Regulatory Matters | Regulatory Matters 2019 Retail Rate Case APS filed an application with the ACC on October 31, 2019 (the “2019 Rate Case”) seeking an increase in annual retail base rates of $69 million. This amount includes recovery of the deferral and rate base effects of the Four Corners Power Plant (“Four Corners”) selective catalytic reduction (“SCR”) project that was the subject of a separate proceeding. See “Four Corners SCR Cost Recovery” below. It also reflects a net credit to base rates of approximately $115 million primarily due to the prospective inclusion of rate refunds currently provided through the Tax Expense Adjustment Mechanism (“TEAM”). The proposed total annual revenue increase in APS’s application is $184 million. The average annual customer bill impact of APS’s request is an increase of 5.6% (the average annual bill impact for a typical APS residential customer is 5.4%). The principal provisions of APS’s application were: • a test year comprised of 12 months ended June 30, 2019, adjusted as described below; • an original cost rate base of $8.87 billion, which approximates the ACC-jurisdictional portion of the book value of utility assets, net of accumulated depreciation and other credits; • the following proposed capital structure and costs of capital: Capital Structure Cost of Capital Long-term debt 45.3 % 4.10 % Common stock equity 54.7 % 10.15 % Weighted-average cost of capital 7.41 % • a 1% return on the increment of fair value rate base above APS’s original cost rate base, as provided for by Arizona law; • a rate of $0.030168 per kWh for the portion of APS’s retail base rates attributable to fuel and purchased power costs (“Base Fuel Rate”); • authorization to defer until APS’s next general rate case the increase or decrease in its Arizona property taxes attributable to tax rate changes after the date the rate application is adjudicated; • a number of proposed rate and program changes for residential customers, including: ▪ a super off-peak period during the winter months for APS’s time-of-use with demand rates; ▪ additional $1.25 million in funding for APS’s limited-income crisis bill program; and ▪ a flat bill/subscription rate pilot program; • proposed rate design changes for commercial customers, including an experimental program designed to provide access to market pricing for up to 200 MW of medium and large commercial customers; • recovery of the deferral and rate base effects of the construction and operating costs of the Ocotillo modernization project (see discussion below of the 2017 Settlement Agreement); and • continued recovery of the remaining investment and other costs related to the retirement and closure of the Navajo Generating Station (the “Navajo Plant”) (see “Navajo Plant” below). On October 2, 2020, the ACC Staff, the Residential Utility Consumer Office (“RUCO”) and other intervenors filed their initial written testimony with the ACC. The ACC Staff recommended, among other things, (i) an $89.7 million revenue increase, (ii) an average annual customer bill increase of 2.7%, (iii) a return on equity of 9.4%, (iv) a 0.3% or, as an alternative, a 0% return on the increment of fair value rate base greater than original cost , (v) the recovery of the deferral and rate base effects of the construction and operating costs of the Four Corners SCR project and (vi) the recovery of the rate base effects of the construction and ongoing consideration of the deferral of the Ocotillo modernization project. RUCO recommended, among other things, (i) a $20.8 million revenue decrease, (ii) an average annual customer bill decrease of 0.63%, (iii) a return on equity of 8.74%, (iv) a 0% return on the increment of fair value rate base, (v) the nonrecovery of the deferral and rate base effects of the construction and operating costs of the Four Corners SCR project pending further consideration, and (vi) the recovery of the deferral and rate base effects of the construction and operating costs of the Ocotillo modernization project. The filed ACC Staff and intervenor testimony include additional recommendations, some of which materially differ from APS’s filed application. On November 6, 2020, APS filed its rebuttal testimony and the principal provisions which differ from its initial application include, among other things, (i) a $169 million revenue increase, (ii) average annual customer bill increase of 5.14%, (iii) return on equity of 10%, (iv) return on the increment of fair value rate base of 0.8%, (v) new cost recovery adjustor mechanism, the Advanced Energy Mechanism (“AEM”), to enable more timely recovery of clean investments as APS pursues its clean energy