Commitments and Contingencies | Commitments and Contingencies Power Purchase Agreements SCE entered into various agreements to purchase power, electric capacity and other energy products. At December 31, 2018 , the undiscounted future expected minimum payments for the SCE PPAs (primarily related to renewable energy contracts), which were approved by the CPUC and met other critical contract provisions (including completion of major milestones for construction), were as follows: (in millions) Total 2019 $ 2,562 2020 2,602 2021 2,570 2022 2,415 2023 2,185 Thereafter 23,855 Total future commitments $ 36,189 Additionally, SCE has executed contracts (including capacity reduction contracts) that have not met the critical contract provisions that would increase contractual obligations by $66 million in 2019, $176 million in 2020, $189 million in 2021, $184 million in 2022, $183 million in 2023 and $2.2 billion thereafter, if all critical contract provisions are completed. Costs incurred for PPAs were $3.8 billion in 2018, $3.6 billion in 2017 and $3.3 billion in 2016, which include costs associated with contracts with terms of less than one year. Certain PPAs that SCE entered into may be accounted for as leases. The following table shows the future minimum lease payments due under the contracts that are treated as operating and capital leases (these amounts are also included in the table above). Due to the inherent uncertainty associated with the reliability of the fuel source, expected purchases from most renewable energy contracts do not meet the definition of a minimum lease payment and have been excluded from the operating and capital lease table below but remain in the table above. The future minimum lease payments for capital leases are discounted to their present value in the table below using SCE's incremental borrowing rate at the inception of the leases. The amount of this discount is shown in the table below as the amount representing interest. (in millions) Operating Leases Capital Leases 2019 $ 148 $ 5 2020 124 6 2021 103 6 2022 79 6 2023 47 5 Thereafter 536 66 Total future commitments $ 1,037 $ 94 Amount representing executory costs (25 ) Amount representing interest (33 ) Net commitments 1 $ 36 1 Includes two contracts with net commitments of $26 million that will commence in 2019. In 2018, SCE amended the termination date of two power purchase agreements, which are classified as operating leases. As a result of this amendment, future minimum payments for these operating leases, totaling $986 million , were removed from the table above. SCE is required to make early termination payments of $100 million in 2019, $77 million in 2020 and $29 million in 2021, which were included in the consolidated balance sheets as of December 31, 2018. Operating lease expense for PPAs was $2.3 billion in 2018 , and $2.3 billion in 2017 and $1.9 billion in 2016 (including contingent rents of $2.1 billion in 2018 , $1.8 billion in 2017 and $1.4 billion in 2016 ). Contingent rents for capital leases were $104 million in 2018, $99 million in 2017 and $109 million in 2016. The timing of SCE's recognition of the lease expense conforms to ratemaking treatment for SCE's recovery of the cost of electricity and is included in purchased power. Other Lease Commitments The following summarizes the estimated minimum future commitments for Edison International's non-cancelable other operating leases (primarily related to vehicles, office space and other equipment related to SCE): (in millions) Total 2019 $ 42 2020 31 2021 27 2022 22 2023 17 Thereafter 101 Total future commitments $ 240 Operating lease expense for other leases were $57 million in 2018 , $59 million in 2017 and $68 million in 2016 . Certain leases on office facilities contain escalation clauses requiring annual increases in rent. The rentals payable under these leases may increase by a fixed amount each year, a percentage over base year, or the consumer price index. Other Commitments The following summarizes the estimated minimum future commitments for SCE's other commitments: (in millions) 2019 2020 2021 2022 2023 Thereafter Total Other contractual obligations $ 79 $ 67 $ 46 $ 44 $ 35 $ 209 $ 480 Costs incurred for other commitments were $124 million in 2018 , $75 million in 2017 and $141 million in 2016 . SCE has fuel supply contracts for Palo Verde which require payment only if the fuel is made available for purchase. SCE also has commitments related to maintaining reliability and expanding SCE's transmission and distribution system. The table above does not include asset retirement obligations, which are discussed in Note 1. Indemnities Edison International and SCE have various financial and performance guarantees and indemnity agreements which are issued in the normal course of business. Edison International and SCE have agreed to provide indemnifications through contracts entered into in the normal course of business. These are primarily indemnifications against adverse litigation outcomes in connection with underwriting agreements, and indemnities for specified environmental liabilities and income taxes with respect to assets sold. Edison International's and SCE's obligations under these agreements may or may not be limited in terms of time and/or amount, and in some instances Edison International and SCE may have recourse against third parties. Edison International and SCE have not recorded a liability related to these