Note 5 - Commitments and Contingencies |
|
| A. | Litigation |
|
From time to time, the Company may be subject to routine litigation, claims, or disputes in the ordinary course of business. The Company defends itself vigorously in all such matters. In the opinion of management, no pending or known threatened claims, actions or proceedings against the Company are expected to have a material adverse effect on its financial position, results of operations or cash flows. However, the Company cannot predict with certainty the outcome or effect of any of the litigation or investigatory matters or any other pending litigation or claims. There can be no assurance as to the ultimate outcome of these lawsuits and investigations. |
|
| B. | Asset Retirement Obligation |
|
The Company currently estimates the costs of plugging and decommissioning of the exploratory wells drilled to date in the Asher-Menashe and Joseph License areas to be approximately $851,000 based on current cost rather than Net Present Value. Liabilities for expenditures are recorded when environmental assessment and/or remediation is probable and the timing and costs can be reasonably estimated. |
|
| C. | Environmental and Onshore Licensing Regulatory Matters |
|
The Company is engaged in oil and gas exploration and production and may become subject to certain liabilities as they relate to environmental cleanup of well sites or other environmental restoration procedures and other obligations as they relate to the drilling of oil and gas wells or the operation thereof. |
|
In March 2011, the Ministry of Environmental Protection (Environmental Ministry) issued initial guidelines relating to oil and gas drilling. This is the first time that the Ministry published specific environmental guidelines for oil and gas drilling operations, relating to onshore and offshore Israel. The guidelines are detailed and provide environmental guidance for all aspects of drilling operations, commencing from when an application for a license is filed, and continuing through license award, drilling exploration, production lease, petroleum production and abandonment of the well. The guidelines address details that must be submitted regarding the drill site, surrounding area, the actual drilling operations, the storage and removal of waste and the closing or abandoning of a well. Following meetings between the Ministry and industry representatives in 2011, the Ministry indicated that certain of their initial published guidelines would be revised. |
|
In January 2012, the Ministry of Energy and Water Resources submitted for review a proposed code titled "Onshore Oil and Gas Exploration and Production-Environment (Health) and Safety Code – Draft". The purpose of the proposed draft code is to regulate and codify onshore environmental and safety matters relating to oil and gas exploration and production in Israel. Under the proposed draft of the code, as a condition to receiving a license for oil and gas exploration, an applicant will have to submit, in writing, an environmental assessment as well as a safety plan that will have to be periodically updated during and after operations. In addition, as a condition to receiving production rights (in the case of a discovery) an applicant will have to submit an environmental impact report as well as a production safety plan. |
|
In April 2012, the “Environmental Protection Law (Emissions and Transfers to the Environment) Reporting Requirements and Register 2012” became effective. This statute imposes reporting obligations on entities engaged in oil and gas exploration activities (amongst others) in Israel relating to quantities of pollutants emitted into the air, water, land and sea (on an annual basis) and the off-site transfer of waste generated in the facility for treatment. The annual report that is to be furnished does not apply to the Company’s operations until we establish oil and/or gas production. |
|
In April 2012, the proposed draft regulations relating to petroleum exploratory drilling were adopted in large measure. The new regulations are entitled “Petroleum Regulations (Permission to deviate from the provisions of the Planning and Building Law) 2012” and detail a new permitting process. Among other things, the new regulations require the submission, to the local regulatory and permitting authorities, of a detailed environmental report relating to the proposed drilling site and surroundings. The report is to address, in detail, the environmental implications of the drilling, including hydrological analysis, surface water management, risk assessment, environmental impact, and abandonment and remediation of the drill site, among others. The drilling application must be published and there are specified time frames (approximately 100 days) for any person (including environmental and other interested bodies) to comment on the drilling application. |
|
In June 2012, the Ministry of Energy and Water Resources (the “Energy Ministry) issued initial guidelines relating to onshore exploratory licensing. Under the guidelines, which have since been adopted, an application will have to meet certain specified conditions and provide detailed information with respect to the requested license area. The applicant must engage, at a minimum, an exploration manager, geologist, geophysicist and engineer with minimum years of experience in oil and gas exploration, and at least one of these persons must be a resident of Israel. |
|
The applicant must also demonstrate the financial resources to support the estimated costs of non-drilling exploratory activities, and at least 50% of the estimated drilling costs, but in any event not less than $5 million. The applicant will be deemed to have the requisite financial resources if it has liquid assets and equity equal to the required amount, less undertakings pursuant to other licenses or permits. The application will be published in a daily newspaper and the Ministry's web site, and other prospective license applicants will then have an opportunity to submit an application for the requested license area within three months from such publication. In the event of more than one application for a license area, the winner will be determined by a grading system that includes certain factors deemed pertinent (i.e., applicant’s corporate structure and experience, team background and experience, financial resources, etc.). A condition to the issuance of any license is the submission by the licensee of a performance bank guarantee in an amount equal to 10% of the cost of the proposed work program. The performance bank guarantee is required at or prior to the award of the exploration rights. |
|
