Exhibit 10.2
GMP AMENDMENT
This GMP Amendment amends the Agreement for Guaranteed Maximum Price Construction Services between Owner and Contractor signed by the Owner on January 16, 2013 and the Contractor on February 5, 2013 (the “Agreement”).
Pursuant to Section 3.1 and Addendum 1 of the Agreement, the Owner and Contractor establish a Guaranteed Maximum Price for the Work as set forth below.
The Contractor’s Guaranteed Maximum Price (“GMP”) for the Work is:
One Hundred Nineteen Million, Five Hundred Eighty-One Thousand, One Hundred Eighty-Six and 00/100 Dollars ($119,581,186.00).
In addition to the Agreement, the Guaranteed Maximum Price is based upon the following assumptions:
| | | | |
$ | 1,500,000 | | | for landscaping and irrigation |
| |
$ | 5,000,000 | | | for kitchen equipment |
| |
$ | 5,990,860 | | | for track relocation and accessories including track irrigation, paddock, winners circle and viewing area |
| |
$ | 818,168 | | | for Owner controlled Design Continuation Allowance |
All of the above are Owner Controlled Allowances.
The parties will reconcile allowances as part of the close out process at project completion to determine any net adjustments. Any amount remaining unused by the Contractor at the end of the project shall accrue solely to the Owner.
2. | Shared Savings: It is agreed that upon Final Completion, if the GMP (as adjusted by Change Orders) exceeds the actual Cost of the Work plus the Contractor’s Fee, then the amount of such excess shall be referred to herein as the “Savings,” with the Savings to accrue to the benefit of the parties as follows: 50% to Owner, 50% to Contractor, exclusive of Owner Controlled Allowances. |
It is further agreed that with respect to Union/MBE Premiums line item estimate of $1,000,000 in the Schedule of Values, any unused funds shall accrue solely to the benefit of the Owner and shall not be subject to the 50/50 shared savings split.
All provisions within the Agreement, including but not limited to Section 3.1.6, are hereby amended to conform to this stated agreement.
3. | It is agreed that the Date of Substantial Completion/Open to the Public is May 1, 2014, subject to extensions of time as may be permitted by the Agreement, including extensions required due to delay in the Owner’s securing of Regulatory Approvals and/or delay in completion of Owner’s responsibilities to the extent same are outside the control of the Contractor. |
Liquidated Damages: Fifteen Thousand Dollars ($15,000.00) per day for each day of delay after the fifth (5th) day after the Guaranteed Date of Substantial Completion (as may be modified by time extensions permitted by the Agreement) until Substantial Completion is achieved, up to a total amount of one-half of the Contractor’s Fee.
Savings Clause: Should the Contractor fail to achieve Substantial Completion/Open to the Public by the Guaranteed Date of Substantial Completion of May 1, 2014 (subject to extensions of time as may be permitted by the Agreement), then the Contractor shall not receive the amount of $500,000 from the Contractor’s portion of any shared savings otherwise due the Contractor pursuant to Paragraph 2 above (if any).
The Project Schedule is attached as Exhibit B.
The Project Schedule ties to Exhibit Q, which states the Project’s Design Deliverable Milestones. Exhibit Q is attached hereto and incorporated by reference. It is agreed that the Contractor shall receive an extension of time, day for day, by which the Project is delayed due to the Owner’s design team’s failure to timely comply with the Design Deliverable Milestones only to the extent that it can be proven by the Contractor that Owner and Design Team were unable to provide sufficient supplemental information satisfactory to maintain the overall Construction Schedule.
4. | Construction Contingency: The Construction Contingency is agreed to be $2,491,513.00. The last two sentences of Paragraph 3.1.6 of the Agreement are deleted. To the extent that the Construction Contingency is not depleted at project completion, all remaining funds in the Construction Contingency shall be deemed as “Savings” and distributed between the parties in accordance with the provisions of Paragraph 2 above. This contractor Construction Contingency is included within the current GMP and is completely independent of the Project Contingency. The Project Contingency is excluded from any savings clause calculation. |
7. | Supporting Exhibits for GMP Amendment as follows. |
| | |
Exhibit B: | | Project Schedule |
Exhibit C: | | Contractor’s Personnel |
Exhibit D: | | Not Used |
Exhibit E: | | Drawing Log |
Exhibit F: | | Not Used |
Exhibit G: | | GMP Bid Estimate & Scope Clarifications |
Exhibit Q: | | Design Deliverable Milestones |
8. | Except to the extent amended by this GMP Amendment, the terms and conditions of the Agreement shall remain unchanged and in full force and effect. |
2
IN WITNESS WHEREOF, the parties hereto have caused this Amendment to the Agreement for Guaranteed Maximum Price Construction Services to be as executed as of July 12, 2013.
| | | | | | | | |
PNK (OHIO), LLC | | | | W.G. YATES & SONS CONSTRUCTION COMPANY |
| | | | |
By: | | /s/ Anthony Sanfilippo | | | | By: | | /s/ Chet Nadolski |
| | | | |
Printed Name: | | Anthony Sanfilippo | | | | Printed Name: | | Chet Nadolski |
| | | | |
Title: | | Chief Executive Officer | | | | Title: | | Senior Vice President |
| | | | |
Date: | | 7/12/13 | | | | Date: | | 07/16/13 |
| | |
| | | | PARIC CORPORATION |
| | | |
| | | | By: | | /s/ P. Joseph McKee, III |
| | | |
| | | | Printed Name: | | P. Joseph McKee, III |
| | | |
| | | | Title: | | Chief Executive Officer |
| | | |
| | | | Date: | | 7-15-13 |
3
EXHIBIT B
PROJECT SCHEDULE

YATES CONSTRUCTION
River Downs Race Track / Gaming and Entertainment Center 031
Summary Schedule
PARIC
EXPERIENCE EXCELLENCE.
Activity ID Activity Name Original Duration Duration % Complete Start Finish J F A M J J A S O N D J F A M J J
Milestones
1000 Notice to proceed 0 100% 11-19-12 A
1028 Contract Start Date 0 100% 12-19-12 A
1027 Relocated track ready for operation 0 0% 9-29-13
1169 Central plant operational 0 0% 10-8-13
1142 Gaming floor ready for VLTS 0 0% 3-3-14
1166 Grandstand complete 0 0% 4-28-14
1167 Gaming/BOH complete 0 0% 4-29-14
1168 Final inspections/turnover 0 0% 5-1-14
Design Activities
1192 Demo plan for track 3 100% 11-19-12 A 11-21-12 A
1200 Track Relocation CD’s complete 30 25% 2-18-13 A 3-26-13
1207 Site Utilities CD’s complete 30 25% 2-18-13 A 3-26-13
1203 Site civil CD’s complete 30 25% 2-18-13 A 3-26-13
1202 Test pile package (by structural) 0 100% 3-4-13 A
1201 Issue foundation package(piles & pile caps) 0 100% 3-11-13 A
1193 Concrete podium structure CD’s complete 0 0% 3-18-13*
1194 Steel Structure Gaming/BOH CD’s complete 0 0% 3-18-13*
1428 Porte Cochere foundation revisions complete 0 0% 3-28-13*
Actual Work Critical Remaining… Page 1 of 20 Data Date 3-4-13
Remaining Work Milestone
Date 3-22-13

Activity ID Activity Name Original Duration Duration % Complete Start Finish J F A M J J A S O N D J F A M J J
1195 Grandstand building Sturcture CD’s complete 0 0% 4-1-13*
1209 Track relocation Utilities/Civil CD’s complete 0 0% 4-1-13*
1198 Gaming/BOH MEP (central plant , risers, rough in) 0 0% 4-30-13*
1196 Gaming/BOH exterior cladding CD’s complete 0 0% 5-1-13*
1197 Grandstand Exterior Cladding CD’s complete 0 0% 5-1-13*
1206 Barns/backside buildings CD’s complete 0 0% 5-1-13*
1199 Grandstand MEP ( rough in) 0 0% 5-17-13*
1204 Gaming/BOH Architectural /Interior finishes CD’s complete 0 0% 5-30-13*
1429 FFE support items(light fixtures, signage, etc.) 0 0% 5-30-13*
1426 Gaming/BOH MEP 100% complete 0 0% 6-10-13*
1205 Grandstand Architectural CD’s complete 0 0% 7-1-13*
1427 Grandstand MEP 100% complete 0 0% 7-15-13*
1208 Interior Design/FFE CD’s Complete 0 0% 7-15-13*
Pre-Construction
1002 Demo permits 21 100% 11-19-12 A 12-14-12 A
1004 Demo Subcontracting/Process 21 100% 11-19-12 A 12-11-12 A
1015 Track relocation subcontractor selection/contracting/mobilizatio 21 100% 11-19-12 A 12-11-12 A
1001 Mobilize on site 21 100% 12-15-12 A 1-15-13 A
1016 Track relocation permits 16 50% 12-19-12 A 3-11-13
1003 Environmental protection measures in place 21 100% 1-16-13 A 1-18-13 A
1105 Civil/utility permits 28 100% 2-18-13 A 3-4-13 A
1103 Building foundation permits 14 0% 3-5-13 A 3-17-13
1106 Podium Structure Building permits 10 0% 3-18-13 3-27-13
1005 Track upper surface Bidding/Contracting 45 0% 4-2-13 5-16-13
1006 New barn/building permits 8 0% 5-1-13 5-8-13
1007 New barn/building procurement/subcontracting process 45 0% 5-1-13 6-14-13
Actual Work Critical Remaining… Page 2 of 20 Data Date 3-4-13
Remaining Work Milestone
Date 3-22-13

Activity ID Activity Name Original Duration Duration % Complete Start Finish J F A M J J A S O N D J F A M J J
Demolition
Phase 1
1008 Demo existing barns 28 100% 1-7-13 A 1-18-13 A
1012 Remove existing track rails/posts/markers 28 100% 1-7-13 A 1-18-13 A
1020 Demo existing grand stand 60 90% 1-14-13 A 3-9-13
1009 Demo existing fences as required 21 100% 1-21-13 A 2-7-13 A
1011 Demo existing parking areas as required 28 50% 2-5-13 A 3-17-13
1029 Demo existing service road as required 45 100% 2-13-13 A 2-15-13 A
Earthwork/Infrastructure
Phase 1
1079 Mobilization 12 100% 2-18-13 A 3-1-13 A
1076 Earthwork/Drainage submittals/approvals 12 50% 2-27-13 A 4-16-13
1089 Silt fence/ environmental protection measures 5 100% 2-27-13 A 3-3-13 A
1091 Strip infield stockpile area/cut fill West half 6 10% 3-4-13 A 4-17-13
1094 Gaming building pad and grade 7 10% 3-4-13 A 4-17-13
1090 West Sediment Basin earthwork 2 50% 3-4-13 A 4-11-13
1077 Storm Structure production 20 0% 4-17-13 5-6-13
1095 Stone access roads 7 0% 4-17-13 4-24-13
1096 Fill main entrance area (including surcharge) 12 0% 4-17-13 4-29-13
1092 Strip and stockpile track material 9 0% 4-17-13 4-26-13
1093 Bulk earthwork West track area and pond 20 0% 4-26-13 5-16-13
1411 Storm crew #1 HW15-102 6 0% 5-9-13 5-14-13
1412 Storm crew #1 Ex to 99 3 0% 5-15-13 5-17-13
1097 Cut/Fill balance of track to West parking lot 22 0% 5-16-13 6-7-13
Actual Work Critical Remaining… Page 3 of 20 Data Date 3-4-13
Remaining Work Milestone
Date 3-22-13

Activity ID Activity Name Original Duration Duration % Complete Start Finish J F A M J J A S O N D J F A M J J
1413 Storm crew #1 HW2 to-#60 3 0% 5-22-13 5-24-13
1414 Storm crew #2 HW16 to #118 and tie in 18 0% 5-22-13 6-8-13
1416 Storm crew #1 HW1 to 4 6 0% 5-25-13 5-30-13
1417 Storm crew #1 #3 to #31 2 0% 5-31-13 6-1-13
1418 Storm crew #1 HW3-HW12 crossing track 5 5 0% 6-2-13 6-6-13
1420 Storm crew #1 #31 to #58 West Lot North Area 9 0% 6-7-13 6-15-13
1098 Track underdrain crew 15 0% 6-7-13 6-22-13
1099 Strip and stock topsoil balance of site 7 0% 6-7-13 6-14-13
1415 Storm crew #2 #60 to #63 and #60 to #95 partial N lot drainage 10 0% 6-9-13 6-18-13
1100 Balance of site cut to fill 27 0% 6-14-13 7-11-13
1421 Storm crew #1 #4 to #30 West lot South Area 15 0% 6-16-13 6-30-13
1419 Storm crew #2 #108 to #152 SE area drainage 16 0% 6-19-13 7-4-13
1422 Storm crew #1 #113 to #134 Barn area drainage 12 0% 7-1-13 7-12-13
1423 Storm crew #2 #63 to #87 drainage at south of building pad 9 0% 7-5-13 7-13-13
1101 Grade pond and swales 6 0% 7-11-13 7-17-13
1424 Storm crew #2 #63 to #74 drainage at North of building pad 11 0% 7-14-13 7-24-13
1102 East Barn Area 14 0% 7-17-13 7-31-13
1104 Back pavement and curb islands 18 0% 7-31-13 8-18-13
1220 Landscape/infield grading 24 0% 8-3-13 8-27-13
Construction
Phase 1
Race Track
1080 Dirt Track layout 3 0% 3-26-13 3-29-13
1082 Install aggregate subbase Section 1 42 0% 6-7-13 7-19-13
1180 Install aggregate subbase Section 3 42 0% 6-7-13 7-19-13
1083 Clay base course Section 1 42 0% 6-22-13 8-3-13
1181 Clay base course Section 3 42 0% 6-22-13 8-3-13
1084 Sand cushion course Section 1 42 0% 7-7-13 8-18-13
Actual Work Critical Remaining… Page 4 of 20 Data Date 3-4-13
Remaining Work Milestone
Date 3-22-13

Activity ID
Activity Name
Original Duration
Duration % Complete
Start
Finish
J F A M J J A S O N D J F A M J J
1182
Sand cushion course Section 3
42
0%
7-7-13
8-18-13
1109
New service road
70
0%
7-19-13
9-27-13
1176
Install aggregate subbase Section 2
42
0%
7-19-13
8-30-13
1184
Install aggregate subbase Section 4
42
0%
7-19-13
8-30-13
1177
Clay base course Section 2
42
0%
8-3-13
9-14-13
1185
Clay base course Section 4
42
0%
8-3-13
9-14-13
1178
Sand cushion course Section 2
42
0%
8-18-13
9-29-13
1186
Sand cushion course Section 4
42
0%
8-18-13
9-29-13
1214
Turf track grassing
60
0%
9-2-13*
10-31-13
1085
Install rails
28
0%
9-14-13
10-12-13
1087
landscaping/grassing
60
0%
10-2-13
11-30-13
1086
Install mile markers/finish posts
7
0%
10-12-13
10-19-13
1088
Clean/Punch/Inspection/turnover
12
0%
12-1-13
12-12-13
New 550 Stall Barns
1017
Site Prep
14
0%
6-15-13
6-28-13
1018
Foundations (shallow)
28
0%
6-22-13
7-19-13
1019
MEP underground rough-in
28
0%
7-6-13
8-2-13
1021
Structure erection
72
0%
7-6-13
9-15-13
1022
Stall fit out
72
0%
7-20-13
9-29-13
1023
MEP installations
72
0%
8-3-13
10-13-13
1024
Accessories/trim out/clean/punch
90
0%
8-17-13
11-14-13
1025
Inspections/Turnover
15
0%
11-15-13
11-29-13
New Maintenance Facility
1042
Site Prep
4
0%
6-7-13
6-10-13
1043
Foundations (shallow)
14
0%
6-14-13
6-27-13
1044
MEP underground rough-in
14
0%
6-17-13
6-30-13
1045
Slab on grade
14
0%
6-28-13
7-11-13
Actual Work
Critical Remaining
Page 5 of 20
Data Date 3-4-13
Remaining Work
Milestone
Date 3-22-13

Activity ID
Activity Name
Original Duration
Duration % Complete
Start
Finish
J F A M J J A S O N D J F A M J J
1046
Structure erection
28
0%
7-12-13
8-8-13
1047
MEP/Equipment installations
35
0%
8-9-13
9-12-13
1049
Exterior finishes
14
0%
8-9-13
8-22-13
1048
Interior finishes
28
0%
8-23-13
9-19-13
1050
Trim out/clean/punch
10
0%
9-20-13
9-29-13
1051
Inspections/Turnover
3
0%
9-27-13
9-29-13
New Test Barn
1052
Site Prep
7
0%
6-11-13
6-17-13
1053
Foundations (shallow)
14
0%
6-18-13
7-1-13
1054
MEP underground rough-in
14
0%
7-2-13
7-15-13
1056
Structure erection
42
0%
7-16-13
8-26-13
1057
Stall fit out
56
0%
7-30-13
9-23-13
1058
MEP installations
56
0%
7-30-13
9-23-13
1059
Accessories/trim out/clean/punch
14
0%
9-24-13
10-7-13
1060
Inspections/Turnover
3
0%
10-8-13
10-10-13
New Receiving Barn
1061
Site Prep
7
0%
6-18-13
6-24-13
1062
Foundations (shallow)
14
0%
6-25-13
7-8-13
1063
MEP underground rough-in
14
0%
7-9-13
7-22-13
1065
Structure erection
56
0%
7-23-13
9-16-13
1066
Stall fit out
56
0%
8-6-13
9-30-13
1067
MEP installations
42
0%
8-6-13
9-16-13
1068
Accessories/trim out/clean/punch
14
0%
10-1-13
10-14-13
1069
Inspections/Turnover
3
0%
10-15-13
10-17-13
Mobile Housing Units
Actual Work
Critical Remaining
Page 6 of 20
Data Date 3-4-13
Remaining Work
Milestone
Date 3-22-13

Activity ID
Activity Name
Original Duration
Duration % Complete
Start
Finish
J F A M J J A S O N D J F A M J J
1032
Site Prep/layout
7
0%
5-31-13
6-6-13
1034
MEP underground rough-in
24
0%
6-7-13
6-30-13
1035
Aggregate Base
28
0%
6-21-13
7-18-13
1036
Fine grading
7
0%
7-19-13
7-25-13
1037
Procure units
84
0%
7-26-13
10-17-13
1038
Install units
35
0%
10-18-13
11-21-13
1039
Accessories/trim out/clean/punch
10
0%
11-22-13
12-1-13
1040
Inspections/Turnover
3
0%
11-29-13
12-1-13
Existing Barn Upgrades
1030
Upgrade/Refurbish existing barns
90
0%
5-31-13
8-28-13
New CAFO
1031
CAFO layout
1
0%
8-29-13
8-29-13
1033
Site prep/fine grading
4
0%
8-30-13
9-2-13
1041
Form Footings/slab
10
0%
9-3-13
9-12-13
1055
Vapor barrier
1
0%
9-13-13
9-13-13
1064
Reinforcing steel
3
0%
9-14-13
9-16-13
1070
Pour/Finish-- Slab/footings
1
0%
9-17-13
9-17-13
1071
Form kneewalls
12
0%
9-20-13
10-1-13
1072
Reinforcing in kneewalls
12
0%
9-21-13
10-2-13
1073
Pour/finish kneewalls
12
0%
9-22-13
10-3-13
1074
Strip forms/touch up
2
0%
10-4-13
10-5-13
1075
Final inspection/turnover
1
0%
10-6-13
10-6-13
Phase 2
Gaming/BOH Building
1108
Piling
30
0%
3-18-13
4-16-13
Actual Work
Critical Remaining
Page 7 of 20
Data Date 3-4-13
Remaining Work
Milestone
Date 3-22-13