commitment, (vi) recognition that securitization is a potentially useful financing tool to recover the remaining book value of retiring assets and effectuate a transition to a cleaner energy future that APS intends to pursue, provided legislative hurdles are addressed, and (vii) a Coal Community Transition (“CCT”) plan related to the closure or future closure of coal-fired generation facilities, of which $25 million would be funds that are not recoverable through rates with a proposal that the remainder be funded by customers over 10 years. The CCT plan includes the following proposed components: (i) $100 million that will be paid over 10 years to the Navajo Nation for a sustainable transition to a post-coal economy, which would be funded by customers, (ii) $1.25 million that will be paid over five years to the Navajo Nation to fund an economic development organization, which would be funds not recoverable through rates, (iii) $10 million to facilitate electrification projects within the Navajo Nation, which would be funded equally by funds not recoverable through rates and by customers, (iv) $2.5 million per year in transmission revenue sharing to be paid to the Navajo Nation beginning after the closure of the Four Corners through 2038, which would be funds not recoverable through rates, (v) $12 million that will be paid over five years to the Navajo County Communities surrounding Cholla Power Plant, which would primarily be funded by customers, and (vi) $3.7 million that will be paid over five years to the Hopi Tribe related to APS’s ownership interests in the Navajo Plant, which would primarily be funded by customers. The commitment of funds that would not be recoverable through rates of $25 million were recognized in our December 31, 2020 financials. In 2021, APS committed an additional $900,000 to be paid to the Hopi Tribe related to APS’s ownership interests in the Navajo Plant, and this amount was recognized in its December 31, 2021 financials. On December 4, 2020, the ACC Staff and intervenors filed surrebuttal testimony. The ACC Staff reduced its recommended rate increase to $59.8 million, or an average annual customer bill increase of 1.82%. In RUCO’s surrebuttal, the recommended revenue decrease changed to $50.1 million, or an average annual customer bill decrease of 1.52%. The hearing concluded on March 3, 2021, and the post-hearing briefing concluded on April 30, 2021. On August 2, 2021, the Administrative Law Judge issued a Recommended Opinion and Order in the 2019 Rate Case (the “2019 Rate Case ROO”) and issued corrections on September 10 and September 20, 2021. The 2019 Rate Case ROO recommended, among other things, (i) a $111 million decrease in annual revenue requirements, (ii) a return on equity of 9.16%, (iii) a 0.30% return on the increment of fair value rate base greater than original cost, with total fair value rate of return further adjusted to include a 0.03% reduction to return on equity resulting in an effective fair value rate of return of 4.95%, (iv) the nonrecovery of the deferral and rate base effects of the operating costs and construction of the Four Corners SCR project (see “Four Corners SCR Cost Recovery” below for additional in formation), (v) the recovery of the deferral and rate base effects of the operating costs and construction of the Ocotillo modernization project, which includes a reduction in the return on the deferral, (vi) a 15% disallowance of annual amortization of Navajo Plant regulatory asset recovery, (vii) the denial of the request to defer, until APS’s next general rate case, the increase or decrease in its Arizona property taxes attributable to tax rate changes, and (viii) a collaborative process to review and recommend revisions to APS’s adjustment mechanisms within 12 months after the date of the decision. The 2019 Rate Case ROO also recommended that the CCT plan include the following components: (i) $50 million that will be paid over 10 years to the Navajo Nation, (ii) $5 million that will be paid over five years to the Navajo County Communities surrounding Cholla Power Plant, and (iii) $1.675 million that will be paid to the Hopi Tribe related to APS’s ownership interests in the Navajo Plant. These amounts would be recoverable from APS’s customers through the Arizona Renewable Energy Standard and Tariff (“RES”) adjustment mechanism. APS filed exceptions on September 13, 2021, regarding the disallowance of the SCR cost deferrals and plant investments that was recommended in the 2019 Rate Case ROO, among other issues. On October 6, 2021 and October 27, 2021, the ACC voted on various amendments to the 2019 Rate Case ROO that would result in, among