Valaris Limited (VAL) 8-KRegulation FD Disclosure
Filed: 18 Aug 14, 12:00am
![]() | Ensco plc Fleet Status Report 18 August 2014 |
Segment / Region / Rig | Design | Water Depth'(1) | Customer/ Status | Day Rate $000′s US | Location | Est. Avail(2) | Comments | |||||||
Floaters | ||||||||||||||
North & South America (excluding Brazil) | ||||||||||||||
ENSCO DS-3 | Drillship, DP3 Samsung | 10000/12000 | BP | Low 500s | U.S. Gulf of Mexico | Jun. 16 | Planned inspection for approx. 15 days in 1Q15. Plus cost adjustments | |||||||
ENSCO DS-4 | Drillship, DP3 Samsung | 10000/12000 | BP | Mid 560s | U.S. Gulf of Mexico | Jul. 16 | Plus cost adjustments | |||||||
ENSCO DS-5 | Drillship, DP3 Samsung | 10000/12000 | Petrobras/Repsol | Mid 430s | U.S. Gulf of Mexico | Jul. 16 | Zero rate for ----- approx. 7 days in 3Q14. Assigned to Repsol for 1 well. Eligible for bonus opportunity up to 17%, plus cost adjustments | |||||||
ENSCO 8500 | Semisubmersible DP | 8500/10000 | Anadarko/Eni | Mid 310s | U.S. Gulf of Mexico | Sep. 15 | -----. Plus cost adjustments and two 1-year same-rate options | |||||||
ENSCO 8501 | Semisubmersible DP | 8500/10000 | Noble Energy | Mid 530s | U.S. Gulf of Mexico | Sep. 14 | Planned inspection for approx. 24 days in 3Q14. Plus cost adjustments | |||||||
ENSCO 8502 | Semisubmersible DP | 8500/10000 | -----Talos | Low 530s | U.S. Gulf of Mexico | Nov. 14 | -----. Plus one 1-well unpriced option. Planned inspection for approx. 24 days in 1Q15 | |||||||
ENSCO 8503 | Semisubmersible DP | 8500/10000 | LLOG | Mid 370s | U.S. Gulf of Mexico | Aug. 14 | -----. Planned upgrade for approx. 60 days in 4Q14/1Q15. Planned inspection for approx. 24 days in 3Q15 | |||||||
ENSCO 8505 | Semisubmersible DP | 8500/10000 | Anadarko/Apache/ Noble Energy | Mid 490s | U.S. Gulf of Mexico | Sep. 14 | Plus cost adjustments. Estimate current customers' drilling programs end in Sep. 14. Contracted to Deep Gulf Energy for 1 well (est. mid Nov. 14 to Jun. 15), mid 370s | |||||||
ENSCO 8506 | Semisubmersible DP | 8500/10000 | Anadarko | Mid 540s | U.S. Gulf of Mexico | Jul. 15 | Plus cost adjustments |
![]() | Ensco plc Fleet Status Report 18 August 2014 |
Segment / Region / Rig | Design | Water Depth'(1) | Customer/ Status | Day Rate $000′s US | Location | Est. Avail(2) | Comments | |||||||
Floaters | ||||||||||||||
Brazil | ||||||||||||||
ENSCO 6001 | Semisubmersible - DP Megathyst | 5700 | Petrobras | Mid 370s | Brazil | Jun. 18 | -----. Mid 250s average rate during planned shipyard upgrade for approx. 65 days in 3Q/4Q14. Plus approx. $16,000 per day amortized Nov. 14 to Jun. 18 for capital upgrades. Plus cost adjustments | |||||||
ENSCO 6002 | Semisubmersible - DP Megathyst | 5700 | Petrobras | Mid 370s | Brazil | Ju1. 18 | -----. Low 170s average rate during planned shipyard upgrade for approx. 65 days in 4Q14. Plus approx. $21,000 per day amortized Jan. 15 to Jul. 18 for capital upgrades. Plus cost adjustments | |||||||
ENSCO 6003 | Semisubmersible - DP Megathyst | 5700 | Petrobras | Low 320s | Brazil | Jan. 17 | Eligible for bonus opportunity up to 15%, plus cost adjustments | |||||||
ENSCO 6004 | Semisubmersible - DP Megathyst | 5700 | Petrobras | Low 320s | Brazil | Oct. 16 | Planned maintenance for approx. 26 days in 1Q15. Eligible for bonus opportunity up to 15%, plus cost adjustments |
![]() | Ensco plc Fleet Status Report 18 August 2014 |
Segment / Region / Rig | Design | Water Depth'(1) | Customer/ Status | Day Rate $000′s US | Location | Est. Avail(2) | Comments | |||||||
