Cumberland Project - On time (2Q-09 COD);
better than budget
Note: See Safe Harbor Statement at the beginning of today’s presentation.
100 MW dual fuel combustion turbine - flexible and
efficient GE LMS 100 technology
Project Cost: $75 million budget
$72 million projection ($720/kW-installed)
Projected net income of $4-7 million/ year
• Capacity value contributes 50% of project value
• Included in 2009/10 and 2010/11 PJM capacity auctions
Project Status
• All equipment has been installed
• Gas & Electrical interconnection installation complete
• Cold Commissioning & Testing in progress
• Commercial operation date - 2Q-09 (on schedule)
Existing CT site (Cumberland, NJ)
• Land available for further expansion (additional 100 MW)
• Additional natural gas and oil storage capacity
• Minimal transmission system upgrades (PJM Queue P06)
• Other infrastructure and resources on site