Environmental Matters | 9 Months Ended |
Sep. 30, 2013 |
Environmental Matters Disclosure [Abstract] | ' |
Environmental Matters | ' |
Environmental Matters |
|
Indiana Senate Bill 251 is also applicable to federal environmental mandates impacting Vectren South's electric operations. The Company is currently evaluating the impact Senate Bill 251 may have on its operations, including applicability of the stricter regulations the EPA is currently considering involving air quality, fly ash disposal, cooling tower intake facilities, waste water discharges, and greenhouse gases. These issues are further discussed below. |
|
Air Quality |
Clean Air Interstate Rule / Cross-State Air Pollution Rule |
In July 2011, the EPA finalized the Cross-State Air Pollution Rule (CSAPR). CSAPR was the EPA’s response to the US Court of Appeals for the District of Columbia’s (the Court) remand of the Clean Air Interstate Rule (CAIR). CAIR was originally established in 2005 as an allowance cap and trade program that required reductions from coal-burning power plants for NOx emissions beginning January 1, 2009 and SO2 emissions beginning January 1, 2010, with a second phase of reductions in 2015. In an effort to address the Court’s finding that CAIR did not adequately ensure attainment of pollutants in certain downwind states due to unlimited trading of SO2 and NOx allowances, CSAPR reduced the ability of facilities to meet emission reduction targets through allowance trading. Like CAIR, CSAPR set individual state caps for SO2 and NOx emissions. However, unlike CAIR in which states allocated allowances to generating units through state implementation plans, CSAPR allowances were allocated to individual units directly through the federal rule. CSAPR reductions were to be achieved with initial step reductions beginning January 1, 2012, and final compliance to be achieved in 2014. Multiple administrative and judicial challenges were filed. On December 30, 2011, the Court granted a stay of CSAPR and left CAIR in place pending its review. On August 21, 2012, the Court vacated CSAPR and directed the EPA to continue to administer CAIR. In October 2012, the EPA filed its request for a hearing before the full federal appeals court that struck down the CSAPR. EPA's request for rehearing was denied by the Court on January 24, 2013. In March 2013, the EPA filed a petition for review with the US Supreme Court, and in June 2013 the Supreme Court agreed to review the lower court decision. A decision by the Supreme Court is expected in 2014. The Company remains in full compliance with CAIR (see additional information below "Conclusions Regarding Environmental Regulations"). |
|
Mercury and Air Toxics (MATS) Rule |
On December 21, 2011, the EPA finalized the Utility MATS Rule. The MATS Rule sets emission limits for hazardous air pollutants for existing and new coal-fired power plants and identifies the following broad categories of hazardous air pollutants: mercury, non-mercury hazardous air pollutants (primarily arsenic, chromium, cobalt, and selenium), and acid gases (hydrogen cyanide, hydrogen chloride, and hydrogen fluoride). The rule imposes mercury emission limits for two sub-categories of coal, and proposed surrogate limits for non-mercury and acid gas hazardous air pollutants. The EPA did not grant blanket compliance extensions, but asserted that states have broad authority to grant one year extensions for individual electric generating units where potential reliability impacts have been demonstrated. Reductions are to be achieved within three years of publication of the final rule in the Federal register (April 2015). Initiatives to suspend CSAPR’s implementation by Congress also apply to the implementation of the MATS rule. Multiple judicial challenges were filed and briefing is proceeding. The EPA agreed to reconsider MATS requirements for new construction. Such requirements are more stringent than those for existing plants. Utilities planning new coal-fired generation had argued standards outlined in the MATS could not be attained even using the best available control technology. The EPA issued its revised emission limits for new construction in March 2013. |
|
Notice of Violation for A.B. Brown Power Plant |
The Company received a notice of violation (NOV) from the EPA in November 2011 pertaining to its A.B. Brown power plant. The NOV asserts that when the power plant was equipped with SCRs the correct permits were not obtained or the best available control technology to control incidental sulfuric acid mist was not installed. |
|
Information Request |
SIGECO and Alcoa Generating Corporation (AGC), a subsidiary of ALCOA, own a 300 MW Unit 4 at the Warrick Power Plant as tenants in common. AGC and SIGECO also share equally in the cost of operation and output of the unit. In January 2013, AGC received an information request from the EPA under Section 114 of the Clean Air Act for historical operational information on the Warrick Power Plant. In April 2013, ALCOA filed a timely response to the information request. |
