Changes in CH Energy Group's and Central Hudson's cash and cash equivalents resulting from operating, investing, and financing activities are summarized in the following chart (In Millions):
Central Hudson's net cash used in operations was $(1.1) million for the three months ended March 31, 2013 and net cash provided by operations was $11.2 million for the three months ended March 31, 2012. Excluding contributions to Central Hudson's pension and OPEB plans (which totaled $26.2 million and $28.2 million in the three months ended March 2013 and 2012, respectively), cash provided by sales exceeded the period's expenses and working capital needs. Recovery of previously deferred electric and natural gas costs had a negative impact on net cash provided by operations during the first three months of 2013 compared to the positive impact in the first three months of 2012 driven by wholesale prices in the respective periods. Costs spent for MGP remediation efforts in excess of amounts collected in rates during the three months ended March 31, 2013 negatively impacted the cash from operations compared to the three months ended March 31, 2012 when amounts collected in rates for MGP site remediation were greater than remediation costs due to the timing of project completion.
Central Hudson's net cash used in investing activities of $28.3 million and $26.6 million in the three months ended March 31, 2013 and 2012, respectively, was primarily for investments in Central Hudson's electric and natural gas transmission and distribution systems.
Central Hudson's net cash provided by financing activities was $12.1 million and $68.7 million, respectively, for the three months ended March 31, 2013 and 2012. At the end of the first quarter of 2012, Central Hudson undertook additional short-term borrowings of $36.0 million from uncommitted lines of credit to fund the repayment of maturing notes as well as issuing $48.0 million of its Series G Medium Term Notes. The proceeds of the sale of the additional notes were used by Central Hudson to refinance short-term borrowings in April 2012 and to redeem preferred stock. Also, in the first three months of 2013 Central Hudson paid dividends of $5.0 million to parent CH Energy Group while comparatively, no dividends were paid in to parent the first three months of 2012. From time to time Central Hudson borrows from its parent CH Energy Group on an intercompany demand note and for the three months ended March 31, 2012 Central Hudson borrowed $20.0 million under this program with no comparable activity in the current year. Central Hudson redeemed $9.7 million of preferred stock in the three months ended March 31, 2013 while no preferred stock was redeemed during the same period in 2012. Finally, CH Energy Group's financing activities in the three months ended March 2012 included final settlement costs associated with the ASR program of $3.0 million.
Capitalization – Issuance of Treasury Stock
Effective July 1, 2011, employer matching contributions to an eligible employee's Savings Incentive Plan ("SIP") account could be paid in either cash or in CH Energy Group Common Stock, and CH Energy Group chose to meet its matching obligation in Common Stock. Since March 1, 2012, the Company has been using cash for all of its matching obligations, except for matching associated with classified employees of Central Hudson. The classified employees will continue to receive matching contributions in CH Energy Group Common Stock. As of March 31, 2013, 44,786 shares had been issued from treasury related to employer matching contributions, of which 3,425 shares were issued in 2013.
For information regarding equity compensation and the purchase of treasury shares, see Note 11 - "Equity Based Compensation" of this Quarterly Report on Form 10-Q.
Financing Program
CH Energy Group believes that it is well positioned with a strong balance sheet and strong liquidity. Significant capacity is available on CH Energy Group's and Central Hudson's committed credit facilities. Central Hudson's investment-grade credit ratings help facilitate access to long-term debt. However, management can make no assurance in regards to the continued availability of financing or the terms and costs.
At March 31, 2013, CH Energy Group maintained a $100 million credit facility with JPMorgan Chase Bank, N.A., Bank of America, N.A., HSBC Bank USA, N.A. and KeyBank National Association as the participating banks. The credit facility has a term of up to three years. The maximum borrowing amount reflects CH Energy Group's projected liquidity needs in accordance with its current business strategy. If the participating lenders are unable to fulfill their commitments under this facility, funding may not be available as needed.
At March 31, 2013, Central Hudson maintained a $150 million committed revolving credit facility with JPMorgan Chase Bank, N.A., Bank of America, N.A., HSBC Bank USA, N.A., KeyBank National Association and RBS Citizens Bank, N.A. as the participating banks. The credit facility has a term of up to five years. If these lenders are unable to fulfill their commitments under these facilities, funding may not be available as needed.
