Exhibit 99.2
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
Management’s Discussion and Analysis
Year ended December 31, 2020
Amounts in United States dollars
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
Orla Mining Ltd. is a mineral exploration and development company which trades on the Toronto Stock Exchange under the ticker symbol “OLA” and on the New York Stock Exchange American (“NYSE American”) under the symbol “ORLA”. The “Company”, “Orla”, “we”, and “our” refer to Orla Mining Ltd. and its subsidiaries.
Our corporate strategy is to acquire, develop and operate mineral properties where our expertise can substantially increase shareholder value. We have two material gold projects with near-term production potential based on open pit mining and heap leaching – the Camino Rojo Oxide Gold Project located in Zacatecas State, Mexico, and the Cerro Quema Gold Project located in Los Santos Province, Panama.
This Management’s Discussion and Analysis (“MD&A”) of the financial condition and results of operations of the Company should be read in conjunction with our consolidated financial statements for the year ending December 31, 2020. You can find additional information regarding the Company, including our Annual Information Form, on SEDAR1 under the Company’s profile at www.sedar.com.
All monetary amounts herein are expressed in United States dollars ($ or US$) unless otherwise stated. C$ refers to Canadian dollars.
This MD&A is current as of March 19, 2021.
Andrew Cormier, P. Eng., is the Qualified Person, as the term is defined in National Instrument 43-101 (“NI 43-101”). He has reviewed and approved the technical information disclosed in this MD&A.
During the year ended December 31, 2020, and to the date of this MD&A:
| A. | CAMINO ROJO OXIDE PROJECT DEVELOPMENT |
| • | In January 2020, Orla completed the required payments to the Mexican federal environment department (“SEMARNAT”) granting the Change of Land Use permit (“Cambio de Uso de Suelo” or “CUS/ETJ”), one of the two key permits required for the development of the Camino Rojo Oxide Gold Project. |
| • | In March 2020, the Company entered into a non-binding letter agreement with Fresnillo plc (“Fresnillo”) as to the commercial terms on which Orla would obtain the right to expand the Camino Rojo oxide pit onto part of Fresnillo’s mineral concession located immediately to the north of Orla’s property. This agreement was finalized in December 2020, and all conditions precedent were met in February 2021. |
| • | In August 2020, the Company was granted approval of the Company’s Environmental Impact Statement (“Manifestos de Impacto Ambiental” or “MIA”) required for the development of the Camino Rojo Oxide Gold Project. With receipt of the MIA, Orla had the two principal permits necessary for commencement of project construction. |
| • | Upon receiving the necessary permits, Orla began earthworks at Camino Rojo in the fourth quarter of 2020. |
1 SEDAR is the System for Electronic Document Analysis and Retrieval, a filing system operated by the Canadian Securities Administrators, accessible at: www.sedar.com
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
| • | Current construction activities include installation of the construction camp and offices, drilling water wells and site fence erection. The power line to site has been approved by the federal electricity commission and construction is currently underway, ahead of schedule. |
| • | As of the date of this MD&A, detailed engineering was 94% complete. |
| • | Process plant equipment, including crusher and conveyors, commenced arriving on site since November 2020. |
| • | An update to the Camino Rojo Feasibility Study was released to include the layback area resulting in a larger oxide pit from the previously announced agreement with Fresnillo. |
| B. | CERRO QUEMA PROJECT DEVELOPMENT |
| • | In Panama, the Company continued work on the Cerro Quema Pre-Feasibility Study update which is expected to be released in the first half of 2021. Specific ongoing workflows include resource modelling, process and metallurgy design, geotechnical drilling, hydrology testing, and environmental study and review. The geotechnical drilling to support the study began during the third quarter of 2020. |
| C. | FINANCING AND CORPORATE |
| • | In April 2020, the Company closed a bought deal financing by issuing 36,600,000 common shares at a price of C$2.05 per common share for aggregate gross proceeds to the Company of C$75 million. |
| • | Drawdown of $50 million for the second tranche of the Credit Facility occurred on October 30, 2020. The Company has $50 million available on its $125 million Credit Facility. |
| • | In December 2020, Orla commenced trading on the NYSE American under the symbol “ORLA”. |
| • | The Company appointed Andrew Cormier as the Chief Operating Officer in April 2020, and appointed Sean Spraggett as the General Manager, Panama, in July 2020. |
| • | In November 2020, Eric Colby was appointed to the Board of Directors of Orla as a nominee of Newmont Corporation (“Newmont”). |
COVID-19 GLOBAL HEALTH EMERGENCY
The global outbreak of the novel coronavirus (“COVID-19”) in 2020 has had a significant impact on businesses through restrictions put in place by governments around the world, including the jurisdictions in which we conduct our business. Our activities have been restricted by government orders related to, among others, travel, business operations, and stay-at-home orders. As of the date of this MD&A, it is not possible to determine the extent of the impact that this global health emergency will have on our activities as the impacts will depend on future developments which themselves are highly uncertain and cannot be predicted with confidence. These uncertainties arise from the inability to predict the ultimate geographic spread of the disease, its extent and intensity, the duration of the outbreak, and possible government, societal, and individual responses to the situation.
On March 20, 2020, Orla suspended all activities at the Camino Rojo and Cerro Quema projects due to government mandated stay-at-home orders issued in response to the COVID-19 Global Health Emergency. Both operations have established COVID-19 committees that meet regularly to discuss operational protocols and safety measures and update as necessary.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
Authorization to resume activities at Camino Rojo was received from the Mexican health authorities on May 23, 2020 after a plan was presented and all requirements had been met for a safe return to work. However, there remains a high degree of uncertainty as to future impacts the pandemic could have on our business. Should there be changes to the current situation, our construction schedule and consequently our timing to production may be affected.
The Board of Directors has oversight over management’s response to COVID-19, and has reviewed the plans and protocols in place. Return-to-work plans and protocols have been implemented at Cerro Quema, Panama, and approved by the health authorities. The Company has implemented strict COVID-19 protocols, including rigorous screening and testing programs at both sites. Vaccination programs in Mexico are ongoing. Vaccinations for senior citizens in the local community of San Tiburcio and other nearby communities have commenced and we expect such programs to expand in the state of Zacatecas as more vaccine shipments are received.
We continue to maintain robust organization-wide COVID-19 prevention protocols to support the health of our employees and local communities. Orla is closely monitoring the potential impacts from the pandemic on areas including equipment delivery and logistics, construction costs and schedule, as well as community and government relations.
| III. | OUTLOOK AND UPCOMING MILESTONES |
We remain focused on advancing the Company’s strategic objectives and near-term milestones, which include the following:
| • | Continue to advance construction activities at the Camino Rojo Oxide Project towards a targeted first pour in the fourth quarter of 2021; |
| • | Continue to maintain robust health and safety protocols, including COVID-19 prevention measures, to support the health of our employees and local communities; |
| • | Complete the update to the Pre-Feasibility Study at the Cerro Quema Oxide Project; |
| • | Advance the preliminary economic assessment study on the Camino Rojo Sulphide Project for completion by year-end 2021; |
| • | Continue to advance exploration programs with activities focused on supporting study work and new target identification. |
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
CAUTIONARY NOTE TO UNITED STATES INVESTORS REGARDING PRESENTATION OF MINERAL RESERVE AND MINERAL RESOURCE ESTIMATES
This MD&A has been prepared in accordance with Canadian standards for reporting of mineral resource and mineral reserve estimates, which differ from the standards of United States securities laws. In particular, and without limiting the generality of the foregoing, the terms “mineral reserve”, “proven mineral reserve” “probable mineral reserve”, “inferred mineral resources,” “indicated mineral resources,” “measured mineral resources” and “mineral resources” used or referenced in this Prospectus are Canadian mineral disclosure terms as defined in accordance with Canadian National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”) and the Canadian Institute of Mining, Metallurgy and Petroleum (the “CIM”) — CIM Definition Standards on Mineral Resources and Mineral Reserves, adopted by the CIM Council, as amended (the “CIM Definition Standards”). These definitions differ significantly from the definitions in Industry Guide 7 (“SEC Industry Guide 7”) under the U.S. Securities Act. Under U.S. standards, mineralization may not be classified as a “reserve” unless the determination has been made that the mineralization could be economically and legally produced or extracted at the time the reserve determination is made. Also, under SEC Industry Guide 7 standards, a “final” or “bankable” feasibility study is required to report reserves, the three-year historical average price is used in any reserve or cash flow analysis to designate reserves and the primary environmental analysis or report must be filed with the appropriate governmental authority.
In addition, the terms “mineral resource”, “measured mineral resource”, “indicated mineral resource” and “inferred mineral resource” are defined in and required to be disclosed by NI 43-101; however, these terms are not defined terms under SEC Industry Guide 7 and are normally not permitted to be used in reports and registration statements filed with the SEC. Investors are cautioned not to assume that any part or all of the mineral deposits in these categories will ever be converted into reserves. “Inferred mineral resources” have a great amount of uncertainty as to their existence and as to their economic and legal feasibility. It cannot be assumed that all or any part of an inferred mineral resource will ever be upgraded to a higher category. Under Canadian rules, estimates of inferred mineral resources may not form the basis of feasibility or pre-feasibility studies, except in rare cases. Investors are cautioned not to assume that all or any part of an inferred mineral resource exists or is economically or legally mineable. Mineral resources that are not mineral reserves do not have demonstrated economic viability. Disclosure of “contained ounces” in a resource is permitted disclosure under Canadian regulations; however, the SEC normally only permits issuers to report mineralization that does not constitute “reserves” by SEC standards as in place tonnage and grade without reference to unit measures. Accordingly, information contained in this Prospectus and the documents incorporated by reference herein that describes the Company’s mineral deposits may not be comparable to similar information made public by U.S. companies subject to reporting and disclosure requirements under the United States federal securities laws and the rules and regulations thereunder.
The SEC has adopted amendments to its disclosure rules to modernize the mineral property disclosure requirements for issuers whose securities are registered with the SEC under the U.S. Securities Exchange Act of 1934, as amended (the “Exchange Act”). These amendments became effective February 25, 2019 (the “SEC Modernization Rules”) with compliance required for the first fiscal year beginning on or after January 1, 2021. Under the SEC Modernization Rules, the historical property disclosure requirements for mining registrants included in SEC Industry Guide 7 will be rescinded and replaced with disclosure requirements in subpart 1300 of SEC Regulation S-K. Following the transition period, as a foreign private issuer that is eligible to file reports with the SEC pursuant to the multi-jurisdictional disclosure system, the Company is not required to provide disclosure on its mineral properties under the SEC Modernization Rules and will continue to provide disclosure under NI 43-101 and the CIM Definition Standards. If the Company ceases to be a foreign private issuer or lose its eligibility to file its annual report on Form 40-F pursuant to the multi-jurisdictional disclosure system, then the Company will be subject to the SEC Modernization Rules which differ from the requirements of NI 43-101.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
As a result of the adoption of the SEC Modernization Rules, the SEC now recognizes estimates of “measured mineral resources”, “indicated mineral resources” and “inferred mineral resources.” In addition, the SEC has amended its definitions of “proven mineral reserves” and “probable mineral reserves” to be “substantially similar” to the corresponding CIM Definition Standards that are required under NI 43-101. While the SEC will now recognize “measured mineral resources”, “indicated mineral resources” and “inferred mineral resources”, U.S. investors should not assume that any part or all of the mineralization in these categories will ever be converted into a higher category of mineral resources or into mineral reserves. Mineralization described using these terms has a greater amount of uncertainty as to its existence and feasibility than mineralization that has been characterized as reserves. Accordingly, U.S. investors are cautioned not to assume that any measured mineral resources, indicated mineral resources, or inferred mineral resources that the Company reports are or will be economically or legally mineable. Further, “inferred mineral resources” have a greater amount of uncertainty as to their existence and as to whether they can be mined legally or economically. Therefore, U.S. investors are also cautioned not to assume that all or any part of the “inferred mineral resources” exist. Under Canadian securities laws, estimates of “inferred mineral resources” may not form the basis of feasibility or pre-feasibility studies, except in rare cases. While the above terms are “substantially similar” to CIM Definitions, there are differences in the definitions under the SEC Modernization Rules and the CIM Definition Standards. Accordingly, there is no assurance any mineral reserves or mineral resources that the Company may report as “proven mineral reserves”, “probable mineral reserves”, “measured mineral resources”, “indicated mineral resources” and “inferred mineral resources” under NI 43-101 would be the same had the Company prepared the reserve or resource estimates under the standards adopted under the SEC Modernization Rules.
CAUTIONARY NOTE REGARDING FORWARD-LOOKING INFORMATION
This MD&A contains “forward-looking statements” or “forward-looking information” within the meaning of applicable securities legislation (collectively referred to herein as “forward-looking information” or “forward-looking statements”). Forward-looking statements are included to provide information about management’s current expectations and plans that allows investors and others to get a better understanding of the Company’s operating environment, the business operations and financial performance and condition. Forward-looking information is provided as of the date of such documents only and the Company does not intend, and does not assume any obligation, to update this forward-looking information, except as required by law.
