Vogtle Units No. 3 and No. 4 Construction Project | Vogtle Units No. 3 and No. 4 Construction Project. We, Georgia Power, the Municipal Electric Authority of Georgia (MEAG), and the City of Dalton, Georgia, acting by and through its Board of Water, Light and Sinking Fund Commissioners, doing business as Dalton Utilities (collectively, the Co-owners) are parties to an Ownership Participation Agreement that, along with other agreements, governs our participation in two additional nuclear units under construction at Plant Vogtle, Units No. 3 and No. 4. The Co-owners appointed Georgia Power to act as agent under this agreement. Pursuant to this agreement, Georgia Power has designated Southern Nuclear Operating Company, Inc. as its agent for licensing, engineering, procurement, contract management, construction and pre-operation services. In 2008, Georgia Power, acting for itself and as agent for the Co-owners, entered into an Engineering, Procurement and Construction Agreement (the EPC Agreement) with Westinghouse Electric Company LLC and Stone & Webster, Inc., which was subsequently acquired by Westinghouse and changed its name to WECTEC Global Project Services Inc. (collectively, Westinghouse). Pursuant to the EPC Agreement, Westinghouse agreed to design, engineer, procure, construct and test two 1,100 megawatt nuclear units using the Westinghouse AP1000 technology and related facilities at Plant Vogtle. Until March 2017, construction on Units No. 3 and No. 4 continued under the substantially fixed price EPC Agreement. In March 2017, Westinghouse filed for bankruptcy protection under Chapter 11 of the United States Bankruptcy Code. Effective in July 2017, Georgia Power, acting for itself and as agent for the other Co-owners, and Westinghouse entered into a services agreement (the Services Agreement), pursuant to which Westinghouse is providing facility design and engineering services, procurement and technical support and staff augmentation on a time and materials cost basis. The Services Agreement provides that it will continue until the start-up and testing of Vogtle Units No. 3 and No. 4 is complete and electricity is generated and sold from both units. The Services Agreement is terminable by the Co-owners upon 30 days' written notice. In October 2017, Georgia Power, acting for itself and as agent for the other Co-owners, entered into a construction completion agreement with Bechtel Power Corporation, pursuant to which Bechtel serves as the primary contractor for the remaining construction activities for Vogtle Units No. 3 and No. 4 (the Bechtel Agreement) and is reimbursed for actual costs plus a base fee and an at-risk fee, subject to adjustment based on Bechtel's performance against cost and schedule targets. Each Co-owner is severally, and not jointly, liable for its proportionate share, based on its ownership interest, of all amounts owed to Bechtel under the Bechtel Agreement. The Co-owners may terminate the Bechtel Agreement at any time for their convenience, provided that the Co-owners will be required to pay amounts related to work performed prior to the termination (including the applicable portion of the base fee), certain termination-related costs and, at certain stages of the work, the applicable portion of the at-risk fee. Bechtel may terminate the Bechtel Agreement under certain circumstances, including certain Co-owner suspensions of work, certain breaches of the Bechtel Agreement by the Co-owners, Co-owner insolvency and certain other events. Cost and Schedule Our current budget for our ownership interest in Vogtle Units No. 3 and No. 4, which includes capital costs, allowance for funds used during construction and some level of contingency is $8.1 billion and is based on commercial operation dates of March 2023 and March 2024 for Units No. 3 and No. 4, respectively. This budget reflects our June 17, 2022 exercise of the tender option in the Global Amendments to the Joint Ownership Agreements as described below. Had we not exercised the tender option, our budget would be approximately $8.6 billion. At June 30, 2022, our total investment for our interest in the additional Vogtle units was approximately $7.5 billion. We and some of our members have implemented various rate management programs to lessen the impact on rates when Vogtle Units No. 3 and No. 4 reach commercial operation. Our initial ownership interest and proportionate share of the cost to construct the additional Vogtle units was 30%, representing approximately 660 megawatts. However, we have exercised the tender option discussed below which caps our capital costs in exchange for a proportionate reduction of our 30% interest in the two units. Based on the current project budget and schedule and our interpretation of the Global Amendments (described below), we would transfer approximately 50 megawatts, out of 660 megawatts, to Georgia Power. Our resulting ownership share would decline from 30% to approximately 28%. However, if the total project budget exceeds the current budget, our ownership