other things, (i) a return on equity of 8.70%, (ii) the recovery of the deferral and rate base effects of the operating costs and construction of the Four Corners SCR project, with the exception of $215.5 million (see “Four Corners SCR Cost Recovery” below), (iii) that the CCT plan include the following components: (a) a payment of $1 million to the Hopi Tribe within 60 days of the 2019 Rate Case decision, (b) a payment of $10 million over three years to the Navajo Nation, (c) a payment of $0.5 million to the Navajo County communities within 60 days of the 2019 Rate Case decision, (d) up to $1.25 million for electrification of homes and businesses on the Hopi reservation, and (e) up to $1.25 million for the electrification of homes and businesses on the Navajo Nation reservation. These payments and expenditures are attributable to the future closures of Four Corners and Cholla, along with the prior closure of the Navajo Plant and all ordered payments and expenditures would be recoverable through rates, and (iv) a change in the residential on-peak time-of-use period from 3 p.m. to 8 p.m. to 4 p.m. to 7 p.m. Monday through Friday, excluding holidays. The 2019 Rate Case ROO, as amended, results in a total annual revenue decrease for APS of $4.8 million, excluding temporary CCT payments and expenditures. On November 2, 2021, the ACC approved the 2019 Rate Case ROO, as amended. On November 24, 2021, APS filed an application for rehearing of the 2019 Rate Case with the ACC and the application was deemed denied on December 15, 2021, as the ACC did not act upon it. On December 17, 2021, APS filed its Notice of Direct Appeal at the Arizona Court of Appeals and a Petition for Special Action with the Arizona Supreme Court, requesting review of the disallowance of $215 million of Four Corners SCR plant investments and deferrals (see “Four Corners SCR Cost Recovery” below for additional information) and the 20 basis point penalty reduction to the return on equity. On February 8, 2022, the Arizona Supreme Court declined to accept jurisdiction on APS’s Petition for Special Action. The appeal at the Arizona Court of Appeals is proceeding in the normal course. APS cannot predict the outcome of this proceeding. Consistent with the 2019 Rate Case decision, APS implemented the new rates effective as of December 1, 2021. On December 3, 2021, ACC Staff notified the ACC of a discrepancy between the written decision, which approved the change in time-of-use on-peak hours to 4 p.m. to 7 p.m. but did not explicitly approve the 10 months contemplated in APS’s verbal testimony to implement the new time-of-use hours. On December 16, 2021, the ACC ordered APS to complete the implementation of the time-of-use peak period by April 1, 2022. On January 12, 2022, the ACC voted to extend the deadline until September 1, 2022, to complete the implementation of the new on-peak hours for residential customers. In addition, the ACC ordered extensive compliance and reporting obligations and will be continuing to explore whether penalties or rebates would be owed to certain customers. APS cannot predict the outcome of this matter. Additionally, consistent with the 2019 Rate Case decision, as of April 2022, APS has completed the following payments that will be recoverable through rates related to the CCT: (i) $3.33 million to the Navajo Nation; (ii) $500,000 to the Navajo County communities; and (iii) $1 million to the Hopi Tribe. Consistent with APS’s commitment to the impacted communities, APS has also completed the following payments: (i) $500,000 to the Navajo Nation for CCT; (ii) $1.1 million to the Navajo County Communities for CCT and economic development; and (iii) $1.25 million to the Hopi Tribe for CCT and economic development. The ACC has also authorized $1.25 million to be recovered through rates for electrification of homes and businesses on both the Navajo Nation and Hopi reservation. Expenditure of the recoverable funds for electrification of homes and businesses on the Navajo Nation and the Hopi reservations is contingent upon completion of a census of the unelectrified homes and businesses in each that are also within APS service territory. APS expects to file an application with the ACC for its next general retail rate case by the end of October 2022, allowing for a test year ending June 30, 2022. Information Technology ACC Investigation On December 16, 2021, the ACC opened an investigation into various matters related to APS’s Information Technology department, including information about technology projects, costs, vendor management leadership and decision making. APS is cooperating with the investigation. APS cannot predict the outcome of this matter. 