COMMITMENTS AND CONTINGENCIES: | NOTE 12-COMMITMENTS AND CONTINGENCIES: Environmental matters: The Company has instituted extensive environmental conservation programs at its mining facilities in Peru and Mexico. The Company’s environmental programs include, among others, water recovery systems to conserve water and minimize the impact on nearby streams, reforestation programs to stabilize the surface of the tailings dams and the implementation of scrubbing technology in the mines to reduce dust emissions. Environmental capital investments in years 2018, 2017 and 2016, were as follows (in millions): 2018 2017 2016 Peruvian operations $ 59.3 $ 93.7 $ 110.3 Mexican operations 43.5 128.9 140.1 Total $ 102.8 $ 222.6 $ 250.4 Peruvian operations : The Company’s operations are subject to applicable Peruvian environmental laws and regulations. The Peruvian government, through the Ministry of Environment (“MINAM”) conducts annual audits of the Company’s Peruvian mining and metallurgical operations. Through these environmental audits, matters related to environmental obligation, compliance with legal requirements, atmospheric emissions, effluent monitoring and waste management are reviewed. The Company believes that it is in material compliance with applicable Peruvian environmental laws and regulations. Peruvian law requires that companies in the mining industry provide assurances for future mine closure and remediation. In accordance with the requirements of this law, the Company’s closure plans were approved by MINEM. See Note 6 “Asset retirement obligation,” for further discussion of this matter. Air Quality Standards (“AQS”): In June 2017, MINAM enacted a supreme decree which defines new AQS for daily sulfur dioxide in the air. The Company believes that these new AQS will allow Peruvian industry to be more competitive with other countries. As of December 31, 2018, the Company maintains a lower daily average level of µg/m3 of SO2, than those required by the new AQS. Soil Environmental Quality Standards (“SQS”): In 2013, the Peruvian government enacted SQS applicable to any existing facility or project that generates or could generate the risk of soil contamination in its area of operation or influence. In March 2014, MINAM issued a supreme decree, which established additional provisions for the gradual implementation of SQS. Pursuant to this regulation, the Company had twelve months to identify contaminated sites in and around its facilities and present a report of identified contaminated sites. These documents were submitted to MINEM for approval in April 2015, and were fully approved in July 2017. The next step is for the Company to prepare a characterization study to determine the depth, extent and physio-chemical composition of the contaminated areas and define an appropriate remediation plan with a time-frame for completion. In addition, the Company must submit a Soil Decontamination Plan ("SDP") for approval within 30 months after being notified by the authority. This SDP must include remediation actions, a schedule and compliance deadlines. Pursuant to this regulation, the Company may request a one year extension for the decontamination plan if deemed necessary with reasonable justification. Soil confirmation tests must be carried out after completion of the decontamination actions (within the approved schedule) and results must be presented to authorities within 30 days after receiving such results. Although no specific sanctions have been established yet, non-compliance with this obligation or with decontamination goals will carry penalties for companies. However, companies cannot be penalized for non-compliance with the SQS during the schedule set forth for compliance. In accordance with the regulatory requirements, the Company has been working on the characterization phase and SDPs for environmentally impacted sites in each of its operating units (Toquepala, Cuajone, and Ilo) with the assistance of consulting companies. It is estimated that the Toquepala and Cuajone SDPs will be presented to the authorities for review and approval at the end of the second quarter of 2019, and the Ilo SDP will be submitted during the third quarter of 2019. While the Company believes that there is a reasonable possibility that a potential loss contingency may exist, it cannot currently reasonably estimate the amount of the contingency. The Company believes that a reasonable determination of the loss will be possible once the characterization study and the SDP are substantially completed, which is expected for the third quarter of 2019. At that time the Company will be in a position to estimate the remediation cost. Furthermore, the Company does not believe that it can estimate a reasonable range of possible costs until the noted studies have substantially progressed and therefore is not able to disclose a range of costs that is meaningful. Water Quality Standards (“WQS”): In June 2017, MINAM enacted a supreme decree which establishes water quality standards in the Peruvian territory. The adoption of these standards have not a material impact on its financial position. Mexican operations : The Company’s operations are subject to applicable Mexican federal, state and municipal environmental laws, to Mexican official standards, and to regulations for the protection of the environment, including regulations relating