Regulatory Matters (Narrative) (Details) | Jan. 03, 2017USD ($) | Oct. 19, 2016USD ($) | Oct. 03, 2016USD ($) | Dec. 31, 2015USD ($) | Sep. 30, 2015USD ($) | Dec. 31, 2016USD ($)MW | Dec. 31, 2015USD ($) | Dec. 31, 2014USD ($) | Jan. 17, 2017USD ($) | Jun. 30, 2016USD ($) | Sep. 02, 2014 |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Net Asset Percentage Limit | | | | | | 25.00% | | | | | |
Regulatory Assets, noncurrent | | | | $ 11,373,000,000 | | $ 12,878,000,000 | $ 11,373,000,000 | | | | |
Net property, plant and equipment | | | | 73,779,000,000 | | 82,520,000,000 | 73,779,000,000 | | | | |
Impairment charges | | | | | | 18,000,000 | 106,000,000 | $ 81,000,000 | | | |
Debt Instrument, Face Amount | | | | 2,700,000,000 | | 9,127,000,000 | 2,700,000,000 | | | | |
Regulated Revenue | | | | | | 21,221,000,000 | 21,379,000,000 | 21,550,000,000 | | | |
Regulatory assets | | | | 12,250,000,000 | | $ 13,901,000,000 | 12,250,000,000 | | | | |
Atlantic Coast Pipeline (ACP) [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Joint owner ownership percentage | | | | | | 47.00% | | | | | 40.00% |
Long-term Purchase Commitment, Period | | | | | | 20 years | | | | | |
Sabal Trail Transmission Pipeline [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Joint owner ownership percentage | | | | | | 7.50% | | | | | |
Estimated capital cost | | | | | | $ 3,200,000,000 | | | | | |
Long-term Purchase Commitment, Period | | | | | | 25 years | | | | | |
Constitution Pipeline [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Joint owner ownership percentage | | | | | | 24.00% | | | | | |
Estimated Contributions For Pipeline And Construction Costs | | | | | | $ 229,000,000 | | | | | |
Accrued Pension And Post Retirement [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory Noncurrent Asset, Amortization Period | | | | | | 9 years | | | | | |
Regulatory assets | | | | 2,151,000,000 | | $ 2,387,000,000 | 2,151,000,000 | | | | |
Retired Generation Facilities [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory assets | | | | 509,000,000 | | 534,000,000 | 509,000,000 | | | | |
NCEMPA deferrals [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory assets | | | | 21,000,000 | | 51,000,000 | 21,000,000 | | | | |
Nuclear asset securitized balance, net [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory assets | | | | 1,237,000,000 | | 1,193,000,000 | 1,237,000,000 | | | | |
Nuclear Deferral [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory assets | | | | 245,000,000 | | 226,000,000 | 245,000,000 | | | | |
Minimum [Member] | Atlantic Coast Pipeline (ACP) [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Estimated capital cost | | | | | | 5,000,000,000 | | | | | |
Maximum [Member] | Atlantic Coast Pipeline (ACP) [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Estimated capital cost | | | | | | 5,500,000,000 | | | | | |
Western Carolinas Modernization Plan [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Approved Appeal Bond | | | | | | 98,000,000 | | | | | |
Duke Energy Carolinas [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory Assets, noncurrent | | | | 2,766,000,000 | | 3,159,000,000 | 2,766,000,000 | | | | |
Net property, plant and equipment | | | | 25,877,000,000 | | 26,762,000,000 | 25,877,000,000 | | | | |
Impairment charges | | | | | | 1,000,000 | 1,000,000 | 3,000,000 | | | |
Debt Instrument, Face Amount | | | | 500,000,000 | | 1,600,000,000 | 500,000,000 | | | | |
Regulatory assets | | | | 3,071,000,000 | | $ 3,397,000,000 | 3,071,000,000 | | | | |
Duke Energy Carolinas [Member] | Atlantic Coast Pipeline (ACP) [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Long-term Purchase Commitment, Period | | | | | | 20 years | | | | | |
Duke Energy Carolinas [Member] | Accrued Pension And Post Retirement [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory assets | | | | 479,000,000 | | $ 481,000,000 | 479,000,000 | | | | |
Duke Energy Carolinas [Member] | Retired Generation Facilities [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory assets | | | | 49,000,000 | | 39,000,000 | 49,000,000 | | | | |
Duke Energy Carolinas [Member] | Nuclear Deferral [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory assets | | | | 107,000,000 | | $ 92,000,000 | 107,000,000 | | | | |
