PACIFIC BOOKER MINERALS INC.
MANAGEMENT'S DISCUSSION AND ANALYSIS (FORM 51-102F1)
For the three month period ended October 31, 2015
Dated: December 16, 2015
The selected financial information set out below and certain comments which follow are based on and derived from the unaudited interim financial statements of Pacific Booker Minerals Inc. (the "Company" or "Pacific Booker" or “PBM”) for the nine months ended October 31, 2015 and from the audited financial statements for the year ended January 31, 2015 and should be read in conjunction with them. Additional information relating to the Company is available on SEDAR at www.sedar.com.
Overview
Pacific Booker Minerals Inc. is a Canadian natural resource exploration company which is in the advanced stage of development of the Morrison deposit, a porphyry copper/gold/molybdenum ore body, located 35 km north of Granisle, BC and situated within the Babine Lake Porphyry Copper Belt. The Company is proposing an open-pit mining and milling operation for the production of copper/gold/silver concentrate and molybdenum concentrate. The Company is a reporting issuer in Alberta and British Columbia and trades on the TSX Venture Exchange under the symbol BKM and on the NYSE MKT Equities Exchange under the symbol PBM.
Overall Performance
The Company is required to conduct an Environmental Assessment to determine the potential for adverse environmental, economic, social, heritage and health effects that may occur during the life cycle of the Morrison Copper/Gold Project. An Environmental Assessment (“EA”) is conducted at the conceptual design level prior to detailed engineering and obtaining the various Licenses and Permits required for the construction, operation, decommissioning and reclamation of a mine. The Company’s Environmental Assessment Certificate (“EAC”) Application for the proposed Morrison Copper/Gold mine was based on a Feasibility level design, which is a comprehensive technical and economic study.
Following the refusal by the Ministry of Environment to issue an EAC for the project on October 1, 2012, the Company challenged that decision in the BC Supreme Court. The December 9, 2013 decision of the Court stated that the rejection failed to comport with the requirements of procedural fairness and that Pacific Booker should not have been prevented from learning at least the substance of the recommendations and the decision stipulated that Pacific Booker and the interveners would be entitled to be provided with the Executive Director’s recommendations to the Ministers, and would be entitled to provide a written response to the recommendations.
On January 24, 2014, the Company received a letter from the EAO outlining their key concerns underlying the negative recommendation of October 2012. In March, Klohn Crippen Berger’s (“KCB”) letter that accompanied the technical response stated “the document continues to support our opinion that the Project will not have a risk of significant adverse environmental effects and addresses the main items of concern identified by the EAO Decision Response Document. KCB’s report states their belief that the design is protective of the environment and presented clarification of the rationale and the potential for environmental effects. Further supporting that assessment, three Technical Expert Opinions were included for lake modeling of water quality predictions, aquatic effects and geomembrane liners. The BCEAO allowed to April 25th for the members of the Working Group to submit their responses to that report. On April 29th, PBM was advised that the second phase of the reconsideration process was complete and was given until May 23rd to reply. The technical response was prepared by KCB with support from a number of Technical Experts. On July 4th, the EAC application was referred to the Minister of Environment and the Minister of Energy and Mines for reconsideration, stating a 45 day (subject to any extensions) timeline for a decision by the Ministers would apply. On August 18th, the Minister of Environment suspended the environmental assessment pending the outcome of the Independent Expert Engineering Investigation and Review Panel of the tailings dam breach at the Mt. Polley mine.
The Independent Review Panel Report on the investigation into the cause of the failure of the tailings storage facility (“TSF”) at the Mount Polley Mine was released on January 30, 2015.
On February 26th, PBM received a letter from Doug Caul, Associate Deputy Minister, BCEAO providing PBM an opportunity to comment on the Mount Polley Investigation and Report in relation to the Morrison project, focusing on the potential implications of the recommendations of the Report to Morrison and effects relating to its proposed tailings management facility. On March 23rd, PBM submitted a report, prepared by KCB, in response to the Recommendations in regards to the TSF Failure at the Mount Polley Mine. The report continues to support their opinion that the Morrison project has been designed using Best Available Practices and can be safely constructed, operated, and closed to protect the environment. On April 17th, the responses from the Lake Babine Nation, the Gitxsan Treaty Society and the Gitanyow Hereditary Chiefs to the March 2015 report from KCB were posted on the BC Government’s e-PIC site. On May 8th, the Company submitted a response in response to the Aboriginal groups’ comments on both the Mount Polley Independent Technical Review Board Panel Report Recommendations and the Company’s response to the Report, including a letter, prepared by Harvey McLeod of Klohn Crippen Berger Ltd., that addresses the points raised in the April 2015 letters from the First Nations. On June 10th, the Company announced that the Minister of Environment had lifted the suspension. The time period remaining for the environmental assessment of the Morrison Project was 30 days, ending on July 9, 2015. On July 8th, PBM announced that the Minister of Environment and the Minister of Energy and Mines made a decision under Section 17(3)(c) of the Environmental Assessment Act, ordering that the Morrison Project undergo further assessment. The scope of the further assessment includes many components which were required to be completed in support of the Mines Act/Environmental Management Act permits and was planned to be completed prior to applying for permits after receiving the Environmental Assessment Certificate.
In July and August, the Company consulted with legal and technical advisors for suggestions on the best method to address the issues raised in the communication received from the Ministers.
PBM believes that it has accommodated all of the concerns of the Ministry of Energy & Mines, Ministry of the Environment and First Nations and proposes a project that uses unprecedented measures to be protective of the environment. PBM has committed to constructing and operating the Morrison mine in compliance with industry best practices, using proven technology and in full compliance with all permit requirements.
On September 30th, the Company announced that Michael McPhie (Founder and CEO of Falkirk Resource Consultants Ltd. and Director with JDS Energy and Mining Ltd.) had agreed to assist the Company with the Morrison Project. He has more than twenty years of experience successfully permitting and financing mining projects in British Columbia and internationally. He is the immediate past Chair of the Association for Mineral Exploration BC, the former CEO of the Mining Association of BC and is a director of several BC based mineral development companies. The Falkirk Resource Consultant team helps resource companies across Canada navigate their projects through complex permitting processes and procedures, successfully moving them into their next phase of development. Their executive team and senior consultants have firsthand experience in the private and government sectors locally, nationally and internationally.
