Regulatory Matters | 12 Months Ended |
Dec. 31, 2013 |
Regulated Operations [Abstract] | ' |
REGULATORY MATTERS | ' |
REGULATORY MATTERS |
|
STATE REGULATION |
|
|
Each of the Utilities' retail rates, conditions of service, issuance of securities and other matters are subject to regulation in the states in which it operates - in Maryland by the MDPSC, in Ohio by the PUCO, in New Jersey by the NJBPU, in Pennsylvania by the PPUC, in West Virginia by the WVPSC and in New York by the NYPSC. The transmission operations of PE in Virginia are subject to certain regulations of the VSCC. In addition, under Ohio law, municipalities may regulate rates of a public utility, subject to appeal to the PUCO if not acceptable to the utility. |
|
|
|
As competitive retail electric suppliers serving retail customers primarily in Ohio, Pennsylvania, Illinois, Michigan, New Jersey and Maryland, FES and AE Supply are subject to state laws applicable to competitive electric suppliers in those states, including affiliate codes of conduct that apply to FES, AE Supply and their public utility affiliates. In addition, if FES, AE Supply or any of their subsidiaries were to engage in the construction of significant new generation facilities in any of those states, they would also be subject to state siting authority. |
|
|
|
|
MARYLAND |
|
|
|
|
|
PE provides SOS pursuant to a combination of settlement agreements, MDPSC orders and regulations, and statutory provisions. SOS supply is competitively procured in the form of rolling contracts of varying lengths through periodic auctions that are overseen by the MDPSC and a third party monitor. Although settlements with respect to residential SOS for PE customers expired on December 31, 2012, by statute, service continues in the same manner unless changed by order of the MDPSC. The settlement provisions relating to non-residential SOS have also expired; however, by MDPSC order, the terms of service remain in place unless PE requests or the MDPSC orders a change. PE recovers its costs plus a return for providing SOS. |
|
|
|
|
|
|
The Maryland legislature in 2008 adopted a statute codifying the EmPOWER Maryland goals to reduce electric consumption by 10% and reduce electricity demand by 15%, in each case by 2015. PE's initial plan submitted in compliance with the statute was approved in 2009 and covered 2009-2011, the first three years of the statutory period. Expenditures were originally estimated to be approximately $101 million for the PE programs for the entire period of 2009-2015. Meanwhile, after extensive meetings with the MDPSC Staff and other stakeholders, on August 31, 2011, PE filed a new comprehensive plan for the second three year period, 2012-2014, that includes additional and improved programs. The 2012-2014 plan is expected to cost approximately $66 million out of the original $101 million estimate for the entire EmPOWER program. On December 22, 2011, the MDPSC issued an order approving PE's second plan with various modifications and follow-up assignments. PE continues to recover program costs subject to a five-year amortization. Maryland law only allows for the utility to recover lost distribution revenue attributable to energy efficiency or demand reduction programs through a base rate case proceeding, and to date such recovery has not been sought or obtained by PE. |
|
|
|
|
|
|
|
Pursuant to a bill passed by the Maryland legislature in 2011, the MDPSC adopted rules, effective May 28, 2012, that create specific requirements related to a utility's obligation to address service interruptions, downed wire response, customer communication, vegetation management, equipment inspection, and annual reporting. The MDPSC will be required to assess each utility's compliance with the new rules, and may assess penalties of up to $25,000 per day, per violation. The new rules set utility-specific SAIDI and SAIFI targets for 2012-2015; prescribe detailed tree-trimming requirements, outage restoration and downed wire response deadlines; and impose other reliability and customer satisfaction requirements. PE has advised the MDPSC that compliance with the new rules is expected to increase costs by approximately $106 million over the period 2012-2015. On April 1, 2013, the Maryland electric utilities, including PE, filed their first annual reports on compliance with the new rules. The MDPSC conducted a hearing on August 20, 2013 to discuss the reports, after which an order was issued on September 3, 2013, which accepted PE's filing and the operational changes proposed therein. |
|
|
|
|
|
|
|
|
Following a "derecho" storm through the region on June 29, 2012, the MDPSC convened a new proceeding to consider matters relating to the electric utilities' performance in responding to the storm. Hearings on the matter were conducted in September 2012. Concurrently, Maryland's governor convened a special panel to examine possible ways to improve the resilience of the electric distribution system. On October 3, 2012, that panel issued a report calling for various measures including: acceleration and expansion of some of the requirements contained in the reliability standards which had become final on May 28, 2012; selective increased investment in system hardening; creation of separate recovery mechanisms for the costs of those changes and investments; and penalties or bonuses on returns earned by the utilities based on their reliability performance. On February 27, 2013, the MDPSC issued an order (the February 27 Order) requiring the utilities to submit several reports over a series of months, relating to the costs and benefits of making further system and staffing enhancements in order to attempt to reduce storm outage durations. The order further requires the Staff of the MDPSC to report on possible performance-based rate structures and to propose additional rules relating to feeder performance standards, outage communication and reporting, and sharing of special needs customer information. PE has responded to the requirements in the order consistent with the schedule set forth therein. PE's final filing on September 3, 2013, discussed the steps needed to harden the utility's system in order to attempt to achieve various levels of storm response speed described in the February 27 Order, and projected that it would expect to make approximately $2.7 billion in infrastructure investments over 15 years to attempt to achieve the quickest level of response for the largest storm projected in the February 27 Order. The MDPSC has ordered that certain reports of its Staff relating to these matters be provided by May 1, 2014, and otherwise has not issued a schedule for further proceedings in this matter. |
|
|
|
|
|
|
|
|
|
NEW JERSEY |
|
|
|
|
|
|
|
|
|
|
JCP&L currently provides BGS for retail customers who do not choose a third party EGS and for customers of third party EGSs that fail to provide the contracted service. The supply for BGS, which is comprised of two components, is provided through contracts procured through separate, annually held descending clock auctions, the results of which are approved by the NJBPU. One BGS component and auction, reflecting hourly real time energy prices, is available for larger commercial and industrial customers. The other BGS component and auction, providing a fixed price service, is intended for smaller commercial and residential customers. All New Jersey EDCs participate in this competitive BGS procurement process and recover BGS costs directly from customers as a charge separate from base rates. |
|
|
|
|
|
|
|
|
|
|
|