Duke Energy Carolinas [Member] | Minimum [Member] | Retired Generation Facilities [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory Noncurrent Asset, Amortization Period | | | | | | 1 year | | | | | |
Duke Energy Carolinas [Member] | Maximum [Member] | Retired Generation Facilities [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory Noncurrent Asset, Amortization Period | | | | | | 6 years | | | | | |
Duke Energy Carolinas [Member] | FERC Transmission Rates [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Approved return on equity percentage amount by state commission | | | | | | 10.20% | | | | | |
Duke Energy Carolinas [Member] | FERC Complaint [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Requested Return on Equity, Percentage | | | | | | 8.49% | | | | | |
Duke Energy Carolinas [Member] | FERC ROE Settlement [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Approved return on equity percentage amount by state commission | | | | | | 10.00% | | | | | |
Duke Energy Carolinas [Member] | Advanced Metering Infrastructure Deferral [Member] | PSCSC [Member] | Maximum [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory Assets, noncurrent | | | | | | $ 45,000,000 | | | | | |
Duke Energy Carolinas [Member] | William States Lee Combined Cycle Facility [Member] | NCEMC [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Estimated capital cost of new utility plant, including AFUDC | | | | | | $ 600,000,000 | | | | | |
Joint owner ownership percentage | | | | | | 13.00% | | | | | |
Duke Energy Carolinas [Member] | William State Lee III Nuclear Station [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Net property, plant and equipment | | | | | | $ 520,000,000 | | | | | |
Duke Energy Progress [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory Assets, noncurrent | | | | 2,710,000,000 | | 3,243,000,000 | 2,710,000,000 | | | | |
Net property, plant and equipment | | | | 17,720,000,000 | | 18,387,000,000 | 17,720,000,000 | | | | |
Payments to Acquire Businesses, Gross | | | | | | | 1,249,000,000 | | | | |
Impairment charges | | | | | | 1,000,000 | 5,000,000 | (18,000,000) | | | |
Debt Instrument, Face Amount | | | | 1,200,000,000 | | 450,000,000 | 1,200,000,000 | | | | |
Regulatory assets | | | | 2,974,000,000 | | $ 3,431,000,000 | 2,974,000,000 | | | | |
Duke Energy Progress [Member] | Atlantic Coast Pipeline (ACP) [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Long-term Purchase Commitment, Period | | | | | | 20 years | | | | | |
Duke Energy Progress [Member] | Accrued Pension And Post Retirement [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory assets | | | | 366,000,000 | | $ 423,000,000 | 366,000,000 | | | | |
Duke Energy Progress [Member] | Retired Generation Facilities [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory Noncurrent Asset, Amortization Period | | | | | | 10 years | | | | | |
Regulatory assets | | | | 179,000,000 | | $ 165,000,000 | 179,000,000 | | | | |
Duke Energy Progress [Member] | NCEMPA deferrals [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory Noncurrent Asset, Amortization Period | | | | | | 24 years | | | | | |
Regulatory assets | | | | 21,000,000 | | $ 51,000,000 | 21,000,000 | | | | |
Duke Energy Progress [Member] | Nuclear Deferral [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory assets | | | | 62,000,000 | | $ 38,000,000 | 62,000,000 | | | | |
Duke Energy Progress [Member] | Maximum [Member] | Retired Generation Facilities [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory Noncurrent Asset, Amortization Period | | | | | | 10 years | | | | | |
Duke Energy Progress [Member] | FERC Transmission Rates [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Approved return on equity percentage amount by state commission | | | | | | 10.80% | | | | | |
Duke Energy Progress [Member] | FERC Complaint [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Requested Return on Equity, Percentage | | | | | | 8.49% | | | | | |
Duke Energy Progress [Member] | FERC ROE Settlement [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Approved return on equity percentage amount by state commission | | | | | | 10.00% | | | | | |