to water supply, water quality, air quality, noise levels and hazardous and solid waste. The principal legislation applicable to the Company’s Mexican operations is the Federal General Law of Ecological Balance and Environmental Protection (the “General Law”), which is enforced by the Federal Bureau of Environmental Protection (“PROFEPA”). PROFEPA monitors compliance with environmental legislation and enforces Mexican environmental laws, regulations and official standards. It may also initiate administrative proceedings against companies that violate environmental laws, which in the most extreme cases may result in the temporary or permanent shutdown of non-complying facilities, the revocation of operating licenses and/or other sanctions or fines. In 2011, the General Law was amended, giving an individual or entity the ability to contest administrative acts, including environmental authorizations, permits or concessions granted, without the need to demonstrate the actual existence of harm to the environment as long as it can be argued that the harm may be caused. In addition, in 2011, amendments to the Civil Federal Procedures Code (“CFPC”) were enacted. These amendments establish three categories of collective actions by means of which 30 or more people claiming injury derived from environmental, consumer protection, financial services and economic competition issues will be considered to be sufficient in order to have a legitimate interest to seek through a civil procedure restitution or economic compensation or suspension of the activities from which the alleged injury derived. The amendments to the CFPC may result in more litigation, with plaintiffs seeking remedies, including suspension of the activities alleged to cause harm. In 2013, the Environmental Liability Federal Law was enacted. The law establishes general guidelines for actions to be considered to likely cause environmental harm. If a possible determination regarding harm occurs, environmental clean-up and remedial actions sufficient to restore environment to a pre-existing condition should be taken. Under this law, if restoration is not possible, compensation measures should be provided. Criminal penalties and monetary fines can be imposed under this law. On February 2019, the Mexican Supreme Court confirmed the constitutionality of an ecological tax to extractive activities developed in the state of Zacatecas, which taxes the environmental remediation actions, emissions of certain gases to the atmosphere, emissions of pollutant substances to the soil or water, and waste storage within the state territory. The Company is evaluating the potential impact of this new environmental regulation in its financial position. The Company believes that all of its facilities in Peru and Mexico are in material compliance with applicable environmental, mining and other laws and regulations. The Company also believes that continued compliance with environmental laws of Mexico and Peru will not have a material adverse effect on the Company’s business, properties, result of operations, financial condition or prospects and will not result in material capital investments. Litigation matters : Peruvian operations The Tia Maria Mining Project There are three lawsuits filed against the Peruvian Branch of the Company related to the Tia Maria project. The lawsuits seek (i) to declare null and void the resolution which approved the Environmental Impact Assessment of the project; (ii) the cancellation of the project and the withdrawal of mining activities in the area and (iii) to declare null and void the mining concession application of the Tia Maria project. The lawsuits were filed by Messrs. Jorge Isaac del Carpio Lazo (filed May 22, 2015), Ernesto Mendoza Padilla (filed May 26, 2015) and Juan Alberto Guillen Lopez (filed June 18, 2015). The del Carpio Lazio case was rejected by the court of first instance on November 14, 2016. The plaintiff filed an appeal before the Superior Court on January 3, 2017. On January 9, 2018, the lawyers of both parties presented their respective positions before the Appellate Court. On March 8, 2018, the Appellate Court issued its final decision, which upholds the first instance ruling. On April 27, 2018, the plaintiff filed an extraordinary appeal before the Supreme Court. As of December 31, 2018, the case remains pending resolution. The Mendoza Padilla case was initially rejected by the lower court on July 8, 2015. This ruling was confirmed by the Superior Court on June 14, 2016. On July 12, 2016, the case was appealed before the Constitutional Court. As of December 31, 2018, the case remains pending resolution without further developments. The Guillen Lopez case is currently before the lower court. As of December 31, 2018, the case remains pending resolution without further developments. The Company asserts that these lawsuits are without merit and is vigorously defending against them. The potential contingency amount for these cases cannot be reasonably estimated by management at this time. Special Regional Pasto Grande Project (“Pasto Grande Project”) In 2012, the Pasto Grande Project, an entity of the Regional Government of Moquegua, filed a lawsuit against SCC’s Peruvian Branch alleging property rights over a certain area used by the Peruvian Branch and seeking the demolition of the tailings dam where SCC’s Peruvian