REGULATORY MATTERS | REGULATORY MATTERS STATE REGULATION Each of the Utilities' retail rates, conditions of service, issuance of securities and other matters are subject to regulation in the states in which it operates - in Maryland by the MDPSC, in Ohio by the PUCO, in New Jersey by the NJBPU, in Pennsylvania by the PPUC, in West Virginia by the WVPSC and in New York by the NYPSC. The transmission operations of PE in Virginia are subject to certain regulations of the VSCC. In addition, under Ohio law, municipalities may regulate rates of a public utility, subject to appeal to the PUCO if not acceptable to the utility. As competitive retail electric suppliers serving retail customers primarily in Ohio, Pennsylvania, Illinois, Michigan, New Jersey and Maryland, FES and AE Supply are subject to state laws applicable to competitive electric suppliers in those states, including affiliate codes of conduct that apply to FES, AE Supply and their public utility affiliates. In addition, if any of the FirstEnergy affiliates were to engage in the construction of significant new transmission or generation facilities, depending on the state, they may be required to obtain state regulatory authorization to site, construct and operate the new transmission or generation facility. MARYLAND PE provides SOS pursuant to a combination of settlement agreements, MDPSC orders and regulations, and statutory provisions. SOS supply is competitively procured in the form of rolling contracts of varying lengths through periodic auctions that are overseen by the MDPSC and a third party monitor. Although settlements with respect to SOS supply for PE customers have expired, service continues in the same manner until changed by order of the MDPSC. PE recovers its costs plus a return for providing SOS. The Maryland legislature adopted a statute in 2008 codifying the EmPOWER Maryland goals to reduce electric consumption and demand and requiring each electric utility to file a plan every three years. PE's current plan, covering the three-year period 2015-2017, was approved by the MDPSC on December 23, 2014. The costs of the 2015-2017 plan are expected to be approximately $68 million , of which $38 million was incurred through September 30, 2016. On July 16, 2015, the MDPSC issued an order setting new incremental energy savings goals for 2017 and beyond, beginning with the level of savings achieved under PE's current plan for 2016, and ramping up 0.2% per year thereafter to reach 2% . PE continues to recover program costs subject to a five -year amortization. Maryland law only allows for the utility to recover lost distribution revenue attributable to energy efficiency or demand reduction programs through a base rate case proceeding, and to date, such recovery has not been sought or obtained by PE. On February 27, 2013, the MDPSC issued an order (the February 27 Order) requiring the Maryland electric utilities to submit analyses relating to the costs and benefits of making further system and staffing enhancements in order to attempt to reduce storm outage durations. The order further required the Staff of the MDPSC to report on possible performance-based rate structures and to propose additional rules relating to feeder performance standards, outage communication and reporting, and sharing of special needs customer information. PE's responsive filings discussed the steps needed to harden the utility's system in order to attempt to achieve various levels of storm response speed described in the February 27 Order, and projected that it would require approximately $2.7 billion in infrastructure investments over 15 years to attempt to achieve the quickest level of response for the largest storm projected in the February 27 Order. On July 1, 2014, the Staff of the MDPSC issued a set of reports that recommended the imposition of extensive additional requirements in the areas of storm response, feeder performance, estimates of restoration times, and regulatory reporting. The Staff of the MDPSC also recommended the imposition of penalties, including customer rebates, for a utility's failure or inability to comply with the escalating standards of storm restoration speed proposed by the Staff of the MDPSC. In addition, the Staff of the MDPSC proposed that the utilities be required to develop and implement system hardening plans, up to a rate impact cap on cost. The MDPSC conducted a hearing September 15-18, 2014, to consider certain of these matters, and has not yet issued a ruling on any of those matters. NEW JERSEY JCP&L currently provides BGS for retail customers who do not choose a third party EGS and for customers of third party EGSs that