The Company also announced that Raymond Mah would also be assisting on the Morrison Project. He is an independent consultant currently providing expertise and assistance to companies with mining, resources, and infrastructure developments. He has over 30 years of experience in the mining industry with an extensive background in mine developments taking projects from evaluations through design, construction and into operations. He was the Chief Operating Officer of Yukon Zinc from 2006 to 2012 and developed the Wolverine Mine. Prior to Yukon Zinc he served with Placer Dome Inc., where he managed evaluations, design and construction for international and Canadian mining projects.
PBM believes that this team will preserve and enhance our shareholder value, ensuring that facts drive the process and that our reputations as well as objectives are protected.
The Company is continuing to meet and discuss the necessary steps to facilitate the approval of the Environmental Assessment Certificate for the Morrison Project
The following table is a summary of the Company’s process through the EA Application, the Supreme Court of BC petition and the reconsideration process.
| |
2002 |
| Commenced baseline data collection to support Application for EAC |
October | PBM outlined project plans and development schedule to BC Energy, Mines and Petroleum Resources (“BCEMPR”), BC Environmental Assessment Office (“BCEAO”), BC Ministry of Environment (“MOE”), BC Ministry of Forests (“MOF”), Canadian Environmental Assessment Agency (“CEAA”), Lake Babine Nation (“LBN”) and the Village of Granisle. |
2003 |
June 17 | Met with BCEAO, BCEMPR and CEAA reporting project progress and EA process and related regulatory requirements |
July | Met with regional mangers of MOE and BCEMPR who were informed that PBM was actively advancing its activities to enter the EA process. |
September | Project Description was first submitted to BCEAO |
September 30 | Entered the Pre-Application stage of EA. under Section 10 (1) (c) |
October 20 | Multi-agency meeting chaired by BCEAO. Provincial, Federal and LBN representatives attended. |
November 6 | Department of Fisheries (“DFO”), CEAA, Canadian Coast Guard (“CCG”), Health Canada (“HC”), Environment Canada (“EC”), Natural Resources Canada (“NRCan”) and PBM met in Vancouver. Project planning, legislation and regulatory, CEAA process and harmonization with provincial EA process discussed. |
2004 |
May 17 | Met with EAO, CEAA & DFO. |
July 6 | Site visit to Morrison property by LBN, EAO, BCEMPR, MOE, BC Ministry of Agriculture and Lands (“BCMAL”), EC, and Fisheries and Oceans Canada (“FOC”). |
September 16 | PBM met with BC Ministry of Energy and Mines (“MOEM”) key personnel. |
2005 |
October 14 | PBM submitted the draft Terms of Reference (“dTOR”) |
2006 |
March 27-29 | Attended 17 meetings with communities in Smithers, Houston, Granisle, Burns Lake and LBN communities to seek information, feedback, suggestions and to develop a relationship with LBN, to listen their thoughts and concerns and to determine appropriate protocol. |
May 15 | Working Group (“WG”) Meeting was held in Smithers, BC |
June 27 | Technical Water Quality Working Group teleconference. EAO, DFO, EC and MOE attended. |
July 5 | Teleconference with CEAA, NRCan, DFO, Navigable Waters and Transport Canada (“TC”). |
July 14 | Three meetings with BC Ministry of Energy, Mines and Petroleum Resources (“MEMPR”), Minister of Mining and BCEAO regarding progress on the project. |
September 1 | PBM met with BCEAO, CEAA. |
September 21-22 | Morrison Project Introduction Meeting with LBN was held in the LBN office. Chief Betty Patrick, LBN Councillors and BCEAO attended. |
2007 |
January 29 | Joan Hesketh, Associate Deputy Minister, (BCEAO) met with PBM to discuss project. |
June 21 | Three meetings with BCEAO, MEMPR and Ministry of Aboriginal Relations and Reconciliation (“MARR”). |
June 25 | Project WG Conference call on the dTOR. DFO, EC, CEAA, NRCan, LBN, BCEAO, MOF, MEMPR, MOE, and PBM attended. |
June 27 | EA Review LBN Community Meeting in Burns Lake, BC. Chief Patrick, Councillors and approximately 75 members from the LBN, BCEAO and PBM attended. |
August 22-25 | LBN Community meetings held in Fort Babine and Tachet. |
September 12 | PBM met with MEMPR, BCEAO. |
October 10 | PBM met with MEMPR to discuss permit requirements. |
November 19 | Met with MEMPR in Smithers office to discuss permitting & First Nations issues. |
November 23 | Met with CEAA and EAO. Updated TOR and a TOR comment tracking table was created. |
November 29 | Met with MEMPR, MLA Dennis Mackay, BCEAO and MARR to update them with project progress. |
2008 |
January 14 | ML/ARD technical working group meeting in Vancouver. DFO, CEAA, EC, BCEAO, MEMPR, NRCan, MOE and PBM attended. |
January 18 | PBM was issued the Section 11 Order, which identifies the scope, procedures and methods for the Environmental Assessment by the BCEAO under the BCEAA. |
January 29 | Teleconference to discuss the request for EAO and PBM meeting with LBN |
February 1 | Meeting with LBN Chief and Council held in Burns Lake, BC. Chief Patrick, Council, Hereditary Chiefs, LBN Administration, LBN Treaty Committee, Fisheries, Consultant to LBN, PBM, BCEAO NRCan, MEMPR and Ministry of Forests and Range-Nadina District (“MFR-ND”) attended. |
March 17 | PBM attended a conference call with BCEAO, TC, NRCan, DFO, CEAA and MEMPR. |
April 1-2 | PBM meeting with LBN was held in Burns Lake, BC. Chief Patrick and Council, Hereditary Chiefs, LBN Administration, LBN Treaty Committee, LBN Fisheries, PBM, BCEAO, NRCan, CEAA, and DFO attended. |
April 25 | Meeting with BCEAO, MEMPR and MOE to discuss issues pertaining to waste management/water quality and LBN. |
April 25 | Meeting to update MARR on PBM interactions with LBN and gain advice. |
June 12 | A WG meeting was held in the CEAA office. BCEAO, DFO, TC, NRCan, CEAA and PBM attended. |
August 27 | Meeting in Victoria with representatives of Aboriginal Relations Branch of the MEMPR. |
August 27 | Meeting in Victoria with representatives of BCEAO. |
November 10 | Resubmitted dTOR. |
November 17 | Comment period on draft Application Terms of Reference was changed from 30 to 40 days by Section 13. |
November 27 | Public comment period on dTOR started |
2009 |
January 6 | Public comment period on dTOR completed |
April and May | PBM requested that EAO provide guidance on data collection during the EA Review period but received no response to our request. |
May 21 | Final approved TOR issued by EAO after 43 months |
September 28 | PBM submitted EAC application |
October 27 | PBM notified by BCEAO that Application failed Screening |
2010 |
January 12 to February 4 | Conducted drilling to further characterize pit walls. |
February 9 | MOE requested PBM to use a Modified Neutralization Potential for testing drill core samples. PBM provided comments recommending the use of the U.S. Environmental Protection Agency’s standard Sobek Neutralization Potential. MOE did not respond to these comments at the time and made the same request of PBM nearly one year later. |