Central Hudson's current senior unsecured debt rating/outlook is 'A'/CreditWatch negative by Standard & Poor's Rating Services ("Standard & Poor's"), 'A'/stable by Fitch Ratings and 'A3'/stable by Moody's Investors Service ("Moody's")1.
On February 22, 2012, Standard & Poor's placed its ratings of Central Hudson on CreditWatch with negative implications, following the February 21, 2012 announcement that CH Energy Group had agreed to be acquired by Fortis. Standard & Poor's stated that they expect to resolve the CreditWatch listing as the merger nears completion and additional information is available. CH Energy Group is unable to predict the outcome of that resolution. The CreditWatch listing is not expected to have a material impact on Central Hudson's financial performance.
CH Energy Group and Central Hudson believe they will be able to meet their short-term and long-term cash requirements, assuming that Central Hudson's future rate plans reflect the costs of service, including a reasonable return on invested capital.
1 These ratings reflect only the views of the rating agency issuing the rating, are not recommendations to buy, sell, or hold securities of Central Hudson and may be subject to revision or withdrawal at any time by the rating agency issuing the rating. Each rating should be evaluated independently of any other rating.
On March 21, 2013, Central Hudson redeemed its two outstanding series of preferred stock. Registered holders of 4 1/2% Cumulative Preferred Stock received $107.00 per share plus accrued and unpaid dividends to the redemption date in the amount of $1.00 per share, for a total redemption price of $108.00 per share. Registered holders of 4.75% Cumulative Preferred Stock received $106.75 per share plus accrued and unpaid dividends to the redemption date in the amount of $1.056 per share, for a total redemption price of $107.806 per share. The premium paid in connection with the redemption of the preferred stock was recorded as a reduction of Retained Earnings on Central Hudson's Balance Sheet and as Premium on Preferred Stock Redemption on Central Hudson's Income Statement.
For additional information related to CH Energy Group's and Central Hudson's financing program, please see Note 7 – "Short-term Borrowing Arrangements," Note 8 – "Capitalization – Common and Preferred Stock" and Note 9 – "Capitalization – Long-term Debt" to the Financial Statements of the Corporations' 10-K Annual Report.
NYSERDA
Central Hudson's outstanding Series B NYSERDA Bonds total $33.7 million at March 31, 2013. These bonds are tax-exempt multi-modal bonds that are currently in a variable rate mode. In its Orders, the PSC has authorized deferral accounting treatment for variations in the interest costs from these bonds. As such, variations between the actual interest rates on these bonds and the interest rate included in the current delivery rate structure for these bonds are deferred for future recovery from or refund to customers and do not have any impact on earnings.
To mitigate the potential cash flow impact from unexpected increases in short-term interest rates on Series B NYSERDA Bonds, on March 26, 2012, Central Hudson purchased an interest rate cap based on an index of short-term tax-exempt debt. The rate cap is two years in length with a notional amount aligned with Series B and will expire on April 1, 2014. The cap is based on the monthly weighted average of an index of tax-exempt variable rate debt, multiplied by 175%. Central Hudson would receive a payout if the adjusted index exceeds 5.0% for a given month. This rate cap replaces an expiring rate cap with substantially similar terms.
REGULATORY MATTERS – PSC PROCEEDINGS
Fortis – Central Hudson Gas & Electric Corporation Section 70 Joint Petition
(Case 12-M-0192 – Proceeding on the Joint Petition for Approval of the Acquisition of CH Energy Group, Inc. by Fortis Inc. and Related Transactions)
Background: On April 20, 2012, CH Energy Group, Central Hudson, Fortis, FortisUS, and Cascade Acquisition Sub Inc., submitted a joint petition to the PSC for approval of the acquisition of CH Energy Group by Fortis and related transactions. The petition describes how the acquisition of Central Hudson by Fortis will produce benefits for constituencies that include customers, employees and communities in Central Hudson's service territory as well as positive public benefits. The petition categorizes the public benefits into three major areas: 1) FortisUS' commitments and intention to preserve and build on the existing strength of Central Hudson as a "stand-alone" company, 2) comprehensive financial protections to mitigate any potential financial risks of the merger consistent with the PSC's disposition of specific issues that have arisen in prior utility merger proceedings in New York State and 3) identifiable financial customer benefits resulting from avoidance of costs otherwise owed to customers by shareholders and cost savings made possible by the merger. The petition includes proposals and commitments that effectively mitigate any potential risks to Central Hudson's customers from foreign holding company ownership and rate increase risk.