Forward-looking statements include, but are not limited to, statements regarding the use of proceeds of an Offering; the timing for completion of any Offering; feasibility studies and economic results thereof, including but not limited to future production, costs and expenses; mine production plans; projected mining and process recovery rates; mining dilution assumptions; timeline for receipt of any required agreements, approvals or permits; sustaining costs and operating costs; interpretations and assumptions regarding joint venture and potential contract terms; closure costs and requirements; the expected additional material to be included in a future mine plan as a result of the Layback Agreement; terms of and ability to reach a subsequent agreement with Fresnillo (as defined herein) to access the sulphide mineral resource at the Camino Rojo Project (as defined herein) and obtaining regulatory approvals related thereto; the planned exploration and development programs and expenditures; the estimation of mineral resources and mineral reserves; expectations on the potential extension of the expired mineral concessions with respect to the Cerro Quema Project (as defined herein); proposed exploration plans and expected results of exploration from each of the Cerro Quema Project and the Camino Rojo Project; Orla’s ability to obtain required mine licences, mine permits, required agreements with third parties and regulatory approvals required in connection with exploration plans and future mining and mineral processing operations, including but not limited to, necessary permitting required to implement expected future exploration plans; community and Ejido relations; availability of sufficient water for proposed operations; competition for, among other things, capital, acquisitions of mineral reserves, undeveloped lands and skilled personnel; commodity prices and exchange rates; currency and interest rate fluctuations and the ability to secure the required capital to conduct planned exploration programs, studies and construction and Orla’s development, objectives and strategies. Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance (often, but not always, identified by words or phrases such as “expects”, “is expected”, “anticipates”, “believes”, “plans”, “projects”, “estimates”, “assumes”, “intends”, “strategy”, “goals”, “objectives”, “potential”, “possible” or variations thereof or stating that certain actions, events, conditions or results “may”, “could”, “would”, “should”, “might” or “will” be taken, occur or be achieved (or the negative of any of these terms and similar expressions)) are not statements of fact and may be forward-looking statements.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
Forward-looking statements are necessarily based upon a number of factors and assumptions that, if untrue, could cause actual results, performance or achievements to be materially different from future results, performance or achievements expressed or implied by such statements. Forward-looking statements are based upon a number of estimates and assumptions that, while considered reasonable by the Company at this time, are inherently subject to significant business, economic and competitive uncertainties and contingencies that may cause the Company’s actual financial results, performance, or achievements to be materially different from those expressed or implied herein. Some of the material factors or assumptions used to develop forward-looking statements include, without limitation, the future price of gold, anticipated costs and the Company’s ability to fund its programs, the Company’s ability to carry on exploration and development activities, the Company’s ability to secure and to meet obligations under property agreements, including the Layback Agreement, that all conditions of the Company’s credit facility will be met, the timing and results of drilling programs, the discovery of mineral resources and mineral reserves on the Company’s mineral properties, the obtaining of a subsequent agreement with Fresnillo to access the sulphide mineral resource at the Camino Rojo Project and develop the entire Camino Rojo Project mineral resources estimate, that political and legal developments will be consistent with current expectations, the timely receipt of required approvals and permits, including those approvals and permits required for successful project permitting, construction and operation of projects, the costs of operating and exploration expenditures, the Company’s ability to operate in a safe, efficient and effective manner, the Company’s ability to obtain financing as and when required and on reasonable terms and that the Company’s activities will be in accordance with the Company’s public statements and stated goals; that there will be no material adverse change or disruptions affecting the Company or its properties,
Forward-looking statements are subject to a variety of known and unknown risks, uncertainties and other factors that could cause actual events or results to differ from those expressed or implied. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Certain important factors that could cause actual results, performance or achievements to differ materially from those in the forward-looking statements include, among others: (i) failure to obtain required regulatory and stock exchange approvals with respect to any Offering; (ii) risks related to uncertainties inherent in the preparation of feasibility studies, including but not limited to, assumptions underlying the production estimates not being realized, changes to the cost of production, variations in quantity of mineralized material, grade or recovery rates, geotechnical or hydrogeological considerations during mining differing from what has been assumed, failure of plant, equipment or processes, changes to availability of power or the power rates, ability to maintain social license, changes to exchange, interest or tax rates, cost of labour, supplies, fuel and equipment rising, changes in project parameters, delays and costs inherent to consulting and accommodating rights of local communities; (iii) title risks; (iv) risks that the interpreted drill results may not accurately represent the actual continuity of geology or grade of the deposit, bulk density measurements may not be representative, interpreted and modelled metallurgical domains may not be representative, and metallurgical recoveries may not be representative; (v) access to additional capital; (vi) uncertainty and variations in the estimation of mineral resources and mineral reserves; (vii) delays in or failure to enter into a subsequent agreement with Fresnillo with respect to the sulphide mineral resource at the Camino Rojo Project and to obtain the necessary regulatory approvals related thereto; (viii) health, safety and environmental risks; (ix) success of exploration, development and operation activities; (x) risks relating to foreign operations and expropriation or nationalization of mining operations; (xi) delays in obtaining or the failure to obtain governmental permits, or non-compliance with permits; (xii) delays in getting access from surface rights owners; (xiii) uncertainty in estimates of production, capital and operating costs and potential production and cost overruns; (xiv) the impact of Panamanian or Mexican laws regarding foreign investment; (xv) the fluctuating price of gold and silver and exchange rates; (xvi) assessments by taxation authorities in multiple jurisdictions; (xvii) uncertainties related to titles to mineral properties; (xviii) the Company’s ability to identify, complete and successfully integrate acquisitions; (xix) volatility in the market price of the Company’s securities; (xx) risks relating to the effects of the novel coronavirus (“COVID-19”) on the Company and (xxi) risks associated with executing the Company’s objectives and strategies.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
This list is not exhaustive of the factors that may affect any of the Company’s forward-looking statements. Although the Company believes its expectations are based upon reasonable assumptions and have attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. See the section entitled “Risk Factors” below, and in the section entitled “Risk Factors” in the Company’s annual information form dated as of March 23, 2020 for the financial year ended December 31, 2019 (the “Annual Information Form”), for additional risk factors that could cause results to differ materially from forward-looking statements.
Investors are cautioned not to put undue reliance on forward-looking statements. The forward-looking statements contained in this Prospectus and the documents incorporated by reference herein are made as of the date of such documents only and, accordingly, are subject to change after such date. The Company disclaims any intent or obligation to update publicly or otherwise revise any forward-looking statements or the foregoing list of assumptions or factors, whether as a result of new information, future events or otherwise, except in accordance with applicable securities laws. Investors are urged to read the Company’s filings with Canadian securities regulatory agencies, which can be viewed online under the Company’s profile on the System for Electronic Document Analysis and Retrieval (“SEDAR”) at www.sedar.com and the Company’s documents filed with, or furnished to, the SEC, which are available through the SEC’s Electronic Data Gathering and Retrieval System (“EDGAR”) at www.sec.gov.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
| V. | DISCUSSION OF OPERATIONS |
PROJECT DESCRIPTION
The Camino Rojo Project is a gold-silver-lead-zinc deposit located in the Municipality of Mazapil, State of Zacatecas, Mexico near the village of San Tiburcio. The project lies 190 kilometres (“km”) northeast of the city of Zacatecas, 48 km south-southwest of the town of Concepción del Oro, Zacatecas, and 54 km south-southeast of Newmont’s Peñasquito mine.
The Camino Rojo property consists of seven concessions held by Minera Camino Rojo S.A. de C.V. (“Minera Camino Rojo”), a wholly-owned subsidiary of Orla, covering in aggregate 163,129 ha, with one concession expiring in 2057 and the remaining seven expiring in 2058. As part of the requirements to maintain the concessions in good standing, bi-annual fees must be paid based upon a per-hectare escalating fee, work expenditures must be incurred in amounts determined on the basis of concession size and age, and applicable environmental regulations must be respected.
Pursuant to the agreement (the “Camino Agreement”) whereby Orla acquired the Camino Rojo Project from Goldcorp Inc. (“Goldcorp”, which was subsequently acquired by Newmont), Goldcorp was granted a right to a 2% net smelter returns (“NSR”) royalty on all metal production from the Camino Rojo Project, except for metals produced under the sulphide joint venture option stipulated in the Camino Agreement. On October 29, 2020, the 2% NSR royalty that pertains to oxide material was acquired by Maverix Metals Inc. (“Maverix”). A 0.5% royalty is also payable to the Mexican government as an extraordinary mining duty, mandated by federal law, and applies to precious metal production from all mining concessions, regardless of owner or other royalty encumbrances. A special mining duty of 7.5% is also payable to the Mexican government on income derived from mineral production.
Orla is the operator of the Camino Rojo Project and has full rights to explore, evaluate, and exploit the property. If a sulphide project is defined through a positive pre-feasibility study outlining one of the development scenarios A or B below, Newmont may, at its option, enter into a joint venture for the purpose of future exploration, advancement, construction, and exploitation of the sulphide project.
| • | Scenario A: A sulphide project where material from the Camino Rojo Project is processed using the existing infrastructure of the Peñasquito mine, mill and concentrator facilities. In such circumstances, the sulphide project would be operated by Newmont, who would earn a 70% interest in the sulphide project, with Orla owning 30%. |
| • | Scenario B: A standalone sulphide project with a mine plan containing at least 500 million tonnes of proven and probable mineral reserves using standalone facilities not associated with the Peñasquito mine. Under this scenario, the sulphide project would be operated by Newmont, who would earn a 60% interest in the sulphide project, with Orla owning 40%. |
Following the exercise of its option, if Newmont elects to sell its portion of the sulphide project, in whole or in part, then Orla would retain a right of first refusal on the sale of the sulphide project.
On December 21, 2020, Orla announced that it had completed the Layback Agreement with Fresnillo, granting Orla the right to expand the Camino Rojo oxide pit onto 21.8 ha of Fresnillo’s 782 ha “Guachichil D1” mineral concessions, located immediately to the north of Orla’s property. The Layback Agreement is only with respect to the portion of the heap leach material included in the mineral reserve. As such, any potential development of the Camino Rojo Project that includes an open pit encompassing the entire mineral resource estimate would be dependent on an additional agreement with Fresnillo (or any potential subsequent owner of the mineral titles).
Fresnillo controls surface rights needed for exploration and mining on the Guachichil D1 mineral concession. Pursuant to the Layback Agreement, 27.5 ha of surface rights controlled by Fresnillo will be acquired by Minera Camino Rojo to mine on a portion of the Guachichil D1 mineral concession that covers the area outside of the Orla concession required for the Project as defined in the January 2021 Camino Rojo Feasibility Study.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
The Company submitted MIA and CUS permit applications to SEMARNAT in August 2019, for the construction and operation of an open pit mine as per the project described in the previous technical report for the Camino Rojo Project entitled “Feasibility Study, NI 43-101 Technical Report on the Camino Rojo Gold Project Municipality of Mazapil, Zacatecas, Mexico” dated effective June 25, 2019 (the “2019 Technical Report”).
Federal environmental authorities approved the CUS permit in December 2019, Minera Camino Rojo made the requisite payment to the National Forestry Commission on January 23, 2020. Minera Camino Rojo received the CUS permit on February 6, 2020, allowing mine development and operation affecting 816.25 ha.
Federal regulations require staged postings of a bond or financial guarantee for the estimated cost of reclamation, proportional to the pending reclamation work created by the project in each development phase, as determined by a technical economic study. On November 11, 2020, Minera Camino Rojo submitted the required first stage reclamation bond of $89,451,775 Pesos (approximately US$4.5 million) which was accepted by the Federal Treasury, with formal notice given to the Procuraduria Federal de Proteccion al Ambiente on November 13, 2020. All MIA and CUS permit conditions have been satisfied, allowing for site activities to commence for the Project described in the 2019 Technical Report.
Minera Camino Rojo currently has all major permits required for construction and operation of the Project described in the 2019 Technical Report. Certain permits, including authorization from the Secretaría de la Defensa Nacional to use and store explosives, cannot be obtained before facilities are built, and routine surface water management permits from Comisión Nacional del Agua, required for constructing surface drainage diversion works and road crossings, are in process. Receipt of these permits is not expected to affect project timelines. There are no impediments to construction, mining, and processing activities for the already authorized project while permit modifications for the project described above are in the application process.
JANUARY 2021 FEASIBILITY STUDY
The January 2021 Camino Rojo Feasibility Study considers open pit mining of 67.4 million tonnes of oxide and transitional ore at a rate of 18,000 tonnes per day. Ore from the pit will be crushed to 80% passing 28 mm, conveyor stacked onto a heap leach pad and leached using a low concentration sodium cyanide solution. Pregnant solution from the heap leach will be processed in a Merrill-Crowe recovery plant where gold and silver will be precipitated and doré will be produced. The site’s proximity to infrastructure, low stripping ratio, compact footprint, and flat pad location all contribute to the Project’s simplicity and low estimated AISC of $543 per ounce of gold.
The technical report for the 2021 Feasibility Study entitled “Unconstrained Feasibility Study NI 43-101 Technical Report on the Camino Rojo Gold Project – Municipality of Mazapil, Zacatecas, Mexico” dated January 11, 2021 (“January 2021 Feasibility Study”) was prepared by a team of independent industry experts led by Kappes Cassiday and Associates (“KCA”) and supported by Independent Mining Consultants (“IMC”), Resource Geosciences Incorporated (“RGI”), John Ward Groundwater Consultant, Barranca Group LLC, Piteau Associates Engineering Ltd. and HydroGeoLogica Inc (“HGL”).
The January 2021 Feasibility Study incorporates geological, assay, engineering, metallurgical, geotechnical, environmental, and hydrogeological information collected by Orla and previous owners since 2007, including 370,566 metres of drilling in 911 holes. Predicted average gold recoveries of 62% are based on results from 85 column tests.
Operating costs are based on contract mining with all other mine components being owned and operated by Orla. Approximately 58% of capital costs are based on purchase orders and updated firm proposals for equipment, material, and construction contracts from ongoing EPCM and site activities. For capital items not yet purchased, budgetary supplier quotes were used.