share and megawatts would be further reduced. The Oglethorpe-level contingency, which we have carried at various levels since the beginning of the project, provides additional margin to cover potential cost, schedule, and financing risks associated with our share of the project. At the end of the project, if there is remaining Oglethorpe-level contingency, we will adjust our project budget to remove this contingency and bill our members based on the actual project costs. The table below shows our project budget and actual costs through June 30, 2022 for our share of the project. (in millions) Project Budget (Tender) Actual Costs at Construction Costs (1) $ 6,021 $ 5,842 Financing Costs 1,966 1,626 Subtotal $ 7,987 $ 7,468 Deferred Training Costs 54 46 Total Project Costs Before Contingency $ 8,041 $ 7,514 Oglethorpe-Level Contingency 59 — Total Contingency $ 59 $ — Totals $ 8,100 $ 7,514 (1) Construction costs are net of $1.1 billion we received from Toshiba Corporation under a Guarantee Settlement Agreement and $99 million in cost sharing benefits associated with the Global Amendments to the Joint Ownership Agreements. Any schedule extension beyond March 2023 and March 2024 for Units No. 3 and No. 4, respectively, is expected to increase our financing costs by approximately $30 million per month for both units and approximately $13 million per month for Unit No. 4. As part of its ongoing processes, Southern Nuclear continues to evaluate cost and schedule forecasts on a regular basis to incorporate current information available, particularly in the areas of engineering support, commodity installation, system turnovers and related test results and workforce statistics. Since March 2020, the number of active cases of COVID-19 at the site has fluctuated consistent with the surrounding area and impacted productivity levels and pace of activity completion. COVID-19 has exacerbated the challenges facing the project, including, but not limited to, higher than expected absenteeism; overall construction and subcontractor labor productivity; system turnover and testing activities; and electrical equipment and commodity installation. As of June 30, 2022, the incremental cost associated with COVID-19 mitigation actions and impacts on construction productivity, substantially all of which occurred during 2020 and 2021, is estimated by Georgia Power to be between $350 million and $438 million and is included in the project budget. Subsequent waves of the COVID-19 pandemic could further disrupt or delay construction, testing, supervisory, and support activities at Vogtle Units No. 3 and No. 4. The Unit No. 3 projected schedule primarily depends on pace of system and area turnovers, timing of fuel load and the progression of startup and other testing. On August 3, 2022, the Nuclear Regulatory Commission approved Southern Nuclear’s 103(G) letter for Unit No. 3 which was the final Nuclear Regulatory Commission finding necessary for Southern Nuclear to begin fuel load and start-up sequence. Georgia Power has disclosed that it projects an in-service date for Unit No. 3 during the first quarter of 2023. Our current budget reflects our expectation of an in-service date for Unit No. 3 in March 2023. Georgia Power has disclosed that it projects an in-service date for Unit No. 4 during the fourth quarter 2023. Given the remaining work to be done and potential risks associated with completing the work, our current budget anticipates an in-service date for Unit No. 4 that is one quarter later, in March 2024. Meeting the projected in-service date for Unit No. 4 primarily depends on Unit No. 3 progress through fuel load, startup and testing, overall construction productivity and production levels significantly improving, particularly in electrical installation, including terminations, as well as appropriate levels of craft laborers, particularly electricians and pipefitters, being added and maintained. As Unit No. 3 completes system turnover from construction and moves to testing and transitions to operations, ongoing and potential future challenges include construction productivity and final component and pre-operational tests. As Unit No. 4 progresses through construction and transitions into testing, ongoing and potential future challenges include the pace and quality of electrical installation; availability of craft and supervisory resources; the pace of work package closures and system turnovers; and the timeframe and duration of hot functional and other testing. As construction, including subcontract work, continues on Unit No. 4, ongoing or future challenges include management of contractors and vendors; subcontractor performance; supervision of craft labor and related productivity, particularly in the installation of electrical, mechanical, and instrumentation and controls commodities, ability to attract and retain craft labor, and/or related cost escalation; and procurement and related installation. New challenges may arise, particularly as Units No. 3 and No. 4 move into initial testing