Engineering, Procurement and Construction Contract
Between
QUAKER CHEMICAL CORPORATION
- and -
FMC TECHNOLOGIES, INC.
Effective Date: May 14, 2008
EPC Contract
TABLE OF CONTENTS
| | |
Introduction: | | 1 |
| |
ARTICLE 1 - Definitions and Appendices | | 1 |
| |
ARTICLE 2 - Interpretation and Order of Precedence | | 8 |
| |
ARTICLE 3 - Scope of Work | | 9 |
| |
ARTICLE 4 - General Requirements of the Work | | 9 |
| |
ARTICLE 5 - Engineering Services | | 12 |
| |
ARTICLE 6 - Owner’s Specified Materials | | 13 |
| |
ARTICLE 7 - Procurement Services | | 14 |
| |
ARTICLE 8 - Construction Work | | 14 |
| |
ARTICLE 9 - Commissioning | | 14 |
| |
ARTICLE 10 - Contractor’s Obligations and Representations | | 14 |
| |
ARTICLE 11 - Contract Time | | 16 |
| |
ARTICLE 12 - Payment | | 16 |
| |
ARTICLE 13 -Changes | | 16 |
| |
ARTICLE 14 - Personnel | | 18 |
| |
ARTICLE 15 - Key Personnel | | 18 |
| |
ARTICLE 16 - Subcontracts and Assignment | | 19 |
| |
ARTICLE 17 - Inspection and Testing | | 20 |
| |
ARTICLE 18 - Performance Tests | | 22 |
| |
ARTICLE 19 - Functional Completion | | 23 |
| |
ARTICLE 20 - Final Completion | | 25 |
| |
ARTICLE 21 - Liquidated Damages | | 26 |
| |
ARTICLE 22 - Incentive Fee | | 26 |
| |
ARTICLE 23 - Warranty | | 26 |
| |
ARTICLE 24 - Compliance with Law | | 27 |
| |
ARTICLE 25 - Safety and Loss Management | | 27 |
| |
ARTICLE 26 - Work Area and Clean Up | | 28 |
| |
ARTICLE 27 - Title and Responsibility | | 28 |
| | |
ARTICLE 28 - Patents and Licenses | | 29 |
| |
ARTICLE 29 - Confidential Information and Publicity | | 30 |
| |
ARTICLE 30 - Proprietary Information | | 31 |
| |
ARTICLE 31 - Force Majeure | | 31 |
| |
ARTICLE 32 – Delays | | 32 |
| |
ARTICLE 33 - Delays not Caused by the Contractor | | 32 |
| |
ARTICLE 34 – Suspension | | 33 |
| |
ARTICLE 35 - Termination for Convenience | | 34 |
| |
ARTICLE 36 - Termination for Cause | | 35 |
| |
ARTICLE 37 – Taxes | | 37 |
| |
ARTICLE 38 - Intentionally Omitted | | 37 |
| |
ARTICLE 39 – Liens | | 37 |
| |
ARTICLE 40 – Survival | | 38 |
| |
ARTICLE 41 - Liability and Indemnity for Third Party Claims | | 38 |
| |
ARTICLE 42 - Liability and Indemnity | | 39 |
| |
ARTICLE 43 - Insurance Provided by Contractor | | 40 |
| |
ARTICLE 44 - Insurance Provided by Owner | | 42 |
| |
ARTICLE 45 - Independent Contractor | | 43 |
| |
ARTICLE 46 - Conflict of Interest | | 43 |
| |
ARTICLE 47 - Audit Access | | 43 |
| |
ARTICLE 48 - Representatives and Notices | | 44 |
| |
ARTICLE 49 - General | | 45 |
ADDENDA
|
Appendix A – Scope of Work |
Appendix B – Compensation |
Appendix C – Work Site |
Appendix D – Warranty Items Procedure |
Appendix E – Liquidated Damages |
Appendix F – Incentive Fee |
Appendix G – Forms |
Appendix H – Dispute Resolution Procedure |
Appendix 1 – Key personnel
Engineering, Procurement and Construction Contract
ThisContractis made effective this 14th day of May, 2008
Between
QUAKER CHEMICAL CORPORATION
- and -
FMC TECHNOLOGIES, INC.
Introduction:
A. TheContractorhas agreed to perform theWorkfor theOwneras set out in thisContract,on the terms and conditions set forth in thisContract;
IN CONSIDERATION of the mutual covenants and conditions contained herein, the parties agree as follows:
ARTICLE 1 - Definitions and Appendices
1.1 | The following terms, wherever capitalized and italicized in theContract,or in any document produced pursuant to the terms of theContract,shall have the following meanings: |
| (a) | AppendixorAppendices,as the case may be, means one or more of the schedules attached to and incorporated in thisContractas set forth in Section 1.2; |
| (b) | As-Built Drawingsmeans the controlled and complete set of documents upon which theContractorrecords each and every instance of differences between theWorkas executed and theWorkas designed and depicted in the documents issued by theContractorforConstruction Work; |
| (c) | Changemeans any change in, addition to, or deletion from theScope of Work, Owner’s Specified Materials,theMilestones,or theContract Timethat is effected by aChange Directive, Change OrderorChange Quotationthat has been approved in writing by Owner; |
| (d) | Change Directivemeans a written instruction from theOwnerdirecting aChange; |
EPC Contract
Page 1 of 47
| (e) | Change Ordermeans a written order signed by both theContractorand theOwnerauthorizing aChange; |
| (f) | Change Quotationmeans a written quotation from theContractorfor an adjustment in theContract Time, Milestonesor theCompensation,or both; |
| (g) | Commencement Datemeans the date that theWorkis to commence, which is May 14, 2008; |
| (h) | Commissioning after Functional Completionmeans those commissioning duties of theOwnerand of theContractorthat shall take place afterFunctional Completionand which are described in theScope of Workand allocated to either theOwneror theContractor; |
| (i) | Commissioning before Functional Completionmeans those commissioning duties of theOwnerand of theContractorthat shall take place beforeFunctional Completionand which are described in theScope of Workand allocated to either theOwneror theContractor; |
| (j) | Compensationmeans the compensation which theOwnershall pay for performance of theWorkin accordance with Appendix B – Compensation; |
| (k) | Confidential Informationmeans all information relating to theWorkand any process or technology relating thereto, and information relating to the nature of theContractor’sand theOwner’sbusiness and affairs, which either party directly or indirectly receives or acquires (or previously received or acquired) from the other party, or the other party’s representative, either in writing or verbally, including information in theContract,or through observation of theOwner’s Site,theWork Site,theWorkor work performed byOther Contractors,except information falling into any one or more of the following categories: |
| (i) | information which the disclosing party can show was in its possession on a non-confidential basis before receipt or acquisition of the information from the other party; |
| (ii) | information which is lawfully in the public domain at the time of the disclosing party’s receipt or acquisition of the information from the other party, other than from theScope of Workor through the process of proposal calls or performing theWork; |
| (iii) | information which, after the disclosing party’s receipt or acquisition of the information from the other party, becomes part of the public domain through no act of the disclosing party or of any third party under an obligation of confidence with respect to such information, but only after such information becomes part of the public domain; or |
EPC Contract
Page 2 of 47
| (iv) | information which, after receipt or acquisition of the information from the other party, is lawfully obtained by the disclosing party from a third party, but only after such information is so received or acquired, and provided such third party is under no obligation of confidence with respect to such information. |
| (l) | Construction Workmeans delivery, fabrication, assembly, construction, testing, commissioning and correction, including professional and technical personnel, labor, supervision, administration, materials, transportation, supplies, tools, equipment, and such other work and materials necessary to be performed or supplied to meet the requirements of theContract,including any work which is not expressly described in theContractbut which is nevertheless necessary for the proper execution of theWork,but does not includeEngineering ServicesorProcurement Services; |
| (m) | Contemplated Change Noticemeans a written notice from theOwneradvising theContractorthat theOwneris contemplating aChange; |
| (i) | this Engineering, Procurement and Construction Contract; |
| (iv) | other documents which come into existence and are incorporated into theContractpursuant to the terms of thisContract; |
| (o) | Contract Timemeans the period of time from theCommencement Dateto theScheduled Functional Completion Date; |
| (p) | Contractormeans FMC Technologies, Inc.; |
| (q) | Contractor’s Representativemeans that person identified as such in Section 48.2, or an approved replacement; |
| (r) | Deficiencymeans any portion of theWorkthat has not been performed in accordance with theScope of Work,theContractor theLaw; |
| (s) | Engineering Servicesmeans those services described in theScope of Workand provided by theContractorfor the design, planning and engineering of theProject,but does not includeConstruction WorkorProcurement Services; |
| (t) | Event of Force Majeuremeans any occurrence, other than the financial capability of a party or an event constituting a delay under Article 32 - Delays or Article 33 - Delays not Caused by the Contractor, which prevents or delays a party |
EPC Contract
Page 3 of 47
| from performing its obligations under theContract(except an obligation to pay any amount) within the time required for the performance of such obligation and which is beyond the control and without the fault or negligence of the party relying on such occurrence, and which by the exercise of reasonable diligence that party could not, at the time theContractwas executed, have reasonably contemplated happening and which at the time of such occurrence, is beyond the reasonable control of the party required by theContractto perform such obligation and such party is unable to reasonably prevent or provide against such occurrence. In no event shall weather conditions be deemed to be anEvent of Force Majeureunless such weather conditions are abnormal and exceed the normally expected inclement weather in the area of theProjectbased on a 15-year moving average of climate data maintained by the National Atmospheric and Oceanic Administration; |
| (u) | Execution Planmeans the schedule developed by theContractorand approved by the Owner for theWorkin accordance with Section 4.2 and which shall be updated from time to time as may be required by theOwnerand which shall include, but not be limited to: |
| (i) | the sequences and methods for the performance of theWork;and |
| (ii) | a detailed schedule with dates for the completion ofMilestones; |
| (v) | Facilitiesmeans the physical works engineered, procured and constructed as a result of theWorkbeing performed; |
| (w) | Final Completion Noticemeans that notice in the form contained in Appendix G – Forms issued by theOwnerto theContractorpursuant to Section 20.2 certifying completion and acceptance of theWorkunder theContract; |
| (x) | Functional Completionmeans that date when theWork: |
| (i) | has passed the requiredPerformance Teststhat are stipulated in theScope of Workto be performed beforeFunctional Completion;and |
| (ii) | is certified by theOwner’s Representativepursuant to Article 19 as being complete or ready to be put into service, or being used for the purpose intended and aFunctional Completion Certificateis issued; and |
| (iii) | only non-critical punch list items remain to be completed by theContractor.Non-critical punch list items are items that do not measurably affect safety, protection of the environment, efficiency or quality. |
| (y) | Functional Completion Certificatemeans that notice, in the form attached hereto as Appendix G – Forms, issued by theOwnerto theContractorpursuant to Article 19, certifying achievement ofFunctional Completion of theWork and identifying the date that theOwner takes over theWork. |
EPC Contract
Page 4 of 47
| (z) | Goodsmeans any goods, supplies, materials or equipment required as part of theWork,or to perform theWork,and which are supplied or fabricated by theContractor,but do not includeProcured Goods; |
| (aa) | Hazardous Materialmeans any substances which are hazardous to persons, animals, property or the environment and includes hazardous substances, hazardous waste, ozone depleting substances and dangerous goods, all as identified or defined under applicable law. |
| (bb) | Incentive Feemeans that fee that shall be paid by theOwnerto theContractor,if applicable, and which is set out in Appendix F – Incentive Fee; |
| (cc) | Inspection and Test Planmeans the plan for inspection and testing, which shall be prepared by either theOwneror theContractoras specified in theScope of Work; |
| (dd) | Key Personnelmeans theContractor’skey personnel for theWorkidentified in Appendix I – Key Personnel , or if not determined before the execution of thisContract,identified in an organizational chart in accordance with Article 15 - Key Personnel and approved by theOwner; |
| (ee) | Lawmeans the common law, the law of equity and all federal or state statutes or municipal by-laws and all regulations, orders, directives, permits and licenses thereunder, which apply to or otherwise affect theWork,theOwneror theContractorwith respect to theWork,or the property of theOwneror theContractor,real or personal, including, but not limited to, all environmental, occupational, health and safety laws; |
| (ee*) | Leased Equipmentmeans those items of equipment identified in Schedule 1 to Appendix B and which will leased by Owner. Owner will perform certain inspection and acceptance activities for the lessor of the equipment, but only in a role as the representative of the lessor. |
| (ff) | Liquidated Damagesmeans those damages agreed by the parties to be a genuine pre-estimate of damages in the event thePerformance Guaranteesare not met or theWorkis not completed in theContract Timeand which are set out in Appendix E– Liquidated Damages; |
| (gg) | MilestoneorMilestonesmeans, as the case may be, one or more milestones that theContractormust meet as set forth in theScope of Work; |
| (hh) | Other Contractorsmeans the contractors, consultants, or engineers retained by theOwner,to perform any work or services at, or related to, theOwner’s Site, other than theContractor; |
EPC Contract
Page 5 of 47
| (ii) | Ownermeans the owner of the Project, Quaker Chemical Corporation; |
| (jj) | Owner’s Representativemeans that person identified as such in Section 48.1 which may include a consultant hired by theOwner,if so designated, or that person’s designated replacement; |
| (kk) | Scope of Workmeans the description of the scope, standards, design criteria,Performance Guarantees, Milestonesand the schedule of work set out in Appendix A–Scope of Work, as amended by anyChanges; |
| (ll) | Owner’s Sitemeans theOwner’sland upon which theWork Siteis located and which may have on it other projects byOther Contractorsor existing facilities, activities or operations; |
| (mm) | Owner’s Specified Materialsmeans those materials, goods, products, processes, and equipment specified in Section 3 of theScope of Workto be used in, or to be incorporated into, theWorkby theContractor; |
| (nn) | Performance Guaranteesmeans the performance guarantees set out in theScope of Work; |
| (oo) | Performance Testsmean the performance tests set out in theScope of Workfor the purpose of determining achievement of thePerformance Guaranteesfor theWork,and such other tests as may be agreed between theOwnerandContractorin order to compare actual performance of theWorkwith thePerformance Guarantees; |
| (pp) | Intentionally omitted. |
| (qq) | Procured Goodsmeans those goods, supplies, materials or equipment obtained by theContractorfor incorporation in, or to perform, theConstruction Work,and procured by theContractoras part of itsProcurement Services; |
| (rr) | Procurement Servicesmeans the procurement ofProcured Goodsperformed by theContractor,for its own account, as stipulated in theScope of Work; |
| (ss) | Projectmeans the Middletown Plant Expansion Turnkey Project; |
| (tt) | Proprietary Informationmeans all inventions, discoveries, improvements and technical information not in the public domain, which theContractor, Subcontractors,or their respective employees or agents who are performing theWork,may conceive of, reduce to practice or develop during theContract Timeor within 12 months thereafter, as a resultof Confidential Information; |
| (uu) | Recordsmeans the books, statements, records and accounts pertaining to theContractand the performance of theWork,whether in paper or electronic form; |
EPC Contract
Page 6 of 47
| (vv) | Safety Planmeans the plan, as prepared by theContractorand approved by theOwner, to be enforced by theContractorwith regard to allWorkperformed at theWork Site.; |
| (ww) | Scheduled Functional Completion Datemeans the date on which theWorkis scheduled to achieveFunctional Completion, which is 15 months after theCommencement Date; |
| (xx) | Subcontractorsmeans any subcontractors, consultants, suppliers or vendors hired by theContractorto perform any portion of theWorkor supply anyGoods; |
| (yy) | Suspended Workmeans anyWork, or portion thereof, which theOwnerhas suspended pursuant to Article 34 - Suspension; |
| (zz) | Systemmeans any component system of theWork, or any part thereof as the context requires; |
| (aaa) | Warranty Itemmeans anyDeficiencythat is identified after theFunctional Completion Certificateis issued or is incorporated into theFunctional Completion Certificateto be remedied afterFunctional Completion; |
| (bbb) | Warranty Periodcommences on the date ofFunctional Completionof theWork, and continues for 12 months from the date ofFunctional Completionas stated in theFunctional Completion Certificate; |
| (ccc) | Workmeans allEngineering Services, project management,Procurement Services,Goods,Procured Goods,Construction Workand those duties allocated to theContractorin theCommissioning before Functional Completion and Commissioning after Functional Completion, as may be necessary to fulfill theScope of Workand includes anything that is ancillary or necessary by implication to fulfill theScope of Work; |
| (ddd) | Work Daymeans any day, except for a Saturday, Sunday, a federal holiday or a holiday which is regularly observed in the construction industry in Middletown, Ohio, or defined as a holiday in a collective agreement pertaining to theWork Site; and |
| (eee) | Work Sitemeans those lands where theProjectis located and which are generally depicted on Appendix C. |
1.2 | The following schedules attached hereto shall form part of and are incorporated in thisContract: |
| | | | |
(a) | | Appendix A | | – Scope of Work |
(b) | | Appendix B | | – Compensation |
(c) | | Appendix C | | – Work Site |
(d) | | Appendix D | | – Warranty Items Procedure |
EPC Contract
Page 7 of 47
| | | | |
(e) | | Appendix E | | – Liquidated Damages |
(f) | | Appendix F | | – Incentive Fee |
(g) | | Appendix G | | – Forms |
| | | | – Key Employee Confidentiality, Proprietary Information and Consent Agreement |
| | | | – Change Order |
| | | | – Functional Completion Notice |
| | | | – Final Completion Notice |
| | | | – Release and Certificate of Final Payment |
| | | | – Statutory Declaration |
(h) | | Appendix H | | – Dispute Resolution Procedure |
(i) | | Appendix I | | – Key Personnel |
ARTICLE 2 - Interpretation and Order of Precedence
2.1 | Unless the context otherwise requires, words importing the singular shall include the plural and vice-versa and words importing gender shall include the masculine, feminine and neuter genders. |
2.2 | The headings and sub-headings of theContractare used for convenience and ease of reference only and in no way define, limit, describe or interpret the scope or intent of theContract. |
2.3 | If there is a conflict in theContract, the order of precedence of documents, from highest to lowest, shall be: |
| (a) | this Engineering, Procurement and Construction Agreement, including theAppendices; |
2.4 | The following shall, in all instances, apply: |
| (a) | for documents revised by either party and approved by theOwner, the latest revision shall govern; |
| (b) | figured dimensions on drawings shall govern, even though they may differ from scaled dimensions; |
| (c) | drawings of larger scale shall govern over those of smaller scale of the same date; and |
| (d) | specifications shall govern over drawings regardless of time. |
EPC Contract
Page 8 of 47
2.5 | Wherever thisContractrequires an action to be performed or an obligation to be undertaken, such action or obligation shall be performed in a reasonable manner by the party taking the action or fulfilling its obligation. |
ARTICLE 3 - Scope of Work
3.1 | TheScope of Workdescribes the scope of the Work. |
3.2 | TheScope of Workshall specify the requirements of theSafety Planand identify the party, or parties, responsible for the development and implementation of theSafety Plan. |
ARTICLE 4 - General Requirements of the Work
4.1 | The scope of theWorkincludes correction of defects and deficiencies by theContractorin accordance with theContract. |
4.2 | Set forth in theScope of Workis anExecution Planfor the performance of theWorkrequired under theContract. TheContractorshall control the progress of theWorkto achieve compliance with theExecution Plan. |
4.3 | In the execution of theWorktheContractorshall comply with, and the completedWorkshall comply with, theLaw, including, without limitation, applicable building codes, technical standards, building construction and environmental regulations and the standards specified in theContract. |
4.4 | References in theContractto applicable codes, standards or regulations shall be understood to be references to the edition applicable on the date of theContract, unless stated otherwise. If substantially changed or new applicable codes, standards or regulations come into force after the date of theContract, theContractorshall submit aChange Quotationfor compliance to those new codes, standards or regulations to theOwner’s Representative. AnyChangein theWork, theContract Timeor theCompensationas a result shall be dealt with under Article 13 - Changes. |
4.5 | TheContractoraccepts theOwner’s Site, theWork Siteand the obligation to perform theWorkin the condition existing at the effective date of thisContractand acknowledges that it has investigated and satisfied itself as to: |
| (a) | the nature of theWork; |
| (b) | the location of and all conditions relating to theOwner’s Siteand theWork Site, including, but not limited to, accessibility, general character, surface conditions, utilities, roads, uncertainties of seasonal weather and all other physical, topographical and geographical conditions but excluding subsurface or other physical conditions not disclosed by theOwneror specified in the Scope ofWork; |
EPC Contract
Page 9 of 47
| (c) | environmental risks resulting from theWork, Lawand restrictions applicable to theContractoror theWorkthat may affect theWork;and |
| (d) | the magnitude of theWork. |
4.6 | TheContractoraccepts the obligation to perform theWorkin accordance with the terms of thisContractfor theCompensationand within theContract Time,and acknowledges that it has investigated and accepts: |
| (a) | the character, quality, quantity and availability of equipment and materials required to execute and complete theWorkfor theCompensationand within theContract Time;and |
| (b) | all conditions affecting labor, including, without limitation, availability, productivity and administrative practices, including those relating to safety, prevailing at or applicable to theWork. |
4.7 | To the extent diligent and reasonable inquiry would lead to discovery, failure by theContractorto discover matters which affect, or could affect, theWorkshall not relieve theContractorfrom its obligations under theContractor otherwise affect theContract Timeor theCompensation. |
4.8 | TheOwnerreserves the right to award separate contracts toOther Contractorsfor work to be performed at theWork Siteand to perform work with its own forces at theWork Site.In such event, theContractorshall co-ordinate and schedule theWorkwith the work of theOther Contractorsand theOwner’sown forces, and theContractorshall share access to and use of theWork Siteto accommodate the work ofOther Contractors.If work performed byOther ContractorsorOwner’sown forces as directed by theOwnermaterially interferes with theWorkperformed by theContractor,theContractormay issue aChange Quotationin accordance with Section 13.7. |
4.9 | TheContractorshall co-operate fully with theOwner, Other Contractorsand all other parties with whom theContractororOwnermay be involved during the performance of theWork.TheContractorshall supervise its employees andSubcontractorsand inspect their work to ensure that theWorkconforms in each and every respect to theScope of Workand in accordance with Section 10.1. |
4.10 | Approval of theEngineering Services,acceptance of any part of theGoods, Procured Goodsor theConstruction Workby theOwner,or payment to theContractor,or any one or more of them, shall not relieve theContractorfrom its responsibilities under theContract,whether pursuant to any of the warranties or guarantees herein, or otherwise. |
4.11 | TheContractorshall provide theOwnerwith written reports detailing the status of theWorkand all issues relating to theWork,promptly upon the reasonable request of theOwner,and shall attend meetings as required by theContract,or as otherwise requested by theOwner’s Representative. |
EPC Contract
Page 10 of 47
4.12 | TheContractorshall have those responsibilities for managing theWorkas stipulated in theScope of Workor elsewhere in thisContract,including, but not limited to: |
| (a) | cost monitoring, scheduling and reporting to theOwner; |
| (b) | scheduling theWorkand monitoring and reporting on the progress of theWorkrelative to theMilestonesto theOwner; |
| (c) | coordination, scheduling and supervisionof Subcontractors; |
| (d) | coordination and management of transportation and related services for theWork; |
| (e) | management of theWorkto ensure theWorkis performed in an efficient and coordinated manner; and |
| (f) | preparation of reports and attendance at meetings with theOwner. |
4.13 | TheContractorshall ensure that no activities or actions are undertaken in the performance of theWork,or otherwise by theContractor,which would adversely affect, restrict or limit in any way the continued operation of theOwner’sfacilities which are in operation, unless required to perform theWork,done in accordance with theExecution Plan,authorized in writing by theOwner’s Representative. |
4.14 | In the performance of theWork,theContractorshall give due consideration to the interest and property of others wherever involved, and shall carry out and perform theWorkin a reasonable manner which shall cause the minimum of inconvenience, injury, and damage to others. |
4.15 | TheOwnershall provide and theContractorshall abide by all documents provided by theOwnerrelating to theOwner’s Site,including, but not limited to, any special restrictions and conditions contained in any easement, regulatory board order, crossing agreement, or other permit relating to theWork Site. |
4.16 | Each of the parties shall promptly and fully inform each other of any errors, omissions or inconsistencies in theContract,defects or deficiencies in theWorkand of any inconsistencies between theContractand theLaw,of which they become aware. TheContractorshall exercise reasonable care and diligence to prevent any actions or conditions which could result in any such inconsistencies, defect or deficiencies. . If theContractordiscovers any inconsistencies in theContract,or between theContractand theLaw,or discovers any defects or deficiencies in theWork,and proceeds without resolution with theOwner,theContractorshall proceed at theContractor’sown risk and expense and waives all rights to claim against theOwnerfor the same. |
4.17 | All documents and drawings prepared as part of theWorkshall be in English. |
EPC Contract
Page 11 of 47
ARTICLE 5 - Engineering Services
5.1 | TheContractorshall perform theEngineering Servicesand be responsible for the design and engineering necessary to execute theWork.TheEngineering Servicesshall be prepared under the supervision of theContractor’sengineers. TheContractor’sresponsibilities in this section 5.1 shall not apply to the selection of the sizes and/or quantities of the materials designated in theScope of WorkasOwner’s Specified Materialsor the conceptual design of the Project as shown on Attachment 7.1 to theScope of Work. |
5.2 | The engineers referred to in Section 5.1 shall be available to meet with theOwner’s Representativeat all reasonable times during theContract TimeandWarranty Period. |
5.3 | TheOwnershall have the right of inspection and review of the design drawings and specifications at all reasonable times. No inspection, or failure to inspect, by theOwnershall relieve theContractorof theContractor’sobligations under theContract.TheContractorshall provide to theOwnerforOwner’swritten approval design documents sufficient to establish the size, quality and character of theProject;its architectural, structural, mechanical and electrical systems; and the materials and such other elements of theProjectto the extent required by theScope of Work.Deviations, if any, from theScope of Workshall be expressly disclosed in writing by the Contractorto theOwner.Upon theOwner’swritten approval of the design documents submitted by theContractor,theContractorshall provide construction documents for review and written approval by theOwner(the“Construction Documents”).TheConstruction Documentsshall set forth in detail the requirements for construction of theProject.TheConstruction Documentsshall include plans, drawings and specifications that establish the quality levels of materials and systems required. Deviations, if any, from theScope of Workor the previously approved design documents shall be expressly disclosed in writing by theContractorto theOwner. Construction Documentsmay include drawings, specifications, and other documents and electronic data setting forth in detail the requirements for construction of theWork.Upon completion and approval byOwner,theConstruction Documentsshall be deemed to be part of theScope of Work. |
5.4 | Prior to commencement of thePerformance Tests,theContractorshall prepare, and submit to theOwner’s Representative,operation and maintenance manuals in accordance with theScope of Work.TheWorkshall not be considered to be completed for the purposes of achievingFunctional Completionuntil such operation and maintenance manuals have been submitted to theOwner’s Representative. |
| (a) | prepare, and keep up-to-date, theAs-Built Drawings; |
| (b) | record the exact locations of each of these differences, sizes and details of theConstruction Workas executed, with cross-references to relevant specifications and other requirements on theAs-Built Drawings |
EPC Contract
Page 12 of 47
| (c) | keep theAs-Built Drawings on theWork Site; |
| (d) | during the Contract Time, provide the Owner with access to the As-Built Drawings; and |
| (e) | upon completion of theWork, submit theAs-Built Drawings and copies (including paper and electronic versions) to theOwner’s Representativein accordance with the Scope of Work. |
5.6 | The preparation and delivery to Owner of As-Built Drawings shall not relieve Contractor of responsibility for any differences or deviations between the Work as constructed and the requirements of the Scope of Work, the Construction Documents and the plans and specifications that have not been accepted and approved in writing by Owner. |
ARTICLE 6 - Owner’s Specified Materials
6.1 | Where theScope of Work directs theContractorto use theOwner’s Specified Materials, theContractor shall review the Owner’s Specified Materials to determine whether such materials are acceptable to meet theEngineering Services andConstruction Work and can be made available for procurement without interfering with the achievement of theMilestones. |
6.2 | If theContractor determines that theOwner’s Specified Materials are acceptable for theWork, then theOwner’s Specified Materialsshall be used and incorporated in theWork in the same manner as those materials and pieces of equipment proposed by theContractor and theContractor shall take responsibility for theOwner’s Specified Materials and all warranty provisions that apply thereto; or |