On September 7, 2011, the Division of Rate Counsel filed a Petition with the NJBPU asserting that it has reason to believe that JCP&L is earning an unreasonable return on its New Jersey jurisdictional rate base. The Division of Rate Counsel requested that the NJBPU order JCP&L to file a base rate case petition so that the NJBPU may determine whether JCP&L's current rates for electric service are just and reasonable. In its written Order issued July 31, 2012, the NJBPU found that a base rate proceeding "will assure that JCP&L's rates are just and reasonable and that JCP&L is investing sufficiently to assure the provision of safe, adequate and proper utility service to its customers" and ordered JCP&L to file a base rate case using a historical 2011 test year. The rate case petition was filed on November 30, 2012. In the filing, JCP&L requested approval to increase its revenues by approximately $31.5 million and reserved the right to update the filing to include costs associated with the impact of Hurricane Sandy. The NJBPU transmitted the case to the New Jersey Office of Administrative Law for further proceedings and an ALJ has been assigned. On February 22, 2013, JCP&L updated its filing to request recovery of $603 million of distribution-related Hurricane Sandy restoration costs, resulting in increasing the total revenues requested to approximately $112 million. On June 14, 2013, JCP&L further updated its filing to: 1) include the impact of a depreciation study which had been directed by the NJBPU; 2) remove costs associated with 2012 major storms, consistent with the NJBPU orders establishing a generic proceeding to review 2011 and 2012 major storm costs (discussed below); and 3) reflect other revisions to JCP&L's filing. That filing represented an increase of approximately $20.6 million over the revenues produced by existing base rates. Testimony has also been filed in the matter by the Division of Rate Counsel and several other intervening parties in opposition to the base rate increase JCP&L requested. Specifically, the testimony of the Division of Rate Counsel's witnesses recommended that revenues produced by JCP&L's base rates for electric service be reduced by approximately $202.8 million (such amount did not address the revenue requirements associated with major storm events of 2011 and 2012, which are subject to review in the generic proceeding). JCP&L filed rebuttal testimony in response to the testimony of other parties on August 7, 2013. Hearings in the rate case have concluded. In the initial briefs of the parties filed on January 27, 2014, the Division of Rate Counsel recommended that base rate revenues be reduced by $214.9 million while the NJBPU Staff recommended a $207.4 million reduction (such amounts do not address the revenue requirements associated with the major storm events of 2011 and 2012). Reply briefs were filed on February 24, 2014. |
|
|
|
|
|
|
|
|
|
|
|
|
On March 20, 2013, the NJBPU ordered that a generic proceeding be established to investigate the prudence of costs incurred by all New Jersey utilities for service restoration efforts associated with the major storm events of 2011 and 2012. The Order provided that if any utility had already filed a proceeding for recovery of such storm costs, to the extent the amount of approved recovery had not yet been determined, the prudence of such costs would be reviewed in the generic proceeding. On May 31, 2013, the NJBPU clarified its earlier order to indicate that the 2011 major storm costs would be reviewed expeditiously in the generic proceeding with the goal of maintaining the base rate case schedule established by the ALJ where recovery of such costs would be addressed. The NJBPU further indicated in the May 31 clarification that it would review the 2012 major storm costs in the generic proceeding and the recovery of such costs would be considered through a Phase II in the existing base rate case or through another appropriate method to be determined at the conclusion of the generic proceeding. On June 21, 2013, consistent with NJBPU's orders, JCP&L filed the detailed report in support of recovery of major storm costs with the NJBPU. On November 15, 2013, the Division of Rate Counsel filed testimony recommending that approximately $15 million of JCP&L’s costs be disallowed for recovery. Evidentiary hearings in this proceeding were scheduled for January 2014 but were subsequently adjourned by the NJBPU before their commencement. On February 24, 2014, a Stipulation was filed with the NJBPU by JCP&L, the Division of Rate Counsel and NJBPU Staff which will allow recovery of $736 million of JCP&L’s $744 million of costs related to the significant weather events of 2011 and 2012. As a result, FirstEnergy recorded a regulatory asset impairment charge of approximately $8 million (pre-tax) as of December 31, 2013, included in Amortization of regulatory assets, net within the Consolidated Statements of Income. The agreement, upon which no other party took a position to oppose or support, is now pending before the NJBPU. Recovery of 2011 storm costs will be addressed in the pending base rate case; recovery of 2012 storm costs will be determined by the NJBPU. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Pursuant to a formal Notice issued by the NJBPU on September 14, 2011, public hearings were held in September 2011 to solicit comments regarding the state of preparedness and responsiveness of New Jersey's EDCs prior to, during, and after Hurricane Irene, with additional hearings held in October 2011. Additionally, the NJBPU accepted written comments through October 28, 2011 related to this inquiry. On December 14, 2011, the NJBPU Staff filed a report of its preliminary findings and recommendations with respect to the electric utility companies' planning and response to Hurricane Irene and the October 2011 snowstorm. The NJBPU selected a consultant to further review and evaluate the New Jersey EDCs' preparation and restoration efforts with respect to Hurricane Irene and the October 2011 snowstorm, and the consultant's report was submitted to and subsequently accepted by the NJBPU on September 12, 2012. JCP&L submitted written comments on the report. On January 24, 2013, based upon recommendations in its consultant's report, the NJBPU ordered the New Jersey EDCs to take a number of specific actions to improve their preparedness and responses to major storms. The order includes specific deadlines for implementation of measures with respect to preparedness efforts, communications, restoration and response, post event and underlying infrastructure issues. On May 31, 2013, the NJBPU ordered that the New Jersey EDCs implement a series of new communications enhancements intended to develop more effective communications among EDCs, municipal officials, customers and the NJBPU during extreme weather events and other expected periods of extended service interruptions. The new requirements include making information regarding estimated times of restoration available on the EDC's web sites and through other technological expedients. JCP&L is implementing the required measures consistent with the schedule set out in the above NJBPU's orders. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
OHIO |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The Ohio Companies primarily operate under an ESP, which expires on May 31, 2014. The material terms of the ESP include: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
• | Generation supplied through a CBP; |
| |
• | A load cap of no less than 80%, so that no single supplier is awarded more than 80% of the tranches, which also applies to tranches assigned post-auction; |
| |
• | A 6% generation discount to certain low income customers provided by the Ohio Companies through a bilateral wholesale contract with FES (FES is one of the wholesale suppliers to the Ohio Companies); |
| |
• | No increase in base distribution rates through May 31, 2014; and |
| |
• | A new distribution rider, Rider DCR, to recover a return of, and on, capital investments in the delivery system. |
|
The Ohio Companies also agreed not to recover from retail customers certain costs related to transmission cost allocations by PJM as a result of ATSI's integration into PJM for the longer of the five-year period from June 1, 2011 through May 31, 2016 or when the amount of costs avoided by customers for certain types of products totals $360 million, subject to the outcome of certain PJM proceedings. The Ohio Companies also agreed to establish a $12 million fund to assist low income customers over the term of the ESP and agreed to additional matters related to energy efficiency and alternative energy requirements. |
|
|