indemnities. The overall maximum amount of the obligations under these indemnifications cannot be reasonably estimated. SCE has agreed to indemnify the City of Redlands, California in connection with the Mountainview power plant's California Energy Commission permit for cleanup or associated actions related to groundwater contaminated by perchlorate due to the disposal of filter cake at the City's solid waste landfill. The obligations under this agreement are not limited to a specific time period or subject to a maximum liability. As of December 31, 2018, there has been no groundwater contamination identified. Thus, SCE has not recorded a liability related to this indemnity. Contingencies In addition to the matters disclosed in these Notes, Edison International and SCE are involved in other legal, tax and regulatory proceedings before various courts and governmental agencies regarding matters arising in the ordinary course of business. Edison International and SCE believe the outcome of these other proceedings will not, individually or in the aggregate, materially affect its financial position, results of operations and cash flows. Southern California Wildfires and Mudslides Approximately 35% of SCE's service territory is in areas identified as high fire risk by SCE. Multiple factors have contributed to increased wildfires, faster progression of wildfires and the increased damage from wildfires across SCE's service territory and throughout California. These include the buildup of dry vegetation in areas severely impacted by years of historic drought, lack of adequate clearing of hazardous fuels by responsible parties, higher temperatures, lower humidity, and strong Santa Ana winds. At the same time that wildfire risk has been increasing in Southern California, residential and commercial development has occurred and is occurring in some of the highest-risk areas. Such factors can increase the likelihood and extent of wildfires. In December 2017 and November 2018, wind-driven wildfires impacted portions of SCE's service territory, causing substantial damage to both residential and business properties and service outages for SCE customers. The largest of the 2017 fires, known as the Thomas Fire, originated in Ventura County and burned acreage located in both Ventura and Santa Barbara Counties. The largest of the 2018 fires, known as the Woolsey Fire, originated in Ventura County and burned acreage in both Ventura and Los Angeles Counties. According to California Department of Forestry and Fire Protection ("CAL FIRE") information, the Thomas Fire burned over 280,000 acres, destroyed an estimated 1,063 structures, damaged an estimated 280 structures and resulted in two fatalities, while the Woolsey Fire burned almost 100,000 acres, destroyed an estimated 1,643 structures, damaged an estimated 364 structures and resulted in three fatalities. As of December 31, 2018, SCE had incurred approximately $89 million of capital expenditures related to restoration of service resulting from the Thomas Fire and the Montecito Mudslides (as defined below) and $82 million resulting from the Woolsey Fire. As described below, multiple lawsuits related to the Thomas Fire and the Woolsey Fire have been initiated against SCE and Edison International. Some of the Thomas Fire-related lawsuits claim that SCE and Edison International have responsibility for the damages caused by mudslides and flooding in Montecito and surrounding areas in January 2018 (the "Montecito Mudslides") based on a theory that SCE has responsibility for the Thomas Fire and that the Thomas Fire proximately caused the Montecito Mudslides. According to Santa Barbara County initial reports, the Montecito Mudslides destroyed an estimated 135 structures, damaged an estimated 324 structures, and resulted in 21 fatalities, with two additional fatalities presumed. The extent of liability for wildfire-related damages in actions against utilities depends on a number of factors, including whether SCE substantially caused or contributed to the damages and whether parties seeking recovery of damages will be required to show negligence in addition to causation. California courts have previously found utilities to be strictly liable for property damage along with associated interest and attorneys' fees, regardless of fault, by applying the theory of inverse condemnation when a utility's facilities were determined to be a substantial cause of a wildfire that caused the property damage. If inverse condemnation is held to be inapplicable to SCE in connection with a wildfire, SCE still could be held liable for property damages and associated interest if the property damages were found to have been proximately caused by SCE's negligence. If SCE were to be found negligent, SCE could also be held liable for, among other things, fire suppression costs, business interruption losses, evacuation costs, clean-up costs, medical expenses, and personal injury/wrongful death claims. Additionally, SCE could potentially be subject to fines for alleged violations of CPUC rules and state laws in connection with the ignition of a wildfire. Investigations into the causes of the Thomas Fire, the Montecito Mudslides and the Woolsey Fire (collectively, the "2017/2018 Wildfire/Mudslide Events") are ongoing and final determinations of liability, including determinations of whether SCE was negligent, would only be made during lengthy and complex litigation