Floaters | ||||||||||||||
Europe & Mediterranean | ||||||||||||||
ENSCO 5004 | Semisubmersible - Conv F & G Enhanced Pacesetter | 1500 | -----Mellitah | Low 300s | The Mediterranean | Jan. 17 | -----. Plus periodic rate increases resulting in mid 310s average rate over contract. Plus approx. $30,000 per day for mobilization and reimbursable upgrades amortized Aug. 14 to Jan. 17 | |||||||
Africa | ||||||||||||||
ENSCO DS-1 | Drillship - DP Gusto 10,000 | 6000/10000 | TOTAL | High 350s | Angola | Jan. 16 | Plus cost adjustments and unpriced options. Eligible for bonus opportunity up to 5% | |||||||
ENSCO DS-2 | Drillship - DP Gusto 10,000 | 6000/10000 | TOTAL | High 430s | Angola | Oct. 14 | ||||||||
ENSCO DS-6 | Drillship, DP3 Samsung | 10000/12000 | BP | High 540s | Angola | Feb. 18 | Zero rate for approx. 12 days in 3Q14. Planned inspection for approx. 10 days in 1Q15. Plus approx. $102,000 per day amortized Feb.13 to Feb. 18 for special day rate ahead of mobilization, upgrade costs and reimbursable mobilization expenses. Plus cost adjustments and two 1-year options at mutually agreed rates | |||||||
ENSCO DS-7 | Drillship, DP3 Samsung | 10000/12000 | TOTAL | Mid 630s | Angola | Nov. 16 | Zero rate for approx. 5 days in 3Q14. Plus periodic rate increases resulting in high 640s average rate over three-year contract. Plus approx. $28,000 per day amortized Nov. 13 to Nov. 16 for mobilization |
![]() | Ensco plc Fleet Status Report 18 August 2014 |
Segment / Region / Rig | Design | Water Depth'(1) | Customer/ Status | Day Rate $000′s US | Location | Est. Avail(2) | Comments | |||||||
Floaters | ||||||||||||||
Asia & Pacific Rim | ||||||||||||||
ENSCO 8504 | Semisubmersible DP | 8500/10000 | Shell | Mid 560s | Malaysia | May 15 | Assigned to Inpex in Malaysia Nov. 14 to Mar. 15, mid 560s. Plus cost adjustments. Plus approx. $8,000 per day for mobilization amortized Jul.13 to May 15 | |||||||
ENSCO 5006 | Semisubmersible - Conv Bingo 8,000 | 6200/7500 | Inpex/ Shipyard | Singapore | Mar. 18 | Shipyard upgrades under contract for 40 month drilling program in Australia with estimated commencement 4Q14, initially low 460s. Plus periodic rate increases resulting in mid 490s average rate over drilling program. Plus estimate of approx. $210,000 per day amortized over the duration of the drilling program for capital upgrades and day rates during shipyard stay and mobilizations | ||||||||
ENSCO 5005 | Semisubmersible - Conv F & G Enhanced Pacesetter | 1500 | -----PTTEP | Low 230s | -----Myanmar | Jul. 15 | -----. Plus approx. $11,000 per day for upgrade costs and mobilization amortized Jul. 14 to Jul. 15. Plus one priced option for up to 2 wells | |||||||
Under Construction | ||||||||||||||
ENSCO DS-8 | Drillship, DP3 Samsung GF12000 | 10000/12000 | Under construction/ Contracted | South Korea | 3Q20 | Contracted to Total in Angola from 3Q15 to 3Q20, initially high 610s. Plus periodic rate increases resulting in mid 650s average rate over drilling program. Plus mob fee of approx. $26 million to be amortized over primary contract term and one 1-year priced option | ||||||||
ENSCO DS-9 | Drillship, DP3 Samsung GF12000 | 10000/12000 | Under construction/ Contracted | South Korea | 3Q18 | Contracted to ConocoPhillips in U.S. Gulf of Mexico from 3Q15 to 3Q18, low 550s. Plus mob fee of approx. $32 million to be amortized over primary contract term. Plus cost adjustments and two 1-year unpriced options | ||||||||
ENSCO DS-10 | Drillship, DP3 Samsung GF12000 | 10000/12000 | Under construction | South Korea | 3Q15 |
