the Company's legal obligation to fully repair the environmental damage caused by the dam rupture. Therefore, this provision may change in the future depending on several factors that are not under the control of the Company.
b) Provision for individual indemnification and other commitments
For the individual indemnification, Vale and the Public Defendants of the State of Minas Gerais formalized an agreement on April 5, 2019, under which those affected by the Brumadinho’s Dam failure may join an individual or family group out-of-Court settlement agreements for the indemnification of material, economic and moral damages. This agreement establishes the basis for a wide range of indemnification payments, which were defined according to the best practices and case law of Brazilian Courts, following rules and principles of the United Nations (“UN”). As at June 30, 2021, the provision recorded is US$158 (US$179 as at December 31, 2020).
In addition to the Global Settlement, the Company has been working to ensure geotechnical safety of the remaining structures at the Córrego do Feijão mine, in Brumadinho, and the removal and proper disposal of the tailings of Dam I. As at June 30, 2021, the provision recorded is US$252 (US$267 as at December 31, 2020).
In addition, the Company was notified of the imposition of administrative fines by the Brazilian Institute of the Environment and Renewable Natural Resources (“IBAMA”), in the amount of US$50 (R$250 million). The Company signed an agreement with IBAMA, of which US$30 (R$150 million) will be used in environmental projects in 7 parks in the state of Minas Gerais, covering an area of approximately 794 thousand hectares, and US$20 (R$100 million) will be used in basic sanitation programs in the state of Minas Gerais.
c) De-characterization of other dams in Brazil
Following the Brumadinho Dam rupture, the Company has decided to speed up the plan to “de-characterize” its tailings dams built under the upstream method (same method as Brumadinho’s dam), certain “centerline structures” and dikes, located in Brazil. The observable rate applied to the provision for the de-characterization of dams, increased from 3.5% at December 31, 2020 to 4.4% at June 30, 2021. The Company has a total provision to comply with these assumed obligations in the amount of US$2,155 at June 30, 2021 (US$2,289 as at December 31, 2020).
(c.i) Operation stoppages
The Company has suspended some operations due to judicial decisions or technical analysis performed by Vale on its upstream dam structures. The Company has been recording losses in relation to the operational stoppage and idle capacity of the ferrous mineral segment in the amounts of US$80 and US$193 for the three and six-months periods ended June 30, 2021 (US$104 and US$267 for the three and six-months periods ended June 30, 2020), respectively. The Company is working on legal and technical measures to resume all operations at full capacity.
d) Contingencies and other legal matters
(d.i) Requests for fines or forfeit of assets
On August 26, 2020, the Public Prosecutor's Office of Minas Gerais (“MPMG”) and other plaintiffs of the Public Civil Actions presented a request for ruling condemning Vale to indemnify alleged economic losses of the State of Minas Gerais and collective moral damages, both claims already considered in said Public Civil Actions filed against Vale in January 2019 as a result of the Brumadinho dam rupture. In that submission, the plaintiffs also requested the immediate freezing of US$5.1 billion (R$26.7 billion) from the Company as a guarantee for the reimbursement of the alleged economic losses, which was dismissed by the judge of the 2nd Lower Court of Public Treasury of Belo Horizonte on October 6, 2020. This claim was extinguished with the Global Settlement.
In other proceeding, in May 2020, the MPMG requested the imposition of fines or forfeit of assets, rights and amounts of the Company, allegedly based on Article 5, item V of Brazilian Law 12.846/2013. According to the MPMG, Vale would have, through its employee’s actions, hindered the inspection activities of public agencies in the complex. Vale was not required to present any guarantees of US$1.4 billion (R$7.9 billion) based on a judicial decision. The Company believes that the likelihood of loss is remote.
In January 2021, the Comptroller General of the State of Minas Gerais (“CGE”) notified Vale to present it defense against the Administrative Liability Proceeding (“PAR”) initiated based on the same article. Vale presented its defense in March 2021, and filed a writ of mandamus in the face of the establishment of this PAR, which had the injunction granted to suspend the proceeding of the PAR.