fail to provide the contracted service. The supply for BGS is comprised of two components, procured through separate, annually held descending clock auctions, the results of which are approved by the NJBPU. One BGS component reflects hourly real time energy prices and is available for larger commercial and industrial customers. The second BGS component provides a fixed price service and is intended for smaller commercial and residential customers. All New Jersey EDCs participate in this competitive BGS procurement process and recover BGS costs directly from customers as a charge separate from base rates. Pursuant to the NJBPU's March 26, 2015 final order in JCP&L's 2012 rate case proceeding directing that certain studies be completed, on July 22, 2015, the NJBPU approved the NJBPU staff's recommendation to implement such studies, which include operational and financial components. The independent consultant conducting the review issued a final report on July 27, 2016, recognizing that JCP&L is meeting the NJBPU requirements and making various operational and financial recommendations. The NJBPU issued an Order on August 24, 2016, that accepted the independent consultant’s final report and directed JCP&L, the Division of Rate Counsel, and other interested parties to address the recommendations. In an Order issued October 22, 2014, in a generic proceeding to review its policies with respect to the use of a CTA in base rate cases (Generic CTA proceeding), the NJBPU stated that it would continue to apply its current CTA policy in base rate cases, subject to incorporating the following modifications: (i) calculating savings using a five -year look back from the beginning of the test year; (ii) allocating savings with 75% retained by the company and 25% allocated to rate payers; and (iii) excluding transmission assets of electric distribution companies in the savings calculation. On November 5, 2014, the Division of Rate Counsel appealed the NJBPU Order regarding the Generic CTA proceeding to the New Jersey Superior Court and JCP&L has filed to participate as a respondent in that proceeding. Briefing has been completed. The oral argument was held on October 25, 2016. On April 28, 2016, JCP&L filed tariffs with the NJBPU proposing a general rate increase associated with its distribution operations that seeks to improve service and benefit customers by supporting equipment maintenance, tree trimming, and inspections of lines, poles and substations, while also compensating for other business and operating expenses. The filing requested approval to increase annual operating revenues by approximately $142.1 million based upon a hybrid test year for the twelve months ending June 30, 2016. On July 13, 2016, this matter was submitted to the Office of Administrative Law for hearing and the issuance of an Initial Decision. On September 30, 2016, JCP&L filed an update to its filing, which includes actual data for the twelve months ended June 30, 2016, requesting an increase to annual operating revenues by approximately $146.6 million . On October 19, 2016, an order was received approving the agreed upon procedural schedule. Hearings are scheduled to occur in January 2017 through March 2017. On November 2, 2016, JCP&L achieved a settlement-in-principle with all the intervening parties providing for an annual $80 million distribution revenue increase, which will take effect on January 1, 2017, subject to finalization, execution and NJBPU approval of a Stipulation of Settlement. On June 19, 2015, JCP&L, along with PN, ME, FET and MAIT made filings with FERC, the NJBPU, and the PPUC requesting authorization for JCP&L, PN and ME to contribute their transmission assets to MAIT, a new transmission-only subsidiary of FET. The procedural schedule was suspended while the NJBPU considered a motion on a legal issue regarding whether MAIT can be designated as a "public utility" in New Jersey. On February 24, 2016, the NJBPU issued an Order concluding that MAIT does not satisfy the “electricity distribution” element necessary for “public utility” status because MAIT would not own any electric distribution assets in New Jersey. On April 22, 2016, JCP&L and MAIT filed a supplemental petition and testimony seeking to include certain JCP&L distributions assets in the transfer to satisfy the "electricity distribution" element necessary for "public utility" status in accordance with the NJBPU’s February 24, 2016 order. In order to allow MAIT to file its formula transmission rate with an effective date of January 1, 2017, on September 8, 2016, JCP&L and MAIT submitted a letter to the NJBPU to withdraw their petition to transfer JCP&L