The proposed mine is located three kilometres from a paved four-lane highway and approximately 190 kilometres from the city of Zacatecas. The area is flat and there are no known social or environmental impediments to mining at this time. There are no residents within the area of development. The town of San Tiburcio is located four kilometres to the east of the development. Orla has a Collaboration and Social Responsibility Agreement with Ejido San Tiburcio and a 30-year temporary occupation right with an expropriation right over the 2,497 hectares covering the portion of the proposed pit that is on the Orla concession and the location of all infrastructure. Subject to receipt of approval from COFECE and subsequent transfer of surface rights, the Layback Agreement provides reasonable expectation that all surface and mineral rights required to develop the Project as described in the January 2021 Feasibility Study will be secured. Orla has sufficient water concessions and existing wells produce in-excess of the average 24 litres per second of water required for the Project.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
The key permits and requirements for mining and exploration activities in Mexico are the Manifesto de Impacto Ambiental (“MIA”) and the CUS, supported by an Estudio Tecnico Justificativo. Orla received the CUS in January 2020 and the MIA in August 2020 for the project constrained by the Orla concession boundary that is described in the 2019 Feasibility Study. Permit amendments will be required for the larger project described in the January 2021 Feasibility Study, including the expanded pit and the eventual increase in the heap leach and mine waste dump. There are no impediments to construction, mining, and processing activities on the Orla concession while these permit modifications are in the application process.
Orla has an active community and social program in San Tiburcio and other nearby communities of El Berrendo and San Francisco de los Quijano.
The January 2021 Feasibility Study highlights a 54% increase in contained gold mineral reserves and a 3.5-year extension to the mine life of the Camino Rojo Project over the January 2019 Feasibility Study. The Camino Rojo Project is currently in construction. The estimated Project after-tax net present value (“NPV”) (5% discount rate) is $452 million with an after-tax internal rate of return (“IRR”) of 62% at a gold price of $1,600 per ounce and silver price of $20 per ounce.
The January 2021 Feasibility Study reflects some of the benefits resulting from a pit expansion made possible through the completion of the layback agreement with Fresnillo announced on December 21, 2020 (the “Layback Agreement”). Closing of the Layback Agreement was subject to receipt of Mexican antitrust approval from the Federal Competition Commission (“COFECE”), which was received on February 19, 2021.
The Layback Agreement allows Orla to expand the north wall of the oxide pit onto the Fresnillo property immediately adjacent to Orla’s mineral concession. This expansion will increase oxide ore available for extraction on Orla’s property below the pit outlined in the previous feasibility study dated June 25, 2019 (“2019 Feasibility Study”). The increase in mineral reserves in the January 2021 Feasibility Study is derived from the conversion of measured and indicated mineral resources located solely on Orla’s concession. There has been no change to the mineral resource estimate dated effective June 7, 2019.
The Layback Agreement also provides Orla with the right to mine from Fresnillo’s mineral concession, and recover for Orla’s account, all oxide and transitional material amenable to heap leaching that is within an expanded open pit. Results from holes drilled on Fresnillo’s concession in close proximity to the most northern holes on the Orla property appear to be consistent with projections of the geological and oxidation models created from Orla’s data and assay results. Additional work is required to bring material on the Fresnillo concession to the measured and indicated mineral resource categories. Therefore, in the January 2021 Feasibility Study, all material to be mined on the Fresnillo concession is classified as waste. Upon the completion of a confirmatory drill program on Fresnillo’s concession by Orla, and integration of Fresnillo’s drill database, a subsequent mineral reserve update is expected which would include all economic oxide and transitional material from the expanded pit.
The January 2021 Feasibility Study continues to support a technically simple open pit mine and heap leach operation but improves upon the economics outlined in the 2019 Feasibility Study. The main notable physical changes from the 2019 Feasibility Study are an increase in the size of the open pit, heap leach pad, and mine waste dump as a result of the Layback Agreement, all of which were anticipated in the initial design. The majority of the infrastructure will remain as presented in the 2019 Feasibility Study and as being currently constructed.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
The following table presents the key assumptions and detailed results of the January 2021 Feasibility Study:
Summary of Key Assumptions and Economics of the Camino Rojo Feasibility Study
Production Data | | Units | | Values |
Life of Mine | | years | | 10.4 |
Mine Throughput | | tonnes/day | | 18,000 |
Mine Throughput | | tonnes/year | | 6,570,000 |
Total Tonnes to Crusher | | tonnes | | 67,363,000 |
Gold Grade (Average) | | g/t | | 0.73 |
Silver Grade (Average) | | g/t | | 14.5 |
Contained Gold | | ounces | | 1,588,000 |
Contained Silver | | ounces | | 31,506,000 |
Average Gold Recovery | | % | | 62% |
Average Silver Recovery | | % | | 20% |
Average Annual Gold Production | | ounces | | 94,000 |
Average Annual Silver Production | | ounces | | 597,000 |
Total Gold Produced | | ounces | | 980,000 |
Total Silver Produced | | ounces | | 6,189,000 |
Life of Mine Strip Ratio | | waste : ore | | 0.92 |
Operating Costs (Average LOM) | | | | |
Mining (mined) | | /tonne mined | | $1.75 |
Mining (processed) | | /tonne processed | | $3.37 |
Processing & Support | | /tonne processed | | $3.20 |
General & Administrative | | /tonne processed | | $1.60 |
Total Operating Cost | | /tonne processed | | $8.17 |
Total Cash Cost (net of by-product credits) 1 | | /ounce Au | | $490 |
AISC 1 | | /ounce Au | | $543 |
Capital Costs (Excluding value added tax) | | | | |
Initial Capital 2 | | US$ million | | $134 |
Life of Mine Sustaining Capital | | US$ million | | $24 |
Life of Mine Capital | | US$ million | | $158 |
Working Capital & Initial Fills | | US$ million | | $10 |
Closure Costs | | US$ million | | $29 |
Financial Evaluation | | | | |
Gold Price Assumption | | $/ounce | | $1,600 |
Silver Price Assumption | | $/ounce | | $20 |
Average Annual Cashflow (Pre-Tax) | | US$ million | | $106 |
Average Annual Cashflow (After-Tax) | | US$ million | | $79 |
IRR, Pre-Tax | | % | | 82% |
IRR, After-Tax | | % | | 62% |
NPV @ 5% (Pre-Tax) | | US$ million | | $668 |
NPV @ 5% (After-Tax) | | US$ million | | $452 |
Pay-Back Period (After-Tax) | | years | | 1.5 |
Notes
| 1 | Total cash cost and AISC are non-GAAP measures and are net of silver credits and includes royalties payable. See reference below regarding non-GAAP measures. January 2021 Feasibility Study economics include a 2% net smelter royalty (“NSR”) and assumes a USD:MXN exchange rate of 19.3. |
| 2 | Includes sunk capital costs to date. |
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
Project Economics Sensitivities to Gold Price
Gold Price ($/oz) | | $1,250 | | $1,425 | | $1,600 | | $1,775 | | $1,950 |
After-tax NPV 5% ($M) | | $288 | | $370 | | $452 | | $534 | | $616 |
After-tax IRR (%) | | 44% | | 53% | | 62% | | 70% | | 78% |
Payback (years) | | 2.0 | | 1.7 | | 1.5 | | 1.3 | | 1.2 |
OPPORTUNITIES
In the January 2021 Feasibility Study, all material mined on the Fresnillo concession is currently classified as waste. The Layback Agreement will provide Orla the right to mine and recover gold from heap leachable material located on the Fresnillo concession within the expanded pit. Further work is required to bring mineralized material on the Fresnillo concession into the measured and indicated mineral resource categories so that it can be included in an updated mine plan and mineral reserve estimate. While the overall open pit will be limited by the Layback Agreement and will not increase in size, any material from the Fresnillo concession located within the layback area that can be economically processed will improve overall project economics.
The January 2021 Feasibility Study only considers oxide and transitional material as testing shows that the heap leaching method cannot economically recover gold from the sulphide material. Orla is actively working on studies to investigate economic opportunities that may exist within the 7.3 million ounces of gold contained within the sulphide measured and indicated mineral resource peripheral to and below the oxides.
Orla has title to mineral concessions covering a large area around the Camino Rojo deposit. While overburden can make exploration challenging, the discovery in 2007 of mineralization that is incorporated within the January 2021 Feasibility Study and mineral resource estimate demonstrates that shallow cover can hide very large near-surface deposits. Additional oxide material in the vicinity of the planned development would leverage the mine infrastructure outlined in the January 2021 Feasibility Study. Any additional sulphide material could add to the long-term potential of the property.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
CAPITAL AND OPERATING COSTS
Initial capital expenditures or pre-production capital for the Camino Rojo Project is estimated at $134 million. Camino Rojo benefits from flat terrain and simple infrastructure, limiting the amount of earthworks required during construction. Total capital for the life of the Project, including sustaining and working capital is estimated at $167 million. Table 4 provides a breakdown of the capital costs for the Project. All costs related to Project development, including those already spent as of the date of this Feasibility Study, are included in the total initial capital costs.
The total capital cost estimate excludes payments to Fresnillo as part of the Layback Agreement as they are considered property purchase payments. Pursuant to the Layback Agreement, an aggregate US$62.8 million is payable to Fresnillo through a staged payment schedule.
Capital Cost Summary (excl. value added tax)
Description | | Cost (US$ ‘000s) | |
Pre-Production Capital Costs | | $ | 91,552 | |
Indirect Costs | | $ | 2,181 | |
Other Owner’s Costs | | $ | 15,904 | |
EPCM | | $ | 8,020 | |
Contingency | | $ | 13,822 | |
Mining Contractor Mobilization & Preproduction | | $ | 2,577 | |
Total Initial Capital | | $ | 134,056 | |
Working Capital & Initial Fills | | $ | 9,845 | |
Sustaining Capital – Mine & Process | | $ | 23,565 | |
Total LOM Capital (incl. working capital) | | $ | 167,467 | |
Closure Costs | | $ | 28,581 | |
In the 2019 Feasibility Study, project economics assumed a two-year construction period and all cash flows were discounted to year -2. However, Orla has already begun construction activities and at February 28, 2021, has committed $96 million in total capital. The Company estimates that there are approximately ten months remaining until first production, placing the project within year -1 of the life of mine plan. In the January 2021 Feasibility Study, NPV is discounted to year -1 and those costs already expended are included but not discounted. This provides the most reasonable and accurate estimate of the project’s NPV and IRR based on the date of the study within the context of the life of mine plan.
The average life of mine operating cost for the Project is estimated at $8.17 per tonne of ore processed. Operating costs were estimated from first principles with project specific staffing, quoted contract mining costs, unit consumptions of materials, supplies, power, water, and delivered supply costs being considered.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
The following table summarizes the different components of the operating costs:
Life of Mine Operating Cost Summary
| | LOM Costs | | | LOM Costs | |
Description | | $/t | | | $/oz | |
Mining | | $ | 3.37 | | | $ | 232 | |
Process | | $ | 3.20 | | | $ | 220 | |
G&A | | $ | 1.60 | | | $ | 110 | |
Total Operating Costs | | $ | 8.17 | | | $ | 562 | |
Refining & Transport | | | | | | $ | 9 | |
Royalties | | | | | | $ | 43 | |
By-product Credits | | | | | | $ | (124 | ) |
Total Cash Costs (net of by products) 1 | | | | | | $ | 490 | |
Sustaining Capital | | | | | | $ | 24 | |
Reclamation | | | | | | $ | 29 | |
AISC 1 | | | | | | $ | 543 | |
Notes
| 1 | Total cash cost and AISC are non-GAAP measures and are net of silver credits and includes royalties payable. See reference below regarding non-GAAP measures. |
The estimated capital and operating costs are considered to have an accuracy of +/-15%.
NEXT STEPS
Orla will begin working on a Change of Land Use permit amendment for the expanded pit and other permitting requirements for the increased tonnes planned to be mined as a result of the Layback Agreement.
Additional work is required to bring material on the Fresnillo concession to the measured and indicated mineral resource category which will then facilitate a mineral reserve update. Work required includes an estimated 2,500 metres of drilling, detailed QA/QC, and integration of Orla’s geological and resource models with Fresnillo’s drill data. We expect to complete the work required by the end of the fourth quarter of 2021.
MINERAL RESERVES
Camino Rojo comprises intrusive related, sedimentary strata hosted, polymetallic gold, silver, arsenic, zinc, and lead mineralization. The mineralized zones correspond to zones of sheeted sulphidic veins and veinlet networks, creating a bulk-mineable style of gold mineralization. Mineralization is almost completely oxidized to a depth of approximately 120 metres and then variably oxidized below (transitional to sulphide). The mineral resource estimate was divided into oxide, high and low transitional and sulphide material. Only the oxide and transitional material are considered in the January 2021 Feasibility Study for heap leach extraction.
The mineral reserve estimate for Camino Rojo is based on an open pit mine plan and mine production schedule developed by IMC. All mineral reserves are located on Orla’s concessions. A portion of the waste mining will be conducted on land controlled by Fresnillo as per the Layback Agreement between Fresnillo and Orla.