![]() | Ensco plc Fleet Status Report 18 August 2014 |
Segment / Region / Rig | Design | Water Depth' | Customer/ Status | Day Rate $000′s US | Location | Est. Avail(1) | Comments | |||||||
Jackups | ||||||||||||||
North & South America (excluding Brazil) | ||||||||||||||
U.S. Gulf of Mexico | ||||||||||||||
ENSCO 68 | MLT 84-CE | 400 | Chevron | Mid 140s | Gulf of Mexico | Jan. 15 | Planned inspection for approx. 15 days in 4Q14. Day rate does not include certain extra reimbursable costs. Planned inspection for approx. 14 days in 3Q15 | |||||||
ENSCO 75 | MLT Super 116-C | 400 | Renaissance | Low 130s | Gulf of Mexico | Sep. 14 | Plus cost adjustments | |||||||
ENSCO 81 | MLT 116-C | 350 | Chevron | Mid 140s | Gulf of Mexico | Jan. 15 | Planned inspection for approx. 14 days in 3Q14. Planned maintenance for approx. 28 days in 1Q15 | |||||||
ENSCO 82 | MLT 116-C | 300 | Energy XXI | Low 140s | Gulf of Mexico | Nov. 14 | Rate decreases Sep. 14 to low 130s. Plus cost adjustments. Planned inspection for approx. 10 days in 3Q15 | |||||||
ENSCO 86 | MLT 82 SD-C | 250 | -----Arena | Mid 120s | Gulf of Mexico | Aug. 14 | ----- | |||||||
ENSCO 87 | MLT 116-C | 350 | Fieldwood | High 140s | Gulf of Mexico | Jan. 15 | Planned inspection for approx. 10 days in 3Q14 | |||||||
ENSCO 90 | MLT 82 SD-C | 250 | ----- | ----- | Gulf of Mexico | Aug. 14 | Planned inspection for approx. 10 days in 3Q15 | |||||||
ENSCO 99 | MLT 82 SD-C | 250 | Energy XXI | Mid 120s | Gulf of Mexico | Sep. 14 | Planned maintenance for approx. 14 days in 3Q14. Plus one 1-well option | |||||||
Mexico | ||||||||||||||
ENSCO 83 | MLT 82 SD-C | 250 | Pemex | Low 90s | Mexico | Oct. 16 | -----. Planned inspection for approx. 14 days in 2Q15 | |||||||
ENSCO 89 | MLT 82 SD-C | 250 | Pemex | Low 90s | Mexico | Nov. 15 | Planned inspection for approx. 14 days in 4Q15 | |||||||
ENSCO 93 | MLT 82 SD-C | 250 | Pemex | Low 90s | Mexico | Jun. 15 | Planned inspection for approx. 14 days in 2Q15 | |||||||
ENSCO 98 | MLT 82 SD-C | 250 | Pemex | Low 90s | Mexico | Aug. 15 | Planned inspection for approx. 14 days in 3Q15 |
![]() | Ensco plc Fleet Status Report 18 August 2014 |
Segment / Region / Rig | Design | Water Depth' | Customer/ Status | Day Rate $000′s US | Location | Est. Avail(1) | Comments | |||||||
Jackups | ||||||||||||||
Europe | ||||||||||||||
ENSCO 70 | Hitachi K1032N | 250 | RWE Dea | Low 170s | UK | Jan. 17 | -----. Rate decreases to mid 140s mid Sep. 14 to mid Dec. 14. Planned shipyard upgrade for approx. 30 days in 4Q14/1Q15. Then to Maersk in Denmark to Jan. 17, low 160s. Plus approx. $18,000 per day for capital upgrades amortized Jan. 15 to Jan. 17. Plus cost adjustments and three 1-year unpriced options | |||||||
ENSCO 71 | Hitachi K1032N | 225 | Maersk | Low 170s | Denmark | May 15 | Planned inspection for approx. 23 days in 2Q15. Plus one 1-year priced option and one 1-year option at mutually agreed rate | |||||||
ENSCO 72 | Hitachi K1025N | 225 | Maersk | Low 140s | Denmark | Sep. 15 | -----. Rate increases Sep. 14 to low 170s. Plus one 1-year priced option and one 1-year option at mutually agreed rate | |||||||
ENSCO 80 | MLT 116-CE | 225 | GDF | Mid 140s | Netherlands | Apr. 17 | -----. Plus cost adjustments and unpriced option | |||||||
ENSCO 92 | MLT 116-C | 225 | ConocoPhillips | Mid 160s | UK | Aug. 15 | -----. Plus cost adjustments | |||||||