assets into MAIT. The NJBPU administratively closed the matter on September 30, 2016. See Transfer of Transmission Assets to MAIT in FERC Matters below for further discussion of this transaction. OHIO On August 4, 2014, the Ohio Companies filed an application with the PUCO seeking approval of their ESP IV entitled Powering Ohio's Progress . ESP IV included a proposed Rider RRS, which would flow through to customers either charges or credits representing the net result of the price paid to FES through an eight-year FERC-jurisdictional PPA, referred to as the ESP IV PPA, against the revenues received from selling such output into the PJM markets. The Ohio Companies entered into stipulations which modified ESP IV and which included PUCO Staff as a signatory party, in addition to other signatories. On March 31, 2016, the PUCO issued an Opinion and Order adopting and approving the Ohio Companies’ stipulated ESP IV with modifications. FES and the Ohio Companies entered into the ESP IV PPA on April 1, 2016. On January 27, 2016, certain parties filed a complaint with FERC against FES and the Ohio Companies requesting FERC review the ESP IV PPA under Section 205 of the FPA. On April 27, 2016, FERC issued an order granting the complaint, prohibiting any transactions under the ESP IV PPA pending future authorization by FERC, and directing FES to submit the ESP IV PPA for FERC review if the parties desired to transact under the agreement. FES and the Ohio Companies did not file the ESP IV PPA for FERC review but rather agreed to suspend the ESP IV PPA. FES and the Ohio Companies subsequently advised FERC of this course of action. On April 29, 2016 and May 2, 2016, several parties, including the Ohio Companies, filed applications for rehearing on the Ohio Companies’ ESP IV with the PUCO. The Ohio Companies’ Application for Rehearing included a modified Rider RRS proposal but did not include a FERC-jurisdictional PPA. The PUCO accepted the applications for rehearing for further consideration and provided parties an opportunity to comment on the Ohio Companies’ Application for Rehearing and file an alternative proposal. PUCO Staff recommended that the PUCO deny the Ohio Companies’ modified Rider RRS proposal and recommended a new Rider DMR providing for the collection of $204 million annually (grossed up for income taxes) for three years with a possible extension for an additional two years. The Ohio Companies recommended that the PUCO approve the proposed modified Rider RRS and that a properly designed Rider DMR would be valued at $558 million annually for 8 years , and include an additional amount that recognizes the value of the economic impact of FirstEnergy maintaining its headquarters in Ohio. Several parties subsequently filed protests and comments with FERC alleging, among other things, that the modified Rider RRS constitutes a "virtual PPA". The filings and FirstEnergy’s responses thereto are pending before FERC. On September 6, 2016, while the applications for rehearing were still pending before the PUCO, the OCC and NOAC filed a notice of appeal with the Ohio Supreme Court appealing various PUCO and Attorney Examiner Entries on the parties’ applications for rehearing. On September 16, 2016, the Ohio Companies intervened and filed a motion to dismiss the appeal. The appeal remains pending before the Ohio Supreme Court. On October 12, 2016, the PUCO issued an opinion and order ruling on the parties’ applications for rehearing and further modified ESP IV. The PUCO order denied the Ohio Companies’ modified Rider RRS proposal, and instead approved a Rider DMR proposed by PUCO Staff, with modifications. As a result of the stipulations, the PUCO’s March 31, 2016 Opinion and Order and the PUCO’s October 12, 2016 order, the material terms of ESP IV include: • An eight -year term (June 1, 2016 - May 31, 2024). • The Rider DMR which provides for the Ohio Companies to collect $132.5 million annually for three years , with the possibility of a two-year extension. The Rider DMR will be grossed up for taxes, resulting in an approved amount of approximately $204 million annually. Revenues from the Rider DMR will be excluded from the significantly excessive earnings test for the initial three-year term but the exclusion will be reconsidered upon application for a potential two-year extension. • Three conditions for continued recovery under the Rider DMR: (1) retention of the corporate headquarters and nexus of operations in Akron, Ohio; (2) no change in control of the Ohio Companies; and (3) a demonstration of sufficient progress in the implementation of grid modernization programs approved by the PUCO. • No restrictions