8-K Filing
Diamond Offshore Drilling (DODRW) 8-KRegulation FD Disclosure
Filed: 25 Apr 06, 12:00am
Dayrate | ||||||||||||||||||||
Rig Name | WD | Design | Location | Status* | Operator | Current Term | (000s) | Start Date | Est. End Date | Future Contracts and Other Information** | ||||||||||
Domestic Deepwater Semisubmersibles (7) | ||||||||||||||||||||
Ocean Quest | 3,500’ | Victory Class | GOM | Contracted | Noble | one year term + option | low 270’s | mid April 2006 | mid April 2007 | Available; actively marketing. | ||||||||||
Ocean Star | 5,500’ | Victory Class | GOM | Contracted | Kerr-McGee | one year term + option | mid 170’s | mid Nov. 2005 | mid Oct. 2006 | One-year term extension with Kerr-McGee, plus option,** in mid 380’s beginning mid Oct. 2006 and ending mid Oct. 2007. Available; actively marketing. | ||||||||||
Ocean America | 5,500’ | Ocean Odyssey | GOM | Contracted | ENI | assignment until June under Mariner one year term | low 230’s | mid April 2006 | mid April 2007 | One year extension from Mariner in low 400’s beginning mid April 2007 and ending mid April 2008. Available; actively marketing. | ||||||||||
Ocean Valiant | 5,500’ | Ocean Odyssey | GOM | Contracted | Kerr-McGee | one year term | low 300’s | mid Mar. 2006 | mid Mar. 2007 | One-year term extension with Kerr-McGee, plus option,** in mid 390’s beginning mid Mar. 2007 and ending mid Mar. 2008. Available; actively marketing. | ||||||||||
Ocean Victory | 5,500’ | Victory Class | GOM | Contracted | Murphy | one year term | low 200’s | mid Nov. 2005 | mid Nov. 2006 | Approximately 23 days maintenance in Q2 2006. Two-year term extension with Murphy in mid 320’s beginning mid Nov. 2006 and ending mid Nov. 2008. Available; actively marketing. | ||||||||||
Ocean Baroness | 7,000’ | Victory Class | GOM | Contracted | Amerada Hess | one year term | low 200’s | mid Nov. 2005 | mid Nov. 2006 | Three-year term extension with Amerada Hess, plus option,** in mid 360’s beginning mid Nov. 2006 and ending mid Nov. 2009. Available; actively marketing. | ||||||||||
Ocean Confidence | 7,500’ | DP Aker H-3.2 Modified | GOM | Contracted | BP | two year term plus option | low 280’s | early Jan. 2006 | early Jan. 2008 | Approximately 21 day survey beginning mid-May 2006. Available; actively marketing. | ||||||||||
Domestic 2nd/3rd Generation Semisubmersibles (5) | ||||||||||||||||||||
Ocean New Era | 1,500’ | Korkut | GOM | Contracted | Walter | 225 day term | mid 120’s | mid Feb. 2006 | late Dec. 2006 | 225 day term, plus option,** with Walter in mid 120’s until mid May, followed by mid 130’s until early Aug.; followed by LOI for two short interim wells in mid 250’s beginning early Aug. and ending early Sept.; followed by remainder of 225 day term in mid 130’s ending late Dec. 2006. Available; actively marketing. | ||||||||||
Ocean Voyager | 2,000’ | Victory Class | GOM | Contracted | Petrobras | one well | low 110’s | mid Mar. 2006 | mid May 2006 | Two wells, plus option,** with Amerada Hess in mid 120’s beginning mid May 2006 and ending mid Aug. 2006. Available; actively marketing. | ||||||||||
Ocean Concord | 2,200’ | F&G SS-2000 | GOM | Contracted | Walter | one well | low 130’s | mid Mar. 2006 | early May 2006 | Approximately 23 days maintenance in Q2 2006. One well with Kerr-McGee in mid 90’s beginningearly May2006 and ending mid June; followed by remainder of 90-day term extension with Tana in low 130’s; followed by new 90-day term extension with Tana, plus option,** in low 170’s beginningearly Aug.and endingearly Nov. 2006. Available; actively marketing. | ||||||||||
Ocean Lexington | 2,200’ | F&G SS-2000 | GOM | Contracted | Walter | one well | low 60’s | late Mar. 2006 | late May 2006 | One well with Walter in low 80’s beginning late May and ending late June; followed by one well with Pogo in low 200,000s beginning late July and ending late Aug. 2006; followed by 60-day prep and mobe to Egypt for 36-month term LOI in mid 260’s ending mid Oct. 2009. Available; actively marketing. | ||||||||||