Activity ID
Activity Name
Original Duration
Duration % Complete
Start
Finish
J F A M J J A S O N D J F A M J J
1110
Pile caps/foundations/grade beams
30
0%
3-28-13
4-26-13
1111
Structure(verticals/columns) to gaming level/BOH level 1
45
0%
4-12-13
5-26-13
1112
Service level slab/paving/docks
60
0%
4-22-13
6-20-13
1113
Gaming/BOH level 1 elevated deck
45
0%
5-12-13
6-25-13
1120
Fill for porte cochere
21
0%
5-31-13
6-20-13
1114
Gaming structural steel erection
42
0%
6-11-13
7-22-13
1121
Porte Cochere structure
75
0%
6-21-13
9-3-13
1115
Gaming roof deck
28
0%
7-9-13
8-5-13
1116
BOH level 1& 2 structural steel erection
49
0%
7-16-13
9-2-13
1119
Roofing all areas
60
0%
8-6-13
10-4-13
1174
Exterior Framing/Sheathing Gaming areas
30
0%
8-6-13
9-4-13
1117
BOH roof deck
28
0%
8-15-13
9-11-13
1118
Set mechanical equipment (central plant)
28
0%
8-15-13
9-11-13
1173
BOH Mezz level deck
20
0%
8-15-13
9-3-13
1126
MEP rough in for Central Plant
45
0%
8-25-13
10-8-13
1125
Interior MEP rough in for Gaming
90
0%
9-4-13
12-2-13
1129
Interior framing/drop ceilings for Gaming
30
0%
9-4-13
10-3-13
1123
Exterior framing/sheathing BOH
90
0%
9-12-13
12-10-13
1127
MEP rough in BOH
45
0%
9-12-13
10-26-13
1124
Exterior EFIS/panels/split face/glass&glazing
120
0%
9-22-13
1-19-14
1128
Gaming raised flooring system (Walker duct)
28
0%
9-25-13
10-22-13
1131
Kitchen equipment
60
0%
10-4-13
12-2-13
1132
Interior finishes/theming for Gaming/restraunts
150
0%
10-4-13
3-2-14
1134
Service bars/restrooms
90
0%
10-4-13
1-1-14
1135
IDF rooms
60
0%
10-4-13
12-2-13
1130
Interior framing BOH
28
0%
10-12-13
11-8-13
1122
Porte Cochere finishes/paving/landscaping
150
0%
11-3-13
4-1-14
1137
Warehouse/BOH finishes/trim out
120
0%
11-9-13
3-8-14
1136
MEP trim outs
120
0%
12-3-13
4-1-14
1133
Flooring/VLT bases for gaming
21
0%
2-11-14
3-3-14
Actual Work
Critical Remaining
Page 8 of 20
Data Date 3-4-13
Remaining Work
Milestone
Date 3-22-13

Activity ID Activity Name Original Duration Duration % Complete Start Finish J F A M J J A S O N D J F A M J J
1138 Install VLTS/testing 60 0% 2-16-14 4-16-14
1140 Warehouse FFE/ equipment 14 0% 3-9-14 3-22-14
1139 Kitchen burn in / training/FFE 28 0% 4-2-14 4-29-14
Grand Stand Building
1141 Piling installation 21 0% 4-7-13 4-27-13
1143 Pile caps/grade beams 21 0% 4-14-13 5-4-13
1144 Slab on grade(grandstand service level) 28 0% 5-31-13 6-27-13
1145 Jockey locker room knee walls 14 0% 6-28-13 7-11-13
1148 Columns/vertical to Gaming level (inc. promenade) 35 0% 6-28-13 8-1-13
1146 Back fill under jockey locker room slab 4 0% 7-12-13 7-15-13
1147 Jockey locker room slab 14 0% 7-16-13 7-29-13
1149 Grandstand gaming level elevated deck 35 0% 7-18-13 8-21-13
1150 Columns/verticals to crows nest level 25 0% 8-7-13 8-31-13
1151 Elevated deck at crows nest level 45 0% 8-22-13 10-5-13
1153 Set Precast for grandstand seating levels 28 0% 10-6-13 11-2-13
1156 MEP Rough ins 60 0% 10-6-13 12-4-13
1157 Interior framing/partition walls 30 0% 10-6-13 11-4-13
1152 Roof truss/steel erection 42 0% 11-3-13 12-14-13
1155 Exterior finishes 90 0% 11-3-13 1-31-14
1159 Jockey locker room finishes 90 0% 11-5-13 2-2-14
1154 Roofing 30 0% 11-23-13 12-22-13
1160 Finishes & fit out 90 0% 12-15-13 3-14-14
1162 Crows nest framing 14 0% 12-23-13 1-5-14
1165 Seating/concourse area finishes 75 0% 12-23-13 3-7-14
1163 Crows nest MEP/equipment installation 30 0% 1-6-14 2-4-14
1164 Crows nest finishes/FFE 60 0% 1-6-14 3-6-14
1158 Concessions/restrooms finishes 60 0% 2-1-14 4-1-14
1161 Gaming equipment/FFE 60 0% 2-28-14 4-28-14
Actual Work Critical Remaining ... Page 9 of 20 Data Date 3-4-13
Remaining Work Milestone
Date 3-22-13

Activity ID Activity Name Original Duration Duration % Complete Start Finish J F A M J J A S O N D J F A M J J
New Permanent Paddock
1170 Complete new permanent paddock Area 60 0% 12-23-13 2-20-14
Parking Lots
1171 Parking lots/hardscape/landscape 120 0% 12-3-13 4-1-14
1187 Demo Existing OTB facility 21 0% 5-12-14 6-1-14
1188 Complete small parking area in way of existing OTB 35 0% 6-2-14 7-6-14
New Permanent Toteboard
1172 Relocate permanent toteboard 30 0% 12-23-13 1-21-14
Podium Concrete Details
Sitework
1189 Building pad to grade 30 0% 3-11-13* 4-9-13
1190 Porte-Cochere area fill/place surcharge 14 0% 3-11-13 3-24-13
1191 Surcharge 30 0% 3-25-13 4-23-13
1308 Remove surcharge 5 0% 4-24-13 4-28-13
Structural
1210 Piling Rig #1 (Section 1A thru 8A) 20 0% 3-18-13 4-6-13
1425 Piling Rig #2 (Section 1B thru 8B) 20 0% 3-22-13 4-10-13
1211 Pile caps/Grade beams 25 0% 3-22-13 4-26-13
1404 Remaining Pilings(in way of surcharge) 18 0% 4-29-13 5-16-13
1405 Pile Caps/Grade Beams(in way of surcharge) 18 0% 5-9-13 5-26-13
1406 Retaining Wall 20 0% 5-18-13 6-6-13
Section 1A
1430 Columns/Verticals to podium deck 3 0% 3-26-13 3-29-13
1431 Form deck 10 0% 3-29-13 4-12-13
Actual Work Critical Remaining ... Page 10 of 20 Data Date 3-4-13
Remaining Work Milestone
Date 3-22-13

\Activity ID Activity Name Original Duration Duration % Complete Start Finish J F A M J J A S O N D J F A M J J
1432 Plumbing rough in on deck 2 0% 4-5-13 4-9-13
1433 HVAC rough in on deck 2 0% 4-5-13 4-9-13
1434 Electrical rough in on deck 3 0% 4-5-13 4-10-13
1435 Place Rebar 5 0% 4-9-13 4-16-13
1436 Prep/Form 3 0% 4-11-13 4-16-13
1437 Place and finish concrete deck 1 0% 4-16-13 4-17-13
Section 2A
1439 Columns/Verticals to podium deck 3 0% 3-29-13 4-3-13
1440 Form deck 10 0% 4-12-13 4-26-13
1441 Plumbing rough in on deck 2 0% 4-19-13 4-23-13
1442 HVAC rough in on deck 2 0% 4-19-13 4-23-13
1443 Electrical rough in on deck 3 0% 4-19-13 4-24-13
1444 Place Rebar 5 0% 4-23-13 4-30-13
1445 Prep/Form 3 0% 4-25-13 4-30-13
1446 Place and finish concrete deck 1 0% 4-30-13 5-1-13
Section 3A
1448 Columns/Verticals to podium deck 3 0% 4-3-13 4-8-13
1449 Form deck 5 0% 4-26-13 5-3-13
1450 Plumbing rough in on deck 2 0% 4-29-13 5-1-13
1451 HVAC rough in on deck 2 0% 4-29-13 5-1-13
1452 Electrical rough in on deck 3 0% 4-29-13 5-2-13
1453 Place Rebar 4 0% 5-1-13 5-7-13
1454 Prep/Form 2 0% 5-3-13 5-7-13
1455 Place and finish concrete deck 1 0% 5-7-13 5-8-13
Section 4A
1461 Columns/Verticals to podium deck 3 0% 4-8-13 4-11-13
1462 Form deck 5 0% 5-3-13 5-10-13
1463 Plumbing rough in on deck 2 0% 5-6-13 5-8-13
1464 HVAC rough in on deck 2 0% 5-6-13 5-8-13
1465 Electrical rough in on deck 3 0% 5-6-13 5-9-13
Actual Work Critical Remaining ... Page 11 of 20 Data Date 3-4-13
Remaining Work Milestone
Date 3-22-13

Activity ID Activity Name Original Duration Duration % Complete Start Finish J F A M J J A S O N D J F A M J J
1466 Place Rebar 4 0% 5-8-13 5-14-13
1467 Prep/Form 2 0% 5-10-13 5-14-13
1468 Place and finish concrete deck 1 0% 5-14-13 5-15-13
Section 5A
1469 Columns/Verticals to podium deck 3 0% 4-11-13 4-16-13
1470 Form deck 5 0% 5-10-13 5-17-13
1471 Plumbing rough in on deck 2 0% 5-13-13 5-15-13
1472 HVAC rough in on deck 2 0% 5-13-13 5-15-13
1473 Electrical rough in on deck 3 0% 5-13-13 5-16-13
1474 Place Rebar 4 0% 5-15-13 5-21-13
1475 Prep/Form 2 0% 5-17-13 5-21-13
1476 Place and finish concrete deck 1 0% 5-21-13 5-22-13
Section 6A
1477 Columns/Verticals to podium deck 3 0% 4-16-13 4-19-13
1478 Form deck 5 0% 5-17-13 5-24-13
1479 Plumbing rough in on deck 2 0% 5-20-13 5-22-13
1480 HVAC rough in on deck 2 0% 5-20-13 5-22-13
1481 Electrical rough in on deck 3 0% 5-20-13 5-23-13
1482 Place Rebar 4 0% 5-22-13 5-28-13
1483 Prep/Form 2 0% 5-24-13 5-28-13
1484 Place and finish concrete deck 1 0% 5-28-13 5-29-13
Section 7A
1485 Columns/Verticals to podium deck 3 0% 6-6-13 6-11-13
1486 Form deck 5 0% 6-11-13 6-18-13
1487 Plumbing rough in on deck 2 0% 6-12-13 6-14-13
1488 HVAC rough in on deck 2 0% 6-12-13 6-14-13
1489 Electrical rough in on deck 3 0% 6-12-13 6-17-13
1490 Place Rebar 4 0% 6-14-13 6-20-13
1491 Prep/Form 2 0% 6-18-13 6-20-13
1492 Place and finish concrete deck 1 0% 6-20-13 6-21-13
Section 8A
Actual Work Critical Remaining ... Page 12 of 20 Data Date 3-4-13
Remaining Work Milestone
Date 3-22-13

Activity ID
Activity Name
Original Duration
Duration % Complete
Start
Finish
J F A M J J A S O N D J F A M J J
1493 Columns/Verticals to podium deck 3 0% 6-11-13 6-14-13
1494 Form deck 5 0% 6-18-13 6-25-13
1495 Plumbing rough in on deck 2 0% 6-19-13 6-21-13
1496 HVAC rough in on deck 2 0% 6-19-13 6-21-13
1497 Electrical rough in on deck 3 0% 6-19-13 6-24-13
1498 Place Rebar 4 0% 6-21-13 6-27-13
1499 Prep/Form 2 0% 6-25-13 6-27-13
1500 Place and finish concrete deck 1 0% 6-27-13 6-28-13
Porte Cochere
1501 Grade Beams/footings 1 0% 6-6-13 6-7-13
1573 Form SOG 10 0% 6-28-13 7-12-13
1574 Plumbing rough in SOG 4 0% 6-28-13 7-4-13
1575 Electrical rough in SOG 4 0% 7-1-13 7-5-13
1576 Vapor Barrier SOG 1 0% 7-5-13 7-8-13
1577 Reinforcing for SOG 5 0% 7-8-13 7-15-13
1578 Pour/Finish SOG 1 0% 7-15-13 7-16-13
Section 1B
1509 Columns/Verticals to podium deck 3 0% 4-1-13 4-3-13
1510 Form deck 8 0% 4-5-13 4-16-13
1511 Plumbing rough in on deck 2 0% 4-10-13 4-11-13
1512 HVAC rough in on deck 2 0% 4-10-13 4-11-13
1513 Electrical rough in on deck 3 0% 4-10-13 4-12-13
1514 Place Rebar 4 0% 4-12-13 4-17-13
1515 Prep/Form 3 0% 4-17-13 4-19-13
1516 Place and finish concrete deck 1 0% 4-22-13 4-22-13
Section 2B
1517 Columns/Verticals to podium deck 3 0% 4-4-13 4-8-13
1518 Form deck 8 0% 4-17-13 4-26-13
1519 Plumbing rough in on deck 2 0% 4-22-13 4-23-13
1520 HVAC rough in on deck 2 0% 4-22-13 4-23-13
Actual Work Critical Remaining... Page 13 of 20 Data Date 3-4-13
Remaining Work Milestone Date 3-22-13

Activity ID
Activity Name
Original Duration
Duration % Complete
Start
Finish
J F A M J J A S O N D J F A M J J
1521 Electrical rough in on deck 3 0% 4-22-13 4-24-13
1522 Place Rebar 4 0% 4-24-13 4-29-13
1523 Prep/Form 3 0% 4-29-13 5-1-13
1524 Place and finish concrete deck 1 0% 5-2-13 5-2-13
Section 3B
1525 Columns/Verticals to podium deck 3 0% 4-9-13 4-11-13
1526 Form deck 5 0% 4-29-13 5-3-13
1527 Plumbing rough in on deck 2 0% 4-30-13 5-1-13
1528 HVAC rough in on deck 2 0% 4-30-13 5-1-13
1529 Electrical rough in on deck 3 0% 4-30-13 5-2-13
1530 Place Rebar 4 0% 5-2-13 5-7-13
1531 Prep/Form 2 0% 5-6-13 5-7-13
1532 Place and finish concrete deck 1 0% 5-8-13 5-8-13
Section 4B
1533 Columns/Verticals to podium deck 3 0% 4-12-13 4-16-13
1534 Form deck 5 0% 5-6-13 5-10-13
1535 Plumbing rough in on deck 2 0% 5-7-13 5-8-13
1536 HVAC rough in on deck 2 0% 5-7-13 5-8-13
1537 Electrical rough in on deck 3 0% 5-7-13 5-9-13
1538 Place Rebar 4 0% 5-9-13 5-14-13
1539 Prep/Form 2 0% 5-13-13 5-14-13
1540 Place and finish concrete deck 1 0% 5-15-13 5-15-13
Section 5B
1541 Columns/Verticals to podium deck 3 0% 4-17-13 4-19-13
1542 Form deck 5 0% 5-13-13 5-17-13
1543 Plumbing rough in on deck 2 0% 5-14-13 5-15-13
1544 HVAC rough in on deck 2 0% 5-14-13 5-15-13
1545 Electrical rough in on deck 3 0% 5-14-13 5-16-13
1546 Place Rebar 4 0% 5-16-13 5-21-13
1547 Prep/Form 2 0% 5-20-13 5-21-13
Actual Work Critical Remaining... Page 14 of 20 Data Date 3-4-13
Remaining Work Milestone Date 3-22-13

Activity ID
Activity Name
Original Duration
Duration % Complete
Start
Finish
J F A M J J A S O N D J F A M J J
1548 Place and finish concrete deck 1 0% 5-22-13 5-22-13
Section 6B
1549 Columns/Verticals to podium deck 3 0% 4-22-13 4-24-13
1550 Form deck 5 0% 5-20-13 5-24-13
1551 Plumbing rough in on deck 2 0% 5-21-13 5-22-13
1552 HVAC rough in on deck 2 0% 5-21-13 5-22-13
1553 Electrical rough in on deck 3 0% 5-21-13 5-23-13
1554 Place Rebar 4 0% 5-23-13 5-28-13
1555 Prep/Form 2 0% 5-27-13 5-28-13
1556 Place and finish concrete deck 1 0% 5-29-13 5-29-13
Section 7B
1557 Columns/Verticals to podium deck 3 0% 4-25-13 4-29-13
1558 Form deck 5 0% 5-27-13 5-31-13
1559 Plumbing rough in on deck 2 0% 5-28-13 5-29-13
1560 HVAC rough in on deck 2 0% 5-28-13 5-29-13
1561 Electrical rough in on deck 3 0% 5-28-13 5-30-13
1562 Place Rebar 4 0% 5-30-13 6-4-13
1563 Prep/Form 2 0% 6-3-13 6-4-13
1564 Place and finish concrete deck 1 0% 6-5-13 6-5-13
Section 8B
1565 Columns/Verticals to podium deck 3 0% 6-14-13 6-19-13
1566 Form deck 5 0% 6-25-13 7-2-13
1567 Plumbing rough in on deck 2 0% 6-26-13 6-28-13
1568 HVAC rough in on deck 2 0% 6-26-13 6-28-13
1569 Electrical rough in on deck 3 0% 6-26-13 7-1-13
1570 Place Rebar 4 0% 6-28-13 7-4-13
1571 Prep/Form 2 0% 7-2-13 7-4-13
1572 Place and finish concrete deck 1 0% 7-4-13 7-5-13
Steel Seq. 11
1579 Produce shop drawings 15 0% 3-18-13* 4-5-13
1595 Shop drawing approvals 5 0% 4-8-13 4-12-13
Actual Work
Remaining Work
Critical Remaining...
Milestone
Page 15 of 20
Data Date 3-4-13
Date 3-22-13

