COMMITMENTS, CONTINGENCIES, AND ENVIRONMENTAL MATTERS | 9 Months Ended |
Sep. 30, 2014 |
Commitments and Contingencies Disclosure [Abstract] | ' |
COMMITMENTS, CONTINGENCIES, AND ENVIRONMENTAL MATTERS | ' |
COMMITMENTS, CONTINGENCIES, AND ENVIRONMENTAL MATTERS |
COMMITMENTS |
In addition to those reported in our 2013 Annual Report on Form 10-K, TEP entered into the following long-term commitments through September 30, 2014: |
|
| | | | | | | | | | | | | | | | | | | | | | | | | | | |
| 2014 | | 2015 | | 2016 | | 2017 | | 2018 | | Thereafter | | Total |
| Millions of Dollars |
Fuel, Including Transportation | $ | — | | | $ | 9 | | | $ | 9 | | | $ | 10 | | | $ | 10 | | | $ | 42 | | | $ | 80 | |
|
Purchased Power | — | | | 18 | | | — | | | — | | | — | | | — | | | 18 | |
|
Renewable Power Purchase Agreements (PPA)(2) | 6 | | | 5 | | | 5 | | | 5 | | | 5 | | | 60 | | | 86 | |
|
Capital Lease Obligations(1) | — | | | 120 | | | — | | | — | | | — | | | — | | | 120 | |
|
Total Purchase Commitments | $ | 6 | | | $ | 152 | | | $ | 14 | | | $ | 15 | | | $ | 15 | | | $ | 102 | | | $ | 304 | |
|
| | | | | | | | | | | | | | | | | | | | | | | | | | | |
(1) | In April 2014, TEP entered into agreements to purchase certain Springerville Coal Handling Facilities leased interests. See Note 4. | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | |
(2) | In July 2014, TEP entered into a 20-year PPA with a renewable energy generation facility that achieved commercial operation in July 2014. TEP is obligated to purchase 100% of the output from this facility. The amounts in the table also reflect updated estimated annual production for existing contracts which increased the minimum annual payment obligations. | | | | | | | | | | | | | | | | | | | | | | | | | | |
CONTINGENCIES |
Planned Purchase of Gas-Fired Generation Facility |
In 2013, TEP and UNS Electric, an affiliate of TEP, entered into an agreement to purchase a gas-fired generation facility. See Note 6. |
Claims Related to San Juan Generating Station |
San Juan Coal Company (SJCC) operates an underground coal mine in an area where certain gas producers have oil and gas leases with the federal government, the State of New Mexico, and private parties. These gas producers allege that SJCC’s underground coal mine interferes with their operations, reducing the amount of natural gas they can recover. SJCC compensated certain gas producers for any remaining production from wells deemed close enough to the mine to warrant plugging and abandoning them. These settlements, however, do not resolve all potential claims by gas producers in the area. TEP owns 50% of Units 1 and 2 at San Juan Generating Station (San Juan), which represents approximately 20% of the total generation capacity at San Juan, and is responsible for its share of any settlements. TEP cannot estimate the impact of any future claims by these gas producers on the cost of coal at San Juan. |
In August 2013, the Bureau of Land Management (BLM) proposed regulations that, among other things, redefine the term “underground mine” to exclude high-wall mining operations and impose a higher surface mine coal royalty on high-wall mining. SJCC utilized high-wall mining techniques at its surface mines prior to beginning underground mining operations in January 2003. If the proposed regulations become effective, SJCC may be subject to additional royalties on coal delivered to San Juan between August 2000 and January 2003 totaling approximately $5 million of which TEP’s proportionate share would approximate $1 million. TEP cannot predict the final outcome of the BLM’s proposed regulations. |
Claims Related to Four Corners Generating Station |
In October 2011, EarthJustice, on behalf of several environmental organizations, filed a lawsuit in the United States District Court for the District of New Mexico against Arizona Public Service Company (APS) and the other Four Corners Generating Station (Four Corners) participants alleging violations of the Prevention of Significant Deterioration (PSD) provisions of the Clean Air Act at Four Corners. In January 2012, EarthJustice amended their complaint alleging violations of New Source Performance Standards resulting from equipment replacements at Four Corners. Among other things, the plaintiffs seek to have the court issue an order to cease operations at Four Corners until any required PSD permits are issued and order the payment of civil penalties, including a beneficial mitigation project. In April 2012, APS filed motions to dismiss with the court for all claims asserted by EarthJustice in the amended complaint. In August 2014, APS submitted a counteroffer with revised settlement terms. The joint participants have agreed to have the matter stayed until November 2014 to make continued progress toward a final agreement that would resolve this matter without further litigation. |
TEP owns 7% of Four Corners Units 4 and 5 and is liable for its share of any resulting liabilities. TEP's estimated share of the settlement offer submitted by APS in August 2014 is less than $1 million. TEP cannot predict the final outcome of the claims relating to Four Corners, and, due to the general and non-specific nature of the claims and the indeterminate scope and nature of the injunctive relief sought for this claim, TEP cannot determine estimates of the range of costs at this time. |
