BHP | Financial results for the half year ended 31 December 2023
9 | Includes some but not all former OZL reflecting progressive migration of employee data onto BHP systems. Updated data will be provided in the full year results for FY24. |
10 | Indigenous employee representation at Minerals Australia operations. |
11 | Indigenous employee representation in Australia, including Minerals Australia operations and some but not all former OZL (operational and non-operational roles) reflecting progressive migration of employee data onto BHP systems. Updated data will be provided in the full year results for FY24. |
12 | Indigenous employee representation at Minerals Americas operations in Chile. |
13 | Indigenous employee representation at the Jansen Potash project and operations in Canada. |
14 | Area under our stewardship that has a formal management plan including conservation, restoration or regenerative practices. 82,132 hectares is the area as at 30 June 2023. This metric (which was previously reported as a percentage of the areas of land and water that we stewarded at 30 June 2023) is measured on an annual basis and an update, including restatement of the FY23 percentage to reflect a correction to underlying data, will be provided in the full year results for FY24. |
15 | Excluding greenfield exploration licences (or equivalent tenements), which are outside the area of influence of our existing mine operations. 30% will be calculated based on the areas of land and water that we steward at the end of FY30. |
The Financial Report for the half year ended 31 December 2023 has been prepared on the basis of accounting policies and methods of computation consistent with those applied in the 30 June 2023 financial statements contained within the Annual Report of the Group. This news release including the Financial Report is unaudited. Variance analysis relates to the relative financial and/or production performance of BHP and/or its operations during the December 2023 half year compared with the December 2022 half year, unless otherwise noted. Medium term refers to a five-year horizon, unless otherwise noted. Numbers presented may not add up precisely to the totals provided due to rounding.
The following abbreviations may have been used throughout this report: billion tonnes (Bt); cost and freight (CFR); cost, insurance and freight (CIF); carbon dioxide equivalent (CO2-e); dry metric tonne unit (dmtu); free on board (FOB); giga litres (GL); greenhouse gas (GHG); grams per tonne (g/t); high-potential injury (HPI); kilograms per tonne (kg/t); kilometre (km); million ounces per annum (Mozpa); million pounds (Mlb); million tonnes (Mt); million tonnes per annum (Mtpa); ounces (oz); OZ Minerals Ltd (OZL); pounds (lb); thousand ounces (koz); thousand ounces per annum (kozpa); thousand tonnes (kt); thousand tonnes per annum (ktpa); thousand tonnes per day (ktpd); tonnes (t); total recordable injury frequency (TRIF); and wet metric tonnes (wmt).
The following footnotes apply to this Results Announcement:
i | Based on a ‘point in time’ snapshot of employees as at 31 December 2023, including employees on extended absence, as used in internal management reporting for the purposes of monitoring progress against our goals. We define gender balance as a minimum 40% women and 40% men in line with the definitions used by entities such as the International Labour Organization. This includes some but not all former OZL reflecting progressive migration of employee data onto BHP systems. Updated data will be provided in the full year results for FY24. ‘People leaders’ are defined as employees with one or more direct reports. |
ii | We use various non-IFRS financial information to reflect our underlying performance. For further information on the reconciliations of certain non-IFRS financial information measures to our statutory measures, reasons for usefulness and calculation methodology, please refer to non-IFRS financial information. |
iii | Calculated on a copper equivalent production weighted average basis. |
iv | Data sourced from the most recent published financial statements of the ASX50 companies and excludes companies that recorded an accounting loss. |
v | Maintenance capital includes non-discretionary spend for the following purposes: deferred development and production stripping; risk reduction; compliance and asset integrity. |
vi | Subject to movements in exchange rates; +/- 50% in any given year. |
vii | Average for FY26-FY28. |
viii | The information in this section is based on BHP data, analysis and desk top research on public data sources. |
ix | There may be differences in the manner that third parties calculate or report unit costs data compared to BHP, which means that third-party data may not be comparable to our data. WAIO C1 unit costs exclude third party royalties, net inventory movements, depletion of production stripping, exploration expenses, marketing purchases, demurrage, exchange rate gains/losses, and other income. |
x | Resettlement cases completed includes completed construction (families either moved in or handover to families in progress) or cash payment made. Overall figures calculated considering total of 727 cases, which is the total of known cases as at 31 December 2023. |
xi | Relates to refined nickel metal only. Excludes intermediate products and nickel sulphate. |
xii | Expected capital intensity for Jansen Stage 2, US$/product tonne, Real 1 July 2023 |
Forward-looking statements
This release contains forward-looking statements, which involve risks and uncertainties. Forward-looking statements include all statements other than statements of historical or present facts, including: statements regarding: trends in commodity prices and currency exchange rates; demand for commodities; global market conditions, guidance; reserves and resources and production forecasts; expectations, plans, strategies and objectives of management; our expectations, commitments, targets, goals and objectives with respect to social value or sustainability; climate scenarios; approval of certain projects and consummation of certain transactions; closure, divestment, acquisition or integration of certain assets, operations or facilities (including associated costs or benefits); anticipated production or construction commencement dates; capital expenditure or costs and scheduling; operating costs, and supply of materials and skilled employees; anticipated productive lives of projects, mines and facilities; the availability, implementation and adoption of new technologies; provisions and contingent liabilities; and tax, legal and other regulatory developments.
Forward-looking statements may be identified by the use of terminology, including, but not limited to, ‘intend’, ‘aim’, ‘ambition’, ‘aspiration’, ‘goal’, ‘target’, ‘prospect’, ‘project’, ‘see’, ‘anticipate’, ‘estimate’, ‘plan’, ‘objective’, ‘believe’, ‘expect’, ‘commit’, ‘may’, ‘should’, ‘need’, ‘must’, ‘will’, ‘would’, ‘continue’, ‘forecast’, ‘guidance’, ‘outlook’, ‘trend’ or similar words. These statements discuss future expectations or performance, or provide other forward-looking information.
Forward-looking statements are based on management’s expectations and reflect judgements, assumptions, estimates and other information available, as at the date made. BHP cautions against reliance on any forward-looking statements. These statements do not represent guarantees or predictions of future financial or operational performance and involve known and unknown risks, uncertainties and other factors, many of which are beyond our control and which may cause actual results to differ materially from those expressed in the statements contained in this release.
For example, our future revenues from our assets, projects or mines described in this release will be based, in part, on the market price of the commodities produced, which may vary significantly from current levels. These variations, if materially adverse, may affect the timing or the feasibility of the development of a particular project, the expansion of certain facilities or mines, or the continuation of existing assets.
In addition, there are limitations with respect to scenario analysis, including any climate-related scenario analysis, and it is difficult to predict which, if any, of the scenarios might eventuate. Scenario analysis is not an indication of probable outcomes and relies on assumptions that may or may not prove to be correct or eventuate.
Other factors that may affect the actual construction or production commencement dates, revenues, costs or production output and anticipated lives of assets, mines or facilities include our ability to profitably produce and deliver the products extracted to applicable markets; the impact of economic and geopolitical factors, including foreign currency exchange rates on the market prices of the commodities we produce and competition in the markets in which we operate; activities of government authorities in the countries where we sell our products and in the countries where we are exploring or developing projects, facilities or mines, including increases in taxes and royalties or implementation of trade or export restrictions; changes in environmental and other regulations, political or geopolitical uncertainty; labour unrest; weather, climate variability or other manifestations of climate change; and other factors
25