6.3 | If theContractor determines that theOwner’s Specified Materials are not acceptable for theWork, then theContractor shall give notice to theOwner that theOwner’s Specified Materialsare not suitable for theWork, which notice will provide details of the reasons why theOwner’s Specified Materialsare not acceptable for use or incorporation into the Work. |
6.4 | Where theContractor has provided notice to theOwner that theOwner’s Specified Materialsare not acceptable for theWork, theOwner shall promptly notify theContractor of theOwner’s decision as to whether or not to include theOwner’s Specified Materials in theWork. |
6.5 | If theOwner chooses to direct theContractor to use theOwner’s Specified Materialsafter theContractor has notified theOwner that theOwner’s Specified Materials are not acceptable for theWork, then theOwner shall take full responsibility for theOwner’s Specified Materials,including any warranty claims and damages, including failure to achieveFunctional Completion, that may occur from the use or incorporation of theOwner’s Specified Materials. |
EPC Contract
Page 13 of 47
ARTICLE 7 - Procurement Services
7.1 | As specified in theScope of Work,the Contractor shall perform theProcurement Services. |
7.2 | Where specified in theScope of Work, theContractor shall provideProcurement Services using such selected vendor lists specified in theScope of Work. |
7.3 | Payment of invoices forProcured Goods shall be made by theContractor to its suppliers in accordance with the terms established between theContractor and his suppliers. Payment on account ofProcured Goods to be made by theOwner to theContractor shall be made when theProcured Goods are delivered and suitably stored at theWork Site for subsequent incorporation in theWork, in accordance with Appendix B. |
ARTICLE 8 - Construction Work
8.1 | TheContractor shall perform theConstruction Work in accordance with theConstruction Documentsand the Contract. |
8.2 | Except for those materials, services and equipment to be provided by theOwner and described in Appendix A–Scope of Work, theContractorshall supply or cause to be supplied all services, equipment and materials required for the proper execution and completion of theConstruction Work. |
8.3 | TheContractorshall take full responsibility for the adequacy, stability and safety of theWork and theWork Siteoperations under its control, of all methods of construction and of all of theConstruction Work, unless theContractor has received written instructions from theOwner’s Representative absolving theContractor of responsibility. |
ARTICLE 9 - Commissioning
9.1 | The duties of theOwner and of theContractor in relation toCommissioning before Functional Completionand Commissioning after Functional Completion, together with theMilestones to be reached for commissioning, are as set out in theScope of Work. |
ARTICLE 10 - Contractor’s Obligations and Representations
| (a) | perform theWork in a professional, efficient and workmanlike manner, using only qualified, skilful and careful workers, in strict accordance with theContract and in accordance with sound and currently accepted design, engineering, procurement, construction and commissioning practices normally employed in industrial construction similar to theWork; |
EPC Contract
Page 14 of 47
| (b) | perform theWorkin a safe and environmentally sound manner and in compliance with theLaw; |
| (c) | ensure that the title to any and allGoodsandProcured Goods shall, upon transfer of title to theOwner, be free from any and all claims, liens, charges, encumbrances or security interests of any kind whatsoever; |
| (d) | ensure equipment and materials furnished, manufactured or fabricated by theContractor, or itsSubcontractors, for incorporation into theWork, shall: |
| (i) | meet the specifications in theContract, if so specified, and if not specified then be of the quality best suited for the required operating conditions and intended use and purpose of the materials and services; and |
| (ii) | shall be fit for the purpose for which the equipment and materials have been manufactured or fabricated; |
| (e) | perform theWork to meet theScope of Work; |
| (f) | comply with theContract, including, but not limited to, all time schedules and Milestones set out in, or called for by, theContract or the Execution Plan; and |
| (g) | ensure theWorkshall be fit for its intended purpose as specified in theScope of Work and successfully completes all inspections and tests under Article 17 and allPerformance Tests under Article 18. |
| (h) | strictly comply with the requirements of Chapters 4115 and 4582 of the Ohio Revised Code relative to prevailing wages including, without limitation the provisions of Revised Code Section 4582.37.Contractor shall ensure that all laborers and mechanics employed in connection with theProject are paid at the prevailing rates of wages of laborers and mechanics for the class of work called for by theProject, which wages shall be determined in accordance with the requirements of Chapter 4115 of the Ohio Revised Code for determination of prevailing wage rates.Contractor further acknowledges and understands that construction of theProject is deemed to be construction of a public improvement within the meaning of Revised Code Section 4115.03 and that, as a result, theContractor shall and shall cause allSubcontractors working on theProject to comply with all applicable requirements of Revised Code Sections 4115.03 to 4115.16 and other Applicable Laws related thereto. Upon request from time to time by theOwner, theContractor shall promptly deliver to theOwner evidence satisfactory to theOwner, thatContractorand allSubcontractors have complied with the foregoing requirement.Contractoragrees, at the request of theOwner, that the prevailing wage coordinator required pursuant to Chapter 4115 in respect of theProject shall be such person or entity as may hereafter be designated by the Butler County Port Authority to perform the duties of wage coordinator. TheContractorspecifically represents and warrants and covenants that neither it, nor any Subcontractor has been or will be included on any list described in Revised Code Section 4115.133. |
EPC Contract
Page 15 of 47
10.2 | The Contractor represents and warrants to theOwnerthat: |
| (a) | it has the experience, resources, personnel and capability to perform theWork; |
| (b) | it is duly incorporated and validly existing under the laws of the jurisdiction(s) of its incorporation and is registered to carry on business in the State of Ohio; |
| (c) | it has all required permits, licenses and authorizations necessary to carry on its business; and |
| (d) | theContractorhas the right to use, employ and incorporate in theWorkthose things or ideas to which theContractorgives theOwnera license under Section 28.2. |
ARTICLE 11 - Contract Time
11.1 | Subject to anyChange Order, theContractor shall commence theWork on theCommencement Date and shall achieveFunctional Completion of all of theWork by theScheduled Functional Completion Date. |
11.2 | TheContractor shall, unless otherwise provided for in thisContract or altered by anyChange Order, perform theWork in accordance with theExecution Plan. |
11.3 | If a party fails to meet its obligations set out in thisContract in a timely manner, the other party may raise the failure of a timely action as provided for in Appendix H – Dispute Resolution Procedure. Nothing in this Section 11.3 shall limit Owner’s right to receive Liquidated Damages as provided in Appendix E or Owner’s rights under Article 36. |
ARTICLE 12 - Payment
12.1 | As full and complete compensation for theWork, theOwnershall pay theContractortheCompensationpursuant to the terms of Appendix B – Compensation which shall in no event exceed theCompensationpayable in accordance with theContract, as adjusted by anyChange Order. |
12.2 | TheContractorshall prepare and submit invoices for allWorkperformed in accordance with Appendix B – Compensation. |
ARTICLE 13 - Changes
13.1 | TheOwnershall have the right, at any time, to make aChange. |
EPC Contract
Page 16 of 47
13.2 | When aChangeis proposed by theOwner, then theOwnershall provide aContemplated Change Noticeto theContractordescribing the proposedChange. |
13.3 | TheContractor, upon receipt of aContemplated Change Notice, shall within five (5) Work Daysprovide theOwner’s Representativewith aChange Quotationwhich shall include a method of adjustment or an amount of adjustment to theCompensation, if any, and any adjustment in theContract Timefor the proposedChange. |
13.4 | Following receipt of aChange Quotation, theOwnershall within five (5) Work Dayseither agree to the adjustments in theContract Timeand theCompensationor to the method to be used to determine the adjustments, or give theContractornotice that theChange Quotationis not acceptable. |
13.5 | If theChange Quotationis agreed to, then theOwnershall issue aChange Orderrecording theChange, which shall be signed by theOwnerand theContractor. The value of theWorkperformed as a result of aChange Ordershall be included in invoices for payment given by theContractorin accordance with the terms of payment in Appendix B – Compensation and shall identify those portions of the invoice charged for theChange Order. |
13.6 | If theOwnerrequests theContractorto provide aChange Quotationand subsequently elects not to proceed with theChange, theContractorshall be reimbursed in accordance with Appendix B – Compensation, or as otherwise agreed between the parties, for its reasonable costs incurred including design and engineering services, and theOwnershall issue aChange Orderfor these costs. |
13.7 | If, during the performance of theWork, theContractoris of the reasonable opinion that any written instruction, interpretation, decision or direction from theOwnershould have, but has not, resulted in aContemplated Change Noticebeing issued, theContractorshall give theOwnerfive (5) Work Daysnotice with aChange Quotationrequesting an adjustment inContract Timeand theCompensationrequired. If theContractordoes not issue aChange Quotationwithin five (5) Work Daysafter the aforesaid instruction, interpretation, decision or direction is given by theOwner, then theContractorshall have no claim for any claim against theOwnerattributable to that instruction, interpretation, decision or direction. |
13.8 | If theOwnerreceives aChange Quotationfrom theContractorpursuant to Section 13.7, theOwnershall promptly consider theChange Quotationand immediately issue aChange Order, within three (3) Working Daysor advise theContractorin writing that theContractor’srequest is denied or suchChange Quotationshall be deemed denied. To the extent there is a dispute as to whether theChange Quotationis appropriate, such dispute shall be resolved in accordance with Appendix H – Dispute Resolution Procedure. |
13.9 | No modification, addition, deletion or other revision to theScope of Workshall be binding on either party unless set out in aChange Order, or determined by Appendix H – Dispute Resolution Procedure. |
EPC Contract
Page 17 of 47
13.10 | TheContractorshall include in itsChange Quotationall costs and changes inContract Timereasonably expected to result from aChangeincluding any impact costs or costs of acceleration. |
13.11 | If theContractorencounters actual subsurface or other concealed physical conditions at theWork Sitewhich are materially different from any representations or written disclosures (including e-mails) of existing conditions made byOwneror described in theScope of Work, then theContractorshall provide notice to theOwnerwithin 5Work Daysof encountering the conditions and shall allow theOwnerthe opportunity for inspection before the conditions are further disturbed. If theContractorfails to provide such notice to theOwnerwithin the specified time then theContractorshall have no claim for any additional costs or delays attributable to such subsurface or concealed physical conditions. |
13.12 | TheOwnershall promptly investigate the conditions described by theContractorpursuant to Section 13.11 and if the actual conditions encountered by theContractorat theWork Sitediffer materially from the conditions represented or disclosed in writing (including e-mails) byOwneror described in theScope of Workso as to increase the cost to theContractoror impact theContract Time, then theOwnershall issue aChange Orderto cover the increased cost andContract Time. |
ARTICLE 14 - Personnel
14.1 | All communications between theOwnerand theContractorand all documents of whatever kind submitted to theOwnerby theContractorand itsSubcontractorsshall be in the English language. All of theContractor’sand theSubcontractors’personnel that deal with or communicate with theOwnershall be fluent in the English language. All training and supervision of theOwner’soperating personnel shall be in the English language. |
14.2 | TheContractorshall employ, or cause to be employed, only supervisory personnel who are appropriately qualified, trained and experienced in safety, efficiency and quality of work supervision. |
14.3 | At theOwner’srequest, theContractorshall reassign, replace or remove personnel who, in theOwner’sopinion, acting in good faith, negatively affect the efficiency, safety orScheduled Functional Completion Dateof theWork. |
ARTICLE 15 - Key Personnel
15.1 | If not agreed to before the execution of theContract, theContractorshall submit a proposed organizational chart for theOwner’sapproval, as part of theExecution Plan. The organizational chart shall show theKey Personneland other supervisory and staff personnel who shall be executing theWork, together with their respective job titles and contact information. |
EPC Contract
Page 18 of 47
15.2 | TheOwnershall identify any of theKey Personnelto which theOwnerobjects within 14Work Daysand if theOwnerdoes not provide theContractorwith its objections to theKey Personnel, theOwnershall be deemed to have accepted theKey Personnel. |
15.3 | If theOwnerobjects to any of theKey Personnelin accordance with Section 15.2, then theContractorwill promptly prepare a new organizational chart identifying theKey Personnelfor theOwner’sapproval. This process shall be repeated until theOwnerapproves theKey Personnel. |
15.4 | Once theOwnerhas approved the organizational chart identifying theKey Personnel, theContractorshall within five (5) Work Daysarrange for each of theKey Personnelto complete and execute an agreement in the form of the Key Employee Confidentiality Proprietary Information and Consent Agreement, attached as part of Appendix G–Forms. |
15.5 | Subject to Section 15.6, theContractorshall not, without theOwner’sconsent, make any changes to theKey Personnelor an organizational chart that has been approved by theOwner. |
15.6 | If anyKey Personnelleave theContractor’sworkforce, theContractorshall forthwith replace suchKey Personnelwith personnel possessing those qualifications necessary for the proper performance of the functions to which assigned. |
ARTICLE 16 - Subcontracts and Assignment
16.1 | TheContractorhas identified in theScope of Workand in Appendix I its intention to subcontract the performance of specified portions of theWorkand/or the supply of specified equipment and materials and the names of the intendedSubcontractorsor suppliers . TheOwnermay for reasonable cause, and acting in good faith, object to the use of a proposedSubcontractorand require theContractorto obtain anotherSubcontractor. Any reviews or approvals by theOwnerpursuant to the provisions of this Article or elsewhere in thisContractshall not release or relieve theContractorof any of its obligations under thisContractor create any contractual relations between theOwnerand anySubcontractor. TheContractorshall require anySubcontractorto agree to be bound by thisContractand to abide by theScope of Workfor safety and loss management. |
16.2 | Prior to theCommencement Date, theContractorshall provide theOwner’s Representativewith a list of the names and addresses of allSubcontractorsand others who theContractorproposes to perform any part of theWork. TheContractorshall provide theOwner’s Representativewith any proposed changes to this list during theContract Time. |
16.3 | TheContractorshall be fully responsible for any part of theWorkperformed bySubcontractorsand for the acts or omissions ofSubcontractorsand all persons either directly or indirectly employed by them, to the same extent as theContractoris for its |
EPC Contract
Page 19 of 47
| own acts or omissions. Without in any way limiting theContractor’sobligations pursuant to the provisions of this Article or elsewhere under thisContract, theContractorshall secure compliance with and enforce, at its own expense, for the benefit of theOwner, each of the contracts concluded by theContractorwithSubcontractors. |
16.4 | ThisContractshall inure to the benefit of and bind any successor in interest to a party to thisContract. ThisContractmay not be assigned by either party without the prior written consent of the other party. Notwithstanding the foregoing,Contractormay assign thisContractto any successor in interest to that portion ofContractor’sbusiness involved in the subject matter of thisContract, provided, however, that FMC Technologies, Inc. shall remain liable for all obligations of “Contractor” hereunder and shall not be released from such liability as a result of any such assignment. |
16.5 | TheOwnershall not assign thisContractincluding all rights and obligations hereunder, at any time without the prior agreement of theContractor, except for any collateral assignment required in connection withOwner’sfinancing of theWork. |
16.6 | TheContractorshall enforce the warranty obligations of itsSubcontractors, and upon the request of theOwner, shall assign any warranty to theOwner. All contracts between theContractorand itsSubcontractorsshall provide that warranties given by theSubcontractorshall be given to both theContractorand theOwnerand the warranties may be enforced by either theContractoror theOwner. |
16.7 | TheContractorshall request and use its best efforts to obtain for the benefit of theOwner, the best warranties and guarantees that it is possible to secure from itsSubcontractorswithout impact to cost and, as a minimum, shall obtain and provide to theOwnerthe warranties required by theContract. TheContractorshall do all things and provide all assistance reasonably necessary to enable theOwnerto enforce warranties and guarantees provided by itsSubcontractors. |
ARTICLE 17 - Inspection and Testing
17.1 | TheInspection and Test Planshall be prepared by the party specified in theScope of Workas having responsibility for the preparation of it and shall be followed when any inspection or testing of theWorkis performed. |
17.2 | At all times during the progress of theWork, theOwnershall have the right to inspect or witness any part of theWork. |
17.3 | TheContractorshall inspect and be solely responsible for the inspection of all workmanship, materials and equipment furnished by itself or itsSubcontractorsin respect of theWork, to ensure conformity in each and every respect to theContract(including, without limitation, theConstruction Documents) and theLawand to ensure that good and proper construction practices are followed and that theWorkis performed in a safe and environmentally sound manner. |
EPC Contract
Page 20 of 47
17.4 | If theLawrequires testing of any part of theWork, theContractorshall provide theOwnerwith sufficient advance notice of the arrangements for the test and shall thereafter conduct the test in compliance withLaw. |
17.5 | TheContractorshall provide theOwner’s Representativewith sufficient advance notice of its readiness for any test and theOwnershall then promptly witness the test. If theOwnerfails to witness the test when scheduled, any re-testing required by theOwnershall constitute aChange. |
17.6 | If any portion of theWorkis closed or covered by theContractorwithout theOwner’spermission and before theOwnerhas been given the opportunity to perform or witness a required test, then, if required by theOwner, that portion of theWorkshall be opened or uncovered for testing and re-closed or recovered, all at theContractor’sexpense and without increasing theContract Time. |
17.7 | AnyWorkwhich must be tested shall not be considered ready for inspection by theOwneruntil theContractorhas satisfied itself and notified theOwner’s Representative, that, in theContractor’sopinion, that portion of theWorkcan successfully pass the test. |
17.8 | Any inspection, testing or witnessing of any of theWorkor tests by theOwner, or omission or failure on the part of theOwnerto inspect or test any of theWorkshall not be construed to be an acceptance of any suchWork, or as relieving theContractorof its responsibilities pursuant to theContractor the Law. |
17.9 | TheContractorshall ensure that all tools, equipment, temporary facilities and other items used in accomplishing theWork, whether purchased, rented, manufactured or fabricated by, or under the direction of theContractor, or otherwise provided by theContractororSubcontractors, are safe, environmentally sound and maintained in good condition, capable of performing their required functions. In the case of tools, meters and other devices which require calibration, theContractorshall ensure that such calibration is performed on the frequency recommended by the manufacturer and in accordance with normal industry practice. |
17.10 | TheOwnerreserves the right to inspect all tools and equipment brought on to theWork Siteat any time during the progress of theWorkupon reasonable notice. TheOwner’s Representativemay require theContractorto supply a qualified, independent engineering evaluation or certification that any item in question is suitable for its intended purpose, or to reject any item and require replacement with a proper and suitable item which is satisfactory to theOwner’s Representativeand shall constitute a Change with cost toOwner. If any tool or item of equipment is determined via independent engineering evaluation or certification to be unsafe, environmentally unsound or incapable of doing the work for which it is intended, then theContractorshall pay for the cost of the independent evaluation or certification and repair or replace it with a safe, environmentally sound and suitable tool or item of equipment at theContractor’sexpense. |
EPC Contract
Page 21 of 47
17.11 | TheOwnermay, at any time during the progress of theWork, conduct additional inspections or tests on any part thereof (in addition to those specified in theScope of Work), to determine whether theWorkis in accordance with theScope of Work. Such tests shall be at the sole expense of theOwnerexcept as otherwise set forth in theScope of Work. If such additional testing causes a delay in theScheduled Functional Completion Date, Contractor shall submit to Owner aChange Quotationsetting forth the proposed newScheduled Functional Completion Datein accordance with Section 13.7. |
17.12 | TheContractorshall develop and provide to theOwner, for theOwner’sreview and approval, anInspection and Test Planin time to allow the Owner to perform the inspections contemplated by this Article 17 – Inspection and Testing. |
ARTICLE 18 - Performance Tests
18.1 | IfPerformance Tests are specified in theScope of Work, this Article shall apply. |
18.2 | Performance Tests may be stipulated in theScope of Workto be performed before, after, or both before and afterFunctional Completionand shall be performed by that party specified in theScope of Work. |
18.3 | Unless otherwise stipulated in theScope of Work: |
| (a) | theOwnershall provide the necessary labor, materials, electricity, fuel, heat, chemicals, disposal of fluids and materials and water for thePerformance Tests; |
| (b) | theContractorshall carry out thePerformance Testsin accordance with the manuals provided by theContractorunder Section 5.4; and |
| (c) | theContractorshall provide such guidance as specified in theScope of Workduring the course of suchPerformance Tests. |
18.4 | When theContractorconsiders that theWork, or anySystem, will pass thePerformance Tests, theContractorshall notify theOwnerthat theContractormay perform thePerformance Testson, or to, theWorkor aSystem. |
18.5 | If theWorkor aSystem, or part thereof, passes one or morePerformance Tests, theOwnershall promptly give notice acknowledging the success of the same to theContractor. Such acknowledgement shall not be deemed to be an acceptance by Owner of theWork or System, or limit or relieve theContractorof its obligation to achieveFunctional Completionof the entirety of theWorkin accordance with Article 19, theScope of Workor any other provision of thisContract. |
EPC Contract
Page 22 of 47
18.6 | If theWorkor aSystem, or part thereof, fails one or more of thePerformance Tests, then theContractorshall: |
| (a) | prepare a report to theOwner, for theOwner’sapproval, proposing the alterations theContractorwill make to theWork or System, or part thereof, to bring theWork or Systemto a condition which theContractorconsiders will pass thePerformance Tests; provided, however, that the Owner’s review and approval of any such proposed alterations shall not limit or relieve the Contractor of its obligation to bring the Work or System to a condition which actually passes the Performance Test; |
| (b) | redo or repair theWork or System, or part thereof, and repair any damage to theWork or Systemcaused by the same in failing to meet thePerformance Test, to make suchWork or System, or part thereof, ready for a repeat and successful completion of the failedPerformance Tests. |
18.7 | To the extent theWork or a System, or part thereof, fails to pass one or morePerformance Testssolely as a result of actions or omissions by theOwner, theOwnershall promptly issue aChange Orderproviding aChangein theContract Timeor theCompensation, or both, as the case may be, to theContractorfor suchPerformance Testsand theContractorshall proceed with its obligations relating to thePerformance Testsas set out in theScope of Work. |
ARTICLE 19 - Functional Completion
19.1 | Intentionally omitted. |
19.2 | TheContractormay apply by notice to theOwner’s Representativefor aFunctional Completion Certificatenot earlier than 3 days before theWorkwill, in theContractor’sreasonable opinion, be complete and ready for taking over by theOwner. Such notice shall include theDeficiencieswhich are acknowledged by theContractor. In no event shall theContractormake application for aFunctional Completion Certificateuntil theWorkhas successfully passed or completed all applicable tests and inspections under theInspection and Test Planand any applicablePerformance Tests. |
19.3 | After receipt of theContractor’sapplication for aFunctional Completion Certificate, theOwner’s Representativeshall, within 3 days after the receipt of the same: |
| (a) | reject the application, giving reasons and specifying the work required to be done by theContractor, which reasons shall specify (to the extent known toOwner) Category “A”Deficiencies, related to theWork, and which, if not remedied, will prevent theOwnerfrom commissioning or starting-up theFacilitiesand thereafter being able to use the same in the manner contemplated, and the Category “B”Deficiencies, related to theWork, which will not prevent theOwnerfrom commissioning or starting-up theFacilities; or |
| (b) | issue theFunctional Completion Certificateto theContractor, stating the date on which theWorkwas completed in accordance with theContract, attaching a list (to the extent known toOwner) of Category “B”Deficiencies, related to the |
EPC Contract
Page 23 of 47
| Work, and which if not remedied will not prevent theOwnerfrom commissioning or starting-up theFacilities, and theContractorshall cease to be liable for, and shall relinquish care, custody and control of, theFacilitiesfrom the date of theFunctional Completion Certificateand responsibility shall pass to theOwner. |
19.4 | If theOwnerreasonably determines that theWorkdoes not meetFunctional Completion, as set out in this Article 19 or theScope of Work, theOwnershall provide a notice to theContractoras specified in Section 19.3(a) and theOwner’s Representativemay: |
| (a) | order further repetition ofPerformance Testsspecified to be performed beforeFunctional Completionin theScope of Work, or other tests necessary to determineFunctional Completion; or |
| (b) | issue aFunctional Completion Certificate, in which case, if theOwnerso requires, theCompensationshall then be reduced by such amount as may be agreed by theOwnerand theContractor(in full satisfaction of such failure only), and theContractorshall then proceed in accordance with theContractor’sother obligations under theContract. |
19.5 | If theOwner’s Representativefails either to issue theFunctional Completion Certificateor to reject theContractor’sproperly submitted application within the period of 3 days, the Functional Completion Certificateshall be deemed to have been issued on the date specified by theContractorforFunctional Completionin the notice in accordance with Section 19.2. |
19.6 | Where theContractor’sapplication for aFunctional Completion Certificateis rejected by theOwnerin accordance with 19.3(a), theContractorshall not re-apply for aFunctional Completion Certificateunder Section 19.2 until the Category “A”Deficienciesare remedied. |
19.7 | TheOwnershall not use any part of theWorkunless theOwner’s Representativehas issued aFunctional Completion Certificatefor theWork, or aFunctional Completion Certificatehas been deemed to have been issued in accordance with Section 19.5. |
19.8 | If theContractoris prevented from carrying out aPerformance Testby a cause for which theOwneror one or more OtherContractorsare responsible, theContractorshall notify theOwnerwithin 48 hours of such delay and if theContractoris further prevented during the next 48 hours from doing so, theOwnershall issue aChange Orderto compensate theContractorfor a change inCompensationorContract Time, as may be applicable. |
19.9 | After aFunctional Completion Certificateis issued, theOwnermay continue to identifyDeficiencies. WhereDeficienciesare identified after issuance of aFunctional Completion Certificate, the procedure for dealing with and resolving suchDeficienciesshall be as set forth in Appendix D – Warranty Items Procedure. |
EPC Contract
Page 24 of 47
ARTICLE 20 - Final Completion
20.1 | It is a condition precedent to the issuance of aFinal Completion Noticethat theContractorsatisfy each of the following requirements: |
| (a) | theWorkhas been fully completed in accordance with the terms and conditions of thisContract; |
| (b) | all Deficiencies with respect to theWorkhave been remedied to meet the requirements of theContract; |
| (c) | all obligations of theContractorto other parties in relation to theWork, for which theOwnercould in any way be held responsible, have been fully satisfied; and |
| (d) | theContractorhas delivered to theOwnerthe following: |
| (i) | a statutory declaration in the form included in Appendix G–Forms and modified as required to include the following: |
| (a) | the amount of final sums payable; |
| (b) | the date theContractorcompleted theWork, to evidence the expiration of the term for filing liens. |
| (ii) | anyAs-Built Drawingsand operations manuals for which theContractoris responsible; |
| (iii) | assignments of any warranties provided by manufacturers or suppliers of materials; |
| (iv) | a Release and Certificate of Final Payment, in the form provided in Appendix G–Forms, releasing all of theContractor’sclaims against theWorkand theOwnerarising under or by virtue of thisContract. |
| (v) | A final lien release from theContractorand eachSubcontractorand material supplier that performed any portion of theWorkor supplied anyGoodsorProcured Goodsin connection with theWork. |
| (vi) | a final certificate of occupancy for theProjectand theProjecthas passed all other governmental inspections. |