|
Water |
Section 316(b) of the Clean Water Act requires that generating facilities use the “best technology available” to minimize adverse environmental impacts in a body of water. More specifically, Section 316(b) is concerned with impingement and entrainment of aquatic species in once-through cooling water intake structures used at electric generating facilities. In April 2009, the U.S. Supreme Court affirmed that the EPA could, but was not required to, consider costs and benefits in making the evaluation as to the best technology available for existing generating facilities. The regulation was remanded back to the EPA for further consideration. In March 2011, the EPA released its proposed Section 316(b) regulations. The EPA did not mandate the retrofitting of cooling towers in the proposed regulation, but if finalized, the regulation will leave it to each state to determine whether cooling towers should be required on a case by case basis. A final rule is expected in 2013. Depending on the final rule and on the Company’s facts and circumstances, capital investments could approximate $40 million if new infrastructure, such as new cooling water towers, is required. Costs for compliance with these final regulations should qualify as federally mandated regulatory requirements and be recovered under Indiana Senate Bill 251 referenced above. |
|
Under the Clean Water Act, EPA sets technology-based guidelines for water discharges from new and existing facilities. EPA is currently in the process of revising the existing steam electric effluent limitation guidelines that set the technology-based water discharge limits for the electric power industry. EPA is focusing its rulemaking on wastewater generated primarily by pollution control equipment necessitated by the comprehensive air regulations. The EPA released proposed rules on April 19, 2013 and the Company is reviewing the proposal. At this time, it is not possible to estimate what potential costs may be required to meet these new water discharge limits, however costs for compliance with these regulations should qualify as federally mandated regulatory requirements and be recoverable under Senate Bill 251 referenced above. |
|
Conclusions Regarding Environmental Regulations |
To comply with Indiana’s implementation plan of the Clean Air Act, and other federal air quality standards, the Company obtained authority from the IURC to invest in clean coal technology. Using this authorization, the Company invested approximately $411 million starting in 2001 with the last equipment being placed into service on January 1, 2010. The pollution control equipment included Selective Catalytic Reduction (SCR) systems, fabric filters, and an SO2 scrubber at its generating facility that is jointly owned with AGC (the Company’s portion is 150 MW). SCR technology is the most effective method of reducing NOx emissions where high removal efficiencies are required and fabric filters control particulate matter emissions. The unamortized portion of the $411 million clean coal technology investment was included in rate base for purposes of determining SIGECO’s new electric base rates approved in the latest base rate order obtained April 27, 2011. SIGECO’s coal-fired generating fleet is 100 percent scrubbed for SO2 and 90 percent controlled for NOx. |
|
Utilization of the Company’s NOx and SO2 allowances can be impacted as regulations are revised and implemented. Most of these allowances were granted to the Company at zero cost; therefore, any reduction in carrying value that could result from future changes in regulations would be immaterial. |
|
The Company continues to review the sufficiency of its existing pollution control equipment in relation to the requirements described in the MATS Rule, the recent renewal of water discharge permits, and the NOV discussed above. Due to the correlation among the various requirements set forth, it is possible some operational modifications to the control equipment will be required. Additional capital investments, operating expenses, and possibly the purchase of emission allowances may be required. The Company is continuing to evaluate potential technologies to address compliance and what the additional costs may be associated with these efforts. Currently, it is expected that the capital costs could be between $80 million and $110 million. Compliance is required by government regulation, and the Company believes that such additional costs, if incurred, should be recoverable under Senate Bill 251 referenced above. The Company is evaluating current and/or deferral of regulatory recovery that will moderate the impact on customer rates in the near term. |