February 12 | PBM requested comments from MOE with respect to a drill program to further characterize the pit walls and collect hydrogeologic information. MOE did not respond, yet approximately one year later, MOE commented that PBM should have collected more information at depth. |
March 7 to 11 | Field Program to collect additional water quality samples and measure water flow and in situ properties of streams 5, 7, 8, 10 and Morrison Lake and to collect visual estimates of flow in stream 6 and other minor streams. |
May 18 | Open pit site investigation report summarizing data collected during drilling. |
May 27 | Application (Addendum) re-submitted to BCEAO |
June 28 | EAC Application accepted for review |
July 12 | Day 1 of 180-day review |
July 13 | Comment period changed from 30 to 70 days by Section 13. |
July 22 | 70-days public comment period began. |
July 26 | EAO requested WG comments by August 19, 2010. Due to complaints by the WG, the period was extended to September 30, 2010 |
July 26 | Full Working Group (WG) meeting in Smithers. |
July 26 | Open House in Granisle. |
September 12-17 | Field work to sample ARD cubes and barrels; check meteorological station & download data; WQ sampling Morrison Lake, Booker Lake, streams; HADD (harmful alteration, disruption or destruction of fish habitat) and Fish Habitat Compensation Plan (“FHCP”) field investigation |
September 20 | PBM received letter from Chris Barnes of Skeena Fisheries |
September 28 | PBM received comments from Greg Tamblyn of the MOE |
September 29 | PBM receives review comments from Peter Lighthall, Geotechnical Engineer. |
September 30 | MEMPR requested that PBM provide a conceptual design for a low permeability cover for Waste Rock Disposal (“WRD”). |
September 30 | PBM receives review comments from Lorax Environmental Services. |
September 30 | PBM received comments from Verna Power, LBN |
October 1 | PBM received comments from Stephen Sheehan, EC |
October 13 | PBM received comments from Kim Bellefontaine, MEMPR |
October 4 | WG meeting in Vancouver |
October 19-25 | Field work for Nakinilerak Lake sampling |
October 20 | PBM received comments form Chris Schell, Resource Stewardship and Parks Division of MOE, Smithers |
October 24 | Received last set of Review comments from Craig Stewart, MOE. |
October 28 | PBM requests suspension and EAO suspends on day #108 of 180-day review |
November 15 | PBM sends wind analysis information to Warren McCormick (WG reviewer), and copied MOE, EAO, CEAA, EC. |
November 19 | PBM sends Review Response Report (“RRR”)-Revision 1 and Agency tracking tables with PBM’s responses to comments to EAO |
November 19 | PBM sends Public Consultation Report to EAO |
November 19 | PBM requests by letter that EAO lift suspension |
December 3 | PBM sends draft Memorandum of Understanding (“MOU”) to Chief Adam, LBN |
December 7 | PBM finalizes FHCP and sends to EAO, DFO, LBN. |
December 15 | EAO declines lifting of suspension |
December 16 | EAO/PBM meeting on commitments; project re-design discussed |
December 16 | PBM receives report from LBN on Overburden Stockpile Study. |
December 16 | EAO requested PBM consider design changes to closure phase and water management, specifically requesting the placement of waste rock into pit on closure. |
December 16 | EAO intended to discuss EAO draft Assessment Report with PBM but did not. |
December 21 | PBM issues First Nations Consultation Summary Report. |
December | Scoping of moose & mule deer survey (LBN requested survey) begins |
December | Compensation talks with Ookpik Lodge begin |
2011 |
January 6 | PBM sends Table of Key Commitments to EAO |
January | Field work for baseline Water Quality sampling of Nakinilerak and Morrison lakes and project streams continued. |
January 19 | PBM receives comments from EC on EAC responses |
January 24 | MOU discussed with LBN |
January 24 | PBM receives report from LBN on Salmon Spawning. |
January 25 | Full WG meeting clarifying issues raised by reviewers; introduced project re-design. This meeting was meant to provide enough clarity for EAO to lift the suspension but the result was that additional sub-committee meetings were required to address reviewer comments and closure design in more detail. |
January 25 | WG stated that in their opinion there was not sufficient Baseline data. |
January 25 | Scoping of moose & mule deer survey completed |
January 26 | Fish Habitat Compensation Plan (“FHCP”) meeting with DFO, MOE, LBN, EAO, PBM |
February 17 | PBM sent Waste Optimization Report to EAO |
February 18 | PBM letter to EAO regarding work completed during suspension period. |
February 21 | WG Hydrogeology meeting |
February 25 | WG Geochemistry meeting |
March 9 | Letter from EAO stipulating the requirement of a complete package to re-enter review period |
March 16 | Inclusion of the Gitxan Chiefs Office and the Gitanyow Hereditary Chiefs’ Office in “First Nations” under Section 13. |
March 23 | FHCP submitted to EAO, CEAA, DFO |
March 30 | RRR-2 submitted to EAO and CEAA for screening |
April 6 | Agency and Public tracking tables submitted to EAO |
April 15 | PBM receives further comments back from Kim Bellefontaine and Lorax |
April 26 | Waste segregation memo sent to CEAA |
May | Compensation talks with Ookpik Lodge completed |
May 10 | LBN sends draft MOU to PBM |
May 18 | PBM speaks with LBN about MOU |
May 19 | Screening comments on RRR-2 received from EC |
May 25 | Screening comments on RRR-2 received from NRCan |
May 31 | PBM provided an agenda and explained to CEAA the requirement for a meeting with EC and NRCan such that they provide technical and scientific basis for their comments. Tentative meeting date of June 7 set. |
June 2 | CEAA advised unable to have EC and NRCan available for June 7th meeting. |
June 13 | CEAA provides a list of viable dates for meeting with EC and NRCan. PBM confirms availability for June 23rd. |
June 17 | PBM issues letter to CEAA with preliminary response to EC and NRCan comments |
June 21 | CEAA advises tentative meeting with EC and NRCan that commentors were difficult to organize and has deemed that it is sufficient to have such a meeting during Review process. |
June 21 | EAO directs that RRR be renamed Addendum 2 irrespective that substantial documentation and correspondence already refers to the RRR |
July 4 | Submitted Final RRR2 and AIK to EAO |
July 5-6 | LBN-PBM community meetings in Burns Lake |
July 13 | Submitted final version RRR2 to WG |
July 18 | Review period resume restarting at day 109 |
August 11 | PBM receives review comments RRR Rev 2 from Kim Bellefontaine and Lorax Environmental Services. Most points addressed by Commitments and Mines Act Permit. |
August 19 | A Settlement Agreement was made to compensate DOJ Holdings Ltd. for any loss the Tukii Hunting Camp or the Babine Guide Outfitters may suffer in connection with the construction, development and overall operation of the Morrison Mine, in the amount of $100, 000 as full and final settlement. Payment would be made three months prior to the commencement of construction. |
August 25 | PBM requested a one-week suspension of the 180-day review period. |