20.2 | When conditions precedent set out in Section 20.1 have been met by theContractor, theOwnershall issue to theContractoraFinal Completion Notice. |
EPC Contract
Page 25 of 47
ARTICLE 21 - Liquidated Damages
21.1 | Liquidated Damagesshall be paid by theContractorto theOwnerin accordance with Appendix E–Liquidated Damages. |
ARTICLE 22 - Incentive Fee
22.1 | TheIncentive Feeshall be paid to theContractorby theOwnerin accordance with Appendix F–Incentive Fee. |
ARTICLE 23 - Warranty
23.1 | If a defect in theFacilitiesis discovered during theWarranty Periodand if theOwnerhas notified theContractorin writing of suchDeficiencyno later than 30 days after the expiry of theWarranty Period, theContractorshall, at its own risk and expense remedy without delay, and in a manner substantially consistent with the originalWork, cure such defect; |
23.2 | TheContractorfurther warrants any and all corrective actions it performs in respect of defects appearing during theWarranty Periodfor a period of up to the later of (i) the end of the originalWarranty Period, or (ii) 6 months from completion of the remedial work. |
23.3 | TheContractorshall immediately advise theOwner’s Representativeof any defects in workmanship, defects, errors, omissions or mistakes in theWorkthat it discovers or becomes aware of during theContract Timeor theWarranty Period. |
23.4 | TheContractorshall perform its warranty obligations set forth in this Article 23 - Warranty in a manner that keeps disruptions to theOwner’scontinued operations at a minimum. |
23.5 | Neither acceptance of theWorkby theOwner, nor payment for performance of theWork, shall relieve theContractorfrom any responsibility for defects in theWork. |
23.6 | The sole remedy for breach of this warranty is the repair or replacement, at the option ofContractorof the defectiveWork, including, without limitation, labor to remove and/or reinstall theWork. |
23.7 | Goods which have been subjected to abuse or other improper use will not be entitled to the benefits of any warranty byContractor. |
23.8 | EXCEPT AS EXPRESSLY SET FORTH IN THIS CONTRACT (INCLUDING, WITHOUT LIMITATION, CONTRACTOR’S OBLIGATIONS UNDER SECTION 10.1(d)(ii) ABOVE, THERE ARE NO OTHER WARRANTIES, STATUTORY, AT LAW, EXPRESS OR IMPLIED, INCLUDING THE IMPLIED WARRANTIES OF MERCHANTABILITY, AND FITNESS FOR A PARTICULAR PURPOSE, WHICH EXTEND BEYOND THE FACE OF THIS AGREEMENT. |
EPC Contract
Page 26 of 47
ARTICLE 24 - Compliance with Law
24.1 | TheContractorshall act in accordance with theLawand with a view to the timely and cost effective completion of theWorkin accordance with theMilestones. |
24.2 | Where there is a change in theLawafter the effective date of thisContract, theContractorshall be responsible for ensuring that theWorkcomplies with theLaw, but any time or cost associated with such change shall be to the account of theOwner. If theContractorconsiders such change to be aChange, theContractormay make a claim for suchChangeunder Section 13.7. |
24.3 | TheContractorshall comply with and shall ensure that its employees and agents comply with and shall contractually require itsSubcontractorsand their respective employees and agents to comply with all applicableLawin connection with theWork. |
24.4 | TheContractorshall obtain from governmental authorities or other third parties, and pay for, those licenses, permits and approvals required by theLawand theContractto perform theWork, except those licenses, permits and approvals required with respect to the land-use aspects of theWorkto be performed on theWork Site, and except for any licenses, permits and approvals required by theContractto be obtained by theOwneras stipulated in Appendix A – Scope of Work. |
ARTICLE 25 - Safety and Loss Management
25.1 | TheOwnerand theContractorare committed to safety and the application of loss management principles in the conduct of their business. The parties recognize that excellence in safety and loss management can only be achieved through the active participation of everyone, includingSubcontractorsand their respective employees, consultants and agents. |
25.2 | TheContractorshall have the highest regard for safety, emergency procedures and loss management at all times during the performance of theWork. Accordingly, theContractorshall at all times be responsible for safety and loss management in the performance of theWork, including, but not limited to, protecting the employees of theOwner, theContractor,Other Contractors,Subcontractors, visitors to theWork Siteand the general public from injury or death and protecting theWork Site, theOwner’sproperty and the property of third parties from loss or damage. Without limiting the generality of the foregoing, theContractorshall comply with all safety requirements specified in theContract. |
25.3 | TheContractorshall comply with theSafety Plan. |
25.4 | All employees of theContractorandSubcontractorsand allWork Sitevisitors must successfully complete any of theOwner’ssafety orientation courses and other similar courses stipulated in theScope of Workbefore being allowed access to theWork Site, and it shall be theContractor’sresponsibility to ensure that they have done so. |
EPC Contract
Page 27 of 47
25.5 | For allWorkperformed on theWork Site,theContractorshall have an alcohol and drug policy that is reasonably acceptable toOwner. |
ARTICLE 26 - Work Area and Clean Up
26.1 | TheContractorshall be responsible for keeping all its working and storage areas clean, orderly and secure. |
26.2 | TheOwneris not responsible for theft, loss or damage to theContractor’stools, equipment or materials howsoever caused. |
26.3 | TheContractorshall not, and shall ensure that itsSubcontractorsdo not, use, transport, or storeHazardous Materialat theWork Siteexcept with the prior approval of theOwner’s Representative.AllHazardous Materialused, transported or stored shall be dealt with in accordance with, and theContractorshall comply with, theLawand theContract. |
26.4 | During the performance of the Work, the Contractor shall comply fully with the Contract and the Owner’s safety and emergency guidelines and publications regarding clean up. The Contractor shall clean up, remove and dispose of all surplus materials, containers, trash and debris resulting from the Work. Upon completion of the Work, or earlier termination of the Contract, the Contractor shall promptly clean up and remove all equipment, tools and surplus materials from the Work Site as reasonably specified by the Owner and shall leave the Work Site clean and ready for the Owner’s use and occupancy. |
ARTICLE 27 - Title and Responsibility
27.1 | Except for any proprietary processes of theContractorlisted in Appendix A - Scope of Work, all of theWorkshall belong to theOwner,and accordingly theContractorshall have no proprietary right or interest in theWork.TheContractorshall not use, copy or disclose any of theScope of Workor theWorkfor any purpose other than performing theWork.Subject to the foregoing, theContractormay retain for its own records a copy of the plans and specifications. |
27.2 | Notwithstanding Section 27.1, where a technology, process or work method belongs to, or is developed by theContractororSubcontractorand is not the result ofConfidential Informationprovided by theOwner,the proprietary rights to that technology, process or work method shall remain with theContractororSubcontractor.Where proprietary rights remain with a party other than theOwner,then theOwnerand its assignees shall, and are hereby granted, the right and irrevocable license without charge to have, retain and use information in respect thereof, for the purpose of theWorkand the operation, repair, maintenance, re-building or renovation of theWorkor any portion thereof. |
EPC Contract
Page 28 of 47
27.3 | Notwithstanding Section 27.1, or any other provision of theContract,theContractorshall be responsible for possession of theEngineering Servicesuntil received by theOwner. If theEngineering Services, or any part thereof is lost, damaged or destroyed prior to receipt by theOwner, then theEngineering Services, or portion thereof, as applicable, shall be promptly redone and replaced by theContractor, at its expense, unless the loss, damage, or destruction was caused by theOwneror persons for whom in Law it is responsible. |
27.4 | Subject to theOwner’srights under Section 16.5, theOwneragrees that it shall not: |
| (a) | sell to third parties theEngineering Services, except as part of the sale of theProject; |
| (b) | distribute theEngineering Services, to third parties except for the purpose of operating, maintaining, repairing or replacing, re-building or renovating theOwner’sproperty encompassing or relating to theWork, or, for the purpose of performing other work directly related to theWork, or for building other facilities, plants or structures of a similar nature or purpose. |
27.5 | The title to allWorkcompleted or in the course of construction at theWork Siteand allGoods, except tools and equipment owned or rented by theContractororSubcontractorsand not intended to be incorporated into theWork, shall become the property of theOwnerupon payment by theOwneron account thereof. |
27.6 | Notwithstanding the provisions of Section 27.5, until theOwnerhas issued aFinal Completion Notice, theContractorshall retain all risk (including loss, theft, damage or destruction), but subject to the application of any insurance proceeds maintained byOwnerorContractoron account of any such risk, with respect to and be responsible for: |
| (a) | all items supplied by theContractoror itsSubcontractorswhich are to be incorporated into theWorkor used in performance of theWork; |
| (b) | all items supplied by theOwnerto theContractorfor incorporation into theWorkor for use in performing theWork; |
| (c) | all temporary structures or facilities used in the performance of theWork; and |
| (d) | anyWorkcompleted or in progress. |
27.7 | No materials, supplies or equipment incorporated into theWorkshall be subject to any general security agreement, chattel mortgage, financing contract or other agreement by which an interest therein is retained by the seller, or any other party. |
ARTICLE 28 - Patents and Licenses
28.1 | TheContractorshall indemnify and save theOwnerharmless from all claims costs and demands, including legal fees, arising out of any suits, claims or demands for patent, trademark, copyright or industrial design infringement pertaining to any |
EPC Contract
Page 29 of 47
| equipment, machinery, materials, compositions, processes, methods or designs supplied by theContractor, or itsSubcontractors, in the performance of theWork. TheContractorshall pay all royalties and license fees pertaining to any equipment, machinery, materials, compositions, processes, methods or designs supplied by theContractor, or itsSubcontractors, in the performance of theWork. |
28.2 | TheContractorshall own all right, title and interest in any Project Intellectual Property (as hereinafter defined) that relates to products or services manufactured or provided by theContractorTheContractorhereby grants to theOwneran irrevocable, worldwide, non-exclusive license to use any Project Intellectual Property owned by theContractor, solely for the purpose of the operation and maintenance but not the manufacture of any equipment provided to theOwnerby theContractorunder this Contract. Where software is embedded or accompanies the systems delivered in theWork, a non-exclusive license is granted to theOwnerto govern the access to and use of such software for the limited purpose of operating or using theWork. “Project Intellectual Property” shall mean all Intellectual Property, including, without limitation, proprietary technical, engineering, and business information, reports, studies, analysis, models, or other similar data and documents that are developed in the performance of anyWorkunder this Contract byContractoror its employees, agents or contractors. |
28.3 | The rights granted to theOwnerby theContractorunder Section 28.2 shall be assignable by theOwnerto any party to whom theOwnermay transfer all or part of title to theWorkor theProject. |
28.4 | TheOwnershall be entitled, at its own expense, to participate in or conduct the defense of any claim with respect to which it is entitled to indemnity under Section 28.1 |
ARTICLE 29 - Confidential Information and Publicity
29.1 | Each party shall keep allConfidential Informationin confidence and shall not disclose it to others without the prior approval of the other party. TheContractorshall not use theConfidential Information, except in performance of theWork. |
29.2 | Notwithstanding Section 29.1, theContractormay discloseConfidential Informationto those of its employees,Subcontractorsand their respective employees to whom disclosure is required in order for theContractorto perform theWork, provided theContractorshall ensure that its employees and agents comply with, and shall contractually require itsSubcontractorsand their respective employees and agents to comply with Section 29.1. |
29.3 | TheContractorshall not disclose any of theScope of Workor theWorkto others without the prior approval of theOwner’s Representative, except as necessary to perform theWork. |
EPC Contract
Page 30 of 47
29.4 | Notwithstanding Section 29.1 or Section 29.3,Confidential Informationmay be disclosed by a party if that party is required to disclose theConfidential Informationas a result of an arbitrator appointed under Appendix H - Dispute Resolution Procedure or an order of a court of competent jurisdiction. If disclosure is required by an arbitrator or an order of a court, the disclosing party shall provide the other party with immediate notice of such arbitration or court order and shall only disclose the minimum amount ofConfidential Informationto comply with the arbitration or court order. In addition, notwithstanding anything herein to the contrary, it is acknowledged thatOwneris a publicly traded company; consequently,Ownershall have the absolute and unbridled right to disclose any information regarding the transaction contemplated by thisContractrequired by law to satisfy disclosure and reporting obligations ofOwneror its affiliates |
29.5 | TheContractorshall not use theOwner’sname, or the names of any of its affiliates and the registered or unregistered trademarks of theOwneror its affiliates in any slogans or otherwise in any advertising or promotional materials or publicity releases, and shall not take, permit to be taken or use any photographs of theWork Site, without the prior approval of theOwner’s Representative. |
ARTICLE 30 - Proprietary Information
30.1 | Where proprietary rights remain with a party other than theOwner, theOwnerand its assigns, shall have the right, and are hereby granted the right, to have and to retain a copy for their own use, and to use, anyEngineering Services,As-Built Drawingsor other information, for the purpose of theWorkor the operation, repair, maintenance, replacement, re-building or renovations of theFacilities. |
30.2 | TheContractorshall keep and maintain adequate and current records of allProprietary Information. |
30.3 | Contractorshall keep allProprietary Informationin confidence, shall not use it, or any part of it except in the performance of theWorkand shall not disclose it to others, without theOwner’sprior consent. |
ARTICLE 31 - Force Majeure
31.1 | Either theOwneror theContractormay claim that anEvent of Force Majeurehas taken place, by giving the other party verbal notice within 48 hours of theEvent of Force Majeure, and, in addition, written notice, together with a proposed plan of corrective action to resolve or minimize the effect of theEvent of Force Majeure, within 72 hours of theEvent of Force Majeure.Contractorshall be deemed to have waived any claim for adjustments to theContract Timeresulting from anEvent of Force Majeureif the aforesaid notice is not timely given toOwner. |
31.2 | If theOwnerhas given a notice of anEvent of Force Majeure, or theOwneragrees with a notice of anEvent of Force Majeureissued by theContractorthat theWorkor a portion thereof is affected by anEvent of Force Majeure, then theOwnershall: |
| (a) | cause theContractorto complete theWork, with such time adjustments to theContract Timeas permitted under Section 31.4 below; or |
EPC Contract
Page 31 of 47
| (b) | suspend theWorkor any portion thereof in accordance with Article 34 - Suspension; or |
| (c) | terminate theContractor any portion thereof in accordance with Section 35.1 and Section 36.6. |
31.3 | If theOwneracting reasonably and in good faith does not agree that theWorkor any portion of theWorkis affected as a result of anEvent of Force Majeurefor which theContractorhas given notice under Section 31.1, then theContractorshall complete theWorkin accordance with theExecution Plan |
31.4 | Notwithstanding anything to the contrary contained herein, no request for an adjustment to theContract Timeshall be allowed unless theWorkis affected as a result of anEvent of Force Majeurefor which theContractorhas given notice under Section 31.1 and (a) the delay resulting therefrom increases the overall critical path duration of the schedule in effect at the time of the delay and (b) theContractorhas used its best efforts to offset such delay by making appropriate changes to the other parts of the schedule. TheContractorshall not be entitled in any circumstances to any adjustments in theCompensationor any damages or other compensation whatsoever in the event of any delays in the progress of theWorkunless such delays were solely caused byOwner. OtherwiseContractorhereby waives any rights to such adjustments toCompensationor damages and agrees that the sole remedy for delay, if appropriate and warranted under the provisions of thisContract, shall be an extension of theContract Time. |
ARTICLE 32 - Delays
32.1 | Except as provided in Article 33 below, if there is any delay in the progress of theWork, or ifContractorfails to complete any portion of theWorkwithin the time limits set forth in theExecution Planor fails to complete the Work by theScheduled Functional Completion Date, then theContractorshall, at no additional cost to theOwnerand without limiting any other rights or remedies available toOwnerhereunder, provide a recovery plan and perform whatever acts are required or reasonably requested by theOwner’s Representativeto make up the lost time and to avoid any further delay in the performance of theWork, including, without limitation, work overtime, and acquire and use any necessary additional labor and equipment. |
ARTICLE 33 - Delays not Caused by the Contractor
33.1 | If theContractoris delayed in the performance of theWorksolely by an act or omission of theOwnerorOther Contractors, contrary to the provisions of theContract, then theContract Timeshall be extended for such reasonable time as may be necessary to allow theContractorto make up the delay and adjustment to Compensation shall be made accordingly. |
EPC Contract
Page 32 of 47
33.2 | If theContractoris delayed in the performance of theWorkby an order issued by a court or other public authority having jurisdiction, providing that such order was not issued as the result of an act or fault of theContractoror any person employed or engaged by theContractordirectly or indirectly, then theContract Timeshall be extended as agreed by the parties or as resolved under Appendix H - Dispute Resolution Procedure. |
33.3 | No claim for delay and no extension of time on account of delay under this Article 33 shall be made by theContractorunless notice of claim with aChange Quotationis given to theOwnernot later than 5Work Daysafter the commencement of delay, provided however, that in the case of a continuing cause of delay only one notice of claim shall be necessary. |
ARTICLE 34 - Suspension
34.1 | In addition to any other right that theOwnermay have under theContractor inLaw, theOwnermay, at any time or times, by notice to theContractorspecifying the effective date of the suspension, require theContractorto suspend theWork, or any portion thereof. |
34.2 | Upon providing notice under Section 34.1, theOwnershall arrange to immediately discuss with theContractorthe specific requirements of the suspension and whether or not theOwneranticipates that demobilization, remobilization or idle equipment or personnel will occur as a result of the suspension. |
34.3 | Upon receiving notice, theContractorshall discontinue theSuspended Work, place no further purchase orders or subcontracts with respect to theSuspended Work, and promptly make reasonable efforts to obtain suspension terms satisfactory to theOwnerwith respect to all purchase orders, subcontracts, supply contracts and rental agreements related to theSuspended Work. TheContractorshall continue to perform all other portions of theWorkwhich have not been suspended by theOwner. |
34.4 | Where requested by theOwner, theContractorshall advise theOwnerof: |
| (a) | the number of theContractor’s personnel made idle by the suspension; |
| (b) | the labor costs resulting from theContractor’s, personnel made idle by the suspension; |
| (c) | transportation costs for the Contractor’s personnel released during the suspension; |
| (d) | the equipment made idle and associated equipment costs resulting from the suspension; and |
| (e) | any other costing, labor, material or equipment information relating to the suspension that theOwnermay require. |
EPC Contract
Page 33 of 47
34.5 | TheOwnermay at any time authorize resumption of theSuspended Workor any part thereof, by giving theContractorreasonable notice specifying the part of theSuspended Workto be resumed and the effective date of such resumption. TheContractorshall resume theSuspended Workon the date and to the extent reasonably specified in the notice. |
34.6 | TheContractorshall use its employees, equipment and materials in such manner, and take such other steps as may be necessary or desirable to minimize the costs associated with theSuspended Work. During the period ofSuspended Work, theContractorshall secure and protect theSuspended Workand all materials and equipment to be used or incorporated therein. |
34.7 | In relation to Suspended Work, theOwnershall reimburse theContractorfor those costs, including profit, reasonably incurred by theContractoras a direct result of the suspension of theWorkin accordance with Appendix B – Compensation. |
34.8 | In the event that theOwner, without cause, fails to make payments as described in Appendix BCompensation, theContractorwill have the option, upon twenty (20) days prior written notice to theOwner, to suspend allWorkuntil the payments have been brought current. |
ARTICLE 35 - Termination for Convenience
35.1 | In addition to any other rights that theOwnermay have under theContractor inLaw, theOwnermay, at any time, terminate theContract, theWorkor any portion thereof by giving notice to theContractorspecifying theWorkor portion thereof to be terminated and the effective date of the termination. |
35.2 | Upon receipt of a notice under Section 35.1, theContractorshall discontinue theWorkin accordance with the notice, and shall take whatever steps are necessary or desirable to terminate theWorkin a safe, cost effective and timely manner with due consideration to environmental impacts and the mitigation of costs and damages. TheContractorshall continue to perform all other portions of theWorknot terminated, if any, in accordance with theContract. TheOwnershall reimburse the Contractor for those costs reasonably incurred by theContractorforWorkproperly executed up to the date of termination, actual losses incurred by theContractoras a direct result of the termination of theContract, theWork, or any portion thereof, and profit on completedWork, but no further damages. |
EPC Contract
Page 34 of 47
ARTICLE 36 - Termination for Cause
36.1 | Without limiting the generality of Section 35.1, theOwnermay immediately terminate theContractby notice to theContractorin any of the following circumstances: |
| (a) | if theContractorbecomes insolvent or makes a general assignment for the benefit of its creditors, enters into a plan of arrangement for the benefit of its creditors or otherwise acknowledges its insolvency or if a bankruptcy or receiving order is filed or made against theContractor; |
| (b) | if an order is made or resolution is passed for the winding up or liquidation of theContractor; |
| (c) | if a custodian, receiver, manager or other officer with similar powers is appointed in respect of theContractoror any of theContractor’sproperty; |
| (d) | if theContractorceases to carry on business in the ordinary course; and |
| (e) | if a creditor takes possession of any of theContractor’sproperty or if a distress, execution or any similar process is levied or enforced against such property and remains unsatisfied by theContractor. |
36.2 | Upon receipt of a notice pursuant to Section 36.1, theContractorshall discontinue theWorkin accordance with the notice, and shall take such steps as may be necessary or desirable to minimize the costs associated with the termination of theWork. |
36.3 | In addition to any rights theOwnermay have atLaw,if theContractoris in default in carrying out any of the terms, conditions, covenants or obligations of theContract,or has made a false representation, declaration or warranty, theOwnermay give theContractornotice of default. |
36.4 | Where theOwnergives theContractora notice of default pursuant to Section 36.3, theContractorshall have fifteen (15) Working Days immediately following receipt of the notice, or such longer time as theOwnerdetermines to be reasonable and has specified in the notice of default or has subsequently agreed upon in writing, to remedy such default. If theContractorfails to remedy the default within the aforesaid fifteen (15) Working Days, theOwnermay terminate the whole or any part of theContract. |
36.5 | In the event theContractor any portion of theWorkis terminated pursuant to Section 36.1 or Section 36.4: |
| (a) | theContractorshall discontinue theWorkin accordance with the notice and shall take such steps as may be necessary or desirable to minimize the costs to theOwnerassociated with the termination of theWork; |
| (b) | theOwnershall have the right to take possession of theGoods,materials and plant and shall have the right to use the same to complete theWork; |
EPC Contract
Page 35 of 47
| (c) | theContractorshall execute and deliver to theOwnerall documents required by theOwner,and shall take all steps required by theOwner,to assign to and fully vest in theOwnerthe rights and benefits of theContractorunder existing agreements with theContractor’s Subcontractors,which are related to theWork. |
36.6 | Subject to the terms of Section 42.5 below, damages to theOwnerfor which theContractorshall be liable in the event of a default byContractorshall consist of an amount equal to the amount by which the cost to theOwnerof achievingFunctional Completionand final completion within theContract Time(or attempting to achieveFunctional Completionand final completion within theContract Time),including amounts paid hereunder, exceeds theCompensation. |
36.7 | TheContractormay immediately terminate theContractby notice to theOwnerin any of the following circumstances: |
| (a) | if theOwnerbecomes insolvent or makes a general assignment for the benefit of its creditors, enters into a plan of arrangement for the benefit of its creditors or otherwise acknowledges its insolvency or if a bankruptcy or receiving order is filed or made against theOwner; |
| (b) | if an order is made or resolution is passed for the winding up or liquidation of theOwner; |
| (c) | if a custodian, receiver, manager or other officer with similar powers is appointed in respect of theOwneror any of theOwner’sproperty; |
| (d) | if theOwnerceases to carry on business in the ordinary course; and |
| (e) | if a creditor takes possession of any of theOwner’sproperty or if a distress, execution or any similar process is levied or enforced against such property and remains unsatisfied by theOwner; |
36.8 | Should theOwnerbe in material default, including delayed payments, of its obligations under thisContract,theContractormay provide a written notice to theOwnerthat should the material default not be remedied within fifteen (15) Work Daysafter delivery of such written notice, that theContractormay suspend or terminate theContractor’sobligations under theContract. |
36.9 | The rights and remedies provided in this Article 36 - Termination for Cause are in addition to the rights and remedies provided by the Law, or under any other provision of the Contract. |
EPC Contract
Page 36 of 47
ARTICLE 37 - Taxes
37.1 | TheContractorshall be responsible for the payment of: |
| (a) | all taxes imposed by reason of the performance or completion of theWorkincluding but not limited to license, permit and registration fees and theContractor’sincome, profit, franchise, business, and personal property taxes; |
| (b) | all employment taxes and contributions imposed by theLawor required to be paid on behalf of the employees of theContractoror itsSubcontractors, including but not limited to taxes and contributions for income tax, workers’ compensation, unemployment insurance, old age benefits, welfare funds, pensions and annuities and disability insurance; |
| (c) | all taxes, other than property taxes, on theWork Siteand arising out of theWork, to the dateof Functional Completion; and |
| (d) | all customs, sales and excise taxes and duties owing with respect to any labor, machinery, materials and equipment to be supplied by theContractorand used in performance of or incorporated into theWork,except for goods and services tax payable by theOwnerwith respect to payments due to theContractor. |
37.2 | Any increase in taxes and charges described in Section 37.1(a) and Section 37.1(b) shall be the sole responsibility of theContractor.In the event of an increase in taxes or charges described in Section 37.1(c), theContractorshall be entitled to aChange Orderaltering theCompensationto account for the difference between the amount of tax that would have been payable by theContractoras of the effective date of thisContractand the actual amount of tax that becomes payable as a result of the tax increase. |
37.3 | TheContractorshall indemnify and hold theOwnerharmless from any liability resulting from the failure of theContractoror itsSubcontractorsto make timely payments of the items referred to in this Section or such similar items for which theContractoris responsible. Any interest, penalties or other liabilities arising from such failure shall be the sole responsibility of and be paid for by theContractor. |
ARTICLE 38 - Intentionally Omitted
(a)
ARTICLE 39 - Liens
39.1 | TheContractorshall at all times reimburse, protect, indemnify and save free and harmless theOwner, theWork Siteand the other lands and property of theOwnerfrom and against all liens and claims made or liability incurred by theOwneron account of theWorkperformed or materials supplied by employees of theContractorandSubcontractors(provided that Owner has made all payments to Contractor then due and payable in accordance with the terms ofAppendix B), or on account of an exaggerated lien filed by theContractor,including, without limitation, legal fees. TheContractorshall cause any such lien or claim which may be filed or made, to be released and discharged forthwith at the expense of theContractor.If theContractor |
EPC Contract
Page 37 of 47
| fails to release or obtain the release and discharge of any such lien or claim, then theOwnermay, but shall not be obliged to, discharge, release or otherwise deal with the lien or claim, and theContractorshall pay any and all costs and expenses incurred by theOwnerin so releasing, discharging or otherwise dealing with the claim or lien, including but not limited to, legal fees on a solicitor-and-own-client (indemnity) basis. Any amounts so paid by theOwnermay be deducted from any amounts due theContractorwhether under theContractor otherwise. |
ARTICLE 40 - Survival
