20
growth project milestones ’09 & ’10…
2009
Mill Creek
ü Expect decision from the MPSC (APPROVED) Q2
ü Begin construction Q3
500 kV Upgrade
ü Complete engineering and planning studies Q4
ü WECC regional planning process begins Q4
¾ Finalize commercial terms w/partners Q4
230 kV Collector System
ü Information meeting with customers Q2
ü FERC ruling allowing “open season” Q2
¾ Identify potential anchor tenant Q4
MSTI
ü Work with FERC to clarify filings process Q3
¾ EIS admin draft for public review due Q4
2010
Mill Creek
¾ Complete construction Q4
¾ Start up, commissioning and completion Q4
500 kV Upgrade
¾ Complete detailed engineering Q3
¾ Complete regional planning process Q4
230 kV Collector System
¾ Conduct “open season” Q1
¾ Siting and permitting process begins Q1
¾ WECC regional planning process Q2
MSTI
¾ Draft EIS Q1
¾ Conduct “open season”/commercial terms Q1
¾ EIS Record of Decision Q3
¾ Begin right of way procurement Q4
¾ Begin Final Engineering Q4