September 1 | PBM sent updated stream and Morrison Lake water quality baseline and predictions to Greg Tamblyn of MOE, and EAO and CEAA |
September 1 | Review period restarted |
September 6 | EAO issued draft Assessment Report for comments |
September 19-27 | Field program conducted to obtain additional baseline fisheries, benthics, zooplankton and phytoplankton, water quality, hydrology, groundwater, and meteorology data from Morrison Lake, Nakinilerak Lake, streams and rivers. |
September 28 | PBM submitted Project Description with Commitments Rev.K to EAO |
September 29 | PBM requested a temporary suspension at day 176 of the 180 day review period due to EAO requesting a 3rd Party Review |
October 3 | MOE, MEMPR, Skeena Fisheries Commission (“SCF”), NRCan, Ministry of Transportation and Infrastructure (“MOTI”), Forests, Lands, Natural Resources Operators (“FLNRO”) comments on Draft Assessment report. |
November 13 | Robertson Geoconsultants Inc (“RGC”) submitted the 3rd party review on Hydrogeology and Water Quality. They concluded that no additional field work was required and that the scope of hydrogeological site characterization work completed to date may exceed baseline data collected for EAC applications of other mining projects in B.C. They also concluded that any uncertainties could be addressed by way of sensitivity analysis. |
November 21 | PBM submitted a response to the report prepared by RGC (dated November 13th). Solander Ecological Research Ltd. (“SER”) submitted the 3rd party review of the Aquatic Resources and Fisheries. They concluded that if PBM is able to demonstrate with reasonable confidence that seepage and effluent discharges will not exceed BC Water Quality Guidelines, then only minimal fisheries work appears to be required for the EA, although additional work may be required for permitting. |
December 2 | RGC submitted revised 3rd Party Review Report. |
December 6 | PBM submitted Response Report in response to SER’s Review Report. |
December 9 | PBM submitted marked up revised RGC report, along with the response report and a letter. |
December 12 | Chris Hamilton, EAO requested that PBM fund a toxicity study to determine effects of cadmium on salmon. PBM responded that a previous study, conducted in 1978, indicated that sockeye are less sensitive than trout. Also, previously MOE advised that Lake Trout and White Fish be used as a reference as they reside in Morrison Lake the longest. |
December 16 | EAO, CEAA, and PBM met with RGC to review the scope of work to address the 3rd party review recommendations. |
December 19 | PBM submitted 3rd Party Review Response Work of Scope to EAO and CEAA. |
December 21 | Chris Hamilton, EAO requested that PBM line the Tailings Storage Facility with a geo-membrane with a permeability of 10-10m/s to reduce seepage. He also questioned the placement of the diffuser in Morrison Lake. PBM responded that, if required, PBM will commit to lining the Tailings Storage Facility (“TSF”) with an engineered soil barrier and/or geo-membrane with an average permeability of 10-9m/s to limit seepage to the receiving streams and Morrison lakebed to meet water quality objectives that are protective of salmon spawning habitat and stream aquatic habitat. The water quality objectives will be developed to the satisfaction of EAO, MOE, EC and DFO. Alternatives to a lined TSF will be considered if the PBM can demonstrate sufficient knowledge of hydrogeologic properties and hydrogeology modeling, aquatic toxicity, and spawning habitat in Morrison Lake and aquatic habitat in the receiving streams to the satisfaction of EAO, MOE, EC and DFO. |
2012 |
January 27 | Received comments from SCF regarding 3rd Party Review Reports. |
January 31 | Submitted revised 3rd Party Review Response Report based on the Response Work of Scope. |
February 2 | Submitted Potentially Acid Generating (“PAG”) backfill response report to EAO |
February 8 | EAO requested that PBM line the TSF with a geo-membrane liner. |
February 9 | KCB sent letter to EAO regarding water quality predictions for a geo-membrane lined TSF situation. |
February 23 | Sent updated Key Commitments to EAO and CEAA. |
February 24 | Sent updated All Commitments and Project Description to EAO and CEAA. |
March 14 | Draft Assessment Report |
March 21 | Received Comments from EC on 3rd Party RRR |
April 19 | Submitted the 3rd Party Review Response Report – Addendum 1 providing the results of lining the TSF with a geo-membrane liner, if needed; leakage through the geo-membrane liner, geo-chemical loading in streams and emerging groundwater and Morrison Lake effects. |
April 27 | Comments from CEAA on 3rd Party RRR |
April 30 | Submitted 3rd Party RRR Addendum to EAO and CEAA |
May 7 | Draft Assessment Report |
June 4 | EAO e-mail re Project Description, Commitments & Tracking Table |
July 23 | PBM announces MOU with LBN. |
August 2 | MOE-Environmental Protection Division Final Comments |
August 8 | MEMPR Comments |
August 9 | Letter from EAO re comments from agencies |
August 13 | PBM Final Comments |
August 21 | EAO, after 763 days, completed the Environmental Application Review Stage and submitted their referral documents to the Ministers for decision. |
August 27 | PBM received the final Certified Project Description and the Table of Conditions that had been submitted to the ministers. These documents would be part of the EA Certificate |
August 29 | PBM received unsigned Environmental Assessment Certificate #M12-01 |
October 1 | EAC Application was rejected. |
2013 |
February 13 | PBM retained John J.L. Hunter, Q.C. of Hunter Litigation Chambers Law Corporation. |
April 4 | Hunter Litigation filed petition in the Supreme Court of BC |
July 18 | PBM received an envelope, anonymously, by mail containing what appears to be an August 13, 2012 draft of the Recommendations of the Executive Director of the Environmental Assessment Office Report in respect of PBM's application for an EA Certificate for the Morrison Copper/Gold Mine. PBM was not aware that this document existed and had never seen the draft Recommendations, which did not include a recommendation that the application for an EAC be denied. |
August 7 to 9 | BC Supreme Court hearing challenging the decision to reject the EAC Application. |
December 9 | BC Supreme Court released Judgement |
December 11 | BC Supreme Court transcript made available to shareholders |
December 16 | PBM posted Affidavit #4 (August 13, 2012 draft of Recommendations document) |
2014 |
January 13 | PBM announced 30 day period for BC Government to challenge decision ended without challenge. |
January 30 | PBM announced that the Recommendations of the Executive Director of the EAO in the matter of an application for an Environmental Assessment Certificate for the proposed Morrison Copper/Gold Mine Project (dated September 20, 2012) had been provided to the Company for review and response to the recommendations made in the report. |
