Contingencies and Commitments | R. Contingencies and Commitments Unless specifically described to the contrary, all matters within Note R are the full responsibility of Alcoa Corporation pursuant to the Separation and Distribution Agreement (see Note A). Additionally, the Separation and Distribution Agreement provides for cross-indemnities between the Company and Arconic for claims subject to indemnification. Contingencies Litigation. Before 2002, ParentCo purchased power in Italy in the regulated energy market and received a drawback of a portion of the price of power under a special tariff in an amount calculated in accordance with a published resolution of the Italian Energy Authority, Energy Authority Resolution n. 204/1999 (“204/1999”). In 2001, the Energy Authority published another resolution, which clarified that the drawback would be calculated in the same manner, and in the same amount, in either the regulated or unregulated market. At the beginning of 2002, ParentCo left the regulated energy market to purchase energy in the unregulated market. Subsequently, in 2004, the Energy Authority introduced regulation no. 148/2004, which set forth a different method for calculating the special tariff that would result in a different drawback for the regulated and unregulated markets. ParentCo challenged the new regulation in the Administrative Court of Milan and received a favorable judgment in 2006. Following this ruling, ParentCo continued to receive the power price drawback in accordance with the original calculation method, through 2009, when the European Commission declared all such special tariffs to be impermissible “state aid.” In 2010, the Energy Authority appealed the 2006 ruling to the Consiglio di Stato (final court of appeal). On December 2, 2011, the Consiglio di Stato ruled in favor of the Energy Authority and against ParentCo, thus presenting the opportunity for the energy regulators to seek reimbursement from ParentCo of an amount equal to the difference between the actual drawback amounts received over the relevant time period, and the drawback as it would have been calculated in accordance with regulation 148/2004. On February 23, 2012, ParentCo filed its appeal of the decision of the Consiglio di Stato (this appeal was subsequently withdrawn in March 2013). On March 26, 2012, ParentCo received a letter from the agency (Cassa Conguaglio per il Settore Eletrico (CCSE)) responsible for making and collecting payments on behalf of the Energy Authority demanding payment in the amount of approximately $110 (€85), including interest. By letter dated April 5, 2012, ParentCo informed CCSE that it disputes the payment demand of CCSE since (i) CCSE was not authorized by the Consiglio di Stato decisions to seek payment of any amount, (ii) the decision of the Consiglio di Stato has been appealed (see above), and (iii) in any event, no interest should be payable. On April 29, 2012, Law No. 44 of 2012 (“44/2012”) came into effect, changing the method to calculate the drawback. On February 21, 2013, ParentCo received a revised request letter from CSSE demanding ParentCo’s former subsidiary, Alcoa Trasformazioni S.r.l. (Trasformazioni is now a subsidiary of Alcoa Corporation), make a payment in the amount of $97 (€76), including interest, which reflects a revised calculation methodology by CCSE and represents the high end of the range of reasonably possible loss associated with this matter of $0 to $97 (€76). ParentCo rejected that demand and formally challenged it through an appeal before the Administrative Court on April 5, 2013. The Administrative Court scheduled a hearing for December 19, 2013, which was subsequently postponed until April 17, 2014, and further postponed until June 19, 2014. On this date, the Administrative Court listened to ParentCo’s oral argument, and on September 2, 2014, rendered its decision. The Administrative Court declared the payment request of CCSE and the Energy Authority to ParentCo to be unsubstantiated based on the 148/2004 resolution with respect to the January 19, 2007 through November 19, 2009 timeframe. On December 18, 2014, the CCSE and the Energy Authority appealed the Administrative Court’s September 2, 2014 decision; however, a date for the hearing has not been scheduled. As a result of the conclusion of the European Commission Matter on January 26, 2016 (see below), ParentCo’s management modified its outlook with respect to a portion of the pending legal proceedings related to this matter. As such, a charge of $37 (€34) was recorded in Restructuring and other charges for the year ended December 31, 2015 on Alcoa Corporation’s accompanying Statement of Consolidated Operations to establish a partial reserve for this matter. At this