In May 2013, the New Mexico Taxation and Revenue Department issued a notice of assessment for coal severance tax, penalties, and interest totaling $30 million to the coal supplier at Four Corners. In December 2013, the coal supplier and Four Corners’ operating agent filed a claim contesting the validity of the assessment on behalf of the participants in Four Corners, who will be liable for their share of any resulting liabilities. TEP’s share of the assessment based on its ownership of Four Corners is approximately $1 million. The New Mexico Taxation and Revenue Department and APS started settlement negotiations in July 2014. TEP cannot predict the outcome or timing of resolution of this claim. |
Mine Closure Reclamation at Generating Stations Not Operated by TEP |
TEP pays ongoing reclamation costs related to coal mines that supply generating stations in which TEP has an ownership interest but does not operate. TEP is liable for a portion of final reclamation costs upon closure of the mines servicing Navajo, San Juan, and Four Corners. TEP’s share of reclamation costs at all three mines is expected to be $44 million upon expiration of the coal supply agreements, which expire between 2017 and 2031. The reclamation liability (present value of future liability) recorded was $21 million at September 30, 2014 and $18 million at December 31, 2013. |
Amounts recorded for final reclamation are subject to various assumptions, such as estimations of reclamation costs, the dates when final reclamation will occur, and the credit-adjusted risk-free interest rate to be used to discount future liabilities. As these assumptions change, TEP will prospectively adjust the expense amounts for final reclamation over the remaining coal supply agreements’ terms. TEP does not believe that recognition of its final reclamation obligations will be material to TEP in any single year because recognition will occur over the remaining terms of its coal supply agreements. |
TEP’s PPFAC allows us to pass through most fuel costs, including final reclamation costs, to customers. Therefore, TEP classifies these costs as a regulatory asset by increasing the regulatory asset and the reclamation liability over the remaining life of the coal supply agreements and recovers the regulatory asset through the PPFAC as final mine reclamation costs are paid to the coal suppliers. |
Discontinued Transmission Project |
TEP and UNS Electric had initiated a project to jointly construct a 60-mile transmission line from Tucson, Arizona to Nogales, Arizona in response to an order by the ACC to UNS Electric to improve the reliability of electric service in Nogales. At this time, TEP and UNS Electric will not proceed with the project based on the cost of the proposed 345-kV line, the difficulty in reaching agreement with the United States Forest Service on a path for the line, and concurrence by the ACC that recent transmission additions by TEP and UNS Electric support elimination of this project. TEP and UNS Electric plan to keep the path approved in the line siting matter in contemplation of using a greater part of the route to serve future customers and to address reliability needs. As part of the 2013 TEP Rate Order, TEP agreed to seek recovery of the project costs from the FERC before seeking rate recovery from the ACC. In 2012, TEP wrote off $5 million of the capitalized costs believed not probable of recovery and recorded a regulatory asset of $5 million for the balance deemed probable of recovery in TEP's next FERC rate case. |
Performance Guarantees |
The participants in each of the remote generating stations in which TEP participates, including TEP, have guaranteed certain performance obligations of the other participants. Specifically, in the event of payment default of a participant, the non-defaulting participants have agreed to bear a proportionate share of expenses otherwise payable by the defaulting participant. In exchange, the non-defaulting participants are entitled to receive their proportionate share of the generating capacity of the defaulting participants. As of September 30, 2014, there have been no such payment defaults under any of the remote generating station agreements. TEP's joint participation agreements expire in 2016 through 2046. |
ENVIRONMENTAL MATTERS |
Environmental Regulation |
The Environmental Protection Agency (EPA) limits the amount of sulfur dioxide (SO2), nitrogen oxide (NOx), particulate matter, mercury and other emissions released into the atmosphere by power plants. TEP may incur added costs to comply with future changes in federal and state environmental laws, regulations, and permit requirements at its power plants. Complying with these changes may reduce operating efficiency. TEP expects to recover the cost of environmental compliance from its ratepayers. |
Hazardous Air Pollutant Requirements |
In February 2012, the EPA issued final rules for the control of mercury emissions and other hazardous air pollutants from power plants. Based on the EPA's final Mercury and Air Toxics (MATS) rules, additional emission control equipment will be required by April 2015. TEP, as operator of Springerville and Sundt, and the operator of Navajo have received extensions until April 2016 to comply with the MATS rules. TEP's share of the estimated costs to comply with the MATS rules includes the following: |
| | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | |
Estimated Mercury Emissions Control Costs: | Navajo | | Springerville(1) | | | | | | | | | | | | | | | | | | | | |
| Millions of Dollars | | | | | | | | | | | | | | | | | | | | |
Capital Expenditures | $ | 1 | | | $ | 5 | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | |
Annual O&M Expenses | 1 | | | 1 | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | |
(1) | Total capital expenditures and annual O&M expenses represent amounts for both Springerville Units 1 & 2, with estimated costs split equally between the two units. TEP will own 49.5% of Springerville Unit 1 upon close of the lease option purchases in January 2015; after the completion of such purchases, third party owners will be responsible for 50.5% of environmental costs attributable to Springerville Unit 1. TEP will continue to be responsible for 100% of environmental costs attributable to Springerville Unit 2. | | | | | | | | | | | | | | | | | | | | | | | | | | |
TEP expects Four Corners, Sundt, and San Juan's current emission controls to be adequate to comply with the EPA's MATS rules. A study determined that Four Corners' emission controls are adequate. Therefore, TEP expects no additional capital expenditures or O&M expenses will be incurred to comply. Although expected to be compliant, Sundt would be required to install additional monitoring equipment, at an estimated cost of less than $1 million, to continue to burn coal after the MATS rules become effective. |
Regional Haze Rules |
The EPA's Regional Haze Rules require emission controls known as Best Available Retrofit Technology (BART) for certain industrial facilities emitting air pollutants that reduce visibility in national parks and wilderness areas. The rules call for all states to establish goals and emission reduction strategies for improving visibility. States must submit these goals and strategies to the EPA for approval. Because Navajo and Four Corners are located on the Navajo Indian Reservation, they are not subject to state oversight; the EPA oversees regional haze planning for these power plants. |
In the western U.S., Regional Haze BART determinations have focused on controls for NOx, often resulting in a requirement to install selective catalytic reduction (SCR). Complying with the EPA’s BART rules, and with other future environmental rules, may make it economically impractical to continue operating all or a portion of the Navajo, San Juan, and Four Corners power plants or for individual owners to continue to participate in these power plants. BART provisions of Regional Haze Rules requiring emission control upgrades do not apply to Springerville because the BART rules apply to plants built prior to Springerville. TEP cannot predict the ultimate outcome of these matters. |
TEP's estimated costs involved in meeting these rules are: |
| | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | |
Estimated NOx Emissions Control Costs: | Navajo (1) | | San Juan (2) | | Four Corners (3) | | Sundt (4) | | | | | | | | | | | | |
| Millions of Dollars | | | | | | | | | | | | |
Capital Expenditures | $ | 42 | | | $ | 35 | | | $ | 35 | | | $ | 12 | | | | | | | | | | | | | |
| | | | | | | | | | | |
Annual O&M Expenses | 1 | | | 1 | | | 2 | | | 6-May | | | | | | | | | | | | | |
| | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | |
-1 | In August 2014, the EPA published a final rule approving a better-than-BART plan wherein: one unit at Navajo will be shut down by 2020; SCR (or the equivalent) will be installed on the remaining two units by 2030; and conventional coal-fired generation will cease by December 2044. In addition, the installation of SCR technology could increase particulates which may require that baghouses be installed. TEP owns 7.5% of Navajo. TEP's share of the capital cost of baghouses in addition to the SCR costs reflected in the table above is approximately $43 million with O&M on the baghouses expected to be less than $1 million per year. | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | |
-2 | In October 2014, the EPA published a final rule approving a state plan covering BART requirements for San Juan, which includes the closure of Units 2 and 3 by December 2017 and the installation of selective non-catalytic reduction (SNCR) on Units 1 and 4 by January 2016. Corresponding to that action, the EPA withdrew the previously applicable FIP addressing the same requirements. Prior to the shutdown of any units in San Juan, PNM must obtain New Mexico Public Regulation Commission approval. If Unit 2 is retired early, TEP expects to request ACC approval to recover all costs associated with the early closure of the unit. TEP owns 50% of San Juan Unit 2. At September 30, 2014, the net book value of TEP's share in San Juan Unit 2 was $111 million. | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | |
-3 | In December 2013, APS, on behalf of the co-owners of Four Corners, notified the EPA that they have chosen an alternative BART compliance strategy; as a result, APS closed Units 1, 2, and 3 in December 2013 and has agreed to the installation of SCR on Units 4 & 5 by July 2018. TEP owns 7% of Four Corners Units 4 and 5. | | | | | | | | | | | | | | | | | | | | | | | | | | |
(4) In June 2014, the EPA issued a final rule that would require TEP to either (i) install SNCR and dry sorbent injection technology on Unit 4 by mid-2017 or (ii) eliminate the use of coal by the end of 2017 as a better-than-BART alternative. TEP is required to notify the EPA of its decision by March 2017. At September 30, 2014, the net book value of the Sundt coal handling facilities was $17 million. If the coal handling facilities are retired early, TEP expects to request ACC approval to recover all the remaining costs of the coal handling facilities. |