ROWAN COMPANIES, INC. | ||||||||||||||||
LAND RIG FLEET AND CONTRACT STATUS | ||||||||||||||||
As of February 21, 2008 | ||||||||||||||||
ONSHORE RIGS | Maximum | Contract Status | ||||||||||||||
Horsepower | Drilling | Estimated | ||||||||||||||
Name | Type | Drawworks | Mud Pumps | Depth (feet) | Location | Customer | Duration | Comments | ||||||||
Rig 9 | Diesel electric | 2,000 | 3,200 | 20,000 | Louisiana | Available | Rig became idle on December 18, 2007 for top drive modifications and is awaiting assignment. | |||||||||
Rig 12 | SCR diesel electric | 1,500 | 2,600 | 18,000 | Oklahoma | Available | Rig became idle on January 31, 2008. | |||||||||
Rig 14 | AC electric | 3,000 | 3,200 | 35,000 | Texas | Newfield | March 2008 | |||||||||
Rig 15 | AC electric | 3,000 | 3,200 | 35,000 | Texas | Winn | April 2008 | |||||||||
Rig 18 | SCR diesel electric | 2,000 | 4,400 | 25,000 | Texas | Anadarko | November 2009 | |||||||||
Rig 26 | SCR diesel electric | 2,000 | 4,800 | 25,000 | Texas | Sandridge | March 2008 | |||||||||
Rig 29 | Mechanical | 1,500 | 2,600 | 18,000 | Oklahoma | Available | Rig became idle on January 21, 2008. | |||||||||
Rig 30 | AC electric | 2,000 | 2,600 | 20,000 | Texas | BBX | May 2008 | |||||||||
Rig 31 | SCR diesel electric | 3,000 | 4,400 | 35,000 | Texas | Subsurface Tech | March 2008 | |||||||||
Louisiana | Energy XXI | June 2008 | ||||||||||||||
Rig 33 | SCR diesel electric | 1,500 | 3,200 | 18,000 | Texas | Devon | June 2009 | |||||||||
Rig 34 | SCR diesel electric | 2,000 | 4,400 | 25,000 | Texas | Marathon | April 2008 | |||||||||
Rig 35 | SCR diesel electric | 1,500 | 4,400 | 18,000 | Texas | EnCana | February 2011 | Rig was idle during January 2008. | ||||||||
Rig 41 | SCR diesel electric | 2,000 | 3,200 | 25,000 | Texas | Petro-Hunt | March 2008 | |||||||||
Rig 51 | SCR diesel electric | 2,000 | 4,400 | 25,000 | Texas | Noble | April 2008 | Rig experienced approximately 16 days of January downtime. | ||||||||
Newfield | September 2008 | |||||||||||||||
Rig 52 | SCR diesel electric | 2,000 | 4,400 | 25,000 | Texas | Newfield | April 2008 | |||||||||
Rig 53 | SCR diesel electric | 2,000 | 4,400 | 25,000 | Oklahoma | Marathon | May 2008 | |||||||||
Rig 54 | SCR diesel electric | 2,000 | 4,400 | 25,000 | Texas | Newfield | July 2008 | |||||||||
Rig 59 | AC electric | 2,000 | 3,200 | 25,000 | Texas | Linn | June 2008 | |||||||||
Rig 60 | AC electric | 2,000 | 3,200 | 25,000 | Texas | Anadarko | March 2008 | |||||||||
Rig 61 | AC electric | 2,000 | 3,200 | 25,000 | Texas | Cheasapeake | April 2009 | |||||||||
Rig 62 | AC electric | 2,000 | 3,200 | 25,000 | Texas | Newfield | February 2009 | |||||||||
Rig 63 | AC electric | 2,000 | 3,200 | 25,000 | Texas | Anadarko | April 2009 | |||||||||
Rig 64 | AC electric | 2,000 | 3,200 | 25,000 | Texas | ExxonMobil | November 2008 | |||||||||
Rig 65 | AC electric | 2,000 | 3,200 | 25,000 | Texas | Pioneer | November 2009 | |||||||||
Rig 66 | AC electric | 2,000 | 3,200 | 25,000 | Texas | PetroQuest | December 2009 | |||||||||
Rig 67 | AC electric | 2,000 | 3,200 | 25,000 | Texas | ConocoPhillips | January 2010 | |||||||||
Rig 68 | AC electric | 2,000 | 3,200 | 25,000 | Alaska | Pioneer | March 2010 | |||||||||
Rig 76 | AC electric | 2,000 | 3,200 | 25,000 | Louisiana | Petro-Hunt | March 2008 | |||||||||
Rig 77 | AC electric | 2,000 | 3,200 | 25,000 | Texas | EnCana | December 2009 | Rig commenced drilling operations on December 5, 2007. | ||||||||
Rig 84 | AC electric | 2,000 | 3,200 | 25,000 | Texas | Rig currently under construction with completion expected by April 1, 2008. | ||||||||||
Rig 85 | AC electric | 2,000 | 3,200 | 25,000 | Texas | Rig currently under construction with completion expected by July 1, 2008. |
Rigs 9 through 41 were constructed at various dates between 1960 and 1982, utilizing new as well as used equipment, and have since been substantially rebuilt. Rigs 51, 52, 53 and 54 were constructed during 2001-02. Rigs 59 through 66 were completed during 2006, and Rigs 67 through 77 were completed in 2007. All but Rig 35 is equipped with a top-drive drilling system. Day rates range from $19,000 to $27,500. Estimated contract durations reflect either stated drilling periods or expected time required for the contracted well or wells. |
ROWAN HEREBY ADVISES THAT THE TABLE SET FORTH ABOVE MAY CONTAIN INACCURATE, INCOMPLETE AND/OR INCORRECT INFORMATION AND IS SUBJECT TO CHANGE AT ANY TIME. | |||||||||||||||||||||||||
THE INFORMATION SHOULD NOT BE RELIED UPON FOR ANY PURPOSE, AND ROWAN HEREBY DISCLAIMS ANY LIABILITY RELATING TO THE USE OF THE INFORMATION SET FORTH ABOVE. | |||||||||||||||||||||||||
This report contains forward looking statements within the meaning of the Private Securities Litigation Reform Act of 1995, including, without limitation, statements as to the expectations, beliefs and future expected financial | |||||||||||||||||||||||||
performance of the Company that are based on current expectations and are subject to certain risks, trends and uncertainties that could cause actual results to differ materially from those projected by the Company. Relevant | |||||||||||||||||||||||||
factors have been disclosed in the Company's filings with the U. S. Securities and Exchange Commission. |