WBS | Description | Initial Capital | Sustaining Capital | Total |
1000 | Open Pit Mining | 415.2 | 192.7 | 607.9 |
2000 | Process Plant | 910.6 | n/a | 910.6 |
3000 | Earthworks, Tailings and Water Management | 651.3 | 842.9 | 1,494.2 |
4000 | On-Site Infrastructure | |||
Site General | 127.6 | n/a | 127.6 | |
Water Treatment Plants | 315.5 | n/a | 315.5 | |
On-Site Infrastructure | 251.7 | n/a | 251.7 | |
5000 | Off-Site Infrastructure | |||
Power Supply | 702.6 | n/a | 702.6 | |
Natural Gas Line | 505.3 | n/a | 505.3 | |
Marine Terminal Site | 253.5 | n/a | 253.5 | |
Ferry | 54.3 | n/a | 54.3 | |
External Access Roads | 507.4 | 18.4 | 525.8 | |
Total Directs | 4,694.9 | 1,054.1 | 5,749.0 | |
6000 | Indirect Costs | 917.9 | 99.9 | 1,017.8 |
7000 | Owner's Costs | 353.0 | 10.0 | 363.0 |
8000 | Contingency | 806.8 | 129.1 | 936.0 |
Total | 6,772.6 | 1,293.1 | 8,065.6 | |
Closure Costs1 | - | 2,755.7 | 2,755.7 |
40-F
2023 FY
NAK
Northern Dynasty Minerals Ltd.
2 Apr 24
Annual report (Canada)
6:03am
Operating Area | Annual Cost (US$M) | LOM Average Cost (US$/ton milled) |
General & Administrative | 62.5 | 0.97 |
Open Pit Mining | 127.2 | 1.97 |
Mineralized Material Handling & Process Plant | 321.7 | 4.99 |
Tailings Operation & Maintenance | 14.4 | 0.22 |
Water Treatment Plant | 24.6 | 0.38 |
Marine Facilities | 33.3 | 0.52 |
Ferry | 13.9 | 0.22 |
Access Road1 | 16.3 | 0.25 |
Infrastructure Lease | 286.5 | 4.44 |
Total | 900.3 | 13.95 |