Duke Energy Progress [Member] | Storm Cost Deferrals [Member] | PSCSC [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Deferred Storm and Property Reserve Deficiency, Noncurrent | | | | | | $ 60,000,000 | | | | | |
Duke Energy Progress [Member] | Storm Cost Deferrals [Member] | NCUC [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Estimated Storm Costs - Capital and Operation Maintenance | | | | | | $ 140,000,000 | | | | | |
Duke Energy Progress [Member] | 2016 South Carolina Rate Case [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory Noncurrent Asset, Amortization Period | | | | | | 15 years | | | | | |
Duke Energy Progress [Member] | 2016 South Carolina Rate Case [Member] | PSCSC [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Requested Return on Equity, Percentage | | | | | | 10.75% | | | | | |
Requested Rate Increase (Decrease), Percentage | | | | | | 14.50% | | | | | |
Requested Rate Increase (Decrease), Amount | | | | | | $ 79,000,000 | | | | | |
Duke Energy Progress [Member] | 2016 South Carolina Rate Case Settlement [Member] | PSCSC [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Approved return on equity percentage amount by state commission | | 10.10% | | | | | | | | | |
Approved rate increase (decrease) amount by state commission | | $ 56,000,000 | | | | | | | | | |
Duke Energy Progress [Member] | 2016 South Carolina Rate Case Settlement Year 1 Increase [Member] | PSCSC [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Approved rate increase (decrease) amount by state commission | | 38,000,000 | | | | | | | | | |
Duke Energy Progress [Member] | 2016 South Carolina Rate Case Settlement Year 2 Increase [Member] | PSCSC [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Approved rate increase (decrease) amount by state commission | | 18,500,000 | | | | | | | | | |
Duke Energy Progress [Member] | 2016 South Carolina Rate Case Settlement Year 2 Offset [Member] | PSCSC [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Approved rate increase (decrease) amount by state commission | | $ (18,500,000) | | | | | | | | | |
Duke Energy Progress [Member] | Western Carolinas Modernization Plan [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Estimated capital cost | | | | | | 1,100,000,000 | | | | | |
Duke Energy Progress [Member] | FERC Mitigation [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Impairment charges | | | | | | | | (18,000,000) | | | |
Duke Energy Progress [Member] | Shearon Harris Nuclear Station [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory Assets, noncurrent | | | | | | 48,000,000 | | | | | |
Duke Energy Florida [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory Assets, noncurrent | | | | 2,725,000,000 | | 2,480,000,000 | 2,725,000,000 | | | | |
Net property, plant and equipment | | | | 10,623,000,000 | | 11,790,000,000 | 10,623,000,000 | | | | |
Impairment charges | | | | | | 6,000,000 | 7,000,000 | 2,000,000 | | | |
Debt Instrument, Face Amount | | | | | | 1,894,000,000 | | | | | |
Regulatory assets | | | | 2,823,000,000 | | 2,693,000,000 | 2,823,000,000 | | | | |
Duke Energy Florida [Member] | Accrued Pension And Post Retirement [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory assets | | | | 441,000,000 | | 458,000,000 | 441,000,000 | | | | |
Duke Energy Florida [Member] | Retired Generation Facilities [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory assets | | | | 230,000,000 | | 257,000,000 | 230,000,000 | | | | |
Duke Energy Florida [Member] | Nuclear asset securitized balance, net [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory assets | | | | 1,237,000,000 | | 1,193,000,000 | 1,237,000,000 | | | | |
Duke Energy Florida [Member] | Nuclear Deferral [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory assets | | | | 76,000,000 | | 96,000,000 | 76,000,000 | | | | |
Duke Energy Florida [Member] | Hines Chiller Uprate Project [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Estimated capital cost | | | | | | 150,000,000 | | | | | |
Duke Energy Florida [Member] | Hines Chiller Uprate Project Phase 1 [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Requested Rate Increase (Decrease), Amount | | | | | | 17,000,000 | | | | | |
