K. Commitments and Contingencies
Litigation
Termination of A-12 Program. In January1991, the U.S. Navy terminated the A-12 aircraft contract for default. The A-12 contract was a fixed-price incentive contract for the full-scale development and initial production of the Navys carrier-based Advanced Tactical Aircraft. We and McDonnell Douglas, the contractors, were parties to the contract with the Navy. (McDonnell Douglas is now owned by The Boeing Company.) Both contractors had full responsibility to the Navy for performance under the contract, and both are jointly and severally liable for potential liabilities arising from the termination. As a consequence of the termination for default, the Navy demanded the contractors repay $1.4billion in unliquidated progress payments. The Navy agreed to defer collection of that amount pending a resolution by the court or a negotiated settlement.
Over more than 16 years of litigation, the trial court (the U.S. Court of Federal Claims) and appeals court (the Court of Appeals for the Federal Circuit) issued multiple rulings, some in favor of the government and others in favor of the contractors. On May3, 2007, the trial court issued a decision upholding the default termination. The court did not, however, award any money judgment to the government. On June2, 2009, a three-judge panel of the appeals court affirmed the trial courts decision, and on November24, 2009, the appeals court denied the contractors petitions for rehearing. The contractors have petitioned the United States Supreme Court for review of the appeals court decision. We continue to believe that the law and facts support a determination that the governments default termination was not justified. Moreover, we continue to believe that there are significant legal obstacles to the governments ability to collect any amount from the contractors given that no court has ever entered a money judgment in favor of the government.
If, contrary to our expectations, the default termination is ultimately sustained and the government prevails on its recovery theories, the contractors could collectively be required to repay the government as much as $1.4billion for progress payments received for the A-12 contract, plus interest, which was approximately $1.5 billion at April4, 2010. This would result in a liability to us of half of the total, or approximately $1.4 billion pretax. Our after-tax charge would be approximately $800, or $2.06 per share, to be recorded in discontinued operations. Our after-tax cash cost would be approximately $715. We believe we have sufficient resources to satisfy our obligation if required.
Other. Various claims and other legal proceedings incidental to the normal course of business are pending or threatened against us. While we cannot predict the outcome of these matters, we believe any potential liabilities in these proceedings, individually or in the aggregate, will not have a material impact on our results of operations, financial condition or cash flows.
Environmental
We are subject to and affected by a variety of federal, state, local and foreign environmental laws and regulations. We are directly |