2016 Retail Rate Case Filing On June 1, 2016, APS filed an application with the ACC for an annual increase in retail base rates. On March 27, 2017, a majority of the stakeholders in the general retail rate case, including the ACC Staff, RUCO, limited income advocates and private rooftop solar organizations signed a settlement agreement (the “2017 Settlement Agreement”) and filed it with the ACC. The 2017 Settlement Agreement provides for a net retail base rate increase of $94.6 million, excluding the transfer of adjustor balances, consisting of: (1) a non-fuel, non-depreciation, base rate increase of $87.2 million per year; (2) a base rate decrease of $53.6 million attributable to reduced fuel and purchased power costs; and (3) a base rate increase of $61.0 million due to changes in depreciation schedules. Other key provisions of the 2017 Settlement Agreement include the following: • an authorized return on common equity of 10.0%; • a capital structure comprised of 44.2% debt and 55.8% common equity; • a cost deferral order for potential future recovery in APS’s next general retail rate case for the construction and operating costs APS incurs for its Ocotillo modernization project; • a cost deferral and procedure to allow APS to request rate adjustments prior to its next general retail rate case related to its share of the construction costs associated with installing SCR equipment at the Four Corners; • a deferral for future recovery (or credit to customers) of the Arizona property tax expense above or below a specified test year level caused by changes to the applicable Arizona property tax rate; • an expansion of the Power Supply Adjustor (“PSA”) to include certain environmental chemical costs and third-party energy storage costs; • a new AZ Sun II program (now known as “APS Solar Communities”) for utility-owned solar distributed generation (“DG”) with the purpose of expanding access to rooftop solar for low-and moderate-income Arizonans, recoverable through the RES, to be no less than $10 million per year in capital costs, and not more than $15 million per year in capital costs; • an increase to the per kWh cap for the environmental improvement surcharge from $0.00016 to $0.00050 and the addition of a balancing account; • rate design changes, including: ▪ a change in the on-peak time-of-use period from noon to 7 p.m. to 3 p.m. to 8 p.m. Monday through Friday, excluding holidays; ▪ non-grandfathered DG customers would be required to select a rate option that has time of use rates and either a new grid access charge or demand component; ▪ a Resource Comparison Proxy (“RCP”) for exported energy of 12.9 cents per kWh in year one; and • an agreement by APS not to pursue any new self-build generation (with certain exceptions) having an in-service date prior to January 1, 2022 (extended to December 31, 2027, for combined-cycle generating units), unless expressly authorized by the ACC. On August 15, 2017, the ACC approved the 2017 Settlement Agreement without material modifications and on August 18, 2017, the ACC issued a final written Opinion and Order reflecting its decision in APS’s general retail rate case (the “2017 Rate Case Decision”). The new rates went into effect on August 19, 2017. See “Rate Plan Comparison Tool and Investigation” below for information regarding a review and investigation pertaining to the rate plan comparison tool offered to APS customers and other related issues. Cost Recovery Mechanisms APS has received regulatory decisions that allow for more timely recovery of certain costs outside of a general retail rate case through the following recovery mechanisms. Renewable Energy Standard . In 2006, the ACC approved the RES. Under the RES, electric utilities that are regulated by the ACC must supply an increasing percentage of their retail electric energy sales from eligible renewable resources, including solar, wind, biomass, biogas and geothermal technologies. In order to achieve these requirements, the ACC allows APS to include a RES surcharge as part of customer bills to recover the approved amounts for use on renewable energy projects. Each year, APS is required to file a five-year implementation plan with the ACC and seek approval for funding the upcoming year’s RES budget. In 2015, the ACC revised the RES rules to allow the ACC to consider all available information, including the number of rooftop solar arrays in a utility’s service territory, to determine compliance with the RES. On November 20, 2017, APS filed an updated 2018 RES budget to include budget adjustments for APS Solar Communities (formerly known as AZ Sun II), which was approved