Underlying Properties (100%)
Relating to the Hugoton Royalty Trust
March 28, 2024
the pressure and temperature bases appropriate for the sales contract or state regulatory authority; therefore, some of the aggregated totals may be stated at a mixed pressure base. No provisions for the possible consequences, if any, of product sales imbalances were included in M&L’s projections since M&L received no relevant data. Estimates of future net revenues and discounted future net revenues are not intended and should not be interpreted to represent fair market values for the estimated reserves. In M&L’s projections, future costs of abandoning facilities and wells were assumed to be offset by salvage values. Estimated costs, if any, for restoration of producing properties to satisfy environmental standards are beyond the scope of this assignment.
Following Appendix 2 (not included) is a list of exhibits that include annual projections of future production and net revenues for each state and reserves category. Also included in the exhibits are one-line summaries for the total royalty trust and for each state showing the proved reserves and future net revenues for the individual properties. These exhibits should not be relied upon independently of this narrative.
The proved developed producing reserves and production forecasts were estimated by production decline extrapolations, water-oil ratio trends, P/Z declines, or in a few cases, by volumetric calculations. For some properties with insufficient performance history to establish trends, M&L estimated future production by analogy with other properties with similar characteristics. The past performance trends of many properties were influenced by production curtailments, workovers, waterfloods, and/or infill drilling. Actual future production may require that M&L’s estimated trends be significantly altered. Reserves estimates from volumetric calculations and from analogies are often less certain than reserves estimates based on well performance obtained over a period during which a substantial portion of the reserves was produced.
The estimated proved developed nonproducing reserves can be produced from existing well bores but require capital costs for recompletions or for pipeline connections. These proved developed nonproducing reserves estimates were based on analogies with other wells that commercially produce from the same formation in the same field. The timing of initial production was provided to M&L by XTO. When actual production history is available for these nonproducing reserves, M&L’s reserves estimates may be significantly revised.
The estimated proved undeveloped reserves require significant capital expenditures, such as for planned drilling and completion costs. The proved undeveloped reserves estimates for infill wells are based on analogies to similar infill wells in the same field and/or the production histories of offset wells in the same field. As actual results of the planned drilling become available, M&L’s reserves estimates may be significantly revised.
The data employed in M&L’s estimations of proved reserves and future net revenues were provided by XTO. The current expenses for each lease were obtained from operating statements provided by XTO except for certain leases where XTO deducted items considered by XTO to be nonrecurring expenditures. No overhead was included for those properties operated by XTO. For some properties, such as large waterfloods, XTO assumed a decline in operating costs due to depleting production that was derived by forecasting a decrease in the property well count. For some gas properties, XTO assumed operating costs would be split between a variable component and a fixed component. The variable component was a constant cost per thousand cubic feet of gas production and the fixed component was a constant cost per well completion. The data provided to M&L by XTO, including, but not limited to, graphical representations and tabulations of past production performance, well tests and pressures, ownership interests, prices, capital expenditures, and operating costs were accepted as represented and were considered appropriate for the purpose of this report. M&L employed all methods, data, procedures, and assumptions considered necessary and appropriate in utilizing the data provided to prepare this report.
The evaluations presented in this report, with the exceptions of those parameters specified by others, reflect M&L’s informed judgments and are subject to the inherent uncertainties associated with interpretation of geological, geophysical, and engineering information. These uncertainties include, but are not limited to, (1) the