The following table presents the mineral reserve estimation for the Camino Rojo Oxide Project. Proven and probable mineral reserves amount to 67.4 million tonnes at 0.73 g/t gold and 14.5 g/t silver for 1.59 million contained gold ounces and 31.5 million contained silver ounces. The mineral reserve was estimated based on a gold price of $1,250 per ounce and a silver price of $17.00 per ounce. Measured mineral resource in the mine production schedule was converted to proven mineral reserve and indicated mineral resource in the schedule was converted to probable mineral reserve.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
Camino Rojo Mineral Reserves
| | 000’s | | | Gold | | | Silver | | | Gold | | | Silver | |
Reserve Category | | tonnes | | | (g/t) | | | (g/t) | | | (koz) | | | (koz) | |
Proven Mineral Reserve | | | 18,067 | | | | 0.80 | | | | 15.4 | | | | 466 | | | | 8,951 | |
Probable Mineral Reserve | | | 49,296 | | | | 0.71 | | | | 14.2 | | | | 1,123 | | | | 22,555 | |
Total Proven & Probable Reserve | | | 67,363 | | | | 0.73 | | | | 14.5 | | | | 1,588 | | | | 31,506 | |
Notes:
| 1 | The Mineral Reserve estimate has an effective date of January 11, 2021 and was prepared using the CIM Definition Standards. |
| 2. | Columns may not sum exactly due to rounding. |
| 3 | Mineral Reserves are based on prices of $1250/oz gold and $17/oz silver. |
| 4 | Mineral Reserves are based on NSR cut-offs that vary by time period to balance mine and plant production capacities. They range from a low of $4.93/t to a high of $12.00/t. |
| 5 | NSR value for leach material is as follows: |
Kp Oxide: NSR ($/t) = 27.37 x gold (g/t) + 0.053 x silver (g/t), based on gold recovery of 70% and silver recovery of 11%
Ki Oxide: NSR ($/t) = 21.90 x gold (g/t) + 0.073 x silver (g/t), based on gold recovery of 56% and silver recovery of 15%
Tran-Hi: NSR ($/t) = 23.46 x gold (g/t) + 0.131 x silver (g/t), based on gold recovery of 60% and silver recovery of 27%
Tran-Lo: NSR ($/t) = 15.64 x gold (g/t) + 0.165 x silver (g/t), based on gold recovery of 40% and silver recovery of 34%
| 6 | Please see Forward-Looking Statements regarding mineral resource and mineral reserve estimates |
Approximately two-thirds of the mineral reserves are within the currently permitted mine plan. The remaining portion will require a CUS and related permit amendments for an expanded pit, and subsequent transfer of surface rights.
MINERAL RESOURCES
No update to the mineral resource estimate was made as part of the January 2021 Feasibility Study. The mineral resource estimate dated June 7, 2019 remains current. Mineral resources are divided between oxide and transitional material that could possibly be extracted by open pit mine and processed in a heap leach operation (“Leach Resource”) and sulphide material that could possibly be extracted by open pit and processed in a mill (“Mill Resource”). For the Mill Resource, estimates are made for contained gold, silver, lead and zinc. As lead and zinc would not be recovered in a heap leach operation, only gold and silver were estimated for the Leach Resource. The following two tables summarize the mineral resource estimate.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
Mineral Resource Estimate – Gold & Silver
| | 000’s | | | Gold | | | Silver | | | Gold | | | Silver | |
Resource Type by Category | | tonnes | | | (g/t) | | | (g/t) | | | (koz) | | | (koz) | |
Leach Resource: | | | | | | | | | | | | | | | | | | | | |
Measured Mineral Resource | | | 19,391 | | | | 0.77 | | | | 14.9 | | | | 482.3 | | | | 9,305 | |
Indicated Mineral Resource | | | 75,249 | | | | 0.7 | | | | 12.2 | | | | 1,680.70 | | | | 29,471 | |
Meas./Ind. Mineral Resource | | | 94,640 | | | | 0.71 | | | | 12.7 | | | | 2,163.00 | | | | 38,776 | |
Inferred Mineral Resource | | | 4,355 | | | | 0.86 | | | | 5.6 | | | | 119.8 | | | | 805 | |
| | | | | | | | | | | | | | | | | | | | |
Mill Resource: | | | | | | | | | | | | | | | | | | | | |
Measured Mineral Resource | | | 3,358 | | | | 0.69 | | | | 9.2 | | | | 74.2 | | | | 997 | |
Indicated Mineral Resource | | | 255,445 | | | | 0.88 | | | | 7.4 | | | | 7,221.40 | | | | 60,606 | |
Meas./Ind. Mineral Resource | | | 258,803 | | | | 0.88 | | | | 7.4 | | | | 7,295.60 | | | | 61,603 | |
Inferred Mineral Resource | | | 56,564 | | | | 0.87 | | | | 7.5 | | | | 1,576.90 | | | | 13,713 | |
| | | | | | | | | | | | | | | | | | | | |
Total Mineral Resource | | | | | | | | | | | | | | | | | | | | |
Measured Mineral Resource | | | 22,749 | | | | 0.76 | | | | 14.1 | | | | 556.5 | | | | 10,302 | |
Indicated Mineral Resource | | | 330,694 | | | | 0.84 | | | | 8.5 | | | | 8,902.10 | | | | 90,078 | |
Meas./Ind. Mineral Resource | | | 353,443 | | | | 0.83 | | | | 8.8 | | | | 9,458.60 | | | | 100,379 | |
Inferred Mineral Resource | | | 60,919 | | | | 0.87 | | | | 7.4 | | | | 1,696.70 | | | | 14,518 | |
Mineral Resource Estimate – Zinc & Lead
| | 000’s | | | Lead | | | Zinc | | | Lead | | | Zinc | |
Resource Type by Category | | tonnes | | | (%) | | | (%) | | | (M lbs) | | | (M lbs) | |
Mill Resource: | | | | | | | | | | | | | | | | | | | | |
Measured Mineral Resource | | | 3,358 | | | | 0.13 | | | | 0.38 | | | | 9.3 | | | | 28.2 | |
Indicated Mineral Resource | | | 255,445 | | | | 0.07 | | | | 0.26 | | | | 404.3 | | | | 1,468.70 | |
Meas./Ind. Mineral Resource | | | 258,803 | | | | 0.07 | | | | 0.26 | | | | 413.6 | | | | 1,496.80 | |
Inferred Mineral Resource | | | 56,564 | | | | 0.05 | | | | 0.23 | | | | 63.1 | | | | 290.4 | |
Notes:
| 1. | The mineral resource has an effective date of June 7, 2019. The mineral resources are classified in accordance with the CIM Definition Standards in accordance with the disclosure requirement of NI 43-101. |
| 2. | Columns may not sum exactly due to rounding. |
| 3. | Mineral resources that are not mineral reserves do not have demonstrated economic viability. |
| 4. | Mineral resources for leach material are based on prices of $1,400/oz gold and $20/oz silver. |
| 5. | Mineral resources for mill material are based on prices of $1,400/oz gold, $20/oz silver, $1.05/lb lead, and $1.20/lb zinc. |
| 6. | Mineral resources are based on net smelter return cut-off of $4.73/t for leach material and $13.71/t for mill material. |
| 7. | Includes 2% royalty and an USD:MXN exchange rate of 19.3. |
| 8. | Operating costs for Leach resource - mining $1.65/t mined; process $3.41/t processed; G&A $1.32/t processed; Operating costs for Mill resource - mining $1.65/t mined; process $12.50/t processed; G&A $1.20/t processed. |
| 9. | Leach resource payable �� Au 100%; Ag 100%; Mill resource payable – Au 95%, Ag 95%, Pb 95%, Zn 85%. |
| 10. | Leach resource refining costs - Au $5.00/oz; Ag $0.50/oz; Mill resource refining costs - Au $1.00/oz; Ag $1.50/oz; Pb $0.194/lb; Zn $0.219/lb. |
| 11. | The mineral resource estimate assumes that the floating pit cone used to demonstrate reasonable prospects for eventual economic extraction extends onto land held by the Fresnillo. Any potential development of the Camino Rojo Project that includes an open pit encompassing the entire mineral resource estimate would be dependent on obtaining an agreement with Fresnillo (or subsequent owner). |
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
| 12. | Mineral resources are inclusive of mineral reserves. |
| 13. | An Inferred Mineral Resource has a lower level of confidence than that applying to an indicated mineral resource and must not be converted to a mineral reserve. It is reasonably expected that the majority of inferred mineral resources could be upgraded to indicated mineral resources with continued exploration. |
| 14. | See Forward-Looking Statements below regarding mineral resource and mineral reserve estimates. Also refer to the Camino Rojo Technical Report dated June 25, 2019 for further details regarding the key assumptions, parameters, and methods used in the mineral resource estimate (including risk factors). |
All the mineralization comprised in the mineral resource estimate with respect to the Project are contained on mineral titles controlled by Orla. However, the mineral resource estimate assumes that the north wall of the conceptual floating pit cone used to demonstrate reasonable prospects for eventual economic extraction extends onto lands where mineral title is held by Fresnillo, and that waste would be mined on Fresnillo’s mineral titles. The Layback Agreement allows Orla to extend the north pit wall onto Fresnillo’s mineral titles to gain access to the oxide and transitional heap leachable mineral resources at depth on Orla’s mineral property.
The existing agreement with Fresnillo is only with respect to the portion of the heap leach material included in the mineral reserve. As such, any potential development of the Camino Rojo property that includes an open pit encompassing the Mill Resource included in the mineral resource estimate is dependent on entering into an additional agreement with Fresnillo (or any potential subsequent owner of the mineral titles). It is estimated that approximately two-thirds of the Mill Resource estimate and one quarter of the Leach Resource are dependent on an additional agreement being entered into with Fresnillo. The Leach Resource dependent on the additional agreement is mainly comprised of less oxidized transitional material with the lowest predicted heap-leach recoveries. The mineral resource estimate has been prepared based on the Qualified Person’s reasoned judgment, in accordance with Canadian Institute of Mining, Metallurgy and Petroleum (“CIM”) Best Practices Guidelines and his professional standards of competence, that there is a reasonable expectation that all necessary permits, agreements and approvals will be obtained and maintained, including the additional agreement with Fresnillo to allow mining of waste material on its mineral concessions. In particular, when determining the prospects for eventual economic extraction, consideration was given to industry practice, and a time frame of 10-15 years.
Delays in, or failure to obtain, an additional agreement with Fresnillo would affect the development of a significant portion of the mineral resources of the Camino Rojo property that are not included in the January 2021 Feasibility Study mine plan, in particular by limiting access to significant mineralized material at depth. There can be no assurance that Orla will be able to negotiate such additional agreement on terms that are satisfactory to Orla or that there will not be delays in obtaining the necessary agreement.
PERMITTING
Exploration and mining activities in Mexico are subject to control by SEMARNAT, the federal government department which has authority over the two principal permits: (1) the MIA, accompanied by a Risk Study, and (2) a CUS permit accompanied by an ETJ.
We submitted permitting documents to SEMARNAT during the third quarter of 2019. We were notified that the CUS was accepted on December 9, 2019 and we paid the required fees on January 17, 2020. On August 11, 2020, the Company received approval of its MIA.
The approval of the MIA was conditional upon Orla meeting certain customary conditions and standard requirements. One of the conditions was the completion of a Technical Economic Study which was submitted to SEMARNAT on August 27, 2020. On November 12, 2020 Orla placed $2.2 million cash collateral pursuant to the environmental bonding requirements. This cash collateral amounts to 50% of the $4.4 million bonding obligation with SEMARNAT. All other conditions of the MIA have been met or submitted to SEMARNAT.
The Company has received the two principal permits necessary for commencement of construction activities at Camino Rojo, and in December 2020 the Company commenced construction.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
PROJECT RISKS
The Camino Rojo Project is subject to similar risks as comparable project. However, Orla believes it has mitigated many of those risks by early engagement with the stakeholders involved in the Project, including government permitting agencies, local land holders, including the Ejidos and Fresnillo, and the advanced stage of activities around mine construction and long-lead time mine equipment. Purchase and construction of required process and other infrastructure is already underway under the plan outlined in the 2019 Feasibility Study. Permits for the Project currently being built were received and the expanded Project requires comparatively minor permit additions and amendments. Construction and operation of the permitted portion of the Project can continue unaffected as additional permitting requirements are met.
In recent years, some mining projects in Mexico have suffered development delays or production stoppages as a result of community interference. Orla has an active community relations and social program and strives to maintain constructive relationships with local communities. Management believes that maintaining a robust community relations program can reduce and mitigate social risks and improve overall operational sustainability.
Under Mexico’s current COVID-19 legislation, mining and construction are permitted economic activities and the Camino Rojo Project site is operating in compliance with the Mexican Health Authority and Company requirements. Orla has implemented a strict COVID-19 protocol, including rigorous screening and testing programs to support the health of Orla’s employees, contractors and local communities. The Company is closely monitoring the potential impacts from the pandemic on areas including equipment delivery and logistics, materials for construction and operation, other necessities, as well as construction costs and schedule, and community and government relations. While some delays to construction and permit amendments may occur due to the COVID-19 pandemic, Orla has taken steps to minimize potential impacts to the overall Project including additional costs related to COVID-19 safety measures.
The Feasibility Study and the Camino Rojo Project may be subject to legal, political, environmental or other risks that could materially affect the development of the Camino Rojo Project which are unknown at this time but could materialize in the future.
DATA VERIFICATION
The sampling data used for the mineral reserve and mineral resource estimate was verified by IMC and RGI. A substantial portion of the database was compared with original assay certificates. There were no limitations on the verification process. IMC and RGI are of the opinion that the database is acceptable for the purpose of this January 2021 Feasibility Study, including the mineral reserve and mineral resource estimation. The Orla sampling data used for the mineral reserve and mineral resource estimate was verified by RGI.
KCA checked the metallurgical test procedures and results to ensure they met industry standards. Metallurgical sample locations were reviewed to ensure that there was material from throughout the resource area and that samples were reasonably representative of the material planned to be processed so as to support the selected process method and assumptions regarding recoveries and costs. Additional data verification information can be found in the Camino Rojo Technical Report dated June 25, 2019 and has been incorporated in the January 2021 Feasibility Study filed on February 9, 2021 on SEDAR and furnished on EDGAR. The 2021 Feasibility Study technical report is intended to be read as a whole, and sections should not be read or relied upon out of context.