processes. Even when investigations are still pending or liability is disputed, an assessment of likely outcomes, including through future settlement of disputed claims, may require a charge to be accrued under accounting standards. Based on SCE's internal review into the facts and circumstances of each of the 2017/2018 Wildfire/Mudslide Events and consideration of the risks associated with litigation, Edison International and SCE expect to incur a material loss in connection with the 2017/2018 Wildfire/Mudslide Events and have accrued a charge, before recoveries and taxes, of $4.7 billion in the fourth quarter of 2018. Edison International and SCE also recorded expected recoveries from insurance of $2.0 billion and expected recoveries through FERC electric rates of $135 million . The net charge to earnings recorded was $1.8 billion after-tax. This charge corresponds to the lower end of the reasonably estimated range of expected potential losses that may be incurred in connection with the 2017/2018 Wildfire/Mudslide Events and is subject to change as additional information becomes available. Edison International and SCE will seek to offset any actual losses realized with recoveries from insurance policies in place at the time of the events and, to the extent actual losses exceed insurance, through electric rates. The CPUC and FERC may not allow SCE to recover uninsured losses through electric rates if it is determined that such losses were not reasonably or prudently incurred. See "—Loss Estimates for Third Party Claims and Potential Recoveries from Insurance and through Electric Rates" for additional information. External Investigations Determining wildfire origin and cause is often a complex and time-consuming process and several investigations into the facts and circumstances of the Thomas and Woolsey Fires are believed to be ongoing. SCE has been advised that the origins and causes of these fires are being investigated by CAL FIRE and the Ventura County Fire Department. In connection with its investigation of the Thomas and Woolsey Fires, CAL FIRE has removed and retained certain of SCE's equipment that was located in the general vicinity of suspected areas of origin of each of the fires. SCE expects that the Ventura County Fire Department and/or CAL FIRE will ultimately issue reports concerning the departments’ findings of origin and cause for each of these fires but cannot predict when these reports will be released. It is SCE's understanding that these reports will not address the causes of the Montecito Mudslides. The CPUC's Safety Enforcement Division ("SED") is also conducting investigations to assess SCE's compliance with applicable rules and regulations in areas impacted by the fires. SCE cannot predict when the investigations of CAL FIRE, the Ventura County Fire Department or the SED will be completed. Internal Review Thomas Fire SCE's internal review into the facts and circumstances of the Thomas Fire is complex and examines various matters including possible ignition points, the location of those ignition points, fire progression and the attribution of damages to fires with separate ignition points. SCE expects to obtain and review additional information and materials in the possession of CAL FIRE and others during the course of its internal review and the Thomas Fire litigation process, including SCE equipment that has been retained by CAL FIRE. Based on currently available information, SCE believes that the Thomas Fire had at least two separate ignition points, one near Koenigstein Road in the City of Santa Paula and the other in the Anlauf Canyon area of Ventura County. With respect to the Koenigstein Road ignition point, witnesses have reported that a fire ignited in the vicinity of an SCE power pole and SCE later learned of a downed electrical wire at this location. SCE believes that its equipment was associated with this ignition. CAL FIRE has removed SCE equipment that was located in the Koenigstein Road area and SCE has not been able to inspect it. SCE is continuing to assess the progression of the fire from the Koenigstein Road ignition point and the extent of damages that may be attributable to that ignition. At this time, based on available information, SCE has not determined whether the ignition in the Anlauf Canyon area involved SCE equipment. CAL FIRE has removed SCE equipment that was located in the Anlauf Canyon area and SCE has not been able to inspect it. Montecito Mudslides SCE's internal review also includes inquiry into whether the Thomas Fire proximately caused or contributed to the Montecito Mudslides, the source of ignition of the portion of the Thomas Fire that burned through the Montecito area and other factors that potentially contributed to the losses that resulted from the Montecito Mudslides. Many other factors, including, but not limited to, weather conditions and insufficiently or improperly designed and maintained debris basins, roads, bridges and other channel crossings, could have proximately caused, contributed to or exacerbated the losses that resulted from the Montecito Mudslides. At this time, based on available information, SCE has not been able to determine the source of ignition of the portion of the Thomas Fire that burned within the Montecito area. In the event that SCE is determined to have caused the fire that spread to the Montecito area, SCE cannot predict whether, if fully litigated, the courts would conclude