Branch has deposited its tailings from the Toquepala and Cuajone operations since 1995. The Peruvian Branch has had title to use the area in question since 1960 and has constructed and operated the tailings dams with proper governmental authorization, since 1995. Upon a motion filed by the Peruvian Branch, the lower court has included MINEM as a defendant in this lawsuit. MINEM has answered the complaint and denied the validity of the claim. As of December 31, 2018, the case remains pending resolution without further developments. SCC’s Peruvian Branch asserts that the lawsuit is without merit and is vigorously defending against it. The amount of this contingency cannot be reasonably estimated by management at this time. Mexican operations The 2014 Accidental Spill at Buenavista Mine In relation to the 2014 accidental spill of copper sulfate solution that occurred at a leaching pond of the Buenavista mine, the following legal procedures are pending against the Company: On August 19, 2014, PROFEPA, as part of the administrative proceeding initiated after the spill, announced the filing of a criminal complaint against Buenavista del Cobre S.A. de C.V. (“BVC”), a subsidiary of the Company, in order to determine those responsible for the environmental damages. During the second quarter of 2018, the criminal complaint was dismissed. This decision was appealed and remains pending resolution. Through the first half of 2015, six collective action lawsuits were filed in federal courts in Mexico City and Sonora against two subsidiaries of the Company seeking economic compensation, clean up and remedial activities in order to restore the environment to its pre-existing conditions. Two of the collective action lawsuits have been dismissed by the court. The plaintiffs in the four remaining lawsuits are: Acciones Colectivas de Sinaloa, A.C. which established two collective actions, Defensa Colectiva A.C.; and Ana Luisa Salazar Medina et al. which has been granted a collective action certification. The remaining plaintiffs have requested cautionary measures on the construction of facilities for the monitoring of public health services and the prohibition of the closure of the Río Sonora Trust. As of December 31, 2018, these cases remain pending resolution. Similarly, during 2015, eight civil action lawsuits were filed against BVC in the state courts of Sonora seeking damages for alleged injuries and for moral damages as a consequence of the spill. The plaintiffs in the state court lawsuits are: Jose Vicente Arriola Nunez et al; Santana Ruiz Molina et al; Andres Nogales Romero et al; Teodoro Javier Robles et al; Gildardo Vasquez Carvajal et al; Rafael Noriega Souffle et al; Grupo Banamichi Unido de Sonora El Dorado, S.C. de R.L. de C.V; and Marcelino Mercado Cruz. In 2016, three additional civil action lawsuits, claiming similar damages, were filed by Juan Melquicedec Lebaron; Blanca Lidia Valenzuela Rivera et al and Ramona Franco Quijada et al. In 2017, BVC was served with thirty-three additional civil action lawsuits, claiming similar damages. The lawsuits were filed by Francisco Javier Molina Peralta et al; Anacleto Cohen Machini et al; Francisco Rafael Alvarez Ruiz et al; Jose Alberto Martinez Bracamonte et al; Gloria del Carmen Ramirez Duarte et al; Flor Margarita Sabori et al; Blanca Esthela Ruiz Toledo et al; Julio Alfonso Corral Dominguez et al; Maria Eduwiges Bracamonte Villa et al; Francisca Marquez Dominguez et al; Jose Juan Romo Bravo et al; Jose Alfredo Garcia Leyva et al; Gloria Irma Dominguez Perez et al; Maria del Refugio Romero et al; Miguel Rivas Medina et al; Yolanda Valenzuela Garrobo et al; Maria Elena Garcia Leyva et al; Manuel Alfonso Ortiz Valenzuela et al; Francisco Alberto Arvayo Romero et al; Maria del Carmen Villanueva Lopez et al; Manuel Martin Garcia Salazar; Miguel Garcia Arguelles et al; Dora Elena Rodriguez Ochoa et al; Honora Eduwiges Ortiz Rodriguez et al; Francisco Jose Martinez Lopez et al; Maria Eduwiges Lopez Bustamante; Rodolfo Barron Villa et al, Jose Carlos Martinez Fernandez et al, Maria de los Angeles Fabela et al; Rafaela Edith Haro et al; Luz Mercedes Cruz et al; Juan Pedro Montaño et al; and Juana Irma Alday Villa. During the first quarter of 2018, BVC was served with another civil action lawsuit, claiming similar damages. The lawsuit was filed by Alma Angelina Del Cid Rivera et al. During the last quarter of 2018, BVC was served with other three civil action lawsuits, claiming similar damages, such lawsuits were filed by Los Corrales de la Estancia, S.C. de R.L.; Jose Antonio Navarro; Jesus Maria Peña Molina, et al. As of December 31, 2018, these cases remain pending resolution. During 2015, four constitutional lawsuits (juicios de amparo) were filed before Federal Courts against various authorities and against a subsidiary of the Company, arguing; (i) the alleged lack of a waste management program approved by SEMARNAT; (ii) the alleged lack of a remediation plan approved by SEMARNAT with regard to the August 2014 spill; (iii) the alleged lack of community approval regarding the environmental impact authorizations granted by SEMARNAT to one subsidiary of the Company; and (iv) the alleged inactivity of the authorities with regard of the spill in August 2014. The plaintiffs of these lawsuits are: Francisca Garcia Enriquez, et al which established two lawsuits, Francisco