QUALIFIED PERSONS
The 2021 Feasibility Study was overseen by KCA of Reno, Nevada. The mineral resource and mineral reserve estimates were conducted by IMC of Tucson, Arizona, under the direction of Michael G. Hester, FAusIMM. Mr. Hester was also responsible for the mining components of the updated Feasibility Study. KCA, under the direction of Carl Defilippi, RM SME was responsible for the metallurgy, process, general and administration and economic components of the updated Feasibility Study. Matthew Gray, Ph.D., C.P.G. (AIPG), of Resource Geosciences Incorporated of Rio Rico, AZ was responsible for the property, geology, and environmental components of the updated Feasibility Study. John Ward, Registered Geologist (AZ, CA), C.P.G. (AIPG) was responsible for the hydrogeology model. Each of Messrs. Hester, Defilippi, Gray and Ward is a Qualified Person for their respective sections of the updated Feasibility Study and each of whom is Independent of Orla under the definitions of National Instrument 43-101 (“NI 43-101”). An independent technical report prepared in accordance with the requirements of NI 43-101 is available under Orla’s profile on SEDAR and EDGAR.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
Andrew Cormier, P.Eng., Orla’s Chief Operating Officer, has reviewed and verified all technical and scientific information contained in MD&A and is a Qualified Person within the meaning of NI 43-101.
CAMINO ROJO OXIDE PROJECT CONSTRUCTION UPDATE
As of the date of this MD&A, detailed engineering of the project described in the 2019 Feasibility Study is 94% complete and procurement is 93% complete.
Minera Camino Rojo commenced the start of earthworks on November 26, 2020 and through February 28, 2021, a total of 123 ha had been cleared for construction activities with over 214,634 cubic meters of topsoil removed and stockpiled. A total of 9,505 plants was rescued as part of flora and fauna relocation, and as of the date of this MD&A, the 44 km, 33-kilovolt powerline was 73% complete. Equipment deliveries to site commenced in November 2020.
The mining contract is being finalized and is expected to be in place in the second quarter of 2021.
First gold production is planned for late 2021.
CAMINO ROJO PROJECT LOAN
In December 2019, the Company entered into a loan agreement with Trinity Capital Partners Corporation (“Trinity Capital”) and certain other lenders with respect to a credit debt facility of $125 million for the development of the Camino Rojo Oxide Gold Project (the “Credit Facility”). The Credit Facility was arranged by Trinity Capital and includes a syndicate of lenders led by Agnico Eagle Mines Limited (“Agnico Eagle”), Pierre Lassonde, and Trinity Capital.
The Credit Facility provides a total of $125 million to the Company, available in three tranches. The first tranche of $25 million was drawn down by the Company on December 18, 2019 upon execution of the definitive loan documentation. The second tranche of $50 million was drawn down on October 30, 2020. The third and final tranche provides $50 million and must be drawn within six months of the second tranche. There is no guarantee that all conditions precedent and covenants will be met in a timely manner and failure to do so could delay or prevent further draws from the Credit Facility in the future.
EXPLORATION
The land package is under-explored and the proximity to the large Camino Rojo mineralized system provides a highly prospective opportunity. Exploration on the project is somewhat challenged due to the presence of a thin alluvial soil and caliche cover impacting geochemical surface expressions, but the potential to discover mineralization is considered excellent.
As well as development-related activities, we continue to conduct a regional exploration program.
Near-Deposit Expansion: A 6,000-metre oriented core drilling program began on the large sulphide resource at the Camino Rojo deposit in the fourth quarter of 2020 to generate additional information regarding the continuity and geometry of the higher-grade mineralization and provide new material for geotechnical and metallurgical studies. 1,960 metres of the drill program were completed in 2020. Assay results are pending for the first holes.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
Regional exploration: Completion of reverse circulation (“RC”) drilling totalling 5,212 metres at Las Miserias, San Tiburcio and Guanamero targets, mechanical trenching totalling 140 metres and geophysical IP surveys over a 233-kilometre line across four target areas. Numerous intermediate composition dykes and encouraging anomalous drill assay results (1.5m at >0.500 ppm Au, or 1.5m at > 50 ppm Ag, or 1.5m at > 1000 ppm Zn) were obtained approximately 7 kilometres to the northeast of the Camino Rojo deposit, along the same NE-SW structural trend interpreted to host the deposit. The most significant new chargeability anomalies were defined at Las Miserias and Hacheros.
Regional exploration continues to field check interpreted targets, consisting of coincident historical geochemical, airborne geophysical and satellite imagery anomalies. Ten areas of alteration of sedimentary strata have been identified, and although no significant geochemical results have been returned from them to date, they are considered of interest as possible distal alteration zones to mineralized areas.
As of the date of this MD&A, Orla has a planned exploration program including:
| • | 2,500 m of core drilling to confirm mineralization on the Fresnillo property that is subject to the Layback Agreement; |
| • | A 6,000 m directional diamond drilling program to test the sulfide zone, over the down plunge extension of the Camino Rojo deposit; and |
| • | continuation of the regional exploration program to discover satellite deposits near the Camino Rojo deposit, including 7,500-metres of RAB reconnaissance drilling to test areas where bedrock is covered by soil and colluvium. The results from the RAB drilling, in combination with 200 line-km of planned IP surveys, will define property exploration targets. |
COMMUNITY AND SOCIAL
We maintain an active community, social relations, and environmental management program. During the quarter, there were no environmental incidents. Community activities during the fourth quarter of 2020 were primarily focused on supporting our local communities and the challenges faced as a result of COVID-19 impacts:
| • | Provided support to the local communities during the COVID-19 pandemic including the donation of food, medical and protective equipment; |
| • | Provided training and educational materials regarding the coronavirus to local communities; |
| • | Continued to provide support to the community in efforts to maintain a doctor assigned to the community. |
At Camino Rojo, the Company is working in collaboration with various local service providers like truck drivers to ensure they have an opportunity to participate in construction activities. An updated database of local services and people available for work has been provided to our contractors as the Company seeks to encourage opportunities for local procurement and employment.
Orla’s community relations team continues to maintain communications with our local communities to understand how the Company can best support them. However, because of COVID-19 protocols which include necessary physical distancing, Orla has reduced direct contact with the local communities as a precautionary measure.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
| B. | CERRO QUEMA PROJECT, PANAMA |
PROJECT DESCRIPTION AND HISTORY
Our 100%-owned Cerro Quema Project is located on the Azuero Peninsula in Los Santos Province, in south western Panama, about 45 kilometres southwest of the city of Chitre and about 190 kilometres southwest of Panama City. The project is at the exploration and development stage for a proposed open pit mine with process by heap leaching. We own the mineral rights as well as the surface rights over the areas of the current mineral resources and mineral reserves, proposed mine development, and the priority drill targets.
The Company owns the surface rights for land required to mine the Cerro Quema mineral reserves and to construct and operate a heap leach facility.
A predecessor company to Orla issued a mineral resource estimate and a Pre-Feasibility Study for Cerro Quema, and an independent technical report entitled “Cerro Quema Project – Pre-Feasibility Study on the La Pava and Quemita Oxide Gold Deposits” dated August 15, 2014 with an effective date of June 30, 2014 (the “Cerro Quema Report”2).
The Cerro Quema Report envisions a standard open pit mine with two pits, one at La Pava and one at Quemita, coupled with a 10,000 tonne per day heap leach facility to extract the gold. The project estimates average head grade of 0.77 g/t Au, crush size of 80% passing minus 50 mm, and an average gold recovery of 86%. This would result in 418,000 ounces of gold production over a 5.3-year mine life.
The Cerro Quema Report, which contains the 2014 mineral resource and mineral reserve estimate and Pre-Feasibility Study, was filed on SEDAR by Pershimco Resources Inc. on August 22, 2014. You can download it from SEDAR at www.sedar.com or from the Company’s website at www.orlamining.com.
ENVIRONMENTAL AND PERMITTING
We have an ongoing environmental management plan that includes maintaining sediment dams, reforestation of previously disturbed areas and active sediment control activities. Baseline surface water quality sampling and groundwater level measurements are also ongoing.
Mineral concessions are comprised of three contracts between the Republic of Panama and Minera Cerro Quema SA, a wholly owned subsidiary of Orla. The original 20-year term for these concessions expired on February 26, 2017 (Contracts 19 and 20) and March 3, 2017 (Contract 21). The Company has applied for the prescribed 10-year extension to these contracts as it is entitled to under Panamanian mineral law. As of the date of this MD&A, formal approval of the extension of these concessions has not yet been received. Since the expiry of the concessions, we have continued to receive ongoing exploration permits and the Ministry of Commerce has continued to accept our annual concession fees.
On March 6, 2017, the Ministry of Commerce and Industry provided written confirmation to the Company that it had received the extension applications, and that exploration work could continue while the Company waits for the renewal. We have received verbal assurances from government officials that the renewal applications are complete with no outstanding legal issues. On April 26, 2017, the Company received authorization from the Ministry of Environment to drill in two areas outside of the existing permitted drill area. On June 28, 2017, the Company received a permit to use water for drilling. In October and November 2017, we received a permit for copper exploration, and two permits allowing temporary use of water for exploration drilling.
1 The “Cerro Quema Report” is an independent technical report for the Cerro Quema Project entitled “Cerro Quema Project – Pre-Feasibility Study on the La Pava and Quemita Oxide Gold Deposits” dated August 15, 2014 with an effective date of June 30, 2014 prepared by Eugene Puritch, P. Eng., Richard H. Sutcliffe, P.Geo., Tracy Armstrong, P.Geo., Antoine Yassa, P.Geo., David Burga, P.Geo., Kenneth Kuchling, P.Eng., and Fred Brown, P.Geo., of P&E Mining Consultants Inc., Gene Tortelli, PE, George Lightwood, PE, and David Brown, P.Geo., of Golder Associates Inc., and Mark Gorman, PE of KCA.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
On May 8, 2018, we received a permit to drill in the Sombrero zone and on May 11, 2018, we received two permits to use water for drilling. In May 2018, an existing permit that allows drilling in the areas of the current mineral resources was extended for two years. In October 2018, the government accepted the payment our 2018 annual concession fees.
In February 2019, we paid the 2019 concession fees. On February 11, 2019, we received a new drilling permit for the Pelona area in the eastern part of the concessions. All drill permits are currently active.
We received two additional temporary water permits on January 13, 2020. In February 2020, we paid the annual concession fees, which were accepted, and in February 2021, we paid the annual concession fees, which also were accepted.
PRE-FEASIBILITY STUDY
We are in the process of updating the Cerro Quema Pre-Feasibility Study (“PFS”) on the oxide heap leach gold project initially completed in 2014. This will include updated mineral reserve and mineral resource estimates, mining plans, process plans, cost estimates, and additional geotechnical, environmental, and metallurgical investigations. Geotechnical drilling started in mid-September 2020. Completion of the PFS is expected during the second quarter of 2021.
EXPLORATION
The discovery of the Caballito mineralized zone and follow-up drilling executed by Orla led to the definition of significant copper and gold sulphide mineralization with open pit potential. The Caballito-style mineralization differs from the Pava and Quemita oxide deposits as it consists of copper-gold (low arsenic) sulphide mineralization that will not be amenable to heap leaching and will require a different processing method. The Cerro Quema property shows some potential for additional oxide mineralization, and the upside resides within the sulphides in an area that is largely under-explored.
Exploration drilling restarted on October 24, 2020. Current exploration activities are focused on advancing the Caballito copper-gold sulphide discovery and exploring for additional zones with similar mineralization. This style of mineralization, identified in 2018, presents potential value to the project in addition to the current heap-leach oxide gold project. The trend that hosts the Caballito mineralized zone, the Quemita deposit area and the Pelona target in the eastern part of the project provides prospective target areas for additional Caballito-style copper-gold (low-arsenic) mineralization.
In the two holes completed in Q4, 2020, multiple intervals of alteration were noted. This included narrow intervals of weakly to moderately advanced argillic alteration and patchy quartz-alunite intervals and mineralization mostly disseminated pyrite and local pyrite-enargite and trace of copper sulphide. Anomalous assays (1.5m at > 0.500 ppm Au, or 1.5m at > 1,000 ppm Cu) included gold and copper with values up to 0.538 ppm Au and 2,400 ppm Cu over 1.5 metres from 344.3 metres in hole CQDH-20-184.
We have included herein certain performance measures (“non-GAAP measures”) which are not specified, defined, or determined under generally accepted accounting principles (in our case, International Financial Reporting Standards, or “IFRS”).
These are common performance measures in the gold mining industry, but because they do not have any mandated standardized definitions, they may not be comparable to similar measures presented by other issuers. Accordingly, we use such measures to provide additional information and you should not consider them in isolation or as a substitute for measures of performance prepared in accordance with generally accepted accounting principles (“GAAP”).
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
ALL-IN SUSTAINING COSTS (“AISC”)
We have provided an AISC performance measure that reflects all the expenditures that are required to produce an ounce of gold from operations. While there is no standardized meaning of the measure across the industry, our definition conforms to the all-in sustaining cost definition as set out by the World Gold Council in its guidance dated June 27, 2013.
We believe that the inclusion of projected AISC has evolved into a common market practice in the mining industry for a feasibility-level study, and that some investors have come to expect this type of disclosure from issuers at the development stage. We acknowledge that this is a performance measure that relates to production, and our mines are not yet in production, but we disclose this measure as an estimate or projection in a similar manner as the general feasibility study results relating to production figures. We have provided AISC to identify it as non-GAAP and to disclose that it lacks a standardized meaning. Upon commencing production and reporting actual AISC, we will provide a reconciliation to IFRS figures then presented.
CASH COSTS PER OUNCE
We calculate cash costs per ounce by dividing the sum of operating costs, royalty costs, production taxes, refining and shipping costs, net of by-product silver credits, by payable gold ounces. While there is no standardized meaning of the measure across the industry, we believe that this measure is useful to external users in assessing operating performance.
| VI. | SELECTED ANNUAL INFORMATION |
The figures in the following table are based on the audited consolidated financial statements of the Company which were prepared in accordance with IFRS as issued by the International Accounting Standards Board.