and start-up, which may result in required engineering changes or remediation related to plant systems, structures or components (some of which are based on new technology that only within the last few years began initial operation in the global nuclear industry at this scale). The ongoing and potential future challenges described above may further impact the projected schedule and estimated cost. There have been technical and procedural challenges to the construction and licensing of Vogtle Units No. 3 and No. 4 at the federal and state level and additional challenges may arise. Additional license amendment requests may be filed with the Nuclear Regulatory Commission. Processes are in place that are designed to ensure compliance with the requirements specified in the Westinghouse Design Control Document and the combined construction and operating licenses, including inspections by Southern Nuclear and the Nuclear Regulatory Commission that occur throughout construction. In connection with the additional construction remediation work described above, Southern Nuclear reviewed the project’s construction quality programs and, where needed, is implementing improvement plans consistent with these processes. On March 25, 2022, the Nuclear Regulatory Commission completed its follow up inspection related to the November 2021 final significance report on its special inspection to review the root cause of this additional construction remediation work and the corresponding corrective action plans. The Nuclear Regulatory Commission closed the findings identified in November 2021 and returned Unit No. 3 to the Nuclear Regulatory Commission’s baseline inspection program. Various design and other licensing-based compliance matters, including the completion of inspections, tests, analyses, and acceptance criteria documentation for Unit No. 4 and the related reviews and approvals by the Nuclear Regulatory Commission necessary to support authorization to load fuel, have arisen and may arise, which may result in additional license amendments or require other resolution. If any license amendment requests or other licensing-based compliance issues, including inspections, tests, analyses, and acceptance criteria, are not resolved in a timely manner, there may be further delays in the project schedule that could result in increased costs to the Co-owners. The ultimate outcome of these matters cannot be determined at this time. Co-Owner Contracts and Other Information In November 2017, the Co-owners entered into an amendment to their joint ownership agreements for Vogtle Units No. 3 and No. 4 to provide for, among other conditions, additional Co-owner approval requirements. These joint ownership agreements, including the Co-owner approval requirements, were subsequently amended, effective August 31, 2018. As described below, certain provisions of the Joint Ownership Agreements were modified further on September 26, 2018 by the Term Sheet that was memorialized on February 18, 2019 when the Co-owners entered into certain amendments (the Global Amendments) to the Joint Ownership Agreements (as amended, the Joint Ownership Agreements). As a result of an increase in the total project capital cost forecast and Georgia Power’s decision not to seek recovery of its allocation of the increase in the base capital costs and the increased construction budget in connection with Georgia Power’s nineteenth Vogtle construction monitoring report (VCM 19) in 2018, the holders of at least 90% of the ownership interests in Vogtle Units No. 3 and No. 4 were required to vote to continue construction. In September 2018, the Co-owners unanimously voted to continue construction of Vogtle Units No. 3 and No. 4. In connection with the September 2018 vote to continue construction, Georgia Power entered into a binding term sheet with the other Co-owners and MEAG’s wholly-owned subsidiaries MEAG Power SPVJ, LLC, MEAG Power SPVM, LLC, and MEAG Power SPVP, LLC to mitigate certain financial exposure for the other Co-owners and offered to purchase production tax credits from each of the other Co-Owners, at that Co-owner’s option (the Term Sheet). On February 18, 2019, the Co-owners entered into the Global Amendments to memorialize the provisions of the Term Sheet. Pursuant to the Global Amendments and consistent with the Term Sheet, the Joint Ownership Agreements provide that: • each Co-owner is obligated to pay its proportionate share of construction costs for Vogtle Units No. 3 and No. 4 based on its ownership interest up to (i) the estimated cost at completion ("EAC") for Vogtle Units No. 3 and No. 4 which formed the basis of Georgia Power's forecast of $8.4 billion in Georgia Power's VCM 19 filed with the Georgia Public Service Commission plus (ii) $800 million of additional construction costs; • Georgia Power will be responsible for 55.7% of construction costs, subject to exceptions such as costs that are a result of a force majeure event, that exceed the EAC in VCM 19 by $800 million to $1.6 billion (resulting in up to $80 million of potential additional costs to Georgia Power which would save Oglethorpe up to $44 million), with the remaining Co-owners responsible for 44.3% of such costs pro rata in accordance with their respective ownership interests (equal to 24.5% for our 30% ownership interest); and • Georgia Power will be responsible for 65.7% of construction costs, subject to exceptions such as costs that are a result of a force majeure event, that exceed the EAC in VCM 19 by $1.6 billion to $2.1 billion (resulting in up to a further $100 million of potential additional costs to Georgia Power which would save Oglethorpe up to an additional $55 million), with the remaining Co-owners responsible for 34.3% of such costs pro rata in accordance with their respective ownership interests (equal to 19.0% for our 30% ownership interest). If the EAC is revised and exceeds the EAC in VCM 19 by more than $2.1 billion, each of the Co-owners, other than Georgia Power, has a one-time option to tender a portion of its ownership interest to Georgia Power in exchange for Georgia Power’s agreement to pay 100% of such Co-owner’s share of construction costs actually incurred in excess of the EAC in VCM 19 plus $2.1 billion. If any Co-owner elects to exercise this tender option, Georgia Power would have the option to cancel the project in lieu of accepting the offer to purchase a portion of the Co-owner’s ownership interest. If Georgia Power does not elect to cancel the project, then Georgia Power must accept the offer, and the ownership interest to be conveyed from the tendering Co-owner to Georgia Power will be calculated based on the percentage of the cumulative amount of construction costs paid by such tendering Co-owner as of the commercial operation date of Vogtle Unit No. 4. For purposes of this calculation, payments made by Georgia Power on behalf of the tendering Co-owner in accordance with the second and third bullets above will be treated as payments made by that Co-owner. This option to tender a portion of our interest to Georgia Power upon such a budget increase would allow us to freeze our construction budget associated with the Vogtle project in exchange for a proportionate reduction of our 30% ownership interest. The VCM 19 total project cost is $17.1 billion (which excludes non-shareable costs) as reflected in numerous Georgia Public Service Commission filings. As of December 31, 2021, budget increases since VCM 19 have reached $3.4 billion for all Co-owners. As a result of these increases, we believe that the tender option was triggered at the Co-owner construction budget vote on February 14, 2022 and that Georgia Power’s increased responsibility for certain construction costs as described above commenced in March 2022. On June 17, 2022, we notified Georgia Power of our election to exercise the tender option and cap our capital costs in exchange for a proportionate reduction of our 30% interest in the two new units. Our decremental ownership interest will be calculated and conveyed to Georgia Power after both Vogtle units are placed in service. Based on the current project budget, our schedule assumptions and our interpretation of the Global Amendments, our project budget is $8.1 billion and we expect to transfer approximately 50 megawatts, out of 660 megawatts, to Georgia Power. Our resulting ownership share will decline from 30% to approximately 28%. By exercising the tender option and based on current assumptions, we estimate that we will avoid incurring approximately $475 million in construction costs associated with the project. However, if the total project budget exceeds the current budget, our ownership share and megawatts would be further reduced. On July 26, 2022, the City of Dalton notified Georgia Power that it had elected to exercise its tender option. MEAG must notify Georgia Power by August 27, 2022 whether it intends to exercise its tender option. Georgia Power and the other Co-owners do not agree on certain aspects of the tender option, including the dollar amount that triggers each Co-owner’s option to tender a portion of its ownership interest to Georgia Power under the tender option or the extent to which costs that are the result of a force majeure event (such as COVID-19) impact the point at which the tender option is triggered. For purposes of determining when the Co-owners’ option to tender has been triggered, the Global Amendments do not exclude costs resulting from force majeure events (such as COVID-19) from the calculation of when the EAC in VCM 19 plus $2.1 billion has been reached. Georgia Power and the other Co-owners also do not agree on the dollar amount that triggers Georgia Power’s increased responsibility for certain construction costs as described above, and the extent to which costs that are the result of a force majeure event (such as COVID-19), impact the calculation of the point at which Georgia Power’s increased responsibility for certain construction costs as described above is triggered. The exclusion of costs resulting from a force majeure