that the Montecito Mudslides were caused or contributed to by the Thomas Fire or that SCE would be liable for some or all of the damages caused by the Montecito Mudslides. Woolsey Fire SCE's internal review into the facts and circumstances of the Woolsey Fire is ongoing. SCE has reported to the CPUC that there was an outage on SCE’s electric system in the vicinity of where the Woolsey Fire reportedly began on November 8, 2018. SCE is aware of witnesses who saw fire in the vicinity of SCE's equipment at the time the fire was first reported. While SCE did not find evidence of downed electrical wires on the ground in the suspected area of origin, it observed a pole support wire in proximity to an electrical wire that was energized prior to the outage. Whether the November 8, 2018 outage was related to contact being made between the support wire and the electrical wire has not been determined. SCE believes that its equipment could be found to have been associated with the ignition of the Woolsey Fire. SCE expects to obtain and review additional information and materials in the possession of CAL FIRE and others during the course of its internal review and the Woolsey Fire litigation process, including SCE equipment that has been retained by CAL FIRE. Wildfire-related Litigation Multiple lawsuits related to the 2017/2018 Wildfire/Mudslide Events naming SCE as a defendant have been filed. A number of the lawsuits also name Edison International as a defendant and some of the lawsuits were filed as purported class actions. The lawsuits, which have been filed in the superior courts of Ventura, Santa Barbara and Los Angeles Counties in the case of the Thomas Fire and the Montecito Mudslides, and in Ventura and Los Angeles Counties in the case of the Woolsey Fire, allege, among other things, negligence, inverse condemnation, trespass, private nuisance, personal injury, wrongful death, and violations of the California Public Utilities and Health and Safety Codes. SCE expects to be the subject of additional lawsuits related to the 2017/2018 Wildfire/Mudslide Events. The litigation could take a number of years to be resolved because of the complexity of the matters and number of plaintiffs. The Thomas Fire and Montecito Mudslides lawsuits are being coordinated in the Los Angeles Superior Court. The Woolsey Fire lawsuits have also been recommended for coordination in the Los Angeles Superior Court. On October 4, 2018, the Superior Court denied Edison International's and SCE's challenge to the application of inverse condemnation to SCE with respect to the Thomas Fire and, on February 26, 2019, the California Supreme Court denied SCE's petition to review the Superior Court’s decision. In January 2019, SCE filed a cross-complaint against certain governmental entities alleging that failures by these entities, such as failure to adequately plan for flood hazards and build and maintain adequate debris basins, roads, bridges and other channel crossings, among other things, caused, contributed to or exacerbated the losses that resulted from the Montecito Mudslides. Additionally, in July 2018 and September 2018, two separate derivative lawsuits for breach of fiduciary duties and unjust enrichment were filed in the Los Angeles Superior Court against certain current and former members of the Boards of Directors of Edison International and SCE. Edison International and SCE are identified as nominal defendants in those actions. The derivative lawsuits generally allege that the individual defendants violated their fiduciary duties by causing or allowing SCE to operate in an unsafe manner in violation of relevant regulations, resulting in substantial liability and damage from the Thomas Fire and the Montecito Mudslides. In November 2018, a purported class action lawsuit alleging securities fraud and related claims was filed in the federal court against certain current and former officers of Edison International and SCE. The plaintiff alleges that Edison International and SCE made false and/or misleading statements in filings with the Securities and Exchange Commission by failing to disclose that SCE had allegedly failed to maintain its electric transmission and distribution networks in compliance with safety regulations, and that those alleged safety violations led to fires that occurred in 2018, including the Woolsey Fire. In January 2019, two separate derivative lawsuits alleging breach of fiduciary duties, securities fraud, misleading proxy statements, unjust enrichment, and related claims were filed in federal court against all current and certain former members of the board of directors and certain current and former officers of Edison International and SCE. Edison International and SCE are named as nominal defendants in those actions. The derivative lawsuits generally allege that the individual defendants breached their fiduciary duties and made misleading statements or allowed misleading statements to be made (i) between March 21, 2014 and August 10, 2015, with respect to certain ex parte communications between SCE and CPUC decision-makers concerning the settlement of the San Onofre Order Instituting Investigation proceeding (the "San Onofre OII") and (ii) from February 23, 2016 to the present, concerning compliance with applicable laws and regulations concerning electric system maintenance and operations related to wildfire risks. The lawsuits generally allege that these breaches of