Effective January 1, 2020, we changed our presentation currency to United States dollars. Internally, we budget in US dollars, report internally in US dollars, our project debt is denominated in US dollars, and our engineering and EPCM reports are presented in US dollars. We believe that presenting our financial information in US dollars is more useful to us internally to manage the business, and more useful to readers because of greater comparability and greater congruence with the underlying currencies of significant transactions.
This change in the financial statement presentation currency is an accounting policy change and we have accounted for it retrospectively. The functional currencies of all our entities remained unchanged. We translated the income statements at the average exchange rates for each reporting period. We recognized exchange differences arising from translating our subsidiaries’ financial results to United States dollars in other comprehensive income.
For the table below, the figures for the years ended December 31, 2019 and 2020 are presented in US dollars. The figures for the year ended December 31, 2018 are presented in Canadian dollars, as that was the presentation currency of the audited financial statements issued in that year.
| | 2020 | | | 2019 | | | 2018 | |
| | US$ 000’s | | | US$ 000’s | | | C$ 000’s | |
Total revenue | | $ | — | | | $ | — | | | C$ | — | |
Net loss | | $ | 27,694 | | | $ | 20,354 | | | C$ | 29,913 | |
Total assets | | $ | 239,195 | | | $ | 151,028 | | | C$ | 187,957 | |
Total non-current financial liabilities | | $ | 70,888 | | | $ | 23,488 | | | C$ | 6,848 | |
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
| VII. | SUMMARY OF QUARTERLY RESULTS |
The figures in the following table are based on the audited consolidated financial statements of the Company which were prepared in accordance with IAS 34 “Interim Financial Reporting” of IFRS as issued by the International Accounting Standards Board.
$ thousands | | 2020-Q4 | | | 2020-Q3 | | | 2020-Q2 | | | 2020-Q1 | | | 2019-Q4 | | | 2019-Q3 | | | 2019-Q2 | | | 2019-Q1 | |
Exploration expense | | $ | 3,943 | | | $ | 3,590 | | | $ | 1,166 | | | $ | 7,603 | | | | 3,069 | | | | 3,630 | | | | 2,612 | | | | 5,642 | |
General and administrative | | | 102 | | | | 162 | | | | 194 | | | | 185 | | | | 148 | | | | 97 | | | | 83 | | | | 201 | |
Professional fees | | | 558 | | | | 425 | | | | 230 | | | | 176 | | | | 165 | | | | 170 | | | | 110 | | | | 94 | |
Regulatory and transfer agent | | | (17 | ) | | | 11 | | | | 66 | | | | 82 | | | | 111 | | | | 30 | | | | 34 | | | | 31 | |
Salaries and wages | | | 802 | | | | 563 | | | | 527 | | | | 264 | | | | 730 | | | | 423 | | | | 450 | | | | 383 | |
Depreciation | | | 36 | | | | 23 | | | | 25 | | | | 22 | | | | 6 | | | | 25 | | | | 25 | | | | 22 | |
Share based payments | | | 434 | | | | 705 | | | | 612 | | | | 772 | | | | 358 | | | | 580 | | | | 673 | | | | 942 | |
Interest and finance costs | | | 1,178 | | | | 1,503 | | | | 609 | | | | 606 | | | | 447 | | | | 467 | | | | 34 | | | | 221 | |
Foreign exchange | | | 648 | | | | 1,688 | | | | (1,220 | ) | | | 479 | | | | 138 | | | | — | | | | 8 | | | | 13 | |
Other gains and losses | | | (39 | ) | | | (1,019 | ) | | | — | | | | — | | | | — | | | | — | | | | — | | | | — | |
Net loss | | | 7,645 | | | | 7,651 | | | | 2,209 | | | | 10,189 | | | | 5,172 | | | | 5,422 | | | | 4,029 | | | | 7,549 | |
Loss per share (basic and diluted) | | $ | 0.03 | | | $ | 0.03 | | | $ | 0.01 | | | $ | 0.05 | | | $ | 0.03 | | | $ | 0.03 | | | $ | 0.02 | | | $ | 0.04 | |
In 2019, we worked on, completed, and publicly filed the 2019 Feasibility Study for Camino Rojo. We commenced detailed engineering and planning for construction of Camino Rojo.
In 2020, we advanced detailed engineering for the mine at Camino Rojo. During the third quarter we received the necessary permits to commence construction, and in the fourth quarter we commenced construction activities. During the year we concluded agreements giving us access to the Layback Area, and we completed and filed the January 2021 Feasibility Study for Camino Rojo which incorporated the Layback Area.
Quarterly variations in exploration expense are due to seasonality and timing of mining concession fees, drilling activities and awaiting results from previous quarters’ exploration activities. During the second quarter of 2020, exploration expenses and site activities were unusually lower than previous quarters due to the temporary global shutdown and work from home orders caused by the COVID-19 pandemic.
Administrative costs and professional fees have trended with the level of activity of the Company, and with major regulatory events such as financings and public listings. In 2018-Q4 we commenced trading on the Toronto Stock Exchange. In 2019-Q4 we closed a $125 million project credit facility. In 2020-Q4 we listed and commenced trading on the NYSE American. Each of these events caused one-time increases in regulatory fees and legal fees. The recovery in regulatory fees in 2020-Q4 results from a reversal of an accrual from a prior year.
Salaries have generally increased in 2019 and into 2020 as we have grown our team in preparation for the construction phase at Camino Rojo. In 2019-Q4 we incurred payments related to the departure of the former Chief Operating Officer.
Share based payments expense is generally related to the number of stock options and RSUs vesting during the quarter. The grants typically occur during the first quarter of each year; consequently, those quarters tend to be greater than the others.
The Company received $25 million in 2019-Q4 as a first draw on the Camino Rojo project loan, which caused an increase in interest expense, and we can expect larger swings in foreign exchange gains and losses, starting in that quarter. We incurred loan initiation costs and those are being amortized over the next five years. The Company received a further draw of $50 million in 2020-Q4, driving the increase in interest expense.
Foreign exchange gains and losses vary based on fluctuation of the Canadian dollar and the Mexican peso versus the US dollar. During 2020-Q1, Q2 and Q3, there were unusually large swings in the Canadian dollar to US dollar and the Mexican peso to US dollar exchange rates related to economic uncertainty arising from the COVID-19 pandemic.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
Other gains and losses consist of modification gains on changes in estimates related to the Newmont loan.
| VIII. | FOURTH QUARTER OF 2020 |
The following table is based on the Company’s consolidated financial statements prepared in accordance with IFRS. Figures are expressed in thousands of United States dollars.
| | | | | | Comparison to last quarter | | | Comparison to same quarter last year | |
$ 000’s | | 2020-Q4 | | | 2020-Q3 | | | Difference | | | 2019-Q4 | | | Difference | |
Exploration expense | | $ | 3,943 | | | $ | 3,590 | | | $ | 353 | | | $ | 3,069 | | | $ | 874 | |
General and administrative | | | 102 | | | | 162 | | | | (60 | ) | | | 148 | | | | (46 | ) |
Professional fees | | | 558 | | | | 425 | | | | 133 | | | | 165 | | | | 393 | |
Regulatory and transfer agent | | | (17 | ) | | | 11 | | | | (28 | ) | | | 111 | | | | (128 | ) |
Salaries and wages | | | 802 | | | | 563 | | | | 239 | | | | 730 | | | | 72 | |
Depreciation | | | 36 | | | | 23 | | | | 13 | | | | 6 | | | | 30 | |
Share based payments | | | 434 | | | | 705 | | | | (271 | ) | | | 358 | | | | 76 | |
Interest and finance costs | | | 1,178 | | | | 1,503 | | | | (325 | ) | | | 447 | | | | 729 | |
Foreign exchange | | | 648 | | | | 1,688 | | | | (1,040 | ) | | | 138 | | | | 510 | |
Other gains and losses | | | (39 | ) | | | (1,019 | ) | | | 980 | | | | — | | | | (39 | ) |
Loss for the quarter | | $ | 7,645 | | | $ | 7,651 | | | $ | (6 | ) | | $ | 5,172 | | | $ | 2,473 | |
Exploration and evaluation expenses during the current quarter are higher than both the previous quarter and the same quarter of 2019. This is due to greater exploration activity in Panama during 2020-Q4 than those comparative periods. During 2020-Q4 we conducted exploration drilling and advanced the pre-feasibility study at Cerro Quema. Site activities at Cerro Quema were limited in 2020-Q3 due to regional travel restrictions related to the COVID-19 pandemic.
The increase in professional fees from previous quarters is due to legal and accounting fees related to execution of the Layback Agreement with Fresnillo and listing in the United States on the NYSE American.
The increase in salaries and wages from previous quarters is due to the hiring of corporate personnel.
The accompanying consolidated financial statements have been prepared on the assumption that the Company will continue as a going concern, meaning it will continue in operation for the foreseeable future and will be able to realize assets and discharge liabilities in the ordinary course of operations. Different bases of measurement may be appropriate if the Company is not expected to continue operations for the foreseeable future. The Company’s ability to continue as a going concern for the next twelve months involves significant judgment. As at December 31, 2020, the Company had not advanced any of its properties to commercial production and may require further financing. During the second quarter of 2020, the Company completed a C$75 million ($53 million) equity financing. To the end of the reporting period, the Company had received $75 million of a $125 million project loan facility in respect of the Camino Rojo project.
Historically the Company's primary source of funding has been the issuance of equity securities for cash, through prospectus offerings and private placements to sophisticated investors and institutions. We have successfully raised equity and debt financing in many of the past few years, in the form of prospectus offerings, private placement financings, the exercise of warrants and options, and debt. While we believe that this success will continue our access to exploration and construction financing is always uncertain, and there can be no assurance of continued access to sources of significant equity or debt funding until we can generate cash from operations. We expect to fund operating costs of the Company over the next twelve months with cash on hand and the third tranche of $50 million on the project loan. After considering its plans to mitigate the going concern risk, management has concluded that there are no material uncertainties related to events or conditions that may cast significant doubt upon the Company’s ability to continue as a going concern for a period of twelve months from the balance sheet date.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
We have no unique or novel financial instruments which would create additional liquidity risk.
In December 2019, we entered into an agreement for a credit facility for the development of the Camino Rojo Oxide Gold Project. This agreement provides a total of $125 million to the Company, available in three tranches. We drew down the first tranche of $25 million in December 2019, and we drew down the second tranche of $50 million in October 2020. Under the terms of the credit facility, the third tranche must be drawn within six months of the second tranche, being April 30, 2021. The third tranche is subject to Orla meeting all the conditions precedent.
Our ability to carry out our long-range strategic objectives in future periods depends on our ability to raise financing from lenders, shareholders, and other investors. We continue to regularly review and consider financing alternatives to fund the Company’s ongoing activities. We expect to fund the operating costs and the operating and strategic objectives of the Company over the next twelve months with existing cash on hand, draws from the Camino Rojo project loan, exercise of options and warrants and with further equity financings as required.
| | Payments due by period | |
Contractual obligations (thousands of US dollars) | | Total | | | Less than 1 year | | | 1-3 years | | | 4-5 years | | | After 5 years | |
Purchase commitments | | $ | 49,050 | | | $ | 49,050 | | | $ | — | | | $ | — | | | $ | — | |
Trade payables | | | 2,583 | | | | 2,583 | | | | — | | | | — | | | | — | |
Lease commitments | | | 294 | | | | 149 | | | | 145 | | | | — | | | | — | |
Camino Rojo project loan and related interest | | | 100,850 | | | | 6,600 | | | | 13,200 | | | | 81,050 | | | | — | |
Newmont loan | | | 11,002 | | | | — | | | | 11,002 | | | | — | | | | — | |
Total contractual obligations | | | 163,779 | | | | 58,382 | | | | 24,347 | | | | 81,050 | | | | — | |
Capital resources available to the Company.
DEBT
The Company has successfully negotiated and executed a $125 million project loan agreement with a syndicate of lenders led by Trinity Capital Partners of which $50 million remained undrawn at December 31, 2020. We expect to draw down on this remaining tranche prior to April 30, 2021.
EQUITY
During the year ended December 31, 2020, the Company raised C$ 75 million ($53 million) in a private placement.
In December 2020, the Company commenced trading in the United States on the NYSE American. This provides access to another channel for financing whether through equity issuances or other instruments.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
The Company has filed a preliminary base shelf prospectus pursuant to which it may raise up to C$300 million in equity or similar instruments. The final base shelf prospectus was filed on March 12, 2021.
There remained, at year end, 48.6 million warrants, all in the money.
Commitments for capital resources are substantially related to the construction of the Camino Rojo mine. We had material commitments for capital expenditures as of December 31, 2020, and we expect to spend all of 2021 constructing the Camino Rojo mine. At December 31, 2020, outstanding commitments arising from unfilled purchase orders and contracts totalled approximately $49 million.
On April 3, 2020, the Company completed a bought deal financing with a syndicate of underwriters. A total of 36,600,000 common shares of Orla were fully subscribed and sold at a price of C$2.05 per common share, for aggregate gross proceeds to the Company of C$75.0 million. The Company incurred issuance costs of approximately C$2.9 million.