Activity ID
Activity Name
Original Duration
Duration % Complete
Start
Finish
J F A M J J A S O N D J F A M J J
1596 Scrub/program 10 0% 4-15-13 4-26-13
1597 Procure/Fabricate steel 32 0% 4-29-13 6-11-13
1598 Delivery/unload/shake out 2 0% 6-12-13 6-13-13
1599 Erect Steel 3 0% 6-14-13 6-18-13
1600 Bolt/ Detail/ Deck 3 0% 6-19-13 6-21-13
Steel Seq. 12
1601 Produce shop drawings 15 0% 3-18-13 4-5-13
1602 Shop drawing approvals 5 0% 4-8-13 4-12-13
1603 Scrub/program 10 0% 4-15-13 4-26-13
1604 Procure/Fabricate steel 35 0% 4-29-13 6-14-13
1605 Delivery/unload/shake out 2 0% 6-17-13 6-18-13
1606 Erect Steel 4 0% 6-19-13 6-24-13
1607 Bolt/ Detail/ Deck 4 0% 6-25-13 6-28-13
Steel Seq. 13
1608 Produce shop drawings 20 0% 3-18-13 4-12-13
1609 Shop drawing approvals 5 0% 4-15-13 4-19-13
1610 Scrub/program 10 0% 4-22-13 5-3-13
1611 Procure/Fabricate steel 34 0% 5-6-13 6-20-13
1612 Delivery/unload/shake out 2 0% 6-21-13 6-24-13
1613 Erect Steel 4 0% 6-25-13 6-28-13
1614 Bolt/ Detail/ Deck 5 0% 7-1-13 7-5-13
Steel Seq. 14
1615 Produce shop drawings 25 0% 3-18-13 4-19-13
1616 Shop drawing approvals 5 0% 4-22-13 4-26-13
1617 Scrub/program 10 0% 4-29-13 5-10-13
1618 Procure/Fabricate steel 32 0% 5-13-13 6-25-13
1619 Delivery/unload/shake out 3 0% 6-26-13 6-28-13
1620 Erect Steel 5 0% 7-1-13 7-5-13
1621 Bolt/ Detail/ Deck 5 0% 7-8-13 7-12-13
Steel Seq. 15
1622 Produce shop drawings 30 0% 3-18-13 4-26-13
Actual Work
Remaining Work
Critical Remaining...
Milestone
Page 16 of 20
Data Date 3-4-13
Date 3-22-13

Activity ID
Activity Name
Original Duration
Duration % Complete
Start
Finish
J F A M J J A S O N D J F A M J J
1623 Shop drawing approvals 5 0% 4-29-13 5-3-13
1624 Scrub/program 10 0% 5-6-13 5-17-13
1625 Procure/Fabricate steel 31 0% 5-20-13 7-1-13
1626 Delivery/unload/shake out 4 0% 7-2-13 7-5-13
1627 Erect Steel 5 0% 7-8-13 7-12-13
1628 Bolt/ Detail/ Deck 5 0% 7-15-13 7-19-13
Steel Seq. 16
1629 Produce shop drawings 30 0% 3-25-13 5-3-13
1630 Shop drawing approvals 5 0% 5-6-13 5-10-13
1631 Scrub/program 10 0% 5-13-13 5-24-13
1632 Procure/Fabricate steel 34 0% 5-27-13 7-11-13
1633 Delivery/unload/shake out 2 0% 7-12-13 7-15-13
1634 Erect Steel 4 0% 7-16-13 7-19-13
1635 Bolt/ Detail/ Deck 5 0% 7-22-13 7-26-13
Steel Seq. 17.1
1636 Produce shop drawings 30 0% 4-1-13 5-10-13
1637 Shop drawing approvals 5 0% 5-13-13 5-17-13
1638 Scrub/program 10 0% 5-20-13 5-31-13
1639 Procure/Fabricate steel 32 0% 6-3-13 7-16-13
1640 Delivery/unload/shake out 3 0% 7-17-13 7-19-13
1641 Erect Steel 7 0% 7-22-13 7-30-13
1642 Bolt/ Detail/ Deck 5 0% 7-31-13 8-6-13
Steel Seq. 18 Porte Cohere
1643 Produce shop drawings 30 0% 4-8-13 5-17-13
1644 Shop drawing approvals 5 0% 5-20-13 5-24-13
1645 Scrub/program 10 0% 5-27-13 6-7-13
1646 Procure/Fabricate steel 34 0% 6-10-13 7-25-13
1647 Delivery/unload/shake out 2 0% 7-26-13 7-29-13
1648 Erect Steel 4 0% 7-30-13 8-2-13
1649 Bolt/ Detail/ Deck 5 0% 8-5-13 8-9-13
Steel Seq. 21
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 17 of 20
Data Date 3-4-13
Date 3-22-13

Activity ID
Activity Name
Original Duration
Duration % Complete
Start
Finish
J F A M J J A S O N D J F A M J J
1650 Produce shop drawings 20 0% 3-18-13 4-12-13
1651 Shop drawing approvals 5 0% 4-15-13 4-19-13
1652 Scrub/program 10 0% 4-22-13 5-3-13
1653 Procure/Fabricate steel 31 0% 5-6-13 6-17-13
1654 Delivery/unload/shake out 3 0% 6-18-13 6-20-13
1655 Erect Steel 7 0% 6-21-13 7-1-13
1656 Bolt/ Detail/ Deck 6 0% 7-2-13 7-9-13
Steel seq. 21.1 Operable Partition Framing
1657 Produce shop drawings 20 0% 3-18-13 4-12-13
1658 Shop drawing approvals 5 0% 4-15-13 4-19-13
1659 Scrub/program 10 0% 4-22-13 5-3-13
1660 Procure/Fabricate steel 39 0% 5-6-13 6-27-13
1661 Delivery/unload/shake out 2 0% 6-28-13 7-1-13
1662 Erect Steel 4 0% 7-2-13 7-5-13
1663 Bolt/ Detail/ Deck 2 0% 7-8-13 7-9-13
Steel Seq. 22
1664 Produce shop drawings 20 0% 3-25-13 4-19-13
1665 Shop drawing approvals 5 0% 4-22-13 4-26-13
1666 Scrub/program 10 0% 4-29-13 5-10-13
1667 Procure/Fabricate steel 34 0% 5-13-13 6-27-13
1668 Delivery/unload/shake out 2 0% 6-28-13 7-1-13
1669 Erect Steel 2 0% 7-2-13 7-3-13
1670 Bolt/ Detail/ Deck 3 0% 7-10-13 7-12-13
Steel Seq. 23
1671 Produce shop drawings 20 0% 4-1-13 4-26-13
1672 Shop drawing approvals 5 0% 4-29-13 5-3-13
1673 Scrub/program 10 0% 5-6-13 5-17-13
1674 Procure/Fabricate steel 31 0% 5-20-13 7-1-13
1675 Delivery/unload/shake out 2 0% 7-2-13 7-3-13
1676 Erect Steel 4 0% 7-4-13 7-9-13
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 18 of 20
Data Date 3-4-13
Date 3-22-13

Activity ID
Activity Name
Original Duration
Duration % Complete
Start
Finish
J F A M J J A S O N D J F A M J J
1677 Bolt/ Detail/ Deck 3 0% 7-15-13 7-17-13
Steel Seq.. 24
1678 Produce shop drawings 20 0% 4-8-13 5-3-13
1679 Shop drawing approvals 5 0% 5-6-13 5-10-13
1680 Scrub/program 10 0% 5-13-13 5-24-13
1681 Procure/Fabricate steel 29 0% 5-27-13 7-4-13
1682 Delivery/unload/shake out 2 0% 7-5-13 7-8-13
1683 Erect Steel 2 0% 7-10-13 7-11-13
1684 Bolt/ Detail/ Deck 4 0% 7-18-13 7-23-13
Steel Seq. 25
1685 Produce shop drawings 20 0% 4-22-13 5-17-13
1686 Shop drawing approvals 5 0% 5-20-13 5-24-13
1687 Scrub/program 10 0% 5-27-13 6-7-13
1688 Procure/Fabricate steel 23 0% 6-10-13 7-10-13
1689 Delivery/unload/shake out 1 0% 7-11-13 7-11-13
1690 Erect Steel 3 0% 7-12-13 7-16-13
1691 Bolt/ Detail/ Deck 5 0% 7-24-13 7-30-13
Steel Seq. 17
1692 Produce shop drawings 20 0% 4-15-13 5-10-13
1693 Shop drawing approvals 5 0% 5-13-13 5-17-13
1694 Scrub/program 10 0% 5-20-13 5-31-13
1695 Procure/Fabricate steel 28 0% 6-3-13 7-10-13
1696 Delivery/unload/shake out 3 0% 7-11-13 7-15-13
1697 Erect Steel 4 0% 7-17-13 7-22-13
1698 Bolt/ Detail/ Deck 4 0% 7-31-13 8-5-13
Steel Seq. 26 Canopy and Padock
1699 Produce shop drawings 20 0% 4-22-13 5-17-13
1700 Shop drawing approvals 5 0% 5-20-13 5-24-13
1701 Scrub/program 10 0% 5-27-13 6-7-13
1702 Procure/Fabricate steel 23 0% 6-10-13 7-10-13
1703 Delivery/unload/shake out 3 0% 7-11-13 7-15-13
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 19 of 20
Data Date 3-4-13
Date 3-22-13