duty and misstatements led to substantial liability and damage resulting from the disclosure of SCE’s ex parte communications in connection with the San Onofre OII settlement, and from the 2017/2018 Wildfire/Mudslide Events. For more information regarding the San Onofre OII, see "—Permanent Retirement of San Onofre" below. Loss Estimates for Third Party Claims and Potential Recoveries from Insurance and through Electric Rates The process for estimating losses associated with wildfire litigation claims requires management to exercise significant judgment based on a number of assumptions and subjective factors, including but not limited to estimates based on currently available information and assessments, opinions regarding litigation risk, and prior experience with litigating and settling other wildfire cases. As additional information becomes available, management estimates and assumptions regarding the causes and financial impact of the 2017/2018 Wildfire/Mudslide Events may change. Such additional information is expected to become available from multiple external sources, during the course of litigation, and from SCE's ongoing internal review, including, among other things, information regarding the extent of damages that may be attributable to any ignition determined to have been substantially caused by SCE's equipment, information that may be obtained from the equipment in CAL FIRE's possession, and information pertaining to fire progression, suppression activities, alleged damages and insurance claims. As described above, the $1.8 billion after-tax charge corresponds to the lower end of the reasonably estimated range of expected losses that may be incurred in connection with the 2017/2018 Wildfire/Mudslide Events and is subject to change as additional information becomes available. Edison International and SCE currently believe that it is reasonably possible that the amount of the actual loss will be greater than the amount accrued. However, Edison International and SCE are currently unable to reasonably estimate an upper end of the range of expected losses given the uncertainty as to the legal and factual determinations to be made during litigation, including uncertainty as to the contributing causes of the 2017/2018 Wildfire/Mudslide Events, the complexities associated with multiple ignition points, the potential for separate damages to be attributable to fires ignited at separate ignition points, whether inverse condemnation will be held applicable to SCE with respect to damages caused by the Montecito Mudslides, and the preliminary nature of the litigation processes. For events that occurred in 2017 and early 2018, principally the Thomas Fire and Montecito Mudslides, SCE has $1 billion of wildfire-specific insurance coverage, subject to a self-insured retention of $10 million per occurrence. SCE also had other general liability insurance coverage of approximately $450 million , but it is uncertain whether these other policies would apply to liabilities alleged to be related to the Montecito Mudslides. For the Woolsey Fire, SCE has an additional $1 billion of wildfire-specific insurance coverage, subject to a self-insured retention of $10 million per occurrence. Edison International and SCE record a receivable for insurance recoveries when recovery of a recorded loss is determined to be probable. At December 31, 2018, Edison International and SCE had recorded $2.0 billion for expected insurance recoveries associated with the recorded loss for the 2017/2018 Wildfire/Mudslide Events. The amount of the receivable is subject to change based on additional information. SCE will seek to recover uninsured costs resulting from the 2017/2018 Wildfire/Mudslide Events through electric rates. Recovery of these costs is subject to approval by regulators. Under accounting standards for rate-regulated enterprises, SCE defers costs as regulatory assets when it concludes that such costs are probable of future recovery in electric rates. SCE utilizes objectively determinable evidence to form its view on probability of future recovery. The only directly comparable precedent in which a California investor-owned utility has sought recovery for uninsured wildfire-related costs is SDG&E’s requests for cost recovery related to 2007 wildfire activity, where FERC allowed recovery of all FERC-jurisdictional wildfire-related costs while the CPUC rejected recovery of all CPUC-jurisdictional wildfire-related costs based on a determination that SDG&E did not meet the CPUC’s prudency standard. As a result, while SCE does not agree with the CPUC’s decision, it believes that the CPUC’s interpretation and application of the prudency standard to SDG&E creates substantial uncertainty regarding how that standard will be applied to an investor-owned utility in future wildfire cost-recovery proceedings. SCE will continue to evaluate the probability of recovery based on available evidence, including guidance that may be issued by the commission on Catastrophic Wildfire Cost and Recovery, and new judicial, legislative and regulatory decisions, including any CPUC decisions illustrating the interpretation and/or application of the prudency standard when making determinations regarding recovery of uninsured wildfire-related costs. While the CPUC has not made a determination regarding SCE's prudency relative to any of the 2017/2018 Wildfire/Mudslide Events, SCE is unable to conclude, at this time, that