ENSCO 100 | MLT 150-88-C | 350 | Ithaca | Mid 160s | UK | Mar. 18 | Planned upgrade for approx. 30 days in 1Q15. Plus cost adjustments and two 1-well options. Then to Premier in UK in direct continuation Apr. 15 to Mar. 18, mid 180s | |||||||
ENSCO 101 | KFELS MOD V-A | 400 | BP | High 210s | UK | Jan. 16 | Planned inspection for approx. 28 days in 1Q15. Plus cost adjustments and two 6-month unpriced options | |||||||
ENSCO 102 | KFELS MOD V-A | 400 | ConocoPhillips | Low 210s | UK | Jun. 16 | -----. Rate firm for 8 wells (est. through Apr. 15) thereafter at mutually agreed rate. Plus cost adjustments and unpriced options | |||||||
ENSCO 120 | ENSCO 120 Series | 400 | Nexen | Mid 230s | UK | Nov. 15 | Plus approx. $13,000 per day for mobilization amortized Mar. 14 to Nov. 15. Plus cost adjustments and eleven 1-well options | |||||||
ENSCO 121 | ENSCO 120 Series | 400 | Wintershall | Low 230s | Denmark | Jun. 16 | Plus approx. $11,000 per day for mobilization amortized Jun. 14 to Jun. 16. Plus one 1-year unpriced option |
![]() | Ensco plc Fleet Status Report 18 August 2014 |
Segment / Region / Rig | Design | Water Depth' | Customer/ Status | Day Rate $000′s US | Location | Est. Avail(1) | Comments | |||||||
Jackups | ||||||||||||||
Middle East | ||||||||||||||
ENSCO 53 | F&G L-780 Mod II-C | 300 | NDC | Low 100s | UAE | Feb. 16 | Plus two 1-year unpriced options | |||||||
ENSCO 54 | F&G L-780 Mod II-C | 300 | Shipyard | UAE | Sep. 17 | In shipyard for capital upgrades. Then to Saudi Aramco Sep. 14 to Sep. 17, mid 110s. Plus approx. $39,000 per day for upgrade costs and mobilization amortized Sep. 14 to Sep. 17. Plus one 1-year priced option | ||||||||
ENSCO 58 | F&G L-780 Mod II | 250 | Saudi Aramco | Mid 60s | Saudi Arabia | Jan. 15 | ||||||||
ENSCO 76 | MLT Super 116-C | 350 | Saudi Aramco | Low 100s | Saudi Arabia | Nov. 15 | Planned inspection for approx. 21 days in 4Q14. Rate increases Dec. 14 to high 150s | |||||||
ENSCO 84 | MLT 82 SD-C | 250 | Saudi Aramco | Low 60s | Saudi Arabia | Mar. 16 | Planned inspection for approx. 21 days in 1Q15. Rate increases Mar. 15 to mid 70s | |||||||
ENSCO 88 | MLT 82 SD-C | 250 | Saudi Aramco | Low 100s | Saudi Arabia | Nov. 16 | Plus one 1-year priced option | |||||||
ENSCO 91 | Hitachi Zosen Drill Hope C-150 | 270 | Saudi Aramco | High 60s | Saudi Arabia | Jan. 15 | Planned inspection for approx. 21 days in 1Q15. Plus one 1-year option, mid 90s | |||||||
ENSCO 94 | Hitachi 250-C | 250 | Saudi Aramco | Low 100s | Saudi Arabia | Jun. 16 | Planned inspection for approx. 14 days in 4Q14. Plus one 1-year priced option | |||||||
ENSCO 96 | Hitachi 250-C | 250 | Saudi Aramco | Low 60s | Saudi Arabia | Feb. 16 | -----. Rate increases Feb. 15 to mid 70s | |||||||
ENSCO 97 | MLT 82 SD-C | 250 | Saudi Aramco | Low 60s | Saudi Arabia | Feb. 16 | -----. Rate increases Feb. 15 to mid 70s |
![]() | Ensco plc Fleet Status Report 18 August 2014 |
Segment / Region / Rig | Design | Water Depth' | Customer/ Status | Day Rate $000′s US | Location | Est. Avail(1) | Comments | |||||||
Jackups | ||||||||||||||
Asia & Pacific Rim | ||||||||||||||
ENSCO 52 | F&G L-780 Mod II-C | 300 | Murphy | High 90s | Malaysia | Aug. 17 | Plus cost adjustments and one 1-year unpriced option | |||||||
ENSCO 56 | F&G L-780 Mod II-C | 300 | Pertamina | Mid 110s | Indonesia | Jul. 15 | Plus approx. $3,000 per day for mobilization amortized Jul. 13 to Jul. 15. Plus one 8-month unpriced option | |||||||
ENSCO 67 | MLT 84-CE | 400 | Pertamina | Mid 130s | Indonesia | Mar. 16 | Plus one 8-month unpriced option | |||||||