Activity ID
Activity Name
Original Duration
Duration % Complete
Start
Finish
J F A M J J A S O N D J F A M J J
1704 Erect Steel
4
0%
7-23-13
7-26-13
1705 Bolt/ Detail/ Deck
4
0%
7-29-13
8-1-13
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 20 of 20
Data Date 3-4-13
Date 3-22-13
EXHIBIT C
CONTRACTOR’S PERSONNEL
EXHIBIT C
CONTRACTOR’S PERSONNEL
Pre-approved Reimbursable Contractor’s Personnel On site
Accounting Clerk - TBD
Document Control Clerk - Cindy Johnson
Project Executive - Stan Wielgosz
Project Executive - Steve L’Hommedieu
Senior Project Manager - Jere Sheehan
Project Manager (Finishes) - TBD
Assistant Project Manager (MEP) - TBD
Assistant Project Manager (Site/Track) - Gavin Ackermann
Assistant Project Manager (Core & Shell) - TBD
General Superintendent - Marvin Chapman
Superintendent (Core & Shell) - Art Petrucci
Superintendent (Site/Track) - Jack Holecz
Site Safety Professional - Kurt Gore
Senior Project Manager (Compressed Schedule) - Scott J. Davis
Superintendent (Compressed Schedule) - TBD
Designer / Expeditor - TBD
Pre-Approved Reimbursable Contractor’s Personnel Off Site
Scheduling Personnel
Purchasing Personnel
Accounting Personnel
Estimating Personnel
IT Personnel
Safety / Quality Personnel
** | Personnel may be added or deleted subject to Owner’s approval; such approval shall not be unreasonably withheld. |
** | Rates to be provided to Owner under separate document and shall be subject to audit verification. |
EXHIBIT D
CONTRACTOR’S OWNED EQUIPMENT
WITH RENTAL RATES
EXHIBIT E
DRAWING LOG
EXHIBIT E
PM Drawing Log
| | | | |
Projects: 53284- - 53284- | | Types: First - Last | | Drawings: First - Last |
All Dates | | | | Show Revisions: Y |
Project: 53284- YATES/PARIC PR RIVER DOWNS; OHIO
Drawing Type: ARCHITECT ARCHITECTUAL DRAWINGS
| | | | | | | | | | | | | | |
Drawing | | | | | | Issued Date | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | Distribution Notes | | |
A0.03 | | GENERAL NOTES, ABBREVIATION & LEGEND | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A0.08 | | WALL TYPES | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A0.09 | | WALLY TYPES | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A1.00 | | OVERALL SITE PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A1.01 | | ENLARGED PARTIAL SITE PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A1.02 | | ENLARGED PARTIAL SITE PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A1.03 | | ENLARGED PARTIAL SITE PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A1.40 | | EGRESS PLAN-SERVICE LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A1.41 | | EGRESS PLAN- CASINO LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A1.42 | | EGRESS PLAN- MEZZANINE LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A5.01 | | BUILDING ELEVATIONS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A6.01 | | EXTERIOR BUILDING SECTIONS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A6.02 | | EXTERIOR BUILDING SECTIONS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A6.03 | | EXTERIOR BUILDING SECTIONS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A6.04 | | EXTERIOR BUILDING SECTIONS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A6.05 | | EXTERIOR BUILDING SECTIONS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A6.06 | | EXTERIOR BUILDING SECTIONS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A6.11 | | WALL SECTIONS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
1 W.G.YATES & SONS CONST CO | | Page 1 | | 03/20/13 10:35:54 AM |
Date Format - MM/DD/YY | | | | PMDrawingLog.rpt |
PM Drawing Log
| | | | |
Projects: 53284- - 53284- | | Types: First - Last | | Drawings: First - Last |
All Dates | | | | Show Revisions: Y |
Project: 53284- YATES/PARIC PR RIVER DOWNS; OHIO
Drawing Type: ARCHITECT ARCHITECTUAL DRAWINGS
| | | | | | | | | | | | | | |
Drawing | | | | | | Issued Date | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | Distribution Notes | | |
| | | | | | | |
| | | | | | | | | | - | | | | |
A6.12 | | WALL SECTIONS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | | | | |
| | | | | | | | | | - | | | | |
A6.13 | | WALL SECTIONS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | | | | |
| | | | | | | | | | - | | | | |
A6.14 | | WALL SECTIONS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | | | | |
| | | | | | | | | | - | | | | |
A7.01 | | STAIR PLANS AND SECTIONS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | | | | |
| | | | | | | | | | - | | | | |
A7.02 | | STAIR PLANS AND SECTIONS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | | | | |
| | | | | | | | | | - | | | | |
A7.03 | | STAIR PLANS AND SECTIONS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | | | | |
| | | | | | | | | | - | | | | |
A7.04 | | STAIR PLANS AND SECTIONS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | | | | |
| | | | | | | | | | - | | | | |
A7.05 | | STAIR PLANS AND SECTIONS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | | | | |
| | | | | | | | | | - | | | | |
A7.11 | | RAMP PLANS AND SECTIONS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | | | | |
| | | | | | | | | | - | | | | |
A7.21 | | ELEVATOR PLANS AND SECTIONS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | | | | |
| | | | | | | | | | - | | | | |
A7.22 | | ELEVATOR PLANS AND SECTIONS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | | | | |
| | | | | | | | | | - | | | | |
A7.23 | | ELEVATOR PLANS AND SECTIONS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | | | | |
| | | | | | | | | | - | | | | |
A8.51 | | MISCELLANEOUS DETAILS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | | | | |
| | | | | | | | | | - | | | | |
A8.52 | | MISCELLANEOUS DETAILS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | | | | |
| | | | | | | | | | - | | | | |
A2.00C | | ORIENTATION FLOOR PLAN- CASINO LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | | | | |
| | | | | | | | | | - | | | | |
A2.00M | | ORIENTATION ROOF PLAN- MEZZANINE LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | | | | |
| | | | | | | | | | - | | | | |
A2.00R | | ORIENTATION PLAN- ROOF LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | | | | |
| | | | | | | | | | - | | | | |
| | | | |
1 W.G.YATES & SONS CONST CO | | Page 2 | | 03/20/13 10:35:54 AM |
Date Format - MM/DD/YY | | | | PMDrawingLog.rpt |
PM Drawing Log
| | | | |
Projects: 53284- - 53284- | | Types: First - Last | | Drawings: First - Last |
All Dates | | | | Show Revisions: Y |
Project: 53284- YATES/PARIC PR RIVER DOWNS; OHIO
Drawing Type: ARCHITECT ARCHITECTUAL DRAWINGS
| | | | | | | | | | | | | | |
Drawing | | | | | | Issued Date | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | Distribution Notes | | |
A2.00S | | ORIENTATION FLOOR PLAN- SERVICE LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A2.01C | | AREA A- FLOOR PLAN- CASINO LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A2.01M | | AREA A- FLOOR PLAN- MEZZANINE LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A2.01R | | AREA A- ROOF PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A2.01S | | AREA A- FLOOR PLAN-SERVICE LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A2.02C | | AREA B- FLOOR PLAN- CASINO LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A2.02M | | AREA B- FLOOR PLAN- MEZZANINE LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A2.02R | | AREA B- ROOF PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A2.02S | | AREA B- FLOOR PLAN- SERVICE LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A2.03C | | AREA C- FLOOR PLAN- CASINO LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A2.03M | | AREA C- FLOOR PLAN- MEZZANINE LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A2.03R | | AREA C- ROOF PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A2.03S | | AREA C- FLOOR PLAN- SERVICE LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A2.04C | | AREA D- FLOOR PLAN- CASINO LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A2.04M | | AREA D- FLOOR PLAN- MEZZANINE LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A2.04R | | AREA D- ROOF PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A2.04S | | AREA D- FLOOR PLAN- SERVICE LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A2.05C | | AREA E- FLOOR PLAN- CASINO LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
1 W.G.YATES & SONS CONST CO | | Page 3 | | 03/20/13 10:35:54 AM |
Date Format - MM/DD/YY | | | | PMDrawingLog.rpt |
PM Drawing Log
| | | | |
Projects: 53284- - 53284- | | Types: First - Last | | Drawings: First - Last |
All Dates | | | | Show Revisions: Y |
Project: 53284- YATES/PARIC PR RIVER DOWNS; OHIO
Drawing Type: ARCHITECT ARCHITECTUAL DRAWINGS
| | | | | | | | | | | | | | |
Drawing | | | | | | Issued Date | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | Distribution Notes | | |
| | | | |
A2.05M | | AREA E- FLOOR PLAN- MEZZANINE LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A2.05R | | AREA E- ROOF PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A2.05S | | AREA E- FLOOR PLAN- SERVICE LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A2.06C | | AREA F- FLOOR PLAN- CASINO LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A2.06M | | AREA F- FLOOR PLAN- MEZZANINE LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A2.06R | | AREA F- ROOF PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A2.06S | | AREA F- FLOOR PLAN- SERVICE LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A2.07C | | AREA G- FLOOR PLAN- CASINO LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A2.07R | | AREA G- ROOF PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A2.07S | | AREA G- FLOOR PLAN- SERVICE LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.00C | | ORIENTATION RCP- CASINO LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.00S | | ORIENTATION RCP- SERVICE LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.01C | | AREA A- REFLECTED CEILING PLAN- CASINO LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.01S | | AREA A- REFLECTED CEILING PLAN- SERVICE LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.02C | | AREA B- REFLECTED CEILING PLAN- CASINO LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.02S | | AREA B- REFLECTED CEILING PLAN- SERVICE LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.03C | | AREA C- REFLECTED CEILING PLAN- CASINO LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.03S | | AREA C- REFLECTED CEILING PLAN- SERVICE LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
1 W.G.YATES & SONS CONST CO | | Page 4 | | 03/20/13 10:35:54 AM |
Date Format - MM/DD/YY | | | | PMDrawingLog.rpt |
PM Drawing Log
| | | | |
Projects: 53284- - 53284- | | Types: First - Last | | Drawings: First - Last |
All Dates | | | | Show Revisions: Y |
Project: 53284- YATES/PARIC PR RIVER DOWNS; OHIO
Drawing Type: ARCHITECT ARCHITECTUAL DRAWINGS
| | | | | | | | | | | | | | |
Drawing | | | | | | Issued Date | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | Distribution Notes | | |
| | | | |
A3.04C | | AREA D- REFLECTED CEILING PLAN- CASINO LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.04S | | AREA D- REFLECTED CEILING PLAN- SERVICE LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.05C | | AREA E- REFLECTED CEILING PLAN- CASINO LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.05S | | AREA E- REFLECTED CEILING PLAN- SERVICE LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.06C | | AREA F- REFLECTED CEILING PLAN- CASINO LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.06S | | AREA F- REFLECTED CEILING PLAN- SERVICE LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.07C | | AREA G- REFLECTED CEILING PLAN- CASINO LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.07S | | AREA G- REFLECTED CEILING PLAN- SERVICE LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A2.010C | | SLAB PLAN- CASINO LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A2.010M | | SLAB PLAN- MEZZANINE LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A2.010S | | SLAB PLAN- SERVICE LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A2.5.100 | | CASINO ORIENTATION PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A2.5.900 | | BOH ORIENTATION PLAN- CASINO LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A2.5.920 | | BOH ORIENTATION PLAN- SERVICE LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.5.100 | | CASINO REFLECTED CEILING ORIENTATION PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.5.101 | | CASINO AREA A- REFLECTED CEILING PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.5.102 | | CASINO AREA B- REFLECTED CEILING PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | | | | |
| | | | | | | | | | - | | | | |
| | | | |
1 W.G.YATES & SONS CONST CO | | Page 5 | | 03/20/13 10:35:54 AM |
Date Format - MM/DD/YY | | | | PMDrawingLog.rpt |
PM Drawing Log
| | | | |
Projects: 53284- - 53284- | | Types: First - Last | | Drawings: First - Last |
All Dates | | | | Show Revisions: Y |
Project: 53284- YATES/PARIC PR RIVER DOWNS; OHIO
Drawing Type: ARCHITECT ARCHITECTUAL DRAWINGS
| | | | | | | | | | | | | | |
Drawing | | | | | | Issued Date | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | Distribution Notes | | |
A3.5.103 | | CASINO AREA C- REFLECTED CEILING PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.5.200 | | STADIUM- REFLECTED CEILING PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.5.300 | | BUFFET- REFLECTED CEILING PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.5.400 | | STEAKHOUSE- REFLECTED CEILING PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.5.600 | | OTB- REFLECTED CEILING PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.5.900 | | BOH- RC ORIENTATION PLAN- SERVICE LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.5.901 | | BOH- AREA A- RCP- SERVICE LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.5.902 | | BOH- AREA B- RCP- SERVICE LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.5.910 | | BOH- RC ORIENTATION PLAN- CASINO LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.5.911 | | BOH- AREA B- RCP- CASINO LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.5.912 | | BOH- AREA C- RCP- CASINO LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A3.5.920 | | BOH- RCP- MEZZANINE LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A4.5.100 | | CASINO AREA A- PLANS | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A4.5.101 | | CASINO AREA B- PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A4.5.102 | | CASINO AREA C- PLANS | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A4.5.200 | | STADIUM- FLOOR FINISH & KEY ELEVATIONS PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A4.5.201 | | STADIUM- FURNITURE PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A4.5.300 | | BUFFET- FLOOR FINISH & KEY ELEVATIONS PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
1 W.G.YATES & SONS CONST CO | | Page 6 | | 03/20/13 10:35:54 AM |
Date Format - MM/DD/YY | | | | PMDrawingLog.rpt |
PM Drawing Log
| | | | |
Projects: 53284- - 53284- | | Types: First - Last | | Drawings: First - Last |
All Dates | | | | Show Revisions: Y |
Project: 53284- YATES/PARIC PR RIVER DOWNS; OHIO
Drawing Type: ARCHITECT ARCHITECTUAL DRAWINGS
| | | | | | | | | | | | | | |
Drawing | | | | | | Issued Date | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | Distribution Notes | | |
| | | | - | | | | |
A4.5.301 | | BUFFET- FURNITURE PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A4.5.400 | | STEAKHOUSE- FLOOR FINISH & KEY ELEVATIONS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A4.5.401 | | STEAKHOUSE- FURNITURE PLAN | | 01/28/13 | | IFC -Issued for Construction | | N |
| | | | |
| | | | - | | | | |
A4.5.500 | | PUBLIC RESTROOMS 1- PLANS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A4.5.501 | | PUBLIC RESTROOMS 2- PLANS | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A4.5.502 | | PUBLIC RESTROOMS 3- PLANS | | -
01/28/13 | | IFC -Issued for Construction | | N |
| | | | |
A4.5.600 | | OTB- FLOOR FINISH & KEY ELEVATIONS PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A4.5.601 | | OTB- FURNITURE PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A4.5.900 | | BOH AREA A- PLANS- SERVICE LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A4.5.901 | | BOH AREA B- PLANS- SERVICE LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A4.5.910 | | BOH AREA A- PLANS- CASINO LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A4.5.911 | | BOH AREA B- PLANS- CASINO LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A4.5.912 | | BOH AREA C- PLANS- CASINO LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
A4.5.920 | | BOH- PLANS- MEZZANINE LEVEL | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
Drawing Type: CIVIL CIVIL DRAWINGS
| | | | | | | | | | | | | | |
Drawing | | | | | | Issued Date | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | Distribution Notes | | |
T-2 | | ENLARGED LAYOUT PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-3 | | ENLARGED LAYOUT PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
1 W.G.YATES & SONS CONST CO | | Page 7 | | 03/20/13 10:35:54 AM |
Date Format - MM/DD/YY | | | | PMDrawingLog.rpt |
PM Drawing Log
| | | | |
Projects: 53284- - 53284- | | Types: First - Last | | Drawings: First - Last |
All Dates | | | | Show Revisions: Y |
Project: 53284- YATES/PARIC PR RIVER DOWNS; OHIO
Drawing Type: CIVIL CIVIL DRAWINGS
| | | | | | | | | | | | | | |
Drawing | | | | | | Issued Date | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | Distribution Notes | | |
| | | | |
T-4 | | DIRT TRACK PROFILES | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-5 | | TURF TRACK PROFILES | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-6 | | DETAILS | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-7 | | ENLARGED GRADING PLAN - CHUTES | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-8 | | DIRT TRACK SECTION- 0+00 TO 2+50 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-9 | | DIRT TRACK SECTION- 3+00 TO 6+00 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-10 | | DIRT TRACK SECTION- 6+50 TO 10+00 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-11 | | DIRT TRACK SECTION- 10+50 TO 13+00 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-12 | | DIRT TRACK SECTION- 13+50 TO 16+00 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-13 | | DIRT TRACK SECTION- 16+50 TO 19+00 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-14 | | DIRT TRACK SECTION- 19+50 TO 22+00 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-15 | | DIRT TRACK SECTION- 22+50 TO 25+00 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-16 | | DIRT TRACK SECTION- 25+50 TO 28+00 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-17 | | DIRT TRACK SECTION- 28+50 TO 31+50 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-18 | | DIRT TRACK SECTION- 32+00 TO 36+00 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-19 | | DIRT TRACK SECTION- 36+50 TO 40+50 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-1A | | LAYOUT PLAN - EXISTING TOPOGRAPHY | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
| | | | |
1 W.G.YATES & SONS CONST CO | | Page 8 | | 03/20/13 10:35:54 AM |
Date Format - MM/DD/YY | | | | PMDrawingLog.rpt |
PM Drawing Log
| | | | |
Projects: 53284 - - 53284 - | | Types: First - Last | | Drawings: First - Last |
All Dates | | | | Show Revisions: Y |
Project: 53284 - YATES/PARIC PR RIVER DOWNS; OHIO
Drawing Type: CIVIL CIVIL DRAWINGS
| | | | | | | | | | | | | | |
Drawing | | | | | | Issued Date | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | Distribution Notes | | |
T-1B | | LAYOUT PLAN - PROPOSED FACILITY | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-20 | | DIRT TRACK SECTION- 41+00 TO 45+00 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-21 | | DIRT TRACK SECTION- 45+50 TO 48+50 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-22 | | TURF TRACK SECTION- 49+00 TO 51+50 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-23 | | TURF TRACK SECTION- 52+00 TO 52+80 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-24 | | TURF TRACK SECTION- 0+00 TO 2+50 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-25 | | TURF TRACK SECTION- 3+00 TO 6+50 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-26 | | TURF TRACK SECTION- 7+00 TO 10+50 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-27 | | TURF TRACK SECTION- 11+00 TO 13+50 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-28 | | TURF TRACK SECTION- 14+00 TO 16+50 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-29 | | TURF TRACK SECTION- 17+00 TO 19+50 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-30 | | TURF TRACK SECTION- 20+00 TO 23+50 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-31 | | TURF TRACK SECTION- 23+50 TO 26+50 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-32 | | TURF TRACK SECTION- 27+00 TO 30+50 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-33 | | TURF TRACK SECTION- 31+00 TO 35+00 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-34 | | TURF TRACK SECTION- 35+50 TO 39+50 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-35 | | TURF TRACK SECTION- 40+00 TO 42+50 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
T-36 | | TURF TRACK SECTION- 43+00 TO 45+50 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
1 W.G.YATES & SONS CONST CO | | Page 9 | | 03/20/13 10:35:54 AM |
Date Format - MM/DD/YY | | | | PMDrawingLog.rpt |
PM Drawing Log
| | | | |
Projects: 53284- - 53284- | | Types: First - Last | | Drawings: First - Last |
All Dates | | | | Show Revisions: Y |
Project: 53284- YATES/PARIC PR RIVER DOWNS; OHIO
Drawing Type: CIVIL CIVIL DRAWINGS
| | | | | | | | | | | | | | |
Drawing | | | | | | Issued Date | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | Distribution Notes | | |
| | | | |