On April 13, 2012, the Ohio Companies filed an application with the PUCO to essentially extend the terms of their ESP for two years. The ESP 3 Application was approved by the PUCO on July 18, 2012. Several parties timely filed applications for rehearing. The PUCO issued an Entry on Rehearing on January 30, 2013 denying all applications for rehearing. Notices of appeal to the Supreme Court of Ohio were filed by two parties in the case, Northeast Ohio Public Energy Council and the ELPC. While briefing has been completed, the matter has not yet been scheduled for oral argument. |
|
|
|
As approved, the ESP 3 plan continues certain provisions from the current ESP including: |
| |
• | Continuing the current base distribution rate freeze through May 31, 2016; |
| |
• | Continuing to provide economic development and assistance to low-income customers for the two-year plan period at levels established in the existing ESP; |
| |
• | A 6% generation rate discount to certain low income customers provided by the Ohio Companies through a bilateral wholesale contract with FES (FES is one of the wholesale suppliers to the Ohio Companies); |
| |
• | Continuing to provide power to non-shopping customers at a market-based price set through an auction process; and |
| |
• | Continuing Rider DCR that allows continued investment in the distribution system for the benefit of customers. |
|
As approved, the ESP 3 plan provides additional provisions, including: |
| |
• | Securing generation supply for a longer period of time by conducting an auction for a three-year period rather than a one-year period, in each of October 2012 and January 2013, to mitigate any potential price spikes for the Ohio Companies' utility customers who do not switch to a competitive generation supplier; and |
| |
• | Extending the recovery period for costs associated with purchasing RECs mandated by SB221 through the end of the new ESP 3 period. This is expected to initially reduce the monthly renewable energy charge for all non-shopping utility customers of the Ohio Companies by spreading out the costs over the entire ESP period. |
|
Under SB221, the Ohio Companies are required to implement energy efficiency programs that achieve a total annual energy savings equivalent of approximately 1,211 GWHs in 2012 (an increase of 416,000 MWHs over 2011 levels), 1,726 GWHs in 2013, 2,306 GWHs in 2014 and 2,903 GWHs for each year thereafter through 2025. The Ohio Companies were also required to reduce peak demand in 2009 by 1%, with an additional 0.75% reduction each year thereafter through 2018. On May 15, 2013, the Ohio Companies filed their 2012 Status Update Report in which they indicated compliance with 2012 statutory energy efficiency and peak demand reduction benchmarks. |
|
|
In accordance with PUCO Rules and a PUCO directive, on July 31, 2012 the Ohio Companies filed their three-year portfolio plan for the period January 1, 2013 through December 31, 2015. Estimated costs for the three Ohio Companies' plans total approximately $250 million over the three-year period, which is expected to be recovered in rates to the extent approved by the PUCO. Hearings were held with the PUCO in October 2012. On March 20, 2013, the PUCO approved the three-year portfolio plan for 2013-2015. Applications for rehearing were filed by the Ohio Companies and several other parties on April 19, 2013. The Ohio Companies filed their request for rehearing primarily to challenge the PUCO's decision to mandate that they offer planned energy efficiency resources into PJM's base residual auction. On May 15, 2013, the PUCO granted the applications for rehearing for the sole purpose of further consideration of the matter. On July 17, 2013, the PUCO denied the Ohio Companies' application for rehearing, in part, but authorized the Ohio Companies to receive 20% of any revenues obtained from bidding energy efficiency and demand response reserves into the PJM auction. The PUCO also confirmed that the Ohio Companies can recover PJM costs and applicable penalties associated with PJM auctions, including the costs of purchasing replacement capacity from PJM incremental auctions, to the extent that such costs or penalties are prudently incurred. On August 16, 2013, ELPC and OCC filed applications for rehearing under the basis that the PUCO's authorization for the Ohio Companies to share in the PJM revenues was unlawful. The PUCO granted rehearing on September 11, 2013 for the sole purpose of further consideration of the issue. |
|
|
|
On September 16, 2013, the Ohio Companies filed with the Supreme Court of Ohio a notice of appeal of the PUCO's July 17, 2013 Entry on Rehearing related to energy efficiency, alternative energy, and long-term forecast rules stating that the rules issued by the PUCO are inconsistent with and are not supported by statutory authority. On October 23, 2013, the PUCO filed a motion to dismiss the appeal. The Ohio Companies' response was filed on November 4, 2013. The motion is still pending and additional briefing has followed. The Ohio Companies filed their merit brief with the Supreme Court of Ohio on February 24, 2014. |
|
|
|
|
SB221 requires electric utilities and electric service companies in Ohio to serve part of their load from renewable energy resources measured by an annually increasing percentage amount through 2024. The Ohio Companies conducted RFPs in 2009, 2010 and 2011 to secure RECs to help meet the renewable energy requirements established under SB221. In September 2011, the PUCO opened a docket to review the Ohio Companies' alternative energy recovery rider through which the Ohio Companies recover the costs of acquiring these RECs and selected auditors to perform a financial and management audit. Final audit reports filed with the PUCO generally supported the Ohio Companies' approach to procurement of RECs, but also recommended the PUCO examine, for possible disallowance, certain costs associated with the procurement of in-state renewable obligations that the auditor characterized as excessive. Following the hearing, the PUCO issued an Opinion and Order on August 7, 2013 approving the Ohio Companies' acquisition process and their purchases of RECs to meet statutory mandates in all instances except for part of the purchases arising from one auction and directing the Ohio Companies to credit non-shopping customers in the amount of $43.3 million, plus interest, and to file tariff schedules reflecting the refund and interest costs within 60 days following the issuance of a final appealable order on the basis that the Ohio Companies did not prove such purchases were prudent. The Ohio Companies, along with other parties, timely filed applications for rehearing on September 6, 2013. On December 18, 2013, the PUCO denied all of the applications for rehearing. Based on the PUCO ruling, a regulatory charge of approximately $51 million, including interest, was recorded in the fourth quarter of 2013 included in Amortization of regulatory assets, net within the Consolidated Statement of Income. On December 24, 2013, the Ohio Companies filed a notice of appeal and a motion for stay of the PUCO's order with the Supreme Court of Ohio. On February 10, 2014, the Supreme Court of Ohio granted the Ohio Companies' motion for stay, which went into effect on February 14, 2014. On February 18, 2014, the Office of Consumers' Counsel and the Environmental Law and Policy Center also filed appeals of the PUCO's order. |
|
|
|
|
|
In March 2012, the Ohio Companies conducted an RFP process to obtain SRECs to help meet the statutory benchmarks for 2012 and beyond. With the successful completion of this RFP, the Ohio Companies achieved their in-state solar compliance requirements for 2012. The Ohio Companies also held a short-term RFP process to obtain all state SRECs and both in-state and all state non-solar RECs to help meet the statutory benchmarks for 2012. The Ohio Companies recently reported that they met all of their annual renewable energy resource requirements for reporting year 2012. The Ohio Companies conducted an RFP in 2013 to cover their all-state SREC and their in-state and all-state REC compliance obligations. |
|
|
|
|
|
|