time, Alcoa Corporation is unable to reasonably predict the ultimate outcome for this matter. European Commission Matter. On November 19, 2009, the EC announced a decision in this matter stating that the extension of the tariff by Italy constituted unlawful state aid, in part, and, therefore, the Italian Government is to recover a portion of the benefit ParentCo received since January 2006 (including interest). The amount of this recovery was to be based on a calculation prepared by the Italian Government (see below). In late 2009, after discussions with legal counsel and reviewing the bases on which the EC decided, including the different considerations cited in the EC decision regarding ParentCo’s two smelters in Italy, ParentCo recorded a charge of $250 (€173), which included $20 (€14) to write off a receivable from the Italian Government for amounts due under the now expired tariff structure and $230 (€159) to establish a reserve. On April 19, 2010, ParentCo filed an appeal of this decision with the General Court of the EU (see below). Prior to 2012, ParentCo was involved in other legal proceedings related to this matter that separately sought the annulment of the EC’s July 2006 decision to open an investigation alleging that such decision did not follow the applicable procedural rules and requested injunctive relief to suspend the effectiveness of the EC’s November 19, 2009 decision. However, the decisions by the General Court, and subsequent appeals to the European Court of Justice, resulted in the denial of these remedies. In June 2012, ParentCo received formal notification from the Italian Government with a calculated recovery amount of $375 (€303); this amount was reduced by $65 (€53) for amounts owed by the Italian Government to ParentCo, resulting in a net payment request of $310 (€250). In a notice published in the Official Journal of the European Union on September 22, 2012, the EC announced that it had filed an action against the Italian Government on July 18, 2012 to compel it to collect the recovery amount (on October 17, 2013, the European Court of Justice ordered Italy to so collect). On September 27, 2012, ParentCo received a request for payment in full of the $310 (€250) by October 31, 2012. Following discussions with the Italian Government regarding the timing of such payment, ParentCo paid the requested amount in five quarterly installments of $69 (€50) beginning in October 2012 through December 2013. On October 16, 2014, ParentCo received notice from the General Court of the EU that its April 19, 2010 appeal of the EC’s November 19, 2009 decision was denied. On December 27, 2014, ParentCo filed an appeal of the General Court’s October 16, 2014 ruling to the European Court of Justice (ECJ). Following submission of the EC’s response to the appeal, on June 10, 2015, ParentCo filed a request for an oral hearing before the ECJ; no decision on that request was received. On January 26, 2016, ParentCo was informed that the ECJ had dismissed ParentCo’s December 27, 2014 appeal of the General Court’s October 16, 2014 ruling. The dismissal of ParentCo’s appeal represents the conclusion of the legal proceedings in this matter. Prior to this dismissal, ParentCo had a noncurrent asset of $100 (€91) reflecting the excess of the total of the five payments made to the Italian Government over the reserve recorded in 2009. As a result, this noncurrent asset, along with the $58 (€53) for amounts owed by the Italian Government to ParentCo mentioned above plus $6 (€6) for interest previously paid, was written-off. A charge of $164 (€150) was recorded in Restructuring and other charges for the year ended December 31, 2015 on Alcoa Corporation’s accompanying Statement of Consolidated Operations (see Note D). As a result of the EC’s November 19, 2009 decision, ParentCo’s management had contemplated ceasing operations at its Italian smelters due to uneconomical power costs. In February 2010, ParentCo’s management agreed to continue to operate its smelters in Italy for up to six months while a long-term solution to address increased power costs could be negotiated. Over a portion of this time, a long-term solution was not able to be reached related to the Fusina smelter, therefore, in May 2010, ParentCo and the Italian Government agreed to a temporary idling of the Fusina smelter. As of September 30, 2010, the Fusina smelter was fully curtailed (44,000 metric-tons-per-year). For the Portovesme smelter, ParentCo executed a new power agreement effective September 1, 2010 through December 31, 2012, replacing the short-term, market-based power contract that was in effect since early 2010. This new agreement along with interruptibility rights (i.e. compensation for power interruptions when