DIAMOND OFFSHORE DRILLING, INC. RIG STATUS REPORT AS OF
June 16, 2009
RECENT COMMITMENTS — (See Body of Report For Contract Details/Date Changes and Other Information)
| | | | | | | | | | | | | | | | | | |
Ocean Columbia | | | | | | 113-day extension | | | | | | | | | | |
| | | | | | | | | | | | Dayrate | | | | Est. End |
Rig Name | | WD | | Location | | Status | | Operator | | Current Term | | ($000s) | | Start Date | | Date |
|
Domestic Deepwater Semisubmersibles (8) | | | | | | | | | | | | | | | | |
Ocean Star | | 5,500’ | | GOM | | Actively Marketing | | DODI | | | | | 0 | | | | | |
Ocean America | | 5,500’ | | GOM | | Current Contract | | Mariner | | 6-month term | | low 550’s | | mid May 2009 | | late Jan. 2010 |
| | | | GOM/Aust. | | Prep and mobe | | DODI | | | | | | | | late Jan. 2010 | | mid May 2010 |
| | | | Australia | | Future Contract [swap from Bounty] | | Woodside | | two-year term | | mid 420’s | | mid May 2010 | | mid May 2012 |
Ocean Valiant | | 5,500’ | | GOM | | Current Contract | | Anadarko | | one-year term extension | | upper 420’s | | mid Dec. 2008 | | late June 2009 |
| | | | GOM/Angola | | Prep, mobe & acceptance test for Total | | DODI | | | | | | | | late June 2009 | | late Sept. 2009 |
| | | | Angola | | Future Contract | | Total | | two-year term +priced options | | low 620’s | | late Sept. 2009 | | late Sept. 2011 |
Ocean Victory* | | 6,000’ | | GOM | | Current Contract | | ATP | | one-year term, minimum — first three of six wells (approx. 108 days) | | low 560’s | | late May 2009 | | early Sept. 2009 |
| | | | | | Actively Marketing | | DODI | | Gap in contract | | | 0 | | | early Sept. 2009 | | early Dec. 2009 |
| | | | | | Contract Continuation | | ATP | | remaining three of six wells (approx. 150 days) | | low 560’s | | early Dec. 2009 | | early May 2010 |
| | | | | | Actively Marketing | | DODI | | Gap in contract | | | 0 | | | early May 2010 | | Q4 2011 |
| | | | | | Contract Continuation | | ATP | | remaining days of one-year term | | low 540’s | | Q4 2011 | | to be determined |
Ocean Baroness | | 7,000’ | | GOM | | Current Contract | | Hess | | term extension +unpricedoption | | mid 360’s | | late Nov. 2007 | | mid April 2010 |
Ocean Endeavor | | 10,000’ | | GOM | | Current Contract | | Devon | | four-year term + unpricedoption | | mid 290’s | | early July 2007 | | late June 2011 |
Ocean Monarch | | 10,000’ | | GOM | | Current Contract | | Plains | | one well assignment | | low 440’s | | mid March 2009 | | early Aug. 2009 |
| | | | GOM | | Future Contract | | Anadarko | | four-year term + unpricedoption | | low 440’s | | early Aug. 2009 | | mid March 2013 |
Ocean Confidence | | 10,000’ | | GOM | | Current Contract | | Murphy | | four-year term + unpricedoption | | low 510’s | | late Feb. 2008 | | late March 2012 |
* Payable in cash and pursuant to an overriding royalty interest structure, as discussed in the Company’s Form 8-K that was filed on June 3, 2009.