40.1 | If theContractor any part of theWorkis terminated pursuant to Article 35 - Termination for Convenience or Article 36 - Termination for Cause, then Article 23 - Warranty shall survive such termination, and theWarranty Period,with respect to theWork(or portion thereof then completed), shall remain in effect notwithstanding the termination of thisContract. |
40.2 | Any terms, covenants, provisions or conditions of theContractwhich expressly or by their nature survive the termination of theContractshall continue in full force and effect subsequent to and notwithstanding such termination, and shall not be merged with the termination, until such terms, covenants, provisions and conditions are satisfied or by their nature expire. |
ARTICLE 41 -Liability and Indemnity for Third Party Claims
41.1 | TheContractorshall be liable to and shall indemnify, and hold harmless theOwner,its officers, directors, employees, consultants and agents for all losses, damages and expenses, including legal fees, which they or any of them may incur as a result of claims, demands, actions or proceedings made or taken against them by persons not party to theContractfor: |
| (a) | any acts or omissions in connection with the performance, purported performance or non-performance of theContractor of theWorkby theContractoror itsSubcontractorsor their respective employees or agents; |
| (b) | any acts or omissions of theOwner, Other Contractorsor their respective employees or agents, or in connection with such acts or omissions, to the extent acting under the direction and control of theContractor,itsSubcontractorsor their respective employees or agents; |
| (c) | any liability, claims, damages, costs and expenses arising from the failure of theContractoror itsSubcontractors, or their respective employees or agents to comply with theLaw. |
EPC Contract
Page 38 of 47
41.2 | TheContractorshall, at its sole expense, if requested by theOwner,defend those persons entitled to be indemnified pursuant to Section 41.1. TheOwnershall have the right, if it so elects, to participate in any such defence and theContractorshall have the right to settle said claims without first consulting with theOwner. |
41.3 | TheOwnershall indemnify and hold harmless theContractor,itsSubcontractors,and their respective officers and directors from and against all claims, demands, losses, damages, expenses, actions and proceedings made or taken by persons not party to theContractand which arise on account of and are attributable to theOwner’sobligations hereunder. |
41.4 | In the event that theOwneraccepts the responsibility to indemnify theContractor,itsSubcontractors,officers and directors pursuant to Section 41.3, then it shall be entitled to retain and instruct counsel to act for and on behalf of those persons and to settle, compromise and pay any claim, demand, action or proceeding without first obtaining prior approval from the party in whose favour the indemnity has been provided. TheContractorshall and shall cause any indemnified party to co-operate in all respects in contesting any third party claim for which theOwnerhas accepted responsibility. |
ARTICLE 42 -Liability and Indemnity
42.1 | TheContractorshall be liable to and shall indemnify theOwner,its officers, directors, employees, consultants and agents for all losses, damages and expenses on account of: |
| (a) | all physical damage caused by theContractoror itsSubcontractorsto theWork,theWork Site,the property of theOwnerorOther Contractorsor property under the care, custody or control of theOwnerorOther Contractors;and |
| (b) | the cost to repair or make good any and all damage to roads, bridges, railroads, highways, land adjacent to theOwner’s Site,irrigation canals or facilities, ditches or equipment relating thereto caused by or resulting from the actions howsoever of theContractoror itsSubcontractors. |
42.2 | Contractorshall defend, indemnify and holdOwner,its officers, agents and employees harmless from and against any and all liability, loss, expense (including reasonable attorneys’ fees) or claims for injury or damages arising out of the performance of this Agreement but only in proportion to and to the extent such liability, loss expense, attorneys’ fees, or claims for injury or damages are caused by or result from the negligent or intentional acts or omissions ofContractor, Subcontractors,and their respective officers, agents or employees. |
42.3 | Ownershall defend, indemnify and holdContractor,its officers, agents and employees harmless from and against any and all liability, loss, expense (including reasonable attorneys’ fees) or claims for injury or damages arising out of the performance of |
EPC Contract
Page 39 of 47
| this Agreement but only in proportion to and to the extent such liability, loss, expense, attorneys’ fees, or claims for injury or damages are caused by or result from the negligent or intentional acts or omissions ofOwner, Other Contractorsand their respective officers, agents or employees. |
42.4 | Notwithstanding anything to the contrary contained herein, neither party shall be liable to the other in contract or in tort, directly or under any indemnity, for lost profits or for any indirect, special, or consequential damages, arising out of or related to this Contract. |
42.5 | Notwithstanding any other provision of theContract,each party’s total liability to the other for damages hereunder (excluding any damages owed to the other party pursuant to any indemnification obligation hereunder, where such damages relate to claims by third parties against the indemnified party) shall be limited to $18,403,721.00. |
42.6 | Contractorshall release, defend, indemnify and hold harmlessOwner,its affiliates and its other contractors from and against any and all liability, loss, expense (including reasonable attorneys’ fees) or claims for injury or damages arising out of or relating toHazardous Materialwhich escapes or emanates directly fromContractor’sor anySubcontractor’sequipment or which is otherwise released as a result of the acts or omissions ofContractoror anySubcontractorsor their respective officers, agents or employees.Ownershall release, defend, indemnify and hold harmlessContractorfrom and against any and all liability, loss, expense (including reasonable attorneys’ fees) or claims for injury or damages arising out of or relating toHazardous Materialwhich exists on theWork Siteas of the date of thisContract,or which is released as a result of the acts or omissions ofOwner. |
42.7 | TheOwnerandContractorwaive all rights against each other and any of their Subcontractors, sub-subcontractors, agents and employees, each of the other, for damages caused by fire or other causes of loss to the extent covered by property insurance obtained pursuant to Sections 43.1(d) or 44.1(a) or other property insurance applicable to the Work. The policies shall provide such waivers of subrogation by endorsement or otherwise. |
ARTICLE 43 - Insurance Provided by Contractor
43.1 | TheContractorshall, and shall ensure that itsSubcontractorsshall, without limiting any of the obligations or liabilities under theContract,continuously carry during the performance of theWorkand any time theContractoror itsSubcontractorsare on theWork Site,at their own expense and cost, the following insurance coverage with limits where applicable not less than those shown in the respective items as set out below: |
| (a) | workers’ compensation coverage for all employees engaged in theWorkin accordance with the statutory requirements of The State of Ohio; |
| (b) | employer’s liability coverage for all employees engaged on theWork Siteand not covered by workers’ compensation, in the amount of $1,000,000; |
EPC Contract
Page 40 of 47
| (c) | automobile liability insurance covering all licensed motor vehicles owned or leased having a limit of not less than $1,000,000 inclusive per occurrence for bodily injury, death, and damage to property; |
| (d) | property and contractor’s equipment insurance covering property, equipment, tools and construction machinery owned, rented or leased by and to be used for the performance of theWork, including machinery, equipment, materials and supplies stored outside of theWork Siteor in transit to theWork Siteand intended to become a part of the finishedWork, but excluding all machinery, materials and supplies at theWork Site, for the full replacement cost value of such property on an “all risks” basis; |
| (e) | commercial general liability insurance policy, including (but not limited to) contractor’s liability coverage, contractual liability coverage (including any indemnification obligations of Contractor set forth in this Contract), completed operations coverage, broad form property damage endorsement and contractor’s protective liability coverage, to afford protection with respect to personal injury, death or property damage of not less than Two Million Dollars ($2,000,000.00) per occurrence combined single limit/Three Million Dollars ($3,000,000.00) general aggregate (but not less than $3,000,000.00 per location aggregate). |
| (f) | umbrella excess liability insurance, on an occurrence basis, that applies in excess of the commercial general liability, automobile liability, aircraft and watercraft liability, professional errors & omissions insurance and employer’s liability insurance described above, having limits of not less than (i) $10,000,000 per occurrence, and (ii) 10,000,000 for the annual aggregate. These limits shall be in addition to and not including those stated for the underlying commercial general liability, automobile liability, aircraft and watercraft liability, professional errors & omissions insurance and employer’s liability insurance required herein. Such excess liability policy shall name Owner as additional insured. |
43.2 | Where a claim is paid by the insurer in respect of losses for which coverage is provided under Section 43.1, theContractorshall be responsible for the deductibles relating to insurance proceeds under the insurance required, |
43.3 | TheContractorshall, and shall ensure that itsSubcontractorsshall: |
| (a) | provide theOwnerwith certificates of insurance for the policies described in Section 43.1 within 15Work Daysof written notice of award of theContractor prior to the commencement of theWork, whichever is earlier, and certificates of insurance evidencing renewal of these policies no fewer that 30Work Daysprior to their expiry date where such policies expire prior toFunctional Completion; |
EPC Contract
Page 41 of 47
| (b) | place all policies with insurers which are licensed to provide insurance in Ohio with an A.M. Best rating no less than A+, and in a form acceptable to theOwner; |
| (c) | ensure that such policies provide for at least 30 days prior written notice to theOwnerof cancellation or change that is material to theContract; |
| (d) | with the exception of the insurance as required by Section 43.1(c), ensure that all insurance provided by theContractorand itsSubcontractorspursuant to Section 43.1 is primary and non-contributory with, or in excess of, any other insurance carried by theOwner; |
| (e) | ensure that theOwneris added as an additional insured with respect to the policies of insurance required under Sections 43.1(e) and 43.1(f), as its interests may appear; and |
| (f) | require the waiver of subrogation in favor of theOwner, its officers, directors, employees, consultants and agents described in Section 42.7 above be included with respect to the insurance coverage required under Section 43.1(d). |
43.4 | If theContractoror itsSubcontractorsfail to furnish theOwnerwith a certificate of insurance for each policy required to be obtained and continually carried, or if after furnishing the certificates of insurance, the policies lapse, are cancelled, or are materially changed, then in every case theOwnermay, but shall not be obligated to, obtain and maintain such insurance in the name of theContractoror anySubcontractor.The cost thereof (includingSubcontractor’sinsurance costs) shall be payable by theContractorto theOwneron demand, and theOwnermay at its election deduct the cost from any monies which are due or may become due to theContractor. |
43.5 | Neither the providing of insurance by theContractorin accordance with the requirements of this Article 43 - Insurance Provided by Contractor, nor the insolvency, bankruptcy, or failure of any insurance company to pay any claim shall be held to relieve theContractorfrom any other provisions of theContractwith respect to liability of theContractor,or otherwise. |
ARTICLE 44 - Insurance Provided by Owner
44.1 | TheOwnershall obtain and, during the progress of theWork,maintain in force the policies of insurance described in this Article 44 - Insurance Provided by Owner, with theOwneras named insured. The actual policies of insurance may be examined by theContractorupon request to theOwner.This insurance applies only to theWorkperformed in connection with theContract: |
| (a) | Property insurance written on a builder’s risk “all-risk” or equivalent policy form in the amount of theCompensation, plus value of subsequentContract modifications and cost of materials supplied or installed by others, comprising total value |
EPC Contract
Page 42 of 47
| for the entireWorkat the site on a replacement cost basis without optional deductibles. Such property insurance shall be maintained, unless otherwise provided in thisContractor otherwise agreed in writing by all persons and entities who are beneficiaries of such insurance, until no person or entity other than theOwnerhas an insurable interest in theWork. |
ARTICLE 45 - Independent Contractor
45.1 | For the purposes of theContractand theWork,theContractorshall be an independent contractor and not the agent or employee of theOwner. |
45.2 | All persons employed or retained by theContractorin connection with the performance of its obligations shall be its employees or those of itsSubcontractors, as the case may be, and not the employees or agents of theOwnerin any respect. |
45.3 | TheContractorshall indemnify and hold harmless theOwner, against all claims, demands, losses, damages, expenses, actions and proceedings whatsoever, including legal fees, which may be incurred by theOwneras a result of any determination by any tribunal or court that any personnel provided by theContractorpursuant to the terms of thisContractare for any purposes agents or employees of theOwner. |
45.4 | TheContractorshall have no authority whatsoever to make any statement, representation or commitment of any kind, or to take any action, which may be binding on theOwner. |
ARTICLE 46 - Conflict of Interest
46.1 | TheContractorshall exercise reasonable care and diligence to prevent any actions or conditions which could result in a conflict with theOwner’sbest interests. This obligation shall apply to the activities of theContractorand itsSubcontractorsand their respective employees and agents, in their relations or dealings with the employees of theOwnerand their families, and other third parties, arising from theContractor the performance of theWork.The efforts made by theContractorin this regard shall include, but shall not be limited to, establishing reasonable precautions to preventSubcontractorsand their respective employees from offering, or providing entertainment, gifts, loans, payments or other considerations to theOwner’semployees, consultants and agents or their family members.Ownershall establish reasonable precautions to prevent its employees from offering, or providing entertainment, gifts, loans, payments or other considerations to theContractoror anySubcontractoror their respective employees, consultants and agents or their family members. |
ARTICLE 47 - Audit Access
47.1 | TheContractorshall preserve theRecordsin good order during theContract Timeand for a period of three (3) years thereafter. |
EPC Contract
Page 43 of 47
47.2 | TheContractorshall permit authorized representatives of theOwnerto review theRecordsat all reasonable times during theContract Time,and for a period of two years thereafter for the purposes of: |
| (a) | determining theContractor’scompliance with all of the terms of theContract,including, but not limited to: |
| (i) | Article 13 - Changes and Article 32 - Delays; and |
| (b) | verifying of allWorkperformed and all reimbursable costs and other charges payable under theContract. |
47.3 | Where theCompensationis not on a cost reimbursable basis, theContractormay black out any information in theRecordsrelating to price before access is given to theOwner. |
ARTICLE 48 - Representatives and Notices
48.1 | TheOwner’s Representativeis Fred Sansom. TheOwner’s Representativehas the authority to bind theOwneron all matters relating to theWorkand theContract,and all communications to or with theOwner’s Representativeshall be deemed to be communications to or with theOwner. |
48.2 | Contractor’s Representativeis Jeff Syed. TheContractorshall not change theContractor’s Representative,except with the prior approval of theOwner.TheContractor’s Representativehas the authority to bind theContractoron all matters relating to theWorkand theContract,and all communications to or withContractor’s Representativeshall be deemed to be communications to or with theContractor. |
48.3 | Unless otherwise specifically indicated in theContract,all notices, approvals, consents, authorizations and other communications required or permitted pursuant to theContract,shall be in writing and shall be communicated to theContractor’s Representativeor theOwner’s Representative,as the case may be, and shall be delivered by personal delivery, overnight courier or facsimile to the parties at the addresses and facsimile numbers shown below: |
| | | | |
(a) | | Contractor: | | |
| | |
| | Address: | | 200 East Randolph Drive |
| | | | Chicago, IL 60601 |
| | Attention: | | |
| | Fax: | | 312-861-6335 |
EPC Contract
Page 44 of 47
| | | | |
(b) | | Owner: | | |
| | |
| | Address: | | 3431 Yankee Road |
| | | | Middletown, OH 45044 |
| | |
| | Attention: | | Fred Sansom |
| | Fax: | | |
| |
| | With a copy to: |
| | |
| | Address: | | One Quaker Park |
| | | | 901 Hector Street |
| | | | Conshohocken, PA 19428 |
| | Attention: | | Robert Traub, Esq. |
| | Fax: | | 610-832-4494 |
48.4 | Either party may change its contact information for the purposes of Section 48.3 by providing the other party with 10 days notice of such a change. |
48.5 | Invoices and all supporting documentation shall be mailed or delivered to the address shown below: |
| | | | |
| | Address: | | 3431 Yankee Road |
| | | | Middletown, OH 45044 |
| | |
| | Attention: | | Fred Sansom |
| | Fax: | | |
48.6 | E-mail may be used for communication between the parties, but e-mail shall not be used for the communication of a notice which is prescribed by theContract. |
ARTICLE 49 - General
49.1 | No failure or delay on the part of either party in exercising any right, power or privilege hereunder shall operate as a waiver thereof. |
49.2 | No waiver of any right, power or privilege by a party shall limit or affect that party’s rights with respect to any breach of theContractby the other party. |
49.3 | Each of the parties hereto shall execute such further documents and give such further assurances as are required to give effect to theContract. |
49.4 | If a court of competent jurisdiction determines that any provision of thisContractis invalid or unenforceable, such determination shall not affect the validity or enforceability of the remaining provisions of theContract. |
EPC Contract
Page 45 of 47
49.5 | All of the covenants and agreements herein contained on the part of either party shall apply and enure to the benefit of and be binding upon their respective legal representatives, successors and assigns. |
49.6 | Each of the parties hereby represents and warrants that it has the power and authority to enter into theContractand to perform all of its obligations hereunder. |
49.7 | TheContractconstitutes the entire agreement between the parties with respect to theWorkand supersedes and replaces all previous communications, representations and agreements, either written or verbal. |
49.8 | ThisContractshall be governed by and construed in accordance with the laws of the State of Ohio. |
49.9 | The execution of thisContractmay be effected by facsimile or other electronically transmitted signatures (such as by electronic scanning and e-mail), all of which shall be treated as originals; provided, however, that the party receiving a document with an electronic signature may, by notice to the other, require the prompt delivery of an original signature to evidence and confirm the delivery of the electronic signature. ThisContractmay be executed in as many counterparts as may be required. It shall not be necessary that the signature on behalf of both parties hereto appear on each counterpart hereof. All counterparts hereof shall collectively constitute a single agreement. |
[BALANCE OF PAGE INTENTIONALLY BLANK]
EPC Contract
Page 46 of 47
49.10 | ThisContractshall be executed by the parties, or their representatives, in person with original signatures, but may be executed in counterpart. Subsequent documents may be executed by the parties, or their representatives, and such execution may be by way of facsimile or electronic transfer. |
TO EVIDENCE THEIR AGREEMENT, the parties have executed and delivered thisContract,by their duly authorized officers, as of the effective date indicated on the first page.
| | |
Owner: | | QUAKER CHEMICAL CORPORATION |
| |
By: | | /s/ Michael F. Barry |
| | Name: Michael F. Barry |
[apply corporate seal]
| | |
Contractor: | | FMC TECHNOLOGIES, INC. |
| |
By: | | /s/ Edward Barth |
| | Name: Edward Barth |
[apply corporate seal]
EPC Contract
Page 47 of 47
Appendix A — Scope of Work
FMC Scope of Work for the
Middletown Plant Expansion
Turnkey Project
May, 2008
TABLE OF CONTENTS
| | | | |
1 | | Contractor (FMC) Scope of Supply and Services | | 3 |
| | 1.1 Process Equipment | | 3 |
| | 1.2 Building | | 6 |
| | 1.3 Utilities | | 6 |
| | 1.4 Miscellaneous | | 9 |
| | 1.5 Clarifications | | 11 |
| | |
2 | | Owner (Quaker) Scope of Supply and Services | | 13 |
| | |
3 | | Owner’s Specified Materials and Subcontractors | | 14 |
| | 3.1 Process Equipment | | 14 |
| | 3.2 Building | | 15 |
| | 3.3 Utilities | | 15 |
| | |
4 | | Execution Plan | | 16 |
| | 4.1 Execution Plan For Engineering and Procurement Work | | 16 |
| | 4.2 Execution Plan For Construction Work | | 20 |
| | 4.3 Inspection and Test Plan | | 22 |
| | 4.4 Project Schedule | | 22 |
| | 4.5 Milestones | | 22 |
| | 4.6 Health and Environmental Protection | | 22 |
| | 4.7 Project Team and Key Personnel | | 23 |
| | |
5 | | Performance Tests and Guarantees | | 23 |
| | 5.1 Measuring Accuracy | | 23 |
| | 5.2 Contamination | | 23 |
| | 5.3 Homogeneity | | 24 |
| | 5.4 Cooling Tower | | 24 |
| | 5.5 Steam Boilers | | 24 |
| | 5.6 Hot Oil Heaters | | 24 |
| | 5.7 Air Compressor | | 24 |
| | 5.8 Floor Scales | | 24 |
| | 5.9 Water Softener | | 24 |
| | 5.10 Pumps | | 25 |
| | 5.11 Controls and Instrumentation | | 25 |
| | 5.12 Drum Filling Line | | 25 |
| | 5.13 Pigg able Lines | | 25 |
| | |
6 | | Functional Completion | | 26 |
| | |
7 | | Attachments | | 26 |
| | 7.1 Process Drawings | | 26 |
| | 7.2 General Arrangement | | 26 |
| | 7.3 Preliminary Project Schedule | | 26 |
| | 7.4 BULK TANKS details 011508.xls | | 26 |
Page 2 of 26
1 | Contractor (FMC) Scope of Supply and Services |
| 1.1.1 | Blenders and Reactors |
| • | | Supply and install four 6,000-gallon automated blender systems, including: |
| • | | 6000 gallon, 304 SS, cone bottom, baffled, internal polish finish, two section half-pipe jacket (150 psig rated), insulated, atm. tank. |
| • | | Weigh cells (three cells) |
| • | | Steam and cooling tower water piped to jacket |
| • | | Blackmer (or equivalent) product/recirculation pump with VFD |
| • | | SS Product bag-style filter |
| • | | SS product recirculation line and “pigged” transfer line to storage and truck loading |
| • | | Instruments, gauges and controls |
| • | | 5’ x 5’ pallet scale for weighing raw materials into blender, installed flush to floor level. |
| • | | Sodium Nitrite Screw Conveyor for unloading supersacks into BBV-01–water based blender |
| • | | Supply and install one 4,500-gallon automated blender system, including: |
| • | | 4500 gallon, 304 SS, cone bottom, baffled, internal polish finish, two section half-pipe jacket (150 psig rated), insulated, atm. tank. |
| • | | Weigh cells (three cells) |
| • | | Steam and cooling tower water piped to jacket |
| • | | Blackmer (or equivalent) product/recirculation pump with VFD |
| • | | SS Product bag-style filter |
| • | | SS product recirculation line and “pigged” transfer line to storage and truck loading |
| • | | Instruments, gauges and controls |
| • | | 5’ x 5’ pallet scale for weighing raw materials into blender, installed flush to floor level. |
| • | | Supply and install one 1,100-gallon manual blender system, including: |
| • | | 1,100 gallon, 304 SS, cone bottom, baffled, internal polish finish, two section half-pipe jacket (150 psig rated), insulated, atm. tank. |
| • | | Steam and cooling tower water piped to jacket, automated heating and cooling |
| • | | Blackmer (or equivalent) product/recirculation pump with VFD |
| • | | SS Product bag-style filter |
| • | | SS product recirculation line and line to scale for local packaging |
| • | | Instruments, gauges and controls |
| • | | 5’ x 5’ pallet scale for weighing raw materials into blender, installed flush to floor level. |
| • | | Supply and install one 350-gallon manual blender system, including: |
| • | | 350 gallon, 304 SS, cone bottom, baffled, internal polish finish, two section half-pipe jacket (150 psig rated), insulated, atm. Tank. |
Page 3 of 26
| • | | Steam and cooling tower water piped to jacket, automated heating and cooling |
| • | | Blackmer (or equivalent) product/recirculation pump with VFD |
| • | | Product bag-style filter |
| • | | SS product recirculation line and line to scale for local packaging |
| • | | Instruments, gauges and controls |
| • | | Pallet scale for weighing raw materials into blender, installed flush to floor. |
| • | | Supply and install two 7,500-gallon automated Reactor systems, including: |
| • | | 7500 gallon, 304 SS, dish bottom, baffled, internal polish finish, three section half-pipe jacket (100 psig @ 550 F rated), insulated, 70 psig/FV rated tank. |
| • | | 3’ diameter packed 304 SS fractionation column with structured packing |
| • | | Nash Liquid Ring Vacuum pump (or equivalent) with oil seal with capacity to achieve 26 in HG. Absolute on reactor system. |
| • | | Condensate receiver and pump - SS |
| • | | Weigh cells (three cells) |
| • | | SS inlet manifold with connections for bulk raw materials |
| • | | Line for unloading from tank trucks direct to reactors |
| • | | Hot Oil piped to jacket |
| • | | Oil cooler using cooling tower water - CS |
| • | | Product/recirculation pump - SS |
| • | | Product cooler using cooling tower water - SS |
| • | | SS Product bag-style filter |
| • | | SS product recirculation line and “pigged” transfer line to Finishing tank, packaging, bulk storage and truck loading |
| • | | Instruments, gauges and controls |
| • | | 5’ x 5’ pallet scale for weighing raw materials into blender installed flush with floor level. |
| • | | Mechanism for opening and closing manway lid |
| • | | Supply and install one 9,000-gallon automated blender system, including: |
| • | | 9000 gallon, 304 SS, cone bottom, baffled, internal polish finish, two section half-pipe jacket (150 psig rated), insulated, atm. tank. |
| • | | Weigh cells (three cells) |
| • | | SS inlet manifold with connections for bulk raw |
| • | | Product/recirculation pump-SS |
| • | | Product cooler piped with cooling tower water-SS |
| • | | Pressure Leaf Filter-SS |
| • | | SS product recirculation line and “pigged” transfer line to packaging, storage and truck loading |
| • | | Instruments, gauges and controls |
Page 4 of 26
| • | | 5’ x 5’ pallet scale for weighing raw materials into blender, installed flush to floor level. |
| • | | One 50 drum per hour drum filling line for reactors and finishing tank, with manual roller |
| • | | The drum filler has one pallet of in feed conveyor and one pallet of outflow conveyor. Both are manual. Filler will handle four drums on a pallet or an IBC. |
| • | | Rework existing bulk storage tanks: |
| • | | Run existing tank level signals to new control system. |
| • | | Tank 35 — new welded carbon steel floor. It is assumed that the sidewalls are in good condition. Repair or reinforcement of the sidewalls, if necessary, is not included in this scope. |
| • | | Add level transmitters to thirteen of the existing storage tanks |
| • | | All existing storage tanks with heating coils need new temperature transmitters |
| • | | Run lines from tank to hose board inside building |
| • | | Add heating coils, steam & condensate pipe, insulation (of pipe and tanks) and controls to 8 tanks- 7 new, 1 replacement (Tank #24) |
| • | | Add temperature element to 7 existing tanks that get new heating coils |
| • | | Cleaning and associated logistics (including waste disposal) of the 8 existing tanks is not included in this scope |
| • | | Two grease tanks (OS-2 and OS-8) get side agitators and bag filters for truck unloading |
| • | | Each line from a bulk tank to the production area (hose board) will have an automatic valve and a dry break disconnect. |
| • | | Purchase and install 9 new storage tanks (UL-142 construction) |
| • | | Existing tank farm berm will be extended to contain the additional |
| • | | Tanks foundations (concrete pads), catwalk and ladders will be provided. Fall protection is not included. |
| • | | Steam coils, heating controls, steam and condensate piping. |
| • | | Insulation of piping and tanks |
| • | | Two of these tanks will be installed in new process and storage building. These tanks will also have containment, catwalk and access ladders. |
1.1.4 | Plant Control System |
| • | | Plant control system to operate the plant in a safe and efficient manner including: |
| • | | Hardware and software needed to automate the following processes as indicated in P&IDs |
| • | | Truck loading/unloading |
| • | | Blender loading, sequencing, recirculation, heating, cooling, unloading |
| • | | Reactor loading, sequencing, heating, cooling, vacuum, unloading |
| • | | Finishing tank loading, sequencing, filtering, heating, cooling, unloading |
| • | | Drum/bin filling for reactor area only |
Page 5 of 26
| • | | Caustic process operation |
| • | | Utilities operation and monitoring |
| • | | Report generation of batch history, tank inventories, alarms, etc. |
| • | | Software safety interlocks |
| • | | 3 Remote HMI’s – 2 in new building, 1 in truck unloading |
| • | | Training of two Owner personnel to maintain hardware and modify programming. |
| • | | Participate in safety review of software when complete. |
| 1.2.1 | New Blend and Storage Building |
| • | | Provide and construct a 12,000 sq ft Butler style building and foundation |
| • | | Roof will be 40 feet over blenders and reactors |
| • | | Building will be built at same floor elevation as existing building |
| • | | One manual overhead door at west end of building with ramp to grade for forklift egress from new building. Make provisions for owner-installed 40’ x 40’ concrete pad with containment curb to west of building. |
| • | | Mezzanine will be designed for to handle 42”x42” pallets weighing 2,200 lbs at each vessel |
| • | | The mezzanine will be 15ft above grade (I thought this was no 16’??) |
| • | | The mezzanine will have checker plate construction with non-slip coating |
| • | | Fork truck safety gates for loading materials to balcony |
| • | | Three docks (with dock levelers, and seals) relocated from the existing loading area. |
The old location for the dock levelers will be filled in level with existing floor.