grids are overloaded) granted to ParentCo for the Portovesme smelter provided additional time to negotiate a long-term solution (the EC had previously determined that the interruptibility rights were not considered state aid). At the end of 2011, as part of a restructuring of ParentCo’s global smelting system, ParentCo’s management decided to curtail operations at the Portovesme smelter during 2012 due to the uncertain prospects for viable, long-term power, along with rising raw materials costs and falling global aluminum prices (mid-2011 to late 2011). As of December 31, 2012, the Portovesme smelter was fully curtailed (150,000 metric-tons-per-year). In June 2013 and August 2014, ParentCo decided to permanently shut down and demolish the Fusina and Portovesme smelters, respectively, due to persistent uneconomical conditions (see Note D). Environmental Matters. A liability is recorded for environmental remediation when a cleanup program becomes probable and the costs can be reasonably estimated. As assessments and cleanups proceed, the liability is adjusted based on progress made in determining the extent of remedial actions and related costs. The liability can change substantially due to factors such as, among others, the nature and extent of contamination, changes in remedial requirements, and technological changes. Alcoa Corporation’s remediation reserve balance was $324 and $235 at December 31, 2016 and 2015 (of which $60 and $28 was classified as a current liability), respectively, and reflects the most probable costs to remediate identified environmental conditions for which costs can be reasonably estimated. In 2016, the remediation reserve was increased by $39 due to a charge of $26 related to the planned demolition of the Suriname refinery and permanent closure of the related bauxite mines (see Note D) and a net charge of $13 associated with a number of other sites. In 2015, the remediation reserve was increased by $107 due to a charge of $52 related to the planned demolition of the remaining structures at the Massena East smelter location (see Note D), a charge of $29 related to the planned demolition of the Poços de Caldas smelter and the Anglesea power station (see Note D), a charge of $12 related to the Mosjøen location (see below), a charge of $7 related to the Portovesme location (see below), and a net charge of $7 associated with a number of other sites. Of the changes to the remediation reserve in 2016 and 2015, $26 and $86, respectively, was recorded in Restructuring and other charges, while the remainder was recorded in Cost of goods sold on the accompanying Statement of Consolidated Operations. Payments related to remediation expenses applied against the reserve were $32 and $24 in 2016 and 2015, respectively. These amounts include expenditures currently mandated, as well as those not required by any regulatory authority or third party. In 2016, the change in the reserve also reflects an increase for each of the following: $60 of obligations transferred from ParentCo in connection with the Separation Transaction (see Note A) on November 1, 2016, including Sherwin and East St. Louis described below; $17 for the reclassification of amounts included in other reserves within Other noncurrent liabilities and deferred credits on Alcoa Corporation’s Consolidated Balance Sheet as of December 31, 2015; and $5 due to the effects of foreign currency translation. In 2015, the change in the reserve also reflects a decrease of $13 due to the effects of foreign currency translation. Included in annual operating expenses are the recurring costs of managing hazardous substances and environmental programs. These costs are estimated to be approximately 2% of cost of goods sold. The Separation and Distribution Agreement (see Note A) includes provisions for the assignment or allocation of environmental liabilities between Alcoa Corporation and Arconic, including certain remediation obligations associated with environmental matters. In general, the respective parties will be responsible for the environmental matters associated with their operations, and with the properties and other assets assigned to each. Additionally, the Separation and Distribution Agreement lists environmental matters with a shared responsibility between the two companies with an allocation of responsibility and the lead party responsible for management of each matter. For matters assigned to Alcoa Corporation under the Separation and Distribution Agreement, Alcoa Corporation has agreed to indemnify Arconic in whole or in part for environmental liabilities arising from operations prior to the Separation Date. The following discussion provides details regarding the current status of certain significant