2
DIAMOND OFFSHORE DRILLING, INC. RIG STATUS REPORT AS OF
June 16, 2009
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | Dayrate | | | | Est. End |
Rig Name | | WD | | Location | | Status | | Operator | | Current Term | | ($000s) | | Start Date | | Date |
|
Domestic 2nd and 3rd Generation Semisubmersibles (2) | | | | | | | | | | | | | | |
Ocean Ambassador | | 1,100’ | | GOM | | Current Contract | | Taylor | | seven-month term | | mid 280’s | | late Dec. 2008 | | mid June2009 |
| | | | GOM/Brazil | | Prep, mobe & acceptance test for OGX | | OGX | | | | | | mid June2009 | | late Oct. 2009 |
| | | | Brazil | | Future Contract | | OGX | | three-year term + unpricedoption | | low 260’s | | late Oct. 2009 | | late Oct. 2012 |
Ocean Saratoga | | 2,200’ | | GOM | | Current Contract | | Taylor | | 410-day term + unpricedoption | | mid 280’s | | early June 2009 | | mid July 2010 |
|
Domestic Jack-ups (6) | | | | | | | | | | | | | | | | |
Ocean Crusader | | 200’ MC | | GOM | | Cold Stacked | | DODI | | | | | | | | |
Ocean Drake | | 200’ MC | | GOM | | Cold Stacked | | DODI | | | | | | | | |
Ocean Champion | | 250’ MS | | GOM | | Cold Stacked | | DODI | | | | | | | | |
Ocean Spartan | | 300’ IC | | GOM | | Current Contract | | Nippon | | 90-day term + option | | mid 50’s | | mid May 2009 | | early Aug. 2009 |
Ocean Summit | | 300’ IC | | GOM | | Prep, mobe and acceptance test for Pemex | | DODI | | | | | | late Feb. 2009 | | midJuly 2009 |
| | | | Mexico | | Future Contract | | Pemex | | 476 day term | | mid130’s | | mid July 2009 | | earlyNov. 2010 |
Ocean Titan | | 350’ IC | | GOM | | Current Contract | | Apache | | four-month extension | | low 130’s | | mid April 2009 | | early July 2009 |
Ocean Tower | | 350’ IC | | GOM | | SOLD Pending close | | DODI | | | | | | | | |
3
DIAMOND OFFSHORE DRILLING, INC. RIG STATUS REPORT AS OF
June 16, 2009
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | Dayrate | | | | Est. End |
Rig Name | | WD | | Location | | Status | | Operator | | Current Term | | ($000s) | | Start Date | | Date |
|
International Semisubmersibles (20) | | | | | | | | | | | | | | |
MEXICO | | | | | | | | | | | | | | | | |
Ocean New Era | | 1,500’ | | GOM | | Current Contract | | PEMEX | | 2 1/2 year term | | mid 260’s | | late Oct. 2007 | | mid Feb. 2010 |
Ocean Voyager | | 3,200’ | | GOM | | Current Contract | | PEMEX | | 2 1/2 year term | | mid 330’s | | early Nov. 2007 | | late Feb. 2010 |
NORTH SEA/MEDITERRANEAN | | | | | | | | | | | | | | | | |
Ocean Nomad | | 1,200’ | | North Sea | | Current Contract | | Talisman | | two-year term extension | | upper 330’s | | late Oct. 2008 | | early July2009, transfer remaining time to Princess |
Ocean Guardian | | 1,500’ | | Ireland | | Current Contract | | AGR | | one well | | low 260’s | | early May 2009 | | mid June 2009 |
| | | | North Sea | | Demobe to North Sea | | DODI | | | | | | mid June 2009 | | mid June 2009 |
| | | | North Sea | | Future Contract | | Nippon | | one well | | high 290’s | | mid June 2009 | | early Aug. 2009 |
Ocean Princess | | 1,500’ | | North Sea | | Current Contract | | Talisman | | resume two-year term extension | | upper 330’s | | late Dec. 2008 | | mid April 2010 |
| | | | North Sea | | Future Contract [swap from Nomad] | | Talisman | | 412 days from Nomad contract | | upper 330’s | | mid April 2010 | | early June 2011 |
| | | | North Sea | | Future Contract | | Talisman | | 120-day additional term | | mid 270’s | | early June 2011 | | early Oct. 2011 |
Ocean Vanguard | | 1,500’ | | North Sea | | Current Contract | | Statoil | | two-year term extension + unpricedoption | | mid 400’s | | late April 2008 | | mid April 2010 |
Ocean Lexington | | 2,200’ | | Egypt | | Current Contract | | BP | | 36-month term | | mid 260’s | | late Nov. 2006 | | mid Aug.2009 |
| | | | Egypt/Brazil | | Prep, mobe & acceptance test for OGX | | OGX | | | | | | mid Aug. 2009 | | late Jan. 2010 |