on the Ohio Companies’ use of funds collected under the Rider DMR. However, the PUCO directed the PUCO Staff to periodically review how the Ohio Companies and FE use the funds to ensure the funds are used, directly or indirectly, in support of grid modernization. Uses of funds to indirectly support grid modernization could include, e.g., reducing outstanding pension obligations or reducing debt. • Continuation of a base distribution rate freeze through May 31, 2024. • Continuation of the supply of power to non-shopping customers at a market-based price set through an auction process. • Continuation of Rider DCR with increased revenue caps of approximately $30 million per year from June 1, 2016 through May 31, 2019; $20 million per year from June 1, 2019 through May 31, 2022; and $15 million per year from June 1, 2022 through May 31, 2024 that supports continued investment related to the distribution system for the benefit of customers. • Collection of lost distribution revenues associated with energy efficiency and peak demand reduction programs. • Continuation of a commitment not to recover from retail customers certain costs related to transmission cost allocations for the longer of the five-year period from June 1, 2011 through May 31, 2016 or when the amount of such costs avoided by customers for certain types of products totals $360 million . • Potential procurement of 100 MW of new Ohio wind or solar resources subject to a demonstrated need to procure new renewable energy resources as part of a strategy to further diversify Ohio's energy portfolio. • An agreement to file a case with the PUCO by April 3, 2017, seeking to transition to decoupled base rates for residential customers. • An agreement to file a Grid Modernization Business Plan for PUCO consideration and approval (which filing was made on February 29, 2016). • A goal across FirstEnergy to reduce CO 2 emissions by 90% below 2005 levels by 2045. • A contribution of $3 million per year ( $24 million over the eight -year term) to fund energy conservation programs, economic development and job retention in the Ohio Companies service territory. • Contributions of $2.4 million per year ( $19 million over the eight -year term) to fund a fuel-fund in each of the Ohio Companies service territories to assist low-income customers. • A contribution of $1 million per year ( $8 million over the eight -year term) to establish a Customer Advisory Council to ensure preservation and growth of the competitive market in Ohio. Finally, on March 21, 2016, a number of generation owners filed with FERC a complaint against PJM requesting that FERC expand the MOPR in the PJM Tariff to prevent the alleged artificial suppression of prices in the PJM capacity markets by state-subsidized generation, in particular alleged price suppression that could result from the ESP IV PPA and other similar agreements. The complaint requested that FERC direct PJM to initiate a stakeholder process to develop a long-term MOPR reform for existing resources that receive out-of-market revenue. This proceeding remains pending before FERC. Under Ohio's energy efficiency standards (SB221 and SB310), and based on the Ohio Companies' amended energy efficiency plans, the Ohio Companies are required to implement energy efficiency programs that achieve a total annual energy savings equivalent of 2,266 GWHs in 2015 and 2,288 GWHs in 2016, and then begin to increase by 1% each year in 2017, subject to legislative amendments to the energy efficiency standards discussed below. The Ohio Companies are also required to retain the 2014 peak demand reduction level for 2015 and 2016 and then increase the benchmark by an additional 0.75% thereafter through 2020, subject to legislative amendments to the peak demand reduction standards discussed below. On September 30, 2015, the Energy Mandates Study Committee issued its report related to energy efficiency and renewable energy mandates, recommending that the current level of mandates remain in place indefinitely. The report also recommended: (i) an expedited process for review of utility proposed energy efficiency plans; (ii) ensuring maximum credit for all of Ohio's Energy Initiatives; (iii) a switch from energy mandates to energy incentives; and (iv) a declaration be made that the General Assembly may determine the energy policy of the state. Legislation was introduced to address issues raised in the Energy Mandates Study Committee report, namely SB320 and HB554. SB320 proposes to freeze energy efficiency and renewable energy requirements for an additional four years at 2014 levels, as well as addressing net metering issues. HB554 proposes to