Notable Activity:
Pursuant to the schedule adopted by the ALJs in the proceeding:
· | On October 12, 2012, the PSC's Staff and other interested parties filed testimony and comments regarding the proposed acquisition. |
· | On November 5, 2012, the PSC Trial Staff filed Supplemental Testimony and Exhibits to correct errors related to their calculation of a Public Benefit Adjustment. |
· | On November 27, 2012, Petitioners submitted Reply Comments and Rebuttal Testimony and PSC Staff filed Rebuttal Testimony. |
· | On December 4, 2012, PSC filed surrebuttal testimony. |
· | Parties filed their lists of Disputed Issues of Material Fact on December 4, 2012. |
· | Pursuant to a Notice of Potential Settlement filed by the Petitioners on December 12, 2012, a series of settlement discussions were held between December 17, 2012 and January 11, 2013. |
· | On January 25, 2013, a Joint Proposal with the Company, Fortis, PSC Staff, Multiple Intervenors, the Department of State Utility Intervention Unit (consumer advocate), and Dutchess, Orange and Ulster counties as signatories, was submitted to the PSC. The signatory parties have concluded that, based on the terms of the Settlement Agreement, the acquisition is in the public interest pursuant to the New York State Public Service Law, Section 70, and recommended approval by the Commission. |
The major components of the Joint Proposal include:
· | Quantified benefits, in addition to a one-year rate freeze for the period July 1, 2013 through June 30, 2014 including: |
- | synergy savings/guaranteed future rate mitigation of $1.85 million per year for 5 years, totaling $9.25 million; |
- | $35 million to write off existing deferred regulatory assets and to provide additional future rate mitigation; |
- | establishment of a Community Benefit Fund of $5 million to be used for economic development and low income programs; |
- | earnings sharing was modified to reduce the threshold from 10.5% to 10% with 50/50 sharing beginning at 10%; and |
- | a provision that Central Hudson file a formal Superstorm Sandy deferral petition as soon as reasonably practicable for review by the Commission on an expedited basis. This petition was filed on February 6, 2013. |
The Joint Proposal also includes various governance, corporate and financial protection conditions. These protections include goodwill and acquisition cost conditions, credit quality and dividend restriction conditions, money pooling conditions and establishing a special class of preferred stock. In addition, the Joint Proposal established provisions for financial transparency and reporting, affiliate transactions, cost allocations and code of conduct. Finally, the terms of the Joint Proposal provide additional customer service protections and benefits
· | Statements in Support/Opposition to the Joint Proposal were filed February 8, 2013, with Statement Replies filed February 15, 2013. |
· | Public Statement Hearings were held in Poughkeepsie and Kingston on February 21, 2013. On April 2, 2013, the Commission issued a notice of additional Public Statement Hearings to be held in Poughkeepsie on April 17, 2013 and in Kingston on April 18, 2013. |
· | The deadline for submission of public comments in the proceeding was extended to May 1, 2013 by the Commission in a notice issued March 22, 2013. |
· | On April 24, 2013, the PSC issued notice that a recommended decision will be issued. |
On May 3, 2013 the Recommended Decision ("RD") of the two Administrative Law Judges ("ALJs") – an advisory document – was issued by the PSC. The RD states that, in its current form, the Joint Proposal does not meet the public interest test as required by New York State Public Service Law, Section 70, but also states that the ALJs recommend the Commission consider adopting the Joint Proposal subject to modifications that would alter the transaction's balance of risks and benefits. In the RD, the ALJs' statements included the following regarding the current terms of the Joint Proposal in relation to the public interest:
· | Customer Benefits include: |
- | Synergy savings of $9.25 million; |
- | Rate mitigation of $35 million; and |
- | Economic development funding of $5 million. |
· | The RD's concerns include the following Residual Risks: |
- | Loss of local ownership and loss of goodwill toward the company, compromising management's ability to perform its service obligations to customers. |
- | Workforce uncertainty regarding job security beyond the 2-year employment commitment in the joint proposal. |
- | Complications in communications and data availability required for effective regulatory oversight due to foreign ownership. |
- | Lack of public confidence in the putative future benefits of the Joint Proposal. |
Management believes that the concerns expressed in the RD can be resolved.