March 12 | PBM announced that it had submitted a response to the letter from the Associate Deputy Minister and Executive Director of the BC Environmental Assessment Office (“EAO”), Doug Caul. Klohn Crippen Berger (“KCB”) prepared a report that clarifies the remaining concerns of the EAO regarding the Morrison Copper/Gold Project, allowing the EAO and the Ministers to make an informed decision with respect to supporting the EAO Conclusion that “EAO is satisfied that the Assessment process has adequately identified and addressed the potential adverse environmental, economic, social, heritage and health effects of the proposed Project, having regard to the successful implementation of the conditions and the mitigation measures set out in Schedule B to the draft EA Certificate”. |
March 28 | PBM was advised by letter from Associate Deputy Minister and Executive Director of the BC Environmental Assessment Office (“EAO”), Doug Caul that a two-week extension (to April 25, 2014) to the deadline for the members of the Working Group to submit their responses to the response prepared by Klohn Crippen Berger and the Company. The Company was also advised that following receipt by EAO, any responses from the Working Group will be provided to the Company and the Company would have 20 days from the receipt of those comments to reply. |
April 25 to 29 | The responses received from the Working Group were posted on the Project Information website. |
April 29 | PBM was advised by letter that the second phase of the reconsideration process was complete. The Company was given until May 20, 2014 to provide a reply to any new comments or evidence by the Aboriginal groups and the Working Group and that following receipt of the reply that all parties would be contacted and provided with a outline of the process and procedure for referral to the Honourable Mary Polak, Minister of Environment and the Honourable Bill Bennett, Minister of Energy and Mines. |
May 20 | PBM requested a 3 day extension (to May 23rd) to the submission date. |
May 23 | PBM submitted it’s response to the Working Group comments received. PBM’s technical response was contained in the report prepared by KCB (with support from a number of Technical Experts). The letter accompanying the technical response states “The document continues to support our opinion that the Project will not have a risk of significant adverse environmental effects and addresses the main items of concern identified by reviewers of the Morrison Copper/Gold Project EAO Decision Response Document (KCB 2014). These comments were received from the Working Group members and associated parties and this report is provided on behalf of PBM who requested the opportunity to respond to the comments received. PBM’s letter provided more general comments on the process to date and the relevant questions for consideration. It also stated that the Morrison Copper/Gold Project is located in a resource development area (not a protected area) within the Morice Land and Resource Management Plan, signed by the BC Government in May 2007, which supports economic activities such as mining and forestry and the Lake Babine Nation's 5-year Economic Development Plan, March 2012, supports mining within its' Traditional Territory. The EAO Assessment Report demonstrates that the mitigation plan is sound and that there are no significant adverse effects. None of the comments by the current reviewers provide any new information to contradict this finding. |
July 16 | PBM announced that it had received a letter from the Associate Deputy Minister and Executive Director of the BC EAO, Doug Caul, advising that the Company’s application for the EAC for the Morrison Copper/Gold Mine Project was referred to the Minister of Environment and the Minister of Energy and Mines for reconsideration on July 4, 2014. The letter stated that the 45 day timeline for a decision by the Ministers, subject to any extensions, will be applied. |
August 19 | PBM announced that the Honourable Mary Polak, Minister of Environment, had suspended the environmental assessment of the Morrison Copper/Gold project pending the outcome of the Independent Expert Engineering Investigation and Review Panel in relation to the tailings dam breach at the Mt. Polley mine, which was announced on August 18th by the Minister of Energy and Mines, the Honourable Bill Bennett. |
2015 |
January 30 | The Independent Review Panel Report on the investigation into the cause of the failure of the tailings storage facility (“TSF”) at the Mount Polley Mine was released |
February 26 | PBM announced that it had received a letter from Doug Caul, Associate Deputy Minister, BCEAO which provided an opportunity to comment on the Mount Polley Investigation Report in relation to the Morrison project by March 20th, focusing on the potential implications of the recommendations of the Report to Morrison and its proposed tailings management facility. The same opportunity was provided to the Lake Babine Nation, the Gitxsan Treaty Society and the Gitanyow Hereditary Chiefs. Any materials provided will be forwarded to the other party, with a short opportunity to respond. |
March 23 | PBM announced that it had submitted a response, prepared by KCB, to the Independent Technical Review Board Panel Report Recommendations in regards to the TSF Failure at the Mount Polley Mine. |
April 17 | The responses from the Lake Babine Nation, the Gitxsan Treaty Society and the Gitanyow Hereditary Chiefs to the March 2015 report from KCB were posted on the BC Government’s e-PIC site. |
May 8 | PBM submitted a response to the BCEAO, the Ministry of Environment and the Ministry of Energy and Mines in response to the Aboriginal groups’ comments on both the Mount Polley Independent Technical Review Board Panel Report Recommendations and PBM’s response to the Report, including a letter, prepared by Harvey McLeod of KCB, that addresses the points raised in the April 2015 letters from the First Nations. |
June 10 | PBM announced that the Minister of Environment had lifted the suspension of the Environmental Assessment of the Morrison Copper/Gold Project. The time period remaining for the environmental assessment of the Morrison Project was 30 days, ending on July 9, 2015. |
July 8 | PBM announced that the Minister of Environment and the Minister of Energy and Mines made a decision under Section 17(3)(c) of the Environmental Assessment Act, ordering that the Morrison Project undergo further assessment. The scope of the further assessment includes many components which were required to be completed in support of the Mines Act/Environmental Management Act permits and was planned to be completed prior to applying for permits after receiving the Environmental Assessment Certificate. |
The audited financial statements for the year ended January 31, 2015 and the Management’s Discussion and Analysis (Form 51-102F1) for the three month period ended January 31, 2015 have been filed on sedar. The 20-F Annual Report required for our NYSE MKT Listing for the year ended January 31, 2015 has been filed on the US Securities and Exchange Commission’s EDGAR website. Both are available for downloading on our website athttp://www.pacificbooker.com/financials.htm.