| • | | Roof and/or walls to have sky-light panels |
| • | | Steam heated drum ovens to maintain 32 drums (2 x 16 arrangement) on skids at 160 F. |
| • | | Building structures designed in accordance with ASCE-7 guidelines, specifically addressing local factors for occupancy, weather, and terrain. |
| • | | Building wall construction utilizes noncombustible materials. |
| • | | Two stairway for access to balcony. |
| • | | New building will be designed to be kept at 65 F in winter |
| • | | The link between the old and new building will be enclosed to keep the weather out with a fire door at one end |
| • | | New dock locks will need to be purchased when docks are moved to west end of new building. |
| • | | Supply and Install a Cooling Tower (pad mounted) outside the production building. |
| • | | Evapco USS-112-312 1200 USGPM from 95F to 85F WBT, or equivalent |
| • | | Cooling tower should have two fans and two pumps |
Page 6 of 26
| • | | Supply and Install a Scrubber: |
| • | | Ceilcote EVS-16 venturi scrubber, or equivalent |
| • | | The scrubber equipment includes: scrubber, pump, piping, duct, stack, controls, panel, feed system, sump heater, and skid. |
| • | | Supply and install 16” diameter, spiral wound stainless steel duct (or equivalent) from scrubber to process area. Duct upstream of reactors (i.e. will not be exposed to reactors) can be made of FRP of an appropriate resin, instead of stainless steel. |
| • | | Supply and install branches from 16” scrubber header to process tanks (blenders and reactors). |
| • | | Supply pad with containment walls on north side of production building for scrubber system |
| • | | Pipe up water supply, power, signal wires (scrubber to main plant process control system) and blow down line to waste water tank. |
| • | | Extend the scrubber header to the drum filling line and all drum unloading scales. Header to be 6-inch frp with 3” drops |
| • | | Scrubber line needs to be run to two storage tanks located inside building. |
| • | | Upgrade burners on existing boilers from 100 HP to 200 HP, to meet steam demands of plant. |
| • | | Determine if a new gas line is required from main to supply new boilers and hot oil equipment. |
| • | | Provide collection and return of all steam condensate from steam consuming equipment in plant. |
| • | | Steam boiler capacity expansion includes any needed ancillary equipment that also needs additional capacity |
| • | | A new gas line is included in the scope of work |
| • | | New burners should give better efficiency than old burners (as much as 12%) |
| • | | Provide two (2) gas-fired hot oil heaters (GTS DH-V-13/40, 4.0 MM BTU/hr. or equivalent) |
| • | | Install heaters on pad outside production building with containment to hold all of hot oil liquid. |
| • | | Provide all connections to gas supply, and process connections |
| • | | Install controls and run signals to main plant process control system. |
| • | | Supply initial fill of Therminol heat transfer fluid. |
| • | | New oil heaters must comply with GE GAP guidelines |
| • | | Expand air compressor & air dryer capacity, one new 1,000 cfm air compressor with one receiver and one regenerative dryer sized for the application |
Page 7 of 26
| • | | Air compressor/dryer system will not exceed 80 db noise limits outside compressor shed. |
| • | | Dryer will provide -40 F dew point air with system operating at full air flow, |
| • | | Install new softwater system including surge tank and pump to supply boilers and blenders |
| • | | Soft water system will have a 1,500 gallon surge tank and 100 gpm pump to feed boiler and blenders. Automated level and pump controls will be provided. |
| • | | CONTRACTOR will provide a 1,500 gallon city water surge tank and 100 gpm pump as well for feeding blenders. Automated level and pump controls will be provided. |
| • | | Expand electrical supply to include a new 1600 amp, 480/277 volt service. |
| • | | Electric utility will provide main transformer. CONTRACTOR will provide main transformer pad, and wiring from pole to transformer. |
| • | | Provide all needed motor controls, fuses, breakers, local disconnects, etc. as needed and as required by code |
| • | | Wiring will be run in cable tray and/or conduit |
| • | | All electrical design work will comply with NFPA 70E arc flash requirements. |
| • | | Relocate existing and provide pole mounted lighting to properly light all outdoor areas of facility for night operations |
| • | | Provide normal area lighting in new blending and storage building |
| • | | Modify existing lighting, if required, in areas modified in project (tank farm, truck loadout, rail loadout, existing production warehouse area) to maintain good work environment. |
| • | | Provide emergency lighting and emergency exit lights in blending and storage building to meet code and allow for safe exit during power outage. |
Page 8 of 26
| • | | Participate in safety review of plant/process design and also of plant during commissioning |
| • | | Provide hard copy and electronic versions of final as-built drawings after project completion |
| • | | Provide equipment files after job completion |
| • | | Apply for (or assist Owner in applying for) all required permits and comply with all regulations related to: |
| • | | Environmental permit to install (Owner will apply for this) |
| • | | Ohio fire code (Owner will apply for storage tank licenses as needed) |
| • | | GE GAP building guidelines |
| • | | Middletown building codes |
| • | | State of Ohio building codes |
| • | | CONTRACTOR will commission and start up all equipment, with the assistance of Owner personnel. |
| • | | Provide training to Owner personnel for control system and maintenance of new instrumentation and equipment |
| • | | Expand asphalt parking lot by 25 spaces as per drawing, |
| • | | Add new truck/car exit from south side of plant property |
| • | | Add two lighting poles for this area |
| • | | Add 5 Hot Water stations in new production area |
| • | | Security gate and fencing: |
| • | | Install manual operated security gates at plant entrance and exit |
| • | | Repair/replace any fencing disturbed by construction process. |
| • | | Road around plant will be moved as needed for new building and graded to retain swale along fence line |
| • | | Demo old equipment once new plant operational and all production has been moved out of old blenders |
| • | | Demo and remove old plant piping |
| • | | Demo and remove old blenders |
| • | | Demo and remove old storage racks |
Page 9 of 26
| • | | Demo and repair old production area floor |
| • | | Note: caustic production process remains as is. |
| • | | Paint all appropriate exposed metal for new installaion |
| • | | Safety Showers / Eye washes |
| • | | Install as per OSHA regulations (approx every 75’ in production, warehouse, tankfarm and truckloading). Freeze protection is included |
| • | | Remove truck scale from truck loading area, repair pad to make smooth. |
| • | | Install truck scale & controls in pit (install flush to ground) between office building and parking lot |
| • | | Install remote controls/readout of scale in shipping office, camera not included |
| • | | Underground cabling for relocated truck weigh scale shall be in PVC pipe |
| • | | Have scale recalibrated once it is relocated. |
| • | | Truck loading/unloading platform: |
| • | | CONTRACTOR will remove existing tank truck access platform and provide an adequate (meets OSHA weight limits) trolly rail over the four truck loading/unloading locations to facilitate owner-provided fall protection. |
| • | | Install all cabling as required for plant control system |
| • | | Provide and install all instrumentation, valves and gauging as indicated in P&IDs and required for operation of CONTRACTOR supplied equipment |
| • | | Provide appropriate training of two Owner personnel to maintain hardware and modify programming. |
| • | | CONTRACTOR will provide storm water retention swales and trenches as necessary for complying with Middletown, OH permit requirement |
Page 10 of 26
| 1.5.1 | Clarifications on Contractor Scope |
| 1. | Offer does not include fire protection for new blend and storage building |
| 2. | Offer does not include insulation and heat tracing for piggable piping except for all launching and receiving stations. |
| 3. | Valves and instruments on existing tanks will be reused as is. |
| 4. | Existing valves, traps and strainers on the steam and condensate branches to existing coils will remain as is. Mains are understood to be reused as is. CONTRACTOR will install branches to 7 existing tanks. |
| 5. | The floor in one tank will be replaced; any repairs to sidewalls would be done at an additional cost. |
| 6. | The reactor system design, steam requirements, and hot oil requirements have been specified by the OWNER. |
Civil
| a) | Following assumptions relating to civil work at plant site were made: |
| • | | Soil at the site is free of any Toxic Contamination and/or any other environmentally unsafe chemical substances, and any under ground obstacles that may interfere with excavation of the site. CONTRACTOR price does not include any costs associated with special handling and disposal of such unsafe soils. |
| • | | No Seismic Zone requirements or provisions are included in the CONTRACTOR price. |
| • | | Since the upgrading work will be constructed within the existing plant facility, no allowance is included for site survey and coordinates verification. CONTRACTOR assumes this data is available at the plant. |
| b) | The Geotechnical Study performed by H.C. Nutting Co. in August 2006, was used to prepare the quote for the civil work. |
| c) | Owner shall, at its own expense, apply for and obtain any required environmental permits from the proper authorities. CONTRACTOR role shall be limited to assisting owner in assembling technical information on an as needed basis for obtaining permits. |
| d) | Owner is responsible for any underground obstructions not on the drawings provided to CONTRACTOR |
Miscellaneous
| e) | Owner will pay for power used during the total construction period. The contractor will pay any costs associated with wiring, transformer, disconnects, etc. to provide such power. |
Page 11 of 26
| f) | The tie-in to existing facilities and demolition and/or reconstruction of existing system will cause operation interruptions. The CONTRACTOR price does not include any temporary facilities required to avoid operation interruptions. It is assumed that the production activities will be planned and scheduled to make existing system available for modification/upgrade/tie-ins etc. based on a tie in schedule from the on-site Construction Manager. Any changes to the provided schedule must be made no less than two working days prior to the tie in activities. |
| g) | All raw materials required to commission and test the blending system shall be provided by Owner at no charge to CONTRACTOR. |
| h) | References to “CONTRACTOR” throughout this document shall mean CONTRACTOR or its authorized subcontractors unless specifically stated otherwise. |
| i) | Paint and other Material at the existing site that is to be dismantled, removed and/or handled by CONTRACTOR and its subcontractor will be free of asbestos. |
| j) | All tanks are UL rated. |
Page 12 of 26
2 | Owner (Quaker) Scope of Supply and Services |
| • | | Railcar spill containment: |
| • | | Apply appropriate resilient labeling to all piping, controls and equipment. |
| • | | Install appropriate plant direction signs, including truck entrance,/exit, visitor, employee, etc. |
| • | | Paint yellow strips around safety equipment |
| • | | Paint yellow row strips in all warehouse areas to direct pallet storage. |
| • | | Hang fire extinguishers as required to meet regulations |
| • | | Railcar Loading Fall Protection: |
| • | | Install fall protection over rail car unloading area. |
| • | | Install main runs of telephone and computer cabling from existing hub to new offices, rooms. |
| • | | Owner will be responsible for final terminations for phone and cable NOT associated with plant control system. |
| • | | Participate in safety review of plant during commissioning |
| • | | Provide resources to commission all equipment and assist in start up of the facility |
| • | | Environmental permit to install |
| • | | Clean storage tanks and process equipment as required for construction activities. |
Page 13 of 26
| • | | Related to the 12,000 sq ft Butler style building and foundation, If the owner desires it, owner will provide.: |
| • | | Lunchroom/training room with HVAC, area to be separated by curtain, tables, free standing chairs, cabinets, power, lighting, exterior windows, phone, sink, computer driven projector in ceiling, screen, white boards, etc. |
| • | | Control room with adequate utilities for main process control system, HVAC, CCTV security and gate controls, work stations, windows to plant production area |
| • | | Laboratory with adequate utilities for sinks, wet testing, 2 work stations, HVAC, one walled off office, sample retain area, laboratory vent hoods, cabinets and work benches for chemical processing |
| • | | Locker rooms. Women’s for 20 people, Men’s for 70 people. HVAC, Lockers, showers, benches, sinks, toilets, mirrors, etc. |
| • | | Maintenance area with adequate utilities storage shelves and work benches as normally used in a maintenance area. |
| • | | Owner will provide office furniture, including desks, chairs, file cabinets, partitions. Contractor to supply all else. |
| • | | Install fire water system in new building and modify protection in old building as required for occupancy permit. |
| • | | Install second fire water main and tie into existing to create fire “loop” per drawings if additional capacity is needed. |
| • | | Move/install fire hydrants per drawings |
| • | | Provide normal alarms and controls as required by code and consistent with existing. |
3 | Owner’s Specified Materials and Subcontractors |
The size and quantity for the following equipment have been specified by the Owner:
| 3.1.1 | Blenders and Reactors |
| • | | Four 6,000-gallon automated blender systems |
| • | | One 4,500-gallon automated blender system, |
| • | | One 1,100-gallon manual blender system, |
| • | | One 350-gallon manual blender system, |
| • | | Two 7,500-gallon automated Reactor systems, |
| • | | One 9,000-gallon automated blender system. |
| • | | One 50 drum per hour drum/IBC filling line for reactors and finishing tank, with manual roller conveyors. |
Page 14 of 26
| • | | Rework existing bulk storage tanks |
| • | | 9 new storage tanks (UL-142 construction) |
| 3.2.1 | New Blend and Storage Building |
| • | | 12,000 sq ft Butler style building |
| • | | delete this. FMC sized cooling tower. |
| • | | A Scrubber - Ceilcote EVS-16 venturi scrubber, or equivalent |
| • | | Steam Boiler - Upgrade burners on existing boilers from 100 HP to 200 HP, to meet steam demands of plant. |
| • | | Two (2) gas-fired hot oil heaters (GTS DH-V-13/40, 4.0 MM BTU/hr. or equivalent) |
| • | | remove this. FMC sized the air compressor. |
| • | | A 8,000 gal per hour new softwater system including surge tank and pump |
Page 15 of 26
CONTRACTOR proposes to execute the design and engineering, procurement, construction, commissioning, startup, and training of the Middletown Plant Expansion Project on a Turnkey basis as described below:
CONTRACTOR shall perform Process and Detail Engineering, and Procurement. CONTRACTOR shall supply all process equipment and material listed in Section 2 of this scope of work. This process & detailed design work and procurement activities can be commenced immediately upon receiving OWNER authorization.
CONTRACTOR shall modify the existing facility piping, electrical tie-ins, equipment setup, erection, installation, and other site activities associated with this expansion.
4.1 Execution Plan For Engineering and Procurement Work
CONTRACTOR proposes to execute this phase of the Project using an experienced project task force. An organization chart for the proposed task force is attached at the end of this section. The task force will be working under the supervision of CONTRACTOR’s project manager to execute the following project tasks:
| 4.1.1 | Engineering Services |
The Process Design task will be performed at CONTRACTOR’s home office in Chicago utilizing highly experienced engineers, designers, and specialists. The Detailed Engineering will be performed by the project team under the supervision of CONTRACTOR. The responsibility of these groups shall be to develop the following items:
| • | | perform all process design calculations and equipment selection and sizing |
| • | | prepare all process design drawing, operating manuals, and plant control philosophy |
| • | | prepare all instrument and equipment specifications |
| • | | prepare all construction drawings and specifications, and installation details |
| • | | Prepare all construction & installation package, issue package for bids and review bid prices. |
| • | | Prepare all instrument and/or equipment purchase requisitions |
| • | | Review all vendor drawings and data |
| 4.1.2 | Procurement Services |
Procurement of process equipment will be performed using experienced CONTRACTOR home office staff in Chicago. CONTRACTOR utilizes the services of several freight forwarding organizations, which will be responsible for packaging and shipping of all equipment to the jobsite. The procurement activities for this project shall be performed under the direction of CONTRACTOR’s Procurement Director and the Project Manager. The responsibilities of this procurement group include(s):
| • | | Prepare quotation and bid documents and review with owner. |
| • | | Solicit suppliers’ quotations |
| • | | Prepare purchase requisitions and review with owner. |
| • | | Perform expediting, inspection, freight forwarding and receiving of equipment at the site |
| • | | Receive, organize and coordinate distribution of all vendor data and drawing submittals |
| • | | Solicit subcontractor installation quotations |
Page 16 of 26
The Procurement Plan establishes critical items and purchasing procedures. It utilizes engineering input from equipment and control lists and integrated project schedules to define the equipment and material-purchasing schedule.
Major milestone activities included in CONTRACTOR’s Procurement Plan are:
| • | | Supplier’s list is prepared for equipment and materials. This list is prepared early in the project as part of the planning cycle. It utilizes area resource and surveys of supplier capabilities. |
| • | | RFQ’s (Request for Quotations) will be prepared by Engineering and Procurement Team (if required) and issued by the Purchasing Group. They will be date-controlled in conjunction with the project schedule. |
| • | | Quotation summaries will be technically reviewed by Engineering, commercially reviewed by Purchasing, and joint approvals are required prior to executing the purchase. |
The Procurement Plan identifies critical equipment needing special expediting and tracking. Expediting begins with contacting the vendor to confirm that he has entered the CONTRACTOR order into the vendor’s manufacturing/supply program. Expediting continues with the checking of status of vendor engineering, procurement, manufacturing and shipping. CONTRACTOR expedites the review and return of reviewed vendor drawings and data. Comments from vendor data reviews will be transmitted to the vendor by e-mail and/or via courier. Expediting continues until equipment has been received on site.
Equipment deliveries will generally not be contingent on drawing reviews so the vendor may order critical raw materials as soon as he receives CONTRACTOR’s purchase order.
Expediting of spare parts parallels the expediting of the equipment for which the parts are ordered. Major problems, which cannot be effectively resolved via fax or telephone, may require visit(s) to the vendor’s shop. CONTRACTOR can send copies of all Expediting Reports and shop visits to OWNER.
| 4.1.2.3 | Inspection Prior to Shipment |
OWNER may wish to inspect equipment supplied by CONTRACTOR. Inspection schedule will be published by CONTRACTOR. OWNER must notify CONTRACTOR two weeks in advance regarding time, date and names of OWNER personnel who would like to witness the shop inspection. OWNER will pay the cost of trips made by OWNER personnel.
CONTRACTOR will develop with OWNER a mutually agreed upon inspection procedure for CONTRACTOR’s scope of supply. This procedure will establish what equipment OWNER would like to inspect, tentative inspection milestones and reporting methods.
CONTRACTOR will submit to OWNER copies of all Inspection Reports within 10 days after receiving the manufacturer’s final report.
All supplied equipment shall be tagged, containerized and shipped to Middletown, OH on CIP basis as part of the project.
Page 17 of 26
| | |
EQUIPMENT | | VENDOR |
MECHANICAL PROCESS EQUIPMENT |
Centrifugal Pumps | | Durco Goulds |
| |
PD Pumps | | Viking Pump Blackmer Plenty Pump (with owner approval) |
| |
Metering Pumps | | Milton Roy Neptune |
| |
Agitators | | Lightnin Chemineer |
| |
Vent Scrubber | | Ceilcote |
| |
Hot Oil System | | Sigma Thermal GTS Fulton Boiler |
| |
Steam Traps | | Armstrong |
| |
Cooling Tower | | BAC Marley Evapco |
| |
Loading Arms | | FMC |
| |
Dry Disconnects | | OPW |
| |
Strainers | | Eaton Sure Flow |
| |
Demisters | | Koch RICSA |
| |
Filters | | FSI Sparkler |
| |
5’x5’Pallet Scale | | Mettler-Toledo Hardy Instruments (with owner approval) |
| |
Air Compressor Systems | | Sullair Quincy Atlas Copco |
| |
Flexible Hose | | Flexible Components Hose Technologies Senior Flexonics |
| |
Spray Nozzles | | BEX Lechler BETE |
Page 18 of 26
| | |
EQUIPMENT | | VENDOR |
FILLING & PACKAGING |
Drum/Tote Filling | | Specialty Equipment |
| | Tri Cal |
| | Velcon |
|
INSTRUMENTATION |
Control Valves | | Neles-Jamesbury |
| |
Air Regulator Valve | | Norgren |
| | ASCO |
| | Control air |
| |
Pressure Regulator Valves | | Fulflo |
| | Fisher Controls |
| | Watts Regulator |
| |
Back Pressure Regulator Valves | | Fulflo |
| | Fisher Controls |
| |
Solenoid Valve | | ASCO |
| | Parker Hannifin |
| |
Level Instruments | | Endress & Hauser |
| | Rosemount |
| | Yokokawa |
| |
Pressure Indicators | | Ashcroft |
| | US Gauge |
| | Weksler |
| |
Temperature Indicators | | Ashcroft |
| | US Gauge |
| | Weksler |
| |
Temperature Transmitters | | Fisher-Rosemount |
| | Endress & Hauser |
| | Yokogawa |
| |
Pressure Transmitters | | Rosemount |
| | Endress & Hauser |
| | Yokogawa |
| |
Positive Displacement Meters | | Brooks Instruments |
| | Smith Meter |
| | Brodie |
CONTRACTOR will supply three sets of operating manuals and user’s guides for all equipment and measuring process units and others within CONTRACTOR’s scope of supply.
Page 19 of 26
CONTRACTOR will provide three sets of installation and maintenance manuals for all equipment within CONTRACTOR’s scope of design supply.
A draft of the manuals for the Plant Control System will be issued to OWNER for review after the Factory Acceptance Test (FAT). Manuals shall be updated and issued at least one month before the facility is commissioned.
4.2 | Execution Plan For Construction Work |
Upon completion of Detail Engineering, CONTRACTOR will issue construction packages including:
| • | | Civil and structural plant modification work |
| • | | Mechanical Package for pipe, pipe support, tie-in, equipment setting and installation |
| • | | Electrical package to install electrical equipment, conduit, cables, cable trays, and instrument cable and wiring. |
CONTRACTOR will send its construction management personnel, which will award Construction Activities. Based on the above the execution plan for the construction work at the site is as follows:
| 4.2.1 | On-Site Construction Management |
On-Site construction of the Project shall be performed by local subcontractor(s), hired by CONTRACTOR, under the supervision of CONTRACTOR’s Construction Manager. The subcontractor duties shall include:
| • | | Obtaining all applicable construction permits. |
| • | | Installation of all furnished Process Equipment. |
| • | | Fabrication and installation of piping systems. |
| • | | Installation of utility piping, as applicable. |
| • | | Installation of electric cable and conduits. |
| • | | Installation of power supply and control wiring cables. |
| • | | Pre-commissioning and commissioning of the facility. |
| • | | On-Site material handling, storage and setting. |
| • | | Develop and administer quality control, safety and environmental site plans. |
| • | | Conduct weekly construction status meetings. |
| • | | Issue monthly progress reports. |
As-Built Drawings will be maintained on work site. The As-Built Drawings are a controlled and complete set of documents upon which the Contractor records each and every instance of differences between the Work as executed and the Work as designed and depicted in the documents issued by the Contractor for Construction Work.
| 4.2.3 | Safety Requirements |
CONTRACTOR will develop, with assistance from OWNER, Site Safety procedures and an orientation program required to meet OWNER’s safety goals. All workers and visitors shall strictly follow the Project Site Safety Plan. Responsibility for administering all safety policies during construction shall rest with CONTRACTOR and its subcontractors.
Page 20 of 26
| 4.2.4 | Temporary Facilities Requirements |
Temporary facilities (i.e., trailer, office, etc.) will be provided by CONTRACTOR’S subcontractors during the construction PHASE. Some large CONTRACTOR equipment, which cannot be stored in a trailer, will require adequate indoor storage space (30 feet x 10 feet) which is to be provided by OWNER. Owner will take reasonable measures to protect the equipment against damage by Quaker activities.
| 4.2.5 | Commissioning Before Functional Completion |
CONTRACTOR will provide technical support services for commissioning, startup and plant operator training of the facility. The commissioning and startup services shall consist of the following:
| • | | Develop commissioning and startup activities schedules and identify manpower required per activity. |
| • | | Develop construction completion checklists and confirm raw materials and spare parts required for plant startup are available. |
| • | | Inspect equipment to ensure that installation and construction activities have been satisfactorily completed by subcontractors. |
| • | | Coordinate on site startup activities with equipment supplier representatives (as required). |
| • | | Witness instrumentation calibration and wiring checkout. |
| • | | Organize and witness dry run for all equipment as well as controls and instrumentation. |
| • | | Witness wet run for the plant and conduct performance verification tests. |
| • | | Conduct performance testing and custody hand over to OWNER personnel. |
| 4.2.6 | Commissioning After Functional Completion |
CONTRACTOR will provide commissioning services following Functional Completion, which will consist of the following activities:
| • | | Demo old equipment once new plant is operational and all production has been moved out of old blenders |
| • | | Demo and remove old plant piping |
| • | | Demo and remove old blenders |
| • | | Demo and remove old storage racks |
| • | | Demo and repair old production area floor |
Operator Training shall consist of the following:
| • | | Conduct no more than four days (32 hours) classroom training for operation personnel prior to commissioning. |
| • | | Conduct hands on training of operators during the commissioning of the plant. |
Page 21 of 26
| • | | Conduct performance tests in accordance with test procedures developed during the detail design to demonstrate the performance guarantee parameters listed in Section 5 of this scope of work. |
4.3 | Inspection and Test Plan |
Contractor will prepare an Inspection and Test Plan and submit to the Owner prior to commissioning of the plant.
A preliminary Project Schedule for this project is attached. The proposed project duration is 15 months after the Contract award. CONTRACTOR will develop a detailed master schedule for the project within four weeks after the Contract Award, to be issued to OWNER for review and comments.
CONTRACTOR’s project scheduling function assists the Project Manager and Client in developing totally integrated engineering, procurement, construction and startup plans for accomplishing time objectives and in implementing these plans through detailed scheduling.
A preliminary schedule for the project is attached.
There will be six major milestones in the project. These are:
| 1. | Preconstruction Activities. |
| 3. | Equipment Order and Delivery. |
| 4. | Site Construction Activities. |
| 6. | Demolition of Existing Piping and Equipment. |
4.6 | Health and Environmental Protection |
OWNER’S health and environment protection standards as well as requirements of local, city and state authorities will be incorporated into the CONTRACTOR execution plan. CONTRACTOR will work very closely with OWNER to ensure that CONTRACTOR has information on the latest state and local requirements.
Page 22 of 26
4.7 | Project Team and Key Personnel |
The Contractor’s Project Team and Key Personnel for the Expansion Project are identified in Appendix I.
5 | Performance Tests and Guarantees |
The blender/reactor weigh cells and in-line blending flow meters will demonstrate the following accuracy by filling blenders with a known amount of water pumped in from a bulk tank using the FMC blender control software and equipment. This will be demonstrated on three consecutive loadings/blendings of not less than 1000 lbs and three consecutive un-loadings of not less than 1000 lbs. For in-line blender accuracy, the PD meters will be tested to provide the below stated accuracy:
| | |
Equipment | | Accuracy |
200 Gallon | | ± 3 Lbs |
900 Gallon | | ± 6 Lbs |
1,500 Gallon | | ± 10 Lbs |
6,000 Gallon | | ± 30 Lbs |
9,000 Gallon | | ± 44 Lbs |
PD (or MF) Meters | | ± 2% |
The accuracy is the difference between the target amount dosed in the vessel and the actual amount in the vessel. So it includes both the error related to the dosing control equipment and the error in weigh cell reading.
The blender/reactor systems (vessel, inlet piping, outlet piping and piggable transfer lines) will not retain more than the amount of product indicated below when emptied. This will be demonstrated by chemical analysis of the first three production batches made in each of the blenders, reactors and drop tank.
| | | | |
Blender | | Max product retained (Lbs) | | vessel volume (gal) |
V-l | | 132 | | 6,000 |
V-2 | | 132 | | 6,000 |
V-3 | | 132 | | 6,000 |
V-4 | | 132 | | 6,000 |
Page 23 of 26
| | | | |
V-5 | | 100 | | 4,500 |
V-6 | | 24 | | 1,100 |
V-7 | | 10 | | 350 |
V-8 | | 150 | | 7,500 |
V-9 | | 150 | | 7,500 |
V-10 | | 165 | | 9,000 |
The blenders, reactors and drop tank will demonstrate proper mixing by loading two miscible liquid chemicals with a viscostiy not greater than 500 cps and blending them for 15 minutes. Samples taken from the top and bottom of the blender will indicate not less than 99% homogeneous. This only needs be demonstrated one time in each vessel to be considered complete.
The cooling tower will circulate 1200 gpm for a demonstrated period of 60 minutes as measured by a flow meter with all plant users in cooling mode (minimal pressure drop through system). During this same period, it will demonstrate the capacity to cool water from 95 to 87 F with an ambient WBT of 85 F at full flow. This will be determined by actual measurements and determination of capacity using standard charts.
The two steam boilers running, both at the same time, will demonstrate the ability to generate 400 Hp of steam for a sustained period of one hour with water levels running at steady state.
Both of the hot oil heaters and pumps will demonstrate the ability to generate 4.0 MM BTU per hour of heat for a period of one hour with the oil temperature greater than 450 F.
The air compressor system will demonstrate the ability to generate the designed flow rate of 1,000 cfm compressed air, and a maximum dew point of-40F while generating less than 80 db of noise outside the compressor shed.
All floor scales will be calibrated by the supplier and they shall provide certificates indicating the accuracy of the scales is within 2 lbs.
Water softener will demonstrate that it is adequate to produce 4,000 gal of soft water in 30 minutes.
Page 24 of 26
Each of the pumps listed below will demonstrate that they can deliver the design flow rate at the design pressure for a period of 15 minutes minimum:
| | | | |
| | V-l recirculation pump V-2 recirculation pump V-3 recirculation pump V-4 recirculation pump V-5 recirculation pump V-6 recirculation pump V-7 recirculation pump V-8 recirculation pump V-9 recirculation pump V-10 recirculation pump V-8 oil recirculation pump V-9 oil recirculation pump | | |
| * | The above are based on viscosity of 500 cP. |
| | | | |
| | Bulk water pump Bulk soft water pump | | |
| * | The above are based on viscosity of water. |
| | | | |
| | All bulk raw material pumps | | |
| * | The above are based on viscosities of raw materials as shown in tank spreadsheet attachment 4 - BULK TANKS details 011508.xls. |
5.11 | Controls and Instrumentation |
All controls and instrumentation will function as designed at Functional Completion of plant.
Drum filling line must demonstrate 50 drums per hour equivalent production rate for a period of one hour for acceptance. This is based on viscosity not to exceed 100 cps.
Piggable lines must demonstrate normal flow and pigging performance under conditions of low and high viscosity material. Performance must also demonstrate cleanliness levels needed to support the criteria in Section 4.2. Since the piggable lines may perform differently in winter weather, if the plant is determined to be functionally complete before winter weather, contractor will make any changes necessary for piggible lines to operate correctly in winter weather as part of their performance guarantee.
Page 25 of 26
Reactor systems will demonstrate a minimum vacuum of 26 inch HG absolute. With the reactor systems isolated, they will demonstrate “air-tightness” such that they do not loose more than 1 inch HG vacuum in 8 hours.
Functional Completion means that date when the Work, or a System:
| a) | has passed the required Performance Tests that are stipulated in the Scope of Work to be performed before Functional Completion; and |
| b) | is certified by the Owner’s Representative as being complete or ready to be put into service, or being used for the purpose intended and a Functional Completion Certificate is issued., and |
| c) | Only non-critical punch list items remain to be completed by contractor. Non-critical punch list items are items that do not measurably affect safety, protection of the environment, efficiency or quality. |
7.3 | Preliminary Project Schedule |
7.4 | BULK TANKS details 011508.xls (F Sansom note: I need to see a copy of this to validate is it the most recent verion) |
Page 26 of 26
ATTACHMENT 7.1
PROCESS DRAWINGS
QUAKER CHEMICAL INC.
