSON GAS & ELECTRIC COMPANY

                         Certified Copy of Resolutions
                       Adopted by the Board of Directors

      RESOLVED, that the proper officers of the Company be, and they hereby are
authorized to enter into a Participation Agreement between the United States of
America, Arizona Public Service Company, Department of Water and Power of the
City of Los Angeles, Nevada Power Company, Salt River Project Agricultural
Improvement and Power District and Tucson Gas & Electric Company for the
ownership of the Navajo Project wherein Tucson Gas & Electric Company shall own
an undivided 7-1/2% interest in the Navajo Generating Station and varying
percentage interests in the transmission system. The Agreement shall be
substantially in the form of the draft filed with the Secretary of the Company
marked "Filed September 23, 1969 with the Secretary of Tucson Gas & Electric
Company, and be it

      FURTHER RESOLVED, that the proper officers of the Company be, and they
hereby are further authorized to execute and enter into on behalf of the Company
the necessary Project Agreements contemplated by said Participation Agreement,
and such other documents reasonably required to implement said Participation
Agreement and Project Agreements.

                           * * * * * * * * * * * * *

      I, P. L. ABBOTT, Secretary of TUCSON GAS & ELECTRIC COMPANY (hereinafter
called the "Company"), DO HEREBY CERTIFY that the above and foregoing is a true
and complete copy of resolutions duly adopted by the Board of Directors at the
Regular Monthly Meeting held on the 23rd day of September, 1969, at which
meeting a quorum was present and acted thereon; and

      I DO FURTHER CERTIFY that said resolution is in full force and effect on
the date hereof.

      IN WITNESS WHEREOF, I have hereunto set my hand and affixed the seal of
the Company this 20th day of August, 1970.

                                                     /s/ Authorized Signatory
                                                     ------------------------
                                                             Secretary