On September 21st, the Company announced that the non-brokered private placement (originally announced on June 11th, and amended on July 24th due to the change in the trading price of the PBM shares) was completed with 277,800 shares issued ata purchase price of $2.00 per share for total proceeds of $555,600 and issued 138,900 share purchase warrants exercisable at a price of $2.50 per share for two years. The proceeds of the private placement will be used for general working capital. No finder’s fee or commission was payable and no insiders participated in the private placement.
On September 30th, PBM approved the granting of 270,000 share purchase options at a price of $2.50 exercisable for a period of five years.
During the quarter under discussion, the Company did not issue any common shares on exercise of options or warrants and has not cancelled any options.
Outlook for 2015/16
PBM believes that the scope of the further assessment should be completed in support of the Mines Act/Environmental Management Act permits and would be completed prior to applying for the permits after receiving the Environmental Assessment Certificate.
PBM is reviewing the Environmental Assessment Application submission along with its consultant to consider the next steps, including a political strategy or challenging the decision based on the reasonableness of the government review.
PBM looks forward to working with the BC Government and First Nations to bring the mine into production, providing employment and training opportunities for residents of north-western BC while successfully implementing the mitigation measures that the Company has committed to.
Subject to receiving all required permits and authorizations, mine construction will proceed with the following activities:
·
Prepare applications for permits and other authorizations and licenses;
·
Finalize our contracting strategy for Pre-production;
·
Tender Pre-Production Contracts (EPC);
·
Proceed with procurement including ordering long lead time items (i.e. HPGR, etc);
·
Site Engineering Survey; and
·
Detailed Engineering and Design.
The Company’s current share capital is 15.5 M shares fully diluted including 250,000 common shares to be issued to Xstrata (formerly Noranda, Falconbridge) upon the start of commercial production as part of the purchase agreement with Noranda.
Subsequent to the period end, the Company has not granted or cancelled any options, announced or completed any private placements and has issued no common shares on exercise of options or warrants.
Results of Operations
A significant expense on the Statement of Comprehensive Loss is the recording of the option based payments and the offsetting contributed surplus in equity. As this is a non-cash transaction, it has no impact on the working capital of the Company. This calculation creates a cost of granting options to Eligible Persons (as defined by the policies of the TSX Venture Exchange and/or National Instrument 45-106). The cost is added to our operating expenses with the corresponding increase in the Company’s equity. The option based payment expense is allocated, in proportion to the number of options granted, to our operating expense accounts for Consulting fees, Directors fees, Investor relations fees and Professional fees.
For the 3 month period ended October 31, 2015 compared with October 31, 2014
The option based payment expense for the quarter was allocated to the accounts for Consulting fees $43,432 (2014 - $40,197), Directors fees $43,433 (2014 - $105,854), Investor relations fees $nil (2014 - $62,152) and Professional fees $nil (2014 - $11,301). These amounts total $86,865 for the 2015 period compared to $219,504 for the 2014 period. If the option based payments amounts were removed from the operating loss, the loss would show as $111,388 for the 2014 quarter compared to $103,413 for the 2015 quarter. The difference between these two quarters was $7,975, with 2015 lower. The largest amount difference was in Shareholder information and promotion which was lower by $16,441 in 2015 reflecting the cost of the Dig Media services, the Standard & Poor’s services and the cost of a meeting in New York during the 2014 fiscal year. The next largest amount difference was in Professional fees, which were higher in 2015 by $7,673 due to the cost for legal fees (relating to the decision by the Ministers). Travel costs were lower in the 2015 quarter by $3,761 due to the costs for the New York meeting in the 2014 quarter. Filing and Transfer Agent fees were higher by $2,977 reflecting the filing fees for the private placement announced in June, amended in July and completed in September 2015. Office and miscellaneous was higher by $1,110 in the 2015 quarter due to the costs related to the new computer set up. Foreign exchange loss was higher by $1,110 in the 2015 quarter due to the change in the US to Cdn $ rate. Depreciation ($304 higher due to new computer equipment), Office Rent ($594 lower due to new rental agreement), Telephone ($167 lower) and Finance income ($186 higher) in the 2015 quarter.
During the 2015 quarter, the Company incurred $67,353 in exploration & evaluation expenditures on the Morrison property compared to $35,400 in 2014 quarter.
At the beginning of the quarter, the cash held was $339,850 (2014 - $658,864). Cash used in operations was $125,409 (2014 - $109,954). Cash raised from sale of shares was $190,600 (2014 - $nil). Cash used to fund exploration activities was $39,959 (2014 - $37,586). Cash used to purchase new computer equipment was $3,990 (2014 - $nil). The net change in cash for the quarter was an increase of $21,242 (2014 - $147,540 decrease) leaving the Company holding $361,092 (2014 - $511,324) in cash at the end of the quarter.