event (such as COVID-19) in the Global Amendments only applies to Georgia Power’s increased cost responsibility during the time period when construction costs exceed the EAC in the nineteenth VCM report by $800 million to $2.1 billion. Accordingly, in March 2022, we notified Georgia Power of a billing dispute with regards to both the starting dollar amount and the application of costs resulting from a force majeure event and how such amounts impact the thresholds and timing of the cost-sharing and tender option provisions. On June 18, 2022, after completing the dispute resolution procedures set forth in the Ownership Participation Agreement for the additional Vogtle units, we and MEAG filed separate lawsuits against Georgia Power in the Superior Court of Fulton County, Georgia seeking to enforce the terms of the Global Amendments. The lawsuits seek declaratory judgment that the cost sharing and tender provisions of the Global Amendments have been triggered based on a VCM 19 forecast of $17.1 billion . The lawsuits also allege breach of contract and assert other claims and seek damages and injunctive relief requiring Georgia Power to track and allocate construction costs consistent with our and MEAG’s interpretations of the Global Amendments. Subsequently, the City of Dalton filed a motion to intervene and join in our and MEAG's claims. On July 28, 2022, Georgia Power filed a counterclaim against us seeking a declaratory judgment that the starting dollar amount is $18.38 billion and that costs related to force majeure events are excluded prior to calculating the cost-sharing and tender provisions and when calculating Georgia Power’s related financial obligations. Based on the current project budget and Georgia Power’s interpretation of the Global Amendments, our project budget would be $8.6 billion, an increase of approximately $475 million, and we would retain our 30% interest in the additional units. Pursuant to the Joint Ownership Agreements, as amended by the Global Amendments, the holders of at least 90% of the ownership interests in Vogtle Units No. 3 and No. 4 must vote to continue construction, or can vote to suspend construction, if certain adverse events occur, including: (i) the bankruptcy of Toshiba Corporation; (ii) termination or rejection in bankruptcy of certain agreements, including the Services Agreement, the Bechtel Agreement or the agency agreement with Southern Nuclear; (iii) Georgia Power publicly announces its intention not to submit for rate recovery any portion of its investment in Vogtle Units No. 3 and No. 4 (or associated financing costs) or the Georgia Public Service Commission determines that any of Georgia Power's costs relating to the construction of Vogtle Units No. 3 and No. 4 will not be recovered in retail rates, excluding any additional amounts paid by Georgia Power on behalf of the other Co-owners pursuant to the Global Amendment provisions described above and the first 6% of costs during any six-month VCM reporting period that are disallowed by the Georgia Public Service Commission for recovery, or for which Georgia Power elects not to seek cost recovery, through retail rates or (iv) an incremental extension of one year or more from the seventeenth VCM report estimated in-service dates of November 2021 and November 2022 for Units No. 3 and No. 4, respectively (each, a Project Adverse Event). The schedule extensions, announced in February 2022, which reflected a cumulative delay of over a year for each unit from the schedules approved in the seventeenth VCM report, triggered the requirement for the holders of at least 90% of the ownership interests in Vogtle Units No. 3 and No. 4 to vote to continue construction, and the Co-owners unanimously voted to continue construction. The Global Amendments provide that Georgia Power may cancel the project at any time at its sole discretion. In the event that Georgia Power determines to cancel the project or fewer than 90% of the Co-owners vote to continue construction upon the occurrence of a subsequent project adverse event, we and the other Co-owners would assess our options for the Vogtle project. If the investment were to be written off, we would seek regulatory accounting treatment to amortize the investment over a long-term period, which requires the approval of our board of directors, and we would submit the regulatory accounting treatment details to the Rural Utilities Service for its approval. Further, if Georgia Power or the Co-owners decided to cancel the project, the Department of Energy would have the discretion to require that we repay all amounts outstanding under our loan guarantee agreement with the Department of Energy over a five-year period as discussed in Note L of Notes to Unaudited Consolidated Financial Statements. The ultimate outcome of these matters cannot be determined at this time. See “Item 1A – RISK FACTORS” in our 2021 Form 10-K for a discussion of certain risks associated with the licensing, construction, financing and operation of nuclear generating units |