|
Coal Ash Waste Disposal & Ash Ponds |
In June 2010, the EPA issued proposed regulations affecting the management and disposal of coal combustion products, such as ash generated by the Company’s coal-fired power plants. The proposed rules more stringently regulate these byproducts and would likely increase the cost of operating or expanding existing ash ponds and the development of new ash ponds. The alternatives include regulating coal combustion by-products that are not being beneficially reused as hazardous waste. The EPA did not offer a preferred alternative, but took public comment on multiple alternative regulations. Rules have not been finalized given oversight hearings, congressional interest, and other factors. |
|
At this time, the majority of the Company’s ash is being beneficially reused. However, the alternatives proposed would require modification to, or closure of, existing ash ponds. The Company estimates capital expenditures to comply could be as much as $30 million, and such expenditures could exceed $100 million if the most stringent of the alternatives is selected. Annual compliance costs could increase slightly or be impacted by as much as $5 million. Costs for compliance with these regulations should qualify as federally mandated regulatory requirements and be recoverable under Senate Bill 251 referenced above. |
|
Climate Change |
In April 2007, the US Supreme Court determined that greenhouse gases (GHG's) meet the definition of "air pollutant" under the Clean Air Act and ordered the EPA to determine whether GHG emissions from motor vehicles cause or contribute to air pollution that may reasonably be anticipated to endanger public health or welfare. In April 2009, the EPA published its proposed endangerment finding for public comment. The proposed endangerment finding concludes that carbon emissions from mobile sources pose an endangerment to public health and the environment. The endangerment finding was finalized in December 2009, and is the first step toward the EPA regulating carbon emissions through the existing Clean Air Act in the absence of specific carbon legislation from Congress. |
|
The EPA has promulgated two GHG regulations that apply to the Company’s generating facilities. In 2009, the EPA finalized a mandatory GHG emissions registry which requires the reporting of emissions. The EPA has also finalized a revision to the Prevention of Significant Deterioration (PSD) and Title V permitting rules which would require facilities that emit 75,000 tons or more of GHG's a year to obtain a PSD permit for new construction or a significant modification of an existing facility. The EPA's PSD and Title V permitting rules for GHG's were upheld by the US Court of Appeals for the District of Columbia. In 2012, the EPA proposed New Source Performance Standards (NSPS) for GHG's for new electric generating facilities under the Clean Air Act Section 111(b). On October 15, the US Supreme Court agreed to review a focused appeal on the issue of whether the GHG rule applicable to mobile sources triggered PSD permitting for all stationary sources such as Vectren's power plants. A decision is not expected until 2014. |
|
In July 2013, the President announced a Climate Action Plan, which calls on the EPA to re-propose and finalize the new source rule expeditiously, and by June 2014 propose, and by June 2015 finalize, NSPS standards for GHG's for existing electric generating units which would apply to Vectren's power plants. States must have their implementation plans to the EPA no later than June 2016. The President's Climate Action Plan did not provide any detail as to actual emission targets or compliance requirements. The Company anticipates that these initial standards will focus on power plant efficiency and other coal fleet carbon intensity reduction measures. The Company believes that such additional costs, if necessary, should be recoverable under Indiana Senate Bill 251 referenced above. |
|
Numerous competing federal legislative proposals have also been introduced in recent years that involve carbon, energy efficiency, and renewable energy. Comprehensive energy legislation at the federal level continues to be debated, but there has been little progress to date. The progression of regional initiatives throughout the United States has also slowed. |
|
Impact of Legislative Actions & Other Initiatives is Unknown |
