OROMIN FILES UPDATED HEAP LEACH
NI 43-101 TECHNICAL REPORT
FOR OJVG GOLD PROJECT
Vancouver, B.C. – Oromin Explorations Ltd. (“Oromin”),on behalf of Oromin Joint Venture Group (“OJVG”), announces that the NI 43-101 Technical Report “OJVG Golouma Gold Project Updated Preliminary Economic Assessment of the Heap Leach Potential” (“PEA”) has been filed on SEDAR (www.sedar.com) and is also available on Oromin’s websiteatwww.oromin.com.
The positive results of the PEA update for the OJVG Gold Project in Senegal, West Africa were previously announced in separate Oromin news release on January 31, 2013 and are summarized below. All figures are in US Dollars.
Heap Leach PEA Update – Highlights
- A proposed heap leach operation provides an opportunity to capture value from lower graderesources on the project.
- At a gold price of $1,550/oz the pre-tax Net Present Value is $98 million and after-tax is $76million at a 5% discount rate generating an after-tax internal rate of return of 36% with an 1.9year payback
- Average annual heap leach gold production for the first full three years of production is 36,000ounces per year at a $760 operating cash cost per ounce
- Average annual life of mine (“LOM”) heap leach gold production is 27,000 ounces per year atan operating cash cost of $929 per ounce
- Several open pit gold deposits will provide a heap leach production period of just over 14 years
- Average estimated LOM gold recovery of 70%
- Based on the assumption that the heap leach operation would be an extension to the proposedCIL operation, the estimated heap leach start-up capital cost is $54 million including a $10.5million contingency
- The size of the heap leach resource potential is such that a significant increase in the throughputrate for the currently assumed 2 Mt up to 4-5 Mt/year is likely warranted
- All of the heap leach deposits remain open to expansion and a minimum of fourteen additionalexploration prospects may further enhance the Project’s future resource base
Oromin emphasizes to readers that the prospective heap leach development scenario summarized above is entirely in addition to the much larger carbon-in-leach (“CIL”) project summarized in our news release last
1
week on March 19th. The CIL conventional mining-milling project anticipates a mine life of 17 years with LOM gold production of 144,000 ounces per year, including 182,000 ounces annually in the initial three years of full production. The pre-tax NPV5%of the CIL project is $740 million and post-tax $558 million, using a $1,550 per ounce gold price.
Oromin is continuing to work with its OJVG partners and its financial advisor, RBC Capital Markets, to access development, financing and strategic alternatives towards maximizing Project value.
Authors / Qualified Persons
The technical report titled “OJVG Golouma Gold Project Updated Preliminary Economic Assessment of the Heap Leach Potential” was prepared on behalf of OJVG by Oromin Explorations Ltd. under the direction of Ken Kuchling, P.Eng. and Douglas Turnbull, P.Geo, Oromin’s designated Qualified Person for this news release who has reviewed and validated that the information in this release is consistent with the information presented in the PEA.
To find out more aboutOromin Explorations Ltd., visitwww.oromin.com.
On behalf of the Board of Directors of
OROMIN EXPLORATIONS LTD.
“Chet Idziszek”
Chet Idziszek, President and CEO
[Readers are referred to the Cautionary Statements on the following page]
2
Cautionary Statements |
This press release contains certain forward-looking information as defined in applicable securities laws (referred to hereinas “forward-looking statements”). Specifically, this press release has as its principal subject a preliminary economicassessment update (the “2013 PEA”) as at today’s date prepared by our independent consultants. It is emphasized to readersthat any PEA is based upon assumptions about such factors as extent and continuity of mineralization, rock density, andvariation between predicted and actual deposit shapes. In addition any PEA is based upon assumptions about such factors asavailability of capital for development, commencement of construction, capital costs, ore grade, anticipated gold production,gold recovery, cash operating costs and other costs, expected mine life, projected internal rate of return, projected paybackperiod, sensitivity to metal prices and other sensitivities, and assumptions underlying any financial analysis. Statements basedon such assumptions may be viewed as forward-looking statements. |
Any company contemplating the development of a mineral resource is subject to such risks and uncertainties ascommodity price volatility, changes in debt and equity markets, the uncertainties involved in interpreting geological data,increases in costs, environmental compliance and changes in environmental legislation and regulation, interest rate andexchange rate fluctuations, market competition, ongoing relations with employees and impacted communities, generaleconomic conditions and other risks involved in the mineral exploration and development industry, as well as those riskfactors discussed in the section entitled “Description of Business - Risk Factors” in Oromin’s Annual Information Form filedon SEDAR May 29, 2012. Statements based on such assumptions may be viewed as forward-looking statements. |
The operating and capital costs in the 2013 PEA which is the principal subject of this news release were developed to bereasonable estimates within industry benchmarks. The 2013 PEA uses estimates of gold prices in line with norms currentlyused in our industry. There is no certainty that the results of the 2013 PEA will ever be realized. Should one or more of therisks or uncertainties involved in forward-looking statements relating to the 2013 PEA materialize, or should the assumptionsunderlying the 2013 PEA prove incorrect, actual results of the 2013 PEA may vary materially from those anticipated,believed, estimated or expected. Statements based on such assumptions may be viewed as forward-looking statements. |
Forward-looking statements involve known and unknown risks, uncertainties and other factors which are beyondOromin’s ability to predict or control and may cause Oromin’s actual results, performance or achievements to be materiallydifferent from any of its future results, performance or achievements expressed or implied by forward-looking statements.Accordingly, readers should not place undue reliance on forward-looking statements. Oromin undertakes no obligation toupdate publicly or otherwise revise any forward-looking statements contained herein whether as a result of new information orfuture events or otherwise, except as may be required by law. |
Cautionary Note to U.S. Readers Regarding Estimates of Indicated and Inferred Resources |
The 2013 PEA is, according to engineering standards in use in Canada, based in substantial measure on “indicatedmineral resources” and “inferred resources”. The Company advises U.S. investors that while these terms are recognized andrequired by Canadian regulations, they are not recognized by the SEC. “Inferred resources” have a great amount ofuncertainty as to their existence, and great uncertainty as to their economic and legal feasibility. It cannot be assumed that allor any part of an “inferred” or “indicated mineral resource” will ever be upgraded to a higher category. Under Canadian rules,estimates of “inferred mineral resources” may not form the basis of a feasibility study or prefeasibility studies, except in rarecases, such as with an initial PEA. The SEC, normally, only permits issuers to report mineralization that does not constitute“reserves” as in-place tonnage and grade, without reference to unit measures. Under U.S. standards, mineralization may not beclassified as a “reserve” unless the determination has been made that the mineralization could be economically and legallyproduced or extracted at the time the reserve determination is made. U.S. investors are cautioned not to assume that any partor all of a measured, indicated or inferred resource exists or is economically or legally mineable. Information concerningdescriptions of mineralization and resources contained herein may not be comparable to information made public by U.S.companies subject to the reporting and disclosure requirements of the SEC. |