The PUCO instituted a statewide investigation on December 12, 2012 to evaluate the vitality of the competitive retail electric service market in Ohio. The PUCO provided interested stakeholders the opportunity to comment on twenty-two questions. The questions posed are categorized as market design and corporate separation. The Ohio Companies timely filed their comments on March 1, 2013, and filed reply comments on April 5, 2013. On June 5, 2013, the PUCO requested additional comments and reply comments on the topics of market design and corporate separation, which the Ohio Companies timely filed on July 8, 2013 and July 22, 2013, respectively. The PUCO held a series of workshops throughout 2013, which included an en banc workshop on December 11, 2013. The PUCO Staff filed a report on January 16, 2014, which contained a limited discussion of the workshops and the PUCO Staff’s recommendations. The Ohio Companies submitted comments on February 6, 2014 and Reply Comments on February 20, 2014. |
|
|
|
|
|
|
|
PENNSYLVANIA |
|
|
|
|
|
|
|
|
The Pennsylvania Companies currently operate under DSPs that expire on May 31, 2015, and provide for the competitive procurement of generation supply for customers that do not choose an alternative EGS or for customers of alternative EGSs that fail to provide the contracted service. The default service supply is currently provided by wholesale suppliers through a mix of long-term and short-term contracts procured through descending clock auctions, competitive requests for proposals and spot market purchases. On November 4, 2013, the Pennsylvania Companies filed a DSP that will provide the method by which they will procure the supply for their default service obligations for the period of June 1, 2015 through May 31, 2017. The Pennsylvania Companies proposed programs call for quarterly descending clock auctions to procure 3, 12, 24, and 48-month energy contracts, as well as, one RFP seeking 2-year contracts to secure SRECs for ME, PN, and Penn. Hearings on the plans are scheduled to be held March 4-7, 2014. The Pennsylvania Companies expect a decision from the PPUC by August 4, 2014. |
|
|
|
|
|
|
|
|
|
The PPUC entered an Order on March 3, 2010 that denied the recovery of marginal transmission losses through the TSC rider for the period of June 1, 2007 through March 31, 2008, and directed ME and PN to submit a new tariff or tariff supplement reflecting the removal of marginal transmission losses from the TSC. Pursuant to a plan approved by the PPUC, ME and PN refunded those amounts to customers over a 29-month period that began in January of 2011. On appeal, the Commonwealth Court affirmed the PPUC's Order to the extent that it holds that line loss costs are not transmission costs and, therefore, the approximately $254 million in marginal transmission losses and associated carrying charges for the period prior to January 1, 2011, are not recoverable under ME's and PN's TSC riders. The Pennsylvania Supreme Court denied ME's and PN's Petition for Allowance of Appeal and the Supreme Court of the United States denied ME's and PN's Petition for Writ of Certiorari. ME and PN also filed a complaint in the U.S. District Court for the Eastern District of Pennsylvania to obtain an order that would enjoin enforcement of the PPUC and Pennsylvania court orders under a theory of federal preemption on the question of retail rate recovery of the marginal transmission loss charges. On September 30, 2013, the U.S. District Court granted the PPUC’s motion to dismiss. As a result of the U.S. District Court's September 30, 2013 decision, FirstEnergy recorded a regulatory asset impairment charge of approximately $254 million (pre-tax) in the quarter ended September 30, 2013 included in Amortization of regulatory assets, net within the Consolidated Statement of Income. The balance of marginal transmission losses was fully refunded to customers by the second quarter of 2013. On October 29, 2013, ME and PN filed a Notice of Appeal of the U.S. District Court’s decision to dismiss the complaint with the United States Court of Appeals for the Third Circuit. On December 30, 2013, ME and PN filed a brief with the Third Circuit that explained why it was legal error for the U.S. District Court to dismiss the complaint. The PPUC filed its brief on February 3, 2014, and ME and PN filed a reply brief on February 21, 2014. Oral argument has been scheduled for April 9, 2014. |
|
Pennsylvania adopted Act 129 in 2008 to address issues such as: energy efficiency and peak load reduction; generation procurement; time-of-use rates; smart meters; and alternative energy. Among other things, Act 129 required utilities to file with the PPUC an energy efficiency and peak load reduction plan (EE&C Plan) by July 1, 2009, setting forth the utilities' plans to reduce energy consumption by a minimum of 1% and 3% by May 31, 2011 and May 31, 2013, respectively, and to reduce peak demand by a minimum of 4.5% by May 31, 2013. Act 129 provides for potentially significant financial penalties to be assessed on utilities that fail to achieve the required reductions in consumption and peak demand. The Pennsylvania Companies submitted a report on November 15, 2011, in which they reported on their compliance with statutory May 31, 2011, energy efficiency benchmarks. ME, PN and Penn achieved the 2011 benchmarks; however WP did not. WP could be subject to a statutory penalty of between $1 and $20 million. On July 15, 2013, the Pennsylvania Companies filed their preliminary energy efficiency and demand reduction results for the period ending May 31, 2013, indicating that all Pennsylvania Companies are expected to meet their statutory obligations. On November 15, 2013, the Pennsylvania Companies submitted their energy efficiency and peak demand reduction report for the period ending May 31, 2013, in which they indicated that all of the Pennsylvania Companies met their statutory requirements. |
|
|
Pursuant to Act 129, the PPUC was charged with reviewing the cost effectiveness of energy efficiency and peak demand reduction programs. The PPUC found the energy efficiency programs to be cost effective and in an Order entered on August 3, 2012, the PPUC directed all of the electric utilities in Pennsylvania to submit by November 15, 2012, a Phase II EE&C Plan that would be in effect for the period June 1, 2013 through May 31, 2016. The PPUC has deferred ruling on the need to create peak demand reduction targets until it receives more information from the EE&C statewide evaluator. Based upon information received, the PPUC has not included a peak demand reduction requirement in the Phase II plans. The Pennsylvania Companies filed their Phase II plans and supporting testimony in November 2012. On January 16, 2013, the Pennsylvania Companies reached a settlement with all but one party on all but one issue. The settlement provides for the Pennsylvania Companies to meet with interested parties to discuss ways to expand upon the EE&C programs and incorporate any such enhancements after the plans are approved, provided that these enhancements will not jeopardize the Pennsylvania Companies' compliance with their required targets or exceed the statutory spending caps. On February 6, 2013, the Pennsylvania Companies filed revised Phase II EE&C Plans to conform the plans to the terms of the settlement. Total costs of these plans are expected to be approximately $234 million. All such costs are expected to be recoverable through the Pennsylvania Companies reconcilable Phase II EE&C Plan C riders. The remaining issue, raised by a natural gas company, involved the recommendation that the Pennsylvania Companies include in their plans incentives for natural gas space and water heating appliances. On March 14, 2013, the PPUC approved the 2013-2016 EE&C plans of the Pennsylvania Companies, adopting the settlement, and rejecting the natural gas companies recommendations. |
|
|
|