· | Briefs on exceptions to the RD are due May 17, 2013 and briefs opposing exceptions are due on May 24, 2013. |
· | A PSC order regarding the Joint Proposal and closing of the merger are expected in the second quarter of 2013. |
Potential Impacts: Central Hudson believes the merger is in the public interest. While no assurance regarding the closing can be given until a final PSC Order is issued, the Company continues to anticipate that the Commission will review and approve the merger in the second quarter of 2013 in time for the closing to occur in the second quarter of 2013. Under the terms of the merger agreement, Fortis must close the transaction if all conditions precedent are met, including PSC approval, and a material adverse effect has not occurred.
Failure to complete the acquisition could negatively affect our share price, including by reducing it to a level at or below the trading range preceding the announcement of the Fortis transaction.
Petition of Central Hudson Gas & Electric Corporation for Commission Approval of Deferred Incremental Costs Associated with Superstorm Sandy
(Case 13-E-0048)
Background: On October 29, 2012, Central Hudson's service territory was impacted by Superstorm Sandy, and approximately 103,000 electric customers were affected. The Sandy storm costs were included in the estimate of $22 million storm costs identified in the $35 million of regulatory liabilities to be funded by Fortis. Consistent with the Joint Proposal, on February 6, 2013, Central Hudson filed a petition with the PSC seeking expedited Commission approval to recover $9.7 million of incremental electric storm restoration expense, with carrying charges. These storm costs represent the amount Central Hudson deferred on its books as of December 31, 2012, based on actual costs incurred, bills received and an estimate for bills outstanding and are above the respective rate allowance during the twelve months ended June 30, 2013, which is the third rate year established by the PSC in its approval of a Joint Proposal in Case 09-E-0588. The Company believes the incremental costs associated with this storm meet the PSC's criteria for deferral: 1) the amount is incremental to the amount in rates; 2) the incremental amount is material and extraordinary in nature and 3) the utility's earnings are below the authorized rate of return on common equity.
Potential Impacts: If the PSC approves any amount less than the $9.7 million reflected in the petition, Central Hudson's expenses would increase by the unapproved amount.
Petition of Central Hudson Gas & Electric Corporation for Commission Approval of Deferred Incremental Costs Associated with Tropical Storm Irene
(Case 11-E-0651)
Petition of Central Hudson Gas & Electric Corporation for Commission Approval of Deferral of October 29, 2011 SnowFall Costs
(Case 12-M-0204)
Background: On October 29, 2011, Central Hudson experienced an unusual fall storm with snow accumulations of up to 20 inches in the service territory, resulting in electric service outages to over 150,000 customers, extensive damage to the electric system and significant restoration costs. Following Tropical Storm Irene, the October snowstorm represented the second extraordinary storm event that occurred within the rate year. Central Hudson filed a petition with the PSC to defer for future recovery with carrying charges the $8.6 million of total incremental electric storm restoration expense. However, because the petition requested the PSC to deviate from its prior precedents, the Company was aware that the amount the PSC granted could have been lower. Accordingly, management deferred only the portion of the incremental costs that strictly follows Commission practice used in the Company's previous requests to defer incremental storm costs. Approximately $3.7 million and $3.3 million of incremental restoration expense associated with this storm was expensed in 2011 and 2012, respectively, so that the return on common equity for the twelve months ending June 30, 2012 did not exceed the authorized rate of return of 10%.
Background: In late August 2011, Central Hudson's service territory was affected by Tropical Storm Irene, disrupting service to approximately 180,000 customers. On November 28, 2011 Central Hudson filed a petition with the PSC seeking to defer for future recovery with carrying charges for the estimated $11.4 million of incremental electric storm restoration expense above the respective rate allowance during the twelve months ended June 30, 2012.