GENERAL NOTES AND INSTRUCTIONS
1. | WHERE USED, HOSE COUPLINGS SHALL BE “DRY-BREAK” DESIGN TO HELP PREVENT ACCIDENTAL SPILLS. |
2. | WHEREVER POSSIBLE, ALL INSTRUMENTS AND MANUAL VALVES SHALL BE ACCESSIBLE TO A TECHNICIAN WITHOUT THE USE OF A LADDER. |
3. | AUTOMATED CONTROL SYSTEM TO INCLUDE VISUAL AND AUDIBLE INDICATORS FOR ALARM CONDITIONS. IF POSSIBLE, TECHNICIAN SHALL BE ABLE TO DISCERN FROM THE INDICATOR THE SERIOUSNESS OF THE ALARM CONDITION (I.E., REQUEST ALARM VERSUS WARNING ALARM VERSUS EMERGENCY ALARM). |
4. | OPEN ENDED LINES SUCH AS VENTS AND OVERFLOWS SHALL BE DIRECTED TO A SAFE LOCATION TO MINIMIZE THE CHANCE OF CONTACT TO PERSONNEL. |
5. | BRANCH CONNECTIONS INTO VENT HEADER SHALL ALWAYS ENTER INTO TOP OF HEADER. THIS DESIGN LESSENS THE CHANCE OF BACK-FLOW OF FLUID FROM HEADER INTO BRANCH LINE. |
6. | EMERGENCY SHUTDOWN BUTTONS (ESD) SHALL BE LOCATED IN NORMAL WORKING AREAS TO ALLOW FOR THE AUTOMATIC SHUTDOWN OF EQUIPMENT AND/OR SYSTEMS. QUANTITY AND LOCATION OF BUTTONS SHALL BE DETERMINED DURING DETAIL DESIGN PHASE. |
7. | WHENEVER POSSIBLE, FLEXIBLE HOSES SHALL BE ORIENTED IN A HORIZONTAL POSITION WHEN CONNECTED TO WEIGH VESSELS (I.E, VESSELS ON LOAD CELLS). |
9. | EACH AUTOMATED RAW MATERIAL INLET VALVE INTO A BLENDER OR REACTOR SHALL BE MOUNTED AS CLOSE AS IS FEASIBLE TO THE VESSEL THE PIPE LINE BETWEEN THE VALVE AND THE VESSEL SHALL BE SLOPED TO RESULT THAT THE LINE CAN FREE DRAIN INTO THE VESSEL THE IDEAL DESIGN IS FOR THE LINE TO BE ORIENTED VERTICALLY FROM THE VALVE INTO THE VESSEL. THIS DESIGN IMPROVES DOSING ACCURACY AND MINIMIZES DRIPPING OF RESIDUAL FLUID FROM LINE INTO THE VESSEL. |
10. | PUMPS, STRAINERS, FILTERS, VALVES, METERS AND OTHER FLUID-FILLED COMPONENTS THAT ARE INSTALLED IN PIPING SYSTEMS THAT ARE TRACED AND/OR INSULATED SHALL ALSO BE TRACED AND INSULATED TO MATCH THE REQUIREMENTS OF THE ATTACHED PIPING SYSTEM. |
11. | WHERE SIZE IS NOT INDICATED ON THE DRAWING FOR A DRAIN OR VENT VALVE, USE THE FOLLOWING GUIDELINES: |
| • | | USE A15 MM (1/2 INCH) VALVE FOR VENT OR DRAIN WHEN CONNECTED TO A MAIN LINE OF 50 MM (2 INCHES) OR SMALLER; |
| • | | USE A18 MM (3/4 INCH) VALVE FOR VENT OR DRAIN WHEN CONNECTED TO A MAIN LINE LARGER THAN 50 MM (2 INCHES); |
12. | VENT AND DRAIN VALVES SHALL HAVE ROUND OR OVAL HANDLES. THIS WILL LESSEN THE CHANCE OF ACCIDENTAL OPENING IF THE VALVE IS BUMPED. ALL VENT AND DRAIN VALVES SHOULD BE FITTED WITH A PLUG OR BLIND ON THE OPEN END WHEN NOT IN OPERATION. |
13. | WHERE INLET LINES TO A BLENDER ARE TRACED AND/OR INSULATED, THE TRACING AND/OR INSULATION SHALL STOP APPROXIMATELY 450 MM (18 INCHES) ABOVE THE TOP OF VESSEL. THIS WILL PREVENT THE TRACING AND/OR INSULATION FROM INTERFEREING WITH THE INSTALLATION OF THE SEAL BOOT BETWEEN THE LINE AND THE VESSEL. |
14. | FLEXIBLE HOSES THAT ARE USED TO CONNECT BETWEEN THERMAL LINES AND WEIGH VESSELS SHALL NOT BE TRACED OR INSULATED. THIS ALLOWS FOR FULL MOVEMENT OF THE HOSE WHICH RESULTS IN MORE ACCURATE WEIGHING USING THE LOAD CELL SYSTEM. |
15. | ALL AUTOMATED VALVES ARE “FAIL CLOSED” UNLESS OTHERWISE INDICATED. |
84
86
ATTACHMENT 7.2
GENERAL ARRANGEMENT
ATTACHMENT 7.3
PRELIMINARY PROJECT SCHEDULE
ATTACHMENT 7.4
BULK TANKS
| | | | | | | | | | | | | | | | | | | | | | |
| | | | REV 2 | | | | 1/15/08 | | | | | | | | | | | | | | |
| | | | TANK DATA | | | | | | | | | | | | | | | | |
Component Code | | Raw Material Name | | Tank ID | | HOSE BOARD column # | | Tank Cap. (gal) | | Tank Status | | Tank Type | | Tank Dimensions (dta x ht) | | Tank Material of Construction | | Tank Heating Available | | Heating Reg’d for Item in storage (dog F) | | Recommended Storage Temperature |
102495 | | Fatty Acid Methyl Ester | | OS-0001 | | 1 | | 30,000 | | Existing | | Flat Btm | | 12’ x 35’ | | Carbon Steel | | No (exist) | | Yes (100) | | 90 to 120 F |
100752 | | Grease - Yellow | | OS-0002 | | 1 | | 30,000 | | Existing | | Flat Btm | | 12’ x 35’ | | Carbon Steel | | Yes (exist) | | Yes (120) | | 120 to 130 F |
100485 | | Nap Oil 20 cST @ 40C | | OS-0003 | | 2 | | 30,000 | | Existing | | Flat Btm | | 12’ x 35’ | | Carbon Steel | | Yes (exist) | | Yes (90) | | 80 to 100 F |
100132 | | Oleic Acid | | OS-0004 | | 2 | | 30,000 | | Existing | | Flat Btm | | 12’ x 35’ | | Carbon Steel | | Yes (new) | | Yes (100) | | 100 to 110 F |
101733 | | Nap Oil 22 cST @ 40C | | OS-0005 | | 3 | | 30,000 | | Existing | | Flat Btm | | 12’ x 35’ | | Carbon Steel | | No (exist) | | No | | Ambient |
100364 | | Sodium Hydrooxide 50% | | OS-0006 | | 1 | | 17,000 | | Existing | | Flat Btm | | 12’ x 35’ | | Carbon Steel | | Yes (exist) | | Yes (135) | | 130 to 140 F |
102958 | | White Grease - Middletown | | OS-0007 | | 1 | | 30,000 | | Existing | | Flat Btm | | 12’ x 35’ | | Carbon Steel | | Yes (exist) | | Yes (120) | | 120 F |
100512 | | White Grease - Detroit | | OS-0008 | | 2 | | 30,000 | | Existing | | Flat Btm | | 12’ x 35’ | | Carbon Steel | | Yes (exist) | | Yes (120) | | 120 F |
100133 | | Technical Acid 47 | | OS-0009 | | 2 | | 30,000 | | Existing | | Flat Btm | | 12’ x 35’ | | Carbon Steel | | Yes (exist) | | Yes (120) | | 120 to 130 F |
101733 | | Nap Oil 22 cST @ 40C | | OS-0010 | | 3 | | 30,000 | | Existing | | Flat Btm | | 12’ x 35’ | | Carbon Steel | | No (exist) | | No | | Ambient |
100315 | | Nap Oil 240 cST @ 40C | | OS-0011 | | 10 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | Yes (exist) | | Yes (100) | | 100 to 120 F |
102673 | | Coconut Oil Crude | | OS-0012 | | 8 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | Yes (exist) | | Yes (110) | | 105 to 130 F |
101757 | | P&G methyl Palmatate | | OS-0013 | | 8 | | 12,000 | | Existing | | Flat Btm | | 12’ x 35’ | | Carbon Steel | | Yes (exist) | | Yes (100) | | 90 to 105 F |
spare | | Spare | | OS-0014 | | 6 | | 12,000 | | Existing | | Flat Btm | | 12’ x 35’ | | Carbon Steel | | No (exist) | | No | | |
101726 | | Para Oil 3.5 cSt @ 40C | | OS-0015 | | 5 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | No (exist) | | No | | Ambient |
101409 | | Severely Hydrotreated Light Distillates Naphtheric | | OS-0016 | | 3 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | No (exist) | | No | | Ambient |
100326 | | Coconut Oil Refined | | OS-0017 | | 10 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | Yes (exist) | | Yes (115) | | 110 to 120 F |
100932 | | Calcium Sulfonate In Mineral Oil | | OS-0018 | | 8 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | Yes (exist) | | Yes (130) | | 120 to 130 F |
000001 | | Stop Oil | | OS-0019 | | 8 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | No (exist) | | NO | | Ambient |
101734 | | Para Oil 20 cST @ 40C | | OS-0020 | | 6 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | No (exist) | | NO | | Ambient |
102651 | | Paraflex Ht-10/ Conosol | | OS-0021 | | 5 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | No (exist) | | NO | | Ambient |
102316 | | Grease - Yellow Sulfurized | | OS-0022 | | 3 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | No (exist) | | Yes (120) | | 100 to 140 F |
014199 | | U14199BS (Made in Reactor) | | OS-0023 | | 10 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | Yes (exist) | | Yes (90) | | 80 to 100 F |
000000 | | Waste water | | OS-0024 | | 9 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | Yes (exist) | | Yes (40) | | >32 F |
101539 | | Sodium Alkyaryl Sulfonate MW 430 | | OS-0025 | | 7 | | 12,000 | | Existing | | Flat Btm | | 13’ x 14’ | | Carbon Steel | | Yes (new) | | Yes (135) | | 120 to 130 F |
101448 | | Calcium Sulfonate In Mineral Oil 1448 | | OS-0026 | | 6 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | No (exist) | | Yes (120) | | 120 F |
100469 | | Low Odor Base Solvent (LOBS) | | OS-0027 | | 5 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | No (exist) | | No | | Ambient |
0 | | spare | | OS-0028 | | 4 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | No (exist) | | | | |
014198 | | U14198BS (Made in Reactor) | | OS-0029 | | 10 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | Yes (exist) | | Yes (90) | | 80 to 100 F |
013590 | | Intermediate 013590 (Made in Reactor) | | OS-0030 | | 9 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | Yes (exist) | | Yes (105) | | 100 to 110 F |
100116 | | Monoethanolamine | | OS-0031 | | 7 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | No (exist) | | Yes (95) | | 95 F |
100413 | | LARD OIL SULFURIZED 10% | | OS-0032 | | 6 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | No (exist) | | Yes (135) | | 130 to 140 F |
101847 | | Coconut Fatty Acid, | | OS-0033 | | 5 | | 12,000 | | Existing | | Flat Btm | | 13’ x 14’ | | Carbon Steel | | No (exist) | | Yes (115) | | 115 F |
102154 | | Severely Hydrotreated Heavy Naphthenic Distillates | | OS-0034 | | 4 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | No (exist) | | No | | Ambient |
100741 | | Severely Hydrotreated Heavy Naphthenic Distillates | | OS-0035 | | 9 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | No (exist) | | Yes (125) | | 120 to 130 F |
102416 | | Sulfurized Fattyacid Ester 10% | | OS-0036 | | 9 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | Yes (exist) | | Yes (110) | | 90 to 130 F |
100854 | | Reclaimed Oil 40 cST @ 40C | | OS-0037 | | 7 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | Yes (exist) | | Yes (80) | | 80 F |
spare | | spare | | OS-0038 | | 7 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | No (exist) | | No | | |
102639 | | Para/Nap Solvent 113C | | OS-0039 | | 4 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | No (exist) | | No | | Ambient |
102667 | | Poly ester blend | | OS-0040 | | 4 | | 12,000 | | Existing | | Flat Btm | | 11’ x 17’ | | Carbon Steel | | No (exist) | | No | | |
013473 | | Ferrocate x 61A-Us Conc. (Made in Blender) | | OS-0041 | | | | 12,000 | | New | | | | 13’ x 14’ | | Carbon Steel | | | | Yes (105) | | 100 to 110 F |
100187 | | Trimethylolpropane (locate tank in reactor bldg) | | OS-0042 | | | | 12,000 | | New | | | | 13’ x 14’ | | Carbon Steel | | | | Yes (200) | | 195 to 210 F |
013725 | | Quintolubric 888 68 (Made in finishing tank) | | OS-0043 | | | | 20,000 | | New | | | | | | Carbon Steel | | | | Yes (105) | | 100 to 110 F |
100793 | | Neopenlyl Glycol (locate tank in reactor bldg) | | OS-0044 | | | | 12,000 | | New | | | | 13’ x 14’ | | Carbon Steel | | | | Yes (135) | | 130 to 140 F |
008055 | | TMP Monomerate (Made in Reactor) | | OS-0045 | | | | 12,000 | | New | | | | 13’ x 14’ | | Carbon Steel | | | | Yes (105) | | 100 to 110 F |
004918 | | Intermediate 4918 (Made in Reactor) | | OS-0046 | | | | 12,000 | | New | | | | 13’ x 14’ | | Carbon Steel | | | | Yes (125) | | 120 to 130 F |
005510 | | Quaker Draw 5510 (Made in Reactor) | | OS-0047 | | | | 12,000 | | New | | | | 13’ x 14’ | | Stainless Steel | | | | Yes (100) | | 90 to 100 F |
100071 | | Diethanolamine | | OS-0048 | | | | 12,000 | | New | | | | 13’ x 14’ | | Stainless Steel | | | | Yes (125) | | 122 F |
014113 | | Quintolubric 888-46 (Made in finishing tank) | | OS-0049 | | | | 20,000 | | New | | | | | | Carbon Steel | | | | Yes (105) | | 100 to 110 F |
| | | | | | | | | | | | | | | | | | | | | | |
| | | | REV 2 | | | | | | | | | | | | | | | | | | |
| | | | TANK DATA | | | | | | | | | | | | | | | | |
Component Code | | Raw Material Name | | Tank ID | | Tank # item is currently stored in Mdt | | Recommended Metallurgy for item in storage | | Raw Material Type Description | | Total Thruput (lb) | | No. of Products | | Blends/ Yr | | Tc/mo | | Truck/ mo | | Tote/wk |
102495 | | Fatty Acid Methyl Ester | | OS-0001 | | 4 | | Carbon Steel | | Bulk Component | | 2,126,452 | | 10 | | 347.7 | | 0.9 | | 3.7 | | 10.2 |
100752 | | Grease - Yellow | | OS-0002 | | | | Carbon Steel | | Bulk Component | | 5,000,130 | | 12 | | 321.8 | | 2.1 | | 8.7 | | 24 |
100485 | | Nap Oil 20 cSt @ 40C | | OS-0003 | | | | Carbon Steel | | Bulk Component | | 21,437,019 | | 42 | | 968.1 | | 8.9 | | 37.2 | | 103.1 |
100132 | | Oleic Acid | | OS-0004 | | | | Stainless Steel | | Bulk and Drum Component | | 10,059,558 | | 44 | | 959.2 | | 4.2 | | 17.5 | | 48.4 |
101733 | | Nap Oil 22 cSt @ 40C | | OS-0005 | | 1 | | Carbon Steel | | Bulk and Drum Component | | 20,531,858 | | 33 | | 684.3 | | 8.6 | | 35.6 | | 98.7 |
100364 | | Sodium Hydroxide 50% | | OS-0006 | | 6 | | Stainless Steel | | Bulk Component | | 2,078,898 | | 25 | | 611.3 | | 0.9 | | 3.6 | | 10.0 |
102958 | | White Grease - Middletown | | OS-0007 | | 7 | | Carbon Steel | | Bulk Component | | 12,000,000 | | 5 | | 112.4 | | 5.0 | | 20.8 | | 57.7 |
100512 | | White Grease - Detroit | | OS-0008 | | | | Carbon Steel | | Bulk and Drum Component | | 11,641,477 | | 17 | | 552.5 | | 4.9 | | 20.2 | | 56.0 |
100133 | | Tachnical Acid 47 | | OS-0009 | | | | Carbon Steel | | Bulk Component | | 12,140,580 | | 7 | | 323.1 | | 5.1 | | 21.1 | | 58.4 |
101733 | | Nap Oil 22 cSt @ 40C | | OS-0010 | | 1 | | Carbon Steel | | Bulk and Drum Component | | 20,531,856 | | 33 | | 684.3 | | 8.6 | | 35.6 | | 98.7 |
100315 | | Nap Oil 240 cSt @ 40C | | OS-0011 | | 11 | | Carbon Steel | | Bulk and Drum Component | | 2,332,768 | | 38 | | 657.2 | | 1.0 | | 4.0 | | 11.2 |
102673 | | Coconut Oil Crude | | OS-0012 | | 12 | | Carbon Steel | | Bulk Component | | 1,130,034 | | 6 | | 85.0 | | 0.5 | | 2.0 | | 5.4 |
101757 | | P& G Methyl palmatate | | OS-0013 | | 3 | | Carbon Steel | | Bulk and Drum Component | | 1,566,423 | | 20 | | 332.6 | | 0.7 | | 2.7 | | 7.5 |
spare | | Spare | | OS-0014 | | | | Carbon Steel | | | | | | | | | | | | | | |
101726 | | Para Oil 3.5 cSt @ 40C | | OS-0015 | | | | Carbon Steel | | Bulk Component | | 2,748,841 | | 5 | | 103.5 | | 1.1 | | 4.8 | | 13.2 |
101409 | | Sevarely Hydrotreated Light Naphthenic Distillates | | OS-0016 | | | | Carbon Steel | | Bulk and Drum Component | | 966,739 | | 18 | | 260.9 | | 0.4 | | 1.7 | | 4.6 |
100326 | | Coconut Oil Refined | | OS-0017 | | | | Carbon Steel | | Bulk Component | | 2,546,208 | | 11 | | 327.8 | | 1.1 | | 4.4 | | 12.2 |
100932 | | Calcium Sulfonate In Mineral Oil | | OS-0018 | | | | Carbon Steel | | Bulk and Drum Component | | 2,120,989 | | 15 | | 353.8 | | 0.9 | | 3.7 | | 10.2 |
000001 | | Stop Oil | | OS-0019 | | | | Carbon Steel | | Slop Oil | | | | | | | | | | | | |
101734 | | Para Oil 20 cSt @ 40C | | OS-0020 | | | | Carbon Steel | | Bulk Component | | 3,608,379 | | 11 | | 362.2 | | 1.5 | | 6.3 | | 17.3 |
102651 | | Paraflex Ht-10/Conosol | | OS-0021 | | 21 | | Carbon Steel | | Bulk Component | | 743,325 | | 2 | | 27.9 | | 0.3 | | 1.3 | | 3.6 |
102316 | | Grease - Yellow Sulfurized | | OS-0022 | | | | Carbon Steel | | Bulk Component | | 3,211,217 | | 12 | | 383.4 | | 1.3 | | 5.6 | | 15.4 |
014199 | | U14199BS (Made in Reactor) | | OS-0023 | | 23 | | Carbon Steel | | Bulk Component | | 1,561,497 | | 6 | | 131.6 | | 0.7 | | 2.7 | | 7.5 |
000000 | | Waste water | | OS-0024 | | 24 | | Carbon Steel | | Waste water | | 625,000 | | | | | | | | | | |
101539 | | Sodium Alkylaryl Sulfonate MW 430 | | OS-0025 | | | | Carbon Steel | | Bulk and Drum Component | | 1,120,735 | | 21 | | 465.6 | | 0.5 | | 1.9 | | 5.4 |
101448 | | Calcium Sulfonate In Mineral Oil 1448 | | OS-0026 | | | | Carbon Steel | | Bulk and Drum Component | | 1,161,918 | | 5 | | 167.3 | | 0.5 | | 2.0 | | 5.6 |
100469 | | Low Odor Base Solvent (LOBS) | | OS-0027 | | | | Carbon Steel | | Bulk Component | | 1,372,489 | | 14 | | 157.7 | | 0.6 | | 2.4 | | 6.6 |
0 | | spare | | OS-0028 | | | | Carbon Steel | | | | | | | | | | | | | | |
014198 | | U14198BS (Made in Reactor) | | OS-0029 | | 2 | | Carbon Steel | | Bulk Component | | 501,804 | | 5 | | 75.6 | | 0.2 | | 0.9 | | 2.4 |
013590 | | Intermediate 013590 (Made in Blender) | | OS-0030 | | | | Carbon Steel | | Bulk Component | | 2,430,311 | | 1 | | 184.0 | | 1.0 | | 4.2 | | 11.7 |
100116 | | Monoethanolamine | | OS-0031 | | | | Carbon Steel | | Bulk and Drum Component | | 1,546,774 | | 68 | | 1,026.3 | | 0.6 | | 2.7 | | 7.4 |
100413 | | LARD OIL SULFURIZED 10% | | OS-0032 | | 8 | | Carbon Steel | | Bulk Component | | 2,078,898 | | 25 | | 611.3 | | 0.9 | | 3.6 | | 10.0 |
101847 | | Coconut Fatty Acid, | | OS-0033 | | | | Carbon Steel | | Bulk and Drum Component | | 1,449,634 | | 4 | | 109.8 | | 0.6 | | 2.5 | | 7.0 |
102164 | | Sevarely Hydrotreated Heavy Naphthenic Distillates | | OS-0034 | | | | Carbon Steel | | Bulk Component | | 794,338 | | 3 | | 86.3 | | 0.3 | | 1.4 | | 3.8 |
100741 | | Sevarely Hydrotreated Heavy Naphthenic Distillates | | OS-0035 | | | | Carbon Steel | | Bulk and Drum Component | | 560,342 | | 14 | | 177.0 | | 0.2 | | 1.0 | | 2.7 |
102416 | | Sulfurized Fattyacid Ester 10% | | OS-0036 | | 36 | | Carbon Steel | | Bulk Component | | 829,433 | | 8 | | 228.6 | | 0.3 | | 1.4 | | 4.0 |
100854 | | Reclaimed Oil 40 cSt @ 40C | | OS-0037 | | | | Carbon Steel | | Bulk Component | | 1,038,306 | | 5 | | 81.4 | | 0.4 | | 1.8 | | 5.0 |
spare | | spare | | OS-0038 | | | | Carbon Steel | | | | | | | | | | | | | | |
102639 | | Para/Nap Solvent 113C | | OS-0039 | | 39/40 | | Carbon Steel | | Bulk Component | | 1,875,950 | | 3 | | 67.8 | | 0.8 | | 3.3 | | 9.0 |
102667 | | Poly ester blend | | OS-0040 | | 10 | | Carbon Steel | | Bulk Component | | 206,000 | | | | | | 0.1 | | 0.4 | | 1.0 |
013473 | | Ferrocote x 61A-Us Conc. (Made in Blender) | | OS-0041 | | | | Carbon Steel | | Bulk Component | | 3,632,271 | | 1 | | 275.2 | | 1.5 | | 6.3 | | 17.5 |
100187 | | Trimethylolpropane (locate tank in reactor bldg) | | OS-0042 | | | | Carbon Steel | | Bulk and Drum Component | | 2,279,864 | | 8 | | 339.0 | | 0.9 | | 4.0 | | 11.0 |
013725 | | Quintolubric 888 66 (Made in finishing tank) | | OS-0043 | | | | Carbon Steel | | Bulk Component and Finished Product | | 251,574 | | 1 | | 12.0 | | 0.1 | | 0.4 | | 1.2 |
100793 | | Neopentyl Glycol (locate tank in reactor bldg) | | OS-0044 | | | | Carbon Steel | | Bulk Component | | 1,899,923 | | 9 | | 253.5 | | 0.8 | | 3.3 | | 9.1 |
008055 | | TMP Monomerate (Made in Reactor) | | OS-0045 | | | | Carbon Steel | | Bulk and Drum Component | | 6,619,473 | | 33 | | 727.2 | | 2.8 | | 11.5 | | 31.8 |
004918 | | Intermediate 4918 (Made in Reactor) | | OS-0046 | | | | Carbon Steel | | Bulk Component | | 888,624 | | 3 | | 147.3 | | 0.4 | | 1.5 | | 4.3 |
005510 | | Quaker Draw 5510 (Made in Reactor) | | OS-0047 | | | | Stainless Steel | | Bulk and Drum Component | | 1,441,679 | | 8 | | 303.5 | | 0.6 | | 2.5 | | 6.9 |
100071 | | Diethanolamine | | OS-0048 | | | | Stainless Steel | | Bulk and Drum Component | | 1,453,231 | | 14 | | 266.2 | | 0.6 | | 2.5 | | 7.0 |
014113 | | Quintolubric 888-46 (Made in finishing tank) | | OS-0049 | | | | Carbon Steel | | Finished Product | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | | | |
| | | | REV 2 | | | | | | | | | | | | | | | | | | | | |
| | | | TANK DATA | | | | | | | | | | | | | | | | | | |
Component Code | | Raw Material Name | | Tank ID | | Drum/day | | Gal/day | | Max Dose (lb) | | Rept Mode | | Receipt (gal) | | Lead Time (days) | | Safety (gal) | | Total (gal) | | Approx 2xMax Dose (gal) | | Recommended Tank Size (gal) |
102495 | | Fatty Acid Mathyl Ester | | OS-0001 | | 18.9 | | 1,063 | | 25,025 | | Truck | | 6,000 | | 10 | | 10,632 | | 10,632 | | 6,256 | | 16,632 |
100752 | | Grease - Yellow | | OS-0002 | | 44.4 | | 2,500 | | 28,995 | | Truck | | 6,000 | | 3 | | 7,500 | | 13,500 | | 7,249 | | 13,500 |
100485 | | Nap Oil 20 cSt @ 40C | | OS-0003 | | 190.6 | | 10,719 | | 52,800 | | Railcar | | 30,000 | | 7 | | 75,030 | | 105,030 | | 13,200 | | 105,030 |
100132 | | Oleic Acid | | OS-0004 | | 89.4 | | 5,030 | | 38,837 | | Railcar | | 30,000 | | 7 | | 35,208 | | 65,208 | | 9,709 | | 65,208 |
101733 | | Nap Oil 22 cSt @ 40C | | OS-0005 | | 182.5 | | 10,266 | | 52,800 | | Railcar | | 30,000 | | 3 | | 30,798 | | 60,798 | | 13,200 | | 60,798 |
100364 | | Sodium Hydroxide 50% | | OS-0006 | | 18.5 | | 1,039 | | 6,600 | | Truck | | 6,000 | | 10 | | 10,394 | | 16,394 | | 1,650 | | 16,394 |
102958 | | White Grease - Middletown | | OS-0007 | | 106.7 | | 6,000 | | 33,572 | | Truck | | 6,000 | | 6 | | 36,000 | | 42,000 | | 8,393 | | 42,000 |
100512 | | White Grease - Detroit | | OS-0008 | | 103.5 | | 5,821 | | 42,812 | | Truck | | 6,000 | | 3 | | 17,462 | | 23,462 | | 10,703 | | 23,462 |
100133 | | Technical Acid 47 | | OS-0009 | | 107.9 | | 6,070 | | 40,831 | | Truck | | 6,000 | | 7 | | 42,492 | | 48,492 | | 10,208 | | 48,492 |
101733 | | Nap Oil 22 cSt @ 40C | | OS-0010 | | 182.5 | | 10,266 | | 52,800 | | Railcar | | 30,000 | | 3 | | 30,798 | | 60,798 | | 13,200 | | 60,798 |
100315 | | Nap Oil 240 cSt @ 40C | | OS-0011 | | 20.7 | | 1,166 | | 12,111 | | Truck | | 6,000 | | 8 | | 6,998 | | 12,998 | | 3,028 | | 12,998 |
102673 | | Coconut Oil Crude | | OS-0012 | | 10.0 | | 565 | | 20,218 | | Truck | | 6,000 | | 6 | | 3,390 | | 9,390 | | 5,055 | | 9,390 |
101757 | | P&G methyl palmatate | | OS-0013 | | 13.9 | | 783 | | 18,506 | | Truck | | 6,000 | | 10 | | 7,832 | | 13,832 | | 4,627 | | 13,832 |
spare | | Spare | | OS-0014 | | | | | | | | Truck | | 6,000 | | | | | | | | | | |
101726 | | Para Oil 3.5 cSt @ 40C | | OS-0015 | | 24.4 | | 1,374 | | 43,780 | | Truck | | 6,000 | | 6 | | 8,247 | | 14,247 | | 10,945 | | 14,247 |
101409 | | Severely Hydrotreated Light Naphthenic Distilates | | OS-0016 | | 8.6 | | 483 | | 13,425 | | Railcar | | 23,000 | | 10 | | 4,834 | | 27,834 | | 3,356 | | 27,834 |
100326 | | Coconut Oil Refined | | OS-0017 | | 22.6 | | 1,273 | | 17,776 | | Truck | | 6,000 | | 10 | | 12,731 | | 18,731 | | 4,444 | | 18,731 |
100932 | | Calcium Sulfonate In Mineral Oil | | OS-0018 | | 18.9 | | 1,060 | | 23,496 | | Truck | | 6,000 | | 10 | | 10,605 | | 16,605 | | 5,874 | | 16,605 |
000001 | | Slop Oil | | OS-0019 | | | | | | | | Process | | 6,000 | | | | | | | | | | |
101734 | | Para Oil 20 cSt @ 40C | | OS-0020 | | 32.1 | | 1,804 | | 21,593 | | Truck | | 6,000 | | 6 | | 10,825 | | 16,825 | | 5,398 | | 16,825 |
102651 | | Paraflex Ht-10/ Conosol | | OS-0021 | | 6.6 | | 372 | | 27,806 | | Truck | | 6,000 | | 10 | | 3,717 | | 9,717 | | 6,951 | | 9,717 |
102316 | | Grease - Yellow Sulfurized | | OS-0022 | | 28.5 | | 1,606 | | 11,936 | | Truck | | 6,000 | | 6 | | 9,634 | | 15,634 | | 2,984 | | 15,634 |
014199 | | U14199BS (Made in Reactor) | | OS-0023 | | 13.9 | | 781 | | 21,080 | | Rxt | | 6,000 | | 3 | | 2,342 | | 8,342 | | 5,270 | | 8,342 |
000000 | | Waste water | | OS-0024 | | | | | | | | Process | | 6,000 | | | | | | | | | | |
101539 | | Sodium Alkylaryl Sulfonate MW 430 | | OS-0025 | | 10.0 | | 560 | | 4,950 | | Truck | | 6,000 | | 10 | | 5,604 | | 11,604 | | 1,238 | | 11,604 |
