Exhibit 10.57
AMENDMENT TO | Franklin Synergy Bank | x | ||
THE CONTRACT | Crossroads Architecture | ¨ | ||
Century Skanska | x | |||
Jobsite | ¨ | |||
DOCUMENT G701 | OTHER | ¨ |
PROJECT: Franklin Synergy Bank, Nolensville Branch Renovation
TO CONTRACTOR: Skanska USA Building Inc. 5000 Meridian Blvd, Suite 100 Franklin, TN 37067
The Contract is changed as follows: | CHANGE ORDER NO.
DATE:
ARCHITECT’S PROJECT NO.:
CONTRACT DATE:
CONTRACT FOR:
REFERENCE CCR # | Two (2)
10/2/2015
N/A
10/6/2015
Construction Management
N/A | ||
Total amount of Change Order Amendment: | $ | 23,111.00 | ||
|
|
Not valid until signed by the Owner, Architect and Contractor.
The original (Estimated Maximum Price) was | $ | — | ||
Net change by previously authorized Change Orders | $ | — | ||
The (Estimated Maximum Price) prior to this Change Order was | $ | — | ||
The (Estimated Maximum Price) will be (increased) ( | $ | 23,111.00 | ||
The new (Guaranteed Maximum Price) including this Change Order will be | $ | 207,111.00 | ||
The Contract Time for this change will be (established) as | (0) days | |||
The date of Substantial Completion as of the date of this Change Order therefore is | December 10, 2015 |
/s/ Dennis Norvet | /s/ Kevin Herrington | |||||||
CONTRACTOR | OWNER | |||||||
Skanska USA Building Inc. | Franklin Synergy Bank | |||||||
Address: | 5000 Meridian Blvd., Suite 100 | Address: | 722 Columbia Avenue | |||||
Franklin, TN 37067 | Franklin, TN 37064 | |||||||
BY: | Dennis Norvet | BY: | Kevin Herrington | |||||
DATE: | 10.26.2015 | DATE: | 10/28/15 |
Franklin Synergy Bank Nolesville GMP Amendment 10262015 Final GMP 1(C),