In addition, Act 129 required utilities to file a SMIP with the PPUC. On December 31, 2012, the Pennsylvania Companies filed their Smart Meter Deployment Plan. The Deployment Plan requests deployment of approximately 98.5% of the smart meters to be installed over the period 2013 to 2019, and the remaining meters in difficult to reach locations to be installed by 2022, with an estimated life cycle cost of about $1.25 billion. Such costs are expected to be recovered through the Pennsylvania Companies' PPUC-approved Riders SMT-C. Evidentiary hearings were held and briefs were submitted by the Pennsylvania Companies and the Office of Consumer Advocate. On November 8, 2013, the ALJ issued a Recommended Decision recommending that the Pennsylvania Companies' Deployment Plan be adopted with certain modifications, including, among other things, that the Pennsylvania Companies perform further benchmarking analyses on their costs and hire an independent consultant to perform further analyses on potential savings. On December 2, 2013, the Pennsylvania Companies submitted exceptions in which they challenged, among other things, certain recommendations in the ALJ’s decision, and requested approval of a modification to the deployment schedule so as to allow the entire Penn smart meter system (170,000 meters) to be built by the end of 2015, instead of the original proposed installation of 60,000 meters by the end of 2016. The Office of Consumer Advocate took exception to one issue and both parties filed replies to exceptions on December 12, 2013. The case is now before the PPUC for consideration. |
A decision is expected during the first quarter of 2014. |
|
|
|
|
In the PPUC Order approving the FirstEnergy and Allegheny merger, the PPUC announced that a separate statewide investigation into Pennsylvania's retail electricity market would be conducted with the goal of making recommendations for improvements to ensure that a properly functioning and workable competitive retail electricity market exists in the state. On April 29, 2011, the PPUC entered an Order initiating the investigation and requesting comments from interested parties on eleven directed questions concerning retail markets in Pennsylvania to investigate both intermediate and long term plans that could be adopted to further foster the competitive markets, and to explore the future of default service in Pennsylvania following the expiration of the upcoming DSPs on May 31, 2015. A final order was issued on February 15, 2013, providing recommendations on the entities to provide default service, the products to be offered, billing options, customer education, and licensing fees and assessments, among other items. Subsequently, the PPUC established five workgroups and one comment proceeding in order to seek resolution of certain matters and to clarify certain obligations that arose from that order. |
|
|
|
|
|
The PPUC issued a Proposed Rulemaking Order on August 25, 2011, which proposed a number of substantial modifications to the current Code of Conduct regulations that were promulgated to provide competitive safeguards to the competitive retail electricity market in Pennsylvania. The proposed changes include, but are not limited to: an EGS may not have the same or substantially similar name as the EDC or its corporate parent; EDCs and EGSs would not be permitted to share office space and would need to occupy different buildings; EDCs and affiliated EGSs could not share employees or services, except certain corporate support, emergency, or tariff services (the definition of "corporate support services" excludes items such as information systems, electronic data interchange, strategic management and planning, regulatory services, legal services, or commodities that have been included in regulated rates at less than market value); and an EGS must enter into a trademark agreement with the EDC before using its trademark or service mark. The Proposed Rulemaking Order was published on February 11, 2012, and comments were filed by the Pennsylvania Companies and FES on March 27, 2012. If implemented these rules could require a significant change in the ways FES and the Pennsylvania Companies do business in Pennsylvania, and could possibly have an adverse impact on their results of operations and financial condition. Pennsylvania's Independent Regulatory Review Commission subsequently issued comments on the proposed rulemaking on April 26, 2012, which called for the PPUC to further justify the need for the proposed revisions by citing a lack of evidence demonstrating a need for them. The House Consumer Affairs Committee of the Pennsylvania General Assembly also sent a letter to the Independent Regulatory Review Commission on July 12, 2012, noting its opposition to the proposed regulations as modified. |
|
|
|
|
|
|
WEST VIRGINIA |
|
|
|
|
|
|
|
MP and PE currently operate under a Joint Stipulation and Agreement of Settlement reached with the other parties and approved by the WVPSC in June 2010 that provided for: |
|
|
|
|
|
|
|
|
| |
• | $40 million annualized base rate increases effective June 29, 2010; |
| |
• | Deferral of February 2010 storm restoration expenses over a maximum five-year period; |
| |
• | Additional $20 million annualized base rate increase effective in January 2011; |
| |
• | Decrease of $20 million in ENEC rates effective January 2011, providing for deferral of related costs for later recovery in 2012; and |
| |
• | Moratorium on filing for further increases in base rates before December 1, 2011, except under specified circumstances. |
|
The WVPSC opened a general investigation into the June 29, 2012, derecho windstorm with data requests for all utilities. A public meeting for presentations on utility responses and restoration efforts was held on October 22, 2012 and two public input hearings have been held. The WVPSC issued an Order in this matter on January 23, 2013 closing the proceeding and directing electric utilities to file a vegetation management plan within six months and to propose a cost recovery mechanism. This Order also requires MP and PE to file a status report regarding improvements to their storm response procedures by the same date. On July 23, 2013, MP and PE filed their vegetation management plans, which provided for recovery of costs through a surcharge mechanism. A hearing was held on December 3, 2013, and briefing followed but the WVPSC has not yet issued an opinion in this matter. |
|
|
MP and PE filed their Resource Plan with the WVPSC in August 2012 detailing both supply and demand forecasts and noting a substantial capacity deficiency. MP and PE filed a Petition for approval of a Generation Resource Transaction with the WVPSC in November 2012 that proposed a net ownership transfer of 1,476 MW of coal-fired generation capacity to MP. The proposed transfer involved MP's acquisition of the remaining ownership of the Harrison Power Station from AE Supply and the sale of MP's minority interest in the Pleasants Power Station to AE Supply. FERC authorized the transfers on April 23, 2013 and the financing on May 13, 2013. A Joint Settlement Agreement was filed by the majority of parties on August 21, 2013. On October 7, 2013, the WVPSC authorized the transaction, with certain conditions, and on October 9, 2013, the transaction closed resulting in MP recording a pre-tax impairment charge of approximately $322 million in the fourth quarter of 2013 to reduce the net book value of the Harrison Power Station to the amount that was permitted to be included in jurisdictional rate base. The charge is included in Impairment of long lived assets within the Consolidated Statement of Income. Concurrently, MP recognized a regulatory liability of approximately $23 million representing refunds to customers associated with the excess purchase price received by MP above the net book value of MP's minority interest in the Pleasants Power Station. The transaction resulted in AE Supply receiving net consideration of $1.1 billion and MP's assumption of a $73.5 million pollution control note. The $1.1 billion net consideration was originally financed by MP through an equity infusion from FE of approximately $527 million and a note payable to AE Supply of approximately $573 million. The note payable to AE Supply was paid in the fourth quarter of 2013. In accordance with the settlement, MP and PE will file a base rate case by April 30, 2014. On November 6, 2013, the WVCAG petitioned for appeal with the West Virginia Supreme Court. MP and PE filed their response to the WVCAG petition on December 27, 2013 and WVCAG filed its reply on January 16, 2014. Oral argument before the Supreme Court is scheduled for March 5, 2014. |