If regulations are enacted by the EPA or other agencies or if legislation requiring reductions in CO2 and other GHG's or legislation mandating a renewable energy portfolio standard is adopted, such regulation could substantially affect both the costs and operating characteristics of the Company’s fossil fuel generating plants, nonutility coal mining operations, and natural gas distribution businesses. At this time and in the absence of final legislation or rulemaking, compliance costs and other effects associated with reductions in GHG emissions or obtaining renewable energy sources remain uncertain. The Company has gathered preliminary estimates of the costs to control GHG emissions. A preliminary investigation demonstrated costs to comply would be significant, first with regard to operating expenses and later for capital expenditures as technology becomes available to control GHG emissions. However, these compliance cost estimates are based on highly uncertain assumptions, including allowance prices if a cap and trade approach were employed, and energy efficiency targets. Costs to purchase allowances that cap GHG emissions or expenditures made to control emissions should be considered a federally mandated cost of providing electricity, and as such, the Company believes such costs and expenditures should be recoverable from customers through Senate Bill 251. |
|
Senate Bill 251 also established a voluntary clean energy portfolio standard that provides incentives to Indiana electricity suppliers participating in the program. The goal of the program is that by 2025, at least 10 percent of the total electricity obtained by the supplier to meet the energy needs of Indiana retail customers will be provided by clean energy sources, as defined. In advance of a federal portfolio standard and Senate Bill 251, SIGECO received regulatory approval to purchase a 3 MW landfill gas generation facility from a related entity. The facility was purchased in 2009 and is directly connected to the Company's distribution system. In 2008 and 2009, the Company executed long-term purchase power commitments for a total of 80 MW of wind energy. The Company currently has approximately 5 percent of its electricity being provided by clean energy sources due to the long-term wind contracts and landfill gas investment. |
|
Manufactured Gas Plants |
In the past, the Company operated facilities to manufacture natural gas. Given the availability of natural gas transported by pipelines, these facilities have not been operated for many years. Under current environmental laws and regulations, those that owned or operated these facilities may now be required to take remedial action if certain contaminants are found above the regulatory thresholds. |
|
In the Indiana Gas service territory, the existence, location, and certain general characteristics of 26 gas manufacturing and storage sites have been identified for which the Company may have some remedial responsibility. A remedial investigation/feasibility study (RI/FS) was completed at one of the sites under an agreed order between Indiana Gas and the IDEM, and a Record of Decision was issued by the IDEM in January 2000. The remaining sites have been submitted to the IDEM's Voluntary Remediation Program (VRP). The Company has identified its involvement in five manufactured gas plant sites in SIGECO’s service territory, all of which are currently enrolled in the IDEM’s VRP. The Company is currently conducting some level of remedial activities, including groundwater monitoring at certain sites. |
|
The Company has accrued the estimated costs for further investigation, remediation, groundwater monitoring, and related costs for the sites. While the total costs that may be incurred in connection with addressing these sites cannot be determined at this time, the Company has recorded cumulative costs that it has incurred or reasonably expects to incur totaling approximately $42.4 million ($23.2 million at Indiana Gas and $19.2 million at SIGECO). The estimated accrued costs are limited to the Company’s share of the remediation efforts and are therefore net of exposures of other potentially responsible parties (PRP). |
|
With respect to insurance coverage, Indiana Gas has received approximately $20.8 million from all known insurance carriers under insurance policies in effect when these plants were in operation. Likewise, SIGECO has settlement agreements with all known insurance carriers and has received to date approximately $14.2 million of the expected $15.7 million in insurance recoveries. |
|
The costs the Company expects to incur are estimated by management using assumptions based on actual costs incurred, the timing of expected future payments, and inflation factors, among others. While the Company’s utilities have recorded all costs which they presently expect to incur in connection with activities at these sites, it is possible that future events may require remedial activities which are not presently foreseen and those costs may not be subject to PRP or insurance recovery. As of September 30, 2013 and December 31, 2012, approximately $5.1 million and $4.6 million, respectively, of accrued, but not yet spent, costs are included in Other Liabilities related to the Indiana Gas and SIGECO sites. |