T-37 | | TURF TRACK SECTION- 46+00 TO 46+20 | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
CD1.01 | | PHASE 1 DEMOLITION PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
CD1.02 | | PHASE 1 DEMOLITION PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
CME1.01 | | TITLE SHEET | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
CME1.02 | | GENERAL NOTES AND MASTER LEGEND | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
CME1.03 | | DETAILS | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
CME1.04 | | RETAINING WALL DETAILS | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
CME1.05 | | EXISTING CONDITIONS AND DEMOLITION PLAN- WEST | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
CME1.06 | | EXISTING CONDITIONS AND DEMOLITION PLAN- EAST | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
CME1.07 | | PROPOSED TRACK- WEST | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
CME1.08 | | PROPOSED TRACK- EAST | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
CME1.09 | | MASS GRADING PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
CME1.10 | | MASS GRADING PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
CME1.11 | | MASS GRADING PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
CME1.12 | | MASS GRADING PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
CME1.13 | | MASS GRADING PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
CME1.14 | | MASS GRADING PLAN | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
CME1.15 | | STORM SEWER PROFILES | | -
01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
1 W.G.YATES & SONS CONST CO | | Page 10 | | 03/20/13 10:35:54 AM |
Date Format - MM/DD/YY | | | | PMDrawingLog.rpt |
PM Drawing Log
| | | | |
Projects: 53284- - 53284- | | Types: First - Last | | Drawings: First - Last |
All Dates | | | | Show Revisions: Y |
Project: 53284- YATES/PARIC PR RIVER DOWNS; OHIO
Drawing Type: CIVIL CIVIL DRAWINGS
| | | | | | | | | | | | | | |
Drawing | | | | | | Issued Date | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | Distribution Notes | | |
| | | | |
| | | | - | | | | |
CME1.16 | | STORM SEWER PROFILES | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
CME1.17 | | STORM SEWER PROFILES CP | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
CME1.18 | | STORM SEWER PROFILES CP | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
CME1.19 | | EROSION CONTROL NOTES AND DETAILS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
CSC1.01 | | TITLE SHEET | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
CSC1.02 | | GENERAL NOTES | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
CSC1.03 | | SITE CONSTRUCTION DETAILS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
CSC1.04 | | SITE CONSTRUCTION PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
CSC1. 05 | | SITE CONSTRUCTION PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
CSC1.06 | | SITE CONSTRUCTION PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
CSC1.07 | | SITE CONSTRUCTION PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
CSC1.08 | | SITE CONSTRUCTION PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
CSC1.09 | | SITE CONSTRUCTION PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
CSC1.10 | | SITE CONSTRUCTION PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
CSC1.11 | | UTILITY PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
CSC1.12 | | UTILITY PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
CSC1.13 | | STORM DAMAGE GRADING PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
| | | | |
1 W.G.YATES & SONS CONST CO | | Page 11 | | 03/20/13 10:35:54 AM |
Date Format - MM/DD/YY | | | | PMDrawingLog.rpt |
PM Drawing Log
| | | | |
Projects: 53284- - 53284- | | Types: First - Last | | Drawings: First - Last |
All Dates | | | | Show Revisions: Y |
Project: 53284- YATES/PARIC PR RIVER DOWNS; OHIO
Drawing Type: CIVIL CIVIL DRAWINGS
| | | | | | | | | | | | | | |
Drawing | | | | | | Issued Date | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | Distribution Notes | | |
CSC1.14 | | STORM DAMAGE GRADING PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
CSC1.15 | | STORM DAMAGE GRADING PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
CSC1.16 | | STORM DAMAGE GRADING PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
CSC1.17 | | STORM DAMAGE GRADING PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
CSC1.18 | | STORM DAMAGE GRADING PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
CSC1.19 | | GRADING DETAILS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
CSC1.20 | | GRADING DETAILS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
CSC1.21 | | GRADING DETAILS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
CSC1.22 | | MANURE STORAGE PAD DETAILS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
|
Drawing Type: COV SHEET COVER SHEET |
| | | | | |
Drawing | | | | | | Issued Date | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | Distribution Notes | | |
A0.01 | | COVER SHEET | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
|
Drawing Type: ELECTRICAL ELECTRICAL DRAWINGS |
| | | | | |
Drawing | | | | | | Issued Date | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | Distribution Notes | | |
E0.00 | | SYMBOL LIST AND GENERAL NOTES | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
E0.01 | | NOTES, FEEDER, AND TRANSFORMER SCHEDULE | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
E0.02 | | FLOOR DUCT DIAGRAMS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
E0.04 | | PANEL SCHEDULES- NORMAL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
1 W.G.YATES & SONS CONST CO | | Page 12 | | 03/20/13 10:35:54 AM |
Date Format - MM/DD/YY | | | | PMDrawingLog.rpt |
PM Drawing Log
| | | | |
Projects: 53284- - 53284- | | Types: First - Last | | Drawings: First - Last |
All Dates | | | | Show Revisions: Y |
Project: 53284- YATES/PARIC PR RIVER DOWNS; OHIO
Drawing Type: ELECTRICAL ELECTRICAL DRAWINGS
| | | | | | | | | | | | | | |
Drawing | | | | | | Issued Date | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | Distribution Notes | | |
| | | | |
| | | | - | | | | |
E0.05 | | PANEL SCHEDULES- NORMAL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
E0.06 | | PANEL SCHEDULES- NORMAL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
E0.07 | | PANEL SCHEDULES- EMERGENCY | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
E0.08 | | PANEL SCHEDULES- STANDBY | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
E0.09 | | PANEL SCHEDULES- STANDBY | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
E0.10 | | SINGLE LINE DIAGRAM- NORMAL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
E0.11 | | SINGLE LINE DIAGRAM- NORMAL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
E0.12 | | SINGLE LINE DIAGRAM- EMERGENCY- STANDBY | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
E0.13 | | SINGLE LINE DIAGRAM- STANDBY | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
E1.01 | | ENLARGED PARTIAL ELECTRICAL SITE PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
E4.00 | | ENLARGED ELECTRICAL ROOM PLANS- CASINO LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
E4.01 | | ENLARGED ELECTRICAL ROOM PLANS- MEZZ LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
E2.00C | | CASINO LEVEL ELECTRICAL OVERVIEW PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
E2.00M | | MEZZANINE LEVEL ELECTRICAL OVERVIEW PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
LV0.00 | | SYMBOL LIST AND GENERAL NOTES | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
LV1.01 | | ENLARGED PARTIAL LOW VOLTAGE SITE PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
LV4.00 | | ENLARGED IDF ROOM PLANS- MEZZANINE LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
| | | | |
1 W.G.YATES & SONS CONST CO | | Page 13 | | 03/20/13 10:35:54 AM |
Date Format - MM/DD/YY | | | | PMDrawingLog.rpt |
PM Drawing Log
| | | | |
Projects: 53284- - 53284- | | Types: First - Last | | Drawings: First - Last |
All Dates | | | | Show Revisions: Y |
Project: 53284- YATES/PARIC PR RIVER DOWNS; OHIO
Drawing Type: ELECTRICAL ELECTRICAL DRAWINGS
| | | | | | | | | | | | | | |
Drawing | | | | | | Issued Date | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | Distribution Notes | | |
LV4.01 | | ENLARGED IDF ROOM PLANS- MEZZANINE LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
LV7.00 | | TR BACKBONE RISER DIAGRAM | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
E2.00CF | | CASINO LEVEL FLOOR DUCT PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
LV2.00C | | CASINO LEVEL LOW VOLTAGE OVERVIEW PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
LV2.00M | | MEZZANINE LEVEL LOW VOLTAGE OVERVIEW PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
LV2.00CF | | CASINO LEVEL FLOOR DUCT PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
|
Drawing Type: FOOD SERV FOOD SERVICE DRAWINGS |
| | | | | |
Drawing | | | | | | Issued Date | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | Distribution Notes | | |
0FS0.1 | | SERVICE LEVEL MASTER PLAN- WAREHOUSE | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
0FS1.0 | | SERVICE LEVEL- RECEIVING DOCK EQUIPMENT PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
1FS0.1 | | CASINO MASTER PLAN AND INDEX | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
1FS0.2 | | CASINO MASTER PLAN- WAREHOUSE | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
1FS0.3 | | MASTER PLAN- CASINO LEVEL | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
1FS0.4 | | MASTER PLAN- STADIUM RESTAURANT | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
1FS1.0 | | WAREHOUSE- EQUIPMENT PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
1FS2.0 | | CASINO LEVEL- EDR, MAIN KCHN, DISHWASH, BAKE & PASTRY EQUIP | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
1FS3.0 | | CASINO LEVEL- BUFFET SERVERY EQUIPMENT PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
1FS4.0 | | CASINO LEVEL- STADIUM RESTAURANT EQUIPMENT PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
1 W.G.YATES & SONS CONST CO | | Page 14 | | 03/20/13 10:35:54 AM |
Date Format - MM/DD/YY | | | | PMDrawingLog.rpt |
PM Drawing Log
| | | | |
Projects: 53284- - 53284- | | Types: First - Last | | Drawings: First - Last |
All Dates | | | | Show Revisions: Y |
Project: 53284- YATES/PARIC PR RIVER DOWNS; OHIO
Drawing Type: FOOD SERV FOOD SERVICE DRAWINGS
| | | | | | | | | | | | | | |
Drawing | | | | | | Issued Date | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | Distribution Notes | | |
| | | | |
| | | | - | | | | |
1FS5.0 | | CASINO LEVEL- STEAKHOUSE EQUIPMENT PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
1FS6.0 | | CASINO LEVEL- GRAB-N-GO SERVICE BARS & LOUNGE BAR EQUIP PLN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
1FS7.0 | | CASINO LEVEL- CASINO SERVICE BARS & LOUNGE BAR EQUIP PLN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
1FS8.0 | | CASINO LEVEL- OTB & GRANDSTAND CONCESSION EQUIP PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
|
Drawing Type: INDEX INDEX |
| | | | | |
Drawing | | | | | | Issued Date | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | Distribution Notes | | |
A0.02 | | SHEET INDEX CODE ANALISYS & VACINITY MAP | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
|
Drawing Type: MECH/HVAC MECHANICAL/HVAC DRAWINGS |
| | | | | |
Drawing | | | | | | Issued Date | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | Distribution Notes | | |
M0.00 | | SYMBOL LIST ABBREVIATIONS, AND SPECIFICATIONS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
M0.01 | | MECHANICAL SCHEDULES | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
M0.05 | | MECHANICAL DIAGRAMS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
M0.06 | | MECHANICAL DIAGRAMS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
M0.07 | | MECHANICAL DIAGRAMS | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
M2.00C | | CASINO LEVEL MECHANICAL OVERVIEW PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
M2.00M | | MEZZANINE LEVEL MECHANICAL OVERVIEW PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
| | | | - | | | | |
M2.00R | | ROOF LEVEL MECHANICAL OVERVIEW PLAN | | 01/28/13 | | IFC - Issued for Construction | | N |
| | | | |
1 W.G.YATES & SONS CONST CO | | Page 15 | | 03/20/13 10:35:54 AM |
Date Format - MM/DD/YY | | | | PMDrawingLog.rpt |
PM Drawing Log
| | | | |
Projects: 53284- - 53284- | | Types: First - Last | | Drawings: First - Last |
All Dates | | | | Show Revisions: Y |
Project: 53284- YATES/PARIC PR RIVER DOWNS; OHIO
Drawing Type: MECH/HVAC MECHANICAL/HVAC DRAWINGS
| | | | | | | | | | | | | | | | | | |
Drawing | | | | | | | Issued Date | | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | | | Distribution Notes | | |
| | | | |
| | | | | | - | | | | | |
M2.00S | | SERVICE LEVEL MECHANICAL OVERVIEW PLAN | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
|
Drawing Type: PLUMBING PLUMBING DRAWINGS |
| | | | | |
Drawing | | | | | | | Issued Date | | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | | | Distribution Notes | | |
P0.00 | | SYMBOL LIST ABBREVIATIONS, AND SPECIFICATIONS | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
P0.01 | | PLUMBING SCHEDULES | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
P0.05 | | PLUMBING DIAGRAMS | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
P1.00 | | PLUMBING OVERVIEW PLAN | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
P4.00 | | ENLARGED PLUMBING PLANS | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
P4.01 | | ENLARGED PLUMBING PLANS | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
P2.00C | | CASINO LEVEL PLUMBING OVERVIEW PLAN | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
P2.00M | | MEZZANINE LEVEL PLUMBING OVERVIEW PLAN | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
P2.00R | | ROOF LEVEL PLUMBING OVERVIEW PLAN | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
P2.00S | | SERVICE LEVEL PLUMBING OVERVIEW PLAN | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
|
Drawing Type: STRUC STRUCTURAL DRAWINGS |
| | | | | |
Drawing | | | | | | | Issued Date | | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | | | Distribution Notes | | |
S0-01 | | STRUCTURAL COVER SHEET | | | | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 STEEL FRAMING DD | | | 02/11/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
| | | | 3 MILL ORDER PACKAGE REV | | | 02/22/13 | | | | IFC - Issued for Construction | | |
| | | | |
1 W.G.YATES & SONS CONST CO | | Page 16 | | 03/20/13 10:35:54 AM |
Date Format - MM/DD/YY | | | | PMDrawingLog.rpt |
PM Drawing Log
| | | | |
Projects: 53284- - 53284- | | Types: First - Last | | Drawings: First - Last |
All Dates | | | | Show Revisions: Y |
Project: 53284- YATES/PARIC PR RIVER DOWNS; OHIO
Drawing Type: STRUC STRUCTURAL DRAWINGS
| | | | | | | | | | | | | | | | | | |
Drawing | | | | | | | Issued Date | | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | | | Distribution Notes | | |
| | | | 4 MILL ORDER PACKAGE REV 2 | | | 03/06/13 | | | | IFC - Issued for Construction | | |
S0.02 | | STRUCTURAL COVER SHEET 2 | | | | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 STEEL FRAMING DD | | | 02/11/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
S3.01 | | PILE AND PILE CAP DETAIL | | | | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
S3.02 | | PILE CAP DETAIL | | | | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
| | | | | |
S3.40 | | STEEL FRAME ELEVATIONS | | | | | | | 02/11/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER REV | | | 02/22/13 | | | | IFC - Issued for Construction | | |
| | | | 3 MILL ORDER PACKAGE REV 2 | | | 03/06/13 | | | | IFC - Issued for Construction | | |
S5.01 | | CONCRETE DETAILS | | | | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
S6.01 | | STEEL DETAILS | | | | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
S6.02 | | STEEL DETAILS | | | | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
S6.03 | | STEEL DETAILS | | | | | | | 02/11/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
S6.04 | | STEEL DETAILS | | | | | | | 02/11/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
S6.10 | | STEEL DETAILS | | | | | | | 02/11/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
S6.11 | | STEEL DETAILS | | | | | | | 02/19/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
S6.12 | | STEEL DETAILS | | | | | | | 02/19/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 MILL ORDER PACKAGE REV 2 | | | 03/06/13 | | | | IFC - Issued for Construction | | |
S2.01C | | FRAMING PLAN- LEVEL 1- AREA “A” | | | | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 STEEL FRAMING DD | | | 02/11/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
S2.01M | | FRAMING PLAN- MEZZANINE LEVEL- AREA “A” | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 STEEL FRAMING DD | | | 02/11/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
| | | | 3 MILL ORDER PACKAGE REV 2 | | | 03/06/13 | | | | IFC - Issued for Construction | | |
S2.01P | | PILE FOUNDATION PLAN AREA “A” | | | | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
S2.01R | | FRAMING PLAN- ROOF- AREA “A” | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | |
1 W.G.YATES & SONS CONST CO | | Page 17 | | 03/20/13 10:35:54 AM |
Date Format - MM/DD/YY | | | | PMDrawingLog.rpt |
PM Drawing Log
| | | | |
Projects: 53284- - 53284- | | Types: First - Last | | Drawings: First - Last |
All Dates | | | | Show Revisions: Y |
Project: 53284- YATES/PARIC PR RIVER DOWNS; OHIO
Drawing Type: STRUC STRUCTURAL DRAWINGS
| | | | | | | | | | | | | | | | | | |
Drawing | | | | | | | Issued Date | | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | | | Distribution Notes | | |
| | | | | |
| | | | 1 STEEL FRAMING DD | | | 02/11/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
| | | | 3 MILL ORDER REV | | | 02/22/13 | | | | IFC - Issued for Construction | | |
S2.01S | | FRAMING PLAN- SERVICE LEVEL- AREA “A” | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
S2.02C | | FRAMING PLAN- LEVEL 1-AREA “B” | | | | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 STEEL FRAMING DD | | | 02/11/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
S2.02M | | FRAMING PLAN- MEZZANINE LEVEL- AREA “B” | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 STEEL FRAMING DD | | | 02/11/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
| | | | 3 MILL ORDER PACKAGE REV 2 | | | 03/06/13 | | | | IFC - Issued for Construction | | |
S2.02P | | PILE FOUNDATION PLAN AREA “B” | | | | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
S2.02R | | FRAMING PLAN- ROOF- AREA “B” | | | | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 STEEL FRAMING DD | | | 02/11/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
S2.02S | | FRAMING PLAN- SERVICE LEVEL- AREA “B” | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
S2.03C | | FRAMING PLAN- LEVEL 1- AREA “C” | | | | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 STEEL FRAMING DD | | | 02/11/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
| | | | 3 MILL ORDER PACKAGE REV | | | 02/22/13 | | | | IFC - Issued for Construction | | |
S2.03M | | FRAMING PLAN- MEZZANINE LEVEL- AREA “C” | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 STEEL FRAMING DD | | | 02/11/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
| | | | 3 MILL ORDER REV | | | 02/22/13 | | | | IFC - Issued for Construction | | |
| | | | 4 MILL ORDER PACKAGE REV 2 | | | 03/06/13 | | | | IFC - Issued for Construction | | |
S2.03P | | PILE FOUNDATION PLAN AREA “C” | | | | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
S2.03R | | FRAMING PLAN- ROOF- AREA “C” | | | | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 STEEL FRAMING DD | | | 02/11/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
| | | | 3 MILL ORDER REV | | | 02/22/13 | | | | IFC - Issued for Construction | | |
S2.03S | | FRAMING PLAN- SERVICE LEVEL- AREA “C” | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
S2.04C | | FRAMING PLAN- LEVEL 1- AREA “D” | | | | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 STEEL FRAMING DD | | | 02/11/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
| | | | |
1 W.G.YATES & SONS CONST CO | | Page 18 | | 03/20/13 10:35:54 AM |
Date Format - MM/DD/YY | | | | PMDrawingLog.rpt |
PM Drawing Log
| | | | |
Projects: 53284- - 53284- | | Types: First - Last | | Drawings: First - Last |
All Dates | | | | Show Revisions: Y |
Project: 53284- YATES/PARIC PR RIVER DOWNS; OHIO
Drawing Type: STRUC STRUCTURAL DRAWINGS
| | | | | | | | | | | | | | | | | | |
Drawing | | | | | | | Issued Date | | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | | | Distribution Notes | | |
| | | | 3 MILL ORDER REV | | | 02/22/13 | | | | IFC - Issued for Construction | | |
S2.04M | | FRAMING PLAN- MEZZANINE LEVEL-AREA “D” | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 STEEL FRAMING DD | | | 02/11/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
| | | | 3 MILL ORDER REV | | | 02/22/13 | | | | IFC - Issued for Construction | | |
S2.04P | | PILE FOUNDATION PLAN AREA “D” | | | | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
S2.04R | | FRAMING PLAN- ROOF- AREA “D” | | | | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 STEEL FRAMING DD | | | 02/11/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
| | | | 3 MILL ORDER REV | | | 02/22/13 | | | | IFC - Issued for Construction | | |
S2.04S | | FRAMING PLAN- SERVICE LEVEL- AREA “D” | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
S2.05C | | FRAMING PLAN- LEVEL 1- AREA “E” | | | | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 STEEL FRAMING DD | | | 02/11/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
S2.05M | | FRAMING PLAN- MEZZANINE LEVEL- AREA “E” | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 STEEL FRAMING DD | | | 02/11/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