freeze energy efficiency and renewable energy requirements through 2027 at 2014 levels. On September 24, 2014, the Ohio Companies filed an amendment to their energy efficiency portfolio plan as contemplated by SB310, seeking to suspend certain programs for the 2015-2016 period in order to better align the plan with the new benchmarks under SB310. On November 20, 2014, the PUCO approved the Ohio Companies' amended portfolio plan. Several applications for rehearing were filed, and the PUCO granted those applications for further consideration of the matters specified in those applications and the matter remains pending before the PUCO. On April 15, 2016, the Ohio Companies filed an application for approval of their three-year energy efficiency portfolio plans for the period from January 1, 2017 through December 31, 2019. The plans as proposed comply with benchmarks contemplated by SB310 and provisions of the ESP IV, and include a portfolio of energy efficiency programs targeted to a variety of customer segments, including residential customers, low income customers, small commercial customers, large commercial and industrial customers and governmental entities. The Ohio Companies anticipate the cost of the plans will be approximately $323 million over the life of the portfolio plans and such costs are expected to be recovered through the Ohio Companies’ existing rate mechanisms. The hearing is scheduled for November 21-23, 2016. On September 16, 2013, the Ohio Companies filed with the Supreme Court of Ohio a notice of appeal of the PUCO's July 17, 2013 Entry on Rehearing related to energy efficiency, alternative energy, and long-term forecast rules stating that the rules issued by the PUCO are inconsistent with, and are not supported by, statutory authority. On October 23, 2013, the PUCO filed a motion to dismiss the appeal, which was denied. On August 9, 2016, upon a Joint Application for Dismissal filed by the Ohio Companies, PUCO and the ELPC, the Ohio Supreme Court dismissed the appeal. Ohio law requires electric utilities and electric service companies in Ohio to serve part of their load from renewable energy resources measured by an annually increasing percentage amount through 2026, subject to legislative amendments discussed above, except 2015 and 2016 that remain at the 2014 level. The Ohio Companies conducted RFPs in 2009, 2010 and 2011 to secure RECs to help meet these renewable energy requirements. In September 2011, the PUCO opened a docket to review the Ohio Companies' alternative energy recovery rider through which the Ohio Companies recover the costs of acquiring these RECs. The PUCO issued an Opinion and Order on August 7, 2013, approving the Ohio Companies' acquisition process and their purchases of RECs to meet statutory mandates in all instances except for certain purchases arising from one auction and directed the Ohio Companies to credit non-shopping customers in the amount of $43.4 million , plus interest, on the basis that the Ohio Companies did not prove such purchases were prudent. On December 24, 2013, following the denial of their application for rehearing, the Ohio Companies filed a notice of appeal and a motion for stay of the PUCO's order with the Supreme Court of Ohio, which was granted. On February 18, 2014, the OCC and the ELPC also filed appeals of the PUCO's order. The Ohio Companies timely filed their merit brief with the Supreme Court of Ohio and the briefing process has concluded. The matter is not yet scheduled for oral argument. On April 9, 2014, the PUCO initiated a generic investigation of marketing practices in the competitive retail electric service market, with a focus on the marketing of fixed-price or guaranteed percent-off SSO rate contracts where there is a provision that permits the pass-through of new or additional charges. On November 18, 2015, the PUCO ruled that on a going-forward basis, pass-through clauses may not be included in fixed-price contracts for all customer classes. On December 18, 2015, FES filed an Application for Rehearing seeking to change the ruling or have it only apply to residential and small commercial customers. On January 13, 2016, the PUCO granted reconsideration for further consideration of the matters specified in the applications for rehearing. PENNSYLVANIA The Pennsylvania Companies currently operate under DSPs that expire on May 31, 2017, and provide for the competitive procurement of generation supply for customers that do not choose an alternative EGS or for customers of alternative EGSs that fail to provide the contracted service. The default service supply is currently provided by wholesale suppliers through a mix of