ENSCO 104 | KFELS MOD V-B | 400 | Shipyard | Singapore | Feb. 15 | In shipyard for planned maintenance and upgrades. Then to SapuraKencana in Malaysia late Aug. 14 to Nov. 14, mid 150s. Next to PVEP in Myanmar to Feb. 15, mid 150s | ||||||||
ENSCO 105 | KFELS MOD V-B | 400 | Shell | Mid 160s | Malaysia | Jun. 15 | Plus approx. $3,000 per day for mobilization amortized Nov. 13 to Nov. 14. Assigned to Shell in China Nov. 14 to May 15, low 190s. Then to Shell in Malaysia to Jun. 15, low 160s. Plus cost adjustments and one 1-year priced option | |||||||
ENSCO 106 | KFELS MOD V-B | 400 | SapuraKencana | High 150s | Malaysia | Aug. 15 | Plus cost adjustments. Then planned inspection and upgrade for approx. 40 days in 4Q14. Next to CPOC in Malaysia Nov. 14 to Aug. 15, initial rate low 150s. Rate increases Jun. 15 to mid 150s | |||||||
ENSCO 107 | KFELS MOD V-B | 400 | OMV | Mid 230s | New Zealand | Feb. 15 | Plus approx. $61,000 per day for contract preparations and mobilization to be amortized Mar. 14 to Feb. 15. Plus cost adjustments and one unpriced option up to 90 days | |||||||
ENSCO 108 | KFELS MOD V-B | 400 | PTTEP | High 150s | Thailand | Apr. 17 | -----. Plus cost adjustments and one 1-year priced option | |||||||
ENSCO 109 | KFELS MOD V-Super B | 350 | Hoang Long | Low 170s | Vietnam | Sep. 14 |
![]() | Ensco plc Fleet Status Report 18 August 2014 |
Segment / Region / Rig | Design | Water Depth' | Customer/ Status | Day Rate $000′s US | Location | Est. Avail(1) | Comments | |||||||
Jackups | ||||||||||||||
Under Construction | ||||||||||||||
ENSCO 140 | ENSCO 140 Series | 340/400 | Under construction | UAE | 2Q16 | |||||||||
ENSCO 141 | ENSCO 140 Series | 340/400 | Under construction | UAE | 3Q16 | |||||||||
ENSCO 122 | ENSCO 120 Series | 400 | Mobilizing/Contracted | ----- | 4Q16 | Mobilizing to Rotterdam. Contracted to NAM in Dutch and UK sector from 4Q14 to 4Q16, low 230s. Plus mob fee of approx. $10 million to be amortized over primary contract term. Plus cost adjustments and two 1-year unpriced options | ||||||||
ENSCO 123 | ENSCO 120 Series | 400 | Under construction | Singapore | 2Q16 | |||||||||
ENSCO 110 | KFELS MOD V-B | 400 | Under construction | Singapore | 1Q15 |
![]() | Ensco plc Fleet Status Report 18 August 2014 |
Segment / Region / Rig | Design | Water Depth' | Customer/ Status | Day Rate $000′s US | Location | Est. Avail(1) | Comments | |||||||
Other | ||||||||||||||
Deepwater Drilling Management | ||||||||||||||
Thunder Horse | Deepwater Semisubmersible | 6000 | BP | Low 100s | U.S. Gulf of Mexico | Jan. 15 | Plus two 1-year priced options, plus cost adjustments | |||||||
Mad Dog | Deepwater Spar Drilling Rig | 4500 | BP | High 60s | U.S. Gulf of Mexico | Jan. 15 | Plus one 1-year priced option, plus cost adjustments | |||||||
Discontinued Operations | ||||||||||||||
Held for Sale | ||||||||||||||
ENSCO 7500 | Semisubmersible DP | 8000 | Mobilizing | Mobilizing to Spain | ||||||||||
ENSCO 6000 | Semisubmersible - DP Amethyst | 3400/4000 | Cold Stacked | Spain | ||||||||||
ENSCO 5002 | Semisubmersible - Conv Aker H-3 | 1000 | Warm Stacked | Singapore | ||||||||||
ENSCO 5001 | Semisubmersible - Conv Sonat | 5000/6500 | PetroSA | Mid 280s | South Africa | Jan. 15 | Planned inspection for approx. 30 days in 3Q14. Plus approx. $7,500 per day for reimbursable mobilization expenses amortized Jan. 13 to Oct. 14. Plus two 120-day options | |||||||
ENSCO 5000 | Semisubmersible - Conv Neptune Pentagon | 2300/2650 | Warm Stacked | South Africa |
![]() | Ensco plc Fleet Status Report 18 August 2014 |