| | | | Brazil | | Future Contract | | OGX | | three-year term + unpricedoption | | mid 330’s | | late Jan. 2010 | | late Jan. 2013 |
AUSTRALASIA | | | | | | | | | | | | | | | | |
Ocean Bounty | | 1,500’ | | Australia | | Current Contract | | Woodside | | 60 days | | mid 380’s | | early April 2009 | | mid July2009, transfer 2-yr. ext. to America |
| | | | Australia | | Future 2-yr. cont. trans. to America; Bounty status TBD | | DODI | | | | | | | | |
Ocean Patriot | | 1,500’ | | Australia | | Current Contract | | Apache | | two-year term + unpricedoption | | between 380-420 | | late Jan. 2009 | | late Jan. 2011 |
Ocean Epoch | | 3,000’ | | Australia | | Current Contract | | BHPB | | 550-day term + unpricedoptions | | low 350’s | | late Feb. 2009 | | mid Sept. 2010 |
Ocean General | | 3,000’ | | Vietnam | | Current Contract | | PVEP | | Approx. two-year term + unpricedoptions | | low 280’s | | mid Oct. 2008 | | early Oct. 2010 |
Ocean Rover | | 8,000’ | | Malaysia | | Current Contract | | Murphy | | two-year term extension | | low 450’s | | late Feb. 2009 | | late Feb. 2011 |
4
DIAMOND OFFSHORE DRILLING, INC. RIG STATUS REPORT AS OF
June 16, 2009
| | | | | | | | | | | | | | | | | | |
| | | | | | | | | | | | Dayrate | | | | |
Rig Name | | WD | | Location | | Status | | Operator | | Current Term | | ($000s) | | Start Date | | Est. End Date |
|
BRAZIL | | | | | | | | | | | | | | | | | | |
Ocean Whittington | | 1,500’ | | Brazil | | Current Contract | | Petrobras | | five-year term plus potential 15% bonus | | mid 220’s | | late Jan. 2009 | | late Aug. 2012 |
Ocean Concord | | 2,200’ | | Brazil | | Current Contract | | Petrobras | | five-year term plus potential 15% bonus | | low 230’s | | early Jan. 2008 | | early Jan. 2013 |
Ocean Yorktown | | 2,200’ | | Brazil | | Current Contract | | Petrobras | | five-year term plus potential 15% bonus | | mid 230’s | | mid Aug. 2008 | | mid Aug. 2013 |
Ocean Yatzy | | 3,300’ | | Brazil | | Current Contract | | Petrobras | | four-year term plus potential 17% bonus | | mid 110’s | | early Oct. 2005 | | early Oct. 2009 |
| | | | Brazil | | Contract interrupted for 5-year survey | | DODI | | | | | 0 | | | mid June 2009 | | late July 2009 |
| | | | Brazil | | Future Contract | | Petrobras | | five-year term plus potential 10% bonus | | mid 240’s | | early Oct. 2009 | | early Oct. 2014 |
Ocean Quest | | 4,000’ | | Brazil | | Current Contract | | ENI Brasil | | assignment from Noble | | mid 380’s | | mid May 2009 | | early Sept. 2009 |
| | | | Brazil | | Future Contract | | OGX | | two-year term + unpriced option | | low 420’s | | early Sept. 2009 | | early Sept. 2011 |
Ocean Winner | | 4,000’ | | Brazil | | Current Contract | | Petrobras | | four-year term plus potential 5% bonus | | low 110’s | | mid March 2006 | | mid March 2010 |
| | | | Brazil | | Future Contract | | Petrobras | | five-year term extension plus potential 10% bonus | | low 270’s | | mid March 2010 | | mid March 2015 |
Ocean Worker | | 4,000’ | | Brazil | | Current Contract | | Petrobras | | six-year term plus potential 10% bonus | | low 270’s | | late Feb. 2009 | | late Feb. 2015 |
Ocean Alliance | | 5,000’ | | Brazil | | Current Contract | | Petrobras | | resume four-year term plus 20% potential bonus | | mid 150’s | | early Jan. 2009 | | mid June 2010 |
| | | | Brazil | | Future Contract | | Petrobras | | six-year term extension plus potential 15% bonus | | low 340’s | | mid June 2010 | | mid June 2016 |
|
International Drillship (1) | | | | | | | | | | | | | | | | | | |
Ocean Clipper | | 7,500’ | | Brazil | | Current Contract | | Petrobras | | five-year term plus potential 5% bonus | | low 180’s | | mid Dec. 2005 | | mid Dec. 2010 |
5
DIAMOND OFFSHORE DRILLING, INC. RIG STATUS REPORT AS OF
June 16, 2009
|
| | | | | | | | | | | | | Dayrate | | | | | |
Rig Name | | WD | | Location | | Status | | Operator | | Current Term | | ($000s) | | Start Date | | Est. End Date |
