Bitdeer Technologies Group (NASDAQ:BTDR) ("Bitdeer" or the "Company"), a world-leading technology company for blockchain and high-performance computing, today announced its unaudited mining and operations updates for April 2024.
Linghui Kong, Chief Business Officer of Bitdeer, commented, "The month of April marked a period of stable operations for our company as we made steady progress towards our long-term development goals. We mined 265 Bitcoins in total during April, representing an increase of 13.7% from the same period last year and a decline of 9.9% from March 2024. This month-over-month decline was related to the impact of the latest Bitcoin halving event, which occurred on April 19, 2024. Our Gedu datacenter maintained stable operations throughout the month of April, thanks in large part to our power pricing agreement for the site, which has allowed us to operate the site with lower costs and without the need to curtail datacenter activity.
"In terms of infrastructure, the ground leveling work at our Jigmeling datacenter site in Bhutan is progressing as planned. At present, around 70% of the ground leveling work for substation construction has been completed. We have also confirmed with our suppliers the purchase plan for the electrical equipment required for the substation, which is expected to happen in June 2024. In the meantime, we are continuing to promote the development of our AI cloud service and ASIC mining machine projects, which are currently proceeding smoothly."
The Company primarily operates three distinct business lines:
- Self-mining refers to cryptocurrency mining for the Company's own account, which allows it to directly capture the high appreciation potential of cryptocurrency.
- Hash Rate Sharing currently primarily includes Cloud Hash Rate, in which the Company offers hash rate subscription plans and shares mining income with customers under certain arrangements.
- Hosting encompasses a one-stop mining machine hosting solution including deployment, maintenance, and management services for efficient cryptocurrency mining.
Operations Update
Metrics | April 2024 | March 2024 | April 2023 |
Total hash rate under management1 (EH/s) | 22.3 | 22.5 | 18.3 |
- Proprietary hash rate2 | 8.4 | 8.4 | 5.6 |
• Self-mining | 6.7 | 6.7 | 4.0 |
• Cloud Hash Rate | 1.7 | 1.7 | 1.6 |
- Hosting | 13.9 | 14.1 | 12.7 |
Mining machines under management | 224,000 | 226,000 | 196,000 |
- Self-owned3 | 86,000 | 86,000 | 66,000 |
- Hosted | 138,000 | 140,000 | 130,000 |
Aggregate electrical capacity4 (MW) | 895 | 895 | 795 |
Bitcoin mined (self-mining only)5 | 265 | 294 | 233 |
1 Total hash rate under management as of April 30, 2024 across the Company's primary business lines: Self-mining, Cloud Hash Rate, and Hosting.
2 Proprietary hash rate as of April 30, 2024 was 8.4 EH/s, equivalent to proprietary hash rate as of March 31, 2024.
3 Self-owned mining machines are for the Company's self-mining business and Cloud Hash Rate business.
4 Aggregate electrical capacity remained steady, totaling 895MW across six mining datacenters as of April 30, 2024.
5 Bitcoin mined in April 2024 increased by 13.7% compared to April 2023. Bitcoin mined in April 2024 declined by 9.9% compared to March 2024, primarily as a result of the impacts of the Bitcoin "halving" event that occurred in April 2024. Currently, the Company promptly converts the cryptocurrencies it obtains into fiat currency.
Infrastructure Update
The Company has continued to make progress in the construction of a 175MW immersion cooling datacenter at its mining facility in Tydal, Norway (the "Tydal Datacenter"). The expansion of the Tydal Datacenter is expected to be completed in mid-2025.
The Company has continued to make progress in the construction of a 221MW datacenter in Ohio, United States (the "Ohio Datacenter"). The land and power resources required for the Ohio Datacenter were secured during 2023. Construction of the Ohio Datacenter is expected to be completed in 2025.
The Company has made progress in the construction of a 500MW datacenter in Jigmeling, Bhutan (the "Jigmeling Datacenter"), which began construction in March 2024. Around 70% of the ground leveling work for the project substation area has been completed to date, and is expected to be fully completed by the end of May 2024. Ground leveling work for the mining datacenter area had commenced as of the beginning of May 2024. The Company has also confirmed its plan to procure the substation's electrical equipment with a supplier, and expects that such equipment will be purchased by June 2024. The Jigmeling Datacenter is expected to be completed in mid-2025.
Manufacturing Update
The Company's mining machines project is progressing as planned. As of now, all laboratory testing and preparations for batch production have been completed. The Company will conduct small batch trial production in May and June 2024. The mining machines produced during the trial production will be delivered to the Company's own mining datacenters for stability testing.