as part of the 2017 Rate Case Decision. APS Solar Communities is a 3-year program authorizing APS to spend $10 million to $15 million in capital costs each year to install utility-owned DG systems for low to moderate income residential homes, non-profit entities, Title I schools and rural government facilities. The 2017 Rate Case Decision provided that all operations and maintenance expenses, property taxes, marketing and advertising expenses, and the capital carrying costs for this program will be recovered through the RES. On July 1, 2019, APS filed its 2020 RES Implementation Plan and proposed a budget of approximately $86.3 million. APS’s budget request supports existing approved projects and commitments and requests a permanent waiver of the RES residential distributed energy requirement for 2020. On September 23, 2020, the ACC approved the 2020 RES Implementation Plan, including APS’s requested waiver of the residential distributed energy requirements for 2020. In addition, the ACC approved the implementation of a new pilot program that incentivizes Arizona households to install at-home battery systems. Recovery of the costs associated with the pilot will be addressed in the 2021 Demand Side Management Implementation Plan (“DSM Plan”). On July 1, 2020, APS filed its 2021 RES Implementation Plan and proposed a budget of approximately $84.7 million. APS’s budget request supports existing approved projects and commitments and requests a permanent waiver of the RES residential distributed energy requirement for 2021. In the 2021 RES Implementation Plan, APS requested $4.5 million to meet revenue requirements associated with the APS Solar Communities program to complete installations delayed as a result of the COVID-19 pandemic in 2020. On June 7, 2021, the ACC approved the 2021 RES Implementation Plan, including APS’s requested waiver of the residential distributed energy requirements for 2021. As part of the approval, the ACC approved the requested budget and authorized APS to collect $68.3 million through the Renewable Energy Adjustment Charge to support APS’s RES programs. In June 2021, the ACC adopted a clean energy rules package which would require APS to meet certain clean energy standards and technology procurement mandates, obtain approval for its action plan included in its IRP, and seek cost recovery in a rate process. Since the adopted clean energy rules differed substantially from the original Recommended Order and Opinion, supplemental rulemaking procedures were required before the rules could become effective. On January 26, 2022, the ACC reversed its prior decision and declined to send the final draft energy rules through the rulemaking process. Instead, the ACC opened a new docket to consider all-source requests for proposals (“RFP”) requirements and the IRP process. See “Energy Modernization Plan” below for more information. On July 1, 2021, APS filed its 2022 RES Implementation Plan and proposed a budget of approximately $93.1 million. APS filed an amended 2022 RES Implementation Plan on December 9, 2021, with a proposed budget of $100.5 million. This budget includes funding for programs to comply with the decision in the 2019 Rate Case, including the ACC authorizing spending $20 million to $30 million in capital costs for the APS Solar Communities program each year for a period of three years from the effective date of the 2019 Rate Case decision. APS’s budget proposal supports existing approved projects and commitments and requests a waiver of the RES residential and non-residential distributed energy requirements for 2022. On May 18, 2022, the ACC approved the 2022 RES Implementation Plan, including an amendment requiring a stakeholder working group convene to develop a community solar program for the Commission’s consideration at a future date. In response to an ACC inquiry, the ACC Staff filed a report providing the history of APS’s long-term purchased power contract of the 280 MW Concentrating Solar Power Plant. This report outlines alternative options that the ACC could pursue to address the costs of this contract, which was executed in February 2008. On July 13, 2022, the ACC approved an option to take no action at this time. Demand Side Management Adjustor Charge . The ACC Electric Energy Efficiency Standards require APS to submit a DSM Plan annually for review and approval by the ACC. Verified energy savings from APS’s resource savings projects can be counted toward compliance with the Electric Energy Efficiency Standards; however, APS is not allowed to count savings from systems savings projects toward determination of the achievement of performance incentives, nor