PSC Orders: On April 22, 2013, the Commission issued Orders approving deferral of $8.9 million and denying deferral of $3.7 million of the incremental electric storm restoration expense related to Tropical Storm Irene and the October snowstorm. Regarding the majority of the disallowed costs, the PSC's decision stated that the Company did not meet the third prong requirement which requires the Company not being in an over earnings position. The Commission adopted a staff recommendation to exclude ratemaking normalization adjustments for purposes of calculating authorized electric regulatory earnings, and therefore denied a portion of these petitioned deferrals based on this third prong criterion. In addition, the PSC's Order stated that approximately $0.6 million of the costs related to Tropical Storm Irene should have been allocated to a separate storm, Tropical Storm Lee, and that this separate amount did not meet the materiality threshold for recovery. Central Hudson expects to file a petition for reconsideration and rehearing on the PSC's April 22, 2013 Order challenging the exclusion of the Company's normalization adjustments used to measure earnings. The petition will seek rehearing for reconsideration and recovery of $3.7 million of costs denied by the Commission for deferral accounting treatment. The Company believes that it is entitled to fully recover all of these incremental electric storm restoration expenses; however Central Hudson cannot predict the final outcome of this proceeding.
Other PSC Proceedings
For the quarter ended March 31, 2013, there has been no significant activity related to the following proceedings:
· | Advanced Metering Infrastructure |
· | The American Recovery and Reinvestment Act of 2009 |
· | Energy Efficiency Portfolio Standard and State Energy Planning |
· | AC Transmission Upgrades Proceeding |
OTHER MATTERS
Changes in Accounting Standards
See Note 1 – "Summary of Significant Accounting Policies" and Note 3 – "New Accounting Guidance" for discussion of relevant changes, which discussion is incorporated by reference herein.
Off-Balance Sheet Arrangements
CH Energy Group and Central Hudson do not have any off-balance sheet arrangements.
Climate
While it is possible that some form of global climate change program will be adopted at the federal level in the next term of Congress, it is too early to determine what impact such program will have on CH Energy Group. It should be noted, however, that the Company's calculated CO2 emission levels are relatively small, mainly because the Company does not generate electricity in significant quantities and the electricity it does generate is primarily from zero emission hydroelectric plants. Therefore, federally mandated greenhouse gas reductions or limits on CO2 emissions are not expected to have a material impact on the Company's financial position or results of operations. However, the Company can make no prediction as to the outcome of this matter. If the cost of CO2 emissions causes purchased electricity and natural gas costs to rise, such increases are expected to be collected through automatic adjustment clauses. If sales are depressed by higher costs through price elasticity, the RDMs are expected to prevent an earnings impact on the Company.
FORWARD-LOOKING STATEMENTS
Statements included in this Quarterly Report on Form 10-Q and any documents incorporated by reference which are not historical in nature are intended to be, and are hereby identified as, "forward-looking statements" for purposes of the safe harbor provided by Section 21E of the Exchange Act. Forward-looking statements may be identified by words including "anticipates," "intends," "estimates," "believes," "projects," "expects," "plans," "assumes," "seeks," and similar expressions. Forward-looking statements including, without limitation, those relating to CH Energy Group's and Central Hudson's future business prospects, revenues, proceeds, working capital, investment valuations, liquidity, income, and margins, as well as the acquisition by a subsidiary of Fortis Inc. and the expected timing of the transaction, are subject to certain risks and uncertainties that could cause actual results to differ materially from those indicated in the forward-looking statements, due to several important factors, including those identified from time to time in the forward-looking statements. Those factors include, but are not limited to: the possibility that various conditions precedent to the consummation of the proposed Fortis transaction will not be satisfied or waived, including regulatory approvals of the proposed Fortis transaction and the timing and terms thereof; the impact of delay or failure to complete the proposed Fortis transaction on CH Energy Group's stock price; the costs associated with the proposed Fortis transaction; deviations from normal seasonal weather and storm activity; fuel prices; energy supply and demand; potential future acquisitions; legislative, regulatory, and competitive developments; interest rates; access to capital; market risks; electric and natural gas industry restructuring and cost recovery; the ability to obtain adequate and timely rate relief; changes in fuel supply or costs including future market prices for energy, capacity, and ancillary services; the success of strategies to satisfy electricity, natural gas, fuel oil, and propane requirements; the outcome of pending litigation and certain environmental matters, particularly the status of inactive hazardous waste disposal sites and waste site remediation requirements; and certain presently unknown or unforeseen factors, including, but not limited to, acts of terrorism. CH Energy Group and Central Hudson undertake no obligation to update publicly any forward-looking statements, whether as a result of new information, future events, or otherwise. Given these uncertainties, undue reliance should not be placed on the forward-looking statements.