101448 | | Calcium Sulfonate In Mineral Oil 1448 | | OS-0026 | | 10.3 | | 581 | | 11,880 | | Truck | | 6,000 | | 10 | | 5,810 | | 11,810 | | 2,970 | | 11,810 |
100469 | | Low Odor Base Solvent (LOBS) | | OS-0027 | | 12.2 | | 686 | | 29,775 | | Truck | | 6,000 | | 10 | | 6,862 | | 12,862 | | 7,444 | | 12,862 |
0 | | spare | | OS-0028 | | | | | | | | | | | | | | | | | | | | |
014198 | | U14198BS (Made in Reactor) | | OS-0029 | | 4.5 | | 251 | | 10,925 | | Rxt | | 6,000 | | 3 | | 753 | | 8,753 | | 2,731 | | 6,753 |
013590 | | Intermediate 013590 (Made in Blender) | | OS-0030 | | 21.6 | | 1,215 | | 13,200 | | Blender | | 6,000 | | 3 | | 3,645 | | 9,645 | | 3,300 | | 9,645 |
100116 | | Monoethanolamine | | OS-0031 | | 13.7 | | 773 | | 6,187 | | Truck | | 6,000 | | 10 | | 7,734 | | 13,734 | | 1,547 | | 13,734 |
100413 | | LARD OIL SULFURIZED 10% | | OS-0032 | | 18.5 | | 1,039 | | 6,600 | | Truck | | 6,000 | | 10 | | 10,394 | | 16,394 | | 1,650 | | 16,394 |
101847 | | Coconut Fatty Acid, | | OS-0033 | | 12.9 | | 725 | | 31,260 | | Truck | | 6,000 | | 10 | | 7,248 | | 13,248 | | 7,815 | | 13,248 |
102164 | | Severely Hydrotreated Heavy Naphthenic Distillates | | OS-0034 | | 7.1 | | 397 | | 24,993 | | Truck | | 6,000 | | 10 | | 3,972 | | 9,972 | | 6,248 | | 9,972 |
100741 | | Severely Hydrotreated Heavy Naphthenic Distillates | | OS-0035 | | 5.0 | | 280 | | 8,712 | | Truck | | 6,000 | | 10 | | 2,802 | | 8,802 | | 2,178 | | 8,802 |
102416 | | Sulfurized Fattyacid Ester 10% | | OS-0036 | | 7.4 | | 415 | | 5,720 | | Truck | | 6,000 | | 10 | | 4,147 | | 10,147 | | 1,430 | | 10,147 |
100854 | | Reclaimed Oil 40 cSt @ 40C | | OS-0037 | | 9.2 | | 519 | | 23,760 | | Truck | | 6,000 | | 10 | | 5,182 | | 11,192 | | 5,940 | | 11,192 |
spare | | spare | | OS-0038 | | | | | | | | Truck | | 6,000 | | | | | | | | | | |
102639 | | Para/Nap Solvent 113C | | OS-0039 | | 16.7 | | 938 | | 33,990 | | Railcar | | 30,000 | | 10 | | 9,380 | | 39,380 | | 8,497 | | 39,380 |
102667 | | Poly ester blend | | OS-0040 | | 1.8 | | 103 | | | | Truck | | 6,000 | | | | | | | | | | |
013473 | | Ferrocote x 61A-Us Conc. (Made in Blender) | | OS-0041 | | 32.3 | | 1,816 | | 13,200 | | Blender | | 6,000 | | 3 | | 5,448 | | 11,448 | | 3,300 | | 11,448 |
100187 | | Trimethylolpropane (locate tank in reactor bldg) | | OS-0042 | | 20.3 | | 1,140 | | 8,887 | | Truck | | 6,000 | | 10 | | 11,399 | | 17,399 | | 2,222 | | 17,399 |
013725 | | Quintolubric 888 68 (Made in finishing tank) | | OS-0043 | | 2.2 | | 126 | | 21,005 | | Finish tank | | 8,000 | | 3 | | 377 | | 8,377 | | 5,251 | | 8,377 |
100793 | | Neopentyl Glycol (locate tank in reactor bldg) | | OS-0044 | | 16.9 | | 950 | | 9,183 | | Truck | | 6,000 | | 10 | | 9,500 | | 15,500 | | 2,296 | | 15,500 |
008055 | | TMP Monomerete (Made in Reactor) | | OS-0045 | | 58.8 | | 3,310 | | 22,022 | | Rxt | | 6,000 | | 3 | | 9,929 | | 15,929 | | 5,506 | | 15,929 |
004918 | | Intermediate 4918 (Made in Reactor) | | OS-0046 | | 7.9 | | 444 | | 9,075 | | Rxt | | 6,000 | | 3 | | 1,333 | | 7,333 | | 2,269 | | 7,333 |
005510 | | Quaker Draw 5510 (Made in Reactor) | | OS-0047 | | 12.8 | | 721 | | 7,424 | | Rxt | | 6,000 | | 3 | | 2,163 | | 8,163 | | 1,856 | | 8,163 |
100071 | | Diethanolamine | | OS-0048 | | 12.9 | | 727 | | 21,534 | | Truck | | 6,000 | | 10 | | 7,266 | | 13,266 | | 5,383 | | 13,266 |
014113 | | Quintolubric 888-46 (Made in finishing tank) | | OS-0049 | | | | | | | | Finish tank | | 8,000 | | | | | | | | | | |
| | | | | | | | | | | | | | | | | | | | | | |
| | | | REV 2 | | | | | | | | | | | | | | | | | | |
| | | | TANK DATA | | | | | | | | | | | | | | | | |
Component Code | | Raw Material Name | | Tank ID | | Goes to Reactor | | pump needed due to ILB or dye Injector? | | pump neededd ue to ILB or direct loadout? | | Is a pump needed for this tank? | | Agitation needed? | | vent dryer needed? | | Proposed Pump Capacity (gpm) | | Proposed Discharge Line Size (inch) | | Trace and Insulate Outside |
102495 | | Fatty Acid Mathyl Ester | | OS-0001 | | | | | | | | NO | | No | | No | | | | 3 | | Yes |
100752 | | Grease - Yellow | | OS-0002 | | | | | | | | NO | | Yes | | No | | | | 3 | | Yes |
100485 | | Nap Oil 20 cSt @ 40C | | OS-0003 | | | | yes | | | | YES, FOR ILB | | No | | No | | 300 | | 3 | | Yes |
100132 | | Oleic Acid | | OS-0004 | | yes | | | | | | YES, TO GET IT TO THE REACTOR | | No | | No | | 225 | | 3 | | Yes |
101733 | | Nap Oil 22 cSt @ 40C | | OS-0005 | | | | Yes | | yes | | YES, FOR ILB | | No | | No | | 350 | | 3 | | No |
100364 | | Sodium Hydroxide 50% | | OS-0006 | | | | | | | | NO | | No | | No | | | | 3 | | Yes |
102958 | | White Grease - Middletown | | OS-0007 | | | | | | | | NO | | No | | No | | | | 3 | | Yes |
100512 | | White Grease - Detroit | | OS-0008 | | | | | | | | NO | | Yes | | No | | | | 3 | | Yes |
100133 | | Technical Acid 47 | | OS-0009 | | yes | | | | | | YES, TO GET IT TO THE REACTOR | | No | | No | | 300 | | 3 | | Yes |
101733 | | Nap Oil 22 cSt @ 40C | | OS-0010 | | | | yes | | gang tank with OS-05 | | NO, BECAUSE IT WILL SHARE A PUMP WITH OS-05 | | No | | No | | 350 | | 3 | | No |
100315 | | Nap Oil 240 cST @ 40C | | OS-0011 | | | | | | | | NO | | No | | No | | | | 3 | | Yes |
102673 | | Coconut Oil Crude | | OS-0012 | | | | | | | | NO | | No | | No | | | | 3 | | Yes |
101757 | | P&G methyl palmatate | | OS-0013 | | | | | | | | NO | | No | | No | | 100 | | 3 | | Yes |
spare | | Spare | | OS-0014 | | | | | | | | NO | | | | | | | | 3 | | |
101726 | | Para Oil 3.5 cSt @ 40C | | OS-0015 | | | | yes, but we only make once per week, so remove is $ too high | | | | NO, WE DO NOT MAKE 014019 OFTEN ENOUGH TO JUSTIFY A PUMP | | No | | No | | 300 | | 3 | | No |
101409 | | Severely Hydrotreated Light Naphthenic Distilates | | OS-0016 | | | | | | yes for HLB in TT. Use loading line in reverse with new meter | | NO, WE WILL LOAD IT OUT THROUGH BLENDER | | No | | No | | 50 | | 3 | | No |
100326 | | Coconut Oil Refined | | OS-0017 | | | | | | | | NO | | No | | No | | | | 3 | | Yes |
100932 | | Calcium Sulfonate In Mineral Oil | | OS-0018 | | | | yes, but we only make once per week, so remove is $ too high | | | | NO, WE DO NOT MAKE 014019 OFTEN ENOUGH TO JUSTIFY A PUMP | | No | | No | | 60 | | 3 | | Yes |
000001 | | Slop Oil | | OS-0019 | | | | | | no, use pump on truck | | NO | | No | | No | | 75 | | 3 | | No |
101734 | | Para Oil 20 cSt @ 40C | | OS-0020 | | | | | | | | NO | | No | | No | | | | 3 | | No |
102651 | | Paraflex Ht-10/ Conosol | | OS-0021 | | | | | | | | NO | | No | | No | | | | 3 | | Yes |
102316 | | Grease - Yellow Sulfarized | | OS-0022 | | | | | | | | NO | | No | | No | | | | 3 | | Yes |
014199 | | U14199BS (Made in Reactor) | | OS-0023 | | | | | | | | NO | | No | | No | | | | 3 | | Yes |
000000 | | Waste water | | OS-0024 | | | | | | no, use pump on truck | | NO | | No | | No | | 100 | | 3 | | Yes |
101539 | | Sodium Alkylaryl Sulfonate MW 430 | | OS-0025 | | | | | | | | NO | | No | | No | | 40 | | 3 | | Yes |
101448 | | Calcium Sulfonate in Mineral Oil 1448 | | OS-0026 | | | | | | | | NO | | No | | No | | 60 | | 3 | | Yes |
100469 | | Low Odor Base Solvent (LOBS) | | OS-0027 | | | | | | | | NO | | No | | No | | | | 3 | | No |
0 | | spare | | OS-0028 | | | | | | | | NO | | | | | | | | 3 | | |
014198 | | U14198BS (Made in Reactor) | | OS-0029 | | | | | | | | NO | | No | | No | | | | 3 | | Yes |
013590 | | Intermediate 013590 (Made in Blender) | | OS-0030 | | | | yes, 1-2 loads per day | | | | YES FOR ILB | | No | | Yes | | 100 | | 3 | | Yes |
100116 | | Monoethanolamine | | OS-0031 | | | | | | | | NO | | No | | No | | | | 3 | | Yes |
100413 | | LARD OIL SULFURIZED 10% | | OS-0032 | | | | | | | | NO | | No | | No | | | | 3 | | Yes |
101847 | | Coconut Fatty Acid, | | OS-0033 | | yes | | | | | | YES, TO GET IT TO THE REACTOR | | No | | No | | 200 | | 3 | | Yes |
102164 | | Severely Hydrotreated Heavy Naphthenic Distillates | | OS-0034 | | | | | | | | NO | | No | | No | | | | 3 | | No |
100741 | | Severely Hydrotreated Heavy Naphthenic Distillates | | OS-0035 | | | | | | | | NO | | No | | No | | | | 3 | | Yes |
102416 | | Sulfurized Fattyacid Ester 10% | | OS-0036 | | | | | | | | NO | | No | | No | | | | 3 | | Yes |
100854 | | Reclaimed Oil 40 cSt @ 40C | | OS-0037 | | | | | | | | NO | | No | | No | | | | 3 | | Yes |
spare | | spare | | OS-0038 | | | | | | | | NO | | | | | | | | 3 | | |
102639 | | Para/Nap Solvent 113C | | OS-0039 | | | | | | once per week TT to Ispat. | | NO, WE DO NOT DO WAND JOB OFTEN ENOUGH, WE WILL LOAD OUT THROUGH BLENDER | | No | | No | | 250 | | 3 | | No |
102667 | | Poly ester blend | | OS-0040 | | | | | | | | NO | | No | | No | | | | 3 | | No |
013473 | | Ferrocote x 61A-Us Conc. (Made in Blender) | | OS-0041 | | | | yes | | | | YES FOR ILB | | No | | Yes | | 100 | | 3 | | Yes |
100187 | | Trimethylopropane (locate tank in reactor bldg) | | OS-0042 | | yes | | | | | | YES, TO GET IT TO THE REACTOR | | No | | No | | 50 | | 3 | | Yes |
013725 | | Quintolubric 888 68 (Made in finishing tank) | | OS-0043 | | | | yes, 1-4 TT per month, Currently do it in a bin and add to bulk truck | | yes, with meter | | YES, FOR INJECTING DYE AND FOR FG LOADOUT | | No | | No | | 150 | | 3 | | Yes |
100793 | | Neopentyl Glycol (locate tank in reactor bldg) | | OS-0044 | | yes | | | | | | YES, TO GET IT TO THE REACTOR | | No | | No | | 75 | | 3 | | Yes |
008055 | | TMP Monomerate (Made in Reactor) | | OS-0045 | | | | | | | | NO | | No | | No | | | | 3 | | Yes |
004918 | | Intermediate 4918 (Made in Reactor) | | OS-0046 | | | | | | | | NO | | No | | No | | | | 3 | | Yes |
005510 | | Quaker Draw 5510 (Made in Reactor) | | OS-0047 | | | | | | | | NO | | No | | No | | 50 | | 3 | | Yes |
100071 | | Diethanolamine | | OS-0048 | | yes | | | | | | NO, we only made 3 batches 5510 per month in reactor. It takes 8 bins per batch. Either use bins, or continue to produce in Detroit. Add pump later if justified. | | No | | No | | 75 | | 3 | | Yes |
014113 | | Quintolubric 888-46 (Made in finishing tank) | | OS-0049 | | | | | | yes, with meter | | YES, TO GET IT TO THE LOADOUT | | No | | No | | 100 | | 3 | | Yes |
| | | | | | | | | | | | | | | | | | | | | | |
| | | | REV 2 | | | | | | | | | | | | | | | | | | |
| | | | TANK DATA | | | | | | | | | | | | | | | | |
Component Code | | Raw Material Name | | Tank ID | | Trace and Insulate Inside | | V-01 water- based | | V-05 Kosher | | V-02-V-04 oil based | | V-06 - V-7 manual | | Caustic Blender | | Rector V-08 & V-09 | | to ILB or Dye Injector | | Direct to TT |
| | | | | | | | | | | |
102495 | | Fatty Acid Mathyl Ester | | OS-0001 | | Yes | | | | | | X | | | | | | | | | | |
| | | | | | | | | | | |
100752 | | Grease - Yellow | | OS-0002 | | Yes | | | | | | X | | | | | | | | | | |
| | | | | | | | | | | |
100485 | | Nap Oil 20 cSt @ 40C | | OS-0003 | | No | | | | X | | X | | | | | | | | X 003385, sometimes use 1733 based on cost | | |
| | | | | | | | | | | |
100132 | | Oleic Acid | | OS-0004 | | No | | YES | | | | X | | | | | | X | | | | |
| | | | | | | | | | | |
101733 | | Nap Oil 22 cSt @ 40C | | OS-0005 | | No | | | | X | | X | | | | | | | | X 007734 | | |
| | | | | | | | | | | |
100364 | | Sodium Hydroxide 50% | | OS-0006 | | Yes | | YES | | | | X | | | | X | | | | | | |
| | | | | | | | | | | |
102958 | | White Grease - Middletown | | OS-0007 | | Yes | | | | | | X | | | | | | | | | | |
| | | | | | | | | | | |
100512 | | White Grease - Detroit | | OS-0008 | | Yes | | | | | | X | | | | | | | | | | |
| | | | | | | | | | | |
100133 | | Technical Acid 47 | | OS-0009 | | Yes | | | | | | | | | | | | X | | | | |
| | | | | | | | | | | |
101733 | | Nap Oil 22 cSt @ 40C | | OS-0010 | | No | | | | X | | X | | | | | | | | X 007734 | | |
| | | | | | | | | | | |
100315 | | Nap Oil 240 cSt @ 40C | | OS-0011 | | Yes | | | | X | | X | | | | | | | | | | |
| | | | | | | | | | | |
102673 | | Coconut Oil Crude | | OS-0012 | | Yes | | | | | | X | | | | | | | | | | |
| | | | | | | | | | | |
101757 | | P&G methyl palmatate | | OS-0013 | | Yes | | | | | | X | | | | | | | | | | |
| | | | | | | | | | | |
spare | | Spare | | OS-0014 | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | |
101726 | | Para Oil 3.5 cSt @ 40C | | OS-0015 | | No | | | | | | X | | | | | | | | X 014019 we do not make this often enough to warrant cost, so we will make in a blender | | |
| | | | | | | | | | | |
101409 | | Severely Hydrotreated Light Naphthenic Distillates | | OS-0016 | | No | | | | | | X | | | | | | | | | | |
| | | | | | | | | | | |
100326 | | Coconut Oil Refined | | OS-0017 | | Yes | | | | | | X | | | | | | | | | | |
| | | | | | | | | | | |
100932 | | Calcium Sulfonate In Mineral Oil | | OS-0018 | | Yes | | | | X | | X | | | | | | | | X 014019 we do not make this often enough to warrant cost, so we will make in a blender | | |
| | | | | | | | | | | |
000001 | | Slop Oil | | OS-0019 | | No | | | | | | | | | | | | | | | | yes, but just flow back wards through loading line and use portable pump to load to truck. No meter needed |
| | | | | | | | | | | |
101734 | | Para Oil 20 cSt @ 40C | | OS-0020 | | No | | YES | | | | X | | | | | | | | | | |
| | | | | | | | | | | |
102651 | | Paraflex Ht-10/ Conosol | | OS-0021 | | No | | | | | | X | | | | | | | | | | |
| | | | | | | | | | | |
102316 | | Grease - Yellow Sulfurized | | OS-0022 | | Yes | | | | | | X | | | | | | | | | | |
| | | | | | | | | | | |
014199 | | U14199BS (Made in Reactor) | | OS-0023 | | Yes | | | | | | X | | | | | | | | | | |
| | | | | | | | | | | |
000000 | | Waste water | | OS-0024 | | No | | | | | | | | | | | | | | | | yes, but just flow back wards through loading line and use portable pump to load to truck. No meter needed |
| | | | | | | | | | | |
101539 | | Sodium Alkylaryl Sulfonate MW 430 | | OS-0025 | | Yes | | YES | | | | X | | | | | | | | | | |
| | | | | | | | | | | |
101448 | | Calcium Sulfonate In Mineral Oil 1448 | | OS-0026 | | Yes | | | | X | | X | | | | | | | | | | |
| | | | | | | | | | | |
100469 | | Low Odor Base Solvent (LOBS) | | OS-0027 | | No | | | | X | | X | | | | | | | | | | |
| | | | | | | | | | | |
0 | | spare | | OS-0028 | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | |
014198 | | U14198BS (Made in Reactor) | | OS-0029 | | No | | | | | | X | | | | | | | | | | |
| | | | | | | | | | | |
013590 | | Intermediate 013590 (Made in Blender) | | OS-0030 | | Yes | | | | X | | | | | | | | | | X 003385 | | |
| | | | | | | | | | | |
100116 | | Monoethanolamine | | OS-0031 | | Yes | | | | | | X | | | | | | | | | | |
| | | | | | | | | | | |
100413 | | LARD OIL SULFURIZED 10% | | OS-0032 | | Yes | | | | | | X | | | | | | | | | | |
| | | | | | | | | | | |
101847 | | Coconut Fatty Acid, | | OS-0033 | | Yes | | | | | | X | | | | | | X | | | | |
| | | | | | | | | | | |
102164 | | Severely Hydrotreated Heavy Naphthenic Distillates | | OS-0034 | | No | | | | X | | X | | | | | | | | | | |
| | | | | | | | | | | |
100741 | | Severely Hydrotreated Heavy Naphthenic Distillates | | OS-0035 | | Yes | | | | X | | X | | | | | | | | | | |
| | | | | | | | | | | |
102416 | | Sulfurized Fattyacid Ester 10% | | OS-0036 | | No | | | | | | X | | | | | | | | | | |
| | | | | | | | | | | |
100854 | | Reclaimed Oil 40 cSt @ 40C | | OS-0037 | | No | | | | | | X | | | | | | | | | | |
| | | | | | | | | | | |
spare | | spare | | OS-0038 | | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | |
102639 | | Para/Nap Solvent 113C | | OS-0039 | | No | | | | | | X | | | | | | | | | | |
| | | | | | | | | | | |
102667 | | Poly ester blend | | OS-0040 | | No | | | | | | X | | | | | | | | | | |
| | | | | | | | | | | |
013473 | | Ferrocote x 61A-Us Conc. (Made in Blender) | | OS-0041 | | No | | | | X | | | | | | | | | | X 007734 | | |
| | | | | | | | | | | |
100187 | | Trimethylopropane (locate tank in reactor bldg) | | OS-0042 | | Yes | | | | | | | | | | | | X | | | | |
| | | | | | | | | | | |
013725 | | Quintolubric 888 68 (Made in finishing tank) | | OS-0043 | | No | | | | | | | | | | | | | | dye mixer 013129 | | yes |
| | | | | | | | | | | |
100793 | | Neopentyl Glycol (locate tank in reactor bldg) | | OS-0044 | | Yes | | | | | | | | | | | | X | | | | |
| | | | | | | | | | | |
008055 | | TMP Monomerate (Made in Reactor) | | OS-0045 | | No | | | | | | X | | | | | | | | | | |
| | | | | | | | | | | |
004918 | | Intermediate 4918 (Made in Reactor) | | OS-0046 | | No | | | | | | X | | | | | | | | | | |
| | | | | | | | | | | |
005510 | | Quaker Draw 5510 (Made in Reactor) | | OS-0047 | | Yes | | YES | | | | X | | | | | | | | | | |
| | | | | | | | | | | |
100071 | | Diethanolamine | | OS-0048 | | Yes | | YES | | | | X | | | | | | X | | | | |
| | | | | | | | | | | |
014113 | | Quintolubric 888-46 (Made in finishing tank) | | OS-0049 | | No | | | | | | | | | | | | | | | | yes |
| | | | | | | | | | | | | | |
| | | | REV 2 | | | | | | | | | | |
| | | | TANK DATA | | | | | | | | |
Component Code | | Raw Material Name | | Tank ID | | Comments | | Quaker tech resource | | Specific Gravity | | Freeze Point | | Flash Point |
102495 | | Fatty Acid Methyl Ester | | OS-0001 | | | | purchasing | | 0.88 | | N/A | | >300 F |
100752 | | Grease - Yellow | | OS-0002 | | | | purchasing | | 0.89 | | 100 F | | 550 F |
100485 | | Nap Oil 20 cSt @ 40C | | OS-0003 | | | | purchasing | | 0.911 | | -60 F | | 260 to 496 F CCC |
100132 | | Oleic Acid | | OS-0004 | | | | purchasing | | 0.891 | | 39 F | | 364 F |
101733 | | Nap Oil 22 cSt @ 40C | | OS-0005 | | | | purchasing | | 0.91 | | -51 F | | >320 F |
100364 | | Sodium Hydroxide 50% | | OS-0006 | | | | purchasing | | 0.99 | | 65 F Pour PL | | 350 F |
102958 | | White Grease - Middletown | | OS-0007 | | | | purchasing | | 0.89 | | 60 F | | 600 F |
100512 | | White Grease - Detroit | | OS-0008 | | | | purchasing | | 0.89 | | 60 F | | 600 F |
100133 | | Technical Acid 47 | | OS-0009 | | | | purchasing | | 0.84 | | 93 F | | 385 F COC |
101733 | | Nap Oil 22 cSt @ 40C | | OS-0010 | | | | purchasing | | 0.91 | | -51 F | | >320 F |
100315 | | Nap Oil 240 cSt @ 40C | | OS-0011 | | | | purchasing | | 0.92 | | 30 F | | >400 F COC |
102673 | | Coconut Oil Crude | | OS-0012 | | | | purchasing | | 0.9 | | 75 to 80 F | | <600 F |
101757 | | P&G Methyl palmatate | | OS-0013 | | | | purchasing | | 0.872 | | >41 F | | 425 F |
spare | | Spare | | OS-0014 | | | | purchasing | | | | | | |
101726 | | Para Oil 3.5 cSt @ 40C | | OS-0015 | | | | purchasing | | 0.84 | | -11 F | | 248 to 275 F CC |
101409 | | Severely Hydrotreated Light Naphthenic Distillates | | OS-0016 | | | | purchasing | | 0.911 | | <0 F | | 258 F |
100326 | | Coconut Oil Refined | | OS-0017 | | | | purchasing | | 0.92 | | 80 F | | >900 F |
100932 | | Calcium Sulfonate In Mineral Oil | | OS-0018 | | | | purchasing | | 0.96 | | -30 F | | 350 F |
000001 | | Slop Oil | | OS-0019 | | | | Michel | | 0.90 | | -51 F | | >320 F |
101734 | | Para Oil 20 cSt @ 40C | | OS-0020 | | | | purchasing | | 0.86 | | 0 F | | 381 F |
102651 | | Paraflex Ht-10/Conosol | | OS-0021 | | | | purchasing | | 0.851 | | 0 F MAX | | 340 F |
102316 | | Grease - Yellow Sulfurized | | OS-0022 | | | | purchasing | | 0.9729 | | 60 F | | 442 F PMCC |
014199 | | U14199BS (Made in Reactor) | | OS-0023 | | | | J Frelin | | 0.92 | | 40 F | | 435 F |
000000 | | Waste water | | OS-0024 | | | | Sansom | | 1.00 | | 32 F | | NONE |
101539 | | Sodium Alkylaryl Sulfonate MW 430 | | OS-0025 | | | | purchasing | | 0.79 | | -15 F | | >200 F |
101448 | | Calcium Sulfonate In Mineral Oil 1448 | | OS-0026 | | | | purchasing | | 1.21 | | 16 F pour pt | | 320 F |
100469 | | Low Odor Base Solvent (LOBS) | | OS-0027 | | | | purchasing | | 0.82 | | -45 F | | 150 to 165 F TCC |
0 | | spare | | OS-0028 | | | | | | | | | | |
014198 | | U14198BS (Made in Reactor) | | OS-0029 | | | | J Frelin | | 0.91 | | <23 F | | 570 F |
013590 | | Intermediate 013590 (Made in Blender) | | OS-0030 | | | | J Krnetz | | 0.92 | | <0 F | | 340 F |
100116 | | Monoethanolamine | | OS-0031 | | careful how this is heated to avoid hazard | | purchasing | | 1.018 | | 51 F | | 205 F |
100413 | | LARD OIL SULFURIZED 10% | | OS-0032 | | | | purchasing | | 0.99 | | 65 F Pour PL | | 350 F |
101847 | | Coconut Fatty Acid, | | OS-0033 | | | | purchasing | | 0.89 | | 57 F | | 315 F COC |
102164 | | Sevarely Hydrotreated Heavy Naphthenic Distillates | | OS-0034 | | | | purchasing | | 0.9 | | -20 F | | 304 F |
100741 | | Sevarely Hydrotreated Heavy Naphthenic Distillates | | OS-0035 | | | | purchasing | | 0.93 | | 10 F | | 468 F COC |
102416 | | Sulfurized Fattyacid Ester 10% | | OS-0036 | | | | purchasing | | 0.94 | | N/A WILL CALL | | >350 F COC |
100854 | | Reclaimed Oil 40 cSt @ 40C | | OS-0037 | | | | purchasing | | 0.875 | | 10 F | | >500 F |
spare | | spare | | OS-0038 | | | | | | | | | | |
102639 | | Para/Nap Solvent 113C | | OS-0039 | | | | purchasing | | 0.79 | | -15 F | | >200 F |
102667 | | Poly ester blend | | OS-0040 | | | | | | 0.97 | | | | |
013473 | | Ferrocote x 61A-Us Conc. (Made in Blender) | | OS-0041 | | | | J Krnetz | | 0.90 | | 13 F | | 363 F |
100187 | | Trimethylolpropane (locate tank in reactor bldg) | | OS-0042 | | | | purchasing | | 1.09 | | 136 F | | 302 F COC |
013725 | | Quintolubric 888 68 (Made in finishing tank) | | OS-0043 | | | | L Palmerio | | 0.92 | | -15 F | | 550 F |
100793 | | Neopentyl Glycol (locate tank in reactor bldg) | | OS-0044 | | | | purchasing | | 0.94 | | <95 F | | 270 F COC |
008055 | | TMP Monomerate (Made in Reactor) | | OS-0045 | | | | J Frelin | | 0.90 | | 34 F | | 435 F |
004918 | | Intermediate 4918 (Made in Reactor) | | OS-0046 | | | | J Krnatz | | 0.87 | | 26 F | | 200 F |
005510 | | Quaker Draw 5510 (Made in Reactor) | | OS-0047 | | | | S Thomas | | 0.99 | | <50 F pour pt | | 370 F |
100071 | | Diethanolamine | | OS-0048 | | | | purchasing | | 1.092 | | 82 F | | 345 F COC (375 F PMCC) |
014113 | | Quintolubric 888-46 (Made in finishing tank) | | OS-0049 | | | | L Palmerio | | 0.92 | | -15 F | | 550 F |
| | | | | | | | | | | | | | |
| | | | REV 2 | | | | | | | | | | |
| | | | TANK DATA | | | | | | | | |
Component Code | | Raw Material Name | | Tank ID | | Molecular Weight | | VOC Content | | HAP Content | | Recommended Pumping Temperature | | Vapor Pressure Recommended Pumping Temperature |
102495 | | Fatty Acid Methyl Ester | | OS-0001 | | 290 | | 59 grams per liter | | | | 90 to 120 F | | |
100752 | | Grease - Yellow | | OS-0002 | | | | | | | | 120 to 130 F | | |
100485 | | Nap Oil 20 cSt @ 40C | | OS-0003 | | 540 | | 24C | | 8 | | 80 to 100 F | | Negligible |
