UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
WASHINGTON, DC 20549
FORM 8-K
CURRENT REPORT
PURSUANT TO SECTION 13 OR 15(d) OF THE
SECURITIES EXCHANGE ACT OF 1934
Date of Report (Date of earliest event reported): October 3, 2008
| | Exact name of registrants as specified in | | |
Commission | | their charters, address of principal executive | | IRS Employer |
File Number | | offices and registrants' telephone number | | Identification Number |
1-14465 | | IDACORP, Inc. | | 82-0505802 |
1-3198 | | Idaho Power Company | | 82-0130980 |
| | 1221 W. Idaho Street | | |
| | Boise, ID 83702-5627 | | |
| | (208) 388-2200 | | |
| | | | |
State or Other Jurisdiction of Incorporation: Idaho |
None |
Former name or former address, if changed since last report. |
Check the appropriate box below if the Form 8-K filing is intended to simultaneously satisfy the filing obligation of the registrant under any of the following provisions (see General Instruction A.2.):
[ ] Written communications pursuant to Rule 425 under the Securities Act (17 CFR 230.425)
[ ] Soliciting material pursuant to Rule 14a-12 under the Exchange Act (17 CFR 240.14a-12)
[ ] Pre-commencement communications pursuant to Rule 14d-2(b) under the Exchange Act (17 CFR 240.14d-2(b))
[ ] Pre-commencement communications pursuant to Rule 13e-4(c) under the Exchange Act (17 CFR 240.13e-4(c))
IDACORP, Inc.
IDAHO POWER COMPANY
Form 8-K
ITEM 8.01 OTHER EVENTS.
On October 3, 2008, Idaho Power Company (Idaho Power) filed a project proposal with the Northern Tier Transmission Group (NTTG) Cost Allocation Committee relating to its proposed 500 kilovolt transmission line to be built between the proposed Hemingway substation in southwestern Idaho and the existing Boardman substation in eastern Oregon (Hemingway-Boardman Line). Idaho Power is requesting approval by the NTTG of the allocation of costs and benefits for the project, but does not expect any recommendation or approval until the second half of 2009.
Idaho Power stated in its proposal that the Hemingway-Boardman Line would be approximately 300 miles. Construction costs for single-circuit 500-kilovolt transmission lines are typically estimated at $1.5 million per mile (excluding rights-of-way, permit and substation interconnection costs), but may vary significantly depending upon route availability, permitting and other variables. Current total cost estimates for the project (including rights-of-way, permit and substation interconnection costs) are approximately $600 million.
In its 2006 Integrated Resource Plan, Idaho Power projected the need for an additional 225 megawatts of transmission upgrade capacity from the Pacific Northwest to the Boise area, commencing as early as 2012. Including the project cost estimate in Idaho Power's existing plant investment and adding 225 megawatts of usage to the System Peak Demand in sample calculations would result in a transmission rate of approximately $40 per kilowatt-year. Additional increases in usage of the transmission would result in a lower rate. Additional information on the rate calculations and components is available on Idaho Power's Open Access Same-Time Information System (OASIS) website.
Idaho Power's share of the total line costs will depend upon whether and to what extent other partners participate in the line, and the amounts contributed by third-party purchasers of capacity on the line. Idaho Power continues to explore opportunities to partner with other entities for up to fifty percent of the project. The current project schedule indicates a likely in-service date of June 2013.
SIGNATURES
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrants have duly caused this report to be signed on their behalf by the undersigned hereunto duly authorized.
Dated: October 3, 2008
IDACORP, Inc.
By: /s/ Darrel T. Anderson
Darrel T. Anderson
Senior Vice President -
Administrative Services
and Chief Financial Officer
IDAHO POWER COMPANY
By: /s/ Darrel T. Anderson
Darrel T. Anderson
Senior Vice President -
Administrative Services
and Chief Financial Officer