|
|
|
RELIABILITY MATTERS |
|
|
|
|
Federally-enforceable mandatory reliability standards apply to the bulk electric system and impose certain operating, record-keeping and reporting requirements on the Utilities, FES, AE Supply, FG, FENOC, ATSI and TrAIL. NERC is the ERO designated by FERC to establish and enforce these reliability standards, although NERC has delegated day-to-day implementation and enforcement of these reliability standards to eight regional entities, including RFC. All of FirstEnergy's facilities are located within the RFC region. FirstEnergy actively participates in the NERC and RFC stakeholder processes, and otherwise monitors and manages its companies in response to the ongoing development, implementation and enforcement of the reliability standards implemented and enforced by RFC. |
|
|
|
|
|
FirstEnergy believes that it is in compliance with all currently-effective and enforceable reliability standards. Nevertheless, in the course of operating its extensive electric utility systems and facilities, FirstEnergy occasionally learns of isolated facts or circumstances that could be interpreted as excursions from the reliability standards. If and when such items are found, FirstEnergy develops information about the item and develops a remedial response to the specific circumstances, including in appropriate cases “self-reporting” an item to RFC. Moreover, it is clear that the NERC, RFC and FERC will continue to refine existing reliability standards as well as to develop and adopt new reliability standards. Any inability on FirstEnergy's part to comply with the reliability standards for its bulk power system could result in the imposition of financial penalties that could have a material adverse effect on its financial condition, results of operations and cash flows. |
|
|
|
|
|
|
FERC MATTERS |
|
|
|
|
|
|
|
PJM Transmission Rates |
|
|
|
|
|
|
|
|
PJM and its stakeholders have been debating the proper method to allocate costs for new transmission facilities. While FirstEnergy and other parties advocated for a traditional "beneficiary pays" (or usage based) approach, others advocate for “socializing” the costs on a load-ratio share basis - each customer in the zone would pay based on its total usage of energy within PJM. On August 6, 2009, the U.S. Court of Appeals for the Seventh Circuit found that FERC had not supported a prior FERC decision to allocate costs for new 500 kV and higher voltage facilities on a load ratio share basis and, based on that finding, remanded the rate design issue to FERC. In an order dated January 21, 2010, FERC set this matter for a “paper hearing” and requested parties to submit written comments. FERC identified nine separate issues for comment and directed PJM to file the first round of comments. PJM filed certain studies with FERC on April 13, 2010, which demonstrated that allocation of the cost of high voltage transmission facilities on a beneficiary pays basis results in certain LSEs in PJM bearing the majority of the costs. FirstEnergy and a number of other utilities, industrial customers and state utility commissions supported the use of the beneficiary pays approach for cost allocation for high voltage transmission facilities. Other utilities and state utility commissions supported continued socialization of these costs on a load ratio share basis. On March 30, 2012, FERC issued an order on remand reaffirming its prior decision that costs for new transmission facilities that are rated at 500 kV or higher are to be collected from all transmission zones throughout the PJM footprint by means of a postage-stamp (or socialized) rate based on the amount of load served in a transmission zone and concluding that such methodology is just and reasonable and not unduly discriminatory or preferential. On April 30, 2012, FirstEnergy requested rehearing of FERC's March 30, 2012 order and on March 22, 2013, FERC denied rehearing. On March 29, 2013, FirstEnergy filed its Petition for Review with the U.S. Court of Appeals for the Seventh Circuit, and the case subsequently was consolidated for briefing and disposition before that court. Briefing is complete, and the case will be scheduled for oral argument, with a decision currently expected in 2014. |
|
|
|
|
|
|
|
|
|
Order No. 1000, issued by FERC on July 21, 2011, required the submission of a compliance filing by PJM or the PJM transmission owners demonstrating that the cost allocation methodology for new transmission projects directed by the PJM Board of Managers satisfied the principles set forth in the order. To demonstrate compliance with the regional cost allocation principles of the order, the PJM transmission owners, including FirstEnergy, submitted a filing to FERC on October 11, 2012, proposing a hybrid method of 50% beneficiary pays and 50% postage stamp to be effective for RTEP projects approved by the PJM Board of Managers on, and after, the effective date of the compliance filing. On January 31, 2013, FERC conditionally accepted the hybrid method to be effective on February 1, 2013, subject to refund and to a future order on PJM's separate Order No. 1000 compliance filing. On March 22, 2013, FERC granted final acceptance of the hybrid method. Certain parties have sought rehearing of parts of FERC's March 22, 2013 order. These requests for rehearing are pending before FERC. On July 10, 2013, the PJM transmission owners, including FirstEnergy, submitted filings to FERC setting forth the cost allocation method for projects that cross the borders between: (1) the PJM region and the NYISO region and; (2) the PJM region and the FERC-jurisdictional members of the SERTP region. These filings propose to allocate the cost of these interregional transmission projects based on the costs of projects that otherwise would have been constructed separately in each region. On the same date, also in response to Order No. 1000, the PJM transmission owners, including FirstEnergy, also submitted to FERC a filing stating that the cost allocation provisions for interregional transmission projects provided in the Joint Operating Agreement between PJM and MISO comply with the requirements of Order No. 1000. On December 30, 2013, FERC conditionally accepted the PJM/SERTP cross-border project cost allocation filing, subject to refund and future orders in PJM's and SERTP's related Order No. 1000 interregional compliance proceedings. The PJM/NYISO and PJM/MISO cross-border project cost allocation filings remain pending before FERC. On January 16, 2014, FERC issued an order regarding the effective date of PJM's separate Order No. 1000 compliance filing, noting that it would address the merits of the comments on and protests to that filing and related compliance filings in a future order. |
|
|
|
|
|
|
|
|
|
|
Numerous parties, including ATSI, FES, TrAIL, OE, CEI, TE, Penn, JCP&L, ME, MP, PN, WP and PE, have sought judicial review of Order No. 1000 before the U.S. Court of Appeals for the D.C. Circuit. Briefing was completed in December 2013 and oral argument is scheduled for March 20, 2014. |
|
|
|
|
|
|
|
|
|
|
|
The outcome of these proceedings and their impact, if any, on FirstEnergy cannot be predicted at this time. |
|
RTO Realignment |
|
|
On June 1, 2011, ATSI and the ATSI zone transferred from MISO to PJM. The move was performed as planned with no known operational or reliability issues for ATSI or for the wholesale transmission customers in the ATSI zone. While many of the matters involved with the move have been resolved, FERC denied recovery by means of ATSI's transmission rate for certain charges that collectively can be described as "exit fees" and certain other transmission cost allocation charges totaling approximately $78.8 million until such time as ATSI submits a cost/benefit analysis that demonstrates net benefits to customers from the move. On December 21, 2012, ATSI and other parties filed a proposed settlement agreement with FERC to resolve the exit fee and transmission cost allocation issues. However, FERC subsequently rejected that settlement stating that its action is without prejudice to ATSI submitting a cost/benefit analysis demonstrating that the benefits of the RTO realignment decisions outweigh the exit fee and transmission cost allocation charges. On October 21, 2013, FirstEnergy filed a request for rehearing of FERC's order. |