Duke Energy Florida [Member] | Hines Chiller Uprate Project Phase 2 [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Requested Rate Increase (Decrease), Amount | | | | | | 3,000,000 | | | | | |
Duke Energy Florida [Member] | Osprey Energy Center Acquisition [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Approved rate increase (decrease) amount by state commission | | | | | | $ 48,000,000 | | | | | |
Duke Energy Florida [Member] | 2013 FPSC Settlement Agreement [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Approved return on equity percentage amount by state commission | | | | | | 10.50% | | | | | |
Approved rate increase (decrease) amount by state commission | | | | | | $ 150,000,000 | | | | | |
Duke Energy Florida [Member] | 2013 FPSC Settlement Agreement [Member] | Minimum [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Approved return on equity percentage amount by state commission | | | | | | 9.50% | | | | | |
Duke Energy Florida [Member] | 2013 FPSC Settlement Agreement [Member] | Maximum [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Approved return on equity percentage amount by state commission | | | | | | 11.50% | | | | | |
Duke Energy Florida [Member] | Citrus County Station [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Estimated capital cost of new utility plant, including AFUDC | | | | | | $ 1,500,000,000 | | | | | |
Duke Energy Florida [Member] | Crystal River Unit 3 [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory Noncurrent Asset, Amortization Period | | | | | | 20 years | | | | | |
Duke Energy Florida [Member] | Crystal River Unit 3 [Member] | ISFSI Projects [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Approved return on equity percentage amount by state commission | | | | | | 7.35% | | | | | |
Regulatory Assets, noncurrent | | | | | | $ 93,000,000 | | | | | |
Duke Energy Florida [Member] | Crystal River Unit 3 [Member] | 2013 FPSC Settlement Agreement [Member] | Original Uprate Project [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory Noncurrent Asset, Amortization Period | | | | | | 7 years | | | | | |
Regulatory Assets, noncurrent | | | | | | $ 128,000,000 | | | | | |
Duke Energy Florida [Member] | Crystal River Unit 3 [Member] | 2013 FPSC Settlement Agreement [Member] | FPSC [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory Assets, noncurrent | | | | 1,283,000,000 | | | 1,283,000,000 | | | | |
Amount of Regulatory Costs Not yet Approved | | | | | | 1,298,000,000 | | | | | |
Impairment charges | | | | | $ 15,000,000 | | | | | | |
Duke Energy Florida [Member] | Levy Nuclear Station [Member] | FPSC [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Approved rate increase (decrease) amount by state commission | | | | | | $ 0 | | | | | |
Duke Energy Florida [Member] | Levy Nuclear Station [Member] | 2013 FPSC Settlement Agreement [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory Noncurrent Asset, Amortization Period | | | | | | 5 years | | | | | |
Regulatory Assets, noncurrent | | | | | | $ 100,000,000 | | | | | |
Net property, plant and equipment | | | | | | 119,000,000 | | | | | |
Net unrecovered investment | | | | | | $ 219,000,000 | | | | | |
Duke Energy Ohio [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Limit of Total Capital | | | | | | 30.00% | | | | | |
Regulatory Assets, noncurrent | | | | 497,000,000 | | $ 520,000,000 | 497,000,000 | | | | |
Net property, plant and equipment | | | | 5,243,000,000 | | 5,547,000,000 | 5,243,000,000 | | | | |
Impairment charges | | | | | | | | 94,000,000 | | | |
Debt Instrument, Face Amount | | | | | | 250,000,000 | | | | | |
Regulated Revenue | | | | | | 1,410,000,000 | 1,331,000,000 | $ 1,316,000,000 | | | |
Regulatory assets | | | | 533,000,000 | | 557,000,000 | 533,000,000 | | | | |
Duke Energy Ohio [Member] | Accrued Pension And Post Retirement [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory assets | | | | 139,000,000 | | 135,000,000 | 139,000,000 | | | | |
Duke Energy Ohio [Member] | East Bend Coal Ash Basin Filing [Member] | KPSC [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Estimated capital cost | | | | | | 93,000,000 | | | | | |