The table below compares the approximate use of proceeds from the Company’s common shares issued in April 2020 and the actual amounts spent from the date of that issuance to December 31, 2020. There are no material variances to the use of proceeds in the March 2020 prospectus supplement that have impacted our ability to achieve our business objectives and milestones as disclosed in that prospectus supplement.
| | Camino Rojo Project construction expenditures | | | Payments related to the Layback Agreement | | | Working capital and general corporate purposes | | | Total | |
| | C$ millions | | | C$ millions | | | C$ millions | | | C$ millions | |
Intended use of proceeds per March 2020 prospectus | | | 31.9 | | | | 33.8 | | | | 6.5 | | | | 72.2 | |
| | | | | | | | | | | | | | | | |
Total spent April 3, 2020 to December 31, 2020 | | | 56.4 | | | | — | | | | 8.1 | | | | 64.5 | |
less: Cash on hand at April 3, 2020 | | | (12.5 | ) | | | — | | | | (8.1 | ) | | | (20.6 | ) |
less: Additional proceeds from the exercise of warrants and options | | | (2.8 | ) | | | — | | | | — | | | | (2.8 | ) |
less: Cash used from Project loan proceeds | | | (17.1 | ) | | | — | | | | — | | | | (17.1 | ) |
Net use of proceeds to December 31, 2020 | | | 24.0 | | | | — | | | | — | | | | 24.0 | |
At April 3, 2020, the Company held cash in various currencies totalling approximately C$21.9 million. At December 31, 2020, the Company held cash in various currencies totaling approximately C$91.9 million.
The Company’s focus over the next year is the construction of the Camino Rojo Project, which initial capital amounts to US$134 million. Together with the initial working capital requirements of approximately US$10 million as the project ramps up in mid-2020, and value added tax of approximately US$21 million (which is refundable over time), the total cash requirement to production for the Camino Rojo Project is expected to be approximately US$165 million. Proceeds from the secured project finance facility of up to US$125 million (the “Facility”), available pursuant to the loan agreement between Orla, Trinity Capital Partners and certain other lenders, will be used to fund the majority of the initial capital requirements for the construction of the Camino Rojo Project. The Company currently has received US$75 million under the Facility. The third and final tranche of US$50 million remains available to Orla upon meeting certain conditions precedent. Orla intends to draw on the balance of the Facility prior to April 30, 2021.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
Funds from the Facility are required to be used to fund the development and construction of the Camino Rojo Project. The balance of the construction capital will come from the proceeds of the offering, being C$31.9 million.
An amount of approximately C$33.8 million (US$25 million) from this Offering was allocated for the first payment related to the Layback Agreement with Fresnillo.
An amount of approximately C$6.5 million from the offering was allocated for planned working capital and corporate general and administrative purposes including, but not limited to, corporate head office personnel costs, public company costs, interest expense, and other general and administrative costs.
| XII. | OFF-BALANCE SHEET ARRANGEMENTS |
We have no off-balance sheet arrangements requiring disclosure under this section.
| XIII. | RELATED PARTY TRANSACTIONS |
The Company’s related parties include “key management personnel”, whom we define as the Chief Executive Officer, the Chief Operating Officer, the Chief Financial Officer, the Senior Vice President Exploration, and members of the Board of Directors of the Company. Other than compensation in the form of salaries or directors’ fees, and termination benefits and share based payments (options, RSU’s, DSU’s and bonus shares), there were no other material transactions with this group of individuals.
Compensation to key management personnel was as follows:
| | Year ended December 31 | |
| | 2020 | | | 2019 | |
Short term incentive plans | | | | | | | | |
Salaries | | $ | 1,361 | | | $ | 941 | |
Directors’ fees | | | 171 | | | | 160 | |
| | | 1,532 | | | | 1,101 | |
Termination benefits | | | — | | | | 284 | |
Share based payments | | | 1,859 | | | | 2,080 | |
Total | | $ | 3,391 | | | $ | 3,465 | |
During the period covered by this MD&A, and to the date of this MD&A, there are no other related parties.
| XIV. | CRITICAL ACCOUNTING ESTIMATES |
In preparing the accompanying consolidated financial statements, we have made judgements, estimates and assumptions that affect the application of accounting policies and the reported amounts of assets, liabilities, income, and expenses. Actual results may differ from these estimates.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
We review estimates and their underlying assumptions on an ongoing basis. Revisions to estimates are recognized prospectively.
Judgements, estimates, and assumptions that we have made in applying accounting policies that have the most significant effects on the amounts recognized in the accompanying consolidated financial statements include:
COMMENCEMENT OF THE DEVELOPMENT PHASE
We must use significant judgment to assess when an exploration and evaluation project is technically feasible and commercially viable. Timing of the work required to conclude the assessment work might change depending on various factors. We use multiple sources of information, including: a positive development decision to proceed with the project; geologic and metallurgic information; existence of mineral reserves; current and forecasted commodity prices; estimated future cash flows; our ability to finance the development phase, general market conditions, and consideration of other factors which may limit our access to the mineral deposit, such as the ability to obtain necessary permits. All of these factors have an impact on the timing of commencement of the development phase.
MINERAL RESOURCE AND MINERAL RESERVE ESTIMATES
Mineral resource and mineral reserve estimates are estimates of the amount of ore that can be economically extracted from the Company’s mining properties. Such estimates may impact the financial statements in the following way:
| • | Mineral resource and mineral reserve estimates is one of the factors considered in determining whether technical feasibility and commercial viability of extracting a mineral resource are demonstrable which influences the classification of expenditure. |
| • | Carrying value of assets may be affected due to changes in estimated mineral reserves and resources if the change is considered an indicator of impairment. |
| • | Site closure provisions may change where reserve estimate changes affect expectations about when such activities will occur and the associated cost of these activities. |
The mineral resource and mineral reserve estimates are based on information compiled by qualified persons within the meaning of National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”). Such information includes geological and technical data on the size, depth, shape and grade of the ore body and suitable production techniques and recovery rates. Such an analysis requires complex geological judgements to interpret the data. The estimation of recoverable reserves is based upon factors such as estimates of foreign exchange rates, commodity prices, future capital requirements and production costs, along with geological assumptions and judgements made in estimating the size and grade of the ore body.
As the economic assumptions used may change and as additional geological information is produced during the operation of a mine, estimates of mineral resources and mineral reserves may change.
TITLE TO MINERAL PROPERTIES
Although the Company has taken steps to verify title to mineral properties in which it has an interest, these procedures do not guarantee the Company’s title. Such properties may be subject to prior agreements or transfers and title may be affected by undetected defects. Further, we make judgements for properties where concessions terms have expired, and a renewal application has been made and is awaiting approval. We use judgement as to whether the concession renewal application is probable to be received, but ultimately this is beyond our control. If a renewal application is not approved, we could lose rights to those concession.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
ASSESSMENT OF IMPAIRMENT INDICATORS
We apply judgement in assessing whether indicators of impairment exist for our E&E assets which could result in a test for impairment. We consider internal and external factors, such as our rights to explore, planned expenditures on E&E activities, the technical results of our E&E activities, and the potential for viable operations, to determine whether there are any indicators of impairment or reversal of a previous impairment.
INCOME TAXES AND VALUE ADDED TAXES
Our operations involve dealing with uncertainties and judgements in the application of complex tax regulations in multiple jurisdictions.
We recognize potential tax liabilities for uncertain tax positions and matters identified based on our judgement of whether, and the extent to which, additional taxes will be due. We adjust these liabilities after considering changing facts and circumstances. However, due to the complexity of some of these uncertainties, the ultimate outcome may result in a payment that is materially different from our estimate of the tax liabilities.
VAT receivables are generated on the purchase of supplies and services by our companies. The timing and collection of VAT receivables is uncertain as VAT refund procedures in certain jurisdictions require a significant amount of documentation and follow-up. We are exposed to liquidity risk, credit risk and currency risk with respect to our VAT recoverable balances if tax authorities are unwilling to make payments in a timely manner pursuant to our refund filings.
The timing of receipt of Mexican VAT is uncertain. Consequently, we have presented this item as non-current.
FAIR VALUE MEASUREMENT
Management uses valuation techniques in measuring the fair value of share options granted and restricted share units, deferred share units, and bonus shares awarded. Such valuation techniques are also used for estimating the fair value of the Newmont loan, which is interest free.
We determine the fair value of share based payments awarded using the Black Scholes option pricing model which requires us to make certain estimates, judgements, and assumptions in relation to the expected life of the share options, expected volatility, expected risk-free rate, and expected forfeiture rate.
Changes to these assumptions could have a material impact on the Company’s financial statements.
NEWMONT LOAN MEASUREMENT
The Newmont loan is to be repaid upon declaration of commencement of commercial production of a heap leach operation at the Camino Rojo Project. Determining the date of repayment requires judgement and involves estimation uncertainty. Any unforeseen delays (such as those caused by COVID-19, or otherwise) may impact the declaration of commercial production date and consequently the maturity date used to measure the loan. Changes in the date will result in modification gains or losses.
FUNCTIONAL CURRENCY
The functional currency for the parent entity and each of its subsidiaries is the currency of the primary economic environment in which the entity operates. Determination of functional currency involves judgements to identify the primary economic environment. We reconsider the functional currency of each entity if there is a change in the underlying transactions, events and conditions which we used to determine the primary economic environment of that entity.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
In the normal course of business, the Company is inherently exposed to certain financial risks, including market risk, credit risk and liquidity risk, through the use of financial instruments. The timeframe and the way we manage these risks varies based upon our assessment of these risks and available alternatives for mitigation. We do not acquire or issue derivative financial instruments for trading or speculative purposes. All transactions undertaken are to support our operations.
| XVI. | OUTSTANDING SHARE DATA |
As of the date of this MD&A, the Company had the following equity securities outstanding:
| • | 237,308,584 common shares |
| • | 921,356 restricted share units |
| • | 644,525 deferred share units |
You can find further details about these potentially issuable securities in the notes to the accompanying audited consolidated financial statements for the year ended December 31, 2020.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
| XVII. | RISKS AND UNCERTAINTIES |
As the Company has not commenced principal operations, historical revenue and expenditure trends are not indicative of future activity. The Company has committed to certain work expenditures and may enter into future agreements. The ability of the Company to fund its future operations and commitments is dependent on its ability to generate revenue and to obtain additional financing. Risks of the Company’s business include the following:
OUR ACTIVITIES MAY BE ADVERSELY AFFECTED BY NATURAL DISASTERS, TERRORIST ACTS, HEALTH CRISES AND OTHER DISRUPTIONS AND DISLOCATIONS, INCLUDING BY THE COVID-19 PANDEMIC, WHETHER THOSE EFFECTS ARE LOCAL, NATIONWIDE OR GLOBAL
Upon the occurrence of a natural disaster, pandemic or upon an incident of war, riot or civil unrest, the impacted country, and the overall global economy, may not efficiently and quickly recover from such an event, which could have a material adverse effect on the Company. Terrorist attacks, public health crises including epidemics, pandemics or outbreaks of new infectious diseases or viruses, and related events can result in volatility and disruption to global supply chains, operations, mobility of people, patterns of consumption and service and the financial markets, which could affect interest rates, credit ratings, credit risk, inflation, business, financial conditions, results of operations and other factors relevant to the Company.
Global markets have been adversely impacted by emerging infectious diseases and/or the threat of outbreaks of viruses, other contagions or epidemic diseases, including COVID-19. A significant outbreak could result in a widespread crisis that could adversely affect the economies and financial and commodity markets of many countries, resulting in an economic downturn which could adversely affect the Company’s business and the market price of the Company’s common shares. Many industries, including the mining industry, have been impacted by these market conditions. If increased levels of volatility continue or in the event of a rapid destabilization of global economic conditions, it may result in a material adverse effect on commodity prices, demand for metals, availability of credit, investor confidence, and general financial market liquidity, all of which may adversely affect the Company’s business and the market price of the Company’s securities. In addition, there may not be an adequate response to emerging infectious diseases, or significant restrictions may be imposed by a government, either of which may impact mining operations. There are potentially significant economic and social impacts, including labour shortages and shutdowns, delays and disruption in supply chains, social unrest, government or regulatory actions or inactions, including quarantines, travel restrictions, declaration of national emergencies, permanent changes in taxation or policies, decreased demand or the inability to sell and deliver doré or concentrates and resulting commodities, declines in the price of commodities, delays in permitting or approvals, suspensions or mandated shut downs of operations, governmental disruptions or other unknown events with potentially significant impacts. At this time, the Company cannot accurately predict what effects these conditions will have on its operations or financial results, including due to uncertainties relating to the ultimate geographic spread, the duration of the outbreak, and the length restrictions or responses that have been or may be imposed by the governments. Given the global nature of the Company’s operations, the Company may not be able to accurately predict which operations will be impacted. Any outbreak or threat of an outbreak of a contagions or epidemic disease could have a material adverse effect on the Company, its business and operational results.
THE CAMINO ROJO PROJECT MINERAL RESOURCE ESTIMATE ASSUMES THAT THE COMPANY CAN ACCESS MINERAL TITLES AND LANDS THAT ARE NOT CONTROLLED BY THE COMPANY
All of the mineralization comprised in the Company’s mineral resource estimates with respect to the Camino Rojo Project is contained on mineral titles controlled by the Company. However, the mineral resource estimate assumes that the north wall of the conceptual floating pit cone used to demonstrate reasonable prospects for eventual economic extraction extends onto lands where mineral title is held by Fresnillo and that waste would be mined on Fresnillo’s mineral titles. On December 21, 2020, Orla announced that it had entered into the Layback Agreement. The Layback Agreement allows Orla to expand the Camino Rojo Project oxide pit onto part of Fresnillo’s mineral concession located immediately north of Orla’s property.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
The Layback Agreement is only with respect to the portion of the heap leach material included in the current mineral reserve. As such, any potential development of the Camino Rojo Project that includes an open pit encompassing the entire mineral resource estimate would be dependent on an additional agreement with Fresnillo (or any potential subsequent owner of the mineral titles). It is estimated that approximately two-thirds of the mill resource estimate and one-quarter of the leach resource estimate comprising the mineral resource estimate are dependent on this additional agreement being entered into with Fresnillo. The leach mineral resource dependent on the additional agreement is mainly comprised of less oxidized transitional material with the lowest predicted heap-leach recoveries.