100132 | | Oleic Acid | | OS-0004 | | 278 | | N/D | | N/D | | 100 to 110 F | | Negligible |
101733 | | Nap Oil 22 cSt @ 40C | | OS-0005 | | 305 | | 26.5 | | NIL | | Ambient | | Negligible |
100364 | | Sodium Hydroxide 50% | | OS-0006 | | | | | | | | 130 to 140 F | | |
102958 | | White Grease - Middletown | | OS-0007 | | 270 | | | | | | 120 F | | |
100512 | | White Grease - Detriot | | OS-0008 | | 270 | | | | | | 120 F | | |
100133 | | Technical Acid 47 | | OS-0009 | | | | | | | | 120 to 130 F | | Negligible |
101733 | | Nap Oil 22 cSt @ 40C | | OS-0010 | | 305 | | 26.5 | | NIL | | Ambient | | Negligible |
100315 | | Nap Oil 240 cSt @ 40C | | OS-0011 | | 460 | | NIL | | NIL | | 100 to 120 F | | |
102673 | | Coconut Oil Crude | | OS-0012 | | -210 | | 0% | | 0% | | 105 to 130 F | | |
101757 | | P&G methyl palmatate | | OS-0013 | | 287 | | | | | | 90 to 105 F | | Negligible |
spare | | Spare | | OS-0014 | | | | | | | | | | |
101726 | | Para Oil 3.5 cSt @ 40C | | OS-0015 | | 237 | | 93.8% Per EPA Method 24 | | NIL | | Ambient | | Negligible |
101409 | | Severely Hydrotreated Light Naphthenic Distillates | | OS-0016 | | 226 | | 99.9% Per EPA Method 24 | | 0.348 PPM CHROMIUM (NOT HEXAVALENT) | | Ambient | | Negligible |
100326 | | Coconut Oil Refined | | OS-0017 | | | | | | | | 110 to 120 F | | |
100932 | | Calcium Sulfonate In Mineral Oil | | OS-0018 | | 1080 | | NIL | | NIL | | 120 to 130 F | | Negligible |
000001 | | Slop Oil | | OS-0019 | | 305 | | 26.5 | | NIL | | Ambient | | Negligible |
101734 | | Para Oil 20 cSt @ 40C | | OS-0020 | | 370 to 400
(est) | | | | | | Ambient | | Negligible |
102651 | | Paraflex H1-10/ Conosol | | OS-0021 | | 292 | | N/A | | N/A | | 68 F | | |
102316 | | Grease - Yellow Sulfurized | | OS-0022 | | 270 | | 0% | | 0% | | 100 to 140 F | | Negligible |
014199 | | U14199BS (Made in Reactor) | | OS-0023 | | -1028 | | | | | | 80 to 100 F | | |
000000 | | Waste water | | OS-0024 | | 18 | | 0 | | 0 | | >32 F | | |
101539 | | Sodium Alkylaryl Sulfonate MW 430 | | OS-0025 | | 196 | | 100% Per EPA Method 24 | | NIL | | 120 to 130 F | | |
101448 | | Calcium Sulfonate in Mineral Oil 1448 | | OS-0026 | | UNKNOWN | | NIL | | NIL | | 120 F | | |
100469 | | Low Odor Base Solvent (LOSS) | | OS-0027 | | | | | | | | Ambient | | Negligible |
0 | | spare | | OS-0028 | | | | | | | | | | |
014198 | | U14198BS (Made in Reactor) | | OS-0029 | | -916 | | | | | | 80 to 100 F | | |
013590 | | Intermediate 013590 (Made in Blender) | | OS-0030 | | | | | | | | 100 to 110 F | | Negligible |
100116 | | Monoethanolamine | | OS-0031 | | 61 | | | | | | 95 F | | Negligible |
100413 | | LARD OIL SULFURIZED 10% | | OS-0032 | | | | | | | | 130 to 140 F | | |
101847 | | Coconut Fatty Acid, | | OS-0033 | | 207 | | N/D | | N/D | | 115 F | | Negligible |
102164 | | Severely Hydrotreated Light Naphthenic Distillates | | OS-0034 | | | | | | | | Ambient | | |
100741 | | Severely Hydrotreated Light Naphthenic Distillates | | OS-0035 | | 500 | | 0.3 | | N/A | | 120 to 130 F | | Negligible |
102416 | | Sulfurized Fattyacid Ester 10% | | OS-0036 | | | | | | | | 90 to 130 F | | |
100854 | | Reclaimed Oil 40 cSt @ 40C | | OS-0037 | | N/A | | N/A | | | | 80 F | | |
spare | | spare | | OS-0038 | | | | | | | | | | |
102639 | | Para/Nap Solvent 113 C | | OS-0039 | | 196 | | 100% EPA24 | | NIL | | Ambient | | |
102667 | | Poly ester blend | | OS-0040 | | | | | | | | | | |
013473 | | Ferrocole x 61A-Us Conc. (Made in Blender) | | OS-0041 | | | | | | | | 100 to 110 F | | |
100187 | | Trimethylolpropane (locate tank in reactor bldg) | | OS-0042 | | 134 | | 0% | | 0% | | 195 to 210 F | | 1 psi @ 210 C |
013725 | | Quintolubric 888 68 (Made in finishing tank) | | OS-0043 | | | | | | | | 100 to 110 F | | |
100793 | | Neopentyl Glycol (locate tank in reactor bldg) | | OS-0044 | | N/A | | 0% | | 0% | | 130 to 140 F | | 1.7 psi |
008055 | | TMP Monomerate (Made in Reactor) | | OS-0045 | | -1030 | | | | | | 100 to 110 F | | |
004918 | | Intermediate 4918 (Made in Reactor) | | OS-0046 | | | | | | | | 120 to 130 F | | |
005510 | | Quaker Draw 5510 (Made in Reactor) | | OS-0047 | | | | | | | | 90 to 100 F | | |
100071 | | Diethanolamine | | OS-0048 | | 105 | | 1087 grams per liter | | | | 122 F | | Negligible |
014113 | | Quintolubric 888 46 (Made in finishing tank) | | OS-0049 | | | | | | | | 100 to 110 F | | |
| | | | | | | | | | |
| | | | REV 2 | | | | | | |
| | | | TANK DATA | | | | |
Component Code | | Raw Material Name | | Tank ID | | Viscosity at Racommended Pumping Temperature (centipolse) | | Viscosity at 40 deg C (104 deg F) | | Viscosity at 100 deg C (212 deg F) |
102495 | | Fatty Acid Mathyl Ester | | OS-0001 | | 6 | | 5 cSt | | 2 cSt |
100752 | | Grease - Yellow | | OS-0002 | | 24 | | 32 cP | | 8 cP |
100485 | | Nap Oil 20 cSt @ 40C | | OS-0003 | | 100 | | 20 cP | | 1 cP |
100132 | | Oleic Acid | | OS-0004 | | 60 | | 17 cP | | 4 cP |
101733 | | Nap Oil 22 cSt @ 40C | | OS-0005 | | 200 | | 22 cSt | | 4 cSt |
100364 | | Sodium Hydroxide 50% | | OS-0006 | | 2820 | | 6100 cp | | 407 cp |
102958 | | White Grease - Middletown | | OS-0007 | | 40 | | 44 cSt | | 9 cSt |
100512 | | White Grease - Detroit | | OS-0008 | | 40 | | 44 cSt | | 9 cSt |
100133 | | Technical Acid 47 | | OS-0009 | | 15 | | 19 cP | | 7 cP |
101733 | | Nap Oil 22 cSt @ 40C | | OS-0010 | | 200 | | 22 cSt | | 4 cSt |
100315 | | Nap Oil 240 cSt @ 40C | | OS-0011 | | 210 | | | | |
102673 | | Coconut Oil Crude | | OS-0012 | | 28 | | 28 cp | | 6 cp |
101757 | | P&G methyl palmatate | | OS-0013 | | 7 | | 7 cSt | | N/A |
spare | | Spare | | OS-0014 | | | | | | |
101726 | | Para Oil 3.5 cSt @ 40C | | OS-0015 | | 35 | | 4 cP | | not avail & not needed |
101409 | | Severely Hydrotreated Light Naphthenic Distillates | | OS-0016 | | 9 | | 5 cSt | | 2 cSt |
100326 | | Coconut Oil Refined | | OS-0017 | | 30 | | 30 cP | | 6 cP |
100932 | | Calcium Sulfonate In Mineral Oil | | OS-0018 | | 480 cps @ 73 F | | not avail | | 20 cps |
000001 | | Slop Oil | | OS-0019 | | 200 | | 22 cSt | | 4 cSt |
101734 | | Para Oil 20 cSt @ 40C | | OS-0020 | | 103 | | 20 cSt | | 4 cSt (TYP) |
102651 | | Paraflex Ht-10/Conosol | | OS-0021 | | 50 | | 10 cp | | 2 cp |
102316 | | Grease - Yellow Sulfurized | | OS-0022 | | 250 | | 250 cP | | 44 cSt |
014199 | | U14199BS (Made in Reactor) | | OS-0023 | | 170 | | 93 cSt | | 12.0 cSt |
000000 | | Waste water | | OS-0024 | | 1 | | | | |
101539 | | Sodium Alkylaryl Sulfonate MW 430 | | OS-0025 | | 2100 cps @ 120 F, 880 cps @ 140 F | | not avail, but hard to pump at this temp! | | 100 cps |
101448 | | Calcium Sulfonate In Mineral Oil 1448 | | OS-0026 | | 1000 | | 1800 cP | | 80 cP |
100469 | | Low Odor Base Solvent (LOBS) | | OS-0027 | | 2 | | < 2 cP | | < 2 cP |
0 | | spare | | OS-0028 | | | | | | |
014198 | | U14198BS (Made in Reactor) | | OS-0029 | | 145 | | 45 cSt | | 10.5 cSt |
013590 | | Intermediate 013590 (Made in Blender) | | OS-0030 | | 85 | | 85 cSt | | 10 cSt |
100116 | | Monoethanolamine | | OS-0031 | | 13 | | 10 cP | | 2 cP |
100413 | | LARD OIL SULFURIZED 10% | | OS-0032 | | 2820 | | 6100 cp | | 407 cP |
101847 | | Coconut Fatty Acid, | | OS-0033 | | 7 | | 9 cP | | 3 cP |
102164 | | Severely Hydrotreated Heavy Naphthenic Distillates | | OS-0034 | | 200 | | 21 cP | | 4 cP |
100741 | | Severely Hydrotreated Heavy Naphthenic Distillates | | OS-0035 | | 40 | | 369 | | 18 cSt |
102416 | | Sulfurized Fattyacid Ester 10% | | OS-0036 | | 18 | | 18 cps | | not avail |
100854 | | Reclaimed Oil 40 cSt @ 40C | | OS-0037 | | 285 | | 34 cSt | | 6 cSt |
spare | | spare | | OS-0038 | | | | | | |
102639 | | Para/Nap Solvent 113C | | OS-0039 | | 10 (assumed) | | 2.2 cSt | | not avail & not needed |
102667 | | Poly ester blend | | OS-0040 | | | | | | |
013473 | | Ferrocote x 61A-Us Conc. (Made in Blender) | | OS-0041 | | 230 | | 40 cSt | | 6 cSt |
100187 | | Trimethylopropane (locate tank in reactor bldg) | | OS-0042 | | 120 | | SOLID | | 80 cP |
013725 | | Quintolubric 888 68 (Made in finishing tank) | | OS-0043 | | 325 | | 68 cSt | | 11 cSt |
100793 | | Neopentyl Glycol (locate tank in reactor bldg) | | OS-0044 | | 50 | | 80 to 120 cP | | <20 Cp |
008055 | | TMP Monomerate (Made in Reactor) | | OS-0045 | | 40 | | 80 cSt | | 12.1 cSt |
004918 | | Intermediate 4918 (Made in Reactor) | | OS-0046 | | 155 | | 37 cP | | 7 cSt |
005510 | | Quaker Draw 5510 (Made in Reactor) | | OS-0047 | | 1000 | | 544 cSt | | 25 cSt |
100071 | | Diethanolamine | | OS-0048 | | 100 | | 200 cP | | NA |
014113 | | Quintolubric 888-46 (Made in finishing tank) | | OS-0049 | | 210 | | 40 cSt | | 8 cSt |
APPENDIX B
COMPENSATION
1. The “Compensation” to be paid by the Owner to the Contractor for performance of the Work shall be Eighteen Million Four Hundred Three Thousand Seven Hundred Twenty One and zero/100 Dollars ($18,403,721.00). The Compensation shall be paid in installments, in accordance with the terms of this Appendix B.
2. Contractor shall prepare a schedule of values (the “Schedule of Values”), which allocates the entire Compensation among the various portions of the Work. Compensation for Engineering Services, Procurement Services and the Construction Work shall each be shown separately. In addition, the Compensation allocated to those items of equipment shown on Schedule 1 attached hereto (the “Leased Equipment”) shall also be shown separately on the Schedule of Values. The Schedule of Values shall be prepared in such form and supported by such data to substantiate its accuracy as the Owner may require. This Schedule of Values, unless objected to by the Owner, shall be used as a basis for reviewing the Contractor’s Requests for Payment (as hereinafter defined).
3. The Contractor shall submit to Owner monthly requests for payment (each a “Request for Payment”), each of which shall cover the immediately-preceding calendar month. Each Request for Payment shall state the percentage of completion of each portion of the Work, as set forth in the Schedule of Values, as of the end of the period covered by the Request for Payment, and the amount of payment to be made by Owner in connection with such Request for Payment. Except with the Owner’s prior approval, the Contractor shall not make advance payments to suppliers for materials or equipment which have not been delivered and stored at the site. The amount of payment to be made by Owner in connection with a Request for Payment shall be calculated as follows:
a. Take that portion of the Consideration properly allocable to completed Work as determined by multiplying the percentage completion of each portion of the Work by the share of the Consideration allocated to that portion of the Work in the Schedule of Values, less retainage ten percent (10%) on the Work;
b. Add that portion of the Consideration properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the completed construction, less retainage often percent (10%);
c. Subtract the aggregate of previous payments made by the Owner; and
d. Subtract amounts, if any, for which the Owner has withheld payment as permitted under the terms of the Agreement.
4. With each Request for Payment, and before issuance of and as a condition precedent to any payment to Contractor under this Agreement, Contractor shall submit: (i) a release and
waiver of all liens, claims, security interests or encumbrances of any kind arising out of the Work covered by the preceding Requests for Payment (except as to retainage), in a form acceptable to Owner, from Contractor and each subcontractor, sub-subcontractor, each vendor that has supplied equipment or materials for the Work and supplier who has performed Work for which payment is being requested in the preceding Requests for Payment, releasing such parties’ right to file a lien with respect to Work done through the date of the Request of Payment; (ii) such other documents, releases, waivers, assignments, papers, estoppel certificates and statements as may be requested by Owner; and (iii) a certification from Contractor stating: “There are no known mechanics’ or materialmen’s liens, or any other liens or claims, outstanding as of the date of this payment; all due and payable bills with respect to the Work have been paid to date and there is no known basis for the filing of any mechanics’ or materialmen’s lien or any other lien or claim on the Work; and any waivers from all contractors, subcontractors, sub-subcontractors, vendors, suppliers and materialmen for Work done or materials furnished for which payment has been made, or, pursuant to this Request for Payment, is to be made, to Contractor have been obtained and provided to Owner in such form as to constitute an effective waiver of all such liens under applicable law.”
5. Each Request for Payment shall be submitted to Owner no later than the fifth (5th) day of each calendar month, and, if such Request for Payment is approved for payment as provided in Section 6 below, Owner shall remit payment in connection with such Request for Payment no later than the twenty-fifty (25th) day of the month in which such Request for Payment was received; provided, however, that in the event any such Request for Payment includes payment on account of any Leased Equipment, then Owner shall use its commercially reasonable efforts to remit the portion of the payment allocated to such Leased Equipment no later than the tenth (10th) day of the month following the month in which such Request for Payment was received.
6. Upon receipt of a Request for Payment, Owner shall review the submissions made by the Contractor and either approve the same for payment or withhold such approval. Approval may be withheld, or prior approval of a previous Request for Payment may be revoked (upon subsequent discovery of evidence), if (i) the Work is not in accordance with the requirements of the Contract, (ii) the Work has not been completed to the extent indicated in the Request for Payment, (iii) there is reasonable evidence that the remainder of the Work cannot be completed for the balance of unpaid Compensation, (iv) there is reasonable evidence that the remainder of the Work cannot be completed within the Contract Time and the balance of the Consideration is inadequate to cover actual or liquidated damages for the anticipated delay, (v) there is reasonable evidence that subcontractors, sub-subcontractors, vendors or suppliers have not been paid by Contractor for Work that was the subject of prior Requests for Payment, (vi) failure to carry out the Work in accordance with the Contract, (vii) reasonable evidence that a lien or other claim has been or will be filed by a subcontractor, sub-subcontractor, vendor or supplier without acceptable security being posted by Contractor, or (viii) any other default by the Contractor is not cured within the applicable cure period. When the above reasons for withholding approval are removed, approval will be made for amounts previously withheld.
7. Notwithstanding anything to the contrary contained herein, upon execution of the Contract, the Owner shall pay to the Contractor an amount equal to fifteen percent (15%) of the Consideration (the “Initial Payment”), which shall be used by the Contractor to secure Contract
pricing and material delivery schedules. Said Initial Payment shall be applied against the first monthly Requests for Payment made by Contractor until fully credited. Contractor shall timely make monthly Requests for Payments, showing the Initial Payment made by Owner and application of said Initial Payment to costs shown on the Schedule of Values.
8. Upon issuance of a Final Completion Notice in accordance with the terms of Article 20 of the Contract, Owner shall pay to Contractor the balance of the Consideration, including all amounts held as retainage, less any amounts payable by the Contractor to the Owner as liquidated damages in accordance with the Contract.
Schedule 1
| | |
DESCRIPTION | | |
| | HARD COST |
Blender #1 - 6,000 Gallon, Pallet Scale, Pump, Agitator, Instruments, Screw Conveyor | | 255,563 |
Blender #2 - 6,000 Gallon, Pallet Scale, Pump, Agitator, instruments | | 239,563 |
Blender #3 – 6,000 Gallon, Pallet Scale, Pump, Agitator, Instruments | | 239,563 |
Blender #4 - 6,000 Gallon, Pallet Scale, Pump, Agitator, Instruments | | 239,563 |
Blender #5 - 4,500 Gallon, Pallet Scale, Pump, Agitator, Instruments | | 186,061 |
Blender #6 -1,100 Gallon, Pallet Scale, Pump, Agitator, Instruments | | 105,224 |
Blender #7 -350 Gallon, Pallet Scale, Pump, Agitator, Instruments | | 78,046 |
Reactor #1 - 7,500 Gallon, Pallet Scale, Pump, Agitator, Instruments | | 403,936 |
Reactor#2 - 7,600 Gallon, Pallet Scale, Pump, Agitator, Instruments | | 403,936 |
Finishing Vessel - 9,000 Gallon, Pallet Scale, Pump, Agitator, Instruments | | 367,733 |
Drum Filing Line, 55 Gallon Drum Semi-Automatic | | 83,285 |
OS-0041 Storage Tank #1,12,000 Gallon, Carbon Steel, Pump, Instruments | | 48,257 |
OS-0042 Storage Tank #2, 12,000 Gallon, Carbon Steel, Pump, Instruments | | 48,257 |
0S-0043 Storage Take #3, 20,000 Gallon, Carbon Steel, Pump, Instruments | | 56,240 |
OS-0044 Storage Tank #4, 12,000 Gallon, Carbon Steel, Pump, Instruments | | 48,257 |
OS-45/46 Storage Tank #5, Dual Compartment, 12,000 Gallon Each, Carbon Steel, instruments | | 76,095 |
OS-47/48 Storage Tank #6,Dual Compartment, 12,000 Gallon Each, Stainless Steel, instruments | | 142,911 |
OS -0049 Storage Tank #7, 20,000 Gallon, Carbon Steel, Pump, Instruments | | 56,240 |
Pumps, Agitators and Instruments for Existing Tank Farm | | 136,510 |
Steam Heated Drum Ovens, (16) 55 Gallon Drum Capacity | | 50,066 |
Cooling Tower including Pumps and Flow Meter, Evapco Model USS-112-312 with TEAO Fan. Motor | | 123,976 |
Vent Scrubber Skid, EST 925 Type 650 acfm Ejector Venturi | | 90,000 |
Vacuum Pumps, Nash XL-45 Direct Drive Iron Recirc Oil Package | | 43,700 |
Hot Oil Heaters, Thermal Fluid System Model kwkh 1.0 S/25,4.0MMBtu/hr | | 348,798 |
Air Compressor System, 1000 cfm Atlas Copco GA200 Air Cooled Rotary Screw, Dryer, Receiver | | 112,197 |
Soft Water System, includes Water Storage Tanks | | 88,576 |
Truck Loading Platforms, Carbia Red-Rack II units | | 37,485 |
Hose Board Manifold isolation Valves | | 122,585 |
Piggable Components, Including Instruments | | 536,247 |
In-Line Blenders, (as Components, not as skids) | | 59,125 |
Process Control Hardware | | 281,988 |
Total | | 5,109,983 |
| | |
REV: A April 17, 2008 BASED ON REVISED QUAKER WRITE-UP AND PFD / P&IDS. | | |
Comments: | | |
SUMMARY Page 1 of 1
APPENDIX C
WORK SITE
Appendix D – Warranty Items Procedure
COAA EPC Appendix D – Warranty Items Procedure
Page 1 of 1
Approved by COAA Board April 13, 2005
APPENDIX E
LIQUIDATED DAMAGES
In the event that Contractor fails to achieve Functional Completion of the Work by the date that is one month after the Scheduled Functional Completion Date (the “Grace Period”), the Contractor shall pay to the Owner, as liquidated damages and not as a penalty, the sum of Thirteen Thousand Dollars ($13,000) for each and every week (or that sum pro-rated, on a per diem basis, in the case of a partial week) up to a maximum of $250,000 following the expiration of the Grace Period until Functional Completion of the Work is achieved. Owner and Contractor agree that, in the event of such a delay in Functional Completion, the actual damages that Owner would sustain as a result thereof would be difficult if not impossible to ascertain, and that these liquidated damages are a reasonable estimate of such actual damages. Owner’s right to receive these liquidated damages shall be Owner’s exclusive remedy for any delay in achieving Functional Completion by the Scheduled Functional Completion Date (but not for any default by Contractor under the Contract arising from or related to such delay). The foregoing shall not be deemed to limit Owner’s rights or the damages to which Owner might be entitled under Article 36 of the Contract, including, without limitation, those rights or damages arising from a default by Contractor under the Contract relating to such delay. Said liquidated damages shall be payable by Contractor to Owner within three (3) Business Days after (i) Final Completion is achieved, or (ii) the termination of the Contract in accordance with its terms.
APPENDIX F
INCENTIVE FEE
In the event that Contractor achieves Functional Completion of the Work prior to the Scheduled Functional Completion Date, Contractor shall be entitled to an additional sum of Thirteen Thousand Dollars ($13,000) for each and every week (or that sum pro-rated, on a per diem basis, in the case of a partial week) that date of Functional Completion precedes the Scheduled Functional Completion Date. Said additional sum shall be payable by Owner to Contractor within three (3) Business Days after Final Completion is achieved.
APPENDIX G
FORMS
| • | | Key Employee Confidentiality, Proprietary Information and Consent Agreement |
| • | | Functional Completion Notice |
| • | | Final Completion Notice |
| • | | Release and Certificate of Final Payment |
THESE FORMS WILL BE JOINTLY DEVELOPED AND APPROVED BY OWNER AND CONTRACTOR AFTER EXECUTION OF THE CONTRACT
APPENDIX H
DISPUTE RESOLUTION PROCEDURE
In the event of any dispute, or difference arising out of, or relating to this Contract, or the breach thereof, the parties shall use their best endeavors to settle such dispute, or difference by consulting and negotiating with each other, in good faith, and understanding of their mutual interests, to reach a just and equitable resolution which is satisfactory to the parties. In the event the parties cannot resolve such dispute up to the level of each party’s Division Manager or President within ninety (90) days after a party’s initial notice of the dispute, the parties shall be free to litigate their differences in accordance with the Laws of the state of Ohio without regard to conflicts of laws rules.
Appendix I
1.1 | Project Team and Key Personnel |
The Project Team for the Expansion Project has extensive experience in similar projects.
| 1.1.1 | Key Personnel for Contractor |
| • | | Jeff Syed- Project Manager |
| • | | Jogesh Chandran - Engineering Manager |
| • | | John Lawlor - Lead Process Engineer |
| • | | Tai Tran - Process Engineer |
| 1.1.2 | Key Personnel for Subcontractors |
| 1.1.2.1Process | Construction: |
| • | | Doug Doxsey - Engineering Manager |
| • | | Joe Doxsey - Project Manager |
| 1.1.2.2 | Wuest Electric Co: |
| • | | Brian Kile - Project Manager |
| 1.1.2.3 | Thomas R. O’Shea Inc: |