reserves related to current or former Alcoa Corporation sites. With the exception of the Fusina, Italy matter, Alcoa Corporation assumed full responsibility of the matters described below. Sherwin, TX Baie Comeau, Quebec, Canada Fusina and Portovesme, Italy— In December 2009, Trasformazioni and Ligestra reached an initial agreement for settlement of the liabilities related to the Fusina operations while negotiations continued related to Portovesme (see below). The agreement outlined an allocation of payments to the MOE for emergency action and natural resource damages and the scope and costs for a proposed soil remediation project, which was formally presented to the MOE in mid-2010. The agreement was contingent upon final acceptance of the remediation project by the MOE. As a result of entering into this agreement, ParentCo increased the reserve by $12 in 2009 for Fusina. Based on comments received from the MOE and local and regional environmental authorities, Trasformazioni submitted a revised remediation plan in the first half of 2012; however, such revisions did not require any change to the existing reserve. In October 2013, the MOE approved the project submitted by ParentCo, resulting in no adjustment to the reserve. In January 2014, in anticipation of ParentCo reaching a final administrative agreement with the MOE, ParentCo and Ligestra entered into a final agreement related to Fusina for allocation of payments to the MOE for emergency action and natural resource damages and the costs for the approved soil remediation project. The agreement resulted in Ligestra assuming 50% to 80% of all payments and remediation costs. On February 27, 2014, ParentCo and the MOE reached a final administrative agreement for conduct of work. The agreement includes both a soil and groundwater remediation project estimated to cost $33 (€24) and requires payments of $25 (€18) to the MOE for emergency action and natural resource damages. Based on the final agreement with Ligestra, ParentCo’s share of all costs and payments was $17 (€12), of which $9 (€6) related to the damages will be paid annually over a 10-year period, which began in April 2014, and was previously fully reserved. The soil remediation project will begin once authorization to dispose of excavated waste into a third-party landfill is received from the MOE, which is expected at some point in the remainder of 2017. The responsibility for the execution of groundwater remediation project/emergency containment has been transferred to the MOE in accordance with the February 2014 settlement agreement and remediation is slated to begin in late 2017 or in 2018. Effective with the Separation Transaction (see Note A), Arconic retained the portion of this obligation related to the Fusina rolling operations. Specifically, under the Separation and Distribution Agreement, Trasformazioni, and with it the Fusina properties, were assigned to Alcoa Corporation. Fusina Rolling S.r.l., entered into a lease agreement for the portion of property that included the rolling operation. Pursuant to the Separation and Distribution Agreement, the liabilities at Fusina described above were allocated between Alcoa Corporation (Trasformazioni) and Arconic (Fusina Rolling S.r.l.). Arconic will pay $7 (€7) for the portion of remediation expenses associated with the section of property that includes the rolling operation. Separately, in 2009, due to additional information derived from the site investigations conducted at Portovesme, ParentCo increased the reserve by $3. In November 2011, Trasformazioni and Ligestra reached an agreement for settlement of the liabilities related to Portovesme, similar to the one for Fusina. A proposed soil remediation project for Portovesme was formally presented to the MOE in June 2012. Neither the agreement with Ligestra nor the proposal to the MOE resulted in a change to the reserve for Portovesme. In November 2013, the MOE rejected the proposed soil remediation project and requested a revised project be submitted. In May 2014, Trasformazioni and Ligestra submitted a revised soil remediation project that addressed certain stakeholders’ concerns. ParentCo increased the reserve by $3 in 2014 to reflect the estimated higher costs associated with the revised soil remediation project, as well as current operating and maintenance costs of the Portovesme site. In October 2014, the MOE required a further revised project be submitted to reflect the removal of a larger volume of contaminated soil than what had been proposed, as well as design changes for the cap related to the remaining contaminated soil left in place and the expansion of an emergency containment groundwater pump and treatment system that was previously installed. Trasformazioni