Delays in, or failure to obtain, an additional agreement with Fresnillo would affect the development of a significant portion of the mineral resources of the Camino Rojo property that are not included in the January 2021 Feasibility Study mine plan, in particular by limiting access to significant mineralized material at depth. There can be no assurance that Orla will be able to negotiate such additional agreement on terms that are satisfactory to Orla and Fresnillo or that there will not be delays in obtaining the necessary additional agreement. Should such a subsequent agreement to access the mineral resource with Fresnillo not be obtained on favourable terms, the economics of any potential mine development using the full mineral resource estimate would be significantly negatively impacted.
THE LAYBACK AGREEMENT REMAINS SUBJECT TO THE TRANSFER OF CERTAIN SURFACE RIGHTS PURSUANT TO THE LAYBACK AGREEMENT
As contemplated in the January 2021 Feasibility Study, the Layback Agreement allows access to oxide and transitional heap leachable mineral resources on Orla’s property at depth. In addition, the Layback Agreement grants Orla the right to mine from Fresnillo’s mineral concession, and recover for Orla’s account, all oxide and transitional material amenable to heap leaching that are within an expanded open pit. In the Feasibility Study, all material to be mined on Fresnillo’s concession is classified as waste. Upon the completion of a confirmatory drill program on Fresnillo concessions by Orla, and integration of Fresnillo’s drill database, a subsequent mineral reserve update is expected which would include all economic oxide and transitional material from the expanded pit. The Layback Agreement remains subject to the transfer of certain surface rights. Delays in, or failure to obtain, the transfer of certain surface rights pursuant to the Layback Agreement could affect the timetable or cost of development of the potential mine modelled in the Feasibility Study.
MINERAL RESOURCE ESTIMATIONS FOR THE CAMINO ROJO PROJECT ARE ONLY ESTIMATES AND RELY ON CERTAIN ASSUMPTIONS
The estimation of mineral resources relies on the judgment of the independent Qualified Person preparing the estimates. The process relies on the quantity and quality of available data and is based on knowledge, mining experience, analysis of drilling results and industry practices. Valid estimates made at a given time may significantly change when new information becomes available.
In particular, the estimation of mineral resources for the Camino Rojo Project has assumed that there is a reasonable prospect for reaching an additional agreement with Fresnillo with respect to the mill resource included in the mineral resource estimate. While the Company believes that the mineral resource estimates for the Camino Rojo Project are well established and reflect best estimates, by their nature resource estimates are imprecise and depend on inferences that may ultimately prove to be inaccurate, including the assumption that an additional agreement with Fresnillo will be reached.
Although all mineralization included in the Company’s mineral resource estimate for the Camino Rojo Project are located on mineral concessions controlled by the Company, failure to reach an additional agreement with Fresnillo would result in a significant reduction of the mineral resource estimate by limiting access to mineral resources below the current mineral reserves. Any material changes in mineral resource estimates may have a material adverse effect on the Company.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
NEGATIVE OPERATING CASH FLOW
The Company is an exploration and development stage company and has not generated cash flow from operations. The Company is devoting significant resources to the development of the Camino Rojo Project, the Cerro Quema Project and to actively pursue exploration and development opportunities, however, there can be no assurance that it will generate positive cash flow from operations in the future. The Company expects to continue to incur negative consolidated operating cash flow and losses until such time as it achieves commercial production at a particular project. Historically the Company’s primary source of funding has been the issuance of equity securities for cash, typically through private placements to sophisticated investors and institutions. The Company has successfully raised equity and debt financing in many of the past few years, in the form of private placement financings, the exercise of warrants and options, and negotiation of a project loan. While the Company believes that success will continue, its access to exploration and construction financing is always uncertain, and there can be no assurance of continued access to significant equity or debt funding. The Company currently has negative cash flow from operating activities.
PERMITS AND LICENSES
The exploitation and development of mineral properties may require the Company to obtain regulatory or other permits and licenses from various governmental licensing bodies. There can be no assurance that the Company will be able to obtain all necessary permits and licenses that may be required to carry out exploration, development, and mining operations on its properties.
The Company is awaiting mineral concession renewals at its Cerro Quema Project. There is no assurance that we will receive necessary approvals or extensions, or receive them within a reasonable period of time. Failure to receive the permits or extensions would have an adverse effect on the Company’s business, financial position, and results of operations. Additional details are provided in the Cerro Quema Project section of this document.
FOREIGN COUNTRY AND POLITICAL RISK
The Company’s principal mineral properties are located in Mexico and Panama. The Company is subject to certain risks, including currency fluctuations, possible political or economic instability that may result in the impairment or loss of mineral titles or other mineral rights, opposition from environmental or other non-governmental organizations, and mineral exploration and mining activities may be affected in varying degrees by political stability and government regulations relating to the mining industry. Any changes in regulations or shifts in political attitudes are beyond the control of the Company and may adversely affect its business. Exploration and development may be affected in varying degrees by government regulations with respect to restrictions on future exploitation and production, price controls, export controls, foreign exchange controls, income taxes, royalties on production, expropriation of property, environmental legislation and mine and/or site safety.
Operating in developing economies such as Mexico and Panama has certain risks, including changes to, or invalidation of, government mining regulations; expropriation or revocation of land or property rights; changes in foreign ownership rights; changes in foreign taxation rates; security issues; corruption; uncertain political climate; narco-terrorist actions or activities; and lack of a stable economic climate.
We do not carry political risk insurance.
ESTIMATES OF MINERAL RESOURCES & MINERAL RESERVES AND PRODUCTION RISKS
The mineral resource and mineral reserve estimates included in this MD&A are estimates based on a number of assumptions, including those stated herein, and any adverse change to those assumptions could require the Company to lower its mineral resource estimate. Until a deposit is actually mined and processed, the quantity and grades of mineral resources must be considered as estimates only. Valid estimates made at a given time may significantly change when new information becomes available. In addition, the quantity and/or economic viability of mineral resources may vary depending on, among other things, metal prices, grades, production costs, stripping ratios, recovery rates, permit regulations and other legal requirements, environmental factors, unforeseen technical difficulties, unusual or unexpected geological formations and work interruptions. Any material change in the quantity of mineral resources or grade may affect the economic viability of the Company’s properties. No assurance can be given that any particular level of recovery of minerals will in fact be realized or that an identified mineral resource will ever qualify as a commercially mineable (or viable) deposit that can be legally and economically exploited. There can also be no assurance that any discoveries of new mineral reserves will be made. Any material reductions in estimates of mineral resources could have a material adverse effect on the Company’s results of operations and financial condition.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
MINING INDUSTRY
The exploration for and development of mineral deposits involves significant risks, which even a combination of careful evaluation, experience and knowledge may not eliminate. While the discovery of an ore body may result in substantial rewards, few properties which are explored are ultimately developed into producing mines. Major expenses may be required to establish ore reserves, to develop metallurgical processes and to construct mining and processing facilities at a particular site. It is impossible to ensure that the current exploration programs planned by the Company will result in a profitable commercial mining operation.
Whether a mineral deposit will be commercially viable depends on many factors, some of which are the particular attributes of the deposit, such as size, grade and proximity to infrastructure, as well as metal prices which are highly cyclical and government regulations, including regulations relating to prices, taxes, royalties, land tenure, land use, importing and exporting of minerals and environmental protection. The exact effect of these factors cannot be accurately predicted, but the combination of these factors may result in the Company not receiving an adequate return on invested capital.
Mining operations generally involve a high degree of risk. The Company’s operations are subject to all the hazards and risks normally encountered in the exploration and development of ore, including unusual and unexpected geological formations, rock bursts, cave-ins, flooding and other conditions involved in the drilling and removal of material, any of which could result in damage to life or property, environmental damage and possible legal liability. The Company’s mineral exploration activities are directed towards the search, evaluation, and development of mineral deposits. There is no certainty that the expenditures to be made by the Company as described herein will result in discoveries of commercial quantities of ore. There is aggressive competition within the mining industry for the discovery and acquisition of properties considered to have commercial potential. The Company will compete with other interests, many of which with greater financial resources, for the opportunity to participate in promising projects. Significant capital investment is required to achieve commercial production from successful exploration efforts.
GOVERNMENT REGULATION
The exploration activities of the Company are subject to various federal, provincial/state, and local laws governing prospecting, development, taxes, labour standards, toxic substances, and other matters. Exploration activities are also subject to various federal, provincial/state, and local laws and regulations relating to the protection of the environment. These laws mandate, among other things, the maintenance of air and water quality standards, and land reclamation. These laws also set forth limitations on the generation, transportation, storage, and disposal of solid and hazardous waste. Although the Company’s exploration activities are currently carried out in accordance with all applicable rules and regulations governing operations and exploration activities, no assurance can be given that new rules and regulations, amendments to current laws and regulations or more stringent implementation thereof could have a substantial adverse impact on the Company’s activities.
TITLE MATTERS
Although the Company has diligently investigated title to all mineral concessions (either granted or under re-application) and, to the best of its knowledge (except as otherwise disclosed herein), titles to all its properties are in good standing, this should not be construed as a guarantee of title. Other parties may dispute title to any of the Company’s mineral properties and any of the Company’s properties may be subject to prior unregistered agreements or transfers and title may be affected by undetected encumbrances or defects or governmental actions.
LAND TITLE
The Company has investigated ownership of all surface rights in which it has an interest, and, to the best of its knowledge, its ownership rights are in good standing. However, all surface rights may be subject to prior claims or agreement transfers, and rights of ownership may be affected by undetected defects. While to the best of the Company’s knowledge, titles to all surface rights are in good standing; however, this should not be construed as a guarantee of title. Other parties may dispute title to the surface rights in which the Company has an interest. The properties may be subject to prior unregistered agreements or transfers and titles may be affected by undetected defects.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
ENVIRONMENTAL RISKS AND HAZARDS
All phases of the Company’s mineral exploration operations are subject to environmental regulation in the various jurisdictions in which it operates. Environmental legislation is evolving in a manner which will require stricter standards and enforcement, increased fines and penalties for non-compliance, more stringent environmental assessments of proposed projects and a heightened degree of responsibility for companies and their officers, directors, and employees. There is no assurance that future changes in environmental regulations, laws and permits, if any, will not adversely affect the Company’s operations. Environmental hazards may exist on the properties on which the Company holds interests which are unknown to the Company at present, which have been caused by previous or existing owners or operators of the properties. The Company may become liable for such environmental hazards caused by previous owners and operators of the properties even where it has attempted to contractually limit its liability.
Government approvals and permits are currently, and may in the future be, required in connection with the Company’s operations. To the extent such approvals are required and not obtained; the Company may be curtailed or prohibited from proceeding with planned exploration or development of mineral properties.
Failure to comply with applicable laws, regulations and permitting requirements may result in enforcement actions thereunder, including orders issued by regulatory or judicial authorities causing operations to cease or be curtailed, and may include corrective measures requiring capital expenditures, installation of additional equipment, or remedial actions. Parties engaged in mining operations may be required to compensate those suffering loss or damage by reason of the mining activities and may have civil or criminal fines or penalties imposed for violations of applicable laws or regulations.
COMMODITY PRICES
The profitability of mining operations is significantly affected by changes in the market price of gold and other minerals. The level of interest rates, the rate of inflation, world supply of these minerals and stability of exchange rates can all cause significant fluctuations in metal prices. Such external economic factors are in turn influenced by changes in international investment patterns and monetary systems and political developments. The price of gold and other minerals has fluctuated widely in recent years, and future serious price declines could cause commercial production to be impracticable.
UNINSURED RISKS
The Company carries insurance to protect against certain risks in such amounts as it considers adequate. Risks not insured against include environmental pollution or other hazards against which such corporations cannot insure or against which they may elect not to insure.
COMPLIANCE WITH ANTI-CORRUPTION LAWS
Orla is subject to various anti-corruption laws and regulations including, but not limited to, the Corruption of Foreign Public Officials Act (1999). In general, these laws prohibit a company and its employees and intermediaries from bribing or making other prohibited payments to foreign officials or other persons to obtain or retain business or gain some other business advantage. The Company’s primary operations are located in jurisdictions which have been perceived as having fairly high levels of corruption. Orla cannot predict the nature, scope, or effect of future anti-corruption regulatory requirements to which the Company’s operations might be subject or the manner in which existing laws might be administered or interpreted.
Failure to comply with the applicable legislation and other similar foreign laws could expose the Company and/or its senior management to civil and/or criminal penalties, other sanctions and remedial measures, legal expenses and reputational damage, all of which could materially and adversely affect the Company’s business, financial condition and results of operations. Likewise, any investigation of any potential violations of the applicable anti-corruption legislation by Canadian or foreign authorities could also have an adverse impact on the Company’s business, financial condition, and results of operations.
ORLA MINING LTD. | |
Management’s Discussion and Analysis | |
Year ended December 31, 2020 | United States dollars unless otherwise stated |
As a consequence of these legal and regulatory requirements, the Company has instituted policies regarding business ethics, which have been designed to ensure that Orla and its employees comply with applicable anti-corruption laws and regulations. However, there can be no assurance or guarantee that such efforts have been and will be completely effective in ensuring the Company’s compliance, and the compliance of its employees, consultants, contractors and other agents, with all applicable anticorruption laws and regulations.
CONFLICTS OF INTEREST
Certain directors of the Company also serve as directors and/or officers of other companies involved in natural resource exploration and development. Consequently, there exists the possibility for such directors to be in a position of conflict. Any decision made by such directors involving the Company will be made in accordance with their duties and obligations to deal fairly and in good faith with the Company and such other companies. In addition, such directors will declare, and refrain from voting on, any matter in which such directors may have a conflict of interest.