S2.05P | | PILE FOUNDATION PLAN AREA “E” | | | | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
S2.05R | | FRAMING PLAN- ROOF- AREA “E” | | | | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 STEEL FRAMING DD | | | 02/11/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
| | | | 3 MILL ORDER REV | | | 02/22/13 | | | | IFC - Issued for Construction | | |
S2.05S | | FRAMING PLAN- SERVICE LEVEL- AREA “E” | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
S2.06C | | FRAMING PLAN- LEVEL 1- AREA “F” | | | | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 STEEL FRAMING DD | | | 02/11/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
| | | | 3 MILL ORDER REV | | | 02/22/13 | | | | IFC - Issued for Construction | | |
| | | | 4 MILL ORDER PACKAGE REV 2 | | | 03/06/13 | | | | IFC - Issued for Construction | | |
S2.06M | | FRAMING PLAN- MEZZANINE LEVEL- AREA “F” | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 STEEL FRAMING DD | | | 02/11/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
| | | | 3 MILL ORDER REV | | | 02/22/13 | | | | IFC - Issued for Construction | | |
S2.06P | | PILE FOUNDATION PLAN AREA “F” | | | | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
S2.06R | | FRAMING PLAN- ROOF- AREA “F” | | | | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | |
1 W.G.YATES & SONS CONST CO | | Page 19 | | 03/20/13 10:35:54 AM |
Date Format - MM/DD/YY | | | | PMDrawingLog.rpt |
PM Drawing Log
| | | | |
Projects: 53284- - 53284- | | Types: First - Last | | Drawings: First - Last |
All Dates | | | | Show Revisions: Y |
Project: 53284- YATES/PARIC PR RIVER DOWNS; OHIO
Drawing Type: STRUC STRUCTURAL DRAWINGS
| | | | | | | | | | | | | | | | | | |
Drawing | | | | | | | Issued Date | | | Status | | Revisions |
| | Sent Date Revision | | Signed Date | | Sent to Firm | | Sent to Contact Rev’d Date | | | | | | Distribution Notes | | |
| | | | | |
| | | | 1 STEEL FRAMING DD | | | 02/11/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
| | | | 3 MILL ORDER REV | | | 02/22/13 | | | | IFC - Issued for Construction | | |
S2.06S | | FRAMING PLAN- SERVICE LEVEL- AREA “F” | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
S2.07C | | FRAMING PLAN- LEVEL 1- AREA “G” | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 STEEL FRAMING DD | | | 02/11/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
| | | | 3 MILL ORDER REV | | | 02/22/13 | | | | IFC - Issued for Construction | | |
| | | | 4 MILL ORDER PACKAGE REV 2 | | | 03/06/13 | | | | IFC - Issued for Construction | | |
S2.07M | | FRAMING PLAN- MEZZANINE LEVEL- AREA “G” | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 STEEL FRAMING DD | | | 02/11/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
| | | | 3 MILL ORDER PACKAGE REV 2 | | | 03/06/13 | | | | IFC - Issued for Construction | | |
S2.07P | | PILE FOUNDATIO PLAN AREA “G” | | | | 01/28/13 | | | IFC - Issued for Construction | | N |
| | | | |
| | | | | | - | | | | | |
S2.07R | | FRAMING PLAN- ROOF- AREA “G” | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 STEEL FRAMING DD | | | 02/11/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
| | | | 3 MILL ORDER PACKAGE REV 2 | | | 03/06/13 | | | | IFC - Issued for Construction | | |
S2.07S | | FRAMING PLAN- SERVICE LEVEL- AREA “G” | | | | 01/28/13 | | | IFC - Issued for Construction | | Y |
| | | | | |
| | | | 1 MILL ORDER PACKAGE | | | 02/19/13 | | | | IFC - Issued for Construction | | |
| | | | 2 MILL ORDER BID PACKAGE REV 2 | | | 03/06/13 | | | | IFC - Issued for Construction | | |
| | | | |
1 W.G.YATES & SONS CONST CO | | Page 20 | | 03/20/13 10:35:54 AM |
Date Format - MM/DD/YY | | | | PMDrawingLog.rpt |
EXHIBIT F
THE WORK WITH EXCEPTIONS
EXHIBIT G
BID SUMMARY & CLARIFICATIONS
| | | | | | |
Estimate Summary | | Bid date | | | 3/14/2013 | |
RIVER DOWNS | | | | | | |
YATES-PARIC | | | | | | |
115 Main Street | | 356,411 | | | SF | |
Biloxi, MS 39530 | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | Labor | | | Material | | | Equipment | | | Subcontract | | | Temp Matl | | | Equip Rental | | | Other | | | Totals | |
Direct costs | | | | % | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Base labor | | | | | | $ | 4,192,938 | | | $ | 1,591,722 | | | $ | 225,182 | | | $ | 103,805,239 | | | $ | — | | | $ | — | | | $ | 1,090,890 | | | $ | 110,905,971 | |
Labor burden | | | 24.00 | % | | $ | 1,006,305 | | | | | | | | | | | | | | | | | | | | | | | | | | | $ | 1,006,305 | |
Labor fringes | | | | | | $ | — | | | | | | | | | | | | | | | | | | | | | | | | | | | $ | — | |
Labor manhours | | | | | | | 103,139 | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Material sales tax | | | 6.50 | % | | | | | | $ | 103,462 | | | | | | | | | | | | | | | | | | | | | | | $ | 103,462 | |
Equipment Surcharge | | | 6.50 | % | | | | | | | | | | $ | 14,637 | | | | | | | | | | | | | | | | | | | $ | 14,637 | |
| | | | | | | | | |
Temporary material markup | | | 0.00 | % | | | | | | | | | | | | | | | | | | $ | — | | | | | | | | | | | $ | — | |
Equipment rental markup | | | 0.00 | % | | | | | | | | | | | | | | | | | | | | | | $ | — | | | | | | | $ | — | |
Other markup | | | 0.00 | % | | | | | | | | | | | | | | | | | | | | | | | | | | $ | — | | | $ | — | |
Gross cost | | | | | | $ | 5,199,243 | | | $ | 1,695,184 | | | $ | 239,819 | | | $ | 103,805,239 | | | $ | — | | | $ | — | | | $ | 1,090,890 | | | $ | 112,030,375 | |
Gross receipts tax | | | 0.00 | % | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | $ | — | |
Builder’s risk insurance | | | 0.00 | % | | | by owner | | | | | | | | | | | | | | | | | | | | | | | | | | | $ | — | |
| | | Overall | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Overhead | | | 0.00 | % | | | 0.00 | % | | | 0.00 | % | | | 0.00 | % | | | 0.00 | % | | | 0.00 | % | | | 0.00 | % | | | 0.00 | % | | | | |
| | $ | — | | | $ | — | | | $ | — | | | $ | — | | | $ | — | | | $ | — | | | $ | — | | | $ | — | | | $ | — | |
Profit | | | 2.75 | % | | | 0.00 | % | | | 0.00 | % | | | 0.00 | % | | | 0.00 | % | | | 0.00 | % | | | 0.00 | % | | | 0.00 | % | | | | |
| | $ | 3,050,836 | | | $ | — | | | $ | — | | | $ | — | | | $ | — | | | $ | — | | | $ | — | | | $ | — | | | $ | 3,050,836 | |
Subcontract bond | | | 0.00 | % | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | $ | — | |
Performance bond | | $ | 0 | | | | separate $ | | | | | | | | | | | | | | | | | | | | | | | | | | | $ | — | |
GL | | | OCIP | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | By Owner | |
Permits/Plan Review Fees | | | 0.00 | % | | | building permits by owner | | | | | | | | | | | | | | | | | | | | | | | | | | | | By Owner | |
Contractor Contingency | | | ‘2 | % | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | $ | 2,218,790 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | $ | 117,300,000 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | |
Project Total | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | $ | 117,300,000 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | U/P per GSF | | | $ | 329.11 | |
| | |
Estimate Detail (Combined) | | W.G. Yates & Sons Construction Company 100 Decker - Suite 210 Irving, TX 75062 Phone: 972870-1483 Fax: 972870-1076 |
Estimate File: RIVER DOWNS SOUTHWEST CORNER BUILDOUT 04302013.est - RIVER DOWNS - SW CORNER BUILDOUT, CINCINNATI, OH
| | | | |
Estimator: SGD | | Sort Sequences: | | 1. Divisions |
Primary Project Qty: 9000 SF | | | | 2. Major Item Code |
Estimate UM: Imperial | | | | 3. Minor Item Code |
| | | | 4. Not Used |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | UNIT COST | | | TOTAL COST | | | | | | | |
Item Code | | Description | | Quantity | | Labor $ | | | Material $ | | | Sub $ | | | Equipt $ | | | Labor $ | | | Material $ | | | Sub $ | | | Equipt $ | | | Total Unit $ | | | Item Total $ | |
02 SITEWORK | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
02300.000 EARTHWORK | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
02315.000 Excavation and fill | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
2316.002 | | Machine fine grade floor | | 9,300.00 SQFT | | | 0.20 | | | | | | | | | | | | | | | | 1,860.00 | | | | | | | | | | | | | | | $ | 0.39 | | | $ | 3,647 | |
2316.009 | | Excavate for slab edge | | 3.89 CUYD | | | 20.00 | | | | | | | | | | | | | | | | 77.78 | | | | | | | | | | | | | | | $ | 39.22 | | | $ | 153 | |
2316.011 | | Excess thickened slab soil | | 3.89 CUYD | | | | | | | | | | | 10.00 | | | | | | | | | | | | | | | | 38.89 | | | | | | | $ | 14.42 | | | $ | 56 | |
2316.023 | | Crushed stone slab fill | | 229.63 CUYD | | | 25.00 | | | | 15.00 | | | | | | | | | | | | 5,740.74 | | | | 3,444.44 | | | | | | | | | | | $ | 72.05 | | | $ | 16,545 | |
2316.100 | | BACKHOE W/OPERATOR | | 1.00 MO | | | 4,156.00 | | | | 1,000.00 | | | | | | | | 2,300.00 | | | | 4,156.00 | | | | 1,000.00 | | | | | | | | 2,300.00 | | | $ | 13,215.93 | | | $ | 13,216 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Excavation and fill | | | | | | | | | | | | | | | | | | $ | 11,835 | | | $ | 4,444 | | | $ | 39 | | | $ | 2,300 | | | | | | | $ | 33,617 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total EARTHWORK | | | | | | | | | | | | | | | | | | $ | 11,835 | | | $ | 4,444 | | | $ | 39 | | | $ | 2,300 | | | | | | | $ | 33,617 | |
| | | | | | | | | | |
02450.000 FOUNDATIONS | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
02450.000 Foundations and load bearing elements | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
2450.000 | | ***AUGERCAST PILES & PILE CAPS - IN EXISTING GMP*** | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Foundations and load bearing elements | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total FOUNDATIONS | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | |
Total SITEWORK | | | | | | | | | | | | | | | | | | $ | 11,835 | | | $ | 4,444 | | | $ | 39 | | | $ | 2,300 | | | | | | | $ | 33,617 | |
| | | | | | | | | | |
03 CONCRETE | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
03100.000 FORMWORK | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
03110.000 Structural CIP forms | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
3110.701 | | Floor edge forms | | 430.00 LNFT | | | 3.25 | | | | 1.15 | | | | | | | | | | | | 1,397.50 | | | | 494.50 | | | | | | | | | | | $ | 8.14 | | | $ | 3,499 | |
3111.204 | | Wood column forms, 16’ to 18’ | | 1,360.00 SQFT | | | 3.15 | | | | 0.95 | | | | | | | | | | | | 4,284.00 | | | | 1,292.00 | | | | | | | | | | | $ | 7.64 | | | $ | 10,384 | |
3111.618 | | Slab form w/2.9 BM/sqft | | 9,300.00 SQFT | | | 3.50 | | | | 2.50 | | | | | | | | | | | | 32,550.00 | | | | 23,250.00 | | | | | | | | | | | $ | 10.70 | | | $ | 99,522 | |
3111.624 | | Slab edge form | | 430.00 SQFT | | | 4.75 | | | | 1.50 | | | | | | | | | | | | 2,042.50 | | | | 645.00 | | | | | | | | | | | $ | 11.62 | | | $ | 4,995 | |
3111.800 | | Slab edge forms at metal deck | | 430.00 LNFT | | | 3.25 | | | | 1.15 | | | | | | | | | | | | 1,397.50 | | | | 494.50 | | | | | | | | | | | $ | 8.14 | | | $ | 3,499 | |
3112.100 | | Chamfer strip | | 680.00 LNFT | | | 1.75 | | | | 0.35 | | | | | | | | | | | | 1,190.00 | | | | 238.00 | | | | | | | | | | | $ | 3.97 | | | $ | 2,699 | |
3112.120 | | Stair forms | | 959.50 SQFT | | | 15.00 | | | | 9.00 | | | | | | | | | | | | 14,392.50 | | | | 8,635.50 | | | | | | | | | | | $ | 43.23 | | | $ | 41,480 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Page 1
| | | | |
Estimator: SGD | | Sort Sequences: | | 1. Divisions |
Primary Project Qty: 9000 SF | | | | 2. Major Item Code |
Estimate UM: Imperial | | | | 3. Minor Item Code |
| | | | 4. Not Used |
| | | | |
10:50:59AM | | Estimate File: RIVER DOWNS SOUTHWEST CORNER BUILDOUT 04302013.est - RIVER DOWNS - SW CORNER BUILDOUT, CINCINNATI, OH | | 4/30/2013 |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | UNIT COST | | | TOTAL COST | | | | | | | |
Item Code | | Description | | Quantity | | Labor $ | | | Material $ | | | Sub $ | | | Equipt $ | | | Labor $ | | | Material $ | | | Sub $ | | | Equipt $ | | | Total Unit $ | | | Item Total $ | |
Total Structural CIP forms | | | | | | | | | | | | | | | | | | $ | 57,254 | | | $ | 35,050 | | | | | | | | | | | | | | | $ | 166,078 | |
03150.000 Concrete accessories | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
3150.650 | | Screeds for slab | | 2,232.00 LNFT | | | 0.35 | | | | 0.35 | | | | | | | | | | | | 781.20 | | | | 781.20 | | | | | | | | | | | $ | 1.22 | | | $ | 2,731 | |
3150.900 | | Form releasing agent | | 11,090.00 SQFT | | | 0.04 | | | | 0.04 | | | | | | | | | | | | 443.60 | | | | 443.60 | | | | | | | | | | | $ | 0.14 | | | $ | 1,551 | |
3150.900 | | Form releasing agent | | 959.50 SQFT | | | 0.04 | | | | 0.04 | | | | | | | | | | | | 38.38 | | | | 38.38 | | | | | | | | | | | $ | 0.14 | | | $ | 134 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Concrete accessories | | | | | | | | | | | | | | | | | | $ | 1,263 | | | $ | 1,263 | | | | | | | | | | | | | | | $ | 4,416 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | |
Total FORMWORK | | | | | | | | | | | | | | | | | | $ | 58,517 | | | $ | 36,313 | | | | | | | | | | | | | | | $ | 170,495 | |
| | | | | | | | | | |
03200.000 CONCRETE REINFORCING | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
03210.000 Reinforcing steel | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
3210.130 | | Supported slab rebar | | 34.18 TONS | | | | | | | 1,200.00 | | | | 650.00 | | | | | | | | | | | | 41,013.00 | | | | 22,215.37 | | | | | | | $ | 2,779.67 | | | $ | 95,002 | |
3210.150 | | Column rebar | | 9.93 TONS | | | | | | | 1,200.00 | | | | 650.00 | | | | | | | | | | | | 11,916.00 | | | | 6,454.50 | | | | | | | $ | 2,779.67 | | | $ | 27,602 | |
3210.400 | | Rebar @ stairs | | 3.27 TONS | | | | | | | 1,200.00 | | | | 650.00 | | | | | | | | | | | | 3,924.00 | | | | 2,125.50 | | | | | | | $ | 2,779.67 | | | $ | 9,090 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Reinforcing steel | | | | | | | | | | | | | | | | | | | | | | $ | 56,853 | | | $ | 30,795 | | | | | | | | | | | $ | 131,694 | |
03220.000 Welded wire fabric | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
3220.012 | | 6x6 W2.9/W2.9 mesh | | 107.42 SQS | | | | | | | 20.00 | | | | 15.00 | | | | | | | | | | | | 2,148.30 | | | | 1,611.23 | | | | | | | $ | 52.34 | | | $ | 5,622 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Welded wire fabric | | | | | | | | | | | | | | | | | | | | | | $ | 2,148 | | | $ | 1,611 | | | | | | | | | | | $ | 5,622 | |
03240.000 Fibrous reinforcing | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
3240.011 | | Fiber reinforcing (fibermesh) | | 258.33 LBS | | | | | | | 5.00 | | | | | | | | | | | | | | | | 1,291.67 | | | | | | | | | | | $ | 7.68 | | | $ | 1,983 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Fibrous reinforcing | | | | | | | | | | | | | | | | | | | | | | $ | 1,292 | | | | | | | | | | | | | | | $ | 1,983 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | |
Total CONCRETE REINFORCING | | | | | | | | | | | | | | | | | | | | | | $ | 60,293 | | | $ | 32,407 | | | | | | | | | | | $ | 139,299 | |
| | | | | | | | | | |
03300.000 CAST IN PLACE CONCRETE | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
03310.000 Structural concrete | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
3310.350 | | **Concrete in slab on grade** | | **** | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
3310.392 | | 4500 psi w/pump | | 190.20 CUYD | | | 20.00 | | | | 105.00 | | | | | | | | 15.00 | | | | 3,804.00 | | | | 19,971.00 | | | | | | | | 2,853.00 | | | $ | 223.47 | | | $ | 42,504 | |
3310.650 | | **Concrete in columns** | | **** | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
3310.688 | | 4500 psi w/crane | | 26.44 CUYD | | | 25.00 | | | | 105.00 | | | | | | | | | | | | 661.11 | | | | 2,776.67 | | | | | | | | | | | $ | 210.24 | | | $ | 5,560 | |
3311.500 | | **Conc in supported slab** | | **** | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
3311.536 | | 5000 psi w/pump | | 361.67 CUYD | | | 18.00 | | | | 110.00 | | | | | | | | 15.00 | | | | 6,510.00 | | | | 39,783.33 | | | | | | | | 5,425.00 | | | $ | 227.23 | | | $ | 82,180 | |
3311.700 | | ** Slab over metal deck** | | **** | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
3311.736 | | 5000 psi w/pump | | 136.63 CUYD | | | 18.00 | | | | 110.00 | | | | | | | | 15.00 | | �� | | 2,459.33 | | | | 15,029.26 | | | | | | | | 2,049.44 | | | $ | 227.23 | | | $ | 31,046 | |
3311.900 | | **Concrete in stairs and landings** | | **** | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
3311.936 | | 5000 psi w/pump | | 44.29 CUYD | | | 35.00 | | | | 110.00 | | | | | | | | 15.00 | | | | 1,550.14 | | | | 4,871.86 | | | | | | | | 664.35 | | | $ | 260.56 | | | $ | 11,540 | |
3315.976 | | * SOG area * | | 9,300.00 SQFT | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
3315.977 | | * Thickened slab length * | | 420.00 LNFT | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Page 2
| | | | |
Estimator: SGD | | Sort Sequences: | | 1. Divisions |
Primary Project Qty: 9000 SF | | | | 2. Major Item Code |
Estimate UM: Imperial | | | | 3. Minor Item Code |
| | | | 4. Not Used |
| | | | |
10:50:59AM | | Estimate File: RIVER DOWNS SOUTHWEST CORNER BUILDOUT 04302013.est - RIVER DOWNS - SW CORNER BUILDOUT, CINCINNATI, OH | | 4/30/2013 |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | UNIT COST | | TOTAL COST | | | | | | | |
Item Code | | Description | | Quantity | | Labor $ | | | Material $ | | | Sub $ | | | Equipt $ | | Labor $ | | | Material $ | | | Sub $ | | | Equipt $ | | | Total Unit $ | | | Item Total $ | |
3315.984 | | * No. of columns * | | 10.00 EACH | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
3315.986 | | * Supported slab area * | | 9,300.00 SQFT | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
3315.991 | | * Slab over metal deck area * | | 9,300.00 SQFT | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
3315.992 | | * No. of concrete stair risers * | | 34.00 EACH | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Structural concrete | | | | | | | | | | | | | | | | $ | 14,985 | | | $ | 82,432 | | | | | | | $ | 10,992 | | | | | | | $ | 172,829 | |
03350.000 Finishing | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
3350.120 | | Rub concrete stairs | | 385.56 SQFT | | | | | | | | | | | 0.95 | | | | | | | | | | | | | | 366.28 | | | | | | | $ | 1.37 | | | $ | 528 | |
3350.130 | | Machine trowel finish | | 27,900.00 SQFT | | | | | | | | | | | 0.85 | | | | | | | | | | | | | | 23,715.00 | | | | | | | $ | 1.23 | | | $ | 34,191 | |
3350.131 | | Point and patch | | 11,663.94 SQFT | | | 0.15 | | | | 0.05 | | | | | | | | | | 1,749.59 | | | | 583.20 | | | | | | | | | | | $ | 0.37 | | | $ | 4,326 | |
3350.144 | | Trowel finish stairs | | 612.00 SQFT | | | | | | | | | | | 1.50 | | | | | | | | | | | | | | 918.00 | | | | | | | $ | 2.16 | | | $ | 1,324 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Finishing | | | | | | | | | | | | | | | | $ | 1,750 | | | $ | 583 | | | $ | 24,999 | | | | | | | | | | | $ | 40,368 | |
03390.000 Curing | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
3390.010 | | Protect and cure | | 28,512.00 SQFT | | | 0.04 | | | | 0.04 | | | | | | | | | | 1,140.48 | | | | 1,140.48 | | | | | | | | | | | $ | 0.14 | | | $ | 3,987 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Curing | | | | | | | | | | | | | | | | $ | 1,140 | | | $ | 1,140 | | | | | | | | | | | | | | | $ | 3,987 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | |
Total CAST IN PLACE CONCRETE | | | | | | | | | | | | | | | | $ | 17,875 | | | $ | 84,156 | | | $ | 24,999 | | | $ | 10,992 | | | | | | | $ | 217,185 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | |
Total CONCRETE | | | | | | | | | | | | | | | | $ | 76,392 | | | $ | 180,761 | | | $ | 57,406 | | | $ | 10,992 | | | | | | | $ | 526,978 | |
| | | | | | | | | | |
05 METALS | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
05100.000 STRUCTURAL FRAMING | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
05120.000 Structural steel | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
5120.000 | | STRUCTURAL STEEL | | 86.00 TONS | | | | | | | 2,350.00 | | | | 1,000.00 | | | | | | | | | | 202,100.00 | | | | 86,000.00 | | | | | | | $ | 5,050.05 | | | $ | 434,304 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Structural steel | | | | | | | | | | | | | | | | | | | | $ | 202,100 | | | $ | 86,000 | | | | | | | | | | | $ | 434,304 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | |
Total STRUCTURAL FRAMING | | | | | | | | | | | | | | | | | | | | $ | 202,100 | | | $ | 86,000 | | | | | | | | | | | $ | 434,304 | |
| | | | | | | | | | |
05500.000 METAL FABRICATIONS | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
05520.000 Handrails and railings | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
5520.011 | | DECORATIVE STEEL GUARDRAIL @ STAIRS | | 100.00 LNFT | | | | | | | | | | | 175.00 | | | | | | | | | | | | | | 17,500.00 | | | | | | | $ | 252.30 | | | $ | 25,230 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Handrails and railings | | | | | | | | | | | | | | | | | | | | | | | | $ | 17,500 | | | | | | | | | | | $ | 25,230 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | |
Total METAL FABRICATIONS | | | | | | | | | | | | | | | | | | | | | | | | $ | 17,500 | | | | | | | | | | | $ | 25,230 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | |
Total METALS | | | | | | | | | | | | | | | | | | | | $ | 202,100 | | | $ | 103,500 | | | | | | | | | | | $ | 459,535 | |
| | | | | | | | | | |
06 WOOD & PLASTICS | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Page 3
| | | | |
Estimator: SGD | | Sort Sequences: | | 1. Divisions |
Primary Project Qty: 9000 SF | | | | 2. Major Item Code |
Estimate UM: Imperial | | | | 3. Minor Item Code |
| | | | 4. Not Used |
| | | | |