long-term and short-term contracts procured through spot market purchases, quarterly descending clock auctions for 3-, 12- and 24-month energy contracts, and one RFP seeking 2-year contracts to serve SRECs for ME, PN and Penn. Following the expiration of the current DSPs, the Pennsylvania Companies will operate under new DSPs for the June 1, 2017 through May 31, 2019 delivery period, which would provide for the competitive procurement of generation supply for customers who do not choose an alternative EGS or for customers of alternative EGSs that fail to provide the contracted service. Under the programs, the supply would be provided by wholesale suppliers through a mix of 12 and 24-month energy contracts, as well as one RFP for 2-year SREC contracts for ME, PN and Penn. In addition, the plan includes modifications to the Pennsylvania Companies’ existing POR programs in order to reduce the level of uncollectible expense the Pennsylvania Companies experience associated with alternative EGS charges. Pursuant to Pennsylvania's EE&C legislation (Act 129 of 2008) and PPUC orders, Pennsylvania EDCs implement energy efficiency and peak demand reduction programs. The Pennsylvania Companies' Phase II EE&C Plans were effective through May 31, 2016. Total Phase II costs of these plans were expected to be approximately $175 million and recoverable through the Pennsylvania Companies' reconcilable EE&C riders. On June 19, 2015, the PPUC issued a Phase III Final Implementation Order setting: demand reduction targets, relative to each Pennsylvania Companies' 2007-2008 peak demand (in MW), at 1.8% for ME, 1.7% for Penn, 1.8% for WP, and 0% for PN; and energy consumption reduction targets, as a percentage of each Pennsylvania Companies’ historic 2010 forecasts (in MWH), at 4.0% for ME, 3.9% for PN, 3.3% for Penn, and 2.6% for WP. The Pennsylvania Companies' Phase III EE&C plans for the June 2016 through May 2021 period, which were approved in March 2016, are designed to achieve the targets established in the PPUC's Phase III Final Implementation Order without recovery to implement the EE&C plans. Pursuant to Act 11 of 2012, Pennsylvania EDCs may establish a DSIC to recover costs of infrastructure improvements and costs related to highway relocation projects with PPUC approval. Pennsylvania EDCs must file LTIIPs outlining infrastructure improvement plans for PPUC review and approval prior to approval of a DSIC. On October 19, 2015, each of the Pennsylvania Companies filed LTIIPs with the PPUC for infrastructure improvement over the five -year period of 2016 to 2020 for the following costs: WP $88.34 million ; PN $56.74 million ; Penn $56.35 million ; and ME $43.44 million . On February 11, 2016, the PPUC approved the Pennsylvania Companies' LTIIPs. On February 16, 2016, the Pennsylvania Companies filed DSIC riders for PPUC approval for quarterly cost recovery associated with the capital projects approved in the LTIIPs. On June 9, 2016, the PPUC approved the Pennsylvania Companies’ DSIC riders to be effective July 1, 2016, subject to hearings and refund or reallocation among customers. On April 28, 2016, each of the Pennsylvania Companies filed tariffs with the PPUC proposing general rate increases associated with their distribution operations that will benefit customers by modernizing the grid with smart technologies, increasing vegetation management activities, and continuing other customer service enhancements. The filings request approval to increase annual operating revenues by approximately $140.2 million at ME, $158.8 million at PN, $42.0 million at Penn, and $98.2 million at WP, based upon fully projected future test years for the twelve months ending December 31, 2017 at each of the Pennsylvania Companies. As a result of the enactment of Act 40 of 2016 that terminated the practice of making a CTA when calculating a utility’s federal income taxes for ratemaking purposes, the Pennsylvania Companies submitted supplemental testimony on July 7, 2016, that quantified the value of the elimination of the CTA and outlined their plan for investing 50 percent of that amount in rate base eligible equipment as required by the new law. Formal settlement agreements for each of the Pennsylvania Companies were filed on October 14, 2016, which provide increases in annual operating revenues of approximately $96 million at ME, $100 million at PN, $29 million at Penn, and $66 million at WP, and are subject to PPUC approval. One item related to the calculation of DSIC rates was reserved for briefing, with briefs filed by two parties. The proposed new rates are expected to take effect in January 2017 pending regulatory approval, which