Ocean Saratoga | 2,200’ | F&G SS-2000 | GOM | Contracted | LLOG | three wells | low 110’s | mid Nov. 2005 | lateJuly 2006 | Special survey and maintenance (approximately 150 days) beginning mid June and ending late Nov.;followed by six-month extension, plus option,** in low 120’s with LLOG beginning in lateNov. 2006 and endinglateMay 2007. Available; actively marketing. | ||||||||||
2
Dayrate | ||||||||||||||||||||
Rig Name | WD | Design | Location | Status* | Operator | Current Term | (000s) | Start Date | Est. End Date | Future Contracts and Other Information** | ||||||||||
Domestic Jackups (10) | ||||||||||||||||||||
Ocean Crusader | 200’ | Mat Cantilever | GOM | Contracted | Woodside | one well | low 50’s | early Feb. 2006 | late May 2006 | Three wells with Walter in low 80’s beginninglate May2006 and ending midAug.2006. Available; actively marketing. | ||||||||||
Ocean Drake | 200’ | Mat Cantilever | GOM | Contracted | Chevron | term contract | high 110’s | late July 2005 | late June 2006 | Indexed term contract. Three-month term extension with Chevron, plus option,** beginning late June and ending late Sept. 2006. Available; actively marketing. | ||||||||||
Ocean Champion | 250’ | Mat Slot | GOM | Contracted | Walter | one well assignment from Stone | mid 50’s | mid April 2006 | late April 2006 | LOI for one well in low 90’s beginning late April and ending early June 2006. Available; actively marketing. | ||||||||||
Ocean Columbia | 250’ | Independent Leg Cantilever | GOM | Contracted | Newfield | six month term + opt | low 100’s | early Feb. 2006 | early Aug. 2006 | Available; actively marketing. | ||||||||||
Ocean Spartan | 300’ | Independent Leg Cantilever | GOM | Contracted | LLOG | — | low 120’s | — | mid May 2006 | Approximately 21-day survey in Q2 2006. Available; actively marketing. | ||||||||||
Ocean King | 300’ | Independent Leg Cantilever | GOM | Contracted | El Paso | one year term | mid 110’s | early Mar. 2006 | early Mar. 2007 | Available; actively marketing. | ||||||||||
Ocean Nugget | 300’ | Independent Leg Cantilever | GOM | Survey/Maintenance | DODI | — | — | — | lateMay 2006 | Approximately 63 day survey and maintenance beginning early April and ending late May 2006. One well with Hunt in mid 130’s beginninglateMay and ending earlyJuly2006; followed by LOI for one well in high 130’s beginning earlyJulyand ending lateAug. 2006. Available; actively marketing. | ||||||||||
Ocean Summit | 300’ | Independent Leg Cantilever | GOM | Contracted | Chevron | six month term + opt | low 100’s | mid Feb. 2006 | mid Aug. 2006 | Approximately 26-day survey in Sept. Available; actively marketing. | ||||||||||
Ocean Titan | 350’ | Independent Leg Cantilever | GOM | Contracted | Dominion | six month term | high 70’s | early Feb. 2006 | early Aug. 2006 | Available; actively marketing. | ||||||||||
Ocean Tower | 350’ | Independent Leg Cantilever | GOM | Contracted | Chevron | two year term extension + option | mid 150’s | late April 2006 | late April 2008 | Indexed ratewith floor in low 140’s and ceiling in low 200’s. Available; actively marketing. | ||||||||||
3
Dayrate | ||||||||||||||||||||
Rig Name | WD | Design | Location | Status* | Operator | Current Term | (000s) | Start Date | Est. End Date | Future Contracts and Other Information** | ||||||||||
International Semisubmersibles (16) | ||||||||||||||||||||
MEXICO | ||||||||||||||||||||
Ocean Ambassador | 1,100’ | Bethlehem SS-2000 | GOM | Contracted | PEMEX | four year term work | mid 50’s | late July 2003 | mid Dec. 2007 | Available. | ||||||||||