Duke Energy Ohio [Member] | Natural Gas Pipeline Extension [Member] | PUCO [Member] | Minimum [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Estimated Capital Cost Excluding AFUDC | | | | | | 86,000,000 | | | | | |
Duke Energy Ohio [Member] | Natural Gas Pipeline Extension [Member] | PUCO [Member] | Maximum [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Estimated Capital Cost Excluding AFUDC | | | | | | 110,000,000 | | | | | |
Duke Energy Ohio [Member] | Accelerated Natural Gas Service Line Replacement Rider | PUCO [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Amount of Regulatory Costs Not yet Approved | | | | | | 240,000,000 | | | | | |
Duke Energy Ohio [Member] | Energy Efficiency and Peak Demand Reduction Program [Member] | PUCO [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulated Revenue | | | | 20,000,000 | | | | | | | |
Duke Energy Ohio [Member] | Mgp Remediation [Member] | PUCO [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory assets | | | | | | 99,000,000 | | | | | |
Duke Energy Ohio [Member] | Advanced Metering Infrastructure Project [Member] | KPSC [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Estimated capital cost | | | | | | 49,000,000 | | | | | |
Amount of Regulatory Costs Not yet Approved | | | | | | 10,000,000 | | | | | |
Duke Energy Ohio [Member] | RTO Realignment [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory assets | | | | 72,000,000 | | $ 71,000,000 | 72,000,000 | | | | |
Approved MVP Proposals | | | | | | 17 | | | | | |
MISO estimate of Duke Energy Ohio's MVP obligation | | | | | | $ 2,700,000,000 | | | | | |
Duke Energy Ohio [Member] | East End Site [Member] | Mgp Remediation [Member] | PUCO [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Environmental Exit Costs, Anticipated Cost | | | | | | $ 46,000,000 | | | | | |
Duke Energy Kentucky [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Required Equity Capital Structure Percent | | | | | | 35.00% | | | | | |
Duke Energy Indiana [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory Assets, noncurrent | | | | 716,000,000 | | $ 1,073,000,000 | 716,000,000 | | | | |
Net property, plant and equipment | | | | 9,523,000,000 | | 9,924,000,000 | 9,523,000,000 | | | | |
Impairment charges | | | | | | 8,000,000 | 88,000,000 | | | | |
Debt Instrument, Face Amount | | | | | | 500,000,000 | | | | | |
Regulatory assets | | | | 818,000,000 | | 1,222,000,000 | 818,000,000 | | | | |
Duke Energy Indiana [Member] | Accrued Pension And Post Retirement [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory assets | | | | 220,000,000 | | 222,000,000 | 220,000,000 | | | | |
Duke Energy Indiana [Member] | Retired Generation Facilities [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory assets | | | | 51,000,000 | | $ 73,000,000 | 51,000,000 | | | | |
Duke Energy Indiana [Member] | FERC Transmission Rates [Member] | Federal Energy Regulatory Commission [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Approved return on equity percentage amount by state commission | | | | | | 12.38% | | | | | |
Approved Return on Equity Percentage Adder | | | | | | 0.50% | | | | | |
Duke Energy Indiana [Member] | Coal Combustion Residual Plan [Member] | IURC [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Requested Rate Increase (Decrease), Amount | | | | | | $ 380,000,000 | | | | | |
Federal Mandate Costs Recovered Through Tracker Mechanism | | | | | | 80.00% | | | | | |
Federally Mandated Costs Recovered In Future Rate Case | | | | | | 20.00% | | | | | |
Percentage of Costs Recovered through Existing Rider | | | | | | 60.00% | | | | | |
Percentage Recovered Through Future Rate Case | | | | | | 40.00% | | | | | |
Long-term Debt Rate | | | | | | 4.73% | | | | | |
Requested Rate Increase (Decrease), Amended, Amount | | | | | | $ 365,000,000 | | | | | |
Duke Energy Indiana [Member] | FERC Complaint 1 [Member] | Federal Energy Regulatory Commission [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Approved return on equity percentage amount by state commission | | | | | | 10.32% | | | | | |
Duke Energy Indiana [Member] | FERC Complaint 2 [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Requested Return on Equity, Percentage | | | | | | 8.67% | | | | | |