|
International Jack-ups (8) | | | | | | | | | | | | | | | | |
Ocean Columbia | | 250’ IC | | Mexico | | Current Contract | | Pemex | | 113-day extension | | low 110’s | | mid June 2009 | | early Oct. 2009 |
| | | | Mexico | | Maintenance | | DODI | | | | | 0 | | | early Oct. 2009 | | mid Oct. 2009 |
Ocean Nugget | | 300’ IC | | Mexico | | Current Contract | | Pemex | | 849 day term | | mid 130’s | | early April 2009 | | early July 2009 |
| | | | Mexico | | Intermediate Survey | | DODI | | | | | 0 | | | early July 2009 | | late July 2009 |
| | | | Mexico | | Current Contract | | Pemex | | resume 849 day term | | mid 130’s | | late July 2009 | | late July 2011 |
Ocean King | | 300’ IC | | Croatia | | Current Contract | | CROSCO | | two-year bareboat charter | | upper 100’s | | mid Nov. 2007 | | late Dec. 2009 |
| | | | Croatia | | Intermediate Survey | | DODI | | | | | 0 | | | late Dec. 2009 | | early Jan. 2010 |
Ocean Sovereign | | 300’ IC | | Indonesia | | Current Contract | | Kodeco | | resume 15-month term + unpriced option | | mid 140’s | | early March 2009 | | mid April 2010 |
Ocean Heritage | | 300’ IC | | Gulf of Suez | | Current Contract | | IPR | | one workover well | | mid 60’s | | early June 2009 | | late June 2009 |
| | | | Gulf of Suez | | Future Contract | | SUCO | | six-month term + six-month option | | mid 60’s | | late June 2009 | | late Dec. 2009 |
Ocean Spur | | 300’ IC | | Egypt | | Current Contract | | WEPCO | | one-year term | | low 140’s | | mid Aug. 2008 | | late Aug. 2009 |
Ocean Shield | | 350’ IC | | Australia | | Current Contract | | ENI | | term | | mid 260’s | | early Jan. 2009 | | early Jan. 2010 |
Ocean Scepter | | 350’ IC | | Argentina | | Current Contract | | Enap Sipetrol/YPF | | 300-day term contract + unpricedoption | | high 190’s | | late Sept. 2008 | | late July 2009 |
NOTES: Rig utilization rates can be adversely impacted by additional downtime due to unscheduled repairs and maintenance, weather conditions and other factors. An LOI is subject to customary conditions, including the execution of a definitive agreement and as such may not result in a binding contract. Options are un-priced and any extension of contract is subject to mutually agreeable terms & conditions unless otherwise indicated. Mobe revenues (if any) and mobe expenses are deferred, and generally are amortized over the life of the contract. GOM = Gulf of Mexico.
On rig utilization, assume 95% for DP units, 96% for conventionally moored rigs, and 98% for jack-ups.
6
DIAMOND OFFSHORE DRILLING, INC. RIG STATUS REPORT AS OF
June 16, 2009
EXPECTED 2009 DOWNTIME LONGER THAN 14 DAYS* (Subject to Change)
| | | | | | | | |
| | | | # Days | | | | |
|
Rig | | (Total ’09 thru Q1 = 558) | | May Act. | | Est. Q2 Total | | Comments |
|
SHIPYARD — 5-YEAR SURVEYS & MAINTENANCE | | | | | | | | |
|
America | | | | 7 | | 37 | | 5-year survey and maintenance |
Titan | | | | 0 | | 14 | | 5-year survey and maintenance |
Yatzy | | | | 0 | | 15 | | 5-year survey & maint. (start moved up from Q3) |
Total 5-year Surveys | | | | 7 | | 66 | | |
|
CONTRACT PREPARATION | | | | | | | | |
|
Ambassador | | | | 0 | | 12 | | Contract prep, mobe, acceptance test for Brazil |
Quest | | | | 14 | | 44 | | Contract prep, mobe, acceptance test for Brazil |
Valiant | | | | 0 | | 0 | | Contract prep, mobe, accept. test for West Africa |
Summit | | | | 31 | | 91 | | Contract prep, maint., mobe for Mexico |
Total Contract Prep | | | | 45 | | 147 | | |
|
OTHER DOWNTIME | | | | | | | | |
|
Bounty | | | | 0 | | 0 | | To Be Determined |
Nugget | | | | 0 | | 15 | | UWILD |
Total Other | | | | 0 | | 15 | | |
Total | | | | 52 | | 228 | | |
|
* | | Does Not Include Warm or Cold Stacked Rigs (see body of report for stacked units) |
2010 Estimated Downtime = 416 days [excludes Bounty work TBD]
5-year Surveys: Spartan (35); New Era (50); Guardian (50); Vanguard (50); Winner (91); Spur (35).