and Ligestra submitted the further revised soil remediation project in February 2015. As a result, ParentCo increased the reserve by $7 in March 2015 to reflect the increase in the estimated costs of the project. In October 2015, ParentCo received a final ministerial decree approving the February 2015 revised soil remediation project. Work on the soil remediation project commenced in mid-2016 and is expected to be completed in 2019. After further discussions with the MOE regarding the groundwater remediation project, Alcoa Corporation and Ligestra are working to find a common remediation solution. The ultimate outcome of this matter may result in a change to the existing reserve for Portovesme. Mosjøen, Norway In April 2015, the NEA notified ParentCo that the revised project was approved and required submission of the final project design before issuing a final order. ParentCo completed and submitted the final project design, which identified a need to stabilize the related wharf structure to allow for the sediment dredging in the harbor. As a result, ParentCo increased the reserve for Mosjøen by $11 in June 2015 to reflect the estimated cost of the wharf stabilization. Also in June 2015, the NEA issued a final order approving the project as well as the final project design. In September 2015, ParentCo increased the reserve by $1 to reflect the potential need (based on prior experience with similar projects) to perform additional dredging if the results of sampling, which is required by the order, don’t achieve the required cleanup levels. Project construction commenced in early 2016 and is expected to be completed by the end of 2017. At December 31, 2016 and 2015, the reserve balance associated with this matter was $8 and $20, respectively. East St. Louis, IL Tax. Additionally, following a corporate income tax audit of the same Spanish tax group for the 2006 through 2009 tax years, Spain’s tax authorities issued an assessment in July 2013 similarly disallowing certain interest deductions. In August 2013, ParentCo filed an appeal of this second assessment in Spain’s Central Tax Administrative Court, which was denied in January 2015. ParentCo filed an appeal of this second assessment in Spain’s National Court in March 2015. At December 31, 2016, the combined assessments, including interest, total $258 (€246). On January 16, 2017, Spain’s National Court issued a decision in favor of the Company related to the assessment received in September 2010. On March 6, 2017, the Company was notified that Spain’s tax authorities did not file an appeal, for which the deadline has passed. As a result, the assessment related to the 2003 through 2005 tax years is null and void. Spain’s National Court has not yet rendered a decision related to the assessment received in July 2013 for the 2006 through 2009 tax years. The amount of this assessment on a standalone basis, including interest, was $136 (€130) as of December 31, 2016. The Company believes it has meritorious arguments to support its tax position and intends to vigorously litigate the remaining assessment through Spain’s court system. However, in the event the Company is unsuccessful, a portion of the remaining assessment may be offset with existing net operating losses available to the Spanish consolidated tax group, which would be shared between the Company and Arconic as provided for in the Tax Matters Agreement related to the Separation Transaction. Additionally, it is possible that the Company may receive similar assessments for tax years subsequent to 2009. Despite the favorable decision received on the first assessment, at this time, the Company is unable to reasonably predict the ultimate outcome for this matter. In March 2013, AWAB was notified by the Brazilian Federal Revenue Office (RFB) that approximately $110 (R$220) of value added tax credits previously claimed are being disallowed and a penalty of 50% assessed. Of this amount, AWAB received $41 (R$82) in cash in May 2012. The value added tax credits were claimed by AWAB for both fixed assets and export sales related to the Juruti bauxite mine and São Luís refinery expansion. The RFB has disallowed credits they allege belong to the consortium in which AWAB owns an interest and should not have been claimed by AWAB. Credits have also been disallowed as a result of challenges to apportionment methods used, questions about the use of the credits, and an alleged lack of documented proof. AWAB presented defense of its claim to the RFB on April 8, 2013. If AWAB is successful in this administrative process, the RFB would have no further recourse. If unsuccessful in this process, AWAB has the option to litigate at a judicial level. Separately from the AWAB’s administrative appeal, in