| · | Schedule and completion risk can be passed through to subcontractors, suppliers, and vendors and then only to the extent of any damages that can be collected from such subcontractors, suppliers and vendors. |
6. | Inspection and Access to Site & License to and Use of Data |
From and after the date of execution of this Agreement, Customer will provide access to and will make available to Energy Vault’s employees and representatives (including without limitation, contractors, consultants, advisers and company representatives) for inspection and review, the proposed sites for the ESS and relevant information and documents relating to the respective Customer’s projects (including estimated production and load data). Such employees and representatives will be required to sign confidentiality undertakings, as required by the Customer.
Starting on the date of substantial completion and for five years thereafter, as Energy Vault may reasonably request in writing, from time to time, Customer may permit Energy Vault physical and/or remote access to the site for Energy Vault to take control of the operation of each Facility in order to test performance of such Facility (understanding that Customer might reasonably reschedule such access or visits, or limit the number of hours of testing, if occurring during high value or critical operation periods). Permission shall not unreasonably be withheld by the Customer, in respect of access required in terms of this provision.
Customer shall permit Energy Vault to bring potential customers to the site for demonstration and marketing purposes as may be reasonably requested from time to time, at a date to be mutually agreed in writing between the Parties and subject to such potential customers signing confidentiality undertakings, as required by the Customer.
As between the Parties, Energy Vault is the owner of “ESS Data” (i.e. technical data concerning the operation, performance, status, integrity and other relevant aspects of the ESS that is collected by various control, monitoring, and protection devices and systems incorporated in or on the ESS). This data ownership is subject to a non-exclusive, royalty-free, fully-paid-up, transferable, perpetual, irrevocable license from Energy Vault to Customer granting Customer the right to use the ESS data for the purposes of (a) operating and maintaining the ESS and its components, (b) training operators for the ESS, and (c) repairing, replacing, completing, or modifying the ESS. All intellectual property regarding the energy storage process shall be exclusively governed by the Parties’ PSA.
7. | Target Round-Trip Efficiency |
The Target Round-Trip Efficiency of the Facility is [***]%.
During final commissioning, Energy Vault will measure the round-trip efficiency of the Facility. If the measured round-trip efficiency is less than the Target Round-Trip Efficiency, Energy Vault will have a period of three (3) months (“Performance Guarantee Correction Period” or “PGCP”) to increase the round-trip efficiency up to the Target Round-Trip Efficiency.
The PGCP will start on the date of substantial completion which shall be the date by which all other requirements for substantial completion have been achieved. During the PGCP, Customer shall provide access to the Facility for Energy Vault to perform such correction efforts, subject to Customer’s operation and maintenance schedule and safety requirements.
To the extent that the Final Round-Trip Efficiency is less than the Target Round-Trip Efficiency, the Facility purchase price will be reduced to the Adjusted Contract Price, calculated according to the formula Annex D.