Additional Information about the Fortis Transaction and Where to Find It
In connection with the proposed acquisition of CH Energy Group by Fortis, CH Energy Group filed a definitive proxy statement with the SEC on May 9, 2012, and has filed other relevant materials with the SEC as well. Investors and stockholders of CH Energy Group are urged to read the proxy statement and other relevant materials filed with the SEC because they contain important information about the proposed acquisition and related matters. Investors and stockholders may obtain a free copy of the proxy statement and other documents filed by CH Energy Group, at the SEC's Web site, www.sec.gov. These documents can also be obtained by investors and stockholders free of charge from CH Energy Group at CH Energy Group's website at www.chenergygroup.com, or by contacting CH Energy Group's Shareholder Relations Department at (845) 486-5204.
ITEM 3 - Quantitative and Qualitative Disclosures About Market Risk
Reference is made to Part II, Item 7A of the Corporations' 10-K Annual Report for a discussion of market risk. The practices employed by CH Energy Group and Central Hudson to mitigate these risks - which were discussed in the Corporations' 10-K Annual Report - continue to operate effectively. For related discussion on this activity, see, in the Financial Statements of the Corporations' 10-K Annual Report, Note 14 – "Accounting for Derivative Instruments and Hedging Activities" and Item 7 – "Management's Discussion and Analysis of Financial Condition and Results of Operations" under the sub-caption "Capital Resources and Liquidity," and Note 9 – "Capitalization - Long-Term Debt" and Item 2 – "Management's Discussion and Analysis of Financial Condition and Results of Operations" under the sub-caption "Financing Program" of this Quarterly Report on Form 10-Q.
ITEM 4 – Controls and Procedures
The Chief Executive Officer and Chief Financial Officer of CH Energy Group and Central Hudson evaluated the effectiveness of the disclosure controls and procedures (as defined in Rule 13a-15(e) under the Securities Exchange Act of 1934, as amended) as of the end of the period covered by this Quarterly Report on Form 10-Q and based on the evaluation, concluded that, as of the end of the period covered by this Quarterly Report on Form 10-Q, the Corporations' controls and procedures are effective.
There were no changes to the Corporations' internal control over financial reporting that occurred during the Corporations' last fiscal quarter that have materially affected, or are reasonably likely to materially affect, the Corporations' internal control over financial reporting.
PART II – OTHER INFORMATION
ITEM 1 – Legal Proceedings
For information about developments regarding certain legal proceedings, see Item 3 ("Legal Proceedings") of the Corporations' 10-K Annual Report, and Note 12 – "Commitments and Contingencies" of that 10-K and/or Note 12 – "Commitments and Contingencies" of this Quarterly Report on Form 10-Q.
RISKS RELATED TO THE PROPOSED ACQUISITION BY FORTIS, INC.
We May Be Unable to Satisfy the Conditions or Obtain the Approvals Required to Complete the Proposed Acquisition
While the proposed acquisition has been approved by CH Energy Group shareholders, the Federal Energy Regulatory Commission and the Committee on Foreign Investment in the United States, the approval of the PSC has not yet been obtained. The PSC may not approve the acquisition or may seek to impose conditions on the completion of the transaction, which could cause the conditions to the acquisition to not be satisfied or which could delay or increase the cost of the transaction. In addition, the occurrence of a material adverse effect could result in a termination of the agreement by Fortis.
The Proposed Acquisition May Not Be Completed, Which May Have a Material Adverse Effect on Our Share Price
Failure to complete the acquisition could negatively affect our share price, including by reducing it to a level at or below the trading range preceding the announcement of the Fortis transaction.