June 2015, new tax law was enacted repealing the provisions in the tax code that were the basis for the RFB assessing a 50% penalty in this matter. As such, the estimated range of reasonably possible loss is $0 to $32 (R$103), whereby the maximum end of this range represents the portion of the disallowed credits applicable to the export sales and excludes the 50% penalty. Additionally, the estimated range of disallowed credits related to AWAB’s fixed assets is $0 to $36 (R$117), which would increase the net carrying value of AWAB’s fixed assets if ultimately disallowed. It is Alcoa Corporation’s management’s opinion that the allegations have no basis; however, at this time, management is unable to reasonably predict the ultimate outcome for this matter. Between 2000 and 2002, Alumínio sold approximately 2,000 metric tons of metal per month from its Poços de Caldas facility, located in the State of Minas Gerais (the “State”), to Alfio, a customer also located in the State. Sales in the State were exempted from value-added tax (VAT) requirements. Alfio subsequently sold metal to customers outside of the State, but did not pay the required VAT on those transactions. In July 2002, Alumínio received an assessment from State auditors on the theory that Alumínio should be jointly and severally liable with Alfio for the unpaid VAT. In June 2003, the administrative tribunal found Alumínio liable, and Alumínio filed a judicial case in the State in February 2004 contesting the finding. In May 2005, the Court of First Instance found Alumínio solely liable, and a panel of a State appeals court confirmed this finding in April 2006. Alumínio filed a special appeal to the Superior Tribunal of Justice (STJ) in Brasilia (the federal capital of Brazil) later in 2006. In 2011, the STJ (through one of its judges) reversed the judgment of the lower courts, finding that Alumínio should neither be solely nor jointly and severally liable with Alfio for the VAT, which ruling was then appealed by the State. In August 2012, the STJ agreed to have the case reheard before a five-judge panel. On February 21, 2017, the lead judge of the STJ issued a ruling confirming that Alumínio should be held liable in this matter. Alumínio is in the process of filing an appeal to have its case reheard before the five-judge panel as originally agreed to by the STJ in August 2012. At December 31, 2016, the assessment totaled $43 (R$142), including penalties and interest. While Alcoa Corporation believes it has meritorious defenses, the Company is unable to reasonably predict the ultimate outcome for this matter. Other. On October 4, 2016, the state of Texas filed suit against Sherwin in the bankruptcy proceeding seeking to hold Sherwin responsible for remediation of alleged environmental conditions at the facility. On October 11, 2016, Sherwin filed a similar suit against Reynolds in the case. On November 10, 2016, Reynolds filed motions to dismiss the Gregory Power complaint and to withdraw the case from bankruptcy court. On November 23, 2016, the bankruptcy court approved Sherwin’s plans for cessation of its operations. On February 16, 2017, Sherwin filed a bankruptcy Chapter 11 Plan and on February 17, 2017 the court approved that Plan. As provided in the Plan, Sherwin, including certain affiliated companies, and Reynolds are negotiating a settlement to allocate among them ownership of and responsibility for certain areas of the refinery. A definitive agreement is anticipated prior to April 30, 2017 and would resolve outstanding claims made by Sherwin against Reynolds. General. Commitments Purchase Obligations. On April 8, 2015, AofA secured a new 12-year gas supply agreement to power its three alumina refineries in Western Australia beginning in July 2020. This agreement was conditional on the completion of a third-party acquisition of the related energy assets from the then-current owner, which occurred in June 2015. The terms of the gas supply agreement required AofA to make a prepayment of $500 in two installments. The first installment of $300 was made at the time of the completion of the third-party acquisition in June 2015 and the second installment of $200 was made in April 2016. Both of these amounts were included in (Increase) in noncurrent assets on the accompanying Statement of Consolidated Cash Flows in the respective periods. At December 31, 2016 and 2015, Alcoa Corporation has an asset of $471 (A$654) and $288 (A$395), respectively, representing the respective prepayments made under this agreement, which was included in Other noncurrent assets (see Note S) on the accompanying Consolidated Balance Sheet. Operating Leases. Guarantees of Third Parties. Bank Guarantees and Letters of Credit. Surety Bonds. |