Public Utilities Disclosure [Text Block] | 3. Below are descriptions of OTP’s major capital expenditure projects that have had, or are expected to have, a significant impact on OTP’s revenue requirements, rates and alternative revenue recovery mechanisms, followed by summaries of specific electric rate or rider proceedings with the Minnesota Public Utilities Commission (MPUC), the North Dakota Public Service Commission (NDPSC), the South Dakota Public Utilities Commission (SDPUC) and the FERC, impacting OTP’s revenues in 2019 2018. Major Capital Expenditure Projects Astoria Station 2021. November 3, 2017, August 3, 2018 Station. In a September 26, 2018 March 6, 2019 December 2018 January 2019. May 2019. September 30, 2019, Merricourt Wind Energy Center (Merricourt) November 16, 2016 November 16, 2016, October 26, 2017 January 10, 2018. November 3, 2017. March 6, 2019 April 2019. In connection with action by the FERC, OTP and EDF agreed, in the First Amendment to the Purchase Agreement and the TEPC Agreement dated June 11, 2019, July 16, 2019, August 2019. September 30, 2019, Big Stone South–Ellendale Multi-Value Transmission Project (MVP) February 6, 2019, December 2011. Recovery of OTP’s major transmission investments is through the MISO Tariff and Minnesota, North Dakota and South Dakota base rates and TCR riders. Minnesota General Rates 2016 March 2017 May 1, 2017. The MPUC’s order also included: ( 1 2 November 1, 2017. Minnesota Conservation Improvement Programs (MNCIP) not May 25, 2016 2017 2018 2019 2017 2018 2019 May 20, 2019 2017 2019 one 2020. On April 1, 2019 2018 2018 not May 31, 2019 2018 June 24, 2019 $3.0 October 24, 2019 2018. Transmission Cost Recovery Rider may In OTP’s 2016 May 1, 2017, two August 18, 2017 On June 11, 2018 July 11, 2018 March 11, 2019. On November 30, 2018 two two 2019. April 1, 2019, not September 30, 2019 Environmental Cost Recovery Rider 2010 2016 November 2017. 2018 zero December 1, 2018. March April 2019. Renewable Resource Adjustment November 1, 2017, 2017 2018. June 21, 2019 September 30, 2019 Fuel and Purchased Power Costs Recovery December 2017 July 31, 2019 twelve January 1, 2020. On implementation of the new mechanism, OTP will be required to accrue a liability and likely refund amounts of fuel and purchased power and related costs per kwh collected in excess of forecasted amounts per kwh submitted to the MPUC for setting rates for the upcoming year. OTP will continue to accrue revenue and a regulatory asset for fuel and purchased power costs incurred in excess of amounts recovered, that it expects to recover under the adjustment mechanism, unless and until recovery of those excess amounts are deemed not not North Dakota General Rates November 2, 2017 December 20, 2017 January 1, 2018. February 27, 2018 March 1, 2018. On March 23, 2018 In a September 26, 2018 March 2018 not February 1, 2019, April 2019 Renewable Resource Adjustment Effective in February 2019 2017 Transmission Cost Recovery Rider 2017 26 26A 2017 OTP filed its annual update to the North Dakota TCR rider on August 30, 2019 January 1, 2020. Environmental Cost Recovery Rider 2017 February 1, 2019, February 1, 2019 October 22, 2019 zero November 1, 2019 December 31, 2019. Generation Cost Recovery Rider March 1, 2019 May 15, 2019. July 1, 2019. South Dakota General Rates April 20, 2018 first two October 18, 2018. second The SDPUC approved a partial settlement on March 1, 2019 second January 1, 2018 October 17, 2018 first 2019. May 14, 2019. May 30, 2019 June 28, 2019 August 1, 2019. October 18, 2018 October 2019 On July 9, 2019 2018 May 30, 2019 first October 18, 2018, October 1, 2019. To ensure rates are appropriately set under the stipulation, the parties agreed to establish an earnings sharing mechanism to share with customers any weather-normalized earnings above the authorized ROE of 8.75%. OTP's annual weather-normalized earnings are reported each year by June 1 30 Transmission Cost Recovery Rider January 29, 2018 October 18, 2018, 2018 OTP made a supplemental filing for the South Dakota TCR rider on February 1, 2019. February 20, 2019 March 1, 2019. January 1, 2019 January 2020. OTP made a supplemental filing for the South Dakota TCR rider on September 5, 2019 2018 September 17, 2019 October 1, 2019. Environmental Cost Recovery Rider October 18, 2018 October 2019 Phase-In Rate Plan Rider May 31, 2019 OTP made a supplemental filing for the South Dakota Phase-In Rate Plan Rider on August 2, 2019. August 21, 2019 September 1, 2019. Revenues Recorded under Rate Riders The following table presents revenue recorded by OTP under rate riders in place in Minnesota, North Dakota and South Dakota. Three Months Ended September 30, Nine Months Ended September 30, Rate Rider (in thousands) 2019 2018 2019 2018 Minnesota Conservation Improvement Program Costs and Incentives $ 1,518 $ 1,488 $ 4,246 $ 4,300 Renewable Resource Recovery 1,316 817 3,949 2,001 Transmission Cost Recovery (284 ) (1,196 ) 301 (1,683 ) Environmental Cost Recovery - 24 (1 ) (25 ) North Dakota Transmission Cost Recovery 908 1,922 3,554 