For the Fiscal Year to October 31, 2015 compared with October 31, 2014
The option based payment expense was allocated to the accounts for Consulting fees $54,995 (2014 - $180,715), Directors fees $73,884 (2014 - $475,906), Investor relations fees $17,880 (2014 - $279,427) and Professional fees $3,251 (2014 - $50,811). These amounts total $150,010 for the 2015 period compared to $986,859 for the 2014 period. If the option based payments amounts were removed from the operating loss, the loss would show as $434,906 for the fiscal year to October 31, 2014, compared to $390,863 for the fiscal year to October 31, 2015. The difference between these two periods was $44,043, with 2015 lower. The largest amount difference was in Shareholder information and promotion which was lower by $59,686 in 2015 reflecting the cost of the Renmark agreement, the Dig Media services, the Standard & Poor’s services and the cost of a meeting in New York during the 2014 fiscal year, offset by the cost for the Progressive Group services in the 2015 fiscal year. The next largest amount difference was in Filing and Transfer Agent fees which was higher by $14,701 in 2015 reflecting the increased cost of the fee for the NYSE MKT Exchange, the costs for filing the private placement, and offset by a decrease in the TSX Venture fee in 2015. The next largest amount difference was in Professional fees, which were higher in 2015 by $5,110 due to the cost for legal fees (relating to the decision by the Ministers) in the current fiscal year. Travel costs were lower in the 2015 quarter by $3,716 due to the costs for the New York meeting in the 2014 fiscal year. Office and miscellaneous was higher by $3,011 in 2015 quarter due to the cost of the US$ D&O insurance cost. Directors fees were lower by $2,000 in 2015 due to a reduced number of board meetings during the current year. Depreciation ($435 lower), Foreign exchange loss ($564 higher), Office Rent ($820 lower due to new rental agreement), Telephone ($757 lower due to new contract) and Finance income ($15 higher) in the 2015 fiscal year.
During the current fiscal period, the Company incurred $165,917 in exploration & evaluation expenditures on the Morrison property compared to $197,858 in 2014.
At the beginning of the fiscal period, the cash held was $368,546 (2014 - $1,166,771). Cash used in operations was $420,386 (2014 - $477,913). Cash raised from sale of shares was $555,600 (2014 - $22,000). Cash used to fund exploration activities was $138,678 (2014 - $199,534). Cash used to purchase new computer equipment was $3,990 (2014 - $nil). The net change in cash for the fiscal year to date was a decrease of $7,454 (2014 - $655,447) leaving the Company holding $361,092 (2014 - $511,324) in cash at the end of the period.
Liquidity
The Company does not yet have a producing mineral property. The Company’s only source of funds has been from sale of common shares and some revenue from reclamation bond interest. The exploration and development of mineral deposits involve significant risks including commodity prices, project financing, permits and licenses from various agencies in the Province of British Columbia and local political and economic developments.
The Company’s financial instruments consist of cash, reclamation deposits, accounts payable and accrued liabilities and amounts owing to related parties. It is management’s opinion that the Company is not exposed to significant interest, currency or credit risks arising from its financial instruments.
At the end of the fiscal year 2015, the Company reported a net loss of $1,713,748 ($0.14 per share) compared to a net loss of $4,205,419 ($0.34 per share) for the year ended January 31, 2014.
Cash held at the end of the period was sufficient to meet our current liabilities.
Pacific Booker has a lease for the rental premise in which the Company’s head office operates. It is a standard rental lease which expired in October 2015 and has been extended for another 6 months to April 30, 2016. Details on the financial obligations are detailed in our annual financial statements (Note 13).
Off-Balance Sheet Arrangements
The Company has one off Balance Sheet arrangement with Xstrata LLP for 250,000 shares to be issued on commencement of commercial production on the Morrison property. The details on this transaction are disclosed in our interim and annual financial statements (Note 5).
The Company has another off Balance Sheet arrangement with M. McPhie to issue 50,000 fully paid for shares at such time as the Company has received the BC Environmental Assessment Certificate.
The Company has signed an agreement with a hunting lodge in the area of the project, which, conditional on the receipt of applicable permits and licences, requires the Company to pay $100,000 (plus sales tax if required) as full and final compensation for any loss of business which the lodge may suffer in connection with the construction, development and overall operation of the mine. This payment is required to be made three months prior to commencement of construction.
Related Party Transactions
Related party transactions were made for services provided in the course of normal business operations with 2 directors and an officer of the Company.
·
to John Plourde, a director of PBM, for shareholder relations and financing duties, in the amount of $33,000 for the current quarter/$99,000 for the fiscal year to date.
·
to Erik Tornquist, a director of PBM, for consulting services related to project management on the Morrison project, in the amount of $24,000 for the current quarter/$72,000 for the fiscal year to date
·
to Ruth Swan, an officer of PBM, for accounting and management services, in the amount of $5,760 for the current quarter/$21,008 for the fiscal year to date.
There are no ongoing contractual or other commitments resulting from the transactions. Fees for these services amounted to $62,760 (2014 - $63,030) in the current quarter and $192,008 (2014 - $191,723) for the fiscal year to date.
Also, payments were made to our independent directors for attendance at board and committee meetings. Fees for this amounted to $2,000 (2014 - $2,000) for the current quarter and $11,000 (2014 - $13,000) for the fiscal year to date.
Proposed Transactions
The Company does not have any proposed transactions planned, with the exception of continued funding arrangements.
Accounting Estimates and changes in policies
The Company has detailed its significant accounting policies in Note 3 of the annual financial statements.
Forward Looking Statements
This discussion does not include any forward-looking statements of a material nature respecting the Company’s strategies. The discussion following the heading “Outlook for 2015/16” does include a statement of future intent. The discussion following the heading “Off-Balance Sheet Arrangements” discloses future obligations. The Company will update or revise these forward-looking statements when and/or if there is a change in intent or future obligations.
Selected Annual Information
The following summary information has been taken from the financial statements of Pacific Booker Minerals Inc., which have been prepared in accordance with International Financial Reporting Standards (“IFRS”). The figures reported are all in Canadian dollars.
The following table shows the total revenue (Finance income), the loss from our financial statements, total assets, and total long term liabilities for each of the three most recently completed financial years.
| | | | | |
For the year ended | Total Assets | Total Long-term Liabilities | Total Revenue | Net Loss |
Total | Per Share |
January 31, 2013 | $ 30,905,845 | $ - | $ 3,960 | $ 1,045,31 | $ 0.09 |
January 31, 2014 | $ 30,287,558 | $ - | $ 1,217 | $ 4,205,419 | $ 0.34 |
January 31, 2015 | $ 29,718,621 | $ - | $ 963 | $ 1,713,748 | $ 0.14 |
Summary of Quarterly Results
The following summary information has been taken from the financial statements of Pacific Booker Minerals Inc., which have been prepared in accordance International Financial Reporting Standards (“IFRS”). The figures reported are all in Canadian dollars. US dollar amounts held as US dollars are converted into Canadian dollars at current exchange rates until actually converted into Canadian dollars, at which time the actual amount received is recorded. Any gains or losses from the exchange of currencies are reported on the Statement of Comprehensive Loss for the company in the current period.