|
|
|
Separately, the question of ATSI's responsibility of certain costs for the “Michigan Thumb” transmission project continues to be disputed. Potential responsibility arises under the MISO MVP tariff, which has been litigated in complex proceedings in front of FERC and certain U.S. appellate courts. The MISO and its allied parties assert that the benefits to the ATSI zone for the Michigan Thumb project are roughly commensurate with the costs that MISO desires to charge to the ATSI zone, estimated to be as much as $16 million per year. ATSI has submitted evidence that the Michigan Thumb project provides no electric benefits to the ATSI zone and, on that basis, opposes the MISO’s efforts to impose these costs to the ATSI zone loads. The MISO and its allied parties also assert that certain language in the MISO Transmission Owners Agreement requires ATSI to pay these charges. In the event of a final non-appealable order that rules that ATSI must pay these charges, ATSI will seek recovery of these charges through its formula rate. While FERC proceedings regarding whether the MISO can charge ATSI for MVP costs remain pending, on February 24, 2014, the U.S. Supreme Court declined to hear appeals filed by FirstEnergy and other parties of the Seventh Circuit's June 2013 decision upholding FERC's acceptance of the MISO's generic MVP cost allocation proposal. |
|
In the May 31, 2011 order, FERC ruled that the costs for certain "legacy RTEP" transmission projects in PJM could be charged to transmission customers in the ATSI zone. ATSI sought rehearing of the question of whether the ATSI zone should pay these legacy RTEP charges and, on September 20, 2012, FERC denied ATSI's request for rehearing. ATSI subsequently filed a petition for review with the U.S. Court of Appeals for the D.C. Circuit. The case thereafter was briefed and oral arguments took place on December 11, 2013. A decision currently is expected in the second quarter of 2014. |
|
|
The outcome of those proceedings that address the remaining open issues related to ATSI's move into PJM cannot be predicted at this time. |
|
California Claims Matters |
|
|
In October 2006, several California governmental and utility parties presented AE Supply with a settlement proposal to resolve alleged overcharges for power sales by AE Supply to the California Energy Resource Scheduling division of the CDWR during 2001. The settlement proposal claims that CDWR is owed approximately $190 million for these alleged overcharges. This proposal was made in the context of mediation efforts by FERC and the U.S. Court of Appeals for the Ninth Circuit in several pending proceedings to resolve all outstanding refund and other claims, including claims of alleged price manipulation in the California energy markets, during 2000 and 2001. The Ninth Circuit had previously remanded one of those proceedings to FERC, which dismissed the claims of the California Parties in May 2011, and affirmed the dismissal in June 2012. On June 20, 2012, the California Parties appealed FERC's decision back to the Ninth Circuit. Briefing was completed before the Ninth Circuit on October 23, 2013. The timing of further action by the Ninth Circuit is unknown. |
|
|
|
In another proceeding, in June 2009, the California Attorney General, on behalf of certain California parties, filed another complaint with FERC against various sellers, including AE Supply, again seeking refunds for transactions in the California energy markets during 2000 and 2001. The above-noted transactions with CDWR are the basis for including AE Supply in this complaint. AE Supply filed a motion to dismiss, which was granted by FERC in May 2011, and affirmed by FERC in June 2012. The California Attorney General has appealed FERC's dismissal of its complaint to the Ninth Circuit, which has consolidated the case with other pending appeals related to California refund claims, and stayed the proceedings pending further order. |
|
|
|
|
FirstEnergy cannot predict the outcome of either of the above matters or estimate the possible loss or range of loss. |
|
PATH Transmission Project |
|
|
The PATH project was proposed to be comprised of a 765 kV transmission line from West Virginia through Virginia and into Maryland, modifications to an existing substation in Putnam County, West Virginia, and the construction of new substations in Hardy County, West Virginia and Frederick County, Maryland. PJM initially authorized construction of the PATH project in June 2007. On August 24, 2012, the PJM Board of Managers canceled the PATH project, which it had suspended in February 2011. As a result, approximately $62 million and approximately $59 million in costs incurred by PATH-Allegheny and PATH-WV, respectively, were reclassified from net property, plant and equipment to a regulatory asset for future recovery. On September 28, 2012, those companies requested authorization from FERC to recover the costs with a proposed return on equity of 10.9% (10.4% base plus 0.5% RTO membership) from PJM customers over the next five years. Several parties protested the request. On November 30, 2012, FERC issued an order denying the 0.5% return on equity adder for RTO membership and allowing the tariff changes enabling recovery of these costs to become effective on December 1, 2012, subject to settlement judge procedures and hearing if the parties do not agree to a settlement. The issues subject to settlement include the prudence of the costs, the base return on equity and the period of recovery. PATH-Allegheny and PATH-WV are currently engaged in settlement discussions with the other parties. Depending on the outcome of a possible settlement or hearing, if settlement is not achieved, PATH-Allegheny and PATH-WV may be required to refund certain amounts that have been collected under their formula rate. |
|
|
|
PATH-Allegheny and PATH-WV have requested rehearing of FERC's denial of the 0.5% return on equity adder for RTO membership; that request for rehearing remains pending before FERC. In addition, FERC has consolidated for settlement judge procedures and hearing purposes three formal challenges to the PATH formula rate annual updates submitted to FERC in June 2010, June 2011 and June 2012, with the September 28, 2012 filing for recovery of costs associated with the cancellation of the PATH project. |
|
|
|
|
Hydroelectric Asset Sale |
|
|
|
|
|
On September 4, 2013, certain of FirstEnergy’s subsidiaries submitted filings with FERC for authorization to sell eleven hydroelectric power plant projects to subsidiaries of Harbor Hydro Holdings, LLC (Harbor Hydro), a subsidiary of LS Power Equity Partners II, LP (LS Power). The eleven hydroelectric projects are: the Seneca Pumped Storage Project, Allegheny Lock & Dam No. 5, Allegheny Lock & Dam No. 6, the Lake Lynn Project, the Millville Hydro Project, the Dam No. 4 Project, the Dam No. 5 Project, and four additional projects located in Shenandoah, Front Royal and Luray, Virginia. The eleven projects have a combined generating capacity of approximately 527 MW. On February 12, 2014, the sale of the hydroelectric power plants to LS Power closed for approximately $395 million. See Note 20, Discontinued Operations and Assets Held for Sale for additional information regarding the assets sold. |
|
|
|
|
|
|
MISO Capacity Portability |
|
|
|
|
|
|
|