In October 2012, the Energy Ministry published proposed guidelines relating to the submission of performance guarantees for new and existing onshore and offshore exploration licenses. Under the proposed guidelines, an applicant for a new onshore exploration license must submit a performance bank guarantee for 10% of the cost of the proposed work program upon the award by the Petroleum Commissioner (the “Commissioner”) of the requested license. An existing onshore exploration license owner will be required to submit a performance bank guarantee equal to 10% of the cost of the balance of the planned work program by the earlier of (a) the application for a license extension, (b) the application for transfer of license rights, or (c) the application for changes to the work program. The face amount of the performance bank guarantee for existing licenses will be based on an estimated budget for the balance of the planned work program that an existing license owner is to submit to the Commissioner, which budget is subject to approval by the Commissioner. In the event that the licensee violates (whether intentionally or not) any of the license terms, then the Commissioner is entitled to demand payment of the bank guarantee, after giving the licensee notice and an opportunity to cure. |
|
In December 2012, the Energy Ministry published proposed guidelines relating to the submission of bank guarantees for potential drilling-related environmental damages. The guidelines will apply to all petroleum exploration licenses to be granted on or after June 30, 2013 (and possibly extensions of existing licenses). Under the proposed guidelines, prior to receiving the approval of the Commissioner for a proposed drilling program, the licensee must submit a bank guarantee in the amount of $100,000 with respect to a drilling depth of up to (and including) 1,000 meters, which increases to $250,000 if the drilling depth is more than 1,000 meters. The Commissioner is entitled to demand a bank guarantee in excess of $250,000 if the Commissioner determines that there is a substantial risk of environmental damage. If the licensee causes environmental damage, the Commissioner is entitled to demand payment of the bank guarantee, after giving the licensee notice and an opportunity to respond to the allegation of damages. |
|
In July 2013, the Environmental Ministry published: “Environmental Guidelines for the preparations of an environmental document supplementary to a license for searching – experimental drilling and land extraction tests.” This document extensively details the requirements for a supplemental environmental document to an oil and gas exploration plan. |
|
The Company believes that these new regulations will significantly increase the expenditures associated with obtaining new exploration rights and considerably increase the time needed to obtain all of the necessary authorizations and approvals prior to drilling. |
|
|
| D. | Drilling Contract with AME/GYP |
|
As previously disclosed, GYP, the owner of the rig previously used by the Company and an affiliated entity of AME (our prior drilling contractor), advised that $550,000 remains unpaid for rig demobilization. The drilling contract between the Company and AME, which was purportedly assumed by GYP, provides that all disputes are to be settled by arbitration in London, United Kingdom. |
|
On February 25, 2013, GYP advised the Company in writing of GYP's intention to seek arbitration under the drilling contract; however, GYP also indicated its desire to find an amicable solution in lieu of initiating arbitration proceedings and offered a deep discount to resolve the matter. The Company, which denies it owes anything, offered a nuisance amount to resolve it. The Company's offer has not been accepted by GYP to date, but GYP has not initiated arbitration proceedings, and periodic communications continue between it and the Company. |
(See Note 6) |
|
| E. | Company License Area Activities |
|
On April 10, 2013, Zion submitted to Israel’s Petroleum Commissioner an application seeking a one-year extension for its Joseph License, which covers approximately 83,000 acres.. On May 12, 2013, the Petroleum Commissioner notified the Company that our Joseph License was extended for only six months, until October 10, 2013 to allow for an orderly plugging and abandonment of the wells drilled to date in such license area as required by our license terms. |
|
In April 2013, Zion submitted to Israel’s Petroleum Commissioner an application seeking a new petroleum exploration license in the Megiddo-Jezreel Valley area, onshore Israel, covering an area of approximately 98,000 acres. As proposed, the Megiddo-Jezreel Valley license area boundary is adjacent to and westward of Zion’s existing Jordan Valley License, which covers approximately 56,000 acres. If granted, the new Megiddo-Jezreel License would likely be for an initial three-year term, extendable at the option of the Petroleum Commissioner for four additional one-year terms, for a total of seven years. (See Note 6) |
|
On May 23, 2013, Zion submitted to Israel’s Petroleum Commissioner an application seeking a one-year extension for its Asher-Menashe License, which covers approximately 79,000 acres, to conduct additional in-well testing operations at the Elijah #3 well in hopes of finding commercially productive hydrocarbons. |
|
On July 7, 2013, the Israeli Petroleum Commissioner notified the Company that it approved the Company’s request for an extension to the scheduled expiration date of the Company’s Asher-Menashe License (Petroleum Exploration License No. 334) to June 9, 2014. Under the terms of the license extension, the Company is required to perform a perforation and stimulation operation at the Elijah #3 well and conduct a production test. If the outcome of the test is negative, the well is to be plugged and abandoned (“P&A”) and within 60 days thereafter, a final report should be submitted and the license is to be returned. |
|
As of the date of this filing, the Company continues to plan for in-well testing of its Elijah #3 well with operations likely to occur in mid to late November, 2013. Zion plans to perforate the zone of interest, fluid stimulate the carbonate rock, and perform a drill stem test. A drill stem test is a procedure for isolating and testing the pressure, permeability and productive capacity of a geological formation within a well. The test is a key method of obtaining information on the formation fluid and establishing whether a well has found a commercial hydrocarbon reservoir. If the test is positive, the Company will contact the Petroleum Commissioner’s office to discuss future development plans. If the outcome of the test is negative, the Company plans to initiate P&A procedures immediately. |