may APS include savings from these system savings projects in the calculation of its Lost Fixed Cost Recovery (“LFCR”) mechanism. See below for discussion of the LFCR. On September 1, 2017, APS filed its 2018 DSM Plan, which proposed modifications to the DSM portfolio to better meet system and customer needs by focusing on peak demand reductions, storage, load shifting and demand response programs in addition to traditional energy savings measures. The 2018 DSM Plan sought a requested budget of $52.6 million and requested a waiver of the Electric Energy Efficiency Standard for 2018. On November 14, 2017, APS filed an amended 2018 DSM Plan, which revised the allocations between budget items to address customer participation levels but kept the overall budget at $52.6 million. On December 31, 2018, APS filed its 2019 DSM Plan, which requested a budget of $34.1 million and focused on DSM strategies to better meet system and customer needs, such as peak demand reduction, load shifting, storage and electrification strategies. On December 31, 2019, APS filed its 2020 DSM Plan, which requested a budget of $51.9 million and continued APS’s focus on DSM strategies such as peak demand reduction, load shifting, storage and electrification strategies. The 2020 DSM Plan addressed all components of the pending 2018 and 2019 DSM plans, which enabled the ACC to review the 2020 DSM Plan only. On May 15, 2020, APS filed an amended 2020 DSM Plan to provide assistance to customers experiencing economic impacts of the COVID-19 pandemic. The amended 2020 DSM Plan requested the same budget amount of $51.9 million. On September 23, 2020, the ACC approved the amended 2020 DSM Plan. On April 17, 2020, APS filed an application with the ACC requesting a COVID-19 emergency relief package to provide additional assistance to its customers. On May 5, 2020, the ACC approved APS returning $36 million that had been collected through the DSM Adjustor Charge, but not allocated for current DSM programs, directly to customers through a bill credit in June 2020. APS has refunded approximately $43 million to customers. The additional $7 million over the ACC-approved amount was the result of the kWh credit being based on historic consumption which was different than actual consumption during the refund period. The difference was recorded to the DSM balancing account and was included in the 2021 DSM Implementation Plan, as described below. On December 31, 2020, APS filed its 2021 DSM Plan, which requested a budget of $63.7 million and continued APS’s focus on DSM strategies, such as peak demand reduction, load shifting, storage and electrification strategies, as well as enhanced assistance to customers impacted economically by COVID-19. On April 6, 2021, APS filed an amended 2021 DSM Plan that proposed an additional performance incentive for customers participating in the residential energy storage pilot program approved in the 2020 RES Implementation Plan. On July 13, 2021, the ACC approved the amended 2021 DSM Plan. On April 20, 2021, APS filed a request to extend the June 1, 2021 deadline to file its 2022 DSM Plan until 120 days after the ACC has taken action on APS’s amended 2021 DSM Plan. The ACC approved the request, granting an extension until 120 days after the ACC action on the 2021 DSM Plan, or December 31, 2021, whichever is later. On December 17, 2021, APS filed its 2022 DSM Plan, which requested a budget of $78.4 million and represents an increase of approximately $14 million in DSM spending above 2021. In March 2022, APS indicated that it intends to file its 2023 DSM Plan within 120 days after the ACC has taken action on APS's 2022 DSM Plan. The ACC has not yet ruled on the 2022 DSM Plan. Power Supply Adjustor Mechanism and Balance. The PSA provides for the adjustment of retail rates to reflect variations primarily in retail fuel and purchased power costs. The following table shows the changes in the deferred fuel and purchased power regulatory asset for 2022 and 2021 (dollars in thousands): Six Months Ended 2022 2021 Beginning balance $ 388,148 $ 175,835 Deferred fuel and purchased power costs — current period 98,707 135,905 Amounts charged to customers (96,842) (10,828) Ending balance $ 390,013 $ 300,912 On November 27, 2019, APS filed its PSA rate for the PSA year beginning February 1, 2020. That rate was $(0.000456) per kWh, which consisted of a forward component of $(0.002086) per kWh and a historical component of $0.001630 per kWh. The 2020 PSA rate is a $0.002115 per kWh decrease compared to the 2019 PSA year. These rates went into effect as filed on February 1, 2020. On November 30, 2020, APS filed its PSA rate for