| PAGE 3 HIGHWATER ETHANOL, LLC VOLUME 2, ISSUE 3 Highwater Ethanol Highlights from your CEO/GM Greetings from Highwater Ethanol, LLC, Lamberton, MN!! As I write this for our summer newsletter construction of the facility is about 99.9% complete. We started receiving corn on July 27, 2009, receiving approximately 450,000 bushels the first week of delivery. We stopped receiving corn deliveries on August 5, 2009 as we had reached storage capacity and have started to receive corn again effective August 19, 2009. We started grinding corn on August 14, 2009, as I write this we are in our 4th day of operations with only minor startup items. We sent our first 190 proof to the tank farm on August 18, 2009. We continue to make progress with the startup and anticipate loading our first ethanol railroad cars the week of August 24, 2009. Highwater Ethanol, LLC started the majority of our employees on May 4th, 2009. Since their start date we have been busy training the employees in the class room, on the Highwater Ethanol site along with some training at Granite Falls Energy, Granite Falls, MN. We would like to thank the Granite Falls Energy Board and employees for allowing Highwater Ethanol Employees to gain some valuable hands on training. Some of you may know that Highwater Ethanol, LLC had contracted with Granite Falls Energy for project construction management. Robin Spaude, Plant Manager filled that role here at HE and did a GREAT job. THANK YOU! Highwater Ethanol, LLC continues to walk from a construction mode to an operations mode, this will last for a few more months. As we enter into the operations mode we continue to monitor the margins on a daily basis, as we have been doing in the hope that we find opportunities for a positive margin for the coming year. It will not be easy, but we will continue to work hard to take advantage of these opportunities. Highwater Ethanol, LLC intends to remain focused on margins and we will operate the plant with this in mind. We believe the Renewable Fuels industry is here to stay, Highwater Ethanol, LLC is poised to be part of this industry. Our management team in place consist of Mark Peterson, CFO, Mark Palmer, Plant Manager, Tom Streifel, Risk/Commodity Manager, Matt Lenning, Operations Manager, Dan Thompson, Maintenance Manager, Lisa Landkammer, Lab Manager, Dan Dahl, Environmental, Health & Safety Coordinator. The majority of our management team comes with excellent experience in the ethanol industry. We believe we have positioned our team to be successful in the ethanol industry. Highwater Ethanol, LLC will be holding elections for the Board of Governors in February 2010 at the annual meeting which is scheduled for February 26, 2010. Information for applying for the Board of Governors is found in this news letter and on our web site. In closing, I can say it has been a “Great” project to be part of, and I believe you, our investor’s owners, will be proud of the facility. We have scheduled our GRAND OPENING for Friday, September 11, 2009 at 9:30 am, starting with a program and then tours of the site and facility that day. I am looking forward to seeing everyone at our Grand Opening. We will take care of the present as we focus on the FUTURE! Brian Kletscher CEO/GM Highwater Ethanol, LLC |