3.7.4 Owner shall be responsible for retaining an independent testing laboratory to determine the nature of the material encountered and whether it is a Hazardous Material requiring corrective measures or remedial action. Such measures shall be the sole responsibility of Owner, and shall be performed in a manner minimizing any adverse effect upon the Work.
3.7.5 If Design-Builder incurs additional costs or is delayed due to the presence or remediation of Hazardous Material discovered at the Worksite, Design-Builder shall be entitled to an equitable adjustment in the GMP, compensation for Design Phase services, Design-Builder’s Fee, or the Date of Substantial Completion or the Date of Final Completion.
3.7.6 To the extent permitted under §6.5 and to the extent not caused by the negligent or intentionally wrongful acts or omissions of Design-Builder, its Subcontractors, Suppliers, and Sub-subcontractors, and the agents, officers, directors, and employees of each of them, Owner shall defend, indemnify, and hold harmless Design-Builder, its Subcontractors, and Subsubcontractors, and the agents, officers, directors, and employees of each of them, from and against all claims, damages, losses, costs, and expenses, including but not limited to reasonable attorneys’ fees, costs, and expenses incurred in connection with any dispute resolution procedure, arising out of or relating to the performance of the Work in any area affected by Hazardous Material.
3.7.7 MATERIALS BROUGHT TO THE SITE
3.7.7.1 Safety Data Sheets (SDS) as required by Law and pertaining to materials or substances used or consumed in the performance of the Work, whether obtained by Design-Builder, Subcontractors, Owner, or Others, shall be maintained at the Project by Design-Builder and made available to Owner and Subcontractors.
3.7.7.2 Design-Builder shall be responsible for the proper handling, application, storage, removal, and disposal of all materials brought to the Worksite by Design-Builder. Upon the issuance of the Certificate of Substantial Completion of the Work, Owner shall be responsible for materials and substances brought to the Worksite by Design-Builder if such materials or substances are required by the Contract Documents.
3.7.7.3 To the extent caused by the negligent or intentionally wrongful acts or omissions of Design-Builder, its agents, officers, directors, and employees, Design-Builder shall indemnify and hold harmless Owner, its agents, officers, directors, and employees, from and against any and all claims, damages, losses, costs, and expenses, including but not limited to attorneys’ fees, costs, and expenses incurred in connection with any dispute resolution procedure, arising out of or relating to the delivery, handling, application, storage, removal, and disposal of materials and substances brought to the Worksite by Design-Builder.
3.7.8 Section 3.7 shall survive the completion of the Work or Agreement termination.
3.8 WARRANTY
3.8.1 Design-Builder warrants that all materials and equipment furnished under the Construction Phase of this Agreement will be new unless otherwise specified, of good quality, in conformance with the Contract Documents, and free from defective workmanship and materials. Warranties shall commence on the Date of Substantial Completion of the Work or of a designated portion.
3.8.2 To the extent products, equipment, systems, or materials incorporated in the Work are specified and purchased by Owner, they shall be covered exclusively by the warranty of the manufacturer. There are no warranties which extend beyond the description on the face of any such warranty. To the extent products, equipment, systems, or materials incorporated in the Work are specified by Owner but purchased by Design-Builder and are inconsistent with selection criteria that otherwise would have been followed by Design-Builder, Design-Builder shall assist Owner in pursuing warranty claims. ALL OTHER WARRANTIES EXPRESSED OR IMPLIED INCLUDING THE WARRANTY OF MERCHANTABILITY AND THE WARRANTY OF FITNESS FOR A PARTICULAR PURPOSE ARE EXPRESSLY DISCLAIMED.