the PSA year beginning February 1, 2021. That rate was $0.003544 per kWh, which consisted of a forward component of $0.003434 per kWh and a historical component of $0.000110 per kWh. The 2021 PSA rate is a $0.004 per kWh increase compared to the 2020 PSA year, which is the maximum permitted under the Plan of Administration for the PSA. This left $215.9 million of fuel and purchased power costs above this annual cap which will be reflected in future year resets of the PSA. These rates were to be effective on February 1, 2021, but APS delayed the effectiveness of these rates until the first billing cycle of April 2021 due to concerns of the impact on customers during COVID-19. In March 2021, the ACC voted to implement the 2021 PSA rate on a staggered basis, with 50% of the rate increase taking effect in April 2021, and the remaining 50% taking effect in November 2021. The PSA rate implemented on April 1, 2021 was $0.001544 per kWh, which consisted of a forward component of $(0.004444) per kWh and a historical component of $0.005988 per kWh. On November 1, 2021, the remaining increase was implemented to a rate of $0.003544 per kWh and consisted of a forward component of $(0.004444) per kWh and a historical component of $0.007988 per kWh. As part of this approval, the ACC ordered ACC Staff to conduct a fuel and purchased power procurement audit to better understand the factors that contributed to the increase in fuel costs. On April 1, 2022, the ACC filed a final report of its audit findings regarding APS’s fuel and purchased power costs for the period January 2019 through January 2021. The report contains an in-depth review of APS’s fuel and purchased power contracts, its monthly fuel accounting activities, its forecasting and dispatching procedures, and its monthly PSA filings, among other fuel-related activities. The report finds that the APS’s fuel processing accounting practices, dispatching procedures, and procedures for hedging activity are reasonable and appropriate. The report includes several recommendations for the ACC’s consideration, including review of current contracts, maintenance schedules, and certain changes and improvements to the schedules in APS’s monthly PSA filings. APS cannot predict the future impacts, if any, of this audit. On November 30, 2021, APS filed its PSA rate for the PSA year beginning February 1, 2022. That rate was $0.007544 per kWh, which consisted of a forward component of $(0.004842) per kWh and a historical component of $0.012386 per kWh. The 2022 PSA rate is a $0.004 per kWh increase compared to the 2021 PSA year, which is the maximum permitted under the Plan of Administration for the PSA. These rates went into effect as filed on February 1, 2022. At the time of the compliance filing, the amount remaining over the annual cap was approximately $365 million of fuel and purchased power costs which will be reflected in future year resets of the PSA. On March 15, 2019, APS filed an application with the ACC requesting approval to recover the costs related to two energy storage power purchase tolling agreements through the PSA, and on January 12, 2021, the ACC approved this application. On October 28, 2021, APS filed an application requesting approval to recover costs related to three additional energy storage projects through the PSA once the systems are in service, and on December 16, 2021, the ACC approved this application. On February 22, 2022, APS filed an application requesting similar recovery through the PSA for a solar plus energy storage project, and on April 13, 2022, the ACC approved this application. For each of these applications that have been approved by the ACC, the ACC has not ruled on prudency. Environmental Improvement Surcharge. The EIS permits APS to recover the capital carrying costs (rate of return, depreciation and taxes) plus incremental operations and maintenance expenses associated with environmental improvements made outside of a test year to comply with environmental standards set by federal, state, tribal, or local laws and regulations. A filing is made on or before February 1 each year for qualified environmental improvements since the prior rate case test year, and the new charge becomes effective April 1 unless suspended by the ACC. There is an overall cap of $0.0005 per kWh (approximately $13 million to $14 million per year). APS’s February 1, 2022 application requested an increase in the charge to $11.4 million, or $1.1 million over the prior-period charge, and it became effective with the first billing cycle in April 2022. Transmission Rates, Transmission Cost Adjustor (“TCA”) and Other Transmission Matters . In July 2008, FERC a |