On June 11, 2012, FERC issued a Notice of Request for Comments regarding whether existing rules on transfer capability act as barriers to the delivery of capacity between MISO and PJM. FERC is responding to suggestions from MISO and the MISO stakeholders that PJM's rules regarding the criteria and qualifications for external generation capacity resources be changed to ease participation by resources that are located in MISO in PJM's RPM capacity auctions. FirstEnergy submitted comments and reply comments in August 2012. In the fall of 2012, FirstEnergy participated in certain stakeholder meetings to review various proposals advanced by MISO. Although none of MISO's proposals attracted significant stakeholder support, in January 2013, MISO filed a pleading with FERC that renewed many of the arguments advanced in prior MISO filings and asked FERC to take expedited action to address MISO's allegations. FirstEnergy and other parties subsequently submitted filings arguing that MISO's concerns largely are without foundation and suggesting that FERC order that the remaining concerns be addressed in the existing stakeholder process that is described in the PJM/MISO Joint Operating Agreement. On April 2, 2013, FERC issued an order directing MISO and PJM to make presentations to FERC regarding ongoing regional efforts to address whether barriers to transfer capability exist between the MISO and PJM regions and the actions the FERC should take to address any such barriers. The RTOs presented their respective positions to FERC on June 20, 2013 and provided additional information regarding their stakeholder prioritization survey, in response to a FERC request on June 27, 2013. On September 26, 2013, the RTOs jointly submitted an informational filing providing a description of and schedule for their Joint and Common Market initiatives. On December 19, 2013, FERC issued an order directing that FERC staff are to attend the “joint and common market” stakeholder meetings for the purpose of monitoring progress on the initiatives described in the September 26, 2013 joint informational filing and establishing a new proceeding to reflect the broadened scope of issues contemplated by that filing and the RTOs' joint and common market initiatives. FERC has not acted on the presentations, and the RTOs and affected parties are working to address the MISO's proposal in stakeholder proceedings. Changes to the criteria and qualifications for participation in the PJM RPM capacity auctions could have a significant impact on the outcome of those auctions, including a negative impact on the prices at which those auctions would clear. |
|
|
|
|
|
|
|
|
MOPR Reform |
|
|
|
|
|
|
|
|
|
On December 7, 2012, PJM filed amendments to its tariff to revise the MOPR used in the RPM. PJM revised the MOPR to add two broad, categorical exemptions, eliminate an existing exemption, and to limit the applicability of the MOPR to certain capacity resources. The filing also included related and conforming changes to the RPM posting requirements and to those provisions describing the role of the Independent Market Monitor for the PJM Region. On May 2, 2013, FERC issued an order in large part accepting PJM's proposed reform of the MOPR, including the proposed exemptions and applicability but also requiring PJM to commit to future review and, if necessary, additional revisions to the MOPR to accommodate changing market conditions. On June 3, 2013, FirstEnergy submitted a request for rehearing of FERC's May 2, 2013 order. In its rehearing request, FirstEnergy referenced the results of the May 2013 PJM RPM capacity auction, and publicly-available data about the reasons for the unexpectedly low "rest-of-RTO" clearing price of $59 per MW-day, as supporting its contention that the MOPR reform depressed prices as predicted in FirstEnergy's December 28, 2012 and January 25, 2013 comments. FirstEnergy's request for rehearing is pending before FERC. |
|
|
|
|
|
|
|
|
|
|
FTR Underfunding Complaint |
|
|
|
|
|
|
|
|
|
|
|
In PJM, FTRs are a mechanism to hedge congestion and they operate as a financial replacement for physical firm transmission service. FTRs are financially-settled instruments that entitle the holder to a stream of revenues based on the hourly congestion price differences across a specific transmission path in the PJM Day-ahead Energy Market. FE also performs bilateral transactions for the purpose of hedging the price differences between the location of supply resources and retail load obligations. Due to certain language in the PJM tariff, the funds that are set aside to pay FTRs can be diverted to other uses, resulting in “underfunding” of FTR payments. Since June of 2010, FES and AE Supply have lost more than $65.5 million in revenues that they otherwise would have received as FTR holders to hedge congestion costs. FES and AE Supply expect to continue to experience significant underfunding. |
|
|
|
|
|
|
|
|
|
|
|
|
On December 28, 2011, FES and AE Supply filed a complaint with FERC for the purpose of modifying certain provisions in the PJM tariff to eliminate FTR underfunding. On March 2, 2012, FERC issued an order dismissing the complaint. In its order, FERC ruled that it was not appropriate to initiate action at that time because of the unknown root causes of FTR underfunding. FERC directed PJM to convene stakeholder proceedings for the purpose of determining the root causes of the FTR underfunding. FERC went on to note that its dismissal of the complaint was without prejudice to FES and AE Supply or any other affected entity filing a complaint if the stakeholder proceedings proved unavailing. FES and AE Supply sought rehearing of FERC's order and, on July 19, 2012, FERC denied rehearing. In April, 2012, PJM issued a report on FTR underfunding. However, the PJM stakeholder process proved unavailing as the stakeholders were not willing to change the tariff to eliminate FTR underfunding. Accordingly, on February 15, 2013, FES and AE Supply refiled their complaint with FERC for the purpose of changing the PJM tariff to eliminate FTR underfunding. Various parties filed responsive pleadings, including PJM. On June 5, 2013, FERC issued its order denying the new complaint. On July 5, 2013, FirstEnergy filed a request for rehearing of FERC's order. FES and AE Supply's request for rehearing, and all subsequent filings in the docket, are pending before FERC. |
|
|
|
|
|
|
|
|
|
|
|
|
|
PJM RPM Tariff Amendments |
|
In November 2013, PJM began to submit a series of amendments to its RPM capacity tariff in order to address certain problems that have been observed in recent auctions. These problems can be grouped into three categories: (i) Demand Response (DR); (ii) imports; and (iii) modeling of transmission upgrades in calculating geographic clearing prices. The purpose of PJM’s tariff amendments is to ensure that resources that clear in the RPM auctions are available and able to satisfy all obligations under the PJM tariffs. In each of the affected dockets, FirstEnergy submitted comments as part of a coalition of utilities (generally including an affiliate of AEP, Duke and Dayton). The FirstEnergy/coalition position was that all of the PJM proposals should be accepted as proposed, and that the FERC should order PJM to take additional steps that should have the effect of eliminating additional distortions and flaws in the RPM market. FERC issued deficiency letters requesting additional information from PJM regarding the imports and modeling filings, and on January 30, 2014 accepted the DR filing as proposed. On February 18 and 21, 2014, respectively, PJM filed its responses to FERC's deficiency letters regarding the modeling and imports filings. PJM's compliance filings and all other filings in the dockets are pending before FERC. |
|
|
Market-Based Rate Authority, Triennial Update |
|
OE, CEI, TE, Penn, JCP&L, ME, PN, MP, WP, PE, AE Supply, FES, FG, NG, FirstEnergy Generation Mansfield Unit 1 Corp., Buchanan Generation, LLC, and Green Valley Hydro, LLC each hold authority from FERC to sell electricity at market-based rates. One condition for retaining this authority is that every three years each entity must file an update with the FERC that demonstrates that each entity continues to meet FERC’s requirements for holding market-based rate authority. On December 20, 2013, FESC submitted to FERC the most recent triennial market power analysis filing for each market-based rate holder for the current cycle of this filing requirement. That filing is pending before FERC. |