As of August 31, 2024, the first development phase (509 lots) is complete and the second development phase (874 lots) is being developed in four subphases, referred to as Phase 2A (229 lots), Phase 2B (211 lots), Phase 2C (228 lots) and Phase 2D (218 lots). As of August 31, 2024, Phase 2A is approximately 99% complete, Phase 2B is approximately 92% complete and Phase 2C is approximately 27% complete. Phases 2A and 2B are substantially completed with some landscaping items remaining. Phase 2C is expected to be complete by the end of Pure Cycle’s fiscal 2025 and Phase 2D is expected to be complete by the end of calendar 2025.
As of August 31, 2024, the single-family rental business had 14 homes built and rented in Sky Ranch and 17 additional homes forecasted for construction in Phase 2B with 12 currently under contract to build. As noted in the prior quarters, due to the overwhelming demand for rental homes at Sky Ranch, we expect to have a total of 94 homes in Phase 2 with the ability to add more than 200 homes as Sky Ranch builds out.
“Our land development segment continued to ramp up in fiscal 2024, and we expect this trend to continue into the next fiscal year with various phases concurrently under development,” commented Marc Spezialy, CFO of Pure Cycle. “We have delivered 949 finished lots to home builders in Sky Ranch while retaining 31 lots for our single-family rental segment, and we are under construction on 228 lots in Phase 2C scheduled for delivery in fiscal 2025. We will also begin to develop an additional 218 lots in Phase 2D with scheduled delivery in fiscal 2026,” concluded Mr. Spezialy.
Working Capital
We reported working capital (current assets less current liabilities) of $28.5 million as of August 31, 2024, with $22.1 million of cash and cash equivalents.
Full Year 2024 Operational Summary
Water and Wastewater Resource Development
Water deliveries increased for the year ended August 31, 2024, to a record 1,818 acre-feet delivered as compared to 964 acre-feet delivered for 2023. Of this, 77% and 64% were sold to oil and gas operations. Oil and gas operations are highly variable and dependent on oil prices, demand for gas, and timing of development of other leases in our service areas; however, our current expectation is for continued strong demand for oil and gas water sales for the coming years. As Sky Ranch continues to develop, we anticipate continued growth in our residential water and wastewater service revenues. Water and wastewater tap sales increased in 2024 compared to 2023, primarily due to the type of taps (commercial vs. residential) sold during each year and a price increase of water and wastewater taps in 2024.
Land Development
Lot sales revenue increased to $16.0 million for the year ended August 31, 2024 compared to $6.8 million in 2023. Increases during the year are primarily due to an increase in lot deliveries at Sky Ranch and our accelerated development activities with three ongoing phases in our Sky Ranch Master Planned Community. The number of lots delivered increased in 2024 compared to 2023 due to the remaining lots of Phase 2B and beginning lots of Phase 2C having been delivered by the end of fiscal 2024.
Single Family Rentals
Fiscal 2024 represented our first year of rental income for our 14 completed homes. An additional 17 homes are forecasted for construction in Phase 2B in calendar 2025.