Ramon Miranda, et al and Jesus David Lopez Peralta et al. During the third quarter of 2016, four additional constitutional lawsuits, claiming similar damages were filed by Mario Alberto Salcido et al; Maria Elena Heredia Bustamante et al; Martin Eligio Ortiz Gamez et al; and Maria de los Angeles Enriquez Bacame et al. During the third quarter of 2017, BVC was served with another constitutional lawsuit filed by Francisca García Enriquez et al. In 2018, BVC was served with two additional constitutional lawsuits that were filed against SEMARNAT by Norberto Bustamante et al. Regarding the constitutional lawsuit filed by Maria Elena Heredia Bustamante et al; in which it was claimed the lack of community approval regarding the authorization granted by SEMARNAT to build the new BVC tailings dam, on September 5, 2018, the Supreme Court of Justice issued a resolution which established that such authorization was granted to BVC in compliance with the applicable legislation. However, SEMARNAT must carry out a public meeting to inform the community of the technical aspects required to build the dam, potential impacts and prevention measures, with no material effects to BVC’s operations. As of December 31, 2018, the remaining cases are still pending resolution. It is not currently possible to determine the extent of the damages sought in these state and federal lawsuits but the Company considers that these lawsuits are without merit. Accordingly, the Company is vigorously defending against them. Nevertheless, the Company considers that none of the legal proceedings resulting from the spill, individually or in the aggregate, would have a material effect on its financial position or results of operations. Corporate operations Carla Lacey, on behalf of herself and all other similarly situated stockholders of Southern Copper Corporation, and derivatively on behalf of Southern Copper Corporation As previously reported, a purported class action derivative lawsuit filed in the Delaware Court of Chancery was served on the Company and its Directors in February 2016 relating to the 2012 capitalization of 99.999% of MGE by Controladora de Infraestructura Energetica Mexico, S.A. de C.V., an indirect subsidiary of Grupo Mexico (the “CIEM Capitalization”), the Company’s entry into a power purchase agreement with MGE in 2012 (the “MGE Power Purchase Agreement”), and the 2012 restructuring of a loan from the Company’s Mexican Operations to MGE for the construction of two power plants to supply power to the Company’s Mexican operations (the “MGE Loan Restructuring”). The action purports to be brought on behalf of the Company and its common stockholders. The complaint alleges, among other things, that the CIEM Capitalization, the MGE Power Purchase Agreement and the MGE Loan Restructuring were the result of breaches of fiduciary duties and the Company’s charter. On March 20, 2018, the parties reached an agreement-in-principle to settle the action. On March 23, 2018, the parties informed the Court of the settlement-in-principle to resolve all claims asserted by Plaintiff against Defendants in the action and requested that the Court stay the action in its entirety pending filing by the parties of a stipulation of settlement. The Parties filed the executed stipulation on August 22, 2018. Under the proposed settlement, Grupo Mexico or Americas Mining would pay to the Company $50 million in cash less any attorneys’ fees (including costs) awarded by the Court to Plaintiff’s counsel (the “Net Settlement Amount”) in return for a release of all derivative and direct claims. A settlement hearing was held on November 27, 2018. On December 27, 2018, the Court issued its ruling approving the $50 million settlement. Pursuant to the Court’s ruling, Plaintiff’s counsel was awarded $13.5 million (for attorneys’ fees, expenses, and a $5,000 incentive fee award to plaintiff Carla Lacey). The remaining $36.5 million was distributed via a special dividend on February 21, 2019 to the Company’s public stockholders (other than the director defendants, Grupo Mexico, Americas Mining, or any entity in which Grupo Mexico or Americas Mining has or had a direct or indirect controlling interest) who held shares of common stock of the Company as of February 11, 2019. As result of the payment of the settlement, the claims against the Defendants have been dismissed with prejudice. Labor matters : Peruvian operations: 75% of the Company's 4,850 Peruvian employees were unionized at December 31, 2018. Currently, there are six separate unions, one large union and five smaller unions. In the first quarter of 2016, the Company signed three-year agreements with all the existing unions at that time. These agreements included, among other things, annual salary increases of 5% for each of the three years. In June 2018, the Company signed a three-year collective bargaining agreement with one of the smaller unions. This agreement includes, among other things, annual salary increases of 5% for each year starting September 2018, and a signing bonus of S/ 45,000 (approximately $13,600) which was recorded as labor expense. In August 2018, the Company signed a three-year collective bargaining agreement with three additional unions. This agreement includes, among other things, annual salary increases of 5% for each year starting December 2018, and a signing bonus of