The following table shows the total revenue (Finance income), the loss from our financial statements (cost of operating expenses, etc) before any unusual items, and the total loss and loss per share for each three month period for the last eight quarters. The second table following shows the same items on an accumulating basis per fiscal year.
| | | | |
For the three months ended | Total Revenue | Loss before other items |
Net Loss |
Total | Per Share |
January 31, 2014 | $ 710 | $ 407,614 | $ 406,904 | $ 0.03 |
April 30, 2014 | $ 171 | $ 620,353 | $ 620,182 | $ 0.05 |
July 31, 2014 | $ - | $ 470,691 | $ 470,691 | $ 0.04 |
October 31, 2014 | $ 159 | $ 331,051 | $ 330,892 | $ 0.03 |
January 31, 2015 | $ 633 | $ 292,616 | $ 291,983 | $ 0.02 |
April 30, 2015 | $ - | $ 236,055 | $ 236,055 | $ 0.02 |
July 31, 2015 | $ - | $ 114,540 | $ 114,540 | $ 0.01 |
October 31, 2015 | $ 345 | $ 190,623 | $ 190,278 | $ 0.01 |
| | | | |
For the period ended | Total Revenue | Loss before other items | Net Loss |
Total | Per Share |
for the year ended January 31, 2014 | $ 1,217 | $ 4,206,636 | $ 4,205,419 | $ 0.34 |
for the 3 month period ended April 30, 2014 | $ 171 | $ 620,353 | $ 620,182 | $ 0.05 |
for the 6 month period ended July 31, 2014 | $ 171 | $ 1,091,044 | $ 1,090,873 | $ 0.09 |
for the 9 month period ended October 31, 2014 | $ 330 | $ 1,422,095 | $ 1,421,765 | $ 0.12 |
for the year ended January 31, 2015 | $ 963 | $ 1,714,711 | $ 1,713,748 | $ 0.14 |
for the 3 month period ended April 30, 2015 | $ - | $ 236,055 | $ 236,055 | $ 0.02 |
for the 6 month period ended July 31, 2015 | $ - | $ 350,595 | $ 350,595 | $ 0.03 |
for the 9 month period ended October 31, 2015 | $ 345 | $ 541,218 | $ 540,873 | $ 0.04 |
Additional Disclosure for Venture Issuers
Mineral Property Interests
The following tables show the cost (write off) of acquisition payments by claim for each of the last eight quarters.
| | |
| Morrison | Total |
As at October 31, 2013 | $ 4,832,500 | $ 4,832,500 |
to January 31, 2014 | - | - |
As at January 31, 2014 | $ 4,832,500 | $ 4,832,500 |
to April 30, 2014 | - | - |
to July 31, 2014 | - | - |
to October 31, 2014 | - | - |
to January 31, 2015 | - | - |
As at January 31, 2015 | $ 4,832,500 | $ 4,832,500 |
to April 30, 2015 | - | - |
to July 31, 2015 | - | - |
to October 31, 2015 | | |
As at October 31, 2015 | $ 4,832,500 | $ 4,832,500 |
Deferred Exploration & Development expenditures
The table following shows the exploration expenditures or (write-offs) for each of the last eight quarters on a per claim basis.
| | | |
| Morrison | Grants/Tax Credits | Total |
As at October 31, 2013 | $ 24,915,631 | $ (859,434) | $ 24,056,197 |
to January 31, 2014 | 42,320 | - | 42,320 |
As at January 31, 2014 | $ 24,957,951 | $ (859,434) | $ 24,098,517 |
to April 30, 2014 | 76,136 | - | 76,136 |
to July 31, 2014 | 86,322 | - | 86,322 |
to October 31, 2014 | 35,400 | - | 35,400 |
to January 31, 2015 | 36,496 | - | 36,496 |
As at January 31, 2015 | $ 25,192,305 | $ (859,434) | $ 24,332,871 |
to April 30, 2015 | 59,866 | - | 59,866 |
to July 31, 2015 | 38,698 | - | 38,698 |
to October 31, 2015 | 67,353 | - | 67,353 |
As at October 31, 2015 | $ 25,358,222 | $ (859,434) | $ 24,498,788 |
Equity
The table following shows the change in capital stock and net operating expenses for each three month period and the accumulated operating deficit and total equity for the last eight quarters.
| | | | | | |
| Capital Stock | Subscriptions Received | Contributed Surplus | Operating Loss | Deficit ending | Total Equity |
As at October 31, 2013 | $ 49,874,704 | $ - | $ 13,438,403 | $ 3,798,515 | $ 32,891,237 | $ 30,421,870 |
to January 31, 2014 | 6,000 | - | 213,440 | 406,904 | 33,298,141 | 30,234,406 |
As at January 31, 2014 | $ 49,880,704 | $ - | $ 13,651,843 | $ 4,205,419 | $ 33,298,141 | $ 30,234,406 |
to April 30, 2014 | - | - | 446,823 | 620,182 | 33,918,323 | 30,061,047 |
to July 31, 2014 | 22,000 | - | 320,532 | 470,691 | 34,389,014 | 29,932,888 |
to October 31, 2014 | - | - | 219,504 | 330,892 | 34,719,906 | 29,821,500 |
to January 31, 2015 | - | - | 135,309 | 291,983 | 35,011,889 | 29,664,826 |
As at January 31, 2015 | $ 49,902,704 | $ - | $ 14,774,011 | $ 1,713,748 | $ 35,011,889 | $ 29,664,826 |
to April 30, 2015 | - | - | 63,145 | 236,055 | 35,247,944 | 29,491,916 |
to July 31, 2015 | - | 365,000 | - | 114,540 | 35,262,484 | 29,742,376 |
to October 31, 2015 | 555,600 | (365,000) | 86,865 | 190,278 | 35,552,762 | 29,829,563 |
As at October 31, 2015 | $ 50,458,304 | $ - | $ 14,924,021 | $ 540,873 | $ 35,552,762 | $ 29,829,563 |
Disclosure of outstanding share data
Details of our share transactions for the period and a listing of our outstanding options and warrants can be found in Note 8 of our financial statements.
Subsequent to the period end, the Company has not issued any shares on exercise of warrants or options, granted or cancelled any options, or announced or completed any private placements.