is expected no later than January 26, 2017. On June 19, 2015, ME and PN, along with JCP&L, FET and MAIT made filings with FERC, the NJBPU, and the PPUC requesting authorization for JCP&L, PN and ME to contribute their transmission assets to MAIT, a new transmission-only subsidiary of FET. On March 4, 2016, a Joint Petition for Full Settlement was submitted to the PPUC for consideration and approval. On April 18, 2016, the ALJs issued an Initial Decision approving the Joint Petition for Full Settlement without modifications. On July 21, 2016, the PPUC adopted a Motion approving the Joint Petition for Full Settlement with minor modifications. On August 24, 2016, the PPUC issued a Final Order approving the Joint Settlement consistent with the July 21, 2016 Motion. See Transfer of Transmission Assets to MAIT in FERC Matters below for further discussion of this transaction. WEST VIRGINIA MP and PE provide electric service to all customers through traditional cost-based, regulated utility ratemaking. MP and PE recover net power supply costs, including fuel costs, purchased power costs and related expenses, net of related market sales revenue through the ENEC. MP's and PE's ENEC rate is updated annually. MP and PE filed with the WVPSC on March 31, 2016 their Phase II energy efficiency program proposal for approval. MP and PE are proposing three energy efficiency programs to meet their Phase II requirement of energy efficiency reductions of 0.5% of 2013 distribution sales for the January 1, 2017 through May 31, 2018 period, as agreed to by MP and PE, and approved by the WVPSC in the 2012 proceeding approving the transfer of ownership of Harrison Power Station to MP. The costs for the program are expected to be $10.4 million and will be eligible for recovery through the existing energy efficiency rider which is reviewed in the fuel (ENEC) case each year. A unanimous settlement was reached by the parties on all issues and presented to the WVPSC on August 18, 2016. An order approving the settlement in full without modification was issued by the WVPSC on September 23, 2016. Under the order, the programs may begin as of the date of such order, but no later than January 1, 2017. The Staff of the WVPSC and the Consumer Advocate Division filed a Show Cause petition on August 5, 2016, requesting the WVPSC order MP and PE to file and implement RFPs for all future capacity and energy requirements above 100 MWs and that they comply with an RFP settlement provision from the Harrison asset acquisition. MP and PE filed a timely response to the petition arguing for dismissal on September 7, 2016. On October 17, 2016, the WVPSC denied the petition filed by the Staff of the WVPSC and the Consumer Advocate Division and dismissed the case. On August 16, 2016, MP and PE filed their annual ENEC case proposing an approximate $65 million annual increase in rates effective January 1, 2017, which is a 4.7% overall increase over existing rates. The $65 million increase is comprised of $119 million under-recovered balance as of June 30, 2016, and a projected $54 million over-recovery for the 2017 rate effective period. A hearing has been set for November 9 and 10, 2016 with an order expected to be issued in the fourth quarter of 2016. On August 22, 2016, MP and PE filed an application for approval of a modernization and improvement plan for coal-fired boilers at electric power plants and cost-recovery surcharge proposing an approximate $6.9 million annual increase in rates proposed to be effective May 1, 2017, which is a 0.5% overall increase over existing rates. The filing is in response to recent legislation by the West Virginia Legislature session permitting accelerated recovery of costs related to modernizing and improving coal-fired boilers, including costs related to meeting environmental requirements and reducing emissions. The filing was supplemented on September 28, 2016, to add two additional projects, resulting in an approximate $7.4 million annual increase in rates. The Staff of the WVPSC has filed a motion to dismiss the case arguing the new statute was not meant to recover these types of projects, but the WVPSC has set the case for hearing for February 21-23, 2017. On December 30, 2015, MP filed an IRP identifying a capacity shortfall starting in 2016 and exceeding 700 MW by 2020 and 850 MW by 2027. On June 3, 2016, the WVPSC accepted the IRP finding that IRPs are informational and that it must not approve or disapprove the IRP. MP Plans to issue a RFP to address its generation shortfall identified in the IRP by the end of the year. RELIABILITY MATTERS Federally-enforceable mandatory reliability standards apply |