Item 7.01 Regulation FD Disclosure.
PNM Resources, Inc. and Subsidiaries (“PNMR” or the "Company") is furnishing in this Current Report on Form 8-K select Comparative Operating Statistics for the months of October and November 2007 and 2006 to provide investors with key business indicators. Readers of this Current Report on Form 8-K should refer to the Management’s Discussion and Analysis of Financial Condition and Results of Operations in the Company’s annual and quarterly periodic reports on Form 10-K and Form 10-Q, respectively, for a discussion of actual results of operations and any significant trends.
Power Plant Performance:
The Company previously reported that a key factor to meeting the stated 2007 ongoing earnings range projection was strong power plant availability during the fourth quarter. The Company’s primary base load power generating stations are the San Juan Generating Station (“SJGS”), the Palo Verde Nuclear Generating Station (“PVNGS”) and the Four Corners Plant (“Four Corners”).
The Company had anticipated 2007 power plant availability at SJGS and PVNGS to be approximately 86% and 80%, respectively. Power plant availability at Four Corners is not expected to materially impact final earnings results.
Due to certain equipment issues, the Company now expects SJGS and PVNGS power plant availability to be materially below targets for the month of December.
The Company's expectations on power plant availability are forward-looking statements and the actual results may differ, as the final base load power plant availability will be dependent on a number of factors, including the ability to execute timely repairs. Information on SJGS and PVNGS availability is presented below.
| | Oct. 2007 | | | Nov. 2007 | | | Year-to-Date Nov. 30, 2007 | |
San Juan Generating Station | | | | | | | | | |
Equivalent Availability Factor (EAF) | | | 65% | | | | 58% | | | | 82% | |
| | | | | | | | | | | | |
Palo Verde Nuclear Generating Station | | | | | | | | | | | | |
Equivalent Availability Factor (EAF) | | | 47% | | | | 55% | | | | 78% | |
Weather – HDD and CDD:
Warmer weather in 2007, compared with 2006, also will be a key factor in the Company meeting its stated ongoing earnings range. A principal operating utility subsidiary for the Company is Public Service Company of New Mexico (“PNM”), a regulated utility operating in New Mexico. The Company is furnishing select weather statistics for this subsidiary in the information presented below.
Heating Degree Day (“HDD”) values and Cooling Degree Day (“CDD”) values represent the accumulation in degrees that the daily mean temperature was below or above, respectively, 65 degrees Fahrenheit during a period of time, typically corresponding to a calendar month. PNM’s HDD and CDD statistics are based on weather in Albuquerque, New Mexico.
| | Oct.-Nov. 2007 | | | Oct.-Nov. 2006 | | | 2007-2006 Variance | | | Oct.-Nov. Normal | |
PNM | | | | | | | | | | | | |
HDD | | | 643 | | | | 768 | | | | (16.3 | %) | | | 784 | |
| | | | | | | | | | | | | | | | |
CDD | | | 25 | | | | 26 | | | | (3.9 | %) | | | 17 | |