S/ 45,000 (approximately $13,600) which was recorded as labor expense. As of December 31, 2018, the Company continues negotiations on collective bargaining agreements with the two unsigned unions. Mexican operations: In recent years, the Mexican operations have experienced a positive improvement of their labor environment, as its workers opted to change their affiliation from the Sindicato Nacional de Trabajadores Mineros, Metalurgicos y Similares de la Republica Mexicana (the “National Mining Union”) to other less politicized unions. The workers of the San Martin mine were on strike since July 2007. On February 28, 2018, the striking workers of the San Martín mine of IMMSA held an election to vote on the union that will hold the collective bargaining agreement at the San Martín mine. The Federacion Nacional de Sindicatos Independientes (the National Federation of Independent Unions), won the vote by a majority. Nevertheless, the vote was challenged by the National Mining Union. On June 26, 2018, the Federal Mediation and Arbitration Board issued a ruling recognizing the election results. Due to the agreement between workers and the Company to end the protracted strike, on August 22, 2018, the Federal Mediation and Arbitration Board authorized the restart of operations of the San Martín mine. Such authorization was challenged by the National Mining Union. The Company is working on a rehabilitation plan to restart operations at the San Martin mine with a budget of $77 million. At December 31, 2018 the plan is in progress with a total expense of $17.7 million. The Company is restoring mining operations in the first quarter of 2019 and expects to restore copper production in the second quarter of 2019. In the case of the Taxco mine, its workers have been on strike since July 2007. After several legal procedures, in August 2015, the Supreme Court decided to assert jurisdiction over the case and to rule on it directly. As of December 31, 2018, the case remains pending resolution without further developments. It is expected that operations at the Taxco mine will remain suspended until the labor issues are resolved. In view of the lengthy strike, the Company has reviewed the carrying value of the Taxco mine to ascertain whether impairment exists. The Company concluded that there is a non-material impairment of the assets located at this mine. Other legal matters : The Company is involved in various other legal proceedings incidental to its operations, but does not believe that decisions adverse to it in any such proceedings, individually or in the aggregate, would have a material effect on its financial position or results of operations. Other commitments: Peruvian Operations Tia Maria: On August 1, 2014, the Company received the final approval of Tia Maria’s Environmental Impact Assessment (“EIA”). However, the issuance of the project’s construction permit has been delayed due to pressures from anti-mining groups. The Company continues working with community groups in order to resolve open issues concerning the project. The Company is also working jointly with the Peruvian government to obtain the construction license for this 120,000 ton (annual) SX-EW copper greenfield project. The Company expects the license to be issued in the first half of 2019. Tia Maria’s project budget is approximately $1.4 billion, of which $333.9 million has been invested through December 31, 2018. When completed, it is expected to produce 120,000 tons of copper cathodes per year. This project will use state-of-the-art SX-EW technology with the highest international environmental standards. SX-EW facilities are the most environmentally friendly in the industry as they do not require a smelting process and consequently, no emissions are released into the atmosphere. The project will only use seawater, transporting it more than 25 kilometers to 1,000 meters above sea level, and includes a desalinization plant which will be constructed at a cost of $95 million. Consequently, the Tambo river water resources will be used solely for farming and human consumption. The Company expects the project to generate 9,000 jobs (3,600 direct and 5,400 indirect) during the construction phase. When in operation, Tia Maria will directly employ 600 workers and indirectly provide jobs to another 4,200. Through its expected twenty-year life, the project related services will create significant business opportunities in the Arequipa region. In view of the delay in this project, the Company continues to review the carrying value of this asset to ascertain whether impairment exists. Should the Tia Maria project not move forward, the Company is confident that most of the project equipment will continue to be used productively, through reassignment to other mine locations operated by the Company. The Company believes that an impairment loss, if any, will not be material. Michiquillay: In June 2018, the Company signed a contract for the acquisition of the Michiquillay copper project in Cajamarca, Peru, at a purchase price of $400 million. Michiquillay is a world class mining project with estimated mineralized material of 1,150 million tons and a copper grade of 0.63%. It is expected to produce 225,000 tons of copper per year (along with by-products of molybdenum, gold and silver) for an initial mine life of more than 25 years. The Company paid $12.5 million