uninsured CPUC-jurisdictional wildfire-related costs are probable of recovery through electric rates. SCE would record a regulatory asset at the time it obtains sufficient information to support a conclusion that recovery is probable. SCE will seek recovery of the CPUC portion of any uninsured wildfire-related costs through its WEMA. See "—Recovery of Wildfire-Related Costs" below. Through the operation of its FERC Formula Rate, and based upon the precedent established in SDG&E's recovery of FERC-jurisdictional wildfire-related costs, SCE believes it is probable it will recover its FERC-jurisdictional wildfire and mudslide related costs and has recorded a regulatory asset of $135 million , the FERC portion of the $4.7 billion charge accrued. At December 31, 2018, the balance sheets include estimated losses (established at the lower end of the reasonably estimated range of expected losses) of $4.7 billion for the 2017/2018 Wildfire/Mudslide Events. For the year-ended December 31, 2018, the income statements include the estimated losses (established at the lower end of the reasonably estimated range of expected losses), net of expected recoveries from insurance and FERC customers, related to the 2017/2018 Wildfire/Mudslide Events as follows: (in millions) Year ended December 31, 2018 Charge for wildfire-related claims $ 4,669 Expected insurance recoveries (2,000 ) Expected revenue from FERC customers (135 ) Total pre-tax charge 2,534 Income tax benefit (709 ) Total after-tax charge $ 1,825 Waiver of CPUC Equity Ratio Requirement Under SCE's interpretation of the CPUC’s capital structure decisions, SCE is required to maintain a 48% equity ratio on average over a 37 -month period and to file an application for a waiver to the capital structure condition if an adverse financial event reduces its spot equity ratio below 47% . On February 28, 2019, SCE is submitting an application to the CPUC for waiver of compliance with this equity ratio requirement, describing that while the charge accrued in connection with the 2017/2018 Wildfire/Mudslide Events caused its equity ratio to fall below 47% on a spot basis as of December 31, 2018, SCE remains in compliance with the 48% equity ratio over the applicable 37 -month average basis. In its application, SCE is seeking a limited waiver to exclude wildfire-related charges and wildfire-related debt issuances from its equity ratio calculations until a determination regarding cost recovery is made. Under the CPUC's rules, SCE will not be deemed to be in violation of the equity ratio requirement, and therefore may continue to issue debt and dividends, while the waiver application is pending resolution. Current Wildfire Insurance Coverage SCE has approximately $1 billion of wildfire-specific insurance coverage, subject to a self-insured retention of $10 million per occurrence, for events (including the Woolsey fire) during the period June 30, 2018 through May 31, 2019. If the $1 billion of insurance coverage is exhausted as a result of liabilities related to the Woolsey Fire, SCE has approximately $700 million of wildfire-specific insurance coverage for wildfire events during the period February 1, 2019 through May 31, 2019, subject to a self-insured retention of $10 million per occurrence and up to $15 million of co-insurance. SCE has also obtained $750 million of wildfire-specific insurance coverage for events that may occur during the period June 1, 2019 through June 30, 2020, subject to a self-insured retention of $10 million per occurrence and up to $115 million of co-insurance. SCE may obtain additional wildfire-specific insurance for this time period in the future. Various coverage limitations within the policies that make up SCE's wildfire insurance coverage could result in material self-insured costs in the event of multiple wildfire occurrences during a policy period or with a single wildfire with damages in excess of the policy limits. SCE's cost of obtaining wildfire insurance coverage has increased significantly as a result of, among other things, the number of recent and significant wildfire events throughout California and the application of inverse condemnation to investor-owned utilities. As such, SCE may not be able to obtain sufficient wildfire insurance at a reasonable cost. SCE’s wildfire insurance expense, prior to any regulatory deferrals, totaled approximately $237 million during 2018. Based on policies currently in effect, SCE anticipates that its wildfire insurance expense, prior to any regulatory deferrals, will total approximately $321 million during 2019. Wildfire insurance expense will increase in 2019 if SCE obtains additional wildfire-specific insurance. As of December 31, 2018, SCE had a regulatory asset of $128 million related to wildfire insurance costs and believes that such amounts are probable of recovery. While SCE believes that amounts deferred are probable of recovery, there is no assurance that SCE will be allowed to recover costs that have been incurred, or costs incurred in the future for additional wildfire insurance, in electric rates. In February 2019, the CPUC approved recovery of $107 million of the costs incurred by SCE to obtain a 12-month, $300 million wildfire insurance policy in December 2017. As a result of this decision, SCE will recover these insurance premiums during 2019. Recovery of Wildfire-Related Costs California courts have previously found investor-owned utilities to be |