10:50:59AM | | Estimate File: RIVER DOWNS SOUTHWEST CORNER BUILDOUT 04302013.est - RIVER DOWNS - SW CORNER BUILDOUT, CINCINNATI, OH | | 4/30/2013 |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | UNIT COST | | TOTAL COST | | | | | | |
Item Code | | Description | | Quantity | | Labor $ | | | Material $ | | | Sub $ | | | Equipt $ | | Labor $ | | | Material $ | | | Sub $ | | | Equipt $ | | Total Unit $ | | | Item Total $ | |
06000.000 BASIC WOOD & PLASTICS MATERIALS & METHODS | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
06000.000 Basic wood and plastic materials and methods | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
6000.000 | | ROUGH CARPENTRY | | 1,650.00 BDFT | | | 2.75 | | | | 0.95 | | | | | | | | | | 4,537.50 | | | | 1,567.50 | | | | | | | | | $ | 6.85 | | | $ | 11,304 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Basic wood and plastic materials and methods | | | | | | | | | | | | | | | | $ | 4,538 | | | $ | 1,568 | | | | | | | | | | | | | $ | 11,304 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total BASIC WOOD & PLASTICS MATERIALS & METHODS | | | | | | | | | | | | | | | | $ | 4,538 | | | $ | 1,568 | | | | | | | | | | | | | $ | 11,304 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total WOOD & PLASTICS | | | | | | | | | | | | | | | | | | $ | 4,538 | | | $ | 1,568 | | | | | | | | | | | | | $ | 11,304 | |
| | | | | | | | | | |
07 THERMAL & MOISTURE PROTECTION | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
07200.000 THERMAL PROTECTION | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
07260.000 Vapor retarders | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
7260.012 | | 6mil Visqueen subgrade paper | | 102.30 SQS | | | 5.00 | | | | 3.50 | | | | | | | | | | 511.50 | | | | 358.05 | | | | | | | | | $ | 15.18 | | | $ | 1,553 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Vapor retarders | | | | | | | | | | | | | | | | $ | 512 | | | $ | 358 | | | | | | | | | | | | | $ | 1,553 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total THERMAL PROTECTION | | | | | | | | | | | | | | | | $ | 512 | | | $ | 358 | | | | | | | | | | | | | $ | 1,553 | |
| | | | | | | | | | |
07400.000 ROOF & SIDING PANELS | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
07430.000 Composite panels | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
7430.000 | | EXTERIOR SKIN - EXISTING SKIN ON COLUMN LINE “C” MOVES TO COLUMN LINE “A” | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Composite panels | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total ROOF & SIDING PANELS | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | |
07500.000 MEMBRANE ROOFING | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
07500.000 Membrane roofing | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
7500.000 | | MEMBRANE ROOF & ROOF ACCESSORIES | | 9,300.00 SQFT | | | | | | | | | | | 15.00 | | | | | | | | | | | | | | 139,500.00 | | | | | $ | 21.63 | | | $ | 201,123 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Membrane roofing | | | | | | | | | | | | | | | | | | | | | | | | $ | 139,500 | | | | | | | | | $ | 201,123 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total MEMBRANE ROOFING | | | | | | | | | | | | | | | | | | | | | | | | $ | 139,500 | | | | | | | | | $ | 201,123 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total THERMAL & MOISTURE PROTECTION | | | | | | | | | | | | | | | | | | $ | 512 | | | $ | 358 | | | $ | 139,500 | | | | | | | | | $ | 202,675 | |
| | | | | | | | | | |
08 DOORS & WINDOWS | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
08100.000 METAL DOORS & FRAMES | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
08100.000 Metal doors and frames | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
8100.000 | | DOORS, FRAMES & HARDWARE - FOH | | 2.00 EACH | | | 300.00 | | | | 1,000.00 | | | | | | | | | | 600.00 | | | | 2,000.00 | | | | | | | | | $ | 2,123.68 | | | $ | 4,247 | |
Page 4
| | | | |
Estimator: SGD | | Sort Sequences: | | 1. Divisions |
Primary Project Qty: 9000 SF | | | | 2. Major Item Code |
Estimate UM: Imperial | | | | 3. Minor Item Code |
| | | | 4. Not Used |
| | | | |
10:50:59AM | | Estimate File: RIVER DOWNS SOUTHWEST CORNER BUILDOUT 04302013.est - RIVER DOWNS - SW CORNER BUILDOUT, CINCINNATI, OH | | 4/30/2013 |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | UNIT COST | | TOTAL COST | | | | | | |
Item Code | | Description | | Quantity | | Labor $ | | | Material $ | | | Sub $ | | | Equipt $ | | Labor $ | | | Material $ | | | Sub $ | | | Equipt $ | | Total Unit $ | | | Item Total $ | |
8100.001 | | DOORS, FRAMES & HARDWARE - BOH | | 2.00 EACH | | | 250.00 | | | | 600.00 | | | | | | | | | | 500.00 | | | | 1,200.00 | | | | | | | | | $ | 1,411.46 | | | $ | 2,823 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Metal doors and frames | | | | | | | | | | | | | | | | $ | 1,100 | | | $ | 3,200 | | | | | | | | | | | | | $ | 7,070 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total METAL DOORS & FRAMES | | | | | | | | | | | | | | | | $ | 1,100 | | | $ | 3,200 | | | | | | | | | | | | | $ | 7,070 | |
| | | | | | | | | | |
08800.000 GLASS & GLAZING | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
08810.000 Glass | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
8810.000 | | UPGRADE EXISTING MIXED EXTERIOR SKIN ON COLUMN LINE 6 TO GLASS STOREFRONT & RELOCATE TO TRACKSIDE | | 960.00 SQFT | | | | | | | | | | | 40.00 | | | | | | | | | | | | | | 38,400.00 | | | | | $ | 57.67 | | | $ | 55,363 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Glass | | | | | | | | | | | | | | | | | | | | | | | | $ | 38,400 | | | | | | | | | $ | 55,363 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total GLASS & GLAZING | | | | | | | | | | | | | | | | | | | | | | | | $ | 38,400 | | | | | | | | | $ | 55,363 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total DOORS & WINDOWS | | | | | | | | | | | | | | | | $ | 1,100 | | | $ | 3,200 | | | $ | 38,400 | | | | | | | | | $ | 62,433 | |
| | | | | | | | | | |
09 FINISHES | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
09100.000 METAL SUPPORT ASSEMBLIES | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
09100.000 Metal support assemblies | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
9100.000 | | FRAMING @ COLUMN LINE “C” IS RELOCATED TO COLUMN LINE “A” | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
9100.001 | | NEW DRYWALL PARTITION @ COLUMN LINE “A” - FOH DRYWALL FINISH ON CASINO SIDE & WHITE BOX ON SHELL SIDE | | 2,400.00 SQFT | | | | | | | | | | | 25.00 | | | | | | | | | | | | | | 60,000.00 | | | | | $ | 36.04 | | | $ | 86,504 | |
9100.002 | | BOH ACOUSTICAL CEILINGS | | 9,300.00 SQFT | | | | | | | | | | | 5.00 | | | | | | | | | | | | | | 46,500.00 | | | | | $ | 7.21 | | | $ | 67,041 | |
9100.010 | | ***NO DRYWALL FINISH, FLOOR FINISH OR PAINT IS INCLUDED IN SHELL SPACE*** | | EACH | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Metal support assemblies | | | | | | | | | | | | | | | | | | | | | | | | $ | 106,500 | | | | | | | | | $ | 153,545 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total METAL SUPPORT ASSEMBLIES | | | | | | | | | | | | | | | | | | | | | | | | $ | 106,500 | | | | | | | | | $ | 153,545 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total FINISHES | | | | | | | | | | | | | | | | | | | | | | | | $ | 106,500 | | | | | | | | | $ | 153,545 | |
| | | | | | | | | | |
15 MECHANICAL | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
15000.000 MECHANICAL | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
15000.000 Mechanical | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
15000.000 | | HVAC DISTRIBUTION - MINIMUM REQ’D TO MAINTAIN TEMP & HUMIDITY | | 1.00 LS | | | | | | | | | | | 98,000.00 | | | | | | | | | | | | | | 98,000.00 | | | | | $ | 141,290.37 | | | $ | 141,290 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Mechanical | | | | | | | | | | | | | | | | | | | | | | | | $ | 98,000 | | | | | | | | | $ | 141,290 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Page 5
| | | | |
Estimator: SGD | | Sort Sequences: | | 1. Divisions |
Primary Project Qty: 9000 SF | | | | 2. Major Item Code |
Estimate UM: Imperial | | | | 3. Minor Item Code |
| | | | 4. Not Used |
| | | | | | |
10:50:59AM | | Estimate File: RIVER DOWNS SOUTHWEST CORNER BUILDOUT 04302013.est - RIVER DOWNS - SW CORNER BUILDOUT, CINCINNATI, OH | | | 4/30/2013 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | UNIT COST | | TOTAL COST | | | | | | | |
Item Code | | Description | | Quantity | | Labor $ | | Material $ | | Sub $ | | | Equipt $ | | Labor $ | | | Material $ | | | Sub $ | | | Equipt $ | | | Total Unit $ | | | Item Total $ | |
Total MECHANICAL | | | | | | | | | | | | | | | | | | | | $ | 98,000 | | | | | | | | | | | $ | 141,290 | |
| | | | | | | | | | |
15300.000 FIRE PROTECTION PIPE | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
15300.000 Fire protection pipe | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
15300.000 | | FIRE PROTECTION - MINIMUM TO MEET CODE | | 1.00 LS | | | | | | | 28,250.00 | | | | | | | | | | | | | | 28,250.00 | | | | | | | $ | 40,729.11 | | | $ | 40,729 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Fire protection pipe | | | | | | | | | | | | | | | | | | | | $ | 28,250 | | | | | | | | | | | $ | 40,729 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | |
Total FIRE PROTECTION PIPE | | | | | | | | | | | | | | | | | | | | $ | 28,250 | | | | | | | | | | | $ | 40,729 | |
| | | | | | | | | | |
15400.000 PLUMBING FIXTURES & EQUIPMENT | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
15400.000 Plumbing fixtures and equipment | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
15400.000 | | ***NO PLUMBING IS INCLUDED IN SHELL SPACE*** | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Plumbing fixtures and equipment | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | |
Total PLUMBING FIXTURES & EQUIPMENT | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | |
Total MECHANICAL | | | | | | | | | | | | | | | | | | | | $ | 126,250 | | | | | | | | | | | $ | 182,019 | |
| | | | | | | | | | |
16 ELECTRICAL | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
16000.000 ELECTRICAL | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
16000.000 Electrical | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
16000.000 | | ELECTRICAL - MINIMUM POWER & LIGHTS TO MEET CODE | | 1.00 LS | | | | | | | 49,500.00 | | | | | | | | | | | | | | 49,500.00 | | | | | | | $ | 71,366.06 | | | $ | 71,366 | |
16000.001 | | WALKER DUCT FOR ADDED SLAB AREA | | 1.00 LS | | | | | | | 138,291.00 | | | | | | | | | | | | | | 138,291.00 | | | | | | | $ | 199,379.46 | | | $ | 199,379 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Electrical | | | | | | | | | | | | | | | | | | | | $ | 187,791 | | | | | | | | | | | $ | 270,746 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total ELECTRICAL | | | | | | | | | | | | | | | | | | | | $ | 187,791 | | | | | | | | | | | $ | 270,746 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | |
Total ELECTRICAL | | | | | | | | | | | | | | | | | | | | $ | 187,791 | | | | | | | | | | | $ | 270,746 | |
| | | | | | | | | | |
ESTIMATE TOTALS | | | | | | | | | | | | $ | 94,375 | | | $ | 392,431 | | | $ | 759,386 | | | $ | 13,292 | | | | | | | $ | 1,902,852 | |
Page 6
| | |
Estimate Detail (Combined) | | YATES-PARIC 115 MAIN STREET BILOXI, MS 39530 Phone: Fax: |
Estimate File: RIVER DOWNS GRANDSTAND AND JOCKEY QUARTERS PRICING ANALYSIS 03282013.est - RIVER DOWNS - GRANDSTAND & JOCKEY QUARTERS ANALYSIS, CINCINNATI, OH
| | | | |
Estimator: SGD | | Sort Sequences: | | 1. Alternates |
Primary Project Qty: 0 SF | | | | 2. Divisions |
Estimate UM: Imperial | | | | 3. Major Item Code |
| | | | 4. Minor Item Code |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | UNIT COST | | TOTAL COST | | | | | | |
Item Code | | Description | | Quantity | | Labor $ | | Material $ | | Sub $ | | | Equipt $ | | Labor $ | | Material $ | | Sub $ | | | Equipt $ | | Total Unit $ | | | Item Total $ | |
00 ADD VIP SUITE TO CROWS NEST | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
03 CONCRETE | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
03000.000 BASIC CONCRETE MATERIALS & METHODS | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
03000.000 Basic materials and methods | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
3000.030 | | VIP SUITE & BATHROOM - CORE & SHELL | | 1.00 LS | | | | | | | 54,000.00 | | | | | | | | | | 54,000.00 | | | | | $ | 57,067.20 | | | $ | 57,067 | |
3000.040 | | AMTOTE - CORE & SHELL | | 1.00 LS | | | | | | | 51,000.00 | | | | | | | | | | 51,000.00 | | | | | $ | 53,896.80 | | | $ | 53,897 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Basic materials and methods | | | | | | | | | | | | | | | | $ | 105,000 | | | | | | | | | $ | 110,964 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total BASIC CONCRETE MATERIALS & METHODS | | | | | | | | | | | | | | | | $ | 105,000 | | | | | | | | | $ | 110,964 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total CONCRETE | | | | | | | | | | | | | | | | $ | 105,000 | | | | | | | | | $ | 110,964 | |
| | | | | | | | | | |
09 FINISHES | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
09000.000 BASIC FINISH MATERIALS & METHODS | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
09000.000 Basic finish materials and methods | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
9000.015 | | VIP SUITE & BATHROOM - FINISHES | | 1.00 LS | | | | | | | 50,000.00 | | | | | | | | | | 50,000.00 | | | | | $ | 52,840.00 | | | $ | 52,840 | |
9000.020 | | AMTOTE - FINISHES | | 1.00 LS | | | | | | | 20,000.00 | | | | | | | | | | 20,000.00 | | | | | $ | 21,136.00 | | | $ | 21,136 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Basic finish materials and methods | | | | | | | | | | | | | | | | $ | 70,000 | | | | | | | | | $ | 73,976 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | |
Total BASIC FINISH MATERIALS & METHODS | | | | | | | | | | | | | | | | $ | 70,000 | | | | | | | | | $ | 73,976 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | |
Total FINISHES | | | | | | | | | | | | | | | | $ | 70,000 | | | | | | | | | $ | 73,976 | |
| | | | | | | | | | |
12 FURNISHINGS | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
12400.000 FURNISHINGS & ACCESSORIES | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
12400.000 Furnishings and accessories | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
12400.005 | | VIP SUITE & BATHROOM - OWNER FFE | | 1.00 LS | | | | | | | 75,000.00 | | | | | | | | | | 75,000.00 | | | | | $ | 79,260.00 | | | $ | 79,260 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Furnishings and accessories | | | | | | | | | | | | | | | | $ | 75,000 | | | | | | | | | $ | 79,260 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | |
Total FURNISHINGS & ACCESSORIES | | | | | | | | | | | | | | | | $ | 75,000 | | | | | | | | | $ | 79,260 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | |
Total FURNISHINGS | | | | | | | | | | | | | | | | $ | 75,000 | | | | | | | | | $ | 79,260 | |
Page 1
| | | | |
Estimator: SGD | | Sort Sequences: | | 1. Alternates |
Primary Project Qty: 0 SF | | | | 2. Divisions |
Estimate UM: Imperial | | | | 3. Major Item Code |
| | | | 4. Minor Item Code |
| | | | | | |
4:28:05PM | | Estimate File: RIVER DOWNS GRANDSTAND AND JOCKEY QUARTERS PRICING ANALYSIS 03282013.est - RIVER DOWNS - GRANDSTAND & JOCKEY QUARTERS ANALYSIS, CINCINNATI, OH | | | 3/28/2013 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | UNIT COST | | TOTAL COST | | | | | | |
Item Code | | Description | | Quantity | | Labor $ | | Material $ | | Sub $ | | | Equipt $ | | Labor $ | | Material $ | | Sub $ | | | Equipt $ | | Total Unit $ | | | Item Total $ | |
16 ELECTRICAL | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
16000.000 ELECTRICAL | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
16000.000 Electrical | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
16000.005 | | VIP SUITE & BATHROOM - MEPFP | | 1.00 LS | | | | | | | 56,000.00 | | | | | | | | | | 56,000.00 | | | | | $ | 59,180.80 | | | $ | 59,181 | |
16000.050 | | AMTOTE - MEPFP | | 1.00 LS | | | | | | | 52,000.00 | | | | | | | | | | 52,000.00 | | | | | $ | 54,953.60 | | | $ | 54,954 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
Total Electrical | | | | | | | | | | | | | | | | $ | 108,000 | | | | | | | | | $ | 114,134 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | |
Total ELECTRICAL | | | | | | | | | | | | | | | | $ | 108,000 | | | | | | | | | $ | 114,134 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | |
Total ELECTRICAL | | | | | | | | | | | | | | | | $ | 108,000 | | | | | | | | | $ | 114,134 | |
| | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | |
Total ADD VIP SUITE TO CROWS NEST | | | | | | | | | | | | | | | | $ | 358,000 | | | | | | | | | $ | 378,334 | |
Page 2
RIVER DOWNS
CINCINNATI, OH
CLARIFICATIONS
JUNE 24, 2013
GENERAL CONDITIONS
| a. | Tie in and extension of existing utilities for temporary and permanent use is included. All temporary power, water, sewer and usage fees for temporary facilities are by Contractor throughout the construction duration. All permanent power is by Owner. |
| b. | Project duration is included for a May 1, 2014 Open to Public, subject to all Regulatory Approvals and completion of Owner responsibilities outside the control of the contractor. We have assumed a readily available workforce and an uninterrupted supply of material and equipment. Project schedule assumes 15 weather days. Weather days/abnormal weather is described as a weather condition that adversely affects critical path work in excess of 25% of the planned work and or precipitation is in excess of a 1/4”. Catastrophic weather events to include flooding, tornados excessive frozen precipitation will be assessed day for a day. |
| c. | The cost of a Performance and Payment Bond has been excluded. Performance and Payment Bond can be provided for an additional amount of 1% of final contract price. Bond availability and insurance is subject to surety approval. Builders Risk insurance must be in place prior to the issuance of a Performance and Payment Bond. |
| d. | All FFE is included per the Responsibility Matrix dated February 28, 2013. |
| e. | No tap or impact fees are included in the budget, all deposits are excluded. |
| f. | No Permanent Utility Service Fees, Utility Service Deposits, Hook Up Fees, or Assessments are included. |
| g. | Additional costs resulting from any tax or additional fees imposed under any statute, court decision or regulation becoming effective after acceptance of the GMP is excluded. |
| h. | Building Permit and Plan Review fees are excluded. The Contractor may be required to pay for early permit fees and such fees shall be reimbursed and invoiced outside of the GMP. |
| i. | All 3rd party testing laboratory costs including water intrusion testing are excluded. |
| j. | The cost of insurance covered under the OCIP and the additional insurance required from enrolled and excluded parties (non-OCIP) are excluded from the GMP pursuant to Exhibit O. |
| k. | All agreed upon allowances as listed, are net numbers and include material, installation, components associated with the allowance, bonds, fee, General Conditions, Insurances and |
| taxes. General Contractor does not represent that allowances are adequate for Design, Owner or Cost Intent. |
| l. | Design build fees are included at the backside facilities only. We are providing design assist services for the MEPFP. |
| m. | We have excluded any cost for a code consultant if one should be required. |
| n. | Selected subcontractor values used in the budget include bond cost. Contractor makes no representation that all subcontractor bonds will be provided. |
| o. | Contractors Burden Rate is included and set at a rate of 36% for non-union management personnel. Rate is auditable. |
| p. | GMP pricing is based on the drawings log offered in a separate attachment to the contract. |
| q. | Construction related costs for the Owner VIP Suite and Amtote areas located at the Crow’s Nest Level of the Grand Stand have been added to GMP in the amount of $378,334. Scope of work to include full core and shell, finishes and MEPFP build out for this added area. |
| r. | Gaming Floor Podium White Box Shell Out area has been added to the GMP in the amount of $1,902,852. Scope of work to include full core and shell, MEPFP rough in only to meet code and “white box” finishes only. No flooring, wall finishes or paint is included. This area is located in the Southwest corner of the podium between column lines A6-A11 to C6-C11 and to include the stair area at column lines A6- A5 to B6-B5. |
DIVISION 02
| a. | Demolition is included as amount currently under subcontract to O’Rourke Wrecking. |
| b. | We have not included any provisions for underground obstructions. Equitable cost adjustments will be required if obstructions are encountered. |
| c. | Earthwork, drainage and retaining walls are included as amount currently under subcontract to Trucco. |
| d. | Water, sewer and gas site utilities are included per GMP bid documents listed on drawing log. |
| e. | Asphalt paving with aggregate stone base is included per GMP bid documents listed on drawing log. |
| f. | Concrete paving and walks are included per GMP bid documents listed on drawing log. |
| g. | Pavement marking and striping are included per GMP bid documents listed on drawing log. |
| | | | | | | | |
| | | | 2 | | | | River Downs Cincinnati, OH |
| h. | Chain link security fence at backside facility is included per GMP bid documents listed on drawing log. |
| i. | Parking/access control gates at VIP parking area are included per GMP bid documents listed on drawing log. |
| j. | Dirt and turf tracks are included per GMP bid documents listed on drawing log. |