at the signing of the contract. An additional $12.5 million has been accrued by the Company as it evaluates the project for development, over a three to five year period. This amount is classified in other non-current liabilities in the Company’s consolidated financial statements. The balance of $375 million will be paid if the Company decides to develop the project. Toquepala Concentrator Expansion: In April 2015, the construction permit for the Toquepala expansion project was approved by the MINEM. The project budget is $1.3 billion, of which $1,227 million has been invested through December 31, 2018. When completed, this project is expected to increase annual production capacity by 100,000 tons of copper and 3,100 tons of molybdenum. The construction of the project was completed and the project began production in the fourth quarter of 2018. Full production is expected to be reached by the second quarter of 2019. Corporate Social Responsibility: The Company has a corporate social responsibility policy to maintain and promote continuity of its mining operations and obtain the best results. The main objective of this policy is to integrate its operations with the local communities in the areas of influence of its operations by creating a permanent positive relationship with them, in order to develop the optimum social conditions and to promote sustainable development in the area. Accordingly, the Company has made the following commitments: Tacna Region : In connection with the Toquepala concentrator expansion, the Company has committed to fund various social and infrastructure improvement projects in Toquepala's neighboring communities. The total amount committed for these purposes is S/ 445.0 million (approximately $131.7 million). Moquegua Region : In the Moquegua region, the Company is part of a “development roundtable” in which the local municipal authorities, the community representatives and the Company discuss the social needs and the way the Company could contribute to sustainable development in the region. As part of this, the roundtable is discussing the creation of a Moquegua Region Development Fund for which the Company has offered a contribution of S/ 700 million (approximately $207.2 million). While final funding is not yet settled, the Company has committed to contribute S/ 108.5 million (approximately $32.1 million) in advance, which is being utilized in an educational project and S/ 48.4 million (approximately $14.3 million) for a residual water treatment plant in Ilo, a sea-wall embankment and a fresh water facility at El Algarrobal. In addition, the Company has committed S/ 202.0 million (approximately $59.8 million) for the construction of six infrastructure projects in the Moquegua region under the “social investment for taxes” (obras por impuestos) program which allows the Company to use these amounts as an advance payment of taxes. These commitments are subject to the continuity of the respective mine operations and, as such, are not considered to be present obligations of the Company. Therefore, the Company has not recorded a liability in its condensed consolidated financial statements. Peruvian operations Power purchase agreements: · Electroperu S.A.: In June 2014, the Company entered into a power purchase agreement for 120 megawatt (“MW”) with the state power company Electroperu S.A., under which Electroperu S.A. began supplying energy for the Peruvian operations for twenty years starting on April 17, 2017. · Kallpa Generacion S.A. (“Kallpa”): In July 2014, the Company entered into a power purchase agreement for 120MW with Kallpa, an independent Israeli owned power company, under which Kallpa will supply energy for the Peruvian operations for ten years starting on April 17, 2017 and ending on April 30, 2027. In May 2016, the Company signed an additional power purchase agreement for a maximum of 80MW with Kallpa, under which Kallpa began supplying energy for the Peruvian operations related to the Toquepala Expansion and other minor projects for ten years starting on May 1, 2017 and ending after ten years of commercial operation of the Toquepala Expansion or on April 30, 2029; whichever occurs first. Mexican operations Power purchase agreements: · MGE: In 2012, the Company signed a power purchase agreement with MGE, an indirect subsidiary of Grupo Mexico, to supply power to some of the Company’s Mexican operations through 2032. For further information, please see Note 16 “Related party transactions”. · Eolica el Retiro, S.A.P.I. de C.V.: In 2013, the Company signed a power purchase agreement with Eolica el Retiro, S.A.P.I de C.V. a windfarm energy producer that is an indirect subsidiary of Grupo Mexico, to supply power to some of the Company’s Mexican operations. For further information, please see Note 16 “Related party transactions”. For an estimate of the Company’s contractual obligations for power purchases, please see, “Contractual Obligations” under Item 7 “Management Discussion and Analysis of Financial Condition and Results of Operations.” Corporate operations Commitment for Capital projects: As of December 31, 2018, the Company has committed approximately $343.1 million for the development of its capital investment projects. Tax contingency matters: Tax contingencies are provided for under ASC 740-10-50-15 Uncertain tax position (see Note 7 “Income taxes”). |