Duke Energy Indiana [Member] | FERC Complaint 2 [Member] | Federal Energy Regulatory Commission [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Requested Return on Equity, Percentage | | | | | | 9.70% | | | | | |
Duke Energy Indiana [Member] | Grid Infrastructure Improvement Plan [Member] | IURC [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Estimated capital cost | | | | | | $ 1,900,000,000 | | | | | |
Duke Energy Indiana [Member] | Revised Grid Infrastructure Improvement Plan [Member] | IURC [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Approved return on equity percentage amount by state commission | | | | | | 10.00% | | | | | |
Approved rate increase (decrease) amount by state commission | | | | | | $ 1,400,000,000 | | | | | |
Estimated capital cost | | | | | | 1,800,000,000 | | | | | |
Duke Energy Indiana [Member] | Advanced Metering Infrastructure Project [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Net property, plant and equipment | | | | | | 46,000,000 | | | | | |
Impairment charges | | | | | | $ 8,000,000 | | | | | |
Duke Energy Indiana [Member] | Edwardsport IGCC Plant [Member] | IGCC Rider Proceeding [Member] | IURC [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory Noncurrent Asset, Amortization Period | | | | | | 8 years | | | | | |
Regulatory assets | | | | | | $ 161,000,000 | | | | | |
Requested Rate Increase (Decrease), Amended, Amount | | | | | | (87,500,000) | | | | | |
Legal Fees | | | | | | $ 5,500,000 | | | | | |
Utilities Operating Expense, Other | | | | | | | 93,000,000 | | | | |
Dominion Resources [Member] | Atlantic Coast Pipeline (ACP) [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Joint owner ownership percentage | | | | | | 48.00% | | | | | 45.00% |
Piedmont Natural Gas [Member] | Atlantic Coast Pipeline (ACP) [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Joint owner ownership percentage | | | | | | | | | | | 10.00% |
Ownership Interest in Jointly Owned Plant Transferred | | | 3.00% | | | | | | | | |
Proceeds from Divestiture of Businesses and Interests in Affiliates | | | $ 14,000,000 | | | | | | | | |
Southern Company Gas [Member] | Atlantic Coast Pipeline (ACP) [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Joint owner ownership percentage | | | | | | 5.00% | | | | | 5.00% |
Spectra Energy [Member] | Sabal Trail Transmission Pipeline [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Joint owner ownership percentage | | | | | | 50.00% | | | | | |
NextEra [Member] | Sabal Trail Transmission Pipeline [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Joint owner ownership percentage | | | | | | 42.50% | | | | | |
Williams Partners L.P. [Member] | Constitution Pipeline [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Joint owner ownership percentage | | | | | | 41.00% | | | | | |
Subsequent Event [Member] | Duke Energy Florida [Member] | Osprey Energy Center Acquisition [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Payments to Acquire Businesses, Gross | $ 166,000,000 | | | | | | | | | | |
Subsequent Event [Member] | Duke Energy Florida [Member] | Osprey Energy Center Acquisition [Member] | USDOJ [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Other Commitment | | | | | | | | | $ 600,000 | | |
DEFPF [Member] | Duke Energy Florida [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Regulatory Assets, noncurrent | | | | | | $ 1,142,000,000 | | | | | |
Debt Instrument, Face Amount | | | | | | 1,294,000,000 | | | | | |
DEFPF [Member] | Duke Energy Florida [Member] | Crystal River Unit 3 [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Debt Instrument, Face Amount | | | | | | | | | | $ 1,294,000,000 | |
Proceeds from Issuance of Debt | | | | | | 1,287,000,000 | | | | | |
Generation Facilities To Be Retired [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Net property, plant and equipment | | | | | | $ 424,000,000 | | | | | |
Capacity (in MW) | MW | | | | | | 1,738 | | | | | |
Generation Facilities To Be Retired [Member] | Duke Energy Progress [Member] | Asheville Plant [Member] | | | | | | | | | | | |
Public Utilities, General Disclosures [Line Items] | | | | | | | | | | | |
Net property, plant and equipment | | | | $ 548,000,000 | | $ 492,000,000 | $ 548,000,000 | | | | |
Capacity (in MW) | MW | | | | | | 376 | | | | | |