| k. | Traffic signalization and turn lanes at Kellogg Road entry is excluded in its entirety. |
| l. | Landscaping/Hardscaping/Irrigation is included as an Allowance of $1,500,000. Track Irrigation is not included in this allowance. |
| m. | Track irrigation, paddock, winners circle and associated items are included in the track budget. |
DIVISION 03
| 1. | Concrete is included per GMP bid documents listed on drawing log. |
| 2. | Grouting of steel base plates is included. |
| 3. | Hoisting for this scope of work is included. |
DIVISION 04
| 1. | Masonry is included per GMP bid documents listed on drawing log. |
DIVISION 05
| 1. | Structural steel, joist and deck are included per GMP bid documents listed on drawing log. |
| 2. | Miscellaneous metals are included per GMP bid documents listed on drawing log. |
| 3. | 126 tons miscellaneous steel is included consisting of framing at roof screen walls, elevator support steel, framing at roof openings, future elevator machine room for the freight traction elevators and roof dunnage for roof top mounted equipment. |
| 4. | Ornamental metals and glass handrails are included per GMP bid documents listed on drawing log. |
DIVISION 06
| 1. | Rough carpentry is included is per GMP bid drawings. |
| 2. | Stalls in new barns are included as 2x8 rough sawn oak. |
| | | | | | | | |
| | | | 3 | | | | River Downs Cincinnati, OH |
| 3. | We include replacing damaged stall materials in existing barns. |
| 4. | Millwork cost by area is shown on Finishes Matrix included under the Estimate Detail tab dated Feb 28, 2013. |
DIVISION 07
| 1. | All flat roof areas are included as fully mechanically fastened TPO membrane with two layers of 2.25” polyiso insulation. No protective cover is included |
| 2. | We have included cleaning and coating the existing barn roofs with a “Kool Seal” roof coating. |
| 3. | Below grade waterproofing is included at elevator pits |
| 5. | Firestopping at rated partitions and ceilings is included per code requirements. |
| 6. | Cementitious spray applied fire proofing is included at gaming facility. |
| 7. | Waterproofing/Air Barrier is included behind profiled metal wall panels. |
| 8. | EIFS, profile metal panels, flat metal panels/fascia, metal screen wall and architectural metal panels are included per GMP bid documents listed on drawing log. |
| 9. | We exclude design responsibility for exterior skin components. We will provide design assistance and coordination through the Yates-Paric BERM process to meet the requirements for the exterior cladding system. |
| 10. | Yates Paric will provide full coordination at the exterior envelope thru the Building Envelope Review Meeting (BERM). All design responsibilities will remain with the architect of record |
DIVISION 08
| 1. | Hollow metal doors, hollow metal frames and hardware have been included at BOH areas. |
| 2. | FOH wood doors, frames and hardware have been included at FOH areas. |
| 3. | Aluminum storefront is included at Gaming and Grandstand areas per GMP bid documents listed on drawing log. |
| 4. | We have included all frames and glazing to be per manufacturer’s standard profiles and colors. |
| | | | | | | | |
| | | | 4 | | | | River Downs Cincinnati, OH |
DIVISION 09
| 1. | Finishes cost by area is shown on the Finishes and material Matrices found under the Estimate Detail tab dated February 28, 2013. |
DIVISION 10
| 1. | Signage is included per the Responsibility Matrix dated February 28, 2013. |
| 2. | Plastic laminate toilet compartments are included in BOH restrooms. |
| 3. | Toilet accessories are included. |
| 4. | Fire extinguishers & cabinets are included. |
| 5. | Lockers are included as metal single tier at jockey locker room and metal four tier at worker locker room. |
DIVISION 11
| 1. | Dock bumpers, seals, lights and dock levelers are included at the three (3) truck bays at loading dock area. |
| 2. | Food service equipment is included as an Allowance of $5,000,000. |
| 3. | We exclude any equipment at Can Wash and Trash areas and assume anything required here to be vendor provided. Rough-in of MEP is included subject to specifications being provided timely. |
| 4. | We exclude trash compactors. Rough-in of MEP is included subject to specification being provided timely. |
| 5. | We exclude 20 cuyd dumpsters at backside facility. |
DIVISION 12
| 1. | FFE is included in accordance with attached Responsibility Matrix dated February 28, 2013. |
DIVISION 13
| 1. | Backside facility barns and buildings are included per GMP bid documents listed on drawing log. No space program has been received at the time of the GMP agreement. |
| | | | | | | | |
| | | | 5 | | | | River Downs Cincinnati, OH |
DIVISION 14
| 1. | We have included elevators and escalators based on the layout and stops showing in the GMP drawings. Specifications are based on ThyssenKrupp products. |
| 2. | We have included an allowance of $15,000 for finishes per passenger elevator only. |
DIVISION 15
MEPFP systems arebased upon the equipment; ductwork and piping completed by the project design-assist members as well as the design narrative from MSA dated January 28, 2013 and associated meetings. Design responsibility remains with the Engineer of Record.
Fire Protection
| 1. | Wet pipe sprinkler system is included at Gaming, Grandstand/OTB and BOH/ Administrative finished areas. |
| 2. | Fire Protection at the Porte Cochere and the under building parking area is not included. |
| 3. | We have not included a FM200 system. |
| 4. | No Fire Pump is included. |
HVAC
| 1. | Nine (9) variable air volume, roof mounted, air handling units to serve the back of house areas, administration areas, kitchen etc. Units feature solid double wall construction, standard roof curb, factory mounted end devices, mixing box, VFD on supply fan, economizer, return fan, chilled water & hot water coils, discharge plenums, and galvanized drain pans, bag/cartage filters. |
| 2. | Four (4) constant volume roof mounted air handling units to serve casino area. Units feature solid double wall construction, standard roof curb, factory mounted end devices, mixing box, VFD on supply fan, economizer, return fan, chilled water & hot water coils, discharge plenums, and galvanized drain pans, bag/cartage filters. |
| 3. | One (1) Annexair or equivalent constant volume air handling unit to serve casino area. Unit features standard roof curb, energy recovery wheel, |
| 4. | Sixty-two variable air volume boxes with hot water reheat. Units feature insulated rectangular plenums, DDC controls, hot water coil and flexible connection mp duct. |
| 5. | Eight (8) kitchen exhaust systems to serve grease hoods and dishwasher exhaust systems. Exhaust values are not available at time of submission, final quantities to be verified. |
| 6. | Three (3) direct fired natural gas make up air units to serve kitchen systems. MUA units are 100% outdoor air units and feature downblast flat roof curb, and weather hood. |
| 7. | Install exhaust hoods supplied by others. Proposal anticipates make up air connection integral to hood. Make up air units to be ducted directly to hood connection. |
| | | | | | | | |
| | | | 6 | | | | River Downs Cincinnati, OH |
| 8. | No vibration isolation curbs are included |
| 9. | Rectangular and spiral duct system built to SMACNA standards. Medium pressure duct built to 4” pressure class, low pressure duct built to 2” pressure class. |
| 10. | Welded black iron duct to serve exhaust systems at all kitchen hoods. Cleanouts to be provided at all fittings, change in direction, etc. Aluminum or stainless steel duct to serve dishwasher exhaust. |
| 11. | Toilet exhaust systems to serve all restrooms and janitor closets ducted to the outside per code. Systems utilize roof mounted exhaust fans and spiral duct distribution systems with flexible connections to exhaust grilles. |
| 12. | Four (4) chilled water fan coil units to serve IDF rooms. |
| 13. | Fourteen (14) cabinet unit heaters to serve entrances, vestibules, and stairwells. |
| 14. | Three (3) Liebert style computer room units to serve computer rooms. Units feature upflow design with two way modulating chilled water valve, microprocessor controls, electric reheat, condensate pump, discharge plenum, DX cooling coil for back up cooling with remote mounted condensing unit, and disconnect switch. |
| 15. | Chilled water fan coil unit to serve elevator equipment rooms. Louvered face air devices are included throughout. Proposal carries an allowance for slot type diffusers located at perimeter of casino. |
| 16. | Heat and ventilation is included for the maintenance building. |
| 17. | Wall mounted exhaust fans are included to provide ventilation in barns. |
| 18. | Refrigerant piping to be “Type L” copper with silver soldered joints. |
| 19. | Suction lines to be insulated with 1/2” Armaflex or equal. |
| 20. | Two way valves to be utilized on all terminal boxes and air handling units. |
| 21. | Three way valves will be provided at remote locations to minimize stagnant water. |
| 22. | Chilled and hot water piping to be Standard Weight Black Steel with standard weight fittings and welded and/or mechanical joints in pipe sizes 3” and larger. |
| 23. | Piping 2- 1/2” and smaller to be Type “L” copper with brazed or mechanical joints. |
| 24. | Condenser water piping to be Schedule 40 Black Steel with standard weight fittings, and welded and/or mechanical joints. |
| 25. | Reverse return pipe systems is are included |
| 26. | Condensate drain lines to have 1/2” Armaflex insulation. Chilled and hot water piping 2 1/2” and greater to have 1 1/2” fiberglass insulation. Chilled and hot water piping 2” and smaller to have 1/2” Armaflex insulation. Supply ductwork will be wrapped with 1 1/2” duct wrap with sealed vapor barrier in casino areas only. |
| 27. | Back of house areas with return air plenums to have exposed ductwork. All welded grease duct is to be wrapped with 3M firewrap. |
| 28. | Return duct will be lined with 1/2” duct liner. Return boots below units to have two joints of duct with one elbow for sound attenuation. |
| 29. | Direct digital control (DDC) system is included to control mechanical plant, air handling units, VAV boxes, and fan coil units. Includes workstation, graphics, and 24 hours owner training. System to operate on BACnet protocol and fully communicate with referenced equipment. DDC Sensors to be located in computer rooms, IDF rooms, elevator equipment rooms, etc to monitor temperature in space. DDC system will monitor alarm contacts on all Liebert computer room equipment. Factory trained service and controls technicians will start up and balance the entire mechanical system. DDC Controls on small equipment (Equipment such as elevator cooling, barn exhaust fans) |
| | | | | | | | |
| | | | 7 | | | | River Downs Cincinnati, OH |
| 30. | Time is included to assist commissioning agent provided by owner’s agent. |
| 31. | Air and water balance is included for our systems. |
| 32. | Certified air and water balance to be completed by our own NEBB certified technicians. |
| 33. | No humidification system is included |
Plumbing
| a. | Underground sanitary to be Sch 40 PVC and all above ground sanitary and vent piping to be cast iron. |
| b. | Sanitary will run underground to various areas and then turn vertical up thru garage level at columns to collect discharge from casino level. This will keep heat trace to a minimum. |
| c. | All piping exposed on garage level will be heat traced. |
| d. | Trap primers included for all floor drains, bathrooms, kitchens. (No trap primers included for floor drains or floor sinks serving coolers and freezers). |
| e. | All garage drains to be run into sanitary. Since more than 50% of this area is walled off code requires drains to be piped to sanitary. |
| f. | No condensate drains from freezer/coolers included. |
| a. | (1) 3000-4000 gallon concrete interceptor. |
| b. | Grease interceptor to be located toward east end of facility near truck dock. |
| c. | All grease waste piping will be heat traced and insulated. |
| d. | Grease waste piping will serve main kitchen, employee kitchen, chop house kitchen. |
| e. | Grandstand to have its own free standing grease interceptor. |
| f. | All grease waste piping to be cast iron. |
| a. | (12) Storm risers located at exterior walls per attached drawing. |
| b. | Secondary storm system included; Architect / Engineer to specify location of downspout nozzles. |
| c. | Included storm drainage for porte cochere. |
| d. | Included storm drainage for the grandstand overhang. |
| e. | All above ground storm to be cast iron. |
| f. | Insulate all horizontal. |
| g. | No heat trace included for any storm piping. |
| h. | Drains for Terrace level roofs and exterior platforms included. |
| | | | | | | | |
| | | | 8 | | | | River Downs Cincinnati, OH |
| a. | A 4” water service with 3” meter included. |
| b. | The static water pressure is 86 psi. Residual pressure is 62psi and flow is 1077gpm. |
| c. | Flow is from third hydrant east of Sutton and static is from second hydrant east of Sutton. This eliminates the need for a booster pump unless the hotel is to be served from the same water service. |
| d. | We have included non-potable water and backflow preventor for HVAC make-up water and irrigation in central plant. |
| e. | Frost proof wall hydrants at 100’ intervals are included. |
| f. | 140 degree water will be recirculated throughout to kitchens and 120 degree will be obtained by point of use tempering valves for all public use fixtures. |
| g. | A water softener will be provided for hot water only. |
| h. | We have provided water to soda and liquor pump room. |
| i. | Based on Stainless Steel and Copper. |
| k. | Re-circulation pumps (4) parallel with by-pass & isolation valves. |
| l. | Backflow for non-potable system 2” with meter. |
| m. | Backflow & deduct meter for irrigation. |
| o. | Plate heat exchanger with (2) storage tanks. |
| p. | 2 re-circulation pumps between exchangers. |
| q. | Refrigeration supply 2” |
| r. | (6) Roof hydrants included. |
| a. | Meter location on north side of building will be extended through building to the central plant and kitchens. |
| b. | Pressure regulating valves vented to exterior, will be provided. Actuated gas valves for kitchen equipment will be furnished and installed. |
| c. | Interlock with fire protection system by others. |
| d. | Based on Sch. 40 Blk Iron A53. |
| e. | 4” gas main brought to the Plant in a box. |
| g. | Regulators for kitchen. |
| h. | Many assumptions made for gas hook-ups in kitchens due to lack of information. Please see drawings which detail drops. |
| i. | No gas at laundry area. |
| | | | | | | | |
| | | | 9 | | | | River Downs Cincinnati, OH |
| a. | Water conserving type fixtures will be provided per specifications. |
| b. | Battery operated sensor type for all front of house and manual flush for back of house fixtures. |
| c. | Plumbing Fixture Material Budget of $138,000.00 is included. |
DIVISION 16
Electrical
All electrical items are to be furnished and installed per the Responsibility Matrix dated February 28, 2013, SD Drawings dated 1/28/2013, MSA Schematic Design Narrative dated 1/28/13.
| 1. | Distribution, Generators, UPS & Transfer Switches |
| a. | Furnish and install all electrical service entrance equipment which includes (2) 4000 amp 480/277 volt 3 phase 4 wire service and secondary conduit and wire. All secondary feeders to be aluminum |
| b. | Furnish and install 285’ of (8) empty 5” PVC concrete encased utility conduits. |
| c. | Furnish and install (1) 1,500kW 480/277 volt diesel generator along with (1) 300kw 480/277 volt diesel generator and necessary automatic transfer switches. |
| d. | Furnish and install at minimum (1) 65KVA UPS 15 minutes battery time. |
| 2. | Lighting and Lighting Controls |
| a. | Furnish and install interior general lighting, which includes can light, troffers, cove lighting, strip lights and egress lighting. Lighting material budget is $1,150,000.00 |
| b. | Labor has been included for the owner furnished fixtures |
| c. | Furnish and install all lighting controls including a complete dimming and relay panel system as required. Budget for this scope of work is $200,000 |
| d. | Furnish and install ETLC lighting transfer cabinet for emergency dimmable light fixtures |
| a. | Provide and install lighting protection according to UL requirements. Structural Steel to be utilized as the down conductors. |
| a. | Provide electrical rough in and single point connection to (1) Central Chiller Plant |
| b. | Provide electrical rough in and single point connection for exhaust fans |
| c. | Provide electrical rough in and single point connection for AHU units |
| d. | Provide electrical rough in and single point connection to pumps and hot water heaters associated with the plumbing scope of work. |
| e. | Provide electrical rough in for elevators. |
| f. | Provide electrical rough in for escalators. |
| g. | Provide electrical rough in for walk in freezers, beer cooler, vegetable cooler and dairy cooler. |
| h. | Provide electrical rough in and single point connection for uniform conveyors. |
| | | | | | | | |
| | | | 10 | | | | River Downs Cincinnati, OH |
| i. | Provide electrical rough in and single point connection for trash compactors. |
| 5. | Restaurant and Kitchens |
| a. | Provide electrical rough in and single point connection for kitchen equipment located in the following areas. |
| b. | Furnish and install task light fixtures per food systems notes. |
| c. | Provide electrical rough in and single point connection for dock levelers. |
| d. | Provide electrical rough in and single connection for automatic door openers. |
| e. | Provide electrical rough in for (1) pump located in the soda / liquor room. |
| a. | Furnish and install 36” wiremold header duct. |
| b. | Furnish and install #4 wiremold duct |
| c. | Furnish and install power and data cabling for slot machines |
| d. | Provide power connections to 120 volt gaming related attractions signs |
| e. | Provide power connections to 120 volt progressive signs |
| f. | Furnish and install dedicated duplex receptacles to feed ATM machines. |
| g. | Furnish and install dedicated receptacles to feed my choice kiosk |
| h. | Furnish and install a complete Telephone & Data distribution network including fiber and cooper cabling and terminations complete. All cabling assumed to be CAT 6. Budget is based on all cabling to be run open in J-hooks. |
| i. | Provide rough-ins, J hooks, cabling and terminations for CCTV systems. CCTV equipment to be provided by owner. |
| j. | Provide cabling and termination for card access doors. All equipment to be provide by owner |
| k. | Provide ceiling mounted speakers along with required cabling. Also provided one paging equipment rack with required amplifiers. |
| a. | Furnish and install dryer receptacles |
| b. | Furnish and install dedicated 20 amp 120 volt duplex receptacles for wash machines. |
| c. | Provide electrical rough in for hand dryers. |
| d. | Furnish and install dedicated and general purpose receptacles. |
| e. | Furnish and install twist lock receptacles located in the IDF rooms |
| f. | Furnish and install weather proof GFI duplex receptacles |
| 8. | Casino, Restaurants, Back of House, Grandstands Low Voltage and Fire Alarm |
| a. | Provide a complete distribution network for the Master Antenna Television System for location, including J hooks, copper cabling and terminations. All cabling to be open in J-hooks |
| b. | Provide complete raceway system for the two way communication system. |
| c. | Provide power, low voltage rough-ins, cabling and terminations for monitors and big screen televisions and roof mounted satellite dishes. Budget based on all monitors, televisions, satellites and head end equipment to be provided by the owner. |
| 9. | Customer and Employee Parking Lot & Site |
| a. | Furnish and install twin head metal halide pole light fixtures |
| b. | Furnish and install single head metal halide pole light fixtures |
| | | | | | | | |
| | | | 11 | | | | River Downs Cincinnati, OH |
| c. | Furnish and install decorative entrance pole light fixtures. |
| d. | Budget included for these fixtures $215,000 |
| 10. | Budget based on the use MC Cable throughout the project where allowed by code and the local Authority Having Jurisdiction |
| | | | | | | | |
| | | | 12 | | | | River Downs Cincinnati, OH |
EXHIBIT Q
MILESTONES
EXHIBIT Q
MILESTONES
Revised Design Deliverable Schedule Dates Required for May 1, 2014 Completion
| | | | |
| | Issued By | | Need By |
Demo Plan For Track | | | | N/A |
Site Civil/Utilities Complete | | 1/17/2013 | | 4/8/2013 |
Track Relocation CDs | | | | 4/2/2013 |
Foundation Package (Piles/Caps) | | 1/17/2013 | | 3/11/2013 |
Foundation Permit | | | | 3/18/2013 |
Structure Foundation Permit | | | | 1/14/2013 |
Response to County | | | | 2/25/2013 |
OTB Expansion | | | | 3/12/2013 |
Coordination Review | | | | 4/8/2013 |
Structural Steel Gaming/BOH | | | | 3/18/2013 |
Structural Steel Mill Order | | | | 2/20/2013 |
Rev 1 | | | | 2/22/2013 |
Rev 2 | | | | 3/6/2013 |
Rev 3 | | | | 4/1/2013 |
Structural Steel Podium Permit - Rev 1 | | | | 5/7/2013 |
Concrete Podium Structure Permit** | | | | 3/22/2013 |
Grandstand Structural CDs - Not Complete | | 6/14/2013 | | 5/17/2013 |
Gaming/BOH Exterior Cladding CDs | | Progress Package Issued on 3/20/13 | | 5/1/2013 |
Barns/Backside CDs - This is Design/Build by YP | | | | 5/1/2013 |
Grandstand MEP Rough In | | | | 5/17/2013 |
Permit Package for Gaming, BOH, and Grand Stand | | Status Set Issued 5/1/13 | | 6/10/2013 |
Interior Design/FFE Complete | | | | 50% Complete by 7/15/13 100% Complete by 9/1/13 |
** | needs to be submitted immediately to County for approval in order to allow review and approval |