5,149 Renewable Resource Adjustment (20 ) 2,220 616 6,266 Generation Cost Recovery 137 - 607 - Environmental Cost Recovery (7 ) 1,823 556 5,474 South Dakota Transmission Cost Recovery 743 496 1,587 1,282 Conservation Improvement Program Costs and Incentives 100 238 440 589 Phase-In Rate Plan Recovery (10 ) - (10 ) - Environmental Cost Recovery (2 ) 545 (29 ) 1,580 Total $ 4,399 $ 8,377 $ 15,816 $ 24,933 Rate Rider Updates The following table provides summary information on the status of updates since January 1, 2017 Rate Rider R - Request Date A - Approval Date Effective Date Requested or Approved Annual Revenue ($000s) Rate Minnesota Conservation Improvement Program 2018 Incentive and Cost Recovery A – October 24, 2019 December 1, 2019 $ 11,926 $0.00710 /kwh 2017 Incentive and Cost Recovery A – October 4, 2018 November 1, 2018 $ 10,283 $0.00600 /kwh 2016 Incentive and Cost Recovery A – September 15, 2017 October 1, 2017 $ 9,868 $0.00536 /kwh Transmission Cost Recovery 2018 Annual Update–Scenario A R – November 30, 2018 June 1, 2019 $ 6,475 Various –Scenario B $ 2,708 Various 2017 Rate Reset A – October 30, 2017 November 1, 2017 $ (3,311 ) Various Environmental Cost Recovery 2018 Annual Update A – November 29, 2018 December 1, 2018 $ - 0% of base 2017 Rate Reset A – October 30, 2017 November 1, 2017 $ (1,943 ) -0.935% of base Renewable Resource Adjustment 2019 Annual Update – Revised R – September 30, 2019 November 1, 2019 $ 12,506 $0.00467 /kwh 2018 Annual Update A – August 29, 2018 November 1, 2018 $ 5,886 $0.00219 /kwh 2017 Rate Reset A – October 30, 2017 November 1, 2017 $ 1,279 $0.00049 /kwh North Dakota Renewable Resource Adjustment 2019 Annual Update A – May 1, 2019 June 1, 2019 $ (235 ) -0.224% of base 2018 Rate Reset for effect of TCJA A – February 27, 2018 March 1, 2018 $ 9,650 7.493% of base 2017 Rate Reset A – December 20, 2017 January 1, 2018 $ 9,989 7.756% of base Transmission Cost Recovery 2019 Annual Update R – August 30, 2019 January 1, 2020 $ 5,739 Various 2018 Supplemental Update A – December 6, 2018 February 1, 2019 $ 4,801 Various 2018 Rate Reset for effect of TCJA A – February 27, 2018 March 1, 2018 $ 7,469 Various 2017 Annual Update A – November 29, 2017 January 1, 2018 $ 7,959 Various Environmental Cost Recovery 2019 Update A – October 22, 2019 November 1, 2019 $ - 0% of base 2018 Update A – December 19, 2018 February 1, 2019 $ (378 ) -0.310% of base 2018 Rate Reset for effect of TCJA A – February 27, 2018 March 1, 2018 $ 7,718 5.593% of base 2017 Rate Reset A – December 20, 2017 January 1, 2018 $ 8,537 6.629% of base Generation Cost Recovery 2019 Initial Request A – May 15, 2019 July 1, 2019 $ 2,720 2.547% of base South Dakota Transmission Cost Recovery 2019 Rate Reset A – September 17, 2019 October 1, 2019 $ 2,046 Various 2019 Annual Update A – February 20, 2019 March 1, 2019 $ 1,638 Various 2018 Interim Rate Reset A – October 18, 2018 October 18, 2018 $ 1,171 Various 2017 Annual Update A – February 28, 2018 March 1, 2018 $ 1,779 Various 2016 Annual Update A – February 17, 2017 March 1, 2017 $ 2,053 Various Environmental Cost Recovery 2018 Interim Rate Reset A – October 18, 2018 October 18, 2018 $ (189 ) -$0.00075 /kwh 2017 Annual Update A – October 13, 2017 November 1, 2017 $ 2,082 $0.00483 /kwh Phase-In Rate Plan Recovery 2019 Initial Request A – August 21, 2019 September 1, 2019 $ 864 3.345% of base TCJA The TCJA, passed in December 2017, January 1, 2018. The MPUC required regulated utilities providing service in Minnesota to make filings by February 15, 2018. August 9, 2018 December 5, 2018 one ten 2017 June 1, 2019. one January 2018 May 2019 August September 2019. As described above, OTP’s recent general rate cases in North Dakota and South Dakota reflected the impact of the TCJA in interim rates. OTP accrued refund liabilities for the time periods during which revenues were collected under rates set to recover higher levels of federal income taxes than OTP incurred under the lower federal tax rates in the TCJA. The North Dakota liability of $0.8 million as of March 31, 2019 January February 2018 April 2019. As of September 30, 2019, March 15, 2018, 2018 FERC Wholesale power sales and transmission rates are subject to the jurisdiction of the FERC under the Federal Power Act of 1935 MVPs ROE November 12, 2013 may 15 November 12, 2013 February 11, 2015. December 22, 2015 September 28, 2016 September 2016 On November 6, 2014 January 5, 2015 November 12, 2013 0.5% September 28, 2016. On February 12, 2015 may second second 15 February 12, 2015 May 11, 2016. June 18, 2015 February 16, 2016. June 30, 2016 second Based on the probable reduction by the FERC in the ROE component of the MISO Tariff, OTP had a $2.7 million liability on its balance sheet as of December 31, 2016, first 15 February June 2017 2016 December 31, 2016 September 30, 2019. In June 2014, two two April 2017 June 2014 not June 2014 April 2017 September 29, 2017 second On October 16, 2018 April 2017. 206 November 15, 2018, two February 13, 2019 April 10, 2019. no September 30, 2019 second On March 1, 2019 two 2019, |