Ocean Whittington | 1,500’ | Aker H-3 | GOM | Contracted | PEMEX | four year term work | low 60’s | late July 2003 | early Oct. 2006 | Special survey and maintenance approximately 120-150 days beginning in early Oct. 2006 and ending in early Feb. 2007. Available. | ||||||||||
Ocean Worker | 3,500’ | F&G 9500 Enhanced Pacesetter | GOM | Contracted | PEMEX | four year term work | high 60’s | mid Aug. 2003 | late July 2007 | Available. | ||||||||||
Ocean Yorktown | 2,850’ | F&G SS-2000 | GOM | Contracted | PEMEX | four year term work | mid 40’s | late Oct. 2003 | mid July 2007 | Available. | ||||||||||
NORTH SEA | ||||||||||||||||||||
Ocean Nomad | 1,200’ | Aker H-3 | North Sea | Contracted | Talisman | one year | high 150’s | early Feb. 2006 | early Feb. 2007 | 18-month extension with Talisman in mid 280’s beginning early Feb. 2007 and ending early Aug. 2008. Available; actively marketing. | ||||||||||
Ocean Guardian | 1,500’ | Earl & Wright Sedco 711 Series | North Sea | Contracted | Shell | one year | low 160’s | late Mar. 2006 | late Mar. 2007 | Available; actively marketing. | ||||||||||
Ocean Princess | 1,500’ | Aker H-3 | North Sea | Contracted | Talisman | two year extension | low 150’s | late Dec. 2005 | late Jan. 2008 | Extension to includeapproximately 45-day survey and maintenance beginning mid May 2006 and ending mid June 2006. Available; actively marketing. | ||||||||||
Ocean Vanguard | 1,500’ | Bingo 3000 | North Sea | Contracted | Statoil | term | low 140’s | late May 2005 | mid Oct. 2006 | Two six-month priced options with Statoil exercised in mid 160’s beginning mid Oct. 2006 and ending mid Oct. 2007.One six-month option priced in mid 160’s remains. Available; actively marketing. | ||||||||||
AUSTRALASIA | ||||||||||||||||||||
Ocean Bounty | 1,500’ | Victory Class | Australia | Contracted | Tap Oil | one assignment well from Coogee | low 200’s | mid April 2006 | early May 2006 | One assignment well with Santos in mid 230’s beginning early May and ending mid June; followed by two wells with Santos in mid 90’s beginning mid June and ending early Sept.; followed by four wells in high 90’s with Woodside beginning early Sept. 2006 and ending early Mar. 2007; followed by four well extension priced in low 100’s beginning early Mar. 2007 and ending late Sept. 2007; followed by one-year term with Woodside in low 350’s beginning late Sept. 2007 and ending late Oct. 2008. Available; actively marketing. | ||||||||||
Ocean Patriot | 1,500’ | Bingo 3000 | Australia | Contracted | Anzon | third and fourth wells | low 140’s | late Mar. 2006 | late May 2006 | Last option well exercised with Anzon in low 350’s beginning late May 2006 and ending mid June 2006; followed byone exercised assignment option well from Apache with Nexus in high 70’sbeginning mid June and ending early Sept. 2006; followed by one wellwith Tap Oilin upper 70’sbeginning early Sept. and ending mid Oct. 2006; followed by four wells, plus option,** with NZOP in low 100’s, beginningmid Oct.2006and ending early April2007; followed by LOI for one-year term in mid 370’s beginning inearly April2007 and ending inearly April2008. Available; actively marketing. | ||||||||||
Ocean Epoch | 1,640’ | Korkut | Malaysia | Contracted | Shell | term program | mid 220’s | early April 2006 | early Nov. 2006 | LOI for 12-well program in mid 220’s beginning early Nov. 2006 and ending early Dec. 2007. Available; actively marketing. | ||||||||||
Ocean General | 1,640’ | Korkut | Malaysia | Contracted | CTOC | sixth of six wells | mid 90’s | early Jan. 2006 | late April 2006 | One well with Premier in high 70’s in Viet Nam beginning late April 2006 and ending mid June 2006; followed by one extension well with Premier in mid 150’s beginning mid June and ending mid July; followed by one assignment well with Idemitsu Vietnam in mid 170’s beginning mid July and ending late Aug. 2006; followed by three wells with Inpex in mid 130’s beginning mid Sept. 2006 and ending late Mar. 2007; followed by two additional wells with Inpex in 170’s beginning late Mar. 2007 and ending late July 2007. Available; actively marketing. | ||||||||||