Termination of the Proposed Acquisition Could Result in CH Energy Group Being Required to Pay Termination Fees to Fortis
CH Energy Group will be obligated to reimburse up to $4 million of FortisUS' expenses if (i) FortisUS or CH Energy Group terminates the merger agreement because the acquisition has not been completed by the outside date of August 20, 2013 or FortisUS terminates the merger agreement based on a breach of the merger agreement by CH Energy Group, and (ii) a competing proposal has been made or publicly disclosed and not withdrawn prior to the termination of the merger agreement or applicable breach. In addition, if within twelve months after such termination, a definitive agreement providing for an acquisition transaction is entered into, or an acquisition transaction is consummated by CH Energy Group with, the person who made the acquisition proposal prior to such termination or applicable breach or with any other third party making an acquisition proposal within three months following such termination, CH Energy Group will be obligated to pay FortisUS a termination fee of $19.7 million (less any expense reimbursement previously paid). In no event will more than one termination fee be payable.
For a discussion identifying additional risk factors that could cause actual results to differ materially from those anticipated, see the discussion under "Item 1A – Risk Factors" of the Corporations' 10-K Annual Report.
ITEM 2 - Unregistered Sales of Equity Securities and Use of Proceeds
The following table provides a summary of shares repurchased by CH Energy Group for the quarter ended March 31, 2013:
| | | | Total Number of Shares Purchased(1) | | Average Price Paid per Share(2) | | Total Number of Shares Purchased as Part of Publicly Announced Plans or Programs | | Maximum Number of Shares that May Yet be Purchased Under the Plans or Programs(3) |
January 1-31, 2013 | 1 | - | | $ | - | | - | | - |
February 1-28, 2013 | 1 | 2,111 | | $ | 65.10 | | - | | - |
March 1-31, 2013 | 1 | - | | $ | - | | - | | - |
Total | | | 2,111 | | $ | 65.10 | 1 | - | | |
(1) | Consists of shares surrendered to CH Energy Group in satisfaction of tax withholdings on the vesting of restricted shares. |
(2) | Value at which reacquired shares of CH Energy Group's common stock credited on the date the stock was surrendered. |
(3) | On July 31, 2007, the Board of Directors authorized the repurchase of up to 2,000,000 shares or approximately 13% of CH Energy Group's outstanding common stock on that date, from time to time, over the five year period ending July 31, 2012. Upon expiration, the repurchase program was not extended under the terms of the merger agreement. |
ITEM 4 – Mine Safety Disclosures
Not applicable.
Incorporated herein by reference to the Exhibit Index for this Quarterly Report on Form 10-Q, which is located immediately after the signature pages to this report.
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrants have duly caused this report to be signed on their behalf by the undersigned thereunto duly authorized.
| | CH ENERGY GROUP, INC. |
| | (Registrant) |
| | |
| | |
| | |
| By: | /s/ Kimberly J. Wright |
| | Kimberly J. Wright |
| | Vice President - Accounting and Controller |
| | |
| | |
| | CENTRAL HUDSON GAS & ELECTRIC CORPORATION |
| | (Co-Registrant) |
| | |
| | |
| | |
| By: | /s/ Kimberly J. Wright |
| | Kimberly J. Wright |
| | Controller |
Dated: May 8, 2013
Following is the list of Exhibits, as required by Item 601 of Regulation S-K, filed as part of this Quarterly Report on Form 10-Q:
Exhibit No. (Regulation S-K Item 601 Designation) | | Exhibit Description |
| | |
| | Rule 13a-14(a)/15d-14(a) Certification by Mr. Lant. |
| | |
| | Rule 13a-14(a)/15d-14(a) Certification by Mr. Capone. |
| | |
| | Rule 13a-14(a)/15d-14(a) Certification by Mr. Lant. |
| | |
| | Rule 13a-14(a)/15d-14(a) Certification by Mr. Capone. |
| | |
| | Section 1350 Certification by Mr. Lant. |
| | |
| | Section 1350 Certification by Mr. Capone. |
| | |
| | Section 1350 Certification by Mr. Lant. |
| | |
| | Section 1350 Certification by Mr. Capone. |
| | |
101.INS | | XBRL Instance Document. |
| | |
101.SCH | | XBRL Taxonomy Extension Schema. |
| | |
101.CAL | | XBRL Taxonomy Extension Calculation Linkbase. |
| | |
101.DEF | | XBRL Taxonomy Extension Definition Linkbase. |
| | |
101.LAB | | XBRL Taxonomy Extension Label Linkbase. |
| | |
101.PRE | | XBRL Taxonomy Extension Presentation Linkbase. |