Intermediate Surveys: Clipper (21), Columbia (10): Other: Confidence (18); Lexington (24); Bounty (TBD); Alliance (32).
IMPORTANT FOOTNOTES, PLEASE READ:
Survey Costs:When rigs are undergoing surveys, normal opex applies, plus additional costs. Addl. costs for 2009 for five new 5-year surveys are expected to be approximately: $5-6 million each for Titan, Yatzy, Concord, Champion and $24 million for America.
Mobe Costs:In addition, we expect to incur approximately $32 million of amortized mobe costs during 2009 ($8 million per qtr). NOTE: Amortized mobe costs are offset by amortized mobe revenues.
7
DIAMOND OFFSHORE DRILLING, INC. RIG STATUS REPORT AS OF
June 16, 2009
Average Per-Day Rig Operating Costs (in $000’s):*
| | |
Jack-Ups | | |
GOM | | mid 40’s |
Mexico | | mid 40’s |
Mideast | | mid 50’s |
Indonesia | | low 50’s |
New-build Australia | | mid-80’s |
New-build Argentina | | upper 70’s |
Bareboat Charter | | low 10’s |
| | |
Semisubmersibles** | | |
GOM 2nd gen. | | mid 50’s |
GOM 4th gen. | | low 80’s |
GOM 4th gen. Victory-class upgrades | | upper 60’s |
GOM 5th gen. Victory-class upgrades | | low 90’s |
Mexico mid-water | | mid 60’s |
Brazil mid-water | | upper 70’s |
Vietnam mid-water | | upper 60’s |
Malaysia 5th gen. Victory-class upgrade | | upper 90’s |
Australia/New Zealand mid-water | | low 90’s |
UK mid-water | | mid 70’s |
Norway mid-water | | mid 130’s |
Egypt mid-water | | upper 70’s |
West Africa 4th gen. | | upper 120’s |
| | |
Semisubmersible DP | | |
GOM 5th gen. upgrade DP | | upper 110’s |
Brazil mid-water DP | | low 90’s |
| | |
Drillship | | |
Brazil deepwater DP | | mid 110’s |
| | |
Other Per-Day Expense | | |
Spare equipment repair, other | | low 30’s |
| | |
* | | Daily operating costs tend to run slightly lower early in the year and slightly higher toward end of year |
|
** | | All floaters conventionally moored unless otherwise noted. |
Cost/Revenue Footnote: Contract Drilling Expenses applies to contract drilling expenses ONLY anddoes not include Reimbursable Expenses
8
DIAMOND OFFSHORE DRILLING, INC. RIG STATUS REPORT AS OF
June 16, 2009
Forward-Looking Statements: The rig status report may contain “forward-looking statements” within the meaning of Section 27A of the Securities Act of 1933, as amended, and Section 21E of the Securities Exchange Act of 1934, as amended. Forward-looking statements include, without limitation, any statement that may project, indicate or imply future results, events, performance or achievements, and may contain or be identified by the words “expect,” “intend,” “plan,” “predict,” “anticipate,” “estimate,” “believe,” should, “could,” “may,” “might,” “will,” “will be,” “will continue,” “will likely result,” “project,” “budget,” “forecast,” and similar expressions. Statements by the Company in the rig status report that contain forward-looking statements include, but are not limited to, statements regarding the current term, future dayrates, start and end dates and comments concerning future contracts and availability, letters of intent, utilization, surveys, downtime and other aspects of the Company’s drilling rigs, as well as statements concerning rigs being upgraded or to be upgraded and rigs under construction. Such statements are inherently subject to a variety of assumptions, risks and uncertainties that could cause actual results to differ materially from those anticipated or projected. A discussion of the risk factors that could impact these areas and the Company’s overall business and financial performance can be found in the Company’s reports and other documents filed with the Securities and Exchange Commission. These factors include, among others, general economic and business conditions, contract cancellations, customer bankruptcy, operating risks, casualty losses, industry fleet capacity, changes in foreign and domestic oil and gas exploration and production activity, competition, changes in foreign, political, social and economic conditions, regulatory initiatives and compliance with governmental regulations, customer preferences and various other matters, many of which are beyond the Company’s control. Given these concerns, investors and analysts should not place undue reliance on forward-looking statements. Each forward-looking statement speaks only as of the date of the rig status report, and the Company undertakes no obligation to publicly update or revise any forward-looking statement.