Ocean Rover | 7,000’ | Victory Class | Malaysia | Contracted | Murphy | 950 day extension | mid 170’s | late June 2005 | mid Jan. 2008 | Available; actively marketing. | ||||||||||
4
Dayrate | ||||||||||||||||||||
Rig Name | WD | Design | Location | Status* | Operator | Current Term | (000s) | Start Date | Est. End Date | Future Contracts and Other Information** | ||||||||||
BRAZIL | ||||||||||||||||||||
Ocean Yatzy | 3,300’ | DP DYVI Super Yatzy | Brazil | Contracted | Petrobras | four year extension plus potential bonus | mid 110’s | early Oct. 2005 | early Oct. 2009 | Approximately 34-day survey and maintenance in Q2 2006. Available. | ||||||||||
Ocean Winner | 3,500’ | Aker H-3 | Brazil | Contracted | Petrobras | 700 day extension | low 110’s | mid Mar. 2006 | mid Mar. 2010 | Available. | ||||||||||
Ocean Alliance | 5,000’ | Alliance Class | Brazil | Contracted | Petrobras | four year extension plus potential bonus | mid 150’s | early Sept. 2005 | early Sept. 2009 | Available. | ||||||||||
International Drillships (1) | ||||||||||||||||||||
Ocean Clipper | 7,500’ | DP Fluor/Mitsubishi | Brazil | Contracted | Petrobras | five year extension plus potential bounus | low 180’s | mid Dec. 2005 | mid Dec. 2010 | Available. | ||||||||||
International Jackups (3) | ||||||||||||||||||||
Ocean Spur | 300’ | Independent Leg Cantilever | Tunisia | Contracted | Soco Tunisia | one year term | mid 120’s | mid March 2006 | mid March 2007 | Available; actively marketing. | ||||||||||
Ocean Sovereign | 300’ | Independent Leg Cantilever | Indonesia | Contracted | Santos | two wells | mid 70’s | early April 2006 | mid June 2006 | Two assignment wells with Anadarko in mid 80’s beginning mid June and ending early Aug.; followed by second of two wells with Amerada Hess in mid 80’s beginning early Aug. and ending late Aug.; followed by approximately 18-day survey ending mid Sept. 2006; followed by 18-month term with Kodeco in mid 90’s beginning mid Sept. 2006 and ending early Mar. 2008. Available; actively marketing. | ||||||||||
Ocean Heritage | 300’ | Independent Leg Cantilever | Qatar | Contracted | Conoco/Phillips | two wells plus option | low 70’s | mid June 2005 | early May 2006 | 12-month program with Maersk in low 140’s in Qatar beginningearly May2006 and ending in mid June 2007(to include approximately 45 day special survey and maintenance beginning early Oct. 2006 and ending mid Nov. 2006). Available; actively marketing. | ||||||||||
Upgrade (2) | ||||||||||||||||||||
Ocean Endeavor | 2,000’ | Victory Class | Shipyard | Upgrading | DODI | — | — | — | — | Singapore shipyard for upgrade to 10,000 ft. capable 5th Generation rig. Estimated completion early 2007; followed by commissioning beginning early Mar. 2007; followed by four year term with Devon in low 250’s. Available; actively marketing. | ||||||||||
Ocean Monarch | 2,200’ | Victory Class | GOM | Preparing to mobilize to Singapore | DODI | — | — | — | — | Singapore shipyard for upgrade to 10,000 ft. capable 5th Generation rig. Estimated completion, including commissioning, fourth quarter 2008. Available; actively marketing. | ||||||||||
Rigs Under Construction (2) | ||||||||||||||||||||
Ocean Shield | 350’ | Independent Leg Cantilever | Shipyard | — | — | — | — | — | — | Singapore shipyard, estimated completion Q1 2008. Available; actively marketing. | ||||||||||
Ocean Scepter | 350’ | Independent Leg Cantilever | Shipyard | — | — | — | — | — | — | Brownsville shipyard, estimated completion Q1 2008. Available; actively marketing. | ||||||||||